of m/s. devashree ispat (p) ltd unit-i · m/s. devashree ispat (p) ltd unit-i sy. nos.458,459...
TRANSCRIPT
DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT
OF
M/s. DEVASHREE ISPAT (P) LTD UNIT-I
Sy. Nos.458,459 &460 Ellikatta village, Farooq Nagar Mandal, Rangareddy District, (Formerly
Mahaboobnagar District), Telangana state
PROPOSAL FOR EXPANSION OF INDUCTION FURNACE
& ROLLING MILL
For Grant of Environmental Clearance (Category B project under 3(a) Sector)
Project Cost for expansion- Rs. 5.75 Cr
Baseline Study Period – December 2017 to Febuary 2018
Project Proponent Environmental Consultant
M/s. Devashree Ispat (P) Ltd Unit-I M/s. Pridhvi Envirotech (P) Ltd., Sy. Nos.458,459 and 460 NABET Accreditation S.No. 119, Ellikatta village,Farooq Nagar Mandal Rev 67 dated 9th July, 2018
Rangareddy District Plot No. 184/C, Lawn House,
Ph: 040-23557186 4th Floor, Vengal Rao Nagar,
Email: [email protected] Hyderabad – 500 038.
Ph: 040 – 40179770
Email:[email protected]
SUBMITTED TO
TELANGANA POLLUTION CONTROL BOARD,
REGIONAL OFFICE, RANGAREDDY
CONTENTS
S.NO DESCRIPTION PAGE NO
Copy of TOR and Compliance
FORM-I
EXECUTIVE SUMMARY
Chapter 1.0: Introduction
1.1 Purpose of the Report 1-1
1.2
Brief Description of Project & Project
proponent 1-2
1.2.1 About Project 1-2
1.2.2 Project Proponents 1-2
1.3 Need of the Project 1-3
1.4 Justification of the project 1-4
1.5 Nature & Description of Project 1-5
1.5.1 Common facilities Unit I and Unit III 1-6
1.6 Location of Project 1-6
1.7 Project Cost 1-7
1.8 Scoping of EIA Study 1-8
1.9
Environmental sensitivities & significant of the
project considered 1-10
1-10 Policy, legal and administrative framework 1-10
1.10.1 Institutional Setting for the project 1-10
1.10.2
Institutional Setting in the Environmental
Contex 1-10
1.10.3
Ministry of Environment, Forests & Climate
Changes (MoEF & CC) 1-11
1.10.4 MoEF & CC Regional Offices 1-11
1.10.5 State Pollution Control Boards (SPCB) 1-11
1.10.6
Departments of Environment and
Forests(DOEF) 1-12
1.11 Other Statutory Licenses/Permission 1-12
1.11.1 Director of Factories & Boilers 1-12
1.11.2 Permissions from Local Panchayat 1-12
1.12 Required Statutory Licenses At A Glance 1-12
1.13 Structure of the EIA Report 1-13
Chapter 2.0: Project Description
2.1 Brief Description of Project 2-1
2.2 Need for the Project 2-2
2.2.1 Steel Industry as a whole 2-2
2.3 Location 2-3
2.4 Site Sensitivity 2-3
2.5 Size & Magnitude of Operation 2-12
2.5.1 Proposed schedule for approval and 2-12
implementation
2.6 Technology & Process Description 2-13
2.6.1 Alternative technologies 2-13
2.6.2 Technology Proposed 2-13
2.6.3 Assessment of new & Untested Technology for the risk of technological failure 2-13
2.6.4 Manufacturing process 2-14
2.6.4.1 The charge 2-14
2.6.4.2 Melting the Charge 2-14
2.6.4.3 Equipment used in steel meting shop 2-16
2.6.5 Manufacturing Process on Rolling Mill 2-18
2.6.6 Scrap Handling 2-20
2.6.7 Slag Handling 2-20
2.6.8 Fume Extraction System-FES 2-20
2.6.9 Re-Heating furnace 2-20
2.6.10 Coal Pulveriser 2-21
2.7 Resource requirement for the project 2-21
2.7.1 Raw material requirement 2-21
2.7.2 Power Requirement 2-22
2.7.3 Man Power Requirement 2-22
2.7.4 Water requirement 2-22
2.7.5 Land Requirement 2-23
2.8 Environmental aspect from different process 2-24
2.9 Environmental Impacts & Control Systems 2-25
2.9.1 Water & Waste water 2-25
2.9.2 Air Emission Sources & Control 2-27
2.9.3 Fugitive Dust Suppression 2-28
2.9.4 Hazardous & Non Hazardous waste generation and handling 2-28
2.9.5 Noise Pollution 2-29
2.10 Current Environmental control mechanisms & Gaps 2-30
Chapter 3.0 Baseline Environmental Status
3.1 Preamble 3-1
3.2 Methodology of Base line data collection 3-1
3.2.1 Scoping 3-1
3.2.2 Reconnaissance Surveys 3-1
3.2.3 Assemble and Analysis of Data 3-2
3.2.4 Documentation of Baseline Conditions 3-2
3.2.5 Assessment of Alternatives 3-2
3.2.6 Assessment of Potential Impacts 3-2
3.2.7 Integration of Environmental Impact in the Design Process Environmental Component 3-3
3.3 Land Environment 3-3
3.3.1 Physiography 3-3
3.3.2 Topography 3-3
3.3 Drainage 3-5
3.4 Land use Pattern 3-6
3.5 Geology 3-10
3.6 Water Environment 3-13
3.6.1 Ground Water Conditions 3-13
3.6.2 Project Site Area 3-14
3.6.3 Climate and Rainfall 3-14
3.6.4 Water-shed and Neighborhood Areas 3-15
3.6.5 Field study and discussion 3-17
3.7 Ground Water Resources Potentials 3-19
3.8 Ground Water Quality 3-21
3.9 Surface Water Quality 3-26
3.10 Soils Environment 3-31
3.11 Air Environment 3-36
3.11.1 Meteorology 3-36
3.11.2 Meteorological Station at Industry Site 3-39
3.11.3 Ambient Air Quality 3-42
3.11.4 Scope of Field Study 3-42
3.11.5 Description of Sampling Locations 3-43
3.11.6 Pre-project Ambient Air Quality Status 3-44
3.11.7 Noise Environment 3-51
3.12 Socio Economic Environment 3-55
3.12.1 Objectives of socio economic study 3-55
3.12.2 Desk Research 3-56
3.12.3 Geographical Coverage 3-57
3.12.4 Impact Zones 3-58
3.12.5 Sampled house holds 3-59
3.12.6 Field Surveys 3-61
3.12.7 Data Analysis 3-63
3.12.7.1 Demographics 3-63
3.12.7.2 Assets Owned 3-64
3.12.7.3 Sources of Livelihood 3-64
3.12.7.4 Family Income 3-64
3.12.7.5 Family Expenditures 3-65
3.12.7.6 Living Standards 3-65
3.12.7.7 Educational Facilities 3-65
3.12.8 Health Status 3-67
3.12.8.1 Health Status of Surveyed Villages 3-71
3.12.9 Physical Infrastructure 3-71
3.12.10 Social Infrastructure 3-71
3.12.11 Archaeological Monuments 3-71
3.12.12 Defense and scientific establishments 3-72
3.12.13 Aspirations and Apprehensions 3-72
3.13 Biotic environment 3-72
3.13.2 Methodology 3-73
3.13.3 Floral study 3-74
3.13.4 Faunal study 3-75
3.13.4.1 Rational for Survey Method 3-75
3.13.4.3 Secondary data 3-76
3.13.5 Present Status of biotic environment 3-76
3.13.6 Ecology at project site 3-77
3.13.6.1 Ecology of core Zone Habitat 3-77
3.13.6.2 Ecology of Buffer Zone Habitat 3-78
3.13.6.3` Quantitative analysis 3-80
3.13.7 Fauna within the Core and buffer zones 3-84
3.14 Aquatic ecosystem 3-84
Chapter-4.0 Identification & Prediction of Impacts
4.1 Identification of impacts 4-1
4.2 Impact Networks 4-1
4.2.1 Air Environment 4-2
4.2.2 Water Environment 4-2
4.2.3 Noise Environment 4-2
4.2.4 Land Environment 4-2
4.2.5 Biological Environment 4-3
4.2.6 Socio-economic Environment 4-3
4.3 Prediction of Impact on Air Quality 4-10
4.3.1 Details of Mathematical Modeling 4-10
4.3.1.1 Model Formulation 4-11
4.3.1.2 Metrological Data 4-12
4.3.2 Plant Emissions 4-13
4.3.2.1 Air Quality Predictions 4-15
4.4 Prediction of Impacts on the Noise Environment 4-22
4.5 Prediction of Impacts on water Environment 4-24
4.6 Prediction of Impacts on Soil 4-26
4.7 Impacts on Socio-Economic Environment 4-26
4.8 Prediction of Impact on Local flora and fauna 4-29
4.8.1 Ecological factors and their impacts due to 4-30
proposed activity
4.8.2 Impacts identified 4-30
4.8.2.1 The direct impacts 4-31
4.8.2.3 Indirect Impacts 4-31
4.8.3 Mitigation Measures 4-31
4.9 Positive impacts on Ecological aspects 4-32
4.9.1 Anticipated general impacts due to steel industry on flora and fauna 4-33
4.9.2 Mitigation Measures for Habitat specific alternations 4-33
4.9.3 Impacts on traffic 4-34
4.11 Prediction of Impact vehicular traffic 4-34
4.10 Overall Environmental Impacts and mitigation measures of the project 4-35
Chapter 5.0 Analysis of Alternative Sites & Technologies
5.1 Proposed Project 5-1
5.2 Alternative Sites 5-1
5.3 Alternative Technologies 5-2
Chapter 6.0 Post Environmental Monitoring
6.1 Introduction 6-1
6.2 Objectives 6-1
6.3 Methodology 6-2
6.4 Ambient air quality (AAQ) Monitoring 6-2
6.5 Water Quality Monitoring 6-5
6.6 Noise Level Monitoring 6-10
6.7 Environmental Monitoring plan 6-11
6.8 Responsibility of Monitoring and Reporting System 6-15
6.9 Environmental Monitoring Budget 6-15
Chapter 7.0 Occupational health, Risk Assessment & Disaster Management
Plan
7.1 Risk Assessment 7-1
7.1.1 Hazards Relating to Foundaries 7-1
7.1.2.1 Induction Furnance 7-1
7.1.2.2 Hot Bilets transfer from Unit III for Rolling operations 7-3
7.1.2.3 Hot Metal transfer from Unit I to Unit Iii 7-3
7.1.2.4 Rolling Mills 7-3
7.1.2.5 Consequential fires outside the premises 7-4
7.2 Risk Mitigation measures 7-4
7.3 Fire Protection System 7-5
7.4 House keeping 7-7
7.5 Occupational Safety and Health 7-7
7.5.1 Health Surveillance Plan 7-9
7.5.2 First Aid Center 7-10
7.5.3 Tie up with Local Hospitals 7-10
7.6 Disaster Management Plan 7-11
7.7 Disaster Management Plan 7-11
7.8 On-Site Emergency Plan 7-12
7.8.1 Action Plan 7-12
7.8.2 Key Personnel 7-13
7.8.3 Emergency Equipment/facilities 7-15
7.8.4 Emergency Control Centre 7-16
7.8.4 Assembly Point 7-16
7.8.5 Emergency Management Training 7-16
7.8.6 Mock Drills 7-17
7.8.7 Incident recording and revision of Disaster Management Plan 7-17
7.9 Off site Emergency Plan 7-18
Chapter 8.0 Project Benefits
8.1 Employment Opportunity 8-1
8.2 Likely Indirect employment Opportunities 8-1
8.3 Environmental Social Responsibility (ESR) & Socio-Economic Development 8-2
8.4 Direct Revenue Earning to the National and State Exchequer 8-2
8.5 Other tangible benefits 8-3
Chapter-9.0 Environment Cost benefit Analysis 9-1
Chapter-10 Environmental Management Plan
10.1 Introduction 10-1
10.2 The Project Location 10-2
10.3 Site Sensitivity 10-2
10.4 Major Findings of the EIA 10-3
10.4.1 Impact on Physical Resources 10-3
10.4.2 Impact on air quality 10-3
10.4.2.1 Measures for fugitive emission control 10-4
10.4.3 Impact on water resources 10-4
10.4.3.1 Pollution Control Measure 10-5
10.4.3.2 Water Conservation Measures 10-5
10.5 Rain water harvesting and recharge methods 10-5
10.5.1 Ground Water Recharge Requirements’-Site conditions 10-7
10.5.2 Ground water Exploration 10-6
10.5.3 Rain Water Harvesting Plans 10-6
10.5.3.1 Open areas over-land Flow 10-6
10.5.3.2 Roof top rain Water Collection 10-7
10.5.3.3 Road top/Paved area rain Water Collection 10-7
10.5.4 Ground Water Recharge Structures 10-7
10.5.4.1 Project Site 10-7
10.6 Impact on Soil 10-8
10.7 Impact on Land use 10-8
10.8 Impact on Noise Quality 10-9
10.9 Impact on Flora 10-9
10.10 Impact on Fauna 10-9
10.11 Impact on Road Network 10-10
10.12 Impact on Power Distribution 10-10
10.13 Environmental Management Measures Proposed 10-10
10.14 Green Belt Development 10-20
10.15 Environmental Management Cell 10-25
10.16 Reporting system & Monitoring System 10-26
10-17 Corporate Environmental Responsibility 10-26
10-18 Environmental Management Budget 10-27
Chapter – 11- Project Summary and Conclusions
Chapter – 13 Disclosure of Consultants
LIST OF TABLES
TABLE NO. DESCRIPTION PAGE NO.
Table 1.1 Production Capacity- Current & Proposed 1-6
Table 1.2 Salient Features of the Site 1-7
Table 1.3 Cost for the Proposed expansion 1-8
Table 1.4 Applicable statutory clearance for the site 1-14
Table 2.1 Current & proposed installations & products 2-1
Table 2.2 Salient feature of the project 2-2
Table 2.3 Proposed production capacities (TPA) 2-13
Table 2.4 List of raw material and Requirement after expansion
2-23
Table 2.5 Details of man power requirement 2-25
Table 2.6 Water requirement for present & proposed plant capacity
2-25
Table 2.7 Land statement 2-26
Table 2.8 Water balance for present & proposed plant capacity
2-29
Table 2.9 Air emission sources & control 2-30
Table 2.10 Solid waste generation disposal 2-31
Table 2.11 Hazardous wastes with recycling option: 2-32
Table 2.12 Current scenario and suggested improvements 2-33
Table 3.1 Land use/land cover classes in study area 3-9
Table 3.2 Annual & Seasonal Rainfall, Departure from Mean Percentage
3-15
Table 3.3 Salient features of ground water conditions in the project area
3-19
Table 3.4 Ground water Resource estimations 3-20
Table3.5. Summarized Chemical analysis of Ground Water 3-23
Table 3.6 Summarized Chemical analysis of Surface Water 3-29
Table 3.7 Analytical data of soil samples 3-34
Table 3.8 Soil test results – reference tables 3-35
Table 3.9 Frequency Distribution of wind speeds and wind directions
3-40
Table 3.10 Locations of ambient air quality monitoring stations 3-43
Table 3.11 Ambient air quality status 3-48
Table 3.12 Noise monitoring location 3-51
Table 3.13 Effects on human beings at different noise levels 3-53
Table 3.14 Equivalent noise levels in the study area 3-54
Table 3.15 Ambient noise standards 3-55
Table – 3.16 Salient features of demographics in study area 3-57
Table 3.17 Important demographic features of impact zones
3-58
Table 3.18 Sample Villages Selected for Socio-Economic Impact Assessment
3-59
Table 3.19 Ownership of Assets by Sample Households 3-66
Table – 3.20 Category of Educational Intuitional Details in Mandal wise
3-59
Table-3.21 Status of health indicators 3-68
Table 3.22 Estimated birth rate, death rate and infant mortality rate of Telangana state
3-69
Table 3.23 Disease patterns observed in sampled villages 3-71
Table 3.24 Phytosociological data of study area 3-81
Table 3.25 Biodiversity Indices values of the sampling sites in buffer 3-83
Table 4.1 Salient features of the iscst3 model 4-11
Table 4.2 Atmospheric stability classification 4-12
Table 4.3 Mixing heights considered for computations 4-13
Table 4.4 Emission details of pollutants from stack 4-14
Table 4.5 Maximum predicted 24 hourly glc’s 4-15
Table 4.6 Predicted glc’s at monitoring locations 4-16
Table 4.7 Cumulative concentrations at various villages 4-17
Table 4.8 Average typical noise levels from existing industrial units
4-23
Table 4.9
Ground water resources of chinnasankarampet mandal, medak district, telangana.
4-25
Table 4.10 Socio economic impacts of the project 4-27
Table 4.11 Environmental impacts and their significance levels 4-35
Table 6.1 National ambient air quality standards 6-3
Table 6.2 Indian standard drinking water specifications – is: 10500:1991
6-5
Table 6.3 Noise standards 6-10
Table 6.4 Environmental monitoring plan 6-11
Table 6.5 Estimated environmental monitoring budget 6-16
Table 7.1 List of Existing fire Extinguishers 7-6
Table 7.2 List of personal protective equipment 7-6
Table 7.3 Occupational hazards and mitigation plan Physical Hazards
7-7
Table 7.4 List of Personnel Protective Equipment 7-9
Table 7.5 Rolls and Responsibilities of key personel Identified by M/s.Devashree Ispat pvt ltd Unit-I
7-13
Table 10.1 Environmental impacts and mitigation measures 10-11
Table 10.2 List of Trees recommended for Green Belt 10-22
Table 10.3 List of Ornamental herbs and shrubs within the greenbeltarea (recommended for aesthetic value):
10-23
Table 10.4 Avenue plantation for Road side and pond side (recommended)
10-24
Table 10.5 Proposed financial Budget for the Green belt development (Rs. in Lakhs)
10-24
Table 10.6 Budget for CER Activities 10-26
Table 10.7 Environmental Budgets for Project 10-27
LIST OF FIGURES
FIGURE
NO.
DESCRIPTION PAGE NO.
Fig.2.1 Location map of the project 2-6
Fig 2.2 Topo map of project site & study area 2-7
Fig 2.3 Base map of the project site & study area 2-8
Fig 2.4 Google map of the site 2-9
Fig 2.5 Plant Layout 2-10
Fig 2.6 Photographs of existing plant & surroundings 2-11
Fig 2.7 Existing Green Belt in the Plant 2-12
Fig 2.8 Process Flow Shart 2-21
Fig 3.1 Google map showing the project area and its surroundings
3-5
Fig 3.2 Topomsp showing drainage distribution and water shed of the study area
3-6
Fig 3.3 Satellite image of the study area 3-7
Fig 3.4 Land use and land cover map of the study area 3-8
Fig 3.5 Pie diagram showing land use & land cover area
3-9
Fig 3.6 Areal Distribution of the Rock Formations 3-12
Fig 3.7. Location of wells inventoried Google Map 3-17
Fig 3.8. Topography and Drainage of the Project Site Neighborhood
3-16
Fig 3.9. Location of wells inventoried- On google Map 3-18
Fig 3.10 Ground water sampling locations in the Study area
3-22
Fig 3.11 Locations of surface water samples in the study ares
3-28
Fig3.12 Soil Sampling Locations 3-33
Fig 3.13 IMD data of meteorological station Hyderabad(1971-2000)
3-37
Fig 3.14 Wind rose Diagram for the study December-2017 to February 2018
3-41
Fig 3.15 Location map of Ambient Air Quality Monitoring Stations
3-50
Fig 3.16 Location Map for Noise Monitoring Stations 3-52
Fig 3.17 Google Map of Sampling Villages 3-61
Fig 3.18 The habit wise and ecosystem wise status of various floral species observed
3-81
Fig 3.19 Graph showing Important Value Indec of dominant tree species within study are
3-82
Fig 4.1 Impacts network for air environment 4-4
Fig 4.2 Impacts network for noise environment 4-5
Fig 4.3 Impacts network for land environment 4-6
Fig 4.4 Impacts network for biological flora & fauna 4-7
Fig 4.5 Identification of likely impacts of waste water 4-8
Fig 4.6 Impacts network for socio economic & cultural environment
4-9
Fig 4.7 Isopleths showing 24 hourly glc’s of pm10 4-18
Fig 4.8 Isopleths showing 24 hourly glc’s of pm2.5 4-19
Fig 4.9 Isopleths showing 24 hourly glc’s of so2 4-20
Fig 4.10 Isopleths showing 24 hourly glc’s of nox 4-21
Fig 10.1 Rainfall Harvesting Pond exsting in the plant 10-8
Fig 10.2 Organization Chart for Environmetal Management
10-25
LIST OF ANNEXURES
ANNEXURE DESCRIPTION NO.
1 Ambient Air Quality Data
2 Demographic features of the villages in the area
3 List of the faunal species in the study area
4 Combined Layout
95
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR
PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
3(a ):STANDARD TERMS OF REFERENCE FOR CONDUCTING
ENVIRONMENT IMPACT ASSESSMENT STUDY FOR
METALLURGICAL INDUSTRIES (FERROUS & NON FERROUS)
PROJECTS AND INFORMATION TO BE INCLUDED IN EIA/EMP
REPORT
A. STANDARD TERMS OF REFERENCE (TOR)
1) Executive Summary
2) Introduction
i. Details of the EIA Consultant including NABET accreditation
ii. Information about the project proponent
iii. Importance and benefits of the project
3) Project Descr iption
i. Cost of project and time of completion.
ii. Products with capacities for the proposed project.
iii. If expansion project, details of existing products with capacities and whether adequate land
is available for expansion, reference of earlier EC if any.
iv. List of raw materials required and their source along with mode of transportation.
v. Other chemicals and materials required with quantities and storage capacities
vi. Details of Emission, effluents, hazardous waste generation and their management.
vii. Requirement of water, power, with source of supply, status of approval, water balance diagram,
man-power requirement (regular and contract)
viii. Process description along with major equipments and machineries, process flow sheet
(quantative) from raw material to products to be provided
ix. Hazard identification and details of proposed safety systems.
x. Expansion/modernization proposals:
a. Copy of all the Environmental Clearance(s) including Amendments thereto obtained for
the project from MOEF/SEIAA shall be attached as an Annexure. A certified copy of the
latest Monitoring Report of the Regional Office of the Ministry of Environment and Forests
as per circular dated 30th May, 2012 on the status of compliance of conditions stipulated
in all the existing environmental clearances including Amendments shall be provided. In
addition, status of compliance of Consent to Operate for the ongoing Iexisting operation
of the project from SPCB shall be attached with the EIA-EMP report.
96
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/
ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
b. In case the existing project has not obtained environmental clearance, reasons for not
taking EC under the provisions of the EIA Notification 1994 and/or EIA Notification
2006 shall be provided. Copies of Consent to Establish/No Objection Certificate and
Consent to Operate (in case of units operating prior to EIA Notification 2006, CTE and
CTO of FY 2005-2006) obtained from the SPCB shall be submitted. Further, compliance
report to the conditions of consents from the SPCB shall be submitted.
4) Site Details
i. Location of the project site covering village, Taluka/Tehsil, District and State, Justification
for selecting the site, whether other sites were considered.
ii. A toposheet of the study area of radius of 10km and site location on 1:50,000/1:25,000 scale
on an A3/A2 sheet. (including all eco-sensitive areas and environmentally sensitive places)
iii. Details w.r.t. option analysis for selection of site
iv. Co-ordinates (lat-long) of all four corners of the site.
v. Google map-Earth downloaded of the project site.
vi. Layout maps indicating existing unit as well as proposed unit indicating storage area, plant
area, greenbelt area, utilities etc. If located within an Industrial area/Estate/Complex, layout
of Industrial Area indicating location of unit within the Industrial area/Estate.
vii. Photographs of the proposed and existing (if applicable) plant site. If existing, show
photographs of plantation/greenbelt, in particular.
viii. Landuse break-up of total land of the project site (identified and acquired), government/
private - agricultural, forest, wasteland, water bodies, settlements, etc shall be included. (not
required for industrial area)
ix. A list of major industries with name and type within study area (10km radius) shall be
incorporated. Land use details of the study area
x. Geological features and Geo-hydrological status of the study area shall be included.
xi. Details of Drainage of the project upto 5km radius of study area. If the site is within 1 km
radius of any major river, peak and lean season river discharge as well as flood occurrence
frequency based on peak rainfall data of the past 30 years. Details of Flood Level of the
project site and maximum Flood Level of the river shall also be provided. (mega green field
projects)
xii. Status of acquisition of land. If acquisition is not complete, stage of the acquisition process
and expected time of complete possession of the land.
xiii. R&R details in respect of land in line with state Government policy
5) Forest and wildlife related issues (if applicable):
i. Permission and approval for the use of forest land (forestry clearance), if any, and
recommendations of the State Forest Department. (if applicable)
ii. Landuse map based on High resolution satellite imagery (GPS) of the proposed site delineating
the forestland (in case of projects involving forest land more than 40 ha)
97
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR
PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
iii. Status of Application submitted for obtaining the stage I forestry clearance along with latest
status shall be submitted.
iv. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves,
Migratory Corridors of Wild Animals, the project proponent shall submit the map duly
authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location
and the recommendations or comments of the Chief Wildlife Warden-thereon
v. Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the State
Government for conservation of Schedule I fauna, if any exists in the study area
vi. Copy of application submitted for clearance under the Wildlife (Protection) Act, 1972, to the
Standing Committee of the National Board for Wildlife
6) Environmental Status
i. Determination of atmospheric inversion level at the project site and site-specific micro-
meteorological data using temperature, relative humidity, hourly wind speed and direction
and rainfall.
ii. AAQ data (except monsoon) at 8 locations for PM10, PM2.5, SO2, NOX, CO and other
parameters relevant to the project shall be collected. The monitoring stations shall be based
CPCB guidelines and take into account the pre-dominant wind direction, population zone
and sensitive receptors including reserved forests.
iii. Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given in the
NAQQM Notification of Nov. 2009 along with - min., max., average and 98% values for
each of the AAQ parameters from data of all AAQ stations should be provided as an annexure
to the EIA Report.
iv. Surface water quality of nearby River (100m upstream and downstream of discharge point)
and other surface drains at eight locations as per CPCB/MoEF&CC guidelines.
v. Whether the site falls near to polluted stretch of river identified by the CPCB/MoEF&CC, if
yes give details.
vi. Ground water monitoring at minimum at 8 locations shall be included.
vii. Noise levels monitoring at 8 locations within the study area.
viii. Soil Characteristic as per CPCB guidelines.
ix. Traffic study of the area, type of vehicles, frequency of vehicles for transportation of materials,
additional traffic due to proposed project, parking arrangement etc.
x. Detailed description of flora and fauna (terrestrial and aquatic) existing in the study area
shall be given with special reference to rare, endemic and endangered species. If Schedule-
I fauna are found within the study area, a Wildlife Conservation Plan shall be prepared and
furnished.
xi. Socio-economic status of the study area.
98
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/
ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
7) Impact and Environment Management Plan
i. Assessment of ground level concentration of pollutants from the stack emission based on
site-specific meteorological features. In case the project is located on a hilly terrain, the
AQIP Modelling shall be done using inputs of the specific terrain characteristics for
determining the potential impacts of the project on the AAQ. Cumulative impact of all sources
of emissions (including transportation) on the AAQ of the area shall be assessed. Details of
the model used and the input data used for modelling shall also be provided. The air quality
contours shall be plotted on a location map showing the location of project site, habitation
nearby, sensitive receptors, if any.
ii. Water Quality modelling - in case of discharge in water body
iii. Impact of the transport of the raw materials and end products on the surrounding environment
shall be assessed and provided. In this regard, options for transport of raw materials and
finished products and wastes (large quantities) by rail or rail-cum road transport or conveyor-
cum-rail transport shall be examined.
iv. A note on treatment of wastewater from different plant operations, extent recycled and reused
for different purposes shall be included. Complete scheme of effluent treatment. Characteristics
of untreated and treated effluent to meet the prescribed standards of discharge under E(P)
Rules.
v. Details of stack emission and action plan for control of emissions to meet standards.
vi. Measures for fugitive emission control
vii. Details of hazardous waste generation and their storage, utilization and management. Copies
of MOU regarding utilization of solid and hazardous waste in cement plant shall also be
included. EMP shall include the concept of waste-minimization, recycle/reuse/recover
techniques, Energy conservation, and natural resource conservation.
viii. Proper utilization of fly ash shall be ensured as per Fly Ash Notification, 2009. A detailed
plan of action shall be provided.
ix. Action plan for the green belt development plan in 33 % area i.e. land with not less than
1,500 trees per ha. Giving details of species, width of plantation, planning schedule etc. shall
be included. The green belt shall be around the project boundary and a scheme for greening
of the roads used for the project shall also be incorporated.
x. Action plan for rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground water and also to
use for the various activities at the project site to conserve fresh water and reduce the water
requirement from other sources.
xi. Total capital cost and recurring cost/annum for environmental pollution control measures
shall be included.
xii. Action plan for post-project environmental monitoring shall be submitted.
99
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR
PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
xiii. Onsite and Offsite Disaster (natural and Man-made) Preparedness and Emergency
Management Plan including Risk Assessment and damage control. Disaster management
plan should be linked with District Disaster Management Plan.
8) Occupational health
i. Plan and fund allocation to ensure the occupational health & safety of all contract and casual
workers
ii. Details of exposure specific health status evaluation of worker. If the workers' health is being
evaluated by pre designed format, chest x rays, Audiometry, Spirometry, Vision testing (Far
& Near vision, colour vision and any other ocular defect) ECG, during pre placement and
periodical examinations give the details of the same. Details regarding last month analyzed
data of above mentioned parameters as per age, sex, duration of exposure and department
wise.
iii. Details of existing Occupational & Safety Hazards. What are the exposure levels of hazards
and whether they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of the workers
can be preserved,
iv. Annual report of heath status of workers with special reference to Occupational Health and
Safety.
9) Corporate Environment Policy
i. Does the company have a well laid down Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA report.
ii. Does the Environment Policy prescribe for standard operating process / procedures to bring
into focus any infringement / deviation / violation of the environmental or forest norms /
conditions? If so, it may be detailed in the EIA.
iii. What is the hierarchical system or Administrative order of the company to deal with the
environmental issues and for ensuring compliance with the environmental clearance
conditions? Details of this system may be given.
iv. Does the company have system of reporting of non compliances / violations of environmental
norms to the Board of Directors of the company and / or shareholders or stakeholders at
large? This reporting mechanism shall be detailed in the EIA report
10) Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be provided to the
labour force during construction as well as to the casual workers including truck drivers during
operation phase.
11) Enterprise Social Commitment (ESC)
i. Adequate funds (at least 2.5 % of the project cost) shall be earmarked towards the Enterprise
Social Commitment based on Public Hearing issues and item-wise details along with time
100
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR PROJECTS/
ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
bound action plan shall be included. Socio-economic development activities need to be elaborated
upon.
12) Any litigation pending against the project and/or any direction/order passed by any Court of Law
against the project, if so, details thereof shall also be included. Has the unit received any notice
under the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air and Water
Acts? If so, details thereof and compliance/ATR to the notice(s) and present status of the case.
13) A tabular chart with index for point wise compliance of above TOR.
B. SPECIFIC TERMS OF REFERENCE FOR EIA STUDIES FOR
METALLURGICAL INDUSTRIES (FERROUS & NON FERROUS)
1) Complete process flow diagram describing each unit, its processes and operations, along with material
and energy inputs & outputs (material and energy balance).
2) Details on blast furnace/ open hearth furnace/ basic oxygen furnace/ladle refining, casting and
rolling plants etc.
3) Details on installation/activation of opacity meters with recording with proper calibration system
4) Details on toxic metals including mercury, arsenic and fluoride emissions
5) Details on stack height requirement for integrated steel
6) Details on ash disposal and management -Non-ferrous metal
7) Complete process flow diagram describing production of lead/zinc/copper/ aluminium, etc.
8) Raw materials substitution or elimination
9) Details on smelting, thermal refining, melting, slag fuming, and Waelz kiln operation
10) Details on Holding and de-gassing of molten metal from primary and secondary aluminum, materials
pre-treatment, and from melting and smelting of secondary aluminium
11) Details on solvent recycling
12) Details on precious metals recovery
13) Details on composition, generation and utilization of waste/fuel gases from coke oven plant and
their utilization.
14) Details on toxic metal content in the waste material and its composition and end use (particularly of
slag).
15) Trace metals Mercury, arsenic and fluoride emissions in the raw material.
16) Trace metals in waste material especially slag.
17) Plan for trace metal recovery
18) Trace metals in water
101
STANDARD TERMS OF REFERENCE (TOR) FOR EIA/EMP REPORT FOR
PROJECTS/ACTIVITIES REQUIRING ENVIRONMENT CLEARANCE
C. ADDITIONAL TOR FOR INTEGRATED STEEL PLANT
1). Iron ore/coal linkage documents along with the status of environmental clearance of iron ore and
coal mines
2). Quantum of production of coal and iron ore from coal & iron ore mines and the projects they cater
to. Mode of transportation to the plant and its impact
3). For Large ISPs, a 3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. MRL details of project site and RL of nearby sources of water shall be indicated.
4). Recent land-use map based on satellite imagery. High-resolution satellite image data having 1m-5m
spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area from
proposed site. The same shall be used for land used/land-cover mapping of the area.
5). Respirable Suspended particulate matter (RSPM) present in the ambient air must be analysed for
source analysis - natural dust/RSPM generated from plant operations (trace elements). The RSPM
shall also be analysed for presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction, where applicable. Chemical characterization of RSPM and incorporating of RSPM data.
6). All stock piles will have to be on top of a stable liner to avoid leaching of materials to ground water.
7). Plan for the implementation of the recommendations made for the steel plants in the CREP guidelines.
8). Plan for slag utilization
9). Plan for utilization of energy in off gases (coke oven, blast furnace)
10). System of coke quenching adopted with justification.
***
Standard Terms of reference for Conducting Environmental Impact
Assessment Study for Secondary Metallurgical Industries
S.No TOR Point Compliance
1 Executive Summary Included in EIA report. 2 Introduction Included in chapter 1 of
EIA report - Page No.1-14 i Details of the EIA Consultant including
NABET accreditation Included in chapter 12 of EIA Report
Ii Information about the project proponent Included in chapter 1 of EIA report -Section 1.2, Page No.1-2
iii Importance and benefits of the project Included in chapter 8 of EIA report
3 Project Description Included in chapter 2 of EIA report
i Cost of project and time of completion Included in chapter 1 of EIA report - Section 1.7, Page No.1-7
ii Products with capacities for the proposed project
Included in chapter 2 of EIA report - Table No 2.1 Page No.2-1
iii If expansion project, details of existing products with capacities and whether adequate land is available for expansion, reference of earlier EC if any
Included in chapter 2 of EIA report –Section 2.1, page 2-1
iv List of raw materials required and their source along with mode of transportation
Included in chapter 2 of EIA report –Section 2.7.1, Page No.2-23
v Other chemicals and materials required with quantities and storage capacities
NA
vi Details of Emission, effluents, hazardous waste generation and their management
Presented in Chapter 2 of EIA, Section 2.9.1, Page No.2-28
vii Requirement of water, power, with source of supply, status of approval, water balance diagram, man-power requirement (regular and contract)
Presented in Chapter 2 of EIA report
viii Process description along with major equipments and machineries, process flow sheet (quantitative) from raw material to products to be provided
Presented in Chapter 2, section 2.6, page no.2-14
ix Hazard identification and details of Presented in Chapter 7 of
proposed safety systems EIA report x Expansion/modernization
proposals:
a Copy of all the Environmental Clearance(s) including Amendments thereto obtained for the project from MOEF/SEIAA shall be attached as an Annexure. A certified copy of the latest Monitoring Report of the Regional Office of the Ministry of Environment and Forests as per circular dated 30th May, 2012 on the status of compliance of conditions stipulated in all the existing environmental clearances including Amendments shall be provided. In addition, status of compliance of Consent to Operate for the ongoing existing operation of the project from SPCB shall be attached with the EIA-EMP report.
