Page 1: Project formulation and management

PROJECT FORMULATION AND

MANAGEMENT

Hari Prasad KafleMPH, SHUATS (India)

Lecturer (Public Health)Pokhara University

Page 2: Project formulation and management

Project

• A Project is a group of milestones or phases, activities or tasks that support an effort to accomplish something.

• A project is a temporary endeavor (attempt) undertaken to produce a unique product or service or result.

Page 3: Project formulation and management

Project

• A collection of linked activities, carried out in

an organized manner, with a clearly defined

start point and end point to achieve some

specific results desired to satisfy the needs of

the organization at the current time.

Page 4: Project formulation and management

Project

• Small segment of business with clearly defined objective, resources and time.

• A Projects has been terminated when objectives are achieved.

• Projects can be large or small and take a short (usually) or long time (but certain) to complete.

Page 5: Project formulation and management

Characteristics

• A project has a unique purpose.

• Temporary: terminated after certain time

• Is developed using progressive elaboration: Specifications of the project are initially broad and then refined and more detailed as the project progresses.

Page 6: Project formulation and management

Characteristics• Requires resources, often from various areas

• Should have a primary customer or sponsor: The project sponsor usually provides the direction and funding for the project.

• Involves uncertainty: Unclear objectives, difficult to estimate time to complete and cost, dependence on external factors

Page 7: Project formulation and management

Program Vs Project

• A program is a group of related projects managed in a coordinated way.

• Project portfolio management involves organizing and managing projects.

• Program managers play a key role in helping all projects and organizations succeed.

Page 8: Project formulation and management

What is not a project?

• Past activities that are repeated in exactly the same way on the periodic basis.

• Activities with no clearly defined goals.

• Activities which can be repeated or translated any where at any moment.

• Ongoing (regular) organizational activities (e.g. board meeting)

Page 9: Project formulation and management

Project Management

• A dynamic process that utilizes the appropriate resources of the organization in a controlled and structured manner, to achieve some clearly defined objectives identified as needs.

• It is always conducted within a defined set of constraints.

Page 10: Project formulation and management

Project Management

• Project Management is the application of skills, knowledge, tools and techniques to meet the needs and expectations of stakeholders for a project.

Page 11: Project formulation and management

Project Management

• Project management is the discipline of organizing and managing resources in such a way that the project is completed within defined scope, quality, time and cost. It should be unique and Temporary.

• Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements”

Page 12: Project formulation and management

Triple constraints of project management

Quality

Time

CostScope

Page 13: Project formulation and management

Triple constraint of project management

• Project managers strive to meet the triple constraint by balancing project scope, time, and cost goals

• However, quality is the quadruple constraint.

Page 14: Project formulation and management

Importance of project management

• Enables us to map out a course of action or work plan

• Helps us to think systematically and thoroughly and logically.

• Unique Task

• Specific Objective

• Variety of Resources

• Time bound

Page 15: Project formulation and management

Importance of project management

• Activity based costing• Easy and early identification of Bottlenecks• Identification and addition of missing and new

activities• Preempting unnecessary activity/expenditure

• Assigning tasks

• Reporting

Page 16: Project formulation and management

Importance of project management

• Better control of financial, physical, and human resources

• Improved customer relations• Better internal coordination• Higher worker morale (less stress)• Satisfaction to stakeholders

Page 17: Project formulation and management

Project Management Framework

Page 18: Project formulation and management

Project Management Framework

1. Scope management2. Time Management3. Cost management4. Quality management5. HR Management6. Communication Management 7. Risk Management8. Procurement Management

Page 19: Project formulation and management

Winners do not do different things, they just do same thing differently.

Work smart not hard to be a

successful project manager !!!

Page 20: Project formulation and management

PROJECT LIFE CYCLE

Page 21: Project formulation and management

Project life cycle

1. Project Idea

2. Situation Analysis 6. Evaluation

3. Planning 5. Implementation

4. Financing

Page 22: Project formulation and management

Project life cycle

Page 23: Project formulation and management

Initiation phase

• Also known as project idea phase.

• The emergence of a project idea is the first stage of the project cycle.

• A project idea may emerge as a result of a need, observation, consultation or inspiration.

Page 24: Project formulation and management

Definition phase

• Situation analysis is done to find out problems, their strengths, potential resources and opportunity to work an area.

