3. final pfr 2.6environmentclearance.nic.in/writereaddata/online/tor/0_0_06_sep_2… · existing...
TRANSCRIPT
![Page 1: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/1.jpg)
NMDC Limited, 10-3-311/A, Khanij Bhavan, Castle Hills, Masab Tank, Hyderabad -500 028 Tel: 91-040-23538713-21, 23, Fax: 91-040-23538711
PRE-FEASIBILITY
REPORT FOR OBTAINING PRIOR ENVIRONMENTAL CLEARANCE
FOR CONSTRUCTION OF
10 MTPA CAPACITY SCREENING &
BENEFICIATION PLANT – II,
SLIME DISPOSAL PIPE LINES &
13.4MT CAPACITY TAILING DAMS
FOR DIOM & KIOM
AT DONIMALAI, KARNATAKA (In terms of the provisions of EIA notification,2006)
Rev 1, June 2014
NMDC LIMITED
![Page 2: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/2.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPE LINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad
CONTENTS
Chapter Description Page No.
1 Executive summary 1
2 Introduction of the project/ Background information 7
3 Project Description 10
4 Site Analysis 12
5 Planning Brief 14
6 Proposed Infrastructure 15
7 Rehabilitation and Resettlement (R & R) Plan 17
8 Project Schedule & Cost Estimates 18
9 Analysis of proposal (Final Recommendations) 21
ADDITIONAL TECHINICAL DETAILS OF FEASIBILITY REPORT
10 Ore Geology & Reserves 23
11 Plant Design & Layout 27
12 Civil & Structural Works 37
13 Electrical & Controls 44
14 Environmental Measures 52
15 Manpower Planning 56
16 Annexures 58
17 List of Plates 65
![Page 3: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/3.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 1
1. Executive Summary
1.1 General
NMDC Limited is a Public Sector Company under the Ministry of Steel, Government
of India. Primarily engaged in the business of exploring minerals and developing
mines to produce raw materials for the industry, it is also expanding its activities
towards steel making and other value added products. It has been conferred
“NAVARATHNA” status by Government of India. Incorporated in 1958, NMDC has
been actively contributing to the development of the nation for five decades and
grown from, strength to strength during its journey.
NMDC is India’s single largest iron ore producer and exporter, presently producing
about 27 million tons of iron ore per annum from 3 fully mechanised mines viz.,
Bailadila Deposit – 14/11C, Bailadila Deposit – 5, 10/11A (Chhattisgarh State) and
Donimalai Iron Ore Mines (Karnataka State) which are awarded ISO 9001-2000
`certification.
NMDC Limited is presently engaged in iron ore mining at Donimalai with a
production capacity of about 7 million tons per annum. NMDC is also operating
another mine in Kumaraswamy hill range i.e., Kumaraswamy Iron Ore Project,
which has a reserve of about 130 million tons of hematite ore. Construction of
Kumaraswamy Mine facilities for processing 7 MTPA of ROM is already on and
expected to be commissioned by end of 2013. Earlier, it was envisaged to utilize
existing Screening & Beneficiation plant of Donimalai mine for Kumaraswamy mines
also, as iron ore reserves in Donimalai were getting depleted. Subsequently, based
on the exploratory core drilling operations, additional iron ore reserves of 95.5 MT
have been established. The combined production of both the mines is proposed to
be about 14 MTPA.
1.2 Plant Capacity
Existing Screening & Beneficiation Plant of Donimalai was originally constructed to
process 4 MTPA of ore and subsequently many equipment were added and one
more screening line was installed to process up to about 7 MTPA. Existing Plant
cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting
in frequent break-downs which lead to considerable loss in the availability of
equipment and hence production. To sustain production without interruption due
to frequent breakdown of the existing plant, it is proposed to set-up a Screening &
Beneficiation Plant-II, which can handle/treat ore from either Kumaraswamy mine
or Donimalai mine or both the mines. Hence, it is prudent to construct a new
Screening & Beneficiation Plant of installed capacity for processing ore up to 7
MTPA in Phase-1, which will be augmented to 10 MTPA in Phase-2 in future.
Necessary provisions for additional 2 lines will be made in the plant building.
1.3 Proposed Scheme
![Page 4: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/4.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 2
Overall plant layout of the proposed scheme is shown in Plate No. 3 and description
of the proposed Screening & Beneficiation plant-II (Refer Plate No. 4.1 & 4.2) is as
follows:
1.3.1 Screening & Crushing
• The Run of Mine (ROM)[(-) 100mm] of Kumaraswamy mines or Donimalai
mines or both the mines is stored in silos of about 4000 tons (each) storage
capacity. The ore is extracted through apron feeders and fed to double deck
primary screens (with 30mm & 20mm apertures) through belt conveyor.
• The oversize material of primary screens is fed to tertiary crusher to crush (-)
100mm ROM to (-) 30mm. The middle fraction and the under size material of
primary screen are fed to Calibrated Lump Ore (CLO) conveyor and secondary
screens respectively.
• The crushed ore of tertiary crusher is fed to double deck tertiary screen (with
30mm and 6mm apertures), wherein the oversize material (+ 30mm) is re-
circulated to tertiary crusher. The middle fraction of tertiary screen (-) 30 (+)
6mm and under size fraction (- 6mm) of tertiary screen are fed to CLO product
conveyor and fines product conveyor respectively.
• Under size of secondary screen is fed to classifier of wet circuit system.
Suitable gate arrangement is envisaged at the bottom of under size chute of
secondary screen, which diverts material to launder leading to classifier circuit
when operating on wet mode. Under dry mode the gate will be lifted /
opened to divert the material to fines conveyor.
• Conveyor receiving middle fraction [(-) 10 mm (+) 6 mm] of secondary screen
is envisaged with reversible operation to feed the material either to fines
conveyor or CLO conveyor based on the requirement.
1.3.2 Wet Circuit
Classifier overflow is fed to dewatering screen and the underflow to hydro-
cyclones. The overflow of dewatering screen is fed to fines conveyor and the
underflow is fed to cyclones. The cyclones (with separation size of 150 microns)
overflow is diverted to thickener and the underflow to filtrate unit to recover some
fines, which in turn is fed to fines conveyor.
1.4 Technological Facilities
The new Screening & Beneficiation plant shall have the following major facilities
• Feeder to receive ore from Kumaraswamy downhill conveyor
• Tripper conveyor
• Storage silos
• Apron feeders
• Belt conveyors
• Double deck primary screens
![Page 5: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/5.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 3
• Double deck secondary screens
• Tertiary crushers
• Double deck tertiary screens
• Spiral classifiers
• Dewatering screens
• Hydro-cyclones
• Horizontal Belt Filters (HBF)
• Tailing thickeners
• Tailing disposal system
• Tailing dam
• Water storage tanks
• Water reclamation and distribution
• Suitable material handling facilities (such as EOT cranes, hoists, etc.)
• Dust control systems
1.5 Land
The proposed Screening & Beneficiation Plant – II is planned to be set up towards
southern side of the existing Screening & Beneficiation Plant-I on the hillock
between existing fine ore belt conveyor number BC 411 and existing lump ore
conveyor number BC 501. The location of the proposed facility considered is in
between N78200 & N78600 and E81600 & E82000 and in the outside lease area.
Tailing thickener facility is considered on eastern side of the proposed Screening &
Beneficiation plant-II near the co-ordinate N78500 & E81800. About 13.0 Ha of land
is required for construction of Screening & Beneficiation plant-II.
1.6 Water
The source of water for the Project is from Water Treatment Plant (WTP) which
draws water from Narihalla Dam. WTP is at Donimalai base camp located about
1km from the proposed plant site. Water from this WTP is pumped to storage tank
of about 5000 m3 located adjacent to the plant site. From this point water is
brought to Screening & Beneficiation Plant by gravity and then distributed to
different equipment. Make up water requirement for processing 7 MTPA ore is
estimated at about 370 m3/hr (2451 m
3/hr is required for operation, out of which
make-up water is 370 m3/hr).
1.7 Power
The incoming power supply for the proposed Screening & Beneficiation Plant- II is
planned to be tapped from existing Valley sub-station through over head line
(11kV)/ underground HT cable (11kV), which is about 2 km distance.
Estimated power requirement of the proposed plant is as follows:
Maximum Demand (Crushing & Screening) : 1.5 MVA (Mega Volt Amperes)
Annual Energy Consumption : 7.2 MU (Million Units)
![Page 6: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/6.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 4
1.8 Man-power Plan
The overall manpower requirement has been estimated at 10 executives and 71
non-executives. Apart from operation and running maintenance (mechanical and
electrical), the proposed manpower also caters to preventive maintenance and shut
down operations.
1.9 Capital Outlay
The capital outlay estimated for the scheme is about Rs. 399.75 crores. The capital
cost includes for Mechanical equipment & works of Rs. 148.32 crores (including all
taxes & duties and E&C), Civil & Structural works of Rs. 108.53 crores, Tailing Dam
works of Rs.51.81 crores and Electrical & Control works of Rs. 25.02 crores. Other
costs considered in the outlay are design, engineering, consultancy services
administration during construction (@ 5% on the Project basic cost), contingencies
(@ 5% on the Project basic cost) and Turnkey Package Concept, overheads and
contractor's profit margin (@ 15% on Project basic cost).
Sl.
No. Description
Approx. Basic Cost
Estimate (Excludes
Spares, E&C, Taxes &
Duties) (Rs. In Cr)
Approx. Cost Estimate
including all taxes,
duties and E & C
(Rs. In Cr)
I Mechanical Equipment & Works 94.12* 148.32**
II Electrical & Controls 17.85 25.02
III Civil & Structural Works 103.10 108.53
IV Tailing Dam 49.22 51.81
V Sub-total (A) 264.29 333.68
VI
Design, Engineering, Consultancy
services and administration during
construction (@ 5% on Project Basic
Cost)
13.21
VII Contingency (@ 5% on Project Basic
Cost) 13.21
VIII
Turnkey Package Concept, overheads
and contractor's profit margin
including local conditions prevailing
in the region (@ 15% on Project Basic
Cost)
39.64
IX Total (V + VI + VII + VIII) - 399.75
* Comprises FC component of Rs. 23.89 Cr and Rs. 70.23 Cr for indigenous items.
** Comprises FC component of Rs. 43.67 Cr (for supply of equipment, spares and
supervision charges during E &C) and Rs. 104.65 Cr for indigenous items.
![Page 7: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/7.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 5
1.10 Production Cost Analysis
Because of the additional capital investment for construction of the proposed
Screening & Beneficiation Plant – II for processing ROM from both Donimalai and
Kumaraswamy Mines, there will be hike in the cost of production as furnished
below:
Capital outlay : Rs. 399.75 crores.
Depreciation : Rs. 22.21 crores per year.
Cost involved due to additional manpower : Rs. 8.10 crores per year
Therefore, increase in cost of production = (22.21+8.10) / 0.7
= Rs. 43.3 per MT at 100%
capacity utilisation.
The increase in cost of production is primarily due to considering ‘Screening &
Beneficiation Plant’ on standalone unit. However, it is an essential unit required for
getting the final product.
1.11 Project Implementation Plan
1.11.1 An EPCM Consultant shall be appointed for Engineering, Procurement, Project
Management, Construction Supervision and Inspection Services, who will be
responsible for executing the Project through the Lump Sum Turnkey (LSTK)
contractor(s).
1.11.2 The total project is proposed to be executed largely on LSTK basis and includes the
following:
i) Site levelling
ii) All the facilities including tertiary crushing and screening – Dry circuit
iii) Wet circuit including process water system
iv) Tapping the power from existing 33/11 kV Substation and the power
distribution facilities at plant site
v) Auxiliary facilities including construction of office building, Stores, Internal
roads, etc.
However, the above packaging philosophy shall be reviewed after engagement of
EPCM consultant.
1.11.3 Statutory clearances: Following clearances are required for establishment of this
Project:
(i) Clearance from MOEF for diversion of forest land for construction of
Screening & Beneficiation Plant, Tailing Dam.
![Page 8: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/8.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 6
(ii) Environmental clearance for the Project.
(iii) Consent for establishment from Karnataka State Pollution Control Board
(KSPCB).
Of the above, Forest clearance for diversion of forest land is most critical.
Subsequent to receipt of this only other clearances can be obtained.
The time period required for commissioning of the Screening & Beneficiation plant
including Performance Guarantee (PG) test of 3 months is 27 months from the date
of receipt of the last statutory clearance, assuming that the LSTK contractors are in
place by that time. Refer Plate No. 16 for the time schedule for implementation of
the scheme.
1.12 Advance actions: Following actions are to be taken prior to Award of LSTK
contracts.
• Clearances to be obtained from the statutory authorities for construction of
Screening & Beneficiation Plant, tailing dam, laying of overhead electric line
and pipe line for slime disposal to tailing dam.
• Survey the plant site area
• Soil investigation to be done in the plant site area
• Enabling works i.e. construction water & construction power
1.13 Recommendation
Towards sustaining overall system efficiency and for processing of ores from both
Donimalai Iron Ore Mines (DIOM) & Kumaraswamy Iron Ore Mines (KIOM), the
installation of this Screening & Beneficiation Plant is inevitable and hence
recommended for immediate implementation.
![Page 9: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/9.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 7
2. Introduction of the project/ Background information
(i) Identification of project and project proponent.
NMDC has started production of iron ore from the Donimalai Iron Ore Mines from
the year 1977. The mine is capable of operating at a capacity of 7 million tons per
annum (MTPA). At present the ore is being treated in the existing Screening &
Beneficiation Plant-I of Donimalai. It is estimated that about 95.5 million tons of
additional ore reserve is proved in Donimalai Mines. The other mine in the area
with NMDC is Kumaraswamy Iron Ore Mine. Kumaraswamy Mine is estimated to
have a reserve of about 130 million tons of hematite ore. Construction of
Kumaraswamy Mine facilities for processing 7 MTPA of ROM is already on and
expected to be commissioned by end of 2013.
Existing Screening & Beneficiation Plant-I at Donimalai was originally designed to
process 4 MTPA ore with a provision of 3 lines. Subsequently additional equipment
and one more line were added to process 7 MTPA ore. Further enhancement of
capacity of existing Screening & Beneficiation Plant is not possible and therefore, a
proposal for construction of new Screening & Beneficiation Plant-II of capacity-10
MTPA was proposed.
(ii) Brief description of nature of the project.
The iron ore processing in the plant mainly involves Iron ore crushing, Screening
and Beneficiation.
(iii) Need for the project and its importance to the country and or region.
The existing Screening & Beneficiation plant is operating since 1977, which is about
36 years old. Initially the Screening & Beneficiation plant was installed with 3 lines
only to process 4 MTPA ROM but at later stage one more line (fourth line) was
installed to treat ore up to 7 MTPA. Out of four (4) lines in the Screening &
Beneficiation plant, any three lines would be in operation and one under
maintenance. In order to handle the enhanced production, there is a requirement
of additional screening lines. Considering plant layout, creation of additional
screening line(s) in the existing Screening & Beneficiation plant is not feasible.
