project management professional (pmp)® exam prep course 11...
TRANSCRIPT
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Project Management Professional (PMP)®
Exam Prep
Course 11 - Project Risk Management
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 1
Looking Glass Development, LLC
(303) 663-5402 / (888) 338-7447
4610 S. Ulster St. #150 Denver, CO 80237
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 2
The processes concerned with conducting risk management planning, identification, analysis, responses and monitoring and control on a project.Updated throughout the project.Increase the probability and impact of positiverisks & decrease the probability and impact of negative risks.
9 / 1 2 /20 13 2v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Planning Process Group
11. Project Risk Management
11.1Plan Risk
Management
11.3Perform
QualitativeRisk Analysis
11.2Identify Risks
11.4Perform
QuantitativeRisk Analysis
11.5Plan Risk
Responses
Monitoring and Controlling Process Group
11. Project Risk
Management
11.6Control Risks
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 3
Risk – an uncertain event or condition
that, if realized, has a positive or negative impact on at least one
project objective (such as time, cost,
scope or quality).
Risks can have one or more causes and one or more impacts.
9 / 1 2 /20 13 3v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 4
Types of RisksKnown Risks - Can be analyzed, possible to plan. Contingency reserve or other plans.
Unknown Risks - Cannot be managed proactively. General contingency or management reserve.
9 / 1 2 /20 13 4v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 5
Key TermsRisk Tolerance
Risk Averse
Risk Factors◦ Probability & impact◦ The range of possible outcomes◦ Expected timing in the project life-cycle
9 / 1 2 /20 13 5v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 6
11.1 Plan Risk ManagementThe process of deciding how to approach & conduct risk management activities for a project.Ensure that the level, type & visibility of risk management are commensurate with both the risk & importance of the project.Provide sufficient resources & time for risk management activities.Establish an agreed-upon basis for evaluating risks.
9 / 1 2 /20 13 6v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Planning Process Group
11. Project Risk Management
11.1Plan Risk
Management
11.3Perform
QualitativeRisk Analysis
11.2Identify Risks
11.4Perform
QuantitativeRisk Analysis
11.5Plan Risk
Responses
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 7
11.1 Plan Risk Management
10/17/2014 7v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Inputs.1 Project management plan
.2 Project charter
.3 Stakeholder register
.4 Enterprise environmental factors
.5 Organizational process assets
Tools & Techniques.1 Analytical techniques
.2 Expert judgment
.3 Meetings
Outputs.1 Risk management plan
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 8
Included in the Risk Management Plan
MethodologyRoles and ResponsibilitiesBudgetingTimingRisk Categories (RBS) . . .Revised stakeholder tolerancesReporting formatsTracking Definitions of probability and impactMatrices . . .
9 / 1 2 /20 13 8v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 9
Sample RBS
9 / 1 2 /20 13 9v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 10
Scales for Impact and Probability
Linear◦ .1, .3, .5, .7,.9
Non-Linear◦ .05, .10, .20, .40, .80
Relative◦ Very low, low, medium,
high, very high
9 / 1 2 /20 13 10v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 11
Project
Objectives Very Low / .05 Low / .10 Medium / .20 High / .40 Very High / .80
Cost Insignificant cost increase
<10% cost increase
10%-20% cost increase
20%-40% cost increase
>40% cost increase
Time Insignificant time increase
<5% Time increase
5%-10% time increase
10%-20% time increase
>20% time increase
Scope Scope decrease barely noticeable
Minor areas of scope affected
Major areas of scope affected
Scope reduction unacceptable to
sponsor
Product of project is
effectively
unusable
Quality Quality degradation barely
noticeable
Only very demanding
applications
are affected
Quality reduction requires sponsor’s
approval
Quality reduction
unacceptable to
sponsor
Product of project is
effectively
unusable
9 / 1 2 /20 13 11v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Sample Impact Matrix
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 12
11.2 Identify RisksDetermine which risks might affect
the project and documents their characteristics◦ Project Manager
◦ Project Team
◦ Stakeholders
◦ Subject matter experts
◦ People outside the project
9 / 1 2 /20 13 12v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Planning Process Group
11. Project Risk Management
11.1Plan Risk
Management
11.3Perform
QualitativeRisk Analysis
11.2Identify Risks
11.4Perform
QuantitativeRisk Analysis
11.5Plan Risk
Responses
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 13
11.2 Identify Risks
9 / 1 2 /20 13 13v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Inputs.1 Risk management plan
.2 Cost management plan
.3 Schedule management
plan
.4 Quality management plan
.5 Human resource
management plan
.6 Scope baseline
.7 Activity cost estimates
.8 Activity duration estimates
.9 Stakeholder register
.10 Project documents
.11 Procurement documents
.12 Enterprise environmental
factors
.13 Organizational process
assets
Tools & Techniques.1 Documentation reviews
.2 Information gathering
techniques
.3 Checklist analysis
.4 Assumption analysis
.5 Diagramming techniques
.6 SWOT analysis
.7 Expert judgment
Outputs.1 Risk register
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 14
Tools & TechniquesInformation gathering◦ Brainstorming◦ Delphi Technique – reduce bias◦ InterviewsAssumption analysisSWOTChecklist analysis – be carefulDiagramming◦ Cause and effect◦ Flow charts◦ Influence diagrams
9 / 1 2 /20 13 14v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Problem
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 15
The Risk RegisterList of identified risks
And possibly
◦ List of potential responses
◦ Root causes
◦ Updated risk categories
9 / 1 2 /20 13 15v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 16
11.3 Perform Qualitative Risk Analysis
Prioritizing the identified risks for further action (including further analysis or response planning).
Uses the probability and impact scoring defined in Plan Risk Management.
9 / 1 2 /20 13 16v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Planning Process Group
11. Project Risk Management
11.1Plan Risk
Management
11.3Perform
QualitativeRisk Analysis
11.2Identify Risks
11.4Perform
QuantitativeRisk Analysis
11.5Plan Risk
Responses
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 17
11.3 Perform Qualitative Risk Analysis
9 / 1 2 /20 13 17v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Inputs.1 Risk management plan
.2 Scope baseline
.3 Risk register
.4 Enterprise environmental
factors
.5 Organizational process
assets
Tools & Techniques.1 Risk probability and
impact assessment
.2 Probability and
impact matrix
.3 Risk data quality
assessment
.4 Risk categorization
.5 Risk urgency
assessment
.6 Expert judgment
Outputs.1 Project document
updates
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 18
Probability Risk Score = P x I0.05 0.10 0.20 0.40 0.80
0.9 0.045 0.09 0.18 0.36 0.72
0.7 0.035 0.07 0.14 0.28 0.56
0.5 0.025 0.05 0.10 0.20 0.40
0.3 0.015 0.03 0.06 0.12 0.24
0.1 0.005 0.01 0.02 .04 0.08
9 / 1 2 /20 13v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC. 18
Probability & Impact Matrix
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 19
11.4 Perform Quantitative Risk Analysis
Analyzes the effect of those risk events that have been prioritized as potentially and substantially impacting the project’s competing demands, and assigns a numerical rating to those risks
Also presents a quantitativeapproach to making decisionsin the presence of uncertainty
9 / 1 2 /20 13 19v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Planning Process Group
11. Project Risk Management
11.1Plan Risk
Management
11.3Perform
QualitativeRisk Analysis
11.2Identify Risks
11.4Perform
QuantitativeRisk Analysis
11.5Plan Risk
Responses
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 20
11.4 Quantitative Risk Analysis
9 / 1 2 /20 13 20v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Inputs.1 Risk management plan
.2 Cost management plan
.4 Schedule management
plan
.5 Enterprise environmental
factors
.5 Organizational process
assets
Tools & Techniques.1 Data gathering &
representation techniques
.2 Quantitative risk analysis &
modeling techniques
.3 Expert judgment
Outputs.1 Project documents
updates
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 21
Data Modeling - SimulationMonte Carlo Simulations
Cost - Use WBS or similar breakdown Schedule - Use PDM
Data Modeling - Sensitivity Analysis
Determine the most potential impact.Impact of single element of uncertainty when all other elements are held at baseline.
