performance-based leakage reduction and management services sawaco zone 1

49
Performance-based Leakage Reduction and Management Services SAWACO Zone 1 Training and Transfer of Technology

Upload: zaina

Post on 23-Feb-2016

30 views

Category:

Documents


0 download

DESCRIPTION

Performance-based Leakage Reduction and Management Services SAWACO Zone 1 Training and Transfer of Technology. Outline. Classroom Training Modules Field Training Modules . Outline. Classroom Training Modules Module 1 DMA Design Module 2 DMA Construction and Commissioning - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

Performance-based Leakage Reduction and Management Services

SAWACO Zone 1Training and Transfer of Technology

Page 2: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

22

Outline

Classroom Training Modules

Field Training Modules

Page 3: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

33

Outline

Classroom Training ModulesModule 1 DMA Design

Module 2 DMA Construction and Commissioning

Module 3 Active Leakage Control

Module 4 Pressure Management

Page 4: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

44

Classroom Training Module 1DMA Design Definition of District Metering Area (DMA)

is a world-wide accepted tool to operate and manage a network area wherein hydraulic boundary is defined by a system of Isolation Valves (IV) an flow Meters

a discrete area of a water distribution network. It is usually created by closing boundary valves so that it remains flexible to changing demands. However, a DMA can also be created by permanently disconnecting pipes to neighboring areas. Water flowing into and out of the DMA is metered and flows are periodically analyzed in order to monitor the level of leakage

Page 5: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

55

Classroom Training Module 1DMA Design Definition of District Metering Area (DMA)

has water service connections ranging from 500-3,000can be categorized into the following types:

Single inlet DMAs Multiple inlet DMAs Cascading DMAs

Page 6: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

66

Classroom Training Module 1DMA Design General Guidelines in DMA Design

DMAs should not include trunk mains or storage tanksEach DMA should preferably be supplied through a single,

metered supply pointDMA boundaries should be created by closing boundary

valvesVariations in ground elevation should be minimal across the

DMAThe types of consumers and their respective water supply

requirements should be assessed

Page 7: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

77

Classroom Training Module 1DMA Design General Guidelines in DMA Design

Legal regulations governing minimum pressures, local constraints due to topography and height of buildings as well as fire fighting requirements have to be respected

Closing boundary valves to create DMAs will increase the number of dead-end pipes

Pressure management plays a key role in leakage management

Page 8: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

88

Classroom Training Module 1DMA Design Planning, Design and Engineering

Planning and

Prioritization

Field Survey

Preliminary Design

Hydraulic Simulation

Draft Report Final report

Page 9: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

99

Classroom Training Module 1DMA Design Planning, Design and Engineering

Planning and Prioritization

• Preliminary design by Manila Water design team in coordination with

MWH network modelling team

• Prioritization by highest leakage potential

• Manila Water prioritization was initially based on the following:• Pipe material• Pipe age• Number of leak occurrences

Page 10: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1010

Classroom Training Module 1DMA Design Planning, Design and Engineering

Field Survey

• Data gathered during site investigation:• Location and status of existing valves, fire hydrants and blow-offs.• Big consumption customers• Pressure• Road classification• Traffic

Page 11: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1111

Classroom Training Module 1DMA Design Planning, Design and Engineering

Preliminary Design

• Preliminary design of 119 DMAs in the Feasibility Study done in 2005

• One line meter per DMA with a range of 1000-2000 service connections

• DMAs per District• District 1 – 24 DMAs• District 3 – 29 DMAs• District 5 – 28 DMAs• District 10 – 38 DMAs

Page 12: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1212

Classroom Training Module 1DMA Design Planning, Design and Engineering

Hydraulic Modelling

• MWH conducted the hydraulic simulation based on the initial design submitted by MWC

• The term hydraulic network model describes the use of a mathematical representation of a real water supply system

• Hydraulic network models are used to simulate the behavior of existing or planned systems under a wide range of conditions without disrupting service to the customer

