project overview surplus plutonium disposition (spd) project
TRANSCRIPT
Project OverviewSurplus Plutonium Disposition (SPD) Project
Savannah River SiteMarch 2021
M3-SR-21-0040, Rev. 1
UNCLASSIFIEDDOES NOT CONTAIN UNCLASSIFED
CONTROLLED NUCLEAR INFORMATIONReviewing Official: C. R. Dyer, QA Specialist, 3/16/2021
Outline
• Mission Need• Project Scope• Process Flow• Background• Roles and Responsibilities• Overview of Modifications• Nuclear Safety• Environmental, Safety and Health• Risks Management
2M3-SR-21-0040, Rev. 1
Background
8
• SPD Project will comply with DOE Order 413.3B, Change 5, Program andProject Management for the Acquisition of Capital Assets and DOE-STD-1189-2016, Integration of Safety into the Design Process.
• In accordance with DOE-STD-1189-2016: The project meets the criteria for a Major Modification Safety Design Strategy (SDS) for Hazard Category (HC) -2 nuclear
facility has been completed and reviewed by DOE/NNSA Conceptual Safety Design Report has been submitted to DOE/NNSA for
review and approval
M3-SR-21-0040, Rev. 1
Background
9
• SPD is unique in that the mission need, project management, execution,and integration. funding reside with NNSA while responsibility for the K-Area Complex in which the Project will be installed and operated is with ofthe Department of Energy Savannah River Operations Office (DOE-SR).
• The facility has a DOE-SR approved Documented Safety Analysis (DSA) andTechnical Safety Requirements (TSR) in place.
• Accordingly, DOE-SR, as delegated by the Assistant Secretary for the Officeof Environmental Management (EM-1), has responsibility for the propermanagement of the safety basis and will continue to approve all facilitysafety basis documents, including safety design basis documentsassociated with the Project or any changes to the operational safety basis(i.e., DSA and TSR) needed to support the Project.
• DOE-SR is also the Authority Having Jurisdiction (AHJ) for fire protectionrelated issues and decisions when called for in DOE Orders, Standards,NFPA or related documents.
M3-SR-21-0040, Rev. 1
10
Project Reporting Structure
M3-SR-21-0040, Rev. 1
11
General Overview105-K Interior Modifications
Presentation:• West Staging Area for in-coming supplies, pre-filled blend cans, empty
CCOs/bins/waste containers, etc.
Final Storage Area:• Process Area (First Floor) - Unpackaging Room, Entry Corridor,
Glovebox Airlocks, Glovebox Rooms, and Packaging Room (CCOPackaging & TRU Waste Handling)
• Support Area (Second Floor) – Service Area, Fire Suppression Rooms 1& 2, and Glovebox HEPA & Fan Room w/ associated Airlock
Shuffler Room:• MC&A Rooms 1&2• North-East Airlock
M3-SR-21-0040, Rev. 1
12
General Overview105-K Interior Modifications (Continued)
Water Seal:• MC&A Rooms 3&4• South-East Airlock• East Staging Area for interim storage of out-going filled CCOs
Assembly:• Material Staging/Inspection Area for incoming supplies, pre-filled blend
cans, empty CCO containers/bins/waste containers, etc.• Storage of empty and filled CCOs (single tier and double stacked)• Access stairs to Support Area / Emergency Egress Platform from
Support Area• Jib Crane/Maintenance Platform
M3-SR-21-0040, Rev. 1
13
General Overview105-K Exterior Modifications
Exterior Slab Over South Heat Exchanger Bay:• HEPA Fan & Filter Building (HEPA Filter & Fan Rooms 1 & 2 and
Electrical Distribution Room)• Diesel Generator w/ Enclosure
Yard Area:• Vehicle access road for HEPA Filter & Fan Building and Diesel
Generator Enclosure• Exhaust Stacks (Active Confinement & Glovebox Exhaust) and
associated foundations
M3-SR-21-0040, Rev. 1
Tailored Critical Decisions
• CD-0 (Mission Need) Approved September 2016 Cost Range $200M to $500M Schedule Range for CD-4 Approval 2Q FY2026 to 4Q FY2027
• Analysis of Alternatives (AoA) approved May 8, 2017• Tailoring Strategy Approved October 2019 which allows for CD-3A
