review group 316 – review of section i of the offtake arrangements document (oad)

33
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD) Offtake Arrangements Workstream – 8 th December 2010

Upload: cana

Post on 26-Jan-2016

30 views

Category:

Documents


3 download

DESCRIPTION

Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD). Offtake Arrangements Workstream – 8 th December 2010. Contents. Actions from previous meeting Rules around OPN rejections Flow Swaps update Difficult Day scenarios OPN Options Pressures - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Offtake Arrangements Workstream – 8th December 2010

Page 2: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Contents

Actions from previous meeting

Rules around OPN rejections

Flow Swaps update

Difficult Day scenarios

OPN Options

Pressures

Potential RIIO Impacts on OAD – Pressures and OPN process

Page 3: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Rules around OPN rejections

Page 4: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Rules around OPN rejections

Note: further rejection reasons will be added as part of the enduring exit regime

Page 5: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Review Group 316 – Flow Swaps update

Mike Wassell

Page 6: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Background

National Grid NTS and the DNOs may initiate flow swaps to manage their systems economically and efficiently.

From the 1st of Oct 2012 DNO User(s) are subject to NTS Exit (flat) Capacity overrun charges and any resulting deemed enduring applications.

Overview provided at last workshop to discuss Flow Swaps and a potential solution to swap capacity was briefly discussed to address this issue.

Page 7: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Potential High level Solution – views sought

Aim

For a National Grid NTS Initiated Flow Swap to not impact upon a DN Flat Overrun position in the enduring regime

How?

Transfer a quantity of Firm NTS Exit (Flat) Capacity entitlement from the reducing Exit Point to the Increasing Exit Point that, where possible, is equivalent to the National Grid NTS requested (and subsequently agreed) offtake flow rate changes.

The equivalent Firm NTS Exit (flat) capacity entitlement swap is calculated based on the requested duration of the Flow swap and the offtake flow rate changes requested.

E.g. 500,000 kWh/day flow rate request from offtake A to offtake B effective from 18.00 until the end of day.

Firm NTS Exit (Flat) Capacity swap would be 500,000 / 24 * 12 = 250,000 kWh/day equivalent of Firm Capacity

Page 8: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Potential High level Solution – views sought

Capacity swap occurs upon agreement of flow swap

DNO be able to view / notified of revised entitlements post agreement

Potential recording / approval via Gemini System

To avoid CV conversion issues, flow swaps could be requested in energy

Page 9: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Potential High level Solution – views sought

If calculated capacity entitlement swap is greater than capacity held by DNO User at reducing offtake, then the maximum possible firm capacity will be transferred across however will not cause the overrun position to be any worst

Example - NTS request flow swap of 4 Units of NTS (Flat) Capacity Entitlement from Exit Point A to Exit point B

A B

Pre Flow Swap Flow 4 Flow 4

Capacity 3 Capacity 4

A B

Post Flow SwapFlow 0 Flow 8

Capacity 0 Capacity 7

Page 10: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Example of Flow Swap

Exit Point A Exit Point B

Flow 10 Flow 0

Capacity 10 Capacity 5

National Grid request a Flow Swap from NTS/LDZ offtake A to NTS/ LDZ offtake B of 7

Post Flow Swap

Exit Point A Exit Point B

Flow 3 Flow 7

Capacity 10 Capacity 5

Pre Flow Swap

Page 11: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Possible Solution

Equivalent capacity of the flow swap to be transferred from exit Point A to Exit Point B hence a reduction of 7 at A and an increase of 7 at B

3

Capacity 12

7Exit Point A Exit Point B

Capacity 3

Flow 7Flow 3

Page 12: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Next steps

Refine potential solution?

Page 13: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Difficult Day Scenarios

Mark Amos

Page 14: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Difficult Days

Transitional & Enduring processes comparison

Real day scenario

Constraint Management tools timing

Issues with inaccurate D1 forecasts

Page 15: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Difficult Days: CM Processes

StepExisting (Transitional)

Constraint Management Process

Future (Enduring) Constraint Management Process

These processes are in addition to the existing transitional processes and GNCC monitoring shall continue as is.

1GNCC continually monitor zonal linepack and critical

offtake pressures.

OPN & DFN data is analysed along with the current telemetered state of the NTS from D-1 onwards

using the online network simulation model.

Continually reanalyse online network model as updated OPN/DFN data is submitted by Users.

2Concern is raised as the levels of linepack/pressure in

an area of the network are rapidly decreasing.

Online Network Analysis indicates a potential exit constraint. Model outputs the predicted

magnitude, timing and location of the constraint.3

Extrapolating the linepack/pressure movement forwards supported by operator judgement gives

cause for concern that minimum obligations/network requirements may be

breached.