Limitations / constrains of the existing & Plant for capacity expansion
a) Congested due to addition of equipment subsequent to Plant construction.
b) Material jamming in many chutes due to inadequate height of fall of material
between equipment.
c) Wet circuit needs augmentation.
d) Impossible to augment capacity more than 7 million tonnes per annum due to
space constraints within the Plant and around it.
![Page 10: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/10.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 8
e) In the ‘Technical Report on Production enhancement of Iron Ore Mines’, Vol-1
(Donimalai Iron Ore Mine), submitted by Mecon in 2007, it is stated that - “The
Equipment of the Plant are worn out and the existing Screening Plant would
have outlived its life till the commissioning and start of the production from
Kumaraswamy Mine. Therefore, it is proposed to erect a new Screening Plant of
matching capacity to commensurate with the production from Kumaraswamy
and Donimalai Mines.”
Considering the above limitations / constrains of the existing Screening &
Beneficiation Plant for capacity expansion, it is proposed to construct a new
Screening & Beneficiation Plant-II consisting of 4 Screening lines (3 working & 1
standby) with installed capacity for processing ore up to 7 MTPA. Provision of
additional 2 lines is proposed for handling additional 3 MTPA for future
requirement.
(iv) Demand-Supply Gap.
The demand for steel in India is projected to grow in the years to come and this in
turn would call for increased demand for iron ore. In this segment, M/s NMDC
Limited (NMDC) is gearing up to meet the expected increase in demand by
enhancing production capabilities of existing mines, by opening up new mines, by
setting up new integrated steel plants and by expanding capacity of existing plants.
(v) Imports vs. Indigenous production.
NA
(vi) Export Possibility.
NA
(vii) Domestic / export Markets.
Prime customers of NMDC are the following:
1 Rashtriya Ispat Nigam Ltd., (VSP)
2 KIOCL Ltd.,
3 Essar Steels Ltd.,
4 JSW Steel Ltd.,
5 Ispat Industries Ltd.,
6 CG based Sponge Iron Units
7 Welspun Max Steel Ltd.,
8 Visveswaraya Iron & Steel Plant
9 Aparant Iron & Steel Co. Ltd.,
10 Tata Metalliks Ltd.,
11 Southern Iron & Steel Co. Ltd.,
![Page 11: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/11.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 9
12 MMTC Ltd.,
13 Vikram Sponge Iron Ltd.,
Iron Ore is also exported to Japan & South Korea on a smaller scale.
(viii) Employment Generation (Direct and Indirect) due to the project.
Direct employment is estimated at about 81 persons which includes Executives: 10
Nos. and Workmen/Non-executives : 71 Nos. and indirect employment is
estimated at about 400 people.
The Executives would be placed during the construction of the project itself, as they
have to get acquainted with the plant and equipment for efficient running of the
concerned units.
Some of the construction personnel can progressively be absorbed with the
tapering of the construction work, particularly in the maintenance and services
areas of the plant. A certain portion of junior executives and supervisory staffs may
have to be recruited during the construction stage itself as acquaintance with
equipment erection will be very much beneficial for them in running the units later.
![Page 12: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/12.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 10
3. Project Description
(i) Type of project including interlinked and interdependent projects, if any.
The proposed Plant is interlinked with existing Donimalai Iron Ore Mine (DIOM),
upcoming Kumaraswamy Iron Ore Mine (KIOM).
(ii) Location (map showing general location, specific location, and project boundary &
project site layout) with coordinates.
Donimalai iron ore deposits are covered in the Survey of India topo-sheet No. 57
A/12 between Lat. 150
02’ 0” and 150
06’30” and Longitude 760
36’ 0” and 760
38’30”. The deposits are situated in Bellary district of Karnataka.
Donimalai deposits are situated on the southern half of the eastern range of hills
flanking Sandur valley. Sandur valley, which is about 40 km long and about 4 – 5 km
wide is surrounded by a long range of hills both on the eastern and western flanks,
giving an elliptical shape to the valley with its long axis running NW and SE. The two
ranges of hills close in towards the southern end and therefore the main opening of
the valley is towards the north.
(iii) Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
The most suitable site for the proposed plant is near to existing loading plant,
product conveyors (fines & lumps), KIOM downhill conveyor, Thickener and
proposed Tailing pond.
(iv) Size or magnitude of operation.
The Plant will process Iron ore up to 7 MTPA in Phase-1 with 3 operating lines and a
standby line. In Phase -2 the plant capacity will be augmented to 10 MTPA by
addition of another 2 lines.
(v) Project description with process details (a schematic diagram/ flow chart showing
the project layout, components of the project etc. should be given)
The ROM of Kumaraswamy mines or Donimalai mines or both the mines is stored in
silos of about 4000 tons (each) storage capacity. The lump ore [(-) 100mm] is
extracted through apron feeders and fed to double deck primary screens (with
30mm & 20mm apertures) through belt conveyor.
The oversize material of primary screens is fed to tertiary crusher to crush (-)
100mm ROM to (-) 30mm. The middle fraction and the under size material of
primary screen are fed to CLO conveyor and secondary screens respectively.
The crushed ore of tertiary crusher is fed to double deck tertiary screen (with
30mm and 6mm apertures), wherein the oversize material (+ 30mm) is re-
![Page 13: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/13.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 11
circulated to tertiary crusher. The middle fraction of tertiary screen (-) 30 (+) 6mm
and under size fraction (- 6mm) of tertiary screen are fed to CLO product conveyor
and fines product conveyor respectively.
Under size of secondary screen is fed to classifier of wet circuit system. Suitable
gate arrangement is envisaged at the bottom of under size chute of secondary
screen, which diverts material to launder leading to classifier circuit when operating
on wet mode. Under dry mode the gate will be lifted / opened to divert the
material to fines conveyor.
Conveyor receiving middle fraction [(-) 10 mm (+) 6 mm] of secondary screen is
envisaged with reversible operation to feed the material either to fines conveyor or
CLO conveyor based on the requirement.
(vi) Raw material required along with estimated quantity, likely source, marketing area
of final product/s, Mode of transport of raw Material and Finished Product.
Finished products fines & lumps are transferred through conveyors to loading plant
and despatched through railway wagons using mechanised loading facilities.
(vii) Resource optimization/ recycling and reuse envisaged in the project, if any, should
be briefly outlined.
About 85 % of process water is recovered from Tailing pond & thickener. About 4 to
5 % of slimes generated will be stored in tailing pond.
(viii) Availability of water its source, Energy/ power requirement and source should be
given.
Source of water is from water treatment Plant which gets water from nearby
Narihalla dam. Make up water requirement for processing 7 MTPA ore is estimated
at about 370 m3/hr (2451 m
3/hr is required for operation)
Estimated power requirement of the proposed plant is as follows:
Maximum Demand (Crushing & Screening) : 1.5 MVA (Mega Volt Amperes)
Annual Energy Consumption : 7.2 MU (Million Units)
(ix) Quantity of wastes to be generated (liquid and solid) and scheme for their
Management/disposal.
About 4 to 5 % of slimes generated will be stored in tailing pond.
(x) Schematic representations of the feasibility drawing which give information of EIA
purpose.
Proposed Screening & Beneficiation plant facilities and tailing dam locations are
shown in the drawing 3-2-148 in the feasibility report
![Page 14: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/14.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 12
4. Site Analysis
(i) Connectivity.
The Plant is located at 50 km from Bellary, district head quarters and 38 km from
Hospet town. The area is connected by road as well rail to Bangalore & Hyderabad.
The Plant area is approachable by a fair-weathered metal road from Toranagallu
town. Toranagallu is well served by the National Highway and Trunk rail/roads. The
distances to important places are as follows:
• Donimalai to Bengaluru - 350 km
• Donimalai to Hyderabad - 460 km
• Donimalai to Toranagallu - 28 km
The nearest rail head is Toranagallu Railway Station, which is 28 km from the plant
site. Chennai port is about 600 km by rail line from Ranjithpura railway station and
is connected to western coast via Sanvardom by about 389 km.
(ii) Land Form, Land use and Land ownership.
Forest land, open mixed jungle
(iii) Topography (along with map).
Proposed Screening & Beneficiation Plant facilities are shown in drawing no. 3-2-
148 & 3-2-131.
(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(including area under CRZ)), shortest distances from the periphery of the project to
periphery of the forests, national park, wild life sanctuary, eco sensitive areas,
water bodies (distance from the NFL of the river), CRZ. In case of notified industrial
area, a copy of the Gazette notification should be given.
Forest Land, open mixed jungle
(v) Existing Infrastructure.
No facilities exist.
(vi) Soil classification
The rock formations of the region consist of phyllites (locally designated as shales),
the well known Banded Hematite Jaspers and Quartzites (BHJ & BHQ) and
quartzites and basic igneous rocks (green stones) which have been generally
metamorphosed to the “Green Schist facies. According to Fermor, it is a folded
![Page 15: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/15.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 13
synclinorium in which the apparently large number of hematite-quartzite bands is
due to repetition by folding.
(vii) Climatic data from secondary sources.
The area receives an annual rainfall ranging from 600 mm to 800 mm. The
predominant rainy season in this area is between July and October. Rain also occurs
occasionally in the months of November and January due to northeast monsoon.
The maximum temperature is around 400 C in summer while minimum temperature
is around 150 C in winter, which occasionally goes to as low as 12
0 C.
(viii) Social Infrastructure available.
Well developed township/colony exists in Donimalai.
![Page 16: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/16.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 14
5. Planning Brief
(i) Planning Concept (type of industries, facilities, transportation etc) Town and
Country Planning/Development authority Classification.
Only Iron Ore Process Plant is proposed
(ii) Population Projection
Roughly about 15000 populations exist.
(iii) Land use planning (breakup along with green belt etc).
NA
(iv) Assessment of Infrastructure Demand (Physical & Social).
NA
(v) Amenities/Facilities.
Well developed township/colony exists in Donimalai.
![Page 17: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/17.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 15
6. Proposed Infrastructure
(i) Industrial Area (Processing Area).
Total area required for Screening & Beneficiation Plant-II & associated facilities is
39.32 Ha which includes – Screening & Beneficiation Plant-II (13 Ha), Tailing Dam-I
(16.2 Ha), Tailing dam-II (9.0 Ha), Pipe line-I (0.06 Ha), Pipe line-II (0.34 Ha) and OHE
line (0.72 Ha)
(ii) Residential Area (Non Processing Area).
NA
(iii) Green Belt.
Afforestation measures shall be taken-up through developing barrier platforms all
around the plant. To maintain ecological balance in the area, plantations of suitable
species of ever green/locally grown trees shall be made. Adequate tree plantations
shall substantially abate dust pollution, filter the polluted air and ameliorate the
plant environment without any hazards in public health.
The Screening & Beneficiation Plant includes development of a green belt that is
expected to reduce noise levels, limit the propagation of fugitive dust and produce
a better occupational / aesthetic environment. The implementation of a green belt
around the plant and side of the roads and the selection of plant species will be
carried out in co-operation with Horticulture Department.
(iv) Social Infrastructure.
Well developed township/colony exists in Donimalai.
(v) Connectivity (Traffic and Transportation Road, Rail/Metro/Water ways etc)
Existing road adjacent to the Proposed Plant will be used for connectivity. Internal
roads will be layed inside the Plant premises for man & material movement.
(vi) Drinking Water Management (Source & Supply of water)
The source of water for the Project is from existing Water Treatment Plant (WTP) at
Donimalai base camp located about 1km from the proposed plant site.
(vii) Sewerage System.
Sewerage system is already available at the adjacent plant which is at 300m
distance.
(viii) Industrial Waste Management.
NA
![Page 18: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/18.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 16
(ix) Solid Waste Management.
The slimes stored in tailing pond will be used as raw material for upcoming Pellet
Plant.
(x) Power Requirement & Supply / source.
The estimated power requirement of the proposed plant is as follows:
T
The incoming power supply for the proposed Screening & Beneficiation Plant-II is
planned to tap from existing Valley sub-station through over head line (11kV) /
underground HT cable(11kV), which is about 2 km distance.
• Maximum Demand (Screening &
Beneficiation Plant - II)
: 1.5 MVA
• Annual Energy Consumption : 7.2 MU
![Page 19: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/19.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 17
7. Rehabilitation and Resettlement (R & R) Plan
(i) (Policy to be adopted (Central/State) in respect of the project affected persons
including home oustees, land oustees and landless laborers (a brief outline to be
given).
There is no settlement of Human population at the proposed Plant location.
![Page 20: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/20.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 18
8. Project Schedule & Cost Estimates
(i) Likely date of start of construction and likely date of completion (Time schedule for
the project to be given).
Clearances to be obtained from the statutory authorities for construction of
Screening & Beneficiation Plant, tailing dam, laying of overhead electric line and
slime disposal pipe line to tailing dam. Thereafter an EPCM Consultant shall be
appointed for Engineering, Procurement, Project Management, Construction
Supervision and Inspection Services, who will be responsible for executing the
Project through the Lump Sum Turnkey (LSTK) contractor(s).
Implementation schedule
By initiating advance action for some of the activities, considering some are parallel
actions and based on minimum time period required for certain activities like
appointment of EPCM consultant, supply of long lead item such as cone crusher
etc., setting up of the proposed system will require 45 months from the date of
approval of TEFR (TEFR approved on 05.11.2013). The time frame required for
construction of the Plant is 24 months after obtaining forest clearance. An
indicative time schedule is presented in the form of ‘Bar Chart’, placed at Plate No.
16.
(ii) Estimated project cost along with analysis in terms of economic viability of the
project.
The capital cost estimated for creation of additional facility by construction of
Screening & Beneficiation Plant – II, is Rs. 399.75 crores. The detail of the break-up
is as below:
Sl.
No. Description
Approx. Basic Cost
Estimate (Excludes
Spares, E&C, Taxes &
Duties) (Rs. In Cr)
Approx. Cost Estimate
including all taxes,
duties and E & C
(Rs. In Cr)
I Mechanical Equipment & Works 94.12* 148.32**
II Electrical & Controls 17.85 25.02
III Civil & Structural Works 103.10 108.53
IV Tailing Dam 49.22 51.81
V Sub-total (A) 264.29 333.68
VI
Design, Engineering, Consultancy
services and administration during
construction (@ 5% on Project Basic
Cost)
13.21
![Page 21: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/21.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 19
VII Contingency (@ 5% on Project Basic
Cost) 13.21
VIII
Turnkey Package Concept, overheads
and contractor's profit margin
including local conditions prevailing
in the region (@ 15% on Project Basic
Cost)
39.64
IX Total (V + VI + VII + VIII) -
399.75
* Comprises FC component of Rs. 23.89 Cr and Rs. 70.23 Cr for indigenous items.