Phases• CD-1 (Approve Alternative Selection and Cost Range) Approved
December 2019 Cost Range $448M to $620M Schedule Range for CD-4 Approval 2Q FY2026 to 2Q FY2028
• CD-3A, Phase 1 (Early Site Preparation) Approved January 2020 Cost $28M Forecast completion 3Q FY2021
• CD-3A, Phase 2 (Long Lead Procurements) Approved December 2020 Cost $33.7M Forecast completion 3Q FY2024
14M3-SR-21-0040, Rev. 1
15
Tailored Critical Decisions Continued
• CD-3A Phase 3, Authorize Additional Site Preparation forecast August 2021 Cost Range $50M to$60M Forecast completion 4Q FY2023
• CD-3A Phase 4, Authorize Additional Long Lead Procurements forecast 1Q, 2022 Cost Range $ 20M to $30M Forecast completion 3Q FY2024
• CD-2/3, Approve Performance Baseline/ Approve Start of Construction forecast 4Q FY2022 (subject to change) Cost Range $448M to $620M Forecast completion 2Q FY2025
• CD-4, Approve Start of Operations or Project Completion 2Q FY2026 to 2Q FY2028
M3-SR-21-0040, Rev. 1
Project Scope (CD-3A Phase 1)
• Perform re-work/D&R of existing conduits and cables within the project area(Telecommunications, Fire Detection, S&S etc.)
• Cut opening in the South wall of A water seal and install door (3-hour fire rateddoor)
• Install a temporary 3-hour Fire Rated Shaft Wall at the opening (between MSAand Presentation)
• Place concrete infill in existing ventilation opening between the A water seal andA vestibule
• Install security plates over doors (Presentation Side, KAMs Corridor Side, andPresentation Side)
• Cut a 10’ x 12’ Construction access opening in South Wall of Presentation• Cut opening in West wall of A water seal from the Final Storage Area (FSA)• Cut an opening in the South wall of Presentation (leave blocks in place)• Cut two (2) new door openings at +15’ elevations (leave blocks in place)• Remove door frame, and associated gypsum wall system
16M3-SR-21-0040, Rev. 1
CD-3A Phase 2 Summary
17
Procurement of the Following Long Lead items:• Safety Class (SC) Gloveboxes
Three (3) gloveboxes with identical specifications Glovebox Shell, Support Frame and Anchorage are Safety Class Glovebox Confinement Boundary is Safety Significant
• Safety Significant (SS) Diesel Generator w/ Enclosure• Safety Significant (SS) HEPA Filter Housings
Two (2) Glovebox Exhaust HEPA Housings Two (2) Glovebox Hood Exhaust HEPA Housings Two (2) Dilute Process Area (DPA) HEPA Housings
M3-SR-21-0040, Rev. 1
CD-3A Phase 3 Summary
18
• Additional concrete cuts not captured in CD-3A Phase 1: West wall of FSA into presentation area East wall of FSA into the B water seal (i.e., shuffler room) South wall of B water seal into A water seal Concrete removal within A and B water seal (Floor and Curtain wall) Concrete removal to support drainpipe work and installation of second floor footings
• Modifications of existing facility drain piping in preparation for installation of new fire suppressionsystem
• Re-work existing expansion joint in FSA Wall• Installation of second floor (Footings, structural steel and reinforced concrete)• Installation of two (2) new doors• D&R of existing commodities within the B water seal to include:
Safeguards and Security Equipment Shaft Wall Fire Suppression items Electrical items
• Installation of new concrete wall and floor slabs in water seal rooms• Removal of Door and placement of concrete in opening• Removal of existing concrete dike South of 105-K (i.e., future stack foundation location)
M3-SR-21-0040, Rev. 1
CD-3A Phase 4 Summary
19
• Additional long lead procurements not captured in CD-3A Phase 2: Safety Class Fire Suppression and Detection System Components HVAC Exhaust Fans and associated components Glovebox Equipment MC&A Assay Equipment Safety Class Electrical Equipment Construction Materials and Equipment needed to support the first 6
months of Post CD-3 approval field work
Note: The content of CD-3A Phase 4 is still under development.
