evolution of long-term lng sales contracts

Upload: mmoszkowski9755

Post on 02-Jun-2018

223 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    1/17

    During the 40+ year history of the LNG industry,

    customs and practices have developed with regard to

    documenting long-term LNG sales (SPAs). Although

    the foundational approach to SPAs has, in general,

    remained unaffected since the first contracts of the

    early 1960s, market changes, fresh challenges and new

    players are resulting in approaches to contractual terms

    that may differ from the traditional LNG way. While

    clearly much can be learned from past LNG precedent,

    present circum-stances may necessitate a different

    course than in past SPAs. This article will review

    common alternative drafting and risk-sharing

    approaches as well as changes to contracting practices

    for representative Asian and Atlantic-basin SPAs, with an emphasis on

    contractual and legal issues rather

    than purely commercial concerns. In

    preparation of this article, the author

    examined many, but not all, of the SPAs

    signed during the relevant period,

    including: 3 from the 1960s; 11 from

    the 1970s; 9 from the 1980s; 17 from

    the 1990s; and 21 since 2000. These

    SPAs are from 14 existing or planned

    exporting nations (and 2 nations whichhoped to do so but the projects were cancelled) and 9

    existing or planned importing nations. Given the task

    of reviewing four decades of experience and the

    necessary brevity of this article despite the intricacy of

    the subject matter, the following is intended to be an

    overview, rather than a comprehensive discussion, on

    the evolution of certain key SPA issues.

    1960s

    Compared to the 14 long-term SPAs executed in 2004,

    relatively few SPAs were signed in the 1960s. In fact,

    long-term sales were limited during this decade to

    Alaskan sales to Japan and Algerian sales to the United

    Kingdom and France.

    The LNG lawyer of today would first

    notice the brevity of SPAs of the 1960s.1

    These SPAs were 20 to 30 page

    documents with guiding contractual

    principles rather than the detailed

    (sometimes overly) clauses we now see.

    In these initial contracts, perhaps due

    to the fact that financing was not

    provided by third parties, no real trend

    was established with respect to the

    choice of law. The choice of contractual

    law was wide,2 from Algerian law to Japanese law to no

    choice of law at all (relying instead on empowering the

    arbitrators to act as amiables compositeurs and

    thereby permitting the arbitrators to decide the dispute

    according to the legal principles they believe to be just,

    without being limited to any particular national law).

    Arbitration of disputes, rather than litigation, by three

    arbitrators was already the norm, with the International

    Chamber of Commerce rules applying and the place of

    arbitration being Geneva, Zurich or Tokyo.

    In these early days of the LNG industry, not all SPAs were

    stated in terms of take-or-pay; instead, the simple

    obligation to purchase the quantity appears to have been

    Evolution of Long-Term LNG Sales Contracts:

    Trends and Issues

    Philip R. Weems, Partner, King & Spalding LLP

    1 For a discussion of principles guiding the choice of contractual structures for LNG export projects and further background on terms of SPAs, see Weems, "Overview of Issues Common

    to Structuring, Negotiating and Documenting LNG Projects," International Energy Law and Taxation Review (Issue 8, 2000) (available at

    www.kslaw.com/practice_areas/energy/publications.asp).

    2 The choice of law under the oldest SPA (signed on December 12, 1961 between British Gas Methane Limited and Compagnie Algerienne de Methane Liquide) is not known. This SPA

    expired in 1979.

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    2/17

    the only necessary requirement:

    The annual contract quantity of LNG which

    Sellers agree to sell and deliver to Buyers, and

    which Buyers agree to receive and pay for under

    this Agreement for each contract year is [____]

    billion Btus. [C]argoes of LNG shall be

    delivered and received during each contract year

    at rates and intervals and volumes which are

    reasonably equal and constant.

    The term of SPAs was 15 years in two instances and 25

    years in the other. It was not unusual for the term of the

    contract to be extended at Buyers election if an event of

    force majeure prevented the delivery of the minimum

    contract quantity. As these contracts pre-dated the 1973

    Oil Crisis, pricing was relatively fixed. The following

    illustrates the three methods of pricing in these early

    agreements: $0.52 per MMBTU delivered ex ship.

    A price based on (a) the value of the

    natural gas (determined based on the value of heavy fuel

    No. 2 from certain Mediterranean and Atlantic refineries

    and based on wholesale coal prices as published by the

    French Institute of Statistics); plus (b) the cost of

    liquefaction (pursuant to a separate liquefaction

    agreement) and indirect taxes.

    $0.305 FOB, escalated annually for

    certain U.S. inflation.

    The most-favored nation pricing concept found its way

    immediately into Japanese contracts through clauses

    requiring that if in the future another [LNG] project is

    placed into operation to supply Japan under similar

    conditions such as volume, distance, liquefaction, and

    ocean transportation techniques, contract term and so

    forth, sellers will hold a discussion with Buyers

    concerning the price and shall endeavor to find a

    solution satisfactory to all parties concerned.

    Noting that each party has the obligation to act in dueregard for appropriate safety precautions, one SPA

    introduced the following concept of liability in relation

    to LNG tankers:

    While the LNG tanker is [at berth at Buyers

    terminal], Buyers shall indemnify Seller for

    any injuries or damages they may suffer as a

    result of the negligence, or willful and malicious

    acts of Buyers, their agents, employees,

    contractors and suppliers of labor and materials

    and their employees while performing services

    for Buyers.

    A mirror indemnity of Buyer for sellers negligence, etc.

    was likewise included.

    Additional observations regarding SPAs of the 1960s are

    as follows: In one contract, there was an obligation

    to use best efforts to obtain government approvals

    within 60 days; otherwise, either party could terminate

    the SPA with no liability.

    Few specifics are included regarding the

    facilities to be constructed by either seller or Buyer.

    In one contract, the port charges payable

    by Buyer for use of sellers loading port are frozen for the

    term (25 years) at the rate existing on July 15, 1969.

    Two SPAs are silent on demurrage (withone simply stating that Sellers and Buyers shall

    cooperate in their efforts to unload an LNG tanker within

    17 hours after docking) while one SPA includes a

    demurrage rate fixed at $24,000 per day.

    In one contract, if a default in the

    performance of any obligation under the SPA occurs and

    is not remedied in 60 days, the non-defaulting party is

    entitled to terminate the contract.

    In general, seller bears the risk of taxes

    imposed by the export country while buyer bears the risk

    of taxes imposed by the importing country; but in oneSPA if any new income or product related taxes are

    imposed on seller, buyer is obligated to reimburse seller

    for 75% of the amount of taxes payable, provided that

    such recovery is not prohibited by law.

    In one contract, force majeure is deemed

    to include serious accidental damage to the principal

    pipelines leading from the regasification facilities and to

    the principal pipeline systems transporting gas to

    buyers Principal Customer (defined as any customer

    who buys at least 10% of the annual contract quantity

    sold under the SPA). However, whenever the force

    majeure event ceases, the quantities of LNG not

    delivered due to force majeure must be sold or purchased

    as make-up quantities in the shortest possible time.

    Each SPA is silent on (i) damages

    payable in the event of a failure to purchase or sell; (ii)

    obligations with regard to off-spec LNG; and (iii)

    financial security to be provided by either seller or buyer.

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    3/17

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    4/17

    Element based on crude oil export prices and a

    Transportation Element (with the LNG Element having

    a minimum LNG price of $0.99 per MMBTU [escalating

    at an agreed rate] and the Transportation Element being

    $0.30 per MMBTU [escalating based on changes in

    sellers actual cost of transportation payable to its

    transporter]).

    $0.63 FOB, adjusted for changes in a

    basket of currencies but not to be less than a stated

    minimum price.

