results of the six- and twelve-month evaluations of the ...€¦ · bixby, oklahoma, with...

108
1. Report No. 2. Government Accession No. TX-95/2908-lF 4. Title and Subtitle RESULTS OF THE SIX- AND TWELVE-MONTH EVALUATIONS OF THE TEXAS SUPPLEMENTAL MAINTENANCE EFFECTIVENESS RESEARCH PROGRAM (SMERP) SITES 7. Author(s) Thomas J. Freeman, P.E. 9. Performing Organization Name and Address Texas Transportation Institute The Texas A&M University System College Station, Texas 77843-3135 12. Sponsoring Agency Name and Address Texas Department of Transportation Research and Technology Transfer Office P. 0. Box 5080 Austin, Texas 78763-5080 15. Supplementsry Notes Technical Report Documentation Page 3. Recipient's Catslog No. 5. Report Date December 1994 6. Performing Organization Code 8. Performing Organization Report No. Research Report 2908- lF 10. Work Unit No. (TRAIS) 11. Contract or Grant No. Study No. 7-2908 13. Type of Report and Period Covered Final: October 1, 1994 to August 31, 1994 14. Sponsoring Agency Code Research performed in cooperation with the Texas Department of Transportation. Research Study Title: Re-Inspection of the SMERP Sites 16. Abstract The SMERP (Supplemental Maintenance Effectiveness Research Program) study was designed to study the types of maintenance treatments typically used in Texas. Six maintenance treatments and a control section were applied at twenty test locations throughout the state. Treatments included: asphalt rubber chip seal, polymer modified emulsion chip seal, latex modified asphalt chip seal, asphalt chip seal, and a micro-surfacing treatment. Researchers re-inspected the sites approximately six and twelve months after construction. The data was entered into ASCII files and is in the same format as the output from the SHRP NIMS (National Information Management System) data base. This report presents the preliminary analysis of the change in levels of distress. 17. Key Words Maintenance Effectiveness, Chip Seal, AC, Asphalt Rubber, Latex, CRS-2P, Emulsion, Slurry, Micro-Surfacing, SMERP 18. Distribution Ststement No restrictions. This document is available to the public through NTIS: National Technical Information Service 5285 Port Royal Road Springfield, Virginia 22161 19. Security Classif.(of this report) Unclassified 20. Security Classif.(of this page) Unclassified 21. No. of Pages 22. Price 108 _Form DuT Jf 17uu.7 (8-72) Reproduction of completed page authorized

Upload: others

Post on 16-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • 1. Report No. 2. Government Accession No.

    TX-95/2908-lF

    4. Title and Subtitle

    RESULTS OF THE SIX- AND TWELVE-MONTH EVALUATIONS OF THE TEXAS SUPPLEMENTAL MAINTENANCE EFFECTIVENESS RESEARCH PROGRAM (SMERP) SITES

    7. Author(s)

    Thomas J. Freeman, P.E.

    9. Performing Organization Name and Address

    Texas Transportation Institute The Texas A&M University System College Station, Texas 77843-3135

    12. Sponsoring Agency Name and Address

    Texas Department of Transportation Research and Technology Transfer Office P. 0. Box 5080 Austin, Texas 78763-5080

    15. Supplementsry Notes

    Technical Report Documentation Page

    3. Recipient's Catslog No.

    5. Report Date

    December 1994

    6. Performing Organization Code

    8. Performing Organization Report No.

    Research Report 2908-lF

    10. Work Unit No. (TRAIS)

    11. Contract or Grant No.

    Study No. 7-2908

    13. Type of Report and Period Covered

    Final: October 1, 1994 to August 31, 1994

    14. Sponsoring Agency Code

    Research performed in cooperation with the Texas Department of Transportation. Research Study Title: Re-Inspection of the SMERP Sites

    16. Abstract

    The SMERP (Supplemental Maintenance Effectiveness Research Program) study was designed to study the types of maintenance treatments typically used in Texas. Six maintenance treatments and a control section were applied at twenty test locations throughout the state. Treatments included: asphalt rubber chip seal, polymer modified emulsion chip seal, latex modified asphalt chip seal, asphalt chip seal, and a micro-surfacing treatment. Researchers re-inspected the sites approximately six and twelve months after construction. The data was entered into ASCII files and is in the same format as the output from the SHRP NIMS (National Information Management System) data base. This report presents the preliminary analysis of the change in levels of distress.

    17. Key Words

    Maintenance Effectiveness, Chip Seal, AC, Asphalt Rubber, Latex, CRS-2P, Emulsion, Slurry, Micro-Surfacing, SMERP

    18. Distribution Ststement

    No restrictions. This document is available to the public through NTIS: National Technical Information Service 5285 Port Royal Road Springfield, Virginia 22161

    19. Security Classif.(of this report)

    Unclassified 20. Security Classif.(of this page)

    Unclassified 21. No. of Pages 22. Price

    108

    _Form DuT Jf 17uu.7 (8-72) Reproduction of completed page authorized

  • RESULTS OF THE SIX- AND TWELVE- MONTH EVALUATIONS OF THE TEXAS SUPPLEMENTAL MAINTENANCE EFFECTIVENESS RESEARCH

    PROGRAM (SMERP) SITES

    by

    Thomas J. Freeman, P .E. Engineering Research Associate,

    Texas Transportation Institute

    Research Report 2908-1 F Research Study Number 7-2908

    Research Study Title: Results of the Six and Twelve Month Evaluation of the Texas Supplemental Maintenance Effectiveness Research Program (SMERP) Sites

    Sponsored by Texas Department of Transportation

    December 1994

    TEXAS TRANSPORTATION INSTITUTE The Texas A&M University System College Station, Texas 77843-3135

  • IMPLEMENTATION STATE1\1ENT

    This report describes the continued data collection for the Supplemental Maintenance Effectiveness Research Program (SMERP) test sections constructed by Keystone Services, Inc., of Bixby, Oklahoma, with International Surfacing, Inc., as a subcontractor, for the Texas Department of Transportation. The data collected and described herein can be used by the districts in Texas to document the performance of these maintenance treatments and to determine whether the maintenance treatments described in this study are performing as expected. The results of this and continued studies of the SMERP treatments could provide data for the Texas pavement management system.

    v

  • DISCLAIMER

    The contents of this report reflect the views of the author who is responsible for the opinions, findings, and conclusions presented herein. The contents do not necessarily reflect the official views or policies of the Texas Department of Transportation (TxDOT). This report does not constitute a standard, specification, or regulation. Additionally, this report is not intended for construction, bidding, or permit purposes. Thomas J. Freeman was the Principal Investigator for the project.

    Vll

  • ACKNOWLEDGMENT

    Special thanks is given to Elias Rmeili, Larry Buttler, James Brown, and James Sassin of TxDOT for their assistant in the development and construction of the SMERP experiment.

    vm

  • TABLE OF CONTENTS

    List of Figures ............................................................. x

    List of Tables ............................................................... x

    Summary ................................................................. xv

    Chapter 1 Background and Objectives ........................................... 1

    Background .......................................................... 1

    Objectives ........................................................... 2

    Experiment Design ..................................................... 2

    Layout, Marking, and Signing Test Sections .................................. 6

    Pre-Construction Condition Surveys ....................................... 8

    Chapter 2 Construction and Post Construction Distress Surveys ....................... 11

    Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

    Post-Construction Condition Surveys . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    Output File Formats . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    Chapter 3 Results and Future Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    Preliminary Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    Site Problems ........................................................ 29

    Future Work ........................................................ 29

    References ................................................................ 30

    Appendix: Results of Distress Data Collection ..................................... 31

    IX

  • LIST OF TABLES

    1 Preliminary Analysis of SMERP Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xvi

    2 Test Sites, Locations, and Section Numbers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

    3 Site Numbering Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

    4 Preliminary Analysis of SMERP Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

    LIST OF FIGURES

    1 Locations of SMERP Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

    2 Typical SMERP Site Layout .................................................. 7

    3 Completed SHRP LTPP Condition Survey Form ................................... 9

    4 Effect of Treatments on Number of Sites With Alligator Cracking . . . . . . . . . . . . . . . . . . . . . 17

    5 Effect of Treatments on Average Area of Alligator Cracking for Sites With Alligator Cracking 18

    6 Effect of Treatments on Number of Sites With Bleeding ............................. 19

    7 Effect of Treatments on Average Area of Bleeding for Sites With Bleeding .............. 20

    8 Effect of Treatments on Number of Sites With Block Cracking ....................... 21

    9 Effect of Treatments on Average Area of Block Cracking for Sites With Block Cracking .... 22

    10 Effect of Treatments on Number of Sites With Longitudinal and Transverse Cracking ...... 23

    11 Effect of Treatments on Average Length of Longitudinal and Transverse Cracking for

    Sites With Longitudinal and Transverse Cracking .................................. 24

    12 Effect of Treatments on Number of Sites With Longitudinal Cracking in the Wheel paths . . . . 25

    13 Average Length of Longitudinal Cracking in the Wheelpaths for Sites With

    Longitudinal Cracking in the Wheelpaths . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

    14 Effect of Treatments on Number of Sites With Ravelling ............................ 27

    15 Effect of Treatments on Average Area of Ravelling for Sites With Ravelling ............. 28

    A-1 Alligator Cracking for Site AOl ............................................... 33

    A-2 Bleeding for Site AOl ....................................................... 33

    A-3 Block Cracking for Site AOl ................................................. 34

