subcontractor delay
TRANSCRIPT
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 1/34
Can a Subcontractor Have a Critical Path DelayCan a Subcontractor Have a Critical Path Delay
When the GC Does Not?When the GC Does Not?
Christopher Carson, PSP
,
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 2/34
Shannon Campbell, PSP
• Degree: – B.S. Civil Engineering
– M.S. Engineering Management
• University:
– B.S – United States Military Academy
– M.S. – University of Missouri-Rolla
• Years of Experience: – 10 years
2
• Professional Field: – Engineering Claims Consultant
• Something you do not know about me: – Served 6.5 years in the military as an army engineer travelling to 14 different countries across 5
continents – many of these visits were to view construction projects throughout the world.
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 3/34
Chris Carson, PSP, CCM, PMP
• Corporate Director of Project Controls, Alpha Corporation – Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project
managers in multiple office locations, as well as analysis, work product, and testimony
– Developed and manages the in-house project controls training program at Alpha
• Certifications:
– PSP (Planning & Scheduling Professional – AACEi) – CCM (Certified Construction Manager - CMAA)
– PMP (Project Management Professional – PMI)
• University: University of Virginia, Mechanical Engineering, 1972
• Professional Field: 38 years of experience in Construction Management Services specializing in
33
, , ,
• Active in AACEi (Association for the Advancement of Cost Estimating International) – Author of Recommended Practices in Scheduling & Forensic Schedule Analysis RP
• Active in PMI (Project Management Institute) College of Scheduling
– Vice President of Scheduling Excellence
– Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines forScheduling and Schedule Impact Analysis
– Serving on team writing Best Practices for Scheduling for GAO
• Active in CMAA (Construction Management Association of America)
– Served on committee revising Time Management Chapter of CMAA’s CM Standards of Practice
• Active in Planning Planet (global planning association)
– Chief Editor for US, writing Planner Users’ Guide, developing accreditation Guild for planners
• Something you don’t know about me: I’m a glider co-pilot, see picture
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 4/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Introduction• Entitlement to Delay Damages only when there is Critical Path
Delay to Project Completion
• What happens when an owner impact extends the time asubcontractor is on the job but the impact does NOT extend the
Project Completion?
4
• What, if any, entitlement does the Subcontractor have to recoverdelay-related costs?
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 5/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act
• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
5
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 6/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act
• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
6
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 7/34
As–Planned Schedule - Office Building
Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Foundations
Structural Steel
Roof
CurtainwallNTP
4
4
1
Interior Finishes PunchListCoord. Dwgs.
Fab/Deliver MEP Rough In MEP Finishes3
43
4
4
3
1
7
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 8/34
As–Planned v. As–Built Schedule
Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Foundations
Structural Steel
Roof
Curtainwall
Interior Finishes PunchListCoord. Dwgs.
NTP
4
4
1
4
4
4
3
43 3
3 Wks
Foundations
Structural Steel
Roof
CurtainwallInterior Finishes Punch
ListCoord. Dwgs.
Fab/Deliver MEP Rough In MEP Finishes
NTP
4
4
1
3
43
4
4
3
1
8
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 9/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act
• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
9
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 10/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Pass-Through Claims• Privity of Contract
• Recovery of Damages through a Pass Through Claim
• Definition:
A pass-through claim is a claim:
10
1) by a Subcontractor who has incurred damages due to theactions of the Owner/Government with whom it has no
contract; and
2) submitted by the GC who has a contractual relationship with
both the Subcontractor and the Owner/Government.
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 11/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Severin Doctrine
“a prime contractor may sue the Government on behalf of its
Subcontractor, in the nature of a pass-through suit, for costsincurred by the Subcontractor [due to the Government’s
conduct] . . . [i]f the prime contractor proves its liability to the
11
. . .
showing [which] overcomes the objection to the lack of privity
between the Government and the Subcontractor.”
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 12/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Liquidating Agreements• Acknowledgement of liability to the Subcontractor
– Satisfies the Severin doctrine requirement that the GC is technically and legally liable to the
subcontractor for the claim before submitting to Government
• Limits liability to the amount that a prime is able to recover from the
owner – Protects the prime
12
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 13/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
E.R. Mitchell Constr. Co. v. Danzig
• Basics of the case
• Players
• Facts
• No dispute of Federal Government liability
13
• Government approved schedule• Government put on notice of damages to both GC and
subcontractor
• Owner responsible delays not of project schedule critical path
• Results
• Subcontractor satisfied all requirements for entitlement to
Eichleay damages
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 14/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Pass Through Claims -
General Information
• J.L. Simmons v. United States – provides the definition of the
requirements of a liquidating agreement
• Case law varies among State courts
14
• Benefits of the Pass Through Claim
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 15/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act
• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
15
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 16/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
The Miller Act
• Basic Purpose – means for a subcontractor to receive payment for labor
and materials furnished Players• Successful recovery of delay damages through the Miller Act
16
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 17/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
The Miller Act -
Recovering Delay Damages
• Generally recoverable if characterized as increased cost of labor andmaterials – other costs have been successfully recovered
• Not relevant whether fault lies with the Owner of the Prime
17
• een as e on y a erna ve n many cases or a su con rac or o recover
increased costs
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 18/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
The Miller Act -
Considerations & Recommendations
• Is a payment bond required?
