  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    1/86

     

    SAPProduction Planning for

    Process Industries

    (PP-PI)Configuration Pack

    Published by Team of SAP

    Consultants at SAPTOPJOBS

    Visit us at www.sap-topjobs.com 

    Copyright 2008-10@SAPTOPJOBS

    All rights reserved. No part of this publication may be reproduced, stored in a

    retrieval system, or transmitted in any form, or by any means electronic or

    mechanical including photocopying, recording or any information storage and

    retrieval system without permission in writing from SAPTOPJOBS 

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    2/86

     

    INDEX

    1.  PRODUCTION PLANNING - PROCESS INDUSTRIES (PP-PI) 3 

    2.  DEFINE PROFILE WITH DEFAULT VALUES 5 

    3.   ASSIGN MATERIAL TYPES 10 

    4.  DEFINE RECIPE STATUS 13 

    5.  DEFINE RECIPE USAGE 16 

    6.  DEFINE PRIORITY SEQUENCE FOR AUTO RECIPE SELECTION 19 

    7.  DEFINE ORDER TYPES 22 

    8.  DEFINE ORDER TYPE DEPENDENT PARAMETER 26 

    9.  DEFINE NUMBER RANGE 36 

    10.  DEFINE CONFIRMATION PROFILE 39 

    11.  PROCESS MANAGEMENT 47 

    12.  TRANSPORT PREDEFINED CHARACTERISTICS 50 

    13.  TRANSPORT PREDEFINED MESSAGE CATEGORIES 52 

    14.  DEFINE AND SETUP CONTROL RECIPE DESTINATION 57 

    15.  DEFINE PROCESS MESSAGE CHARACTERISTICS 64 

    16.  DEFINE AND SETUP MESSAGE DESTINATIONS 69 

    17.  DEFINE AND SETUP PROCESS MESSAGE CATEGORIES 72 

    18.  PROCESS INSTRUCTION CATEGORY 78 

    19.  SUMMARY:- 86 

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    3/86

     

    1. Production Planning - Process Industries (PP-PI)

    PP-PI is used in process industries where there areinstructions and activities are to be confirmed during theprocess.

    PP-PI using process orders without process Instruction andcontrol recipe also used in many places where there is no needto get confirmation of intermediate activities performed alongthe process.

    If the process is long and there are many actions to be

    confirmed during the process, it is achieved through thecontrol recipe and process Instructions.

    Following are the steps involved to explain PI in a simple term.

    • 

    In the Master Recipe, Process Instructions areattached to the phase.

    •  While creating the process orders, control recipe will

    be created, which will contain the processInstructions.

    •  Control recipe will be sent to the proper destinationor to the operator who has to input the data toconfirm his action performed.

    •  Control recipe will be sent back to the process orderand instructions with data will be available.

    Master Data in PP-PI:-

    Bill Of Material:-

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    4/86

     

    List of components along with the required quantity tomanufacture a product.

    Resource:-

    Machine and process equipments are termed as Resource. Indiscrete it is known as Work center.

    Master Recipe:-

     Task list specifying the sequence of operations and itsduration is termed as Master Recipe. In discrete it is known asRouting.

    Master Recipe contains:-

    Sequences of operations are detailed in operation andphases. Each operation has to have at least one phase.

    Duration for each processing is maintained in the phase.

    Production version to be used in the master recipe

     There are more terminologies about Process Messages andcontrol recipe, which are explained in the chapter 9.

    Configuration explained here are the only extra configurationsettings to be performed for PP-PI.

    Balance configurations explained for the DiscreteManufacturing process are same applicable to PP-PI also.

    Few Example: - Configuration of BOM item category, Workcenter field selection, BOM selection.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    5/86

     

    2. Define Profi le with Default Values

    BACKGROUND:-

    Default values to be displayed while creating Master Recipeare maintained in Profile.

