performance-based leakage reduction and management services sawaco zone 1
DESCRIPTION
Performance-based Leakage Reduction and Management Services SAWACO Zone 1 Training and Transfer of Technology. Outline. Classroom Training Modules Field Training Modules . Outline. Classroom Training Modules Module 1 DMA Design Module 2 DMA Construction and Commissioning - PowerPoint PPT PresentationTRANSCRIPT
Performance-based Leakage Reduction and Management Services
SAWACO Zone 1Training and Transfer of Technology
22
Outline
Classroom Training Modules
Field Training Modules
33
Outline
Classroom Training ModulesModule 1 DMA Design
Module 2 DMA Construction and Commissioning
Module 3 Active Leakage Control
Module 4 Pressure Management
44
Classroom Training Module 1DMA Design Definition of District Metering Area (DMA)
is a world-wide accepted tool to operate and manage a network area wherein hydraulic boundary is defined by a system of Isolation Valves (IV) an flow Meters
a discrete area of a water distribution network. It is usually created by closing boundary valves so that it remains flexible to changing demands. However, a DMA can also be created by permanently disconnecting pipes to neighboring areas. Water flowing into and out of the DMA is metered and flows are periodically analyzed in order to monitor the level of leakage
55
Classroom Training Module 1DMA Design Definition of District Metering Area (DMA)
has water service connections ranging from 500-3,000can be categorized into the following types:
Single inlet DMAs Multiple inlet DMAs Cascading DMAs
66
Classroom Training Module 1DMA Design General Guidelines in DMA Design
DMAs should not include trunk mains or storage tanksEach DMA should preferably be supplied through a single,
metered supply pointDMA boundaries should be created by closing boundary
valvesVariations in ground elevation should be minimal across the
DMAThe types of consumers and their respective water supply
requirements should be assessed
77
Classroom Training Module 1DMA Design General Guidelines in DMA Design
Legal regulations governing minimum pressures, local constraints due to topography and height of buildings as well as fire fighting requirements have to be respected
Closing boundary valves to create DMAs will increase the number of dead-end pipes
Pressure management plays a key role in leakage management
88
Classroom Training Module 1DMA Design Planning, Design and Engineering
Planning and
Prioritization
Field Survey
Preliminary Design
Hydraulic Simulation
Draft Report Final report
99
Classroom Training Module 1DMA Design Planning, Design and Engineering
Planning and Prioritization
• Preliminary design by Manila Water design team in coordination with
MWH network modelling team
• Prioritization by highest leakage potential
• Manila Water prioritization was initially based on the following:• Pipe material• Pipe age• Number of leak occurrences
1010
Classroom Training Module 1DMA Design Planning, Design and Engineering
Field Survey
• Data gathered during site investigation:• Location and status of existing valves, fire hydrants and blow-offs.• Big consumption customers• Pressure• Road classification• Traffic
1111
Classroom Training Module 1DMA Design Planning, Design and Engineering
Preliminary Design
• Preliminary design of 119 DMAs in the Feasibility Study done in 2005
• One line meter per DMA with a range of 1000-2000 service connections
• DMAs per District• District 1 – 24 DMAs• District 3 – 29 DMAs• District 5 – 28 DMAs• District 10 – 38 DMAs
1212
Classroom Training Module 1DMA Design Planning, Design and Engineering
Hydraulic Modelling
• MWH conducted the hydraulic simulation based on the initial design submitted by MWC
• The term hydraulic network model describes the use of a mathematical representation of a real water supply system
• Hydraulic network models are used to simulate the behavior of existing or planned systems under a wide range of conditions without disrupting service to the customer
1313
Classroom Training Module 1DMA Design Planning, Design and Engineering
Draft Report
• The preliminary DMA design report is based on Decree 209/2004 (Quality Managements of Construction Works) which contains the following:• DMA Description• DMA Information• Quantity of work• Applicable Standards• DMA Design• Drawings• Work Schedule• Work Methodology• Site Regulation and Safety
1414
Classroom Training Module 1DMA Design Planning, Design and Engineering
Final Report
• Approval of the preliminary report is sought in order to produce the 10
copies of final report
• Combination of DMAs are done in order to pass the requirements of the
hydraulic simulation and other design criteria
1515
Classroom Training Module 2DMA Construction and Commissioning
Permit Acquisition Civil Works Commissionin
g Works
1616
Classroom Training Module 2DMA Construction and Commissioning
Permit Acquisition
• Preparation of Drawings with underground obstructions
• Process of Issuance of UTM Agreement
• Submission of DOT Agreement
• Submission of DOT Permit
• Issuance of Permit
1717
Classroom Training Module 2DMA Construction and Commissioning Permit Acquisition