The unit obtained CFE and CFO of the Board and started operations.
b In case the existing project has not obtained environmental clearance, reasons for not taking EC under the provisions of the EIA Notification 1994 and/or EIA Notification 2006 shall be provided. Copies of Consent to Establish/No Objection Certificate and Consent to Operate (in case of units operating prior to EIA Notification 2006, CTE and CTO of FY 2005-2006) obtained from the SPCB shall be submitted. Further, compliance report to the conditions of consents from the SPCB shall be submitted
Included in chapter 1 of EIA report
4 Site Details i Location of the project site covering
village, Taluka/Tehsil, District and State, Justification for selecting the site, whether other sites were considered
Included in chapter 2 of EIA report -Section 2.3,
ii A Topo sheet of the study area of radius of 10km and site location on 1:50,000/1:25,000 scale on an A3/A2 sheet. (including all eco-sensitive areas
Included in chapter 2 of EIA report –Figure 2.1,
and environmentally sensitive places) iii Details w.r.t. option analysis for
selection of site This is an existing unit going for expansion
iv Co-ordinates (lat-long) of all four corners of the site
Included in chapter 2 of EIA Section 2.3
v Google map-Earth downloaded of the project site
Included in chapter 2 of EIA report –Figure 2.4
vi Layout maps indicating existing unit as well as proposed unit indicating storage area, plant area, greenbelt area, utilities etc. If located within an Industrial area/Estate/Complex, layout of Industrial Area indicating location of unit within the Industrial area/Estate
Included in chapter 2 of EIA report –Page 2-10
vii Photographs of the proposed and existing (if applicable) plant site. If existing, show photographs of plantation/greenbelt, in particular
Included in chapter 2 of EIA, Figure 2.6, page No.2-11
viii Land use break-up of total land of the project site (identified and acquired), government/ private - agricultural, forest, wasteland, water bodies, settlements, etc shall be included. (not required for industrial area)
Included in chapter 3 of EIA report –Section 3.4, Page 3-6 to 3-9 in table No.3.1
ix A list of major industries with name and type within study area (10km radius) shall be incorporated. Land use details of the study area
Included in chapter 3 of EIA report – Page 3-3
x Geological features and Geo-hydrological status of the study area shall be included
Included in chapter 3 of EIA report –Section 3.3, Page 3-5
xi Details of Drainage of the project up to 5km radius of study area. If the site is within 1 km radius of any major river, peak and lean season river discharge as well as flood occurrence frequency based on peak rainfall data of the past 30 years. Details of Flood Level of the project site and maximum Flood Level of the river shall also be provided. (mega green field projects)
Included in chapter 3 of EIA report –Figure 3.2, Page 3-6
xii Status of acquisition of land. If acquisition is not complete, stage of the acquisition process and expected time
Land is owned by the company
of complete possession of the land xiii R&R details in respect of land in line
with state Government policy Land is owned by the company
5 Forest and wildlife related issues (if applicable):
i Permission and approval for the use of forest land (forestry clearance), if any, and recommendations of the State Forest Department. (if applicable)
There is no involvement of forest land
ii Land use map based on High resolution satellite imagery (GPS) of the proposed site delineating the forestland (in case of projects involving forest land more than 40 ha)
Included in chapter 3 of EIA report –Figure 3.4, Page 3-8
Status of Application submitted for obtaining the stage I forestry clearance along with latest status shall be submitted
There is no involvement of forest land
The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden-thereon
Not applicable
Wildlife Conservation Plan duly authenticated by the Chief Wildlife Warden of the State Government for conservation of Schedule I fauna, if any exists in the study area
Not applicable
Copy of application submitted for clearance under the Wildlife (Protection) Act, 1972, to the Standing Committee of the National Board for Wildlife
Not applicable
6 Environmental Status i Determination of atmospheric inversion
level at the project site and site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall
Presented in chapter 3 section 3.11.1
ii AAQ data (except monsoon) at 8 locations for PM10, PM2.5, S02, NOX, CO and other parameters relevant to the project shall be collected. The monitoring stations shall be based CPCB guidelines and take into account the pre-dominant wind direction, population zone and sensitive receptors including reserved forests
Presented in chapter 3 section 3.11.5 Table – 3.9
iii Raw data of all AAQ measurement for 12 weeks of all stations as per frequency given in the NAQQM Notification of Nov. 2009 along with - min., max., average and 98% values for each of the AAQ parameters from data of all AAQ stations should be provided as an annexure to the EIA Report
Included in chapter 3 of EIA report
iv Surface water quality of nearby River (100m upstream and downstream of discharge point) and other surface drains at eight locations as per CPCB/MoEF&CC guidelines.
Included in chapter 3 of EIA report –Section 3.9
v Whether the site falls near to polluted stretch of river identified by the CPCB/MoEF&CC, if yes give details
Nil
vi Ground water monitoring at minimum at 8 locations shall be included
Included in chapter 3 of EIA report –Section 3.8
vii Noise levels monitoring at 8 locations within the study area
Included in chapter 3 of EIA report –Section 3.12
viii Soil Characteristic as per CPCB guidelines
Included in chapter 3 of EIA report –Section 3.10
ix Traffic study of the area, type of vehicles, frequency of vehicles for transportation of materials, additional traffic due to proposed project, parking arrangement etc
Included in chapter 4 of EIA report –Section 4.10
x Detailed description of flora and fauna (terrestrial and aquatic) existing in the study area shall be given with special reference to rare, endemic and endangered species. If Schedule-I fauna are found within the study area, a Wildlife Conservation Plan shall be prepared and furnished
Included in chapter 3 of EIA report –Section 3.13
xi Socio-economic status of the study area Included in chapter 3 of EIA report –Section 3.12, Page 3-64
7 Impact and Environment Management Plan
i Assessment of ground level concentration of pollutants from the stack emission based on site-specific meteorological features. In case the project is located on a hilly terrain, the AQIP Modelling shall be done using inputs of the specific terrain characteristics for determining the potential impacts of the project on the AAQ. Cumulative impact of all sources of emissions (including transportation) on the AAQ of the area shall be assessed. Details of the model used and the input data used for modelling shall also be provided. The air quality contours shall be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any
Included in Chapter 4 of EIA report
ii Water Quality modelling - in case of discharge in water body
Process water is recycled and domestic effluents are treated in STP
iii Impact of the transport of the raw materials and end products on the surrounding environment shall be assessed and provided. In this regard, options for transport of raw materials and finished products and wastes (large quantities) by rail or rail-cum road transport or conveyorcum-rail transport shall be examined
Included in Chapter 4 of EIA report, Section 4.10,page No. 4-42
iv A note on treatment of wastewater from different plant operations, extent recycled and reused for different purposes shall be included. Complete scheme of effluent treatment. Characteristics of untreated and treated effluent to meet the prescribed standards of discharge under E(P) Rules
Included in Chapter 2 of EIA report, table No 2.8, page no. 2-29
v Details of stack emission and action plan for control of emissions to meet standards
Included in Chapter 2 of EIA report, table No 2.9, page no.2-30
vi Measures for fugitive emission control Included in Chapter 2 of EIA report, section 2.9.3, page no.2-30
vii Details of hazardous waste generation and their storage, utilization and management. Copies of MOU regarding utilization of solid and hazardous waste in cement plant shall also be included. EMP shall include the concept of waste-minimization, recycle/reuse/recover techniques, Energy conservation, and natural resource conservation.
Included in Chapter 2 of EIA report, section 2.9.4, page no.2-31 and Table No.2.10
viii Proper utilization of fly ash shall be ensured as per Fly Ash Notification, 2009. A detailed plan of action shall be provided
Bottom ash is sold to brick manufacturers and cement plants
ix Action plan for the green belt development plan in 33 % area i.e. land with not less than 1,500 trees per ha. Giving details of species, width of plantation, planning schedule etc. shall be included. The green belt shall be around the project boundary and a scheme for greening of the roads used for the project shall also be incorporated
Included in chapter 10, Section 10.14 page 10-26
x Action plan for rainwater harvesting measures at plant site shall be submitted to harvest rainwater from the roof tops and storm water drains to recharge the ground water and also to use for the various activities at the project site to conserve fresh water and reduce the water requirement from other sources
Included in chapter 10, Section 10.5 page 10-6
xi Total capital cost and recurring cost/annum for environmental pollution control measures shall be included
Included in chapter 10, Section 10.18 page 10-33
xii Action plan for post-project environmental monitoring shall be submitted
Included in chapter 6
Onsite and Offsite Disaster (natural and Man-made) Preparedness and Emergency Management Plan including Risk Assessment and damage control. Disaster management plan should be linked with District Disaster Management Plan
Included in chapter 7
8 Occupational health Included in Chapter 7 of EIA Report, section 7.5, page 7-6
i Plan and fund allocation to ensure the occupational health & safety of all contract and casual workers
Included in Chapter 7 of EIA Report
ii Details of exposure specific health status evaluation of worker. If the workers' health is being evaluated by pre designed format, chest x rays, Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision and any other ocular defect) ECG, during pre placement and periodical examinations give the details of the same. Details regarding last month analyzed data of above mentioned parameters as per age, sex, duration of exposure and department wise
Included in Chapter 7 of EIA Report
iii Details of existing Occupational & Safety Hazards. What are the exposure levels of hazards and whether they are within Permissible Exposure level (PEL). If these are not within PEL, what measures the company has adopted to keep them within PEL so that health of the workers can be preserved
Included in chapter 7, Section 7.5, page no.7-6
iv Annual report of heath status of workers with special reference to Occupational Health and Safety
Included in chapter 7, Section 7.5, page no.7-6
9 Corporate Environment Policy i Does the company have a well laid
down Environment Policy approved by its Board of Directors? If so, it may be detailed in the EIA report
No
ii Does the Environment Policy prescribe for standard operating process /
No
procedures to bring into focus any infringement / deviation / violation of the environmental or forest norms / conditions? If so, it may be detailed in the EIA
iii What is the hierarchical system or Administrative order of the company to deal with the environmental issues and for ensuring compliance with the environmental clearance conditions? Details of this system may be given
Included in Chapter 2 of EIA report
iv Does the company have system of reporting of non compliances / violations of environmental norms to the Board of Directors of the company and / or shareholders or stakeholders at large? This reporting mechanism shall be detailed in the EIA report
Included in Chapter 2 of EIA report
10 Details regarding infrastructure facilities such as sanitation, fuel, restroom etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase
Included in Chapter 10 of EIA report
11 Enterprise Social Commitment (ESC) i Adequate funds (at least 2.5 % of the
project cost) shall be earmarked towards the Enterprise Social Commitment based on Public Hearing issues and item-wise details along with time bound action plan shall be included. Socio-economic development activities need to be elaborated upon
Included in Chapter 10 of EIA report, section 10.17, page no.10-32 to 10-33
12 Any litigation pending against the project and/or any direction/order passed by any Court of Law against the project, if so, details thereof shall also be included. Has the unit received any notice under the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air and Water Acts? If so, details thereof and compliance/ATR to the notice (s) and
No
present status of the case 13 A tabular chart with index for point wise
compliance of above TOR This check list provides the compliance with references of EIA report
SPECIFIC TERMS OF REFERENCE FOR EIA STUDIES FOR METALLURGICAL INDUSTRIES (FERROUS & NON FERROUS)
1 Complete process flow diagram
describing each unit, its processes and operations, along with material and energy inputs & outputs (material and energy balance)
Included in chapter 2 of EIA report –figure no.2.5,
2 Details on blast furnace/ open hearth furnace/ basic oxygen furnace/ladle refining, casting and rolling plants etc
Included in chapter 2 of EIA report
3 Details on installation/activation of opacity meters with recording with proper calibration system
Included in chapter 2 of EIA report
4 Details on toxic metals including mercury, arsenic and fluoride emissions
Not applicable
5 Details on stack height requirement for integrated steel
Details given in chapter 2, table no 2.9, page no 2-29
6 Details on ash disposal and management -Non-ferrous metal
Details given in chapter 2, table no 2.10, page no 2-30
7 Complete process flow diagram describing production of lead/zinc/copper/ aluminium, etc
Not applicable
8 Raw materials substitution or elimination
No
9 Details on smelting, thermal refining, melting, slag fuming, and Waelz kiln operation
Details given in chapter 2
10 Details on Holding and de-gassing of molten metal from primary and secondary aluminum, materials pre-treatment, and from melting and smelting of secondary aluminum
Not applicable
11 Details on solvent recycling Not applicable 12 Details on precious metals recovery Not applicable
13 Details on composition, generation and utilization of waste/fuel gases from coke oven plant and their utilization
Not applicable
14 Details on toxic metal content in the waste material and its composition and end use (particularly of slag)
Not applicable
15 Trace metals Mercury, arsenic and fluoride emissions in the raw material
Not applicable
16 Trace metals in waste material especially slag
Not applicable
17 Plan for trace metal recovery
Not applicable
18 Trace metals in water Not applicable
FORM I
I) Basic information
S No. Item Details
1 Name of the project/s M/s DEVASHREE ISPAT (P) Ltd Unit I
2 S. No. in the schedule 3(a) Metallurgical industries ( Ferrous & Non
ferrous)
3 Proposed capacity /area/ length/
tonnage to be
handled/command area/lease
area/ No of the well to be drilled
Induction furnace - 200 TPD /70,000 TPA
Rolling Mill - 800 TPD / 2,80,000 TPA
TMT Bars- 2,80,000 TPA
4 New/Expansion /Modernization Expansion of Existing capacities
5 Existing capacity/Area etc… Induction furnace - 100 TPD / 30,000 TPA
Rolling Mill – 300 TPD /90,000TPA
6 Category of project A or B Category ‘B’,
7 Does it attract the general
condition? If yes please specify
No
8 Does it attract the specific
condition? If yes please specify
No
9 Location:
Plot No. / Survey No. / Khasra No.
Village
Tehsil / Mandal
District
State
Sy Nos. 458,459 &460
Elliketta
Farooqnagar
Rangareddy Disrict (Formerly
Mahaboobnagar District),
Telangana
10 Nearest Railway station/Air port
along with the distance in kms
Shadnagar Railway Station 7.15 kms (SE)
11 Nearest Town, City, District
Headquarters along with distances
in kms.
Shadnagar - 6.41kms (SE)
Hyderabad - Rangareddy
12 Village Panchayats Zilla Parishad
Municipal Corporation, Local body
(complete postal Address with
telephone no. to be given
Elliketta Village
Rangareddy- Zilla Parishad Farooqnagar -
Mandal
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 1
13 Name of the applicant Sri Prakash Goenka, Managing Director
14 Registered address M/s DEVASHREE ISPAT (P) LIMITED.,
8-2-293/82, Plot No.86, Prashasan Nagar,
Road No.72 , Jubilee Hills, Hyderabad-
500096,
15 Address of the correspondence
Name
Designation /owner/partner/CEO
Address
Pin code
Telephone no
Fax no
Sri Prakash Goenka
Managing Director
8-2-293/82, Plot No.86, PrashasanNagar, Road
No.72 , Jubilee Hills, Hyderabad
500096.
040 - 23557186 & 9949135000
-
16 Details of Alternative Sites
examined if any.
Location of these sites Should be
shown on a Topo sheet.
The existing premises would be used for the
expansion project
17 Interlinked Projects No
18 Whether separate application of
interlinked projects has been
submitted
Not Applicable
19 If yes, date of submission Not Applicable
20 If no reason Not Applicable
21 Whether the proposal involves
approval / clearances under: if
yes, details of the same and their
status to be given.
(a) The Forest (conservation) Act,
1980?
(b) The Wild life (protection)Act,
1972?
(c) The C.R.Z notification, 1991?
No
No
No
No
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 2
22 Whether there is any Government
order/policy relevant/relating to
the site?
No
23 Forest land involved (Hectares) Nil
24 Whether there is any litigation
pending against the project
and/or land in which the project is
propose to be set up?
(a)Name of the court
(b)Case no.
(c) Orders/directions of the court, if
any and its relevance with the
proposed project.
No
(II) Activity
1.0 Construction, operation or decommissioning of the Project involving actions, which
will cause Physical Changes in the locality (topography, land use, changes in
water bodies, etc.).
S.No. Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
1.1 Permanent or temporary change
in land use, land cover or
topography including increase in
intensity of land use (with respect
to local land use plan)
No There is no change in land use, as the
expansion project is proposed in the
existing land used for industrial
purpose.
1.2 Clearance of existing land,
vegetation and buildings?
No Few additional buildings will be
constructed/existing buildings will be
expanded
1.3 Creation of new land uses? No No new land use will be created.
1.4 Pre-construction investigations
e.g. bore holes, soil testing?
Yes Soil bearing tests were conducted
before constructing the new buildings.
1.5 Construction works? No No new constructions are proposed.
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 3
1.6 Demolition Works? No No demolitions are proposed.
1.7 Temporary sites used for
construction works or housing of
construction works?
No Not required as labor would be
sourced from nearby areas.
1.8 Above ground buildings,
structures or earthworks including
linear structures, cut and fill or
excavations
No Few additional buildings will come up.
As site is level, no cut and fill is
required. Excavations for foundations
will be there
1.9 Underground works including
mining or tunneling?
No Not required
1.10 Reclamation Works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing
processes?
Yes MS Scrap, Sponge Iron & Cast Iron are
melted in the Induction furnace and
cast into billets in the Concast
machine, which are rolled into TMT
bars of different sizes in the Rolling mill.
1.14 Facilities for storage of goods or
materials?
Yes Yes, raw material such as MS scrap,
sponge iron and silico manganese
would be stored in the RM Yard.
Finished goods will be stored in
earmarked location
1.15 Facilities for treatment or disposal
of solid waste or liquid effluents?
Yes 7000 TPA of Slag after recovery of iron
is disposed for land filling,
4000 TPA of Mill scale generated will be
reused.
Dust collected from pollution control
systems would be sold to brick makers.
1.16 Facilities for long term housing of
operational workers?
No As the work force would be sourced
from local areas only, long term
housing of operational workers is not
required.
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 4
1.17 New road, rail or sea traffic during
construction or operation?
No Existing facilities will be used for the
proposed project.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes
and stations, ports, airports etc?
No Not Required.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No Not envisaged
1.20 New or diverted transmission lines
or pipelines?
No No diversions
1.21 Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No The proposed development will not
disturb the natural terrain of the area
and will not disturb the water courses
in any ways i.e. no drain flows through
the site.
1.22 Stream crossings? No There are no stream crossings the
proposed site.
1.23 Abstraction or transfers of water
from ground or surface waters?
Yes Fresh Water requirement (145 KLD) of
the project will be met from
Groundwater from private sources
by tankers 1.24 Changes in water bodies or the
land surface affecting drainage
or run-off?
No The expansion project will not cause
any changes to water bodies or land
surface, affecting drainage or runoff.
1.25 Transport of personnel or
materials for construction,
operation or decommissioning ?
Yes Transportation of material will be by
trucks
1.26 Long-term dismantling or
decommissioning which could
have an impact on the
environment?
No Not envisaged
1.27 Ongoing activity during
decommissioning which could
have an impact on the
No Not envisaged
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 5
environment?
1.28 Influx of people to an area in
either temporarily or permanently
No There will not be influx of other people
except the workmen and staff of the
plant
1.29 Introduction of alien species? No Not envisaged
1.30 Loss of native species or genetic
diversity?
No Not envisaged
1.31 Any other actions? No Nil
2.0 USE OF NATURAL RESOURCES for construction or operation of the Project (Such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S.No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with sources of information data
2.1 Land especially undeveloped or
agricultural land (ha)
No The existing project land is developed
as Industrial land.
2.2 Water (expected source &
competing users) Unit : KLD
Yes Fresh Water Requirement - 145 KLD for
cooling make up and other purposes
will be sourced from Groundwater
from private sources by tankers
2.3 Minerals (MT) No No natural minerals are used in
process.
2.4 Construction material – stone,
aggregates, and / soil (expected
source- MT)
No Stones, aggregate, cement, sand and
iron will be used for construction for
expansion. All are sourced locally
2.5 Forests and timber (source – MT) No Not required.
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Power Required : App. 11 MVA
Source: TSSPDCL
Back-up power: 1x250 KVA DG set for
emergency during power failures.
Proposed 1x159 KVA DG set and 1x265
KVA D G set additionally for back up
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 6
power for expansion activities
Fuel: HSD required 200 Liters/hour for
operating DG sets, will be sourced
from local traders.
2.7 Any other natural resources (use
appropriate standard units)
No Not Applicable
3.0 Use, storage, transport, handling or production of substances or materials which
could be harmful to human health or THE ENVIRONMENT or raise concerns about
actual or perceived RISKS TO HUMAN HEALTH.
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
3.1 Use of substance or materials,
which are hazardous (as per
MSIHC rules) to human health or
the environment (flora, fauna,
and water supplies)
yes Only HSD in small quantities will be
used for DG sets as back up power
3.2 Changes in occurrence of
disease or affect disease vectors
(e.g. insect or water borne
diseases)
No Not envisaged
3.3 Affect the welfare or people e.g.
by changing living conditions?
No The expansion project will provide
additional employment to 120 people.
Living condition of employed people
and families will improve
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patient’s children, the elderly etc.,
No Not envisaged.
3.5 Any other causes No --
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 7
4.0 Production of SOLID WASTES during construction or operation or decommissioning
(MT/ month)
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
4.1 Soil, overburden or mine wastes No There are no overburden or mine
waste
4.2 Municipal waste (domestic and
or commercial wastes)
Yes STP sludge will be used as manure &
Other domestic waste would be given
to recyclers
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
Yes Waste Oils – 400 LPA - Disposed to
authorized reprocessors
Used Batteries – 6 Nos./ year -
returned to manufacturers / dealers on
buy back basis.
4.4 Other industrial process wastes yes Slag from furnace – 7000 TPA
Mill waste from rolling mill – 4000 TPA
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge
from effluent treatment
Yes STP sludge -10 TPA will be used as
manure
4.7 Construction or demolition
wastes
No Few new buildings will be constructed
4.8 Redundant machinery or
equipment
No Not envisaged
4.9 Contaminated soils or other
materials
No No soil contamination is anticipated as
the proposed project is over the
existing plant premises.
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes No Tarry waste from Reheating furnace-
35.1 TPA and 1500 TPA Stack bottom
ash
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 8
5.0 Release of pollutants or any hazardous, toxic or noxious substances to AIR (Kg/hr)
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes Fossil fuel is used only in back up power
DG sets
5.2 Emissions from production
processes
Yes Main emissions are from Induction
furnace, Stand by Coal gasifier, re-
heating furnace, DG sets and fugitive
dust from raw material handling.
Bag Filters are proposed to contain
dust with outlet standards prescribed
by the state Pollution control Board
5.3 Emissions from materials handling
including storage or transport
Yes Vehicular emissions are anticipated
during operation.
5.4 Emissions from construction
activities including plant and
equipment
Yes The main emissions during the
transportation will be PM from the
loading and unloading of materials on
the site. NOX, CO & other emissions
from vehicles
5.5 Dust or odors from handling of
materials including construction
materials, sewage and waste.
yes Fugitive dust is anticipated from slag
crusher and material transportation
5.6 Emissions from incineration of
waste
No Not envisaged
5.7 Emissions from burning of waste
in open air (e.g. slash materials,
construction debris)
No Not envisaged
5.8 Emissions from any other sources No Not envisaged
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 9
6.0 Generation of Noise and Vibration, and Emissions of Light and Heat:
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
6.1 From operation of equipment
e.g. engines, ventilation plant,
crushers
Yes Noise is anticipated from operation of
equipment e.g. rolling mill & slag
crushers etc. Noise will be minimized by
adopting proper maintenance such of
equipment. However noise levels are
restricted to operational areas &
proper PPE would be recommended
for work force
DG set is acoustically enclosed to
meet noise standards prescribed
6.2 From industrials or similar
processes
Yes As above
6.3 From construction or demolition No The noise and vibrations are only
during the construction phase and
proper precautions will be taken to
ensure that the decibel levels are
below the standards and the
equipment utilized for constructions
are properly serviced and maintained
for reducing vibration and noise levels.
Construction work force will be
provided with personal protective
equipment
6.4 From blasting or piling No Not envisaged
6.5 From construction or operational
traffic.
Yes Noise levels of 70 dB (A) are
anticipated during daytime due to the
vehicular movement and construction
activities, but it will be of temporary
nature 6.6 From lighting or cooling systems No None
6.7 From any other sources No --
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 10
7.0 Risks of CONTAMINATION OF LAND OR WATER from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea :
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
7.1 From handling, storage, use or
spillage of hazardous materials
No No hazardous materials are used in
process
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and
place of discharge )
yes STP sludge would be used as manure
7.3 By deposition of pollutants
emitted to air into the land or
into water
No Not anticipated any deposition of
pollutants as adequate pollution
control equipment and stack heights
are proposed
7.4 From any other sources No --
7.5 Is there a risk of long term build
up of pollutants in the
environment from these sources?
No --
8.0 Risk of accidents during construction or operation of the Project, which could
affect human or the environment
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
8.1 From explosions, spillages, fires
etc from storage, handling, use
or production of hazardous
substances
No NO hazardous substances are used or
produced from the unit
8.2 From any other causes No Not Applicable
8.3 Could the project be affected
by natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides,
cloudburst etc)?
No The project site is located at a higher
elevation and the seismic zone for the
project area is Zone-II, which is
considered safe.
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 11
9.0 Factors which should be considered (such as consequential DEVELOPMENT) which
could lead to ENVIRONMENTAL EFFECTS or the potential for cumulative impacts with
other existing or planned activates in the locality
S. No. Information /Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible )
with sources of information data
9.1 Lead to development of
supporting. utilities, ancillary
development or development
stimulated by the project which
could have impact on the
environment e.g.:
Supporting infrastructure
(roads, power supply,
waste or waste water
treatment, etc.)
Housing development
Extractive industries
Supply industries
Other
No
No
No
No
Yes
No
As raw materials, energy, water etc
are available from domestic sources,
additional impact would be minimum.
9.2 Lead to after use of the site,
which could have impact on the
environment
No --
9.3 Set a precedent for later
developments
No --.
9.4 Have cumulative effects due to
proximity to other existing or
planned project as with similar
effects )
No -
-
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 12
(III) Environment Sensitivity
S. No. Areas Name
/
Identit
y
Aerial distances (within 15 km.)
Proposed project location boundary
1. Areas protected under
international conventions,
national or local legislation for
their ecological, landscape,
cultural or other related values
No There are no ecological sensitive
areas.
2. Areas which are important or
sensitive for ecological reasons –
Wetlands, water courses or other
water bodies, coastal zone,
biospheres. Mountains, forests
No Not applicable no ecologically
sensitive areas within 10 KM radius
3. Areas and by protected,
important or sensitive species of
flora or fauna for breeding,
nesting, foraging, resting, over
wintering, migration
No
4. Inland, coastal, marine or
underground waters
No
5. State, National boundaries No -
6. Routes or facilities used by the
public for access to recreation
or other tourist, pilgrim areas
No
7. Defense installations No
8. Densely populated or built-up
area
No
9. Areas occupied by sensitive
man-made land uses (hospitals,
schools, places of worship,
community facilities )
Yes There are few hospitals and schools in
the near by town at distance of 7.15
KM
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 13
10. Areas containing important, high
quality or scarce resources
(ground water resources, surface
resources, forestry, agriculture,
fisheries, tourism, minerals)
No
11. Areas susceptible to natural
hazard which could cause the
project to present environmental
problems (earthquakes,
subsidence, landslides, erosion,
flooding or extreme or adverse
climatic conditions)
No --
IV. Proposed Terms of Reference for
EIA Studies
(IV) Proposed Terms of Reference for EIA studies
Scope of Work of EIA
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 14
“ The EIA shall cover the following:
Description of the proposed project:
The first task:” Description of the proposed project” forms a vital component of the Environmental Impact Assessment (EIA) as it provides the basis for evaluating the likely causes of
Environmental Impacts.
Existing Environment and Baseline Conditions:
The baseline assessment will be carried out to identify potentially sensitive and critical areas that
may be affected by the project in an area of 10 km surrounding the project location. The
critical and sensitive targets shall be plotted on land use map of project impact area. The
existing environment and baseline conditions should be established from:-
Analysis of existing information published and secondary data.
-Consultation with relevant statutory authorities, and Field visits for supplementation of missing
gaps.
The key subject areas which the EIA shall address include Ecology and Nature conservation, Air
quality, surface and water quality in project impact area, soil quality, cultural heritage,
landscape, land use, noise quality, etc. Natural habitats like national parks, wildlife reserves,
sanctuaries, sacred grove, protected areas, forests, wetlands, major rivers and waterways if any,
shall also be identified and marked.
Assessment of Environmental Impacts:
Based upon the results from the review of existing information, field visits, site data collection and
consultation, for each component of environment (physical, biological and socio economic)
the positive, negative, direct and indirect, temporary and permanent impacts will be evaluated
along with an indication of the degree of impact, i.e., whether the impact is significant,
moderate, minor or negligible. The degree of impact shall also be quantified by using state of
the art air quality impact prediction models based on ISCST3 algorithms.
Environment Management Plan And Mitigation Plan:
For each significant negative impact identified, specialist shall work closely with the engineering
team/technical consultants to suggest practicable measures to avoid or mitigate the impact.
The mitigation of environmental impacts will be by three mechanisms.
=>Introduction of mitigation features through the engineering practices.
=>Implementation of environmental controls during construction and operation.
M/s. Devashree Ispat (P) Limited Unit I, Ellikatta (V)
Farooqnagar (M), Rangareddy (Dist), Telangana State
PRIDHVI ENVIROTECH (P) LIMITED Page 15
=>Legislative control involving compliance with Indian environmental laws.
The Environmental management plan shall include an estimate of capital and recurring costs of
mitigation measures and will identify the institutional framework for implementation.
Monitoring Plan:
Having identified the significant environmental impact that is likely to arise as a result of the
project, the project team shall specify what monitoring is required during the various phases of
the project cycle.
The monitoring plan will identify parameters and frequency of monitoring and responsible
organization.
All elements prescribed in standard TOR will be followed
EXECUTIVE SUMMARY
M/S DEVASHREE ISPAT (P) LTD UNIT-I
Sy. Nos.458,459 and 460
Ellikatta village,Farooq Nagar Mandal, Rangareddy District, (Formerly Mahaboobnagar District)
Telangana state
PROPOSAL FOR EXPANSION OF INDUCTION FURNACE & ROLLING MILL
For Grant of Environmental Clearance
(Category B project under 3(a) Sector) Project Cost for expansion- Rs. 5.75 Cr
Project Proponent Environmental Consultant
M/s. Devashree Ispat (P) Ltd Unit-I M/s. Pridhvi Envirotech (P) Ltd.,
Sy. Nos.458,459 and 460 Nabet Accreditation S.No. 119,
Ellikatta village,Farooq Nagar Mandal Rev 67 dated 9th July, 2018
Rangareddy District Plot No. 184/C, Lawn House,
Ph: 040-23557186 4th Floor, Vengal Rao Nagar,
Email: [email protected] Hyderabad – 500 038.
Ph: 040 – 40179770
Email: [email protected]
SUBMITTED TO
TELANGANA POLLUTION CONTROL BOARD,
REGIONAL OFFICE, RANGAREDDY
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 1 of 11 M/s. Pridhvi Envirotech (P) Limited.
EXECUTIVE SUMMARY
M/s.Devashree Ispat (P) Ltd Unit-I is situated near Ellikatta (Vil), Farooq
Nagar (M), Rangareddy District (Formerly Mahaboobnagar District),
Telangana State is manufacturing M.S.Billets and Thermo Mechanically
Treated (TMT) Bars in their plant spread over 10.62 Ac. The unit is in
operation since 2006.
The company is operating one Induction Furnace in this unit and one
Rolling Mill with a capacity of 30,000 TPA of MS Billets and 72,000 TPA of
TMT bars. The Rolling Mill located in this unit is also catering to the needs
of their other unit i.e., M/s. Devashree Ispat (P) Ltd Unit - III. Also the
hot metal from this unit is transferred to Unit - III, where Concast
Machine is located. Hot billets formed in Concast Machine are again
brought back to this unit to feed the Rolling Mill.
Due to market demand, the unit now proposed to expand the production
capacity by upgrading existing 100 TPD Induction Furnace to 200 TPD
induction furnace by changing circuit and coil and that of the Rolling Mill
from 300 TPD to 800 TPD by changing existing stands and by adding new
stands for increasing the production capacity of MS Billets from current
level of 30,000 TPA to 70,000 TPA & TMT Bars from 72,000 TPA to
2,80,000 TPA.
Total Cost of expansion of the Project is Rs.5.75 Cores out of this an
investment of Rs.0.75 Crores is proposed to invest on environmental
infrastructure.
Location of the Plant
The proposed unit is located over the existing premises at
Sy.Nos. 458, 459 & 460, Elikatta (V), Farooqnagar (M), Rangareddy
District, Telangana State.
The project site is located between Latitude 17004’32.6”N, Longitude
780 08’44.8” E and Latitude17004’30.0”N, Longitude780 08’ 54.4”E.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 2 of 11 M/s. Pridhvi Envirotech (P) Limited.
The nearest human habitation from the site is at Male Elikatta (V) located
at distance of 0.6 KM from the site. The nearest railway station
Shadnagar is located at a distance of 7.15 KM from the site. The nearest
airport is located at a distance of 26 KM at Shamshabad. There is one
Reserve Forests by name Kammadanam RF is at 9.07 KM from the site.
A total of 75 villages with a total population of 1,38,080 are existing in
the 10KM radius of the site covering 2 Districts and 5 Mandals.
Rangampally Cheruvu is at about 1.29 KM in the South West Direction is
the nearest surface water body. Bheemavarm nallah is at about 8.4 KM
distance in the South West direction of the site.
There are no ecologically sensitive zone, National Parks or wild life
sanctuaries within 10 KM radius of the site.
Road Connectivity
The major road access to the site is NH-44 which is at a
distance of 7.20 KM on the East. Shadnagar to Pargi Road is
adjacent to the plant site which connects to National Highway .
Land Requirement for the project:
The unit is having 10.62 acres of land. Out of this 3.80 Acres are utilized
for existing plant. In 3 acres of land, green belt is developed. Additional
Land requirement for expansion would be 1.0 Acres for constructions and
additional Green belt proposed is 0.54 Acres. The land requirement can be
met from the existing open areas of the plant, without any additional land
acquired for the project.
Product Profile The proposed products & capacities are presented in the following table.
Production capacity- Current & Proposed
S No
Furnace Present After Expansion
Capacity TPD
Production TPA
Capacity TPD
Production TPA
1 Induction Furnace
100 30,000 200 70,000
2 Rolling Mill 300 72,000 800 2,80,000
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 3 of 11 M/s. Pridhvi Envirotech (P) Limited.
Water Requirement and Water Balance
The water requirement for various purposes after expansion of activity is
mentioned in the table below. Water will be procured from Public supply
and through tankers from outside agencies.
