CP-45:An Implementation Guide to Subcontractor Management
Natalie Scicluna, Deltek
Session OverviewMost companies partner and work with subcontractors on a day to day basis and it is vital to successful contract completion to be able to smoothly and accurately capture subcontractor costs. This session will walk through the implementation and setup of Subcontract Management in order to streamline their invoicing and reconciliation process.
*Understand the steps involved in setting up a subcontractor from PO to timesheet to invoice
*Tips and tricks for a successful implementation
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 2
Meeting Agenda1. Managing Subcontractor Information
2. Subcontractor Management Process Flow
3. Subcontractor Agreements
4. Work Assignments
5. Subcontractor Time & Expense Entry
6. Subcontractor Invoice Creation
7. Payments to Subcontractors
8. Billing Invoice Creation
9. Implementation Tips & Tricks
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 3
Managing Subcontractor Information
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 4
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 5
» Setup Subcontractor Companies as
Vendors
» Select Subcontractor check box to
denote use of Sub in Subcontractor
Management module
» This check box is also used for
reporting purposes
» Manage Subcontractor Employees
as Vendor Employees tied to
Subcontractor Company
Subcontractor Setup
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 6
» Link Vendor Employees to
Subcontractor record
» One-One or Multiple-One
» Manage Labor Information and
maintain Historical records
» Manage Skills, Training, Security
and Company Property
Subcontractor Employees
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 7
» Link Subcontract Company to
Project
» Link Subcontract Employees to
Project via Vendor Employee
Workforce
» Assign PLCs to Subcontract
Employees
» Vendor Employee Workforce can be
used for subcontractor labor
assignment
Subcontractor Workforce
Subcontractor Management Process Flow
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 8
Subcontractor Management Process Flow
9
• Identify opportunities & the need for subcontractors
• Link POs to Subcontract record
Manage Subcontracts
• Subcontractor Agreement POs are negotiated and approved
Subcontractor Agreement • Work Assignments are
created from the PO
• Once approved, are available for contractor resources for time recording
Work Assignments
• Subcontractors charge labor against work assignments authorized
• Project Managers can review/approve labor along with monitoring budgets
Time Collection • Subcontractor resources’
approved time creates the subcontractor invoice
• Invoice approval creates the PO Voucher
Invoice/PO Voucher
• Once the PO Voucher is posted, the PO is relieved and subcontractor time is ready to be billed to the final customer
Project Billing
CONFIDENTIAL © Deltek, Inc. All Rights Reserved
Manage Subcontracts
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 10
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 11
Manage Subcontracts
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 12
» Part of the Contracts Management
Module (optional module)
» Subcontractor information is tied to
a Vendor ID
» Multiple subs/vendors can be linked
to one contract record
» Funding for each individual sub can
be maintained by Subcontract ID
Manage Subcontracts
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 13
» Manage key subcontract details
» Security Requirements
» ITAR Status
» NAICS Codes
» Business Classification
Requirements specific to agreement
Subcontract Info
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 14
» Copy FAR Clauses from Prime
Contract
» Determine what is Applicable to
Subcontract
» Ensure Vendors are aware of
their responsibilities
» Send Clauses/Provisions to PO for
printing
FAR Clauses and Provisions
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 15
» Specific Requisitions and Purchase Orders tied to the subcontract record can be linked in the screen
» Users can view the status of the Reqs and POs
» Hyperlinks allow users to drill into the Reqs and POs from the subcontract record
» Use Security Rights to control screen access
» Coming soon: Initiate Purchase Req and/or Purchase Order from Manage Subcontracts
Requisitions & Purchase Orders
Subcontractor Agreement
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 16
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 17
Subcontractor Agreement
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 18
» Resources can be assigned at the
line level of the PO
» Optional step
» Multiple resources can be assigned
to one line
» Rate and PLC can be entered for
each resource
» Specific subcontractor employees
can be entered in the Vendor
Employees subtask
Assign Subcontractor Resources
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 19
» Accounting Defaults can be entered
and used across all lines of the PO
» Each line of the PO can be
assigned to a different
Project/Org/Account combination
» Could have a different resource
and P/O/A per line
» Could have a PO for one
resource with multiple charge
lines and different P/O/A for
each line
PO Charging
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 20
» Statements of Work (SOWs) can be
uploaded in the system
» The SOW can be attached at the
header level and/or the line level of
the PO
» Only one SOW can be entered
at the header level
» Multiple SOWs can be entered
at the line level
» The SOW can be viewed from the
Manage POs screen
Statement of Work
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 21
» If using Costpoint’s Contract
Management module to manage
and maintain Subcontract
Information, the Subcontract ID can
be linked to the PO record
» FAR, DFARs and Supplemental
Regulations linked to the
Subcontract ID can be tied to the
PO for printing
Subcontract Information
Work Assignment
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 22
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 23
Work Assignment
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 24
» Rules will default from Controls
screen
» Define Validation Rules
» Charging in T&E
» Subcontractor Invoice
» Default Accounts for Unallowable
charges
Work Assignment Business Rules
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 25
» PO Line Detail information will
populate the Work Assignment lines
» Charges subtask is used to define
what, when and who can charge to
the individual lines of the Work
Assignment
» If resources were not assigned
when the PO was entered, they can
be assigned here
» Multiple resources can be
assigned to each line
Work Assignment Charges
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 26
» Vendor Employee Assignment can;
» Default in from PO
» Be loaded from Project Workforce
