q u a l i t y 1 austin energy electric service delivery quality management system

17
1 q u a l i t y quality Austin Energy Electric Service Delivery Quality Management System

Upload: madeline-lester

Post on 17-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

1

q u a l i t yquality

Austin EnergyElectric Service Delivery

Quality Management System

Page 2: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 2

ISO Project Charter

Develop and implement a quality management system using ISO standards for Austin Energy’s Electric Service Delivery (ESD) business unit

Page 3: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 3

ISO 9001: 2000 - What is it?

ISO is the International Organization for Standardization

ISO 9000:2000 defines the standards and requirements for a quality management system

Page 4: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 4

Quality Management System Requirements Quality Manual including quality

policy and objectives ISO required procedures

– Documentation management– Records management – Internal audit system – Performance measurement– Preventive and corrective Actions– Non-conforming product management

ESD process documentation

Page 5: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 5

Why did ESD implement a quality management system?

Meet customer needs and expectations

Establish credibility with external customers

Facilitate improvements in system reliability

Establish consistency in processes & service delivery

Facilitate knowledge transfer of processes & procedures

Establish a forum for continuous improvement

Page 6: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 6

Implementation Schedule

Hired consultant to assist with implementation

Aug 2006

Conducted ISO 9001:2000 training for Project Team, ESD Management & Employees

Aug – Dec 2006

Developed & obtained approval of ESD Quality Management System (QMS) project plan

Sep - Oct 2006

Conducted gap analysis Oct 2006 Established Customer Advisory

Council (Samsung, Freescale & National Instruments)

Oct 2006

Purchased and implemented QMS software

Dec 2006 - Apr 2007

Page 7: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 7

Implementation Schedule (cont.)

Developed QMS including: Quality Manual (policy and objectives) ISO required procedures ESD process documentation

Oct 2006 – Jul 2007

Implemented QMS Conducted employee training on QMS Conducted internal management

reviews & audits on QMS

Jul – Dec 2007

Pre-assessment audit conducted by registrar

Nov 2007

Registration audit conducted by registrar Dec 2007 Obtained ISO registration Jan 3, 2008 Continuous improvement of QMS Ongoing

Page 8: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 8

Benefits to Date

Documented work processes Improved consistency in execution of

processes across organization Improved documentation of records Increased communication across

workgroups More focused efforts for implementing

corrective and preventive actions and improvements

Page 9: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 9

Multi Meter Calibration

All multi meters are tested and calibrated.

Two new meters failed initial testing and calibration.

Meters were returned to the manufacture with a Safety Warning!

Page 10: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 10

Metrology tests all new meters before they are used.

Page 11: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 11

Established ESD Quality Center

Page 12: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 12

Benefits to Date

Page 13: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 13

Page 14: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 14

UG Locating Tickets 2008

0

500

1000

1500

2000

2500

3000

3500

4000

4500

January February March April May June July August September October November December

Total Tickets

Cleared in Office

Page 15: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 15

Page 16: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 16

Page 17: Q u a l i t y 1 Austin Energy Electric Service Delivery Quality Management System

q u a l i t y 17