microsoft project for professionals - 5 simple & practical steps to mastering task basics in...
TRANSCRIPT
Project 2013Microsoft Project for
Professionals5 Simple & Practical Steps to Mastering Task Basics
in under 30 Minutes
Jakub MarciniakSolution ConsultantDeltaBahn LLC
Agenda
Task Basics
Insert tasks Set the task mode
Estimate duration
Link the tasks
Set task constraints
Task context
Structure in summary
tasks
Add milestones
Add recurring
tasks
Adjust lag, lead and
elapsed time
Determine critical tasks
Resources Assign resources
Setup project
calendar
Adjust task
types
Reporting Create a dashboard
Modify the dashboard Set up views Setup
tables
1. Create new project from template
2. The Gantt Chart - Overview
1) Timeline2a) Outline pane (tasks)2b) Gantt Chart
Get more space to work
Hide the timeline:
3. Insert Task
4. Analyze the new task created
Name it:
Make sure that new tasks are created in Auto Scheduled Mode:
Observe the changes of its’ summary task:
Explanation: Auto vs Manually Scheduled
Auto Scheduled Manually ScheduledSchedule is calculated based on Project Start, Project Finish, Task Dependencies, Calendar selections, Resource Scheduling
Is not calculated by Project
Uses Duration, Work and Resources for scheduling Is not scheduled by Project
Allows only Numbers for Duration and Work Numbers, date and text can be entered for Duration and Work
Allows only valid dates for Start and Finish date Numbers, date and text can be entered for Start and Finish date
Explanation: Scenarios
Less maintenance Automatic rescheduling with cascading
effects
Uncertainty: Not all parameters are defined Task is completely independent
Strengths
Auto Scheduled Manually ScheduledTask parameters are defined Not all parameters are defined
Dependencies and Constraints are defined Task is completely independent
5. Change Task Duration
Change the duration with the arrows:
Select the new task, one task before and after and zoom in on the selected tasks:
The estimated duration is indicated by the question mark
View tab
Or type in, for example “2d”:
You can enter the duration in different scales. Try to type in2m = Minutes2h = Hours2d = Days2w = Weeks2mon = Months
6. Link the tasks together
Select the new task, one task before and after and link the tasks together:
Task tab:Observe the adjustments due to linking in the cells highlighted in light blue:
And the arrows in the Gantt Chart indicating the link:
7. Display the task form for Task Dependencies
View tab:
Select Details and choose the Task Form:
Right-click in a free spot in the Task Form and select Predecessors & Successors:
Explanation: Task Dependency Types
Finish-to-Start (FS)
Start-to-Start (SS)
Finish-to-Finish (FF)
Start-to-Finish (SF)
The finish date of the predecessor task determines the start date of the current task.Both task start at the same start date.
Both task end at the same finish time.
The start date of the predecessor task determines the finish date of the current task.
8. Explore Task Dependencies
Select different task dependencies in the Type column of the Task Form:
9. Constrain a task with a deadline
Double click on a task:
In the Advanced tab, set a “Finish No Later Than” constraint and date:
10. Save your projectFile tab:
Thank [email protected] (281) 344-0437
www.deltabahn.com