    The higher of the base price (set initially

    at $1.30 FOB) or a Floor Price, with monthly

    adjustments to the base price based on changes in

    certain fuel oils and semi-annual adjustments to the

    Floor Price based on changes in a basket of European

    exchange rates.

    The higher of the base price (set initially

    at $1.50 FOB) or a Floor Price (escalating at an agreedrate), with semi-annual adjustments to the base price to

    be based on crude oil export prices and on U.S. inflation.

    These different approaches to pricing were obviously

    influenced by major changes in oil pricing from 1973

    onward. Uncertainty about pricing in the buyers market

    led to the adoption of perhaps the first LNG price review

    clause (governed by the laws of the United Kingdom).

    This clause (i) required the parties to meet every four

    years; (ii) required the parties to adapt the price in a

    reasonable and fair manner to the economiccircumstances then prevailing on the imported Natural

    Gas market and on the market for other imported energy

    supplies competing with this product in the East Coast

    and Gulf Coast areas of the [U.S.] within the framework

    of long term contracts; (iii) provided for arbitration to

    determine the price revision if the parties could not

    reach agreement in 90 days; and (iv) provided that no

    arbitration award on price revision would become

    effective until approved by governmental authorities

    having jurisdiction in the countries of the parties.

    As had been the practice in the 1960s, specific remedies

    applicable to non-performance were not included (aside

    from the ability in one contract to terminate the contract

    if non-performance is not remedied in 60 days).

    Therefore, remedies for seller non-performance were

    based to a great extent on the underlying choice of law

    (such as the Uniform Commercial Code Article 2 when

    New York law was chosen). A 1970 SPA confirmed the

    view of take-or-pay as sel lers exclusive remedy by

    stating that in respect of non-fulfillment by any Buyer

    of its obligations to take delivery of LNG hereunder,

    Seller shall rely solely on the remedy afforded by [the

    clause requiring buyer to pay the shortfall at the contract

    price].

    Although the 1973 Pertamina - Pacific Lighting SPA

    ensured that the obligations to sell and purchase LNG

    were not effective until satisfaction of certain conditions

    precedent, the maximum 30 month period to obtain U.S.

    approval to import LNG and to obtain financing of

    Pacific Lightings import facilities proved, in hindsight,

    to be a major underestimation. In fact, it was not until

    1981 that Pacific Lighting abandoned its hope to obtain

    California approval of the siting of the import terminal.

    In another Indonesian contract, although no conditions

    precedent were included, seller obtained the right to

    terminate the SPA if it was unable to obtain, within six

    months, firm and binding commitments from Japanese

    lenders on terms satisfactory to Seller, for financing of

    construction of [the port and liquefaction facilities].

    Destination restrictions were common, reinforced often

    through the requirement that ships be dedicated to

    trading between seller and buyer. Limited rights to alter

    the receiving terminal were incorporated into a few SPAs,

    such as the following provision:

    The scheduled port of destination is the port of

    Boston (Massachusetts) where Buyer has now atits disposal the required facilities. However,

    Buyer shall have the right to designate any safe

    port on the East Coast of the United States of

    America, subject to the designation being

    notified to Seller in writing at least 15 days prior

    to the scheduled date of delivery; provided,

    however, that all required authorizations and

    permits, and any delay which may result

    therefrom, shall be the responsibility of the

    Buyer; provided also that the sales price stated

    shall be adjusted in such case to take intoaccount the variations in the length of the

    voyage and any additional costs which would be

    incurred as a result therefrom.

    Additional observations regarding SPAs of the 1970s are

    as follows:

    A distinguishing characteristic between

    force majeure under some Asian SPAs and those from

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    5/17

    other regions was introduced in 1973 with one Asian

    contract deeming force majeure to include [t]he reserves

    of natural gas in [certain named fields] which can

    economically be produced for purposes of this Contract

    have been fully depleted.

    In one instance under an ex ship SPA, even

    if the buyer was excused from purchasing LNG due to a

    buyer force majeure, the buyer was nonetheless obliged to

    pay certain transportation costs incurred by seller during

    the force majeure.

    Tax risks continued to be divided based on

    the concept that seller bears the risk of taxes imposed by

    the export country while buyer bears the risk of taxes by

    the importing country. In one instance, buyers agreed to

    an equal sharing of sellers increased natural gas or freight

    taxes outside of the importing country, provided seller had

    exercised reasonable diligence to avoid the increase or

    new imposition of taxes.

    Not all SPAs included the obligation to pay

    demurrage if loading (or unloading) of a particular cargo

    was delayed. Furthermore, in other agreements, cargoes

    loaded/unloaded quickly over the year were netted against

    cargoes loaded/delayed over the same year, in order to

    determine any demurrage payable.

    Scheduling of deliveries was to be at rates

    and intervals reasonably equal and constant throughout

    the year. In a precedent setting move that is, with

    increasing frequency, today challenging receiving terminal

    operations with multiple users, different scheduling yearsevolved during this decade. For example, a contract year of

    April 1 to March 31 was established in the 1970 Brunei -

    Japan SPA while a contract year of January 1 to December 31

    was set in both the 1973 SPA between Indonesia

    (Pertamina) and the Western Buyers and in the 1976 SPA

    between Algeria (Sonatrach) and Distrigas of the U.S.

    A few SPAs addressed liabil ities in

    relation to an accident occurring while loading (or

    unloading) of an LNG tanker. When such liability was

    addressed, the negligence, willful misconduct or

    intentional act of the party or its agents (including the LNGtransporter) was the determining factor, with no stated

    financial limit for such liability exposure.

    1980s

    Indonesia and Algeria dominated this decade, signing the

    vast majority of executed SPAs.6 However, the 1980s did

    see the emergence of new supplies from Malaysia and

    Australia (and a failed potential supplier, Dome Petroleum

    Limited of Canada). On the importing side, South Korea

    began its big push into LNG by signing ex ship agreements

    with Indonesia, while new buyers in Belgium and Taiwan

    also joined the industry. Most of these contracts were for a

    term of 20 years, although Algerias SPAs with France were

    25 year agreements. The average length of SPAs began to

    approach 75 pages (though Algerian SPAs continued to fallin the 40 page range).

    It should be noted that the first major dispute on a SPA

    occurred during this period, when the Algerian government

    refused to approve the LNG pricing authorized by U.S.

    agencies, leading to various disagreements on pricing which

    led to the eventual termination (or renegotiation) of most

    Algerian SPAs providing for deliveries to U.S. terminals.7

    Gas competition issues began to influence the structuring

    approach to SPAs. For the first time, multiple participants in

    one joint venture chose to execute separate, parallel SPAs with

    each buyer. However, because performance of the multiple

    SPAs was to occur simultaneously from an operational

    standpoint, the parties agreed in each SPA that the LNG to be

    sold and delivered to each Buyer under [the SPA] shall be sold

    and delivered commingled with LNG to be sold and delivered by

    [named other sellers] to each Buyer under the other sale and

    purchase agreements concluded between Buyer and the Other

    Sellers. Each of the multiple SPAs deems a set portion of each

    commingled cargo to be from the respective seller.

    This decade saw much less variety in the choice of law to

    govern the SPA, with English law and New York being

    almost the exclusive choices. Although the ICC arbitration

    rules were still chosen on several occasions (with the

    arbitration to be held in either Paris or New York), for the

    first time the UNCITRAL Rules, adopted in 1976, were also

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    6/17

    utilized (with hearings to be in Geneva or New York). In one

    unique provision in the 1981 Arun II Trade SPA signed between

    Indonesia and Japanese buyers, the place of arbitration was

    agreed to be Paris; yet, the SPA provides that if Pertamina had,

    at the time of its dispute with the Japanese buyer, another

    ongoing arbitration in Paris with another LNG purchaser and

    if arbitrating in Paris could require Pertamina to take

    mutually contradictory actions in its respective disputes,

    then the place of arbitration would be moved to New York.

