Vanderbilt Beach Road Extension Project

Recommendation to approve the revised alignment of Vanderbilt Beach Road Extension from Collier Boulevard to 16th Street NE. (Project No. 60168).

BCC Meeting October 22, 2019 – Item 11.F.

1

Jay Ahmad, P.E., Director Transportation Engineering

• June 26, 2018: Public Information Meeting: 30% conceptual design

• Sept 25, 2018: Board discussed frontage road connections; approved shifting VBRX northward and relocating Cypress Canal to the south.

• December 2018: Greyhawk community asked for revised alignment (preserve the original 2-lane VBR as a frontage road, straighten VBRX)

• May 22, 2019: Public Information Meeting: alternative alignment

2

Vanderbilt Beach Road Extension Project:

3

BCC Approved Alignment between Massey Street and Greyhawk:

4

Revised alignment removing “S” curve is safer, requires purchase of 2 homes – see item 11.G.:

163FEE 164FEE

5

Vanderbilt Country Club concerns regarding Old VBR intersection with Massey Street:

163FEE 164FEE

6

VCC’s sale to County provides ~ 1 mile of western half of property needed for future Massey Street project:

~ to Tree Farm Rd

PROJECT SCHEDULE

7

60% PLANS: 05/2020

90% PLANS: 09/2020

100% PLANS: 12/2020

TARGET BID START: 05/2021

TARGET CONSTRUCTION START: 12/2021

TARGET CONSTRUCTION COMPLETION: 05/2024

To approve the revised alignment of Vanderbilt Beach Road Extension from Collier Boulevard to 16th Street NE. (Project No. 60168).

ITEM 11.F. - RECOMMENDATION:

8