Water Balance– Current & Proposed
Stream
Water Requirement (KLD)
Waste water
Generation (KLD)
Treatment
and disposal method
Present
After expansion Present
After
expansion
Fresh Recycled
Total
Induction Furnace
Rolling Mill Cooling water
(Make-up)
75.0 100.0 75.0 175.0 32.0 75.0 Cooling water is continuously
recycled after settling in the
tanks
DM Plant 2.0 4.0 - 4.0 - - To be used for dust
suppression
Domestic 18.0 24.0 - 24.0 14.0 19.0 Proposed to
treat in STP
and re-use back for
gardening purpose
Dust Suppression
- - 5.0 5.0 - -
Green Belt 10.0 17.0 18.0 35.0
Total 105.0 145.0 8.0 243.0 46.0 94.0 -
Currently the domestic waste water is let into septic tank followed by soak
pit. As a part of expansion, it is proposed to establish STP which can cater
to both units of Devashree Ispat (P) Ltd. Also it is proposed to provide
primary treatment plant for Rolling Mill Unit for treating and recycling the
cooling water to remove oil & grease and suspended solids.
Baseline Environmental Data
The baseline data for ambient quality, surface and ground water quality,
noise and soil quality collected and analyzed for various parameters
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 4 of 11 M/s. Pridhvi Envirotech (P) Limited.
during December 2017 – February 2018. The analysis results show that
the base line environmental conditions are within the prescribed limits for
air quality. The water quality of the area is found to be within the
permissible limits.
Identification and Quantification of Impacts
The sources of pollution in the proposed project are Air emissions from
utilities, liquid effluents from cooling water and domestic sources, solid
waste from process and noise pollution from plant activities and DG sets.
The impact assessment report identified various sources of pollution and
quantified the pollution loads and has identified the technologies to be
adopted for the mitigation and control of the same.
Impacts of air Quality
The additional impacts of air quality due to the proposed project are from
the 1 induction furnace with upgraded capacity & 2 additional DG sets of 1
X 150 KVA and 1 x 265 KVA capacity each. The impacts are quantified
using ISC- AERMOD model based on ISCST3 Algorithm. The results
indicate marginal increase in the ambient air quality parameters and the
predicted concentrations are within the prescribed limits of CPCB for 24
hours concentrations.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 5 of 11 M/s. Pridhvi Envirotech (P) Limited.
Cumulative Concentrations at Various locations in 10 KM radius
Cumulative Concentrations at Various Villages
AAQ
Location
Base Line Concentration (µg/m3)
Predicted GLCs (µg/m3)
Cumulative Concentration (µg/m3)
PM10 PM2.5 SO2 Nox PM10 PM2.5 SO2 Nox PM10 PM2.5 SO2 Nox
Project Site 85.6 44.6 16.2 21.4 3.506 1.845 7.124 5.243 89.11 46.45 23.32 26.64
Elikatta 73.5 30.2 15.2 18.3 0.095 0.050 0.461 0.142 73.59 30.25 15.66 18.44
Rangampalli 64.3 30.5 15.2 17.3 1.318 0.706 1.524 1.922 65.62 31.21 16.72 19.22
Chowlapalli 67.2 27.4 15.2 17.3 0.259 0.137 0.396 0.383 67.46 27.54 15.60 17.68
Mughalgidda 65.3 27.4 15.2 18.3 1.658 0.878 2.019 2.454 66.96 28.28 17.22 20.75
Antaram 62.3 28.4 15.2 17.3 0.033 0.017 0.184 0.049 62.33 28.42 15.38 17.35
Shadnagar 63.2 26.4 14.6 17.2 0.023 0.012 0.102 0.034 63.22 26.41 14.70 17.23
Pidkiryla 60.2 23.5 14.2 17.3 0.195 0.103 0.754 0.290 60.39 23.60 14.95 17.59
Reserve Forest
Reserve Forest
Predicted Ground Level Concentrations (µg/m3)
PM10 PM 2.5 SO2 NOx
MysuraKammadhanam
RF 0.065 0.034378 0.30764 0.098497
Note: All values are in µg/m3
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 6 of 11 M/s. Pridhvi Envirotech (P) Limited.
Impacts on water resources
No impact on water quality is anticipated as the unit proposed primary
treatment of cooling water and re-use. The domestic water is proposed to
be treated in STP and re-used for gardening purpose. The total fresh
water requirement for the plant after expansion is 145 KLD. It is proposed
to be met through private tankers.
There is an existing rain water harvesting system in the company. The
total rain water is diverted to a surface water pond near main gate and
water is utilized for plant purposes. This is also helping to re-charge the
ground water in the area.
Impacts on Noise quality
The noise levels may marginally increase due to the Rolling Mill expansion
and DG sets. However the impact is limited to boundary of the company.
Additional green belt proposed to reduce the noise impact on outside
environment.
Impacts on Soil
The solid waste generated from the slag crusher and mill waste can
contaminate soil if not handled properly. Adequate safeguards are
proposed in the EMP for proper handling and disposal of the waste. A total
of 7000 TPA of slag is produced from operations and 4000 TPA of Mill
scale is produced from rolling mill. Both these wastes have commercial
values. Mill scale is sold to downstream users and crushed slag after
recovering iron will be used as filling material, road construction and brick
making.
Impacts on Ecology
There are no endangered flora and fauna in the impact area. Further it is
proposed to increase the green belt area from current 3.0 Acres to 3.54
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 7 of 11 M/s. Pridhvi Envirotech (P) Limited.
Acres with expansion activity. Thus there will be positive impact on the
environment.
Impacts on Socio Economy
The expansion project generates 120 additional jobs as direct
employment and almost equal number of indirect employment. As a
policy the management proposed to give priority to local youth for the
recruitment. The area which has low industrial density and sloe
agricultural activity will have positive benefits due to this project.
The Overall impacts of the project on environment and mitigation
measures proposed are summarized in the table below:
S No Environmental Impact Mitigation measures proposed
1 Air emissions from the Induction Furnace
It is suggested to upgrade the existing Bag Filter and ID fan
capacities to meet the additional emission load likely to be generated
from production enhancement of furnace.
It is suggested to provide
Secondary Dust Extraction System at roof level to avoid emissions
going into environment during material charging time and tapping
time of metal.
2 Air emissions from Re-
Heating Furnace
As M/s .Devashree Ispat (P) Ltd
established Continuous Casting
Machine in Unit - III. Hot MS Billets
are directly fed to Rolling Mill
through conveyor. The existing Re-Heating Furnace will be kept as
standby only. Re-Heating Furnace is connected to Bag Filters.
3 Dust emissions from Coal Pulverizer
Coal is used for Re-Heating Furnace which is only stand by equipment.
However emissions from Coal Pulverizer are connected to Bag
Filter of Re-Heating Furnace.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 8 of 11 M/s. Pridhvi Envirotech (P) Limited.
4 Dust from roads due to
handling of raw materials and finished goods
It is suggested to provide water
sprinklers at dust prone points of stock yards.
5 Cooling water handling It is suggested to provide primary
treatment of mill cooling water to control oil & grease and suspended
solids and recycle water completely.
6 Domestic waste water
discharge
About 19 KLD of domestic effluents
likely to be generated after
expansion. It is proposed to establish STP to treat and re-use
the effluents for green belt development. A combined STP with
Unit III is proposed in the premises of Unit III.
7 Withdrawal of ground water Out of the total water requirement of 243 KLD after expansion, 98 KLD
of water would be met from
recycled water and rest 145 KLD of water would be taken from private
water suppliers through tankers.
8 Handling and re-use of waste generated
The project is likely to generate 7000 TPA of Slag and 4000 TPA of
Mill Scale. As both waste can be re-used it is suggested to sell the Mill
Scale for downstream users like paint industries.
Iron will be recovered from slag and
crushed slag is good inert material to be used as land fill material for
road construction and housing construction. Also the slag can be
used in cement bricks making and local youth can be encouraged to
establish such units.
9 Occupational Health M/s.Devashree Ispat (P) Ltd
established occupational health
center in the plant with trained first aiders. It is suggested to improve
facilities further in the health center.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 9 of 11 M/s. Pridhvi Envirotech (P) Limited.
10 Fire safety Presently M/s.Devashree Ispat (P) Ltd established fire extinguishers at
various point of operation in Furnace, Rolling Mill and Electrical
Installations. It is suggested to establish water
lines and fire hoses at Furnace area and Rolling Mill to tackle any
accidental fire.
It is recommended to provide diesel run pump for Fire Fighting System
in the event of power failures.
Environmental Management Plan
The management plan is drawn in consultation with the project
proponents, technical consultants after evaluating a number of
technologies available for mitigation and control of pollution.
The environmental management plan is drawn to address the impact
identified during construction which is temporary and the impacts
identified during operation stages & remedial measures are in corporate.
Prevention, maintenance and operation of environment control
system
The pollution control equipment, effluent treatment systems and effluents
will be monitored periodically and will be checked for its performance and
pro- active maintenance will be adopted. The environmental monitoring
results will be evaluated to identify the problems/ under performance of
the equipment. Necessary steps will be taken to rectify the identified
problems/defects. The management agrees that the evaluation of the
performance of pollution control measures and occupational safety
measures to arrive at their efficiency and purposes to adopt new
measures for efficient pollution control, which will be regular exercise.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 10 of 11 M/s. Pridhvi Envirotech (P) Limited.
Transport systems
All the raw materials and finished products are transported by road.
Sufficient parking facilities are provided for vehicles loading and unloading
of goods. As the plant is located adjacent to Shadnagar - Pargi Road.
There will be 20 truck trips per day to the factory and another 50 PCU/
day of passenger vehicles. Thus total traffic load is only 3 PCU/Hour which
can be taken by the existing road net work safely. The vehicles are
provided with parking space near the gate & steel yard and traffic signs
will be placed in the battery limit.
Reduce, Reuse and Recycle
Rolling Mill cooling water is continuously recycled after primary treatment.
The domestic waste is water also proposed to be treated and re-used for
gardening. Iron is recovered from slag waste and waste proposed to be
re-used as landfill material, road constructions and for brick making. Mill
waste proposed to be sold to downstream users.
Green Belt Development
Green belt is recommended as one of the major components of
Environmental Management Plan. The existing industry has green belt and
the management emphasizes the development of further greening of the
site to enhance environmental quality through; mitigation of fugitive
emissions, attenuation of noise levels, balancing eco-environment,
consumption of treated effluent, prevention of soil erosion, and creation of
aesthetic environment.
In addition to the existing 3.0 Acres of greenery in the plant, it is
proposed to add an additional 0.54 Acres of greenery in this plant.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
Page 11 of 11 M/s. Pridhvi Envirotech (P) Limited.
Post project monitoring in plant
Environmental monitoring for water, air, noise and solid waste quality
shall be conducted periodically either by the proponent or a third party,
the frequency of monitoring and the quality parameters shall be as
suggested by the Ministry of Environment and Forests Government of
India.
Environmental Management Cell
The Environmental Management Cell of the project shall be headed by the
plant manager, and shall be assisted by adequate supporting staff is
suggested.
Budget for implementation of EMP:
A total of Rs.0.75 Crores is proposed for implementation of EMP during
construction and operational phases of the project. A recurring
expenditure of Rs. 19.0 lakhs/annum is earmarked for implementation
cost of EMP including waste handling, disposal, environmental monitoring,
green belt development, storm water management etc.
Corporate Environmental Responsibility
As a part of corporate social responsibility, M/S Devashree ispat (P)
Limited. proposed a budget of Rs.9.5 lakhs over next 5 years period.
Detailed ESR activities are out lined in the EIA report. Based on the inputs
from local villages, the plan can be implemented through District
authorities.
As per the Companies Act, additional funds under CER activities from the
profits will be allocated.
Chapter-1
INTRODUCTION
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-1 Pridhvi Envirotech (P) Ltd.
CHAPTER-1 INTRODUCTION
1.1 Purpose of the Project
M/s. Devashree Ispat (P) Ltd Unit-I situated near Shadnagar – Pargi
Road, at Sy.Nos:458, 459 and 460, Ellikatta (Vil), Farooq Nagar (M),
Rangareddy District (Formerly Mahaboobnagar District), Telangana State
is manufacturing Thermo Mechanically Treated (TMT) Bars in their plant
spread over 10.62 Ac.
The unit obtained CFE on 05-10-2004 from State Pollution Control Board
to manufacture 100 T/Day of MS Ingots and CFO on 12-04-2006. Further
the unit obtained CFE for Rolling Mill with a capacity to produce 300 TPD
of TMT Bars on 14-03-2005 and CFO on 17-01-2007. The unit obtained
the respective Consent Orders accordingly and started its operations.
As the unit was established prior to EIA Notification of 2006 and there are
no prior environmental clearance requirements under EIA notification
1994, Environmental clearance was not applicable to this unit.
The unit is operating with valid Consent of the Board and the current CFO
is valid up to 31.12.2021.
Now the project proposes to expand the production capacity by upgrading
existing 100 TPD Induction Furnace to 200 TPD induction furnace by
changing circuit and coil and that of the Rolling Mill from 300 TPD to 800
TPD by changing existing stands and by adding new stands for increasing
the production capacity of MS Billets from current level of 30,000 TPA to
70,000 TPA & TMT Bars from 72,000 TPA to 2,80,000 TPA.
As per the Environmental Impact Assessment (EIA) notification S.O. 1533
issued on 14-09-2006 by Ministry of Environment and Forests (MoEF),
New Delhi, the proposed expansion project for manufacturing MS Billets
and TMT Bars is categorized as Category B project under 3(a) Secondary
Metallurgical Industries and is mandated to obtain prior Environmental
Clearance from State Environmental Impact Assessment Authority
(SEIAA), under Ministry of Environment & Forests, Govt. of India
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-2 Pridhvi Envirotech (P) Ltd.
In this regard the project proponent has submitted application in the
prescribed Form-I along with Pre Feasibility Report and Standard
Template, to obtain Terms of Reference (TOR) for conducting
Environmental Impact Assessment study in the proposed expansion
project area.
After detailed scrutiny of the application submitted and the presentation
about the project made in the SEAC meeting, the project proponent was
directed to carry out the EIA study and prepare the report as per the
standard terms of reference (TORs) issued by the MoEF&CC, GOI, vide
TOR letter SEIAA /TS /OL / రెడ్/176 /2017 - 2733 dated 21 .11 .2017.
To carry out EIA studies in and around 10 Km’s range of project site to
identify the negative and positive impacts and delineate effective
measures to mitigate the environmental pollution and preparing the EIA
study report has been entrusted to M/s. Pridhvi Envirotech (P) Limited,
Hyderabad.
Accordingly the EIA study was carried out in the study area as per
standard TOR sand the EIA report has been compiled based on the data
collected during the study and details about the project provided by the
proponents.
1.2 Brief Description of Project & Project Proponent
1.2.1 About Project
Now the project proposes to expand the production capacity by upgrading
existing 100 TPD Induction Furnace to 200 TPD induction furnace by
changing circuit and coil and that of the Rolling Mill from 300 TPD to 800
TPD by changing existing stands and by adding new stands for increasing
the production capacity of MS Billets from current level of 30,000 TPA to
70,000 TPA & TMT Bars from 72,000 TPA to 2,80,000 TPA.
1.2.2 Project Proponents
M/s Devashree Ispat (P) Ltd, registered with the Registrar of Companies
at Kolkata and having their City Office 8-2-293/82, Plot No.86, Prash
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-3 Pridhvi Envirotech (P) Ltd.
Nagar, Road No.72, Jubilee Hills, Hyderabad, is manufacturing Thermo
Mechanically Treated (TMT) Bars, in their plant situated near Shadnagar –
Pargi Road, at Sy Nos. 458, 459 and 460, Ellikatta (Vil), Farooq Nagar
(M), Rangareddy District, Telangana State.
The plant was established in 2006 and the company is producing TMT Bars
of 8 mm to 32 mm diameter size by rolling MS Billets. All the products
conform to the Bureau of Indian Standards (BIS) and the products are
marketed under brand name ‘SHREE TMT’ Bars, a well known and
recognized brand in Hyderabad and other areas.
Background of Promoters
The project proponents of M/s.Devashree Ispat (P) Ltd are in the line of
steel business for more than three decades and commands goodwill and
reputation in the Steel industry.
The company is headed by Sri Prakash Goenka, the Managing Director &
Sri. Neeraj Kumar Goenka, the Director.
The company is a family concern, having vast and vivid experience in steel
business since 1980 and is one of the pioneers and most trusted name in
the South Indian Steel industry.
1.3 Need of the Project
India’s rapid economic growth and soaring demand in sectors like
infrastructure, real estate and automobiles at home and abroad have put
Indian steel industry on the global map. According to the latest report by
International Iron and Steel Institute (IISI), India is the third largest steel
producer in the world.
The Indian Steel industry is organized in three categories i.e., main
producers, other major producers and the secondary producers. The main
producers and other major producers have integrated steel making facility
with plant capacities over 0.5 MT and utilize iron ore and coal/gas for
production of steel. The main producers are Tata Steel, SAIL, and RINL,
while the other major producers are ESSAR, ISPAT and JVSL etc.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-4 Pridhvi Envirotech (P) Ltd.
The secondary sector is dispersed and consists of: (1) Forward linkage
with about 120 sponge iron producers that use iron ore and non-coking
coal, providing feedstock for steel producers; (2) Approximately 650 mini
blast furnaces, electric arc furnaces, induction furnaces that uses iron ore,
sponge iron and melting scrap to produce steel; and (3) backward linkage
with about 1,200 re-rollers that roll out semis into finished steel products
for consumer use.
In 2015-16, production of finished Steel is 90.98 million tones. India is 3rd
largest steel producer in the world. The share of secondary steel
producers is 67% of total steel production in the country. Due to its
growing demand, India has been identified as one of the hottest
destination of steel exports from all over the world.
Secondary steel producers play vital role in reaching end customers in the
country. Induction steel melting and rolling mills are growing at rapid rate
due it’s accessibility to small and medium users, housing sector,
infrastructure, transportation etc.,
This demand is further boosted by the demand from foreign countries. The
Indian Market is exporting the steel products to more than 51 countries
and earning valuable foreign exchange to the country.
In view of the above, the proposed expansion project would contribute in
meeting the increasing demand for steel in both domestic and export
markets.
The project would provide direct employment and indirect business and
service opportunities in the region.
Also the project contributes to economic development in the region and
revenues to Government.
1.4 Justification of the project
Secondary steel industry is having its strong presence in Telangana State.
Nearly 40 Medium and large scale steel industries are working in the
state. The industrialization in the state are supported by
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-5 Pridhvi Envirotech (P) Ltd.
Good infrastructure
Availability of skilled manpower
Government’s positive attitude towards the industrialization
Presence of Entrepreneurs with steel industry back ground
M/s. Devashree Ispat (P) Ltd is in forefront in the last 14 years with
excellent customer base and markets. The demand for Rolled Mill products
such as TMT Bars is increasing existing infrastructure and land availability
near Male Ellikatta and Elikatta village, Rangareddy District (TS) prompted
the industry to increase the production levels. The project is justified in
techno commercial point of view.
1.5 Nature & Description of Project
The project activity is manufacturing MS Billets /Ingots by melting MS
scrap and Sponge iron in Induction Furnace and casting billets in
Continuous Casting Machine and TMT Bars by Rerolling in Rolling Mill.
The company is producing TMT Bars of 8 mm to 32 mm diameter size by
rolling MS Billets. All the products conform to the Bureau of Indian
Standards (BIS) and the products are marketed on ‘SHREE TMT’ Bars
brand, a well known and recognized brand in Hyderabad and other areas.
The company now proposes to increase the capacity of existing Induction
Furnace and the capacity of Rolling Mill so as to produce 70,000 TPA of
Billets and 2,80,000 TPA of TMT Bars.
The details of capacities of Current & Proposed expansion activities are as
given in the table 1.1.
Table 1.1
Production capacity- Current & Proposed
S No
Furnace
Existing After Expansion
Capacity TPD
Production TPA
Capacity TPD
Production TPA
1 Induction Furnace 100 30,000 200 70,000
2 Rolling Mill 300 72,000 800 2,80,000
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-6 Pridhvi Envirotech (P) Ltd.
1.5.1 Common Facilities of Unit I and Unit III
Rolling Mill of the plant will be common facility which can cater to the
needs of M/S. Devashree Ispat (P) Ltd Unit - I and M/S.Devashree Ispat
(P) Ltd Unit -III situated adjacent to Unit-I. M/s.Devashree Ispat (P) Ltd
Unit - III (earlier named as M/s.Srinath Metal (P) Ltd is also applying for
EC separately for expansion of its activity. The Concast Machine is also a
common facility for both the units and is located in M/s.Devashree Ispat
(P) Ltd Unit III. Hot metal from Induction Furnace goes to Unit III and
hot billets are formed and they come back to Unit - I which are fed to
Rolling Mill here in Unit - I. Similarly Hot Billets produced in Unit III will
also come to Rolling Mill situated in Unit - I. The slag storage and crusher
is in Unit - III which will serve for both units together. STP facilities are
proposed in unit III and 132 KVA sub station facilities established in Unit
III will be common for both units.
This optimized sharing of resources between two plants, which are
adjacent to each other, will reduce overall impacts on environment and
helps in conservation of resources.
1.6 Location of Project
The proposed expansion project will be located at the existing premises
situated at Sy.Nos.458, 459 & 460, Elikatta (V), Farooqnagar (M),
Shadnagar Rangareddy District, Telangana State. The nearest village,
Male Ellikatta is at about 0.6 KM from the site.
The salient features of the site are presented in table 1.2 below
Table No: 1.2 Salient Features of the Site
Site Location Sy. Nos. 458,459 and 460, Ellikatta (V), Farooqnagar (M),Rangareddy(Dt) (Formerly Mahaboobnagar District)Telangana State
Latitude and Longitude 1.N 17004’32.6” 2.N17004’35.8” 3.N 17004’34.5” 4.N 17004’30.0” 1.E780 08’44.8” 2.E780 08’45.7”
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-7 Pridhvi Envirotech (P) Ltd.
3. E780 08’56.3” 4.E 780 08’ 54.4”
Total area of land 10.62 Acres Total area of green belt developed 3.54 Acres After expansion Nearest High way NH-44 @ 7.2 KM (ENE) Nearest Rly Stn Shadnagar @ 7.15 KM (E) Nearest Air Port RGI AIRPORT @ 36.2 KM (NE) Nearest fire station 7.15 kms (E)Shadnagar Nearest village Male Elikatta @ about 0.6 KM SE
from the site Nearest surface water bodies Rangampalli 1.29 kms (SW)
Sardarnagar Cheruvu – 1.40 kms (NE), Pirlaguda – 3.02 kms (SW), Duntikunta – 3.88 kms (SW), PeddaCheruvu – 8.77 kms (SE), Inayakhanguda -7.24 kms (SE), KesaramCheruvu – 7.21 kms (NE) Bheemavaram Naala-8.4 Kms (SW)
Nearest Reserve Forest MysuraKammadhanam RF 9.07kms(SE)
Any ecologically sensitive areas Nil within 10 km radius
1.7 Project Cost
The project cost of existing facilities is Rs. 24.07 Cr. and Rs. 30.15 Cr. for
Furnace Division and Rolling Mill Division including Reheating Furnace
respectively.
The projected cost for the proposed expansion is estimated as Rs 5.75 Cr.
approximately as detailed below.
Table 1.3 Cost for the proposed expansion
S
No Description
Cost Rs. Cr.
Upgrading
Furnace
Upgrading
Rolling
Mill
Total
1 Buildings & Civil works 0.50 0.50 1.00
2 Plant & Machinery and Electrical Installation
1.00 3.00 4.00
3 Pollution Control Equipment for furnace, Primary treatment of mill cooling water, STP , Fire safety system , water sprinklers & green belt development
0.30 0.45 0.75
Total 1.80 3.95 5.75
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-8 Pridhvi Envirotech (P) Ltd.
1.8 Scoping of EIA Study.
Terms of References
The project comes under category 3(a) of EIA Notification under
Metallurgical industries (Ferrous & Non Ferrous) under Secondary
Metallurgical processing industry under non toxic category. The unit is
Category B Project and comes under purview of state appraisal committee
of MOEF & CC Telangana.
As the project proponent was directed in the SEAC meeting held on
29.03.2018 to prepare EIA Report, as per the standard terms of reference
(TORS) issued by the MoEF & CC, GOI, available in the website, the EIA
Study was carried out during December,2017 - February,2018, as per the
standard TORs.
Study Details
Reconnaissance survey of the region was carried out during the first week
of September 2017, and various sampling locations to monitor
environmental parameters have been identified. Subsequently,
monitoring has commenced for collection of data on meteorology, ambient
air quality, surface and ground water quality, soil characteristics, noise
levels, flora and fauna at the specified locations. The other studies such
as socio-economic profile, land use pattern etc., are based on both
Primary & secondary data collected from various government agencies
and validated through the primary surveys. The ambient air monitoring
locations have been selected based on the initial Wind model carried out
by using the meteorological data generated at India Meteorological
Department (IMD) by comparing with Site Specific Micro metrological
station established at the site.
Field team of M/s Lawn Enviro Associates, the environmental laboratory
associated with M/s. Pridhvi Envirotech (P) Ltd, worked in the study area
during the months of December,2017 to February,2018 and base line data
for various environmental components i.e., air, water, soil, noise and flora
and fauna and socio economic status of the people was collected in a
radius of 10 km, to assess the existing environmental status as per the
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-9 Pridhvi Envirotech (P) Ltd.
guidelines specified by Ministry of Environment and Forest (MOEF),
Government of India. This report presents the results of Environmental
Impact Assessment study along with the Environmental Management Plan,
necessary to contain the observed environmental impacts of the proposed
primary metallurgical project.
As M/S Devashree Ispat P Ltd. Proposed to expand both Unit I (ie., this
unit) and Unit III which is adjacent to this unit, and applied for
environmental clearance, the base line studies are conducted for
combined activities of both plants.
Environmental impact assessment study involves three basic components,
i.e., identification, prediction and evaluation of impacts.
Accordingly the detailed scope of EIA study is as follows;
An intensive reconnaissance survey and preliminary collection of
environmental information to plan field study.
Field studies to collect preliminary information, particularly on the
quality of the physical environment, social environment and biotic
environment - Experienced scientists and engineers collected the
data.
Base line data generation and characterization of air, water, soil,
noise and vegetation in the 10 kilometer radius area (impact zone)
over a period of Three months.
A thorough study of the process including provisions for pollution
control, and environmental management that includes prediction
of impacts and relevant mathematical modeling.
Preparation of Environmental Monitoring Program.
Preparation of Environmental Management plan suggesting
suitable methods for mitigating and controlling the pollution levels.
Environmental monitoring plan is suggested for monitoring the
pollution loads at various facilities in the premises and outside to
ensure compliance with the statutory requirements.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-10 Pridhvi Envirotech (P) Ltd.
1.9 Environmental sensitivities & significant impacts of the project
considered
Project Site is located on the boundary of northern Musa Nadi
watershed which is part of Musi River catchment. The location is
in rural back ground with a total population of around 1,38,080
in 75 villages covering 5 mandals & 2 districts, in the study
area of 10 KM radius of the site. There is one Reserve forest in
the 10 KM radius of the site. There are no National Parks/ Bio
Reserves/Wildlife Sanctuaries in the 10 KM radius of the site.
The Key Environmental Impacts considered are Air Pollution
from Induction Furnace, fugitive dust from material handling
and slag handling facilities. Water to be taken from private
suppliers through tankers. Impacts on flora and fauna from the
process emissions, social impact of the expansion project on
nearby population are to be considered. These key impacts are
discussed in detail and mitigation measures are addressed in
Environmental Management Plan.
1.10 Policy, legal and administrative frame work
This Section presents a review of the existing regulations and
legislations relevant to this project, at the National and the
State Levels. Regulations concerning procedures and
requirements that may directly concern the project .
1.10.1 Institutional Setting for the Project
The proposed expansion project will be located at the existing
premises situated at Sy.Nos.458, 459 & 460, Elikatta (V),
Farooq- nagar (M), Rangareddy District, Telangana State.
1.10.2 Institutional Setting in the Environmental Context
The environmental regulations, legislation policy guidelines and
control that may impact this project, are the responsibility of a
variety of government agencies. In all, as discussed in the
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-11 Pridhvi Envirotech (P) Ltd.
subsequent sections, the following agencies would play
important roles in this project.
1.10.3 Ministry of Environment, Forests & Climate Change
(MoEFCC)
The primary responsibility for administration and
implementation of the Government of India’s policy with respect
to environmental management, conservation, ecologically
sustainable development and pollution control rests with the
Ministry of Environment and Forests (MoEF&CC). MoEF & CC is
the agency primarily responsible for the review and approval of
EIAs pursuant to G.O.I Notification in September,2006 and
subsequent amendments.
1.10.4 MoEF & CC Regional Offices
The Ministry of Environment and Forests Regional office in
Chennai is responsible for collection and furnishing of
information relating to compliance to conditions of
Environmental Clearance of projects, pollution control
measures, methodology and status, legal and environment
measures and environmental protection in special conservation
areas such as wetlands, mangroves and biological reserves.
1.10.5 State Pollution Control Board (SPCB)
The Telangana State Pollution Control Board plays the role of
environmental management at the state level, which
emphasizes on air and water qualities. The project needs to
obtain Consent for Establishment (CFE) & Consent for Operation
(CFO) before construction and during operational phase of
project. It enforces the waste water and air emission standards
compliance and other conditions of EC and CFE/CFO granted. It
is also responsible for granting of authorization under
Hazardous Waste Management, Transboundary movement Rules
1998.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-12 Pridhvi Envirotech (P) Ltd.
1.10.6 Departments of Environment and Forests (DOEF)
The department of Environment, Forests, Science and
Technology performs the functions similar to the MoEF & CC at
the state level in Telangana.
1.11 Other Statutory Licenses/Permission
1.11.1 Director of Factories & Boilers
Under Factories Act, 1948 as amended, the unit is required to
obtain clearance for expansion activities and for construction of
new production block and other utilities.
1.11.2 Permissions from Local Panchayat
The unit needs to obtain permission for construction and new
activities proposed from local Panchayat of Elikatta.
1.12 Required Statutory Licenses At A Glance
The table gives the requirement & status of various applicable
clearances for the project and its current status is given in the
table 1.4 below;
Table 1.4 Applicable statutory clearances for the site
S.No Nodal Agency License/NOC /Approval
requirements Current Status
1 Ministry of Environment, Forests & Climate change State Level EIA Authority
Environmental Clearance Obtained TOR and this EIA Report submitted for the grant of EC
2 Local Panchayat Lay out & Building plan approvals
Will be applied once the EC is cleared as EC is mandatory requirement before issue of the same
3 Director of Factories Permission of expansion activity and approval of building plans
Will apply once Environmental clearance is issued
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-13 Pridhvi Envirotech (P) Ltd.
4 Telangana State Pollution Control Board Water & Air Acts
Consent for Establishment Consent for operation
Will be applied after getting Environmental Clearance. Can be obtained once expansion activity is ready for operation
5 Hazardous Waste (Management & transboundary movement) Rules 1998
Authorization Can be obtained once expansion activity is ready for operation
1.13 Structure of the EIA Report
The report is organized in 12 chapters as follows
Chapter 1 Is introduction chapter which highlights briefly about the
project, introduction to project proponents, nature & size of the project
and its importance & scope of study & regulatory frame work applicable to
the project under Environment
Chapter 2 Outlines project description provides the complete description
of the expansion project of M/s.Devashree Ispat (P) Ltd Unit - I. The
details are presented from the environmental perspective along with the
salient features such as land use, process adopted, water consumption
and waste water discharges, solid wastes generation, resource
requirement for the project and current compliance levels of the unit vis-
à-vis previous clearances from Pollution Control Board.
Chapter 3 Discuss the study area, period of study, components &
methodology adopted, base line data established and environmental
components.
Chapter 4 Discuss the details of investigated environmental impacts due
to project at various stages of development and operations. Also the
chapter outlines the measures for minimizing or off-setting adverse
impacts identified and mitigation measures.
Chapter 5 Discuss the details of alternative sites & technologies
considered if any.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
1-14 Pridhvi Envirotech (P) Ltd.
Chapter 6 Discuss the details of environmental monitoring program,
frequencies & costs during implementation and operation.
Chapter 7 Discuss the potential hazards and risks associated with project
& risk mitigation measures proposed and out lines disaster management
plan.
Chapter 8 Discuss the benefits from the project to various stake holders.
Chapter 9 Discuss the Environmental Cost Benefit Analysis (Not specified
in TOR in this case).
Chapter 10 Discuss the detailed Environmental Management Plan which
addresses the measures to be adopted for effective environmental
conservation. It also gives estimated budget for implementation of EMP,
both capital investment and recurring costs & Outline the commitment
from project proponents on Corporate Environmental responsibility and
budget
Chapter 11 Gives the Summary & Conclusion of the EIA and justification
of implementation of project.
Chapter 12 Gives the credentials of M/s. Pridhvi Envirotech (P) Ltd, their
accreditation details and team which conducted the EIA studies.
Chapter - 2
PROJECT DESCRIPTION
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-1
Pridhvi Envirotech (P) Ltd.
Chapter 2.0
PROJECT DESCRIPTION
2.1 Brief Description of Project
Now the project proposes to expand the production capacity by upgrading
existing 100 TPD Induction Furnace to 200 TPD induction furnace by
changing circuit and coil and that of the Rolling Mill from 300 TPD to 800
TPD by changing existing stands and by adding new stands
This will enhance production capacity of MS Billets from current level of
30,000 TPA to 70,000 TPA & TMT Bars from 72,000 TPA to 2,80,000 TPA.
The details of proposed installations and products with
production capacity are given in Table 2.1.
Table 2.1 Current & Proposed Installations and Products
The salient features of the project are given in the Table 2.2.
Table No 2.2
SALIENT FEATURES OF THE PROJECT
FEATURE DETAILS
PROJECT
Present Production capacity MS Ingots/ Billets – 30,000 TPA/ 100 TPD TMT Bars – 90,000 TPA/ 300 TPD
After expansion – Capacity MS Billets – 72,000 TPA/ 200 TPD
TMT BARS – 2,80,000 TPA/ 800 TPD
Total Project cost for expansion Rs. 5.75 Cr.
Cost of proposed Environmental Infrastructure for expansion
Rs 0.75 Cr.
Raw Materials Required Sponge Iron, MS Scrap , Pig Iron and Ferro Alloys
S No
Furnace Present After Expansion
(350days)
Capacity
TPD
Production
TPA
Capacity
TPD
Production
TPA
1 Induction Furnace 100 30,000 200 70,000
2 Rolling Mill 300 72,000 800 * 2,80,000
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-2
Pridhvi Envirotech (P) Ltd.
Total Water requirement for
expansion
Current – 105 KLD
After expansion- 243 KLD
(Fresh water 145 KLD & Recycling 98 KLD) Source of water is through private tankers
from outside
Power Requirement Current Power requirement – 8.5 MVA
After expansion - 11 MVA
Man Power Requirement Current – 325 After expansion - 445
2.2 Need for the Project
Now the project proposes to expand the production capacity by upgrading
existing 100 TPD Induction Furnace to 200 TPD induction furnace by
changing circuit and coil and that of the Rolling Mill from 300 TPD to 800
TPD by changing existing stands and by adding new stands for increasing
the production capacity of MS Billets from current level of 30,000 TPA to
70,000 TPA & TMT Bars from 72,000 TPA to 2,80,000 TPA.
2.2.1 Steel Industry as a Whole
Crude steel production grew at 5% annually (CAGR) from 74.29 mtpa
in 2011-12 to 89.79 mtpa in 2015-16.
Such growth in production was driven by capacity expansion, from
90.87 million tonnes per annum (mtpa) in 2011-12 to 121.97 mtpa in
2015-16, with a CAGR growth of 9% during this five year period.
Production for sale of total finished steel (alloy + non-alloy) stood at
90.98 million tons during 15-16, as against 75.69 million tones in
2011-12, an average annual (CAGR) growth of 6%.
Domestic consumption of total finished steel (alloy + non-alloy) was
at 81.52 million tones in 2015-16 as against 71.02 million tones in
2011-12, growing at a CAGR of 4.2% during the last five years.