    Take-or-pay clauses remained, typically on an annual basis

    but in at least two instances on a quarterly basis. In the first

    part of the decade, buyers had little ability to reduce their

    take-or-pay amount (and in some cases the reduced amount

    had to be re-taken within a certain number of years via so-

    called Make-Good provisions). Interestingly, as the decade

    drew to a close and lower oil prices brought on more of a

    buyers market for LNG, buyers enjoyed more flexibility to

    increase or decrease annual take-or-pay amounts.

    Pricing of LNG generally followed existing approaches; for

    example:

    An initial price of $5.78 per MMBTU, FOB,

    based on a 1981 crude oil export price of $35.69, with

    annual adjustments for changes in such export prices.

    A price determined, in part, on the average

    landed price, in dollars, of all other liquefied natural gas on

    long term contracts being imported into Japan, and the

    actual figure shall be determined prior to the first delivery of

    LNG in a fair and reasonable manner. The remaining portion

    of the price was to be based on the Japanese Crude-oil Cocktail,

    a weighted average landed price of all crude oil imported into

    Japan during a reasonable period to be agreed.

    An ex ship price divided into an LNG

    Element based on crude oil export prices and a

    Transportation Element (with the LNG Element having a

    base LNG price of $4.284 per MMBTU and the

    Transportation Element having a base price of $0.47 per

    MMBTU (escalating at an agreed rate)).

    Price review clauses, if included, were typically only an

    obligation of the parties to review the price in good faith in the

    light of all the circumstances relevant at the time; the contract

    price would only be changed if the parties agreed to do so.

    Continuing the practice in the 1960s and 1970s, few

    specific remedies applicable to sellers non-performance

    were built-in. If a clause dealing with remedies was

    inserted, it was typically along these lines (in both English

    law and New York law governed SPAs):

    [Subject to Buyers liability for any take-or-pay

    deficiency], the Seller shall be liable to either

    Buyer and either Buyer shall be liable to Seller for

    loss and damage which has been suffered as a

    result of the breach by the party liable of any one or

    more of its obligations hereunder, to the extent

    that the party liable should reasonably have

    forseen the loss or damage.

    An important development occurred when the initial Japanese

    FOB buyers from Indonesia insisted that a liability regime for

    LNG accidents at the loading port be incorporated into the

    SPA. Accordingly, a 1981 Indonesian SPA added a multi-page

    exhibit of principles for determining the liability of the

    shoreside interests and of the LNG vessel interests in theevent of an LNG incident. These SPA principles obligated

    the parties to agree to separate Omnibus and Waiver

    Agreements, governed by English law and subject to the

    jurisdiction of the High Court of Justice in London, overriding

    the existing Conditions of Use the Master of the LNG vessel

    was required to sign upon entry of the vessel into the

    Indonesian port. Under these liability principles the parties

    set the liability limit of the LNG vessel owner at $150 million,

    a limitation of liability which was to continue in effect for as

    long as the [vessel] Owner can obtain customary P and I Club

    cover for the risk. Somewhat surprisingly, although almost25 years has elapsed since the port liability limit for vessel

    owners was established in Indonesia, the $150 million liability

    limit has not been increased; recent SPAs have also adopted

    this limit for other LNG ports, based in part on the view that

    higher liability coverage is not yet available from P&I Clubs

    insuring LNG vessels.

    Additional observations regarding SPAs of the 1980s are as

    follows:

    In at least one instance, the SPA had a

    hardship clause which (in recognition that the SPA was a

    long-term contract that the parties intended to be fair and

    reasonable for its full term) obligated the parties to make,

    in a spirit of mutual understanding and cooperation,

    mutually acceptable revisions to the SPA to eliminate any

    substantial hardship suffered from a change in

    circumstances.

    Tax clauses in some instances became more

    comprehensive. For example, some clauses required seller in

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    7/17

    ex ship contracts to not take any action which would lead to

    seller having a permanent establishment in buyers country.

    In place of an unrestricted indemnity for taxes in the buyers

    country, in some cases the seller agreed to use its best

    efforts to cease to be subject to [the importing countrys]

    income tax, by appropriately reordering its affairs connected

    with the performance of the SPA.

    As a result of a disputed force majeure

    event centered on whether a party could claim force

    majeure if an employee caused an accident due to its

    negligence, a few contracts entered into late in the decade

    were amended to remove the outside the reasonable

    control of the party requirement. In its place, force

    majeure was deemed to also comprise, for example, any

    serious accidental damage to a facility unless it resulted

    from the willful negligence on the part of the partys

    management.

    Moreover, several SPAs began to address

    the possibility of extended force majeure, providing either

    that the other party had the right to terminate the SPA

    after a set period (2 to 3 years) or, in the case of seller, to

    sell otherwise undeliverable LNG to third parties if the

    force majeure had exceeded 9 months.

    Non-utilization provisions first

    appeared during this period to address the exposure of the

    shipping party to un-reimbursed transportation costs if the

    other party suffered a force majeure. Under some SPAs, the

    party claiming force majeure would in certain instances

    still be required to make payments during the force

    majeure in an attempt to make the other party whole for

    the cost of its unused, dedicated LNG shipping fleet.

    Destination restrictions existed, either

    expressly in the SPA or practically due to transportation

    limitations and location specific pricing provisions. For

    example, one ex ship SPA stated if buyer made an

    emergency need request, seller may, in its discretion,

    agree to change the place of delivery to another port in the

    same country as the buyer.

    Again, not all SPAs included the obligation

    to pay demurrage if loading/unloading of a cargo wasdelayed. One ex ship SPA simply required the parties to

    discuss in good faith how to distribute any additional costs

    incurred by a party as a result of a delay in berthing,

    unloading or departing.

    Most favored nations pricing provisions

    were not uncommon, with the stated purpose in one

    instance being to maintain comparability between the

    Contract Sales Price under the [SPA] and prices payable

    under the Japanese Contracts existing on the date of the

    SPA.

    The rise in project financed liquefaction

    facilities resulted in more provisions aimed at ensuring that

    sellers revenues are not unnecessarily interrupted. An example

    is the disputed force majeure clause in one SPA of this period

    that required buyer to continue to pay in full, to an escrow

    account at a bank in a neutral country, for the contractual

    quantity of LNG regardless of buyers assertion that buyer is

    excused from taking LNG due to a force majeure event.

    1990s

    The 1990s saw a steep rise in developments affecting the

    LNG industry, with SPAs being signed by new exporters in

    Qatar, Oman, Nigeria and Trinidad and by new importers in

    Turkey, Puerto Rico and Greece. In the first part of the

    decade, Asian suppliers (particularly Indonesia8, Malaysia and

    Qatar) signed, renewed or substantially amended a multitude

    of SPAs with principally Japanese, South Korean or Taiwanese

    buyers. On the other hand, the second half of the decade

    witnessed the re-birth of U.S. LNG imports, increases in

    supplies to Europe and the emergence of the Middle East as a

    key Asian supplier. The decade also saw, in dollars terms, the

    largest contractual dispute to date on an SPA.

    11 For the Indonesian perspective on contractual and legal issues associated with SPAs, see A. Nasution, Special Advisor to Pertamina President Director, "Allocating

    Price Risk in LNG Sales Contracts" (IBA Energy Law Conference, The Netherlands, 1990). To contrast the Indonesian seller's view with the Japanese buyer's approach,

    see Greenwald, "LNG Export Projects to Japan: The Purchaser's View" (IBA Energy Law Conference, The Netherlands, 1990).

