Page 1: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

2016

Page 2: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Scott Wheeler, Comcast, Co‐ChairCorey Cook, PacifiCorp, Incoming Co‐ChairJerry Donovan, PGE, Outgoing Co‐ChairTerry Blanc, Tillamook PUDBill Hamelman, FrontierMark Rettmann, OPUCSanjeev King, Springfield Utility BoardStuart Sloan, Consumers PowerTom Jorgenson, CenturyLinkMike Allen, ComcastTodd Gover, Bend BroadbandVeronica Voelker, PGE (New) Laureal Williams, Staff

Page 3: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Four Key Deliverables1. Matrix of Common Joint Use Violations ‐ Complete

(Dropdowns for corrective actions and assignments)

2. PowerPoint of Common Joint Use Violations ‐ Complete

(Descriptions, photos of scenarios with correction options)

3. Inspection/Correction Best Practices Manual ‐ Complete

(Version 1: Training tool and field reference guide)

4. Guidelines for Measuring Success ‐ Developing(Measuring inspection/correction accuracy and effectiveness)

Page 4: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Sample ‐Matrix of Common Joint Use Violations

Pole # Alternate Pole # Deviation Equipment 1 Equipment 2 Action Assigned Party Comments

1 CTL 1111 MidspanVertical_24_inchesPDRP‐Power Service Drop

COMM‐Comm Messenger Place California Top POWER1

Power Company permit for pole top extension attachment on phone pole.

2 CTL 2222 MidspanVertical_30_inches SEC‐Power SecondaryCOML‐Comm Main Line Share Arm COMM1

CATV seek joint arm agreement with phone company to clear 40" PV and 30" MV.

3 CTL 3333 PoleVertical_12_inches_3_SLCOML‐Comm Main Line PDLP‐Power Drip‐Loop Ground/Bond POWER1

Light owner to cover SLT driploop and ground/bond SLT bracket.

4 CTL 4444 PoleVertical_40_inchesCOML‐Comm Main Line SEC‐Power Secondary Lower CATV COMM1

CATV seek joint arm agreement with phone company and other Comm clear 40" PV.

5 CTL 5555 MidspanVertical_12_inchesPDRP‐Power Service Drop COMD‐Comm Drop Relocate/Move TELCOM1

Relocate phone drop from power mast to structure for minimum 12" separation from power service drop.

6 CTL 6666 ClimbingSpaceCOML‐Comm Main Line Other‐See Comments Relocate/Move COMM1

CATV to cut/splice strand and coax feeder to opposite side of pole.

Page 5: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Violation Description:Midspan Vertical 24”

Conductor to Conductor

NESC Rule 233C1, Table 233‐1

5

High Level     PowerPoint  Presentation –

Getting Everyone on the Same Page

Page 6: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Violation:Supply to Comm clearance of different supporting structures

OJUA Codes: MV,COML,PDRP

Scenario #1:Less than 24” clearance between supply and comm crossing each other

Options to Fix:Raise supply; Lower comm;Install span messenger and bridle supply; Interset pole

6

Sample PowerPoint Slide

Page 7: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Best Practices Manual

7

Page 8: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Best Practices Manual

8

Page 9: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Best Practices Manual

9

Page 10: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Best Practices Manual  –

Example: Discussion of Clearances Involving Street Light

10

Page 11: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Best Practices Manual  –

Photo(s) Showing a Clearance Issue Involving a Street Light

11

Page 12: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Best Practices Manual  –

The Applicable Rules are Cited and the Scenario is Explained with Assumptions and Facts, Before Suggested “Best Practice(s)” are Offered

12

Page 13: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Using the Tools –

How the Matrix and Best Practices Might be Used to Develop a Joint Inspection Program

PRACTICE STEPS:

1. Select a scenario from the Best Practices.

2. Select the appropriate deviation (violation) from the dropdown options in the Matrix.

3. Select Equipment 1 and Equipment 2 from the dropdown options.

4. Select the best correction from the dropdown options.

5. Assign the correction to the best entity who can safely perform the work.

13

Page 14: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Guidelines for Measuring Success

NEXT STEPS: Determine what quantity and quality metrics are important to measure.

Develop guidance for selecting samples and a sample size.

Evaluate* concept of different quantity/quality targets for Rural, Suburban and Urban areas (based on # of poles, # of services per square mile, # of operators, height or age of poles,  etc.). 

*Using Regression Analysis ‐A statistical process for estimating the relationships among variables. 