    A-4 Longitudinal and Transverse Cracking for Site AOl ................................ 34

    A-5 Longitudinal Cracking in the Wheelpaths for Site AOl .............................. 35

    x

  • A-6 Ravelling for Site AOl ...................................................... 35

    A-7 Alligator Cracking for Site BO 1 ............................................... 36

    A-8 Bleeding for Site BOl ....................................................... 36

    A-9 Block Cracking for Site BO 1 ................................................. 37

    A-10 Longitudinal and Transverse Cracking for Site BOl ................................ 37

    A-11 Longitudinal Cracking in the Wheelpaths for Site BOl .............................. 38

    A-12 Ravelling for Site BOl ...................................................... 38

    A-13 Alligator Cracking for Site C04 ............................................... 39

    A-14 Bleeding for Site C04 ....................................................... 39

    A-15 Block Cracking for Site C04 ................................................. 40

    A-16 Longitudinal and Transverse Cracking for Site C04 ................................ 40

    A-17 Longitudinal Cracking in the Wheelpaths for Site C04 .............................. 41

    A-18 Ravelling for Site C04 ............... , ...................................... 41

    A-19 Alligator Cracking for Site D04 ............................................... 42

    A-20 Bleeding for Site D04 ....................................................... 42

    A-21 Block Cracking for Site D04 ................................................. 43

    A-22 Longitudinal and Transverse Cracking for Site D04 ................................ 43

    A-23 Longitudinal Cracking in the Wheelpaths for Site D04 .............................. 44

    A-24 Ravelling for Site D04 ...................................................... 44

    A-25 Alligator Cracking for Site E06 ............................................... 45

    A-26 Bleeding for Site E06 ....................................................... 45

    A-27 Block Cracking for Site E06 ................................................. 46

    A-28 Longitudinal and Transverse Cracking for Site E06 ................................ 46

    A-29 Longitudinal Cracking in the Wheelpaths for Site E06 .............................. 47

    A-30 Ravelling for Site E06 ...................................................... 47

    A-31 Alligator Cracking for Site F06 ............................................... 48

    A-32 Bleeding for Site F06 ....................................................... 48

    A-33 Block Cracking for Site F06 .................................................. 49

    A-34 Longitudinal and Transverse Cracking for Site F06 ................................ 49

    Xl

  • A-35 Longitudinal Cracking in the Wheelpaths for Site F06 .............................. 50

    A-36 Ravelling for Site F06 ...................................................... 50

    A-37 Alligator Cracking for Site G08 ............................................... 51

    A-38 Bleeding for Site G08 ....................................................... 51

    A-39 Block Cracking for Site G08 ................................................. 52

    A-40 Longitudinal and Transverse Cracking for Site G08 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52

    A-41 Longitudinal Cracking in the Wheelpaths for Site G08 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

    A-42 Ravelling for Site G08 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

    A-43 Alligator Cracking for Site H08 ............................................... 54

    A-44 Bleeding for Site H08 ....................................................... 54

    A-45 Block Cracking for Site H08 ................................................. 55

    A-46 Longitudinal and Transverse Cracking for Site H08 ................................ 55

    A-47 Longitudinal Cracking in the Wheelpaths for Site H08 .............................. 56

    A-48 Ravelling for Site H08 ...................................................... 56

    A-49 Alligator Cracking for Site I09 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57

    A-50 Bleeding for Site I09 ....................................................... 57

    A-51 Block Cracking for Site I09 .................................................. 58

    A-52 Longitudinal and Transverse Cracking for Site I09 ................................. 58

    A-53 Longitudinal Cracking in the Wheelpaths for Site I09 ............................... 59

    A-54 Ravelling for Site I09 ....................................................... 59

    A-55 Alligator Cracking for Site no . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 A-56 Bleeding for Site no ........................................................ 60 A-57 Block Cracking for Site no .................................................. 61 A-58 Longitudinal and Transverse Cracking for Site no ................................. 61 A-59 Longitudinal Cracking in the Wheelpaths for Site no ............................... 62 A-60 Ravelling for Site n 0 ....................................................... 62 A-61 Alligator Cracking for Site K13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63

    A-62 Bleeding for Site K13 ....................................................... 63

    A-63 Block Cracking for Site K13 ................................................. 64

    Xll

  • A-64 Longitudinal and Transverse Cracking for Site K13 ................................ 64

    A-6S Longitudinal Cracking in the Wheelpaths for Site K13 .............................. 6S

    A-66 Ravelling for Site K13 ...................................................... 6S

    A-67 Alligator Cracking for Site Ll3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66

    A-68 Bleeding for Site Ll3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66

    A-69 Block Cracking for Site L13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67

    A-70 Longitudinal and Transverse Cracking for Site Ll3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67

    A-71 Longitudinal Cracking in the Wheelpaths for Site L13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68

    A-72 Ravelling for Site L13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68

    A-73 Alligator Cracking for Site Ml S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69

    A-74 Bleeding for Site MIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69

    A-7S Block Cracking for Site MIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70

    A-76 Longitudinal and Transverse Cracking for Site MIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70

    A-77 Longitudinal Cracking in the Wheelpaths for Site MIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7I

    A-78 Ravelling for Site MIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7I

    A-79 Alligator Cracking for Site NI S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72

    A-80 Bleeding for Site NI S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72

    A-8 I Block Cracking for Site NI S . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73

    A-82 Longitudinal and Transverse Cracking for Site NIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73

    A-83 Longitudinal Cracking in the Wheelpaths for Site NIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74

    A-84 Ravelling for Site NIS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74

    A-8S Alligator Cracking for Site OI 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7S

    A-86 Bleeding for Site OI 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7S

    A-87 Block Cracking for Site 017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76

    A-88 Longitudinal and Transverse Cracking for Site 0 I 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76

    A-89 Longitudinal Cracking in the Wheel paths for Site 0 I 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77

    A-90 Ravelling for Site 0 I 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77

    A-9I Alligator Cracking for Site PI9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78

    A-92 Bleeding for Site Pl9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78

    xm

  • A-93 Block Cracking for Site P 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79

    A-94 Longitudinal and Transverse Cracking for Site P19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79

    A-95 Longitudinal Cracking in the Wheelpaths for Site P19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80

    A-96 Ravelling for Site P19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80

    A-97 Alligator Cracking for Site Q 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81

    A-98 Bleeding for Site Q 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81

    A-99 Block Cracking for Site Q 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82

    A-100 Longitudinal and Transverse Cracking for Site Q19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82

    A-101 Longitudinal Cracking in the Wheelpaths for Site Q19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83

    A-102 Ravelling for Site Q19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83

    A-103 Alligator Cracking for Site R20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84

    A-104 Bleeding for Site R20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84

    A-105 Block Cracking for Site R20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85

    A-106 Longitudinal and Transverse Cracking for Site R20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85

    A-107 Longitudinal Cracking in the Wheelpaths for Site R20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86

    A-108 Ravelling for Site R20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86

    A-109 Alligator Cracking for Site S23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87

    A-110 Bleeding for Site S23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87

    A-111 Block Cracking for Site S23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88

    A-112 Longitudinal and Transverse Cracking for Site S23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88

    A-113 Longitudinal Cracking in the Wheelpaths for Site S23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89

    A-114 Ravelling for Site S23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89

    A-115 Alligator Cracking for Site T23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90

    A-116 Bleeding for Site T23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90

    A-117 Block Cracking for Site T23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91

    A-118 Longitudinal and Transverse Cracking for Site T23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91

    A-119 Longitudinal Cracking in the Wheelpaths for Site T23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92

    A-120 Ravelling for Site T23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92

    XlV

  • SUMMARY

    The Administration at the Texas Department of Transportation decided in 1990 to develop

    and construct test sites of various preventive maintenance treatments currently used in Texas. The

    primary objectives for the research are to establish the cost effectiveness of typical and promising

    maintenance treatments used in Texas in prolonging the life of asphalt pavements, to determine the

    optimum time and preventive maintenance strategies to prolong pavement life, and to demonstrate

    positive rates of return on preventive maintenance funds.

    1. Twelve Districts participated in the study. The Districts were: Paris (1 ), Amarillo ( 4), Odessa (6), Abilene (8), Waco (9), Tyler (10), Yoakum (13), San Antonio (15), (17), Atlanta (19), Beaumont (20), and Brownwood (23).

    2. Twenty sites were constructed. Each site included a total of seven 700 foot (213.4 m) sections. The sections were micro-surfacing, fog seal, a control section, and four seal coat types: asphalt rubber, latex modified, polymer modified, and conventional. Two sites did not have a fog seal or a control section.

    3. The contractor was Keystone Services, Inc., with International Surfacing, Inc., as a subcontractor. State forces constructed the fog seal sections. Overall, the project was completed with a TxDOT rating of "Good."

    4. Construction of the test sections began April 5, 1993, and was completed July 14, 1993.

    5. The sections were inspected approximately six and twelve months after construction. The sites will be re-inspected once per year until failure to accomplish the objectives.

    Considerable construction data was collected in order to determine the quality of treatment.

    The data collected can be used by the districts in Texas to see if they should be collecting any

    additional data and by researchers studying the effectiveness of the SMERP treatments. Research

    report TX-93/1981-lF, "Development and Construction of the Texas Supplemental Maintenance

    Effectiveness Research Program (SMERP) Experiment," contains additional details on the

    construction sequence, data collection during construction, materials used, and other information

    pertinent to the construction of the test sites.

