pfr of 1.25 mtpa rohera watera limestone...

40
PRE-FEASIBILITY REPORT FOR THE PROPOSED ROHERA-WATERA LIMESTONE MINE (Production : 1.25 Million Ton Per Annum) Lease Area: 73.7421 ha Area: Non-Forest Category Of Mine / Deposit: ‘A’ Category Village Rohera Tehsil: Pinwara Dist: Sirohi (RAJASTHAN) Proponent J K Lakshmi Cement Ltd. Jaykaypuram, Tehsil Pindwara District Sirohi Rajasthan JUNE 2015

Upload: others

Post on 10-May-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

PRE-FEASIBILITY REPORT

FOR

THE PROPOSED

ROHERA-WATERA LIMESTONE MINE (Production : 1.25 Million Ton Per Annum)

Lease Area: 73.7421 ha

Area: Non-Forest

Category Of Mine / Deposit: ‘A’ Category

Village Rohera

Tehsil: Pinwara

Dist: Sirohi

(RAJASTHAN)

Proponent

J K Lakshmi Cement Ltd. Jaykaypuram, Tehsil – Pindwara

District – Sirohi Rajasthan

JUNE 2015

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 2

Contents

Title Page

1. Executive Summary 3

2. Introduction of Project/ Background Information 4

3 Project Description 6

4 Site Analysis 20

5. Planning Brief 22

6 Proposed Infrastructure 24

7. Rehabilitation and Resettlement (R & R) Plan. 27

8. Project Schedule & Cost Estimates 28

9. Analysis of Proposal (Final Recommendations) 29

A-1 Location Map 30

A-2 Map Showing Plant Site & Surrounding 10 km Area 31

A-3 Google Image Showing Topography of the Area 32

A-4 LOI from State Government 33

A-5 Surface Plan 37

A-6 Geological Plan 38

A-7 Conceptual Plan 39

A-8 Reclamation Plan 40

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 3

1. Executive Summary Name of Mine Rohera - Watera Limestone Mine

Lat / Long of any boundary point Topo Sheet 45 D/14, F.R.P Mataji Ka Temple

Latitude 240 36’45.3” Longitude 72

0 56’44.2”

Date of Grant of Lease Letter of Intent No. P 3(76) Khan/Group-2/2012

dated 17.12.2014. (ML No. 07/2009)

Period / Expiry Date Lease not yet granted.

Name of Lease Holder M/s J K Lakshmi Cement Limited

Village where the Mine is Located Rohera

Tehsil Pindwara

District & State Sirohi, Rajasthan

Forest / Non Forest Non Forest

Landuse and Ownership

Ownership / Type of Land Area in ha.

Govt. Waste Land 55.5

Private Agriculture Land 18.24

73.7421

Land is free from all encumbrances of Forest, Grazing Land and Aravalli Hills.

Total Lease Area 73.7421 ha.

Limestone Production 1.25 Million Tons Per Annum (MTPA)

ROM Limestone Handling 1.30 MTPA

Net Mineable reserve 25.5 million tons

Life of the Mine 20 years

Terrain Hilly terrain, highest elevation is 302 mRL

and lowest elevation is 270 mRL

Mining depth (Ultimate Pit Depth) 250 mRL

Stripping Ratio 1 : 0.022

Overburden / Wastes 5% of ROM handling

Height and Width of Benches 7 m height, 20-30 m width

Project cost Rs.170 crores

Employment 67 people

Water requirement and source 30 KL/day (mine pit water will be used)

Existence of public road / railway line, if any nearby and approximate distance

Nearest National

Highway

7.6 km. From Rohera to Swaroopganj on NH 14/NH 927A, between

Pindwara & Abu Road.

Nearest Railway Stn 7 km Swroopganj Railway station on Ahmedabad – Delhi Route.

Nearest Airport 130 km. Udaipur (Dabok) Airport, via NH 14/ NH 76/NH8

Nearest Town Rohera at 1 km.

Nearest major city Swaroopganj ( District Sirohi, Rajasthan) at 7.6 km.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 4

1. Introduction of Project / Background Information

(i) Identification of Project and Project proponent. In case of mining project, a copy of

mining lease / letter of intent should be given:

Name of Project: Rohera - Watera Limestone Mine

Category of Project: “A” Category.

Project Proponent: J K Lakshmi Cement Limited

M/s. JK Lakshmi Cement Ltd. is a flagship company of Late Shri Hari Shankar Singhania, JK Organization (Eastern Zone). The other well known companies of the group are JK Tyre & Industries Ltd., JK Paper Ltd., Fenner (India) Ltd., JK Sugar Ltd., JK Agri-Genetics Ltd. etc.

JKLCL's Cement Plant was set up in year 1982 with a capacity of 5 Lakh Tonnes Per Annum (LTPA), this capacity over the years have been increased to the level of 53.0 LTPA including Cement Grinding Unit of 5.5 LTPA each in Kalol in Gujarat & Jhajjar in Haryana .

JK Lakshmi Cement Limited is the first cement producer of Northern India to be awarded an ISO 9002 certificate and be accredited by NABL (Department of Science & Technology, Government of India) for its Lab Quality Management systems. JK Lakshmi Cement manufacturing facility has been rated amongst Greenest Cement Plant of India by CSE GRP 2005 thus highlighting our commitment to the environment even while ensuring the highest standards of quality for our products. JKLC have also won the 10

th & 11

th Safety Innovation award by IE(I), Greentech Safety Gold Award for 2013 & 2014,

International Safety award for 2013 & 2014 by British Safety Council, CII Energy Efficient Award 2013 & 2014, NCB award 2013, Golden Peacock Award for Corporate Social Responsibility 2013.

(ii) Brief description of nature of the project: JKLCL is operating a limestone mine near village Basantgarh, Tehsil Pindwara, District Sirohi over an area of 390.625 ha. The Company applied for Mining Lease for mineral limestone over an area of 74.072 ha. near village Rohera & Watera, Tehsil Pindwara, District Sirohi, Rajasthan for a period of twenty years on 01.04.2009. The area was explored in the past by Department of Mines & Geology in the year 1982-87. During the exploration period detailed Geological mapping of Limestone and channel sampling covering 3.3 km. long belt east of Watera village, 297 line samples were collected at regular interval of 200 m from 16 lines. Sixteen inclined bore holes were drilled for total length of 684.95 m and analysed.

Govt. of Rajasthan issued a letter of intent (LOI) No. P.3(76)/Gr.-2/2012 dated 17.12.2014 ( ML.

No. 07/2009) over an area of 73.7421 ha.

(ii) Need of Project and importance to the country or Region:

The cement demand in the country is going at the rate 9-10% (Compound Average Growth rate CAGR) particularly in the eastern states , due to various infrastructural projects planned by State/Central Governments and also due to rapid growth of industries, the demand is likely to be higher than average for the country.

(iii) Demand – Supply Gap: The cement demand in the country is going at the rate 9-10% (Compound Average Growth rate CAGR) particularly in the eastern states , due to various infrastructural projects planned by State/Central Governments and also due to rapid growth of industries, the demand is likely to be higher than average for the country.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 5

(iv) Imports / Export Vs Indigenous production:

Extraction of limestone will be done as indigenous production from mines and the same will be used as raw material for manufacturing of clinker in cement plant. Raw materials will not be imported for manufacturing of clinker.

(v) Domestic / Export Markets:

Limestone mine is a captive mine and the limestone from Mine will serve as raw material for clinker manufacturing in Cement Works. The cement so produced will be sold in the western part of country where it is assumed that there will be a acute demand of cement due to various projects taken by state / central Govt. as well as local builders / colonizers.

(vi) Employment Generation (Direct & Indirect) due to project:

The project will create the direct employment of 67 people.