Export of total finished steel (alloy + non-alloy) during 2015-16 stood
at 4.08 million tones (4.59 million tones in 2011-12) while import of
total finished steel (alloy + non-alloy) during the same year stood at
11.71 million tones (6.86 million tones in 2011-12)
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-3
Pridhvi Envirotech (P) Ltd.
(Source: Annual Report 2016-17 of Ministry Of Steel, Government of
India)
The ever increasing demand and opportunities for export in steel
industry have prompted the company to expand the existing
facility at the same premises, as a measure of expanding the
production capacity so as to capture major markets while
ensuring the quality of products.
2.3 Location
The proposed unit is located over the existing premises at
Sy.Nos. 458, 459 & 460, Elikatta (V), Farooqnagar (M), Rangareddy
District, Telangana State.
The project site is located between Latitude 17004’32.6”N, Longitude 780
08’44.8” E and Latitude17004’30.0”N, Longitude780 08’ 54.4”E.
2.4 Site Sensitivity:
The nearest human settlement from the site is at Male
Ellikatta village located at a distance of 0.6 vkm in South East
direction. And in ellikatta @ 0.87Km in NE direction.
Total number of villages in 10 KM radius of the site is 75
and the total population in 10 KM radius is 1,38,080.
Nearest town is Shadnagar is at a distance of 7.15 KM with a
population of around 45675.
Rangampalli Cheruvu is at 1.29 Km from SW Direction and
Beemavaram nallah at 8.4 Km from South west direction.
ZP High School is in Shadnagar which is about 7.20 KM away
from the site.
One primary health center & Anganwadi School in Elikatta
village.
Mysuram Kammadhanam Reserve forest is at a distance of
9.07 km in South East direction.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-4
Pridhvi Envirotech (P) Ltd.
The major road access to the site is NH-44 which is at a
distance of 7.20 KM on the East. Shadnagar to Pargi Road is
adjacent to the plant site which connects to National Highway.
The nearest railway station is Shadnagar Railway station at a
distance of 7.15 km from the site in the East direction.
There are no sanctuaries, ecologically sensitive areas or
national parks with in 10 km radius of the site.
Indian Remote sensing agency, data receiving and analysis
center is located near shadnagar area.
Sri Ramalingeswara Swami Temple at Rameswaram built in the 19th
Century is an important religious place in the study area
Location Map of the Project is given at Figure 2.1
The Topo sheet of the area is given at Figure 2.2
The Base feature of the study area is given at Figure 2.3
The Google Map of the area is given at Figure 2.4
Plant Layout is given at Figure 2.5
Photographs of the existing plant are given at Figure 2.6
Photographs Existing Green Belt Phoes are given at Figure 2.7
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-5
Pridhvi Envirotech (P) Ltd.
Fig.2.1 Location Map of the project
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-6
Pridhvi Envirotech (P) Ltd.
Fig 2.2: TOPO Map of Project Site & Study Area
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-7
Pridhvi Envirotech (P) Ltd.
Fig. 2.3: BASE MAP OF THE PROJECT SITE & STUDY AREA
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-8
Pridhvi Envirotech (P) Ltd.
Fig 2.4: GOOGLE MAP OF THE SITE
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-9
Pridhvi Envirotech (P) Ltd.
Fig 2.5: PLANT LAYOUT
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-10
Pridhvi Envirotech (P) Ltd.
Fig 2.6: PHOTOGRAPHS OF EXISTING
SURROUNDINGS
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-11
Pridhvi Envirotech (P) Ltd.
Fig: 2.7 Existing Green Belt in the Plant
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-12
Pridhvi Envirotech (P) Ltd.
2.5 Size & Magnitude of Operation
The main products manufactured in the existing plant are MS Billets/Ingots
and TMT Bars of 8 mm to 32 mm diameter by Re-rolling.
The present and proposed capacities of Induction furnaces and Rolling mill
are as given in the table 2.3.
Table 2.3 Proposed Production Capacities (TPA)
2.5.1 PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION
In the process of obtaining Environmental Clearance to the proposed
project as per the EIA Notification, 2006, M/s.Devashree Ispat (P) Ltd Unit–
I submitted application in the prescribed Form1 along with Pre-Feasibility
Report and Standard Template, to SEIAA, Telangana state, to obtain Terms
of Reference for carrying out EIA study in and 10 KM around the project
site.
After detailed discussions on the application submitted and the
presentation about the details of the project made in the SEAC
meeting, the project proponent was directed to conduct EIA
study and prepare the EIA Report, as per the standard terms of
reference (TORs) issued by the MoEF & CC, GOI, which are available
in the website vide TOR letter SEIAA /TS /OL / RD/176 /2017 2733 dated
21 .11 .2017.
The EIA study has been carried out and the draft EIA Report has been
prepared as per standard terms of reference for submission to TS Pollution
Control Board for conducting public hearing.
S No
Furnace
Present After Expansion
Capacity
TPD
Production
TPA
Capacity
TPD
Production
TPA
1 Induction
Furnace
100 30,000 200 70,000
2 Rolling mill 300 90,000 800 2,80,000
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-13
Pridhvi Envirotech (P) Ltd.
The project proposed to complete the expansion activity within 6 months
time once all statutory permissions are obtained.
2.6 TECHNOLOGY & PROCESS DESCRIPTION
2.6.1 Alternative technologies
Steel production is mainly done by 3 routes
Blast Furnace
Electrical Arc Furnace
Induction Furnace
The Blast Furnace technology is highly capital intensive and small & Medium
scale units cannot make such high investment.
The Electrical Arc Furnace is also high capital intensive but low energy
requirement. However process complication is higher.
The Induction Furnace is well established technology for small and medium
scale units.
The company now proposes to increase the capacity of existing Induction
Furnace and the capacity of Rolling Mill, so as to produce 70,000 TPA of MS
Billets and 2,80,000 TPA of TMT Bars.
2.6.2 Technology Proposed
The technology of manufacturing MS Billets & TMT Bars in Induction
Furnace and Bar Mill is Induction Furnace - Continuous Casting
Machine – Rolling Mill route process.
2.6.3 Assessment of technology for the risk of technological failure
The technology presently employed in the manufacture of MS Billets and
Steel Construction Bars using Induction Furnace & Rolling Mill is well
established and widely adopted technology.
The technology proposed for manufacturing MS Billets & TMT Bars is
well tested and proven for consistent quality & quantity of output and is
adopted worldwide.
Hence there is no risk of technological failure.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-14
Pridhvi Envirotech (P) Ltd.
2.6.4 Manufacturing Process
The greatest advantage of the Induction Furnace is its low capital cost
compared to other types of steel melting units. Its installation is relatively
easier and its operation is simpler. The molten metal in an Induction
Furnace is circulated automatically by electromagnetic action so that when
alloy additions are made, a homogeneous product is ensured in minimum
time. While making steel in the electric Induction Furnace, the fore-most
consideration is the optimum utilization of the furnace as well as elimination
of delays. The time between tap and charge, the charging time, casting
time etc., are items of utmost importance in meeting the objective of
maximum output in tons/hour at a low operation cost.
2.6.4.1 The Charge
Sponge Iron constitutes the major raw material for Billet making from the
Induction Furnace. Sponge Iron of consistence quality, shall be selected for
the type of steel composition to be made. This is because elimination of
some elements from the molten metal is difficult in an Induction Furnace
melting, and in the cases where these are present in high quantities,
dilution is the only possible solution. That is why procurement of the
appropriate kind of sponge iron (Fe. Metallic 85 to 90) is the utmost
importance in furnace melting practice.
The charge should added with pig iron or iron scrap and required quantity
of ferro alloys.
2.6.4.2 Melting the Charge
After the furnace is switched on currents starts at a high rate and low
voltage through the Induction Furnace coils, producing an induced magnetic
field inside the central space of the coils where the crucible is located. The
induced magnetic fluxes thus generated cut through the packed charge in
the crucible, which is placed centrally over the induction coil. As the
magnetic flux cut through the scraps and complete the circuit, they
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-15
Pridhvi Envirotech (P) Ltd.
generate an induced eddy current in the scrap. This induced eddy current,
as it flows through the high resistive path of scrap, generates tremendous
heat and melting starts. It is thus apparent that the melting rate depends
primarily on two factors. (I) the density of fluxes and (II) compactness of
the charge. The magnetic flux can be controlled by varying the input power
of the furnace, especially the current and frequency.
In a medium frequency furnace the frequency range normally varies
between 150 to 100 K cycles/second. This heat is generally developed
mainly in the outer rim of the metal in the charge but is carried quickly to
the centre.
Soon a pool of molten metal forms in the bottom causes the charge to sink.
At this point, any remaining charge is added gradually. The eddy current,
which generated in the charge, has other uses. It imparts a motor effect
on the liquid steel, which is thereby stirred and mixed and heated more
homogeneously. This stirring effect is inversely proportional to the
frequency of the furnace & so the furnace frequency is selected in
accordance with the purpose for which the furnace will be utilized. The
motion of the metal continues till all the charge is melted and the bath
develops a convex surface.
However, as the convex surface is not favorable to slag treatment, the
power input is then naturally decreased to flatten the convexity and to
reduce the circulation rate when refining under a reduced slag. The
reduced flow of the liquid metal accelerates the purification reaction by
constantly bringing new metal into close contact with the slag. Before the
actual reduction of steel is done, the liquid steel, which might contain some
trapped oxygen, is first treated with some suitable de-oxidizer.
As soon as charge has melted clear and de-oxidized action have ceased,
any objectionable slag is skimmed off, and the necessary alloy elements are
added. When these additives have melted and then been defused through
the bath, the power input may be increased to bring the desired
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-16
Pridhvi Envirotech (P) Ltd.
temperature of the molten metal for pouring. The current is then turned off
and the furnace is tilted for pouring.
Continuous Casting of Molten steel:
CCM (Continuous Casting Machine) is used to continuously cast the liquid
steel in required cross section and in length.
2.6.4.3 Equipment Used in Steel Melting Shop
Steel Melt Shop (SMS) is created to melt the Sponge Iron along with
melting scrap and fluxes to make pure liquid steel and then to mould it
through CCM in required size billets. The shop consists of following
equipment and subassemblies.
Induction Furnaces:
Induction Furnace is a device to melt the charge material using electrical
power. It consist of Crucible lined with water cooled induction coils,
electrical system to give controlled power to induction coil, hydraulic tilting
system, Heat exchanger to cool the circulating water, water softener for
generating soft water, furnace transformer, power factor improvement
system and surge suppressor.
Ladles:
Ladles are pots with refractory lining inside to withstand 16000C
temperature. It has side arms so that can be lifted with the help of crane.
Ladles are used to store the liquid steel from Induction Furnace and take it
for further processing. Ladles are with bottom nozzle and pneumatically
operated gate for discharge of liquid.
Ladle Refining Furnace (LRF):
Ladle furnace is a mini electric arc furnace. It has three carbon electrodes,
roof to cover the ladle, and furnace transformer of suitable capacity. The
operation of electrodes, roof etc are controlled by hydraulic system. Ladle
furnace is used either to keep the liquid steel hot for sequence casting or
for further refining of the liquid steel to make better quality steel.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-17
Pridhvi Envirotech (P) Ltd.
Cranes:
Electric Over-head Travelling (EOT) cranes of various capacities are used to
carry the ladles / materials at different places. Cranes are used in Melting
hall to charge melting scrap, further to place it over the Tundish of the
Continuous Caster, to remove billets from the cooling bed and store at
designated places, and also for other petty use. Accordingly the sizes,
capacity and numbers of cranes are decided.
Continuous Casting Machine (CCM):
CCM is used to continuously cast the liquid steel in required cross section
and in length. It consists of tundish, mould, Bow with withdrawal
mechanism, straightening mechanism and cooling bed, hydraulic system for
withdrawal mechanism. Dummy bar is provided to start the casting.
Tundish is a rectangular vessel, lined with refractory and having discharge
nozzle with pneumatically operated gate. A stand is erected over it where
the ladle is stationed for discharging the liquid in it. Mould is of copper with
water cooled jacked its cross section in the bottom is of the size of which
billet is to be drawn.
Water spray nozzles are installed to spray water over the just drawn billet
to cool it further and to harden the skin of the drawn billet. The withdrawal
rolls are used to provide motoring action to the billet to come out and travel
further for cooling. The billet is either manually cut or a travelling gas
cutter is provided which cuts the belts automatically as desired size.
Cooling bed is of steel rolls driven by electric motor. Water spray is done
from the top till the temperature of billets comes down to desired level.
Cooling Tower is provided to cool the water collected from the cooling bed
for cooling and re-use.
In this case Continuous casting machine is established in Unit III. Hot metal
from induction furnace will be transferred through a mechanical rail trolley
system to unit III for casting the billets
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-18
Pridhvi Envirotech (P) Ltd.
2.6.5 Manufacturing Process in Rolling Mill
The process involves converting the shape stock viz. MS Billets to desired
finished section in hot condition by way of passing the material between a
pair of grooved rolls and providing suitable draft at various stages. The
whole operation is conducted at a particular temperature range and within a
limited time span. The stages of rolling operation are comprised of heating
of feed stock to rollable temperature, rolling the feed in different mill
stands, cropping the hot bar during process of rolling between stands as
applicable and subsequently finishing in the form of hot rolled deformed bar
in straight length.
The hot bar coming out of last pass is then conveyed through TMT Box and
then to a cooling bed after shearing. The bars at almost ambient
temperature are sheared to commercial length stored and kept ready for
dispatch. In TMT process hot bars are subjected to quenching by means of
an intense cooling installation (cooling installation specially designed water
spray system). This step hardens the surface layer to marten site while the
core structure remains austenite. When the bar is free of water chamber ,
heat flows from core to surface and surface gets tempered to structure
called marten site. In the cooling bed due to atmosphere cooling, the
hardened zone is tempered by temperature homogenization in the cross
section and the austenite core is transferred to ductile-ferrite-pearlite core.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-19
Pridhvi Envirotech (P) Ltd.
Fig No.2.8. PROCESS FLOW CHART
CONTINUOUS CASTING MACHINE (CCM)
in UNIT III
MS BILLETS
FERRO ALLOYS
M S SCRAP/Pig Iron
INDUCTION
FURNACE
SPONGE
IRON
FLUE GASES
To Bag Filters
SLAG TO
CRUSHERS
RE ROLLING MILL
MILL SCALE
(Sold )
Ladle Refining
Furnace (LRF)
TMT BARS TO FG
YARD
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-20
Pridhvi Envirotech (P) Ltd.
2.6.6 Scrap Handling
Processed & sized scrap will be brought into the scrap storage yard from
outside plant or the scrap preparation area. The properly weighed scrap
will be transported to the Induction furnace by means of EOT Cranes for
direct charging.
2.6.7 Slag Handling
Slag generated from the plant is transferred to Unit III where Slag Crusher
is established.
2.6.8 Fume Extraction System – FES
The Induction Furnace will be provided with an advanced high efficient gas
cleaning system. Dust loaded fumes, generated in the Induction Furnace
during operation, and are extracted directly from the furnace roof canopy
provided on furnace. Fumes that escape during the charge time would be
extracted through secondary ducting placed at higher elevation of shed.
Gases from both from primary and secondary ducts will be passed through
High-efficient spark arrestor and then enter into pulse jet bag filters. Bag
Filters cleans the dust and leave the clean air into environment. The dust
collected from bag filters would be disposed off along with Slag as it is inert
dust.
2.6.9 Re-heating Furnace
In case when direct hot charged billets cannot feed the Rolling Mill with the
help of conveyor sufficiently, billets from Re-heating Furnace would be fed.
Pulverized coal is used as fuel in the reheating furnace. The emissions of
the Re-heating Furnace would pass through the duct to “spark arrester” and
then to the “Bag Filters” where the air would be purified. After the cleaning
of the fumes, it will pass through chimney.
Re-heating furnace is kept as stand by only and will be used as & when the
rolling mill is stopped due to any reason.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-21
Pridhvi Envirotech (P) Ltd.
2.6.10 Coal Pulveriser
The unit established a 30T/day capacity Pulveriser to supply the pulverised
coal to re-heating furnace. Pulveriser is thoroughly enclosed and emissions
are passed through the Bag Filter and chimney of the Re-heating furnace as
it is connected to the same.
2.7 Resource requirement for the project
2.7.1 Raw material requirement
The raw materials requirement for producing 200 TPD of MS Billets will be
232 TPD of different raw materials as specified in the below table.
The details of main raw materials and requirement after expansion are as
given in the table below 2.4.
Table 2.4
List of Raw Materials and Requirement after Expansion
S.No
Raw Material
Quantity
Source TPD TPA
1 Sponge Iron 140 49,000 Local & Neighboring states
2 Iron Scrap 80 28,000 Local & imported sources
3 Pig Iron 10 3,500 Local & Neighboring states
4 Ferro Alloys 2 1,400 Local & Neighboring states
Total 232 81,900
As, M/s.Devashree Ispat (P) Ltd established one Continuous Concast
Machine (CCM) in Unit - III, the molten metal is shifted to M/s.Devashree
Ispat (P) Ltd Unit - III which is adjacent to Unit – I.
The casted billets are conveyed in red hot condition by a conveyor system
to the Rolling Mill and are rolled into bars of different sizes.
The requirement of MS Billets for producing 800 TPD of different MS Rolled
products will be 850 TPD or 2,97,500 TPA.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-22
Pridhvi Envirotech (P) Ltd.
As the production of MS Billets in the Furnace Division will be 70,000 TPA
only, balance requirement will be taken from M/s.Devashree Ispat (P) Ltd
Unit – III.
2.7.2 Power Requirement
Power is required for operating the Induction Furnaces, Rolling Mill, Bag
Filter, ID Fan, Cooling Towers etc., and for general lighting in the plant.
Presently the connected load of 8.5 MVA is being sourced from TSSPDCL.
The total power requirement after expansion will be approximately 11 MVA
and the additional power required will be sourced from TSSPDCL.
2.7.3 Man Power Requirement
The total man power required after expansion will be 445 as against the
present 325 as detailed below.
The man power requirement for different purposes is given in the table
2.5.
Table 2.5 Details of Man Power Requirement
The man power includes technical, non-technical, administrative and skilled
& unskilled labor.
2.7.4 Water Requirement:
The total water requirement of the project after its expansion will be 243
KLD, out of this 98.0 KLD of water will be recycled back from cooling
towers. Thus total fresh water requirements will be 145 KLD. The fresh
water of 145.0 KLD will be purchased from private suppliers through
tankers. The water requirement for the present and proposed activities is
summarized in the table 2.6.
S No Division Present Proposed After Expansion
1 Induction Furnace 125 60 185
2 Rolling Mill 200 60 260
Total 325 120 445
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-23
Pridhvi Envirotech (P) Ltd.
Table 2.6
Water Requirement for present & proposed plant capacity
Stream
Water Requirement (KLD)
Present After expansion
Fresh Recycled Total
Induction Furnace,
Rolling Mill Cooling water ( Makeup)
75.0 100.0 75.0 175.0
DM Plant re-
generation water
2.0 4.0 - 4.0
Domestic 18.0 24.0 - 24.0
Dust Suppression - - 5.0 5.0
Green belt 10.0 17.0 18.0 35.0
Total 105.0 145.0 98.0 243.0
Currently the domestic waste water is let into septic tank followed by soak
pit. As a part of expansion, it is proposed to establish STP which can cater
to both units of M/s.Devashree Ispat (P) Ltd. Also it is proposed to provide
primary treatment plant for treating and recycling the Mill cooling water to
remove oil & grease and suspended solids.
2.7.5 Land Requirement
The existing project is spread over 42997.14 Sq mts. or 10.62 Acres of
land. Out of this 2.72 Acres is utilized for construction and 3.00 acres is
utilized for Green Belt area. The remaining area comprises of roads and
open area. Additional land requirement for the proposed expansion would
be 1.0 Acre for expansion of the plant facilities. It is proposed to add an
additional Green Belt of 0.54 acres with expansion activities. This additional
land of 1.54 will be utilized from existing open areas of the plant.
The land use statement for present & expansion project are presented in
Table 2.7.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-24
Pridhvi Envirotech (P) Ltd.
Table 2.7
Land Statement
S No Utilization Present After Expansion
Acres Sq.M Acres Sq.M
1 Total Built up area
Including stock yards
2.72 11007.84 3.72 15054.84
2 Green Area 3.00 12141.00 3.54 14326.38
3 Roads 1.08 4370.76 1.08 4370.76
4 Open Area 3.82 15459.54 2.28 9227.16
Total 10.62 42979.14 10.62 42979.14
2.8 Environmental aspects from different processes
Raw material handling
The Induction Furnace Units consumes Steel Scrap, Sponge Iron, Pig Iron
and other Ferro Alloys as needed. Dust generation during transport and
storage is expected.
Induction Furnace
The emissions from Induction Furnace include suspended particulate
matter, Oxides of Sulphur, Oxides of Nitrogen and Co2.
Slag Handling
Slag generated from the Induction Furnace needs to be disposed off. Slag is
crushed in slag crusher and iron is removed using magnets. Rest of the
crushed slag is used as land fill material and brick manufacturing.
Re-heating Furnace
Pulverized Coal is used for Re-heating Furnace. As Continuous Casting
Machine is used, Re-heating Furnace is kept as standby and will be used
only in case of any shutdown of rolling mill. SPM, SO2 and NOx are
emission from Coal re-heating furnace
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-25
Pridhvi Envirotech (P) Ltd.
Coal Pulverser: Pulverised coal is supplied to re-heating furnace by
crushing coal in pulveriser. There is possibility of dust generation from the
coal pulveriser
Fly Ash Handling
The ash handling from re-heating furnace will create fugitive dust
emissions.
Rolling Mill
Rolling Mill generates waste water used for cooling purpose. Water will be
continuously re-cycled after settling of heavy suspended matter in water.
Some amount of Oil & Grease would also be generated from Mill cooling
water.
Mill waste
The Mill Waste is primarily iron waste and having market value. The sludge
generated from cooling water settling tanks should be handled properly to
avoid land contamination.
2.9 Environmental Impacts & Control Systems
2.9.1 Water & Waste Water
Steel making is a heat intensive process wherein a considerable
quantity of cooling water is required for control of metallurgical
process. Water is mainly needed for cooling various furnace
components, rolling mill, domestic consumption and other uses.
Water is not used in manufacture of Billets & TMT bars. Water is
used only for cooling purpose. Water circulation systems are
planned to facilitate recycling and reuse of 98 KLD of return
water, after cooling in cooling towers. There is no generation of
waste water in the manufacturing process.
The daily total fresh water requirement for the plant after
expansion will be 145 KLD which would be outsourced from
private parties nearby. Fresh water will be utilized for cooling
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-26
Pridhvi Envirotech (P) Ltd.
water make up & Green Belt development. The total water
balance is given in table 2.8.
Table 2.8 Water Balance for present & proposed plant capacity
Stream
Water Requirement (KLD) Waste water Generation
(KLD)
Treatment
and disposal
method
Prese
nt
After expansion Pres
ent
After expansi
on
Fresh
Recycl
ed Total
Induction
Furnace Rolling Mill
Cooling water
(Make-up)
75.0 100.0 75.0 175.0 32.0 75.0 Cooling
water is continuously
recycled
after treatment
DM Plant 2.0 4.0 - 4.0 - - To be used for dust
suppression
Domestic 18.0 24.0 - 24.0 14.0 19.0 Proposed to treat in STP
and re-use back for
gardening purpose
Dust Suppression
- - 5.0 5.0 - -
Green Belt 10.0 17.0 18.0 35.0
Total 105.0 145.0 98.0 243.0 46.0 94.0 -
Currently the domestic waste water is let into septic tank followed by soak
pit. As a part of expansion, it is proposed to establish STP which can cater
to both units of Devashree Ispat (P) Ltd. Also it is proposed to provide
primary treatment plant for Rolling Mill Unit for treating and recycling the
cooling water to remove oil & grease and suspended solids.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-27
Pridhvi Envirotech (P) Ltd.
2.9.2 Air Emission Sources & Control
The details of emission sources and their control measures after expansion
are given in table 2.9.
Table 2.9
Air Emission Sources & Control
S No Emission
source Capacity
Stack Height
(M)
Emissions Control
Equipment
1 Induction
Furnace
200 TPD 30 SPM/NOX/SO2 Bag Filters
2 Reheating Furnace*
340 TPD 30 SPM/NOX/SO2 Bag Filters
3 DG set 1x125KVA Existing
5 M above DG set
room
SO2/ Nox/SPM Acoustic Enclosure
4 DG Sets 1x 150 KVA &
1x265 KVA Proposed
5 M above DG Room
SO2/ Nox/SPM Acoustic Enclosure
*In case when Direct Hot charged Billets through conveyor cannot feed the
Rolling Mill sufficiently, Billets from Re-heating Furnace will be fed. Hence
re-heating furnace is kept as standby only.
In case the Reheating Furnace is used in full capacity, the production
capacity would be 340 TPD.
Particulate emissions are the main sources of pollution from the proposed
activity.
It is proposed to enhance a high efficiency fume extraction system with Bag
Filters for both primary and secondary duct extraction system designed to
extract the dust and meet the emissions norms of 100 mg/Nm3 at stack
level as per CPCB guidelines in both Furnace Division and in Rolling Mill
Division.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-28
Pridhvi Envirotech (P) Ltd.
2.9.3 Fugitive Dust Suppression
Fugitive dust is generated from the roads during transportation of raw
materials and finished products within the plant.
Slag generated from the plant is transferred to Unit III where Slag Crusher
is established. Bag filter with fume extraction system is proposed for slag
crusher.
Fugitive emissions may also likely to be generated during coal and ash
handling system. Coal Pulveriser is enclosed and fume extractions are
cleaned in bag filter (Combined bag filter for re-heating furnace and coal
pulveriser).
Cement roads are laid within the plant area. Dust generation is observed in
FG Stock yard.
Currently Tractor mounted water tanker is deployed for sprinkling water in
the areas within the plant premises and along the approach roads regularly.
It is proposed to establish water sprinklers wherever dust generation is
anticipated.
2.9.4 HAZARDOUS & SOLID WASTE GENERATION AND HANDLING:
Hazardous and Non Hazardous wastes generated from operations of the
project and mode of disposal are presented in the table 2.10 and table
2.11 respectively.
Table 2.10 SOLID WASTE GENERATION DISPOSAL:
S No
Non
Hazardous Waste
Quantity
Disposal Option Present
After Expansion
1 Slag after
recovering iron content
3000 TPA 7000 TPA Disposed for filling low level
areas and to construction sites. Also extensively being
used for brick manufacturing
2 Mill waste &
ETP sludge
1000 TPA 4000 TPA Sold to secondary steel
manufacturers and paint
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-29
Pridhvi Envirotech (P) Ltd.
industries
3 STP Sludge - 10 TPA Used as manure for Green
Belt
4 Bottom ash
from the Re-heating
Furnace
1500 TPA 1500 TPA Disposed to brick makers and
cement plants. Currently Re-heating Furnace is kept as
stand by and very little ash is
generated
5 Dust trapped
in Bag filters and other
pollution control
equipment
100 TPA 200 TPA To be sent as land fill
material along with crushed slag
Table 2.11
HAZARDOUS WASTES WITH RECYCLING OPTION:
S No Hazardous
Waste
Quantity
Disposal Option Present
After
Expansion
1 Waste Oil 100 Lit/yr
400 Lit/yr Will be purified and re-used/To be sent to
Authorized Re-processors / Re-cyclers
2 Used Lead
Acid Batteries
2
Nos./yr
6 Nos./yr To be returned to
manufacturers / dealers on buy back
basis
2.9.5 Noise Pollution
Noise is anticipated from Furnace, Rolling Mill and DG sets. The
DG sets will be kept in separate rooms with acoustic enclosures.
The employees working in noise generating areas wi ll be
provided with earmuffs.
The employees will be trained in the mitigation measures and
personal protection measures to be taken to avoid noise related
health impacts.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-30
Pridhvi Envirotech (P) Ltd.
2.10 Current Environmental Control Mechanisms & Gaps
As this is brown field project and going for expansion activity. It
is essential to assess the current scenario of environmental
impacts from the current operations and controls and to assess
the adequacy of current Environmental Management practices.
Below table summarizes the current scenario and suggested
improvements.
Table 2.12:
Current scenario and suggested Improvements
S.NO Source
Current
control system
Current scenario
Suggested improvements
I Air Pollution
1 Induction
Furnace
Bag Filters Currently both
Primary and Secondary
Hoods are
connected to Bagfilter
As proposed to
upgrade the furnace from
100 TPD to 200
TPD, it is suggested to
upgrade the existing bagfilter
and ID fan to meet the higher
capacity of the furnace.
2 Slag handling Generated slag is transferred
to unit III for
slag crushers
Current system is adequate
None specific
3 Dust from coal pulveriser
Closed system is provided and
pulveriser transfer points
are connected to bag filters
adequate No additional measures
required. As re-heating furnace is
only stand by, use of coal
pulveriser is very limited
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-31
Pridhvi Envirotech (P) Ltd.
4 Emissions
from re-
heating furnace
Currently bag
filter is
provided for control of dust
emissions from re-heating
furnace
Adeqate No additional
measures
required. Re-heating furnace is
kept as stand by only
5 Dust from
Roads
Tractor with
sprinklers are wetting roads
Dust
generation is observed
It is suggested to
establish sprinklers.
II Water Pollution
1 Mill Cooling
water
Water is settled in
settling tanks and re-used
Not adequate Suggested to
provide primary treatment for mill
cooling waste water as it contain
oil and grease and suspended solids
2 Domestic
waste water
Currently about 325
Employees are working in the
factory. After expansion 445
employees will be there. Domestic
effluents are send to septic tank
followed by soak pit
Water re-use is
not there
It is
suggested establish STP for
both units and re-use the treated
domestic waste water for
plantation purpose
III Solid Waste Management
1 Slag waste Slag waste is crushed and crushed
waste is used for land filling purpose.
The slag crusher is established in unit
III
Current system is adequate
None
2 Mill Waste Mill waste is being
sold to Sponge Iron Plants
Mill waste will
be sold to Sponge Iron
Plants
It is
suggested to provide impervious
plat form for de-watering mill
waste
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-32
Pridhvi Envirotech (P) Ltd.
IV Storm Water Management & Rain water harvesting
1 Storm water Currently few
cement drains established for
proper flow of storm water
Not adequate It is suggested to
upgrade storm water
management in the site wherever
water logging is reported in heavy
rain period
2 Rain water harvesting
unlined surface water collection
pond at the entrance gate in the
North-East, of dimensions 47m X
23m with average depth of 4m
Rain water is adequately re-
charged currently by
the existing pond
Total storm water anticipated is
directed to the existing pond rain
water pond.
V Green Belt Development
1 Greenery Out of total 10.62
acres green belt is developed in
about 3.0 acres
Currently
green belt is developed in
3.0 acres. As per the norm
33% green belt shall be
developed
It is proposed to
increase green belt by 0.54 acres to
make. The total area for green belt
after expansion will be 3.54 Ac.
VI Occupational Health and Safety
1. Personal
Protective equipment
Helmets, Shoes, nose
masks are provided to employees working in
shop floor and
material handling areas
Enforcement
needs improvement
It is suggested
to conduct frequent
training on
awareness classes to
employees on wearing the
PPEs
2 Firefighting
equipment
Portable fire
extinguishers are provided at all
vulnerable points
As per the fire
department norms, current
facilities are
adequate
It is suggested
to provide diesel run pump
and fire hoses
as improvement measures to
takle emergency fires
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-33
Pridhvi Envirotech (P) Ltd.
3 Emergency
siren
Siren for emergency
evacuation
Siren is
provided in
production areas of
Furnace and Rolling Mill
It is suggested
to conduct
mock drill once in six months
4 Ambulance 24 hour vehicle availability is
there in the plant to meet any emergency
Adequate Adequate
5 Fire Tenders Nearest fire tender is available at
Shadnagar which is 7 KM from site
Adequate. Water storage
sump at the plant is
currently there which can hold
400 M3
Adequate. Emergency
telephone numbers shall
be maintained by emergency
controller. Suggested
Emergency Diesel operated
pump & Fire
hoses
6 Health
Monitoring
Currently all
employees health are checked at the factory
premises by a Regd Medical Practitioner
Needs
improvement in maintenance of
health surveillance
records
It is suggested
to establish the health
surveillance system as
described in EIA report
7 Occupational Health
Center and First Aid
facilities
First Aid facility is established in the
plant with adequate trained staff
Need to enhance the
facilities
Periodic training is required for
in house personnel
8 Tie up with
Local Hospitals
Local Government and
private nursing homes identified
Need to
enter into formal
agreement with hospitals for
emergency care
It is suggested
to enter into formal
agreement with private &
government Nursing homes
in Shadnagar area
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
2-34
Pridhvi Envirotech (P) Ltd.
VII – Environmental Monitoring program
1 Regular
monitoring of emissions
Regular monthly
monitoring is done by NABL
Accredited recognized
agency and reports are
submitted
Regular
monthly monitoring is
done by NABL Accredited
recognized agency and
reports are maintained
It is suggested to
establish the environmental
monitoring program as
prescribed in EIA report
VIII – Staffing for EMP Implementation
1 Environmental
Management cell
Presently 8
Employees are there to take
care of the
Pollution Control
Equipment
In all 8
Employees will be there to take
care of the
Pollution Control Equipment
Dedicated staff
for Environment & Safety is
suggested for
implementation and monitoring
Current inadequacies are addressed in Environmental
Management Plan and budget provisions are proposed for
effective implementation.
Chapter-3
BASELINE ENVIRONMENTAL STATUS
M/s. DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-1
Pridhvi Envirotech (P) Ltd.
CHAPTER 3
BASELINE ENVIRONMENTAL STATUS
3.1 Preamble
Collection of base line data is an integral aspect of the preparation of
environmental impact assessment report. Baseline data reflects the present
status of environment before the initiation of any activity of the proposed
project. The possible effects due to the proposed expansion project of
M/s.Devashree Ispat (P) Ltd are estimated and superimposed on the
compiled baseline data subsequently, to assess environmental impacts.
Baseline environment assessment was conducted in the impact zone of 10
km surrounding the site area during the months of December 2017 -
February 2018. Studies were undertaken to generate baseline data of
micrometeorology, air quality, water quality, noise levels, flora and fauna,
land use, soil quality, Ecology biodiversity and socio-economic status of the
community were collected in a circular area of 10 km radius surrounding
the project site.
3.2 Methodology of Base line data collection
3.2.1 Scoping
The scope of the assessment for this study was determined by the Terms of
Reference, granted by Ministry of Environment, Forests & climate change, by
the State level Expert appraisal Committee and approved by SEIA,
Telangana. An initial discussion with the project proponents and other stake
holders was conducted in the study area so that the focus would be on
valued ecosystem components (VECs) they considered important.
3.2.2 Reconnaissance Surveys
The study team made initial site visit to ascertain basic information on
various aspects like availability of infrastructure, physiological condition of
the project site, surroundings of the site such as road connectivity, nearby
population, nearby water bodies & neighboring industrial activity etc. The
M/s. DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-2
Pridhvi Envirotech (P) Ltd.
information collected has been used for identifying the valued eco
components to be chosen for specific consideration in the study.
3.2.3 Assembly and Analysis of Data
The data from initial surveys was recorded. Various work sheets are used for
collection base line data by various functional area experts focusing on
different components of EIA study. The Supplementary information was
collected from Survey of India topo sheets, census handbooks, published
flora and fauna data etc. Standard statistical techniques were used for
analysis of the socio-economic data, etc. Qualitative analysis was done for
more descriptive data.
3.2.4 Documentation of Baseline Conditions
The documentation of the baseline conditions was completed for a 10km
radius circle from the site Project influence Area (PIA) as per the MoEF
guidelines. Primary surveys were carried out for determination of ambient air
quality, water quality, noise quality and socio economic conditions of nearby
residents etc. A detailed ecology survey was also conducted to determine
base line conditions of biotic environment in core and buffer zones of the
study.
