project 2013: 3 simple & practical steps to resource basics in under 20 minutes

11
Project 2013 Microsoft Project for Professionals 5 Simple & Practical Steps to Mastering Resource Basics in under 20 Minutes Jakub Marciniak Solution Consultant DeltaBahn LLC

Upload: deltabahn

Post on 12-Jan-2017

639 views

Category:

Technology


2 download

TRANSCRIPT

Page 1: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

Project 2013Microsoft Project for

Professionals5 Simple & Practical Steps to Mastering Resource

Basics in under 20 Minutes

Jakub MarciniakSolution ConsultantDeltaBahn LLC

Page 2: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

Agenda

Task Basics

Insert tasks Set the task mode

Estimate duration

Link the tasks

Set task constraints

Task context

Structure in summary

tasks

Add milestones

Add recurring

tasks

Adjust lag, lead and

elapsed time

Determine critical tasks

Resources Assign resources

Setup project

calendar

Adjust task

types

Reporting Create a dashboard

Modify the dashboard Set up views Setup

tables

Page 3: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

1. Open the project saved last time

• Open the project that was created and saved from the previous part of the series Task Context

OR

• Create a new project from the Commercial Construction Template and follow the instructions choosing different tasks

Page 4: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

2. Assign Resources to a TaskSelect the task Resource Allocation and choose a resource:

Alternatively, select the task and assign resources through the Task Form:

Page 5: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

2. Set the project calendarProject tab:

Create a new calendar:

Page 6: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

3. Set exceptions to the calendar (Holidays)

Add Thanksgiving as a non-working day: Add Christmas as a non-working day:

Page 7: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

4. Apply the new calendarProject tab: Choose the newly created calendar:

Page 8: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

5. Work with Fixed UnitsSelect the task Pour concrete elevator walls

Right-click in the Task Form and choose work:

Increase the duration to 2 days and click OK:

Because it is a Fixed Unit task, the 100% of assignment units don’t change. Instead, the end date gets pushed out and work is added.

Page 9: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

6. Work with Fixed DurationSelect the task Install pneumatic tube in elevator pit

Select Fixed Duration as the Task Type:

Increase the Units to 200% and click OK:

Because it is a Fixed Duration task, work is added:

Page 10: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

7. Work with Fixed Work

Select Fixed Work as the Task Type:

Decrease the Units to 50% and click OK:

Because it is a Fixed Work task, the duration increases:

Page 11: Project 2013: 3 Simple & Practical Steps to Resource Basics in under 20 Minutes

Thank [email protected] (281) 344-0437

www.deltabahn.com