order of west bengal electricity regulatory ... 2017-18.pdftariff order of wbsedcl for the year 2017...
TRANSCRIPT
-
ORDER
OF
WEST BENGAL ELECTRICITY REGULATORY COMMISSION
FOR THE YEAR 2017 – 2018
IN
CASE NO: TP – 65 / 16 - 17
IN RE THE TARIFF APPLICATION OF THE WEST BENGAL STATE
ELECTRICITY DISTRIBUTION COMPANY LIMITED FOR THE
YEAR 2017 – 2018 COVERING FIFTH CONTROL PERIOD
UNDER SECTION 64(3)(a)
READ WITH SECTION 62(1) AND SECTION 62(3)
OF THE ELECTRICITY ACT, 2003
DATE: 04.07.2018
-
Tariff Order of WBSEDCL for the year 2017 – 2018
CHAPTER – 1
INTRODUCTION
West Bengal Electricity Regulatory Commission 2
1.1 The West Bengal Electricity Regulatory Commission (hereinafter referred to as
the “Commission”), a statutory body under the first proviso to section 82(1) of the
Electricity Act, 2003 (hereinafter referred to as the “Act”), has been authorized in
terms of the section 86 and section 62(1) of the Act to determine the tariff for a)
supply of electricity by a generating company to a distribution licensee, b)
transmission of electricity, c) wheeling of electricity and d) retail sale of electricity,
as the case may be, within the State of West Bengal.
1.2 The West Bengal State Electricity Distribution Company Limited (hereinafter
referred to as WBSEDCL), is deemed to be a licensee under the Electricity Act,
2003 in terms of fifth proviso to Section 14 of the Act wholly owned by the State
Government and is engaged in the business of distribution of electricity within the
area of supply of WBSEDCL in the State of West Bengal and the distribution tariff
of WBSEDCL shall be determined by the Commission.
1.3 West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)
Regulations, 2011 has come into effect from 29th April, 2011. The said Tariff
Regulations, 2011 was further amended by notifying the West Bengal Electricity
Regulatory Commission (Terms and Conditions of Tariff) (Amendment)
Regulations, 2012 in the extra ordinary edition of The Kolkata Gazette dated 27th
August, 2012 and West Bengal Electricity Regulatory Commission (Terms and
Conditions of Tariff) (Amendment) Regulations, 2013 in the extra ordinary edition
of The Kolkata Gazette dated 30th
1.4 In terms of definition contained in regulation 1.2.1 (xxx) of the West Bengal
Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,
2011, as amended from time to time (hereinafter referred to as the ‘Tariff
July, 2013.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 3
Regulations’), each control period after third control period shall be normally for a
period of five ensuing years or such other period of number of ensuing years as
may be decided by the Commission from time to time. The Commission vide his
order dated 04.05.2016 in Case No. SM-13/16-17 decided that the fifth control
period shall also be consisting of three ensuing years for the period from 2017 –
2018 to 2019 – 2020. But, after careful consideration of all relevant factors, vide
its order dated 14.12.2016 in Case No. SM-15/16-17 decided that the fifth control
period shall be for one year and consist of 2017 – 2018 only and vide its order
dated 14.12.2016 in file no B-11/20 decided that the last date for filing of tariff
petition for the fifth control period shall be 31.12.2016. WBSEDCL accordingly
submitted the petition for determination of tariff for the fifth control period
consisting of the year 2017 - 2018 on 22nd
1.5 On scrutiny of the application, it was observed that some documents required as
per regulation 2.5.2 and some Forms as prescribed in the different annexures as
per regulation 2.7.2 of the Tariff Regulations, were not submitted along with the
tariff application. Accordingly, WBSEDCL was requested to submit all those
documents/forms vide Commission’s letter no. WBERC/TP-65/16-17/2171 dated
27
December, 2016
th January, 2017. In reply, WBSEDCL submitted the required documents /
forms vide their letter No. REG/SERC/MYT 5th Control Period/479 dated 8th
1.6 The tariff application submitted on 22.12.2016 along with the information / data,
documents, forms submitted on 08.02.2017 as per Tariff Regulations (collectively
called as “tariff application”), were admitted by the Commission in case No.TP-
65/16-17 and communicated to WBSEDCL vide letter dated 20.02.2017 with the
direction to publish the gist of their tariff application, as approved by the
Commission, in the news papers and also in their website as per provisions of
the Tariff Regulations. The gist was, accordingly, published simultaneously on
February, 2017.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 4
24.02.2017 in the news papers - (i) ‘Business Line’ (English), (ii) ‘Ekdin’
(Bengali), (iii) ‘Dainik Statesman’ (Bengali) and (iv) ‘Jansatta’ (Hindi). The gist
along with the tariff application and additional information / data submitted vide
letter dated 08.02.2017 were also posted in the website of WBSEDCL. The
publication invited the attention of all interested parties, stake holders and the
members of the public to the application for determination of tariff of WBSEDCL
for the fifth control period and requested for submission of suggestions,
objections and comments, if any, on the tariff application to the Commission by
20.03.2017 at the latest. Opportunities were also afforded to all to inspect the
tariff application and to take copies thereof. It is noticed by the Commission that
the approved gist published in the news papers are not in consonance with the
with the stipulations contained in its letter dated 20.02.2017, nor does it satisfy
the requirement for publishing a notice containing a gist of the tariff application in
the daily newspapers “widely circulated in your area” as specified in regulation
2.7.3 of the Tariff Regulations. WBSEDCL was, therefore, directed to publish the
gist afresh in newspaper “widely circulated in your area” vide its letter dated
15.03.2017. WBSEDCL was directed to publish a notice extending the last date
of submission of objections / suggestions / comments against the tariff
application for the year 2017 – 2018 in those newspapers where the gist of the
tariff application was earlier published on 24.02.2017.
1.7 WBSEDCL accordingly published on 23.03.2017 a notice duly approved by the
Commission regarding extension of due date for submission of objections and
suggestions against the tariff application for the year 2017 – 2018 upto
27.03.2017. The notice regarding extension of date of submission was also
posted in the official website of WBSEDCL.
1.8 Objections to / comments on the aforementioned tariff petition of WBSEDCL for
the fifth control period were received by the Commission from the following
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 5
objectors within the stipulated time i.e., 27.03.2017 and the same have been
recorded in a summarized form in Chapter 3 of the instant order.
I. Rashmi Metaliks Limited,
II. Organization of Indian Engineering Industry,
III. Rohit Ferro-Tech Ltd,
IV. Ankit Metal and Power Limited,
V. Modern India Concast Limited,
VI. All Bengal Electricity Consumers’ Association (ABECA).
1.9 Commission, vide letter dated 28.03.2017 requested WBSEDCL to submit
additional clarifications in regard to sales forecast, power purchase, load-
generation balance and cost of outsourcing. In reply to Commission’s letter dated
28.03.2017, WBSEDCL submitted the required clarification, as asked for, vide
their letter dated 12.04.2017.
1.10 The Commission determines the tariff in accordance with the Electricity Act, 2003
and the Tariff Regulations framed thereunder and for this purpose, the
Commission has estimated the expenditure for 2016 – 2017 to arrive at the
estimated expenditure / cost under different heads for the years 2017 – 2018.
1.11 The estimation made for 2016 – 2017 by the Commission shall not be construed
by WBSEDCL as admission of at least such estimated amount in APR for 2016 –
2017. On the other hand, if in APR any deduction is made then as a conclusion
from such decision one shall not expect that the impact of such deduction is to be
continued in fifth control period as this will tantamount to imposing a penalty for
infinite nature or double penalty for the same inefficiency.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
CHAPTER – 2
THE CASE OF WBSEDCL
West Bengal Electricity Regulatory Commission 6
2.1 The applicant WBSEDCL has submitted the application for determination of
Aggregate Revenue Requirement (ARR) and tariffs for the fifth control period
covering the year 2017 – 2018 under MYT framework in accordance with the
Tariff Regulations. The applicant has projected the ARR and the tariffs for 2017 –
2018 under the fifth control period and has prayed for allowing the same. The
applicant has also prayed for other dispensations which are mentioned in
subsequent paragraphs.
