PRE- SUBMITTAL CONFERENCE REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION # H27-VMFDB-2019-006 Al Oracion Sr. Procurement Specialist Houston Airport System Thursday, January 10, 2019, 10:00 A.M. 18600 Lee Road, Humble, Texas 77338

Upload: others

Post on 17-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

PRE- SUBMITTAL CONFERENCEREQUEST FOR QUALIFICATIONS (RFQ)

VEHICLE MAINTENANCE FACILITY DESIGN BUILD

SERVICES

SOLICITATION H27-VMFDB-2019-006

Al Oracion

Sr Procurement Specialist

Houston Airport System

Thursday January 10 2019 1000 AM

18600 Lee Road Humble Texas 77338

Pre-Qualification Meeting Agenda

I Opening Remarks

II Solicitation Overview

III Office of Business Opportunity

IV Project Scope and Overview

V QuestionsAnswers

Justina Mann

Procurement Officer

Al Oracion

Sr Procurement Officer

Jason McLemore

Deputy Asst Director HAS OBO

Jose Enriquez

Project Manager

2

Procurement Process Reminder

Quiet Period

3

The Quiet Period begins on the date the solicitations are published

Contact only with the designated procurement specialist (Al Oracion)

Quiet Period extends until an award recommendation appears on a

City Council Agenda or a City Council Committee Meeting Agenda

Solicitation Overview

PURPOSE

The City of Houston (City) Houston Airport

System (HAS) invites interested firms to submit

statements of qualifications for the design-build

services for the vehicle maintenance facility at

George Bush Intercontinental Airport (IAH)

4

Solicitation Overview

SOLICITATION DUE DATE AND TIME

Thursday February 28 2019 200 PM CST

QUESTIONS AND REQUESTS FOR ADDITIONAL INFORMATION DUE BY

Friday January 18 2019 1200 PM CST

Must be received electronically and directed via email to

alfredooracionhoustontxgov

5

Addtrsquol InfoSpecification Changes

LETTER OF CLARIFICATION

Responses to questions received from potential Firm(s) and

any changes to the scope shall be confirmed in writing and

will be posted to the HAS website (wwwfly2houstoncom)

prior to submittal due date

6

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 2: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Pre-Qualification Meeting Agenda

I Opening Remarks

II Solicitation Overview

III Office of Business Opportunity

IV Project Scope and Overview

V QuestionsAnswers

Justina Mann

Procurement Officer

Al Oracion

Sr Procurement Officer

Jason McLemore

Deputy Asst Director HAS OBO

Jose Enriquez

Project Manager

2

Procurement Process Reminder

Quiet Period

3

The Quiet Period begins on the date the solicitations are published

Contact only with the designated procurement specialist (Al Oracion)

Quiet Period extends until an award recommendation appears on a

City Council Agenda or a City Council Committee Meeting Agenda

Solicitation Overview

PURPOSE

The City of Houston (City) Houston Airport

System (HAS) invites interested firms to submit

statements of qualifications for the design-build

services for the vehicle maintenance facility at

George Bush Intercontinental Airport (IAH)

4

Solicitation Overview

SOLICITATION DUE DATE AND TIME

Thursday February 28 2019 200 PM CST

QUESTIONS AND REQUESTS FOR ADDITIONAL INFORMATION DUE BY

Friday January 18 2019 1200 PM CST

Must be received electronically and directed via email to

alfredooracionhoustontxgov

5

Addtrsquol InfoSpecification Changes

LETTER OF CLARIFICATION

Responses to questions received from potential Firm(s) and

any changes to the scope shall be confirmed in writing and

will be posted to the HAS website (wwwfly2houstoncom)

prior to submittal due date

6

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 3: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Procurement Process Reminder

Quiet Period

3

The Quiet Period begins on the date the solicitations are published

Contact only with the designated procurement specialist (Al Oracion)