9 / 1 2 /20 13 21v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 22
9 / 1 2 /20 13v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC. 22
Expected Monetary Value (EMV)
Calculates the average outcome when future events are uncertain
Cost Probability Product
Optimistic Outcome $150,000 .20 $ 30,000
Likely Outcome $225,000 .50 $112,500
Pessimistic Outcome $300,000 .30 $ 90,000
$ 232,500
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 23
Decision Tree Analysis
9 / 1 2 /20 13 23v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
ChoiceEvent
ChanceEvent
ChanceEvent
60%
40%
20%
80%
Outcome EMV
$250K $150K
-$100K -$40K
-$45K -$9K
$20K $16K
Conservative EMV = $7,000
Aggressive EMV = $110,000
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 24
9/18/2013v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC. 24
OTS or
Develop
OTS
Develop
Well
received
Rejected
Well
received
Rejected
$ - 250K
$ - 350K
65%
$550 K
35%
$ -100 K
85%
$500 K
15%
-60K
$ 300K
$ - 350K
$ 150K
$ - 410K
$ 195K
$ -123K
$ 128K
$ -61.5K
OTS
$ 72.5K
Develop$ 66K
A.Cost ofChoice
B.Probability
&Outcome
C.Outcome
MinusCost
D.C * Probability
E.Final Outcomes
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 25
11.5 Plan Risk ResponsesDeveloping options and determining actions to enhance opportunities and reduce threats to the project’s objectives.
Addresses the risks by their priority, inserting resources and activities into the budget, schedule, and project
management plan, as needed.
9 / 1 2 /20 13 25v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Planning Process Group
11. Project RiskManagement
11.1Plan Risk
Management
11.3Perform
QualitativeRisk Analysis
11.2Identify Risks
11.4Perform
QuantitativeRisk Analysis
11.5Plan Risk
Responses
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 26
11.5 Plan Risk Responses
9 / 1 2 /20 13 26v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Inputs.1 Risk management plan
.2 Risk register
Tools & Techniques.1 Strategies for negative
risk or threats
.2 Strategies of positive
risks or opportunities
.3 Contingent response
strategy
.4 Expert judgment
Outputs.1 Project management
plan updates
.2 Project document
updates
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 27
Response Strategies
Threats Opportunities
Avoid Exploit
Transfer Share
Mitigate Enhance
Accept
9 / 1 2 /20 13v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC. 27
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 28
9 / 1 2 /20 13v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC. 28
Impacts to the projectOwnerAnalysis dataSelected strategyAction itemsFallback plans
Symptoms/warning signs (Triggers)Budget and schedule updates to be madeContingency requests, requirements, plans
Risk Register Updates
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 29
11.6 Control RisksIdentifying, analyzing, and planning for newly arising risks.Keeping track of identified risks and those on the watchlist.Monitoring trigger conditions for contingency plans.Reviewing the execution of risk responses while evaluating their effectiveness.Reanalyzing existing risks.Monitoring residual risks.
9 / 1 2 /20 13 29v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Monitoring and Controlling Process Group
11. Project Risk
Management
11.6Control Risks
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 30
11.6 Control Risks
9 / 1 2 /20 13 30v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
Inputs.1 Project management
plan
.2 Risk register
.3 Work performance
data
.4 Work performance
reports
Tools & Techniques.1 Risk reassessment
.2 Risk audits
.3 Variance & trend analysis
.4 Technical performance
measurement
.5 Reserve analysis
.6 Meetings
Outputs.1 Work performance
information
.2 Change requests
.3 Project management
plan updates
.4 Project document
updates
.5 Organizational process
assets updates
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 31
Results of Risk Monitoring & Control
Workarounds
Contingency plans
Residual risks – expected to remain
Secondary risks – result of responses
Contractual updates
9 / 1 2 /20 13 31v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 32
Project Risk Management –Summary
Six (6) processesActivities of Monitor & Control Risks
Seven types of risk responses
Risk registerDefinition of risk, positive and negative
Solving & interpreting decision trees & EMV
9 / 1 2 /20 13 32v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Slide 33
Project Risk Management –Summary
Delphi techniqueSWOT analysisRisk data quality assessmentSensitivity analysisQualitative vs. Quantitative analysisInterpret quantitative probability and outcome data chart
9/18/2013 33v. 7.0 - © Copyright and all rights reserved –2013 Looking Glass Development, LLC.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Review Questions – Part 1:
1. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $10,000
with a probability of 20%, a most likely case estimate of U.S. $12,000 with a
probability of 50%, and a worst case estimate of U.S. $14,400 with a probability
of 30% what is the EMV for the project?
A. U.S. $12,320
B. U.S. $12,400
C. U.S. $13,010
D. U.S. $13,260
2. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $15,000
with a probability of 30%, a most likely case estimate of U.S. $19,500 with a
probability of 50%, and a worst case estimate of U.S. $26,325 with a probability
of 20% what is the EMV for the project?
A. U.S. $19.190
B. U.S. $19,515
C. U.S. $20,110
D. U.S. $20,350
3. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $25,000
with a probability of 22%, a most likely case estimate of U.S. $31,250 with a
probability of 53%, and a worst case estimate of U.S. $40,625 with a probability
of 25% what is the EMV for the project?
A. U.S. $30.190
B. U.S. $31,560
C. U.S. $32,219
D. U.S. $33,350
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
4. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $50,000
with a probability of 25%, a most likely case estimate of U.S. $55,000 with a
probability of 45%, and a worst case estimate of U.S. $68,750 with a probability
of 30% what is the EMV for the project?
A. U.S. $55,975
B. U.S. $56,550
C. U.S. $57,125
D. U.S. $57,875
5. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $75,000
with a probability of 30%, a most likely case estimate of U.S. $86,250 with a
probability of 40%, and a worst case estimate of U.S. $99,188 with a probability
of 30% what is the EMV for the project?
A. U.S. $86.756
B. U.S. $87,247
C. U.S. $87,691
D. U.S. $88,121
6. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $30,000
with a probability of 24%, a most likely case estimate of U.S. $34,500 with a
probability of 56%, and a worst case estimate of U.S. $45,540 with a probability
of 20% what is the EMV for the project?
A. U.S. $35,121
B. U.S. $35,628
C. U.S. $36,222
D. U.S. $36,923
7. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $35,000
with a probability of 15%, a most likely case estimate of U.S. $40,250 with a
probability of 60%, and a worst case estimate of U.S. $54,338 with a probability
of 25% what is the EMV for the project?
A. U.S. $41,652
B. U.S. $42,111
C. U.S. $42,984
D. U.S. $43,596
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
8. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $20,000
with a probability of 10%, a most likely case estimate of U.S. $23,200 with a
probability of 65%, and a worst case estimate of U.S. $32,480 with a probability
of 25% what is the EMV for the project?
A. U.S. $23,950
B. U.S. $24,220
C. U.S. $24,880
D. U.S. $25,200
9. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $5,000
with a probability of 30%, a most likely case estimate of U.S. $5,900 with a
probability of 45%, and a worst case estimate of U.S. $8,024 with a probability of
25% what is the EMV for the project?