    In a profile you can specify default values for the followingareas:

    • 

    General recipe data such as control keys and theincrement between

    •  Operation numbers

    •  Recipe graphics

    •  Quality data

    When creating or changing a master recipe, you have to entera profile. The values of this profile are then offered as defaultvalues in the new recipe or the new recipe objects. You caneither accept or overwrite these values.

    SCENARIO:-

    Standard profile will be sufficient. Discuss the standardProfile.

    MENU PATH:-

    IMG Production Planning for Process Industries  MasterData  Master Recipe  Settings for the task list type  Define profiles with default values

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    6/86

     

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    7/86

     

    Click

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    8/86

     

    Field name Explanation for field

    Control Key Default control key to appearin the master recipe

    Operation increment Incremental number for eachoperation.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    9/86

     

    Field Key Any user defined field key toappear in the operation

    PI Increment Process Instruction incrementcount

    PIC increment Process InstructionCharacteristic increment

     To create new entries,

    Click

    Maintain the above explained data.

    Click

    Note: - Profile is a mandatory entry while creating MasterRecipe.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    10/86

     

    3.   Assign Material Types 

    BACKGROUND:-

    Only materials of the material types allocated in this step canbe allocated to a master recipe at the header level, that is, asthe material to be produced.

    SCENARIO:-

    Discuss the material type assignment setting.

    MENU PATH:-

    IMG Production Planning for Process Industries  MasterData  Master Recipe  Settings for the task list type  Assign Material types

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    11/86

     

    Click

    Maintain Task List type. E.g. 2 to indicate Master Recipe

    Maintain Material type. E.g. FERT to indicate Finished goods.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    12/86

     

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    13/86

     

    4.  Define Recipe status 

    BACKGROUND:-

     The recipe status determines:

    •  Whether a recipe is released for use in process orders

    •  Whether a recipe is released for costing

    •  Whether a consistency check is carried out before therecipe is posted

    When a master recipe is created, a status must be assigned toit. This status can later be changed according to theprocessing stage of the recipe.

     Together with the recipe usage, the recipe status is used tocreate priority sequences that serve as a basis for theautomatic selection of recipes during order creation, capacityplanning and costing.

    SCENARIO:-

    Define / Discuss the Recipe status.

    MENU PATH:-

    IMG Production Planning for Process Industries  Master

    Data  Master Recipe  Data for the Recipe Header  DefineRecipe status

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    14/86

     

    Field Name Description and Value

    Status Number identifying the statusof the master recipe

    Description Description to the statuscreated

    Rellnd Indicates Release status of therecipe. If the recipe is not

    released, it can not be used tocreate process order.

    Cstng Indicates relevancy to costing.Status number with thischeck box will be consideredduring costing run.

    Cons.chk. Indicates to carryout theconsistency checkautomatically while saving.

     To create new status,

    Click

    Maintain the data as explained above

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    15/86

     

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    16/86

     

    5. Define Recipe usage

    BACKGROUND:-

     The recipe usage determines:

    •   The purpose or area, for which a recipe is created

    example, the chemical, the pharmaceutical or the foodindustry

    When you create a master recipe, you must assign a recipeusage to it.

    You can create several recipes with different recipe usages forone material.

    SCENARIO:-

    Create Recipe usage

    MENU PATH:-

    IMG Production Planning for Process Industries  MasterData  Master Recipe  Data for the Recipe Header  DefineRecipe usage

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    17/86

     

    Click

    Field name Field description and value

    Usage Number identifying the usage.E.g. 1

    Description Description of the usage. E.g.Production indicates thisusage is for process order

    creation.

    DCr Dynamic Modification Criteriato change the inspection scopedynamically if required.001 – for material base tochange the inspection scope.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    18/86

     

    002 for material and customercombination to change theinspection scope.003 for material and vendor

    combination to change theinspection scope.

    Optional entry can be leftblank if no DynamicModification Criteria isrequired.

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    19/86

     

    6. Define Priority sequence for Auto RecipeSelection

    BACKGROUND:-

    Priority sequences are defined according to which masterrecipes are selected in the following cases:

    • 

    for order creation

    • 

    for costing

    Each priority sequence is identified by a selection ID.