Quiet Period extends until an award recommendation appears on a

City Council Agenda or a City Council Committee Meeting Agenda

Solicitation Overview

PURPOSE

The City of Houston (City) Houston Airport

System (HAS) invites interested firms to submit

statements of qualifications for the design-build

services for the vehicle maintenance facility at

George Bush Intercontinental Airport (IAH)

4

Solicitation Overview

SOLICITATION DUE DATE AND TIME

Thursday February 28 2019 200 PM CST

QUESTIONS AND REQUESTS FOR ADDITIONAL INFORMATION DUE BY

Friday January 18 2019 1200 PM CST

Must be received electronically and directed via email to

alfredooracionhoustontxgov

5

Addtrsquol InfoSpecification Changes

LETTER OF CLARIFICATION

Responses to questions received from potential Firm(s) and

any changes to the scope shall be confirmed in writing and

will be posted to the HAS website (wwwfly2houstoncom)

prior to submittal due date

6

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 4: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Solicitation Overview

PURPOSE

The City of Houston (City) Houston Airport

System (HAS) invites interested firms to submit

statements of qualifications for the design-build

services for the vehicle maintenance facility at

George Bush Intercontinental Airport (IAH)

4

Solicitation Overview

SOLICITATION DUE DATE AND TIME

Thursday February 28 2019 200 PM CST

QUESTIONS AND REQUESTS FOR ADDITIONAL INFORMATION DUE BY

Friday January 18 2019 1200 PM CST

Must be received electronically and directed via email to

alfredooracionhoustontxgov

5

Addtrsquol InfoSpecification Changes

LETTER OF CLARIFICATION

Responses to questions received from potential Firm(s) and

any changes to the scope shall be confirmed in writing and

will be posted to the HAS website (wwwfly2houstoncom)

prior to submittal due date

6

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 5: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Solicitation Overview

SOLICITATION DUE DATE AND TIME

Thursday February 28 2019 200 PM CST

QUESTIONS AND REQUESTS FOR ADDITIONAL INFORMATION DUE BY

Friday January 18 2019 1200 PM CST

Must be received electronically and directed via email to

alfredooracionhoustontxgov

5

Addtrsquol InfoSpecification Changes

LETTER OF CLARIFICATION

Responses to questions received from potential Firm(s) and

any changes to the scope shall be confirmed in writing and

will be posted to the HAS website (wwwfly2houstoncom)

prior to submittal due date

6

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 6: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Addtrsquol InfoSpecification Changes

LETTER OF CLARIFICATION

Responses to questions received from potential Firm(s) and

any changes to the scope shall be confirmed in writing and

will be posted to the HAS website (wwwfly2houstoncom)

prior to submittal due date

6

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 7: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Submittal Procedures

One (1) original marked ldquooriginalrdquo signed in BLUE ink ten (10) hardcopies as well as ten (10) electronic PDF copies on a non-returnable USBdrive of the submittals One (1) marked ldquoOriginalrdquo and one (1) copy ofFinancial Statements must be received at the address below no later thanThursday February 28 2019 200 PM CST

Address to sendsubmit to

Attn Justina J Mann

Procurement Officer

Supply Chain Management

18600 Lee Road

Humble Texas 77338

Please include the phrase ldquoRFQ No H27-VMFDB-2019-006 VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICESrdquo in the subject line and provide all applicable contact information

7

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 8: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

SOQ Submittal Requirements

bull Each SOQ must be organized and follow the required format as stated in Section 105 of the RFQ

bull Each Section must be appropriately tabbed and inclusive of all the required submittals

bull Submissions to the RFQ must be valid for a period of one-hundred and eighty (180) consecutive calendar days from the date of receipt by the City

bull Forms to be submitted with Statement of Qualifications are listed in Section 170 and must be properly and completely filled-up

8

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 9: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Procurement Timeline

