order of west bengal electricity regulatory ... 2017-18.pdftariff order of wbsedcl for the year 2017...

202
ORDER OF WEST BENGAL ELECTRICITY REGULATORY COMMISSION FOR THE YEAR 2017 – 2018 IN CASE NO: TP – 65 / 16 - 17 IN RE THE TARIFF APPLICATION OF THE WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED FOR THE YEAR 2017 – 2018 COVERING FIFTH CONTROL PERIOD UNDER SECTION 64(3)(a) READ WITH SECTION 62(1) AND SECTION 62(3) OF THE ELECTRICITY ACT, 2003 DATE: 04.07.2018

Upload: others

Post on 30-Jan-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

  • ORDER

    OF

    WEST BENGAL ELECTRICITY REGULATORY COMMISSION

    FOR THE YEAR 2017 – 2018

    IN

    CASE NO: TP – 65 / 16 - 17

    IN RE THE TARIFF APPLICATION OF THE WEST BENGAL STATE

    ELECTRICITY DISTRIBUTION COMPANY LIMITED FOR THE

    YEAR 2017 – 2018 COVERING FIFTH CONTROL PERIOD

    UNDER SECTION 64(3)(a)

    READ WITH SECTION 62(1) AND SECTION 62(3)

    OF THE ELECTRICITY ACT, 2003

    DATE: 04.07.2018

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    CHAPTER – 1

    INTRODUCTION

    West Bengal Electricity Regulatory Commission 2

    1.1 The West Bengal Electricity Regulatory Commission (hereinafter referred to as

    the “Commission”), a statutory body under the first proviso to section 82(1) of the

    Electricity Act, 2003 (hereinafter referred to as the “Act”), has been authorized in

    terms of the section 86 and section 62(1) of the Act to determine the tariff for a)

    supply of electricity by a generating company to a distribution licensee, b)

    transmission of electricity, c) wheeling of electricity and d) retail sale of electricity,

    as the case may be, within the State of West Bengal.

    1.2 The West Bengal State Electricity Distribution Company Limited (hereinafter

    referred to as WBSEDCL), is deemed to be a licensee under the Electricity Act,

    2003 in terms of fifth proviso to Section 14 of the Act wholly owned by the State

    Government and is engaged in the business of distribution of electricity within the

    area of supply of WBSEDCL in the State of West Bengal and the distribution tariff

    of WBSEDCL shall be determined by the Commission.

    1.3 West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff)

    Regulations, 2011 has come into effect from 29th April, 2011. The said Tariff

    Regulations, 2011 was further amended by notifying the West Bengal Electricity

    Regulatory Commission (Terms and Conditions of Tariff) (Amendment)

    Regulations, 2012 in the extra ordinary edition of The Kolkata Gazette dated 27th

    August, 2012 and West Bengal Electricity Regulatory Commission (Terms and

    Conditions of Tariff) (Amendment) Regulations, 2013 in the extra ordinary edition

    of The Kolkata Gazette dated 30th

    1.4 In terms of definition contained in regulation 1.2.1 (xxx) of the West Bengal

    Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations,

    2011, as amended from time to time (hereinafter referred to as the ‘Tariff

    July, 2013.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 3

    Regulations’), each control period after third control period shall be normally for a

    period of five ensuing years or such other period of number of ensuing years as

    may be decided by the Commission from time to time. The Commission vide his

    order dated 04.05.2016 in Case No. SM-13/16-17 decided that the fifth control

    period shall also be consisting of three ensuing years for the period from 2017 –

    2018 to 2019 – 2020. But, after careful consideration of all relevant factors, vide

    its order dated 14.12.2016 in Case No. SM-15/16-17 decided that the fifth control

    period shall be for one year and consist of 2017 – 2018 only and vide its order

    dated 14.12.2016 in file no B-11/20 decided that the last date for filing of tariff

    petition for the fifth control period shall be 31.12.2016. WBSEDCL accordingly

    submitted the petition for determination of tariff for the fifth control period

    consisting of the year 2017 - 2018 on 22nd

    1.5 On scrutiny of the application, it was observed that some documents required as

    per regulation 2.5.2 and some Forms as prescribed in the different annexures as

    per regulation 2.7.2 of the Tariff Regulations, were not submitted along with the

    tariff application. Accordingly, WBSEDCL was requested to submit all those

    documents/forms vide Commission’s letter no. WBERC/TP-65/16-17/2171 dated

    27

    December, 2016

    th January, 2017. In reply, WBSEDCL submitted the required documents /

    forms vide their letter No. REG/SERC/MYT 5th Control Period/479 dated 8th

    1.6 The tariff application submitted on 22.12.2016 along with the information / data,

    documents, forms submitted on 08.02.2017 as per Tariff Regulations (collectively

    called as “tariff application”), were admitted by the Commission in case No.TP-

    65/16-17 and communicated to WBSEDCL vide letter dated 20.02.2017 with the

    direction to publish the gist of their tariff application, as approved by the

    Commission, in the news papers and also in their website as per provisions of

    the Tariff Regulations. The gist was, accordingly, published simultaneously on

    February, 2017.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 4

    24.02.2017 in the news papers - (i) ‘Business Line’ (English), (ii) ‘Ekdin’

    (Bengali), (iii) ‘Dainik Statesman’ (Bengali) and (iv) ‘Jansatta’ (Hindi). The gist

    along with the tariff application and additional information / data submitted vide

    letter dated 08.02.2017 were also posted in the website of WBSEDCL. The

    publication invited the attention of all interested parties, stake holders and the

    members of the public to the application for determination of tariff of WBSEDCL

    for the fifth control period and requested for submission of suggestions,

    objections and comments, if any, on the tariff application to the Commission by

    20.03.2017 at the latest. Opportunities were also afforded to all to inspect the

    tariff application and to take copies thereof. It is noticed by the Commission that

    the approved gist published in the news papers are not in consonance with the

    with the stipulations contained in its letter dated 20.02.2017, nor does it satisfy

    the requirement for publishing a notice containing a gist of the tariff application in

    the daily newspapers “widely circulated in your area” as specified in regulation

    2.7.3 of the Tariff Regulations. WBSEDCL was, therefore, directed to publish the

    gist afresh in newspaper “widely circulated in your area” vide its letter dated

    15.03.2017. WBSEDCL was directed to publish a notice extending the last date

    of submission of objections / suggestions / comments against the tariff

    application for the year 2017 – 2018 in those newspapers where the gist of the

    tariff application was earlier published on 24.02.2017.

    1.7 WBSEDCL accordingly published on 23.03.2017 a notice duly approved by the

    Commission regarding extension of due date for submission of objections and

    suggestions against the tariff application for the year 2017 – 2018 upto

    27.03.2017. The notice regarding extension of date of submission was also

    posted in the official website of WBSEDCL.

    1.8 Objections to / comments on the aforementioned tariff petition of WBSEDCL for

    the fifth control period were received by the Commission from the following

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 5

    objectors within the stipulated time i.e., 27.03.2017 and the same have been

    recorded in a summarized form in Chapter 3 of the instant order.

    I. Rashmi Metaliks Limited,

    II. Organization of Indian Engineering Industry,

    III. Rohit Ferro-Tech Ltd,

    IV. Ankit Metal and Power Limited,

    V. Modern India Concast Limited,

    VI. All Bengal Electricity Consumers’ Association (ABECA).

    1.9 Commission, vide letter dated 28.03.2017 requested WBSEDCL to submit

    additional clarifications in regard to sales forecast, power purchase, load-

    generation balance and cost of outsourcing. In reply to Commission’s letter dated

    28.03.2017, WBSEDCL submitted the required clarification, as asked for, vide

    their letter dated 12.04.2017.

    1.10 The Commission determines the tariff in accordance with the Electricity Act, 2003

    and the Tariff Regulations framed thereunder and for this purpose, the

    Commission has estimated the expenditure for 2016 – 2017 to arrive at the

    estimated expenditure / cost under different heads for the years 2017 – 2018.