A. U.S. $6,161
B. U.S. $6,437
C. U.S. $6,918
D. U.S. $7,020
10. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $7,500
with a probability of 20%, a most likely case estimate of U.S. $9,150 with a
probability of 55%, and a worst case estimate of U.S. $11,529 with a probability
of 25% what is the EMV for the project?
A. U.S. $8,919
B. U.S. $9,126
C. U.S. $9,415
D. U.S. $9,783
11. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $12,500
with a probability of 35%, a most likely case estimate of U.S. $15,500 with a
probability of 55%, and a worst case estimate of U.S. $19,375 with a probability
of 10% what is the EMV for the project?
A. U.S. $14,117
B. U.S. $14,838
C. U.S. $15,236
D. U.S. $15,911
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
12. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $17,500
with a probability of 36%, a most likely case estimate of U.S. $21,875 with a
probability of 44%, and a worst case estimate of U.S. $25,375 with a probability
of 20% what is the EMV for the project?
A. U.S. $21,467
B. U.S. $20,918
C. U.S. $20,641
D. U.S. $21,000
13. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $22,500
with a probability of 28%, a most likely case estimate of U.S. $25,875 with a
probability of 42%, and a worst case estimate of U.S. $30,533 with a probability
of 30% what is the EMV for the project?
A. U.S. $26,327
B. U.S. $26,914
C. U.S. $27,456
D. U.S. $28,011
14. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $3,250
with a probability of 18%, a most likely case estimate of U.S. $3,575 with a
probability of 42%, and a worst case estimate of U.S. $4,433 with a probability of
40% what is the EMV for the project?
A. U.S. $3,645
B. U.S. $3,860
C. U.S. $4,012
D. U.S. $4,125
15. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $32,000
with a probability of 15%, a most likely case estimate of U.S. $34,560 with a
probability of 55%, and a worst case estimate of U.S. $43,891 with a probability
of 30% what is the EMV for the project?
A. U.S. $35,798
B. U.S. $36,152
C. U.S. $36,975
D. U.S. $37,513
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
16. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $80,000
with a probability of 20%, a most likely case estimate of U.S. $102,400 with a
probability of 50%, and a worst case estimate of U.S. $123,904 with a probability
of 30% what is the EMV for the project?
A. U.S. $101,995
B. U.S. $102,822
C. U.S. $103,543
D. U.S. $104,371
17. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $60,000
with a probability of 25%, a most likely case estimate of U.S. $70,200 with a
probability of 65%, and a worst case estimate of U.S. $86,346 with a probability
of 10% what is the EMV for the project?
A. U.S. $69,265
B. U.S. $67,240
C. U.S. $70,613
D. U.S. $68,687
18. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $200,000
with a probability of 30%, a most likely case estimate of U.S. $228,000 with a
probability of 55%, and a worst case estimate of U.S. $287,280 with a probability
of 15% what is the EMV for the project?
A. U.S. $227,764
B. U.S. $228,106
C. U.S. $228,492
D. U.S. $229,621
19. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $250,000
with a probability of 28%, a most likely case estimate of U.S. $322,500 with a
probability of 42%, and a worst case estimate of U.S. $422,475 with a probability
of 30% what is the EMV for the project?
A. U.S. $330,465
B. U.S. $332,193
C. U.S. $343,167
D. U.S. $355,891
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
20. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $500,000
with a probability of 12%, a most likely case estimate of U.S. $660,000 with a
probability of 58%, and a worst case estimate of U.S. $739,200 with a probability
of 30% what is the EMV for the project?
A. U.S. $660,465
B. U.S. $662,193
C. U.S. $663,167
D. U.S. $664,560
21. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $100,000
with a probability of 16%, a most likely case estimate of U.S. $134,000 with a
probability of 64%, and a worst case estimate of U.S. $152,760 with a probability
of 20% what is the EMV for the project?
A. U.S. $132,312
B. U.S. $132,615
C. U.S. $133,213
D. U.S. $133,814
22. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $70,000
with a probability of 22%, a most likely case estimate of U.S. $74,900 with a
probability of 58%, and a worst case estimate of U.S. $82,390 with a probability
of 20% what is the EMV for the project?
A. U.S. $74,230
B. U.S. $74,670
C. U.S. $75,110
D. U.S. $75,320
23. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $5,000
with a probability of 24%, a most likely case estimate of U.S. $5,800 with a
probability of 46%, and a worst case estimate of U.S. $6,670 with a probability of
30% what is the EMV for the project?
A. U.S. $5,660
B. U.S. $5,869
C. U.S. $5,910
D. U.S. $5,976
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
24. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $1,000
with a probability of 30%, a most likely case estimate of U.S. $1,180 with a
probability of 50%, and a worst case estimate of U.S. $1,369 with a probability of
20% what is the EMV for the project?
A. U.S. $1,164
B. U.S. $1,179
C. U.S. $1,191
D. U.S. $1,199
25. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $6,500
with a probability of 32%, a most likely case estimate of U.S. $7,865 with a
probability of 48%, and a worst case estimate of U.S. $9,202 with a probability of
20% what is the EMV for the project?
A. U.S. $7,584
B. U.S. $7,610
C. U.S. $7,696
D. U.S. $7,713
26. You have been asked to establish an estimated project cost using Expected
Monetary Value (EMV). If the project has a best case estimate of U.S. $4,800
with a probability of 35%, a most likely case estimate of U.S. $6,000 with a
probability of 45%, and a worst case estimate of U.S. $7,200 with a probability of
20% what is the EMV for the project?
A. U.S. $5,776
B. U.S. $5,820
C. U.S. $5,901
D. U.S. $6,030
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Review Questions – Part 2:
1. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $650,000 and B will cost U.S. $467,000. There is a
56% chance that project A will be successful, which will result in a gain of U.S.
$1,800,000. If project A fails there will be a loss of U.S. $900,000. There is a 67%
project B will be successful, and that will result in a U.S. $950,000 gain. If Project B
fails there will be a loss of U.S. $670,000. Based on this information, what is the
value of the best alternative?
A. U.S. $-38,000
B. U.S. $38,000
C. U.S. $-51,600
D. U.S. $51,600
2. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $54,000 and B will cost U.S. $90,000. There is a
54% chance that project A will be successful, which will result in a gain of U.S.
$206,540. If project A fails there will be a loss of U.S. $90,500. There is a 61% project
B will be successful, and that will result in a U.S. $269,000 gain. If Project B fails
there will be a loss of U.S. $118,000. Based on this information, which project do you
choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
3. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $300,000 and B will cost U.S. $255,000. There is a
67% chance that project A will be successful, which will result in a gain of U.S.
$650,000. If project A fails there will be a loss of U.S. $310,000. There is a 58%
project B will be successful, and that will result in a U.S. $650,000 gain. If Project B
fails there will be a loss of U.S. $225,000. Based on this information, what is the
value of the best alternative?
A. U.S. $60,700
B. U.S. $27,500
C. U.S. $33,200
D. U.S. $51,600
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
4. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $345,000 and B will cost U.S. $300,000. There is a
67% chance that project A will be successful, which will result in a gain of U.S.
$789,000. If project A fails there will be a loss of U.S. $310,000. There is a 58%
project B will be successful, and that will result in a U.S. $980,000 gain. If Project B
fails there will be a loss of U.S. $289,000. Based on this information, which project
do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
5. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $288,000 and B will cost U.S. $225,500. There is a
61% chance that project A will be successful, which will result in a gain of U.S.
$650,000. If project A fails there will be a loss of U.S. $287,000. There is a 57%
project B will be successful, and that will result in a U.S. $560,000 gain. If Project B
fails there will be a loss of U.S. $225,000. Based on this information, what is the
value of the best alternative?
