rhic machine/detector planning meeting 4 dec 07
DESCRIPTION
RHIC Machine/Detector Planning Meeting 4 Dec 07. Agenda Misc and Power (Pile) Proposal for Low Energy Au-Au Run (Satogata). Planning Meeting Web Site : http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm. Note: STAR Physics for min-bias only. Run08, First “Physics” Store. - PowerPoint PPT PresentationTRANSCRIPT
1
RHIC Machine/Detector Planning Meeting 4 Dec 07
Agenda
– Misc and Power (Pile)
– Proposal for Low Energy Au-Au Run (Satogata)
Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm
2
Run8 RHIC dAu Available Integrated Luminosity for Physics
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
27
-No
v
28
-No
v
29
-No
v
30
-No
v
1-D
ec
2-D
ec
3-D
ec
4-D
ec
mb
-1/d
ay
STAR
PHENIX
Lmax
Lmin
3Note: STAR Physics for min-bias only
Run8 RHIC dAu Integrated Luminosity for Physics
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
27-No
v
28-No
v
29-No
v
30-No
v
1-Dec
2-Dec
3-Dec
4-Dec
Since beginning of Physics
m b-1
per
day
STAR
PHENIX
Lmax
Lmin
4
Machine declared operational for Physics at 1600 hrs*=1 m, 56x56 bunches
5.3 x 1028 cm-2s-1
(1 kHz = 0.192 x 1028 cm-2s-1)*
* 11/29/07 vernier ScanIR8=0.52b, IR6=0.47b
4.8 x 1028 cm-2s-1
(1 kHz = 0.212 x 1028 cm-2s-1)*
Run08, First “Physics” Store
5
Today…87 x 87 bunches, 1 meter *, stochastic cooling ON
“Maximum” Goals:• d/bunch: 1.2 x 1011
• Au/bunch: 1.1 x 109
• # bunches: 83• *: 1 meter
7.0 x 108Au/bunch
0.55 x 1011d/bunch
6
Today…87 x 87 bunches, stochastic cooling ON
* 11/29/07 vernier ScanIR8=0.52b, IR6=0.47bPHENIX: 1 kHz = 0.192 x 1028 cm-2s-1
STAR: 1 kHz = 0.212 x 1028 cm-2s-1
7.5 x 1028 cm-2s-1 half-life = 3.2 hrs
“Maximum”average lumi/store(based on PHENIX vernier scan)
Run-3 Achieved average ZDC rate/store(scaled to present PHENIX vernier scan)
7
As of 11/30/07
BNL Energy Use FY 2006-8(C-AD Bldg 911 power is in AGS-Exp/Mach)
0
5
10
15
20
25
30
35
40
45
501
-Oct
-05
1-D
ec-
05
1-F
eb
-06
1-A
pr-
06
1-J
un
-06
1-A
ug
-06
1-O
ct-0
6
1-D
ec-
06
1-F
eb
-07
1-A
pr-
07
1-J
un
-07
1-A
ug
-07
1-O
ct-0
7
1-D
ec-
07
Date
Dai
ly A
vera
ge
Po
wer
(M
W)
$-
$10
$20
$30
$40
$50
$60
$70
$80
$90
$100
$110
$/M
Wh
r
RHIC Cryo RHIC otherAGS-Mach CAD Bldg less SMDTandem BoosterAGS-Exp NSRLSite Base Peak-Av$/MWhr
begin "balanced billing"
8
New for FY08 – 45 degree cold wave
As of 11/29/07
RHIC Cryo Operations FY07-08
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
-30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30
Days since beginning of Run
MW
RHIC Cryo 07
RHIC Cryo 08
9
As of 11/29/07
RHIC Cryo Operations FY06-08
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
-30 -10 10 30 50 70 90 110 130 150 170 190
Days since beginning of Run
MW
RHIC Cryo 06
RHIC Cryo 07
RHIC Cryo 08
10
As of 11/29/07
RHIC Operations FY06-08
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
-30 -10 10 30 50 70 90 110 130 150 170
Days since beginning of Run
MW
CAD Power 06
CAD Power 07
CAD Power 08
11
FY 2006-7 Power Bill
$-
$20
$40
$60
$80
$100
$120
$140Ju
n-0
5
Se
p-0
5
De
c-0
5
Ma
r-0
6
Jun
-06
Au
g-0
6
No
v-0
6
Fe
b-0
7
Ma
y-0
7
Au
g-0
7
No
v-0
7
Fe
b-0
8
Ma
y-0
8
Au
g-0
8
No
v-0
8
$/M
Wh
rWith Balanced Billing
Without BalancedBilling
Projection
12
RHIC Machine/Detector Planning Meeting4 Dec 07
Next Meeting
Tuesday, December 11