3.2.5 Assessment of Alternatives
Alternatives of the project site is not relevant in this case as this project is
expansion of existing unit.
3.2.6 Assessment of Potential Impacts
Potential significant impacts were identified on the basis of analytical review
of baseline data; review of land uses and environmental factors; analytical
review of the socio-economic conditions within the PIA; biotic environment in
study zone.
M/s. DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-3
Pridhvi Envirotech (P) Ltd.
3.2.7 Integration of Environmental Impacts in the Design Process:
Environmental Component
The design and decision – making process integrated environmental and
social issues and prompted the early identification of appropriate actions.
Such actions included, for example, optimizing the layout, use of existing
infrastructure with both units, current air pollution control systems and
improvements, measures for water conservation, measures for solid waste
management etc.
As this is brown field project, existing environmental infrastructure is
reviewed and gaps are identified for improvements in the expansion project
3.3Land Environment
Land and soil constitute the basic components of the physical environment.
The expansion of this unit may not cause significant changes in land, land
use, soil and denudation processes.
3.3.1 Physiography
M/s.Devashree Ispat (P) Ltd Unit I, propose the expansion project in the
existing plant premises at Sy.Nos.458,459 & 460, Ellikatta(V), Farooq
Nagar (M), Rangareddy District, Telangana State. The project site is about
6.62 Km away from the NH44 (old name NH7) on the east north east. The
nearest habitation is at about 0.6 Km i.e., the Maleellikatta village in SE
direction. The nearest railway station is Shadnagar Railway station at a
distance of 6.2 km from the site on the East. There are no sanctuaries,
ecologically sensitive areas or national parks within 10 km radius of the
site.
3.3.2 Topography:
M/s. Devashree Ispat (P) Ltd site is in Ellikatta village, Farooq
Nagar mandal of Rangareddy District, and is located 0.87 km
North East of village. The site is accessible from the National
Highway No.44, through Shadnagar – Pargi Road. The study area
M/s. DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-4
Pridhvi Envirotech (P) Ltd.
is as well shown in Topo Sheet Nos. 56 K4 & 56 L1 of the Survey
of India.
Project Site is situated on the high surface relief at an altitude of about 650
meters Above Mean Sea Level (AMSL). The neighborhood area is of
undulating terrain with rocky knobs at places. The East-West running
Shadnagar and Pargi Road up to Moghaligidda village follows an elevated
region which divides the total area into north and south sloping segments
between Shadnagar in the east and Moghaligidda in the west. Taking
advantage of high relief, water supply pipe laying work of Pranhitha-
Chevella. Water Supply Scheme is under progress along the Road.
In the Northern segment the surface elevation is maximum of 660 meters
AMSL. The surface slope in the northern segment is towards north-east and
north. In the southern segment, land gradient is towards south-east and
south. The northern and southern surface gradients are relatively higher
than the north-eastern and south-eastern surface slopes. The overall
surface elevation in an area of about 10 km radius ranges from 660 to 620
meters AMSL.
The Google map showing the project area and its surroundings is as shown
in figure 3.1
M/s. DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-5
Pridhvi Envirotech (P) Ltd.
Figure-3.1: Google map showing the project area and its
surroundings
3.3 DRAINAGE
Morpho-Metric parameters such as drainage density and slope
characteristics provide a basis for evaluation of run-off and
ground water potentials of a drainage basin. Total drainage basin
areal extent determines the total quantity of water available in a
basin. A low network of drainage courses is indicative of the
presence of highly resistant or highly permeable rocks on the
surface. High drainage density characterizes hilly terrain and
areas underlain by weak or impermeable rocks result in more
run-off than infiltration. Low network drainage density
corresponds to high infiltration rates.
M/s. DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-6
Pridhvi Envirotech (P) Ltd.
Topo map of the study area and Water shed details of proposed
project site is given in Figure 3.2.
Figure 3.2 Topomap Showing Drainage distribution and
water shed of the study area.
3.4 Land use Pattern
Land use / Land cover Classification of the Study area
Based on the scale and the satellite resolution the Land Use/Land Cover
classification can be made. The satellite data of IRS LISS IV was used while
carrying out the analysis. Digital image processing was carried out to
delineate various land use / land cover categories viz. build up area, crop
areas and forests, waste lands such as land with or without scrub, water
bodies and Transportation. The interpreted map was verified on ground at
limited points and final land use / land cover map was prepared.
The Satellite image of the study area is given at Figure 3.3 and land use
and land cover map of the study area is given at Figure3.4
M/s DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-7
Pridhvi Envirotech (P) Ltd.
Figure 3.3 Satellite image of the study area
M/s DevashreeIspat (P) Ltd Unit-I Draft EIA Report
3-8
Pridhvi Envirotech (P) Ltd.
Figure 3.4 Land Use and Land Cover map of the study area
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-9
Pridhvi Envirotech (P) Ltd.
Below table provides land use for various requirements in the study area
TABLE 3.1
Land Use/Land Cover classes in Study area
LULC PATTERN AREA (IN SQ/KM) AREA (IN %)
Built Up Area 7.065 2.25
Agricultural Land 288.287 91.60
Open Shrub 10.522 3.34
Water Bodies 8.825 2.80
TOTAL LAND 314.729 100.00
The Pie diagram of the land use is given in Figure 3.5. Based on the study it can
be noted that, it is predominantly agriculture area with 91.60% land area is
Agricultural Land, 3.34% is Open Shrub, 2.25% is Built Up area and 2.80% is
Water Bodies are there in the study area.
Figure 3.5
Pie Diagram Showing Land use & Land cover area
2%
92%
3% 3%
Pie Graph Showing LULC Pattern of
M/s Devashree Ispat (P) Ltd (Area In %)
BUILT UP AREA
AGRICULTURE LAND
OPEN SCURB
WATERBODIES
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-10
Pridhvi Envirotech (P) Ltd.
3.5 Geology
Geological formations occurring in the project site and its watershed area are of
igneous in origin. They were emplaced beneath crystal layers at hypabyssal
depths (intermediate depths) by the hot acidic and basic magmas at different
time periods in the geological past. After undergoing a number of tectonic events
like orogenic (mountain building activity) destructional and denudational
processes of rock disintegration and decomposition, the present day land
configuration has come in to existence in the area. The generalized rock
sequence of the area is as under.
Eocene Deccan traps Dark colored Basalts
Pre-
Cambrian
Archaean
Group
Peninsular
Gneissic
Complex
Younger
Intrusive
Epidote Veins, Quartz Veins
Dolerite Dykes, Pegmatite
Veins, Quartz Feldspathic Veins
Migmatite
Group
Granites:
Biotite- Hornblende- Granite-
Gneiss; Migmatite Gneiss,
Granitoid
Larger part of the area is occupied by highly undulating rocky out-crops and
ridges of Granitic formations without much soil cover on them. At places they
show gneissosity with linear arrangement of mafic minerals associated in the
rock assemblage. They are hard, massive and blocky in nature standing out
prominently as remnants of destructional and denudational processes of rock
disintegration and decomposition.
Granites and granite gneisses are fine grained, coarse to very coarse grained and
blocky with widely spaced joints having pink feldspar and quartz as major
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-11
Pridhvi Envirotech (P) Ltd.
minerals. They occur as isolated rocky Knobs and ridges occupying the surface
relief highs. Very hard, fine grained, brittle and un-weathered fresh granite
outcrops occur at number of places. They are being extracted and used as road
metal and building material.
At places these granite formations are intruded by basic and acidic rock
formations of later period. Dark coloured dolerite intrusions emplaced along
major tensional joints developed in the parent rock during tectonic activity in the
earth’s crust, occur as linear features cutting across the host rock extending
several meters as at Moghiligidda village south of road, south-west of Pidikiriyal
village and north of Hajipalli.
Basic lava flows of Eocene Period covering the granite formations occur in the
north-western part of the area beyond Mughalgidda village covering the
Bodampahad and Monmeri village areas. The areal distribution of the rock
formations is shown in the Figure-3.6.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-12
Pridhvi Envirotech (P) Ltd.
Granite Rock
Figure-3.6: Areal Distribution of the Rock Formations
Dolerite Dyke
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-13
Pridhvi Envirotech (P) Ltd.
3.6 Water Environment
The industrial development of any region is contingent on the
availability of sufficient water resources, as most of the process
industries would require water for process or cooling purposes. The
potential for exploitation of ground water resources increases as
development of new projects increases in industrial and agricultural
areas. With the increasing industrial ization and urbanization the
possibilities of contamination of surface water and ground water
sources are rapidly increasing. The water resources in the area
broadly fall into following categories:
1. Ground Water resources : Accumulation in deeper strata of
ground.
2. Surface Water resources : Streams, ponds, etc.
3.6.1 GROUND WATER CONDITIONS
General Features:
Geomorphic features, Climate and Rainfall, Topography and Land
Slope, Drainage pattern, Soils and Agricultural activities and
ultimately the nature, thickness, distribution and structure of
different geological formations, independently or collectively or in
association with each other play a distinct role in the occurrence,
movement, quality and availability of Ground Water.
Geographical set-up and Geomorphic features control, in a large
measure the amount of precipitation that contributes to run off and
ground water recharge. Dry conditions in arid and semi-arid climatic
conditions results in large scale evaporation losses, promotes
oxidation processes and results in the deep ground water level.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-14
Pridhvi Envirotech (P) Ltd.
High rainfall contributes higher amounts of infiltration and deep
percolation to recharge ground water. Development of land forms
mainly depends upon the nature of the rocks, their resi stance to
erosion and the geologic structure, climatic conditions and vegetative
cover.
Morpho-Metric parameters such as drainage density and slope
characteristics provide a basis for evaluation of run-off and ground
water potentials of a drainage basin. Total drainage basin areal
extent determines the total quantity of water availab le in a basin. A
low network of drainage courses is indicative of the presence of
highly resistant or highly permeable rocks on the surface. High
drainage density characterizes hilly terrain and areas underlain by
weak or impermeable rocks result in more run-off than infiltration.
Low network drainage density corresponds to high infiltration rates.
3.6.2. Project Site Area:
The project site is existing industrial unit underlain by granitic
formations.
3.6.3 Climate and Rain Fall:
The average annual rainfall of the district is 833 mm, which ranges from no
rainfall in January and December months to 190 mm in July. July is the wettest
month of the year. The mean seasonal rainfall distribution is 652 mm in south-
west monsoon (June-September), 114 mm in north-east monsoon ( Oct-Dec), 4
mm rainfall in Winter (Jan-Feb) and 63 mm in summer (March – May). The
percentage distribution of rainfall, season-wise, is 78.3% in south-west
monsoon, 13.7 % in northeast monsoon, 0.5 percentage in winter and 7.6 % in
summer. The annual and seasonal rainfall distribution along with percentage
distribution and their departure from mean for year-wise is given in Table.3.2
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-15
Pridhvi Envirotech (P) Ltd.
Table.3.2 Annual & Seasonal Rainfall, Departure from Mean Percentage
Distribution
3.6.4. Water-shed and Neighborhood Areas:
Project Site is located on the boundary of northern Musa Nadi watershed. Both
Musa nadi water shed and bhimavaram water shed are in catchment of Dindi
River. Overall the site and surroundings falls under river basin the Krishna.
Important surface water storage bodies are at Choulapalli, Devunpalli,
Rangareddinagar, Sardarnagar, Krishnanagar and Kesaram villages. During
monsoon season depending on the amount of rainfall received in the watershed
area they receive the flows and support the ayacut area cultivation in the Khariff
period.
The Topography and Drainage of the area is shown in the Figure-3.8
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-16
Pridhvi Envirotech (P) Ltd.
Figure-3.8: Topography and Drainage of the Project Site Neighborhood
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-17
Pridhvi Envirotech (P) Ltd.
3.6.5 Field study and discussion:
During the field study, depth to water levels and total depth of wells
were measured using embossed steel measuring tape. Quality of
ground water in terms of its Specific Electrical Conductance values
was measured by using a sensitive pocket type Electrical Conductivity
Meter. The hydro-geological data of wells inventoried and location of
wells is shown in the Google Map Vide Figure-3.7
Field Agricultural Bore Well
Ground Water Level
Measurement
Industry Bore Well
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-18
Pridhvi Envirotech (P) Ltd.
Figure3.9:Location of Wells inventoried-Google Map
The following conclusions are drawn from filed study
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-19
Pridhvi Envirotech (P) Ltd.
Table 3.3
Salient features of ground water conditions in the project area
S.NO Parameters Field observation
1 Ground water usage Drinking water
purposes, agriculture
and industrial uses
2 Types of wells Mostly bore wells
3 Average depth of bore wells 45 to 150 meters
4 Minimum depth of water levels
observed in the area
3 –9 meters
5 Ground water level fluctuations
in the water shead area
4- 6 meters
6 Well yields during monsoon 6-10 M3/hour
7 Well yield during dry season 4-6 M3/hour
3.7 GROUND WATER RESOURCE POTENTIALS
Ground Water Resources Estimation Committee (GEC–1997) revised
the norms and circulated methodology in the year 1997. Following
the revised methodology watershed / basin wise assessment has been
done taking into account long term pre-monsoon and post-monsoon
water level trends.
Devashree Ispat (P) Ltd Project Site is in the Farooqnagar Mandal.
This Mandal area was included in the Mahabubnagar District and it
formed the MBNR_D_44_Balanagar drainage basin assessment Unit.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-20
Pridhvi Envirotech (P) Ltd.
Mandal wise and Unit wise ground water resources potentials have
been estimated by the SGWD based on the long period average values
following the Estimation Methodology. At present, the mandal and the
area assessment unit are falling under the Rangareddy District.
Latest approved and accepted Ground Water Resource estimations is
given in the table 3.4
As per the estimates, the assessment unit area with Stage of Ground
Water Development as 10% falls under Safe Category. The mandal
area with 84% of Development also remains in the Safe Category as
there is no significant reported long term pre-monsoon and post –
monsoon ground water level declining trends with resource
development potential remaining in the range of more than 70% and
but less than 90%.
Table-3.4 Ground Water Resource Estimations
1. Ground Water Resources Assessment area.
MBNR_ D_ 44_ Balanagar
Farooknagar/Shadnagar
2. Recharge from rainfall during monsoon (ha m)
3639 1694
3. Recharge from other sources during monsoon (ha m)
117 257
4. Recharge from rainfall during non-monsoon (ha m)
1411 479
5. Recharge from other sources during non-monsoon (ha m)
180 379
6. Total Ground water Recharge (ha m) 5134 2809 7. Natural discharge curing non-monsoon
(ha m) 513 281
8. Net annual ground water availability (ha m)
4621 2528
9. Existing ground water draft for irrigation (ha m)
428 2012
10. Existing ground water draft for domestic and Industrial
54 105
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-21
Pridhvi Envirotech (P) Ltd.
use (ha m) 11. Existing gross ground water draft for all
uses (ha m) 482 2117
12. Allocation for domestic and Industrial requirement for next 25 years (ha m)
151 327
13. Net ground water availability for future irrigation (ha m)
4042 189
14. Stage of ground water Development (%) 10 84 15. Is there significant decline of pre-
monsoon water table NO NO
16. Is there significant decline of post-monsoon water table
NO NO
17. Categorisation of Assessment Unit SAFE SAFE
3.8 GROUND WATER QUALITY
Quality of ground water can be expressed in terms of Specific
Electrical Conductance (E.C.) which is a measure of dissolved salt
content. The location of Bore wells and other sources examined are
shown in the figure 3.8. The permissible limits of E. C. for drinking
and irrigation purposes respectively are 1500 and 2000 µ/cm at 25
°C.
EC Measrement
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-22
Pridhvi Envirotech (P) Ltd.
The samples were collected from 8 Bore Wells around Project Site in
10 km radius i.e., Kisan Nagar, Elikatta, Rangapalli, Mughalgidda,
Chowlapalli, Project Site, Sardar Nagar and Farooqnagar and got
them analyzed for associated parameters. The sampling location map
of the area is given in Figure 3.11. Summarized Results of Chemical
Analysis of Ground Water Samples is shown in the Table -3.5.
Fig.3.10. Ground water sampling locations in Study area
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-23
Pridhvi Envirotech (P) Ltd.
Table.3.5.
Summarized Chemical analysis of Ground Water
S. No.
PARAMETER
Metho
d APHA 22nd
Edition
Unit
RESULTS As per IS:10500 -
2012
KISHAN
NAGAR
Elkat
ta
Ranga
mPalli
Mogalgi
dda
Chowlap
alli
DEVA
SHREE
(PROJAREA)
Sardar
Nagar
Farooqna
gar
Requirement
Acceptable limit
Permissi
ble limit in the
absence
of alternati
ve source
1 pH 4500 H+B
−− 7.30 7.45 7.64 7.67 7.50 7.42 7.57 7.49 6.50 -
8.50 NS
2 Colour (Hazen units)
2120 B Hazen
<01 <01 <01 <01 <01 03 <01 <01 5 max 15 max
3 Total dissolved solids
2540 C mg/l 372 379.0
0 386 390.60 378.00 867
884.00
402.00 500 max 2000 max
4 Total alkalinity as CaCo3
2320 B mg/l 143 145.0
0 151 150.15 148.00 373
379.00
147.00 200 max 600 max
5 Total hardness as CaCo3
2340 C mg/l 164.6
5 167.0
0 130 172.88 127.00 470
479.00
127.00 200 max 600 max
6 Calcium as Ca
3500 Ca B
mg/l 39.20 40.00 40 41.16 39.00 96 97.00 39.00 75 max 200 max
7 Magnesium as Mg
3500-Mg B
mg/l 16.20 16.50 7.30 17.01 7.15 55.90 57.00 7.20 30 max 100 max
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-24
Pridhvi Envirotech (P) Ltd.
8 Sulphates as SO4
4500 SO4D
mg/l 38.40 39.10 12 40.32 11.70 75.40 77.00 11.80 200 max 400 max
9 Chlorides as Cl
4500 Cl-C
mg/l 93.96 95.80 20 98.66 20.00 175.14 178.0
0 19.50 250 max
1000 max
10 Lead as Pb
3111B mg/l <0.00
1 <0.001
<0.001 <0.001 <0.001 0.006 0.01 <0.001 0.01 max No
relaxation
11 Cadmium as Cd
3111B mg/l <0.00
1 <0.001
<0.001 <0.001 <0.001 0.003 0.00 <0.001 1 max No
relaxation
12
Total Chromium as Cr
3111B mg/l <0.00
1 <0.001
<0.001 <0.001 <0.001 <0.00
1 <0.00
1 <0.001 0.05 max
No relaxation
13 Copper as Cu
3111B mg/l 0.009 0.01 0.014 0.01 0.01 0.036 0.04 0.01 0.05 max 1.5 max
14 Zinc as Zn
3111B mg/l 0.005 0.01 0.021 0.01 0.02 0.048 0.05 0.02 5.0 max 15 max
15 Nickel as Ni
3111B mg/l <0.00
1 <0.001
<0.001 <0.001 <0.001 <0.00
1 <0.00
1 <0.001 0.02 max
No relaxation
16 Flourides as F
4500 F-D
mg/l 0.62 0.63 0.50 0.65 0.48 0.89 0.90 0.49 1.0 max 1.5 max
17 Aluminium as A1
3500 Al B
mg/l <0.00
1 <0.001
<0.001 <0.001 <0.001 0.026 0.03 <0.001 0.03 max 0.2 max
18 Boron as B
4500 B B
mg/l 0.25 0.26 0.36 0.26 0.35 0.62 0.63 0.35 0.5 max 1 max
19 Manganese as Mn
3111 B mg/l 0.004 0.004 0.008 0.00 0.007 0.031 0.03 0.007 0.1 max 0.3 max
20 Iron as Fe
3500 Fe B
mg/l 0.29 0.30 0.21 0.30 0.21 0.37 0.38 0.21 0.3 max No
relaxation
21 Nitrates 4500 mg/l 5.60 5.71 1.86 5.88 1.82 16.10 16.40 1.82 45 max No
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-25
Pridhvi Envirotech (P) Ltd.
as NO3 NO3B relaxation
22 Sodium as Na
3500 Na B
mg/l 70.18 71.50 25.90 73.69 25.40 105.92 108.0
0 25.30 NS NS
23 Potassium as K
3500 K B
mg/l 2.20 2.20 5.20 2.31 5.10 8.41 8.58 5.10 NS NS
24 Odour 2150 C −− Agreeable
Agreeable
Agreeable
Agreeable Agreeabl
e Agreea
ble Agreeable
Agreeable Agreeabl
e Agreeable
25 E.C (micromhos/cm)
2510 B µmho/cm
640.00
652.80
386 672.00 378.00 1,422 1450.
44 378.20 NS NS
26 Phosphorus as P
4500 P B
0.12 0.12 0.25 0.13 0.25 0.58 0.59 0.24 NS NS
27 Carbonates as CaCo3
2320 B mg/l Nil Nil Nil Nil Nil Nil Nil #VALUE! NS NS
28 Bicarbonates as Hco3
2320 B mg/l 174.4
6 177.9
0 184.22 183.18 180.50 454.45
463.53
180.53 NS NS
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-26
Pridhvi Envirotech (P) Ltd.
The results indicate that ground water is of average natural type
with pH ranging from 7.30 to 7.67. Against desirable limit of 250
mg/l and permissible limit of 1000 m/l of Chloride, ground water
samples had a minimum of 19.5 mg/l and maximum of 178 mg/l
indicating that ground water is within the limits of good taste, its
palatability is not affected. Total Hardness of ground water ranged
between 127 mg/l and 479 mg/l and is well within the limits of 300
– 600 mg/l (permissible and acceptable levels) . Total Dissolved
Solids ranged from 372 mg/l to 884 mg/l. showing low salt content
at all places well within the permissible ranges of 500 and 2000
mg/l respectively. The low values are attributable to the dilution
through good recharge from upper terrain storm water flow. At
sardarnagar village ground water is found to possess Cadmium and
Lead beyond acceptable limits for drinking purposes. Ground water
is found less mineralized with no harmful substances and all the
chemical constituents well within the suitable limits for drinking
and all other purposes.
3.9 Surface Water Quality
Project Site is located on the boundary of northern Musa Nadi
watershed. Drainage area of Musa River sub basin and southern
Bhimawaram Nadi watershed are part of catchment of Dindi River
sub basin total drainage area of the major river basin the Krishna.
Surface water samples were collected from 4 minor irrigation tanks
i.e. Kishan Nagar Cheruvu, RangampalliCheruvu, Mogalgidda
Cheruvu and Sardar Nagar Cheruvu. The map showing the surface
water bodies is as shown Figure 3.12.
Summarized results of chemical analysis of surface water samples
are shown in the Table-3.6.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-27
Pridhvi Envirotech (P) Ltd.
Devunipalli
Sardarnagar
Krishnanagar Bhimawaram Nadi -
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-28
Pridhvi Envirotech (P) Ltd.
Figure 3.11 Locations of surface water samples in the study area
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-29
Pridhvi Envirotech (P) Ltd.
Table 3.6
Summarized Chemical Analysis of Surface Water
S.No. PARAMETER
Method
APHA 22nd
Edition
Unit
RESULTS
Kishan
Nagar
Chervu
Rangamp
alliChervu
Mogalg
idda
Chervu
Sardar
Nagar
Chervu
1 pH 4500 H+B −− 8.32 8.16 8.28 8.04
2 Color (Hazen units) 2120 B Hazen 04 03 05 06
3 Odour 2150 B −− Disagreable Agreable Agreabl
e Disagreable
4 E.C (micromhos/cm) 2510 B µmho/cm 524 347 243 279
5 Dissolved Oxygen 4500-O C mg/l 2.30 2.80 1.90 2.50
6 Turbidity (NTU) 2130 B NTU 2.60 1.10 3.20 1.60
7 Total Suspended Solids 2540 D mg/l 34 25 48 31
8 Total dissolved solids 2540 C mg/l 316 182 136 154
9 Chemical Oxygen Demand 5220 B mg/l 41 36 30.00 58
10 Biochemical Oxygen Demand IS 3025(Part-
44) 2009 mg/l 8.50 5.90 3.50 10.20
11 Total alkalinity as CaCo3
2320 B mg/l 136.65 114.40 80.10 92.16
12 Total hardness as CaCo3
2340 C mg/l 108 52 36.40 41.90
13 Calcium as Ca 3500 Ca B mg/l 28.8 14.50 9.8 12.6
14 Magnesium as Mg 3500-Mg B mg/l 8.75 3.90 2.9 2.53
15 Sulphates as SO4
4500 SO4D mg/l 36.00 18.00 12.60 14.50
16 Chlorides as Cl 4500 Cl-C mg/l 58.15 26.24 18.40 21.20
17 Lead as Pb 3111 B mg/l 0.14 0.08 0.05 0.02
18 Cadmium as Cd 3111 B mg/l 0.09 0.04 0.01 0.003
19 Total Chromium as Cr 3111 B mg/l 0.06 0.02 0.008 0.005
20 Copper as Cu 3111 B mg/l 0.25 0.17 0.13 0.07
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-30
Pridhvi Envirotech (P) Ltd.
21 Zinc as Zn 3111 B mg/l 0.31 0.26 0.19 0.22
22 Nickel as Ni 3111 B mg/l 0.12 0.08 0.03 0.09
23 Flourides as F 4500 F-D mg/l 0.56 0.49 0.42 0.36
24 Aluminium as Al 3500 Al B mg/l 0.07 0.03 0.005 0.007
25 Boron as B 4500 B B mg/l 0.68 0.45 0.36 0.41
26 Manganese as Mn 3111 B mg/l 0.03 0.06 0.01 0.005
27 Iron as Fe 3500 Fe B mg/l 0.37 0.28 0.22 0.32
28 Nitrates as NO3 4500 NO3B mg/l 7.25 4.15 2.90 3.34
29 Sodium as Na 3500 Na B mg/l 67.50 54.65 38.26 44
30 Potassium as K 3500 K B mg/l 5.71 2.11 1.48 1.70
31 Phosphorus as P 4500 P B mg/l 1.20 1.58 1.02 0.85
32 Oil & Grease 5520 B mg/l <1.0 <1.0 <1.0 <1.0
33 Total Coliform IS 1622 MPN/100 ml 274 210 180 162
34 Feacal Coliform IS 1622 MPN/100 ml Present Present Present Present
35 Bicarbonates as Hco3 2320 B mg/l 166.72 139.57 97.73 112.40
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-31
Pridhvi Envirotech (P) Ltd.
Surface water is found to be of poor quality in terms of odour (in
two samples) and presence of coliform bacteria (In all samples).
The results indicate the water with pH ranging from 8.04 to 8.32
and fall in the average natural type pH range of 6.5 to 8.5.
chlorides of the samples ranges between 18.4mg/l and 58.85 mg/l.
Total Hardness of ground water ranged between 36.4 mg/l and 108
mg/l and is well within the limits of 300 – 600 mg/l and Total
Dissolved Solids ranged from 136 mg/l to 316 mg/l. The dissolved
oxygen is varying between 1.9 to 2.8 mg/lit.
Overall the surface water quality in the region comes in the
category B and C of IS 2296: 1982.
3.10 Soil Environment
Soils types are more important for agricultural production as well
as ground water recharge. Soils in the area are of ‘insitu ’ type
mainly derived from the underlying rock formations through
pedagogical processes of rock disintegration and rock
decomposition over a pro-longed period of time. Soils derived from
the Granitic basement are mainly red sandy and clayey loams.
whereas, the area underlain by Biotite- Hornblende-Granite
Gneisses has dark steel grey soils and light grey Silty Clay soils.
The project site neighborhood has red soils and low lying areas are
having Gneissic formations possess grey Silty soils on them.
Mainly rain-fed corn and jowar are grown selectively in the area.
There is no Major, Medium or Minor Surface Water Irrigation
Projects in the area. Some of the past cultivated area for
agriculture development is now converted in to housing lay outs
and industrial areas.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-32
Pridhvi Envirotech (P) Ltd.
Dry crops such as Maize, Millets, Grams and ground nut are
cultivated under rain-fed agriculture in the monsoon khariff period
in the far flung areas. Irrigated crops like rice are grown to some
extents under wells utilizing ground water source in the Monsoon
Season only. There are fruit bearing orchards at some places.
The Soil characteristics include both physical and chemical
parameters. M/s. Pridhvi Envirotech (P) Limited field team carried
out soil survey to assess the soil characteris tics of the study area.
The soil sampling was done at representative locations and these
locations are shown in Figure 3.13.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-33
Pridhvi Envirotech (P) Ltd.
Fig.3.13. Soil Sampling Locations
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-34
Pridhvi Envirotech (P) Ltd.
Table 3.7.
Analytical data of soilSmaples S.
No. Parameters Units
Devashree
Ispat (P) Ltd Mogalgidda
Sardar
Nagar
Farooq
nagar
1 pH (1:5 Soil water extract)
7.60 7.75 7.28 7.35
2 E.C (1:5 Soil water extract)
µmhos/cm 348 356.00 210 212
3 Bulk Density g/cc 1.29 1.32 1.38 1.39
4 Moisture % 6.54 6.67 2.28 2.3 5 Nitrates as N kg/ha 101.35 103.30 88.7 89.5 6 Phosphorous as P kg/ha 85.86 87.50 57.40 57.9 7 Potassium as K+ kg/ha 362.72 369.90 345.00 348 8 Sodium as Na kg/ha 582.44 594.00 367 370 9 Calcium as Ca mg/kg 2,737.04 2791.00 1,150.20 1161 10 Magnesium as Mg2+ mg/kg 1,250.58 1275.50 505 510
11 Sulphates as So4 mg/kg 510 520.00 396 400 12 Organic Carbon % 0.92 0.93 0.45 0.45 13 Texture a) Sand % % 20.30 20.50 31.50 31.7 b) Silt % % 52.30 52.40 50.20 50.5 c) Clay % % 27.40 27.10 18.30 17.8 Type of Soil Silty Loam Silty Loam Silty
Loam Silty Loam
14 Copper as Cu mg/kg 0.72 0.73 0.54 0.54
15 Zinc as Zn mg/kg 1.89 1.90 1.46 1.47 16 Lead as pb mg/kg 0.51 0.52 0.33 0.33 17 Cadmium as Cd mg/kg 0.56 0.57 0.29 0.29 18 Chromium as Cr mg/kg 0.38 0.38 0.16 0.16 19 Nickel as Ni mg/kg 0.3 0.30 0.12 0.12 20 Ca/ Mg Ratio 2.188 2.23 2.27 2.29 21 Cation Exchange
Capacity (CEC) meq/kg 81.5 83.10 108.2 109.2
22 Base Saturation % 5.7 5.81 7.40 7.47 23 Total Nitrogen as N % 0.004 0.004 0.006 0.006
The analysis results of soil samples collected in the impact area are interpreted
referring to the book; “Interpreting soil test results”. The reference tables are
presented in Table 3.6.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-35
Pridhvi Envirotech (P) Ltd.
The pH of soil ranges from Neutral to moderately alkaline. The cation exchange
capacity of the soils is very high. The level of extractable potassium is high.
The Ca/Mg ratio varies from balanced to low. The total Nitrogen as N is low in
the area. The base saturation of the samples is predominantly very strongly
leached. Bulk density of soil of impact varies from 1.29- 1.39 g/cc. Soil texture
is predominantly red sandy and clayey loams
Table 3.8 Soil Test Results – Reference Tables
General interpretation of pH measured Rating for Cation exchange Capacity
pH Range Classification CEC (Cmol)+)/kg
<4.5 Extremely Acidic Very low <6 * 4.51 -5.0 Very Strong Acidic Low 6-12
5.1-5.5 Strong Acid Moderate 12-25 5.6- 6.0 Moderately Acid High 25-40
6.1-6.5 Slightly acid Very High >40 6.6-7.3 Neutral
Source: Metson (1961) * Soils with CEC less than three are often low in fertility and susceptible to soil acidification.
7.4-7.8 Mildily Alkaline
7.9 -8.4 Moderately Alkaline
8.5-9.0 Strongly Alkaline
>9.0 Very Strongly Alkaline
Source: Bruce and Rayment (1982).
Ca/mg Ratio Base Saturation as a criterion of leaching
Description Range (%BS) Rating
<1 Ca Deficient 70-100 Very Weakly Leached 1-4 Ca (Low) 50-70 Weakly Leached
4-6 Balanced 30-50 Moderately Leached
6-10 Mg (Low) 15-30 Strongly Leached
>10 Mg deficient 0-15 Very Strongly Leached Source: Eckert (1987) Source: Metson (1961)
Rating of Total Nitrogen Extractable Potassium (K)
Rating (% by W)
Description K
<0.05 Very low low <150 ppm* (< 0.4 meq/100 g soil) 0.05-0.15 Low medium 150–250 ppm (0.4–0.6 meq/100 g
soil) 0.15-0.25 Medium high 250–800 ppm (0.6–2.0 meq/100 g
soil) 0.25-0.50 High excessive >800 ppm (>2.0 meq/100 g soil) >0.5 Very High Source: Abbott (1989)
Source: Bruce and Rayment (1982)
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-36
Pridhvi Envirotech (P) Ltd.
3.11 Air Environment
3.11.1 Meteorology
Methodology plays a vital role in effecting the dispersion of
pollutants, once discharged into the atmosphere, their transport,
dispersion and diffusion into the environment. The meteorological
data is very useful for interpretation of the baseline information
and for model study of air quality impacts also. Since
meteorological data show wide fluctuations with time, meaningful
interpretation can only be drawn from long term and reliable data.
Such source of data is the India Meteorological Department (IMD)
that maintains a network of meteorological stations at several
important locations. The data recorded for nearest IMD station at
Hyderabad is summarized for the period 1979 to 2000 and the same
is represented Figure 3.14.
Also Micro Meteorological studies are conducted at the site during
study period.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-37
Pridhvi Envirotech (P) Ltd.
Fig 3.13 IMD data of meteorological station Hyderabad (1971-2000)
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-38
Pridhvi Envirotech (P) Ltd.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-39
Pridhvi Envirotech (P) Ltd.
3.11.2 Meteorological Station at Industry Site
The micro meteorological data in the area is collected
simultaneously with the ambient air quality monitoring. The station
was installed in such a way that there are no obstructions for free
flow of wind. Wind speed, wind direction, humidity &temperature
are recorded on hourly basis in the study period. Salient features of
micro meteorological data collected are as follows:
Wind Direction and Speed
The hourly wind speed and wind direction observations are computed during
the seasons of study period and the same are presented in Table 3.7 and the
wind rose diagrams are presented in Figure 3.15. The following observations
can be made from the collected data;
The predominant wind direction is NE.
Calm period is observed to be 45.883% during the time of monitoring.
Mostly the wind speeds are observed to be in the range of 0 – 9.3 m/s.
The maximum and minimum temperature and relative humidity and total
seasonal rainfall are summarized in below table. The salient features are
discussed in brief as follows.
Temperature:
(a) Maximum: 33.40C,(b) Minimum: 13.2 0C and (c)Average:
22.0 0C during study period from micro meteorological station
Humidity: The daily relative humidity values are observed to
range between 25 – 77%. during study period from micro
meteorological station
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-40
Pridhvi Envirotech (P) Ltd.