1818
Classroom Training Module 2DMA Construction and Commissioning
Civil Works
• Line Meter Assemblies
• Isolation Valves
• Looping and Interconnection Activities
• Pipelaying Activities
• Fire Hydrants
1919
Classroom Training Module 2DMA Construction and Commissioning Civil Works
Line Meter Assembly Electromagnetic Flow Meter Pressure Reducing Valve Strainer By Pass Connection Panel Box
2020
Classroom Training Module 2DMA Construction and Commissioning
Commissioning Works
• Water Adequacy Test
• Zero Pressure Test
• Baseline Measurement
• Baseline Report
2121
Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test
Water Adequacy Test will be conducted to ensure sufficiency of water supply within the isolated DMA despite of having only a single supply point
WAT starts with the measurement of pressure at benchmark points within and outside of the DMA prior to and after closure of all isolation valves
It is important that during the conduct of Water Adequacy Tests (WAT), all service connections covered by a particular DMA is identified, verified and tagged
2222
Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test Steps
1. Identify all boundary valves.2. Determine if the valves are operable, if not, replace the boundary valve.3. Monitor the pressure before and after isolation inside and outside the DMA4. Before closing any valve, install pressure gage in the hydrant inside the
DMA5. Close the boundary valve one by one6. Continue closing all boundary valves7. Compare the pressure before and after the isolation8. If there is a big pressure drop, the DMA needs to be redesigned or
introduce and additional supply usually by opening the critical boundary valve
2323
Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test
1 23
45
6
7 8 9
10
1112
13
600mm CIP
600m
m C
IP
200mm
150mm
100mm
100mm
150mm 150mm
100mm
100mm
100mm 75mm
100m
m
75m
m
75m
mM
14
1516 17
18
1920
21
2223
24
252627
Check Pressure w/in & outside DMA
– Close all Isolation Valves– Let water pass thru District Meter (inflow &outflow).
– If water is adequate within & outside the DMA, let all Isolation Valves be remained closed as supply will now pass through the District Meter.
2424
Classroom Training Module 2DMA Construction and Commissioning Zero Pressure Test
ZPT is conducted following the Water Adequacy Test to ensure the tightness of isolations
In principle, once all the isolation valves are closed including the inflow/s, pressure inside the DMA should drop to zero until no water comes out of the monitoring point/s
The test is normally done during off-peak hours (1AM to 4AM), when demand is at its lowest and pressure is theoretically at its peak
2525
Classroom Training Module 2DMA Construction and Commissioning Zero Pressure Test Steps
1. Inform the customers about the schedule of the water interruption.2. Identify critical point, usually the hydrant in the lowest elevation of the DMA.3. Closed all the supply points4. Open the hydrant to check if there will be no water (preferably the hydrant in the lowest elevation
inside the DMA).5. If there is still water after several minutes, check all the boundary valves if they are tightly closed. 6. If all the boundary valves are fully closed and still there is water in the monitoring point, then there
is unknown inflow inside the DMA.7. Check where the pressure is the highest as the unknown inflow may be in that area.8. Check old maps for old lines.9. Use GPR, pipe locator and other equipment to find old lines.10. Conduct step testing to localize the location of unknown lines.
2626
Classroom Training Module 2DMA Construction and Commissioning Water Adequacy Test
1 23
45
6
78
9
10
11
12
131 2
34
5
6
78
9
10
11
12
131 2
34
5
6
78
9
10
11
12
13
MSupply
-Leaks (Physical Loss)
-Identified Night Users
Supply= Allowable Night Flow + Physical + Identified Night UsersPhysical Losses= Supply- Allowable Night Flow -Identified Night Users
- Unidentified night users
(0.06lpm/wm)
2727
Classroom Training Module 2DMA Construction and Commissioning Baseline Measurement
If Water Adequacy and Zero Pressure Test are successful, the next step is to conduct the baseline measurement
Baseline Measurement is done to determine the baseline NRW of a particular DMA
Baseline measurement is usually done on the period of 7 days to capture one complete cycle of water consumption pattern in the DMA
2828
Classroom Training Module 2DMA Construction and Commissioning Baseline Measurement Steps
1. Identify all the water service connection inside the DMA based on the design boundary.
2. Identify and replace all defective water meters before baseline measurement to increase the accuracy of data.
3. Carry out the baseline measurement. Read all DMA meters (inflow and outflow) on the 1st and 7th day, ideally at the same time. Compute Qi in m3/day.
4. Read all customer meters on day 1 and 7 of the measurement. First and second reading of a specific meter should be at approximately the same hour of the day.
5. Calculate the total metered consumption of all customers in the DMA by utilizing the 90 day billing average from SAWACO or JSC and calculate the daily average QM (m3/d).