Page 13: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1313

Classroom Training Module 1DMA Design Planning, Design and Engineering

Draft Report

• The preliminary DMA design report is based on Decree 209/2004 (Quality Managements of Construction Works) which contains the following:• DMA Description• DMA Information• Quantity of work• Applicable Standards• DMA Design• Drawings• Work Schedule• Work Methodology• Site Regulation and Safety

Page 14: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1414

Classroom Training Module 1DMA Design Planning, Design and Engineering

Final Report

• Approval of the preliminary report is sought in order to produce the 10

copies of final report

• Combination of DMAs are done in order to pass the requirements of the

hydraulic simulation and other design criteria

Page 15: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1515

Classroom Training Module 2DMA Construction and Commissioning

Permit Acquisition Civil Works Commissionin

g Works

Page 16: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1616

Classroom Training Module 2DMA Construction and Commissioning

Permit Acquisition

• Preparation of Drawings with underground obstructions

• Process of Issuance of UTM Agreement

• Submission of DOT Agreement

• Submission of DOT Permit

• Issuance of Permit

Page 17: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1717

Classroom Training Module 2DMA Construction and Commissioning Permit Acquisition

Page 18: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1818

Classroom Training Module 2DMA Construction and Commissioning

Civil Works

• Line Meter Assemblies

• Isolation Valves

• Looping and Interconnection Activities

• Pipelaying Activities

• Fire Hydrants

Page 19: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

1919

Classroom Training Module 2DMA Construction and Commissioning Civil Works

Line Meter Assembly Electromagnetic Flow Meter Pressure Reducing Valve Strainer By Pass Connection Panel Box

Page 20: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2020

Classroom Training Module 2DMA Construction and Commissioning

Commissioning Works

• Water Adequacy Test

• Zero Pressure Test

• Baseline Measurement

• Baseline Report

Page 21: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2121

Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test

Water Adequacy Test will be conducted to ensure sufficiency of water supply within the isolated DMA despite of having only a single supply point

WAT starts with the measurement of pressure at benchmark points within and outside of the DMA prior to and after closure of all isolation valves

It is important that during the conduct of Water Adequacy Tests (WAT), all service connections covered by a particular DMA is identified, verified and tagged

Page 22: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2222

Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test Steps

1. Identify all boundary valves.2. Determine if the valves are operable, if not, replace the boundary valve.3. Monitor the pressure before and after isolation inside and outside the DMA4. Before closing any valve, install pressure gage in the hydrant inside the

DMA5. Close the boundary valve one by one6. Continue closing all boundary valves7. Compare the pressure before and after the isolation8. If there is a big pressure drop, the DMA needs to be redesigned or

introduce and additional supply usually by opening the critical boundary valve

Page 23: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2323

Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test

1 23

45

6

7 8 9

10

1112

13

600mm CIP

600m

m C

IP

200mm

150mm

100mm

100mm

150mm 150mm

100mm

100mm

100mm 75mm

100m

m

75m

m

75m

mM

14

1516 17

18

1920

21

2223

24

252627

Check Pressure w/in & outside DMA

– Close all Isolation Valves– Let water pass thru District Meter (inflow &outflow).

– If water is adequate within & outside the DMA, let all Isolation Valves be remained closed as supply will now pass through the District Meter.

Page 24: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2424

Classroom Training Module 2DMA Construction and Commissioning Zero Pressure Test

ZPT is conducted following the Water Adequacy Test to ensure the tightness of isolations

In principle, once all the isolation valves are closed including the inflow/s, pressure inside the DMA should drop to zero until no water comes out of the monitoring point/s

The test is normally done during off-peak hours (1AM to 4AM), when demand is at its lowest and pressure is theoretically at its peak

Page 25: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2525

Classroom Training Module 2DMA Construction and Commissioning Zero Pressure Test Steps

1. Inform the customers about the schedule of the water interruption.2. Identify critical point, usually the hydrant in the lowest elevation of the DMA.3. Closed all the supply points4. Open the hydrant to check if there will be no water (preferably the hydrant in the lowest elevation

inside the DMA).5. If there is still water after several minutes, check all the boundary valves if they are tightly closed. 6. If all the boundary valves are fully closed and still there is water in the monitoring point, then there

is unknown inflow inside the DMA.7. Check where the pressure is the highest as the unknown inflow may be in that area.8. Check old maps for old lines.9. Use GPR, pipe locator and other equipment to find old lines.10. Conduct step testing to localize the location of unknown lines.