Agenda items:– open
Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm
13
Lave(store) - GOAL
RHIC Machine/Detector Planning Meeting26 Mar 2003Page 10/14
ZDC=22K-11K in 2.2 hrs,*=2m d=58, Au=35
14
ZDC=29K-14.5K in 3 hrs,*=1m
d=45, Au=35
Expected ZDC rate (scaling from Run 03) = 22K*(45*35)/(58*35)*2/1 = 34
15
Run 8 Log– 25 Oct, begin 45 degree cold wave (2.5 MW-NEW)
– 1 Nov, Cool-down to 4.5 degrees begins
– 4 Nov, Blue ring cold but still stabilizing
– 6 Nov, Blue and Yellow cold and stable (0.9 weeks into run)
– 8 Nov, Beam in Blue ring, “Setup Mode begins”
– 16 Nov, Beam in Blue and Yellow rings
– 18 Nov, First collisions (2.6 weeks into run)
– 19 Nov, Experiment Magnets on, begin night shifts for experiments, “Ramp-up Mode” begins (2.7 weeks into run)
– 26 Nov (1600 hrs), Machine declared operational for Physics (3.7 weeks into run)
16
8
BNL Power Cost, past 6 years
$0
$20
$40
$60
$80
$100
$120
Jun
-00
Jun
-01
Jun
-02
Jun
-03
Jun
-04
Jun
-05
Jun
-06
Jun
-07
Jun
-08
$/M
Wh
rBilled Cost/MWhr
Projection
?
17
Experiments luminosity goals for Run 8, 100 x 100 GeV pp
– PHENIX• Delivered luminosity = 140 nb-1
• Recorded luminosity = 35 nb-1
– Longitudal Polarization goal: 26 nb-1
– Transverse polarization luminosity goal: 9 nb-1
• Assumed efficiencies: 48% vertex, 64% up, 82% live 25% overall• Assumed polarization: 65%• Approximate physics weeks: 12
– STAR• Delivered luminosity = 90 nb-1
– Longitudal polarization goal: 60 nb-1
– Transverse polarization luminosity goal: 30 nb-1
• Slow detector sampled luminosity (Transverse and Longitudal) = 30 nb-1
• Assumed efficiencies: 50% uptime, 65% live 33% overall• Assumed polarization: 65%• Approximate physics weeks: 12
• pp2pp: 3 days of dedicated running • Goals: 20M elastics, 300K double pomeron exchange events
An issue: In 2006 it took 6 weeks of physics running to get from ~45% polarization to ~60% polarization, above goals assume 65% from physics day 1
(Last update 23 Oct 07)
18
Phenix Goal
Phenix GoalPHENIX Goal
STAR Goal
STAR and PHENIX Plan
19
(last update 10/23/07)
Experiments luminosity goals for Run 8 100 x 100 GeV/n d-Au
– PHENIX• Delivered luminosity = 230 nb-1
• Recorded luminosity = 58 nb-1
• Assumed efficiencies: 48% vertex, 53% live 25% overall• Approximate weeks: 10
– STAR• Delivered luminosity = 120 nb-1
• Fast Detector sampled luminosity = 60 nb-1
• Slow Detector sampled luminosity = 30 nb-1
• Fast detector overall sampling efficiency = 50%• Approximate weeks: 10
– Monopole Proposal – Detector Tests• Once ~ 20:1 signal to background is achieved in building 902, move to 10:00 IR,
reestablish good signal to background and then request collisions
20
PHENIX Goal
STAR Goal
STAR and PHENIX Plan
21
http://www.bnl.gov/cad/esfd
AGS-Booster-Tandem/Linac Startup
RHIC Cryo Cooldown/Warm-up
RHIC Cryo Operation
RHIC Cryo off
RHIC Research with s = 200 GeV/n d-Au
RHIC Research with s = 200 GeV pp
RHIC Other (TBD)
NSRL (NASA Radiobiology)
Shutdown (RHIC)
C-A Operations-FY08
Program Element Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
FY 2008
1 Oct 07
setup with beams in both rings
Planned, subject to change
30.3 weeks
Sep
concurrent with RHIC
ramp up luminosity
27 May
switch date to be determined
schedule to be determined
10 weeks
12 weeks
22
Fischer et.al. Possible 30 week run schedule