qwp - tr council (mar 2012)
TRANSCRIPT
-
8/2/2019 QWP - TR Council (Mar 2012)
1/30
QUALITY WIND PROJECTDistrict of Tumbler Ridge
March 5, 2012
From Development to Construction
-
8/2/2019 QWP - TR Council (Mar 2012)
2/30
Capital Power
Steve Owens Project Manager
Larry Stubben Construction Manager
Mortenson Construction
Jim Davis Site Construction Manager
Quality Wind Project
2
-
8/2/2019 QWP - TR Council (Mar 2012)
3/30
Experience in generation
Capital Power (TSX: CPX) is a growth-oriented North American powerproducer, building on more than a century of innovation and reliableperformance.
We own more than 3,300 megawatts of power generation capacity at16 facilities across North America. An additional 487 megawatts ofowned wind generation capacity is under construction or in advanceddevelopment in BC, AB and ON.
In November 2011, Atlantic Power acquired CPILP and its 18 facilities,
including the 66 MW biomass facility in Williams Lake, BC.
Capital Power
3
-
8/2/2019 QWP - TR Council (Mar 2012)
4/30
CPC Projects
4
Project Location Capacity
(MW)
Anticipated
Commissioning
Quality Wind Tumbler Ridge, BC 142 Q4 2012
Halkirk Wind Halkirk, AB 150 Q4 2012Port Dover &Nanticoke
Counties ofHaldimand &Norfolk, ON
105 Q4 2013
K2 WindOntario
Township ofAshfield-Colborne-
Wawanosh, ON
90* Late 2014
*270 MW wind facility jointly owned with Samsung Renewable Energy Inc., Pattern Renewable Holdings CanadaULC and Capital Power
-
8/2/2019 QWP - TR Council (Mar 2012)
5/30
5
Clean power generation in British Columbia
In BC, Capital Power currently operates two small hydro facilities and the275 MW natural gas-fired Island Generation facility on Vancouver Island.
-
8/2/2019 QWP - TR Council (Mar 2012)
6/30
Quality Wind ProjectTumbler Ridge, BC
3
-
8/2/2019 QWP - TR Council (Mar 2012)
7/30
Quality Wind Projectdescription
Approximately 142 megawatt (MW) project near Highway 52
Vestas will supply and commission 79 1.8 MW wind turbines35 model V90 and 44 model V100 (95-100 m tall)
43 km of roads 21 km upgraded / existing, 22 km new
Project substation, a 230 kV 22 km overhead transmission lineto Tumbler Ridge substation, 44 km of collection lines and anOperations & Maintenance facility
Commercial operation anticipated by late 2012
7
-
8/2/2019 QWP - TR Council (Mar 2012)
8/30
Project locationand lay-out
8
Project area = ~1720 ha
-
8/2/2019 QWP - TR Council (Mar 2012)
9/309
From Development to Construction
Electricity Purchase Agreementawarded by BC Hydro in March 2010
Environmental Assessment Certificatereceived in July 2010
Mortenson Construction Canada
(MCC) commenced construction inNovember 2010. MCCs role includes:
Design, procurement
Sub-contracted: Civil (roads),electrical
Foundations, mechanical
Turbine assembly
Commissioning support
-
8/2/2019 QWP - TR Council (Mar 2012)
10/30
Project timelineCulvert installation
Site roads
Excavation and concrete pouring for turbinefoundations
Transmission line and collector line right-of-ways
Start substation (into 2012)
O&M building
Wind turbine transportation
Wind turbine assembly and commissioning
2011 Activity
2012 Activity
10
-
8/2/2019 QWP - TR Council (Mar 2012)
11/30
Pre-construction activities
November 2010 to April 2011
Surveying, flagging
Clearing and stump removal (grubbing) of project footprint,including right-of-ways for roads, transmission and collectorlines, turbine foundations and substation area
Harvesting merchantable timber; disposal of non-merchantable timber and waste; mulching debris
Geo-technical investigation bore hole drilling at each turbinelocation
Mortenson held job fairs in the region prior to start of civilwork
I toured the Capital Power site and was pleased to note
how much attention they are paying to the environment.