     The selection criteria are:

    •  task list type (2 for master recipe)

    •  task list (recipe) usage

    • 

    task list (recipe) status

    Priority sequence will be determined within a selection ID bydefining selection priorities for different value combinations ofthese selection criteria.

    During the automatic selection of recipes, the system choosesthe recipe with the highest priority.

    Use

     The selection of recipes is carried out automatically

    •  if you have not maintained a production version and

    • 

    if you have entered a corresponding key for theparameter "Master recipe selection" in the order type

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    20/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    21/86

     

    Field name Field description and Value

    ID Selection id number. E.g. 04

    Selection priority. E.g. 1 toindicate first priority in the idgroup 04.

     Task list type. E.g. 2 toindicate Master recipe

    Usage. E.g. 1 to indicate therecipe usage number 1 to bepicked up.

    Status of the recipe to be

    picked up. E.g. 4 will firstpickup the recipe with statusnumber 4 i.e. Released statusas first priority

    Above settings are for selection id 04 with selection priority 1.Similarly maintain rest of the selection priority 2,3 and 4 asshown above in the screen.

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    22/86

     

    7. Define Order types

    BACKGROUND

    An order type covers control information that is required formanaging orders. Order type must be assigned to each order.

     The order type defines the following:

    •  Order category

    • 

    CO (Controlling) Partner update

    •  Order classification

    •  Open item management

    • 

    Settlement profile

    • 

    Retention period of the order

    •  Number assignment

    • 

    Status management

    SCENARIO:-

    Define / Discuss an Order type

    MENU PATH:-

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    23/86

     

    IMG Production Planning for Process Industries  ProcessOrder  Master Data  Order  Define Order Types

    Click

     To create new entries, it is suggested to copy from the SAPstandard order type PI01.

    Select PI01

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    24/86

     

    Field name Field description and value

    Order category Internally defined field withpredefined value as 40.

    Order type Field referring the order type.E.g. YA70 to define your ownorder type

    Description Description to the order type.E.g. Process order (internal

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    25/86

     

    number)-IND6

    Leave the rest of the fields with the existing entries.

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    26/86

     

    8. Define order type dependent parameter

    BACKGROUND:-

    Parameters that are valid for each order type and plant aredefined here. The parameters are split up as follows:

    •  Master data

    Here, you define the data that influences master dataselection or order master data maintenance.

     The screen contains the following indicators:

    •  Master Recipe Selection

    • 

    Recipe selection ID

    • 

    Application defines how the BOM alternatives areselected.

    • 

    Cost accounting

    Here, you define the parameters relevant for costaccounting, such as costing variants for planned andactual costs and a results analysis key.

    •  General data

    Here, you define the following parameters:

    Substitute MRP controller/substitute productionscheduler. These are proposed when you create processorders if an MRP controller or production scheduler isnot specified in the material master.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    27/86

     

    CopyPlannedOrdSchedg - defines that scheduling of theplanned order is transferred unchanged to the processorder.

    SCENARIO:-

    Create an order type dependent parameter in Plant IND6 fororder type YA70

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessOrder  Master Data  Order  Define Order Type-Dependent parameters

    Click

    It is always suggested to create new one by copying fromstandard sap settings.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    28/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    29/86

     

    Field Name Field description and Value

    Plant Key identifying the plant.E.g. IND6

    Order type Key identifying the order typealready created.E.g. YA70.

    Production Version Selection of production duringprocess order creation.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    30/86

     

    E.g. Select Automaticselection of productionversion.

     Tick in this check box will

    check the components whenexploding the Bill Of Material.Leave this blank.

    Indicator specifying that anorder of this order typerequires approval.If you have set this indicator,the entire order or parts of itcan only be released if theorder has status Approvalgranted. Leave it blank.

    Operation screen will bechecked when transferring thedata from Master recipe intothe order. Tick this check box. 