• Project goals, scope and project constraints are determined also project members and their roles are identified.

Page 25: Project formulation and management

Planning phase

Planning Systematically and rationally.

Project documentation and proposal writing.

Resource Planning and Work Breakdown.

Project Schedule Development.

Development of Quality Assurance Plan.

Page 26: Project formulation and management

Implementation phaseExecute project plan to accomplish project goals.

Train human resources

System Build.

Staff hiring.

Page 27: Project formulation and management

Deployment phase

※Also known as adoption, use or consumption phase.

※User Training

※Production Review

※ Maintain service quality.

Page 28: Project formulation and management

Closing phase Also called as evaluation phase

Evaluation of the outcomes and impacts.

Contractual Closeout.

Lessons Learned.

Page 29: Project formulation and management

29

Project cycle based on activity

Page 30: Project formulation and management

Now project is completed successfully, Let’s celebrate !

Page 31: Project formulation and management

PROJECT PROPOSAL WRITING

Page 32: Project formulation and management

PROJECT PROPOSAL

A project proposal is a detailed description of a series of activities aimed at solving a certain problem.

Page 33: Project formulation and management

PROJECT PROPOSAL

• The proposal should contain a detailed explanation of the: Justification of the project (objectives); Activities and implementation timeline; Methodology; and Human, material and financial resources

required.

Page 34: Project formulation and management

ELEMENTS OF A PROJECT PROPOSAL

1. Cover Sheet

2. Project Summary/ abstract

3. Introduction

4. Problem statement

5. Overview of Target Area (4 &5)

6. Project Detail: Goal, Objectives, Strategies and Activities

Page 35: Project formulation and management

ELEMENTS OF A PROJECT PROPOSAL

6. Project Implementation Plan

7. Project Administration

8. Project Budget

9. References

10. Annexes

Page 36: Project formulation and management

1. COVER SHEET

• Also known as title page/cover page.

• Should be clear but not “cute”.

• Do not waste time using fancy report covers and making expensive binding.

Page 37: Project formulation and management

COVER SHEET

• Title page Should contain: Proposed Project title, Organization that proposed the project, Name of the donor agency, Date of proposal preparation and submission, Signatures of key people.

Contd..

Page 38: Project formulation and management

2. PROJECT TITLE

• Title should be clear.

• Should reflect as a mini-abstract of project.

• A good title should provide quick picture of the key ideas of project.

• For example: – HIV/AIDS Prevention Project among

Clients of Female Sex Workers in Pokhara Valley.

Page 39: Project formulation and management

PROJECT TITLE

• Western highway project in HIV/AIDS for transport worker and their partners.

• Increasing access to care and treatment in HIV/AIDS among Migrant in Kaski.

• Prevention of HIV/AIDS among injecting drug users in Kaski.

Contd..

Page 40: Project formulation and management

3. SUMMARY/ ABSTRACT

• Many readers lack the time needed to read the whole project proposal.

• Therefore useful to insert a short project summary: an abstract.

• For a small project the abstract may not be longer than 10 lines.

• For Bigger projects often provide abstracts as long as two pages.

Page 41: Project formulation and management

SUMMARY/ ABSTRACT

• Briefly summarize why this project is necessary?

• What is the problem and how does this project contribute to the solution?.

• Briefly state the organization’s experience in implementing such a project.

• Abstract/summary should be prepared at the end of the proposal documentation.

Contd..

Page 42: Project formulation and management

SUMMARY/ ABSTRACT

•The abstract should include: Problem statement; Project’s objectives; Implementing organizations; Key project activities; and Total project budget.

Contd..

Page 43: Project formulation and management

4. CONTENTS PAGE

• If the total project proposal is longer than 10 pages it is helpful to include a table of contents.

• The contents page enables readers to quickly find relevant parts of the document.

• It should contain the title and beginning page number of each section of the proposal.

Page 44: Project formulation and management

5. INTRODUCTION

• Also called background information.

• Introduces the project subject matter very briefly.

• Issue to be covered and how solving the issue.

• It introduces the organization briefly – its Vision, Mission and propose of organization.

• Maximum 2 pages.

Page 45: Project formulation and management

6. PROBLEM STATEMENT

• The problem statement provides a description of the specific problem the project is trying to solve.

• The project proposal should point out why a certain issue is a problem for the community.

