subcontractor delay

34
8/2/2019 Subcontractor Delay http://slidepdf.com/reader/full/subcontractor-delay 1/34 Can a Subcontractor Have a Critical Path Delay Can a Subcontractor Have a Critical Path Delay When the GC Does Not? When the GC Does Not? Christopher Carson, PSP ,

Upload: errajeshkumar

Post on 05-Apr-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 1/34

Can a Subcontractor Have a Critical Path DelayCan a Subcontractor Have a Critical Path Delay

When the GC Does Not?When the GC Does Not?

Christopher Carson, PSP

,

Page 2: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 2/34

Shannon Campbell, PSP

• Degree: – B.S. Civil Engineering

 – M.S. Engineering Management

• University:

 – B.S – United States Military Academy

 – M.S. – University of Missouri-Rolla

• Years of Experience: – 10 years

2

• Professional Field: – Engineering Claims Consultant

• Something you do not know about me: – Served 6.5 years in the military as an army engineer travelling to 14 different countries across 5

continents – many of these visits were to view construction projects throughout the world.

Page 3: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 3/34

Chris Carson, PSP, CCM, PMP

• Corporate Director of Project Controls, Alpha Corporation – Responsible for standards, processes, and procedures for a team of schedulers, analysts, and project

managers in multiple office locations, as well as analysis, work product, and testimony

 – Developed and manages the in-house project controls training program at Alpha

• Certifications:

 – PSP (Planning & Scheduling Professional – AACEi) – CCM (Certified Construction Manager - CMAA)

 – PMP (Project Management Professional – PMI)

• University: University of Virginia, Mechanical Engineering, 1972

• Professional Field: 38 years of experience in Construction Management Services specializing in

33

, , ,

• Active in AACEi (Association for the Advancement of Cost Estimating International) – Author of Recommended Practices in Scheduling & Forensic Schedule Analysis RP

• Active in PMI (Project Management Institute) College of Scheduling

 – Vice President of Scheduling Excellence

 – Managing Director for SEI (Scheduling Excellence Initiative) writing Best Practices and Guidelines forScheduling and Schedule Impact Analysis

 – Serving on team writing Best Practices for Scheduling for GAO

• Active in CMAA (Construction Management Association of America)

 – Served on committee revising Time Management Chapter of CMAA’s CM Standards of Practice

• Active in Planning Planet (global planning association)

 – Chief Editor for US, writing Planner Users’ Guide, developing accreditation Guild for planners

• Something you don’t know about me: I’m a glider co-pilot, see picture

Page 4: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 4/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Introduction• Entitlement to Delay Damages only when there is Critical Path

Delay to Project Completion

• What happens when an owner impact extends the time asubcontractor is on the job but the impact does NOT extend the

Project Completion?

 

4

• What, if any, entitlement does the Subcontractor have to recoverdelay-related costs?

Page 5: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 5/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act

• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

5

• From the Owner’s Standpoint

Page 6: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 6/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act

• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

6

• From the Owner’s Standpoint

Page 7: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 7/34

As–Planned Schedule - Office Building

Months

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Foundations

Structural Steel

Roof

CurtainwallNTP

4

4

1

Interior Finishes PunchListCoord. Dwgs.

Fab/Deliver MEP Rough In MEP Finishes3

43

4

4

3

1

7

Page 8: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 8/34

As–Planned v. As–Built Schedule

Months

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Foundations

Structural Steel

Roof

Curtainwall

Interior Finishes PunchListCoord. Dwgs.

 

NTP

4

4

1

4

4

4

 3

43 3

3 Wks

Foundations

Structural Steel

Roof

CurtainwallInterior Finishes Punch

ListCoord. Dwgs.

Fab/Deliver MEP Rough In MEP Finishes

NTP

4

4

1

3

43

4

4

3

1

8

Page 9: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 9/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act

• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

9

• From the Owner’s Standpoint

Page 10: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 10/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Pass-Through Claims• Privity of Contract

• Recovery of Damages through a Pass Through Claim

• Definition:

A pass-through claim is a claim:

10

1) by a Subcontractor who has incurred damages due to theactions of the Owner/Government with whom it has no

contract; and

2) submitted by the GC who has a contractual relationship with

both the Subcontractor and the Owner/Government.

Page 11: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 11/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Severin Doctrine

“a prime contractor may sue the Government on behalf of its

Subcontractor, in the nature of a pass-through suit, for costsincurred by the Subcontractor [due to the Government’s

conduct] . . . [i]f the prime contractor proves its liability to the

11

. . .

showing [which] overcomes the objection to the lack of privity

between the Government and the Subcontractor.”

Page 12: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 12/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Liquidating Agreements• Acknowledgement of liability to the Subcontractor

 – Satisfies the Severin doctrine requirement that the GC is technically and legally liable to the

subcontractor for the claim before submitting to Government

• Limits liability to the amount that a prime is able to recover from the

owner – Protects the prime

12

Page 13: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 13/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

E.R. Mitchell Constr. Co. v. Danzig

• Basics of the case

• Players

• Facts

• No dispute of Federal Government liability

 

13

• Government approved schedule• Government put on notice of damages to both GC and

subcontractor

• Owner responsible delays not of project schedule critical path

• Results

• Subcontractor satisfied all requirements for entitlement to

Eichleay damages

Page 14: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 14/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Pass Through Claims -

General Information

•  J.L. Simmons v. United States – provides the definition of the

requirements of a liquidating agreement

• Case law varies among State courts

 

14

• Benefits of the Pass Through Claim

Page 15: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 15/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act

• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

15

• From the Owner’s Standpoint

Page 16: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 16/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

The Miller Act

• Basic Purpose – means for a subcontractor to receive payment for labor

and materials furnished Players• Successful recovery of delay damages through the Miller Act

16

Page 17: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 17/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

The Miller Act -

Recovering Delay Damages

• Generally recoverable if characterized as increased cost of labor andmaterials – other costs have been successfully recovered

• Not relevant whether fault lies with the Owner of the Prime

 

17

• een as e on y a erna ve n many cases or a su con rac or o recover

increased costs

Page 18: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 18/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

The Miller Act -

Considerations & Recommendations

• Is a payment bond required?

