plant start up timeline - 24 aug 09 - rev 1

Upload: siska-friedman

Post on 06-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Plant Start Up Timeline - 24 Aug 09 - Rev 1

    1/1

    23rd 24th 25th 26th 27th 28th 29th 30th 31st 1st 2nd 3rd 4th

    AUGUST SEPTEMBER

    0800 hrs

    26/8

    26th 27th

    0800 hrs

    K1601

    Start Up

    SR/MGS

    4 hours

    1200 hrs

    NH3

    Converter

    Heating Up

    8 hours

    2000 hrs

    NH3 Prod

    to Tank/

    Urea Plant

    4 hours

    0000 hrs

    Reduce

    NH3 PL to

    40-60%

    4 hours

    0400 hrs

    IS1trigger

    0400 hrs

    27/8

    24 hrs

    cooling

    24 hrs

    repair of

    13TICA37

    0800 hrs

    29/8

    0800 hrs

    28/8

    36 hrs

    Start up

    NH3 plant

    2000 hrs

    30/8

    CO2

    available

    for urea

    plant

    2000 hrs

    31/8

    NH3 prod

    to urea

    plant

    0200 hrs

    1/9

    Urea

    reactor

    overflow

    first

    drop

    Urea plant

    shutdown

    IS1

    trigger

    Urea

    plantshutdown

    As per discussion

    24th Aug 2009 -

    morning meeting