    1.11 The estimation made for 2016 – 2017 by the Commission shall not be construed

    by WBSEDCL as admission of at least such estimated amount in APR for 2016 –

    2017. On the other hand, if in APR any deduction is made then as a conclusion

    from such decision one shall not expect that the impact of such deduction is to be

    continued in fifth control period as this will tantamount to imposing a penalty for

    infinite nature or double penalty for the same inefficiency.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    CHAPTER – 2

    THE CASE OF WBSEDCL

    West Bengal Electricity Regulatory Commission 6

    2.1 The applicant WBSEDCL has submitted the application for determination of

    Aggregate Revenue Requirement (ARR) and tariffs for the fifth control period

    covering the year 2017 – 2018 under MYT framework in accordance with the

    Tariff Regulations. The applicant has projected the ARR and the tariffs for 2017 –

    2018 under the fifth control period and has prayed for allowing the same. The

    applicant has also prayed for other dispensations which are mentioned in

    subsequent paragraphs.

    2.2 WBSEDCL has projected the ARR for the year 2017 – 2018 at Rs 1912327.00

    lakh and the average cost of supply for 2017 – 2018 at 755.00 Paise / kWh. The

    reasons for enhancement of tariff are stated as follows:

    i) The Fuel Cost Adjustment (FCA), Monthly Fuel Cost Adjustment (MFCA) and Monthly Variable Cost Adjustment (MVCA) payable to different

    agencies for purchase of power has increased considerably.

    ii) Due to increasing network, improved customer service facilities and price index expenses towards Repair & Maintenance (R&M), outsourcing cost

    due to maintenance and operation of new line and substations, spot

    billing service, mobile maintenance service and zonal call centre, etc. has

    increased.

    iii) Increase of employee cost considering impact of 7th

    iv) Probable enhancement of transmission charges payable to WBSETCL.

    Pay Commission.

    v) Increase in CTU charges due to implementation of Point of Connection (POC) charge mechanism by CERC.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 7

    2.3 It is also submitted by the applicant that the Commission may consider rise in

    price index and consumer base, rise in power purchase cost and operating cost

    resulting in increased cost of business.

    2.4 It is stated by the applicant that while determining the ARR for the year 2017 –

    2018 under the fifth control period, all infrastructure investment and power

    procurement plan have been made assuming that all consumers under

    WBSEDCL area will continue with power supply from WBSEDCL.

    2.5 WBSEDCL has claimed that with fast growing / expanding distribution network,

    additional consumers are being added with WBSEDCL system during the last

    few years. It is stated that based on trend of increase in number of consumers in

    last five years, consumers’ strength of WBSEDCL has been projected for the

    year 2017 – 2018. The consumption of different categories of consumers during

    the year 2017 – 2018 stated to have been estimated as per CAGR of

    consumption during the last four years of the respective category of consumers

    in the following manner:

    � For LT & HT (Domestic, Commercial, Public Bodies) and LT (Industrial,

    Irrigation, Public Lighting), CAGR of consumption during the last four years.

    � For Commercial Plantations, Construction Power and Others, the

    consumption during 2015 – 2016 has been considered.

    � 1% annual increase during the year 2018 in HT Industrial category has been

    considered due to introduction of various incentives.

    2.6 Total sale of energy to own consumers of WBSEDCL has been projected as

    25327.00 MU in the year 2017 – 2018. Distribution loss has been projected on

    the normative basis at a level of 17.50% for 2017 – 2018.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 8

    2.7 The applicant has also projected sale of energy to other licensees viz. CESC

    Limited, Damodar Valley Corporation (DVC), The Durgapur Projects Limited

    (DPL) and India Power Company Limited (formerly known as DPSC Limited)

    (IPCL) during the year under the control period. The projection of sale of energy

    to CESC Limited stated to have been made on the basis of drawal trend by

    CESC Limited during the year 2016 – 2017 at a level of 10 MU for the year 2017

    – 2018. The projection of sale of power to DVC has been projected to be 5 MU

    during the year 2017 – 2018. The projection of sale of power to DPL as stated to

    have been estimated at 20 MU for 2017 – 2018 as per drawal trend of DPL. The

    sale of power to IPCL stated to have been estimated at 40 MU during the year

    2017 – 2018 as per the drawal trend of IPCL during the year 2016 – 2017.

    2.8 In terms of an agreement signed between the Govt. of West Bengal and Govt. of

    Sikkim, the applicant has claimed that 20% of the sent out generation from

    Rammam Hydel station Stage-II shall be supplied to Government of Sikkim

    during the year 2017 – 2018. Accordingly, energy to be supplied to Government

    of Sikkim has been estimated at 50 MU during the year 2017 – 2018.

    2.9 WBSEDCL projected power purchase requirement based on the factor as

    specified in 2.5 to 2.8 above and the cost of power purchase has been

    considered based on the bill of respective generating stations during the month

    of August, 2016 or the tariff petition/application where available or from the price

    as projected by the generating companies.

    2.10 WBSEDCL has submitted the projection of the energy balance that has been

    arrived based on the estimated consumption, loss in distribution system of

    WBSEDCL and loss in transmission system of WBSETCL at the normative level

    as per Tariff Regulations. It is also submitted that the petitioner has to consider

    the loss in central and state grid, as applicable.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 9

    2.11 Sale of incidental surplus energy to the persons other than consumers and

    licensees during 2017 – 2018 has been estimated by the applicant to be at a

    level of 7102 MU. In view of the present poor and unpredictable condition of

    power market, the price for such power sale has been considered at pool rate of

    power purchase of respective year. No projection has, however, been made by

    WBSEDCL towards banking of power through swap arrangement for the year

    under the control period. WBSEDCL may have to swap out power during real

    time operation during the year 2017 – 2018.

    2.12 WBSEDCL has two main hydel power stations situated at Rammam and

    Jaldhaka. Based on same PLF as in 2015 – 2016 with auxiliary consumption, the

    generations for the year 2017 – 2018 from Rammam hydel power station and

    Jaldhaka Stage – I hydel power station has been projected as 251.46 MU and

    136.62 MU respectively.

    2.13 WBSEDCL also has a pumped storage project at Purulia. WBSEDCL submitted

    that, the Purulia Pumped Storage Project (PPSP) provides spinning reserve and

    utilized as and when required to meet the system demand. Annual gross

    generation at a level of 1055 MU has been projected for the year 2017 – 2018

    according to the system requirement and considering optimum utilization of the

    surplus power during the off peak hours.

    2.14 WBSEDCL stated to have 10 (ten) small / micro hydel generating stations and

    the generation from those generating stations are projected as generation from

    renewable sources of energy. While projecting the generation from those

    generating stations, it is stated that the generation from all such generating

    stations have been estimated based on previous trend. The generation from the

    small / micro power stations has been projected at 141.63 MU for the year 2017

    – 2018.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 10

    2.15 WBSEDCL is maintaining a diesel generating plant at Rudranagar in Sagar

    Island which was earlier supplying power to the consumers at Sagar Island. The

    load at Sagar Island is now being catered through grid. No generation has been

    projected from the diesel generating station for the year under the control period.

    2.16 WBSEDCL has installed grid connection solar PV plants (10 kW) each at 92

    schools out of 100 Government and Government aided schools in different

    districts in October, 2015. WBSEDCL has also commissioned 10 MW solar PV

    project at Teesta canal bank in August, 2016. Some more solar PV projects are

    in pipe line of either finalization or consideration for commission during the year

    under control period. The annual generation from those new solar power stations

    is project at a level of 75.250 MU considering 13% CuF.

    2.17 WBSEDCL is continuing to purchase power from different agencies namely West

    Bengal Power Development Corporation Ltd. (WBPDCL), The DPL, IPCL,

    Damodar Valley Corporation (DVC), NTPC Ltd. (NTPC), NHPC Ltd (NHPC) and

    PTC Ltd (PTC). It is also submitted that conventional power will also be

    purchased directly from the new units of WBPDCL, NTPC, NHPC, DVC and

    other generators and from electricity traders to meet the system demand of

    WBSEDCL during the fifth control period. WBSEDCL will also purchase power

    from different renewable and co-generation sources of energy during the ensuing

    years under the fourth control period.

    2.18 The planning of power purchase has been claimed by WBSEDCL to have been

    done keeping in view the following aspects:

    a) Estimated system demand for the ensuing years based on the projected load

    growth.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 11

    b) Maximum generation that may be available from the hydel power stations of

    WBSEDCL.

    c) Commitment to meet the peak system demand.

    d) Requirement of pumping energy for optimum utilization of PPSP to meet the

    system demand.

    e) Effort to keep spinning reserve as per regulation to meet emergency situation

    while sudden break down of any unit occurs.