Mayor Larry White, TR News (Feb 2011)
11
-
8/2/2019 QWP - TR Council (Mar 2012)
12/3012
Clearing andgrubbing
-
8/2/2019 QWP - TR Council (Mar 2012)
13/30
Roadwork
Began June 6, 2011
IDL northern portion of site
Duz Cho, Dunne Za and Sipugahma (First Nations)southern portion
Wet weather throughout summer 2011 caused some delays
13
-
8/2/2019 QWP - TR Council (Mar 2012)
14/30
14
Wind turbine generator foundations
Stages of Installation
Excavation
Mud mat
Base rebar
Anchor bolt cage
Pour base concrete
Pedestal rebar
Pedestal concrete
Backfill
Crane Pads
Excavation
-
8/2/2019 QWP - TR Council (Mar 2012)
15/30
15
Mud mat
Pour foundation base
Base rebar, anchor bolt
Pedestal rebar and concrete
-
8/2/2019 QWP - TR Council (Mar 2012)
16/30
16
Completed WTG foundation
Ready for: backfill and crane pad
-
8/2/2019 QWP - TR Council (Mar 2012)
17/30
17
Transmission and collection
Collection System
34.5 kV, four circuits
610 structures
79 UG connectors
Transmission System
230 kV
99 structures
1.2 km free span crossing of the Murray River
-
8/2/2019 QWP - TR Council (Mar 2012)
18/30
Transmission line poles
18
*Source: Eye for Detail Photography
-
8/2/2019 QWP - TR Council (Mar 2012)
19/30
19
A look ahead:Spring/summer 2012
*Source: Eye for Detail Photography
-
8/2/2019 QWP - TR Council (Mar 2012)
20/30
20
Operations & Maintenance building
Contractor: Kor-Alta
Anticipated opening:May 2012
-
8/2/2019 QWP - TR Council (Mar 2012)
21/30
QWP Substation
QWP Substation completion: anticipated forJune 2012
*Shown: Existing TR Substation (Eye for Detail Photography)
21
QWP MPT set,assembled, oil-filled,tested and inspected
-
8/2/2019 QWP - TR Council (Mar 2012)
22/30
22
Turbine transportation
Wind turbine components, currentlybeing manufactured in Colorado, arenow being unloaded in Rycroft, AB.
Each turbine is made up of ninelarge components: four tower
sections, one nacelle, one hub andthree blades.
The components will be stored untilneeded for the turbine assemblyscheduled throughout this summer.
Vestas is responsible fortransportation of the wind turbines tothe QWP site.
-
8/2/2019 QWP - TR Council (Mar 2012)
23/30
23
Ground transportShipped to site via Schnable trailer starting in May
-
8/2/2019 QWP - TR Council (Mar 2012)
24/30
24
Turbine assembly
Starting in early June andcontinuing throughout the summer,the wind turbine generators will beassembled by Eagle West, anexperienced crane operator in thePeace Region (Dokie, Bear
Mountain).
-
8/2/2019 QWP - TR Council (Mar 2012)
25/30
25
Working with local businesses
Direct business* with Tumbler Ridge firms to date(as at Jan 31, 2012):$3.85-5.0M*
LaPrairie Crane
Southpaw Rentals
Dig-it Bobcat Services Tumbler Ridge Sand and Gravel
Kodiak Ridge
Northern Metallic
PRM Camps and Catering
And many more
*Combined Capital Power and Mortenson local spending (not including hotels,restaurants, groceries or fuel); does not include contracting through First Nationbusinesses.
-
8/2/2019 QWP - TR Council (Mar 2012)
26/30
26
First Nations: A case for partnership
Local expertise, local knowledge
Joint venture between Duz Cho Construction (McLeodLake Indian Band) and Dunne-za Ventures (WestMoberly First Nations)
Extensive experience in civil construction andenvironmental services, and possess a deep knowledge
and understanding of local conditions.Have also worked with Sipughma, Kinuseo, Paul
Paquette & Sons, 4EvergreenMcLeod Lake Indian Band2010 Annual Gathering
McLeod Lake Indian Band and Duz Cho Construction are proud to be part of this project as
it will create more environmentally responsible electric power for British Columbia. CPCvalues corporate integrity and community responsibility; Mortenson Construction Canada isa world leader in wind farm development. Together, the two companies have accommodatedthe needs of aboriginal and small business.
- Jim Humphreys, General Manager, Duz Cho Construction
-
8/2/2019 QWP - TR Council (Mar 2012)
27/30
27
Building positive, long-term
relationships with First Nations
Three long term Community BenefitAgreements signed with:
Saulteau First Nation April 2011
West Moberly First Nations Nov 2011
McLeod Lake Indian Band Mar 2012
Capital Power employees at the McLeod LakeIndian Band 2010 Annual Gathering
-
8/2/2019 QWP - TR Council (Mar 2012)
28/30
28
CPC in your community
2011 contributions:
TR Reusable bags program ad purchase and support
TR Search and Rescue Satellite phone purchase of phone and air-time
Community Garden and Composting Society funding for building gazebo
Library Youth Summer Reading Program
Grizfest face-painting tent
Wolverine Nordic Mountain Society hiking trail improvements
Fire safety purchase of educational materials
Tumbler Ridge News purchase of ad space throughout the year
-
8/2/2019 QWP - TR Council (Mar 2012)
29/30
29
In your community (cont.)
Coming up
QWP Spring 2012 newsletter
QWP Community event
Anticipated early summer 2012
Community blade signing (AM), followed by blade hoisting (PM)
*Source: Tumbler Ridge News
-
8/2/2019 QWP - TR Council (Mar 2012)
30/30
Contact us
www.capitalpower.com/[email protected]
Steve Owens Project [email protected]