Page 26: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2626

Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test

1 23

45

6

78

9

10

11

12

131 2

34

5

6

78

9

10

11

12

131 2

34

5

6

78

9

10

11

12

13

MSupply

-Leaks (Physical Loss)

-Identified Night Users

Supply= Allowable Night Flow + Physical + Identified Night UsersPhysical Losses= Supply- Allowable Night Flow -Identified Night Users

- Unidentified night users

(0.06lpm/wm)

Page 27: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2727

Classroom Training Module 2DMA Construction and Commissioning Baseline Measurement

If Water Adequacy and Zero Pressure Test are successful, the next step is to conduct the baseline measurement

Baseline Measurement is done to determine the baseline NRW of a particular DMA

Baseline measurement is usually done on the period of 7 days to capture one complete cycle of water consumption pattern in the DMA

Page 28: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2828

Classroom Training Module 2DMA Construction and Commissioning Baseline Measurement Steps

1. Identify all the water service connection inside the DMA based on the design boundary.

2. Identify and replace all defective water meters before baseline measurement to increase the accuracy of data.

3. Carry out the baseline measurement. Read all DMA meters (inflow and outflow) on the 1st and 7th day, ideally at the same time. Compute Qi in m3/day.

4. Read all customer meters on day 1 and 7 of the measurement. First and second reading of a specific meter should be at approximately the same hour of the day.

5. Calculate the total metered consumption of all customers in the DMA by utilizing the 90 day billing average from SAWACO or JSC and calculate the daily average QM (m3/d).

6. Calculate baseline leakage

Page 29: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

2929

Classroom Training Module 2DMA Construction and Commissioning Baseline Measurement Formula

Lb = Qi – Qm

Where

Lb = Leakage during baseline in m3/day

Qi = DMA inflow in m3/day

Qm = metered consumption (billed volume) in m3/day

Page 30: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3030

Classroom Training Module 2DMA Construction and Commissioning Data Logging and Data Transfer

Page 31: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3131

Classroom Training Module 3Active Leakage Control

Analysis and Control

Leak location/detectio

nLeak repair Monitoring and

Measurement

Page 32: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3232

Classroom Training Module 3Active Leakage Control

Infra

stru

ctur

e M

anag

emen

t

Pre

ssur

e M

anag

emen

tSpeed/

Quality of Repairs

Active Leakage Control

Water Losses due to Leakage

Four Pillars of Physical Loss Management

Page 33: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3333

Classroom Training Module 3Active Leakage Control

Analysis and Control

• A proactive strategy to reduce water loss through detection of

nonvisible leaks

• Involves the regular survey of the water network using one or

more techniques in detecting leaks in water mains

• Performing night flow measurements on a regular basis to detect

new leaks as soon as possible

Page 34: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3434

Classroom Training Module 3Active Leakage Control

Leak location /detection

• Leak Detection or localizing by means of a step test or acoustic logging survey enables the leakage engineer to narrow down the location of the leak or burst to an individual road or length of main

• Next activity for the leakage engineer is to precisely locate or pinpoint the position of the leak and mark the point clearly on the ground surface where the repair teams will have to excavate

Page 35: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3535

Classroom Training Module 3Active Leakage Control Step Testing

Step testing is the technique whereby a leak or leaks are detected by making temporary successive valve closures to reduce the size of a DMA

The valves are closed for a short duration whilst simultaneously measurements of the rate of flow are being made

Page 36: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3636

Classroom Training Module 3Active Leakage Control Step Testing Procedure

Survey and check the operability of all the existing valves inside the DMA. Plan the sequence of step test segment carefully utilizing the information

gather from the valve survey. Schedule the activity during minimum demand usually 12:00 – 4:00 am. Inform the customers in advance regarding the Step test activity. Start closing the valves from the segment farthest from the line meter.