Table 3.9
Frequency Distribution of Wind Speeds and Wind Directions
Directions / Wind Classes (m/s)
0.50 - 2.10
2.10 - 3.60
3.60 - 5.70
5.70 - 8.80
8.80 - 11.10
>= 11.10
Total (%)
N 1.7 0.6 0.0 0.0 0.0 0.0 2.2
NNE 5.1 0.2 0.0 0.0 0.0 0.0 5.3
NE 0.0 0.0 0.0 0.0 0.0 0.0 0.0
ENE 9.3 5.6 0.1 0.0 0.0 0.0 15.0
E 6.7 3.2 0.6 0.0 0.0 0.0 10.5
ESE 6.9 1.6 0.0 0.0 0.0 0.0 8.5
SE 2.2 0.1 0.0 0.0 0.0 0.0 2.3
SSE 1.7 0.0 0.0 0.0 0.0 0.0 1.7
S 0.5 0.0 0.0 0.0 0.0 0.0 0.5
SSW 0.4 0.0 0.0 0.0 0.0 0.0 0.4
SW 0.9 0.0 0.0 0.0 0.0 0.0 0.9
WSW 0.0 0.0 0.0 0.0 0.0 0.0 0.0
W 0.5 0.0 0.0 0.0 0.0 0.0 0.5
WNW 1.0 0.0 0.0 0.0 0.0 0.0 1.0
NW 2.5 0.4 0.0 0.0 0.0 0.0 2.9
NNW 1.7 0.2 0.0 0.0 0.0 0.0 1.9
Sub-Total 41.0 12.0 0.7 0.0 0.0 0.0 53.7
Calms
45.8
Missing/Incomplete
0.5
Total
100
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-41
Pridhvi Envirotech (P) Ltd.
Figure 3.14 Wind rose Diagram for the study December-2017
to February 2018
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-42
Pridhvi Envirotech (P) Ltd.
3.11.3 Ambient Air Quality
Air pollution means the presence of one or more contaminants or
combinations thereof in such quantities and of such duration as are
or may tend to be injurious to human, plant or animal life or
property. Air pollutants include smoke, vapors, soot, fumes, gases,
mist, odors, particulate matter, radioactive material or noxious
chemicals. With increasing industrial activity a range of different
pollutants are released into the atmosphere that are dispersed and
can have a significant impact on neighborhood air environment.
Thus collection of base line data of air environment occupies a
predominant role in the impact assessment statement. The ambient
air quality status across the study zone forms basis for prediction
of, the impacts due to the proposed project.
The data required to assess air quality impacts in and around
neighborhood is achieved by designing such a network, which
encompasses micro meteorological conditions, quantity and quality
of emissions, locations, duration, resources/monitoring technology
and operational criteria. The optimal scheme for air quality
monitoring should consider all the above factors.
3.11.4 Scope of Field Study
The scope of baseline status of the ambient air quality can be
accessed through a well-designed ambient air quali ty stations
network. An intensive ambient air quality monitoring of the study
area consisting of 10 km. radius from the site was carried out
during the period from December 2017 - February 2018. As
Devashree Ispat (P) Ltd Unit I and Unit III are going for expansion
activity and both are adjacent to each other . The ambient air
quality was monitored at 7 locations spread over entire study area
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-43
Pridhvi Envirotech (P) Ltd.
which can be taken as base line studies for both plants together.
Current ambient quality at the plant levels are measured
individually at both plants.
Figure 3.16 presents the locations of ambient air quality-
monitoring stations. At each sampling station monitoring was
carried out for 24 hours in a day for 2 days a week, and for three
months. The major air pollutants monitored on 24 hourly basis are,
PM10, PM2.5, Carbon Monoxide, Sulfur dioxide and Oxides of
Nitrogen. Sampling and analysis of the above variables is according
to the guidelines of Central Pollution Control Board.
3.11.5 Description of Sampling Locations
The location of ambient air quality stations is contingent on the
meteorological status of the area. Hence the micro meteorological
data was collected before initiating the ambient ai r quality
monitoring. Table 3.10 presents the ambient air quality locations
and their distances and directions from the p lant site.
Table 3.10
Locations of Ambient Air Quality Monitoring Stations
S. No
Location Name
Direction
Distance
Wind
Frequency
Latitude Longitude
1 Project Site -- -- -- N17004’33.05’’ E78008’53.09” 2 Ellikatta NE 0.87 Km Up N17004’29.04’’ E78009’29.78” 3 Rangampalli SW 1.4 Km Down N17004’08.23’’ E78008’09.08”
4 Chaupalli SW 3.4 Km Down N17003’30.42’’ E78007’17.46” 5 Mughalgidda W 3.0 Km Down N17005’07.73’’ E78007’25.65”
6 Antaram N 5.2 Km Cross N17007’20.15’’ E78009’17.22” 7 Shadnagar E 6.2 Km Up N17004’26.30’’ E78012’19.77” 8 Pidkiryla SE 3.2 Km Cross N17003’10.39’’ E78009’58.66”
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-44
Pridhvi Envirotech (P) Ltd.
3.11.6 Pre-project Ambient Air Quality Status
a. Plant Site
The air quality station was fixed on the top of an administration
building at a height of about 3.0 m above the ground ensuring the
free flow of winds.
The monitoring results of the station shows that the PM10 and
PM2.5 values range between 69.3 – 85.6 µg/m3 and 30.4-44.6
µg/m3 the mean values are 77 µg/m3 and 37.7 µg/m3 respectively.
The SO2 and NOX levels vary between 11.4 -16.2 µg/m3 and 21.4
14.2 -21.4 µg/m3 and the mean values are 13.7 µg/m3 and 18.6
µg/m3 respectively.
b. Ellikatta
This location lies at a distance of about 0.87km towards North East
from the center of the plant. This village is in the up- wind from the
site. This village is selected as it is nearest village to the site and
considering the prevailing meteorological conditions during the
study period. The air quality station was fixed on the top of a
residential building at a height of about 3.0 m above the ground
ensuring the free flow of winds.
The monitoring results of the station shows that the PM 10 and PM2.5
values range between 54.2 -73.5µg/m3 and 19.4 - 30.2 µg/m3 the
mean values are 62.2 µg/m3 and 25.1 µg/m3respectively. The SO2
and NOX levels vary between 10.3-15.2 µg/m3 and 12.3 -18.3
µg/m3 and the mean values 12.0 µg/m3 and 12.3 µg/m3 respectively
c. Rangampalli
This location lies at a distance of about 1.4 km towards SW from
the plant. This village is in the down wind direction from the
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-45
Pridhvi Envirotech (P) Ltd.
siteThe village selected based on prevailing meteorological
conditions during the study period. The air quality station was
fixed on the top of a residential building at a height of about 3.5 m
above the ground ensuring the free flow of winds.
The monitoring results of the station shows that the PM 10 and PM2.5
values range between 54.3 -64.3 µg/m3 and 17.4 -30.5 µg/m3 the
mean values are 60.2 µg/m3 and 22.3 µg/m3. The SO2 and NOX
levels vary between 9.8-15.2 µg/m3 and 13.2-17.3 µg/m3 and the
mean values 11.8 µg/m3 and 13.2 µg/m3 respectively.
d. Chaupalli
This location lies at a distance of about 3.4 km towards SW from
the site in the down wind direction. This site is considered
considering the prevailing meteorological conditions during the
study period. The air quality station was fixed on the top of a
residential building at a height of about 3.0 m above the ground
ensuring the free flow of winds.
The monitoring results of the station shows that the PM 10 and PM2.5
values range between 50.6- 67.2 µg/m3 and 18.4 -27.4 µg/m3 the
mean values are 56.4 µg/m3 and 22.9 µg/m3. The SO2 and NOX
levels vary between 10.3- 15.2 µg/m3 and 11.4-17.3 µg/m3 and the
mean values 12.7 µg/m3 and 13.9 µg/m3 respectively.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-46
Pridhvi Envirotech (P) Ltd.
e. Mughalgidda
This location lies at a distance of about 3.3 km towards west from
the plant in the down wind direction this village is considered to
assess the downwind dispersion of the ambient pollutants
considering the prevailing meteorological conditions during the
study period. The air quality station was fixed on the top of a
residential building at a height of about 2.5 m above the ground
ensuring the free flow of winds.
The monitoring results of the station shows that the PM 10 and PM2.5
values range between 45.3- 65.3 µg/m3 and 19.4 - 27.4 µg/m3 the
mean values are 54.7 µg/m3 and 23.1 µg/m3. The SO2 and NOX
levels vary between 10.4- 15.2µg/m3 and 12.5-18.3 µg/m3 and the
mean values 12.7 µg/m3 and 15.2 µg/m3 respectively.
f. Antaram
This location lies at a distance of about 5.2 km towards North from
the plant in the cross wind direction. This village is considered to
assess the cross wind direction of the ambient pollutants
considering the prevailing meteorological conditions during the
study period. The air quality station was fixed on the top of a
residential building at a height of about 3.0 m above the ground
ensuring the free flow of winds.
The monitoring results of the station shows that the PM10 and PM2.5
values range between 50.2- 62.3 µg/m3 and 18.7-28.4 µg/m3 the
mean values are 54.6 µg/m3 and 22.4 µg/m3. The SO2 and NOX
levels vary between 10.5- 15.2 µg/m3 and 13.2- 17.3 µg/m3 and
the mean values 12.9 µg/m3 and 14.9 µg/m3 respectively.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-47
Pridhvi Envirotech (P) Ltd.
g. Shadnager
This location lies at a distance of about 6.2 km towards East from
the plant in the up wind direction. This town is considered to
assess the dispersion of ambient pollutants considering the
prevailing meteorological conditions during the study period and
the important town in the study region. The air quality station was
fixed on the top of a residential building at a height of about 3.0 m
above the ground ensuring the free flow of winds.
The monitoring results of the station shows that the PM10 and PM2.5
values range between 50.2 - 62.3 µg/m3 and 18.7- 28.4 µg/m3 the
mean values are 54.6µg/m3 and 22.4µg/m3. The SO2 and NOX levels
vary between 10.5-15.2 µg/m3 and 13.2 -17.3 µg/m3 and the mean
values 12.9 µg/m3 and 14.9 µg/m3respectively
h. Pidkiryla
This location lies at a distance of about 3.2 km towards SE from the
plant in the cross wind direction this village is considered to assess
the cross wind dispersion of the ambient pollutants considering the
prevailing meteorological conditions during the study period. The
air quality station was fixed on the top of a residential building at a
height of about 3.0 m above the ground ensuring the free flow of
winds.
The monitoring results of the station shows that the PM 10 and PM2.5
values range between 49.3- 60.2µg/m3 and 16.3- 23.5 µg/m3 the
mean values are 53 µg/m3 and 21.3 µg/m3. The SO2 and NOX levels
vary between 9.4- 14.2 µg/m3 and 11.2-17.3 µg/m3 and the mean
values 11.7 µg/m3 and 14.4 µg/m3 respectivel.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-48
Pridhvi Envirotech (P) Ltd.
Table 3.11
Ambient Air Quality Status (24 hourly)(Unit; µg/m3)(CO-ppm) Pollutant Maximum Minimum Mean 98%
1) Location: Plant Site
PM10 85.6 69.3 77.0 84.8 PM2.5 44.6 30.4 37.7 43.1 SO2 16.2 11.4 13.7 16.2
NOx 21.4 14.2 18.6 21.2 CO 2.2 1.3 1.8 2.2
2) Location: Elikatta
PM10 73.5 54.2 62.2 72.0 PM2.5 30.2 19.4 25.1 30.2 SO2 15.2 10.3 12.0 14.7
NOx 18.3 12.3 15.3 18.3
CO 2.2 1 1.3 1.9 3) Location: Rangampalli
PM10 64.3 54.3 60.2 63.8
PM2.5 30.5 17.4 22.3 30.0 SO2 15.2 9.8 11.8 15.2
NOx 17.3 13.2 14.8 17.0 CO 1.4 1 1.2 1.4 4) Location: Chaulapalli
PM10 67.2 50.6 56.4 66.3 PM2.5 27.4 18.4 22.9 27.4
SO2 15.2 10.3 12.7 15.0 NOx 17.3 11.4 13.9 16.8 CO 1.4 1 1.2 1.4
5) Location: Mughalgidda
PM10 65.3 45.3 54.7 63.4 PM2.5 27.4 19.4 23.1 26.9 SO2 15.2 10.4 12.7 15.2
NOx 18.3 12.5 15.2 17.8 CO 1.7 1.1 1.3 1.7 6) Location: Antanam
PM10 62.3 50.2 54.6 61.4 PM2.5 28.4 18.7 22.4 27.4 SO2 15.2 10.5 12.9 15.2 NOx 17.3 13.2 14.9 16.8
CO 1.6 1 1.3 1.6 7) Location: Shadnagar PM10 63.2 49.6 53.9 61.8
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-49
Pridhvi Envirotech (P) Ltd.
PM2.5 26.4 18.3 21.3 25.8 SO2 14.6 10.5 12.4 14.5
NOx 17.2 12.5 14.7 17.2 CO 2.4 0.18 1.8 2.4 8) Location: Pidkiryla PM10 60.2 49.3 53.0 59.4
PM2.5 23.5 16.3 20.0 23.5 SO2 14.2 9.4 11.7 14.2 NOx 17.3 11.2 14.4 16.8 CO 1.9 1 1.3 1.8
Three months Ambient Air Quality data is given at ANNEXURE - I
The Location Map of Ambient Air Quality Monitoring Stations in the
study area is as shown in figure 3.16.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-50
Pridhvi Envirotech (P) Ltd.
Figure 3.15: Location Map of Ambient Air Quality Monitoring
Stations
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-51
Pridhvi Envirotech (P) Ltd.
3.11.7 Noise Environment
Noise is an unwanted sound without musical quality. Artificial noise
and its impact on environment, grown apace with advancing human
civilization. Noise pollution is equally hazardous to environment as
air, water and other forms of pollution. Various noise measurement
units have been introduced to describe, in a single number, the
response of an average human to a complex sound made up of
various frequencies at different loudness levels. The most common
scale is, weighted decibel dB (A), measured as the relative intensity
level of one sound with respect to another sound (reference sound).
The noise monitoring locations and their directions with respect to
the project site are given in Table 3.12. And Location Map for Noise
Monitoring stations is presented in Fig 3.17.
Table No.3.12 Noise Monitoring Locations
S.No Location
Name
Direction Distance Latitude Longitude
1 Project Site -- -- N17004’33.05’’ E78008’53.09” 2 Elikatta NE 0.87 Km N17004’29.04’’ E78009’29.78” 3 Rangampalli SW 1.4 Km N17004’08.23’’ E78008’09.08” 4 Chaupalli SW 3.4 Km N17003’30.42’’ E78007’17.46” 5 Mughalgidda W 3.0 Km N17005’07.73’’ E78007’25.65” 6 Antaram N 5.2 Km N17007’20.15’’ E78009’17.22” 7 Shadnagar E 6.2 Km N17004’26.30’’ E78012’19.77” 8 Pidkiryla SE 3.2 Km N17003’10.39’’ E78009’58.66”
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-52
Pridhvi Envirotech (P) Ltd.
Figure 3.16 Location Map for Noise Monitoring stations
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-53
Pridhvi Envirotech (P) Ltd.
The impact of noise depends on its characteristics (instantaneous,
intermittent or continuous in nature), time of day (day or night)
and location of noise source. Table 3.13 shows the effects of
different noise levels on human beings. The environmental impact
of noise can have several effects varying from noise induced
hearing loss to annoying depending on noise levels.
The assessment of noise pollution on neighborhood environment
due to the proposed industry was carried out keeping in view, all
the considerations mentioned above. The existing status of noise
levels is measured at 8 locations at various villages including the
site within the study area. Figure 3.14 shows noise level measured
locations. The measured noise values are shown in Table 3.13.
Noise levels are high at the urban traffic junctions compared to the
industrial and village areas.
Table 3.13
Effects on Human Beings at Different Noise Levels
Source Noise Level
dB(A) Effects
Large Rocket Engine (Near By)
180 Threshold of Pains
Hydraulic Press (1m) 130 Jet take off (60 m) 120 Maximum vocal effort
possible Automobile Horn (1m) 120
Construction Noise (3m) 110 Shout, Punch, Press, Circular Saw
100 Very annoying
Heavy Truck (15m), Farm Machinery
90 Prolonged exposure Endangers Lathes, Sports Car, Noisy Machines hearing loss
Automobile (15m) 80 Annoying Loud Conversations 60 Living Room in Home 50 Quiet
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-54
Pridhvi Envirotech (P) Ltd.
Power Station (15m) 50 Bed Room in Home 40
Tick of Wall clock (1m) 30 Whisper 20 Rattling of Leaves by Breeze
10 Barely audible
Table 3.14
Equivalent Noise levels in the Study Area Time N1 N2 N3 N4 N5 N6 N7 N3 6:00 60.3 43.2 42.3 43.6 42.9 44.1 53.3 39.1 7:00 62.4 44.7 44.2 45.1 44.9 45.6 54.3 40.9 8:00 63.4 47.3 49.2 47.8 49.9 48.3 60.4 43.5 9:00 65.7 51.4 52.3 51.9 53.1 52.4 62.3 46.2 10:00 63.2 53.2 54.3 53.7 54.5 54.3 63.2 46.8 11:00 66.8 51.6 53.4 52.1 54.2 52.6 60.4 46.6 12:00 70.2 53.2 52.3 53.7 53.1 54.3 59.6 43.9 13:00 68.4 50.7 51.5 51.2 52.3 51.7 62.3 40.5 14:00 64.3 52.3 49.2 52.8 49.9 53.4 61.2 43.9 15:00 70.6 51.3 47.2 51.8 47.9 52.3 59.3 41.7 16:00 64.5 52.6 53.2 53.1 54.0 53.7 60.2 43.6 17:00 60.4 53.2 53.4 53.7 54.2 54.3 58.2 43.2 18:00 59.7 50.3 52.6 50.8 53.4 51.3 59.7 44.1 19:00 64.3 49.2 50.8 49.7 51.6 50.2 57.3 40.0 20:00 62.5 50.3 48.3 50.8 49.0 51.3 55.3 39.0 21:00 60.6 46.3 45.7 46.8 46.4 47.2 52.3 40.5 22:00 59.7 44.3 43.2 44.7 43.8 45.2 53.4 41.2 23:00 60.4 42.3 42.7 42.7 43.3 43.2 50.6 38.1 0:00 62.3 43.9 41.2 44.3 41.8 44.8 49.6 40.2 1:00 59.2 40.6 42.6 41.0 43.2 41.4 50.3 37.6 2:00 61.2 42.6 40.8 43.0 41.4 43.5 48.3 41.4 3:00 63.5 42.4 43.3 42.8 43.9 43.3 51.3 38.2 4:00 60.3 41.2 41.4 41.6 42.0 42.0 53.4 38.7 5:00 61.6 43.6 43.2 44.0 43.8 44.5 50.5 39.8 Min 59.2 40.6 40.8 41.0 41.4 41.4 48.3 37.6 Max 70.6 53.2 54.3 53.7 54.5 54.3 63.2 46.8 Ld 65.6 50.9 51.1 51.4 51.9 51.9 59.7 43.4 Ln 61.2 42.8 42.4 43.2 43.0 43.6 51.2 39.6
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-55
Pridhvi Envirotech (P) Ltd.
Observations of Noise Levels
The noise data reveals that the values were well within the standards. In the
study area maximum value 70.6 dB (A) was observed at Plantsite
andminimum value 37.6 dB (A) was observed at Pidikiryala village. The higher
noise levels in the plant area is due to the plant operation and allied activities.
All remaining stations are under rural (Residential) Category and all the noise
levels are well within the CPCB prescribed standards as shown in Table 3.15.
Table 3.15
Ambient Noise Standards
Area
Code
Category of Area/Zone Limits in dB(A) Leq*
Day Time Night Time
A Industrial Area 75 70 B Commercial Area 65 55 C Residential Area 55 45 D Silence Zone 50 40
3.12 Socio Economic Environment
Industrial development reflects in social development, i.e., growth
in infrastructure facilities, growth in employment rates, increased
demands for housing, and other amenities etc., which will have a
bearing on the socio economic status. The Study area is rural in
nature. The study area is dependent mostly on dry crop
agriculture. The area is irrigated by ground water sources and few
tanks. In this context it is necessary to study the present
socioeconomic status with respect to the proposed development in
the coming future.
3.12.1 Objectives of socio economic study
The primary objectives of the socio-economic assessment are:
i. Understanding the baseline socio-economic environment
obtaining in the impact zone.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-56
Pridhvi Envirotech (P) Ltd.
i i. Identifying the key stakeholders who are likely to be impacted
by the establishment of the proposed expansion project.
iii. Predicting the positive and negative impacts of the project on
the socio-economic environment in the area.
iv. Suggesting mitigation measures to minimize the negative
impacts.
3.12.2 Desk Research
A fairly comprehensive desk research to understand the socio-
economic setting in and around the project site was the first
initiative towards carrying out the SEIA of the project. Accordingly,
published and unpublished information available on the subject was
referred, reviewed and cr itical information gaps identified by the
SEIA team. The major documents and information sources
extensively referred to are:
Sl.No. Publication/Document Source
1 Handbook of Statistics –Rangareddy District, 2015
Chief Planning Officer –Rangareddy District
2 Census – 2011 Provisional Population Tables for Rangareddy District in Telangana
Registrar General of India
3 Rangareddy and Mahaboobnagar District Industrial Profile
District Industries Centre, Rangareddy, Mahaboobnagar
4 Brief Industrial Profile of Rangareddy, Mahaboobnagar
MSME Development Institute, Hyderabad
5 Brief Educational Institutional Details (Schools are Colleges)
Directorate of Economics and Statistics, Government of Telangana-2017 andDistrict DEO Office and MEO office
6 Brief Health Status Direcotrate of Economics and Statistics 2017 Govt of Telangana
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-57
Pridhvi Envirotech (P) Ltd.
Besides, information from various department like Departments of Industries,
Education, Health, Irrigation, Agriculture and Social Welfare was also referred to
gain deeper insights into the socio-economic setting of Rangareddy district in
general and the project area in particular.
The desk research has enabled the study team to effectively leverage the macro
level socio-economic information available and identify information gaps at the
village and household levels.
It was during this stage, the key stakeholders were identified and study
instruments – schedules and checklists – prepared, tested and finalised.
Similarly, the sampling frame and sample size were also designed and finalised.
The sampling frame for the study consisted of villages, households and District
and Mandal level officials as also local opinion leaders.
3.12.3 Geographical Coverage
The geographical coverage for SEIA extends over the area falling within the 10
km radius from Elikatta and comprises as many as 75 villages which are
administratively distributed across 2 Districts and 5 Mandals (Blocks). The details
of villages and their demographic features are given at Annexure II of the
report. The brief description of data is presented in table 3.16
Table – 3.16
Salient Features of Demographics in Study Area Sl. No.
Demographic Parameter
Data as per Census
2011
Salient Features
1 Total Population (No.) - Males - Females
1.38 lakhs 0.70lakhs 0.68 lakhs
Sex Ratio in the area is 969 compared to 977 for the district
67.0% of the population in the study area is Rural population
2 SCs (No.) 0.21 lakhs Forms 15.2% of the
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-58
Pridhvi Envirotech (P) Ltd.
total population 3 STs (No.) 0.10 lakh Forms 7.24% of the
total population. 4 Average Literacy (%) 57.3% Lower than the district
average of 71.9%
3.12.4 Impact Zones
For a more systematic impact assessment, the study area has been divided into
three impact zones: core, buffer and transition.
Of the total 75 villages in the overall project impact zone, 3 villages fall in the
core impact zone (up to 2 km in aerial distance from the project site) with 2.1%
of the total No. of households and 2.0% of the population in the area.
18 villages are falling under buffer zone (2-5 km from the site) with a relative
share of 45.9% in terms of the households and 46.6% in terms of population.
54 villages accounting for 52.0% in terms of households and 51.4% in terms of
population fall in the transition zone (beyond 5 km and up to 10 km).
The SEIA study lays more emphasis on covering more villages in the core and
buffer zones vis-à-vis the transition zone
Below table shows important statistics of the impact zones
Table 3.17
Important demographic features of impact zones
S.NO
Impact zone and
distance from
site
Number
of
villages
Total
populatio
n
Males Female
% of SC
populati
on
% of
ST
popula
tion
% of
Literac
y
1 Core zone( 0-2 KM from site )
3 2806 1365 1441 437 21 48.8
2 Buffer zone( 2-5 KM from site)
18 64331 32721 31610 6227 2719 66.1
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-59
Pridhvi Envirotech (P) Ltd.
3 Transit zone ( 5-10 KM from the site)
54 70943 36026 34917 14342 7408 49.7
Grand Total
75 138080 70112 67968 21006 10148 57.3
3.12.5 Sampled house holds :
A stratified random sampling technique was followed to select the sample
villages and households. Accordingly, the sample villages were picked up at
random from the three impact zones considered – core, buffer and minimally
affected. The number of households to be contacted in each sample village was
determined on the basis of the size of population of the respective village. In the
absence of household level information, the respondent households were
selected randomly during the course of visit to the respective village. However,
while selecting the respondent households, emphasis was on contacting
households, who are economically poor, susceptible to shifts in livelihood
patterns and belonged to vulnerable social communities. Accordingly, the sample
villages selected for the survey together with the number of households across
each village are presented in Table – 3.18.
Table – 3.18
Sample Villages Selected for Socio-Economic Impact Assessment
Sl. No
Sample Village
Mandal
Location from
Project Site Popul
ation
2011 Censu
s
House Holds
(No.)
Directi
on
Distance
(km)
Total Sampl
e
1 Male ellikatta Farooqnagar SE 0.6 Km
Under Ellikatta Revenue Population Data is Same
10
2 Ellikatta Farooqnagar NE 0.87 Km
2806 665 13
3 Rangampalle Farooqnagar SW 1.4 Km
Under Mogalgidda Revenue
11
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-60
Pridhvi Envirotech (P) Ltd.
Population Data is Same
4 Mogalgidda Farooqnagar NW 2.6 Km 4778 1044 11
5 Kishannagar Farooqnagar SE 3.0 Km 3784 893 10
6 Kakloor Shabad NE 3.4 Km 4954 1151 13
7 Hajipalle Farooqnagar SE 4.2 Km 795 188 11
8 Chowlapalli Farooqnagar SW 3.2 Km 2950 661 10
9 Bodampahed Shabad NW 4.6 Km 3758 866 12
10 Shadnagar Farooqnagar E 5.0 Km 45675 10328 14
11 Nagulapalle Farooqnagar NE 6.2 Km 2088 536 11
12 Srirangapur Kondurg NW 6.9 Km 905 216 11
13 Chinchode Farooqnagar SW 7.2 Km 5445 1322 12
14 Edulapalle Nandigam NE 8.1 Km 1467 320 12
Total 79405 18190 161
The sample villages account for 57.5% of the population and 57.2%of the
number of households of the total 75 villages.
It needs to be mentioned in this context that an element of purposiveness was
induced into selection of sample villages with a view to focusing more on villages
in the core and buffer zones of impact. Such a selection of the sample villages
was well justified as the entire area beyond the core and buffer impact zones is
likely to have only minimal impact of the project and the same cannot be
distinguished.
The Socio Economic Impact Assessment collecting sample villages located
detailed in Figure – 3.18
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-61
Pridhvi Envirotech (P) Ltd.
Figure – 3.17 Google Map of Sample Villages
3.12.6 Field Surveys
On the conclusion of the desk research, a three member study team was
constituted. The team members have had considerable exposure and experience
in conducting large size socio-economic research studies especially in Telangana
and Andhra Pradesh. They are well versed with the socio-economic setting in the
project area and understood the local dialect.
Planned and in-depth field surveys for Five days, between29th January 2018 to
02nd February 2018, constituted the most important element of the
methodology. Field surveys helped collect fairly reliable primary data with
respect to the major livelihood sources, family incomes and expenditure,
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-62
Pridhvi Envirotech (P) Ltd.
education and health status, basic amenities available, lifestyles, standard of
living etc., of residents and small businesses in the project impact zone. They
also helped in eliciting information from the natives about the negative
environmental impacts of industrial units already existing in the area and the
measures initiated by them to mitigate the impacts.
Field surveys were carried out in all the 14sample villages contacting a total of
161 households. The potential respondents in the sample households were
approached personally by the Field Investigators who explained the purpose of
the visit and solicited their participation by sharing the relevant information
unabashedly. The Field Investigators also clarified the doubts and apprehensions
expressed by the respondents. Once the respondents were willing and ready to
participate, household level socio-economic information was collected with the
help of a structured questionnaire. A number of questions were open ended to
facilitate capturing perceptions of the respondents objectively.
In addition to household surveys, Participatory Rapid Assessment (PRA) tools
comprising Transect Walks, Focus Group Discussions, and Opinion Leader
Interviews were used for collecting village level qualitative information.
Accordingly, the study team carried out:
Transect walks around all the sample villages along with a few natives.
Carried out 3 Focus Group Discussions, comprising 10 members per
group representing women, youth, household heads and opinion leaders
to elicit information pertaining to their awareness, expectations and
apprehensions about the proposed expansion projects.
Detailed discussions with Sarpanch, MPDO and Chairperson-ZPTC, District
Planning Officer, District Agriculture Officer, District Industries Centre and
Lead Bank Manager to understand the major livelihood sources – existing
and alternative – in the area.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-63
Pridhvi Envirotech (P) Ltd.
Accordingly, the study team carried out:
Transect walks around all the sample villages along with a few natives.
Carried out 3 Focus Group Discussions, comprising 10 members per
group representing women, youth, household heads and opinion leaders
to elicit information pertaining to their awareness, expectations and
apprehensions about the proposed expansion projects.
3.12.7 Data Analysis
The data collected during the field survey and desk research phases
was processed, tabulated and analyzed with the help of basic
quantitative and qualitative analytical tools. The emerging results
were validated through in-house brainstorming and discussions with
district level officials.
The socio-economic impact of the proposed expansion project was
assessed in terms of its effects on:
Livelihoods and incomes
Life styles and quality of life
Community infrastructure – physical and social – facilities available
3.12.7.1 Demographics
The 161 sample households have a total population of 830 implying an
average 5.1 members per household. 50.7% of the population comprises of
males and 49.3% females. 55.5% are adults; 26.2% children and 18.3%
aged.
59.0% of the households are BCs followed by SCs (21.7%), OCs (8.7%), STs
(5.0%), and Minorities (5.6%).
Average literacy among the households is 48.8%. Male literacy is notably high
at 60.0% compared to female literacy of 40.0%. 47.6% of the household
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-64
Pridhvi Envirotech (P) Ltd.
population pursued Secondary education, while 41.2%Primary education,
10.2% Graduation, and 1.0% Post-graduation.
3.12.7.2 Assets Owned
The various assets owned and the percentage of household population owning
these assets is presentedin Table 3.19.
Table – 3.19
Ownership of Assets by Sample Households
Sl.No Assets Magnitude of Ownership
(%)
1 Land 64.6 2 House 100.0 3 TV 94.4 4 Fridge 19.9 5 Mobile Phone 96.3 6 Cooking Gas 95.6 7 2-wheeler 44.1 8 Cycle 11.8 9 Sewing machine 6.8 10 Tractor/Truck/Mini-truck 2.5
3.12.7.3 Sources of Livelihood
The Project 10km Radios area more than village’s people depend on
agricultural activity. Surveyed households reported Source of livelihood
varying, Daily Wage Labour for 33.3%, Agriculture is the primary sources of
livelihood for 30.2%, Pension for 14.3%, Self-employment for 11.2%, Private
sector employment for 10.0%, and Government service for 1.0%.
3.12.7.4 Family Incomes
Surveyed households reported family incomes varying predominantly between
83.9% of the family incomes >Rs. 10,000/- p.m, while 16.1% had incomes
ranging between Rs 5001/- to Rs. 10000/- p.m.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-65
Pridhvi Envirotech (P) Ltd.
3.12.7.5 Family Expenditures
52.2% of the households reported family expenditures ranging from >Rs.
10,000 p.m, 44.7% Rs. 5001-10000 p.m and 3.1% Rs. 2000 – 5000 p.m.
The pattern of average family expenditure points out that 32.8% of the
expenditure went for food;; 29.3% for clothing and other household expenses;
12.9% for education; 2.2% for healthcare; and 0.1% for housing&22.7% for
other needs
3.12.7.6 .5Living Standards
56.5% have pucca house, 42.3%of the households have semi-pucca
house, and 1.2% have kutcha houses
98.1% have own house while hardly 1.9% live in rented
accommodation
93.1% households have toilet on the premises
88.8% households have access to safe drinking water
94.4% have access to cable/DTH TV connection
95.6% have cooking gas connection
96.2% have mobile phones
3.12.7.7 Educational Facilities
The Government of India with an objective to provide universal education to all
of its citizens has enacted the Right of Children to Free and Compulsory
Education Act, 2009 to provide free and Compulsory Education to all the
children in the age group of 6 to 14 years, in the country.
Govt & Private educational Institutes in 14 sample villages falls under 4
mandals of the District. Mandal wise information is presented in the table
below
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-66
Pridhvi Envirotech (P) Ltd.
Table-3.20
Category of Educational Intuitional Details in Mandal wise
Category
Farooqnaga
r Shabad Nandigam Kondurg
Gov
t
Privat
e
Go
vt
Priv
ate Govt
Priva
te Govt
Priva
te
Anganwadi 16 0 3 0 1 0 1 0
Primary and
Upper Primary
Schools
15 8 2 1 1 0 1 0
Minority
Schools
7 0 1 0 0 0 0 0
Z.P.H.Schools 4 6 0 0 0 0 0 0
Jr. Collges 1 8 0 0 0 0 0 0
Senior Colleges 1 1 0 0
Engg. Colleges 0 2 0 0 0 0 0 0
DIET/BED/
Pharma
Colleges
1 7 0 0 0 0 0 0
Model Schools,
KGBV Schools &
Vocational
Colleges
1 0 0 0 0 0 0 0
Total 46 32 6 1 2 0 2 0
Source : MEO Farooqnagar, Rangareddy District.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-67
Pridhvi Envirotech (P) Ltd.
3.12.8 Health Status
Health and Family Welfare
The health and family welfare status information was collected the state health
commission office website. I have observed the area health status information.
There are 107 general hospitals, 17 hospitals for special treatment, totaling to
124 hospitals rendering services in the State. Apart from this, there are 683
primary health centers 32 Panel Clinics and 74 dispensaries functioning in the
State as on 31-03-2016. The strength of doctors in these hospitals is 3622,
including 419 contract doctors to provide maternal and child health care and
family welfare services to the people of the State.
The status of health indicators is detailed in Table 3.21 below:
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-68
Pridhvi Envirotech (P) Ltd.
Table 3.21
STATUS OF HEALTH INDICATORS
Sl.
No
District MMR
2011-
13*
IMR
2013*
TFR
2013*
CPR*** CBR
2013*
ASR
2011*
CSR
2011*
*
Full
Immuniz
ation
1 Rangareddy 78 33 2.0 65.1 18.0 961 933 35.5 2. Mahabubnagr 98 53 2.0 58.8 17.7 977 925 55.9
State Average 92 39 1.8 66.7 17.4 988 933 48.3
Source: 1.*- Commr. Health and Family welfare, Hyd. 2.**- Census 2011 , 3.***-DLHS -4-2012-13. IMR -Infant Mortality Rate (per 1000 live births) MMR -Maternity Mortality Ratio (per1 lakh live births) TFR -Total Fertility Rate CBR- Crude Birth Rate CPR -Contraceptive Prevalence Rate ASR - Adult sex Ratio (per 1000 males) CSR-Child Sex Ratio (per 1000 males) Note: *Erstwhile districts.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-69
Pridhvi Envirotech (P) Ltd.
