PROJECT:Ultrasonic Metering

Gas Flow Monitoring System

Bucharest, Ramada Parc HotelJune 23rd, 2011

Ledererhof 4, A-1010, Vienna, Austria2nd Trei Ierarhi Street, Ploiesti PH, RO-100010, Romaniawww.ipm-partners.com

Project: Ultrasonic Metering –Gas Flow Monitoring System

1

AGENDA

Who we are? Targeted Projects Targeted Partners Projects Brief Ultrasonic Metering – Basic Principles Project: Bragareasa Gas Flow Metering System Conclusions Q&A

Project: Ultrasonic Metering –Gas Flow Monitoring System

2

Who we are?

The successful sum of few experienced people, gathered together in 2008, to perform projects in a professional manner;

Oil and Gas Upstream projects as main previous businesses of key team members;

Most of them developed for PETROM, in organizations which are still existing or not;

Some of them still being references for OMV Petrom as recent success stories.

Civil and industrial projects (not Oil and Gas), also on the competences list;

Different roles played in past projects, ensuring pretty much all needed competences for the new projects targeted;

High level education, and international projects experience, are the binders which integrates all the above in a recipe we want to develop furthermore;

Project: Ultrasonic Metering –Gas Flow Monitoring System

3

AGENDA

Who we are? Targeted Projects Targeted Partners Projects Brief Ultrasonic Metering – Basic Principles Project: Bragareasa Gas Flow Metering System Conclusions Q&A

Project: Ultrasonic Metering –Gas Flow Monitoring System

4

Targeted Projects

• Small to Medium (for now) upstream construction projects, preferably EPCC type ones, in which we can take advantage of our knowledge and experiences.

• Upstream Turn Key projects, in which we are able to emphasize the qualitative services of our Engineering partners, primarily, and then the quality services of our manufacturing partners, E&I Partners, and suppliers of material, equipment and services for the above described works, all together.

• Main contracting for execution of industrial installations and sub-assemblies, such as measuring skids, tanks, vessels, manifolds, etc., from basic design to detail design, mechanical execution, E&I execution and testing, Commissioning, according to international standards and references.

• Civil constructions, but mostly connected to industrial environment, such as platforms, power and gas supply installations, environmental works, or combinations of these all.

Project: Ultrasonic Metering –Gas Flow Monitoring System

5

AGENDA

Who we are? Targeted Projects Targeted Partners Projects Brief Ultrasonic Metering – Basic Principles Project: Bragareasa Gas Flow Metering System Conclusions Q&A

Project: Ultrasonic Metering –Gas Flow Monitoring System

6

Targeted Partners

Small to medium local services providers, in the area of civil construction, mechanical fabrication, electrical and instrumentation design and equipping, with proven technological experiences and skills, but with low or no Project Management experience and also low Marketing abilities. We can use their skills together with our Marketing strategies and with our core business, Project Management.

Medium to large foreign companies, again, with proven capabilities on needed areas of execution, with low or weak knowledge of Romanian market, or with weak operational and/or Marketing nucleuses in Romania.

Romanian manufacturers or importers, with good quality of the materials and/or products delivered, but once more, with sales functions not acting properly, this bringing them into the position of not having enough clients for good products usable in the referenced industry;

People: Young and skilled, experienced people, to be hired project based, or undetermined, to support all the disciplines, whether in Engineering, Procurement, Execution or Commissioning phases of the project. Not only Romanians, but also from EU area.

Project: Ultrasonic Metering –Gas Flow Monitoring System

7

AGENDA

Who we are? Targeted Projects Targeted Partners Projects Brief Ultrasonic Metering – Basic Principles Project: Bragareasa Gas Flow Metering System Conclusions Q&A

Project: Ultrasonic Metering –Gas Flow Monitoring System

8

Projects Brief

Fabrication of LPG Metering Skids,

Client Emerson Process Management Flow, BV, The Netherlands

End User: Petrol Ofisi, Turkey,

Location: Izmit Refinery

Project: Ultrasonic Metering –Gas Flow Monitoring System

9

Projects Brief

Mechanical Fabrication Of Steam Jacketed Metering Skid – Liquid Sulpher

Client Emerson Process Management Flow, BV, The Netherlands

End User: Dolphin Energy, Quatar

Location: Ras Lafan Refinery, Quatar

Project: Ultrasonic Metering –Gas Flow Monitoring System

10

Projects Brief

Bragareasa Gas Flow Monitoring System

Client: OMV Petrom

Location: Bragareasa Area, Buzau County

Project: Ultrasonic Metering –Gas Flow Monitoring System

11

AGENDA

Who we are? Targeted Projects Targeted Partners Projects Brief Ultrasonic Metering – Basic Principles Project: Bragareasa Gas Flow Metering System Conclusions Q&A