Designation Nos. Remark

First Class Mine Manager 01 MMR 1961

Assistant Mine Manager 02 MMR 1961

Mining Engineer 01 MCDR 1988

Blasting Engineer 01

Asst. Manager Geology 01 MCDR 1988

Mine Foreman 02

Mechanical Engineer 01

Env. Supervisor 01

Electrical engr. 01

Instrumentation Engr. 01

Doctor 01

Compounder 01

Skilled / Semi-skilled/ Unskilled

Electrician / Mechanic 02 Skilled

HEMM Operators 36 Skilled

Blaster 01 Skilled

Drivers 02 Skilled

Helpers 12 Semi-skilled

Misc Work 10 Un-skilled

Total 67

It will also generate indirect employment for approx 100 tipper operators which will transport ROM limestone from Mine site to Crusher which will be installed in Mines. JKLCL will give preference to the local peoples during construction and operation phase of the project depending upon the skill, job requirement and capability. Several other indirect employment opportunities will be created in the surrounding areas like Transport for men and material, hotel operators, vehicle drivers and attendants, workshops, grocery and retails, medical, etc.

Adequate number of staff, officers, managers and workmen will be deployed at mine to achieve the desired objective. For operations of HEMM, skilled and semi skilled manpower will be required. And for generic various jobs, unskilled manpower will be required.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 6

2. Project Description

(i) Type of project including interlinked and interdependent projects, if any: None

(ii) Location (map showing general location, specific location, and project boundary &

project site layout) with coordinates: Location Map in Annexure 1

Latitude 24036’24.22’’ to 24

037’45.42” and Longitude from 72

056’20.27’’ to 72

057’22.7’’.

Project Boundary and Project Site Layout: Attached as Annexure 2

(iii) Details of alternate sites considered and the basis of selecting the proposed site,

particularly the environmental conditions gone into to be highlighted:

This is a mining project which is site specific and site so selected for mining operations is due to presence of insitu cement grade limestone. Alternate site cannot to excercised due to this reason.

(iv) Size and Magnitude of Operation:

1.25 MTPA Limestone production. Opencast Mining with Shovel / Dumper combination. 500 TPH Crusher will be established inside ML area

(v) Project description with process details (a schematic diagram/flow chart showing

the project layout, components of the project etc. should be given:

Regional Geology The eastern part of the area is mainly occupied by Ajabgarh series and Erinpura granite and pegmatite where as amphibolites of pre and post Erinpura granite, schist & phyliites of Ajabgarh group are forming isolated and detached hillocks in western part. Ajabgarh group is represented by calc-schist, calc-gneiss, mica-schist, phyliites, limestones and impure coarse grained limestone and quartzite where as rocks of pre and post Erinpura granite are represented by amphibolites and hornblende schist. The strartgraphic succession established by Colsun is mentioned below

Post Delhi Intrusives Soil & Cultivated fields Pegmatite &Quartz veins Erinpura Granites Hornblende and Amphibolites

Delhi Super Group Ajabgarh Group Limestone, Calc-schist & gneisses Mica schist, Phyliites and Quartzite

The general trend of rocks of Ajabgarh group varies from N45

0-70

0E to S45

0-70

0W with steep dips due

SE. The pre-dominant rocks of Ajabgarh group are schist, limestone and impure limestone, which cover wide part of this terrain. The spread of calcareous rocks are found in the east and south east of Pindwara which continues up to Amli village.

Geology of Lease Area The Mining lease area is mild hilly land. Mainly consist of Limestone rock and various types of lime stone present in this area such as Black Limestone, Gray Limestone and grayish Black Limestone. Geologically Lime stone of lease area belong to Delhi Super Group. The Lime Stone Assigned is Lower Proterozoic Age. The deposit is northern extension of Amli - Pindwara belt of Sirohi district. The limestone is part of Kumbhalgarh Group of rocks of Delhi Supergroup. The rock formation extends from village Thandiberi to north of Bharja village. The strike extension being 9 kms and maximum width is 2.7 kms. The northern part of this limestone is siliceous. Lime stone rock is consist of CaCO3 . In Lime stone CaO content is more than 42.3% hence it is used in Cement Industries. In lease area highest

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 7

elevation is 302 mRL and lowest elevation is 270 mRL. The rock is dipping 720

to 800. Lime stone is

Sedimentary rock form by chemical precipitation of lime stone.

Prospecting/ Exploration The preliminary investigations carried out by the Department of Mines & Geology, Govt. of Rajasthan during the year 1982-84 resulted in identifying the cement grade limestone deposit in the area. It occurs in the form of isolated discontinuous outcrops containing 45 to 49% CaO, which can be used as raw material in cement making. With this view Department of Mines & Geology, Govt. of Rajasthan carried out the regional as well as detailed investigation as per norms of prospecting of Cement Research Institute of India during the period 1982 to 1987. To estimate the reserves of limestone along with its grade and to find out the depth continuity. In the year 1982-87 the regional geological mapping and detailed geological mapping and channel sampling work was carried out in the entire Watera limestone belt and prospecting by drilling was carried during the year 1986 to 1987. In the year 1982-83, an area of 30 Sq.km. was covered under RGM and out of this 2 Sq.km. was selected for DGM over a strike length of 3.3 km. The rock types in the area are quartzites, phyllites and limestones of Ajabgarh group. The strike of the rock types varies from N-S to N30°E-S30°W and dips 40°-60° due NW & SE direction between Watera & Khara village. The rock types found in the Watera area are Quartzite, Phyllites and Limestones of Delhi super Group. These are at places intruded by quartz veins. The area under mapping was 3.5 km. In length and 0.6 km. In width with an area of 2 Sq. Km. The quartzites are the oldest rock in the area. These lies in SE part, quartzites generally occupy high hillocks in the area and are conical in shape. Quartzites generally strike N30°E-S30°W and dips 50°-60° due NW. Quartzites are massive in colour. Phyllites follows the quartzites in the west which mainly cover the valley portion, slopes of the hills and fields. These are argillaceous and micaceous in nature. The strike of foliation of phyllites vary from N10°E-S10°W to N30°E-S30°W and dips 50° due west. At places dips are vertical. IN the NE of the area limestone is intercalated in the phyllites. The limestone also looks phyllitic in nature in this portion. In the west of phyllites limestone is exposed in seven hillocks trending N30°E-S30°W in the east of Watera village.

It was planned to put bore holes at 200 m strike interval covering the entire strike length of limestone band to prove the cement grade limestone up to 20 m bgl. And to cover maximum width and synclinal structure of limestone, two bore holes were put from the same foundation on either direction. Two Bore holes were drilled at hole position 1, 2, 3, 4 & 9 and designated as A & B. All the 16 bore holes were drilled between 20.0 m to 51.0 m inclined depth. The bore hole details of drilling, inclination, depth & direction of the holes falling in lease area are given below: DMG drilled 16 core bore holes but only 11 holes are falling within the lease area. Details of 11 holes are given below:

S.No. Bore hole No. Type

(core/RC/DTH)

Inclination Direction Depth in

m

No. of

samples

1 WDH 1 A Core 450 124

0 20.0 10

2 WDH 1B Core 450 304

0 35.0 18

3 WDH 2 A Core 550 120

0 30.0 13

4 WDH 2B Core 450 300

0 40.0 21

5 WDH 3A Core 450 112

0 30’ 35.0 17

6 WDH 3B Core 700 292

0 30’ 25.0 13

7 WDH 4B Core 600 120

0 50.05 27

8 WDH 4B Core 500 300

0 50.20 24

9 WDH 5 Core 500 300

0 48.0 20

10 WDH 6 Core 500 300

0 51.0 26

11 WDH 7 Core 500 120

0 50.0 28

434.25

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 8

Sample Analysis A total of 297 line samples were taken at regular strike interval of 200 m. and sample lines at right angles to the general strike. Details are given in the attached geological report. Core samples mostly for every two metre depth were prepared lithology wise by splitting the core longitudinally. Half of the core was preserved and another half was used for analysis.

S.no. . Sample No. Sample Type

(Surface/ sub-

surface from

pits/ trenches/

borehole etc.)

