ACC 23.01.2017
Remediation of Mined out areas at
Jamul Cement Works Limestone Mine
ESTD. SINCE-1963
Location Details
Area (Ha)
Mine Jamul Cement Works Limestone Mine
Lease Area
269.95 Ha
Area Non-Forest
Category of Mine
“A” (Fully Mechanized)
Village Jamul, Dhaur & Kurud
District Durg
State Chhattisgarh
Country India
1
ACC 23.01.2017
Present Land use Pattern
Land use Pattern Area (Ha)
Active Pit Area 31.59
Mined out Pit converted in Water Reservoir
51.55
Area storage for top soil 0.85
Waste Dump rehabilitated 26.61
Backfill area 2.1
Sub grade mineral storage area 4.18
Area under infrastructure 5.32
Area under roads 2.1
Area under green belt 7.7
Drainage 4.42
Afforestation 65.13
Undisturbed Area 68.40
2
ACC Limited
Green Belt developed between residential area and mines
Green Belt and Afforestation area of 72.83 Ha developed to attenuate noise and arrest dust
3
ACC Limited
Rehabilating of Peepal tree
Preserving the flora by uprooting of Peepal tree and established them at suitable location
4
ACC Limited
Rehabilitated Overburden and Waste dump
Rehabilitated Overburden and Waste dump towards eastern lease boundary
5
ACC Limited
Rehabilitated Overburden and Waste dump
Rehabilitated Overburden and Waste dump towards Southern side lease boundary
6
ACC Limited
Rehabilitated Overburden and Waste dump
Rehabilitated overburden and Waste dump towards Southern side lease boundary
7
ACC Limited
Making the rehabilated area self sustainable
Bamboo Forestry/ fruit orchard will work as a cash crop
8
ACC Limited
New Strategy of planting 12’ height plants for high survival rate and less maintenance cost.
9
ACC Limited
Mined pit-1 converted into Water Reservoir
Rain water harvested in Water Reservoir covering area of 16.24Ha with storage capacity of 9 Lac cu. m of water
Beneficiaries
1.Surrounding
Villagers
(3000 families)
2. ACC Colony
3.Industrial purpose
4.Use at Agriculture land
10
ACC Limited
Mined pit-1 converted into Water Reservoir
Video(Double Click on black screen)
11
ACC Limited
Mined pit-1 converted into Water Reservoir
Rain water harvested in Water Reservoir covering area of 16.24Ha with storage capacity of 9 Lac cu. m of water
Beneficiaries
1.Surrounding
Villagers
(3000 families)
2. ACC Colony
3.Industrial purpose
4.Use at Agriculture land
12
ACC Limited
Mined pit-1 converted into Water Reservoir
Rain water harvested in Water Reservoir covering area of 16.24Ha with storage capacity of 9 Lac cu. m of water
Beneficiaries
1.Surrounding
Villagers
(3000 families)
2. ACC Colony
3.Industrial purpose
4.Use at Agriculture land
13
ACC Limited
Mined pit-2 converted into Water Reservoir
Rain water harvested in Water Reservoir covering area of 35.31Ha with storage capacity of 22 Lac cu. m of water
Beneficiaries
1.Surrounding
Villagers
(3000 families)
2. ACC Colony
3.Industrial purpose
4.Use at Agriculture land
14
ACC Limited
Safety Measures at Water Reservoir
Provided
1.Fencing around the water reservoir
2. Lifebuoy Rings posted along fencing.
3.Caution Notices along the Water reservoir
4.SOP to use Lifebuoy
15
ACC Limited
Backfilled area rehabilated into Island Park
Before After
16
ACC Limited
Backfilled area rehabilated into Picnic spot
Picnic Spot
17
ACC Limited
Thank you