A. U.S. $6,480
B. U.S. -$3,050
C. U.S. $3,200
D. U.S. -$3,430
6. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $750,000 and B will cost U.S. $594,000. There is a
68% chance that project A will be successful, which will result in a gain of U.S.
$1,600,000. If project A fails there will be a loss of U.S. $978,000. There is a 63%
project B will be successful, and that will result in a U.S. $1,400,000 gain. If Project B
fails there will be a loss of U.S. $725,000. Based on this information, which project
do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
7. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $663,500 and B will cost U.S. $589,000. There is a
66% chance that project A will be successful, which will result in a gain of U.S.
$1,399,000. If project A fails there will be a loss of U.S. $663,500. There is a 69%
project B will be successful, and that will result in a U.S. $1,005,000 gain. If Project B
fails there will be a loss of U.S. $225,000. Based on this information, what is the
value of the best alternative?
A. U.S. $34,250
B. U.S. $34,700
C. U.S. $68,950
D. U.S. $68,525
8. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $89,000 and B will cost U.S. $130,000. There is a
78% chance that project A will be successful, which will result in a gain of U.S.
$284,000. If project A fails there will be a loss of U.S. $310,000. There is an 81%
project B will be successful, and that will result in a U.S. $332,500 gain. If Project B
fails there will be a loss of U.S. $361,900. Based on this information, which project
do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
9. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $79,250 and B will cost U.S. $75,500. There is a
71% chance that project A will be successful, which will result in a gain of U.S.
$690,000. If project A fails there will be a loss of U.S. $309,500. There is a 75%
project B will be successful, and that will result in a U.S. $570,500 gain. If Project B
fails there will be a loss of U.S. $219,500. Based on this information, what is the
value of the best alternative?
A. U.S. $320,895
B. U.S. $618,395
C. U.S. $297,500
D. U.S. $648,716
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
10. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $300,000 and B will cost U.S. $255,000. There is a
67% chance that project A will be successful, which will result in a gain of U.S.
$284,000. If project A fails there will be a loss of U.S. $310,000. If project B is
successful it will result in a U.S. $332,500 gain. If Project B fails there will be a loss of
U.S. $361,900. Based on this information, which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
11. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $40,000 and B will cost U.S. $55,000. There is a
59% chance that project A will be successful, which will result in a gain of U.S.
$151,000. If project A fails there will be a loss of U.S. $94,000. There is a 55% project
B will be successful, and that will result in a U.S. $168,500 gain. If Project B fails
there will be a loss of U.S. $72,500. Based on this information, what is the value of
the best alternative?
A. U.S. $5,500
B. U.S. $15,600
C. U.S. $10,550
D. U.S. $21,525
12. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $27,500 and B will cost U.S. $32,250. There is a
71% chance that project A will be successful, which will result in a gain of U.S.
$200,500. If project A fails there will be a loss of U.S. $173,700. There is a 65%
chance B will be successful and if it is successful it will result in a U.S. $243,000 gain.
If Project B fails there will be a loss of U.S. $191,500. Based on this information,
which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
13. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $77,230 and B will cost U.S. $91,980. There is a
63% chance that project A will be successful, which will result in a gain of U.S.
$740,000. If project A fails there will be a loss of U.S. $300,000. There is a 77%
project B will be successful, and that will result in a U.S. $500,000 gain. If Project B
fails there will be a loss of U.S. $225,000. Based on this information, what is the
value of the best alternative?
A. U.S. $703,200
B. U.S. $425,230
C. U.S. $277,970
D. U.S. $256,990
14. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $27,500 and B will cost U.S. $32,250. There is a
71% chance that project A will be successful, which will result in a gain of U.S.
$200,500. If project A fails there will be a loss of U.S. $173,700. There is a 65%
chance B will be successful and if it is successful it will result in a U.S. $243,000 gain.
Based on this information, which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
15. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $210,000 and B will cost U.S. $255,000. There is a
60% chance that project A will be successful, which will result in a gain of U.S.
$650,000. If project A fails there will be a loss of U.S. $325,000. There is a 65%
project B will be successful, and that will result in a U.S. $550,000 gain. If Project B
fails there will be a loss of U.S. $207,750. Based on this information, what is the
value of the best alternative?
A. U.S. $79,788
B. U.S. $29,788
C. U.S. $27,970
D. U.S. $50,000
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
16. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $177,500 and B will cost U.S. $212,500. There is a
76% chance that project A will be successful, which will result in a gain of U.S.
$630,000. If project A fails there will be a loss of U.S. $310,000. There is a 69%
chance B will be successful and if it is successful it will result in a U.S. $580,000 gain.
If project B fails there will be a loss of U.S. $200,000. Based on this information,
which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
17. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $12,500 and B will cost U.S. $15,250. There is a
72% chance that project A will be successful, which will result in a gain of U.S.
$65,000. If project A fails there will be a loss of U.S. $31,000. There is a 66% project
B will be successful, and that will result in a U.S. $56,500 gain. If Project B fails there
will be a loss of U.S. $22,500. Based on this information, what is the value of the
best alternative?
A. U.S. $14,390
B. U.S. $19,780
C. U.S. $25,620
D. U.S. $40,010
18. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $85,000 and B will cost U.S. $99,000. There is a
67% chance that project A will be successful, which will result in a gain of U.S.
$600,000. If project A fails there will be a loss of U.S. $345,000. There is a 58%
chance B will be successful and if it is successful it will result in a U.S. $685,000 gain.
If project B fails there will be a loss of U.S. $255,000. Based on this information,
which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
19. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $241,250 and B will cost U.S. $225,500. There is a
65% chance that project A will be successful, which will result in a gain of U.S.
$550,500. If project A fails there will be a loss of U.S. $310,000. There is a 60%
project B will be successful, and that will result in a U.S. $568,000 gain. If Project B
fails there will be a loss of U.S. $270,000. Based on this information, what is the
value of the best alternative?
A. U.S. $7,300
B. U.S. $8,075
C. U.S. $11,650
D. U.S. $15,375
20. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $1,250,500 and B will cost U.S. $1,500,000. There is
a 67% chance that project A will be successful, which will result in a gain of U.S.
$3,000,000. If project A fails there will be a loss of U.S. $2,250,000. There is a 58%
chance B will be successful and if it is successful it will result in a U.S. $3,500,000
gain. If project B fails there will be a loss of U.S. $1,221,428. Based on this
information, which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
21. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $500 and B will cost U.S. $750. There is a 65%
chance that project A will be successful, which will result in a gain of U.S. $2,500. If
project A fails there will be a loss of U.S. $1,650. There is a 59% project B will be
successful, and that will result in a U.S. $3,000 gain. If Project B fails there will be a
loss of U.S. $1,750. Based on this information, what is the value of the best
alternative?
A. U.S. $303
B. U.S. $548
C. U.S. $641
D. U.S. $850
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
22. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $55,250 and B will cost U.S. $68,750. There is a
61% chance that project A will be successful, which will result in a gain of U.S.
$655,000. If project A fails there will be a loss of U.S. $309,500. There is a 65%
chance B will be successful and if it is successful it will result in a U.S. $600,000 gain.
If project B fails there will be a loss of U.S. $230,000. Based on this information,
which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
23. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $194,500 and B will cost U.S. $175,000. There is a
66% chance that project A will be successful, which will result in a gain of U.S.
$645,000. If project A fails there will be a loss of U.S. $315,500. There is a 55%
project B will be successful, and that will result in a U.S. $715,500 gain. If Project B
fails there will be a loss of U.S. $220,500. Based on this information, what is the
value of the best alternative?