No. of samples Details of Chemical Analysis(%)

SiO2 R2O3 CaO Mg

O

LOI

1 WDH-1A Core 10 9.79 2.17 47.43 1.25 36.66

2 WDH 1B Core 18 13.41 3.24 44.62 1.30 36.55

3 WDH-2A Core 13 11.85 2.26 46.15 0.72 37.75

4 WDH 2B Core 21 13.60 2.71 45.33 1.29 36.81

5 WDH-3A Core 17 13.55 3.44 42.90 1.47 35.12

6 WDH 3B Core 13 14.48 4.47 43.56 1.60 35.80

7 WDH-4A Core 27 13.17 3.13 43.95 1.27 35.89

8 WDH 3B Core 24 14.32 4.20 43.28 1.21 35.39

9 WDH-5 Core 20 17.79 3.55 41.58 1.71 34.56

10 WDH-6 Core 26 13.56 2.09 45.13 1.41 37.01

11 WDH-7 Core 28 11.88 1.94 47.13 1.33 36.89

13.4 3.01 44.64 1.32 36.22

Thus bore holes in the applied lease area contains CaO from 41.58% to 47.13%, MgO from 0.72% to 1.71% and SiO2 from 9.79% to 17.79%.

Reserves and Resources (UNFC)

Level of

Exploration

UNFC Code for

area

Category of reserve / resource

estimation

Reserve / resource as

per UNFC

G1 331 Measured 18,026,328

G2 332 Indicated 15,595,118

G3 333 Inferred 14,306,313

Total 47,927,759

Mineable Reserve

Level of Exploration Resources in million

Tonnes

Total Grade

Block I Block II

G1-Detailed

Exploration

15,930,143 2,096,185 18,026,328 CaO 44.64%.

MgO 1.32%

SiO2 13.4%

- G2-General

Exploration

12,823,746 2,771,372

15,595,118

G3-Prospecting - - 14,306,313

G4-Reconnassance

Total 28,753,889 4,867,557 47,927,759

Feasibility Assessment of Resources Measured Resources (UNFC Code 331) and Indicated Resources (UNFC Code 332) have been considered for reserve assessment and following are the criteria:

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 9

a. Geological: Exploration of the area has been carried by line sampling and core bore hole drilling. The area considered under G2 and G3 category will be further explored by way of core bore holes. Overall grade of the deposit is suitable for cement making.

b. Mining : Deposit is exposed on surface with no overburden. There exists inter bands of phyllites and schist and are estimated at 05% of total volume based on bore hole logs. These phyllites & schist will be dumped as waste. Mine is planned to produce 1.3 million tonnes (ROM) when fully developed by fully mechanised opencast method of mining. Proper barriers are proposed to be left. Mining will be carried out as per the provisions of MMR 1961.

c.Beneficiation: It is proposed to install a mobile crusher of 500TPH capacity with screening. After crushing, sized limestone will be fed to the cement plant by trucks / dumpers. In future Over Land Belt Conveyor may be installed for transportation of limestone from the mine to cement plant at Basantgarh.

d. Environmental Concern: This is a new mining lease and the company’s application for prior Environment Clearance is being processed. Mining operation will only commence after obtaining EC and Consent to Operate. All conditions imposed in EC and consent to operate will strictly be complied.

e. Legal / Administrative Aspects: Mining operations will commence only after getting EC and consent to Operate from SPCB. Company will comply with the provisions of MMR 1961, MCR 1960, MCDR 1988 and is committed for implementation of these and related mining laws. No mining will be carried out in the private land without obtaining NOC from land owners.

Limestone Reserve As Per UNFC

Category UNFC

Code

Quantity in tons

Grade

---

Total

Resources

(A+B) 47,927,759

Reserves (A) Proved (111) -

Probable (121) 13,557,819 43.88% CaO 1.44% SiO2

(122) 11,916,677

47.88% CaO 1.33% SiO2

Remaining Resources (B)

Feasibility Mineral Resources

(211) -

Pre-Feasibility Mineral resources

(221) 4,468,509

(222) 3,678,441

Remaining Measured Mineral Resources

(331) -

Remaining Indicated Mineral Resources

(332) -

Inferred Mineral Resources (333) 14,306,313

Reconnaissance Mineral Resources

(334) -

Mineable Reserves and Anticipated Life of the Mine Mineable reserves have been calculated by taking into account the reserves in probable categories only. Future rate of production for ROM will be maintained at 1.25 MTPA.

Sl.No. In tons

1. Net Mineable Reserves 25,474,496

2. Mineral to be mined in five years . 3,550,175

3. Remaining reserves at the end of plan period 21,924,321

4. Proposed rate of production per year (ROM) 1,250,000

5. Life of mine at the end of Mining Plan period 16.86

6 Life of the mine in years 21.86

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 10

Broad chemical specification of Cement grade Run of Mine Limestone;

Oxide

Components

Acceptable range for

manufacture of OPC

Grade 33, 43 & 53

%

Limiting value taking in to

consideration other types of

cements, scope of beneficiation

and blending

%

Grade of

Rohera

Watera

Limestone

%

CaO 44-52 40 (Min) 45.18

MgO 3.5 (Max) 5.0 1.45

SiO2 To satisfy LSF, Silica Modulus & Alumina Modulus

- 12.65

Al2O3 -

Fe2O3 -

TiO2 <0.5 <1.0 Not analysed

Mn2O3 <0.5 <1.0 ,,

R2O(Na2O+K2O) <0.6 <1.0 ,,

Total S as SO3 <0.6 <0.8 ,,

P2O5 <0.6 <1.0 ,,

Cl <0.015 <0.05 ,,

Free Silica <8.0 <10.0 ,,

OPENCAST MINING

The limestone deposit is exposed right on surface with very little overburden of weathered limestone. The proposed method of mining will be fully mechanised opencast method of mining with the use of HEMM. It is proposed to mine with benches of 7 m height and width of benches about 20-30 m. Blast holes of 150 mm dia. are proposed to be drilled by using DTH wagon drill machine and blasting with ANFO with Booster charge. Loading of blasted material is proposed with 2.1 cu.m. bucket capacity excavator in dumpers of 40 tonne capacity and transported to crusher for sizing. Following are the mining parameters:

S.No. Particulars Details

1 Method of Mining Fully mechanised opencast method using HEMM

2 Bench Height 7 m

3 Bench width 20-30 m

4 Slope of Bench 800

5 Hole Dia. 150 m

6 Hole burden 4 m

7 Hole Spacing 6 m

8 Sub-grade drilling 7%

9 Hole Depth 7.5 m

10 Powder Factor 6.0 t/kg

11 Excavator capacity 2.1 m3

12 Dumper capacity 40 t

13 Road Gradient 1:16

14 Stripping Ratio (t: cu.m.) 1:0.022 Waste in the form of interburden.

15 No. of working days per year 300

16 No. of shifts per day 2

17 Ultimate pit slope 450

Provisions of MMR 1961 will be strictly be adhered. Lessee will obtain necessary permission from DGMS for use of HEMM.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 11

Yearwise tentative excavation in cu.m. indicating development, ROM, pit wise

I. Insitu Tentative Excavation:

Year Pit

No.

Total

tentative

Excavation

in cu.m.

Top

Soil

in

cu.m.

OB/ SB

/ IB

in

cu.m.

ROM cu.m. Mineral

Reject

ROM /

waste

Ratio Ore

Ratio

cu.m.

Mineral

Reject

cu.m.

Waste Limestone Cu.m:

1st 1 128012 Nil 6400 121612 Nil Nil 1:0.02

2nd

1 192002 Nil 9600 182402 Nil Nil 1:0.02

3rd

1 256074 Nil 12804 243270 Nil Nil 1:0.02

4th 1&2 320693 Nil 16035 304658 Nil Nil 1:0.02

5th 1&2 523289 Nil 26164 497125 Nil Nil 1:0.02

Total 1420070 Nil 71003 1349067 Nil Nil 1:0.02

Dump Re-handling: No old dump exists in the area. It is a new applied area.

Brief description of salient features of the proposed method of working: The limestone deposit lies on surface with no overburden. There is no top soil cover over the proposed area of mining for next five years. Deposit is having strike in N-S to N30°E-S30°W direction with 10

0 to 15

0 dip in either

direction. It is proposed to work the deposit by fully mechanised method of mining using drills, excavator and dumper combination. The mine is proposed to produce 1.25 MTPA of ROM when fully developed. This production rate is planned to be achieved in the fifth year of plan period. Following broad design parameters have been considered.