    Recipe selection Specifies whether a masterrecipe is selected when youcreate a process order and

    how it is selected. E.g SelectMaster recipe proposedManual selection.

    Selection ID Key which specifies thepriorities according to which,master recipe will be selected.

    When you create the orders,they are automaticallyassigned status Order

    record required. This status isdeleted when you archive theorder record. Only then can you archive and delete theorders.

    If the entry tool is on,

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    31/86

     

    system automaticallybranches to the operation'sdetail screen after youcreate an operation in the

    routing.Increment for each operation.E.g. 0010 will makeincremental order of 10.

    Click tab screen

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    32/86

     

    Key indicates when to createthe reservation to thecomponents.E.g. 3 will create thereservation to the component

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    33/86

     

    as soon as the order iscreated.

    Key identifies the right BOMapplication.

    E.g. Process manufacturingwill ensure selection of PI01.

    Click

    Maintain the entry as shown above screen.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    34/86

     

    Contents are same as to that of Production order type entries.Hence it is not repeated here.

    Click

    Below displayed is the controlling tab screen detail.

    Entries here (costing variant planned and actual, resultsanalysis key and default rule) are maintained in discussion

    with Controlling Module.

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    35/86

     

    Maintain the entry as shown above. This is mainly to displaythe information in the reports of missing parts list.

    Click

    Note: - You will get a message No1 entry copied.

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    36/86

     

    9.  Define Number Range 

    BACKGROUND:-

    Each order is uniquely identified by an order number withinone client.

    You allocate each order to a number range group via the ordertype. You can allocate several order types to the same numberrange and thus the same interval.

     There are two types of number assignment:

    • 

    Internal number assignment

    When you create an order, the SAP System automaticallyassigns a consecutive number from the number rangethat you have defined.

    • 

    External number assignment

    When you create an order, you must specify a numberfrom the allowed number range.

    SCENARIO:-

    Define Number range for order type YA70

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessOrder  Master Data  Order  Number Ranges  DefineNumber Range for Orders

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    37/86

     

    Click

     To display the number range assignment Click

     To maintain the number range assignment click

    Note:- Since the new order type has been created throughcopying from standard sap order type, automatically numberrange has been assigned.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    38/86

     

    If the order type has not been assigned with the numberrange, it will appear at the bottom.

    Click

     To select and assign the number range

    Go to below in the screen where list of Not Assigned order willbe displayed

    Click on the order type

    Click select element

     Tick the check box where it is to be assigned. E.g. as shownbelow

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    39/86

     

    10. Define Confirmation profile

    BACKGROUND:-

     This confiugration setting enables to define the confirmationprofile for single screen entry.

    Confirmation profile is used in transaction COR6N forperforming confirmation.

    Process order confirmation can be performed using COR6Ntransaction. This transaction similar to CO11N has the abilitydefine the tab fields to be displayed to the user by which moreoption can be exercised.

    In order to use this, it is required to understand theconfirmation profile configuration.

    SCENARIO:-

    Define Confirmation profile.

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessOrder  Operations  Confirmation  Single entry Screen  Define Single Screen Entry

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    40/86

     

    Click

    Maintain the entry as shown below

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    41/86

     

    Note:- click at

    the to view how the header to look.

    After selecting, click to view it

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    42/86

     

    Click

    Similarly it can be done in the detail area also

    Right side maintain the desired text for each area

    Note:- Tick at the closed check box indicates that by defaultthis tab screen is closed. User has to open if required.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    43/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    44/86

     

    Click

    Click

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    45/86

     

    Click the desired profile as Standard profile.

    Click

    Click

    Impact of this configuration in Master Data /Transaction

    While performing the confirmation using COR6N, screen willappear as per the setting maintained here.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    46/86

     

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    47/86

     

    11.  Process Management

    Friends,

    Configurations similar to that of discrete production processare

    BOM Selection

     Task List selection

    Availability check

    Scheduling

    Confirmation parameter

    Now the next important settings related to PP-PI are theprocess instructions and process messages.