A. U.S. $115,960
B. U.S. $119,300
C. U.S. $123,930
D. U.S. $243,230
24. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $296,250 and B will cost U.S. $341,500. There is a
68% chance that project A will be successful, which will result in a gain of U.S.
$715,000. If project A fails there will be a loss of U.S. $305,500. There is a 61%
chance B will be successful and if it is successful it will result in a U.S. $890,000 gain.
If project B fails there will be a loss of U.S. $225,000. Based on this information,
which project do you choose?
A. A
B. B
C. The projects offer the same valuation
D. There is not enough information to determine
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
25. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $255,000 and B will cost U.S. $300,000. There is a
67% chance that project A will be successful, which will result in a gain of U.S.
$650,000. If project A fails there will be a loss of U.S. $310,000. There is a 75%
project B will be successful, and that will result in a U.S. $565,000 gain. If Project B
fails there will be a loss of U.S. $225,000. Based on this information, what is the
value of the best alternative?
A. U.S. $59,900
B. U.S. $67,500
C. U.S. $78,200
D. U.S. $86,300
26. You are asked to choose between two projects A or B based on the highest gain (or
the lowest loss). A will cost U.S. $10,000,000 and B will cost U.S. $7,500,000. There
is a 65% chance that project A will be successful, which will result in a gain of U.S.
$35,000,000. If project A fails there will be a loss of U.S. $26,000,000. There is a
75% project B will be successful, and that will result in a U.S. $27,000,000 gain. If
Project B fails there will be a loss of U.S. $18,000,000. Based on this information,
what is the value of the best alternative?
A. U.S. $11,900,000
B. U.S. $8,250,000
C. U.S. $6,175,000
D. U.S. $3,650,000
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Review Questions – Part 3:
1. Which of the following is not a process found in the risk management knowledge
area?
A. Develop risk management plan
B. Identify risks
C. Perform quantitative risk analysis
D. Plan risk responses
2. Which of the following is a process found in the risk management knowledge
area?
A. Plan risk management
B. Identify risks
C. Plan risk responses
D. All of the above are processes found in the risk management knowledge
area
3. Which of the following is not an input to the plan risk management process?
A. Stakeholder register
B. Activity cost estimates
C. Project charter
D. Enterprise environmental factors
4. Which of the following is an input to the plan risk management process?
A. Quality management plan
B. Project documents
C. Communications management plan
D. Project management plan
5. Which of the following is a tool or technique used in the plan risk management
process?
A. Analytical techniques
B. Information gathering techniques
C. Assumption analysis
D. Documentation review
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
6. Which of the following is an output to the plan risk management process?
A. Risk register
B. Risk management plan
C. Change requests
D. Project document updates
7. Which of the following is not an input to the identify risks process?
A. Risk management plan
B. Activity cost estimates
C. Project scope statement
D. Cost management plan
8. Which of the following is not an input to the identify risks process?
A. Scope baseline
B. Human resource management plan
C. Schedule management plan
D. Risk register
9. Which of the following is not an input to the identify risks process?
A. Work performance information
B. Activity cost estimates
C. Activity duration estimates
D. Procurement documents
10. Which of the following is an input to the identify risks process?
A. Cost management plan
B. SWOT analysis
C. Risk related contracts
D. Technical performance measurements
11. Which of the following is not a tool or technique used in the identify risks
process?
A. Documentation review
B. Risk categorization
C. Information gathering techniques
D. Checklist analysis
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
12. Which of the following is not a tool or technique used in the identify risks
process?
A. Information gathering techniques
B. Checklist analysis
C. Risk urgency analysis
D. SWOT analysis
13. Which of the following is not a tool or technique used in the identify risks
process?
A. SWOT analysis
B. Expert judgment
C. Risk assessment
D. Checklist analysis
14. Which of the following is a tool or technique used in the identify risks process?
A. SWOT analysis
B. Risk assessment
C. Risk urgency assessment
D. Risk categorization
15. Which of the following is an output from the identify risks process?
A. Organizational process assets updates
B. Project management plan updates
C. Risk register
D. Project document updates
16. Which of the following is not an input to the perform qualitative risk analysis
process?
A. Risk register
B. Organizational process assets
C. Risk management plan
D. WBS
17. Which of the following is not an input to the perform qualitative risk analysis
process?
A. Enterprise environmental factors
B. Organizational process assets
C. Project scope statement
D. Risk management plan
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
18. Which of the following is an input to the perform qualitative risk analysis process?
A. Scope baseline
B. Project scope statement
C. Cost management plan
D. Schedule management plan
19. Which of the following is not a tool or technique used in the perform qualitative
risk analysis process?
A. Risk data quality assessment
B. Risk urgency assessment
C. Assumption analysis
D. Probability and impact matrix
20. Which of the following is not a tool or technique used in the perform qualitative
risk analysis process?
A. Project documents
B. Risk categorization
C. Risk urgency assessment
D. Expert judgment
21. Which of the following is a tool or technique used in the perform qualitative risk
analysis process?
A. Risk response analysis
B. SWOT analysis
C. Empirical data analysis
D. Risk categorization
22. Which of the following is an output from the perform qualitative risk analysis
process?
A. Project document update
B. Organizational process asset updates
C. Project document updates
D. Project management plan updates
23. Which of the following is not an input to the perform quantitative risk analysis
process?
A. Risk management plan
B. Cost management plan
C. Quality management plan
D. Schedule management plan
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
24. Which of the following is not an input to the perform quantitative risk analysis
process?
A. Scope baseline
B. Enterprise environmental factors
C. Schedule management plan
D. Risk register
25. Which of the following is an input to the perform quantitative risk analysis
process?
A. Human resource management plan
B. Scope management plan
C. Quality management plan
D. Organizational process assets
26. Which of the following is not a tool or technique used in the perform quantitative
risk analysis process?
A. SWOT analysis
B. Data gathering and representation techniques
C. Quantitative risk analysis and modeling techniques
D. Expert judgment
27. Which of the following is a tool or technique used in the perform quantitative risk
analysis process?
A. Data gathering and representation techniques
B. Empirical data analysis
C. Qualitative risk analysis and modeling techniques
D. All of the above are tools and techniques used in the perform quantitative
risk analysis
28. Which of the following is an output to the perform quantitative risk analysis
process?
A. Project document updates
B. Risk register updates
C. Project management plan updates
D. Risk management plan updates
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
29. Which of the following is not an input to the plan risk responses process?
A. Schedule management plan
B. Risk register
C. Risk management plan
D. All of the above are inputs to the plan risk responses process
30. Which of the following is not an input to the plan risk responses process?
A. Risk management plan
B. Cost management plan
C. Risk register
D. All of the above are inputs to the plan risk responses process
31. Which of the following is an input to the plan risk responses process?
A. Risk strategies
B. Risk response plan
C. Risk register
D. Project management plan
32. Which of the following is a tool or technique used in the plan risk response
process?
A. Risk response analysis
B. Risk response planning
C. Contingent response strategies
D. Strategic risk response planning
33. Which of the following is not a tool or technique used in the plan risk response
process?
A. Strategies for negative risks or threats
B. Strategies for positive risks or opportunities
C. Expert judgment
D. Contingency reserve analysis
34. Which of the following is an output to the plan risk responses process?
A. Risk management plan updates
B. Project document updates
C. Risk register updates
D. Risk-related contract decisions
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
35. Which of the following is an input to the control risks process?
A. Organizational process assets updates
B. Change requests
C. Risk register
D. Project document updates
36. Which of the following is not an input to the control risks process?
A. Risk register
B. Project management plan
C. Enterprise environmental factors
D. Work performance data
37. Which of the following is an input to the control risk process?
A. Organizational process assets
B. Approved change requests
C. Project management plan
D. Project documents
38. Which of the following is not a tool or technique used in the control risks
process?
