Session Objectives Review reimbursement requirements Ensure understanding of reporting
requirements Examine the details of budget
modifications
2014 Project Director Training & Annual Meeting 2
3
Reimbursements
2014 Project Director Training & Annual Meeting
New York State CommissionReimbursements Reimbursement is made based on actual expenses Reimbursements may not be for estimated,
unauthorized, or unallowable expenses Reimbursements must be for approved and
budgeted expenditures that programs have already incurred
New York State Commission does allow advance funds Up to ¼ of their annual CNCS budget Recouped during subsequent quarters
2014 Project Director Training & Annual Meeting 4
2014 Project Director Training & Annual Meeting 5
New York State CommissionReimbursements Reimbursements are made
Quarterly Based on Expenditure Reports via Contract
Management System (CMS) Based on approved, budgeted expenses
Programs must retain All documents and invoices that support its
financial information
6
New York State CommissionReimbursements When Expenditure Reports are submitted, must
upload to CMS: Member Activity Report Grantee Share Report
Must also demonstrate compliance with program operations Current Progress Report
MWBE Quarterly Reports need to be emailed to [email protected] (cc your program manager)
2014 Project Director Training & Annual Meeting
7
CNCS ReimbursementAmeriCorps Grant Provisions
“A living allowance is not a wage. Programs must not pay a living allowance on an hourly basis. Programs should pay the living allowance in regular increments, such as weekly or bi-weekly, paying an increased increment only on the basis of increased living expenses such as food, housing, or transportation. Payments should not fluctuate based on the number of hours served in a particular time period, and must cease when a member concludes a term of service.”
No “lump sum” if member completes term earlyNo “lump sum” if member starts late, e.g., “make up” missed payments
2014 Project Director Training & Annual Meeting
8
New York State CommissionPayments
14 days = Target Date for Reimbursement May take longer
Delays Occur Because: Insufficient match Failure to provide Member Activity Report Failure to submit Progress Report Failure to submit reimbursement timely Other information requested
2014 Project Director Training & Annual Meeting
9
Reporting
2014 Project Director Training & Annual Meeting
Key Elements of Financial Reporting Prepare all financial reports with information
from your organization’s accounting system Review and reconcile the information to
ensure accuracy prior to report submission Joint review by program and fiscal staff
Files must have the proper documentation to support all information reported in financial reports
Submit all reports on time2014 Project Director Training & Annual Meeting 10
11
New York State CommissionFinancial Reporting Requirements Grantee Share Expenditure Report
Due according to dates on the Financial Reporting Schedule
By the last day of the required month If last day falls on a weekend, the Report is due the
Friday before the weekend Must be submitted via CMS
Failure to submit the Expenditure Report on time will result in reimbursement delays
andreflect negatively on program compliance
2014 Project Director Training & Annual Meeting
New York State CommissionFinancial Reporting Requirements Expenditure Reporting Schedule
2014 Project Director Training & Annual Meeting
Reporting Period Due DateProgram Start – 11/30/14 12/31/201412/1/14 – 2/28/15 3/31/20153/1/15 – 5/31/15 6/30/20156/1/15 – 8/31/15 9/30/20159/1/15 – 11/30/15 12/31/201512/1/15 – 12/31/16 1/30/2016
New York State CommissionFinancial Reporting Requirements Expenditure Reporting Schedule - CFA
2014 Project Director Training & Annual Meeting
Reporting Period Due DateProgram Start – 2/28/15 3/31/20152/28/15 - 5/31/15 6/30/20156/1/15 - 8/31/15 9/30/20159/1/15 - 11/30/15 12/31/201512/1/15 - 3/31/16 4/30/2016
14
New York State CommissionLate Reports
If you are late Notify the New York State Commission Program
Administrator with the reason and the expected date This will reflect negatively on your program
compliance If a report is 5 days overdue, New York State
Commission will send a letter that grant requirements have not been met
2014 Project Director Training & Annual Meeting
Late is late!
15
Program Income Gross Program Income
All funds collected as a direct result of grant funded-activities
Net Program Income The amount after deducting costs associated
with generating the income All Program Income
Must be used for grant-related purposes “Auditable” = Program Income and its
supporting documentation2014 Project Director Training & Annual Meeting
16
Program Income Program Income
Must be retained by the grantee Used to finance match
Program income earned in excess of the amount needed must be deducted from the total claimed costs
Programs must report the excess amount on the FFR to CNCS
See 2014 AmeriCorps Provisions Section V. F. for details
2014 Project Director Training & Annual Meeting
17
Program Income Reporting Issues Program Income common errors found
Program Income used as match was erroneously reported as Program Income
Corrective Action If all your program income was used as
match, your comments related to Program Income should be entered
2014 Project Director Training & Annual Meeting
18
Budget Modifications
2014 Project Director Training & Annual Meeting
2014 Project Director Training & Annual Meeting 19
What are Budget Controls? Your budget = estimate of expected costs Estimates may change as the program is
implemented Monthly review of budget to actual expense Joint review by both program and fiscal staff to compare
Identify expenditures not in the budget to ensure they can be claimed Could be disallowed if not in an approved budget Know your budget
2014 Project Director Training & Annual Meeting 20
What are Budget Controls? Identify costs that need approval before they
are incurred Request budget revisions promptly Do not wait until last month of year to request
budget modification
2014 Project Director Training & Annual Meeting 21
Budget ModificationsNew York State Commission must receive written approval from CNCS for these budgetary changes:
Specific costs requiring approval under the cost principles, such as: Overtime pay and pre-award costs
Equipment purchases over $5,000 using CNCS funds, unless specified in the approved application and budget
Subgrants and subcontracts not previously approved in the original budget
2014 Project Director Training & Annual Meeting 22
Budget ModificationsNew York State Commission must receive written approval from CNCS for these budgetary changes:
Changes in the cumulative budget line items that amount to 10% or more of the total budget, unless the CNCS share is $100,000 or less
The total budget includes both the CNCS and grantee shares Grantees may transfer funds among approved direct costs
categories when the cumulative amount of such transfers do not exceed 10% of the total budget
Key Date April 1 If CNCS approval is needed you must make the request by April 1
2014 Project Director Training & Annual Meeting 23
New York State CommissionRequesting Budget Modifications
Submit a Budget Modification request E-mail to Program Administrator
1. The reason the modification is needed, and
2. Adverse consequences if the request is denied
Program Administrator will discuss your request with you
Program Administrator denies or approves request within 5 business days
Do not assume approvals have been granted unless documented
2014 Project Director Training & Annual Meeting 24
New York State Commission Key Budget Modifications Pitfalls Budget changes are made before New York State
Commission approved the change– Corrective Action: Seek approval before making the change
Adequate written justification was not provided– Corrective Action: Provide a detailed written justification
Budget Modification letter/e-mail was incomplete– Corrective Action: Complete all requirements
Inadequate monitoring of budget throughout the year resulted in major budget changes at year-end
– Corrective Action: Throughout the year review your budget
2014 Project Director Training & Annual Meeting