    WBSEDCL has claimed that besides purchasing power through grid system, they

    will also purchase some quantum of power in radial mode from DVC at Asansol,

    Burdwan and other areas, from DPL (at 33 KV & 11 KV) in and around Durgapur

    area and from DPSC (at 11 KV) at Asansol area, Govt. of Sikkim (at 11 KV) at

    Rangpoo area and WBREDA (at 11 KV) at Frezerganj area for catering its own

    consumers during the year under the fifth control period

    2.19 It is stated by WBSEDCL that the net generation to be available from the existing

    generating stations of WBPDCL have been computed based on the projection

    received from WBPDCL. As per the projection of WBPDCL, the net energy to be

    available from KTPS, BKTPS, BTPS, STPS, SgTPS (Units I & II) and SgTPS

    (Units III & IV) is 5018.00 MU, 7164.00 MU, 1676.00 MU 3651.00 MU, 2409.00

    MU and 3250 MU respectively.

    2.20 As it is learnt by WBSEDCL that the COD of unit III of the SgTPS has been

    achieved in July 2016 and COD of unit IV of SgTPS was expected in January

    2017. The capacity charges and energy charges for all the existing generating

    stations of WBPDCL for the year 2017 – 2018 have been estimated by

    WBSEDCL considering the same as in August, 2016 including MFCA for the

    respective generating station.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 12

    2.21 WBSEDCL has projected the purchase of power from DPL at 132 kV, 33 kV and

    11 kV during the year 2017 – 2018 considering the trend of drawal by them from

    DPL during 2016 – 2017 and the cost of such power purchase has been

    estimated as per existing rate along with MVCA claimed by DPL in the month of

    August, 2016.

    2.22 The applicant has submitted that any revision of tariff in respect of WBPDCL,

    DPL and IPCL for the year 2017 – 2018 by the Commission have an impact in

    power purchase prices projected by WBSEDCL and that may be considered

    while determining the power purchase cost of WBSEDCL for the year under the

    fifth control period.

    2.23 WBSEDCL has planned to purchase power also from NTPC Limited, NHPC

    Limited and Damodar Valley Corporation (DVC) besides purchase of power from

    WBPDCL, DPL, CESC Ltd and IPCL. WBSEDCL shall also purchase power

    from other generating stations on commissioning of those generating stations

    during the year 2017 – 2018 to meet their load growth. The price of power

    purchase is considered as per tariff applicable to the respective generating

    companies, wherever available or from the price as projected by the generating

    companies. The applicant submitted to consider selling price as may be allowed

    by the CERC in the tariff order of NTPC Ltd., NHPC Ltd, DVC and other

    generators for the respective years while passing tariff orders in respect of

    WBSEDCL for the year 2017 – 2018 if the tariff order in respect of those

    agencies are issued before the tariff order for WBSEDCL are passed by the

    Commission. The applicant also submitted that the proposed power purchase

    price from all thermal power stations are exclusive of impact arising out of FCA or

    MFCA or MVCA (in case of radial power) and any hike of power purchase cost

    due to hike in FCA, MVCA and MFCA may be allowed to be claimed from

    consumers and licensees through MVCA.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 13

    2.24 It is proposed that any hike in power purchase cost of WBSEDCL due to hike in

    FCA, MVCA and MFCA of the generating stations be allowed to claim through

    MVCA from the sale to own consumers and licensees in the State.

    2.25 WBSEDCL has estimated own consumption at the offices and substations for the

    year 2017 – 2018 at 52 MU. WBSEDCL have projected 3350 MU to be procured

    through purchase of short term power generally in the months of April and March

    in order to bridge the gap between supply of power and system demand which

    usually occurs during those months. WBSEDCL submitted that in order to fulfill

    the Solar and Non-Solar RPO, the projection of short term purchase has been

    estimated at 138 MU and 266 MU respectively during the year 2017 – 2018.

    WBSEDCL also stated that in the event of sale price of surplus power in the

    power market becoming not cost effective, the surplus power is being banked

    through swap management for utilization of this surplus power effectively to

    contain the idle capacity charge as well as to maintain grid discipline. The actual

    banking of power under swap arrangement will be considered during FPPCA

    application for 2017 – 2018.

    2.26 WBSEDCL has also projected purchase of power from different new

    conventional and non-conventional power plants during the year 2017 – 2018. As

    per projection, the power purchase from Dagachhu HEP and Assam Power

    under new conventional power plant is 360 MU and 3.50 MU respectively.

    Similarly, WBSEDCL plans to purchase solar power from SECI and VGF scheme

    or other such schemes of Government of India to fulfil its RPO. WBSEDCL has

    indicated its solar power requirement for RPO to the tune of 100 MW during the

    year 2017 – 2018.

    2.27 Considering the projected sent out generation from its own generating stations,

    power purchase from different agencies and the projected sales, energy

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 14

    consumption at own premises, WBSEDCL has projected the energy balance for

    the year 2017 – 2018.

    2.28 The applicant has projected Rs.1408931.00 lakh as power purchase cost for the

    year 2017 – 2018. This power purchase cost includes the cost of purchase of

    estimated quantum of infirm power from the units under stabilization.

    2.29 WBSEDCL projected Rs. 66447.00 lakh for Central Transmission Utility (CTU)

    charges for the year 2017 – 2018 for transmission of WBSEDCL’s share of

    power from the central sector generating stations and other generators outside

    the State through the transmission system of CTU. However, the charges paid to

    the CTU in actual will be claimed in the APR for the respective year.

    2.30 Transmission charges payable to WBSETCL for the energy required to be

    transmitted by the petitioner through WBSETCL system has been projected as

    Rs. 110606.00 lakh for the year 2017 – 2018. However, WBSEDCL has claimed

    Rs. 2034.00 lakh as SLDC charges during the year 2017 – 2018. ERPC charges

    for the year 2017 – 2018 have been projected at Rs. 385.00 lakh. The system

    operation charges payable to POSOCO have been estimated by WBSEDCL at

    Rs. 543.00 lakh for 2017 – 2018.

    2.31 An amount of Rs. 151746.00 lakh has been estimated as employee-cost for the

    year 2017 - 2018. It is submitted that due to demographic and geographic

    considerations, WBSEDCL is to maintain minimum level of employees to provide

    service to its consumers. In the backdrop of the growing consumer strength and

    augmentation of the distribution infrastructure, WBSEDCL has planned to

    augment its manpower strength during the year 2017 – 2018. The manpower

    strength during the year 2017 – 2018 has been planned to be 16363.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 15

    2.32 15% hike has been considered in salary and allowances due to pay revision in

    line with the 7th Pay Commission during the year 2017 – 2018 with a

    retrospective effect from 1st January, 2016. The applicant has considered a D.A

    hike @ 4% for 2017 – 2018. Moreover, increase in pay in respect of normal

    increment of employee-cost has been considered @ 3% on the basic and grade

    pay during the year 2017 – 2018. Other employee expenses are projected in

    proportion to the manpower strength. WBSEDCL has further claimed that

    terminal benefits are calculated based on the actuarial valuation of pension,

    gratuity and leave encashment benefits. As per actuarial valuation made in 2016,

    the projected pension and gratuity liability increased at a CAGR of 3.23%

    assuming future salary inflation rate of 6% per annum. Hence, growth rate of

    3.23% over the expenses for 2016 – 2017 has been considered to arrive at the

    figures for 2017 – 2018. In order to accommodate impact of the 7th

    2.33 The applicant has projected Operation and Maintenance (O&M) expenses

    including Repair & Maintenance (R&M) cost for the year 2017 – 2018 at

    Rs.135317.00 lakh, out of which, O&M expenses for generation is 6314.00 lakh

    and for distribution function is 129003.00 lakh. WBSEDCL has claimed that

    distribution assets and consumer strength of WBSEDCL are increasing rapidly

    due to DDUGJY programme and other work such as R-APDRP, National

    Cyclone Risk Mitigation Project, etc. at different parts of their operational area. In

    order to deliver power with reasonable quality parameters and to reduce

    instances of outages for the widely scattered large consumer base, the

    expenditure of R & M works of WBSEDCL has been increased. The O&M

    expenses during the year 2017 – 2018 have been estimated considering the

    consumer growth and general inflation level.