A. Risk reassessments
B. Variance and trend analysis
C. Reserve analysis
D. Change request analysis
39. Which of the following is not a tool or technique used in the control risks
process?
A. Risk urgency assessment
B. Risk audits
C. Meetings
D. Technical performance measurement
40. Which of the following is a tool or technique used in the control risks process?
A. Risk urgency assessments
B. Meetings
C. Expert judgment
D. SWOT analysis
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
41. Which of the following is a tool or technique used in the control risks process?
A. Diagramming techniques
B. Checklist analysis
C. Technical performance measurement
D. Assumption analysis
42. Which of the following is a tool or technique used in the control risks process?
A. Data gathering and representation techniques
B. Variance and trend analysis
C. Risk data quality assessment
D. Planning meetings and analysis
43. Which of the following is not an output of the control risks process?
A. Work performance information
B. Change requests
C. Risk management plan updates
D. Project document updates
44. Which of the following is not an output of the control risks process?
A. Organizational process asset updates
B. Project management plan updates
C. Project document updates
D. Risk probability and impact assessment updates
45. Which of the following is an output from the control risk category?
A. Project document updates
B. Risk probability and impact assessment updates
C. Risk management plan updates
D. Communications management plan updates
46. In which of the following processes do the project manager and project team
identify project risks?
A. Plan risk management and identify risks
B. Identify, monitor and control risks
C. Identify risks
D. Identify risks and perform qualitative risk analysis
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
47. You are acting as the portfolio manager and must select a project to execute
from a pool of three choices. Each of the choices has an expected payout of
$20,000 and an equal 75% chance of succeeding. In this situation what does
$15,000 represent?
A. Net present value
B. Risk value
C. Expected monetary value
D. It cannot be determined with the provided information
48. You are leading a large complex project within your organization that is forecast
to continue for ten more months. The project has an 18% chance of being
impacted in a given month by a particular risk. What is the probability that the
project will be impacted by the risk in the 3rd month?
A. 18%
B. 36%
C. 54%
D. 72%
49. You have been asked to select one of four projects for your organization to
execute. The organization is very risk adverse. If you assume the ends of a
range of estimates are +/- 3 sigma from the mean, which of the following range
estimates involves the least risk?
A. Mean of 33 days
B. 40 days plus or minus 8 days
C. 32 - 46 days
D. Optimistic = 33 days, most likely 40 days, pessimistic 46 days
50. You have been asked to select one of four projects for your organization to
execute. The organization is very risk adverse. If you assume the ends of a
range of estimates are +/- 3 sigma from the mean, which of the following range
estimates involves the least risk?
A. Optimistic = 21 days, most likely 27 days, pessimistic = 32 days
B. 26 days plus or minus 5 days
C. 20 - 33 days
D. Mean of 26 days
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
51. Which of the following is not a factor in the assessment of project risk?
A. Transference costs
B. Risk probability
C. Value at stake
D. Risk event
52. You take over a project from a previous project manager. As part of the turn over
process they hand you a risk watchlist. What should be done with the risks on
the watchlist?
A. Add the information to your takeover report
B. Add them to the lessons learned for future projects
C. Read over the watchlist as they are already covered in the properly
completed contingency plans
D. Read over the watch list then revisit during monitoring and controlling
53. Which of the following is not always an input to the risk management process?
A. Work breakdown structure
B. Lessons learned
C. Project status reports
D. Historical information
54. Which of the following is not a common result of risk management?
A. The communications management plan is changed
B. The project charter is changed
C. The schedule management plan is changed
D. The project management plan is changed
55. Which of the following risk strategies is represented by insurance?
A. Avoidance
B. Acceptance
C. Transfer
D. Mitigation
56. You have just determined that you need to transfer a risk. In which of the
following risk management processes are you?
A. Identify risks
B. Plan risk responses
C. Monitor and control risks
D. Perform quantitative risk analysis
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
57. You are acting as the project manager for a large project U.S. $1,500,000 within
your organization. You have just finished the risk response plan for your project.
Which of the following should you probably do next?
A. Begin a project risk reassessment
B. Begin to analyze the risks that appear in major project documents
C. Complete the work breakdown structure
D. Determine the overall risk rating for the project
58. You are in the process of quantifying risks on a project you are leading. Several
of your key resources are non-collocated, but have needed input. How can this
be done?
A. Make use of the Delphi Technique
B. Make use of Monte Carlo Analysis
C. Make use collaboration software
D. Apply Critical Chain Modeling
59. You are the project manager on a large IT project. You have assembled your
team, identified the major risks on the project, determined what would trigger
those risks, rated the risks on a rating matrix, tested the major risk assumptions,
and assessed the quality of the data used. The team is continuing to move
through the risk management process. What have you forgotten to do?
A. Involve other stakeholders
B. Use a Monte Carlo simulation
C. Mitigate the risks
D. The overall risk ranking for the project
60. You have worked with different stakeholders to determine the probability and
impact of a project's risks. You have also analyzed the assumptions. Before you
move on to the next step in the risk management process, what do you need to
do?
A. Identify and evaluate triggers
B. Develop your risk rating matrix
C. Evaluate the trends in risk analysis
D. Create a contingency plan
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
61. You apply for a job with a large consulting company. As part of the interview
process you are provided with a sample project charter and asked to provide an
analysis of the project risks. Which of the following would best help you
complete the exercise?
A. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
- Fifth Edition, Project Management Institute, Inc., 2013
B. A discussion with several team members within the organization from a
similar project that failed in the past
C. The scope statement from the project planning process
D. The resource plan from the project planning process
62. You are working as a project manager on a large new product development
project. While preparing your risk responses your team identifies additional risks.
What should you do?
A. Get management to allocate another 5% to the project budget to cover the
risks
B. Determine the risk events and the associated cost, then add the cost to
the project budget as a reserve
C. Document the risks, and calculate the expected monetary value based on
the PI score that result from the risk occurrence
D. Add reserves to the project to accommodate the new risks and notify
management
63. You are leading a project that has an SPI of 0.69 and a CPI of .71. The project
has more than 1,000 work packages, and it is being completed over three years.
The team has not worked together before, and the project has not been well
supported. Which of the following is the best thing to do?
A. Update the risk register with any new risks and analysis
B. Examine the WBS for unnecessary work packages
C. Examine the RAM for necessary changes
D. Examine the budget for necessary changes
64. You are the project manager on a multiyear facilities development project.
Significant spring rains caused major flooding that caused power outages and
the loss of all project records not stored on your laptop. What should have been
done to prevent this problem?
A. Approve a larger contingency reserve
B. Plan for a larger management reserve
C. Maintain the records outside a flood plain
D. Monitor the weather and have a contingency plan
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
65. You are leading a high technology product development project that was
originally scheduled to take 18 months. The project has faced significant
problems and has had to use all its reserves. You currently have an SPI of 0.68
and a CPI of 0.73. There are only six deliverables left and three of them are on
the critical path. The project sponsor has just told you that you only have four
weeks to finish the project or risk losing all funding and support. This is three
weeks faster than your current ETC. In response, you send out a RFP to four
vendors for some of the work that the internal team was going to perform hoping
an external organization could get the work done faster. This can best be
described as an effort on the part of the project manager to work with:
A. Contingencies
B. Threats
C. Opportunities
D. Reserves
66. Which of the following is a primary characteristic of the Delphi Technique?
A. Expert opinion
B. Simulation modeling in a hierarchical process
C. Use of heuristic analysis
D. Extrapolation from historical documents
67. You are leading a large IT project that is nearing completion. Your sponsor
requests a change to the project that would increase the project risk. What
should you do first?