Description Scheduled Date

Advertisement of Solicitation 122818

Pre-Submittal Conference 011019

Questions from Respondents Due to City 011819

SOQ Submittals Due from Respondents (Step 1) 022819

Notification of Shortlisted Firms 032019

Technical amp Cost Proposals Due (Step 2) 040319

Negotiation 050319

City Council Agenda Date (Estimated) 062619

9

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 10: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Evaluation Criteria

bull Similar Project Experience 15 Points

bull Project Approach 15 Points

bull Firm(s) Qualifications 15 Points

bull Project Team Qualifications 20 Points

bull Design and Pre-Construction and

Construction Phase Services 10 Points

bull Management and Staffing Plan 15 Points

bull Project Controls 10 Points

Total Score 100 Points

bull Financial Capabilities PassFail

bull Safety Record PassFail

bull OSHA Citations PassFail

10

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 11: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

OFFICE OF BUSINESS OPPORTUNITY

HAS Office of Business Opportunity

hasobohoustontxgov

11

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 12: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

OFFICE OF BUSINESS OPPORTUNITY

DIVERSITY REQUIREMENTS

The goals on the project are the following

MBE Goal ndash28

WBE Goal ndash10

12

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 13: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

OFFICE OF BUSINESS OPPORTUNITY

CERTIFICATION

bull Participating Firms Must Be Certified MBE or WBE with the Cityof Houstonrsquos Office of Business Opportunity

bull Firms Must Be Certified MWBE At Time Of QualificationSubmission If Not Certified MWBE They Will Not Be CountedTowards Contract Participation

bull Questions About Certification Visit httpwwwhoustontxgovobo Or By Phone (832) 393-0600

13

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 14: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

HOUSTON AIRPORT SYSTEM

Jose Enriquez

Project Manager

14

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 15: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

bull Overview

bull Scope

bull Approach

bull Location (Site Visit Upon Request)

15

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 16: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

Overview

Construct a new facility as the home for Vehicle Maintenance

Shuttle Bus Maintenance Airside OPS and Supply Chain This

new construction would

bull Ensure safe working environment for HAS and FMD employees

bull Be fully air conditioned except vehicle maintenance bays

bull Have efficient layout and proper equipment

bull Complete all work using phased approach

16

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 17: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

Scope bull Proposed Vehicle Maintenance Facility (VMF)

ndash Facility Size is approximately 51000 SF

ndash Structural Steel Options

ndash Mechanical yard

ndash Associated site concrete paving and landscaping

ndash Fenced and lighted 100000sf gravel vehicle hold yard

ndash Parking for approx 180 vehicles

bull The VMF will be shared by 4 separate City entities

ndash Vehicle Maintenance (VMF)

ndash Airside Operations (OPS)

ndash Supply Chain Management (SCM)

ndash 3rd party maintenance operator (Shuttle Bus Maintenance)

bull Shuttle Bus Maintenance must be able to occupy their

designated area by December 2019

17

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 18: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

Phasing Approach

The Design-Build firm will perform services for this Project under aTwo-Phase delivery method

bull Phase 1 ndash Pre-Construction and Shuttle Bus MaintenanceConstruction Phase 1 includes Pre-Construction activities sitework the building shell as well as the build-out of the VMF andShuttle Bus Maintenance areas Shuttle Bus Maintenance is theinitial priority and must be able to occupy their designated area byDecember 2019

bull Phase 2 ndash Remaining Construction Services Phase 2 ofconstruction includes the build out of the second floor for SCM andOPS spaces At no time will Phase 2 interfere with the set Phase 1completion date of December 2019 unless the proposed work isconducive to the completion of Phase 1

18

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 19: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

Project Location

19

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 20: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Project Scope and Overview

20

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 21: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Questions

bull Questions to be official must be in writing and submitted via email to

alfredooracionhoustontxgov

bull Answers will be posted in HAS website as Letter of Clarification

httpwwwfly2houstoncom

21

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006

Page 22: REQUEST FOR QUALIFICATIONS (RFQ) VEHICLE ......Solicitation Overview III. Office of Business Opportunity IV. Project Scope and Overview V. Questions/Answers Justina Mann Procurement

Closing Remarks

HOUSTON AIRPORT SYSTEM

Thank you

22

VEHICLE MAINTENANCE FACILITY DESIGN BUILD SERVICES SOLICITATION

H27-VMFDB-2019-006