    Pay

    Commission, an increase of 15% over the expenses in 2015 – 2016 has been

    considered during 2016 – 2017.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 16

    2.33.1 Operation and Maintenance (O&M) expenses for generation: WBSEDCL

    submitted that in order to arrive at the O&M expenses for generation hydro plants

    for the year 2017 – 2018, they have considered increase of 3 year CAGR on the

    O&M expenses for the years 2014 – 2015 to 2016 – 2017 approved by the

    Commission based on per MW basis as per the Tariff Regulations. For O&M for

    Solar, WBSEDCL has considered Rs. 7 lakh per MW with escalation of 5.72% as

    per CERC Renewable Energy tariff order dated 30th March, 2016. WBSEDCL

    has estimated Rs. 4943.00 lakh on account of O&M for Hydro and Rs. 398.00

    lakh for Solar.

    2.33.2 Repair and Maintenance (R&M) expenses for distribution function: WBSEDCL

    submitted that repair and maintenance expenses are a part of the core

    distribution activities which reflect the expenditure incurred in respect of

    maintenance of the distribution assets. WBSEDCL also submitted that the ratio of

    R&M expenses to the O&M expenses for distribution is considered to be equal to

    the 2015 – 2016 level, adjusted by a year-on-year growth from the 2014 – 2015.

    Additional expenses are considered on account of IT implementation.

    Accordingly, the projected figure for R&M expenses for the year 2017 – 2018 is

    32831.00 lakh.

    2.33.3 Administrative and General (A&G) expenses for distribution function: WBSEDCL

    submitted that A&G expenses are a part of the core distribution activities which

    reflect the expenditure associated with the necessary administrative support to

    be arranged in order to ensure execution of the electricity distribution activities in

    a smooth and uninterrupted manner. WBSEDCL also submitted that A&G

    expenses are projected at the CAGR from 2012 – 2013 to 2015 – 2016 (i.e.,

    6.5%) over the value of 2015 – 2016.. Additional expenses are considered on

    account of IT implementation. Accordingly, the projected figure for A&G

    expenses for the year 2017 – 2018 is 18348.00 lakh.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 17

    2.33.4 WBSEDCL claimed an amount of Rs. 6123.00 lakh for 2017 – 2018 Rs. for

    establishing and maintaining communication network set up for the complaint

    management mechanism as per West Bengal Electricity Regulatory Commission

    (Standard of Performance) Regulations, 2010 under the head Lease Rental.

    2.33.5 WBSEDCL has claimed Rs. 351.00 lakh considering the present trend under the

    head Complaint Management Mechanism to meet the expenses for – i) toll free

    telephone for registering grievances at ZCC, ii) SMS charge for forwarding

    grievance to Mobile Van, iii) rental charge for IVRS system, iv) separate

    telephone facility at each customer care centre and v) antitheft toll free telephone

    charges.

    2.33.6 WBSEDCL has claimed Rs. 56790.00 lakh for the year 2017 – 2018 under the

    fifth control period towards outsourcing cost.

    2.33.7 WBSEDCL has claimed Rs. 1128.00 lakh towards insurance premium for the

    year 2017 – 2018 considering an annual growth rate equal to the average of the

    past 3-year and 4-year CAGR (i.e., 18%).

    2.33.8 An amount of Rs. 14407.00 lakh has been estimated as expenses towards Rates

    and Taxes. It is submitted that due to increase in number of consumers, the

    number of office establishments, i.e., CCC, Divisional Manager Office have been

    increased and the tax on the establishments has also been revised / increased

    by civic bodies from time to time. The effect of such hike in rates and taxes has

    been considered. The CAGR for rates and taxes was 37% during the year 2016 –

    2017 over the year 2015 – 2016. Therefore, rates and taxes for 2017 – 2018 has

    been increase at a CAGR of 37% over the year 2016 – 2017. It is further

    submitted that Goods and Service Tax (GST) is likely to be implemented during

    the year 2017 – 2018 as per the declaration of Government of India and hence

    the proposed rate of GST on rates and taxes are not assessable at the moment.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 18

    Impact, if any, of GST on rates and taxes shall be claimed at actuals in APR

    petition for the respective year.

    2.34 The applicant has claimed Rs. 2500.00 lakh towards bad debt for the year 2017

    – 2018 for waiver of LPSC of Water Resource Development Department

    (WRDD). However, bad and doubtful debts will be considered on actual basis in

    the APR of respective year.

    2.35 The applicant has stated that the capitalization of expenses for employees cost,

    interest, administrative and other expenditure under the construction activities

    are made for the year 2017 – 2018 following the existing policy of WBSEDCL.

    2.36 WBSEDCL has projected Rs. 49096.00 lakh towards interest on borrowed

    capital, Rs. 30600.00 lakh towards repayment of 1st

    2.37 WBSEDCL has projected Rs. 11500.00 lakh for the year 2017 – 2018 under the

    head interest on security deposit payable to the consumers.

    installment of pension trust

    bond, Rs. 10404.00 lakh towards interest on Pension Bonds and Rs. 2420.00

    lakh towards other finance charges for the year 2017 – 2018. The applicant has

    provided the computations showing actual amounts of interest chargeable in

    revenue accounts in the Form-C to Annexure – 1 in Volume – IIB of their petition.

    2.38 Cost of depreciation of assets of WBSEDCL which will be in service during the

    years 2017 – 2018 stated to have been computed following depreciation

    schedule as per Annexure – A in the Tariff Regulations and projected at Rs.

    69810.00 lakh. The details of the calculation of depreciation have been given in

    the Form – B to Annexure – 1 in Volume – IIB of their petition.

    2.39 WBSEDCL has not claimed any amount under the head advance against

    depreciation for 2017 – 2018.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 19

    2.40 Regarding interest on working capital requirement, WBSEDCL has submitted

    that, based on the directive of the Commission vide paragraph 8.11 of its tariff

    order for 2008 – 2009, the average security deposit of permanent consumers

    (excluding provision for security deposit) for the ensuing year 2017 – 2018 has

    been considered for utilization as working capital for the respective year. The

    gap, if any, between the normative working capital requirement and the average

    security deposit, is required to be considered as working capital requirement for

    the year and the interest thereon be claimed as per provisions of the Tariff

    Regulations. WBSEDCL, however, has not claimed any amount as interest on

    working capital during the year under the control period.

    2.41 The applicant has not claimed any amount towards reserve for unforeseen

    exigencies for the year 2017 – 2018 under the fifth control period. WBSEDCL

    stated that Reserve for Unforeseen Exigencies will be considered if invested as

    per direction of Commission in the APR of respective year.

    2.42 The applicant has not considered any provision for net DSM charges payable for

    the year 2017 – 2018. However, WBSEDCL prayed to consider DSM charges on

    actual basis in the APR of respective year.

    2.43 WBSEDCL has projected Rs. 201.00 lakh towards contingent expenses under

    the head ‘other debits’ for the year 2017 – 2018. However, the expenses under

    this head will be claimed at actuals in the APR of the respective year.

    2.44 WBSEDCL has not considered any provision for special allocation for the year

    2017 – 2018. However, special allocation will be considered on actual basis in

    the APR of respective year.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 20

    2.45 WBSEDCL has estimated the provision for Minimum Alternative Tax (MAT) for

    the years 2017 – 2018 considering MAT rate 21.3416% which is the effective tax

    rate for 2015 – 2016.

    2.46 WBSEDCL has projected the return on equity at Rs. 44700.00 lakh for the year

    2017 – 2018 under the control period stated to be considered on pre-tax basis on

    the permitted returns @ 16.5% on the average equity base as per the Tariff

    Regulations. It is submitted that no new equity addition for the year 2017 – 2018

    has been considered.

    2.47 WBSEDCL has proposed to release the balance amount of Rs. 22140.00 lakh

    against the payable arrear arisen out of tariff order dated 30.12.2011 for new

    units of WBPDCL. WBSEDCL has also requested to release an amount of Rs.

    30091.26 lakh against the balance payable FCA of WBPDCL for the year 2012 –

    2013 as per the order of the Commission dated 11.12.2014 in respect of

    WBPDCL. WBSEDCL has referred a letter no. 148-PO/O/VS/55-30/2016 dated

    5th September, 2016 issued by the Government of West Bengal wherein a grant

    of Rs. 191607.00 lakh equivalent to outstanding loan and interest was extended

    to WBPDCL, which may be considered for adjustment against the APR & FCA of

    WBPDCL for the years 2013 – 2014 to 2015 – 2016. WBSEDCL has claimed a

    sum of Rs. 76483.00 lakh towards carrying cost on the amount claim amount of

    APR and FPPCA for the year 2013 – 2014 onwards considering the interest rate

    as per SBI PLR of 14.05% as on 1st

    2.48 Total expenditure of Rs.2097241.00 lakh has been computed by the applicant

    and after excluding the revenue earned from other income, from bulk supply and

    supply to Sikkim, expenses attributable to export and taking into account the

    benefits passed on to the consumers, interest credit on depreciation and taking

    into account the part release of regulatory assets and carrying cost as proposed

    April, 2016.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 21

    by them the annual revenue required from sale of energy to its consumers has

    been estimated by the applicant at Rs. 1912327.00 lakh for 2017 – 2018.