A. Update the risk register
B. Gain an understanding of why the sponsor wants the change
C. Analyze the impacts of making the change with the project team
D. Calculated the EMV of the risk and create a new cost estimate
68. You are leading a major construction project. During project executing a major
problem occurs that does not appear in the risk register. What should you do
first?
A. Inform the project stakeholders
B. Look for secondary risks
C. Exam the identify risks process for flaws
D. Create a workaround
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
69. You are leading a research and development project. You are in the executing
process group when one of your senior resources identifies a risk that is not
listed in the risk register. What should you do?
A. Determine how the team member identified the risk
B. Analyze the risk
C. Inform the sponsor and key stakeholders of the risk
D. Place the risk in the risk register
70. You are taking over a U.S. $50,000 IT project for your organization. The project
is entering its third phase. Although there appear to be many risks on the
project, no one has evaluated them to assess the range of possible impacts.
What needs to be done?
A. Perform qualitative risk analysis
B. Plan risk management
C. Plan risk responses
D. Monitor and control risks
71. Which of the following best describes a heuristic?
A. An advanced statistical calculation used to model risks
B. A simulation used to model risks
C. A rule of thumb
D. A calculation used to produce a weighted measure of risk
72. From which of the following processes would you expect to generate a watchlist?
A. Plan risk management
B. Identify risks
C. Perform qualitative risk analysis
D. Plan risk responses
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Answer Key – Part 1:
1. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
2. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
3. C
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
4. D
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
5. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
6. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
7. C
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
8. D
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
9. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
10. C
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
11. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
12. D
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
13. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
14. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
15. C
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
16. D
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
17. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
18. C
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
19. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
20. D
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
21. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
22. D
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
23. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
24. A
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
25. C
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
26. B
To get the correct answer you must first realize you are dealing with three
mutually exclusive options. You cannot simultaneously have the best and worst
case scenarios. Therefore, your probabilities must sum to 100%. Use the
calculation probability * result for each case and then add the results together to
get the EMV.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Answer Key – Part 2:
1. A
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
2. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
3. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
4. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
5. D
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
6. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
7. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
8. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
9. A
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
10. D
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
11. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
12. A
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
13. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
14. D
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
15. D
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
16. A
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
17. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
18. A
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
19. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
20. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
21. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
22. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
23. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
24. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
25. C
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
26. B
To answer this question you must calculate the expected monetary value of each
choice using the decision tree model found in your LGd training guide and then
compare the options. Whichever option has the greatest value is the one you
should choose.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
Answer Key – Part 3:
1. A
PMBOK® Guide - The processes found in the risk management knowledge area
include:
- Plan risk management
- Identify risks
- Perform qualitative risk analysis
- Perform quantitative risk analysis
- Plan risk responses
- Control risks
2. D
PMBOK® Guide - The processes found in the risk management knowledge area
include:
- Plan risk management
- Identify risks
- Perform qualitative risk analysis
- Perform quantitative risk analysis
- Plan risk responses
- Control risks
3. B
PMBOK® Guide - The inputs to the plan risk management process include:
- Project management plan
- Project charter
- Stakeholder register
- Enterprise environmental factors
- Organizational process assets
4. D
PMBOK® Guide - The inputs to the plan risk management process include:
- Project management plan
- Project charter
- Stakeholder register
- Enterprise environmental factors
- Organizational process assets
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
5. A
PMBOK® Guide - The tools and techniques used in the plan risk management
process are:
- Analytical techniques
- Expert judgment
- Meetings
6. B
PMBOK® Guide - The only output from the plan risk management process is the
risk management plan.
7. C
PMBOK® Guide - The inputs to the identify risks process includes:
- Risk management plan
- Cost management plan
- Schedule management plan
- Quality management plan
- Human resource management plan
- Scope baseline
- Activity cost estimates
- Activity duration estimates
- Stakeholder register
- Project documents
- Procurement documents
- Enterprise environmental factors
- Organizational process assets
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
8. D
PMBOK® Guide - The inputs to the identify risks process includes:
- Risk management plan
- Cost management plan
- Schedule management plan
- Quality management plan
- Human resource management plan
- Scope baseline
- Activity cost estimates
- Activity duration estimates
- Stakeholder register
- Project documents
- Procurement documents
- Enterprise environmental factors
- Organizational process assets
9. A
PMBOK® Guide - The inputs to the identify risks process includes:
- Risk management plan
- Cost management plan
- Schedule management plan
- Quality management plan
- Human resource management plan
- Scope baseline
- Activity cost estimates
- Activity duration estimates
- Stakeholder register
- Project documents
- Procurement documents
- Enterprise environmental factors
- Organizational process assets
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
10. A
PMBOK® Guide - The inputs to the identify risks process includes:
- Risk management plan
- Cost management plan
- Schedule management plan
- Quality management plan
- Human resource management plan
- Scope baseline
- Activity cost estimates
- Activity duration estimates
- Stakeholder register
- Project documents
- Procurement documents
- Enterprise environmental factors
- Organizational process assets
11. B
PMBOK® Guide - The tools and techniques of the identify risks process include:
- Documentation review
- Information gathering techniques
- Checklist analysis
- Assumption analysis
- Diagramming techniques
- SWOT analysis
- Expert judgment
12. C
PMBOK® Guide - The tools and techniques of the identify risks process include:
- Documentation review
- Information gathering techniques
- Checklist analysis
- Assumption analysis
- Diagramming techniques
- SWOT analysis
- Expert judgment
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
13. C
PMBOK® Guide - The tools and techniques of the identify risks process include:
- Documentation review
- Information gathering techniques
- Checklist analysis
- Assumption analysis
- Diagramming techniques
- SWOT analysis
- Expert judgment
14. A
PMBOK® Guide - The tools and techniques of the identify risks process include:
- Documentation review
- Information gathering techniques
- Checklist analysis
- Assumption analysis
- Diagramming techniques
- SWOT analysis
- Expert judgment
15. C
PMBOK® Guide - The output from the identify risks process is the risk register.
16. D
PMBOK® Guide - The inputs to the perform qualitative risk analysis process
include:
- Risk management plan
- Scope baseline
- Risk register
- Enterprise environmental factors
- Organizational process assets
17. C
PMBOK® Guide - The inputs to the perform qualitative risk analysis process
include:
- Risk management plan
- Scope baseline
- Risk register
- Enterprise environmental factors
- Organizational process assets
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
18. A
PMBOK® Guide - The inputs to the perform qualitative risk analysis process
include:
- Risk management plan
- Scope baseline
- Risk register
- Enterprise environmental factors
- Organizational process assets
19. C
PMBOK® Guide - The tools and techniques used in the perform qualitative risk
analysis include:
- Risk probability and impact assessment
- Probability and impact matrix
- Risk data quality assessment
- Risk categorization
- Risk urgency assessment
- Expert judgment
20. A
PMBOK® Guide - The tools and techniques used in the perform qualitative risk
analysis include:
- Risk probability and impact assessment
- Probability and impact matrix
- Risk data quality assessment
- Risk categorization
- Risk urgency assessment
- Expert judgment
21. D
PMBOK® Guide - The tools and techniques used in the perform qualitative risk
analysis include:
- Risk probability and impact assessment
- Probability and impact matrix
- Risk data quality assessment
- Risk categorization
- Risk urgency assessment
- Expert judgment
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
22. C
PMBOK® Guide- The output from the perform qualitative risk analysis process
are project document updates.