2.2 WBSEDCL has projected the ARR for the year 2017 – 2018 at Rs 1912327.00
lakh and the average cost of supply for 2017 – 2018 at 755.00 Paise / kWh. The
reasons for enhancement of tariff are stated as follows:
i) The Fuel Cost Adjustment (FCA), Monthly Fuel Cost Adjustment (MFCA) and Monthly Variable Cost Adjustment (MVCA) payable to different
agencies for purchase of power has increased considerably.
ii) Due to increasing network, improved customer service facilities and price index expenses towards Repair & Maintenance (R&M), outsourcing cost
due to maintenance and operation of new line and substations, spot
billing service, mobile maintenance service and zonal call centre, etc. has
increased.
iii) Increase of employee cost considering impact of 7th
iv) Probable enhancement of transmission charges payable to WBSETCL.
Pay Commission.
v) Increase in CTU charges due to implementation of Point of Connection (POC) charge mechanism by CERC.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 7
2.3 It is also submitted by the applicant that the Commission may consider rise in
price index and consumer base, rise in power purchase cost and operating cost
resulting in increased cost of business.
2.4 It is stated by the applicant that while determining the ARR for the year 2017 –
2018 under the fifth control period, all infrastructure investment and power
procurement plan have been made assuming that all consumers under
WBSEDCL area will continue with power supply from WBSEDCL.
2.5 WBSEDCL has claimed that with fast growing / expanding distribution network,
additional consumers are being added with WBSEDCL system during the last
few years. It is stated that based on trend of increase in number of consumers in
last five years, consumers’ strength of WBSEDCL has been projected for the
year 2017 – 2018. The consumption of different categories of consumers during
the year 2017 – 2018 stated to have been estimated as per CAGR of
consumption during the last four years of the respective category of consumers
in the following manner:
� For LT & HT (Domestic, Commercial, Public Bodies) and LT (Industrial,
Irrigation, Public Lighting), CAGR of consumption during the last four years.
� For Commercial Plantations, Construction Power and Others, the
consumption during 2015 – 2016 has been considered.
� 1% annual increase during the year 2018 in HT Industrial category has been
considered due to introduction of various incentives.
2.6 Total sale of energy to own consumers of WBSEDCL has been projected as
25327.00 MU in the year 2017 – 2018. Distribution loss has been projected on
the normative basis at a level of 17.50% for 2017 – 2018.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 8
2.7 The applicant has also projected sale of energy to other licensees viz. CESC
Limited, Damodar Valley Corporation (DVC), The Durgapur Projects Limited
(DPL) and India Power Company Limited (formerly known as DPSC Limited)
(IPCL) during the year under the control period. The projection of sale of energy
to CESC Limited stated to have been made on the basis of drawal trend by
CESC Limited during the year 2016 – 2017 at a level of 10 MU for the year 2017
– 2018. The projection of sale of power to DVC has been projected to be 5 MU
during the year 2017 – 2018. The projection of sale of power to DPL as stated to
have been estimated at 20 MU for 2017 – 2018 as per drawal trend of DPL. The
sale of power to IPCL stated to have been estimated at 40 MU during the year
2017 – 2018 as per the drawal trend of IPCL during the year 2016 – 2017.
2.8 In terms of an agreement signed between the Govt. of West Bengal and Govt. of
Sikkim, the applicant has claimed that 20% of the sent out generation from
Rammam Hydel station Stage-II shall be supplied to Government of Sikkim
during the year 2017 – 2018. Accordingly, energy to be supplied to Government
of Sikkim has been estimated at 50 MU during the year 2017 – 2018.
2.9 WBSEDCL projected power purchase requirement based on the factor as
specified in 2.5 to 2.8 above and the cost of power purchase has been
considered based on the bill of respective generating stations during the month
of August, 2016 or the tariff petition/application where available or from the price
as projected by the generating companies.
2.10 WBSEDCL has submitted the projection of the energy balance that has been
arrived based on the estimated consumption, loss in distribution system of
WBSEDCL and loss in transmission system of WBSETCL at the normative level
as per Tariff Regulations. It is also submitted that the petitioner has to consider
the loss in central and state grid, as applicable.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 9
2.11 Sale of incidental surplus energy to the persons other than consumers and
licensees during 2017 – 2018 has been estimated by the applicant to be at a
level of 7102 MU. In view of the present poor and unpredictable condition of
power market, the price for such power sale has been considered at pool rate of
power purchase of respective year. No projection has, however, been made by
WBSEDCL towards banking of power through swap arrangement for the year
under the control period. WBSEDCL may have to swap out power during real
time operation during the year 2017 – 2018.
2.12 WBSEDCL has two main hydel power stations situated at Rammam and
Jaldhaka. Based on same PLF as in 2015 – 2016 with auxiliary consumption, the
generations for the year 2017 – 2018 from Rammam hydel power station and
Jaldhaka Stage – I hydel power station has been projected as 251.46 MU and
136.62 MU respectively.
2.13 WBSEDCL also has a pumped storage project at Purulia. WBSEDCL submitted
that, the Purulia Pumped Storage Project (PPSP) provides spinning reserve and
utilized as and when required to meet the system demand. Annual gross
generation at a level of 1055 MU has been projected for the year 2017 – 2018
according to the system requirement and considering optimum utilization of the
surplus power during the off peak hours.
2.14 WBSEDCL stated to have 10 (ten) small / micro hydel generating stations and
the generation from those generating stations are projected as generation from
renewable sources of energy. While projecting the generation from those
generating stations, it is stated that the generation from all such generating
stations have been estimated based on previous trend. The generation from the
small / micro power stations has been projected at 141.63 MU for the year 2017
– 2018.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 10
2.15 WBSEDCL is maintaining a diesel generating plant at Rudranagar in Sagar
Island which was earlier supplying power to the consumers at Sagar Island. The
load at Sagar Island is now being catered through grid. No generation has been
projected from the diesel generating station for the year under the control period.
2.16 WBSEDCL has installed grid connection solar PV plants (10 kW) each at 92
schools out of 100 Government and Government aided schools in different
districts in October, 2015. WBSEDCL has also commissioned 10 MW solar PV
project at Teesta canal bank in August, 2016. Some more solar PV projects are
in pipe line of either finalization or consideration for commission during the year
under control period. The annual generation from those new solar power stations
is project at a level of 75.250 MU considering 13% CuF.
2.17 WBSEDCL is continuing to purchase power from different agencies namely West
Bengal Power Development Corporation Ltd. (WBPDCL), The DPL, IPCL,
Damodar Valley Corporation (DVC), NTPC Ltd. (NTPC), NHPC Ltd (NHPC) and
PTC Ltd (PTC). It is also submitted that conventional power will also be
purchased directly from the new units of WBPDCL, NTPC, NHPC, DVC and
other generators and from electricity traders to meet the system demand of
WBSEDCL during the fifth control period. WBSEDCL will also purchase power
from different renewable and co-generation sources of energy during the ensuing
years under the fourth control period.
2.18 The planning of power purchase has been claimed by WBSEDCL to have been
done keeping in view the following aspects:
a) Estimated system demand for the ensuing years based on the projected load
growth.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 11
b) Maximum generation that may be available from the hydel power stations of
WBSEDCL.
c) Commitment to meet the peak system demand.
d) Requirement of pumping energy for optimum utilization of PPSP to meet the
system demand.
e) Effort to keep spinning reserve as per regulation to meet emergency situation
while sudden break down of any unit occurs.
WBSEDCL has claimed that besides purchasing power through grid system, they
will also purchase some quantum of power in radial mode from DVC at Asansol,
Burdwan and other areas, from DPL (at 33 KV & 11 KV) in and around Durgapur
area and from DPSC (at 11 KV) at Asansol area, Govt. of Sikkim (at 11 KV) at
Rangpoo area and WBREDA (at 11 KV) at Frezerganj area for catering its own
consumers during the year under the fifth control period
2.19 It is stated by WBSEDCL that the net generation to be available from the existing
generating stations of WBPDCL have been computed based on the projection
received from WBPDCL. As per the projection of WBPDCL, the net energy to be
available from KTPS, BKTPS, BTPS, STPS, SgTPS (Units I & II) and SgTPS
(Units III & IV) is 5018.00 MU, 7164.00 MU, 1676.00 MU 3651.00 MU, 2409.00
MU and 3250 MU respectively.