    Before we go ahead, let’s discuss some of the important

    terminologies and definitions related to Process Instructionsand process messages.

    Control Recipe Destination:- 

     The control recipe destination specifies

    • 

     The technical address to which a control recipe istransferred

    •  How the transfer takes place (for example, initiated byR/3 or by process control)

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    48/86

     

    Process Instruction Characteristics:-

    A characteristic of a characteristics group released for use inprocess instructions.

    Process instruction characteristics are allocated to processinstructions either directly or via the instruction category.

     Together with the corresponding characteristic values, theydetermine:

    • 

     The information transferred or requested in a processinstruction (for example, the status of a control recipe)

    • 

    How the requested data is to be processed (for example,the message category to be used to report the data)

    Process Message Characteristics:-

    A characteristic in a characteristic group which has beenreleased for use in process messages. Process messagecharacteristics are allocated to process message categories.

     Together with the corresponding characteristic values, theydetermine the content of a process message.

    Process Message Categories:-

     The process message category specifies:

    • 

     The characteristics to be allocated to a process message,i.e. the information to be sent

    •   The message destinations to which a process message isto be sent.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    49/86

     

    Process Instruction categories:-

     The process instruction category specifies:

    • 

    the type of process instruction (for example, processparameter or process data request)

    • 

    the characteristics of this process instruction, that is, theinformation to be sent via this instruction

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    50/86

     

    12. Transport predefined Characteristics

    BACKGROUND:-

    In this step, transport the process instruction characteristicsand process message characteristics predefined by SAP fromthe SAP reference client to the logon client.

    You need these characteristics

    • 

    For the message categories predefined by SAP

    •   To create your own message and process instructioncategories

    Note:-

     The names of the characteristics predefined by SAP all startwith PPPI_.

    You cannot change these characteristics in your logon client.

    After carrying out this step, the standard characteristics areavailable in all Plants in the client.

    When you import these characteristics, the system will issue aWarning which informs you that this data is of type "A".Ignore this message.

    SCENARIO:-

    Copy the characteristics to the new client.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    51/86

     

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessManagement  Standard Settings  Transport Predefined

    Characteristics

    Click

    Message will be displayed as shown above in the system afterperforming this task.

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    52/86

     

    13.  Transport Predefined Message Categories 

    BACKGROUND:-

    Predefined (by SAP) message categories will be copied to therequired new client In this step as Customizing settings.

     These message categories are required for:

    •   The link to PP, MM and QM

    • 

     The link to higher-level systems (linking of externalrequirements)

    • 

    status management in the case of orders and controlrecipes

     The predefined message categories are copied together with alltheir assignments (assignments of characteristics, estinationsand destination-specific target fields).

    Note:-

    First characteristics for process management predefined bySAP have to be copied before performing this step.

    SCENARIO:-

    Copy the standard Process message categories (created bySAP) to the new client.

    MENU PATH:-

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    53/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    54/86

     

    Click to copy

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    55/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    56/86

     

    Click

    Click

    Click to display the list of message categories

    Click to copy

    Click

    Click

    Note:-

     This above settings of copying the standard settings created bySAP will be sufficient to work with process instructions.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    57/86

     

    14.  Define and setup control recipe destination 

    BACKGROUND:-

     This configuration setting enables to define the control recipedestination.

    A control recipe destination defines the following:

    •  Whether the process instruction of a phase is transferredto an external system or is converted into an R/3 PI sheetfor a line operator

    •  Which system or line operator processes the processinstructions of a phase

    An operation can contain many phases.

    Each phase can have different control recipe destination.

    In the process order, one control recipe can be created for eachcontrol recipe destination.

    Make the following settings for the control recipe destinations you want to use in your plant:

    •  Define the control recipe destinations as below.

    - Information on the type of signature used in PI sheets (forexample, signature with password check or digitalsignature)

    - Data that controls system performance during PI sheetdisplay

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    58/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    59/86

     

    Enter Plant. E.g IND6

    Click

    Click to create new entries. Standard setting shouldbe sufficient.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    60/86

     

    Field Name Field description and Value

    Plant Enter plant code. E.g. IND6

    Ctrol Rec.Destin. Code identifying the controlrecipe destination. E.g. 06

    Description of control recipeDestination

    Enter the control recipedescription. E.g. PI Sheet.

