Double-sized motor room
Teacher workroom
Youth Lounge
Small Motor Room
Secure school entrance
Child restrooms
2 new family restrooms
Stroller-friendly walkway from Jocelyn Street
No loss of playground space
Site Fencing
Break Ground
Initial playground reconfigure
Sanctuary renovation
Addition continues
Minor exterior sitework
Addition continues
Select exterior sitework
Classrooms available
Sanctuary open
Social Hall construction
Complete sitework
Other interior renovations
Projected Project
Completion
Spring 2020
Summer 2020
Fall 2020 to Spring 2021
Summer 2020
Fall 2021