Bench height is proposed to be at 7.0 m. Minimum bench width will be 20-30 m. Individual bench slope will be 80

0 from vertical.

Rock Breaker will be used for secondary breaking. Excavator with bucket capacity 2.1cu.m. will be used for loading of mineral For mineral 20 / 30 t capacity dumpers / tippers will be used. Haul roads will be maintained at minimum gradient of 1:16. Limestone after loading in to dumpers is taken to crusher for sizing. Water sprinkler will be used for dust suppression in the mine. Mine lies in close proximity to habitation and hence all necessary precautions related to blasting

will be taken

Brief description of layout of mine workings, pit road layout of faces and sites for disposal of

overburden / waste along with ground preparation prior to disposal of waste : Mine is planned to be worked by mechanised opencast method of mining. The lease area is in close proximity to village hutments and one seasonal nalla runs through the area. Following preparatory works are proposed to be completed before commencement of mining operations in the area.

Diversion of Nalla; Seasonal nallas entering the ML area needs to be diverted before commencement of mining/ waste dump creation. The diverted nallas will run in the statutory barrier along pillars B-A and join the original seasonal nalla between pillar B & A. The total nalla diversion length will be about 242 m. Final position will be clear during the hydro-geological study of the ML area / core zone.

Statutory barriers: 7.5 m wide statutory barrier along the lease boundary and 300 m radius safety zone around temple will be maintained. No mining is proposed within these zones.

Disposal of waste: There is no overburden but waste will be generated from inter-bands of phyllites & schist. Estimated quantity of waste will be around 05% of ROM. This waste is proposed to be dumped in the SW corner of the lease area. Dump will be of 10 m height and

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 12

spread over 0.88 ha. area by the end of plan period. Any incidental top soil generated will be removed separately and simultaneously used for plantation. If required it will be stacked temporarily. Soil stack will be protected by bund all around.

FIRST YEAR For mine planning the area is divided into two Blocks i.e. I & II. Initially it is proposed to develop Block I and from third year onwards Block II will also be opened. Mining in five year plan period is proposed within proved and probable reserves area. Mining in first year is proposed in pit no. 1 in Block No. I. Two benches at 292.0 & 285.0 mRL are proposed to be opened. Existing approach road to the area will be used. There is no top soil cover over the proposed area of mining. Any top soil encountered in the crevices will be used for plantation. During the year 128,012 cu.m. of ROM is proposed to be excavated. Details of area of mining are given in table below. About 05% of ROM is likely to be generated as waste due to intercalated beds of phyllites and schist. This waste will be dumped over the proposed area of waste dump in south-west corner of the lease area. During the year about 2.24 ha. will be degraded by way of pits and approach roads. Bench wise, pit wise excavation details are given below:

First Year

Pit

no.

Bench

mRL

Area

in

Sq.m.

Depth

in m

Volume

in cu.m.

ROM

Tonnes

Limestone

Tonnes

Remark Mining

area co-

ordinates

1 292.0 15942 4.5 71739 179347 170380 BH 1B & 2B

137N to 496N & 20W to 182E

285.0 8039 7.0 56273 140682 133648

128012 320029 304028

SECOND YEAR: Mining in the second year will continue on 285.0mRL bench and another bench at 278.0 mRL will be opened. During the year 192002 cu.m. of ROM is proposed to be excavated. During the year about 1.785 ha surface area will be degraded by way of pits. Bench wise, pit wise excavation details are given below:

Second Year

Pit

no.

Bench

mRL

Area

in

Sq.m.

Depth

in m

Volume

in cu.m.

ROM

Tonnes

Limestone

Tonnes

Remark Mining

area co-

ordinates

1 282.0 22936 5.0 114680 286700 272365 BH 1B & 2B

102N to 532N & 27W to 173E

278.0 11046 7.0 77322 193305 183639

192002 480005 456004

THIRD YEAR Mining in the third year will continue on 285.0 & 278 mRL bench and another bench at 271.0 mRL will be opened. During the year 256074 cu.m. of ROM is proposed to be excavated. During the year about 0.97 ha. will be degraded by way of pits. Bench wise, pit wise excavation details are given below:

Third Year

Pit

no.

Bench

mRL

Area

in

Sq.m.

Depth

in m

Volume

in cu.m.

ROM

Tonnes

Limestone

Tonnes

Remark Mining

area co-

ordinates

1 285.0 2688 4.0 10752 26880 25536 BH 1B & 2B

252N to 637N & 53W to 169E

278.0 19953 7.0 139671 349177 331718

271.0 5093 7.0 105651 264128 250921

256074 640185 608175

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 13

FOURTH YEAR Mining in the fourth year will continue on 278.0 & 271.0 mRL bench in Block I. New bench at 292.0 & 285.0 mRL will be opened in Block No. II. During the year 320693 cu.m. of ROM is proposed to be excavated. During the year about 3.904 ha. will be degraded by way of pits. Bench wise, pit wise excavation details are given below:

Fourth Year

Pit no.

Bench mRL

Area in Sq.m.

Depth in m

Volume in cu.m.

ROM Tonnes

Limestone Tonnes

Remark Mining area co-ordinates

1 278.0 9845 5.5 54148 135368 128600 BH 1B & 2B

86N to 656N & 61W to 155E

271.0 14652 7.0 102564 256410 243590

2 292.0 8013 5.5 44071 110178 104669 BH 6 1095N to 1278N & 283W to 438E

285.0 17130 7.0 119910 299775 284786

320693 801731 761645

FIFTH YEAR Mining in the fifth year will continue on 278.0 & 271.0 mRL bench in Block I and new bwench at 264.0 mRL will be opened. In Block II mining will continue on 292.0 & 285.0 mRL and a new bench at 278.0 mRL will be opened up. During the year 523289 cu.m. of ROM is proposed to be excavated. During the year about 3.02 ha. will be degraded by way of pits. Bench wise, pit wise excavation details are given below:

Fifth Year

Pit no.

Bench mRL

Area in Sq.m.

Depth in m

Volume in cu.m.

ROM Tonnes

Limestone Tonnes

Remark Mining area co-ordinates

1

278.0 9539 5.0 47695 119238 113276 BH 1B & 2B

154N to 444N & 147W to 132E

271.0 8270 7.0 57890 144725 137489

264.0 22184 7.0 155288 388220 368809

2 292.0 7518 4.5 33831 84577 80348 BH 6 1080N to 1312N & 221E to 472E

285.0 9020 7.0 63140 157850 149957

278.0 23635 7.0 165445 413612 392932

Total 523289 1308222 1242811

Year wise Land Degradation in ha. :

Year Area degraded at the beginning

Additional surface area during the year

Area at the end of year

First 0.558 2.24 2.798

Second 2.798 1.785 4.583

Third 4.583 0.97 5.553

Fourth 5.553 3.904 9.457

Fifth 9.457 3.02 12.477

System of Drilling & Blasting;

a) Broad Blasting Parameters:

Mineral / OB ( Max) per day 4300 t

Volume of Rock to be blasted (in-situ) 1720 cu.m.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 14

Height of bench 7.0 m

Depth of hole including sub grade drilling 7.5 m

Burden 4.0 m

Spacing 6.0 m

Sub Grade Drilling 7%

Inclination of Holes from vertical 800

Volume blasted per hole (7 x 4 x 6 = 168) 168 cu.m.