4NTS configuration is optimised to maximise the capability and increase linepack/pressures in the area

where the potential constraint is identified.

5Linepack/pressure monitored during/after network

optimisation.Online Network Simulation continues to evaluate the

predicted state of the network.

6Further concern is raised that the reconfiguration will

not avoid the constraint. Constraint forecast to be reached in x hours.

Online Network Analysis indicates a potential exit constraint still exists. Model outputs the

magnitude and location of the constraint.

Page 16: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Difficult Days: CM Processes cont.

Step Existing (Transitional) ProcessFuture (Enduring) Process

These processes are in addition to the existing transitional processes and GNCC monitoring shall continue as is.

7

Constraint Management Procedures Initiated

Consider potential actions to take to avoid the constraint:

Cost analysis of the following options undertaken to highlight the most cost-effective tools to use in order

to avoid the constraint:

Day-ahead Options (D-1):

OPN Checking & Rejection

Low Demand Days

Constrained Storage Usage

SFRN (System Flexibility Restriction Notice (Can notify within day also)

Restricting within-day Firm Capacity Release (08:00 clearing auction restriction, identified @ EOD D-1).

Within-day Options (D):

OPN Revisions Checking & Rejection

Flow-Swapping

Locational Energy Buy Action

Operating Margins

Interruption

Off-Peak Capacity Management (Can initiate @ D-1)

Exit Capacity Surrender Auction (Can initiate @ D-1)

Constraint Management Agreements (Can initiate @ D-1)

Offtake Reduction Invitations (Can initiate @ D-1)

Page 17: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Difficult Days: CM Processes cont.

Step Existing (Transitional) ProcessFuture (Enduring) Process

These processes are in addition to the existing transitional processes and GNCC monitoring shall continue as is.

8 Constraint management actions taken.Constraint Management Options evaluated and

Users notified/requested to submit bids where necessary.

9Monitoring continues to confirm actions taken will

avoid the constraint. Further actions may be necessary.

Offers received from Users and simple cost analysis undertaken to confirm least cost solution for the

community. Bids accepted/Users notified.

Where time permits, on-line analysis is used to confirm the most efficient constraint

management option in terms of flow change and location.

Page 18: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Difficult Day: Real Data

0

2

4

6

8

10

12

14

16

18

06:0

0

08:0

0

10:0

0

12:0

0

14:0

0

16:0

0

18:0

0

20:0

0

22:0

0

00:0

0

02:0

0

04:0

0Hour Bars

Agg

rega

te D

N O

ffta

ke F

low

(m

cm)

0

0.2

0.4

0.6

0.8

1

1.2

06:0

0

08:0

0

10:0

0

12:0

0

14:0

0

16:0

0

18:0

0

20:0

0

22:0

0

00:0

0

02:0

0

04:0

0

Hour Bars

LD

Z F

low

(m

cm

)

0

0.2

0.4

0.6

0.8

1

1.2

06:0

0

08:0

0

10:0

0

12:0

0

14:0

0

16:0

0

18:0

0

20:0

0

22:0

0

00:0

0

02:0

0

04:0

0

Hour Bars

LD

Z F

low

(m

cm)

0

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

1.8

06:0

0

08:0

0

10:0

0

12:0

0

14:0

0

16:0

0

18:0

0

20:0

0

22:0

0

00:0

0

02:0

0

04:0

0

Hour Bars

LD

Z F

low

(m

cm

)

Aggregate, All DNOs

LDZ 01

LDZ 02 LDZ 03

= Actual Flow

= OPN

Page 19: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Within-day CM Tools Timeline

Forecast Constraint Start Time

4Off-Peak Scaleback: Min 4 hrs notice

2Offtake Flow Reduction: Min 2 hrs notice following invitation/allocation 1

1Locational Buy Action: Time required to Request / Accept / Re-nominate

11Surrender (Buyback): Hour bar + 1 notice following bid acceptance

11Options Contract Exercise: Hour bar + 1 notice following bid acceptance

1Flow Swaps: User driven, possibility of action within 1 hour, potentially greater

4Ops Margins: 6hrs notice for standby, 2hrs LNG otherwise

DRestricting Within-day Firm: Constraint forecast prior to 08:00 capacity auction

1

2

1Constrained Storage: Min 1hr following revised demand forecast

Page 20: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Potential Outcome of Inaccurate D-1 Forecast

Constraint is not forecast and within-day Firm Capacity remains unrestricted, potentially exacerbating any constraint management costs (buybacks)

SFRN not issued, with the potential that further flexibility capacity is released within-day

The more time available to deal with a constraint (i.e. the earlier the forecast), the lower the cost associated with dealing with the constraint and the higher the liklihood the constraint will be avoided:

Issue notifications/invitations to Users early

Give Users more time to evaluate their turn-down/up options

More time to evaluate multiple options in GNCC

Page 21: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Pressures

Glenn Bryn-Jacobsen

Page 22: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

0600 Pressure Process

Concept of 0600 pressure is based upon providing the maximum amount of linepack to the downstream system at the start of the gas day

OAD Section I seeks to establish a process to operationally manage the real time practical pressures for transporters to meet the obligation of being economic, safe and efficient. On days other than a 1 in 20 day an LDZ may not require the assured pressure – this forms the basis for an agreed pressure

Timing of the process / agreed pressures may impact OPN submission

Page 23: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Agreed pressure is not revised

after the 2300 process

NTS will contact DNO if an issue occurs which will cause significant

deviance from agreed pressure (e.g. if experiencing issues with

system)

Potential impact on OPN submission

Agreed pressures process based upon ‘critical list’ of key offtakes for each DNO

D-1 0600 pressure assessed for key offtakes by 2300

Operational discussions as

required

Revised OPN submissions

23002300 24002400

If DNO request a different pressure

which can be provided then the

agreed pressure will be revised

NTS conditions (e.g. terminal/storage behaviour) may

vary from operational assumptions leading to actual 0600 pressure differing from agreed pressures

NTS may also advise DNO if significant occurrence on the NTS will affect offtakes which are not included on

the agreed list

(DNO may contact NTS Gas Operations to review

‘critical list’)

Page 24: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

OPN Options

Mark Amos

Page 25: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

OPN Options – “What is the problem?”

OPN Accuracy

Wish to maintain accuracy measure (tolerances) against prevailing OPNs

Current tolerances seem inappropriate

What can we do to improve accuracy?

Invest to ensure all OPNs are provided accurately?

Manage current resource to focus on improving accuracy for key offtakes?

Remove storage booking/risk from OPNs?

OPN Timing

Ensure OPNs provide sufficient warning of flow changes

Ensure NTS system takes into account OPNs provided in a timely manner

Page 26: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

NTS Preferred Option

Make improvements to meet current OAD obligations & improve accuracy of OPNs that will feed into Enduring Exit Regime processes

Advantages

Maintains current obligations for provision of offtake info to NTS

Supports Enduring Exit constraint management tools

Minimises Constraint Management Costs for Community

Increased System Operator efficiency in other NTS processes through more accurate within-day modelling

Disadvantages

Costs? Practicality? Resources?

Page 27: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Discuss: How to achieve preferred option?

Can the NTS preferred option be achieved?

What are the potential blockers?

What prevents accuracy?

How to separate short term flexibility capacity booking from flow profile notification forecasts?

Issues related to pressure controlled offtakes?

Possible drivers for improvements

Additional info from NTS?

Incentives?

Charges?

Page 28: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Alternative options

Alternative options that could be explored;

Focus on key offtakes – may be some merit?

Aggregate at LDZ / Flex zones – not recommended by NTS

National Grid is happy to work with DNOs to explore cost / benefit analysis of alternative approaches

Page 29: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Provide accurate OPNs for key Offtakes?

Rather than providing OPNs for all offtakes irrespective of the size / criticality to system, focus scarce DN resources on ensuring accurate & timely OPNs are provided for key offtakes

Change OAD to enhance existing rules for key offtakes

Options include;

Volume based process i.e. accurate OPNs submitted for larger sites i.e. > x mcm/hour

Accurate OPNs are provided for a ‘critical’ list of x sites agreed by NTS & DNs against set criteria

Appropriate tolerances would need to be set for all key and less key offtakes

Page 30: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Next Steps

DNs to provide an understanding of forecasting processes

DNs to provide details regarding what the issues are that prevent accuracy

DNs to deliver preferred options with pros/cons

Page 31: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

Potential RIIO Impacts on OAD Section I – Pressures & OPN processes

Chris Shanley

Page 32: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Ofgem Capacity Working Group meeting held on 11th November

Ofgem want DNs and NTS to share information in order to deliver investment for capacity in Networks in the most efficient way across the NTS/DN interface

Ofgem are looking to develop output measures, indicators and uncertainty mechanisms to achieve this

To achieve an efficient investment outcome between the NTS and the DNs a number of factors may need to be considered:

NTS/DN investment

Diurnal Storage provision

DN interruption

Fit for purpose Capacity and Pressure processes

The interaction between capacity, flexibility and pressures

Other changes, i.e. UNC, Charges, etc.

Page 33: Review Group 316 – Review of Section I of the Offtake Arrangements Document (OAD)

Next Steps

Ofgem to produce initial strategy document in Dec 2010

Strategy Decision document in March 2011

Uncertain at this stage as to what the knock on changes to the UNC will be.

Where does this leave the OAD Section I Review?