    To date, one site ( 48Q 19, site 17 in Panola county west of Carthage) has failed and been

    taken out of service. The entire roadway section is to be rehabilitated due to structural failure. The

    xv

  • -------------------------------------

    Fog Seal and Control Section at one other site (48G08, site 7 in Taylor County southeast of Abilene)

    have been lost due to maintenance forces placing a chip seal on top of these sections. A contributing

    factor may have been that this site did not have the test section signs installed.

    With only two post-construction inspections (six months and twelve months), it is too early

    to establish the performance of the treatments. The phenomena of development or initiation of

    distress will need to be separated from those sections where the quantity of an existing distress is

    increasing. Another complicating factor is that the six month inspection was done during the cold

    season. The purpose of performing this early distress survey was to gather data in case of an early

    failure of a treatment and to establish a baseline performance for the treatments. However, a lesson

    learned during the SHRP SPS-3 analysis is that there may be a seasonal factor to the results of

    distress surveys. If more distress surveys could be performed during various seasons, this effect of

    this factor could be determined.

    With the preceding cautions it appears, in general, that as of approximately twelve months

    after construction, the treatments (except for the Fog and Control sections) have had a positive

    impact on reducing the occurrence of distresses. Table 1 lists the trends for each distress type and

    treatment. It must be noted that this information is very preliminary and future analysis may

    contradict these trends.

    Table 1. Preliminary Analysis of SMERP Sites

    (*) Long and Alligator Block Trans Long WP (*) Cracking Bleeding Cracking Cracking Cracking Ravelling

    Rubber Reduced Increased Reduced Reduced Reduced Increased

    Micro Reduced Reduced Reduced Mixed Increased Reduced

    Emulsion Reduced Reduced Reduced Reduced Reduced Reduced

    Latex Reduced Increased Reduced Reduced Reduced Mixed

    AC Mixed Increased Reduced Reduced Reduced Mixed

    Fog Reduced Increased Increased Reduced Mixed Increased

    Control Mixed Increased Increased Reduced Increased Increased

    (*) - Few sites affected, trends questionable.

    XVI

  • ----------------------------------~

    CHAPTER 1. BACKGROUND AND OBJECTIVES

    BACKGROUND

    Now that most of the new road construction in the United States is complete, the major

    emphasis has switched to maintaining those roads. In an effort to improve the information on the

    performance of maintenance treatments, the Strategic Highway Research Program (SHRP)

    implemented research on the effectiveness of maintenance treatments. SHRP is gathering field

    performance data from pavement test sections spread over the various climatic regions of the United

    States. However, the SHRP data is not applicable to all pavement preventive maintenance treatments

    currently used in Texas.

    The SHRP (Strategic Highway Research Program) H-101 Maintenance Effectiveness program

    studied the effects of selected preventive maintenance treatments (Ref. 1). Texas is in the SHRP

    Southern region. The SHRP Southern region has test sites throughout Texas, as far north as

    Tennessee, and as far east as Florida. The SHRP research required that the contractor use the same

    asphalt and aggregate at each site constructed within the specific SHRP region. In addition, the SHRP

    research studied the following maintenance treatments only: emulsified asphalt chip seal, crack seal,

    slurry seal, and a thin overlay. When SHRP personnel were looking for SHRP sites on which to build

    the Asphalt Maintenance Cost Effectiveness Study, Specific Pavement Study-3 (SPS-3), they offered

    to State Highway Agencies the option to build supplemental test sections adjoining the SPS-3 sections

    under the agreement that SHRP would monitor all test sections constructed. Interest was expressed

    by several Texas Districts after the SHRP offer. However, a combination of limited funding in the

    individual district's maintenance allocation and lack of consensus on which treatments to place resulted

    in a decision by the Administration to adjust the state's overall preventive maintenance program and

    develop a comprehensive preventive maintenance experiment.

    The Texas Department of Transportation (TxDOT) spends approximately $450 million per year

    on its overall maintenance program and approximately $150 million per year on its Preventive

    Maintenance Program. The Texas Department of Transportation introduced the Texas Preventive

    Maintenance Research Program at the annual District SHRP Coordinators meeting in October 1990.

    The name of this program was later changed to SMERP (Supplemental Maintenance Effectiveness

    Research Program). One million dollars was allocated to the experiment to build test sections of

    1

  • preventive maintenance treatments of interest to Texas but not considered in the SHRP national

    experiment.

    The SMERP study was designed to more closely study the types of maintenance treatments

    typically used in Texas, and it allowed the contractor to use local materials if desired. The treatments

    constructed in the SMERP study were asphalt rubber chip seal, polymer modified emulsion chip seal,

    latex modified asphalt chip seal, asphalt chip seal, and a micro-surfacing treatment. All treatments were

    placed on test sections that were 700 feet (213.4 m) long. Both lanes were treated and, where they

    existed, the shoulders were also treated. Shoulders were not treated under the SHRP SPS-3 study.

    A fog seal section was constructed by state forces and a control section was established on which no

    treatment was placed. In general, the SMERP contractor did not use local materials at each site but

    did use local sources of asphalt and aggregate where available.

    OBJECTIVES

    The goal for the SMERP Experiment is to establish the cost effectiveness of typical and

    promising maintenance treatments used in Texas in prolonging the life of asphalt pavements.

    Factors contributing to increased maintenance effectiveness and optimum pavement life-cycle

    cost are maintenance planning, spending, and performance monitoring. TxDOT will be able to address

    these factors by using the pavement management system and the data collected from the SHRP SPS-3

    and SMERP studies. By combining the data and analysis of both programs, the department will be

    assured optimal planning strategies in selecting preventive maintenance treatments. Once again, the

    primary objective is to determine optimum preventive maintenance strategies that prolong pavement

    life and to demonstrate positive rates of return on preventive maintenance funds.

    EXPERIMENT DESIGN

    It was decided that the experiment design should incorporate factors considered to be key

    variables in the analysis and that the basic design matrix should be similar to the one developed for the

    SHRP study. At that point, it was decided to fill the matrix with candidate projects that fit the

    following criteria.

    2

  • A Performance Regions West, East, South, NorthWest, and Central.

    B. Pavement Condition Good and Fair.

    C. Traffic Low and high.

    After reviewing all of the sites submitted, the goal of filling all of the above criteria could not

    be met. However, the performance regions criteria were met. Not all of the pavement condition and

    traffic criteria were met, but the sites were typical candidates to receive preventive maintenance

    treatments. The final list of sites is shown in Table 2, and the geographical distribution of the sites is

    shown in Figure 1.

    The sites where the SMERP sites were to be constructed were identified by the districts that

    offered to participate in the study and accepted by the TxDOT Design Division. The districts marked

    the beginning and end of each treatment and provided signs along the roadway to indicate each of the

    SMERP treatments.

    3

  • Table 2. Test Sites, Locations, and Section Numbers

    REF MARKER LOCATION SITE PROJ NO. DIST ROAD COUNTY FROM TO FROM TO NUMBER

    I I SH 11 Grayson 600+0.00 600+0.80 2.8 mi S. ofFM 637 0.76 mi S. 48AOI

    2 I SH 19 Hopkins 246+0.00 246+0.76 Sulphur Springs City Limits 0.76 mi S. 48801

    3 4 us 385 Deaf Smith 116+0.00 116+1.00 FM 1412 FM 1062 48C04

    4 4 FM 1061 Potter 102+0.00 104+0.00 0.75 mi E. ofFM 2381 2.0miE. 48D04

    5 6 FM 181 Ector 326+0.00 336+0.50 Andrews County Line Near SH 158 48E06

    6 6 SH349 Maitin 288+0.00 302+1.85 Neai·FM 87 Dawson Co. 48F06

    7 8 SH36 Taylor 296+7.00 302+3.00 Abilene Citv Limits Callahan Co. 48G08

    8 8 us 84 Scurry 407+1.74 404+4.00 Snyder City Limits us 180 48H08

    9 9 FM933 McLennan 356+1.367 358+0.161 FM 3051 0.8miS. 48109

    ~ 10 10 SH 135 Smith 302+1.962 304+1.752 0.26 mi NE of SH 64 0.79 mi NE 48JIO

    11 13 SH 35 Calhoun 602+0.00 606+0.26 Jackson Co. Line FM 1593 48K13

    12 13 SH71 Fayette 644+0.283 648+0.310 Baylor Creek FM955 48Ll3

    13 15 SH46 Bandera 472+0.442 468+0.042 Kendall Co. Line SH 16 48Ml5

    14 15 FM484 Comal 462+0.041 464+0.988 FM32 FM306 48Nl5

    15 17 us 190 Milam 628+0.685 628+1.485 1.9 mi S. of US 77 0.8 mi S. 48017

    16 19 SH49 Titus 700+1.l l I 700+1.774 1.1 mi W. of Morris Co. Morris Co. 48P19

    17 19 SH315 Panola 738+0.709 738+1.37 1.4 mi W. of SH 149 0.3 mi W. of SH 149 48Ql9

    18 20 FM 105 Jasper 424+0.000 424+1.500 US96 1.5 mi S. 48R20

    19 23 US67 Brown 558+0.54 558+1.47 Blanket Creek Bridge 1.0 mi N. 48S23

    20 23 US377 McCulloch 472+1.908 474+0.836 1.0 mi N. ofFM 2996 S. FM2996 48T23

  • NORTHWEST

    DENOTES COUNTY WITH TEST SECTION

    CENTRAL

    Figure 1. Locations of SMERP Sites

    5

  • LAYOUT, MARKING, AND SIGNING TEST SECTIONS

    Figure 2 shows the typical layout of test sections within each site. All sections are grouped

    together unless there is a change in pavement structure, traffic, or condition. The monitoring section

    will be 500 feet (152.4 m) long and only in the designated lane. However, visual distress data has been

    collected on all lanes, and the evaluation may include both lanes.