23. C
PMBOK® Guide - The inputs to the perform quantitative risk analysis process
include:
- Risk management plan
- Cost management plan
- Schedule management plan
- Risk register
- Enterprise environmental factors
- Organizational process assets
24. A
PMBOK® - The inputs to the perform quantitative risk analysis process include:
- Risk management plan
- Cost management plan
- Schedule management plan
- Risk register
- Enterprise environmental factors
- Organizational process assets
25. D
PMBOK® Guide - The inputs to the perform quantitative risk analysis process
include:
- Risk management plan
- Cost management plan
- Schedule management plan
- Risk register
- Enterprise environmental factors
- Organizational process assets
26. A
PMBOK® Guide - The tools and techniques used in the perform quantitative risk
analysis process include:
- Data gathering and representation techniques
- Quantitative risk analysis and modeling techniques
- Expert judgment
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
27. A
PMBOK® Guide - The tools and techniques used in the perform quantitative risk
analysis process include:
- Data gathering and representation techniques
- Quantitative risk analysis and modeling techniques
- Expert judgment
28. A
PMBOK® Guide - The output to the perform quantitative risk analysis process are
project document updates.
29. A
PMBOK® Guide - The inputs to the plan risk responses process include:
- Risk management plan
- Risk register
30. B
PMBOK® Guide - The inputs to the plan risk responses process include:
- Risk management plan
- Risk register
31. C
PMBOK® Guide - The inputs to the plan risk responses process include:
- Risk management plan
- Risk register
32. C
PMBOK® Guide - The tools and techniques used in the plan risk response
process include:
- Strategies for negative risks or threats
- Strategies for positive risks or opportunities
- Contingent response strategies
- Expert judgment
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
33. D
PMBOK® Guide - The tools and techniques used in the plan risk response
process include:
- Strategies for negative risks or threats
- Strategies for positive risks or opportunities
- Contingent response strategies
- Expert judgment
34. B
PMBOK® Guide - The outputs to the plan risk responses process include:
- Project management plan updates
- Project document updates
35. C
PMBOK® Guide - The inputs to the control risks process include:
- Project Management Plan
- Risk Register
- Work performance data
- Work performance reports
36. C
PMBOK® Guide - The inputs to the control risks process include:
- Project Management Plan
- Risk Register
- Work performance data
- Work performance reports
37. C
PMBOK® Guide - The inputs to the control risks process include:
- Project Management Plan
- Risk Register
- Work performance data
- Work performance reports
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
38. D
PMBOK® Guide - The tools and techniques used in the control risks include:
- Risk reassessment
- Risk audits
- Variance and trend analysis
- Technical performance measurement
- Reserve analysis
- Meetings
39. A
PMBOK® Guide - The tools and techniques used in the control risks include:
- Risk reassessment
- Risk audits
- Variance and trend analysis
- Technical performance measurement
- Reserve analysis
- Meetings
40. B
PMBOK® Guide - The tools and techniques used in the control risks include:
- Risk reassessment
- Risk audits
- Variance and trend analysis
- Technical performance measurement
- Reserve analysis
- Meetings
41. C
PMBOK® Guide - The tools and techniques used in the control risks include:
- Risk reassessment
- Risk audits
- Variance and trend analysis
- Technical performance measurement
- Reserve analysis
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
42. B
PMBOK® Guide- The tools and techniques used in the control risks include:
- Risk reassessment
- Risk audits
- Variance and trend analysis
- Technical performance measurement
- Reserve analysis
- Meetings
43. C
PMBOK® Guide - The outputs to the control risks process include:
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- Organizational process assets updates
44. D
PMBOK® Guide - The outputs to the control risks process include:
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- Organizational process assets updates
45. A
PMBOK® Guide - The outputs to the monitor and control risks process include:
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- Organizational process assets updates
46. C
PMBOK® Guide - Identify risks is the process where risks are identified.
Hopefully, this was an easy one.
47. C
The expected monetary value is calculated by multiplying the probability times the
impact of any event.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
48. A
Many people miss this question. Remember, each month in the scenario is
independent. So if the probability is 18% in one month and the probability is
equal it is 18% in all months.
49. D
This question is actually much easier than it first appears. Because we are
assuming a range of estimates that is +/- 3 sigma, meaning it is a normal
distribution all you have to do is determine which range estimate has the smallest
difference or variance. The 3 point estimate has a range of 13, the 32-46 days is
a range of 14, and 40 +/- 8 days is 16.
50. B
This question is actually much easier than it first appears. Because we are
assuming a range of estimates that is +/- 3 sigma, meaning it is a normal
distribution all you have to do is determine which range estimate has the smallest
difference or variance. The 3 point estimate has a range of 11 days. The plus or
minus 5 days is a range of 10 and 20-33 days is 13.
51. A
"Transference costs" is a fancy way of saying insurance premiums. These do
not come into play until you are evaluating the risk responses.
52. D
A good project manager is constantly monitoring the identified risks on a project.
53. C
Although project status reports can be a vital input to the risk management
process, they are usually not available during the risk planning process and are
therefore not always an input to the risk management process.
54. B
Of the choices the project charter is the least likely to be changed because of the
risk management process. Remember, the charter authorizes the project.
55. C
Insurance is the most common type of risk transfer. It is making the risk someone
else's problem.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
56. B
Be careful here. The question states you have just determined that you NEED to
transfer a risk. This is done in the plan risk response process.
57. C
Finishing the risk response plan is done in the planning process group. The only
of the options that is also in the planning process group is the completion of the
work breakdown structure.
58. A
The Delphi Technique is specifically designed to survey your experts, aggregate
their responses and then feed the aggregated result back to them for
confirmation. This is the best option in a situation where the resources are not all
together.
59. A
There is nothing wrong with this process. It simply needs to be continued. Then
best answer in this case is to involve other stakeholders.
60. B
Before you can move on to the next step in the process you need a definition for
how you will be rating the risks.
61. B
This question is all about imagining where you are in the project. The question
gives you a charter and nothing else. Therefore, you must assume you are in the
initiating process. Two of the other choices say they are from the planning
process and therefore not available. The PMBOK® Guide is a nice framework,
bur remember Project Management Institute (PMI)® suggests the situation is
critical.
62. C
Before you can determine the appropriate response you have to determine the
value or cost of the risk as well as the impacts. Only then can you determine if
you or management needs to add reserves or another response is needed.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
63. A
To answer this question correctly you had to notice the project is already
significantly over budget and behind schedule. Changing the WBS, RAM or
budget should only happen in response to risks that occur. So you should start
there.
64. D
With the information provided you do not know what the best solution would have
been. The only thing you can say for sure is that you should have had a
contingency plan, oh and watching the weather probably wasn't a bad idea
either.
65. C
This is a bad situation, but that does not impact the answer. Only the last three
sentences matter. You are trying to gain an opportunity to do the project more
quickly.
66. A
The Delphi Technique is a process where you survey your subject matter expert,
aggregate their responses, and then feedback the aggregation for confirmation.
67. C
According to PMI®, the first thing you must do in any situation is understand the
impacts. Only then can you devise the correct response.
68. D
This is a risk that has already happened. The first thing you need to do is deal
with the problem and then take the workaround to the sponsor and key
stakeholders.
69. B
The first thing you always do is analyze the risk. Only then can you determine
what should be done next.
70. B
The project has started, and it should complete the risk management process.
That process begins by planning risk management. Since that step has not
already occurred it needs to be completed first.
PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
71. C
A heuristic is simply a rule of thumb. There is no calculating involved.
72. C
A watchlist is made up of low priority risks that, in the perform qualitative risk
analysis process, were determined to be too low priority or low impact to move
further in the risk process.