    Destination Type Destination for processInstructions to be sent viacontrol recipe. E.g 1 indicatesthe Control recipe transfer toR3 PI sheet.

    Address Name or group of line operatorwho maintains the PI sheet.E.g. Group 1.

    Click

    Click

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    61/86

     

    Select 01 destination by clicking left side grey box

    Double click in the left side of thescreen.

    Click . Maintain the entry if it is required to defaultcertain process instruction other wise leave it blank. It can bemaintained at recipe level.

    Screen without any Process instruction for your reference: -

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    62/86

     

    Field name Field description and value

    Position PI position in the controlrecipe to be maintained. 01refers to at the start of thecontrol recipe and 05 refers toat the start of the phase.

    Sequence Number defining thesequence.

    Instruction category Instruction category to which

    PI are to be generated.

    Click

    Click

    Lick

    Note:-

    Process Instructions will be determined from the InstructionCategory. No need to assign the PI to the destination type 01.

    However Process Instructions to be generated will define theposition of PI in the control recipe.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    63/86

     

    It is only optional entry. Process Instructions can be definedinside the master recipe also.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    64/86

     

    15.  Define Process Message Characteristics 

    BACKGROUND:-

    Process message characteristics in addition to the existingcreated by SAP, can be created if required.

    SCENARIO:-

    Create Process message characteristics

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessManagement  Process Messages  Process MessageCharacteristics  Define characteristics for Process Message

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    65/86

     

    Double Click

    Enter the characteristic name as LOT_QUANTITY

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    66/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    67/86

     

    Status

    Data TypeNumber of digit incase of numeric data

    Click

    Click

    Additional information

    Automatic value assignment

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    68/86

     

    Maintain the data if automatic value is to be assigned.

     Table 01 will refer the Process order header. Press F4 toDisplay more choices

    Field Select the desire field. E.g GAMNG refers to orderquantity.

    Will ensure automatic assignment of value

    Click

    Click

    Note:- Most of the standard Process message characteristicscan be used to meet the requirements. New characteristics canbe created as explained above.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    69/86

     

    16.  Define and Setup Message Destinations 

    BACKGROUND:-

    Define the following setting for the message destinations:

    • 

    Define the message destinations with their addresses.

    Message destinations are defined per plant.

    Assign destinations to messages via the message categoryor directly in the process message.

    SCENARIO:-

    Define and setup Message Destinations

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessManagement  Process Messages  Process MessageDestinations  Define and Setup Message Destinations

    Click

    Enter Plant E.g IND6

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    70/86

     

    Click

    By default required standard settings will be available.

    Field Name Field description and Value

    Destination Key identifying destination

    Description Description of the destination

     Type Destination type. E.g 01

    indicates the R3 Functionmodule

    Destination address Name of the function moduleto be called.

    Note:-

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    71/86

     

    Below are the example of SAP standard function module anddefinitions.

    Function module

    COCI_CONFIRM_ACTIVITYConfirmation of activities

    COCI_CONFIRM_MATERIAL_CONSPosting of goods issues

    COCI_CONFIRM_MATERIAL_MOVEMENTPosting of general goods movements

    COCI_CONFIRM_MATERIAL_PRODPosting of goods receipts

    COCI_CONFIRM_OPERATIONConfirmation of processing time events

    COCI_CONFIRM_TIMETICKETConfirmation of time ticket

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    72/86

     

    17.  Define and Setup Process Message Categories 

    BACKGROUND:-

    Every process message that you want to send via processmanagement must be assigned to a process instructioncategory.

    In this section, define the message categories that you want touse in your plant.