    To alert the public to the existence of a test site, a sign was installed alongside the test section

    6 feet (1.8 m) to the right of the shoulder and 200 feet (61.0 m) before the first test section. This sign

    reads "TEST SITE NEXT 1 :MILE. 11 Signs identifying the specific treatment type were installed near

    the right-of-way line at the beginning of each section. Each sign listed SMERP, the test section

    number, treatment type, and section number. At the one site where these signs were not installed, the

    fog seal and control section were chip sealed and have been removed from the experiment.

    White, non-reflectorized traffic buttons were placed on the edge of the shoulder at the

    beginning of every section and at every 100 feet (30.5 m). Ifa site did not have a shoulder, buttons

    were not installed.

    A white paint stripe (3-4 inches wide [0.076 m - 0.102 m]) was placed at the beginning and end

    of each treatment across the treatment lane. A white stripe (3-4 inches wide [0.076 m - 0.-102 m]) was

    also placed at the beginning and end of the monitoring section across the treatment lane. The stripe

    at the end of a treatment was used for the beginning of the next treatment if the two treatments were

    adjacent.

    White crosses were painted at the beginning and end of the monitoring section and at every 100

    feet (30.5 m) within the monitoring section. The station numbers (0, 1, 2, 3, 4, and 5) were painted

    to the right of the crosses to aid in location for distress surveys and other data collection efforts.

    6

  • "fj

    ao· c:: ""! ~

    !""

    ~ "O ;;· ::..

    -..J C'1

    ~ M

    ~ C'1 ;:,: ~

    t-i ~

    "< 0 c:: -

    Asphalt Micro- Latex Asphalt ~ Fog Control Rubber Surfacing CRS-2P Modified Cement Seal Section

    ~ [!/(~~~PfPY~~~

    Cl_

    Asphalt Rubber

    Non-Test Lane Shoulder Non-Test Lane

    Test Lane Test Lane Shoulder

  • The section number was painted to the right of the white stripe at the beginning of the

    monitoring test section (the numbers and letters were about 5 inches high [0.127 m]). The section

    numbering scheme of the SMERP sections is similar to the SHRP scheme. The numbering of a site

    consists of four parts. The first two digits (48) represent the state code for Texas. The next character

    is the site number expressed alphabetically (i.e., A is site 1, Bis site 2, C is site 3, etc.). The next two

    digits signify the TxDOT district where the site is located. The final character is the site type. Table

    3 lists the site types and their appropriate description.

    Table 3. Site Numbering Description

    Example: 48AO lH

    H- Asphalt Rubber Test Lane R- Asphalt Rubber Non-Test Lane M- Micro-Surfacing Test Lane I - Micro-Surfacing Non-Test Lane E- CRS-2P Test Lane U- CRS-2P Non-Test Lane L- Latex Modified Test Lane T- Latex Modified Non-Test Lane C- Straight AC Test Lane 0- Straight AC Non-Test Lane F- Fog Seal Test Lane G- Fog Seal Non-Test Lane X- Control Section Test Lane N- Control Section Non-Test Lane

    PRE-CONSTRUCTION CONDITION SURVEYS

    Prior to construction of the SMERP treatments, a manual condition survey and an automated

    distress survey using the Automated Road Analyzer (ARAN) (video image analysis) were conducted.

    The ARAN data has not yet been analyzed, but provides an excellent historical video log of the

    pavement prior to construction. In the initial survey, only the test lane was surveyed. Future manual

    distress surveys will be conducted on both lanes of the test sections. The manual survey was conducted

    in accordance with the procedures set up for a SHRP LTPP distress survey (Ref 3.). In addition to

    measuring the number and quantity of each distress at each severity level, a crack map showing the

    location of each distress was also produced. An example of a completed form is shown in Figure 3.

    The distress data from the manual surveys were summarized and entered into a spreadsheet.

    The data were also placed in an ASCII file in a format that is compatible with the output from the

    SHRP LTPP database.

    8

  • T g'

    1

    DA TE 03/0'3/Cf J State Assigned ID 4$017 H

    State Code

    SHRP Sectlon ID ----

    O' 10' 20' 30' 40' 50' 5m1--~-~-~----'-~-~-~~-'--~-~-~-'-~-~-~___,~~-~-~~ . . . . . . .

    ••• 0 •••• 1 ••• 1 •••• • •••

    . . . . ... • ......... · .... -....•............ · .... ·. . . . . . . . . ··:···. : .. ...... :. ···:· ... : .. . .. 15' . . . . . . . . . . . . . . ... · ...... - . , ..... - .... · ... ' ... ~ . 4m . . ···.····1···1····.··· . . . . . . . . . ···:···1····.····.····:···r···,····.····.····.··· •··•·,···

    . . . . . . . . : : . . . . : : : : I : : .. ·:· .. ·:· ... : ... ~ ... ·:· .. ·:· ... : ... : ... ·: ... ·:· .. -~ ... '. ... ~- .. ·: ... -~ .. -~ ... ;· .. ·:· .. ·:· -. -~ -.. ~- .. ·:· .. ·:· . ·:· ... ~- .. ~- .. ·:· ---r ... '." -. ~ .

    . :.---.~~~,-_.:·~v·:-~~A.~~-. ~-"-i--~~~~~···i····: .... :.~ 10·

    ···•·•• :•••.••~•••I.••••·••:••.:•.•:••I•• :•[••:••I•• : ..• :(•·:••I•• :•••.••.:••I•• :•.·:•.:.•I•.•••••··••:• 3m

    2m . . . . . . . . . . . . . . . . . ··

  • CHAPTER 2. CONSTRUCTION AND POST CONSTRUCTION

    DISTRESS SURVEYS

    CONSTRUCTION

    Twelve Districts participated in the study. The Districts were: Paris (1), Amarillo (4), Odessa

    (6), Abilene (8), Waco (9), Tyler (10), Yoakum (13), San Antonio (15), Atlanta (19), Beaumont (20),

    and Brownwood (23). A total of twenty sites were constructed. Each site included a total of seven

    700 foot (213.4 m) sections. The sections were micro-surfacing, fog seal, a control section, and four

    seal coat types asphalt rubber, latex modified, polymer modified, and conventional. Two sites did not

    have a fog seal or a control section.

    After preparation of the plans, specifications, and special provisions, bid documents were

    distributed to interested parties. Upon receipt and opening of the bids, Keystone Services, Bixby,

    Oklahoma, was selected as the prime contractor to perform the work.

    Construction of the SMERP project started April 5, 1993, and was completed July 14, 1993.

    The contractor was Keystone Services, Inc. (KS), and the subcontractor was International Surfacing,

    Inc. (ISI). KS constructed the micro-surfacing and three chip seals sections: polymer modified, latex

    modified, and conventional. ISI constructed the asphalt rubber chip seal section. Overall, the project

    was completed with a TxDOT rating of "Good. 11 The fog seal sections were constructed by the local

    districts. No treatment was applied to the control section. This treatment will explain the "do nothing"

    approach.

    Construction began on SH 35, Yoakum District, and began moving north because of rainy

    weather. The contractor constructed all five test sections within each site before moving to the next

    site. The contractor provided all materials and equipment to construct all sections and provided traffic

    control throughout construction.

    Prior to beginning construction at each site, the contractor would meet with the design division

    personnel and the local district to review all construction details. After the meeting, the construction

    of the site was turned over to the local inspector and the site was constructed according to the normal

    construction procedures of the local District.

    The contractor would always begin work on the non-test lane and shoulder. The traffic was

    then switched to the treated lane and the test lane and shoulder were then treated. The reason behind

    11

  • treating the non-test lane first was to make sure everything was working properly by the time the test

    section was constructed. It usually took two days to construct the five treatments on both lanes and

    shoulders within a site. Usually three sections were treated the first day and the other two sections

    were treated the next day. Sometimes the contractor was able to construct four treatments the first

    day.

    The following are the average target rates for the individual materials. The actual rate used for

    the sites in that district was provided by the local district. Target rates were modified in the field as

    necessary to ensure a high quality treatment.

    TARGET APPLICATION RATES

    Asphalt Rubber Polymer Modified Emulsion Asphalt Cement With Latex Straight Asphalt Cement Combined Micro-Surfacing Lightweight Grade 4 Precoat Grade 4 Precoat Grade 3

    1.8 - 2.7 l/m2

    1.4 - 1.8 l/m2

    1.4 - 1.8 l/m2

    1.4 - 1.8 l/m2

    13.6 Kg/m2

    6.5 Kg/m2

    11.4 - 12.5 Kg/m2

    12.5 - 16.3 Kg/m2

    (.40 - .60 Gal/SY) (.30 - .40 Gal/SY) (.30 - .40 Gal/SY) (.30 - .40 Gal/SY) (25 Lbs/SY) (12 Lbs/SY) (21 - 23 Lbs/SY) (23 - 30 Lbs/SY)

    After completing the Asphalt Rubber chip seal test section, construction of the chip seal with

    viscosity graded asphalt cement binder (Asphalt Cement) was begun. The previously described

    sequence of operations was followed for the Asphalt Cement chip seal section. The next treatment

    completed was the chip seal with polymer modified cationic rapid set emulsified asphalt cement (CRS-

    2P) chip seal test section. After completing both sides of the CRS-2P emulsified asphalt chip seal,

    construction was usually halted until the next day. Prior to leaving the site, all chip seal sections except

    for the CRS-2P emulsified asphalt chip seal section were swept to remove loose rock. The emulsion

    test section was usually swept the next day.

