public financial management (pfmx) module 7 · module budget execution and ... before legal...

40
This training material is the property of the International Monetary Fund (IMF) and is intended for use in IMF Fiscal Affairs Department (FAD) courses. Any reuse requires the permission of the IMF and FAD. Module Budget Execution and Control Processes Public Financial Management (PFMx) 7

Upload: ngodiep

Post on 04-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

This training material is the property of the International Monetary Fund (IMF) and is intended for use in IMF Fiscal Affairs Department (FAD) courses.Any reuse requires the permission of the IMF and FAD.

Module

Budget Execution and Control Processes

Public Financial Management (PFMx)7

Page 2: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

The Budget Cycle

Page 3: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Defining Budget Execution

Budget Execution is the process by which…

… financial resources are made available to,

and used by the Executive based on an approved budget.

ApprovedBudgetExecutiveLegislature

Page 4: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Key Aspects of Budget Execution

ApprovedBudget

$

$

ExecutiveLegislature

MinistryofFinance/Treasury

Ministries,Departments,andAgencies

Page 5: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Key Aspects of Budget Execution

$

$ $ $

MinistryofFinance/Treasury

Ministries,Departments,andAgencies

Spendand

Control

Spendand

Control

Spendand

Control

Page 6: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Key Aspects of Budget Execution

$

$ $ $

MinistryofFinance/Treasury

Ministries,Departments,andAgencies

Spendand

Control

Spendand

Control

Spendand

Control

Legal andAdministrativeRequirements

Page 7: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution and Integrity of PFM

EffectiveBudgetExecutionandControl

GoodPublicFinancialManagement

Page 8: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

ArrearsSizeofarrears

Budget Execution Control : Assessments

BudgetcredibilityAccuracyofExpenditureforecasts

PEFASCORES(For85countries)

Source:(www.pefa.org).Note.Theratings“Strong,”“ModeratelyStrong,”“ModeratelyWeak,”and“VeryWeak”arealignedwiththePEFA“A”through“D”scores.

VeryModeratelyModeratelyVeryWeakWeakStrongStrong

StrengthofExpenditureControl

NoDeviation

SmallDeviation

ModerateDeviation

VeryLargeDeviation

VeryModeratelyModeratelyVeryWeakWeakStrongStrong

StrengthofExpenditureControl

Small

Moderate

ModeratelyLarge

VeryLarge

Notreported

Page 9: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Executive

ApprovedBudget

Characteristics of a Government Budget

Funded through compulsory taxation

Authorized by a law of Parliament/Legislature

Page 10: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Four Constraints imposed by Budget Law

Administrative unit responsible to execute expenditure

Allowed time period for expenditure

Specific purpose of expenditure

Limit on the amount of expenditure

Page 11: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

7KeyStagesoftheBudgetExecutionCycle

IncurrenceofObligations

AuthorityandIntenttoSpend

ClearanceofObligations

1.Authorization 2.Apportionment 3.Reservation

4.Commitment 5.Verification

6.PaymentOrder 7.Payment

Page 12: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Authority and Intent to Spend

§ Legalspendingauthority

§ Example:BudgetAppropriation

1.Authorization

Page 13: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Authority and Intent to Spend

§ Apportionedforspecifictimeperiod,and/orspendingunits

§ Example:Monthlyallotment

1.Authorization 2.Apportionment

Page 14: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

§ Fundsreservedforspendingbeforelegalcommitment

§ Example:SpanishSystem

Authority and Intent to Spend

1.Authorization 2.Apportionment 3.Reservation

Page 15: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Incurrence of Obligations

§ Futureobligationto pay

§ Example:Suppliercontract

4.Commitment

Page 16: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

§ Confirmationofgoodsandservicesreceived,andrecognitionof liability

§ Example:Recordof stock

Incurrence of Obligations

4.Commitment 5.Verification

Page 17: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Clearance of Obligations

§ OrdertoPaya billtoclearthe liability

§ Example:‘Ordonnancement’in FrenchSystem

6.PaymentOrder

Page 18: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

§ ActualPaymenttodischargeliability

§ Example:Checkto supplier

Clearance of Obligations

6.PaymentOrder 7.Payment

Page 19: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

7KeyStagesoftheBudgetExecutionCycle

IncurrenceofObligations

AuthorityandIntenttoSpend

ClearanceofObligations

1.Authorization 2.Apportionment 3.Reservation

4.Commitment 5.Verification

6.PaymentOrder 7.Payment

Page 20: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Risks to Budget Execution without Effective Control

$

$ $ $

MinistryofFinance/Treasury

Ministries,Departments,andAgencies

Budgetoverruns

Arrears

Bypasskeystages

Poorqualityofdata

Lackoffiscalresponsibility

Page 21: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Seven Budget Execution Controls

Page 22: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Appropriation

Page 23: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Commitment

Page 24: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Aggregate Cash

Page 25: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Verification

s

Page 26: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Regularity

Page 27: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Accounting

Page 28: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution Controls: Other

Page 29: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Seven Budget Execution Controls

Page 30: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Financial Management Information System (FMIS)

GFMISGovernment

Financial Management

Information System

FMISFinancial

Management Information System

IFMISIntegrated Financial

Management Information System

FMIS defined:

An IT based system supporting government financial management

Page 31: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Financial Management Information Systems (FMIS)

A tool that:Performs financial management functions

Provides timely and accurate financial information

Strengthens expenditure controls

Improves transparency and accountability

Page 32: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

The Budget Cycle and FMIS

Maintains approved budget

Tracks budget execution steps

Generates payment instructions

Maintains accounts

Enables some automatic controls

Page 33: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

FMIS Core and Non-core Systems

Page 34: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Four Stages of the FMIS Development Process

Page 35: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

The Budget Cycle

Page 36: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Function of Internal Audit

Page 37: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Internal Audit versus Internal Control

Page 38: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Internal Audit versus External Audit

Page 39: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

Budget Execution and the Budget Cycle

Spend

Control

Support Systems

Page 40: Public Financial Management (PFMx) Module 7 · Module Budget Execution and ... before legal commitment §Example: Spanish System Authority and Intent to Spend 1. Authorization 2

• BudgetExecution

Budget Execution is the process by which…

… financial resources are made available to,

and used by the Executive based on an approved budget.