M3-SR-21-0040, Rev. 1
Environmental, Safety & Health
• NEPA Strategy completed; additional Environmental Checklistcompleted; no further action is required to complete construction andturnover to operations.
• Environmental Compliance Strategy was developed that identifiesenvironmental requirements, permits, and approvals for constructionand operation which are included in the project schedule.
• Preliminary Hazard Analysis Report (PHAR) and Facility Classificationapproved August 2019. Hazards studied include fires, explosions, loss of confinement,
radiation exposure, external events and Natural PhenomenaHazard.
20M3-SR-21-0040, Rev. 1
Status of Safety Basis Documents
Safety Basis Document Status
Safety Design Strategy Complete (will be updated throughout project as needed)
CSDR Complete
KAC DSA Addendum and TSRs for Site Preparation Complete
Safety Documentation For Long Lead Procurements Complete
KAC DSA Revision/ TSRs for Construction In-ProcessFinish: 3/25/2021
PDSA In-ProcessFinish: 10/21/2022
KAC DSA and TSR Revision to Incorporate SPD ScheduledStart: 1/9/2023Finish: 9/5/2024
21M3-SR-21-0040, Rev. 1
Risk Management
• Project utilizes risk analysis software Active Risk Manager(ARM) based on DOE Guide (G) 413.3-7A, Risk ManagementGuide.
• MR and DOE Contingency are based on detailed quantitativerisk analysis.
• Monte Carlo analysis includes both discrete risk/opportunitiesand cost and schedule uncertainty analysis.
• We review all the project risks on a monthly basis as a team.
22M3-SR-21-0040, Rev. 1
Top Project Risks
Risk Handling Strategy Description
Funding Delays Accept Lack of funds will increase cost and schedule.
Mitigated dose consequences challenge regulatory limits requiring additional modifications
Mitigate Preliminary accident analysis calculations are being performed early to minimize design impacts
Life Safety and building occupancy codes increase fire suppression and fire alarm requirements
Mitigate Early and continued engagement with DOE and the Authority Having Jurisdiction (AHJ) as the fire protection plan matures.
Safeguards measurement systems do not meet throughput requirements requiring additional units
Mitigate
Early and continued engagement with the Program to ensure activities required to determine uncertainty levels and the count time requirements for the Neutron Multiplicity Counters (NMC) are validated.
Engineered equipment vendors fail to perform Mitigate
Vendors are being audited and qualified early in the design process to ensure sufficient qualified vendors are available once the project is ready to award engineered equipment subcontracts.
EVMS Certification is not obtained prior to CD-2/3 delaying the project schedule
MitigateProject is requesting an early Assist Visit in summer of 2020. Corrective actions will be addressed prior to the Certification Visit.
23M3-SR-21-0040, Rev. 1
24
Safety-In-Design Project Risks
Record Type
ID Title Handling Strategy Current Risk Level Target Risk Level
Risk 7050 K-Area Safety Basis Increases Consequence Mitigate Moderate (18) Moderate (18)
Risk 6656 Changing requirements for multi-tool Mitigate Moderate (17) Moderate (12)
Risk 3543 Fire Protection system fails seismic qualifications resulting in additional modifications
Accept Moderate (16) Moderate (16)
Risk 3546 Lightning Protection requirements of current codes extended to legacy systems increases
project scope
Mitigate Moderate (16) Moderate (12)
Risk 3547 Fire System Qualification repeated due to vendor design changes and delaying delivery
Accept Moderate (12) Moderate (12)
Risk 6634 Fire Suppression in the HEPA Housing is Required Mitigate Moderate (12) Low (6)
Risk 5391 Adulterant formula increases worker dose and results in changes to project scope
Mitigate Moderate (9) Moderate (9)
Risk 5384 Results of HEPA filter soot loading calculation increases project scope
Accept Low (8) Low (8)
Risk 5379 Fire barrier design is not approved by DOE Mitigate Low (6) Low (6)
Risk 5385 Fire in emergency lights after power is de-energized
Accept Low (6) Low (6)
Risk 5394 Fire caused by security devices after primary power is de-energized
Accept Low (2) Low (2)
M3-SR-21-0040, Rev. 1