    Operation the next day typically began with the above construction sequence being performed

    on the chip seal with the Latex Modified asphalt cement binder (Latex Modified). After completing

    the Latex Modified chip seal, the Micro-Surfacing treatment was begun.

    12

  • POST-CONSTRUCTION CONDITION SURVEYS

    Two post-construction distress surveys have now been performed. These were conducted

    manually in accordance with the procedures set up for a SHRP LTPP distress survey (Ref 3. ). In

    addition to measuring the number and quantity of each distress at each severity level, a crack map

    showing the location of each distress was also produced. An example of a completed form was shown

    in Figure 3. These surveys were conducted approximately six months and twelve months after

    construction. In addition to the distress surveys, a video tape recording of the condition of each site

    was made by either walking through the section or by video taping from a car being driven down the

    lane or shoulder on higher traffic or reduced visibility sites.

    The distress data from the manual surveys were summarized and entered into a spreadsheet.

    The data were also placed in an ASCII file in a format that is compatible with the output from the

    SHRP LTPP databas.e.

    OUTPUT FILE FORMATS

    The data collected were entered into a Quattro ProR spreadsheet for the purpose of properly

    formatting the data. The data is contained in ASCII files formatted into the SHRP LTPP SPS-3

    compatible format. Data could not be entered directly into the SHRP L TPP data base because neither

    TTI nor TxDOT has access to the SHRP L TPP data base. Therefore, the format used to output data

    from the SHRP National Information Management System (NIMS) into ASCII files was selected (Ref

    3). The data can then be easily combined with the SPS-3 data for analysis.

    The data files follow the data sheets quite closely and since the data sheets include a longer

    description of the data item, it is advisable to have both the data sheets and this file format available

    during analysis.

    13

  • CHAPTER 3. RESULTS AND FUTURE WORK

    PRELIMINARY RESULTS

    Although it is too early to determine the effectiveness of each of the treatments, the general

    trends of the data and an analysis of the construction process can be accomplished. Some early results

    regarding the application process were shown in the research report TX-93/1981-lF "Development

    and Construction of the Texas Supplemental Maintenance Effectiveness Research Program (SMERP)

    Experiment." Actual application rates were shown and compared to the target rates for the treatments.

    In general, with the exception of the Asphalt Rubber, the percent difference between proposed

    application and actual application rates were quite small. The previous report discussed possible

    complications in the application of the asphalt rubber.

    With only two post-construction inspections (six months and twelve months), it is too early to

    establish the performance of the treatments. The phenomena of development or initiation of distress

    will need to be separated from those sections where the quantity of an existing distress is increasing.

    Another complicating factor is that the six month inspection was done during the cold season. The

    purpose of performing this early distress survey was to gather data in case of an early failure of a

    treatment and to establish a baseline performance for the treatments. However, a lesson learned during

    the SHRP SPS-3 analysis is that there may be a seasonal factor to the results of distress surveys. If

    more distress surveys could be performed during various seasons, this effect of this factor could be

    determined.

    With the preceding cautions it appears, in general, that as of approximately twelve months after

    construction, the treatments (except for the Fog and Control sections) have had a positive impact on

    reducing the occurrence of distresses. Table 4 lists the trends for each distress type and treatment.

    Figures 4 - 15 illustrate the number of sites and average area, or length, of distress measured during

    the pre-construction, six month, and twelve month survey that was used to develop Table 4.

    It must be noted that this information presented here is very preliminary and future analysis may

    contradict these trends. No attempt has been made to include the severity of the distress in the

    analysis. While the analysis of progression of distress from low to high is very important, there is not

    yet enough data to support this type of analysis.

    The distresses from the SHRP distress manual have been combined to produce the following

    15

  • six distress types: alligator (or fatigue) cracking, bleeding (or flushing), block cracking, longitudinal

    and transverse cracking (many SHRP distresses combined), longitudinal cracking in the wheelpaths,

    and ravelling. Other distresses did not occur often enough to warrant inclusion. These included edge

    cracking, patching, reflection cracking, shoving, potholes, polished aggregate, lane-to-shoulder-

    dropoff, and water bleeding and pumping. Rutting is included in another file and is not expected to

    have a short term impact.

    Table 4. Preliminary Analysis of SMERP Sites

    (*) Long and Alligator Block Trans Long WP (*) Cracking Bleeding Cracking Cracking Cracking Ravelling

    Rubber Reduced Increased Reduced Reduced Reduced Increased

    Micro Reduced Reduced Reduced Mixed Increased Reduced

    Emulsion Reduced Reduced Reduced Reduced Reduced Reduced

    Latex Reduced Increased Reduced Reduced Reduced Mixed

    AC Mixed Increased Reduced Reduced Reduced Mixed

    Fog Reduced Increased Increased Reduced Mixed Increased

    Control Mixed Increased Increased Reduced Increased Increased

    (*) - Few sites affected, trends questionable.

    16

  • ,..... -....)

    "' Q) .., ·-en '+--0 I.. Q) .c E ::::s z

    20

    18

    16

    14

    12

    10

    8

    6

    4

    2

    --Rubber -a-Micro .. ,,.,.{!.. Emulsion

    "" X'-" Latex ----AC --•-·Fog .......... Control

    ·-·--·-~- __;.__·.:.:-;~--,.,..,..;..--~--- - - ----

    - ..... .a - ... - - .. --.....

    0 ' """""'"'l)c.·.·.·.·.·.·.·.·.W.·.·W·.·.·.·.·.·.·.-.·.·W.·.•.W·.·.·.•.•.•.•.•.•.•W·.·.W.·.·.·.·.·.·.·.·.·.W·.·.·W.•.·.·.•.-.•.•.•.•.W.·.·W·.·.··Q

    Pre Const 6 Months 12 Months

    Inspection Number

    Figure 4. Effect of Treatments on Number of Sites with Alligator Cracking

  • ........ 00

    -u. Cl) -C') c: ·-~ (.) ns s...

    (.) s... 0

    '+-' ns C') ·---

  • 20

    18

    16 :;:;.::::·:;;:::·:::

    ·,.:.:;-. ·,:-::-::-:.::·:;:)( ::::·:. ::::·:·:=·:-:;·:-:-:

    -:;:-: .-..::·:-:::::·:.Y;.

    ~-;--;, ·;y:.:::·:-::·:·:::;

    "' 14 Cl> ~Y.'' ..... ·-CJ) 12 ..... 0

    10 I-' I.. \0 Cl>

    :·:·.· .·:·:·:·.·.···:·:·: ·:·:·:· ;.::: •. ;.·>:·:·:-·:·:····

    ~~ .;.;.;:·:·:·::::~·~·:·'"'.::::-:-:-::·:·:·:·:·

    ~ :::-:· ... ,.,.,.,,.,.d ~

    -•. ---~- -~--~ -~--~- -~-- -· -- --.c 8 E :::s z 6

    4~ Rubber ·:·:·:·:·:·X< Latex

    2

    --m-- Micro ., A Emulsion

    ->Jl.-AC --• -·Fog

    """""foO Control II

    0

    Pre Const 6 Months 12 Months

    Inspection Number

    Figure 6. Effect of Treatments on Number of Sites with Bleeding

  • N 0

    4000

    U::- 3500 Cl) -g> 3000 ---~ -- - - .......... .-· --... - -+- - - -""""'. - - - --.. ·-"'C (1) 2500 (1) -m

    '+- 2000 0 ns (1)

    '""" 1500 1000 '""" (1) > 500

  • 20 -~Rubber

    18 -1- I -m-Micro :·:·:·:-:-:·A:· Emulsion

    16 + :

  • tv tv

    7000

    6000

    ~ (.)

    0 5000 --CO LL \to- en 0 - 4000 ~ C>

    (1) ·= "- ~ 3000 "-~ (.)

    2000 "-(1) > tJ• Emulsion

    ''" »,., Latex

    ---AC ··•··Fog """"'° Control

    .-.,;,.

    ... ~

    ./ .......... ....._....~

    6 Months

    Inspection Number

    ~ ~

    ~

    Figure 9. Effect of Treatments on Average Area of Block Cracking for Sites With Block Cracking

    ~

    12 Months

  • N VJ

    20

    18

    16

    ti) 14 Q) .... ·-en 12 ..... 0

    10 a.. Q) .c 8 E :l z 6

    4

    2

    0

    Pre Const

    -...-Rubber -m-Micro , .. ,.,.,,.. Emulsion '''" x,, Latex ----AC --• -·Fog ........,. Control

    ;,,-;,;;,;,---...... . ...,_ __ --·-~- .......... -- --

    6 Months

    -:-;:.· a:. .;.-q ":·:·:·:-::·:·:·:· :f?.;~ :~;~·:·:·::·; .:::::·

    Inspection Number

    .,. .... - .... - .. - .......... - ..

    ;:::: .. :·:-:-:-·-:···· .;:::::·:·:··

    ~ .. .::;.: :::::- ;:;:.; %:. :?...: «·.

    12 Months

    Figure 10. Effect of Treatments on Number of Sites for Longitudinal and Transverse Cracking

  • N .j::..