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    8/17

    The length of SPAs signed during the 1990s continued to

    vary, in part based on the style of the draftsmen; while a

    few remained in the 50-60 page range, several exceeded 80

    pages and one SPA, in a rather odd example for a major

    project that did not proceed after signing, exceeded 175

    pages. With an average length reaching around 90 pages,

    most agreements were for a 20 year term, but at least two

    Middle East SPAs had a term of 25 years.

    None of the SPAs from this decade that were reviewed for this

    article had a governing law other than New York or England.

    Although the number of SPAs governed by New York law

    exceeded that of English law, especially during the end of the

    decade, the number of agreements governed by English law saw

    a marked increase. In some SPAs, the parties expressly agreed

    that the newly effective United Nations Convention on Contracts

    for the International Sale of Goods 9 and the Convention on the

    Limitation Period in the International Sale of Goods would not

    apply to the SPA. From a dispute resolution standpoint, the

    methods chosen were the following: (i) ICC in Geneva; (ii) ICC in

    London; (iii) UNCITRAL in London; (iv) UNCITRAL in New York;

    and (v) in several instances, ICC in Paris.

    As mentioned above, the SPAs of the 1990s bred the largest

    SPA dispute to date and one of the largest in English legal

    history. When the Italian state electric utility, ENEL,

    attempted in 1996 to cancel its SPA with Nigeria LNG Ltd

    (reportedly claiming force majeure), the result was the filing

    of a breach of contract arbitration against ENEL for $13billion. At the time, this claim was reportedly the largest one

    ever brought under English law. Fortunately, the matter

    soon settled when the parties agreed that Nigerian LNG

    would be shipped to France instead of Italy, in exchange for

    Russian gas diverted by French buyers to Italy. 10

    Take-or-pay clauses continued to be relied upon,

    determined now almost exclusively on an annual basis. In

    spite of this, the parties to a 175 page SPA, which was

    governed by English law, decided to avoid using the words

    denoting take-or-pay; instead, the buyer under this SPA

    was granted an annual right to either lift and purchasethe annual contractual quantity or accrue a right to be

    allocated Make-Up LNG by payment for the

    corresponding quantity not lifted. Buyers continued to

    have some limited ability to reduce their take-or-pay

    amounts (generally not exceeding 5%). With the evolution

    of annual contract quantities, quantities to be made-up

    from prior year reductions, make-up LNG, option

    quantities, force majeure restoration quantities, etc.,

    provisions were added to the SPA to account for the relative

    priority of each contractual quantity right or obligation.

    Flexibility in scheduling delivery of the take-or-payquantity began to be of major concern to some buyers,

    especially those located in countries with peak winter

    demand. This resulted in one Atlantic SPA requiring

    delivery of 62% of the annual contract quantity during

    October 1- March 1 and 38% of the annual contract quantity

    during April 1 to September 30.

    As new markets for LNG opened, pricing of LNG began to

    move gradually more away from its crude oil origins; for

    example:

    A price based on the Net Back Fraction

    calculated using actual sales of LNG and regasified LNG by

    buyer to customers within certain U.S. states, with buyer

    having the obligation to diligently seek to maximize the

    proceeds from such resale by negotiating terms with

    customers which in Buyers reasonable commercial

    judgment are the most favorable available to Buyer in the

    prevailing circumstance.

    A price based approximately 90% on crude

    oil export prices (based on an initial factor of $3.24 MMBTU

    at $18 per barrel) and approximately 10% on changes in U.S.inflation.

    A price divided into an LNG element based

    on certain crude oil prices and on a transportation element,

    with buyer paying sellers actual cost of transportation

    using certain dedicated LNG tankers.

    A price based on crude oils imported in

    Japan in that month plus a Constant (initially set at $.77)

    to be revised upward prior to the first delivery under the

    SPA if agreed by the parties to be necessary by taking into

    consideration relevant factors including the prevailing

    energy situation.

    Notwithstanding that the importer was

    located in another country, a price based on crude oils

    9 The CISG came into effect in 1988; it is presently in effect in the U.S. but not in England. Note that the United Kingdom, however, may soon ratify the CISG as well.

    See UK Parlimentary Debate, 7 Feb 2005.

    10 See Weems and Keenan, "Greenfield LNG Import Terminal Approvals," LNG Journal (May-June 2002) (www.kslaw.com/practice_areas/energy/publications.asp).

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    9/17

    imported in Japan; however, the price automatically

    adjusts upon a 5% differential between the contract price

    and pricing under buyers existing SPAs for Middle East

    LNG supplies.

    Aside from the SPA mentioned above, the 1990s saw few

    uses of most favored nations clauses for comparative

    pricing. Price review clauses, also called contract price

    reopeners, were sometimes incorporated into Atlantic SPAs

    supplying LNG to Europe. Rather than making any changes

    dependent on the parties ability to reach agreement, a party

    was allowed to resort to arbitration to determine

    adjustments, bearing in mind pricing of LNG and gas in

    Western Europe, which in any event allow buyer to market

    the LNG supplied in competition with all competing

    sources or forms of energy (including, but not limited to,

    natural gas, fuel oil, gasoil, coal, LPG, district heating and

    electricity). such that Buyer is able to achieve a reasonable

    rate of return on the LNG delivered hereunder.

    Creditworthiness of the buyer became more of a focus

    during this decade as special purpose companies and

    subsidiaries of smaller gas companies without large

    balance sheets executed SPAs. This was especially the case

    in situations where the seller project financed its

    liquefaction facilities partly on the strength of the buyers

    credit. The importance of the soundness of contractual

    arrangements increased as sellers had to find comfort that

    buyer would perform by examining the soundness ofbuyers gas resale agreements and power sales agreements.

    In one example, the subsidiary was required to provide a

    parent guarantee for several hundred million dollars.

    However, if seller was not required to finance the

    construction of additional facilities to provide the

    quantities sold under the SPA, the buyer was simply

    required to obtain the issuance of letters of credit for the

    value of 2 to 3 cargoes. In some SPAs, in exchange for

    buyers guarantor being able to limit its parent guarantee

    amount, the seller limited its maximum liability.

    Extensive remedies clauses became more fashionable

    during the 1990s. Although many contracts maintained

    the prior approach of relying on remedies afforded under

    the governing law (including those governed by the

    Uniform Commercial Code via the choice of New York law

    and certain Asian SPAs into Japan governed by English

    law), other contracts chose more detailed and specific

    remedies for non-performance. The remedies for seller

    non-performance were broadly divided into three

    categories: (a) the actual net cost of replacement gas or

    LNG; (b) the actual net cost of alternative replacement

    fuels; or (c) liquidated damages. The following are

    highlights of example provisions detailing remedies for

    non-performance of the sale or purchase obligations:

    As to sellers liability, determined based on

    the costs buyer reasonably incurs to purchase either LNG

    (on an FOB basis), natural gas or a reasonable alternative

    fuel in replacement for the shortfall quantity of LNG, plus

    reasonable additional shipping costs incurred by buyer, but

    minus the contract sales price and any costs saved.

    As to sellers liabil ity, a Shortfall

    Payment in dollars for the quantity (exceeding a minimum

    threshold of 2.5%) not delivered, determined by multiplying

    the Shortfall Quantity by the following:

    (a) the cost to buyer of replacement

    naptha/condensate/distillate volumes, delivered to thedischarge port; multiplied by (b) a pre-agreed heat rate

    adjustment factor to convert the LNG Shortfall Quantity to

    naptha/condensate/distillate (which buyer would utilize at

    its downstream power station to generate the same amount

    of electricity), minus a pre-agreed adjustment for LNG boil-

    off and losses during regasification; minus

    the cost (on a $/MMBTU basis, delivered ex

    ship) which would have been incurred by buyer for the

    Shortfall Quantity of LNG.