» Be entered manually
» Be left open for all Vendor Employees tied
to the Subcontract Vendor
» Period of Performance can be entered for each
Vendor Employee
» PLC and Rate information can default or be
entered in specifically for the Work Assignment
» Skills, Training, Security and Property is visible
by Vendor Employee
» Once the line is approved, the Work Assignment
becomes visible in TE for charging
Work Assignment Vendor Employees
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 27
» Roles must be assigned for review
and/or approval of Work Assignment
charge lines in Time & Expense
» The roles codes assigned on this
screen must match the Functional
Role codes established in Deltek
Time & Expense
Work Assignment Roles
Subcontractor Time & Expense Entry
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 28
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 29
Time & Expense
≠
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 30
» Subs can use the same timesheet solution as employees to enter time
» Subs can only see the Work Assignments they have been tasked to work on
» Period of performance information can be made visible to subs
» Once the period of performance has ended, the Work Assignment no longer appears in the lookup list for charging
» Timesheet can entered, saved and submitted from a mobile device
Subcontractor Timesheet Approval
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 31
» Timesheet approvals can be done
by the Subcontract Manager and/or
the Project Manager
» Can review hours detail by day and
pending approvals
» Work Assignment budget
information is visible, allowing
Managers to Approve/Reject hours
under or over budget
Subcontractor Timesheet Approval
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 32
» Expense entry can be allowed via
the Work Assignment
» Charge numbers are limited to the
Work Assignments assigned
» Detailed or summary level
expenses can be entered
» Workflows can be configured for
sub expense entry and approval
Subcontractor Expense Entry
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 33
» Expense approvals can be done by
the Subcontract Manager and/or the
Project Manager
» Expense detail and receipt
attachments can be viewed both
from the desktop and mobile device
Subcontractor Expense Approval
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 34
» Export Timesheets and Export
Expense Reports screens in T&E10
contain a Subcontractor Export
check box
» Timesheets and Expense Reports
records import into
SUBC_TS_HDR, SUBC_TS_LN,
SUBC_EXP_HDR, SUBC_EXP_LN
» New tables within the
Subcontractor Management
module
Subcontractor Time & Expense Export
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 35
» Provide Subcontractors with a
dashboard view of assigned POs
» Portal allows for communication
between external Subcontractors
and internal Buyers
» Actions, messages and history is
maintained in the portal
» Coming soon: Invoice visibility and
approval, AP Voucher payment
status, Vendor Quotes, self sourcing
capabilities and more…
Supplier Portal
Subcontractor Invoice Creation
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 36
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 37
Subcontractor Invoice
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 38
» Provides users the ability to review
timesheet and expense detail prior
to generating the subcontract
invoice
» Timesheet lines and expense detail
can be placed on hold for invoicing
at a later date
Manage Open Subcontractor Detail
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 39
» Time and Expenses are pulled from
the new Subcontractor
Management tables
» Daily time detail exists within
these tables
» Can create invoices for specific
POs, Vendors, Projects and Work
Assignments
» Specific Timesheet Line Date
ranges can be imported where
timesheet periods cross over billing
period end
Create Subcontractor Invoice
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 40
» Subcontractor Invoice information is
visible within the screen
» Lines can be deleted from the
invoice if needed
» Lines will be pushed back into
the new Subcontractor Time &
Expense tables
» Vendor Labor Timesheet Line
details are pulled into the invoice
» Over ceiling rules applied on the
Work Assignment appear here
Review of Subcontractor Invoices
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 41
» Subcontractor Invoices can be
printed directly out of Costpoint and
sent to the Subcontract Company
for approval
» Multiple selections available for
what to show on the invoice
Print Subcontractor Invoice
» Invoice printed based on print
selections
» Summary information on first page
» Detail information on following
pages to include:
» PO line information
» Work Assignment details
» Vendor Employee and PLC
information
» Timesheet Line details
Print Subcontractor Invoice
CONFIDENTIAL © Deltek, Inc. All Rights Reserved.42
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 43
» Approval can be internal or external
» Internal approval automatically
inserts User Name with Date and
Timestamp
» External approval can be entered
manually
» Timesheet approval could be
the only external approval
required
» Approval of the invoice
automatically generates a PO
Voucher
Approve Subcontractor Invoice
Payments to Subcontractors
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 44
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 45
PO Voucher
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 46
» Labor details follow the Work
Assignment into the PO Voucher to
include daily timesheet line detail
» PO Voucher approvals can be
established within the system
Vendor Labor in PO Voucher
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 47
» As the PO Voucher is approved and
posted, PO Commitments are
relieved
» Visible in both Hours and
Dollars
» Commitment information is visible in
Purchasing and on the Work
Assignment
PO Commitments
Billing Invoice Creation
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 48
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 49
Project Billing
» Subcontractor charges included
with other billing items
» Invoice printed based on print
selections
» Subcontractor Labor and Expense
details can be printed on supporting
schedules
» Can include timesheet line
details
Final Customer Billing
CONFIDENTIAL © Deltek, Inc. All Rights Reserved.50
Sessions for Reference
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 51
» CP-32: Got Subcontracts - See What Costpoint Can Do for You
» CP-91: Got PO's? Streamlining PO’s Using the New Supplier Portal
Additional Sessions
CONFIDENTIAL © Deltek, Inc. All Rights Reserved.52
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 53
Natalie Scicluna, Deltek
Principal Solutions Architect
Thank you for attending!