    "C c: ns -ns -C: LL ·- CJ) "C -~ tn ·- c: tn ·-c: ~ 0 (.)

    ..J E ~ (.) .c: (1)

    500

    450

    400

    350

    300

    250 ........... ........... 200

    +' "' tn S-c: (1) (1) >

    ~~------~--~ ~ -- ----------~ ~ __ ._...~ .. -------- -- ....... --·""

    ..J "' c: (1) ns tn i-ns I-'-(1)

    ~

    150

    100

    50

    0

    Pre Const

    .• ;.• •.

    6 Months

    Inspection Number

    Figure 11. Average Length of Longitudinal and Transverse Cracking for Sites With Longitudinal and Transverse Cracking

    ·:-::·:·:·:·:·:

    -+-Rubber

    ---im-Micro

    ·=···=A· Emulsion

    ,." x=-,, Latex

    ---*-AC

    ··•··Fog

    .....,.. Control

    ''"'· "" ,.,:; .,.: . .,;:;-=·=·=·=·=i::::

    ~->. :f:!:· ·:"·:·:·:·:·:·:-:·

    12 Months

  • N Vi

    20

    18

    16

    t/I 14 Cl,) .... ·-"' 12 .... "=: ... ,,, .. 0

    10 ., ..

    Cl,)

    .c 8 E ::::s z 6

    ·=:: .. ,:: ... ,,,,

    ~:· -.*"-4

    2

    0

    Pre Const

    - ........... ...

    ~: . .::__, ":"'::::·:::'·

    .. ,.,"':·::::,ti-=·:·:· """""=·: .. :·:·: """ .......... .

    6 Months

    Inspection Number

    ---+--Rubber --M-- Micro ;.,.,.,.,.,.~.,. Emu Is ion

    •» >«"' Latex ~AC

    ··•-·Fog ~ Control

    ..............

    ;;-:·:· *:. {«· .:-:--..

    Figure 12. Effect of Treatments on Number of Sites With Longitudinal Cracking in the Wheelpaths

    12 Months

  • N 0\

    °' c 500 ·-.:i.::: 0 ~ ....

    (..) -~ u. c ..J ·- -

    "'C "' .a .c ·- '+-' °' ~ c c. o-..J ~ 't- .c 0 3: £ °'.c c '+-' c

    ..J ·-

    °' ~ ....

    ~

    450

    400

    350

    300

    250

    200

    150

    100

    50

    0

    Pre Const

    ···:·:·.:

    ·:·.:·:·.·

    - - ........

    ·'.-'.; . ..:·:·::.::.::.

    :·:;.; ··=:·4'·=··:·:·: ·:·:·: :·:·:·:-:-:-::·:·:·:

    6 Months

    Inspection Number

    ·:·:·:·:·:·:-:::::::

    ...,..~Rubber

    --m- Micro =·=·=·=·=·t.= Emulsion

    >

  • tv -...l

    20

    18

    16

    ti) 14 Cl) ~ ·-en 12 ..... 0

    10 I.. Cl) .c 8 E ::s z 6

    4 I ___.-

    :-:·:·:·:·:·:·:·:·:· :·:-:·

    2 r:: ........ .,..;,:_- --

    0

    Pre Const

    .... -Rubber ---Micro =·=·===·=A= Emulsion ,,,. ~.,, Latex

    -*-AC ··•··Fog .......... Control

    '*"'"" ~~ '1Jw ~ ;: .::..M _:.." .. .:. _:"7 = ~-::: .. _,,; • ·, - .. ----. --.. - - . --. -.. --. ---·- .. -.. - ..... -.. -. -.

    6 Months

    Inspection Number

    Figure 14. Effect of Treatments on Number of Sites With Ravelling

    ·:·:·:·:·:·.· ... :

    12 Months

  • N 00

    -u. Cl) -C> c: ·---Q) > ('CS

    0::: '+-0 ('CS Q) I.. ('CS I.. Q)

    ~

    2500

    2000

    1500

    1000

    ...... -Rubber

    -m-Micro =·=A Emulsion

    "'' x'-" Latex

    -----AC · -•··Fog """""" Control

    ~

    '"~.~ ··-:-;

    ~:-0::·;:-

    k·::

    ~

    ·::-:: ~:-:

    500 :::·:·:·:·:-:····· ::·:·.

    0

    Pre Const

    ...- -- -..-. ' -- ...- _... ~+""""""'

    ~ ~

    :;:::: .. ;.;.:·:·:·:·:·:·:· 1;.,., ..... . ·:~:·:::··

    %-;: ...... .-;-

    ;·;:-;

    '''=?< : -=·=·;" -:-:-:- -:--..-;; *-==~

    6 Months

    Inspection Number

    , ,

    :·:-:·: ·:·.:. :·::·:·:·

    ·:·:·: ·,·,·-=:·:·:·

    ;.:-:-: :.:-=~ .-:·:·: ;.:-:-: ~::.-;: ~:::;> ;-:;:-: w..:

    12 Months

    Figure 15. Effect of Treatments on Average Area of Ravelling for Sites With Ravelling

  • Appendix A contains the results of the site inspections on a site by site basis.

    SITE PROBLEMS

    To date, one site (48Ql9, site 17 in Panola county west of Carthage) has failed and been

    taken out of service. The entire roadway section is to be rehabilitated due to structural failure. The

    Fog Seal and Control Section at one other site (48G08, site 7 in Taylor county southeast of Abilene)

    have been lost due to maintenance forces placing a chip seal on top of these sections. A contributing

    factor may have been that this site did not have the test section signs installed.

    FUTURE WORK

    Since the treatments have been constructed, the next stages will be to monitor the

    performance of the sections and to continue the analysis of that performance. It has been proposed

    that a distress survey be performed on a yearly basis. This data should be recorded in the SHRP

    compatible format. If possible, the frequency of inspection should be increased. The short term

    nature of this maintenance research project suggests that the data should be taken as often as possible.

    This will allow us to determine a seasonal correction for distress and will improve the predictive

    nature of the experiment.

    Additional data collection will include inspecting all of the test sections using the ARAN.

    Non-destructive deflection testing will be performed one year after construction and then every two

    years. All of the sections will be monitored until failure.

    The data analysis should begin after the next cycle of distress surveys. If these treatments

    behave similarly to the SHRP H-101 test sections, distress will remain relatively minimal until at least

    eighteen months after construction. However, due to the condition of some of the test sections prior

    to construction, the S.l\1ERP test sections may exhibit some early distress including bleeding, rutting,

    and on one or two sections, alligator cracking. Future analysis will determine the effectiveness of

    each treatment based on the different conditions at each site. The analysis of the cost-effectiveness

    should begin when adequate data is available. To date, no attempt has been made to include the

    severity of the distress in the analysis. While the analysis of progression of distress from low to high

    is very important, there is not yet enough data to support this type of analysis. However the data will

    exist in the near future, and this task should be undertaken. This task will be made easier if the

    distress surveys are conducted twice per year.

    29

  • REFERENCES

    1. Smith, R. E., T. J. Freeman, and 0. Pendleton, "H-101 Pavement Maintenance Effectiveness," Strategic Highway Research Program, National Research Council, 1993.

    2. "Distress Identification Manual for the Long-Term Pavement Performance Project," Strategic Highway Research Program, National Research Council, SHRP-P-338, 1993.

    3. "Data Base Structure Reference Manual," Strategic Highway Research Program, National Research Council, 1993.

    4. Freeman, T. J., and E. Rmeili, "Development and Construction of the Texas Supplemental Maintenance Effectiveness Research Program (SMERP) Experiment," TxDOT, May 1994.

    30

  • APPENDIX

    Results of Distress Data Collection

    31

  • Ill Ill e ..... Ill c ~

    Ill Ill e ..... Ill

    c ~

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction

    -... A01H -A01M

    -6-A01E

    '"'-X'"'A01L

    -lll-A01C

    • • • A01F

    -+· A01X

    " y ... ----+ 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-1. Alligator Cracking for Site AOl

    Construction

    31-May-93

    - - -,,,.)Co,._., ""'· ,.,,,,

    ....... ·~·····. . .: .. ··

    .. . -

    -A01M """"6-A01E "''·>

  • VI VI e .... VI

    c ~ 0

    VI VI

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0% .......

    30.0%

    20.0% . -10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    Construction

    ... .. . .. ,...., . ... ... 31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • .. A01H

    -A01M

    -t.-A01E

    """X""'A01L

    -A01C

    • • • A01F

    05-Jul-94

    Figure A-3. Block Cracking for Site AOl

    Construction

    • .. A01H

    -A01M

    -6-A01E

    .... ~ .. ··A01L

    -llE-A01C

    • • • A01F

    ~- A01X e a.0% ]! c ~ 6.0%

    4.0%

    ........... ¥ .. _...... D ... -- >< ... ,.,...._'.I',,_~ ... _,, ....... & .., - ..... ,.. ,. .,....,.:l•,,...•..,•~ .. u.: ~ : : "' "' .,. ., .... - ., ,.. "' a .., .., • ""' "" ..,. -. ""'+ ~ ....... - ......