    As to sellers liability, liquidated damages

    of 25% of the average contract sales price multiplied by theshortfall quantity.

    As to buyers liability, confirmation that

    Buyers sole liability for or arising out of or in connection

    with any failure to take delivery of, or if not taken, to pay for

    LNG when required to do shall be limited to its obligation

    to make [take-or-pay] payments.

    Broad force majeure clauses, covering much more than

    simply acts of God, retained their dominance in SPAs

    during this decade. The traditional approach to defining aforce majeure event as an event occurring outside the

    partys reasonable control remained popular; but, several

    SPAs of this period avoided such a test and instead named a

    specific and exclusive list of events that were deemed to

    constitute force majeure. The debate also centered on

    events affecting transportation assets and downstream

    assets which should be specifically included or excluded;

    for example:

    Inclusion of damage to, loss or failure of

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    10/17

    the pipeline transmission and distribution facilities or of

    trucks engaged in the transportation of LNG or Regasified

    LNG from the receiving facilities.

    Inclusion of delays in construction of

    relevant upstream facilities, new liquefaction trains and

    related facilities, certain new buyer facilities, and port

    facilities and the dredging thereof.

    Inclusion of the inability of one or more

    of buyers customers to take delivery of LNG, Regasified

    LNG or Natural Gas pursuant to its/their purchase

    contract(s) with Buyer.

    Inclusion of certain events preventing a

    power plant from continuously purchasing regasified LNG

    from buyer for at least 30 consecutive days (but pro-rating

    the effects of such event based on a comparison of the

    contract quantity under the SPA over the last 12 months to

    the total amount of Natural Gas whether domestic or

    otherwise and including LNG purchased by Buyer duringthe same period of time).

    Exclusion of circumstances which

    constitute a Political Force Majeure, as defined in the

    Power Purchase Agreement between buyer and the state

    electricity board.

    Exclusion of damage to an LNG tanker

    during certain voyages when carrying LNG not produced by

    seller.

    Exclusion of circumstances affecting

    buyers facilities if damage or failure resulted from gross

    negligence on the part of buyers management.

    A marked difference in the approach to reserves depletion

    developed. Asian SPAs addressed depletion of specified

    reserves of natural gas, while Atlantic SPAs specifically

    excluded the natural depletion by production of gas

    reservoirs. Lastly, although apportionment clauses had

    long been used to require seller to divide any available LNG

    supplies between long-term buyers, provisions were added

    requiring buyer to (for example) devise and notify to Seller

    a fair and equitable system for apportioning its purchasesbetween Seller and such other suppliers.

    The approach to conditions precedent varied by project. In

    some SPAs, the parties decided to bear considerable

    condition precedent risk for a set period of time while

    awaiting certain governmental approvals, the execution of

    ancillary contracts, and financing or other investment

    decisions. In one instance (addressed in a 4 page provision in

    the SPA), in addition to conditions precedent relating to

    government approvals obtained in form and substance

    satisfactory to the [relevant party] in it sole discretion, seller

    was able to terminate the SPA with no liability unless seller

    had (a) executed a gas supply contract, an additional SPA with

    another purchaser, and an EPC contract for construction of

    sellers LNG facilities, each in form acceptable to seller in

    sellers sole discretion; and (b) made an affirmative final

    investment decision, in its sole discretion, to construct, own

    and operate sellers proposed LNG facilities.

    Destination restrictions lingered in SPAs of the 1990s,

    with the following being representative of the effects of

    such restrictions:

    all LNG sold hereunder shall be for Buyers

    account only. Buyer shall deliver LNG purchased

    hereunder into the LNG receiving facilities at

    [______] (the Discharge Port), unless prevented

    from so doing by reasons of Force Majeure or

    operational problems encountered at the DischargePort or with the LNG Ship, in which case, Buyer may

    change the discharge destination to another

    suitable port in [Buyers country]. Should Buyer

    wish to change the destination to a port outside

    [Buyers country] in accordance with the foregoing,

    Buyer must first secure Sellers consent, which

    shall not be unreasonably withheld.

    Some, but by no means all, SPAs executed during this

    period addressed liabilities for LNG accidents occurring at

    the loading/unloading terminal. While some contractswere silent on the subject, others specifically required the

    party responsible for transportation to take certain actions

    aimed at causing the vessel owner and other related parties

    to execute port liability agreements provided the

    agreements are (in one instance) reasonably acceptable to

    reputable insurers; the level of protection and indemnity

    insurance required does not unreasonably increase the

    cost of such insurance; and Seller is not exposed to any

    liability under the [agreement]. An unusual provision

    used for an SPA (governed by English law) for Japanese

    deliveries provided the following in order to resolve non-legal claims, presumably resulting from an LNG incident

    involving the vessel:

    If any demand or claim is made by any third party

    in Japan against Seller, Ship Owner, and each

    Buyer collectively or any of them, although according

    to the unanimous opinion of Seller and each Buyer

    there is no legal liability for the claim (for which

    purpose legal liability shall include cases of

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    11/17

    strict liability under the law or by contract) on the

    part of any of the parties, including Ship Owner

    against which it is bro ught, then the parties,

    together with the Ship Owner if willing, shall

    promptly discuss the claim in good faith and shall

    continue to do so as necessary until the claim is

    disposed of in order to find a reasonable solution

    with a view to disposing of the claim, protecting theinterest of all the parties, including Ship Owner, and

    preserving the smooth operation of the matters

    contemplated in this Agreement.

    In another SPA, Buyer agreed to be jointly liable with its

    transporter for any damage to the Loading Port Facilities,

    discharge of oil within the Loading Port or any other

    obstruction affecting the normal operation of the Loading

    Port Facilities. Under this provision, the aggregate liability

    of Buyer and its transporter for any one incident was limited

    to $150 million or such higher amount of insurance

    coverage as the Parties may agree from time to time is

    available and would generally be taken out by reputable

    operators of LNG vessels, based on normal industry practice,

    to cover such incidents and which is available from a

    recognised P&I club under usual P&I club rules.

    Not surprisingly, as more complex project structures came to

    pass (especially as more special purpose entities became

    LNG purchasers), more detailed termination clauses were

    adopted. In some SPAs these provisions occupy severalpages of the agreement. For example, in one instance buyer

    is specifically authorized to terminate the SPA if (a)

    construction of Sellers Facilities is not completed by a

    deadline; (b) seller becomes bankrupt, etc.; (c) seller fails to

    pay to Buyer an amount exceeding an agreed threshold

    amount; (d) seller fails to deliver at least 50% of the annual

    quantity in two consecutive years (for reasons other than

    force majeure); (e) if a sellers force majeure prevents

    delivery of at least 50% of the annual quantity in any year

    and it is apparent such prevention will continue for another

    year; or (f) if seller disposes of a substantial part of Sellers

    Facilities without the prior consent of buyer. Moreover, in

    circumstances where the buyer was entitled to resell a

    portion of its LNG to a third party for import into a different

    receiving terminal, special termination provisions arose to

    enable seller to terminate such resale SPA if such seller is

    unable to receive LNG under its supply SPA for a specified

    period of time (e.g., 48 months) due to a breach of contract

    and if such seller shares a portion of the damages payable to

    it for breach of the supply SPA.

    Lastly, during the 1990s yet another scheduling year was

    established, with Trinidad contracts adopting an October 1 to

    September 30 contract year.