Tonnes blasted per hole (168 x 2.5) In ore 420 t

Powder Factor t / kg of explosive 6

Explosive per hole 70 kg

Booster Charge 05% 3.5 kg / hole

ANFO @ 90% / SMS Emulking -100 66.5 kg/ hole

Holes will be drilled at an inclination of 10

0 from vertical and 7% sub grade drilling to avoid formation of

toe at the bottom of the bench. Holes will be in staggered pattern in the subsequent rows.

b) Types of Explosive to be used: For the booster charge, any cap-sensitive explosive and for column charge, any non cap-sensitive explosive, mainly ANFO/ SMS Emulking – 100 would be used. The ratio of booster charge to column charge would be 05:95.

c) Powder Factor Assumed Powder factor is 6.0 tons / kg.

d) Secondary Blasting Hydraulic Rock Breaker will be used in place of secondary blasting.

e) Storage of Explosives JKLCL is having explosive magazines at its Basantgarh mine and same magazine will be used for this mine also. No separate magazine is proposed for this mine.

f) Precautionary Measures: As the mining area is in close proximity to human settlements, adequate precautionary measures will be taken as given below: Adequate siren system will be in operation. Legible warning sign in the language understood by the local people. Enough security guards, especially posted on roads etc. Before blasting the upper surface of the bench shall be cleaned off, of any stones lying on top, as it

is a major source of flying stones. The trunk line of the detonating cord shall be covered with sand to reduce air over pressure, as it is

major source of air blast noise. Controlled blasting shall be practiced and only during day time. All safety measures as prescribed under MMR 1961 and circulars issued by DGMS. The danger zone shall be distinctly demarcated (by means of red flags properly arranged and

supported) at least 30 minutes before firing of holes is to commence. Ten minutes before firing, a siren installed for the purpose shall be blown three times for one minute

each at interval of one minute. An effective record of instruction to guards given for working and clearance shall be maintained. No shots shall be fired when there is traffic on any road within danger zone.

Extent of Mechanisation: M/s J K Lakshmi Cement Limited is operating a cement plant and a mine at Basantgarh about 25 km from this area. To reduce the spares inventory, mobility of equipment and efficient utilisation of trained manpower, it is proposed to use the same type of equipment at this mine also.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 15

Following design parameters are used for calculation of equipment requirement:

Parameters Limestone in tonnes

ROM in tonnes per year ( Maxm in 5

th Year) 13,00,000 t

No. of Working Days per year 302

Tonnes per day 4,300 t

Bulk Density limestone t/cu.m. 2.5

Volume of rock ( In-situ) 1,720 cu.m.

No. of Shifts per day (Excavation & Maintenance) 2 + 1

Working Hours per shift 6.0

Tonnes per hour 4300/12 =358

In-situ Volume per shift in cu.m 860

In-situ Volume per hr. in cu.m. 144

Drill Machine Requirement; 2 Nos.

Drill machine proposed to be used IBH- 10

Hole dia. 150 mm

Bench Height 7.0 m

Hole burden 4.0 m

Hole spacing 6.0 m

Inclination of Hole from vertical 100

Sub Grade drilling 7%

Volume blocked per hole 4.0 x 6.0 x 7.0 = 168

Tonnes per hole 168 x 2.50= 420t

Tonnes to be blasted per day 4,300 t

No. of holes to be blasted per day 4300/420 = 10.2holes =11

Length of hole including Sub grade drilling @ 7% 7.5 m

Total drilling meters per day 12 x 7.5 = 90 m

Drilling rate per hour 10 m

Meters per shift = 11 x 6.5hrs. 10 x 6.0 m = 60 m

Meters per day = 60x 2 = 120 m 120 m

No. of machines required 90/120= 0.375 0.75

Actual requirement @ 80 % Availability 0.94

Stand by machine 1

Total requirement 2

Excavator – Komatsu PC 300 / PC 200 Limestone

Production per day 4,300 t

Production per day ( Limestone ) 4080 t

Waste handling per day 215 t

Bucket capacity (Stuck) in cu.m. PC 300 2.1

Bucket Capacity (Stuck) in cu.m. PC 200 0.9

Loading Capacity in TPH PC 300 230

Loading Capacity in TPH PC 200 120

Excavator (PC 300) required for limestone from face 4080/12/230 = 1.47 1.47

Excavator (PC 200) required for waste handling from face 215/12/120=0.15

0.15 = 1

Excavator (PC300) required for limestone handling after crushing = 1 1

Excavators required PC 300 3

Excavator required PC 200 1

Total Excavators required 4

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 16

Tipper capacity (Leyland 2523) 20 tons (12.0 m3)

Fill factor 0.9

Tipper Capacity in tonnes 20

Tipper Capacity in cu.m. 12

No. of passes required to fill the tipper 6

Spotting ( in minute ) 1

Loading time (minute) @ 30 sec/load 3

Average speed in kmph 30

Distance in km to Plant 2.5 km

Hauling time in minute 10

Unloading time in minute 1

Cycle time in minute 15

Nos. of trips per hour (N) 60/15 =4

Handling per / hr. = NxT, 4x20 = 80 t

Working hours available/Shift 6.0 hours

Average handling per tipper per shift 80 x 6.0 =480

Average handling per day 480x2 = 960

Tippers Required 4300/960 = 4.5

Availability 80%

Tippers Required 5.6 (Say 6)

Total required 6

Dumper Requirement

TPH /Excavator 230

Trips / hr / dumper 4.0

Tonnes / hr / dumper 80

Dumper required to match excavator loading capacity 230/80 = 2.8

Availibility 80% (2.8/0.80 = 3.5) 3.5

Excavator requirement 2 unit

Dumper required 2 x 3.5= 7 7

Total required 7

Two excavators of 2.1 m

3 cu.m. bucket capacity 7 dumper of 20 tons capacity will be required for

limestone loading. Two dumpers will be required for waste handling. Other equipment i.e. rock breaker (one), water sprinkler (one), Dozer (one), etc. will be provided. Summary of HEMM requirement year wise is given in table below:

Equipment Make Model Capacity / Output HP/kw

1st

yr 5th

yr

Excavator Komatsu PC 300 LC 2.1 m3 / 230TPH 242 / 182 kw 1 3

Excavator Komatsu PC 210 LC 0.9 m3 / 120 TPH 155 / 116 kw 1 1

Dumpers Leyland 2523 20 tonnes / 16 m3 225 4 7

Rock Breaker Komatsu PC 200 - 155 / 116 kw 1 1

Rock Drill Atlas Copco IBH - 10 115-165 mm dia. 1 1

Rock Drill Atlas Copco ICM - 341 115-140 mm dia. 1 1

Loader CASE 921 F 242 /180kw 1 1

Water Sprinkler Tata 20 KL 1 1

Dozer BEML BD-40 Blade 4260mm (L) x 1080 mm (H)

180 134 kW

1 1

ANFO Mixing & Loading Machine

1 1

Pick Up Van Mahindra Bolero DI 10 Seater 63 / 46.5kW 1 1

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 17

Maintenance Mobile Van

Tata Equipped as per requirement

1 1

Tyre handler 85 1 1

Road Grader BEML 1 1

Explosive Van Tata 1 1

Diesel Browser Tata 1 1

CONCEPTUAL MINING PLAN Basic and long term mine design parameters are as follows:

i. Mining will be carried out by conventional method of mining by using drills, excavator and dumpers.

ii. Height of benches will be 7 m and width of benches 20-25 m.

iii. 150 mm dia. holes will be drilled & blasted using ANFO and slurry explosive.

iv. Loading is proposed by Excavator of 2.1 cu.m. bucket capacity and loaded in to 30/20 t capacity dumpers.

v. Mine is planned to produce 1.3 MTPA of limestone per year when fully developed and at this rate life of mine is estimated to be 22 years.

Ultimate Pit Limit : The limestone mineralisation is proved up to 250 mRL and ultimate pit depth is planned up to this depth only. Ultimate pit limit is designed keeping in view the statutory barriers. The pits are designed with 7.5 statutory barrier along lease boundary and 300 m safety zone around temple etc. The ultimate pit slope will be 45

0. The mine life and conceptual limits are based on present mineable reserves. In future with

proposed exploration mineral resources / reserves are likely to change and this will result in change of conceptual plan. In the end two pits will be formed and their dimensions will be as follows:

Pit Number Length, in m Width, in m Depth, in m Area, in Ha. Pit bottom, mRL

1 1352 319 44 22.84 250mRL

2 222 270 46 4.931 250mRL

Total 27.771

Post Mining Land Use: The mined out pits will be fenced all around as per DGMS circular at the end of mine life. The pits will be used for rainwater storage. In all the two pits, at places suitable ramps will be provided for access to cattle.

Anticipated Landuse Of The Ml Area (73.7421 Ha.)