    2.0% ---- - _ ... _ . . ····~·· ---0.0% ...... • ..... 20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-4. Longitudinal and Transverse Cracking for Site AO 1

    34

  • Cl) Cl)

    ~ ..... Cl)

    i:5 ~ 0

    Cl) Cl)

    ~ ..... Cl)

    i:5 ~ 0

    Construction

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    • .. A01H

    -A01M

    --A01E

    ,, .... ~·"·A01L

    -A01C

    • • • A01F

    --+• A01X

    - - . .. . . - - - . - - " - -- - - ,,,.,.., :i ...... -:-...... _ ....... ~-""• ...... ....0... • ... - ........ -......... "' ,.. -.rr> .... :& - ...... 0.0% +----...:...:..;;.:.;ii.,;....-...;....;...;;...;;.;;~-----..li.oO-... ________ ~

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-5. Longitudinal Cracking in the Wheelpaths for Site AOl

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    Figure A-6. Ravelling for Site AOl

    35

    • .. A01H

    -A01M

    --A01E

    ····~····A01L

    -A01C

    • • • A01F

    -+· A01X

    05-Jul-94

  • Construction 100.0%

    - .. B01H 90.0% -so1M

    --B01E 80.0%

    ""··l< ..... ·B01L

    70.0% -so1c

    • • • B01F Ill 60.0%

    --+· B01X Ill e:! - 50.0% .!!? c ~ 0 40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-7. Alligator Cracking for Site BOl

    Construction 100.0%

    - .. B01H -so1M 90.0%

    80.0% ...... -B01E """-?

  • IJI IJI !!:? .. IJI

    c ~ 0

    IJI IJI !!:? .. . !!! c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    .. 0.0%

    20-Feb-93 - -

    Construction

    -.. B01H -B01M

    ......,e.-B01E

    ""K'"·B01L

    --!l!--B01C

    • • • B01F

    --t- • B01X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-9. Block Cracking for Site BOl

    Construction

    -.. B01H -B01M

    -t.-B01E

    .... K .... B01L

    --!l!--B01C

    • • • B01F

    -+· B01X

    -31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-10. Longitudinal and Transverse Cracking for Site BOl

    37

  • 14.0%

    12.0%

    10.0%

    Cl) Cl)

    ~ 8.0% ... • !!? c ~ "

    6.0%

    4.0%

    2.0%

    0.0% 20-Feb-93

    60.0%

    50.0%

    40.0%

    Cl) Cl)

    ~ ... 30.0% .!!? c ~ "

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • .. B01H

    -B01M

    --B01E

    wo•1( "'801L

    -B01C

    • • • B01F

    -+· B01X

    05-Jul-94

    Figure A-11. Longitudinal Cracking in the Wheelpaths

    Construction

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    Figure A-12. Ravelling for Site BOl

    38

    • .. B01H

    -B01M

    --B01E

    .... ~····B01L

    -B01C

    • • • B01F

    -+· B01X

    05-Jul-94

  • Construction 100.0% -.. C04H 90.0% -C04M

    -6-C04E 80.0%

    .,,,-te~·c04L

    70.0% -C04C

    • • • C04F Ill 60.0% Ill -+· C04X e - 50.0% .!!! c '#. 40.0%

    30.0%

    20.0%

    10.0%

    0.0% -20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-13. Alligator Cracking for Site C04

    Construction 100.0%

    • .. C04H

    90.0% -C04M

    80.0% """"6-CQ4E

    "''·K"''C04l 70.0%

    -C04C

    Ill 60.0% Ill ·•·C04F e - 50.0% .!!! c ~ 0 40.0%

    30.0%

    20.0%

    10.0%

    0.0% ...... - ... - - ... - .. '!8 ..

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-14. Bleeding for Site C04

    39

  • en en e ... en i5 ~ 0

    en en e ... en i5 ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    Construction ... C04H -C04M

    --C04E

    .,,,-M.,,·C04L

    -ll-C04C

    • •·C04F

    -+• C04X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-15. Block Cracking for Site C04

    Construction

    . - ..._. ...... -. .._ -

    • .. C04H

    -C04M

    --ti.-C04E

    ·· .. K··· C04L

    -ll-C04C

    • • • C04F

    -+· C04X

    '-+-·------------·+ 4.0% : .... · - . -- .... - - - - - - . - .. ...... ___ _

    -- . -. -- --2.0%

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-16. Longitudinal and Transverse Cracking for Site C04

    40

  • (/) (/)

    ~ -.!!? c ~ 0

    (/) (/)

    ~ -(/) i:5 ~ 0

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    0.0% .

    20-Feb-93

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    Construction .... C04H -C04M

    --C04E

    .,,,-K.,,·C04L

    -C04C

    • • • C04F

    -+· C04X

    -31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-17. Longitudinal Cracking in the Wheelpaths

    Construction

    •.,. C04H

    -C04M

    --C04E

    .... IC··· C04L

    -C04C

    • • • C04F

    -+• C04X

    _______ .. 0.0% -H------------------.......... -..... -------------l

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-18. Ravelling for Site C04

    41

  • tJI tJI ~ .... tJI

    i:3 ~ 0

    tJI tJI ~ ....

    .!:!? 0 ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    ... - -0.0% 20-Feb-93

    100.0%

    90.0%

    80.0%

    70.0%

    .. -60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction

    - .. D04H -D04M

    --D04E

    "'"·l

  • Cl) Cl)

    ~ ..... Cl)

    0 ~ 0

    Cl) Cl)

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    ~ 8.0% ti 0 ~ 6.0%

    4.0%

    2.0%

    )( •..... ······.· ........

    Construction

    -.. 004H -004M

    .......&.-D04E

    .,,,-l

  • Ill Ill

    ~ -Ill c ~

    Ill VI ~ -Ill c ~ 0

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    0.0% ~·· 20-Feb-93

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • .. 004H

    -CXJ4M

    -6-CXJ4E

    w.•~w. CXJ4L

    -004C

    • • • 004F

    -+• 004X

    05-Jul-94

    Figure A-23. Longitudinal Cracking in the Wheelpaths

    Construction

    • .. 004H

    -CXJ4M

    --CXJ4E

    ····IC··· CXJ4L -004C

    -•·D04F

    -+• 004X

    0.0% -H-----... --------------------------1 20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-24. Ravelling for Site D04

    44

  • (/) (/) e +J (/)

    0 ~ 0

    (/) (/)

    e +J

    .!!? c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction ... E06H -E06M

    """"6-EOOE

    ...... IC'" E06L

    -E06C

    • • • E06F

    -+· E06X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-25. Alligator Cracking for Site E06

    Construction

    • .. E06H -E06M --6 - E06E .... IC ... E06L

    -E06C • • • E06F -+· E06X

    - " 50.0%

    .. .. . ~ ............ -... flt : .................... .. fl"

    -N ' -40.0%

    - • '!"" .. .. .. .. 30.0%

    20.0%

    10.0% , 0.0%

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-26. Bleeding for Site E06

    45

  • (/) (/)

    ~ ... .!!? c ~ 0

    (/) (/)

    ~ ... (/)

    c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    0.0% 20-Feb-93

    Construction .... E06H -E06M

    ........e.-EOOE

    ····~ .. ··EOOL

    -E06C

    • • • E06F

    -+· E06X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-27. Block Cracking for Site E06

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • ... E06H

    -E06M

    '"'"'"°"-EOOE

    '""'·" ., .. , E06L

    -E06C

    • • • E06F

    -+• E06X

    05-Jul-94

    Figure A-28. Longitudinal and Transverse Cracking for Site E06

    46

  • Cl) Cl) e ... • !!? c ~ 0

    Cl) Cl) e ...

    .!!? c ~

    Construction

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    0.0%

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • ... E06H

    -E06M

    --1>-E06E

    ····tc .... E06L

    -E06C

    • • • E06F

    -+· E06X

    05-Jul-94

    Figure A-29. Longitudinal Cracking in the Wheelpaths for Site E06

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    -0.0% 20-Feb-93

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    47

    -... E06H -E06M

    --E06E

    ····>< ···E06L

    -E06C

    ·•·E06F

    --+· E06X

    27-Mar-94 05-Jul-94

  • (/) (/)

    I!:! -(/) c '#.

    (/) (/)

    I!:! -(/) c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    -0.0% 20-Feb-93

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction ... F06H -F06M

    """"lll-F06E

    ····K····F06L

    -F06C

    ·•·F06F

    -+· F06X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-31. Alligator Cracking for Site F06

    Construction

    .. ..... ..

    ...

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    Figure A-32. Bleeding for Site F06

    48

    • .- F06H

    -F06M

    -6-F06E

    ···->< ···F06L

    -ll--F06C

    ·•·F06F

    -+· F06X

    ... ..

    05-Jul-94

  • (/) (/)

    !!! -(/) c ~ 0

    (/) (/)

    !!! -(/) c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    8.0%

    6.0% l\

    4.0%

    2.0%

    0.0% 20-Feb-93

    Construction ... F06H -F06M

    --6-F06E

    ····'>

  • (I) (I)

    ~ ..... (I)

    c :::!;! 0

    (I) (I)

    ~ ..... (I)

    c :::!;! 0

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    X·., .

    0.0% 20-Feb-93

    ..... ., •• , •• ,J'

    Construction

    ·~· .. 31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    -.. F06H -F06M

    '"""""6-F06E

    ····~····F06L

    -F06C

    . • • F06F -- F06X

    27-Mar-94 05-Jul-94

    Figure A-35. Longitudinal Cracking in the Wheelpaths for Site F06

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction

    . I , .

    ' ,

    I. ,

    , , , I

    J, I ¥ ,

    , , /,'

    , , , ,

    1.: ,,

    ,. t' ,,.

    ,. _/

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    Figure A-36. Ravelling for Site F06

    50

    , '

    I .• , . ' I

    I

    I , . , I .