2.20 As it is learnt by WBSEDCL that the COD of unit III of the SgTPS has been
achieved in July 2016 and COD of unit IV of SgTPS was expected in January
2017. The capacity charges and energy charges for all the existing generating
stations of WBPDCL for the year 2017 – 2018 have been estimated by
WBSEDCL considering the same as in August, 2016 including MFCA for the
respective generating station.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 12
2.21 WBSEDCL has projected the purchase of power from DPL at 132 kV, 33 kV and
11 kV during the year 2017 – 2018 considering the trend of drawal by them from
DPL during 2016 – 2017 and the cost of such power purchase has been
estimated as per existing rate along with MVCA claimed by DPL in the month of
August, 2016.
2.22 The applicant has submitted that any revision of tariff in respect of WBPDCL,
DPL and IPCL for the year 2017 – 2018 by the Commission have an impact in
power purchase prices projected by WBSEDCL and that may be considered
while determining the power purchase cost of WBSEDCL for the year under the
fifth control period.
2.23 WBSEDCL has planned to purchase power also from NTPC Limited, NHPC
Limited and Damodar Valley Corporation (DVC) besides purchase of power from
WBPDCL, DPL, CESC Ltd and IPCL. WBSEDCL shall also purchase power
from other generating stations on commissioning of those generating stations
during the year 2017 – 2018 to meet their load growth. The price of power
purchase is considered as per tariff applicable to the respective generating
companies, wherever available or from the price as projected by the generating
companies. The applicant submitted to consider selling price as may be allowed
by the CERC in the tariff order of NTPC Ltd., NHPC Ltd, DVC and other
generators for the respective years while passing tariff orders in respect of
WBSEDCL for the year 2017 – 2018 if the tariff order in respect of those
agencies are issued before the tariff order for WBSEDCL are passed by the
Commission. The applicant also submitted that the proposed power purchase
price from all thermal power stations are exclusive of impact arising out of FCA or
MFCA or MVCA (in case of radial power) and any hike of power purchase cost
due to hike in FCA, MVCA and MFCA may be allowed to be claimed from
consumers and licensees through MVCA.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 13
2.24 It is proposed that any hike in power purchase cost of WBSEDCL due to hike in
FCA, MVCA and MFCA of the generating stations be allowed to claim through
MVCA from the sale to own consumers and licensees in the State.
2.25 WBSEDCL has estimated own consumption at the offices and substations for the
year 2017 – 2018 at 52 MU. WBSEDCL have projected 3350 MU to be procured
through purchase of short term power generally in the months of April and March
in order to bridge the gap between supply of power and system demand which
usually occurs during those months. WBSEDCL submitted that in order to fulfill
the Solar and Non-Solar RPO, the projection of short term purchase has been
estimated at 138 MU and 266 MU respectively during the year 2017 – 2018.
WBSEDCL also stated that in the event of sale price of surplus power in the
power market becoming not cost effective, the surplus power is being banked
through swap management for utilization of this surplus power effectively to
contain the idle capacity charge as well as to maintain grid discipline. The actual
banking of power under swap arrangement will be considered during FPPCA
application for 2017 – 2018.
2.26 WBSEDCL has also projected purchase of power from different new
conventional and non-conventional power plants during the year 2017 – 2018. As
per projection, the power purchase from Dagachhu HEP and Assam Power
under new conventional power plant is 360 MU and 3.50 MU respectively.
Similarly, WBSEDCL plans to purchase solar power from SECI and VGF scheme
or other such schemes of Government of India to fulfil its RPO. WBSEDCL has
indicated its solar power requirement for RPO to the tune of 100 MW during the
year 2017 – 2018.
2.27 Considering the projected sent out generation from its own generating stations,
power purchase from different agencies and the projected sales, energy
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 14
consumption at own premises, WBSEDCL has projected the energy balance for
the year 2017 – 2018.
2.28 The applicant has projected Rs.1408931.00 lakh as power purchase cost for the
year 2017 – 2018. This power purchase cost includes the cost of purchase of
estimated quantum of infirm power from the units under stabilization.
2.29 WBSEDCL projected Rs. 66447.00 lakh for Central Transmission Utility (CTU)
charges for the year 2017 – 2018 for transmission of WBSEDCL’s share of
power from the central sector generating stations and other generators outside
the State through the transmission system of CTU. However, the charges paid to
the CTU in actual will be claimed in the APR for the respective year.
2.30 Transmission charges payable to WBSETCL for the energy required to be
transmitted by the petitioner through WBSETCL system has been projected as
Rs. 110606.00 lakh for the year 2017 – 2018. However, WBSEDCL has claimed
Rs. 2034.00 lakh as SLDC charges during the year 2017 – 2018. ERPC charges
for the year 2017 – 2018 have been projected at Rs. 385.00 lakh. The system
operation charges payable to POSOCO have been estimated by WBSEDCL at
Rs. 543.00 lakh for 2017 – 2018.
2.31 An amount of Rs. 151746.00 lakh has been estimated as employee-cost for the
year 2017 - 2018. It is submitted that due to demographic and geographic
considerations, WBSEDCL is to maintain minimum level of employees to provide
service to its consumers. In the backdrop of the growing consumer strength and
augmentation of the distribution infrastructure, WBSEDCL has planned to
augment its manpower strength during the year 2017 – 2018. The manpower
strength during the year 2017 – 2018 has been planned to be 16363.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 15
2.32 15% hike has been considered in salary and allowances due to pay revision in
line with the 7th Pay Commission during the year 2017 – 2018 with a
retrospective effect from 1st January, 2016. The applicant has considered a D.A
hike @ 4% for 2017 – 2018. Moreover, increase in pay in respect of normal
increment of employee-cost has been considered @ 3% on the basic and grade
pay during the year 2017 – 2018. Other employee expenses are projected in
proportion to the manpower strength. WBSEDCL has further claimed that
terminal benefits are calculated based on the actuarial valuation of pension,
gratuity and leave encashment benefits. As per actuarial valuation made in 2016,
the projected pension and gratuity liability increased at a CAGR of 3.23%
assuming future salary inflation rate of 6% per annum. Hence, growth rate of
3.23% over the expenses for 2016 – 2017 has been considered to arrive at the
figures for 2017 – 2018. In order to accommodate impact of the 7th
2.33 The applicant has projected Operation and Maintenance (O&M) expenses
including Repair & Maintenance (R&M) cost for the year 2017 – 2018 at
Rs.135317.00 lakh, out of which, O&M expenses for generation is 6314.00 lakh
and for distribution function is 129003.00 lakh. WBSEDCL has claimed that
distribution assets and consumer strength of WBSEDCL are increasing rapidly
due to DDUGJY programme and other work such as R-APDRP, National
Cyclone Risk Mitigation Project, etc. at different parts of their operational area. In
order to deliver power with reasonable quality parameters and to reduce
instances of outages for the widely scattered large consumer base, the
expenditure of R & M works of WBSEDCL has been increased. The O&M
expenses during the year 2017 – 2018 have been estimated considering the
consumer growth and general inflation level.
Pay
Commission, an increase of 15% over the expenses in 2015 – 2016 has been
considered during 2016 – 2017.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 16
2.33.1 Operation and Maintenance (O&M) expenses for generation: WBSEDCL
submitted that in order to arrive at the O&M expenses for generation hydro plants
for the year 2017 – 2018, they have considered increase of 3 year CAGR on the
O&M expenses for the years 2014 – 2015 to 2016 – 2017 approved by the
Commission based on per MW basis as per the Tariff Regulations. For O&M for
Solar, WBSEDCL has considered Rs. 7 lakh per MW with escalation of 5.72% as
per CERC Renewable Energy tariff order dated 30th March, 2016. WBSEDCL
has estimated Rs. 4943.00 lakh on account of O&M for Hydro and Rs. 398.00
lakh for Solar.