Record valve details (location and no. of turns) and time of closure; Read the transmitter (totalizer and instantaneous flow) after every valve

closure or set data logging every minute for more comprehensive data.

Page 37: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3737

Classroom Training Module 3Active Leakage Control Step Testing Procedure

Continue the step test until all segment are completed, the last segment being the area supplied by the line meter. If possible, check if there is no water in each segment.

Open the valves slowly in reverse order. Do flushing activity to avoid dirty water complaint. Analyze the step test data to determine the segment with the highest

possible leakage.

Page 38: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3838

Classroom Training Module 3Active Leakage Control Step Testing

M1 2

3

4

5

6

78

9

10

11

12

13

M1 2

3

4

5

6

78

9

10

11

12

13

M1 2

3

4

5

6

78

9

10

11

12

13

• Close Step-Test Valves @ 15min interval

• Open Step-Test Valves @ 15min interval (REVERSE OPERATION)

Upload Mtr (if Logger Ready)

If DM has no Data Logger, read mtr. @ 5 min. interval

This is done 15min before the 1st STV is closed up to the last STV is re-opened.

Page 39: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

3939

M1 2

34

5

6

78

9

10

11

12

13

M1 2

34

5

6

78

9

10

11

12

13

M1 2

34

5

6

78

9

10

11

12

13

1145 lpm 795 lpm

195 lpm

100WSC

500WSC

150WSC195 lpm

600 lpm

350 lpm

Highest physical loss

Classroom Training Module 3Active Leakage Control Step Testing

Page 40: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4040

Classroom Training Module 3Active Leakage Control Equipment

Leak Noise Loggers

Ground Microphone

Leak Noise Correlators

GPR

Page 41: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4141

Classroom Training Module 3Active Leakage Control Leaks commonly occur on:

Service Connection Service pipe Tapping House meter assembly

Mainline Main pipe Joints

Valve

Page 42: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4242

Classroom Training Module 4Pressure Management Definition of Pressure Management

the practice of managing system pressures to the optimum levels of service ensuring sufficient and efficient supply to legitimate uses and consumers, while reducing unnecessary excess pressures, eliminating transients and faulty level controls all of which cause the distribution system to leak unnecessarily

Page 43: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4343

Classroom Training Module 4Pressure Management Zone 1 Experience

the overall aim is to ensure that the pressure during the day is not significantly lower that the pressure at night. To keep the pressure within optimal levels inside the DMA, PRVs previously installed with the rest of the flow meter set assembly will be operated

Page 44: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4444

Classroom Training Module 4Pressure Management Pressure Reducing Valve (PRV)

maintains the optimum pressure in the network at all times, but automatically compensates for the reduced flow following the repair of the leaks whilst maintaining the original operating pressures in the DMA

Page 45: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4545

Classroom Training Module 4Pressure Management Pressure Management and Modulation

Page 46: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4646

Classroom Training Module 4Pressure Management Pressure Management and Modulation

Modulation Location Local point pressure modulation Critical point pressure modulation

Modulation Type Fixed outlet pressure modulation Time-based pressure modulation Flow-based pressure modulation

Page 47: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4747

Outline

Field Training Modules Water Adequacy TestZero Pressure TestStep-TestingUse of leak noise correlatorUse of leak pen in leak detectionUse of ground microphone for leak detectionLine meter and PRV operationPMAC Familiarization/ Data Center

Page 48: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1

4848

Xin Cám Ơn!

Page 49: Performance-based  Leakage  Reduction  and  Management Services  SAWACO Zone 1