    For each message category, specify

    • 

    the information to be contained in messages of thecategory (via characteristic assignments)

    • 

    the destination to which the messages should be sent

    •  the destination fields to which the values of theindividual message characteristics should be transferred

    SCENARIO:-

    Define and setup process Message categories

    MENU PATH:-

    IMG Production Planning for Process Industries  ProcessManagement  Process Messages  Define and SetupMessage Categories

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    73/86

     

    Enter Plant. E.g IND6

    Click

    Note:-

    Above displayed message categories are assigned to plantIND6

    Let’s look Characteristics for PI_CONS message category

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    74/86

     

    Select PI_CONS by pressing left grey box

    Double Click in the left side of thescreen

    Above shown characteristics are attached to the messagecategory PI_ CONS

    Let’s look at the destinations to the PPPI_BATCH

    Select PPPI_BATCH by clicking the left grey box

    Double click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    75/86

     

     To the message categories there are many messagecharacteristics were attached. Now there are only selected

    characteristics attached specific to the destination.

    Let’s look at the characteristics attached to the PI01 and to thePI04 destination.

    Select PI01 by clicking grey box in the left

    Double click in the left side ofthe screen

    Important Note:-

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    76/86

     

     Though there are many message characteristics attached tothe message category, to the destination PI01onlyPPPI_PROCESS_ORDER characteristic is attached

    Click

    Similarly repeat for PI04

    Click till you reach the main IMG screen

    We have discussed

    Control recipe destination definition

    Message characteristics

    Message Destinations

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    77/86

     

    Message categories

    Now let’s discuss Process Instruction characteristics.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    78/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    79/86

     

    Click

    Field Name Field description and Value

    Instr Cat Key identifying the instructioncategory. E.g ACONS_1

    Description Description identifying theinstruction category

    ProcessInstr.Type*** Number identifying theinstruction type.

    *** Instruction type describes the type of process Instruction

    1-- Refers to Process Parameter

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    80/86

     

    It is used in PI Instruction to attach some notes, any textdetails through Long text

    2 – Refers to Process Data Request

    It is used whenever there is a need to get the data asinput

    3 – Message subscription

    A process instruction that specifies that processcontrol is to send a message every time a specificevent, for example, a goods receipt, occurs.

    4 – Process Data calculation formula

    A type of process instruction that specifies that avalue must be calculated in the PI sheet. This value isthen sent to a particular destination using a processmessage.

    5 – Inspection Result Request

     The inspection results request specifies the operationsand phases for which inspection results must berecorded. For these operations and phases, the functionfor recording inspection results can be accesseddirectly from within the PI sheet.

    6 – Dynamic Function Call

    Process instruction which enables the line operator tocall a user-defined function module from within the PIsheet.

    Depending on the function module, this option can beused to access order confirmation or material quantitycalculation or to start a user defined function module.

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    81/86

     

    7 – Sequence Definition

    It is used to define the PI sheet entry sequence

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    82/86

     

    Let’s try to look at the list of characteristics assigned to theprocess Instruction category ACONS_1

    Select ACONS_1 by clicking the grey box in the left

    Double click in the left side ofthe screen

    Here any newly created characteristics can also be attached ifrequired.

    Note:-

    Field Name Field description and Value

    No Serial number forcharacteristics

    Characteristics*** Process InstructionCharacteristics. Here we haveto mention the PIcharacteristics predefined by

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    83/86

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    84/86

     

    Select CONS_1

    Double click in the left side ofthe screen

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    85/86

     

    Note:-

    First characteristic is PPPI_DATA_REQUEST_TYPE which willdiver to the goods issue module. Always first characteristic

    should be the one which takes to the right module.

    In the above,

    PPPI_REQUESTED_VALUE is assigned to get the quantityof material consumed. Whenever it is required to get theinput this characteristic is to be used.

    Click

  • 8/17/2019 Production Planning for Process Industries-ecc6.0-Ver1

    86/86

     

    19. Summary:-

    Guys, I am sure, you are now equipped to configure the SAP

    PP-PI production process with process messages according tothe business blue print with this configuration manual.

    Wish you all the best.