• There should also be an explanation of the needs of the target group that appear as a direct consequence of the described problem.

Page 46: Project formulation and management

7.OVERVIEW OF TARGET AREA

• Generally not more than 1-2 pages.

• Based on the situation analysis.

• Briefly describe the location and population group of the proposed program.

• Discuss the primary characteristics of the target area in detail (i.e. morbidity & mortality rates, ethnicity, literacy, etc.)

• Discuss how this area was chosen over others.

Page 47: Project formulation and management

7. PROJECT DETAIL

• Include Project Goals, Objectives, strategy, Interventions and Critical Activities

• Describe in about 1- 2 page.

• Link the project’s goal, objectives, and interventions to the assessment findings or situational analysis

Page 48: Project formulation and management

PROJECT DETAILContd..

Page 49: Project formulation and management

HIERARCHY OF AIMS

• Goal (Impact): the ultimate end of the program to which the specific project will contribute (to improve Adolescent Reproductive Health of City A)

• Objectives/Purpose (Outcome/Effect): what the project is expected to achieve once it is completed within the allocated time (Reduction of teenage pregnancy by 20% in 3 years)

Contd..

Page 50: Project formulation and management

HIERARCHY OF AIMS

• Outputs: products or deliverables of activities (trained peer counselors; clinical services provided)

• Activities (Inputs; Process): actions to be undertaken and the resources available to produce the outputs (upgrading of clinics)

Contd..

Page 51: Project formulation and management

Goal

Project Activity

2

Project Objective 1 Project Objective 3

Project Objective 2

Project Activity

3Project Activity 1

Result 1.1Result 1.2

Result 2.1Result 2.2

Result 3.1Result 3.1

Contd..

Page 52: Project formulation and management

Goal: Improving the health status of community

Project Activity 2 • Construction of

latrines in BB households

• Establishment BB clinics

• Health education to BB members of community

Project Objective 1Improving the water Supply from X to Y

Project Objective ............................…………………

Project Objective 2Reducing the diarrhoeal disease from A to B

Project

Activity

……….………..……….…………

Project Activity 1•Construction of YY water supply source

•Distribution of water supply to YY households

Contd..

Page 53: Project formulation and management

8. IMPLEMENTATION PLAN

• How Project will be implemented and what will be the time line for major critical activities and who will be responsible for each activities?

• For example: Tentative Plan of Actions, Work schedule, Program model, Gantt chart etc.

Page 54: Project formulation and management

Gantt Chart

Activities to be under

taken

Responsible

person

Timeline to accomplish the determined

Activities 2010

Month 1

Jan

Month 2

Feb

Month 3

Mar

Month 4

Apr

Staff selection

PM XXXXXX

XXXXXX

Staff training

TO XXXXXX

XXXXXX

Clinic established

PM XXXXXX

XXXXXX

Service started

MO XXXXXX

XXXXXX

Contd..

Page 55: Project formulation and management

9. PROJECT ADMINISTRATION

• Key persons associated with the project/ staffing pattern.

• Role and responsibility of the each person and their importance for the project.

• Name, title, experience, and qualifications of each person.

Page 56: Project formulation and management

PROJECT ADMINISTRATION

• If new staffs are needed for project how they will be selected/hired?

• If using a Steering Committee (Advisory Committee, Governing Board, etc.) to assist the project, how it will be organized?

Contd..

Page 57: Project formulation and management

10. PROJECT BUDGET

• Total budget for the entire project period.

• Contribution from internal and external resources.

• Detailed budget by each and every activities and cost types.

• Potential funders and sources of income.

• State currency and exchange rate on which your budget is based.

Page 58: Project formulation and management

PROJECT BUDGET

Particulars Year 1 Year 2 Year 3

Personnel

Person #1

Person #2

Subtotal

Equipment

Equip. # X

Equip # Y

Sub total

Contd..

Page 59: Project formulation and management

PROJECT BUDGET

Particulars Year 1 Year 2 Year 3

Supply

Supply #1

Supply #2

Subtotal

Communication

Telephone

Internet

Sub total

Contd..

Page 60: Project formulation and management

PROJECT BUDGET

Particulars Year 1 Year 2 Year 3

Travel

Fuel

Vehicle rent

Subtotal

Year 1 Year 2 Year 3

Total

Sum total

Contd..