    2.49 With projected revenue requirement of Rs. 1912327.00 lakh from sale of

    25327.00 MU of energy to its own consumers, the average cost of supply per unit

    has been computed by the applicant at 755.00 paise / kWh for the year 2017 –

    2018.

    2.49.1 It is stated that CESC draws power occasionally from WBSEDCL to meet power

    shortage when CESC fails to arrange such power from other sources. CESC was

    asked to project their requirement of power during the year 2017 – 2018, but no

    reply has been received from CESC. In such circumstances, the sale of power to

    CESC has been estimated at 10 MU during the year 2017 – 2018. CESC has yet

    to execute a fresh PPA with WBSEDCL for two part tariff. In view of above,

    WBSEDCL proposed that CESC should intimate at least one/two month in

    advance the demand for power from WBSEDCL and also proposed to supply

    such scheduled power to CESC at single part tariff at an energy charge of Rs.

    6.96 per kWh, average 33 KV industrial tariff under CESC area in 2016 – 2017.

    However, for drawal of power more than the scheduled demand or sudden

    requirement of power, WBSEDCL proposes 30% more than the above stated

    energy charge of Rs. 6.96, i.e., Rs. 9.05 shall be payable by CESC.

    2.49.2 WBSEDCL also proposed to sell power to DVC on single part tariff at a rate of

    Rs. 6.96 per kWh and Rs. 9.05 per kWh following the methodology proposed for

    consideration of sale rate for CESC, since no rate has been determined by the

    Commission for sale to DVC by WBSEDCL. This is for the reason that no PPA

    has been executed between WBSEDCL and DVC regarding two part tariff.

    2.49.3 The applicant has also proposed to sale power to IPCL and DPL on single part

    tariff basis at an energy rate of Rs. 5.40 per kWh and Rs. 4.63 per kWh

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 22

    respectively with a further proposal of 30% higher tariff for the same reason as

    that of CESC.

    2.50 Changes proposed by WBSEDCL in their tariff for 2017 – 2018 are as follows.

    (I) As a part of demand side management to encourage the 33 kV and 132

    kV industrial consumers reduce their drawal of load in peak period and to

    shift the load to off-peak period the following rebates shall be allowed:

    a) a rebate equivalent to the difference of the following two will be

    allowed,

    i) Demand charge calculated as per regulation 4.3.6 of the

    Tariff Regulations; and

    ii) Demand charge computed based on the maximum

    demand of normal \

    b) Similarly for the above consumers keeping their maximum

    demand during off-peak period within 150% of contract demand, a

    rebate equivalent to the difference of the following two will also be

    allowed:

    period or maximum demand of peak

    period or contract demand in case of off-peak period or

    85% of contract demand whichever is higher, if those

    industries keep their maximum demand during off-peak

    period within 150% of contract demand.

    i) Additional demand charge calculated as per regulation

    4.7.2 of Tariff Regulations; and

    ii) Demand charge computed .based on the methodology for

    additional demand charge for the normal and peak period

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 23

    will be as per regulation 4.7.2 of Tariff Regulations but

    there will be no additional demand charge applicable for

    off-peak period.

    c) Similarly for the above consumers keeping their maximum

    demand during off-peak period within 150% of contract demand, a

    rebate equivalent to the difference of the following two will also be

    allowed:

    i) Load factor rebate computed as per the rates without

    considering the additional kWh and KVA drawn during off-

    peak period over contractual demand; and

    ii) Load factor rebate computed as per the rate.

    All the above rebates are effective from the month of April, 2017 subject

    to the condition that payment is made within the due date.

    (II) Treatment of Life line category consumers:

    It has been observed that some of the domestic consumers of WBSEDCL

    (with contract demand not more than 0.3 KW) consume more than 75

    units during some quarters and consume less than 75 units for other

    quarters. Accordingly whenever such a domestic consumer consumes

    less than 75 units in a quarter, such consumer is billed at the tariff of Life

    Line Consumer for that particular quarter. For other quarters wherein the

    consumption of the domestic consumer exceeds 75 units, the consumer

    is billed at the tariff of Domestic (Urban) or Domestic (Rural) category as

    the case may be.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 24

    WBSEDCL submits that the Commission has created such a provision of

    Life Line Consumers in order to make electricity affordable to those poor,

    consumers who don’t have the capability to afford electricity at the normal

    rates. In this respect, WBSEDCL submits that increased electricity

    consumption by this domestic consumer beyond 75 units / quarter should

    debar them for availing life line category tariff for increased consumption

    in its house hold.

    WBSEDCL appeals before the Commission to consider such consumers

    as either domestic (rural) or domestic (urban) and not as Life line for the

    future years if the quarterly consumption for such domestic consumer

    (having CD < 0.3 kW) exceeds 75 units taking average of energy

    consumption of last 12 months.

    (III) Minimum Charge of various consumer categories:

    WBSEDCL submits that Minimum charges on consumers will guarantee a

    certain amount of Revenue for part-recovery of fixed charges for

    WBSEDCL. WBSEDCL has PPAs with generators based on demand of

    the consumers to keep power supply uninterrupted. Thus, WBSEDCL has

    to pay fixed cost to the generators even without drawal of power from the

    generators due to lesser system demand.

    In view of the above, WBSEDCL proposes Minimum charge for various

    categories of consumers with revision in Minimum charge for categories

    as shown in the Form 3.7 of Annexure-3 of Volume-IV.

    WBSEDCL submits that the proposed Minimum charges should be

    applicable as per regulation 4.13 of notification no.48/WBERC dated

    25.04.2011, the same is reproduced below for ready reference:

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 25

    “Minimum Charge shall be applicable when the sum of energy

    charge and fixed charge including rebate/surcharge (except

    rebate for timely payment) is less than the minimum charge for the

    billing period"

    (IV)

    WBSEDCL submits that it collects meter rent from its consumers for

    meters installed by WBSEDCL at its cost. Meter Rent paid by consumers

    was last revised by WBERC via tariff order of 2010-11 dated 30.12.2011,

    WBSEDCL proposes revision in Meter Rent as shown in the Form 3.7 of

    Annexure-3 of Volume-IV.

    Meter Rent:

    (V)

    WBSEDCL submits that other charges are borne by consumers due to

    Meter testing charge and Disconnection / re-connection of supply at

    consumer premises. Such charges are collected from the consumer by

    WBSEDCL if the activity is undertaken due to consumers fault and not

    otherwise.

    Such charges borne by the consumers were last revised by WBERC via

    tariff order of 2010-11 dated 30.12.2011. WBSEDCL proposes revision of

    these charges as the cost borne by WBSEDCL for such Meter testing and

    Disconnection / reconnection of supply has gone up considerably since

    2011-12.

    Other charges - Meter testing and Disconnection / Re-connection

    Charges:

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 26

    The existing and proposed Meter testing charge and Dis-connection / re-

    connection of supply charges is shown in the Form 3.7 of Annexure-3 of

    Volume-IV

    (VI) In the backdrop of reduced electricity consumption by the 33 kV and 132

    kV industrial consumers of WBSEDCL, WBSEDCL proposed a scheme

    for revenue enhancement through increased sale to 33 kV and 132 kV'

    industrial consumers, the scheme is enclosed as Annexure 8 of Volume

    5. The scheme may be continued till issuance of the tariff order for 2017-

    18. Rates mentioned in this scheme may be considered for modification

    for the year in accordance with the tariff order of 2017 – 2018.

    (VII) Tariff for Military Engineering Services (MES) applicable for High and

    Extra-high voltage has been proposed to be applicable for LV&MV

    consumer (50 KVA and above but upto 125 KVA).

    (VIII) Presently off-peak period means the time period from 11 pm to 6 am.

    Considering demand position of WBSEDCL system, WBSEDCL proposes

    to increase off-peak period for industrial consumers with supply of 33 kV

    onwards as 11 pm to 8 am and normal period as 8 am to 5 pm for

    consideration of Commission and shall be applicable after two months of

    issue of tariff order.