2.33.2 Repair and Maintenance (R&M) expenses for distribution function: WBSEDCL
submitted that repair and maintenance expenses are a part of the core
distribution activities which reflect the expenditure incurred in respect of
maintenance of the distribution assets. WBSEDCL also submitted that the ratio of
R&M expenses to the O&M expenses for distribution is considered to be equal to
the 2015 – 2016 level, adjusted by a year-on-year growth from the 2014 – 2015.
Additional expenses are considered on account of IT implementation.
Accordingly, the projected figure for R&M expenses for the year 2017 – 2018 is
32831.00 lakh.
2.33.3 Administrative and General (A&G) expenses for distribution function: WBSEDCL
submitted that A&G expenses are a part of the core distribution activities which
reflect the expenditure associated with the necessary administrative support to
be arranged in order to ensure execution of the electricity distribution activities in
a smooth and uninterrupted manner. WBSEDCL also submitted that A&G
expenses are projected at the CAGR from 2012 – 2013 to 2015 – 2016 (i.e.,
6.5%) over the value of 2015 – 2016.. Additional expenses are considered on
account of IT implementation. Accordingly, the projected figure for A&G
expenses for the year 2017 – 2018 is 18348.00 lakh.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 17
2.33.4 WBSEDCL claimed an amount of Rs. 6123.00 lakh for 2017 – 2018 Rs. for
establishing and maintaining communication network set up for the complaint
management mechanism as per West Bengal Electricity Regulatory Commission
(Standard of Performance) Regulations, 2010 under the head Lease Rental.
2.33.5 WBSEDCL has claimed Rs. 351.00 lakh considering the present trend under the
head Complaint Management Mechanism to meet the expenses for – i) toll free
telephone for registering grievances at ZCC, ii) SMS charge for forwarding
grievance to Mobile Van, iii) rental charge for IVRS system, iv) separate
telephone facility at each customer care centre and v) antitheft toll free telephone
charges.
2.33.6 WBSEDCL has claimed Rs. 56790.00 lakh for the year 2017 – 2018 under the
fifth control period towards outsourcing cost.
2.33.7 WBSEDCL has claimed Rs. 1128.00 lakh towards insurance premium for the
year 2017 – 2018 considering an annual growth rate equal to the average of the
past 3-year and 4-year CAGR (i.e., 18%).
2.33.8 An amount of Rs. 14407.00 lakh has been estimated as expenses towards Rates
and Taxes. It is submitted that due to increase in number of consumers, the
number of office establishments, i.e., CCC, Divisional Manager Office have been
increased and the tax on the establishments has also been revised / increased
by civic bodies from time to time. The effect of such hike in rates and taxes has
been considered. The CAGR for rates and taxes was 37% during the year 2016 –
2017 over the year 2015 – 2016. Therefore, rates and taxes for 2017 – 2018 has
been increase at a CAGR of 37% over the year 2016 – 2017. It is further
submitted that Goods and Service Tax (GST) is likely to be implemented during
the year 2017 – 2018 as per the declaration of Government of India and hence
the proposed rate of GST on rates and taxes are not assessable at the moment.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 18
Impact, if any, of GST on rates and taxes shall be claimed at actuals in APR
petition for the respective year.
2.34 The applicant has claimed Rs. 2500.00 lakh towards bad debt for the year 2017
– 2018 for waiver of LPSC of Water Resource Development Department
(WRDD). However, bad and doubtful debts will be considered on actual basis in
the APR of respective year.
2.35 The applicant has stated that the capitalization of expenses for employees cost,
interest, administrative and other expenditure under the construction activities
are made for the year 2017 – 2018 following the existing policy of WBSEDCL.
2.36 WBSEDCL has projected Rs. 49096.00 lakh towards interest on borrowed
capital, Rs. 30600.00 lakh towards repayment of 1st
2.37 WBSEDCL has projected Rs. 11500.00 lakh for the year 2017 – 2018 under the
head interest on security deposit payable to the consumers.
installment of pension trust
bond, Rs. 10404.00 lakh towards interest on Pension Bonds and Rs. 2420.00
lakh towards other finance charges for the year 2017 – 2018. The applicant has
provided the computations showing actual amounts of interest chargeable in
revenue accounts in the Form-C to Annexure – 1 in Volume – IIB of their petition.
2.38 Cost of depreciation of assets of WBSEDCL which will be in service during the
years 2017 – 2018 stated to have been computed following depreciation
schedule as per Annexure – A in the Tariff Regulations and projected at Rs.
69810.00 lakh. The details of the calculation of depreciation have been given in
the Form – B to Annexure – 1 in Volume – IIB of their petition.
2.39 WBSEDCL has not claimed any amount under the head advance against
depreciation for 2017 – 2018.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 19
2.40 Regarding interest on working capital requirement, WBSEDCL has submitted
that, based on the directive of the Commission vide paragraph 8.11 of its tariff
order for 2008 – 2009, the average security deposit of permanent consumers
(excluding provision for security deposit) for the ensuing year 2017 – 2018 has
been considered for utilization as working capital for the respective year. The
gap, if any, between the normative working capital requirement and the average
security deposit, is required to be considered as working capital requirement for
the year and the interest thereon be claimed as per provisions of the Tariff
Regulations. WBSEDCL, however, has not claimed any amount as interest on
working capital during the year under the control period.
2.41 The applicant has not claimed any amount towards reserve for unforeseen
exigencies for the year 2017 – 2018 under the fifth control period. WBSEDCL
stated that Reserve for Unforeseen Exigencies will be considered if invested as
per direction of Commission in the APR of respective year.
2.42 The applicant has not considered any provision for net DSM charges payable for
the year 2017 – 2018. However, WBSEDCL prayed to consider DSM charges on
actual basis in the APR of respective year.
2.43 WBSEDCL has projected Rs. 201.00 lakh towards contingent expenses under
the head ‘other debits’ for the year 2017 – 2018. However, the expenses under
this head will be claimed at actuals in the APR of the respective year.
2.44 WBSEDCL has not considered any provision for special allocation for the year
2017 – 2018. However, special allocation will be considered on actual basis in
the APR of respective year.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 20
2.45 WBSEDCL has estimated the provision for Minimum Alternative Tax (MAT) for
the years 2017 – 2018 considering MAT rate 21.3416% which is the effective tax
rate for 2015 – 2016.
2.46 WBSEDCL has projected the return on equity at Rs. 44700.00 lakh for the year
2017 – 2018 under the control period stated to be considered on pre-tax basis on
the permitted returns @ 16.5% on the average equity base as per the Tariff
Regulations. It is submitted that no new equity addition for the year 2017 – 2018
has been considered.
2.47 WBSEDCL has proposed to release the balance amount of Rs. 22140.00 lakh
against the payable arrear arisen out of tariff order dated 30.12.2011 for new
units of WBPDCL. WBSEDCL has also requested to release an amount of Rs.
30091.26 lakh against the balance payable FCA of WBPDCL for the year 2012 –
2013 as per the order of the Commission dated 11.12.2014 in respect of
WBPDCL. WBSEDCL has referred a letter no. 148-PO/O/VS/55-30/2016 dated
5th September, 2016 issued by the Government of West Bengal wherein a grant
of Rs. 191607.00 lakh equivalent to outstanding loan and interest was extended
to WBPDCL, which may be considered for adjustment against the APR & FCA of
WBPDCL for the years 2013 – 2014 to 2015 – 2016. WBSEDCL has claimed a
sum of Rs. 76483.00 lakh towards carrying cost on the amount claim amount of
APR and FPPCA for the year 2013 – 2014 onwards considering the interest rate
as per SBI PLR of 14.05% as on 1st
2.48 Total expenditure of Rs.2097241.00 lakh has been computed by the applicant
and after excluding the revenue earned from other income, from bulk supply and
supply to Sikkim, expenses attributable to export and taking into account the
benefits passed on to the consumers, interest credit on depreciation and taking
into account the part release of regulatory assets and carrying cost as proposed
April, 2016.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 21
by them the annual revenue required from sale of energy to its consumers has
been estimated by the applicant at Rs. 1912327.00 lakh for 2017 – 2018.