** Comprises FC component of Rs. 43.67 Cr (for supply of equipment, spares and
supervision charges during E &C) and Rs. 104.65 Cr for indigenous items.
Cost of Production
Because of the additional capital investment for construction of the proposed
Screening & Beneficiation Plant – II for processing ROM from Kumaraswamy and
Donimalai Iron Ore Mines, there will be hike in the cost of production as furnished
below:
Capital outlay : Rs. 399.75 crores
Depreciation : Rs. 22.21 crores per year
Cost involved by additional manpower required : 81 X 10 lacs
= Rs. 8.10 crores per year
Increase in cost of production : (22.21+8.1) / 0.7
= Rs. 43.3 per ton at 100%
capacity utilization
Notes
1. Depreciation is considered for 18 years of life for Kumaraswamy Mines.
2. Only manpower cost towards fixed cost of production cost is considered keeping
variable cost for producing 7 MTPA of CLO & Fines unchanged. Increase on Rs.
43.3/- per ton is at 100% utilisation and will vary according to the utilisation of the
facility.
3. The environment and forest clearances are yet to be obtained. In case of delay in
obtaining the same, the calculation may also need to be revised.
4. Considering the production target of Donimalai complex, the level of production
may sustain at about 10 MTPA for few years from 2016-17, as more reserves are
proved in Donimalai Mines. Hence, to sustain the continuity of production from
both mines and for better working environment with better maintenance facility, it
is required to consider construction of Screening & Beneficiation Plant – II. At later
![Page 22: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/22.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 20
date, the Screening & Beneficiation plant – II will be augmented with by installing
additional two lines to process ore up to 10 MTPA. Equipment of existing Screening
& Beneficiation plant in serviceable conditions can be used for augmentation of
Screening & Beneficiation -II in phased manner. However, the increase in cost of
production due to this Screening & Beneficiation Plant is Rs. 43.3/ton, which is
primarily due to depreciation and additional manpower considered.
![Page 23: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/23.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 21
9. Analysis of proposal (Final Recommendations)
(i) Financial and social benefits with special emphasis on the benefit to the local
people including tribal population, if any, in the area.
• Direct employment of about 81 people (Executives & non executives).
• Indirect employment of about 400 people.
• Uninterrupted production of Iron ore products to supply Steel industries.
• Increased level of production to match with future increased demand of Iron
Ore.
Towards sustaining overall system efficiency and for processing of ores from both
Donimalai Iron Ore Mines (DIOM) & Kumaraswamy Iron Ore Mines (KIOM), the
installation of this Screening & Beneficiation Plant-II is inevitable and hence
recommended for immediate implementation.
![Page 24: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/24.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 22
ADDITIONAL TECHNICAL
DETAILS OF
FEASIBILITY REPORT
![Page 25: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/25.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 23
10. ORE GEOLOGY & RESERVES
10.1 Geology of Deposits of Donimalai & Kumaraswamy
10.1.1 Donimalai Iron Ore Deposit
(1) Location
Donimalai iron ore deposits are covered in the Survey of India topo-sheet
No. 57 A/12 between Lat. 150
02’ 0” and 150
06’30” and Longitude 760
36’ 0”
and 760 38’30”. The deposits are situated in Bellary district of Karnataka.
Donimalai deposits are situated on the southern half of the eastern range of
hills flanking Sandur valley. Sandur valley, which is about 40 km long and
about 4 – 5 km wide is surrounded by a long range of hills both on the
eastern and western flanks, giving an elliptical shape to the valley with its
long axis running NW and SE. The two ranges of hills close in towards the
southern end and therefore the main opening of the valley is towards the
north.
(2) General Geology
The rock formations of the region consist of phyllites (locally designated as
shales), the well known Banded Hematite Jaspers and Quartzites (BHJ &
BHQ) and quartzites and basic igneous rocks (green stones) which have been
generally metamorphosed to the “Green Schist facies. According to Fermor,
it is a folded synclinorium in which the apparently large number of
hematite-quartzite bands is due to repetition by folding.
(3) General description of the Deposit
The iron ore range in Donimalai constitutes prominent ridges extending over
a total strike length of about 7.0 km having trend of NW to SE following
general strike of the country rocks with steep (700) to vertical beds
dominantly towards the east.
The deposit is conveniently divided in to two blocks, namely North Block
and South Block. In South block, one ore zone followed NNW for about 2.6
km after which it splits into two, one limb following the original trend for
another 0.6 km and the eastern limb making a small angle with the main
zone and traceable for about 0.8 km. These two limbs do not join up and are
separated by a small band of shale. The main western ore zone has been
designated as Deposit 1 and the small eastern limb as Deposit 1A. The south
block ends to the south against a private lease hold in which the main ore
body is found to extend for about 100 m.
Further north, the continuity of Deposit 1 and 1A is lost and outcrops of
lateritised shale and BHJ are found. This break in the continuity of ore has
![Page 26: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/26.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 24
been taken as the boundary between the North and South Blocks of
Donimalai.
In the general strike continuity of Deposit 1 further north, two isolated ore
bodies are observed. Those ore bodies have been designated as 2W and
3W. Similarly, in the general strike continuity of Deposit 1A further north
and occurring to the east of Deposit 2Wand 3W, two isolated ore bodies are
found. These have been designated as Deposit 2E and 3E.
10.1.2 Kumaraswamy Iron Ore Deposit
(1) Location:
Kumaraswamy Iron Ore deposits situated at the southern closure of the hill
ranges of Bellary – Hospet sector. The Kumaraswamy deposits in turn
consists of 5 iron ore blocks namely, A,B,C,D & E. Out of which ‘B’ & ‘C’
blocks are within the mining lease of NMDC Ltd. covers an area of 647.50
ha.
The ore bodies ‘B’ & ‘C’ of Kumaraswamy are covered in the survey of India
topo-sheet No. 57A/12 and lie between latitude 1500’10” to 15
00’50” and
Longitude 76034’5” to 76
036’20”.
(2) Geology of the Ore Deposits
Kumaraswamy ‘B’ and ‘C’ blocks lie on the Southern flank of Sandur Basin,
which is grouped under Dharwarian schist belt. The range forms the eastern
continuation of the Ramanadurg Range. “B’ Block is contiguous to ‘C” Block
on eastern side except for the small patch of non-mineralised valley portion.
The general strike of the ore body is WNW – ESE which is almost parallel to
the trend of Kumaraswamy range i.e., East-West. The dip is towards North
with an angle varying from 150 to 16
0. All along the strike length of the ore
body the foot wall is characterised by Ferrugenous shale / tuff. Cherty
quartzite and banded hematite quartzite occur on the Northern flanks.
(3) Ore Types
NMDC has grouped all the ore types into 5 individual ore types, viz., Hard
ore (Type-1), Limonitised Laminated ore (Type-2), Soft Laminated Ore (Type-
3), Powdery Ore (Type-4) and Lateritic ore (Type-5). NMDC conducted
laboratory tests at R&D Laboratory on individual ore types.
10.2 Mineable Reserves
Estimation of Ore Reserves and Grade of Donimalai & Kumaraswamy Deposits
![Page 27: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/27.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 25
Mineable ore reserves have been computed within the pit limits of drawn on each
of the slice plans. Ore reserves following within the pit limits thus designed are
considered mineable reserves for mechanized operations.
(1) BLOCKWISE MINEABLE RESERVES, GRADE AND LUMP
RECOVERY OF DONIMALAI BLOCKS
AS ON 01.04.2013
Sl.
No. Block
Reserves in
Million
Tons (MT)
Grade % Lump
Recovery
(%) Fe
1 South Block 56.02 66.00 32.50
2 3E Deposit 12.52 65.34 25.30
3 2W Deposit 3.81 61.83 26.20
4 3W & 2E
Deposit 1.77 63.76 28.10
5 Beyond MM
Cross Section 21.37 65.86 31.51
Total 95.48 65.68 31.00
(2) BLOCKWISE MINEABLE RESERVES, GRADE AND LUMP RECOVERY OF
KUMARASWAMY
‘B’ & ‘C’ BLOCKS AS ON 01.04.2012
Sl.
No. Block
Reserves
in MT
Grade % Lump
Recovery
(%) Fe SiO2 Al2O3 P
1 Kumaraswamy
- ‘B’ Block 29.559 65.00 1.55 1.92 0.070 35.70
2 Kumaraswamy
- ‘C’ Block 100.421 63.85 1.85 3.15 --- 30.72
Total 129.980 64.11 1.78 2.87 0.070 31.85
10.3 Ore Characteristics
It is conceptualised that the feed material to the proposed Screening &
Beneficiation plant is (-) 100 mm, either from Kumaraswamy deposit or from
Donimalai or from Kumaraswamy and Donimalai deposits together. To generate
data in respect of:
![Page 28: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/28.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 26
(i) Physical & Chemical properties of Lump ore (-) 100 mm size
(ii) Product studies of proposed sized material (-) 30 (+) 6 mm size.
(iii) Product studies of proposed sized material (-) 6 mm
(iv) Product characterization and material balance
Representative samples of Kumaraswamy Mines were collected and mineralogical
tests conducted by R&D. Relevant data from test results have been considered for
the purpose of preparation of this Report.
Based on the test results of composite samples of Kumaraswamy Mines, Material &
Water Balance Diagrams are prepared (Refer Plate No. 1.1 & 1.2).
![Page 29: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/29.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 27
11. PLANT DESIGN AND LAYOUT
11.1 Layout considerations
o The proposed Screening & Beneficiation plant is planned to ensure best
possible interconnection with minimal disturbance to the existing facilities.
o The new Screening & Beneficiation plant-II is planned to make best use of
contours between existing lump ore Conv. 501 and fine ore Conv. 411 from EL
722m to EL 690m.
o Considering the topography, storage silos are envisaged instead of open
stockpile in order to have more live volume, clean & safe storage and easy
retrieval of material, which are eco-friendly.
11.2 Process flow sheet development
NMDC has adopted the screening, crushing and wet screening facilities based on
the results of the following tests conducted on composite sample of Kumaraswamy
ore.
o Mineralogy and liberation studies
o Chemical analysis
o Characterisation studies
o Settling studies
o Filtration studies
Based on the above, a conceptual process flow diagram (Refer Plate No. 2.1 & 2.2)
along with material and water balance is prepared by NMDC, which forms basis for
the design of plant and selection of equipment.
11.2.1 Material Balance
a) ROM input : 1800 TPH
b) CLO production rate : 819 TPH
c) Fines production rate : 938 TPH
d) Tailings / Slimes : 43 TPH
11.3 Feed Ore Characteristics
The Screening & Beneficiation plant is designed to handle ROM from Kumaraswamy
mines or Donimalai mines or both the mines and the specifications of feed material
are as follows:
![Page 30: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/30.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 28
a) Size of ROM : (-) 100mm
b) ROM Bulk density : 2.2 to 2.5 T/m3
(approx.)
c) Specific gravity : 4.5 to 5.2
d) Compressive strength : 4500 kg/cm2
e) Angle of repose : 350
f) Surcharge angle : 200
g) Bond work index : Up to 11
h) Moisture content : about 5%
i) Quality : Fe-63%, SiO2-2.74%, Al2O3-3.23% & LOI – 3.8%
j) Typical size analysis of feed
to the proposed plant : (+) 100 mm - 2.49 %
(-) 100 mm (+) 80 mm - 3.33 %
(-) 80 mm (+) 50 mm - 4.75 %
(-) 50 mm (+) 30 mm - 8.19 %
(-) 30 mm (+) 6 mm - 26.25 %
(-) 6 mm (+) 3 mm - 11.38 %
(-) 3 mm (+) 1 mm - 8.67 %
(-) 1 mm - 34.94 %
(The above size analysis may vary by 3 to 5 % points at each size)
11.4 Product Specification expected:
Products & Size CLO
(-) 30 mm (+) 6 mm
Fines
(-) 6 mm
Fe 64.29 % 62.44 %
SiO2 + Al2O3 6.0 (max.) 7.00 % (max.)
Over size (+) 30 mm – 5 % (max.) (+) 6 mm - 5 % (max.)
Under size (-) 6 mm – 15 % (max.) (-) 100 mesh - 25 % (max.)
11.4.1 As per the present scenario in the iron ore market and recent Government
directives for selling of iron ore products, the product size of calibrated lump ore
(CLO) shall be ( - ) 40 ( + ) 10mm and fines size shall be ( - ) 10mm. Though the test
works for the scheme was carried out and results were analyzed considering the
product size of CLO as ( - ) 30 ( + ) 6mm and fines as ( - ) 6mm, some tests were
redone and analyzed for product size of CLO as ( - ) 40 ( + ) 10mm and fines as ( - )
10mm. Accordingly, the recovery rate of CLO, fines, slimes, chemical analysis such
as %Fe, Al2O3, SiO2, apertures of the primary screen and secondary screen are
estimated. For change in specifying the product size, there will not be any change in
the process, whereas layout & design care is taken while developing the proposed
scheme. An indicative comparative statement for the different products size is as
below:
![Page 31: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/31.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 29
CLO Fines
(-) 40 (+) 10
mm
(-) 30 mm (+) 6
mm (-) 10mm (-) 6mm
Primary screen
aperture size (mm) 40 & 20 30 & 20
Secondary screen
aperture size (mm) 10 & 3 10 & 6
% Fe 63.75 64.29 62.26 62.44
% SiO2 1.65 1.08 2.73 2.91
% Al2O3 2.88 3.53 4.08 3.31
% Weight recovery 41.00 45.50 51.00 52.12
While preparing Tender Document for implementation of the Project, the above
aspect needs to be taken care in finalizing the specification of above screens
including tertiary screens.
11.5 Design Criteria
The total estimated available quantity of iron ore reserve available as on
01.04.2012, from Kumaraswamy Deposit and Donimalai Deposit is about 225
million tons. Therefore, new Screening & Beneficiation plant-II processing capacity
has been considered to be 7 MTPA in Phase-1 similar to the existing Screening &
Beneficiation plant-I and matching with capacity of Kumaraswamy Project.
Hence, to take feed @ 2000 TPH (design) from Kumaraswamy downhill conveyor,
Screening & Beneficiation Plant-II is envisaged with 4 lines (3 working and 1
standby) for processing ROM of 7 million tons per annum (MTPA) for reliable &
continuous trouble free operation. Each screening line is envisaged to operate at
650 TPH rated capacity with design capacity of 750 TPH.
Taking a view of in-built operational allowance, it has been considered that the
Screening & Beneficiation Plant will be operating at rated capacity of 1800 TPH to
achieve projected target of 7 MTPA ROM handling.
The Plant capacity will be augmented to 10 MTPA in Phase-2 in future by adding 2
more lines for which required provision would be made.