Page 61: Project formulation and management

11. MONITORING AND EVALUATION PLAN

• How project will be monitored and evaluated to ensure that the project is on track and that the results are being achieved.

• Approximately in ½ to 1 page.

• Establish the performance indicators.

• Describe how and when the baseline, mid-term and final evaluations will be carried out.

Page 62: Project formulation and management

MONITORING & EVALUATION PLAN

• Describe information collection systems

• Briefly describe information analysis, interpretation, publication and dissemination plan.

• Briefly describe the qualifications of the personnel implementing the evaluation plan.

Contd..

Page 63: Project formulation and management

S.N.

Activity Key indicator Base

line

Target Means of verification

Frequency

of Data Collection

Important

Assumption

1 ANC service

1st ANC Coverage

4th ANC Coverage

IFA coverage

TT2 coverage

40 %

25%

41%

55%

80%

50%

90%

95%

Clinic report

Monthly

and Quarterly

Community support

Coordination with SHP/HP

2 INC

service

Institutional delivery

Skill birth Attendance

16%

31%

70%

85%

Clinic report

Monthly

and Quarterly

‘’

3 PNC

service

PNC coverage

Postnatal Vit. A coverage

19%

NA

50%

100%

Clinic report

Monthly

and Quarterly

‘’

4 New Born Care

Birth weight

BCG Coverage

NA

85%

85%

95%

Clinic report

Monthly

and Quarterly

‘’

Page 64: Project formulation and management

12. COORDINATION

• Only if applicable: If project is carried out in coordination with various organizations (~1-2 paragraphs).

• Briefly describe the type and frequency of activities that will be undertaken to ensure coordination among the various local and international organizations working in the area.

Page 65: Project formulation and management

13. TRAINING PLAN

• Only if applicable for the project.

• Include a training plan in table format highlighting the learning objectives, training methods, key activities, key personnel, and audience.

Page 66: Project formulation and management

14. SUSTAINABILITY• Describe in about 1 paragraphs.• How key activities will continue after project

funding ends.• Roles various actors, partners, and

communities members expect to play in ensuring sustainability.

• Other projects or similar project in different regions attesting sustainability.

Page 67: Project formulation and management

15. MAJOR CHALLENGES

• Describe in about 1-2 paragraphs.

• Summarize major challenges the project team expects to face and how they will be dealt with.

• Internal, External, Political. Cultural etc.

Page 68: Project formulation and management

16. REFERENCE

• Reference cited during project proposal formulation.

• Reverent and scientific methods of reference writing.

• Vancouver or Harvard style according to organizational policy

Page 69: Project formulation and management

17. APPENDICES

• Include any relevant supporting documents in appendices that may have been too lengthy to include in the body of the proposal e.g.

• Resumes of key personnel.

• Summary of needs assessments.

• Log frame or results framework.

Page 70: Project formulation and management

APPENDICES

• Organization Registration Certificate in District Administration

• Affiliation Certificate of Social Welfare Council.

• PAN Registration Certificates.

• Tax Execration Certificate.

• Audit Report of previous fiscal year.

• Bank clearance.

Contd..

Page 71: Project formulation and management
Page 72: Project formulation and management

CRITICAL PATH METHOD AND

PROGRAMME EVALUATION REVIEW TECHNIQUE

Page 73: Project formulation and management

PERT/CPM

• Both CPM and PERT are project management techniques, which have been created out of the need of western industrial and military establishments to plan, schedule and control the large and complex projects.

Page 74: Project formulation and management

PERT/CPM

• PERT/CPM are some time also called as Network Analysis.

• CPM/PERT are developed along two parallel streams, one industrial and the other military.

Page 75: Project formulation and management

PROGRAMME EVALUATION REVIEW TECHNIQUE

• PERT was developed primarily to simplify the planning and scheduling of large and complex projects.

• PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project.

Page 76: Project formulation and management

PERT

• Incorporates uncertainty by scheduling project activities.

• An event-oriented technique rather than start- and completion-oriented, and is used more in projects where time, rather than cost, is the major factor.

Page 77: Project formulation and management

PERT

• PERT is valuable to manage where multiple tasks are going simultaneously to reduce the redundancy.

Page 79: Project formulation and management

PROCESS OF PERT

• Step I: Identification of Activities: Activities represents job that should be performed in order to complete the project.