    ... F06H -F06M

    --F06E

    .... >< ••• F06L

    -F06C

    • • • F06F

    --+· F06X

    05-Jul-94

  • Ill Ill e -.!!? 0 ~ 0

    Ill Ill e -.!!? 0 ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    -0.0% 20-Feb-93

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction

    - ... G08H -GOBM

    --GOBE

    .... l

  • (/) (/)

    e ... (/)

    i3 ~ C>

    (/) (/)

    e ... (/)

    i3 ~ C>

    100.0%

    90.0%

    S0.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    0.0% 20-Feb-93

    Construction

    -... GOSH -GOSM

    """"A-GOSE

    ····IC .. ·GOSL

    -Gose

    • • • GOSF

    -+• GOSX

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-39. Block Cracking for Site G08

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    •.., GOSH

    -GOSM

    --GOSE

    m.-l(m GOSL

    -GOSC

    " • • GOOF

    -+· GOSX

    05-Jul-94

    Figure A-40. Longitudinal and Transverse Cracking for Site G08

    52

  • (/) (/)

    e -.!!? c ~ 0

    Cl) Cl)

    ~ ... Cl)

    c cf!.

    Construction

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0% ... ~- . " -... ... - It - - . 0.0%

    20-Feb-93 31-May-93

    - "

    -.. G08H -GOBM

    -t.-GOBE

    w-.)(w·GOBL

    -lf-GOBC

    - • • GOBF --t· GOBX

    --· ... -..Y!':r -08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-41. Longitudinal Cracking in the Wheelpaths for Site G08

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    ~

    0.0%

    20-Feb-93

    Construction

    31-May-93 OS-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    Figure A-42. Ravelling for Site G08

    53

    -... GOSH -GOSM

    --GOSE

    "'·"l< .,,, GOSL

    -Gase

    • • • GOSF

    -+~ GOSX

    05-Jul-94

  • Cl) Cl)

    ~ ... Cl)

    c ~ Cl

    100.0%

    90.0%

    S0.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    -0.0%

    20-Feb-93

    Construction

    - .. HOSH -HOSM

    .......i.-HOSE

    W•"•X""·HOSL

    -Hose

    ·•-HOSF

    -+- HOSX

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-43. Alligator Cracking for Site HOS

    Construction 100.0%-.--.lr-----,.-_-.-.-.-.-.-.~.~.,,....,,..~.,....,...~~---~-~----.-.-~~-~.-=o.-llA!---. - .. - /

    30.0%

    20.0%

    10.0%

    ...... ··

    / ,x / _.,, .

    I_,,·· ,

    _.,.: I

    ,., _..// ; " .......... /;

    .... / .... ·· / ;

    ,..-. • .. HOSH -HOSM )f

    ...••• -

    / ;/ ./ '/

    / , ;/ / , ,,. /

    - ,If ; / ; /

    / " ,.,. ,/ "/

    '/ ./" ,,.,.

    --1>-HOSE """·X""'HOSL

    -HOSC ·•·HOSF

    -+• HOSX

    ./p:;...-.-:/-

    0.0% +-------------------..... !::.....-+-------+--------1 20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-44. Bleeding for Site HOS

    54

  • (/) (/)

    ~ -.!!? c ~ 0

    Construction 100.0% -,.------------------------------~

    90.0%

    S0.0%

    70.0% \

    ' ' 60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0%

    20-Feb-93

    .. . . • .. HOSH -HOSM

    -t. - HOSE .. "l< ··· HOSL

    -Hose - • - HOSF

    -+· HOSX

    31-May-93 OS-Sep-93

    . . . ': .. - . - - - - . -· ... -... -.. '·

    '+

    17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-45. Block Cracking for Site H08

    Construction

    - . . ..

    31-May-93

    . . .

    OS-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • .. HOSH

    -HOSM

    .....i.-HOSE

    unl(m HOSL

    -Hose

    ·•·HOSF

    -+· HOSX

    05-Jul-94

    Figure A-46. Longitudinal and Transverse Cracking for Site H08

    55

  • Cl) Cl)

    f!:! -.!!! c '#.

    Cl) Cl)

    f!:! -.!!! c ~ 0

    Construction

    14.0%

    12.0%

    10.0%

    S.0%

    6.0%

    4.0%

    2.0%

    0.0%

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    •.., HOSH

    -HOSM

    ......il.-HOBE

  • VI VI !!:! -.!!! c ~ 0

    VI VI !!:! -VI i:5 ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0%

    20-Feb-93

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0%

    20-Feb-93

    Construction .... 109H -109M

    """'"6-J09E

    ""·"X"'·I09L

    -109C

    • • • 109F

    ......... 109X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-49. Alligator Cracking for Site 109

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    • ... 109H

    -109M

    -~100E

    un}(m 109L

    -ill-109C

    • • • 109F

    --+· 109X

    --.. -. ..

    27-Mar-94 05-Jul-94

    Figure A-50. Bleeding for Site 109

    57

  • I/) I/)

    ~ ... I/)

    c ~ 0

    I/) I/)

    ~ ... • !!? c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    0.0% 20-Feb-93

    Construction

    -.. 109H -109M

    """"'"6-109E

    "'···X"'·I09L

    -lll-109C

    • " • 109F

    -+· 109X

    -31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-51. Block Cracking for Site 109

    Construction

    .: -. -_ -_: -_: ·.....:. : ~ ~ : :

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    27-Mar-94

    • .. 109H

    -109M

    ......a.-109E

    ·······1

  • (I) (I) e -(I) i5 ~ Cl

    (I) (I) e -(I) i5 ~ Cl

    Construction

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    • .. 109H

    -109M

    ....-o6-!09E

    ""···X...,·109L

    -W-109C

    • • • 109F

    --+· 109X

    05-Jul-94

    Figure A-53. Longitudinal Cracking in the Wheelpaths for Site I09

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    ..... 0.0% 20-Feb-93

    , / ,

    , --

    Construction

    ""' ' , ' , ' / ' , ' , '-.,,

    / ' • ,

    ' ; / ' ' ; ,

    ./ , ,.

    ) ' ,

    / ·' , , .

    / . . , , , . . . . . . -- --•·' - ---- - - - - -31-May-93 08-Sep-93 17-Dec-93 27-Mar-94

    Date Inspected

    Figure A-54. Ravelling for Site I09

    59

    -... 109H -109M

    -A-!09E

    -.-.·.·X"'!09L

    -W-109C

    - • • 109F --+- 109X

    ' ' .......

    ' '

    ).. , ; .. . ,

    ;

    - -- .. 05-Jul-94

  • en en e -en Ci ~ 0

    en en e -.~ c ~ 0

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93

    Construction -.. J10H -J10M

    -A-J10E

    ····X ···J10L

    -lf-J10C

    • • • J10F

    -+· J10X

    31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-55. Alligator Cracking for Site JlO

    Construction

    .. .. .. - --- -- ........ .... ,_.... ....... - y.,

    • .. J10H

    -J10M

    -ll-J10E

    '-"'-1< """J10L

    -lf-J10C

    • • • J10F

    -+· J10X

    ...

    - .. - ·+ 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-56. Bleeding for Site Jl 0

    60

  • Construction 100.0% -.. J10H

    90.0% -J10M

    -6-J10E 80.0%

    ""IC"' J10L

    70.0% --llf--J10C

    • • - J10F (/I 60.0% (/I -+· J10X

    e - 50.0% (/I c ~ 0 40.0%

    30.0%

    20.0%

    10.0%

    0.0% 20-Feb-93 31-May-93 08-Sep-93 17-Dec-93 27-Mar-94 05-Jul-94

    Date Inspected

    Figure A-57. Block Cracking for Site no

    Construction

    -.. J10H 14.0%

    -J10M

    -.6-J10E 12.0%

    ...... ··l

  • (/) (/)

    e! -(/) Ci ~ 0

    (/) (/)

    e! -(/) Ci ~ 0

    14.0%

    12.0%

    10.0%

    8.0%

    6.0%

    4.0%

    2.0%

    ~

    0.0% 20-Feb-93

    Construction

    31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    -.. J10H -J10M

    ....,.._J10E

    ""·I< ...... J10L

    -W-J10C

    .... - J10F

    -+· J10X

    27-Mar-94 05-Jul-94

    Figure A-59. Longitudinal Cracking in the Wheelpaths for Site JlO

    Construction 60.0% -r--------,------------------=====

    50.0%

    40.0%

    30.0%

    20.0%

    .. 10.0%

    • .. J10H

    -J10M

    ----4-J10E

    ........ l

  • (I) (I)

    2:! -(I) c ~ 0

    Cl) Cl)

    2:! -(I) c ~ 0

    Construction 100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0%

    10.0%

    ~ 0.0%

    20-Feb-93 31-May-93 08-Sep-93 17-Dec-93

    Date Inspected

    - .. K13H -K13M

    .......i.~K13E

    ----x ,,. K13L

    -t1-K13C

    • • • K13F

    -+· K13X

    27-Mar-94 05-Jul-94

    Figure A-61. Alligator Cracking for Site K13

    Construction 100.0%

    90.0%

    80.0%

    70.0%

    60.0%

    50.0%

    40.0%

    30.0%

    20.0% I

    10.0% , I

    I

    0.0%

    20-Feb-93 31-May-93

    .....................

    I

    ,

    ............... ,. .......

    08-Sep-93 17-Dec-93 27-Mar-94

    Da