11.6 Scheme Proposed
Overall plant layout of the proposed scheme is shown in Plate no. 3 and description
of the proposed Screening & Beneficiation plant (Refer Plate No. 4.1) is as follows:
11.6.1 Screening & Crushing
• The ROM of Kumaraswamy mines or Donimalai mines or both the mines is
stored in silos of about 4000 tons (each) storage capacity. The lump ore [(-)
![Page 32: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/32.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 30
100mm] is extracted through apron feeders and fed to double deck primary
screens (with 30mm & 20mm apertures) through belt conveyor.
• The oversize material of primary screens is fed to tertiary crusher to crush (-)
100mm ROM to (-) 30mm. The middle fraction and the under size material of
primary screen are fed to CLO conveyor and secondary screens respectively.
• The crushed ore of tertiary crusher is fed to double deck tertiary screen (with
30mm and 6mm apertures), wherein the oversize material (+ 30mm) is re-
circulated to tertiary crusher. The middle fraction of tertiary screen (-) 30 (+)
6mm and under size fraction (- 6mm) of tertiary screen are fed to CLO product
conveyor and fines product conveyor respectively.
• Under size of secondary screen is fed to classifier of wet circuit system.
Suitable gate arrangement is envisaged at the bottom of under size chute of
secondary screen, which diverts material to launder leading to classifier circuit
when operating on wet mode. Under dry mode the gate will be lifted /
opened to divert the material to fines conveyor.
• Conveyor receiving middle fraction [(-) 10 mm (+) 6 mm] of secondary screen
is envisaged with reversible operation to feed the material either to fines
conveyor or CLO conveyor based on the requirement.
11.6.2 Wet Circuit
• Process water after washing of iron ore contains high concentration of
suspended solids (iron ore fines) and is called as slurry, which is collected from
underflow chute of secondary screens in a ore processing plant for
beneficiation to attain the following objectives:
(i) To minimise slime loss by more fines recovery
(ii) To recover process water for recirculation
(iii) To deposit less tailings (iron ore bearing) in tailing dam
• Classifier overflow is fed to dewatering screen and the underflow to hydro-
cyclones. The overflow of dewatering screen is fed to fines conveyor and the
underflow is fed to cyclones. The cyclones (with separation size of 150
microns) overflow is diverted to thickener and the underflow to filtrate unit to
recover some fines, which in turn is fed to fines conveyor.
11.7 Technological Facilities
The plant shall comprise of tertiary crushing, screening, classifying, filtering and
conveying facilities to be set up in an integrated manner and consists of the
following technological units. The description of the technological facilities specified
in this chapter is as proposed for this plant and as per the drawings enclosed.
![Page 33: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/33.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 31
11.7.1 Travelling Tripper & Tripper Conveyor
Ore conveyed either from KIOM or DIOM or both is extracted from a storage
bunker at the discharge of downhill conveyor BC 723 of KIOM and feed to a
1200mm wide tripper conveyor (@ 2500 rated capacity with 10% design margin)
provided with travelling tripper, which feeds to silos.
11.7.2 Silos
Four numbers - RCC silos of about 8m square (inner dimension) and about 40m
height for storage of 4,000 tons (each silo) of ROM ore from secondary crushers of
either KIOM or DIOM or both are envisaged.
11.7.2.1 Functional Design of Silos/Bins of Reliable Gravity Flow
The extraction of the ore from the silos is based on gravity flow. The problems
associated with the silos/bunkers, hoppers and transfer chutes while handling Iron
ore are numerous particularly when the bulk solid contain a significant portion of
fines at higher moisture levels. The typical flow problems include “No flow”,
“Reduced live capacity”, “Segregation” etc., which significantly affect the
performance of the plant in general.
A properly designed silo system results in better capacity utilization, better flow
rate control and an improved uniformity in the extraction of the ore. For this,
proper geometrical configuration of silos suitable for specific iron ore application is
important, in order to minimize or avoid the flow problems.
The functional design of proposed silos/bins shall conform to IS 9178 (Part 3) for
reliable gravity flow. The flow properties of Iron ore proposed to be handled in the
silos at different moistures is to be established in the laboratory by using the Jenike
shear tester. The parameters like Internal angle of friction, wall angle of friction and
flow function thus established form the inputs to arrive at the silo design
parameters like minimum slope and outlet dimensions. The minimum slope and
outlet dimensions of the silo vary with the geometry and the wall liner used for
specified flow regimes like Mass Flow or Expanded Flow. Normally, an abrasive ore
like iron ore shall be stored in a silo designed to promote Expanded Flow (bottom
portion Mass Flow and top self emptying Funnel Flow).
The trouble free movement (flow) of ore from the silos/bunkers/hoppers and
transfer chutes play a vital role in the productivity of the screening plant. It is also
required to exercise due care while designing the transfer bin / transfer chutes in
order to avoid plugging and excessive wear. The minimum wall inclination to
initiate flow after impact depends on the ore moisture content as well as the
friction between the liner used and ore.
The outlet size and slope of the bins envisaged in this report are largely in order for
the envisaged application based on flowability tests conducted (May, 2012) by R&D
Centre on Kumaraswamy composite sample. However, fine tuning of functional
![Page 34: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/34.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 32
design of silo/bin and transfer chute shall be carried out based on flow properties
of combined sample of Kumaraswamy & Donimalai Deposits after required test
works at NMDC R&D Centre during further course of engineering.
11.7.3 Apron Feeders
Apron feeder - one number for each line for extracting ore from silo to feed primary
screen feed conveyor. The design capacity of apron feeder and belt conveyors
(1200mm wide) is 800 TPH.
11.7.4 Primary Screen
The double deck vibrating screen of circular motion/linear motion vibrating screen
of 2400mm x 6100mm size is considered in each line. The screen is mounted on
rigid structural support in the screen building. The rated capacity of the screen is
650 TPH. The design capacity of the screen is 750 TPH.
11.7.5 Secondary Screen
The double deck vibrating screen of circular motion/linear motion vibrating screen
of 2400mm x 6100mm size is considered in each line. The screen is mounted on
structural trolley in the screen building. The design capacity of the screen is 550
TPH.
11.7.6 Tertiary Crusher
Two Nos. (1 working & 1 standby) 7’ cone crushers for crushing (-) 100mm ROM to
30mm are considered with operating capacity of each about 750 TPH (500 TPH
fresh feed & about 250 TPH recirculation load). The crusher foundation is designed
for dynamic loading and is isolated from main building foundations.
11.7.7 Tertiary Screen
The double deck vibrating screen of circular motion/linear motion vibrating screen
of 2400mm x 6100mm size. The decks are of 30 mm & 6 mm aperture panels for
screening the material. The screen is mounted on rigid structural support in the
screen building. The rated capacity of the screen is 650 TPH. Two nos. screens (One
working and one standby) are envisaged. The design capacity of the screen is 750
TPH.
11.7.8 Classifiers
Secondary screen underflow is diverted to classifier (4 Nos. - 72” dia. and 37’ long)
for separation of 150 microns. The raking capacity of each classifier is considered as
350 TPH. The raked sand is diverted to fines product conveyor and the overflow is
fed to hydro-cyclone.
![Page 35: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/35.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 33
11.7.9 Dewatering screens
4 Nos. Dewatering screens of 2400mm X 6100mm are envisaged to dewater the
classifier sand.
11.7.10 Hydro-cyclones
Classifier overflow and dewatering underflow is fed to cluster of hydro-cyclones for
separation size of 150 microns. The underflow of cyclone is fed to filter circuit. The
overflow of hydro-cyclone is fed to tailing thickener. Two circuits of cyclones are
considered in series, one circuit of desliming cyclone and one circuit of densifying
cyclone.
11.7.11 Tailing Thickener
The overflow from the cyclone is fed to φ35m hi-rate thickener (1 number) for
thickening. The capacity to handle feed is approximately 150 TPH solid. The
thickener is of civil construction and it consists of flocculent system for faster
settling.
The under flow is pumped to the tailing dam by slurry pump provided below the
thickener. A stand-by pump is also considered. The slurry is transported through
rubber lined MS pipeline of approximately 200m & 1110m length into Tailing dam-1
& 2 respectively. Density meter and flow meter is provided in the discharge line for
measuring the density of the slurry. The pump suction is provided with
automatically operated knife gate valve for isolation. Flush water is provided in the
suction line for cleaning the pipeline before starting and after stopping of pump.
11.7.12 Slurry Pumps and Sumps
The sumps are fabricated with MS plate and rubber lined for abrasion resistance.
The sumps are provided with ultrasonic level sensor for measurement of level.
Make-up water line with automatic modulating valve is provided for each sump.
The level measurement from ultrasonic level sensor is interlocked with the
automatic modulating valve to ensure the sump level is maintained within the pre
determined level to avoid starving of the pump.
The slurry pumps are of heavy duty abrasion resistance centrifugal pumps. The
impeller and casing are rubber lined / hard metal for handling abrasive slurry. The
slurry pumps are driven through Variable Frequency Drive (VFD).
The suction lines are of MS pipe with rubber lined and provided with automatic
knife gate valves for isolation purpose. The flush water line is provided to clear the
slurry, if any before starting and after stopping of the pumps. A drain valve is
provided for draining out slurry from the pipeline. All discharge lines are of MS pipe
with rubber lined and provided with the magnetic flow meter to measure the flow
rate. Nucleonic type density meter is provided in tailing disposal pipe line.
![Page 36: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/36.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 34
11.7.13 EOT Cranes
EOT cranes and suitable handling facilities at various locations are considered in the
Plant for servicing and maintenance of equipment and facilities.
11.7.14 Belt Conveyors
All belt conveyors are 1200mm wide provided with skirt-boards, chutes, safety
switches, scrapers, take-up units etc. Skirt-board shall be suitably lined with liner
plates (preferably chrome-carbide liners) while chutes with Mn-steel liners at
impact/abrasive zones. The belt conveyors running at out-door are provided with
covered structural gallery with maintenance walk-ways on both sides.
11.7.15 Horizontal Belt Feeders (HBF)
Horizontal belt filters are considered to recover some iron values and also to
recover some water in the process, from under flow of densifying cyclones. Slurry
from densyfying cyclone underflow is passed on to a moving perforated belt
conveyor, which allows filtrate (water) to drain through the perforations on the belt
and collected suitably by vacuum principle. Filter cloth fastened on the belt top of
perforated belt conveyor retains slurry at the feeding end and as it moves towards
discharge it holds the cake to be discharged at the head end. Three units are
considered in the circuit with two operating and a standby.
11.8 Service & Common Facilities
11.8.1 Process Water Circulation System
The process water requirement for Screening & Beneficiation Plant-II is as follows:
Sl. No. Consumer Qty. (m3/hr)
INPUT
1 Process water for Primary screen 1440
2 Process water for Secondary screen 1011
Total 2451
OUTPUT
1 CLO 55
2 Fines 156
3 Thickener underflow 64
4 Thickener overflow 1117
5 Cyclone overflow 736
6 HBF Filtrate 322
Total 2451
MAKE UP WATER
1 Products 276
2 Extra for floor washing , dust control etc., 90
366
![Page 37: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/37.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 35
A recirculation water tank of 5000 m3 capacity is envisaged to receive the cleaned
water from the tailings thickener and the size of tank is 35m dia. & 5.5m height.
The makeup water requirement for the process will be brought by a pipe line from
the Donimalai filter house / WTP to make up water storage tank located at +745.00
m level near the Screening & Beneficiation plant-II. Water balance for the plant is
indicated in Plate no. 1.2.
11.8.2 Make-up Water Supply System
The make-up water required for the project is pumped from the water treatment
plant at Donimalai base. 2nos. (1W+1S) pumps of capacity 500 m3/h with a head of
about 700m are envisaged to pump water from Sump at WTP to 5000 cu.m
recirculation tank near the Screening & Beneficiation plant-II. A pump room is
envisaged to accommodate make-up water pumps adjacent to the water storage
sump at WTP.
Currently the sanctioned quantity of water from Narihalla dam is 745 cum/hr.
Presently Project is withdrawing water @ 350 cum/hr. The proposed augmentation
of water supply from Narihalla dam for another 400 cum/hr (total 745 cum/hr) is
under progress.
11.8.3 Dust Control System
Dry Fog Dust Suppression System is considered for various material transfer points
at Screening & Beneficiation Plant-II. The fugitive air borne dust generated during
material transfers at conveyors, crushing, screening, etc., will be suppressed by
superfine atomization of water droplets produced with the help of compressed air
to form a blanket of extremely fine fog to entrap the fugitive air borne dust such
that the suppression is achieved due to agglomeration by impact of dust particles
with water droplets until mass becomes heavy enough to cause the particle to
settle on the main material without wetting the product being handled.
The system shall comprising of MS water tanks, pipe work, nozzles, solenoid valves,
manual shut-off valves, pumps (one working and one stand-by), air compressor
(one working and one stand-by), all necessary electrics with MCC and
instrumentation required for operation of the system through PLC etc.,
11.8.4 Fire Fighting
Fire fighting extinguishers will be suitably located in transfer towers and buildings in
their respective maintenance and operating floors.
![Page 38: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/38.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 36
11.9 Tailing Reservoirs
The locations of the proposed tailing ponds of 8 MT & 5.4 MT capacity are indicated
in the Plate No. 14 will be used for storage of tailings of the new Screening &
Beneficiation plant-II. Area of tailing dams considered is about 9 Ha (initial stage)
and 16.2 Ha (second stage).
11.10 The final products Fines & CLO are proposed to be carried to stockyard through
existing fine ore conveyor and CLO conveyor systems. To meet the increased
production rate, a proposal for augmentation of BC 411 is ready and is to be
implemented appropriately. In a similar manner augmentation of CLO conveyor
systems should be taken up appropriately.
Existing stocking and loading facilities are proposed for the utilization of dispatch of
the products. However, a proposal for additional fine ore stockpile for increased
production fines and a loading line is in pipeline. This additional loading line will
take care of the increased production rate of CLO, fines and other products like
pellets, etc.
11.11 The requirements / facilities described / envisaged here are indicative and may
undergo change for design improvement, process and layout optimization, if any,
during further engineering stage.
![Page 39: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/39.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 37
12. CIVIL AND STRUCTURAL WORKS
12.1 The following facilities are envisaged for the subject work
1. RCC Silos 4000T cap. each-4 nos., with lift & staircase,
2. RCC Silos for future provision- with foundation & walls up to plinth,
3. Primary & Secondary Screening Plant buildings with EOT crane of 30/5 & 15/3T
capacity
4. Tertiary Crusher House (TCH) building with EOT crane of 30/5T capacity,
5. Tertiary Screening House (TSH) ,
6. Conveyor galleries nos. 801, 806, 810, 812, 813, 814, 819, 823, 829 & 832.
7. Junction Houses nos. JH-1 to JH-4,
8. Horizontal Belt Filter Building,
9. Thickener – 1 no. of dia. 35m,
10. Ground Level Reservoir (GLR) of 5000 cu.m capacity,
11. Plant office, Canteen & Rest shelter buildings,
12. Service roads (2.0 km) to all facilities with drains, culverts, metal crash barriers
on Valley side at turnings,
13. MCC Buildings – 2 nos., size 18m x 10m.
12.2 For the above facilities, the following civil & structural works are considered
A. Civil Works
1. RCC Silos of 4 nos. each 4000T capacity of size 8m x 8m with top elevation fixed
at RL (+) 762.25 (approx). Accordingly, earthwork, RCC quantities etc. have been
worked out. Further, for future provision, 2 nos. of silos kept and foundation &
walls up to plinth level has been considered for easy vertical rising of
superstructure only, if required, later. 25mm thick Mn steel liners are suitably
considered in the walls and hopper area of silos.