    2000s

    During the period since 2000 the LNG industry has

    experienced the signing of an unprecedented number of

    SPAs. The International Group of Gas Importing Companies

    (GIIGNL) reported earlier this year that at least 63 long

    term and medium term contracts were in force at the end of

    2004. GIIGNL also reported that 14 SPAs were signed in

    2004, and 2005 has seen the signature of many others (e.g.,

    Yemen with Kogas, Total and Suez LNG; Sakhalin in Russia

    with various Japanese buyers; and Iran with Indian buyers).

    Many of these contracts anticipate deliveries to North

    America. 11 While the first decades of LNG history were

    dominated by a few players, recent years have opened the

    industry to many more participants. As noted in the

    following table, 12 countries exported LNG in 2004 while 13

    countries imported LNG.

    11 LNG imports into the U.S. in 2004 reached a record 652 Bcf, compared to 2003 imports of 507 Bcf. However, LNG imports still represent only about 2.9 % of U.S.

    consumption and 15.5 % of U.S. imports, so additional LNG demand in the U.S. is expected by many LNG suppliers.

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    12/17

    The signing of the latest SPAs suggests that, by the end of

    the decade, the number of exporting countries is set to

    increase to at least 18 and importing countries to at least 16.

    In early 2005, liquefaction facilities began shipping from

    Egypt, and facilities in Norway, Russia, and Equatorial

    Guinea are now under construction (with Iran and Yemen

    soon to commence construction). On the import side, a new

    regasification terminal opened in the United Kingdom in

    2005 and new regasification terminals are now under

    construction in Mexico and China. As shown in the

    following map of key trade routes in operation as of 2004,

    Asian and Atlantic trades are becoming much more

    intertwined than in the past.

    Key LNG Trade Routes 2004 12

    In the sampling of recent SPAs reviewed, New York law was

    chosen in half. The length of SPAs continues to rise

    somewhat from the last decade (e.g., after excludingtechnical exhibits, this sampling contains, respectively,

    106, 99, 75, 74, 80, 65, 95, 109, 104 and 151 pages).

    Arbitration provisions in both Asian and Atlantic SPAs

    have followed similar paths, with common choices being

    UNCITRAL arbitration in London or New York, ICC

    arbitration in Paris or London, or, in at least one instance,

    AAA in New York. While the majority of current SPAs are

    consistently for a term of 20 years (or 25 years, for some

    Middle East and Australian agreements), a 3.4 million tons

    per annum agreement signed in 2004 was for a term of only

    17 years. It is noteworthy that of the 14 SPAs that GIIGNLreports were signed in 2004, 10 of these were for an annual

    volume of less than one million ton per annum.

    At least two significant public SPA disputes have occurred

    since 2000. First, as a result of the failure of Enrons LNG

    terminal project in Dabhol, India, it is reported that both

    Oman LNG LLC and Abu Dhabi Gas Liquefaction Company

    Limited have each invoiced for take-or-pay amounts due

    under SPAs signed in the late 1990s with the Enron

    subsidiary Dabhol Power Company. Recently, these ongoing

    SPA claims, along with amounts not paid under related

    shipping contracts, were said to amount to $1.3 billion. 13

    Second, a dispute concerning an Algerian SPA signed in

    1987 with Trunkline LNG is ongoing in both London and

    Houston. In an UNCITRAL arbitration seated in London,

    Sonatrach and its affiliates are reportedly seeking

    approximately $600 million of damages. In 2003, the

    London arbitration panel found that Duke Energy LNG

    Sales Inc. repudiated the 1987 SPA by failing to diligently

    perform LNG marketing obligations; however, the panel

    also found that Sonatrach and Sonatrading breached their

    obligations under the 1987 SPA to provide shipping.

    Apparently, a hearing on damages issues is scheduled to

    commence in September 2005. The Houston portion of the

    second dispute concerns Dukes contract for the sale of the

    Algeri an regasified LNG. After Sonatrading ceased

    supplying LNG to Duke under the 1987 SPA, Duke asserted

    in 2002 to its gas buyer under the resale contract, Citrus

    Trading, that it had suffered a loss of LNG supply

    preventing it from performing its supply obligations. As a

    result, Citrus filed a lawsuit in March 2003 in the U.S.

    District Court for the Southern District of Texas 14 against

    Duke LNG alleging that Duke LNG breached the Citrus gas

    resale agreement by failing to provide sufficient volumes of

    gas to Citrus. Citrus has denied that Duke LNG had the

    right to terminate the gas resale agreement and contends

    12 Source: "The LNG Industry in 2004," GIIGNL, Paris.

    13 See GE, Bechtel Clear Last Hurdle in Dabhol Restart, The Financial Express, July 7, 2005 (available at www.financialexpress.com).

    14 Citrus Trading Corp. v. Duke Energy LNG Sales, Inc., Cause No. 2003-12166 (U.S. 165th District Court, Harris County, Texas).

    15 The Sonatrach and Citrus disputes are reported in Duke Energy Corp.'s 10-Q filing with the SEC, filed on August 9, 2005 (available at www.duke-

    energy.com/investors/publications/sec.asp).

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    13/17

    that Duke LNGs termination of the agreement was itself a

    breach, entitling Citrus to terminate the gas resale

    agreement and recover damages in the amount of

    approximately $187 million.15 The Duke-Citrus case has

    not yet gone to trial.

    Recent SPAs have granted the buyer somewhat more

    flexibility as to its take-or-pay obligations (however, this

    flexibility should be viewed in context, because the buyers

    commitment is still typically well in excess of 90% of the

    annual contract quantity). In any event, the take-or-pay

    contract remains alive and well (although some argue that

    in concept take-or-pay is less of an issue for the U.S.

    because the markets liquidity now always provides a gas

    purchaser at the market price). A recent major Asian SPA

    governed by English law clearly sets out the basic sale and

    purchase obligation on an FOB basis:

    Seller shall sell and deliver LNG in Cargoes at the

    Delivery Point or make available for delivery LNG

    and Buyer shall take and pay for, or pay for if not

    taken, LNG in accordance with and subject to the

    provisions of this Agreement.

    The October 13, 2003, Nigeria LNG Limited and BG LNG

    Services, LLC agreement (as filed with the U.S. Securities

    and Exchange Commission) states the basic take-or-pay

    obligation in the English law SPA as follows:

    in any Sales Period, Buyer shall be entitled to take

    the [annual contract quantity] required to be made

    available for loading pursuant to the above (less

    Boil-off and LNG Heel) in such Sales Period or to

    accrue a right to Make up LNG in respect of all or

    part of such quantity as it does not so take but in

    any event Buyer shall have the obligation to make

    full payment in respect of the entire [annual

    contract quantity].

    It is not uncommon for an SPA to now address quantity

    adjustments in relation to a multitude of circumstances,

    such as: (i) buyers right to increase or decrease the annual

    quantity by a set amount (in one SPA, referred to as Buyer

    Upward Flexibility Quantity or Buyer Downward

    Flexibility Quantity); (ii) sellers ability, upon Buyers

    agreement, to reduce the annual quantity for a Sellers

    Diversion (i.e., a diversion from delivery to buyer); (iii)

    sellers right to reduce the annual quantity for major

    scheduled maintenance of sellers facilities or its vessels; (iv)

    buyers right to reduce the annual quantity for major

    scheduled maintenance of buyers facilities or its vessels or

    due to operational constraints at [a third partys LNG import

    facilities]; (v) sellers right to reduce the annual contract

    quantity due to inadequate gas reserves or deliverability

    from the defined gas supply area; (vi) adjustments due todifferences in gross heating value from that estimated in the

    annual scheduling program; (vii) differences in the parties

    obligations to purchase during a build-up period versus the

    basic quantities to be sold and purchased throughout the

    term of the SPA; (viii) the parties rights to cancel a cargo

    which buyer cannot schedule for delivery; (ix) the effects of a

    force majeure; (x) fractional cargoes due to the conversion

    from cargoes to BTUs; and (xi) off-spec LNG. Such quantity

    adjustments, especially if multiple delivery destinations are

    anticipated under the SPA, are resulting in more detailed

    quantities provisions; for instance, the quantities provisionsin one recent SPA approach 25 pages, in part to address

    separate rules for sellers deliveries under the ex ship SPA to

    European receiving terminals and to North American

    receiving terminals.