The information was collected state Sample Registration system. The right to health is the economic,
social and cultural right to the highest attainable standard of health. Estimated Birth, Death, Infant
Mortality, Total Fertility and Under 5 Mortality rates from 2012 to 2015 of Telangana State detailed in
Table 3.22
Table 3.22
Estimated Birth, Death, Infant Mortality, Total Fertility and Under 5 Mortality rates from
2012 to 2015 of Telangana State
Sl. No
Particular
s
2012 2013 2014 2015
Rural Urb
an
Tot
al
Rur
al
Urb
an
Tot
al
Rur
al
Urba
n
Tota
l
Rural Urb
an
Total
1 Crude Birth Rate (per 1,000 Population)
17.9 16.6 17.5 17.7 16.7 17.4 18.4 17.4 18.0 18.2 17.2 17.8
2 Crude Death Rate (per 1,000 Population)
8.4 5.1 7.4 8.3 5.0 7.3
7.8 4.9 6.7 7.5 4.9 6.5
Males 9.7 5.4 8.4 9.2 5.6 8.1 8.5 5.3 7.3 - - - Females 7.2 4.8 6.4 7.4 4.5 6.6 7.1 4.6 6.1 - - -
3 Infant Mortality Rate (per 1,000
46 30 41 44 29 39 39 28 35 37 27 34
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-70
Pridhvi Envirotech (P) Ltd.
population)
Male 45 27 40 43 28 39 40 26 34 - - - Female 47 33 43 45 30 40 38 30 35 - - -
4 Total Fertility
Rate (TFR)
1.9 1.7 1.8 1.9 1.7 1.8 1.9 1.7 1.8 1.9 1.6 1.8
5 U5MR - - - - - - 41 29 37 37 28 34 Note: i). 2012 and 2013 rates pertains to combined state,
ii). U5MR: under Five Mortality Rate. Source: Sample Registration system 2012, 2013, 2014and 2015-16.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-71
Pridhvi Envirotech (P) Ltd.
3.12.8.1 Health Status of Surveyed Villages
There are 4 PHC, 4 Private clinics, 20 Private hospitals, and 24
RMP’s in the sampled villages.
7.9% of the household population reported incidence of lifestyle
and other diseases. The decease incidents reported 57.6% of
active adults, 42.4% of aged. The following diseases are
prevalent among the sampled population in the area.
Table 3.23
Disease patterns observed in sampled villages
S.No Diseases %percentage
1 T.B 0
2 Asthma 6.1
3 Hypertension 13.6
4 Diabetes 19.7
5 Others (Skin allergies, backaches, arthritis etc..)
60.6
3.12.9 Physical Infrastructure
The entire study area has access to well-developed and reliable physical
infrastructure - road, rail, power and telecommunication network. Both
public and private modes of road transport are common.
3.12.10 Social Infrastructure
Fairly well developed and reliable infrastructure exists in the
area for basic education, healthcare, housing, banking,
recreation and marketing of goods and services.
3.12.11 Historical Monuments and Places of Worship
Sri Ramalingeswara Swami Temple at Rameswaram built in the 19th
Century AD is the most significant place of worshipin the study area at a
distance of 7.2 km from the site.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-72
Pridhvi Envirotech (P) Ltd.
3.12.12 Defense and scientific establishments:
Indian Remote sensing Agency signal receiving and processing center is
located near Shadnagar which is an important national institution.
3.12.13 Aspirations and Apprehensions
As revealed during focus group discussions, nearly 62% of the respondents
are aware of the industrial growth in the area, but less than 38% are aware
of the proposed expansion project. While they are convinced with the
positive impacts of industrial development in the area, they are also wary of
the negative impacts on the surrounding environment. The perceptions of
the respondents as regards the establishment of more industrial projects in
the area could be summarized as follows:
o Industrial growth in the region will significantly support the
sustainable livelihoods in the area especially for skilled and semi-
skilled persons.
o Development of the secondary sector in the area has positively
contributed to induced development leading to creation of multiplier
self and wage employment opportunities.
o It would help further strengthen infrastructure development in the
area.
3.13 BIOTIC ENVIRONMENT
Scope of work for this study is in line with the ToR assigned to the company
which include identification of ecologically sensitive receptors based on
literature survey and field investigations, prediction of impacts and their
mitigation with conservation action plan. The study was carried out in core
area (project site) and in buffer area i.e. 10.0 km periphery from the
project site. The study was carried out scientifically using primary and
secondary data in order to bring out factual information on the ecological
conditions of the project site and its surroundings. Biological assessment of
the site was done to identify the presence of any Rare or Endangered or
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-73
Pridhvi Envirotech (P) Ltd.
Endemic or Threatened (REET) species of flora or fauna in the project site
or core area as well its buffer zone and to identify whether there are any
ecologically sensitive area within the area that is likely to be impacted
(buffer zone). The study also designed to suggest suitable mitigation
measures if necessary for protection of wildlife habitats conservation of
REET species if any.
The following approach has been chosen by the IAIA to help achieve ‘no net
loss’ of biodiversity:
Avoidance of irreversible loss of biodiversity
Seeking alternative solutions to minimize biodiversity losses
Use of mitigation to restore biodiversity resources
Compensation for unavoidable loss by providing substitutes of at least
similar biodiversity value
Looking for opportunities for enhancement
This approach can be called “positive planning for biodiversity.” It helps
achieve no net loss by ensuring the safety and survival of rare or
endangered or endemic or threatened (REET) species. This approach has
been adopted by the proposed project in the study under report.
3.13.1 Methodology
A reconnaissance survey has been made randomly to observe the critical
habitats to study in detail. General interviews were made with local people
on native animals and medicinal plants used frequently. A thorough review
was made at each sampling point and spent about 20-30 minutes at each
point. The present environmental condition is observed at core and buffer
areas.
A detailed survey of flora and fauna was carried out during the study
period.
The total area was analyzed in detail and with GIS tools and marked around
15 sampling points by covering the various ecosystems of core and buffer
zones in all the directions. Only photographs were taken during the field
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-74
Pridhvi Envirotech (P) Ltd.
survey and no damage is created to flora and fauna during the sampling.
Specimens were not collected and preserved.
Equipment / Instruments deployed
Digital Camera (NIKON 42 X zoom) GPS Binoculars Field observation book, Pen etc
3.13.3 Floral study
Quadrate method has been used for carryout the study of trees, shrubs,
herbs and grasses. 10 m X 10 m Quadrates for tree species, 5 m X 5 m
quadrates for shrubs and 1 m X 1 m quadrates for herbs. Statistical
analysis is made for 15 sampling points. Species were compared with
standard floras and identifying the plants need for conservation. The status
of the each species was represented by common, sporadic or rare. The data
was compared with the list mentioned in red data book to check REET
species.
Ecological parameters viz., abundance, density, frequency, Relative
abundance (RA), Relative density (RD), Relative frequency (RF), Important
value index (IVI), Shannon-Wiener diversity index were derived from the
quantitative primary data collected during field survey.
Importance Value Index (IVI): RD + RF +RA
Species Diversity
Shannon Diversity Index (H’) has been used for estimating the diversity
among the core & buffer zones in order to know the species richness and
dominance.
H’= - Pi. ln Pi
S= Number of individuals of one species Where Pi = -------------------------------------------------------- N = Total number of all individuals in the sample
and, ln is the logarithm to the base e
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-75
Pridhvi Envirotech (P) Ltd.
Communities with less number of species with high level of dominance or
low level of uniformity will have lower diversity. Thus it is a statistical
function based on the richness and evenness components. Evenness and
dominance are inversely related.
3.13.4 Faunal study
A detailed study has been carried out for faunal species by direct and
indirect methods. Direct sightings were made for aves, reptiles and insects
and secondary data on mammals was collected from local villagers. Bird
surveys were carried out through point count method at dawn and desk
near water bodies. These techniques are accepted in EIA studies as per the
EIA Notification of 2006. The species sighted were photographed and
identified with standard pictorial guides. Scheduling of species were done
according to Indian Wildlife Protection act (1972) and IUCN is done for each
species and checked the REET species. No quantitative data was calculated
as some species are listed through secondary source. As the animals were
migratory, habitats used by protected, important or sensitive species for
breeding, nesting, foraging, resting, over wintering, migration were
ascertained.
3.13.4.1 Rationale for Survey Method:
in the study area most of the region is dry and mesophytic conditions.
There is only one Reserve forest (Mysura Kammadhanam RF at 9.07 km
(SE) exists within the study area. Natural Vegetation is limited to pond side
and road side apart from the existing Reserve forests. The impacts of the
proposed activity and cumulative impact on all aquatic ecosystems are
studied. All aquatic bodies are studied for birds and other aquatic flora and
fauna. The sampling points are selected in all the directions and ecosystems
along with the wind direction pattern. During the survey, belt transact
method applied in all natural vegetation identified in the study area.
Numbers of sampling points were finalized through area-species graph
method. 20 sampling points were finally taken to do statistical analysis of
the vegetation in Reserve forest and natural vegetation at open lands. No
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-76
Pridhvi Envirotech (P) Ltd.
statistical analysis done for faunal components. Only the list of species were
collected from Forest department working plan and crosschecked with
primary and secondary data collected during field visit.
3.13.4.2 Secondary data:
Secondary data: The key referral material is from Telangana state working
plan data of the forest department. Certain published papers related to
region in the recent years are also considered. Ground validation has done
through elderly village people and personal field visits. Besides measuring
these parameters, other biodiversity aspects, such as species endemicity
(Pascal, 1988; Pascal and Ramesh 1990; FRLHT, 2001), conservation status
and life forms, have been collected from published literature. For all the
species found in the area during ecological survey, IUCN, Red Data Books
of the Botanical Survey of India and Wildlife Schedule I and II are examined
to verify their present conservation status.
3.13.5 Present Status of biotic environment
Description of the project site environment: The project site is open land
with vegetation like natural grass and common weeds and developed green
belt
The proposed project falls in
6D – Deccan Peninsula Deccan Plateau as per the Biogeography
Classification of India.
Hot Semi arid type as per the India's Köppen climate classification.
The vegetation of the study area falls under
5A: Southern tropical dry deciduous forests C3: Southern dry mixed
deciduous forest;
6A: Southern tropical thorn forests DS1: Southern thorn scrub, 2S1:
Secondary dry deciduous forest
By revised classification of Indian forest types (Champion and Seth, 1968).
These types of forests are seen throughout the Eastern Ghats and few parts
of Western Ghats of the country.
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-77
Pridhvi Envirotech (P) Ltd.
The proposed project site does not encounter with any kind of forest types
like Reserve Forest, Protected forest or un- classed Forest (declared
Protected under “ The Indian Forest Act, 1927”) and “Forest (Conservation)
Act, 1980 with Amendments Made in 1988”. (Source: Forest Department).
Further no tree cutting is involved in the project as there is no vegetation at
all within this project site. Thus no forest Clearance is required for the
proposed development. There no Scheduled species recorded within the
proposed construction site.
Wetland: No wetland notified under “The Ramsar Convention – 1971” or
listed under “the National wetland Conservation Programme – 2009” is
reported within 10 km from project boundary.
3.13.6 Ecology at project site:
For the proposed project activity, no vegetation needs to be removed.
There are good number of plants maintained under greenbelt towards the
boundary wall and all the directions. These plantations include
Peltophorumpterocarpum, Leucaenaleucocephala, Tectonagrandis,
Terminalia catappa, Polialthialongifolia, Plumaria alba, Cocos nucifera,
Plumaria pendula, Mangiferaindica, Sapota, Guava, Amla and other hedges
and ornamental plants. Tall and broad leaved trees were grown towards the
boundary wall to check the pollution dispersal rate. Vincarosea, Aloe vera
and other herbaceous plants are grown near the entrance gate.
Except few common birds such as Common babblers, Green bee eaters,
Purple sunbirds etc, no major fauna or breeding sites found within the site.
There no migratory paths or boundary of any protected areas or ecological
sensitive zones present in the proposed site.
3.13.6.1 Ecology of Core Zone Habitat:
The core zone habitat from project site boundary to 5 sq. km. Eucalyptus
globules, LeucaenaleucocephalaTectonagrandis, Cocos nucifera. Phoenix
aculis, Borassusflabellifer, Azadirachtaindica, Prosopisjuliflora,
Tribulusterrstris, Achyranthesaspera, Balanitesaegyptiaca, Opuntia, are
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-78
Pridhvi Envirotech (P) Ltd.
mainly restricted to waste and cultivable waste lands. Albizialebbeck,
Delonixregia, Azadirachtaindica, Peltophorumpterocarpum., Terminalia
catappa, Dalbergiasissoo and Tamarindusindica are predominant near
villages.
The faunal composition generally with arboreal and semi arboreal based
animals. Within the core zone common mongoose, Squirrels are sighted
apart from few reptilian species. From the secondary source (local people
working in the plant) it is also revealed that presence of common snakes
exists here. Common bird species such as Herons, Paddy egrets, Green bee
eaters, Indian rollers, Parakeets, White headed babblers, Weaver birds,
Mynas, Black drangos, Crows, Sparrows are sighted here. Butterflies and
dragonflies are fairly common near herbs and flowering shrubs. Two poultry
forms are exists nearer to the project site.
3.13.6.2 Ecology of Buffer Zone Habitat:
The buffer zone habitat from 5 sq. km radius of the project site to 10
sq km. There are no endangered and endemic plants present in the buffer
and core zones. The faunal composition was also estimated based on the
direct and indirect evidences. Buffer zone is mostly with human habitations.
Buffer area is mainly non cultivable waste land. This area has few trees and
shrubs with Mesophytic adaptation.
The faunal composition was also estimated based on the direct and indirect
evidences. Azadirachtaindica, Prosopisspicegera, Borassusflabellifera,
Phoenix aculis, Eucalyptus globules, Thespeciapopulnea, Delonixregia,
Dalbergiasisso, Pongamiapinnata and Polyalthialongifolia, Ficussp, Acacia
sp, Euphorbia caudifolia, E. tirucelli, Opuntia are mainly restricted to waste
and culturable waste lands. Albiziaprocera, Albizialebbeck, Delonixregia,
Azadirchtaindcia, Peltoforum sp., Terminalia catapa, Dalbergiasisso and
Tamarindusindica are predominant near surrounding villages.
The predominant vegetation under reserve forest block are
Diospyrosmelanoxylon, Lanneacoromandelica, Madhucaindica,
Soymidafebrifuga, Caesalpiniabonduc, Borassusflabellifer, Phoenix
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-79
Pridhvi Envirotech (P) Ltd.
sylvestris, Prosopisjuliflora, Acacia nilotica, Azadirachtaindica,
Dodonaeaviscosa Phoenix acaulis and Randiadumetorum. Natural terrestrial
vegetation along with few plantations such as Leucaenaleucocephala,
Eucalyptus were found in buffer zone. Manmade ecosystem is predominant
in this zone.
Endemic, Threatened and Endangered Plant Species
In the floristic checklist, the study area shows moderate floristic diversity.
Number of floral species in the study area is 219. A good number of species
are commercially cultivated in orchards. Number of plant species have
medicinal value and also important for other non-timber produces. From
the present survey it appears that no endangered plant species exist in the
study area.
Tamarindusindica in Buffer zone Cattle egrets in the agricultural fields near Buffer zone
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-80
Pridhvi Envirotech (P) Ltd.
Greenbelt within the campus Greenbelt within the campus
3.13.6.3 Quantitative analysis
The study is mainly focused through secondary data validation from
primary observations. Checklist is prepared and marked the species noticed
during rapid assessment. 20 sampling points are selected through Area-
Species graph.
The habitat wise and ecosystem wise status of various floral species
observed are given here graphically in Figure 3.19.
And pyto sociological data of the area is presented in table 3.24
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-81
Pridhvi Envirotech (P) Ltd.
Figure 3.18 The habit wise and ecosystem wise status of various
floral species observed
Table 3.24 Phyto sociological data of study area
S.No Scientific Name Density Rel
Density
Freq-
uency
Rel
Freq-
uency
Abun-
dance
Rel
Abun-
dance
IVI
1 Randiadumetorum 0.85 4.14 55.00 5.56 1.55 4.00 13.69
2 Diospyrosmelanoxylon 0.35 1.70 25.00 2.53 1.40 3.62 7.85
3 Acacia nilotica 0.90 4.38 60.00 6.06 1.50 3.88 14.32
4 Azadirachtaindica 0.85 4.14 60.00 6.06 1.42 3.67 13.86
5 Caesalpiniapulcherrima 0.45 2.19 40.00 4.04 1.13 2.91 9.14
6 Cassia fistula 0.50 2.43 40.00 4.04 1.25 3.24 9.71
7 Eucalyptus globules 2.70 13.14 50.00 5.05 5.40 13.98 32.17
8 Delonixregia 0.80 3.89 55.00 5.56 1.45 3.76 13.21
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-82
Pridhvi Envirotech (P) Ltd.
9 Diospyrosmelanoxylon 0.60 2.92 50.00 5.05 1.20 3.11 11.08
10 Lanneacoromandelica 0.35 1.70 35.00 3.54 1.00 2.59 7.83
11 Soymidafebrifuga 0.55 2.68 55.00 5.56 1.00 2.59 10.82
12 Leucaenaleucocephala 2.45 11.92 60.00 6.06 4.08 10.57 28.55
13 Peltophorumpterocarpum 1.60 7.79 70.00 7.07 2.29 5.92 20.77
14 Phoenix sylvestris 1.35 6.57 70.00 7.07 1.93 4.99 18.63
15 Prosopisjuliflora 1.15 5.60 65.00 6.57 1.77 4.58 16.74
16 Pongamiapinnata 1.05 5.11 50.00 5.05 2.10 5.44 15.60
17 Lantana camara 1.50 7.30 50.00 5.05 3.00 7.77 20.11
18 Dalbergiasissoo 0.95 4.62 35.00 3.54 2.71 7.03 15.18
19 Dodonaeaviscosa 1.60 7.79 65.00 6.57 2.46 6.37 20.72
100
100
100 300.00
Figure 3.19 Graph showing Important Value Index of dominant tree
species within study area
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-83
Pridhvi Envirotech (P) Ltd.
Table 3.25 Biodiversity indices values of the sampling sites in buffer
zone
Distribution pattern (A/F ratio): The ratio between abundance and
frequency was used to interpret the distribution pattern of species
(Whitford, 1949). Distribution pattern of species in the study area is
identified as random distribution as the value of A/F ratio is 0.039. This
random distribution of species is mainly due to various ecosystems present
in the core zone. The Shannon indices value of study area is 2.855 indicates
moderate diversity (Normal diversity in ecological studies is 1.5 to 3.5
range (Kerkhoff, 2010). Population size and Dominance of the species is
6% and Evenness is around 95% which indicates the species are evenly
distributed in core and buffer zones. This might be due to contiguous
patches of Eucalyptus and Subabul species and natural species such
Azadirachtaindica, Phoenix, Prosopisjuliflora (near the villages),
Peltophorumpterocarpum and Delonix regia (near road side). The present
study indicates A<B<C>D>E in frequency classification and as per the
Raunkiaer’s law of frequency classification indicates that species diversity is
distributed maximum for 40 to 60%.
This result indicates that all most all plants frequency is more or less equal
due to some of the plant species such as Diospyrosmelanoxylon, Acacia
nilotica, Azadirachtaindica, Caesalpiniapulcherrima, Cassia fistula,
Eucalyptus globules and Delonixregia are frequently found floral species
throughout the region.
Dominance D 0.060
Shannon H 2.855
Simpson 1-D 0.940
Evenness e^H/S 0.945
A/F value 0.039
M/s. Dashree Ispat (P) Ltd Unit-I Draft EIA Report
3-84
Pridhvi Envirotech (P) Ltd.
3.13.7 Fauna within the Core and buffer zones
Throughout the study area, there no direct evidence of wild animal species
observed. From the secondary source (local people near villages) it is also
revealed that presence of common snakes exists here. Common bird
species such as Paddy egrets, Green bee eaters, Indian rollers, Parakeets,
common babblers, Weaver birds, Mynas, Black drangos, Crows, Sparrows
are sighted here.
List of faunal species identified in the area are given in Annexure III
3.14 Aquatic ecosystem
The study area comprises of many small and medium sized tanks. The main
aquatic bodies present in the region are Rangampalli 1.29 kms (SW),
SardarnagarCheruvu – 1.40 kms (NE), Pirlaguda – 3.02 kms (SW),
Duntikunta – 3.88 kms (SW), PeddaCheruvu – 8.77 kms (SE),
Inayakhanguda -7.24 kms (SE), KesaramCheruvu – 7.21 kms (NE). These
ponds provide the suitable habitat for fresh water aquatic and semi aquatic
plants. Hydrilla, Ipomoea aquatic, Lemna minor, Limnophilaheterophylla,
Marsileaquadrifolia,
NeptuniaoleraceaOperculinaturpethum,Neptuniaoleracea, Typhaangustata
are most common in the study area. There were no REET category species
of aquatic and semi aquatic plants in the study area. The floristic survey of
the existing farming site witnesses scattered growth of grasses (mainly
weeds), rooted hydrophytes, emerging hydrophytes, shrubs in undisturbed
area where human movement is absent. Among herbaceous species, weeds
are commonly reported such as Congress grass
(Partheniumhysterophorus), Lantana (Lantana Camara), and Datura
(Datura stromonium). Rooted hydrophytes are reported along the banks,
where water level is less than a foot
Chapter – 4
IDENTIFICATION & PREDICTION
OF IMPACTS
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
4-1
Pridhvi Envirotech (P) Ltd.
CHAPTER - 4
IDENTIFICATION & PREDICTION OF IMPACTS
4.1 Identification of impacts
Identification of impacts is one of the basic analytical steps of EIA for
subsequent prediction and evaluation of impacts. A number of
methodologies are available for the identification of impacts. “Net Work
Method”, which follows the cause – condition- Effect relationship is adopted
for identifying impacts due to the activities of proposed expansion of M/s.
Devashree Ispat (P) Limited Unit I.
The generation of cause –condition –effect networks (chain of events)
should follow the above mentioned activities and actions. This type of
method is advantageous in recognizing the series of impacts triggered by
the plant activities. Thus this method had provided a “Road map” type of
approach to the identification of second and third order effects.
The idea was to account for the project activity and identify the different
types of impacts that would initially occur. The next was to select each
impact and identify the impacts. The main advantage of this approach is
that it allowed identifying the impacts by selecting and tracing out the
events as they may occur.
4.2 Impact Networks
The purpose of identifying the impacts is that if it aids in making
appropriate decision to mitigate the adverse consequences if any. It may be
pointed out that the distinction between magnitude and importance of the
impact should be appreciated. Thus the degree of extensiveness and scale
of impacts and consequence based on value judgments are generalized
while identifying impacts. As it is imperative that the impact will normally
lead to a chain of reactions, the construction of network charts brings out to
certain extent the appropriate levels of the risks that may occur due to the
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
4-2
Pridhvi Envirotech (P) Ltd.
interventions while interacting with hydrogeological, biological and social
systems.
Fig 4.1 to 4.6 represents the identified impacts for various components of
environment viz. air, noise, and water land and socio economic aspects. In
the above mentioned figure the lines means –“had an effect on”.
4.2.1 Air Environment
The Primary impact of air pollutants will be on the air quality. As dust
emissions are the main pollutant from this type of industries, the air quality
will change if dispersion is slow. This will lead to if pollution is for shorter
period, immediate health problems. If it continues for a long period, it may
also have an impact on climatic changes, ecological equilibrium and
economic production of crops. The odor and visibility aspects of air pollutant
can have impacts on aesthetics of region.
4.2.2 Water Environment
Waste water will affect the environment both directly and indirectly
primarily it may affect the land and water quality. This leads to
deterioration of re-production levels of both terrestrial and aquatic flora and
fauna.
4.2.3 Noise Environment
The noise will primarily affect the ambient noise levels. Excessive noise will
trigger health risks such as headaches, depression, deafness and
retardation of sensory mechanisms.
4.2.4 Land Environment
The change in the land use during and after the construction phase is
unavoidable. However as long as it is not affecting the soil quality chemistry
and sedimentation, the impact is not an undesirable one
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
4-3
Pridhvi Envirotech (P) Ltd.
4.2.5 Biological Environment
The particulate matter tend to alter soil matrix and water quality. The
impact will be on the native biota leading to density reduction and
extinction of sensitive species. There may be change in the species diversity
and food chain.
4.2.6 Socio-economic Environment
Primarily, the impact is expected on the economic environment. The
generation of jobs will occur during operation and construction phases.
There is scope of multiplier effect on secondary and tertiary employment.
The socio economic structure will have a positive change and quality of life
would improve due to increase in urbanization.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-4
Pridhvi Envirotech (P) Ltd.
PROJECT
RELEASE OF AIR POLLUTANTS RELEASE OF HEAT
CHANGE IN
AIR QUALITY
IMPACTS ON
VISIBILITY
PARTICULATES
DEPOSITION ON
SOIL, WATER,
LAND
PRIMARY
IMPACTS
SECONDARY
IMPACTS
TERTIARY
IMPACTS
IMPACT ON
HUMAN HEALTH
IMAPCTS ON
ECONOMIC
OUTPUT
AESTHETIC
IMPACTS
IMPACTS ON
AGRICULTURAL
CLIMATIC CHANGES
IMPACTS ON FLORA &
FAUNA
IMPACTS ON SOCIO CULTURAL ENVIRONMENT
Fig 4.1 Impacts Network for Air Environment
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-5
Pridhvi Envirotech (P) Ltd.
PROJECT
NOISE EMISSION
PRIMARY
IMPACTS
SECONDARY
IMPACTS
TERTIARY
IMPACTS
CHANGE IN AMBIENT
NOISE LEVEL
HEALTH RISKS
Fig 4.2 Impacts Network for Noise Environment
MIGRATION OF BIRDS,
REPTILES POPILATION
IMPACTS ON WORK
OUTPUT & EFFICIENCY
IMPACTS ON
ECONOMIC OUTPUT
IMPACTS ON SOCIO
CULTURAL ENVIRONMENT
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-6
Pridhvi Envirotech (P) Ltd.
PROJECT
PRIMARY
IMPACTS
SECONDARY
IMPACTS
TERTIARY
IMPACTS
Fig 4.3 Impacts Network for Land Environment
IMPACTS ON
ECONOMIC OUTPUT
IMPACTS ON SOCIO
CULTURAL ENVIRONMENT
DISTRUBANCE OF
LAND
ABSTRACTION OF
WATER
DISPOSAL OF WASTE
WATER SLUDGE ON LAND
CHANGE IN SOIL
TEXTURE &
PERMEABILITY
CHANGE IN GROUND
WATER REGIME
SALTWATER
INTRUSION
SUBSTANCES ON LAND
PARTICULATE DEPOSITION
ON LAND
IMPACTS ON
LANDSCAPE
SOIL SALINITY IMPACTS ON FLORA &
FAUNA
IMPACTS ON AGRICULTURAL
PRODUCE
IMPACTS ON LIVE
STOCK
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-7
Pridhvi Envirotech (P) Ltd.
PROJECT
Fig 4.4 Impacts Network for Biological Flora & Fauna
AIR EMISSION WASTE WATER SOLID WASTE
SOIL MATRIX
SOIL ACIDIFICATION
AFFECT NATIVE SOIL BIOTA
NITROGEN FIXING NITRIFYING OTHER pH SENSITIVE MICRO FLORA
DECOMPOSITION MINERILIZATION OF ORGANIC MATTER
REDUCTION IN SOIL FERTILITY & PRODUCTIVITY
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-8
Pridhvi Envirotech (P) Ltd.
EFFECTS OF WASTE WATER
Fig 4.5 Identification of Likely Impacts of waste water
DIRECT INDIRECT
LAND ECO SYSTEM WATER ECO SYSTEM LAND ECO SYSTEM WATER ECOSYSTEM
ECOLOGICAL IMBALANCES SOCIO ECONOMIC
IMBALANCES
CHANGE IN SOIL
TEXTURE
SHIFT IN GROUP OF
DESIRED ORGANISMS
INJURIOUS TO
EXISTING PLANT
COMMUNITY
CHANGE IN WATER
RESOURCES
SHIFT IN THE DYNAMIC
POPULATION OF ACQUATIC
FLORA AND FAUNA
DELETERIOUS TO WATER
LIVING BODIES
FERTILITY OF LAND
PATTERN OF CROPS
GROUND WATER
TABLES & ITS QUALITY
COMMUNITY
HEALTH
SHIFT IN DYNAMICS
FLORA FAUNA
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-9
Pridhvi Envirotech (P) Ltd.
PROJECT
Fig 4.6 Impacts Network for Socio Economic & Cultural Environment
ECONOMIC INPUT
COST
DEVELOPMENT OF
ANCILLARY
INDUSTRIES
ECONOMIC
OUTPUT COST
BETTER
PRODUCT
AVAILABILITY
AIR WATER
LAND NOISE
POLLUTION
EFFECT ON
HUMAN HEALTH
SAVING OF FOREIGN
EXCHANGE
NET INCOME OUTPUT
CHANGE IN ECONOMIC
BASE OF THE REGION
Employment
Opportunities
DEMAND for
Communication
FACILITIES
Demand for
Infrastructure
Facilities
EFFECT ON
Agriculture &
Fisheries
EFFECT ON Visual
Environment
EFFECT ON Building
Materials,
Monuments
EFFECT on Supply,
Sewerage, solid
waste Management
EFFECT on
Educations, Medical,
Transport Facilities
EFFECT on Human
health & Recreational
facilities
AESTHETIC
RISK
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-10
Pridhvi Envirotech (P) Ltd.
4.3 Prediction of Impact on Air Quality
4.3.1 Details of Mathematical Modeling
A large number of different mathematical models for dispersion calculations
are in practice in many parts of the world. Most of the models for
prediction of downwind concentrations are based on Gaussian dispersion.
The principle behind the Gaussian dispersion models is Gaussian probability
distribution of concentration in both vertical and horizontal cross wind
directions about the plume central line.
Predictions of ground level concentrations of the pollutants were carried
out based on site meteorological data collected during the study period. For
calculation of predicted ground level concentrations, AERMOD, a model of
Lakes Environmental based on USEPA, ISCST3 algorithms, was used; as
it’s based on more sophisticated algorithm incorporating deposition, better
algorithm for area sources, etc.
The AERMOD-9.5.0 model include several new features. A revised area
source algorithm and revised dry deposition algorithm have been
incorporated in the models. The AERMOD model also include an algorithm
for modeling impacts of particulate emissions from open pit sources, such
as surface coal mines. The Short Term model includes a new wet
deposition algorithm, and also incorporates the COMPLEX1 screening model
algorithms for use with complex and intermediate terrain. When both
simple and complex terrain algorithms are included in a Short Term model
run, the model will select the higher impact from the two algorithms on an
hour-by-hour, source-by-source, and receptor by- receptor basis for
receptors located on intermediate terrain, i.e., terrain located between the
release height and the plume height.
The salient features of the ISCST3 model are presented below in Table
4.1. The air quality predictions have been made using the model evaluation
protocol for fugitive dust impact modeling for surface coal mining
operations (EPA 1995, EPA 1994).
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-11
Pridhvi Envirotech (P) Ltd.
Table 4.1
Salient Features of the AERMOD Model
S.No Item Details
1 Model name AERMOD 9.5.0
(Based on USEPA algorithm)
2 Source Types Point, Area, Volume, Open Pits
3 Dispersion Equation Steady State Gaussian Plume
Equation
4 Diffusion Parameters Pasquill Gifford Co-efficient
5 Plume Rise Briggs Equation
6 Time Average 1 hr to Annual/Period Has Short
Term and Long Term modeling
options
7 Deposition Both Dry and Wet Deposition
8 Application Input Data:
(i) Source Data Stack co-ordinates, Stack Height,
Exit Gas Temperature and Exit gas
velocity
(ii) Receptor Data Grid interval, number of receptors,
receptor elevations
(iii) Meteorological
Data
Hourly meteorological data i.e.
wind speed, Wind direction, ambient
temperature, humidity, rain fall and
Cloud cover.
4.3.1.1 Model Formulation
The model uses the following steady state Gaussian plume equation. The
basic equation for calculating the concentration of pollutants for any point
in x, y, z co-ordinates is given below:
C(x,y,z,H) = Q/2 y z U exp[-1/2(y/y)2] x [exp{-1/2(z-h/z)
2}
+ exp {-1/2 (z+H/z)2}]
Where
C= Concentration of pollutants in mg/cu m
Q= Strength of emissions in g/sec.
H= Effective Height (m), i.e., physical height + plume raise
y, z= diffusion coefficients in y and z directions in m.
U= average wind velocity in m/sec.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-12
Pridhvi Envirotech (P) Ltd.
The following assumptions are made in Gaussian dispersion model.
The dispersion parameter values used for horizontal dispersion coefficient
and vertical dispersion coefficients are those given in the “Work book of
atmospheric dispersion estimates”. These dispersion coefficients assume a
sampling time of about 10 min., the height values of interest to be in the
lowest several hundred meters of the atmosphere, a surface corresponding
to the open country. The stacks are tall enough to be free from building
turbulence so that no aerodynamic down wash occurs. The given stability
exists from ground level to well above the top of the plume.
The Gaussian dispersion model has been tested extensively for its validity
and found to be reasonably applicable for different atmospheric conditions.
BIS has also adopted this basic plume dispersion model. Hence the same
model is adopted for predictions of downwind concentrations of pollutants
in this report.
4.3.1.2 Meteorological Data
Data recorded by the weather monitoring station at site on wind speed,
direction, solar insolation, temperature and cloud cover at one hourly
interval for three months i.e. One full season has been used for
computations. Hourly atmospheric stability determined based on the
technique suggested by Turner. Visual observations were made on for the
solar insolation and cloud cover during study period. The methodology
adopted for establishing the hourly stability class is given in Table 4.2.
Table 4.2
Atmospheric Stability Classification
Wind
Speed
(m/sec)
Insolation (Day time) Night time
Strong Moderate Slight
Thin over cast
or >4/8 low
cloud
<3/8
Cloud
<2 A A-B B - -
2-3 A-B B C E F
3-5 B B-C C D E
5-6 C C-D D D D
>6 C D D D D
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-13
Pridhvi Envirotech (P) Ltd.
Mixing Height:
As the site specific mixing height is not available USEPA approved general
mixing heights as applicable for Industrial Source Complex (ISC) model
have been considered for modeling to establish the worst case scenario.
The mixing heights considered for modeling is given Table 4.3.
Table 4.3
Mixing Heights Considered for Computations
Stability Class Mixing Height (m)
A 1300
B & C 900
D 750
E & F 400
4.3.2 Plant Emissions
The sources of air pollution from the plant of M/s. Devashree Ispat (P)
Limited Unit-1 are outlined in the table. The major pollutants generated
from the induction furnace and re-heating furnace are SO2, NOx and
Particulate Matter. Based on the steel melting process, details the emission
rates of various pollutants are calculated. The emission rates of SO2, NOx
and Particulate Matter from each stack are presented in Table 4.4.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-14
Pridhvi Envirotech (P) Ltd.
Table 4.4
Emission Details of Pollutants from Stack
S. No Emission source Status Control Equipment
Stack height
(M)
Exit Gas Temperature
(oC)
Exit Gas Velocity (m/s)
Emission Rates (g/Sec)
PM10 PM2.5 SO2 NOx
1 induction furnace-200
TPD
Upgrading existing furnace
from 100 TPD
Bag Filters
30
150
9.45
0.80
0.35
1.80
1.10
2 Reheating Furnace (1x340 TPD)*
Existing Bag Filters 30 142 7.36 0.75 0.26 1.58 1.20
3 DG set: 1x125 KVA
Existing Acoustic Enclosure
10 125 12.3 0.148 0.081 0.17 0.22
4 DG set :
1x 150 KVA
Proposed Acoustic
Enclosure
10 130 13.2 0.17 0.09 0.18 0.24
5 DG set : 1x265 KVA
Proposed Acoustic Enclosure
10 137 12.7 0.20 0.1 0.19 0.32
*In case when Direct Hot charged Billets through conveyor cannot feed the Rolling Mill sufficiently, Billets from Re-
heating Furnace which is standby would be made available.
In case the Reheating Furnace is used in full capacity, the production capacity would be 340 TPD.
