ogl_scottgreer_negotiating lng epc contracts

Upload: zhangj5

Post on 02-Jun-2018

240 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    1/39

    Negotiating LNGNegotiating LNG EPCEPC Contracts in a TightContracts in a Tight

    Construction MarketConstruction Market

    Scott A. Greer

    International Bar Association Annual Conference - ChicagoLNG from A to Z - September 18, 2006

    Scott Greer, King & Spalding

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    2/39

    CriticalCritical IssuesIssues

    1. Selection of Contractor

    2. Cost3. Change Orders

    4. Schedule

    5. Quality of Work and Performance

    6. Liability Limitations

    7. Financial Security

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    3/39

    11-- Selection of ContractorSelection of Contractor

    Who shou ld I select as the EPC contracto r?

    Contractor with LNG experience

    Financially strong

    Ability to perform within budget, on timeand with quality work

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    4/39

    Selection of ContractorSelection of Contractor

    Sample Lis t of LNG Con tracto rs

    Bechtel

    Technip

    Saipem

    CBI

    Chiyoda

    KBR/JGC

    Tractebel

    Zachry

    Aker Kvaerner

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    5/39

    Selection of ContractorSelection of Contractor

    But no matter how good the contractor, thesuccess of your project depends on theind iv iduals

    Must specify contractor key personnel

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    6/39

    Selection of ContractorSelection of Contractor

    However, it is a very tight construction

    market for LNG projects. Contractors are becoming choosy.

    at least one currently declines most terminalwork

    Therefore, currently more difficult to choosecontractors.

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    7/39

    Selection of ContractorSelection of Contractor

    FEED Stage

    Its become challenging even at the FEED

    stage

    Why?

    Not want to tie up key people

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    8/39

    Selection of ContractorSelection of Contractor

    Beware o f Key Contract Issues at FEEDStage

    ownership of drawings and specs

    confidentiality

    guarantee of EPC work

    http://images.google.com/imgres?imgurl=http://fawny.org/blog/images/ArchitecturalDrawingSheaf-SM.jpg&imgrefurl=http://blog.fawny.org/2005/05/&h=350&w=500&sz=42&tbnid=5CFPZcJehK_utM:&tbnh=88&tbnw=127&hl=en&start=99&prev=/images%3Fq%3Darchitectural%2Bdrawings%26start%3D80%26svnum%3D10%26hl%3Den%26lr%3D%26sa%3DN
  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    9/39

    Selection of ContractorSelection of Contractor

    2 Ways to Con tract for EPC Work

    1 Bid

    2 Open-Book Sole Source Negotiation

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    10/39

    Selection of ContractorSelection of Contractor

    If Bid . . .

    Recommended Approach FEED by one contractor Bid of EPC not include FEED contractor

    Advantages/Disadvantages Time

    Competition

    Flexibility

    But Bidding less common in tight market may be possible only in larger projects

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    11/39

    Selection of ContractorSelection of Contractor

    If Open-Book Sole Source Negotiation . . .

    More common currently for LNG terminals Advantages/Disadvantages

    Time

    Competition Flexibility

    Recommended Approach Competitively negotiate MOU for FEED andEPC, setting out key terms, includingmarkups (profit, etc.)

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    12/39

    22-- CostCost

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    13/39

    Cos t of LNG Projec ts Has Increased

    CostCost

    Historically, prices dip due to improved technology

    Now, due to (1) contractor demand (i.e., profit margin and riskcontingencies) and (2) material and equipment escalation, cost

    of LNG projects has significantly increased

    Example Liquefaction Plants

    Poten & Partners

    Recen tly (2004)- $200 t/yr

    Now - $250 - 350 t/yr

    Zeus

    Recen tly (2003)- $200 t/yr

    Now- in excess of $500 t/yr

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    14/39

    CostCost

    Reported Examples:

    RasGas III EPC - $256 t/yr Yemen LNG - $300 t/yr

    Tangguh - 18 month delay in investmentdecision led to increase from $1.4 B to $1.8 B

    Woodside Petroleums North-West Shelf Gas

    Project - Reported on September 6, 2006 that Cost

    blowouts hit Woodside Petroleum

    Increase from $2B to $2.4B for 4.2 M tonneplant = $571 t/yr

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    15/39

    CostCost

    LNG projects typ ical ly lump sum with maybe exception for nickel steel exception to Lump Sum - Chenieres Sabine

    Expansion project

    But now have seen exceptions for other raw

    materials Contractors have hard time holding prices, orcharge for the risk

    e.g ., carbon s teel

    ways to m it igate contractor hedge

    tie to index

    limit time of variability

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    16/39

    CostCost

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    17/39

    CostCost -- IPA AnalysisIPA Analysis

    One Study of Project Costs - Independent ProjectAnalysis (for SPE Foundation, by E.W. Merrow)

    # Projects Surveyed: 118 (from year 2002 and forward)

    Project Cost Range: $340 million - $6.8 billion

    Project Location: North America (5%); Middle East (21%); Asia (19%);

    West Africa (25%); South America (16%); Europe (5%); South Africa (5%);Mexico (3%)

    Type of Projects: LNG (17%); Mineral (17%); Chemical (14%); Oil Refining

    (7%); Oil and Gas Field Develop. (55%)

    Contracting Strategy: EPC lump sum (71%); Reimbursable EPC (71%);

    Reimbursable EPCM (17%); and Other (5%)

    Contractor Selection: Bid (61%); sole source (10%); preferred (29%)

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    18/39

    EscalationEscalation -- IPA AnalysisIPA Analysis

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    19/39

    Profit Margin and RisksProfit Margin and Risks -- IPA AnalysisIPA Analysis

    IPA reports.