2.49 With projected revenue requirement of Rs. 1912327.00 lakh from sale of
25327.00 MU of energy to its own consumers, the average cost of supply per unit
has been computed by the applicant at 755.00 paise / kWh for the year 2017 –
2018.
2.49.1 It is stated that CESC draws power occasionally from WBSEDCL to meet power
shortage when CESC fails to arrange such power from other sources. CESC was
asked to project their requirement of power during the year 2017 – 2018, but no
reply has been received from CESC. In such circumstances, the sale of power to
CESC has been estimated at 10 MU during the year 2017 – 2018. CESC has yet
to execute a fresh PPA with WBSEDCL for two part tariff. In view of above,
WBSEDCL proposed that CESC should intimate at least one/two month in
advance the demand for power from WBSEDCL and also proposed to supply
such scheduled power to CESC at single part tariff at an energy charge of Rs.
6.96 per kWh, average 33 KV industrial tariff under CESC area in 2016 – 2017.
However, for drawal of power more than the scheduled demand or sudden
requirement of power, WBSEDCL proposes 30% more than the above stated
energy charge of Rs. 6.96, i.e., Rs. 9.05 shall be payable by CESC.
2.49.2 WBSEDCL also proposed to sell power to DVC on single part tariff at a rate of
Rs. 6.96 per kWh and Rs. 9.05 per kWh following the methodology proposed for
consideration of sale rate for CESC, since no rate has been determined by the
Commission for sale to DVC by WBSEDCL. This is for the reason that no PPA
has been executed between WBSEDCL and DVC regarding two part tariff.
2.49.3 The applicant has also proposed to sale power to IPCL and DPL on single part
tariff basis at an energy rate of Rs. 5.40 per kWh and Rs. 4.63 per kWh
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 22
respectively with a further proposal of 30% higher tariff for the same reason as
that of CESC.
2.50 Changes proposed by WBSEDCL in their tariff for 2017 – 2018 are as follows.
(I) As a part of demand side management to encourage the 33 kV and 132
kV industrial consumers reduce their drawal of load in peak period and to
shift the load to off-peak period the following rebates shall be allowed:
a) a rebate equivalent to the difference of the following two will be
allowed,
i) Demand charge calculated as per regulation 4.3.6 of the
Tariff Regulations; and
ii) Demand charge computed based on the maximum
demand of normal \
b) Similarly for the above consumers keeping their maximum
demand during off-peak period within 150% of contract demand, a
rebate equivalent to the difference of the following two will also be
allowed:
period or maximum demand of peak
period or contract demand in case of off-peak period or
85% of contract demand whichever is higher, if those
industries keep their maximum demand during off-peak
period within 150% of contract demand.
i) Additional demand charge calculated as per regulation
4.7.2 of Tariff Regulations; and
ii) Demand charge computed .based on the methodology for
additional demand charge for the normal and peak period
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 23
will be as per regulation 4.7.2 of Tariff Regulations but
there will be no additional demand charge applicable for
off-peak period.
c) Similarly for the above consumers keeping their maximum
demand during off-peak period within 150% of contract demand, a
rebate equivalent to the difference of the following two will also be
allowed:
i) Load factor rebate computed as per the rates without
considering the additional kWh and KVA drawn during off-
peak period over contractual demand; and
ii) Load factor rebate computed as per the rate.
All the above rebates are effective from the month of April, 2017 subject
to the condition that payment is made within the due date.
(II) Treatment of Life line category consumers:
It has been observed that some of the domestic consumers of WBSEDCL
(with contract demand not more than 0.3 KW) consume more than 75
units during some quarters and consume less than 75 units for other
quarters. Accordingly whenever such a domestic consumer consumes
less than 75 units in a quarter, such consumer is billed at the tariff of Life
Line Consumer for that particular quarter. For other quarters wherein the
consumption of the domestic consumer exceeds 75 units, the consumer
is billed at the tariff of Domestic (Urban) or Domestic (Rural) category as
the case may be.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 24
WBSEDCL submits that the Commission has created such a provision of
Life Line Consumers in order to make electricity affordable to those poor,
consumers who don’t have the capability to afford electricity at the normal
rates. In this respect, WBSEDCL submits that increased electricity
consumption by this domestic consumer beyond 75 units / quarter should
debar them for availing life line category tariff for increased consumption
in its house hold.
WBSEDCL appeals before the Commission to consider such consumers
as either domestic (rural) or domestic (urban) and not as Life line for the
future years if the quarterly consumption for such domestic consumer
(having CD < 0.3 kW) exceeds 75 units taking average of energy
consumption of last 12 months.
(III) Minimum Charge of various consumer categories:
WBSEDCL submits that Minimum charges on consumers will guarantee a
certain amount of Revenue for part-recovery of fixed charges for
WBSEDCL. WBSEDCL has PPAs with generators based on demand of
the consumers to keep power supply uninterrupted. Thus, WBSEDCL has
to pay fixed cost to the generators even without drawal of power from the
generators due to lesser system demand.
In view of the above, WBSEDCL proposes Minimum charge for various
categories of consumers with revision in Minimum charge for categories
as shown in the Form 3.7 of Annexure-3 of Volume-IV.
WBSEDCL submits that the proposed Minimum charges should be
applicable as per regulation 4.13 of notification no.48/WBERC dated
25.04.2011, the same is reproduced below for ready reference:
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 25
“Minimum Charge shall be applicable when the sum of energy
charge and fixed charge including rebate/surcharge (except
rebate for timely payment) is less than the minimum charge for the
billing period"
(IV)
WBSEDCL submits that it collects meter rent from its consumers for
meters installed by WBSEDCL at its cost. Meter Rent paid by consumers
was last revised by WBERC via tariff order of 2010-11 dated 30.12.2011,
WBSEDCL proposes revision in Meter Rent as shown in the Form 3.7 of
Annexure-3 of Volume-IV.
Meter Rent:
(V)
WBSEDCL submits that other charges are borne by consumers due to
Meter testing charge and Disconnection / re-connection of supply at
consumer premises. Such charges are collected from the consumer by
WBSEDCL if the activity is undertaken due to consumers fault and not
otherwise.
Such charges borne by the consumers were last revised by WBERC via
tariff order of 2010-11 dated 30.12.2011. WBSEDCL proposes revision of
these charges as the cost borne by WBSEDCL for such Meter testing and
Disconnection / reconnection of supply has gone up considerably since
2011-12.
Other charges - Meter testing and Disconnection / Re-connection
Charges:
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 26
The existing and proposed Meter testing charge and Dis-connection / re-
connection of supply charges is shown in the Form 3.7 of Annexure-3 of
Volume-IV
(VI) In the backdrop of reduced electricity consumption by the 33 kV and 132
kV industrial consumers of WBSEDCL, WBSEDCL proposed a scheme
for revenue enhancement through increased sale to 33 kV and 132 kV'
industrial consumers, the scheme is enclosed as Annexure 8 of Volume
5. The scheme may be continued till issuance of the tariff order for 2017-
18. Rates mentioned in this scheme may be considered for modification
for the year in accordance with the tariff order of 2017 – 2018.
(VII) Tariff for Military Engineering Services (MES) applicable for High and
Extra-high voltage has been proposed to be applicable for LV&MV
consumer (50 KVA and above but upto 125 KVA).
(VIII) Presently off-peak period means the time period from 11 pm to 6 am.
Considering demand position of WBSEDCL system, WBSEDCL proposes
to increase off-peak period for industrial consumers with supply of 33 kV
onwards as 11 pm to 8 am and normal period as 8 am to 5 pm for
consideration of Commission and shall be applicable after two months of
issue of tariff order.
