  • 8/12/2019 Ppt Sukhbir

    1/33

    Methodology of HMA

    construction

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    2/33

    To Be Covered

    Hauling

    Placement

    Compaction

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    3/33

    Tandem Axle End Dump Truck

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    4/33

  • 8/12/2019 Ppt Sukhbir

    5/33

    Loading of Hot Mix Asphalt in Truck

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    6/33

    Cover the HMA

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    7/33

    Reason For Compaction

    To prevent further compaction

    To provide shear strength or resistanceto rutting

    To ensure the mixture is waterproof

    To prevent excessive oxidation of the

    asphalt binder

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    8/33

  • 8/12/2019 Ppt Sukhbir

    9/33

    Temperatureduring construction

    Stage of Work Viscosity of Binder Indicated Temperature

    Binder at Mixing Max 2 Poise 165-185

    Aggregate Temperature 165-185

    Mix Temp. at Plant Max 4 Poise 150-170

    Mix Temp. at Laying site

    Max 5 Poise

    130-160

    Rolling Temperature Min 115

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    10/33

    Rolling Procedures

    Rolling should start as soon as possible afterthe hot mix has been spread.

    Rolling consists of three consecutive phases.

    1) Breakdown or initial rolling2) Intermediate rolling

    3) Finish rolling

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    11/33

    Breakdown rolling compacts the material

    beyond the compaction imparted by the

    paver, to obtain practically all of the needed

    density.

    Intermediate rolling densifies and seals the

    surface.

    Finish rolling removes roller marks and other

    blemishes left from pervious rolling

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    12/33

  • 8/12/2019 Ppt Sukhbir

    13/33

    If rolling causes material displacement, the

    affected area are loosened at once with lutes

    or rakes and restored to their original grade

    with loose material before being re-rolled.

    Heavy equipment, including roller should not

    be permitted to stand on the finished surface

    it has thoroughly cooled

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    14/33

    Rolling freshly placed asphalt

    mix is done in the following

    order:1. Transverse joints

    2. Longitudinal joints3. Initial or breakdown rolling

    4. Second or intermediate rolling

    5. Finish rolling

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    15/33

    Transverse JointsFirst pass in made with a steel-wheeled roller moving along the

    longitudinal joint for a short distance.

    This operation should be repeated with successive passes covering 150

    to 200 mm (6 to 8 in) of fresh material until the entire width of a drive rollsin on the new mix.

    If boards are not used, transverse rolling must 150 to 200 mm short of the

    outside edge in order to prevent damage to the edge.

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    16/33

    Longitudinal Joints

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    17/33

  • 8/12/2019 Ppt Sukhbir

    18/33

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    19/33

    The roller should be shifted to the

    previously so that not more then 150 mmrides on the as of newly spread material

    This position being shifted graduallyacross the joint until thoroughly

    compacted.

    Vibration should not be used when

    operating on a cold mat.

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    20/33

  • 8/12/2019 Ppt Sukhbir

    21/33

    Overlapping of Roller Passes

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    22/33

    Rolling Pattern

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    23/33

    For thick lift construction, the rolling process

    should start 300 to 375 mm from lower

    unsupported edge until certain portion of the

    spread is compacted to some stability.

    The steel wheeled rollers the operation should

    always progress with drive wheel forward in the

    direction of paving.

    A main reason why breakdown rolling should be

    done with the drive wheel is that there ia a some

    mor5e direct vertical load applied by this wheel

    then tiller wheel.

    If the breakdown pass of the roller is made withtiller wheel forward, the pushing force and the

    weight is slightly ahead of the vertical, causing

    material to push up in front of the wheel.

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    24/33

    Wrong Direction of Roller Wheels

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    25/33

    Advantages of Pneumatic Tires

    Roller

    1) They provide more uniform degree of

    compaction then Tandem Roller

    2) They improve the seal near surface

    and decreasing the permeability of layer.

    3) They orient the aggregate for greatest

    stability.

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    26/33

    Finish Rolling

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    27/33

    Paving Operation

    The feed truck reverse up to the paver andstops few centimetres in fronts of it. As

    the paver approaches, its push rollers

    touch the rear wheels of truck.

    The hear of mix in front of screed should

    uniformly spread over the full pave width.

    Distance between surface of mat and

    lower edge of Auger flights shouldequivalent to roughly 5 times of max size

    of aggregate

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    28/33

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    29/33

    Auger and Limiting Plates for

    Auger tunnel

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    30/33

    Head of Mix in front of Screed

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    31/33

    Layer thickness and Grain

    size of Mix

    SUKHBIR SINGH

  • 8/12/2019 Ppt Sukhbir

    32/33

  • 8/12/2019 Ppt Sukhbir

    33/33

    Extracting A Core

    SUKHBIR SINGH