6. Calculate baseline leakage
2929
Classroom Training Module 2DMA Construction and Commissioning Baseline Measurement Formula
Lb = Qi – Qm
Where
Lb = Leakage during baseline in m3/day
Qi = DMA inflow in m3/day
Qm = metered consumption (billed volume) in m3/day
3030
Classroom Training Module 2DMA Construction and Commissioning Data Logging and Data Transfer
3131
Classroom Training Module 3Active Leakage Control
Analysis and Control
Leak location/detectio
nLeak repair Monitoring and
Measurement
3232
Classroom Training Module 3Active Leakage Control
Infra
stru
ctur
e M
anag
emen
t
Pre
ssur
e M
anag
emen
tSpeed/
Quality of Repairs
Active Leakage Control
Water Losses due to Leakage
Four Pillars of Physical Loss Management
3333
Classroom Training Module 3Active Leakage Control
Analysis and Control
• A proactive strategy to reduce water loss through detection of
nonvisible leaks
• Involves the regular survey of the water network using one or
more techniques in detecting leaks in water mains
• Performing night flow measurements on a regular basis to detect
new leaks as soon as possible
3434
Classroom Training Module 3Active Leakage Control
Leak location /detection
• Leak Detection or localizing by means of a step test or acoustic logging survey enables the leakage engineer to narrow down the location of the leak or burst to an individual road or length of main
• Next activity for the leakage engineer is to precisely locate or pinpoint the position of the leak and mark the point clearly on the ground surface where the repair teams will have to excavate
3535
Classroom Training Module 3Active Leakage Control Step Testing
Step testing is the technique whereby a leak or leaks are detected by making temporary successive valve closures to reduce the size of a DMA
The valves are closed for a short duration whilst simultaneously measurements of the rate of flow are being made
3636
Classroom Training Module 3Active Leakage Control Step Testing Procedure
Survey and check the operability of all the existing valves inside the DMA. Plan the sequence of step test segment carefully utilizing the information
gather from the valve survey. Schedule the activity during minimum demand usually 12:00 – 4:00 am. Inform the customers in advance regarding the Step test activity. Start closing the valves from the segment farthest from the line meter.
Record valve details (location and no. of turns) and time of closure; Read the transmitter (totalizer and instantaneous flow) after every valve
closure or set data logging every minute for more comprehensive data.
3737
Classroom Training Module 3Active Leakage Control Step Testing Procedure
Continue the step test until all segment are completed, the last segment being the area supplied by the line meter. If possible, check if there is no water in each segment.
Open the valves slowly in reverse order. Do flushing activity to avoid dirty water complaint. Analyze the step test data to determine the segment with the highest
possible leakage.
3838
Classroom Training Module 3Active Leakage Control Step Testing
M1 2
3
4
5
6
78
9
10
11
12
13
M1 2
3
4
5
6
78
9
10
11
12
13
M1 2
3
4
5
6
78
9
10
11
12
13
• Close Step-Test Valves @ 15min interval
• Open Step-Test Valves @ 15min interval (REVERSE OPERATION)
Upload Mtr (if Logger Ready)
If DM has no Data Logger, read mtr. @ 5 min. interval
This is done 15min before the 1st STV is closed up to the last STV is re-opened.
3939
M1 2
34
5
6
78
9
10
11
12
13
M1 2
34
5
6
78
9
10
11
12
13
M1 2
34
5
6
78
9
10
11
12
13
1145 lpm 795 lpm
195 lpm
100WSC
500WSC
150WSC195 lpm
600 lpm
350 lpm
Highest physical loss
Classroom Training Module 3Active Leakage Control Step Testing
4040
Classroom Training Module 3Active Leakage Control Equipment
Leak Noise Loggers
Ground Microphone
Leak Noise Correlators
GPR
4141
Classroom Training Module 3Active Leakage Control Leaks commonly occur on:
Service Connection Service pipe Tapping House meter assembly
Mainline Main pipe Joints
Valve
4242
Classroom Training Module 4Pressure Management Definition of Pressure Management
the practice of managing system pressures to the optimum levels of service ensuring sufficient and efficient supply to legitimate uses and consumers, while reducing unnecessary excess pressures, eliminating transients and faulty level controls all of which cause the distribution system to leak unnecessarily
4343
Classroom Training Module 4Pressure Management Zone 1 Experience
the overall aim is to ensure that the pressure during the day is not significantly lower that the pressure at night. To keep the pressure within optimal levels inside the DMA, PRVs previously installed with the rest of the flow meter set assembly will be operated
4444
Classroom Training Module 4Pressure Management Pressure Reducing Valve (PRV)
maintains the optimum pressure in the network at all times, but automatically compensates for the reduced flow following the repair of the leaks whilst maintaining the original operating pressures in the DMA
4545
Classroom Training Module 4Pressure Management Pressure Management and Modulation
4646
Classroom Training Module 4Pressure Management Pressure Management and Modulation
Modulation Location Local point pressure modulation Critical point pressure modulation
Modulation Type Fixed outlet pressure modulation Time-based pressure modulation Flow-based pressure modulation
4747
Outline
Field Training Modules Water Adequacy TestZero Pressure TestStep-TestingUse of leak noise correlatorUse of leak pen in leak detectionUse of ground microphone for leak detectionLine meter and PRV operationPMAC Familiarization/ Data Center
4848
Xin Cám Ơn!