2. Earthwork excavations in over area and in foundations are considered including
back-filling. An average lead of 5 km considered for disposal of 280,000 cu.m
excavated earth. This is proposed to be dumped in an area to be identified by
project, later.
3. RCC M25 grade (conforming to IS: 456-2000) are considered in RCC silo,
Screening & Beneficiation plant, TCP, TSP, Junction houses, MCC buildings,
Office building, Canteen, Rest shelter building etc. Design mix for RCC in silo
structure shall be used.
RCC M20 grade (conforming to IS: 456-2000) is considered in retaining walls,
drains, cross drainage works etc. All steel reinforcement shall be of Fe-415
grade conforming to IS: 1786 (latest version).
In Junction houses, RCC floor slabs (M25 grade) supported on structural beams
are considered to support machines/equipment. CC flooring above hard soling
![Page 40: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/40.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 38
at ground levels of junction houses is considered including CC apron around
with drains all-round.
Mud mat PCC (1:4:8) below foundations.
4. Service roads of 10m wide (7m bitumen carpet width & 1.5m shoulders width)
with 1 in 16 longitudinal gradient and 1 in 20 on curves are considered for
access to all plant facilities and connecting to existing road. Double W-Beam
metal crash barriers on valley side of roads are considered with RCC drains &
culverts.
In the construction stage, only soling and metalling works in roads shall be
carried out with proper consolidation. The bitumen carpet work shall be done
after opening to traffic and after one rainy season.
5. Automatic Fire Detection and Suppression System (FDSS) is considered for
conveyor between down-hill conveyor system of KIOP and Tripper Conveyor.
6. NMDC shall carry out preliminary soil investigation works in the plant areas for
inclusion of the sub-soil test results in tender documents, which will serve as a
general guidance to tenderers about the sub soil type and strength in the area.
However, turnkey contractor shall carry out both detailed survey and soil
investigation works in the plant areas for doing engineering of plant structures
and their design of foundations; earth cut slopes and benches etc.
B. Structural Works
1. Supply, fabrication and erection of all structural steel works in plant buildings,
junction houses, conveyor galleries & supporting trestles, HGTU’s/VGTU’s are
considered.
2. The structural steel shall be of Grade Fe-410WA & Fe-410WB as required
conforming to IS: 2062.
Pre-coated colour galvalume sheeting (Steel grade 550 Mpa, Zn coating not less
than 120 gsm, 0.50mm TCT) in both roof and side sheeting of all houses and
galleries are considered.
FRP translucent sheeting of 2mm thick (conforming to IS: 12866 having
matching corrugations to galvalume sheets) are also considered on side
sheeting only. The quantity of FRP sheeting shall be 15% of total sheeting in
both roofing and cladding put together.
3. Both primer and finish paintings (total DFT of 205 microns) to structural steel
surfaces are considered.
![Page 41: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/41.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 39
4. Necessary modification/dismantling works at interfacing areas of new galleries
with existing conveyor nos. 504 & 411 are considered.
5. Clearance of 6m (min.) below structural conveyor gallery at road crossing points
is considered. Muck tray plates below galleries at these crossing points are also
considered.
6. Monorails of sufficient capacity at all floor levels in Junction houses / Plant
buildings to handle machine / equipment are considered. Doors of sufficient
size in all buildings / houses are considered towards approach road side.
C. Enabling Works
These works include construction of site office (semi-permanent) required
during survey, soil investigation works in the area. Construction water supply
required during construction shall be drawn from existing near-by sources.
Provision for enumeration of trees in the area is kept in the estimate.
Enumeration shall be done by project with local forest department.
12.3 Scope of Major Civil Work
The scope of major civil works includes, but not limited to, the following
• RCC Silos
• Screening & Tertiary Crushing Plant building foundation, platform slabs and
Equipment foundations
• Conveyor foundations
• Junction Houses
• RCC Elevated Thickener
• Makeup water pump house with pipe line (500 cum/hr)
• Filter water tank (63 m3/hr)
• Main water pump house with RCC recirculation tank of 5000 m3
/hr.
• Office building with store rooms
• Roads, Drains and Cross Drainage
• Electrical Substation and MCC / control room building etc.
12.3.1 General
The general specifications / details in respect of type of structures, grade of
concrete, materials, etc. for all major units have been assumed to be similar to
standard practice of civil works as per relevant latest Indian standard codes.
12.3.2 Site Grading/Plant Level Philosophy
The general topography of the site for Screening & Beneficiation-II is undulating
and surrounded by hills. Proposed plant area has been divided into number of sub-
![Page 42: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/42.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 40
areas. Finished ground levels of the unit and other non plant areas have been fixed
to minimize cut and fill. This has resulted in step formation due undulating area of
the site. Overall grading pattern is such that it facilitates good drainage.
12.3.3 Roads
The principal roads are 6 m wide whereas other roads are 4 m wide. Road width
covers carriage way and berm but excludes drain or bund. Generally the finished
road level is 300mm above FGL. Being hilly terrain, maximum permissible gradient
is limited to 1:20 and occasionally 1:16.
12.3.4 Drains
Concrete apron shall be provided around the Plant building with side drains. From
plant & non plant building area, the rain water is collected through drains in a
settling pond and finally discharged to existing Nala, as is the present practice at
Donimalai. A plant drainage system of trenches for collection and disposal of rain
water has been developed to meet environmental objectives. Drains are self
cleaning with a minimum slope of 0.2%.
Open trapezoidal and rectangular shape drains are provided along with pipe
culverts and box culverts are considered for drainage system. The sanitary waste is
collected and treated through septic tanks and soak pits. Existing network of water
supply is extended to cater to the proposed area requirements with suitable
storages, pumps and piping network.
12.3.5 Layout Plan
The overall Layout plan (Refer Plate No. 4.1) is developed keeping in view the
overall material flow and vacant areas available for locating new facilities. Efforts
were made to locate the new facilities within the land available with NMDC. The
Overall layout Plan shows all process & non process units and other Plant facilities.
12.3.6 Primary Screening Building
Primary & Secondary screening building is located on the adjoining hill near to the
existing Screening & Beneficiation plant. The arrangements of facilities are
indicated in the drawings enclosed.
12.3.7 Tertiary Crushing & Screening Building
Tertiary crushing plant building is located on the slope adjoining the Primary
Screening Building at a suitable distance to permit transfer of material to feeding
Tertiary Crusher and tertiary Screens.
12.3.8 Others
![Page 43: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/43.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 41
Outdoor switch yard is proposed for feeding the electrical loads of the new
facilities.
12.3.9 Foundation system
Open cast foundations are envisaged for all plant structures. The costing for this
Report is based on the assumptions that open foundations will be used for all
structures.
12.3.10 Water proofing for underground RCC basement structures
All underground basement structures like sumps, etc. in contact with earth shall
have standard water proofing treatment mainly consisting of the following:
� Water proofing paint to be provided in outside faces of walls and base raft in
contact with soil.
� Pressure grouting through perforated and threaded nozzles (to be inserted
during concreting) along the constructions joints only.
� All underground RCC basement structures (base raft, walls, etc.) have been
assumed to be designed as cracked section. However, water retaining
structure like underground/partly underground/on ground water reservoirs/
sumps etc. have been assumed to be designed as uncracked section as per
relevant Indian standard codes.
12.3.11 Concrete grade
In general the following concrete grades will be adopted for RCC & PCC works.
• RCC works
M – 25 RCC works for all foundation works, substructures, superstructure
elements of all plant buildings
M – 20 RCC works for drains, base slab of grade floors and intermediate
floor slab and roof slab supported on steel superstructures and
cable trenches, etc.
• PCC works
M – 10 Lean concrete below foundations, etc.
M – 15 For PCC works in drain, screed concrete, etc.
12.3.12 Building material
• Cement
In general cement shall be ordinary Portland cement conforming to latest IS
standards.
• Reinforcement steel for RCC
For all RCC work, reinforcement bars shall be TMT bars of Fe415/500 grade with
strength requirement conforming to IS 1786-1985.
• Brick/ solid concrete block masonry work
![Page 44: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/44.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 42
Brick/solid concrete block shall be of locally available best quality conforming to
the architectural requirements.
12.4 Design of steel structures
o Steel structures will be designed to meet the technological requirements and
general conditions of the projects on totality basis.
o In order to achieve maximum economy in the use of steel, the frames will be
designed as rigid portals.
o Design of steel structures will be carried out as per IS: 800-2007and/ or any
other recognized standards approved/ accepted by the agencies concerned.
Adequate ventilation will be provided in the buildings for successful operation
of the plant & equipment installed therein.
o All staircases will have a minimum width of 800 mm formed from chequered
plates or Open grid panels. The slope of staircases will be preferably within 36
to 40 degrees.
o Hand rails of platforms will be of tubes. The top rail will be 1.1 m above
platforms level. The top rail, knee rail and the posts will be tubes and toe
guards will be of steel plates (i.e. skelp plate).
o The thickness of structural elements will not be less than 6 mm (except for
webs of rolled Sections). An allowance for corrosion is kept for structures
exposed to outside atmosphere. In case of load bearing welds the thickness of
fillet welds shall not be less than 6 mm.
12.4.1 Loading
Superimposed loads to be considered in the design of steel structures are as per IS:
875-1987 in addition to technological loads, if any. Live loads for platforms, stairs,
etc. are 300 kg/m2 unless other-wise specified.
Design of buildings and structures for the effect of wind load shall be carried out as
per IS: 875 (Part-3)-1987. Design of buildings and structures for the effect of seismic
loads shall be carried out as per IS: 1893-2002.
12.4.2 Method of construction
All steel structures are generally of welded construction. However, structural
members like roof purlins and side runners will be of bolted construction.
![Page 45: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/45.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 43
12.4.3 Material of construction
o All structural steel sections and plates up to and including 20 mm thick shall
conform to IS: 2062-2006 Grade A and plates of thickness more than 20 mm
thick shall conform to IS: 2062-2006 Grade B.
o Crane rails shall conform to IS: 3443-1980.
o Non designed sections such as walkways shall be of steel conforming to IS:
977-1995 and Handrail tubes shall conform to IS: 1161-1198 and toe guard
skelp plate shall conform to IS: 1079-1994.
o Roofing and Side sheeting shall be of 0.68 mm thick Industrial Troughed
Colour Coated Steel Sheets.
o Electrodes shall conform to IS: 814-2004
o Black hexagonal bolts, nuts shall conform to IS: 1363-1992.
o Primer paints conforming to IS: 2074-2002 and Finish paints conforming to IS:
2932-1993 will be used.
12.5 Standard and codes of practices
Standard and codes of practice referred to do this job shall be as per Indian code of
practice.
12.6 Basis of Working of Quantities & Rates
The Civil & Structural works have been worked out based on the scheme layout
and site contour drawings.
The earthwork quantities for all plant buildings and service roads are calculated
based on the contours and finished floor levels shown in the scheme drawings. The
RCC and structural steel quantities have been worked out based on the geometry of
plant sizes and general sizing of various civil & structural members arrived in similar
works of Dep.10&11A, Dep.11B, Kumaraswamy Project etc.
12.7 The works and requirements listed above are indicative and may undergo change
for improvement / optimization of the scheme if any, during further engineering
stage.
![Page 46: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/46.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 44
13. ELECTRICAL & CONTROLS
13.1 Power Required
The estimated power requirement of the proposed plant is as follows:
13.2 Source of Power Supply
The incoming power supply for the proposed Screening & Beneficiation Plant-II is
planned to tap from existing Valley sub-station through over head line (11kV) /
underground HT cable(11kV), which is about 2 km distance. 3.3kV HT supply shall
be considered for the equipments whose power rating is 160kW and above. One
number 11kV HT switch board (Incomer, Power Transformer feeder & Lighting
transformer feeder and one no. of 3.3kV HT switch board, 14 feeders app.) is
envisaged. As the number of LT equipments are more, two number of intelligent LT
MCCs (80 feeders of various ratings) are envisaged. One number of 2.5 MVA,
11kV/3.3kV Power transformer, one no. 2.0 MVA, 3.3kV/440V distribution
Transformer, one no. 125 kVA, 11kV/230V Lighting Transformer is considered.
13.3 Power distribution system
The 11 kV over head power line / underground HT cable at proposed Screening &
Beneficiation plant-II from the proposed 33/11 kV substation shall be terminated in
a DP structure. For further power distribution it is envisaged to provide one number
11/3.3 kV transformer of suitable rating, 11kV & 3.3 kV switch boards, 3.3/0.433
transformer of suitable rating 125kVA, 11kV/230V, Ph-Ph for, lighting transformer,
LTMCC, MLDBs, LDBs & other equipment as required. All connections from the DP
structure onwards are foreseen by means of cables.
13.4 Design Considerations
o The design of power distribution system and selection of equipment shall be
based on the main considerations of reliability, ease of operation &
maintenance, simplicity, safety and as well as convenience of future
expansion.
o The equipment shall conform to relevant IS/IEC specifications and code of
practice to meet the operational requirements and to ensure reliable and
trouble free service in the plant.
o Electrical switchgear rooms shall be of ventilated design maintaining slight
positive pressure to exclude dust from entering. The enclosure class of
switchgears shall be IP42 or better.
• Maximum Demand (Screening &
Beneficiation Plant - II)
: 1.5 MVA
• Annual Energy Consumption : 7.2 MU
![Page 47: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/47.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 45
13.5 Basic Design Parameters
Incoming Power supply : 3.3 kV, 3 Ph, 50 Hz
Utilisation voltage : 3.3 and 415 V, 3 ph, 50 Hz
Motors rated above 160 kW : 3.3 kV, 3 Ph, 50 Hz
Motors rated 160 kW & below
and other LT consumers : 415V, 3 ph, 50 Hz
Illumination : 240 V, phase to phase, 50 Hz
Auxiliary supply : 240 V, 1Ph-Nuetral, 50Hz
Control power supply
AC : 240 V, 1Ph-Nuetral, 50Hz
DC : 110 V
System Earthing
- 3.3 kV : Resistance earthed
- 415 V : Solidly earthed
Maximum Symmetrical Short Circuit level considered for the system
- 3.3 kV bus : 13.1kA (rms) for 1 sec
- 415 V bus : 35kA (rms) for 1 sec
13.6 Major Facilities
13.6.1 HT Switchgear
11kV switch board with required incomer is also envisaged. The 3.3 kV switchgear
envisaged shall be indoor, sheet metal clad type with draw-out VCB circuit breakers
and shall be provided with necessary protection, control gear, metering and audio-
visual alarm annunciation system. The circuit breaker mechanism shall be
mechanically and electrically trip free. The circuit breakers shall be electrically
operated, stored energy type and shall be operated on 110 V DC control power
supply.