• Each activity takes some specific time under given condition.

Page 80: Project formulation and management

Step I: Identification of activities

• A PERT Event: is a point that marks the start or completion of one or more tasks.

• It consumes no time, and uses no resources.

• It marks the completion of one or more tasks.

Page 81: Project formulation and management

Step I: Identification of activities

• A PERT Activity: is the actual performance of a task. It consumes time, it requires resources and it can be understood as representing the time, effort, and resources required to move from one event to another.

Page 82: Project formulation and management

Step II: Sequential Arrangement of Activities:

• There is always technological sequence in various activities of a project.

• Preceding and succeeding events should be located to bring the sequence.

Page 83: Project formulation and management

Step II: Sequential Arrangement of Activities:

• Preceding events are those which should be completed before a particular event can start.

• Succeeding events are those that immediately follow another event.

Page 84: Project formulation and management

Step III: Time estimation of activities:

Optimistic time (O): Pessimistic time (P): Most likely time (M): Expected time (TE):

Page 85: Project formulation and management

Step III: Time estimation of activities:

• Optimistic Time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.

• Pessimistic Time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong.

Page 86: Project formulation and management

Step III: Time estimation of activities:

• Most Likely Time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.

Page 87: Project formulation and management

Step III: Time estimation of activities:

• Expected Time (TE): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal (the average time the task would require if the task were repeated on a number of occasions).

• TE = (O + 4M + P) ÷ 6

Page 89: Project formulation and management

STEP IV: Net Work Construction

• All activities of programme are connected sequentially to form a network called as PERT Network.

Page 90: Project formulation and management

STEP IV: Network Construction

• A PERT chart has its events sequentially in 10s (10, 20, 30, etc.) to allow the later insertion of additional events.

• Two consecutive events in a PERT chart are linked by activities, which are represented as arrows.

Page 91: Project formulation and management

STEP IV: Network Construction

• The events are presented in a logical sequence and no activity can commence until its immediately preceding event is completed.

• The planner decides which milestones should be PERT events and also decides their “proper” sequence.

• A PERT chart may have multiple pages with many sub-tasks

Page 92: Project formulation and management

Network Construction

Recruitment manpower

Plan

Training

Ready for action, schedule & activity

Plan implementation

Tender for equipment

Procurement & distribution

Installation

Results & Evaluation

Page 93: Project formulation and management

STEP V: CRITICAL PATH

• The next step is to determine the critical path.

• Critical Path is the longest possible continuous pathway taken from the initial event to the terminal event.

• The critical path is the path that takes the longest to complete.

Page 94: Project formulation and management

CRITICAL PATH

• To determine the path times, add the task durations for all available paths.

• Any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.

Page 95: Project formulation and management

10

30

20

50

4070

60

80

90

CRITICAL PATH

The duration of path ADFh is 7 working months. The duration of path ACEG is 9 working months. The duration of path BEG is 7.5 working Months.

A=1m

G=1m

H=2mF=2m

E=4.5m

C=3.5m

D=2m

B=2mE=3.5m

Page 96: Project formulation and management

CRITICAL PATH

• The critical path is ACEG and the critical time is 9 working months.

• It is important to note that there can be more than one critical path or that the critical path can change.

Page 97: Project formulation and management

CRITICAL PATH

• A critical path of a project can be shortening by: Fast tracking: performing more activities in

parallel, and/or Crashing the critical path: shortening the

durations of critical path activities by adding resources.

Page 98: Project formulation and management

PERT: Advantages

• PERT chart explicitly defines and makes visible dependencies.

• PERT facilitates identification of the critical path and makes this visible.

Page 99: Project formulation and management

PERT: Advantages

• PERT facilitates identification of early start, late start, and dalaying for each activity,

• PERT provides for potentially reduced project duration due to better understanding of dependencies leading to improved overlapping of activities and tasks where feasible.

Page 100: Project formulation and management

Disadvantages

• There can be potentially hundreds or thousands of activities and individual dependency relationships.

• The network charts tend to be large and may requiring several pages to print and requiring special size paper.

Page 101: Project formulation and management

Disadvantages

• The lack of a timeframe on most PERT/CPM charts makes it harder to show status.

• When PERT/CPM charts become unfamilier, they are no longer used to manage the project.

Page 102: Project formulation and management