    (IX) The fixed charge/ demand charge in Rs/KVA/Month for consumers has

    been proposed as shown in the Forms 3.2 & 3.3 of Annexure-3 of

    Volume-IV. The demand charge shall be applicable to different categories

    of consumers as per rates as shown in above tariff schedule on the basis

    of recorded demand as specified in regulation 4.3.3 of the Tariff

    Regulations subject to the conditions specified in the Tariff Regulations.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 27

    When a new consumer gets connected to the system, the computation of

    fixed charge or demand charge for that month shall be made pro-rata for

    the number of (

    (X) All other terms & conditions of tariff have been proposed to remain

    unaltered and are provided in the Annexure 3 of Volume IV of the

    Application.

    days of supply in that particular month.

    (XI) Other terms and conditions are proposed to be remained unaltered.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    CHAPTER - 3

    OBJECTIONS AND SUGGESTIONS

    West Bengal Electricity Regulatory Commission 28

    3.1 Suggestions, objections and comments on the tariff application of WBSEDCL for

    the fifth control period covering the year 2017 – 2018 have been received within

    27.03.2017 i.e., the due date from the persons are mentioned in paragraph 1.10

    of Chapter-1. The main points of the suggestions, objections and comments etc.

    relevant to the instant tariff petition are summarized in the following paragraphs

    in this chapter. The Commission’s views on the objections, comments etc. are

    also recorded in this Chapter.

    3.2 Modern India Con-Cast Limited have stated a number of issues which are

    discussed below:

    3.2.1 Operation and Maintenance Expenses: During 2015 – 2016, 2016 – 2017,there is a large expansion of distribution network through implementation of

    different Rural Projects related to distribution. Moreover there is large volume of

    replacement of meters – namely from electro mechanical to hybrid / static etc.

    and continuous replacement of meter involves a large increase in distribution

    expenses. Since a large chunk of distribution system, commissioned under

    various district project, and being almost new, maintenance expenses requires to

    be reviewed and should not be allowed on normative basis. Otherwise it will not

    be possible to arrest regular increase in tariff, while power purchase cost has

    reached to an uncontrollable limit, particularly when market price of power is low.

    The modality of fixing the normative value of O&M expenses in view of addition

    of new assets requires to be reviewed. It often takes time to submit and issue of

    order on APR.

    The above point has been noted by the Commission and will be duly addressed

    in the subsequent chapter.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 29

    3.2.2 Employee expenses: The pay commission report is yet to be submitted. Since the tariff petition is for 2017-2018, any impact on implementation of pay

    commission shall be recovered separately. The reason is due to high tariff of

    WBSEDCL compared to the most of the other States in India. High ATC Loss

    should not be compensated in any manner through the increase of tariff. In fact

    pay structure of the employee as well as the Board of Directors should be based

    on performance in line with MNC and not in line with Government of Public sector

    undertaking.

    The above points have been noted by the Commission and will be taken care of

    in the relevant portion of the tariff order. However, the employee cost will be

    admitted as per the provision of Tariff Regulations, subject to prudence check by

    the Commission.

    3.2.3 Pension Fund: Pension fund appears to be a welfare scheme of the licensee. WBSEDCL is not a Govt. institution. All the employees are not in the same

    pension scheme. Any cost on account of pension should be incurred by the

    licensee out of its profit and the same should not be a pass through.

    The Commission has dealt with the issue suitably in subsequent chapter.

    3.2.4 Outsourcing expenses: Outsourcing expense should have a prudence check. Cost of outsourcing is 67% of direct employee cost which should be reduced.

    Such expenses are being checked prudently as per the Tariff Regulations at the

    time of determination of APR for the respective year.

    3.2.5 Interest on working capital: Since the Bank rate is decreasing, the principles of considering the rate of interest on working capital should be changed & it should

    be at actual subject to truing up through APR.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 30

    The rate of interest on working capital is being allowed by the Commission as per

    the rate prevailing on 1st

    3.2.6 Carrying costs: Normally any deficit in cash or working capital is managed through grants/Govt. aid/borrowings from financial institution etc. Consumers

    bear the burden of loan or borrowing from financial institution in terms of interest.

    Allowing carrying cost in addition to interest burden will put extra burden to

    consumers of all category. As such carrying cost should not be allowed, since

    the licensee is a profit making utility, should absorb the carrying cost of its own.

    April of the previous year for which the tariff order is

    determined, subject to truing up through APR as per regulation 5.6.5 of the Tariff

    Order.

    The Commission has noted the contents.

    3.2.7 Bad Debts: Consumers are already heavily burdened with high tariff. Any Bad Debt should not be a pass through in the ARR. Any loss due to it should be

    compensated by Govt. of West Bengal or adjusted with the regulatory Assets.

    The Commission goes by the Tariff Regulations framed as per the Electricity Act,

    2003 which only allows such amount of bad debts as actually has been written

    off, subject to a ceiling of 0.5%.

    3.2.8 Compensations paid by licensee: Compensation to outsiders, loss of obsolete store materials, compensation of Power Trader should not be allowed, as the

    same will be a reward to inefficiency.

    The Commission does not allow the compensation amount as a pass through

    element in tariff as per provisions of Tariff Regulations.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 31

    3.2.9 Report on Power for All (PFA):

    (i) WBSEDCL submitted report on Power for All to Govt. of West Bengal in

    consultation with M/s Deloitte India Ltd. As such all relevant data should

    be in line with this.

    The projections are generally being made in the Tariff petition in

    accordance with the Tariff Regulations. However, the Commission has

    taken a note of it.

    (ii) As per report of Power For All (PFA), energy input requirement is 34118

    MU against energy sale volume of 25993 MU with total peak demand

    6152 MW. With the vast network (Transmission) strengthening, at higher

    voltage, transmission loss should be reduced & impact of the same, may

    require less input.

    While computing the transmission loss, the Commission follows the

    norms stipulated in the Tariff Regulations.

    (iii) In line with PFA, Employee Cost – with escalation @ 10% YOY,

    considering CPI, AG cost escalation @ 6% should be considered @ 1%

    of GFA.

    The Commission has noted the comment.

    (iv) Depreciation for new assets should be considered as 5.28% in line with

    PFA.

    While computing depreciation in the tariff order, the Commission follows

    the provisions as laid down in the Tariff Regulations.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 32

    3.2.10 Sale to other distribution licensees: As none of the other distribution licensee has intimated WBSEDCL, their requirement, projection of sale to other Licensee

    should be considered nil.

    The Commission has noted the comment.

    3.2.11 Power purchase cost: Power purchase cost should be computed based on prevailing tariff, not based on tariff petition of ISG, POSOCO and CTU etc.

    Requirement of Power as per PFA is 34118 MU. The average cost of power

    purchase may be considered as 350 P/KWH less by 2% rebate. Accordingly

    Power Purchase Cost for sale to consumers shall be Rs 11702 Cr.

    The Commission does not find any valid logic in objector’s estimation of power

    purchase cost for sale to consumers. The Commission determines power

    purchase cost based on the provisions given in the Tariff Regulations and on its

    decision felt to be the best.

    3.2.12 Purchase of power from Renewable and co-generation sources: While average power purchase cost is around Rs. 350 P/KWH, WBSEDCL is reluctant

    to pay the cap price of Co-Gen power i.e. @ 334 P/KWH, thereby depriving this

    green power producer & discouraging to inject the same in the grid. Tariff model,

    built in the PPA for Co-gen power should be quashed & CERC model should be

    implemented.

    The above comments are related to RE Regulations and do not attract the Tariff

    Regulations which is followed for preparation of tariff order. However,

    Commission will give direction to the licensee to fulfill their RPO obligations.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 33

    3.2.13 Power purchase from WBPDCL:

    (i) R&M work of BTPS 5th

    (ii) Generation from KTPS first 3 units appears to be uncertain due to penal

    action taken by Green Tribunal. Generation from other 3 units need to be

    maximized.

    unit has been done & it should supply regularly the

    rated capacity as the investment cost is very high. The available

    generation from other units of BTPS i.e. 4X60 MW should confirm to

    around 55% considering Renovation and Modernization work.

    (iii) However, the performance of WBPDCL appears not in order in spite of a

    lot of investment under R&M Programme. There should be more penal

    measure, unless the generator is able to achieve a good performance as

    required by the system. It is to be kept in mind, that a good performance

    in the matter of available generation will reduce the net power purchase

    cost. As such any bad performance should be reflected in the pay

    structure of the employee as well the Board of director.