    Although (as discussed below) destination restrictions have

    eased further, pricing provisions remain based on the gas

    market where the LNG will be imported. The following table

    indicates the wide differences in LNG pricing in 2004-2005

    for Asian import prices. 16

    16 www.abareconomics.com/australiancommodities/june05/pdf/asiapacificlng.pdf.

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    14/17

    While the Indonesian SPAs of the 1990s did not include S

    Curves which moderate LNG prices when oil is above or

    below a certain range, many recent Asian SPAs tend to

    include such S Curves. There has also been a move in

    some markets to link LNG pricing to power pricing.

    Examples of pricing approaches in recent Atlantic SPAs are

    as follows:

    A price for North American deliver ies

    which is a set percentage of the NYMEX Henry Hub

    Natural Gas Futures Contract traded at the Nymex

    Exchange for the calendar month when completion of

    unloading or deemed completion of unloading of the

    relevant cargo takes place.

    A price for U.S. deliveries where the

    formula varies depending on whether the agreed NYMEX

    Henry Hub Price for the month is less than $2.50, between

    $2.50 and $4.50, or greater than $4.50 per MMBTU.

    A price determined for each receivingterminal where seller will deliver LNG, such price to be

    based on an agreed reference price for that receiving

    terminal for the month, minus adjustments for certain

    agreed shipping costs to that receiving terminal, minus

    agreed pipeline costs, minus agreed terminal costs, and

    minus agreed fuel costs for such receiving terminal.

    A price for deliveries into the U.S. based in

    part on the net proceeds, after actual transportation costs,

    received by buyer from reselling the LNG purchased under

    the SPA at named receiving terminals, with the

    understanding that Buyer shall diligently seek tomaximize the net proceeds from its sales of LNG and

    Regasified LNG acquired hereunder [, an obligation]

    which is intended to ensure that the amount paid to Seller

    under this Contract reflects the fair market value to

    Buyers LNG customers.

    For deliveries into Europe, for 85% of the

    quantities, a price based on the unweighted average of the

    monthly average prices for Gas Oil and Heavy Fuel Oil as

    published in Platts Oilgram, and for 15% of the volumes, a

    price based on an index for downstream power prices.

    Most favored nations provisions are not as typical in

    Asian SPAs as they once were. Lengthy price review

    provisions are no longer uncommon. A recent SPA for sales

    into Europe contains a 4 page procedure (which leads to

    arbitration if the parties cannot agree to revised pricing) if

    either party has a good faith basis for believing that for

    reasons outside the control of the requesting party the

    method for determining the [price] does not reflect the

    value of regassified LNG at the import points in the

    European system at the time when the review is

    requested. In fact, some contracts now specify when a

    price review procedure will not apply, such as the 2003

    Nigeria LNG Limited and BG LNG Services, LLC agreement

    (as filed with the U.S. SEC) which states that [f]or the

    avoidance of doubt there is no price review mechanism

    for deliveries to Lake Charles.

    Creditworthiness of both parties is becoming an issue in

    some SPAs, but no uniform approach has developed. Full

    parent guarantees are sometimes required to support the

    buyers credit. In one instance for the U.S. market, both the

    parent of the buyer and the parent of the seller issued

    certain payment guarantees. In another instance, although

    the stated limit of the payment guarantee provided by the

    buyers parent is several hundred million dollars, the

    guarantee amount reduces if the buyer provides Step-In

    Rights to apply to any termination of the SPA by the buyer,

    namely: (i) a release of buyers capacity and associated

    vaporization rights in a specified regasification terminal;

    and (ii) an assignment of buyers rights under specified

    shipping contracts.

    Specific remedy provisions for failure to purchase or sell, as

    the case may be, are now commonly found in many, but not

    all, recent SPAs. Although prior contracts were often silent

    on the issue, buyers limit of liability is typically

    specifically stated. For instance, the limit may be a phrase

    such as the payment of the Annual TOP Quantity shallconstitute the sole and exclusive remedy Sellers shall have

    against Buyer for the obligation to take delivery of LNG.

    On the other hand, the practice still varies, if a remedy is

    stated, for sellers liability for non-performance. For

    example:

    In Asia, capping the sellers liability, in

    effect, to a percentage of the value of the cargo not

    delivered.

    Providing for liquidated damages of 25% of

    the total amount that would have been payable by buyer for

    the quantity that was not delivered (unless the non-delivery

    was due to wilful misconduct, in which case the liquidated

    damages percentage increased to 35%).

    If the shortfall in deliveries in a year is less

    than 10 cargoes, buyer is granted a 10% discount in the

    nature of liquidated damages; a stated liquidated damage

    amount is payable if the shortfall exceeds 10 cargoes.

    Different remedies depending, in part, on

    the timing of when seller provided notice of cancellation of

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    15/17

    delivery or of substitution of an LNG vessel with reduced

    capacity.

    A shortfall payment based on the average

    contract price over the last 12 months, minus certain costs

    saved by buyer.

    The lesser of the cost to replace the gas not

    delivered or 20% of the contract price.

    Liquidated damages may also be payable if seller fails todeliver on a timely basis.

    No major alteration in the approach to force majeure has

    occurred in SPAs of this decade, although provisions are

    tending to lengthen as more detail is devoted to the parties

    obligations to take actions to resume deliveries of LNG (e.g.,

    procuring additional shipping). Noteworthy developments

    with regard to force majeure in recent SPAs are:

    In SPAs providing for multiple delivery

    destinations: (i) coverage of certain downstream facilitiesor events in a different manner for each receiving terminal;

    and (ii) if force majeure prevents deliveries at buyers

    nominated terminal, the obligation for buyer to use

    reasonable endeavors to receive LNG at another LNG

    terminal that seller approves (with seller having the right

    to refuse to unload at such other terminal due to potential

    additional cost or risk to seller, scheduling difficulties, or

    safety/operational issues).

    The express obligation of seller, in the

    event of an accident affecting gas production, to take such

    measures that are required to resume deliveries, includingnew investments and also temporary deliveries of LNG

    from [other LNG terminals].

    In some recent Asian contracts, the

    exclusion of depletion of gas reserves from allowable force

    majeure events.

    Coverage of buyers downstream power

    customers only for events which occur during the first 5

    contract years or only while such customer is off-taking at

    least a certain percentage of all of the regasified LNG sold

    at the receiving terminal.

    The exclusion of events affecting LNG

    receiving terminals other than the scheduled receiving

    terminal.

    The inclusion of provisions detailing

    sellers rights if a buyer force majeure occurs.

    The obligation of buyer to apportion

    available capacity at the receiving facility between the SPA

    and other long-term contracts (i.e., having a term of at least

    15 years) only.

    In a recent Asian SPA, the obligation of

    buyer to use reasonable endeavors to take any quantity of

    LNG not taken previously as a result of Force Majeure.

