report, really a good cause?
TRANSCRIPT
-
7/30/2019 Report, Really a good cause?
1/8
Agreement
Between
Rotary Club Of Khartoum
And
Water & Environment Sanitation (WES) Project
Contract Title: Rehabilitation of the water yard in Magarif Village, Wad El Hilao
Start Date: 15 April 2006
End Date: 1 June 2006
This contract agreement is made and entered this day 1\4\2006 into action between
Khartoum Rotary Club (KRC) referred to as the contractee and Water and EnvironmentalSanitation Project Kassala State (WES), referred to as the Contractor
Contract object
Rehabilitation of a water yard in Magarif Village, Wad El Hilao
Scope of work
The contractor agrees to carry out the activities described in this contract according to the
detailed project description in Annex 1.
Activity implementation will take place according to the contract starting and ending dates
unless otherwise extended or terminated in accordance with the terms of the contract and
any of its attachments.
The contractor will closely adhere to the technical specifications in Annex 1.
All required technical documents and letters of agreement will be provided prior to
implementation
Cost and Terms of Payment
The total amount to be paid under this contract of Agreement will be 8,400,000 Sudanese
Dinars.
The payment will be made in two equal installments. 60% of the total amount, equivalent
to 5,040,000 SD (five million forty thousand Sudanese Dinars) will be paid at the beginning
of the work. The remaining 40%, equivalent to 3,360,000 SD (three million three hundred
& sixty thousand Sudanese Dinars) will be paid after the completion of 75% of the work.
Payment will be made directly to WES Project Manager, Kassala State, EL Tadamon
Islamic Bank, Kassala, account no. 2767).
-
7/30/2019 Report, Really a good cause?
2/8
Monitoring and Evaluation
WES staff will monitor activity progress and quality of work and or services and will send a
final progress report to Khartoum Rotary Club no later than one month after the end of the
contract.
Safety and security provisions
Rotary Club of Khartoum is not liable under this agreement for any illness, injury, or
accident incurred by any person(s) while engaged in the fulfillment of the contracted
activities.
Final provisions
Each party shall be bound by all terms of this Contract and all its annexes;
This Contract and annexes shall supersede all prior contracts between the signing parties
to date.
This Contract and all annexes constitute the sole and entire agreement between the
parties. No change, alteration, or modification will be effective unless a written addendum,
is signed by both parties;
In the case of dispute, Khartoum Rotary Club and WES will attempt to settle the issues
between themselves. Should this not be possible, the dispute shall be resolved through a
competent legal court, according to Sudanese law.
Khartoum Rotary Club and the Contractor agree to abide by the terms of this Contract and
all its Annexes by signing below and initialing each page of the Contract.
For Khartoum Rotary Club For WES:
Club President WES Project Manager Kassla
_____________ ________ ____________ ________
Signature Date Signature Date
_____________ _________ ____________ ________
Printed Name Title Printed Name Title
-
7/30/2019 Report, Really a good cause?
3/8
Annex 1.
WES will invited tenders for the rehabilitation of the water yard and construction of a
distribution system to a maximum of the cost provided by Rotary (stated above)
Rehabilitation of the water yard
Description Unit Quantity
1 Development of the existing bore hole and pumping test JOB ---
2 Replacement of the old pump unit with a new one as follows:-
Submersible pump (2inch) with pipes. H= 120 m
b-Generator 10 kw
JOB ---
3 Rehabilitation of the elevated tank and change of the drainage
system outlet (2inch) with (3inch).
JOB ---
4 Construction of the pump room (3mx4m) using zinc (galvanized)
sheets & steel angles
JOB ---
5 Construction of the wire fencing of the water yard with
foundation of (50cmx50cm)
ML 80
Sub Total
Construction of a distribution system
No. Description Unit Quantity
1 Provision & installation of the main water line using 4inch/8
bar PVC pipes
ML 1000
2 Provision & installation of sub lines using 2 inch PVC pipes ML 1500
3 Construction of 4 Water points with (8) Taps JOB ---
Sub Total
TECHNICAL SPECIFICATIONS
1. Development of the existing bore hole and pumping test
2. Replacement of the old pump unit with a new one as follows:
a-submersible pump (2inch) with pipes. H= 120 m Q =7 m^3\ hour
b-Generator 10 KW
3. Rehabilitation of the elevated tank and drainage system change outlet (2inch) with
(3inch).
4. Construction of the pump room (3mx4m) using zinc (galvanized) sheets & steel angles
5. Construction of the wire fencing of the water yard, foundation (50cmx50cm)
-
7/30/2019 Report, Really a good cause?