13.6.2 415 V Switchgear
The 415 V switchboard shall be sheet steel enclosed, non-draw out type in multi
tier formation. The switchboard shall be provided with incomer of draw-out type
and required number of outgoing motor and power supply feeders as per
requirement and shall include spare feeders of each type/rating. The air circuit
breaker shall be electrically operated and equipped with microprocessor based
direct acting releases for over load and short circuit as well as earth fault
protection.
The motor feeders shall be provided with MPCB/MCCBs with magnetic release,
thermal overload relay and contactor so as to provide Type 2 co-ordination. In
addition, motor feeders shall be equipped with CBCT and Earth leakage relay.
MCCBs shall be provided for outgoing power supply feeders. The MCCBs shall be
equipped with direct acting O/L, S/C releases and earth fault module with in-built
![Page 48: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/48.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 46
CBCTs. The 415V switchgear and control-gear shall conform to IS-8623 and IS
13947.
13.6.3 Transformers
The 11/3.3 kV transformer is envisaged at Screening & Beneficiation plant shall be
outdoor, ONAN, oil immersed, three phase, copper wound type as per IS-2026. The
3.3/0.433kV transformer envisaged at the Screening & Beneficiation Plant shall also
be of ONAN outdoor type’. Lighting transformer shall be of dry type with class H
insulation and temperature rise limited to class ‘B’. The rating of transformers shall
provide a design margin of 20%. Transformer magnetic core shall be made of low
loss CRGO silicon steel sheet of thickness not exceeding 0.3 mm.
The windings shall be made of electrolytic grade copper and shall be vacuum dried.
Inter turn and inter coil insulation shall be so designed that the di-electrical stress is
distributed uniformly throughout the winding under all operating conditions.
The transformers shall be designed to withstand short circuit on the secondary side
for duration of 2 seconds without any damage. Off circuit tap-changers shall be
provided for 11/3.3 kV transformer whereas for the 3.3/0.433 kV transformer, taps
with links has been foreseen. All the standard accessories such as conservator,
breather, Buchholz relay, OTI, WTI, oil level gauge, valves, explosion vent etc. shall
be provided for the 11/3.3 kV transformer. The dry type transformer shall be
provided with embedded RTDs and temperature scanner.
13.6.4 Cables
Power inside the plant shall be distributed through cables to various loads. Where
possible, cables shall be laid along wall/columns inside enclosed premises with
power cables being laid in ladder type GI cable trays and control cable laid on
perforated cable trays. Elsewhere, depending on constraints, cables may be buried
directly.
All 11 kV (UE) and 3.3 kV (UE) cables shall be heavy duty, XLPE insulated, PVC
sheathed, multi core, aluminum conductor, steel wire armoured suitable for
resistance earthed system.
Cables for 415 V systems shall be heavy duty, 1.1 kV grade, XLPE insulated, PVC
sheathed aluminum conductor, armoured / unarmoured as required. The control
cables shall be multi strand copper conductor, PVC insulated and PVC sheathed
with minimum cross section of 1.5 mm2 for control circuit and 4.0 mm
2 for power
circuit.
The HT cables shall conform to IS-7098 –1985, whereas LT power and control cable
shall confirm to IS-1554-1988 and IS-5831.
![Page 49: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/49.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 47
13.6.5 Shop Electrics
Power supply to all drives up to 160 kW and other loads operating at 415 V, 3
phase, 50 Hz system is envisaged through motor control centers (MCC). Motors
rated above 160 kW shall be supplied power from 3.3 kV H.T switchboard.
All motors shall be TEFC type and provided with class F insulation with temperature
rise limited to class B insulation, with enclosure class IP55. The motors generally
shall be squirrel cage type suitable for direct on line starting.
Slip ring induction motors is considered for cone crusher. Use of energy efficient
drive motors shall be preferred in general. Process building shall be provided with
100A, 415V interlocked receptacles as well as small power industrial socket outlets.
13.6.6 Illumination
Illumination for the Screening & Beneficiation Plant is foreseen through LDB, SLDBs
and appropriate luminaries. The LDB shall be fed from MCC through 415/230V dry
type lighting transformer LDBs shall supply power to the various sub-lighting
Distribution Boards (SLDBs) installed in various locations. The internal illumination
of process buildings shall be with HPMH light fittings. Average illumination inside
the shop building shall be 150 lux, wherever high colour rendering is required (low
colour distortion); metal halide lamp fittings shall be used.
Switchgear rooms/Control rooms shall be provided with decorative light fittings
employing CFL/LED lamps to attain illumination level of 300 lux.
All the approach roads shall have street lighting up to 100 m from plant. Area
illumination shall be provided with HPMH flood light fittings. The average
illumination level shall be 15 to 30 lux for outdoor illumination. 4 numbers of 25 m
height high mast towers are also envisaged for outdoor lighting with minimum of 8
numbers of 400 W HPMH lighting for each tower.
13.7 Instrumentation / Automation / Communication & Networking
13.7.1 Instrumentation and Automation
Instrumentation system has been envisaged with adequate measurement and
control and monitoring facilities with a view to attain efficient, reliable and trouble-
free operation of the plant and its facilities, safety of the plant, equipment and
operating personnel and user friendly man-machine communication.
For this purpose, hierarchical process control of the plant and equipment has been
envisaged. The automation equipment and devices have been identified by
different levels. The latest state-of-the art instrumentation and automation
equipment from product have been envisaged for the plant.
Instrumentation system shall generally consist of Micro-processor based two-wire
field instruments, Smart type (HART) transmitters. All the Instrumentation &
![Page 50: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/50.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 48
control equipment shall be new and supplied from the latest product-ranges of
reputed and approved manufacturers / vendors.
In addition to required measurements and controls, adequate sequential and safety
interlocks and logic functions, monitoring and display of all abnormal process
operating conditions have also been envisaged. Final control elements will be
pneumatically or electrically actuated types depending on specific application.
All Slurry pumps shall be VFD driven fitted with Flow indicating Transmitters for
better control of the operation.
Nucleonic type Density Transmitters shall be provided based on the critical
requirement.
Process Water Sumps shall be provided with Ultrasonic Level Transmitters.
Silos/Bins shall be provided with Radar type Level Transmitters along with paddle
Switch.
13.7.2 Control Hierarchy
The control and Automation system (PLC) shall be designed with geographical &
functional distribution of hardware in a multi-level hierarchy, via, Level-0, Level-1,
etc, as applicable, to meet specific plant requirements for monitoring, control,
process visualization & optimization of all the plants / shop units.
The instrumentation & automation system shall be structured in general,
considering the following hierarchical levels:
Level-0
This level is realized based on the primary sensing elements, transmitters, switches,
converters; microprocessor based intelligent systems and final control elements.
The components of this level shall be grouped and distributed geographically
around the plant as per main process equipment location.
Level-1
This level, also called supervisory level, is functionally responsible for supervision of
the individual process equipment & functions, monitoring, control, visualization and
regulation of process parameters to the desired level based on the signals
generated from the field level. This level is also responsible for processing of signals
for generating compatible control commands to control the process parameters by
activation of the final control elements.
![Page 51: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/51.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 49
Level-2
This level is realized based on the controllers & systems, input & output systems,
data base units, data communication, visualization system (HMI stations) and
interface units for connectivity to the other levels of the instrumentation &
automation system. In addition to routine PID functions, advanced process
optimization functions comprising special control algorithms, mathematical
computations etc. will be able to permit distribution of control and data acquisition
functions throughout the entire plant.
13.7.3 Appropriate Instrumentation & Automation is envisaged for the following:
a) Equipment: Storage Bins, Belt Weigh Scales, Tertiary Crusher, Screens, Metal
Detectors, Classifiers, Thickener.
b) Belt conveyors.
c) All sumps / pumping system are provided with measurements / controls for
flow, density, level, speed, pressure etc.
d) Screening & Beneficiation Plant and other units are controlled from the
Central Control Room (CCR).
Control instrumentation equipment will be microprocessor based Control System.
This will basically comprise of colored video monitors with keyboards, log, event
and alarm printers, colored hard copy units, field control stations, Input/output
Systems, power supply units, control and communication processors. Data High
Way and interfacing facilities for integrated operation with programmable logic
controllers. Suitable power supply and distribution network has also been
envisaged.
The PLC system shall be microprocessor based having functional distribution and
data base distribution sub-system wise. The system shall be modular construction
and expandable in future by adding additional modules. Programmable logic
controller (PLC) shall be with dual redundant cold standby CPU, power supply and
communication module and communication bus as minimum with additional
redundancy for I/O’s / Power supply for critical loops.
The proposed PLC system shall utilize latest and proven microprocessor-based
controller, which shall be configured to perform in real-time, such essential
functions as:
� Data acquisition / Control
� Transaction processing
� Operator interface
� Interactive graphic displays
� Database for data collection, achieving reporting and trending
� Process alarms and system diagnostics
One dedicated Control Room for controlling the operations of Screening &
Beneficiation Plant is envisaged.
![Page 52: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/52.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 50
13.7.4 Telecommunication facilities
Telecommunication system envisaged shall include:
� CCTV system.
� Public Addressing System( Loud Speaker Inter-Communication System)
13.8 Air Conditioning & Ventilation
13.8.1 General
Air-conditioning, Ventilation and Air pollution control facilities are considered for
the various electrical premises, equipment, service premises etc. of Screening &
Beneficiation Plant to ensure proper working environment both for men and
machines and to maintain necessary environmental conditions for proper storage /
working of equipment and materials.
The Air conditioning, Ventilation and Pollution control equipment to be provided
will be of industrial duty type suitable for continuous operation throughout the
year.
13.8.2 Design data
The selection of equipment / Systems is based on the following Climatic conditions:
i) Annual Max. Temp. : 45 deg C
ii) Annual Min. Temp. : 15 deg C
iii) Annual Rainfall : 416 – 865 mm
13.8.3 General Description of Facilities Provided
• Natural Ventilation
The main shop in general will be designed for Natural Ventilation with about 20 air
changes per hour. It will be ensured that the temperature in the working zones
does not exceed permissible limits during summer.
• Mechanical Ventilation
Exhaust Ventilation are envisaged with suitable fans in the areas like store rooms,
battery rooms, DG rooms, welding shop, repair shops, canteen, pump house,
compressor room, capacitor rooms and other areas as required.
• Air conditioning facilities
Suitable Air conditioners will be provided for Control rooms, VFD rooms, PLC/ RIO
Panel room, UPS rooms for heat removal and to maintain desired inside temperature
![Page 53: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/53.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 51
conditions for air conditioning. Some of the rooms in the office will be provided with
AC units for comfort air conditioning.
13.9 The requirements / facilities described / envisaged here are indicative and may
undergo change for design improvement, process and layout optimization, if any,
during further engineering stage.
![Page 54: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/54.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 52
14. ENVIRONMENTAL MEASURES
14.1 Forest Clearance
The proposed new Screening & Beneficiation plant-II is located in forest area near
existing tailing dam. About 13.0 ha of forest land is required for construction of
Screening & Beneficiation plant-II and allied facilities. On 11/9/2008, Donimalai
project has applied for obtaining diversion of 177.63 ha of forest land which
includes 10.00 ha for construction of new Screening & Beneficiation plant at
Donimalai and balance 167.63 ha pertains to un-diverted forest land of
Kumaraswamy ML area to Chief Conservator of Forests cum Nodal Officer,
Bengaluru. After processing the application in State Forest Department, Bengaluru,
Dy. Conservator of Forests, Bellary is directed to examine the proposal and submit
the proposal with full details. The survey and Demarcation work completed in the
month of April’10 and also tree enumeration by 30/9/10. On 18/2/10, Range Forest
Officer, Sandur submitted the detail inspection report to Asst. Conservator of
Forests, Bellary. The proposal is pending at office of ACF, Bellary for onward
submission to State Forest Department through DCF & CF, Bellary for obtaining
approval of State Government for forwarding the proposal to Ministry of
Environment & Forests (MOEF), New Delhi for seeking forest clearance.
The forest clearance may take considerable time as the application is required to
pass through various levels in State and Central Government.
14.2 Environmental Clearance
The proposed Screening & Beneficiation plant is going to adopt wet screening
operations for obtaining high quality grade ore. The wet operations include mineral
processing system such as spiral classifiers, de-watering screens, hydro-cyclones,
thickeners, etc. The wet screening operations at Screening & Beneficiation plant
attract EIA Notification 2006 which requires prior Environmental Clearance for
construction of project. The capacity of Screening & Beneficiation plant is 10 MTPA
and hence, it shall be categorised as “Category A” project requiring Environmental
Clearance from GoI, MoEF, New Delhi. As per MoEF’s circular no; J-
11015/200/2008.IA.II (M) dated 31/3/2011, MoEF will consider for issue of
Environmental Clearance only after obtaining 1st
stage Forest clearance of the area
involved in the proposal. The procedures involved in obtaining EC are given below.
1) Appointment of EIA Consultant duly accredited with Quality Council of India
for preparation of EIA reports for mineral processing plant sector for category
- A projects.
2) Submission of Form-I along with pre-feasibility report to MoEF, GoI, New
Delhi.
3) Attending Expert Appraisal Committee (Mining) for obtaining terms of
reference for preparation of EIA report.
4) Preparation of Draft EIA report and submission to Karnataka State Pollution
Control Board, Bengaluru for organizing Environmental Public Hearing.
![Page 55: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/55.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 53
5) Finalization of EIA report based on public hearing proceedings and submission
to MoEF, GoI, New Delhi.
6) Attending EAC meeting for presentation and clarifications
7) Obtaining Environmental clearance from MoEF.
The entire process may take minimum of one year time in getting EC. It is pertinent
here to mention that MoEF will consider for issue of EC only after receipt of 1st
stage Forest clearance for area involved for Screening & Beneficiation Plant.
14.3 Consent for Establishment (CFE)
During the process of Environmental clearance, application under Air (Prevention &
Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act,
1974 are to be submitted to KSPCB, Bengaluru for obtaining Consent for
Establishment (CFE) for construction of the plant.
14.4 Environmental Control Measures
The proposed Screening & Beneficiation Plant mainly comprises of silos, apron
feeders, cone crushers, double deck screens, inter connecting conveyors, spiral
classifiers, cyclones, tailing thickeners, etc. The tertiary crusher will be operated in
dry condition and Screening & Beneficiation plant will be in wet condition. Hence,
an environmental management plan suitable to tackle air, noise and water
pollution arising from these plants is envisaged.