(IX) The fixed charge/ demand charge in Rs/KVA/Month for consumers has
been proposed as shown in the Forms 3.2 & 3.3 of Annexure-3 of
Volume-IV. The demand charge shall be applicable to different categories
of consumers as per rates as shown in above tariff schedule on the basis
of recorded demand as specified in regulation 4.3.3 of the Tariff
Regulations subject to the conditions specified in the Tariff Regulations.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 27
When a new consumer gets connected to the system, the computation of
fixed charge or demand charge for that month shall be made pro-rata for
the number of (
(X) All other terms & conditions of tariff have been proposed to remain
unaltered and are provided in the Annexure 3 of Volume IV of the
Application.
days of supply in that particular month.
(XI) Other terms and conditions are proposed to be remained unaltered.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
CHAPTER - 3
OBJECTIONS AND SUGGESTIONS
West Bengal Electricity Regulatory Commission 28
3.1 Suggestions, objections and comments on the tariff application of WBSEDCL for
the fifth control period covering the year 2017 – 2018 have been received within
27.03.2017 i.e., the due date from the persons are mentioned in paragraph 1.10
of Chapter-1. The main points of the suggestions, objections and comments etc.
relevant to the instant tariff petition are summarized in the following paragraphs
in this chapter. The Commission’s views on the objections, comments etc. are
also recorded in this Chapter.
3.2 Modern India Con-Cast Limited have stated a number of issues which are
discussed below:
3.2.1 Operation and Maintenance Expenses: During 2015 – 2016, 2016 – 2017,there is a large expansion of distribution network through implementation of
different Rural Projects related to distribution. Moreover there is large volume of
replacement of meters – namely from electro mechanical to hybrid / static etc.
and continuous replacement of meter involves a large increase in distribution
expenses. Since a large chunk of distribution system, commissioned under
various district project, and being almost new, maintenance expenses requires to
be reviewed and should not be allowed on normative basis. Otherwise it will not
be possible to arrest regular increase in tariff, while power purchase cost has
reached to an uncontrollable limit, particularly when market price of power is low.
The modality of fixing the normative value of O&M expenses in view of addition
of new assets requires to be reviewed. It often takes time to submit and issue of
order on APR.
The above point has been noted by the Commission and will be duly addressed
in the subsequent chapter.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 29
3.2.2 Employee expenses: The pay commission report is yet to be submitted. Since the tariff petition is for 2017-2018, any impact on implementation of pay
commission shall be recovered separately. The reason is due to high tariff of
WBSEDCL compared to the most of the other States in India. High ATC Loss
should not be compensated in any manner through the increase of tariff. In fact
pay structure of the employee as well as the Board of Directors should be based
on performance in line with MNC and not in line with Government of Public sector
undertaking.
The above points have been noted by the Commission and will be taken care of
in the relevant portion of the tariff order. However, the employee cost will be
admitted as per the provision of Tariff Regulations, subject to prudence check by
the Commission.
3.2.3 Pension Fund: Pension fund appears to be a welfare scheme of the licensee. WBSEDCL is not a Govt. institution. All the employees are not in the same
pension scheme. Any cost on account of pension should be incurred by the
licensee out of its profit and the same should not be a pass through.
The Commission has dealt with the issue suitably in subsequent chapter.
3.2.4 Outsourcing expenses: Outsourcing expense should have a prudence check. Cost of outsourcing is 67% of direct employee cost which should be reduced.
Such expenses are being checked prudently as per the Tariff Regulations at the
time of determination of APR for the respective year.
3.2.5 Interest on working capital: Since the Bank rate is decreasing, the principles of considering the rate of interest on working capital should be changed & it should
be at actual subject to truing up through APR.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 30
The rate of interest on working capital is being allowed by the Commission as per
the rate prevailing on 1st
3.2.6 Carrying costs: Normally any deficit in cash or working capital is managed through grants/Govt. aid/borrowings from financial institution etc. Consumers
bear the burden of loan or borrowing from financial institution in terms of interest.
Allowing carrying cost in addition to interest burden will put extra burden to
consumers of all category. As such carrying cost should not be allowed, since
the licensee is a profit making utility, should absorb the carrying cost of its own.
April of the previous year for which the tariff order is
determined, subject to truing up through APR as per regulation 5.6.5 of the Tariff
Order.
The Commission has noted the contents.
3.2.7 Bad Debts: Consumers are already heavily burdened with high tariff. Any Bad Debt should not be a pass through in the ARR. Any loss due to it should be
compensated by Govt. of West Bengal or adjusted with the regulatory Assets.
The Commission goes by the Tariff Regulations framed as per the Electricity Act,
2003 which only allows such amount of bad debts as actually has been written
off, subject to a ceiling of 0.5%.
3.2.8 Compensations paid by licensee: Compensation to outsiders, loss of obsolete store materials, compensation of Power Trader should not be allowed, as the
same will be a reward to inefficiency.
The Commission does not allow the compensation amount as a pass through
element in tariff as per provisions of Tariff Regulations.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 31
3.2.9 Report on Power for All (PFA):
(i) WBSEDCL submitted report on Power for All to Govt. of West Bengal in
consultation with M/s Deloitte India Ltd. As such all relevant data should
be in line with this.
The projections are generally being made in the Tariff petition in
accordance with the Tariff Regulations. However, the Commission has
taken a note of it.
(ii) As per report of Power For All (PFA), energy input requirement is 34118
MU against energy sale volume of 25993 MU with total peak demand
6152 MW. With the vast network (Transmission) strengthening, at higher
voltage, transmission loss should be reduced & impact of the same, may
require less input.
While computing the transmission loss, the Commission follows the
norms stipulated in the Tariff Regulations.
(iii) In line with PFA, Employee Cost – with escalation @ 10% YOY,
considering CPI, AG cost escalation @ 6% should be considered @ 1%
of GFA.
The Commission has noted the comment.
(iv) Depreciation for new assets should be considered as 5.28% in line with
PFA.
While computing depreciation in the tariff order, the Commission follows
the provisions as laid down in the Tariff Regulations.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 32
3.2.10 Sale to other distribution licensees: As none of the other distribution licensee has intimated WBSEDCL, their requirement, projection of sale to other Licensee
should be considered nil.
The Commission has noted the comment.
3.2.11 Power purchase cost: Power purchase cost should be computed based on prevailing tariff, not based on tariff petition of ISG, POSOCO and CTU etc.
Requirement of Power as per PFA is 34118 MU. The average cost of power
purchase may be considered as 350 P/KWH less by 2% rebate. Accordingly
Power Purchase Cost for sale to consumers shall be Rs 11702 Cr.
The Commission does not find any valid logic in objector’s estimation of power
purchase cost for sale to consumers. The Commission determines power
purchase cost based on the provisions given in the Tariff Regulations and on its
decision felt to be the best.
3.2.12 Purchase of power from Renewable and co-generation sources: While average power purchase cost is around Rs. 350 P/KWH, WBSEDCL is reluctant
to pay the cap price of Co-Gen power i.e. @ 334 P/KWH, thereby depriving this
green power producer & discouraging to inject the same in the grid. Tariff model,
built in the PPA for Co-gen power should be quashed & CERC model should be
implemented.
The above comments are related to RE Regulations and do not attract the Tariff
Regulations which is followed for preparation of tariff order. However,
Commission will give direction to the licensee to fulfill their RPO obligations.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 33
3.2.13 Power purchase from WBPDCL:
(i) R&M work of BTPS 5th
(ii) Generation from KTPS first 3 units appears to be uncertain due to penal
action taken by Green Tribunal. Generation from other 3 units need to be
maximized.
unit has been done & it should supply regularly the
rated capacity as the investment cost is very high. The available
generation from other units of BTPS i.e. 4X60 MW should confirm to
around 55% considering Renovation and Modernization work.
(iii) However, the performance of WBPDCL appears not in order in spite of a
lot of investment under R&M Programme. There should be more penal
measure, unless the generator is able to achieve a good performance as
required by the system. It is to be kept in mind, that a good performance
in the matter of available generation will reduce the net power purchase
cost. As such any bad performance should be reflected in the pay
structure of the employee as well the Board of director.