4/8
6. Provision & installation of the main water line using 4inch PVC, 8 bar pipes
7. Provision & installation of the sub lines using 2inch PVC pipes.
8. Construction of 4 Water points with (8) Taps
9. WES will present a technical report to Khartoum Rotary Club on progress and present a
final progress report not later than one month after the contract.
-
7/30/2019 Report, Really a good cause?
5/8
Agreement
Between
Rotary Club Of Khartoum
And
Water & Environment Sanitation (WES) Project
Contract Title: Water Wells Construction in El Amara village
Start Date: 1 April 2006
End Date: 1 May 2006
This contract agreement is made and entered this day 1\4\2006 into action between
Khartoum Rotary Club (KRC) referred to as the contractee and Water and Environmental
Sanitation Project Kassala State (WES), referred to as the Contractor.
Contract object
Drilling of four complete productive bore holes with hand pumps India mark (11) in El
Amara Village
Geophysical survey and selection of the bore holes sites.
Water quality examination.
Scope of work
The contractor agrees to carry out the activities described in this contract according to the
detailed project description in Annex 1.
Activity implementation will take place according to the contract starting and ending dates
unless otherwise extended or terminated in accordance with the terms of the contract and
any of its attachments.
The contractor will closely adhere to the technical specifications in Annex 1.
All required technical documents and letters of agreement will be provided prior to
implementation
Cost and Terms of Payment
The total amount to be paid under this contract of Agreement will be 3,600,000 Sudanese
Dinars .
Payments will be made in two equal installments. The first installment, equivalent to
I,800,000 SD (one million eight hundred thousand Sudanese Dinars) will be paid at the
beginning of the work. The remaining 50%, equivalent to I, 800,000SD (one million eight
-
7/30/2019 Report, Really a good cause?
6/8
hundred thousand Sudanese Dinars), will be paid after the completion of work and
submission of a technical report.
Payment will be made directly to WES Project Manager, Kassala State, EL Tadamon
Islamic Bank, Kassala, Account No. 2767).
Monitoring and Evaluation
WES staff will monitor activity progress and quality of work and or services and will send a
final progress report to Khartoum Rotary Club no later than one month after the end of the
contract.
Safety and security provisions
Khartoum Rotary Club is not liable under this agreement for any illness, injury, or accident
incurred by any person(s) while engaged in the fulfillment of the contracted activities.
Final provisions
Each party shall be bound by all terms of this Contract and all its Annexes;
This Contract and annexes shall supersede all prior contracts between the signing parties
to date.
This Contract and all annexes constitute the sole and entire agreement between the
parties. No change, alteration, or modification will be effective unless a written addendum,
is signed by both parties;
In the case of dispute, Khartoum Rotary Club and WES will attempt to settle the issuesbetween themselves. Should this not be possible, the dispute shall be resolved through a
competent legal court, according to Sudanese law.
Khartoum Rotary Club and the Contractor agree to abide by the terms of this Contract and
all its Annexes by signing below and initialing each page of the Contract.
For Khartoum Rotary Club For WES
Club President WES Project Manager Kassla
_____________ ________ ____________ ________
Signature Date Signature Date
_____________ _________ ____________ ________
Printed Name Title Printed Name Title
-
7/30/2019 Report, Really a good cause?
7/8
Annex 1.
Drilling of 4 bore holes:
Budget Items SD
Drilling of 4 bore hole 1,724,783
Installation of casing and development of the 4 wells 698,261
Water quality test for 4 wells 138,452
Provision and installation of India Mark 2 hand pumps for 4
wells
519,252
Construction of platform and drainage system for 4 wells 519,252
Geophysical survey for sitting Contractor
Transportation of supplies to Kassala To be met by the Kassala State
Government
Total 3,600,000
TECHNICAL SPECIFICATIONS
1. Drill 4.5-inch diameter water wells to a depth of at least 100 feet to ensure all
year availability of water.
2. Design and construct the drilled wells to ensure successful output of fresh wateras per contract.
3. Carry out water quality test on all the successfully completed wells, and ensure
the water is safe for human consumption.
4. Construct aprons and drainage gutters around constructed wells.
5. Install (India Mark ll) pumps on completed wells.
6. Provide training to the community in the correct operation and maintenance of
the pumps to ensure sustainability.
7. Oversee community management of the water points to ensure long-term usage
of the water pumps.
8. WES will present a technical report to Rotary Clubo0f Khartoum at the end of thecontract
The report should include the following
Information on geology/hydrogeology
Geophysical & drilling report
Water quality test result
-
7/30/2019 Report, Really a good cause?
8/8