    The Commission noted the comments. While determining the power purchase

    cost of WBSEDCL, the capacity charge payable by WBSEDCL for each

    generating station of WBPDCL is being considered based on the reduced

    projected Plant Availability Factor.

    3.2.14 Sale of surplus Power:

    (i) As per PFA, Energy availability during FY 18 is 37723 MU and surplus

    will be 3605 MU. Again peak demand is 6152 MW, against availability of

    7029 MW i.e. a surplus of 877 MW. Any surplus of power / energy may

    be traded in the market. As per CERC report average realization of sale

    through Traders is Rs. 411 P/KWH. As such Power purchase cost shall

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 34

    be considered as Rs. 12940 Cr. After 2% rebate that may be availed as

    per PPA if payment is made within due date.

    The entire expenditure and income of the licensee for a particular year is

    being checked prudently at the time determination of APR for the said

    year. Therefore, the comments of the objector regarding trading of excess

    power are being dealt at the time of APR determination. Regarding power

    purchase cost, the view of the Commission is already given at paragraph

    3.2.11 above.

    (ii) Profits, if any, from sale to persons other than own consumers shall be

    deducted from Gross ARR. However, if sale price / market price is less

    than pool power purchase cost, some alternative means for assured

    income may be invested, so that burden due to loss of revenue for sale at

    low price may be avoided.

    The Commission takes care of the comments as per the provisions of the

    Tariff Regulations while determining tariff order/APR.

    (iii) As there appears to be a surplus power, except some incidental

    requirement, requirement of power purchase from market should not be

    considered through.

    The Commission noted the contents.

    3.2.15 Alternative means to dispose surplus power instead of Banking of Power :

    (i) Banking of Power may be avoided as it involves cost due to open access

    charges & losses, interest cost of energy purchased. It is better that

    surplus power may be sold through trader, allowing open access to the

    interested buyer. A model may be built up as here under. Some high

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 35

    value consumer, who may have a variable demand, who may be captive

    generator also or who intend to be group captive owner may opt to buy

    such surplus power through trader at some concessional rate, if open

    access is allowed under this model.

    (ii) Trader should have PPA with a person who may be consumer of the

    licensee.

    (iii) Interested buyer shall be allowed short term open access with a provision

    for ABT complaint meter for energy accounting and power to be sold on

    schedule basis.

    (iv) Buyer should draw power over and above Contract Demand.

    (v) If it is an additional power, over and above contract demand then there

    shall be no Cross Subsidy Surcharge (CSS). Otherwise CSS will be

    applicable along with additional surcharge.

    (vi) Price should be fixed in between night off peak power and average price

    of power in the Power market.

    (vii) This will enable WBSEDCL –

    � to avoid Open Access Charges & Loss due to sale to person other than

    own consumers and Licensees,

    � the demand for Open access approval for import by consumers from a

    source other than the licensee concerned,

    � additional revenue on account of wheeling charge and

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 36

    � backing down may be avoided and full utilization of generation

    capacity.

    The objector has sought for certain change in Tariff Regulations. It may be put on

    record that the Tariff Regulations were finalized through previous publication.

    Having received suggestions, objections and comments the Commission in

    exercise of its delegated legislative power duly considered the matter in details

    and framed such regulations and the regulations were notified in the Kolkata

    Gazette. In tariff determination proceedings once the regulations are framed by

    the Commission, there is no scope to review or change such statutory norms in

    tariff determination proceedings. Accordingly, the comments for change in the

    Tariff Regulations are not considered. Thus, such issue will not be dealt in

    subsequent chapter further.

    3.2.16 Reduction of distribution loss:

    (i) Distribution Transformer failure in the district varies in the range of 4% to

    10%. It should be brought down.

    (ii) Reduction in ATC loss level, in districts particularly Birbhum, Beharampur

    and Malda needs special attention. However, Technical loss can be

    improved through religious implementation of distribution project, i.e.

    DDUGJY, IPDS, RAPADRP & RGGVY. A lot of investment around Rs.

    9056 Cr, up to financial year 2018-19, is under process. Entire

    investment is funded through grants.

    (iii) WBSEDCL should take initiative religiously to improve distribution loss

    through Condition Monitoring for preventive maintenance, Transformer

    Transaction Management System, Feeder Length Reduction, Feeder

    Segregation, Use of Amorptious core DTR installation, Re-conductoring,

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 37

    Installation of AB cable etc. Further commercial Loss to be reduced a lot.

    Consumption analysis is required at Field level to identify loss area.

    The Commission has already taken various steps with the licensees in

    different forum for reduction of AT&C / Distribution losses. However,

    necessary directions are being given to the licensees for energy audit /

    loss audit.

    3.2.17 Regarding proposal for increase in Fixed Cost:

    (i) Consumers are paying charges effectively under 3 part tariff scheme i.e.

    Demand Charge or fixed charge, energy charge & MVCA. A lot of

    irregularities may be found out, if consumption pattern is religiously

    analyzed for each of the consumers. This is because, the connected load

    (CD) / declared capacity, in a large number of cases will reflect that those

    are, not appropriate and commensurate with their consumption volume. It

    is the general experience that almost all categories of consumers have

    declared their contract demand, not commensurate with their

    consumption. Majority of household consumers have suppressed

    contract demand, thereby licensees fixed cost recovery is not

    commensurate with their drawal petition of the consumers. If each of the

    consumers is put under scanning it will be found that there is no need to

    increase the fixed cost. It is the inefficiency and lack of initiative of the

    management to set right the issue, considering it to be difficult. Rather

    they want to find an easy solution, for loss of revenue in this regard, by

    increasing tariff in the form of fixed cost. Hon’ble Commission may quash

    the demand in increase in fixed cost. Moreover, charges of fixed cost of

    house hold have been increased within a short span. It should not be

    further increased rather leakage in this area should be arrested.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 38

    The Commission has noted the contents and will give appropriate

    directions to the licensee. However, the fixed charge / demand charge is

    allowed as per provisions of the Tariff regulations.

    (ii) Again some of the households have more than one meter which are

    overlooked by the licensee. In turn the recovery of energy charge under

    slab rate is low. A loss in this case, automatically put burden on energy

    rate. Licensee should be directed to reduce loss under above cases.

    The comments are noted.

    (iii) As WBSEDCL have to off-take minimum drawal, even after backing down

    of generation, in the event of low demand, subject to the technical limit of

    the generating unit, minimum drawal of all consumers should be

    guaranteed in terms of charges.

    The comments are noted.

    (iv) WBSEDCL has executed lot of PPA, considering a very optimistic

    perspective planning. It was considered granted that there would be an

    industrial revolution in West Bengal and a surge of demand.

    Unfortunately, the revolution is yet to take place but the obligation of PPA

    for drawal of power remain. This ill-considered planning of the then

    management of WBSEDCL has not yet been highlighted. As such

    consumer should not be burdened with increase in fixed cost to protect

    the inefficiency.

    The Commission has noted the comments. Commission will consider the

    fixed cost of generating stations from which the power are being

    purchased by WBSEDCL as per their PPA to the extent of sale of power

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 39

    by WBSEDCL adjusted with normative T&D losses. Any incidental

    surplus has been considered to be sold at average power purchase cost.

    3.2.18 Regarding other Tariff Proposals:

    (i) Reference to the report on Power for All, West Bengal. Table – 14, the

    anticipated peak demand is 6152 MW while Peak availability including

    Renewable is 7029 MW i.e. there may remain 877 MW surplus during

    Peak Hours. Now WBSEDCL should rethink whether they would like to

    sale surplus evening power at in the market depriving its own consumer

    setting Peak hour tariff at high level. This is against natural justice. As

    such to boost industrial sale, tariff for the peak hour of high valued

    industrial consumer should be kept low at a reasonable level and to

    compensate the loss of revenue tariff for normal period may be revised.

    The comments are noted.

    (ii) Any changes of existing rate / charges, terms and conditions as proposed

    in the tariff petition shall not be allowed as the same shall be considered

    through amendment of existing tariff regulation. The stake holders should

    be given opportunity to put up their views/suggestions and objection.

    The Commission has noted the comments.

    (iii) There is a proposal for change TOD timing, through increase in off-peak

    period, it does not indicates, how the loss of revenue due to increase in

    off period will be compensated.

    The Commission has not considered any change in TOD timing due to

    non-submission of any loss benefit analysis by the licensee.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 40

    (iv) Any loss in revenue due to implementation of rebate scheme on

    additional Load Factor rebate, Maximum demand charge for 33 KV/132

    KV industrial consumers, or in multiple licensee area shall not be a pass

    through.