    The purchase and sale obligations under many, but by no

    means all, SPAs of this decade are conditional on the

    fulfillment of one or more conditions precedent. As is

    customary, the listed events are centered aroundgovernment approvals, financing (including the

    satisfaction of all conditions precedent to the initial draw-

    down of funds), or the execution of ancillary contracts,

    with the obligation to satisfy the condition within a

    relatively short time (generally less than 6 months). In one

    instance, the SPA was conditional on seller making a final

    investment decision on the construction of an additional

    train. The parties typically agree to use reasonable

    endeavors, or at least to act in good faith, in attempting to

    satisfy the stated conditions precedent. Given the shortage

    of excess receiving terminal capacity over the last fewyears in some countries, one SPA specifically stated that

    buyers obligations are not conditional on buyer making an

    investment decision, constructing or purchasing capacity

    at any receiving terminal.

    As a result of pressure during 2001-2002 by the European

    Commission, SPAs for supply into Europe no longer contain

    destination restrictions (for example, it is reported that

    Nigeria LNG undertook not to introduce territorial

    restriction clauses in its SPAs signed after October 2002).

    Many SPAs (especially those of an ex ship nature) forsupply into Asia continue to have some restrictions on the

    ability of the buyer to alter the destination of the cargo;

    however, some contracts for supply into the U.S. are

    becoming more flexible (with one FOB contract mentioning

    that buyer may redeliver any cargo to any LNG terminal so

    long as the redelivery does not result in buyer failing to

    arrive timely at the load port in accordance with the

    loading schedule). Moreover, a change in destination for

    deliveries to a North American port in an ex ship

    agreement, in addition to requiring sellers permission to

    divert, may result in the use of a pre-agreed (or agreed atthe time of the proposed diversion) alternative pricing

    approach or formula.

    With respect to each partys liability for an LNG accident in

    the others terminal, practices in this respect remain

    inconsistent. While some SPAs elect to not lay out a special

    liability regime for the LNG loading or unloading port, an

    Asian SPA included a detailed provision requiring buyer,

    transporter, seller, and all their related associates, to sign

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    16/17

    a separate agreement governed by English law that

    implements the liability regime enunciated in the SPA.

    Where under such liability provisions a party agrees to

    indemnify for damages caused by such partys LNG vessels,

    the limitation of liability is typically set at $150 million or

    such higher amount of insurance coverage which is

    available from a recognized protection and indemnity club

    under usual protection and indemnity rules covering anLNG tankers liabilities while in or near docking facilities.

    In some cases, a party is required to waive, on behalf of

    itself and the disponent owner and charterer of the LNG

    vessel, any right of such party to limit buyers liability

    under applicable laws, including the Convention on

    Limitation of Liability for Maritime Claims 1976.

    Termination clauses, once infrequent, are now common, with

    some being very detailed and several pages in length. Events

    which allow termination of the long-term sales contract can

    be grouped generally into those related to extended force

    majeure, those related to failure to pay or deliver LNG, or

    those related to other events which give rise to the partys

    ability to continue to perform in the future (e.g., insolvency-

    related events, credit support events). With regard to

    extended force majeure, termination is now an available

    remedy, generally, if the event has occurred for at least 24-36

    consecutive months and the event prevented the delivery of at

    least 50% of the annual contract quantity for such period. As

    an alternative to termination in one instance, if only a portion

    of the annual contract quantity had been affected, the party

    was granted the right to reduce the annual contract quantity

    under the remaining term of the SPA to in effect eliminate the

    portion that was not deliverable. Failure of the seller to

    deliver for non-Force Majeure events may be addressed in

    several ways, including sellers (i) failure to make available an

    amount of LNG of at least [__]% of the annual contract

    quantity in [__] consecutive years; (ii) failure to deliver any

    LNG Cargo Lot for a period of more than 120 consecutive

    days; and/or (iii) delay of at least [__] in commencement of

    deliveries during the first contract year. Termination for

    buyers failure to make payment is normally tied to a

    threshold amount (in one case, at least $100 million), whichmay be directly tied to the amount of credit security provided

    by buyers guarantor. Lastly, other events which have (in at

    least one instance) been added to the list of those justifying

    termination of the SPA are (x) buyers failure to make

    available regasification capacity equivalent to [__ billion

    cubic meters] in any period of [__] years or less and (y) changes

    in control of a party without the execution of documents

    confirming existing credit support obligations or without a

    corresponding transfer of the underlying gas supply assets.

    Transfer of title, thought to be an issue long ago resolved,

    has become an issue of import again in some SPAs,

    especially ex ship sales when the seller is concerned with

    potential liability for accidents or the parties wish to

    ensure that the sale is not considered a taxable event in the

    importing country. Such concerns have in more than one

    instance driven the parties in ex ship sales to agree to

    transfer title offshore, immediately prior to the vesselreaching the boundary line of the importing country. A host of

    issues arise from such offshore title transfers, compounded by

    situations in which the buyer assumes responsibility for

    transportation from the offshore delivery point to the

    receiving terminal and back to the offshore delivery point.

    True CIF sales, in which seller retains responsibility for

    transportation but buyer acquires title to LNG at the loading

    port, are also a recent phenomenon in SPAs.

    Lastly, the following are some additional observations

    regarding SPAs signed since 2000:

    Although some SPAs allow the buyer to

    reject an off-spec cargo if quality non-conformance is

    known soon after loading (e.g., within one day), most SPAs

    commonly obligate the buyer to use reasonable endeavors

    to attempt to receive the off-spec LNG (i.e., such as treating

    or blending the LNG with other LNG at the receiving

    terminal). In light of known quality issues in North

    American and UK gas markets for todays typical LNG

    specification and caps (e.g., 15% of the contract price) in

    some SPAs on the amount which seller will reimburse buyer

    for costs incurred in attempts to treat/blend off-spec LNG,

    some of the risk associated with off-spec LNG appears to

    have been transferred from seller to buyer.

    Due to multiple offtakers in many loading

    and unloading terminals (particularly receiving terminals

    under construction which will be used by multiple

    customers based on two and three day set windows for

    unloading), scheduling issues have taken on increasing

    complexity.

    Although the LNG industry is said to be

    moving to more of a commodity business, few SPAs requireseller to issue negotiable bills of lading. Instead, the

    common approach remains to rely on the issuance of cargo

    receipts evidencing the quantity loaded, rather than having

    the effect of a document of title. However, in one late 2001

    SPA, the seller is required to provide appropriate bills of

    lading; if the bill of lading is not available when buyer is

    obligated to pay for the cargo, the SPA requires the seller to

    issue an indemnification letter in a form (attached to the

  • 8/11/2019 Evolution of Long-Term LNG Sales Contracts

    17/17

    SPA) which heretofore has been utilized for shipments of

    crude oil rather than for LNG.

    Conclusion

    This article has provided a general overview of changes to

    contracting practices for representative Asian andAtlantic-basin SPAs and common alternative drafting and

    risk-sharing methodologies. The 1960s concept of rather

    succinct, fixed price SPAs linking a creditworthy seller

    with a creditworthy buyer and using ships dedicated to a

    single trade has evolved over the last four decades. SPAs

    today vary in complexity, influenced by a variety of factors

    such as the parties concerned and their creditworthiness

    (or lack thereof), the pricing basis for LNG sold, the depth

    of buyers downstream gas market and its competing fuels,

    the delivery point, LNG transportation structures, take-or-

    pay flexibility, whether multiple users aggravate scheduleissues, influences by gas competition regulators, concerns

    of lenders, sufficiency of sellers gas reserves, and the

    allocation of commercial, operational and political risks

    related to performance of the agreement. Counsel drafting

    and negotiating SPAs would be wise to consider both past

    LNG precedent gained from decades of experience with

    LNG issues and the need to develop new techniques to

    appropriately deal with the multitude of challenges

    presented by the rapidly expanding LNG trade.

    www.kslaw.com