Particulars Present At the end of Mining Plan Period

At the end of life of mine

Pit/Quarries 0.558 11.500 27.771

Waste Dump 0.000 0.880 4.000

Mineral Stack 0.000 0.000 0.000

Tar Road 0.000 0.000 0.000

Infrastructure 0.000 0.200 0.200

Temple 0.007 0.007 0.007

Plantation 0.000 3.000 4.970

Katcha Road 0.775 1.150 1.200

Ag Land (Pvt) 10.720 10.720 0.000

Remaining Land 61.6821 46.2851 35.5941

Total 73.7421 73.7421 73.7421

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 18

By the end of life of mine 27.771 ha will be degraded as pit out of which plantation will be done over upper two mined out benches, covering an area of 4.870 ha. Remaining pit area of 22.901 ha will be used for rain water storage. This rain water will help in recharging of ground water and for use by local villagers and cattle. In each pit suitable ramps will be provided for access. All around the water filled pits, stone wall will be constructed.

Schedule of Plantation in ha. (Stage Wise)

Stage Along lease boundary

Along road

Over Waste dump

Mined out benches

Total

Present 0.000 0.000 0.000 0.000 0.000

At the end of plan period

3.000 0.000 0.000 0.000 3.000

At the end of life of mine

4.970 0.000 10.720 4.870 20.560

Ground Water The sources of potable water are the tube wells and dug wells in the area. Depth of Water Level is given below:

Village Pre Monsoon Post Monsoon

Min Max Min Max

Rohera - Watera 10 20 5 10

In general DTW varies from 10 to 20m pre monsoon and 5 to 10 m post monsoon. Seasonal fluctuation is in the range of 5 to 15 m. Seasonal fluctuation for Pindwara Block is (Rise) is in the range of 3.50 m to 22.28 m. Decadal trend in Pindwara block is fall of 0.21 m/year pre-monsoon and rise of 0.14 m/year post monsoon.

Maximum and Minimum Depth of Workings

Year Maximum depth of workings in mRL Minimum depth of workings in mRL

I 285.0 292.0

II 278.0 285.0

III 271.0 285.0

IV 271.0 292.0

V 264.0 292.0

Quantity and Quality of water likely to be encountered, the pumping arrangements and places

where the mine water is finally proposed to be discharged: No mine water is proposed to be discharged outside lease area. Mine water from direct precipitation will be used for water sprinkling and plantation. Water qualities will be monitored regularly. Accumulated rain water will be pumped using diesel engine operated pump to a water tank and used. Shallow ground water of dug well is alkaline in nature with pH ranging from 7.5 to 7.98. The sp. Conductance is within 4500 mmhos/cm at 25

0C but higher values are recorded in very small pockets.

The chloride content varies from 21 ppm to 2978 ppm. The concentration of bi-carbonate varies from 183 ppm to 830 ppm. The fluoride content is generally within 1.5 mg/lit in major part of the district. The concentration of nitrates ranges from 0.16 ppm to 146 ppm. The ground water is moderately hard to very hard in major part of the district.

Regional and Local drainage pattern indicating annual rainfall, catchments area and likely

quantity rain water to flow through the lease area, arrangement for arresting solid wash off etc.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 19

The area is mostly hilly with long and high hills. The hillocks are isolated & scattered in continuous long belt. Cultivated fields are scattered on either side of limestone belt. The drainage is formed by small seasonal nalas flows along the hills which meet to big seasonal nallas flowing E-W cutting across the hills. These seasonal nallas then merge into the Sukli river flowing in this area. The long term average rainfall is 591.1 mm.

Arrangement for arresting solid wash off: Retention wall with garland drain are proposed to be built around waste / rejects dump. Retention walls are built at sufficient distance away. The purpose of retention wall is to arrest silt and rolling material. A drain parallel to retention wall will be made between the dump and retention wall which will act as a dissipater against boulders directly hitting the retention wall and collection of wash off from dump. The face of the retention wall away from the dump filled with vegetative soil and plantation done. This would take care of retention wall weakening over a period of time.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 20

3. Site Analysis (i) Connectivity:

Nearest National Highway

7.6 km. From Rohera to Swaroopganj on NH 14/NH 927A, between Pindwara & Abu Road.

Nearest Railway Station

7 km Swroopganj Railway station on Ahmedabad – Delhi Route.

Nearest Airport 130 km. Udaipur (Dabok) Airport, via NH 14/ NH 76/NH8

Nearest Town Rohera at 1 km.

Nearest major city Swaroopganj ( District Sirohi, Rajasthan) at 7.6 km.

(ii) Land Form, Land use and Land Ownership

Ownership / Type of Land Area in ha.

Govt. Waste Land 55.5

Private Agriculture Land 18.24

73.7421

(iii) Topography (along with map): Map in Annexure 3 The area is mostly hilly with high and long hills. The hillocks are isolated & scattered in a continuous long belt. Cultivated field are scattered on either side of the limestone belt. The drainage is formed by small seasonal nalas which flows along the hills and meet into big seasonal nalas flowing E-W cutting across the hills. These seasonal nalas then merge into the Sukli river flowing in this area. In general DTW varies from 10 to 20m pre monsoon and 5 to 10 m post monsoon. Seasonal fluctuation is in the range of 5 to 15 m. A considerable portion of the area is covered with trees and bush jungle. In this area near villages trees such Neem (Asadirachits Indica), Pipal (Ficus Religies) and Bar ( F. bengalansis) are common. The bush jungle varies according to the nature of the ground. The Khair ( Acacia catechu ) Dhok (Anogeissus) are the commonest on the rocky ground, on sandy and alluvial area Awal (cassia auriculeta), Akra (Calatropiorocera), Dhak (Butea frondasa) and fauna is varied but not plentiful. In jungle rabbits are common. The animals is in this area are cows, buffaloes, dogs, hens & camel etc. The area is mostly dry with mild climate. The average rainfall in this area is only about 591 cm. per annum, nearly all of which falls during the short rainy season from July to September.

(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including

area under CRZ)), shortest distances from the periphery fo the project to periphery of

the forests, national park, wild life sanctuary, eco sensitive areas, water bodies

(distance from the HFL of the river), CRZ. In case of notified industrial area, a copy of

the Gazette notification should be given):

Ownership / Type of Land Area in ha.

Govt. Waste Land 55.5

Private Agriculture Land 18.24

73.7421

There are agricultural lands within the applied lease area. The main crops grown are Castor, Maize, Wheat, Mustard & Chickpea. It does not form a part of any reserve forest, national park, wild life sanctuary or natural / biosphere reserves. Crop productivity in the district is given in table below:

Crop Productivity

(kg/ha)

Castor 1988

Maize 1902

Wheat 2700

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 21

Mustard 1250

Chickpea 1000

Horticulture crops 100

Tomato 40000

Vegetables 17500

(v) Existing Infrastructure: JKLCL is operating a cement plant and a mine at Basantgarh at a distance of about 25 km. Various facilities are already in operation at cement plant and running mine and the same will be used for this mine also. However, the following facilities will be provided for this mine separately.

Mine Office; Mine office complex will have Manager’s office, time office, engineers’ office, Mine planning and quality control cell, stores etc.

First Aid Station; A fully equipped first aid station will be established and maintained as per Mines Rules 1955.

Canteen cum rest shelter: As per Mines Rules 1955.

Drinking water

Ablution Block; Urinals & lavatories will be provided at the mine office, rest shelter.

Vocational Training Centre: Company will establish and operate a group Vocational Training centre for its mine and plant.

Residential facilities: Residential facilities will be provided in the company’s established colony.

Portable Blasting Shelters: Portable blasting shelters will be provided as per the requirement.

(vi) Soil Classification:

The mining lease area is hilly without any top soil in most places. Soil is found only along the curves and depressions. The soil is sandy to sandy loam.

(vii) Climatic Data from secondary sources: The climate of the district is quite dry and parched. The summer season extends from April to June and is quite hot. The highest temperature in summer reaches to 38

0C and the lowest in winter goes down to

50C. The highest temperature in year ranges from 19

0C to 38

0C and lowest ranges between. 19

0C to

380C . The monsoon season falls during the months of June to August. The average rainfall is 591 mm.