• Was the payment bond actually attained?

• Timely initiation of a payment bond

 

18

• Limited liability by surety – multiple claimants may require each to take apro rata share of the penal sum

Page 19: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 19/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

19

• From the Owner’s Standpoint

Page 20: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 20/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

No Damage for Delay (NDFD)

• Basic Purpose – protects an owner or GC from paying monetary damages

when a project is delayed• Sample Clause

“ 

20

 

 for damages because of hindrance or delay from any cause in the

 progress of the work, whether such hindrances or delays be avoidable or 

unavoidable.” 

Page 21: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 21/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

No Damage for Delay - Enforceability

• Unenforceable in many states

• Established exceptions otherwise –• (1) not contemplated by the parties;

• (2) so unreasonable in length as to amount to an abandonment of 

21

 

• (3) caused by acts of bad faith or fraud by the Owner; or

• (4) caused by active interference by the Owner.

• A fifth exception is also sometimes cited - delays caused by gross

negligence.

Page 22: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 22/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

No Damage for Delay – Considerations

• Sometimes incorporated by reference or in a “Flow-Down” Provision

• May be defense for an owner when presented with a pass through claim• Has been circumvented by use of a liquidating agreement as already

discussed

22

Page 23: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 23/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

23

• From the Owner’s Standpoint

Page 24: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 24/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Review and Negotiation of the Contract

• Timely Notice• Waiver of Rights

• Good Documentation

 

24

• nvo vement n t e ase ne c e u e an u sequent p ates

Page 25: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 25/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Review and Negotiation of the Contract

• Subcontractor should

• Carefully review contract, especially from a legal perspective

• Assume any NDFD will be enforced

• Attem t to remove or reduce eneral assum tion of dela risk

25

 

• Reduce to specific risks that are under sub’s control

• Watch for verbiage that limits recovery to “active interference”

only by Owner

• Attempt to include language that provides a “Grace Period” that

delays must exceed to allow an adjustment for delays

• Allows a contingency for that period to be carried

• Seek language related to specific events, proof required or price

Page 26: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 26/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Timely Notice

• Assume that notice requirements will be enforced and meet them• Keep the GC informed so he can inform the Owner

• Owner then has opportunity to participate in mitigation

 

26

• wner must e ma e aware o e ays contemporaneous y

Page 27: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 27/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Waiver of Rights

• Watch for waiver language• Could be part of a payment application or certification

• Could be part of a change order indicating all past claims are

27

 

• Provide reservation of rights language to any document if 

contemplating submitting a delay claim

Page 28: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 28/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Good Documentation

• Key to proving damages• Accurate and contemporaneous

• All documents including bid documentation, daily reports, pay

28

, , ,

update scheduling process, minutes, resources both planned andactual

Page 29: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 29/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Involvement in the Baseline Schedule and Subsequent Updates

• Ensure input into all schedules• Review any updates provided by GC to ensure no acceleration or

stacking of crews are planned

 

29

 

• Note subcontractor’s expectations for period of performance

• Includes planned resources in crews and composition

• Stockpiling and materials distribution needs

• Watch for reduction in durations or overlapping of work• Watch for shifts in start dates, access dates, or completion dates

• Document any problems with schedules

Page 30: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 30/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Strategies for Proving a Subcontractor’s Delay Claim

• Involvement in the Baseline Schedule and Subsequent Updates

• Review total float for subcontractors’ work to identify criticality atproject schedule

• Attempt to have the impacts to the subcontractor shown on the

30

• If failed, document the delay or disruption

• Recognize that the Measured Mile is the most effective analysis for

loss of efficiency

• Requires good resource information

• Related to the schedule to prove impacted & unimpacted times

• Includes participation in any REAs submitted by GC – subcontractors

can lose their rights against the Owner if not involved with REAs

Page 31: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 31/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Topics to be Covered• Example

• Pass-Through Claims

• The Miller Act• Combating the No Damage For Delay Clause

• Strategies for Proving a Subcontractor’s Delay Claim

 

31

• From the Owner’s Standpoint

Page 32: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 32/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

From the Owner’s Standpoint

• Provide fair allocation of risk

• Assign risk to the party most able to control it• This will reduce claims efforts

• Provide timely and fair review and approval of legitimate time extension

32

requests

• Follow the same general rules as outlined in the strategies for the

Subcontractor

• Should an Owner be able recover equivalent damages from a

Subcontractor due to Subcontractor impacts?

Page 33: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 33/34

Can a Subcontractor Have a Critical Path Delay When the GC Does Not?

Conclusion• Negotiate the Contract

• Know the Contract

• Be involved in the schedule from start to finish• Maintain accurate documentation

• Seek legal advice

33

Page 34: Subcontractor Delay

8/2/2019 Subcontractor Delay

http://slidepdf.com/reader/full/subcontractor-delay 34/34

Can a Subcontractor Have a Critical Path DelayCan a Subcontractor Have a Critical Path Delay

When the GC Does Not?When the GC Does Not?

Shannon Cam bell PSP

Questions? 

Chris Carson, PSP