• Was the payment bond actually attained?
• Timely initiation of a payment bond
18
• Limited liability by surety – multiple claimants may require each to take apro rata share of the penal sum
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 19/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
19
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 20/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
No Damage for Delay (NDFD)
• Basic Purpose – protects an owner or GC from paying monetary damages
when a project is delayed• Sample Clause
“
20
for damages because of hindrance or delay from any cause in the
progress of the work, whether such hindrances or delays be avoidable or
unavoidable.”
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 21/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
No Damage for Delay - Enforceability
• Unenforceable in many states
• Established exceptions otherwise –• (1) not contemplated by the parties;
• (2) so unreasonable in length as to amount to an abandonment of
21
• (3) caused by acts of bad faith or fraud by the Owner; or
• (4) caused by active interference by the Owner.
• A fifth exception is also sometimes cited - delays caused by gross
negligence.
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 22/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
No Damage for Delay – Considerations
• Sometimes incorporated by reference or in a “Flow-Down” Provision
• May be defense for an owner when presented with a pass through claim• Has been circumvented by use of a liquidating agreement as already
discussed
22
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 23/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
23
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 24/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Review and Negotiation of the Contract
• Timely Notice• Waiver of Rights
• Good Documentation
24
• nvo vement n t e ase ne c e u e an u sequent p ates
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 25/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Review and Negotiation of the Contract
• Subcontractor should
• Carefully review contract, especially from a legal perspective
• Assume any NDFD will be enforced
• Attem t to remove or reduce eneral assum tion of dela risk
25
• Reduce to specific risks that are under sub’s control
• Watch for verbiage that limits recovery to “active interference”
only by Owner
• Attempt to include language that provides a “Grace Period” that
delays must exceed to allow an adjustment for delays
• Allows a contingency for that period to be carried
• Seek language related to specific events, proof required or price
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 26/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Timely Notice
• Assume that notice requirements will be enforced and meet them• Keep the GC informed so he can inform the Owner
• Owner then has opportunity to participate in mitigation
26
• wner must e ma e aware o e ays contemporaneous y
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 27/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Waiver of Rights
• Watch for waiver language• Could be part of a payment application or certification
• Could be part of a change order indicating all past claims are
27
• Provide reservation of rights language to any document if
contemplating submitting a delay claim
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 28/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Good Documentation
• Key to proving damages• Accurate and contemporaneous
• All documents including bid documentation, daily reports, pay
28
, , ,
update scheduling process, minutes, resources both planned andactual
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 29/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Involvement in the Baseline Schedule and Subsequent Updates
• Ensure input into all schedules• Review any updates provided by GC to ensure no acceleration or
stacking of crews are planned
29
• Note subcontractor’s expectations for period of performance
• Includes planned resources in crews and composition
• Stockpiling and materials distribution needs
• Watch for reduction in durations or overlapping of work• Watch for shifts in start dates, access dates, or completion dates
• Document any problems with schedules
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 30/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Strategies for Proving a Subcontractor’s Delay Claim
• Involvement in the Baseline Schedule and Subsequent Updates
• Review total float for subcontractors’ work to identify criticality atproject schedule
• Attempt to have the impacts to the subcontractor shown on the
30
• If failed, document the delay or disruption
• Recognize that the Measured Mile is the most effective analysis for
loss of efficiency
• Requires good resource information
• Related to the schedule to prove impacted & unimpacted times
• Includes participation in any REAs submitted by GC – subcontractors
can lose their rights against the Owner if not involved with REAs
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 31/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Topics to be Covered• Example
• Pass-Through Claims
• The Miller Act• Combating the No Damage For Delay Clause
• Strategies for Proving a Subcontractor’s Delay Claim
31
• From the Owner’s Standpoint
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 32/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
From the Owner’s Standpoint
• Provide fair allocation of risk
• Assign risk to the party most able to control it• This will reduce claims efforts
• Provide timely and fair review and approval of legitimate time extension
32
requests
• Follow the same general rules as outlined in the strategies for the
Subcontractor
• Should an Owner be able recover equivalent damages from a
Subcontractor due to Subcontractor impacts?
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 33/34
Can a Subcontractor Have a Critical Path Delay When the GC Does Not?
Conclusion• Negotiate the Contract
• Know the Contract
• Be involved in the schedule from start to finish• Maintain accurate documentation
• Seek legal advice
33
8/2/2019 Subcontractor Delay
http://slidepdf.com/reader/full/subcontractor-delay 34/34
Can a Subcontractor Have a Critical Path DelayCan a Subcontractor Have a Critical Path Delay
When the GC Does Not?When the GC Does Not?
Shannon Cam bell PSP
Questions?
Chris Carson, PSP