Highest rainfall is observed in July with 276 mm of precipitation with 24 rainy days.

(viii) Social Infrastructure available:

A very structured social infrastructure has been already developed in and around mine site which comprises of villages, schools, markets, temples, state highway, Bank, Hospitals, etc.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 22

4. Planning Brief

(i) Planning Concept (types of industries, facilities, transportation etc) Town and

Country planning/Development authority Classification:

There is no industry in the 10 km area. Nearest cement plant is located at Basantgarh.

(ii) Population Projection:

The study area covers total 09 villages. There are 6033 human settlement in study area having a total population of 30792. The total break-up of household, population and literacy is given in Table below:

Human Settlements around the ML Area

Public buildings, places of worship and monuments: A temple is located just outside lease area on eastern side. No others places or structures of historical importance exist on the area or in its immediate neighbourhood.

(iii) Land use planning (breakup along with green belt etc):

Particulars Present in ha At the end of Mining Plan Period in ha

At the end of life of mine in Ha

Pit/Quarries 0.558 11.500 27.771

Waste Dump 0.000 0.880 4.000

Mineral Stack 0.000 0.000 0.000

Tar Road 0.000 0.000 0.000

Infrastructure 0.000 0.200 0.200

Temple 0.007 0.007 0.007

Plantation 0.000 3.000 4.970

Katcha Road 0.775 1.150 1.200

Ag Land (Pvt) 10.720 10.720 0.000

Remaining Land 61.6821 46.2851 35.5941

Total 73.7421 73.7421 73.7421

Sr.

No.

Name Of

Villages

Details Of Population Total -ST Literacy Direction

Distance

In

[Km.] NOHH T-P T-m T-F T-ST T-M T-F T-LIT T-M T-F

1 Watera 1174 6205 3205 3000 2083 1052 1031 2492 1665 827 SOUTH

EAST

2.41

2 Rohera 1532 7661 3999 3662 816 435 381 4328 2767 1561 EAST 1.69

3 Wasa 972 4845 2477 2368 1571 772 799 2154 1405 749 EAST 3.32

4 Naya

Sanwara

845 4191 2205 1986 33 19 14 5 4 1 SOUTH 4.72

5 Pipela 324 1822 944 878 1389 711 678 347 271 76

6 Sanwada 337 1581 812 769 172 97 75 829 516 313 SOUTH

EAST

3.42

7 Mandwara 283 1536 765 771 903 432 471 486 323 163 EAST 2.95

8 PeetariPadar 309 1634 809 825 1633 809 824 436 309 127 EAST 4.56

9 Udvariya 257 1317 681 636 367 180 187 537 375 162 WEST 4.25

Total 6033 30792 15897 14895 8967 4507 4460 11614 7635 3979

% 19.59 100 51.62 48.37 29.12 14.63 14.48 37.71 65.73 34.26

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 23

By the end of life of mine 27.771 ha will be degraded as pit out of which plantation will be done over upper two mined out benches, covering an area of 4.870 ha. Remaining pit area of 22.901 ha will be used for rain water storage. This rain water will help in recharging of ground water and for use by local villagers and cattle. In each pit suitable ramps will be provided for access. All around the water filled pits, stone wall will be constructed.

During next five year plan period about 3.0 ha. will be developed as green belt, 0.88 ha. as waste dump and 11.500 ha. area as pit. About 3.000 ha. is proposed to be developed as green belt along the lease boundary during next five year plan period. In addition a nalla diversion will be there over a length of 242.0 m. At the end of life of mine two pits of size 1352 x 319 x 44 m and 222 x 270 x 46 m will be formed. The bottommost bench will at 250 mRL. Plantation will be done over a total area of 20.560 ha. out of which 4.970 will be as green belt along lease boundary, 4.870 ha. over mined out benches and 10.720 ha. over waste dump. Remaining area of pit about 22.901 ha. will be developed as rain water storage facility. Waste dump will be properly stabilised and plantation done over the dumps.

Progressive Reclamation Plan: Land degradation is one of the major adverse impact of opencast & other miscellaneous activities related to mining and any effort to control adverse impacts would be incomplete without appropriate land reclamation strategy. No mined out land shall achieve the final position during the mining scheme period, However, at the end of scheme period (projected) total 11.50 ha. area will be covered under mining and at the end of life of mine will be 27.771 ha. At the end of mining Plan period about 3.0 hect. area will be covered by green belt. Barbed wire fencing will be made around the proposed area of plantation and around mined out area for safety purpose and also plantation will be done.

Activity 1st Year 2

nd Year 3

rd year 4

th year 5

th year

Plantation area in ha. 0.6 0.6 0.6 0.6 0.6

Plantation (Nos) 600 600 600 600 600

Wire fencing (In Meter) 343 225 225 225 225

(iv) Assessment of infrastructure demand (Physical as well as social):

Adequate physical and social infrastructure is available near mine site.

(v) Amenities / Facilities:

Adequate physical and social infrastructure is available near mine site.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 24

5. Proposed Infrastructure

(i) Industrial Area (Processing Area):

Infrastructure for catering mining activity will be developed at the time of commencement of project

(ii) Residential Area (Non Processing area):

Colony for all employees of JKLCL is already in place and the employees working in mine will reside in the existing colony.

(iii) Green Belt:

By the end of life of mine 27.771 ha will be degraded as pit out of which plantation will be done over upper two mined out benches, covering an area of 4.870 ha.

(iv) Social Infrastructure:

Social infrastructure is already available in villages around mine site which comprises of schools, markets, temples, state highway, community centers, hospitals, etc. Company has plan to maintain and improve this infrastructure under CSR initiatives.

(v) Connectivity(Traffic and Transportation Road/ Rail/Metro/ water ways etc): The mine is connected by road to National Highway

(vi) Drinking Water Management (Source and supply of water):

No mineral processing is proposed within lease area. A total of 30 KLD of water will be required. Water for drinking will be brought from well. Mine pit water will be used for spraying and plantation.

Particulars Quantity in KLD

Dust suppression 10

Green Belt * 10

Drinking & Sanitation 5

Mine Workshop 5

Total 30

For drinking and sanitation, fresh water will be used and for other activities mine water and recycled water will be used. Water discharged from workshop will be used for plantation. Fresh water will be sourced from dug well and bore wells in the area. The water table is about 7 to 9 m from surface. Shallow ground water of dug well is alkaline in nature with pH rangining from 7.5 to 7.98. The sp. Conductance is within 4500 mmhos/cm at 25

0C but higher

values are recorded in very small pockets. The chloride content varies from 21 ppm to 2978ppm. The concentration of bi-carbonate varies from 183 ppm to 830 ppm. The fluoride content is generally within 1.5 mg/lit in major part of the district. The concentration of nitrates ranges from 0.16 ppm to 146 ppm. The ground water is moderately hard to very hard in major part of the district.

(vii) Sewerage System:

At mine site, there is no such sewerage system developed and maintained shall be developed later on.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 25

(viii) Industrial Waste Management:

No industrial waste will be generated from mining activity.

(ix) Solid waste Management:

Waste Dump Management: There is no overburden; however there are intercalations of phyllites and schist within the limestone. Waste generation will from intercalated waste bands. The estimated quantity is about 05% of ROM from interbands. Year wise waste generation for five year period is given in table below:

Inter burden

Year IB in cu.m. Swelled volume In Cu.m.

A B=Ax1.25

1st 6400 8000

2nd

9600 12000

3rd

12804 16005

4th 16035 20044

5th 26164 32705

Total 71003 88754

This waste is proposed to dumped in the South – Western part of the lease area along the boundary. No top soil cover exists over proposed area of mining. Any top soil encountered in crevices will carefully removed and used for green belt development. Top soil cover exists in the SW and NE of the area. Soil is sandy & clay loamy. There is no proposal of mining in these areas. Waste will from inter-bands of phyllites and schist. All limestone mined will be used in cement plant. Year wise generation of waste is given in table below:

Year Top soil

(cu.m.)

Waste in cu.m. Mineral Reject (cu.m.)