High capacity silos are envisaged as storage bunkers in the Screening &
Beneficiation plant instead of open stockpile in order to prevent dust generation
and which are eco-friendly.
A comprehensive environmental management plan as intended for the entire
Screening & Beneficiation plant is detailed below. In addition to the control
measures envisaged for primary pollutants like air, noise and water, house-keeping
is also addressed in this chapter to maintain the plant in an environmental friendly
condition.
14.5 Air Pollution control
To prevent air pollution in the plant, suitable integrated dust suppression systems
are to be adopted. Enclosures are to be provided for the conveyors & junction
houses and green barriers around the Plant shall be developed, similar to the
existing practice. Also, air pollution measuring shall be monitored regularly at all
such sources in plants.
Particulate matter (PM) generation at all dry material transfer points is expected to
increase suspended particulate matter (PM10 & PM2.5) in the surrounding
environment. The major sources of dust hazard in the Screening & Beneficiation
Plant are as follows:
![Page 56: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/56.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 54
� Feeding point of tripper conveyor
� Apron feeders, Cone crusher, conveyor feed points and discharge points
� Ore transfer points and operation of cone crusher
� Dust generation from conveyors while running
14.5.1 Proposed dust control system at crusher house
The iron ore transportation to crusher bound to generate dry fines while
transferring material into crusher. The generation of dry fines in the form of
particulate matter as respire-able dust is expected to travel some distance from the
crusher area and will suspend in the environment for longer time if it is not
controlled at the generation point itself. Since the proposed crusher house is a
covered area, dry fog system is envisaged at crusher house.
Fog based system is generally provided to limit water consumption used for dust
suppression at above dust generation points. In order to reduce plant water
requirement, dust suppression in particular dry fog system is envisaged.
In this system, compressed air and water based dual fluid works on the principle of
agglomeration. Dust particle generated from the material handling become air
borne and are made to pass through a blanket of extremely fine fog jet. The dust
particle and the fog jet collide and adhere to each other. This increases their mass
of the dust. After a series of such collisions the dust particles mass become heavier.
The system employs compressed air for atomization of water particle. Water at the
pressure of 1.5 ~ 2 kg/cm2 and compressed air at the pressure of 5 ~ 6 kg/cm
2 are
supplied at the atomizing spray point.
14.5.2 Following dust suppression system is suggested for other places of Screening &
Beneficiation Plant
For loaded belt conveyors (Starting and end point of the belt) and for screening
area, dry fog system is envisaged.
In addition to the above, pressurised filtered air supply system and mechanical
exhaust system will be provided at suitable places.
14.6 Water Pollution Control System
Water pollution in the form of iron ore tailings is expected from the plant. These
tailing are non hazardous in nature. The tailings will be impounded in new Tailing
dam. It is expected that about 85-90% of the Screening & Beneficiation plant’s
process water requirements will be met by recycled process water. A recirculation
tank with a live storage capacity of 5000 m3 is envisaged to receive the clean water
from tailing thickener. The make-up water requirement for the process will be
brought by pipeline from 5000m3 make-up water storage tank located at +745 m
level near to the Screening & Beneficiation plant. The make-up water demand for
![Page 57: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/57.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 55
the plant is expected to be about 370 m3/hr. However, the same will be about 500
m3/hr for treating 10 MTPA iron ore.
All unit operations in the Screening & Beneficiation Plant will be carried out in wet
mode. However, the tertiary crusher and screening unit will be working in dry
condition. Tailings will be generated from the Screening & Beneficiation Plant at a
rate 150 m3/hr. Tailings thickener overflow water about 2100 m
3/hr will be recycled
back to the process.
14.7 Noise control system
All the noise generating equipment like crusher, belt pulley, motors will be housed
or provided with acoustic barriers or isolating material capable of reducing noise to
desire level. To arrest and minimise the noise produced beyond acceptable levels
from running machinery in the plant, closed enclosures will be made for the plant
buildings / junction houses. Further, necessary measures to contain noise levels as
per IS/statutory rules will be ensured. Also, noise level measuring shall be
monitored regularly at all such sources in plants.
14.8 Green belt development
Afforestation measures shall be taken-up through developing barrier platforms all
around the plant. To maintain ecological balance in the area, plantations of suitable
species of ever green/locally grown trees shall be made. Adequate tree plantations
shall substantially abate dust pollution, filter the polluted air and ameliorate the
plant environment without any hazards in public health.
The Screening & Beneficiation Plant includes development of a green belt that is
expected to reduce noise levels, limit the propagation of fugitive dust and produce
a better occupational / aesthetic environment. The implementation of a green belt
around the plant and side of the roads and the selection of plant species will be
carried out in co-operation with Horticulture Department.
![Page 58: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/58.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 56
15. MANPOWER PLANNING
15.1 Organizational Structure
The proposed Screening & Beneficiation Plant shall be headed by one overall plant
in-charge. Each shift in-charge shall be directly reporting to the Plant in-charge.
15.2 Manpower
The requirement of manpower for the operation and maintenance of the proposed
Screening & Beneficiation Plant has been estimated by considering the following:
• Capacity of the Crushing & Screening & Beneficiation Plant complex
• Type of equipment to be installed
• Degree of automation envisaged
• Number of operating shifts to achieve the rated capacity
• Requirement of personnel as off and leave reserve etc.
The overall manpower requirement has been estimated at 81. In addition, there
will be some contract employees.
Apart from operation and maintenance (mechanical and electrical), the proposed
manpower also caters to preventive maintenance and shut down operations.
The summary & details of category-wise manpower requirement other than
contract employees is given below:
Production and Maintenance staff:
� Executives : 10 Nos.
� Workmen/Non-executives : 71 Nos.
�
15.2.1 Manpower Details – Executives
Sl.
No. Description
No. of
shifts
No. of
persons
per shift
Reserve Total Remarks
1 Overall In-charge 1 1 - 1 General Shift
2 Assistant 1 1 - 1 General Shift
3 Electrical/Electronics
Engineer 3 1 1 4 3 shifts
4 Shift In-charge 3 1 1 4 3 shifts
Total 10
![Page 59: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/59.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 57
15.2.2 Manpower Details – Workmen (Non-Executives)
Sl.
No. Description
No. of
shifts
No. of
persons per
shift
Reserve Total Remarks
1 Screening &
Beneficiation Plant
Operation
3 14 3 45 3 shifts
2 Maintenance crew 1 8 - 8 General Shift
3 Electrician &
control room 3 4 2 14 3 shifts
4 Truck driver 1 1 - 1 General Shift
5 Crane operator 1 1 - 1 General Shift
6 Misc./Stores 2 1 - 2 General Shift
Total 71
15.3 Recruitment
After the project is approved, plant in-charge and a few key personnel of different
categories shall have to be diverted from the existing DIOM to form the nucleus of
the Screening Plant for further development and to take necessary advance actions
for project construction.
The Executives would be placed during the construction of the project itself, as they
have to get acquainted with the plant and equipment for efficient running of the
concerned units.
Some of the construction personnel can progressively be absorbed with the
tapering of the construction work, particularly in the maintenance and services
areas of the plant. A certain portion of junior executives and supervisory staffs may
have to be recruited during the construction stage itself as acquaintance with
equipment erection will be very much beneficial for them in running the units later.
15.4 Training
All the Executives are suggested to be trained, mostly in the operation and
maintenance of plants of similar type. They in turn would share the technical
knowledge attained during the training with their subordinates. At least 3-4 months
before the commissioning of the project, these employees ought to complete their
training and be associated with the commissioning activities of the units.
![Page 60: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/60.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 58
16. ANNEXURES
Annexure Description Page No.
I.1 Mechanical cost estimate 59
I.2 Electrical cost estimate 61
I.3.1 Civil & structural cost estimate 62
I.3.2 Abstract of quantities of Civil & Structural works 63
I.4 Cost estimate of Tailing Dam 64
![Page 61: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/61.jpg)
ANNEXURE I.1
Rs. In Lakhs
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 246.02 Estimated as per Annexure-(i)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
4 Nos. 243.02 Estimated as per Annexure-(ii)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 84.41 Estimated as per Annexure-(iii)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 135.86 Estimated as per Annexure-(iv)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 79.98 Estimated as per Annexure-(v)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 88.36 Estimated as per Annexure-(vi)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 158.36 Estimated as per Annexure-(vii)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 131.64 Estimated as per Annexure-(viii)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 38.15 Estimated as per Annexure-(ix)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 130.33 Estimated as per Annexure-(x)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 59.06 Estimated as per Annexure-(xi)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 81.56 Estimated as per Annexure-(xii)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 42.91 Estimated as per Annexure-(xiii)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 69.11 Estimated as per Annexure-(xiv)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 76.73 Estimated as per Annexure-(xv)
Conv. Tecnological structure, idler assys., pulleys, frames, counter
weight (as applicable), skirt boards, safety switches, LCS, drive unit incl.
motor etc.,
1 No. 28.54 Estimated as per Annexure-(xvi)
17 Tripper conveyor Feeder 1 No. 150.12
As per HQMM/2050-09/11A049/2234
16.6.11 with Price escalation as per RBI
Index
16
Conveyor 826 (1200 mm wide X 6.5 m Length)
15
Conveyor 814 (1200 mm wide X 57.5 m Length)
Conveyor 837 (1200 mm wide X 55.2 m Length)
11
Conveyor 854 (1200 mm wide X 51.2 m Length)
12
Conveyor 838 (1200 mm wide X 44.2 m Length)
13
Conveyor 852 (1200 mm wide X 30.8 m Length)
Conveyor 829 (1200 mm wide X 176 m Length)
Conveyor 823 (1200 mm wide X 135 m Length)
Conveyor 825 (1200 mm wide X 18 m Length)
Conveyor 832 (1200 mm wide X 90 m Length)
9
10
Basic Cost at works
April ' 2013
Conveyor 812 (1200 mm wide X 103 m Length)
Conveyor 801 including tripper (1200 mm wide X 432 m Length)
Conveyor 806 (1200 mm wide X 36 m Length)
Conveyor 809 (1200 mm wide X 110 m Length)
Conveyor 810 (1200 mm wide X 188 m Length)
Conveyor 813 (1200 mm wide X 115 m Length)
Sl. No.
MECHANICAL COST ESTIMATE FOR SCREENING & BENEFICIATION PLANT - II AT DONIMALAI
Remarks #Equipment Description Qty. Unit
2
3
A
5
4
1
6
7
8
14
* Annexures are with Mech. Engg. Dept.
![Page 62: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/62.jpg)
Rs. In Lakhs
Basic Cost at works
Conveyor 801 including tripper (1200 mm wide X 432 m Length)
Sl. No. Remarks #Equipment Description Qty. Unit
A
118 Apron Feeders 4 No. 400.00
As per HQMM/2050-09/11A049/2234
dt 16.6.11 with Price escalation as per
RBI Index
19 Vibrating Screens (Primary, secondary, tertiary & DWS) 14 Nos. 695.22
HQMM/1002-06/10C904; 908 &
910/1079 dt. 26.6.08 with price
escalation as per RBI Index
20 Vibrating feeders 2 Nos. 58.48HQMM/11057-07/10C 906 & 909/1119
dt 14.05.2009
21 Handling Facilities (EOT cranes & manual Hoists) 1 Lot 132.00 Estimated as per Annexure-(xviii)
22 Weightometers 7 Nos. 35.00 Lumpsum
23 Cross belt magnetic separator 2 Lot 80.00 Estimated as per Annexure-(xxii)
24 Classifiers 4 No. 220.00HQMM / 3019-06 / 16CN 36&44 /
Dt.30.03.11
25 Horizontal Belt Filters(HBF) 3 No. 1761.00Budgetary quote and price esclation as
per RBI Index
26 Cyclone feed tanks 2 Nos. 15.00 Estimated as per Annexure-(xix)
27 Centrifugal Slurry pumps 5 Nos. 475.00 Lumpsum
28 Hydro Cyclones 17 Nos. 192.27HQMM/3011-07/16CN61/ dt. 23.5.12
and price esclation as per RBI Index
29 Tailing Thickner 1 Nos. 106.00Budgetary quote dt. 14.10.10 and price
esclation as per RBI Index
30 Launders 1 Lot 50.00 Lumpsum
31 Chutes and Liners 1 Lot 410.32 As per Annexure - (xx)
32 Belting for all the above mentioned conveyors 1 Lot 348.62 As per Annexure-(xxi)
33Miscellanous (Tools & Tackles + Vulcanising machine & material + Dust
control system as required)1 Lot 200.00
34 Tertiary Crushers 2 No. 2389.01As per HQMM/2020-08/11X027/2189
Dt. 29.7.10 & esclation as per RBI index
35
a Spares (7.5% on Sl. No. 1 to 30) - Indigenous component - Lot 511.73
b Spares (25% on Sl. No.32) - Import component - Lot 597.25
36 Total Supplies and Spares - Indegenous (Sl. No. 1 to 33 & 35.a) - - 7534.80 -
37 Total Supplies and Spares - Imported (Sl. No. 34 & 35.b) - - 2986.26 -
38Total Supplies including Spares (Indegenous) + *Taxes & Duties on the
same (@20.14% on Sl. No.36)- - 9052.31 -
39Total Supplies including Spares (Imported) + *Taxes & Duties on the
same (@44.72% on Sl. No. 37)- - 4321.72 -
B 40TOTAL BASIC COST OF SUPPLIES (excluding spares and taxes & duties) (I
to 34)- - 9412.08 -
C 41 Provision towards system engineering by contractor (5% of Sl. No. 40) - - 470.60 -
D 42 Erection & Commissioning (10% on Sl. No. 40) - - 941.21 -
E 43 Supervision charges for E & C of Crusher & HBF 46.17 As per Annexure xxii
F 44 Total Mechanical Cost (38 + 39 + 41 + 42 +43) - - 14832.01 -
148.32 CRORES
Spares
-
COST ESTIMATE FOR PLANT EQUIPMENT (MECHANICAL) IS ABOUT Rs.
A
* Annexures are with Mech. Engg. Dept.
![Page 63: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/63.jpg)
ANNEXURE I.2
S.N Description Unit Qty Cost/ unit Amount in Rs.
