project for developing the date sector in jericho and the jordan valley
DESCRIPTION
Palestinian Agriculture Relief Committees (PARC) in collaboration with Asian People's FundTRANSCRIPT
![Page 1: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/1.jpg)
Moon Valley Date Factory
Project for developing the Date Sector in
Jericho and the Jordan Valley
![Page 2: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/2.jpg)
Moon Valley Date Factory• It was
established in 2009 by PARC, and it is run by Al Reef Company, which is the commercial arm of PARC.
![Page 3: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/3.jpg)
Capacity: 500 kg
per hour.
![Page 4: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/4.jpg)
Project area: 12000 m2
Location: JerichoComponents of the
Project: 1. Refrigerators for storing
the dates with a storage capacity of 400 tonnes
2. Filling and packaging lines
3. Sun-drying facilities4. Filling station of 616 m2
5. Lab for quality analysis6. Two vehicles for
distribution
![Page 5: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/5.jpg)
Production capacity: 1 ton per hourJob creation: 30 employees (men and women)
Number of farmer beneficiaries: 45 (450 beneficiaries when including the farmers’ families)
![Page 6: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/6.jpg)
Capacity of the quantity of dates in the Jordan valley
- 1000 ton medjoul dates
- 1900 ton different varieties like Baladi, Hiyani, Barhi, Zheidi
Note: annual increase from medjoul dates is around 25%
![Page 7: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/7.jpg)
Markets
Export medjoul dates to different international markets like Italy, Belgium, France, Britain, new Zealand, USA, UAE, plus the local market.
![Page 8: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/8.jpg)
![Page 9: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/9.jpg)
Use of the Loan: construction and rehabilitation process in the dates factory in Jericho
• 1. Build 120 meter of offices in front of the factory
![Page 10: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/10.jpg)
During Work
![Page 11: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/11.jpg)
2. Rehabilitate the walls around the warehouses (fridges) by adding a cement cover.
![Page 12: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/12.jpg)
3. Fix the gate of the warehouses (fridges)
![Page 13: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/13.jpg)
4. Provide a generator for the factory.
![Page 14: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/14.jpg)
5. Rehabilitate a road from the main street to the factory and plant palm trees on the sides.
![Page 15: Project for developing the Date Sector in Jericho and the Jordan Valley](https://reader036.vdocuments.site/reader036/viewer/2022062704/555cb897d8b42a64718b4591/html5/thumbnails/15.jpg)