Reuse/

spreading

Storage Storage Back

filling

Storage Blending Beneficiation

First Nil Nil 6400 Nil Nil Nil Nil

Second Nil Nil 9600 Nil Nil Nil Nil

Third Nil Nil 12804 Nil Nil Nil Nil

Fourth Nil Nil 16035 Nil Nil Nil Nil

Fifth Nil Nil 26164 Nil Nil Nil Nil

71003

Location of proposed dumping ground: Dumps are proposed to be located in the area in SW and NE corner of the lease area.

Manner of disposal of waste, configuration and sequence of year wise build up of dumps along

with protective measures: During the first five year of Mining Plan period waste will be generated from the inter-bands of phyllites & schist. The waste will be dumped over in SW and NE corner of the lease area. The total area covered by waste dump will be 0.88 ha. by the end of plan periods and 4.0 ha. area by the end of life of mine. Dump will have two terraces of 10 m height each. On maturity dumps will be stabilised by adopting following measures.

Protective Measures: Waste dump at the conceptual stage will have four terraces. Following protective and stabilisation measures are proposed to prevent rolling of rocks and wash off entering into drainage system of the area:

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 26

Final slope of the dump will be divided into terraces with berms in between.

Retention walls: Retention walls are built at sufficient distance away. The purpose of retention wall is to arrest silt and rolling material. A drain parallel to retention wall will be made between the dump and retention wall which will act as a dissipater against boulders directly hitting the retention wall and collection of wash off from dump. The face of the retention wall away from the dump filled with vegetative soil and plantation done. This would take care of retention wall weakening over a period of time.

Each terrace will be provided with Gabion toe wall with multching to promote vegetation.

Coir Matting: Once the part of the dump is matured, the dump slope shall be covered with coir matting and secured with U pins. The coir matting has an advantage of absorbing water and keeping the soil damp. Once the natural vegetation takes over the mat decomposes gradually and disintegrates.

Plantation; Seedlings grown with root trainer will be planted on the slope and floor of the terrace at a spacing of 3 x 3 m. staggered pattern. In between the plants Vetiver or Hemata grass will be grown which has good soil binding characteristics.

At the final stage contour ripping will be done on top of the dump to prevent formation of gullies along the slope of the dump.

Disposal of Waste and Backfilling : During the first five year of Mining Plan period waste will be generated from the inter-bands of phyllites & schist. The waste will be dumped in SW and NE corner of the lease area. The total area covered by waste dump will be 0.88 ha. by the end of plan period and 4.0 ha. area by the end of life of mine. Dump will have two terraces of 10 m height each. On maturity dumps will be stabilised by adopting following measures.

Protective Measures: Waste dump at the conceptual stage will have four terraces. Following protective and stabilisation measures are proposed to prevent rolling of rocks and wash off entering into drainage system of the area:

Final slope of the dump will be divided into terraces with berms in between.

Retention walls: Retention walls are built at sufficient distance away. The purpose of retention wall is to arrest silt and rolling material. A drain parallel to retention wall will be made between the dump and retention wall which will act as a dissipater against boulders directly hitting the retention wall and collection of wash off from dump. The face of the retention wall away from the dump filled with vegetative soil and plantation done. This would take care of retention wall weakening over a period of time.

Each terrace will be provided with Gabion toe wall with multching to promote vegetation.

Coir Matting: Once the part of the dump is matured, the dump slope shall be covered with coir matting and secured with U pins. The coir matting has an advantage of absorbing water and keeping the soil damp. Once the natural vegetation takes over the mat decomposes gradually and disintegrates.

Plantation; Seedlings grown with root trainer will be planted on the slope and floor of the terrace at a spacing of 3 x 3 m. staggered pattern. In between the plants Vetiver or Hemata grass will be grown which has good soil binding characteristics.

At the final stage contour ripping will be done on top of the dump to prevent formation of gullies along the slope of the dump.

(x) Power requirement supply and source:

Electricity is mostly used for dewatering purpose, in offices and for maintenance of HEMM. Power will be sourced from SEB. As the mine is not under operation, the connected load is NIL but it is planned to consume approx 200000 Units/year.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 27

6. Rehabilitation and Resettlement (R & R) Plan

(i) Policy to be adopted (Central/ State) in respect of the project affected persons

including home oustees, land oustees and landless laborers (a brief outline to be

given):

There will be no person displaced from houses due to this project. Agriculture land owners will be paid financial compensation more than the prevailing market rate. The rate and purchase will be decided based on mutual negotiation.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 28

8. Project Schedule & Cost Estimates

(i) Likely date of start of construction and likely date of completion (time schedule for the

project to be given): As on date, mine is not under operation, the proposed production will be done only after getting all related statutory approvals from govt agencies.

(ii) Estimated project cost along with analysis in terms of economic viability of the project:

Project cost: Rs.170 crores

Financial Assurance is required to be submitted under Rule 23(F) (2) of MCDR 1988 for the area proposed to be put to use by the end of plan period. Financial Assurance has been calculated as per the circular 04/2006 issued by the CCOM, IBM, Nagpur. Details of the calculation for FA are given below. Proposed area to be put to use by the end of SOM period is 17.23 ha.

S. No.

Item Area put on use at start of plan (Ha) (A)

Additional requirement during plan period (Ha) (B)

Total (Ha) C = (A+B)

Area considered as fully reclaimed & rehabilitation (Ha) (D)

Net area considered for calculation (Ha) E = (C-D)

1. Area to be excavated

0.558 10.942 11.500 0 11.500

2. Storage for topsoil 0 0 0 0 0

3. Waste disposal 0 1.650 0.88 0 0.88

4. Mineral storage 0 0 0 0 0

5. Infrastructure (Workshop, Adm. Building, Road)

0.775 0.375 1.150 1.150

6. Rainwater storage 0 0 0 0 0

7. Railways 0 0 0 0 0

8. Green belt 0 3.000 3.000 3.000

9. Tailing dam 0 0 0 0 0

10. Effluent treatment plan

0 0 0 0 0

11. Mineral Separation plant

0 0 0 0 0

12. Township area 0.700 0 0.700 0 0.700

13. Others (Reclaimed

& Rehabilitated )

0 0 0 0 0

Total 2.033 15.967 17.23 0 17.23

Total of 17.23 hect. area will be put to use by the end of plan period. This mine is category ‘A’ mine and hence FA is calculated @ Rs. 25000/ per hectare. FA for an amount of Rs.4,30,750- in the form of BG will be submitted before execution of lease deed.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 29

9. Analysis of Proposals (Final Recommendations)

(i) Financial and social benefits with special emphasis on the benefit to the local people

including tribal population, if any in the area:

Based on the growing demand in the state over the next 10 years, the proximity of the project location to this market is an advantage with utilization of mineral limestone for manufacturing of clinker. The financial viability also shows a good rate of return from the project. Considering the above, JKLCL is planning to go ahead with the project, once it gets all the statutory approvals.

Employment: Preference will be given to locals for employment based on qualification & requirement. Medical facilities: Medical facilities will be provided for employees as well as people of nearby villages by conducting various camps under CSR Initiatives Educational facilities: Basic educational and vocational facilities will be provided for the children of employees as well as nearby villagers. Infrastructure facilities: Roads and facility for sanitation and drinking water will be provided for the villages coming under buffer zone of the project area. Additional: The establishment of project will create other source of income for nearby locals by establishing

micro business, opening shops, hotels, local street vendors, etc.

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 30

ANNEXURE 1 : LOCATION MAP

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 31

ANNEXURE 2 : TOPOSHEET SHOWING SITE AND 10 KM AREA

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 32

ANNEXURE 3: GOOGLE IMAGE OF PROJECT SITE AND SURROUNDINGS

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 33

ANNEXURE 4 : LOI OF MINING LEASE AREA FROM RAJASTHAN GOVT

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 34

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 35

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 36

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 37

ANNEXURE 5 : SURFACE PLAN

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 38

ANNEXURE 6 : GEOLOGICAL PLAN

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 39

ANNEXURE 7 : CONCEPTUAL PLAN

PFR of 1.25 MTPA Rohera Watera Limestone Mine

J K Lakshmi Cement Limited Page 40

ANNEXURE 8 : RECLAMATION PLAN