The Commission noted the comments. While determining the power purchase
cost of WBSEDCL, the capacity charge payable by WBSEDCL for each
generating station of WBPDCL is being considered based on the reduced
projected Plant Availability Factor.
3.2.14 Sale of surplus Power:
(i) As per PFA, Energy availability during FY 18 is 37723 MU and surplus
will be 3605 MU. Again peak demand is 6152 MW, against availability of
7029 MW i.e. a surplus of 877 MW. Any surplus of power / energy may
be traded in the market. As per CERC report average realization of sale
through Traders is Rs. 411 P/KWH. As such Power purchase cost shall
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 34
be considered as Rs. 12940 Cr. After 2% rebate that may be availed as
per PPA if payment is made within due date.
The entire expenditure and income of the licensee for a particular year is
being checked prudently at the time determination of APR for the said
year. Therefore, the comments of the objector regarding trading of excess
power are being dealt at the time of APR determination. Regarding power
purchase cost, the view of the Commission is already given at paragraph
3.2.11 above.
(ii) Profits, if any, from sale to persons other than own consumers shall be
deducted from Gross ARR. However, if sale price / market price is less
than pool power purchase cost, some alternative means for assured
income may be invested, so that burden due to loss of revenue for sale at
low price may be avoided.
The Commission takes care of the comments as per the provisions of the
Tariff Regulations while determining tariff order/APR.
(iii) As there appears to be a surplus power, except some incidental
requirement, requirement of power purchase from market should not be
considered through.
The Commission noted the contents.
3.2.15 Alternative means to dispose surplus power instead of Banking of Power :
(i) Banking of Power may be avoided as it involves cost due to open access
charges & losses, interest cost of energy purchased. It is better that
surplus power may be sold through trader, allowing open access to the
interested buyer. A model may be built up as here under. Some high
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 35
value consumer, who may have a variable demand, who may be captive
generator also or who intend to be group captive owner may opt to buy
such surplus power through trader at some concessional rate, if open
access is allowed under this model.
(ii) Trader should have PPA with a person who may be consumer of the
licensee.
(iii) Interested buyer shall be allowed short term open access with a provision
for ABT complaint meter for energy accounting and power to be sold on
schedule basis.
(iv) Buyer should draw power over and above Contract Demand.
(v) If it is an additional power, over and above contract demand then there
shall be no Cross Subsidy Surcharge (CSS). Otherwise CSS will be
applicable along with additional surcharge.
(vi) Price should be fixed in between night off peak power and average price
of power in the Power market.
(vii) This will enable WBSEDCL –
� to avoid Open Access Charges & Loss due to sale to person other than
own consumers and Licensees,
� the demand for Open access approval for import by consumers from a
source other than the licensee concerned,
� additional revenue on account of wheeling charge and
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 36
� backing down may be avoided and full utilization of generation
capacity.
The objector has sought for certain change in Tariff Regulations. It may be put on
record that the Tariff Regulations were finalized through previous publication.
Having received suggestions, objections and comments the Commission in
exercise of its delegated legislative power duly considered the matter in details
and framed such regulations and the regulations were notified in the Kolkata
Gazette. In tariff determination proceedings once the regulations are framed by
the Commission, there is no scope to review or change such statutory norms in
tariff determination proceedings. Accordingly, the comments for change in the
Tariff Regulations are not considered. Thus, such issue will not be dealt in
subsequent chapter further.
3.2.16 Reduction of distribution loss:
(i) Distribution Transformer failure in the district varies in the range of 4% to
10%. It should be brought down.
(ii) Reduction in ATC loss level, in districts particularly Birbhum, Beharampur
and Malda needs special attention. However, Technical loss can be
improved through religious implementation of distribution project, i.e.
DDUGJY, IPDS, RAPADRP & RGGVY. A lot of investment around Rs.
9056 Cr, up to financial year 2018-19, is under process. Entire
investment is funded through grants.
(iii) WBSEDCL should take initiative religiously to improve distribution loss
through Condition Monitoring for preventive maintenance, Transformer
Transaction Management System, Feeder Length Reduction, Feeder
Segregation, Use of Amorptious core DTR installation, Re-conductoring,
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 37
Installation of AB cable etc. Further commercial Loss to be reduced a lot.
Consumption analysis is required at Field level to identify loss area.
The Commission has already taken various steps with the licensees in
different forum for reduction of AT&C / Distribution losses. However,
necessary directions are being given to the licensees for energy audit /
loss audit.
3.2.17 Regarding proposal for increase in Fixed Cost:
(i) Consumers are paying charges effectively under 3 part tariff scheme i.e.
Demand Charge or fixed charge, energy charge & MVCA. A lot of
irregularities may be found out, if consumption pattern is religiously
analyzed for each of the consumers. This is because, the connected load
(CD) / declared capacity, in a large number of cases will reflect that those
are, not appropriate and commensurate with their consumption volume. It
is the general experience that almost all categories of consumers have
declared their contract demand, not commensurate with their
consumption. Majority of household consumers have suppressed
contract demand, thereby licensees fixed cost recovery is not
commensurate with their drawal petition of the consumers. If each of the
consumers is put under scanning it will be found that there is no need to
increase the fixed cost. It is the inefficiency and lack of initiative of the
management to set right the issue, considering it to be difficult. Rather
they want to find an easy solution, for loss of revenue in this regard, by
increasing tariff in the form of fixed cost. Hon’ble Commission may quash
the demand in increase in fixed cost. Moreover, charges of fixed cost of
house hold have been increased within a short span. It should not be
further increased rather leakage in this area should be arrested.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 38
The Commission has noted the contents and will give appropriate
directions to the licensee. However, the fixed charge / demand charge is
allowed as per provisions of the Tariff regulations.
(ii) Again some of the households have more than one meter which are
overlooked by the licensee. In turn the recovery of energy charge under
slab rate is low. A loss in this case, automatically put burden on energy
rate. Licensee should be directed to reduce loss under above cases.
The comments are noted.
(iii) As WBSEDCL have to off-take minimum drawal, even after backing down
of generation, in the event of low demand, subject to the technical limit of
the generating unit, minimum drawal of all consumers should be
guaranteed in terms of charges.
The comments are noted.
(iv) WBSEDCL has executed lot of PPA, considering a very optimistic
perspective planning. It was considered granted that there would be an
industrial revolution in West Bengal and a surge of demand.
Unfortunately, the revolution is yet to take place but the obligation of PPA
for drawal of power remain. This ill-considered planning of the then
management of WBSEDCL has not yet been highlighted. As such
consumer should not be burdened with increase in fixed cost to protect
the inefficiency.
The Commission has noted the comments. Commission will consider the
fixed cost of generating stations from which the power are being
purchased by WBSEDCL as per their PPA to the extent of sale of power
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 39
by WBSEDCL adjusted with normative T&D losses. Any incidental
surplus has been considered to be sold at average power purchase cost.
3.2.18 Regarding other Tariff Proposals:
(i) Reference to the report on Power for All, West Bengal. Table – 14, the
anticipated peak demand is 6152 MW while Peak availability including
Renewable is 7029 MW i.e. there may remain 877 MW surplus during
Peak Hours. Now WBSEDCL should rethink whether they would like to
sale surplus evening power at in the market depriving its own consumer
setting Peak hour tariff at high level. This is against natural justice. As
such to boost industrial sale, tariff for the peak hour of high valued
industrial consumer should be kept low at a reasonable level and to
compensate the loss of revenue tariff for normal period may be revised.
The comments are noted.
(ii) Any changes of existing rate / charges, terms and conditions as proposed
in the tariff petition shall not be allowed as the same shall be considered
through amendment of existing tariff regulation. The stake holders should
be given opportunity to put up their views/suggestions and objection.
The Commission has noted the comments.
(iii) There is a proposal for change TOD timing, through increase in off-peak
period, it does not indicates, how the loss of revenue due to increase in
off period will be compensated.
The Commission has not considered any change in TOD timing due to
non-submission of any loss benefit analysis by the licensee.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 40
(iv) Any loss in revenue due to implementation of rebate scheme on
additional Load Factor rebate, Maximum demand charge for 33 KV/132
KV industrial consumers, or in multiple licensee area shall not be a pass
through.