    The Commission noted the contents and shall be dealt with at the time of

    preparation of tariff.

    (v) The Commission has introduced a new scheme through the notification

    dated 8.02.2017 whereby the difference of the price between DVC and

    WBSEDCL has been kept at 50 paise. Presently the price of DVC stands

    at Rs. 4.30 per unit for 132 KV DVC consumers whereas the price for

    WBSEDCL is Rs. 6.10 per unit for its 132 KV consumers. Hence, the

    rebates have to be increased for load enhancement so that the difference

    between DVC and WBSEDCL is kept not more than 50 paise per unit.

    The Commission has noted the contents. .

    3.2.19 Whatever cost has been incurred in terns of FCA, MFCA or MVCA during FY 16-

    17, shall be considered for ARR calculation. Implication of Tariff revision of

    ISGS/CTU etc. should be taken in account through FPPCA.

    Commission has noted the comment and specific direction will be given in the

    tariff order in this regard as per provisions of the Tariff Regulation.

    3.2.20 Over and above, M/s Modern India Con-Cast Limited have made some additional

    important points to note.

    i) WBSEDCL fails to comply direction of the Hon’ble Commission as they

    have not implemented Energy audit in its organization. Some penal

    measure is required in terms of tariff.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 41

    ii) Generation is PPSP for 2017-18 with PAF 98% has been considered in

    the same level of 2015-16 i.e. 1055MU when PAF was 76.57%. It may

    be noted that with PAF 90.78% generation was 1416 MU. As such

    correction should made accordingly i.e. we can get around 400MU more

    peak power from PPSP.

    iii) WBSEDCL has not yet participated in UDAY scheme which is beneficial

    to the Licensee and in turn consumer will also be benefitted.

    iv) Cost of Backing down of generation and sale of surplus power in the

    unregulated volatile market at an average rate of Rs 2.72 p/kWh indicates

    poor and inefficient power purchase plan.

    v) Increased R&M cost indicated poor maintenance plan and condition

    monitoring.

    vi) Any waiver of LPSC should not be a pass through a tariff.

    vii) WBSEDCL may purchase power from market after having an exercise for

    cost benefit analysis where there should be a net gain in the process.

    viii) WBSEDCL realize Minimum Charges in terms of Fixed cost / Demand

    charge. Though in the tariff petition, WBSEDCL, cleverly, has not given

    any annexure of computation of fixed cost / Demand charge, the increase

    in consumer base has largely increased. In the process of computation

    for average billing rate (ABR), there should not any adjustment on

    account of Rebate / Penalty etc. Average energy rate may be computed

    after assured revenue income on account of Fixed cost / Demand charge.

    Power purchase cost may also be computed without rebate / penalty.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 42

    ix) Format 1.10 does not contain the contracted capacity/installed capacity.

    Moreover there is no information about hour of operation and Backing

    down of generation. They same should be incorporated for having a clear

    view of operation and power procurement planning efficiency.

    x) Similarly the formats do contain any information of category wise total

    consumer, contract demand and the demand met. The same should be

    incorporated. This will enable to have a check on the fixed cost / demand

    charge that should have been realized.

    The Commission has taken note of the above comments and shall deal with the

    same, wherever required as per the Tariff Regulations, in the subsequent

    chapter.

    3.3 M/s Ankit Metal & Power Limited, M/s Rohit Ferro-Tech Limited, Organization of

    Indian Engineering Industry and Rashmi Metaliks Limited have submitted their

    printed objections with same contents as that of Modern India Con-Cast Limited

    against the tariff proposal of WBSEDCL for the year 2017 – 2018. Since the

    objections submitted by the above four stakeholders are same with the

    objections submitted by M/s Modern India Con-Cast Limited and that they are

    already dealt with as above, the objections of above four stakeholders are not

    dealt here separately.

    3.4 All Bengal Electricity Consumers’ Association (ABECA) has made the following

    suggestions:

    3.4.1 ABECA commented that if the tariff proposal of the WBSEDCL is allowed then

    there will be a further tariff hike of 65.68 paise per unit including MVCA of 23

    paise per unit. Besides this tariff hike both the W.B.P.D.C.L. and W.B.S.E.D.C.L.

    off and on enhances tariff on the plea of MVCA / MFCA etc. The entire system is

    nothing but to enhance the tariff which will affect 1.50 Crores of Electrical

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 43

    Consumers of West Bengal and there will be a further inflation in the state and

    prices of all goods and services will be increased. Small traders, small scale

    industrial units and cultivation in Agriculture will be badly affected and will

    virtually close down their activity. This cannot be let loose.

    3.4.2 In the gist of Tariff Proposal the W.B.S.E.D.C.L. said that the reasons of increase

    of tariff are (i) increase of power purchase cost; (ii) Increase of Transmission

    charges; (iii) Increase of employee cost; (iv) Increase of interest on loan; (v) O. &

    M. expenses increase; (vi) Release of Regulatory asset etc. ABECA is to state

    that the reasons stated in the gist of tariff for 2017-18 are not tenable. The

    reasons are as follows:

    3.4.2.1 Increase of power purchase cost:

    It may be stated here that the W.B.S.E.D.C.L. purchase the power from the

    W.B.P.D.C.L. The W.B.S.E.D.C.L. submitted the increased tariff for 2017-18 to

    the commission and as per proposal they demanded the increase of average

    cost of supply at 9.88 paise per unit.

    ABECA already submitted the objection on the enhanced tariff proposal. The

    W.B.E.R.C, has not yet allowed the enhanced proposal of the W.B.P.D.C.L.

    Moreover W.B.S.E.D.C.L. and the W.B.P.D.C.L. are the Government enterprise.

    Previously there was one company i.e. W.B.S.E.B. Then there would be one tariff

    for W.B.S.E.B. But due to the evil affect of 2003 Electricity Act for the break up of

    W.B.S.E.B. into three Government companies, viz. (i) Generation Company (ii)

    Transmission Company and (iii) Distribution Company. The enhancement of tariff

    of these three companies imposed a burden of severe tariff hike collectively on

    the shoulder of the ultimate consumers and thereby brings an inflationary

    situation in West Bengal and the production of Agriculture and Small Scale

    Industry will be hampered and in addition to this there will become another

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 44

    increase of unemployment in the state. Hence we strongly object the tariff hike

    proposal of the W.B.S.E.D.C.L. for 2017-18.

    In this context, the Commission likes to mention that at the time of preparation of

    tariff order of any licensee, the Commission allows expenditure based on the

    provisions of the Tariff Regulations and after prudence check of the proposed

    expenditure.

    3.4.2.2 Increase of Transmission charges – The reason stated herein above at para

    3.3.2.1 above holds goods here also.

    The Commission’s views remain same as that of paragraph 3.3.2.1 above.

    3.4.2.3 Increase of Labour cost - The imposition of fixed charge and fixed cost in the

    Tariff is projected on the higher side. Already 6% growth rate of estimated

    Energy Sale to its own consumer of W.B.S.E.D.C.L. is allowed by the

    commission in the tariff order dated 28-10-2016 for 2016-17 and considering this

    inflated rate of Energy Sale the commission allowed the Aggregate Revenue

    Requirement of Rs. 1829944.36 Lakh in 2016-17 which includes Labour Cost

    also. Hence a mere annual increment of the employees. Nothing more

    enhancement on this

    The Commission in the direction to W.B.S.E.D.C.L. in the tariff order dated 28-

    10-2016 at page 50 para 4.9 (i) directed a detail breakup showing total

    expenditure and employee strength against each level of all categories of

    employees including the whole time directors of the Board. If any function of

    other companies also then the allocation of cost among the companies shall be

    shown separately and distinctly against each level." The direction of the

    commission is to be complied within 31st March 2017.

    item for which the enhancement of tariff hike is not

    reasonable.

  • Tariff Order of WBSEDCL for the year 2017 – 2018

    West Bengal Electricity Regulatory Commission 45

    From the direction of the Commission it is quite clear that the W.B.S.E.D.C.L. failed to provide the required information relating to employee cost. Hence the proposal of tariff hike on the plea of increase of employee cost is not tenable. As such we oppose the tariff hike of the W.B.S.E.D.C.L. for 2017-18.

    The Commission has noted the comments and will be dealt with in subsequent

    paragraphs

    3.4.2.4 In