1 Constuction of OH 11KVLine / Under ground cable
(3x300 sq.mm UE) from valley sub station to the
SP-2 switchyard
KM 3 3125000 9375000
2 One no. HT 3.3KV switch Boards (14no. including
incomer)
NO 1 11200000 11200000
3 One no. HT 11KV switch Board (three for incomer
& T/Former feeder)
NO 1 2400000 2400000
4 Intelligent LTMCC (app. 37+37 feeders of various
rating and etc.,) @1.05lakhs
Lot 8,400,000 8,400,000
5 Distribution Transformer with OLTC
2.0MVA,3.3KV/440V
NO 1 3000000 3000000
6 Power Transformer with OLTC
2.5MVA,11KV/3.3KV for HT
NO 1 3750000 3750000
7 Automation / PLC for the plant (750 I/O appr. ) Lot 24000000
8 Power cables ( HT , LT) of different sizes as per
requirement
Lot 30000000
9 Cable trays 5Km Km 5 450000 2250000
10 Instruments Lot 12000000
11 Instrumentation & Control cables Lot 18000000
12 IP based CCTV System app. 45cameras Lot 10300000
13 VVVF Drives for Vibrating feeders (4+1) and
Classifiers (4)
NO 9 1500000 13500000
14 UPS 12KVA, with batteries 150AH NO 1 1000000 1000000
15 110V Battery Charger(30A) with batteries (180AH) NO 2 2500000 5000000
16 Capacitor Bank HT Set 1 1200000 1200000
17 Lighting Transformer 11KV/230V ac, 125KVA NO 1 400000 400000
18 IP based PA system Lot 2000000
19 Illumination(Lighting fixtures, 25m High mast
towers 2no. etc)
LS 6000000
20 Earthing LS 3000000 3000000
21 3.3KV NGR Set 2 100000 200000
22 Utilities (AC, Exhaust fans etc.,) LS 500000
23 Enabling works
a Construction Power (app 300KVA, 11KV/440V
including cables, DB's etc)
NO 1 750000 750000
b Illumination LS 500000 500000
24 Miscellaneous 5% 8373750
A Total cost 177098750
A1Total cost with Esclation of 0.8% as per RBI Index 178550959.8
B
Provision towards system engineering by
contractor (5% of 'A1')
8927547.988
C Total Cost + Taxes & duties @ 20.15% on 'A1' 214528978.1
D Erection & Comissioning @15% of 'A1' 26782643.96
Total B + C +D 250239170.1
COST ESTIMATE FOR PLANT EQUIPMENT (ELECTRICAL) IA ABOUT RS.25.02 CRORES
ELECTRICAL COST ESTIMATE FOR SCREENING & BENEFICIATION PLANT - II AT DONIMALAI
![Page 64: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/64.jpg)
ANNEXURE I.3.1
April 2013
Cost estimate
during Sep. 2012.Remarks
(Rs. Ps)(1) (2) (3) (5)
1 CIVIL WORKS 613760037.30
2 STRUCTURAL WORKS 405684651.25
3Provision towards system engineering by
contractor (5% of '1+2')50972234.43
4
Automatic Fire Detection and Supression
System(FDSS) in connecting Down hill
Conveyor to RCC silo (L=0.5Km approx)
(Piping, civil, electrical, mandatory spares
etc.,)
12521000.00
Amount calculated on pro-rata
basis based on estimate for the
Dep-5 Conv no.28 & 29 (Rs
250.42Lakhs/KM) during May
2012.
5Enabling works. (Construction water & Site
office accommodation) -LS-1000000.00 Lumpsum
6 Survey works 200000.00 Lumpsum7 Soil Investigation work 500000.00 Lumpsum
8Enumeration of Trees for 1 hectares of
area @ 7 Lakhs per hectare.700000.00 Rate details from Env. Deptt.
9 Grand Total Amount = Rs. 1085337922.97
Say Rs. 108.53Crores
COST ESTIMATE FOR CIVIL & STRUCTURAL WORKS IS ABOUT Rs. 108.53 CRORES
FOR CIVIL & STRUCTURAL WORKS COST ESTIMATE FOR SCREENING & BENEFICIATION PLANT -II
AT DONIMALAI.
Refer Annexure I.3.2
Sl. No. Item Description
![Page 65: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/65.jpg)
April 2013
Sl. AmountNo. (Rs. Ps)(1) (2) (3) (4) (5)
1 Earthwork Cu.m 279794.47 56819933.25
2 PCC Cu.m 2824.66 11359895.03
3 RCC grade Cu.m 18292.20 116519600.12
4 Reinforcement Steel MT 2466.13 153516484.41
5 Anchor Bolts MT 27.58 1869938.57
6 Structural Steel MT 4486.05 296701703.21
7Galvalume Sheet 0.5mm TCT for both Roofing
& Cladding Sq.m 40844.34 34717688.75
8 FRP translucent sheeting-Cladding (2mm thk.) Sq.m 5094.89 8389841.32
9 Other civil works 133349100.89
10
Miscellaneous works (pipes, valves with
fittings for drinking water, process water,
pump house with Pumps & motors, service
water, finishing works,etc., (@ 5% of total
civil works) ( B)
40662209.28
853906394.84
Cost as on
Sep. 2012
Escalation
13.98 on 70%
material
SRNPP 9.60% Total
CIVIL WORKS (Sl. No.1+2+3+4+5+9+10) = 514097161.56 50309548.23 49353327.51 613760037.30STRUCTURAL WORKS (Sl. No.6+7+8) = 339809233.28 33253731.57 32621686.40 405684651.25
Annexure I.3.2
Total = Rs.
Abstract of Quantities of Civil & Structural works
Item Description Unit Quantity
![Page 66: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/66.jpg)
Annexure I.4
Item Rate Amountno. (Rs. Ps) (Rs. Ps)(1) (2) (3) (4) (5) (6)
Item rate analysis based prevailing market rate on April 2012 and DSR 2007- CPWD rate analysis.
1
EW in rough excavation & banking earth in
layars(20cm) Cu.m 287.40 783137.50 225073717.50
(Ref:Item no. 2.2.1/DSR '12)2 Transportation of Earth (Avg 3Km lead) Cum 125.92 783137.50 98612674.00
(Ref:Item no. 1.1.2/DSR '12)3 Extra for compaction of MDD 95% Cum 7.75 783137.50 6069315.63
(Ref:Item no. 16.2/DSR '12)
4Earth fill in core imprevious material & Cut of
trenches Cu.m 600.00 96702.00 58021200.00
(Ref:BHQ/TD Est /Aug 2012)
5 S/L of sand Cum 749.30 19740.00 14791182.00
(Ref: Item no.2.27/DSR'12)
6 S/S. of boulders 22.5cm thk….. Cu.m 607.55 705.00 428322.75
(Ref:Item no. 16.72/DSR' 12)
7 Jungle clearance sqm 4.82 70500.00 339810.00
(Ref: Item no.2.31/DSR'12)
8 Earth work in foundation & Trenches Cum 130.80 5640.00 737712.00
(Ref:Item no. 2.8.1/DSR '12)9 Earth work in stripping upto 300mm sqm 37.86 70500.00 2669130.00
(Ref:Item no. 2.1.1/DSR '12)10 Turfing in th D/S side Sqm 15.10 33370.00 503887.00
(Ref:Item no. 19.82/ BPWD SOR 2011)
11 Stone pitching sqm 336.50 940.00 316310.00
(Ref:Item no. 16.1/DSR '12)
Total Amount ( A ) 407563260.88
Miscellaneous works (Core, pipes, valves with
fittings, fillter works,etc., (@ 5% of total civil
works) ( B)
20378163.04
427941423.92With an esclation of 13.98% as per RBI index on (C ) 487767634.98
SRNPP factor @ 7.08% on (C ) 30298252.81Grand Total 518065887.80
Say Rs. 51.81Crores
Gross Amount (C)=(A)+(B) = Rs.
COST ESTIMATE FOR TAILING DAM FOR PROPOSED SCREENING & BENEEFICIATION PLANT-II
Item Description Unit Quantity
(Rate Analysis based on DSR 2012)AT DONIMALAI.
![Page 67: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/67.jpg)
PRE FEASIBILITY REPORT FOR CONSTRUCTION OF SCREENING & BENEFICIATION PLANT-II,
SLIME DISPOSAL PIPELINES AND TAILING DAMS FOR DIOM & KIOM, DONIMALAI JUNE – 2014
NMDC Limited, Hyderabad Page 65
17. LIST OF PLATES
SL NO PLATE
NO. DRAWING TITLE
DRAWING
NO.
1 1.1 Material & water Balance diagram (Sheet 1 of 2) 3-2-136
2 1.2 Material & water Balance diagram (Sheet 2 of 2) "
3 2.1 Equipment flow sheet (Sheet 1 of 2) 3-2-135
4 2.2 Equipment flow sheet (Sheet 2 of 2) "
5 3 Conceptual layout of proposed Screening & Benf. Plant-II 3-2-137
6 4.1 Screening & Beneficiation Plant-II layout (Sheet 1 of 2) 3-2-138
7 4.2 Screening & Beneficiation Plant-II layout (Sheet 2 of 2) "
8 5.1 GA of Silo & Tripper conveyor 801 (Sheet 1 of 3) 3-2-139
9 5.2 GA of Silo & Tripper conveyor 801 (Sheet 2 of 3) "
10 5.3 GA of Silo & Tripper conveyor 801 (Sheet 3 of 3) "
11 6 Silo, Screening & Beneficiation Plant-II Arrangement 3-2-140
12 7.1 GA of Screening & Beneficiation Plant-II (Sheet 1 of 5) 3-2-141
13 7.2 GA of Screening & Beneficiation Plant -II (Sheet 2 of 5) "
14 7.3 GA of Screening & Beneficiation Plant -II (Sheet 3 of 5) "
15 7.4 GA of Screening & Beneficiation Plant -II (Sheet 4 of 5) "
16 7.5 GA of Screening & Beneficiation Plant -II (Sheet 5 of 5) "
17 8 GA of TC Plant conveyors 3-2-142
18 9 GA of Tertiary Crushing Plant 3-2-143
19 10.1 Classifier & DWS Plan & Elevation (Sheet 1 of 2) 3-2-144
20 10.2 Classifier & DWS Plan & Elevation (Sheet 2 of 2) "
21 11 Plan of Horizontal Belt Filters (HBF) 3-2-145
22 12 GA of fine ore conv. 829 3-2-146
23 13 GA of lump ore conv. 832 3-2-147
24 14 Proposed Tailing dam location 3-2-148
25 15 Land required for proposed Screening & Beneficiation Plant-II 3-2-131
26 16 Time Schedule -
a) All dimensions and grid spacing are in millimeters unless specified otherwise.
b) All levels and contours are in meters unless specified otherwise.
c) All dimensions & elevations are indicative only and shall be reviewed during engineering stage.
d) Design & construction of all discharge chutes as shown are indicative.
e) Equipment/Conveyor’s drive location, its arrangement and type as shown is indicative only.
f) Minimum 1000mm clear passage shall be considered all around the equipment located in
buildings & Transfer House.
g) Trestles locations as shown are indicative only.
h) Maintenance hoists with monorail beams shall be considered, wherever required.
i) Staircase in all the buildings/houses shall be provided for access to all the floors and a good road
network for approaching all the buildings/transfer houses shall be planned suitably.
j) Dust suppression/ventilation/sampling units etc., are not shown in the drawing. However the
same shall be considered as per requirement.
k) Shall review the individual equipment / components / items / buildings / structures / system
during engineering stage for any improvements to ensure satisfactory working of the same for
the proposed application.
![Page 68: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/68.jpg)
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 69: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/69.jpg)
LUMPS
819.00 55.25
874.25 93.68
FINES
938.34 156.23
1094.57 85.73
NMDC LIMITED
1440
1116.90
736.38
321.58
1011
Input
Output
Make Up
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 70: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/70.jpg)
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 71: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/71.jpg)
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 72: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/72.jpg)
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 73: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/73.jpg)
801
806
804 805
808
811
813
810
814
824823822
821
820
829
802
832
837
835
836
813
805
809
812
825
826
838
851
852
854
ITEM NO DESCRIPTION QTY
1
1
1
1
1
1
ITEM NO DESCRIPTION QTY
857
NMDC LIMITED
841855848 843846
![Page 74: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/74.jpg)
![Page 75: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/75.jpg)
NMDC LIMITED
801
802
801
800
723
727
801
802
804
805806
801
![Page 76: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/76.jpg)
NMDC LIMITED
801
805
802
804
806
801
801
805
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 77: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/77.jpg)
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 78: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/78.jpg)
NMDC LIMITED
808
809
810
811
812 813 814
815804
805
806
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 79: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/79.jpg)
NMDC LIMITED
824
808
809
810
811
812 813 814
815
824
808
811
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 80: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/80.jpg)
824.1 824.2 808.C808.D 808.B 808.A
809
810
811.C811.D 811.B 811.A
813
814
812
829
825826
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 81: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/81.jpg)
829
814 813812 813 814
812
829
814
825
826
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 82: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/82.jpg)
824.2
824.1
809
810
810
823
823
815
809
810
823
824809
829
825
826
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 83: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/83.jpg)
809
812
NMDC LIMITED
813
809
832
FOR TEFR PURPOSE & INDICATIVE ONLY
813812
![Page 84: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/84.jpg)
820
821.1821.2
822.1822.2
823
810
NMDC LIMITED
824.1824.2
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 85: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/85.jpg)
NMDC LIMITED
820
821.1821.2
822.1822.2 823
810
827
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 86: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/86.jpg)
811 814
837
835
836
841855
838
848
NMDC LIMITED
813
843846
![Page 87: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/87.jpg)
835836
837
NMDC LIMITED
841
840
839
815
848
847
![Page 88: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/88.jpg)
838
851
852
854
NMDC LIMITED
829
![Page 89: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/89.jpg)
NMDC LIMITED
FOR TEFR PURPOSE & INDICATIVE ONLY
![Page 90: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/90.jpg)
NMDC LIMITED
839
809
812
![Page 91: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/91.jpg)
THIS DRAWING IS N.M.D.C.'S PROPERTY AND MUST NOT BE USED EXCEPT IN
CONNECTION WITH OUR WORK. ALL RIGHTS OF DESIGN OR INVENTION RESERVED
![Page 92: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/92.jpg)
THIS DRAWING IS N.M.D.C.'S PROPERTY AND MUST NOT BE USED EXCEPT IN
CONNECTION WITH OUR WORK. ALL RIGHTS OF DESIGN OR INVENTION RESERVED
![Page 93: 3. Final PFR 2.6environmentclearance.nic.in/writereaddata/Online/TOR/0_0_06_Sep_2… · Existing Plant cannot process iron ore beyond 7 MTPA. Moreover, it has outlived its life, resulting](https://reader036.vdocuments.site/reader036/viewer/2022081615/5fd2a8de320f8113143f2b8d/html5/thumbnails/93.jpg)
YEARMONTH J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
1 Preparation & Finalisation of TEFR2 Approval of TEFR Start date of Project ‐ July 20133 Forest Clearance and Enviromental Clearance4 Appointment of agency for soil investigation5 Soil Investigation and submission of report6 Getting additional power supply (as required)7 Appointment of EPCM consultant8 Preperation of Tender document(s) for LSTK
package(s) for construction of Plant9 Invitation of bids and order placement for
package(s) for Plant construction 10 Engineering, manufacture, supply & construction
of Plant11 Trial Runs & Commissioning (Apr' 2017)
9Sl. no. Activity
3 6 3912 15 18 21 24 27 30 33 362012 20172013 2014 2015 2016
Plate No. 16Time schedule
6042 45 48 51 54 57