Project: Ultrasonic Metering –Gas Flow Monitoring System

12

Ultrasonic Metering – Basic Principles (1)

Referenced: Daniel Ultrasonic Flowmeters

Juniorsonic•2-path design•Bouncing paths

Seniorsonic•4-path design•Chordal paths

Project: Ultrasonic Metering –Gas Flow Monitoring System

13

Ultrasonic Metering – Basic Principles (2)

Referenced: Daniel Ultrasonic Flowmeters - Juniorsonic

Two path meter

Uses bouncing paths

Requires live Reynolds number correction

Project: Ultrasonic Metering –Gas Flow Monitoring System

14

Ultrasonic Metering – Basic Principles (3)

Referenced: Daniel Ultrasonic Flowmeters - Juniorsonic

As both paths travel through centreline, they measure flow velocity at its highest point on the flow profile

A Reynolds number correction must be applied

Project: Ultrasonic Metering –Gas Flow Monitoring System

15

Ultrasonic Metering – Basic Principles (4)

Referenced: Daniel Ultrasonic Flowmeters - Juniorsonic

Flow profile correction is done in the USM MkIII Electronics • Flow Profile Correction Factor (CF)

Correction Factor calculated as shown below:

Requires knowledge of pipe roughness (WR) and Reynolds number

Project: Ultrasonic Metering –Gas Flow Monitoring System

16

Ultrasonic Metering – Basic Principles (5)

Referenced: Daniel Ultrasonic Flowmeters

Sr. Sonic• Accuracy 0.3%• Repeatability + 0.05% in range• Accuracy maintained with pipe wall

buildup

Jr. Sonic• Accuracy + 1.5%• Repeatability + 0.1% • Bounce path technology, dependent

on clean bounce areas

Sr/Jr Sonic

– Pressure loss < equivalent pipe length

– Self diagnostic – uptime with assurance

– Significantly increased rangeability up to 1:100

– High accuracy

– Allows higher velocities

Project: Ultrasonic Metering –Gas Flow Monitoring System

17

Ultrasonic Metering – Basic Principles (6)

Simple application – Leak detection

Definition: The comparison of measurement results by metering and comparing throughput at both ends of a transmission line.

Boss, we found the small leak in the pipe

Project: Ultrasonic Metering –Gas Flow Monitoring System

18

Meter A Meter B

Ultrasonic Metering – Basic Principles (6)

Simple application – Leak detection

Normally used in medium to long distance hard-to-access pipelines

Both throughput and pressure monitored

Difference noted results in alarm and pipeline shutdown

Does the flow measurement in “A” = flow measurement in “B”?

Page18

Project: Ultrasonic Metering –Gas Flow Monitoring System

19

AGENDA

Who we are? Targeted Projects Targeted Partners Projects Brief Ultrasonic Metering – Basic Principles Project: Bragareasa Gas Flow Metering System Conclusions Q&A

Project: Ultrasonic Metering –Gas Flow Monitoring System

20

Project – Bragareasa Gas Flow Monitoring System

Leak detection as the main reason to update the system.

Flow metering was efficient enough in the old solution.

Project: Ultrasonic Metering –Gas Flow Monitoring System

21

Project – Bragareasa Gas Flow Monitoring System

Simple fabrication in workshop of mechanical auxiliaries

Extra local sensors installed, information used to correct the metering and to be sent to operational centers (Temperature, Pressure)

Also local indication available.

Very short downtime of the pipeline for installation.

Project: Ultrasonic Metering –Gas Flow Monitoring System

22

Conclusions

Simple solutions are available on the market to solve metering problems, even when fiscal metering is not needed locally.

Some other problems can be solved by modern flow meters and by their interconnection and communication capabilities;

Not expensive solutions, however with performances which can be reached and balanced for the purpose.

Through simple yet efficient concepts, design, fabrication and installation, important problems can be solved.

Project: Ultrasonic Metering –Gas Flow Monitoring System

23

QUESTIONS?

Project: Ultrasonic Metering –Gas Flow Monitoring System

24

Thank you for your attention!

IPM-PartnersLedererhof 4, A-1010, Vienna, Austria

2nd Trei Ierarhi Street, Ploiesti PH, RO-100010, Romaniawww.ipm-partners.com

Bogdan [email protected]

Technical Support: Marius Barlogeanu, Emerson Romania