Page 1: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Proposed River FootbridgeAlta Vista - Old Ottawa East

AVCA Meeting

September 2020

Page 2: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Proposal

•Conduct cost-benefit analysis of footbridge over the Rideau River from Old Ottawa East / Old Ottawa South

•Add footbridge to TMP and “ultimate” cycling and pedestrian networks.

Page 3: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Location of Proposed Rideau River Footbridge

Page 4: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Context•New OP includes “support for active transportation”

•Dedicated pedestrian/cycling facilities are safer

•New footbridges: transformative and well-used

•Benefits: community, environmental, economic

•Covid: adventuring / accessibility

•Bonus: new public spaces with beautiful new views.

Page 5: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Benefits of Rideau River Footbridge1. Provides safe convenient link to and from the east and southeast

→ the Smyth Bridge not safe or well-connected.

Page 6: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Benefits (cont.)2. Connects communities

→ supports the OP’s “walkable 15-minute neighbourhoods” and “context-sensitive approach to neighbourhood evolution”

3. Supports Hurdman transit oriented development plans

4. Provides new cycling/pedestrian connection to Hurdman LRT.

Page 7: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Benefits (cont.)

5. Completes four-bridge canal-river loop.

Page 8: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Benefits (cont.)6. Links the two major Ottawa Hospital campuses

- safe & convenient cyclist route to Health Campus

- reduces traffic on Smyth

7. Fosters better “cross-town” cycling route

Page 9: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Benefits (cont.)8. Strengthens accessibility and appreciation of river

9. Provides easier and safer access to Lansdowne Park from east

10. Provides improved access to and safety of Riverside Drive greenspace and isolated Rideau River Eastern Pathway.

Page 10: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Cost• Could be modestly constructed

- Not World Heritage Site

- Minor navigation requirements

- Studies for the Adàwe are relevant

- Carleton footbridge will be $5M

• Economy should be the prime evaluation factor in design.

Page 11: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Priority• Supports LRT / OP / TOD

• Doing EA work and design work = “shovel-ready” project eligible for federal infrastructure funding

• Proposed footbridge should take priority over proposed footbridge between LRT and old railway bridges.

Page 12: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Alternative Location – Windsor Park

Clegg=

Windsor Pk=

Page 13: Proposed River Footbridge · 2020. 9. 10. · Proposed River Footbridge Alta Vista - Old Ottawa East AVCA Meeting September 2020. Proposal •Conduct cost-benefit analysis of footbridge

Assessment of Alternative Locations

Clegg• Connects to Hospital Link and RRWP-

RREP

• Connection to west via Flora and Main Street

• Requires some new east pathways

• Supports LRT and TOD

• 85m crossing

• Little impact on park / greenspace

• Benefits Riverview Pk & AV

Windsor Park• Connects to Pleasant Park cycling

route and RRWP-RREP

• Poor connections to west

• Requires new pathway through park

• No LRT or TOD benefits

• 95m crossing

• Some impact on park / greenspace

• Benefits AV and Heron Park

• Not better alternative to Bank Street / Billings Bridge