The Commission noted the contents and shall be dealt with at the time of
preparation of tariff.
(v) The Commission has introduced a new scheme through the notification
dated 8.02.2017 whereby the difference of the price between DVC and
WBSEDCL has been kept at 50 paise. Presently the price of DVC stands
at Rs. 4.30 per unit for 132 KV DVC consumers whereas the price for
WBSEDCL is Rs. 6.10 per unit for its 132 KV consumers. Hence, the
rebates have to be increased for load enhancement so that the difference
between DVC and WBSEDCL is kept not more than 50 paise per unit.
The Commission has noted the contents. .
3.2.19 Whatever cost has been incurred in terns of FCA, MFCA or MVCA during FY 16-
17, shall be considered for ARR calculation. Implication of Tariff revision of
ISGS/CTU etc. should be taken in account through FPPCA.
Commission has noted the comment and specific direction will be given in the
tariff order in this regard as per provisions of the Tariff Regulation.
3.2.20 Over and above, M/s Modern India Con-Cast Limited have made some additional
important points to note.
i) WBSEDCL fails to comply direction of the Hon’ble Commission as they
have not implemented Energy audit in its organization. Some penal
measure is required in terms of tariff.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 41
ii) Generation is PPSP for 2017-18 with PAF 98% has been considered in
the same level of 2015-16 i.e. 1055MU when PAF was 76.57%. It may
be noted that with PAF 90.78% generation was 1416 MU. As such
correction should made accordingly i.e. we can get around 400MU more
peak power from PPSP.
iii) WBSEDCL has not yet participated in UDAY scheme which is beneficial
to the Licensee and in turn consumer will also be benefitted.
iv) Cost of Backing down of generation and sale of surplus power in the
unregulated volatile market at an average rate of Rs 2.72 p/kWh indicates
poor and inefficient power purchase plan.
v) Increased R&M cost indicated poor maintenance plan and condition
monitoring.
vi) Any waiver of LPSC should not be a pass through a tariff.
vii) WBSEDCL may purchase power from market after having an exercise for
cost benefit analysis where there should be a net gain in the process.
viii) WBSEDCL realize Minimum Charges in terms of Fixed cost / Demand
charge. Though in the tariff petition, WBSEDCL, cleverly, has not given
any annexure of computation of fixed cost / Demand charge, the increase
in consumer base has largely increased. In the process of computation
for average billing rate (ABR), there should not any adjustment on
account of Rebate / Penalty etc. Average energy rate may be computed
after assured revenue income on account of Fixed cost / Demand charge.
Power purchase cost may also be computed without rebate / penalty.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 42
ix) Format 1.10 does not contain the contracted capacity/installed capacity.
Moreover there is no information about hour of operation and Backing
down of generation. They same should be incorporated for having a clear
view of operation and power procurement planning efficiency.
x) Similarly the formats do contain any information of category wise total
consumer, contract demand and the demand met. The same should be
incorporated. This will enable to have a check on the fixed cost / demand
charge that should have been realized.
The Commission has taken note of the above comments and shall deal with the
same, wherever required as per the Tariff Regulations, in the subsequent
chapter.
3.3 M/s Ankit Metal & Power Limited, M/s Rohit Ferro-Tech Limited, Organization of
Indian Engineering Industry and Rashmi Metaliks Limited have submitted their
printed objections with same contents as that of Modern India Con-Cast Limited
against the tariff proposal of WBSEDCL for the year 2017 – 2018. Since the
objections submitted by the above four stakeholders are same with the
objections submitted by M/s Modern India Con-Cast Limited and that they are
already dealt with as above, the objections of above four stakeholders are not
dealt here separately.
3.4 All Bengal Electricity Consumers’ Association (ABECA) has made the following
suggestions:
3.4.1 ABECA commented that if the tariff proposal of the WBSEDCL is allowed then
there will be a further tariff hike of 65.68 paise per unit including MVCA of 23
paise per unit. Besides this tariff hike both the W.B.P.D.C.L. and W.B.S.E.D.C.L.
off and on enhances tariff on the plea of MVCA / MFCA etc. The entire system is
nothing but to enhance the tariff which will affect 1.50 Crores of Electrical
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 43
Consumers of West Bengal and there will be a further inflation in the state and
prices of all goods and services will be increased. Small traders, small scale
industrial units and cultivation in Agriculture will be badly affected and will
virtually close down their activity. This cannot be let loose.
3.4.2 In the gist of Tariff Proposal the W.B.S.E.D.C.L. said that the reasons of increase
of tariff are (i) increase of power purchase cost; (ii) Increase of Transmission
charges; (iii) Increase of employee cost; (iv) Increase of interest on loan; (v) O. &
M. expenses increase; (vi) Release of Regulatory asset etc. ABECA is to state
that the reasons stated in the gist of tariff for 2017-18 are not tenable. The
reasons are as follows:
3.4.2.1 Increase of power purchase cost:
It may be stated here that the W.B.S.E.D.C.L. purchase the power from the
W.B.P.D.C.L. The W.B.S.E.D.C.L. submitted the increased tariff for 2017-18 to
the commission and as per proposal they demanded the increase of average
cost of supply at 9.88 paise per unit.
ABECA already submitted the objection on the enhanced tariff proposal. The
W.B.E.R.C, has not yet allowed the enhanced proposal of the W.B.P.D.C.L.
Moreover W.B.S.E.D.C.L. and the W.B.P.D.C.L. are the Government enterprise.
Previously there was one company i.e. W.B.S.E.B. Then there would be one tariff
for W.B.S.E.B. But due to the evil affect of 2003 Electricity Act for the break up of
W.B.S.E.B. into three Government companies, viz. (i) Generation Company (ii)
Transmission Company and (iii) Distribution Company. The enhancement of tariff
of these three companies imposed a burden of severe tariff hike collectively on
the shoulder of the ultimate consumers and thereby brings an inflationary
situation in West Bengal and the production of Agriculture and Small Scale
Industry will be hampered and in addition to this there will become another
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 44
increase of unemployment in the state. Hence we strongly object the tariff hike
proposal of the W.B.S.E.D.C.L. for 2017-18.
In this context, the Commission likes to mention that at the time of preparation of
tariff order of any licensee, the Commission allows expenditure based on the
provisions of the Tariff Regulations and after prudence check of the proposed
expenditure.
3.4.2.2 Increase of Transmission charges – The reason stated herein above at para
3.3.2.1 above holds goods here also.
The Commission’s views remain same as that of paragraph 3.3.2.1 above.
3.4.2.3 Increase of Labour cost - The imposition of fixed charge and fixed cost in the
Tariff is projected on the higher side. Already 6% growth rate of estimated
Energy Sale to its own consumer of W.B.S.E.D.C.L. is allowed by the
commission in the tariff order dated 28-10-2016 for 2016-17 and considering this
inflated rate of Energy Sale the commission allowed the Aggregate Revenue
Requirement of Rs. 1829944.36 Lakh in 2016-17 which includes Labour Cost
also. Hence a mere annual increment of the employees. Nothing more
enhancement on this
The Commission in the direction to W.B.S.E.D.C.L. in the tariff order dated 28-
10-2016 at page 50 para 4.9 (i) directed a detail breakup showing total
expenditure and employee strength against each level of all categories of
employees including the whole time directors of the Board. If any function of
other companies also then the allocation of cost among the companies shall be
shown separately and distinctly against each level." The direction of the
commission is to be complied within 31st March 2017.
item for which the enhancement of tariff hike is not
reasonable.
-
Tariff Order of WBSEDCL for the year 2017 – 2018
West Bengal Electricity Regulatory Commission 45
From the direction of the Commission it is quite clear that the W.B.S.E.D.C.L. failed to provide the required information relating to employee cost. Hence the proposal of tariff hike on the plea of increase of employee cost is not tenable. As such we oppose the tariff hike of the W.B.S.E.D.C.L. for 2017-18.
The Commission has noted the comments and will be dealt with in subsequent
paragraphs
3.4.2.4 In