    Significant increase in profit margins: 2 to 5% from 1990 - 2002 9 to 12% targets from 2004 and 2005

    Significant increase in risk contingencies,particularly West Africa and Middle East

    Significant premium for EPC lump sumcompared to reimbursable/mixed contracts

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    20/39

    CostsCosts

    What can be done about the rising costs?

    increase competition

    additional investigation prior to contractsigning

    allow flow-through of costs for certainvolatile raw material costs

    where financing and plant performance willallow it, consider whether the project can bedivided into smaller projects

    negotiate profit margins, etc. up front

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    21/39

    33-- Change OrdersChange Orders

    What contractual measu res can youimp lement to reduce Change Orders?

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    22/39

    Change OrdersChange Orders

    Act ions Before Con tract Signed?

    Good Scope of Work Both parties work diligently on scope

    Performance based specifications, to theextent possible, but with sufficient detail todescribe requirements.

    Owner should fully vet scope of work,particularly if FEED contractor is same asEPC contractor

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    23/39

    Change OrdersChange Orders

    Soil Issues - key area

    of claims

    Risks unknown soil

    piles

    Mitigation - drive test

    piles before signingEPC (if possible)

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    24/39

    Change OrdersChange Orders

    Con trac t Measures?

    Get Contractor contractualbuy-in to scope

    Tight change order clauses:

    Change only by change order

    Unilateral by Owner or mutual

    Monthly lien & claim waivers

    No cumulative impact claims

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    25/39

    44-- DelayDelay

    What measu res canyou take to reduce

    your chances of

    hav ing a lateproject?

    If it is late, what areyour remedies?

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    26/39

    DelayDelay

    Schedul ing

    Obl igat ions

    Good, detailed CPM

    Schedule

    Strong contract rights

    re: scheduling

    obligations Must tie to TUA

    obligations

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    27/39

    DelayDelay

    Iden ti f icat ion o f Miles tones /Damages

    Milestones: Ready for Cool Down (RFCD) or Ready for LNG

    Critical juncture is the delivery of LNG

    Partial Operation? Notice Requirements - tie to TUA obligations

    Substantial Completion

    Operation

    Final Completion

    Others?

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    28/39

    DelayDelay

    Delays Caused by Owner, Force Majeure, etc.?

    Clear definition of force majeure

    Clear definition of when schedule extensionis justified

    Effects of 2005 Gulf Coast Hurricanes

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    29/39

    DelayDelay

    Late delivery?

    Recovery rights

    Acceleration rights

    Delay LDs at Substantial Completion

    Daily liquidated damage amounts stepped - low to high ranges of LDs

    Caps Exceptions to caps

    willful misconduct, gross negligence

    Not exclusive remedy

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    30/39

    DelayDelay

    What if there is a delay at RFCD or Ready forLNG for a terminal?

    Contractual protection --- indemnification for demurrage charges Liquidated damages

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    31/39

    55-- PerformancePerformance Guarantees andGuarantees and

    WarrantiesWarranties

    Key Issues w ith Performance Guarantees andWarranties

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    32/39

    Performance Guarantees/WarrantiesPerformance Guarantees/Warranties

    Perfo rmance Guarantees

    Tie Contractor obligations tocommercial obligations in TUA

    If inadequate performance, what is the

    sponsors remedy against contractor? Liquidated damages? Fix?

    Examples: send-out rate

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    33/39

    Performance Guarantees/WarrantiesPerformance Guarantees/Warranties

    Other Cri t ical Issues Re: Perfo rmance

    Guarantees New technologies - ex: regasification

    Availability of ships for terminals Downstream capacity

    Who operates prior to SubstantialCompletion?

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    34/39

    Performance Guarantees/WarrantiesPerformance Guarantees/Warranties

    Warranties

    Length of warranty - usually 18 months to 2years

    Owner right to correct Assignment of Subcontractor warranties

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    35/39

    66-- Limitation of LiabilityLimitation of Liability

    Aggregate L iab i l i ty Cap

    Range of Cap

    Except ions to cap:

    Willful misconduct & gross negligence Contract specified exceptions

    Common law exceptions

    Insurance proceeds Obligation to finish work

    Indemnification obligations

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    36/39

    Limitation of LiabilityLimitation of Liability

    Delay & Performance Liqu idated Damages

    Exceptions to cap

    Applicability in the event of termination

    Combined cap?

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    37/39

    77-- Financial SecurityFinancial Security

    What financ ial secu r i ty shouldI get from the Contracto r?

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    38/39

    Financial SecurityFinancial Security

    1. Parent Guarantee

    2. Letter of Credit/Bank Guarantee or

    Payment/Performance Bonds1. general sponsor preference - letter of

    credit/bank guarantee

    2. range of amount of letter of credit/bankguarantee

    3. Retainage -1. Trend: letter of credit/bank guarantee taking

    the place of retainage in many cases

    THANK YOUTHANK YOU

  • 8/10/2019 OGL_ScottGreer_Negotiating LNG EPC Contracts

    39/39

    Scott A. Greer

    www.kslaw.com