Terry Blanc, Tillamook PUD is leading this effort and working with a Willamette University professor. He has compiled and provided 5 years' worth of Detailed Inspection findings to Dr. Kawika Pierson. He is also including specific data from TPUD plant records, including pole height and class, age of the pole, presence of a transformer, pole occupants, number of electric customers served from the pole  and pole‐specific detailed inspection results.

A Simple Example: Density of Poles in PGE Service Territory

Is the density of poles a reliable “predictor” of the number of violations for a given area and therefore, should different quality targets  be established based on number of poles per square mile?

2744 Sections in PGE Service Territory (one section = one mile square)

10 sections with at least 1000 poles per square mile 23 sections with 750 – 1000 poles47 sections with 500 – 750 poles105 sections with 250 – 500 poles454 sections with 100 – 250 poles2105 sections with less than 100 poles

14

Page 15: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

Joint Inspection Pilots?

Who?What?When?How?

15

Page 16: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

‐Who ‐

2016 Joint Inspection Pilot Participants:

•Comcast •CenturyLink •Frontier •PGE

16

Page 17: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

‐What ‐

Scope: Focused on approximately 25,000 “joint use” poles in PGE Service Territory

•All Poles w/ PGE Attachments

• Includes CenturyLink and Frontier Poles w/ PGE Attachments

•Comcast Attachments on Poles w/ PGE  Attachments

17

Page 18: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile
Page 19: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

‐What ‐

“Joint use” Poles by Owner 

PIE CHART SHOWING # POLES BY OWNER* (*FOCUS OF PILOT ON JOINT USE POLES = THOSE WITH POWER & AT LEAST ONE OTHER OPERATOR)

19

Page 20: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

‐What ‐

Poles Attached by Participating Operator

BAR CHART # OF POLES ATTACHED (*INCLUDED IN PILOT)

20

Page 21: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

‐When ‐

Inspection Pilot Milestone Dates

December 16, 2015Invited Operators to Participate  February 15, 2016Kicked off Inspection TrainingFebruary 22, 2016“Production” Inspection Started December 1, 2016Projected Inspection Complete

21

Page 22: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

‐How ‐

How we did it

• Worked with Accent to incorporate OJUA Joint Inspection developments into PGE’s Varasset Program

• Followed PGE inspection cycle (per map)

• Limited scope to poles with PGE attached (“known data”)

• Simplified cost sharing based on poles attached

• Used OJUA Joint Inspection tools to train pole inspectors on joint inspection concepts

• Communication partners working on shared contractor

• Modified Existing PGE Equipment & Processes: 

‐ Full Inspection (Visual + Test/Treat) on PGE‐owned poles only 

‐Visual Only Inspection on Foreign‐owned

‐ PGE paying 100% of test/treat portion

‐ Violation Notifications = Assignments

‐Merging corrections assigned to PGE into FITNES Repair Crew schedule

22

Page 23: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

What are the cost components of a joint inspection?

23

Page 24: OJUA 2016 Annual Meeting Donovan JIS Presentation - Hard ...2744 Sections in PGE Service Territory (one section = one mile square) 10 sections with at least 1000 poles per square mile

What are  we Learning?

Consider: Start at least 1 year ahead of planned inspection cycle Signed supplemental agreements to address cost sharing, scope, specifications, etc. Centralized program administration with input from stakeholders/participants Flexibility is needed for realignment of inspection cycles Keep inspection variables to a minimum:

NESC inspection vs. full pole audit w/measurements, etc. Use same treatments Photos (yes/no, how many, when?) Use same materials ‐ guy markers, ground molding, etc. Other billable items ‐ clip tails, ground rods, ID tagging, etc. Fixes, best practices for corrections (what is allowed):

Pole top extensions? Adding Pupi arms? Sharing of existing communication cross arms?

“Joint QC” early and often, adjust/retrain as needed Poles inspected per day will likely decrease (assume 20% decrease) Assume at least 5% for Start‐up Costs (training/non‐production time, preparations –

processes, system readiness, equipment, etc.) Assume at least 5% Program Administration Costs (PM, admin support,  analyst 

support, system maintenance, etc.) Consider invoicing at least monthly based on poles attached, including share of start‐

up  and program admin costs, with “true up” at end of year Merge assigned power corrections into repair crew cycle Share contractor for assigned communications corrections and pole transfers Run inspection as a project (Project Manager, Stakeholders, Control  ‐

Scope/Cost/Schedule) Any others?