Note: 1) DG sets are being used as standby power source only. (Average running hours per day is about 30
minutes)
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-15
Pridhvi Envirotech (P) Ltd.
4.3.2.1 Air Quality Predictions
Predictions of ground level concentrations of the pollutants were carried
out based on site meteorological data collected during the period from
December 2017–February 2018. For calculation of ground level
concentrations a grid of 20 km X 20 km with a receptor interval of 1000
meters is considered.
The composition of particulate matter was obtained from USEPA AIRCHIEF
AP-42 and the same was considered in determining the source
concentration of PM10 for prediction purpose. The predicted maximum 24
hourly ground level concentrations of PM10, PM2.5 SO2 and NOx and
distance of occurrence during different seasons of study period are
presented in Table 4.5.
It may be observed that the annual predicted maximum 24 hourly GLC’s
of PM10, PM2.5, SO2 and NOx are 3.506, 1.845, 7.124 and 5.243 µg/m3
respectively and the maximum values are observed at Project. However it
may be noted that the predicted values of the SO2 and NOx are based on
the assumption that the DG sets are used constantly, where as the DG set
usage is only during load shut down from TSCPDCL.
The GLC’s are also predicted at air quality monitoring locations and the
predicted GLC’s are presented in Tables 4.6 and the cumulative
concentrations at various villages are tabulated in Table 4.7.
Table 4.5
Maximum Predicted 24 hourly GLC’s
S.No Parameter Predicted GLC
(g/m3)
Location
1 PM10 3.506 Project Site
2 PM2.5 1.845 Project Site
3 SO2 7.124 Project Site
4 NOX 5.243 Project Site
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-16
Pridhvi Envirotech (P) Ltd.
Table 4.6
Predicted GLC’s at Monitoring Locations
S. No
Monitoring Location
Direction
Distance (Km)
Predicted GLC (µg/m3)
PM10 PM2.5 SO2 NOx
1 Project Site -- -- 3.506 1.845 7.124 5.243
2 Ellikatta NE 0.87 Km 0.095 0.050 0.461 0.142
3 Rangampalli SW 1.4 Km 1.318 0.706 1.524 1.922
4 Chowlapalli SW 3.4 Km 0.259 0.137 0.396 0.383
5 Mughalgidda W 3.0 Km 1.658 0.878 2.019 2.454
6 Antanam N 5.2 Km 0.033 0.017 0.184 0.049
7 Shadnagar E 6.2 Km 0.023 0.012 0.102 0.034
8 Pidkiryla SE 3.2 Km 0.195 0.103 0.754 0.290
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-17
Pridhvi Envirotech (P) Ltd.
Table 4.7
Cumulative Concentrations at Various Villages
AAQ
Location
Base Line Concentration (µg/m3)
Predicted GLCs (µg/m3)
Cumulative Concentration (µg/m3)
PM10 PM2.5 SO2 Nox PM10 PM2.5 SO2 Nox PM10 PM2.5 SO2 Nox
Project Site 85.6 44.6 16.2 21.4 3.506 1.845 7.124 5.243 89.11 46.45 23.32 26.64
Elikatta 73.5 30.2 15.2 18.3 0.095 0.050 0.461 0.142 73.59 30.25 15.66 18.44
Rangampalli 64.3 30.5 15.2 17.3 1.318 0.706 1.524 1.922 65.62 31.21 16.72 19.22
Chowlapalli 67.2 27.4 15.2 17.3 0.259 0.137 0.396 0.383 67.46 27.54 15.60 17.68
Mughalgidda 65.3 27.4 15.2 18.3 1.658 0.878 2.019 2.454 66.96 28.28 17.22 20.75
Antaram 62.3 28.4 15.2 17.3 0.033 0.017 0.184 0.049 62.33 28.42 15.38 17.35
Shadnagar 63.2 26.4 14.6 17.2 0.023 0.012 0.102 0.034 63.22 26.41 14.70 17.23
Pidkiryla 60.2 23.5 14.2 17.3 0.195 0.103 0.754 0.290 60.39 23.60 14.95 17.59
Reserve Forest
Reserve Forest
Predicted Ground Level
Concentrations (µg/m3)
PM10 PM 2.5 SO2 NOx
MysuraKammadhanam RF 0.065 0.034378 0.30764 0.098497
The predicted ground level concentrations are graphically displayed for PM10, PM2.5, SO2, and NOx respectively in
Figure 4.7 – 4.10.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-18
Pridhvi Envirotech (P) Ltd.
Figure 4.7 Isopleths Showing 24 Hourly GLC’s of PM10
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-19
Pridhvi Envirotech (P) Ltd.
Figure 4.8 Isopleths Showing 24 Hourly GLC’s of PM2.5
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-20
Pridhvi Envirotech (P) Ltd.
Figure 4.9 Isopleths Showing 24 Hourly GLC’s of SO2
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-21
Pridhvi Envirotech (P) Ltd.
Figure 4.10 Isopleths Showing 24 Hourly GLC’s of NOX
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-22
Pridhvi Envirotech (P) Ltd.
It may be observed from the Table that the predicted results show that
the incremental rise over existing base line status of ambient air quality is
marginal and predicted ambient air quality after expansion activity will be
within the prescribed limits by CPCB for residential and rural areas. The
pollution control measures and height of stack is sufficient to disperse the
pollutants into the atmosphere and keeping the baseline levels within the
prescribed limits.
4.4 Prediction of Impacts on the Noise Environment
The sound intensity level generated by noise sources decreases with
increasing the distance from the source due to wave divergence. An
additional decrease in sound pressure level with distance from the source
is expected, due to atmospheric effect or its interaction with objects in the
transmission path.
For hemispherical sound wave propagation through homogeneous loss
free medium, cane and estimate noise levels at various locations, due to
different sources using model based of first principle as per the following
equation:
Lp2 = Lp1 Log (r2/r1) – Area ……… (1)
Where Lp1 and Lp2 are sound pressure levels at points located at distances
r1 and r2 from the source and Ae1.2 is the excess attenuation due to
environmental conditions.
Combined effect of all the sources can then be determined at various
locations by logarithmic addition.
In the first approximation one can assume that for all general population
in the villages, every noise source in the plant is a point source. The
average equivalent sound power level of such a point source can be
estimated for different distances and directions from hypothetical source
by applying equation:
Lp = Lw - 20 Log r Ae – 81 ………(2)
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-23
Pridhvi Envirotech (P) Ltd.
Where Lw is the sound power level3 of the source, Lp is the sound
pressure level at a distance of a r and Ae Is environmental attenuation
factor. A combined noise level Lp (Total) of all the sources at a particulate
place is given by:
Lp (Total) = 10 Log ( 10(Lp1/10) + 10 (Lp2/10)+ …..) ……(3)
Noise levels emanating from most of the proposed steel plant complex are
given in Table 4.8
Table 4.8
Average typical Noise Levels from Existing Industrial Units
No Source Noise Level – dB(A)
1 DG Sets 80 – 85
2 Rolling mill
operations
70 – 85
3 Furnace
operations
70 – 80
4 Material
movement &
Transportation
70 - 80
The DG sets are used only during power failure for controlling emergency
operations. Predictions have been made taking into account all operations
and utilities thus reflecting the worst – case scenario. The predicted
cumulative noise levels due to the source and the existing level as
calculated from the logarithmic model without noise attenuation ranged
between 40 dB to 70 dB at a distance ranging between 100 m and 150 m.
There is no residential area in the immediate surroundings and hence the
impact of noise on the population is the surrounding areas are negligible.
The model assumes that there are no obstructions/structures on the path
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-24
Pridhvi Envirotech (P) Ltd.
However it must be noted that green belt will attenuate the noise levels
further.
4.5 Prediction of Impacts on Water Environment
Impact on water quality
No impact on water quality is anticipated as the unit proposes to cool the
hot water from furnace and rolling mill sections and recycle back. Mill
cooling waste water is settled in settling tanks to remove Oil & Grease
contamination and Suspended solids. The mill waste generated from
settling tanks would be sold as bi-product.
As the mill waste need to be dewatered and dried before sold out,
contamination of soil likely to be there if no proper facilities of de-
watering are not adopted
The sewage Treatment plant is proposed to treat domestic waste water
generated at tune of 19.0 KLD from toilets and canteen facilities. The
treated water will be re used for gardening purpose.
Ground water quality improvement
The overall type of groundwater occurring around the proposed site is
indicative of fresh water with low to moderate total dissolved solids
(TDS), dominance of calcium bicarbonate (HCO3) and sulphate (SO4), and
presence of magnesium (Mg) concentrations.
To replenish water resources and rejuvenation of streams to some extent,
suitable water conservation measures like artificial recharge can be
adopted to minimize the ground water depletion and maximize the
replenishment of groundwater resources. It also provides an opportunity
to utilize the surplus monsoon runoff which is otherwise lost unutilized.
Rainwater harvesting, storm water management, ridges, ditch and furrow
system are some of the popular artificial recharge methods suitable to the
study area.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-25
Pridhvi Envirotech (P) Ltd.
With the rainwater harvesting system the ground water will be recharge
resulting in rise of ground water levels and improvement in the quality of
ground water.
Impact on water resources
In collaboration with the state departments, Central Ground Water Board
(CGWB) carried out ground water resource estimation and categorization
studies for the Farooq Nagar Mandal of Rangareddy District for the year
1998-2009. As per the estimates, the assessment unit area with Stage of
Ground Water Development as 10% falls under Safe Category. The
mandal area with 84% of Development also remains in the Safe Category
as there is no significant reported long term pre-monsoon and post –
monsoon ground water level declining trends with resource development
remaining in the range of more than 70% and but less than 90%. The
ground water Resource estimations of the area is given in the Table 4.9.
Table-4.9: Ground Water Resource Estimations
1. Ground Water Resources Assessment area. MBNR_ D_ 44_
Balanagar
Farooknagar/Shadna
gar
2. Recharge from rainfall during monsoon (ha m) 3639 1694
3. Recharge from other sources during monsoon
(ha m)
117 257
4. Recharge from rainfall during non-monsoon
(ha m)
1411 479
5. Recharge from other sources during non-monsoon (ha m)
180 379
6. Total Ground water Recharge (ha m) 5134 2809
7. Natural discharge curing non-monsoon (ha m) 513 281
8. Net annual ground water availability (ha m) 4621 2528
9. Existing ground water draft for irrigation (ha m)
428 2012
10. Existing ground water draft for domestic and
Industrial use (ha m)
54 105
11. Existing gross ground water draft for all uses (ha m)
482 2117
12. Allocation for domestic and Industrial 151 327
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-26
Pridhvi Envirotech (P) Ltd.
requirement for next 25 years (ha m)
13. Net ground water availability for future
irrigation (ha m)
4042 189
14. Stage of ground water Development (%) 10 84
15. Is there significant decline of pre-monsoon
water table
NO
NO
16. Is there significant decline of post-monsoon water table
NO NO
17. Categorisation of Assessment Unit SAFE SAFE
4.6 Prediction of Impacts on Soil
The overall impact on soil is negligible as the used water is recycled in the
plant and the domestic sewage generated will be treated in STP and
treated water will be used for greenbelt. The dust collected from bag
filters, Mill waste generated from recycling water treatment shall be
stored and disposed properly to avoid any soil contamination.
Green belt development surrounding the plant site would reduce the soil
erosion and surrounding ecology and aesthetic appearance of the area.
Trees will absorb specific air pollutants, reduce noise pollution, reduce soil
temperature, help in holding moisture in the soil, attract more birds and
overall will help in maintaining the homeostasis of the environment.
Further to existing green belt, an additional area of greenbelt is proposed
to be developed which will significantly improve the environmental
quality.
4.7 Impacts on Socio-Economic Environment
The socio-economic impacts of the proposed expansion project could be
assessed in terms of demand-supply aspects for goods and services in the
area, pressure on natural resources and infrastructure, growth of
industry, sustainability of livelihoods and employment.
Some indirect impacts can also be understood in terms of public health
and safety, preserving local culture and aesthetics of the area
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-27
Pridhvi Envirotech (P) Ltd.
Based on a close understanding and assessment, the socio-economic
impacts of DIPL’s proposed secondary steel making project are predicted as follows:
Table 4.10 Socio Economic Impacts of the project
Sl.
No. Impact Area
Predicted Impacts
Positive Negative
1 Impact on
land resources
No shifts in land use pattern would occur.
Nil
2 Human
Settlement
No land acquisition and displacement of people or
habitations would be involved. Land required
for project expansion already exists within
factory premises of the project proponents in
Elikatta
Nil
3 Livelihoods No loss of existing
livelihoods in the area is
expected to occur. Additional livelihood
opportunities are expected directly as also
as spinoffs.
Increased influx
of people in
project construction and
operation phases.
4 Employment
Generation
Creation of employment
opportunities for about 40 local skilled and semi-
skilled workers during
project construction phase.
Creation of sustainable employment for
additional 120 skilled& semi skilled workers
during project operation phase, in production as
also auxiliary activities. Multiplier effect due to
induced growth during construction and
operational phases in
Nil
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-28
Pridhvi Envirotech (P) Ltd.
downstream and upstream project
activities will generate more employment
opportunities to local women and youth.
5 Spinoffs Emergence of local entrepreneurs in
complementary activities such as small business,
transportation, education,
housekeeping, repairs,
Houses rents, Ration
shops and maintenance etc.
Possible emergence of
increased and unfair
competition in
local markets
adversely
impacting businesses and
livelihoods of some.
6 Incomes and
Revenues
Improved tax revenues to Elikatta Village and State
exchequer
Nil
7 Demographics The population levels of the neighboring villages
are not likely to change in any significant manner.
The lifestyles are expected to improve in
tune with the rise in incomes and
improvement in infrastructure facilities.
The skill sets of the local
residents are expected to improve in keeping with
the emerging employment
opportunities.
Health of people residing in the
buffer impact zone is likely to
be impacted adversely if
pollution control systems does not
work efficiently
8 Impact on
Physical
Infrastructure
such as roads
and power
distribution
net work
Road and power network in the area is expected to
be strengthened further as a sequel to industrial
development around.
Increased vehicle traffic due to
movement of raw material and
finished products can increase
traffic on existing roads
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-29
Pridhvi Envirotech (P) Ltd.
9 Social
Infrastructure
Improvement to housing stock, educational
facilities and healthcare facilities in the
neighboring villages.
Increased pressure on
residential accommodation,
water supply and sanitation in the
neighbourhood.
10 Community
Aesthetics
Housing construction in
the area is expected to improve in the years to
go as a sequel to industrial development.
There are no heritage precincts and
archaeological monuments around the
project location that would be adversely
impacted.
Nil
4.8 Prediction of Impact biotic environment
This project is aimed at expansion of existing production capacity. Hence
no physical changes happens in core area. No removal of existing
buildings and tree cover in the expansion project.
The activities associated with the proposed activity will have very less
impacts on terrestrial flora and fauna of the core area and buffer zone
area. There are no migratory corridors, nesting and Breeding sites within
the core zone. No need to take any mitigation measures specific to these
parameters. From the list of floral and faunal species it is very clear that
there are no Rare or Endangered or Endemic or Threatened (REET)
species present in core or buffer zones.
The overall impact of the project on ecological aspects is:
Magnitude: less
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-30
Pridhvi Envirotech (P) Ltd.
Extent: The extent of the impact is on-site as the impacts will be limited
to the boundaries of the Site.
Duration: The duration would be short-term as the natural vegetation of
the site would not be affected during the construction phase.
Intensity or magnitude: The intensity is very less during construction
and operation phases.
Reversible or Irreversible: No irreversible impacts
4.8.1 Ecological factors and their impacts due to proposed
activity:
Species diversity No
reduction
Habitat loss or fragmentation Nil
Affect on any additional risk or threat to the rare or
endangered or endemic or threatened (REET) species
Nil
Any impairment of ecological functions such as (i) disruption of
food chains, (ii) decline in species population and or (iii) alterations in predator-prey relationships
Nil
Is it possible to attain the global objectives of “no net loss” of biodiversity
Yes
Is it possible to improve the biological diversity through the
proposed mitigation activity
Yes
From the above table, it is very clear that proposed activity will not
impact the biodiversity of the region. Hence it is recommended to
construct the proposed project in the existing plant premises by following
certain conservation measures. However, some positive impacts of the
proposed projects are habitat and species conservation may give some
benefit to the surrounding region.
4.8.2 Impacts Identified:
Major impacts on ecology due to the operation of proposed project are
likely to occur because of materials storage & handling, manufacturing
process, utility emission and Breakdown & maintenance of control
equipment. Industry will have process emissions (SPM, NOx SO2 and
CO2) from the induction furnace, Reheating Furnace and DG set. Fugitive
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-31
Pridhvi Envirotech (P) Ltd.
dust is generated from the Roads during transportation of raw materials
and finished products within the plant. The major impacts of these
activities will occur only due to contamination of other environmental
attributes mainly air, water & soil. Beside of major impacts due to these
activities, minor impact will occur on ecology due to the transportation
activities, water & wastewater Management Activities and Hazardous &
Solid Waste Management Activities. Minor beneficial impacts are likely to
occur on ecological status of the area due to greenbelt development
activities. The details of identified impacts are described in details as
below.
4.8.2.1 Site specific Impacts
There are few site specific impacts due to existing and proposed project
activities. Long term cumulative impacts on production and yield of crops
in the immediate surrounding area should be monitored.
4.8.2.2 The direct impacts
There no direct impacts due to proposed project construction. No
vegetation needs to be removed. No significant long-term residual
impacts on fauna due to project.
4.8.2.3 Indirect Impacts
Indirect impacts on vegetation and fauna includes resource utilization
during construction of project.
4.8.3 Mitigation Measures
Even though the emissions are within the standard levels prescribed
by CPCB, sensitive floral and aquatic ecosystems will get long term
impacts. Hence all necessary control & measures for prevention of
release of dust emissions from project shall be implemented as
suggested in the Environmental Management plan.
Environmental education activities will also mitigate the negative
impacts of the site specific industrial and anthropogenic activities.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-32
Pridhvi Envirotech (P) Ltd.
Precautionary measures & action plan for prevention of spreading of
dust during transportation of raw materials shall be ensured.
Safety measures & action plan for control & prevention of hazards
associated operation of proposed project shall be provided to ensure
safety & protection of ecological factors during major accident.
Creation & Maintenance of dense greenbelt in and around the
company premises.
No disposal of effluent and solid & hazardous waste on land and in
water bodies.
4.9 Positive impacts on Ecological aspects
Aesthetics
Due the present plantation activities within the boundary of the site, the
aesthetic value of the region will be enhanced. The beauty of the region
will be enhanced through various flowering plants which intern attracts
bird species of the region. More ornamental, palm trees, uncommon
verities of the climbers and shrubs which are suitable to the region can be
taken into criteria. Involving local villagers in plantation activities and
educating the people on importance of biodiversity leads to protection and
conservation of flora and fauna in long term.
Carbon sink
Within the study area i.e in the buffer zone, the avenue plantation
activities, rehabilitating degraded lands contribute to mitigating climate
change. These actions increase the rate and quantity of carbon
sequestration in biomass. Introduction of trees on non-forest or degraded
forest lands, Village plantations, restoration of natural forest, watershed
protection, orchards and perennial cultures, agro-forestry activities
enhance the ecological and economic values.
Based on the above analysis, it can be concluded that even though there
are no ecologically sensitive habitats in core and buffer zones, the impact
will not be there on any habitat in any other manner. However, to
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-33
Pridhvi Envirotech (P) Ltd.
promote the environmental sustainability of the total area, the above
measures can be taken.
4.9.1 Anticipated general impacts due to Steel industry on Flora
and fauna:
Steel production has a number of impacts on the environment, including
air emissions (PM 10, PM2.5, Sox & NOx), wastewater contaminants,
hazardous wastes and solid wastes. Virtually all of the greenhouse gas
emissions associated with steel production is from the carbon dioxide
emissions related to energy consumption. Gaseous emissions and metal
dust are the most prominent sources of waste from furnaces.
Dust may be generated during the operation phase of the unit. Fugitive
dust is anticipated from slag crusher and material transportation. During
operation of plant, dust particles may be emitted from the
processes/activities. The generation of dust can have a negative effect on
vegetation when emitted to the surrounding environment. Gaseous
emissions may reduce air quality with impacts on human health.
4.9.2 Mitigation Measures for Habitat specific alternations
Maintenance of the native plant species for conservation.
Not to discharge and solid or liquid wastes directly or indirectly into
the surrounding habitat.
Regular consultation with local forest officials and NGOs to improve
the degraded habitat and participate in conservation practices also
with them.
Conducting more awareness programmes near the surrounding
villagers and local staff members.
The core project area, the adjoining areas shares similar habitat, and thus
clearing of ground will not eliminate habitat of any species permanently.
Overall, there are no threats for increasing the rarity of any species under
this criterion.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-34
Pridhvi Envirotech (P) Ltd.
Considering these aspects, a comprehensive green belt development plan
is proposed which shall improve the existing status of ecosystems and
associated biodiversity in the nearby area. These habitat improvement
efforts shall not only cover the project core area but adjoining areas as
well.
4.9.3 Impacts on traffic
The plant is located adjacent to Shadnagar – Parigi Road. This is currently
2 lane road wit a traffic handling capacity of 2900 PCU/ hour. The current
traffic volumes are very low. Due to expansion activity, there will be 40
truck trips of raw materials per day. Also due to increase in number of
work force, additional traffic volume of 50 PCU/Day ie. 3 PCU/ hour. This
is very insignificant compared to capacity of existing road.
4.10 Prediction of Impact on Vehicular Traffic
The plant is located adjacent the Shadnagar to Parigi State road. As this
is 2 lane road, the Traffic volume is 2600 PCU/Hour. There will be
marginal increase in traffic density to the extent of 20 truck trips in a day
and another 50 PCU’s per day of passenger vehicles. Thus total traffic
load will be 3 PCU per Hour which can be taken by existing road network
safely. The vehicles are provided with parking place and Steel yard and
Traffic signs will be placed in the battery limits of the plant.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-35
Pridhvi Envirotech (P) Ltd.
4.11 Overall Environmental Impacts and mitigation measures of the
project
Below Table summarizes the overall impact of the expansion project on
the environment i.e., physical, biotic and social environments in the
surrounding area.
Table: 4 Environmental Impacts and their significance levels
Environmental Issues/Impacts
Significance level On a scale of 1-5
( 1- low 2- Marginal 3-
Medicum 4- High &
5- very high
Management Action
CONSTRUCTION PHASE
Dust generation
due to construction
activities
Significance level
is 2 with marginal significance
Plantation will be improved
Horticulturists to identify the species.
Supervising consultants/ contractor to ensure the
water sprinkling
Exhaust gases
from construction
machinery and
transportation
S i gn i f i c an ce
Leve l i s 2 w i t h marg i na l
s i gn i f i c an ce
Contractors to be educated
and superv i s ing consu l tan t to ensure the
same.
Sedimentation
of storm water
during rainy season
Significance level
of 2
Storm water drains existing
Proper traps will be planned to avoid sediments reaching
storm water drains
Alteration of
Drainage
Significance level
is 1 As there are no
natural drains
passing through the plant and there
is no alteration of drainage pattern.
Rain water harvesting will
be augmented to re-charge ground water
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-36
Pridhvi Envirotech (P) Ltd.
Water Consumption
Significance level is 2
Rain water harvesting measures are incorporated
in the EMP
Pollution from construction
workers
Significance level is 2
No labor camps required at the site as local labor will be
employed
Toilets with septic tanks will be provided for work force
during construction
Loss of productive soil
Significance level is 2
Top soil would be stock piled separately to re-use
for plantation purposes
Soil Erosion
Significance level
is 2 as large scale construction
activity is not involved in the
expansion activity
Cut and fill operation to be
done during non-monsoon season.
Silt traps to ensure silt does not enter storm water
drains. Side slopes of storm water
drains will be kept flatter wherever possible, and in
case of steeper slopes it is mulched.
Contamination of Soil
Significance level is 2
Vehicle washing and machinery washing to be
avoided in site. Parking of vehicles and
maintenance of vehicles to be avoided in site.
Disposal of solid wastes by construction workers to be
made in garbage bins only.
Natural Resource
consumption
Significance level is 3
Use the sane from government-authorized
suppliers.
Use robotic sand to maximum extent possible
Use bricks made from crushed slag from the unit
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-37
Pridhvi Envirotech (P) Ltd.
Noise Pollution from
heavy machinery, and
transportation.
Significance level is 3
Noise causing activities to be conducted during
daytime. Maintenance of equipment
and vehicles to mitigate noise generation.
PPE shall be provided to workers
Construction
debris
Significance level is
2
Construction debris to be
used for aggregate and or sub grade purpose in the
case of RCC recyclable metals to be
collected and sold to recyclers
Avoidance of excess inventory of materials.
OPERATION STAGE
Dust
Generation from material
transport
Significance level
is 3
Plantation.
Maintenance of roads by way of sweeping.
Water sprinklers on roads
Emissions from
Induction furnaces
Significance level
is 5 as it can impact outside
environment if pollution control
measures are not taken
Install high efficiency bag
filter Provision of primary and
secondary ducts for induction furnace to extract
emissions Provide higher capacity of
ID fans for suction of
emissions from furnace Use of good grade scrap
Maintenance of bag filters
regularly
Availability of spare bags Stack heights as per the
CPCB Norms Periodical monitoring of
emissions Provision of acoustic
enclosures for DG sets
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-38
Pridhvi Envirotech (P) Ltd.
Emissions from Re-eating
furnace
• Significance level is 3
As this is stand by unit only
• Operate bag filter system effectively
• Used as only stand by in case of any failure of
Continuous casting machines
• Periodical monitoring of emissions
Emissions Coal
pulverizer
Significance level
is 4 as dust can impact work
force
• Enclose the conveyor
systems thoroughly • Provide bag filter with
suction points to extract dust generated at transfer
points • Provide shed for storage of
coal • Provide water sprinklers in
coal storage area
Emissions from
DG sets
• Significance level
is 3 • DG sets are only
stand by arrangements
• Enclose the DG sets with
acoustic enclosures • Provide enough stack height
as per the CPCB norms • Maintain DG sets as per the
manufacturers recommendation
Waste Water
Management
Significance level
is 4
The cooling water from
rolling mill shall be pre-treated to remove oil &
grease and suspended solids and recycled back
All cooling water shall be completely recycle back to
reduce fresh water consumption
Domestic waste water shall
be treated in STP and re-used for gardening
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-39
Pridhvi Envirotech (P) Ltd.
Storm water Management
Significance level is 3
Storm water drains will be maintained periodically
before monsoon. Accidental discharges
spillages shall not be allowed to join storm water drains.
Roads, pavements and other surfaces are swept regularly.
Storm water quality shall be monitored regularly and
records shall be maintained
Water Conservation
Measures
Significance level is 4 as natural
resource is used
for plant purposes
Water conservation measures shall be adopted to reduce
resource consumption
Water consumption for various uses shall be
measured and records shall be maintained
Rain water conservation shall be done by re-charge pits.
Recharge wells for roof water and Rain water
harvesting pits for other open areas
Solid &
Hazardous Wastes
Significance level
is 4
Slag waste shall be used for
land filling at low lying areas in the plant premises
Proper storage of slag and mill waste shall be done
Waste oil generated from
Rolling mill and DG sets shall be filtered and re-used for
lubrication purpose
Noise Levels Significance level
is 3 as they are
confined to plant
premises
Noise levels due to traffic will
increase in the area and the
mitigation measures like
maintaining greenery Noise levels from DG sets to
be mitigated by the provision of acoustic enclosures.
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-40
Pridhvi Envirotech (P) Ltd.
Traffic Control Significance level is 3
The plant management must ensure proper parking
of vehicles carrying raw materials in designated
areas only Cleaning operations of
trucks shall not be allowed in plant premises or nearby
water bodies Contractors shall be educate
on this by M/s. Devashree Ispat (P) Limited.
Impact on Flora
and Fauna
Significance level
3 As a part of
expansion activity, there
will be increase in green belt and
hence will be positive aspect
• The Project authorities M/s.
Devashree Ispat (P) Limited Unit-I management to
ensure to maintain greenery in the
Additional area
Energy Conservation
Significance level is 3
The energy conservation measures for operation of
various equipments and motors shall be ensured
Energy efficient lighting shall
be ensured Use of solar street lighting is
suggested
Fire Safety Significance level
is 5
The plant management must
provide necessary emergency equipments
outlined in chapter 7. Regular mock drills shall be
done by team
M/s. Devashree Ispat (P) Limited Unit-1 Draft EIA Report
4-41
Pridhvi Envirotech (P) Ltd.
Worker Safety Significance level is 5
Personal protective equipment shall be provided
to all employees working in furnace and rolling mill areas
Regular health check up shall be done as per the norms
and records shall be maintained
Display of Safety warnings in rolling mill and induction
furnace area Periodic breaks shall be given
to people working in hot areas of furnace and rolling
mill
Periodic audit of electrical installations shall be carried
out Emergency vehicle shall be
available at site 24x7
Chapter-5
ANALYSIS OF ALTERNATIVE
SITES & TECHNOLOGIES
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
5-1
Pridhvi Envirotech (P) Ltd.
Chapter-5
Analysis of Alternative Sites & Technologies
5.1 PROPOSED PROJECT
M/s.Devashree Ispat (P) Ltd Unit-I situated on Shadnagar – Pargi
Road, at Sy.Nos: 458, 459 and 460, Ellikatta (Vil), Farooq Nagar
(M), Rangareddy District (Formerly Mahaboobnagar District),
Telangana State is manufacturing Thermo Mechanically Treated
(TMT) Bars in their plant spread over 10.62 Ac.
The unit obtained CFE from state Pollution Control Board in the
year 2004 to manufacture MS Ingots and in the year 2005 to
manufacture TMT Bars by Induction Furnace of capacity 100 TPD
of and Rolling Mill of capacity 300 TPD. The unit obtained CFO
from the Board on 12.4.2006 for manufacture of MS Ingots and
obtained CFO on 17-01-2007 for manufacture of TMT Bars and
started operations.
Now the project proposes to expand the production capacity by upgrading
existing 100 TPD Induction Furnace to 200 TPD induction furnace by
changing circuit and coil and that of the Rolling Mill from 300 TPD to 800
TPD by changing existing stands and by adding new stands for increasing
the production capacity of MS Billets from current level of 30,000 TPA to
70,000 TPA & TMT Bars from 72,000 TPA to 2,80,000 TPA.
5.2 ALTERNATIVE SITES:
The unit was established in 10.62 acres of land at Sy.Nos: 458,
459 and 460, Ellikatta (Vil), Farooq Nagar (M), Rangareddy
District (Formerly Mahaboobnagar District), Telangana State. The
unit is operating current units since 2004. It is proposed to
enhance the production capacities of existing Induction Furnace
and Rolling Mill. As this is expansion activity of existing plant
and enough infrastructure and land resources are available at the
current plant location, alternative sites evaluation does not
arise.
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
5-2
Pridhvi Envirotech (P) Ltd.
5.3 ALTERNATIVE TECHNOLOGIES
Steel Bars and Ingots/Billets are been manufactured by adopting
three technologies.i.e:
Blast Furnace
Electrical Arc Furnace
Induction Furnace
The Blast Furnace technology is highly capital intensive and
small & medium scale units cannot make such high investment.
The Electrical Arc Furnace is also high capital intensive but low
energy requirement. However process complication is higher in
this.
The Induction Furnace is well established technology for small
and medium scale units.
The existing unit is based on Induction Furnace and Rolling Mill;
it is proposed to enhance the capacity of furnace to enhance the
production capacity.
As efficient outcome is been achieved by the present technology, no
alternatives technologies are evaluated and proposed.
Chapter-6
POST ENVIRONMENTAL
MONITORING
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-1
Pridhvi Envirotech (P) Ltd.
Chapter-6
Post Environmental Monitoring
6.1 Introduction
The environmental monitoring program provides such
information on which management decision can be taken
during construction and operation phases. It provides basis for
evaluating the efficiency of mitigation and pollution control
measures and suggest further actions that need to be taken to
achieve the desired effect.
The monitoring includes:
(i) Visual observations.
(ii) Selection of environmental parameters at specific
locations.
(iii) Sampling and regular testing of these parameters.
6.2 Objectives
The objectives of the environmental monitoring programmers
are:
Evaluation of the efficiency of mitigation and pollution
control measures.
Updating of the action plan to mitigate any adverse
impacts.
Adoption of additional mitigation measures if the present
measures are not sufficient.
Generating the data, which may be incorporated in
environmental management plan in future projects.
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-2
Pridhvi Envirotech (P) Ltd.
6.3 Methodology
Monitoring methodology covers the following key aspects:
Components to be monitored
Parameters for monitoring of the above components
Monitoring frequency
Monitoring standards
Responsibilities for monitoring & reporting
Monitoring costs
Environmental monitoring of the parameters involved and the
threshold limits specified are discussed below.
6.4 Ambient air Quality (AAQ) Monitoring
Ambient air quality parameters recommended are Particulate
Matter (Size less than or equal to 2.5µm) or PM10 µg/m3,
Particulate Matter (Size greater 2.5µm & less than or equal to
10 µm), Oxides of Nitrogen (Nox) and Sulphur Dioxide (SO2).
These are to be monitored at designated locations starting
from the commencement of project activity. Data should be
generated at all identified locations in accordance to the
National Ambient Air Quality Standards (Table 6.1) location,
duration and the pollution parameters to be monitored and the
responsible institutional arrangements are detailed out in the
Environmental Monitoring Plan.
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-3
Pridhvi Envirotech (P) Ltd.
Table 6.1 National Ambient Air Quality Standards
SNo Pollutant Time
Weighted
Average
Concentration in Ambient Air
Industrial, Residential
Rural and Other Area
Ecological Sensitive
Area
(Notified by Central
Govt.)
Methods of
Measurement
(1) (2) (3) (4) (5) (6)
1 Sulphur Dioxide (SO2)
µg/m3
Annual* 24
Hours**
50
80
20
80
- Improved west and Gaeke
- Ultraviolet fluorescence
2 Nitrogen Dioxide
(NO2) µg/m3
Annual*
24 Hours**
40
80
30
80
- Modified Jacob &Hochheiser(
Nn-Arsenite) - Chemilumines
cence
3 Particulate Matter
Annual*
24 Hours**
60
100
60
100
- Gravimetic - TOEM
- Beta Attenuation
4 Particulate Matter
(Size less than 2.5 µm)or
PM2.5 µg/m3
Annual*
24 Hours**
40
60
40
60
- Gravimetic - TOEM
- Beta Attenuation
5 Ozone (O3)
µg/m3
8 Hours**
1 Hour**
100
180
100
180
- UV Photometric
- Chemilminescence
- Chemical
Method
6 Lead (Pb)
µg/m3
Annual*
24
Hours**
0.5
1.0
0.5
1.0
- AAS / ICP
method after sampling on
EPM 2000 or eequivalent filter paper
- ED-XRF using Teflon filter
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-4
Pridhvi Envirotech (P) Ltd.
7 Carbon Monoxide
(CO) mg/m3
8 Hours**
1 Hour**
02
04
02
04
- Non Dispersive
Infra Red (NDIR)
- Spectroscopy
8 Ammonia (NH3)
µg/m3
Annual*
24 Hours**
100
400
100
400
- Chemilminescence
Indophenol
blue method
9 Benzene
C6H6
Annual*
05 05 - Gas
Chromotography based
continuous analyzer
- Absorption and
Desorption followed by GC analysis
10 Benzo(o) Pyrene(Ba
P)-Particulate
Phase only, ng/ m3
Annual*
01 01 - Solvent extraction
followed by HPLC/GC
analysis
11 Arsenic (As), ng/
m3
Annual* 06 06 - AAS/ICP method after
sampling on EPM 2000 or
equivalent filter paper
12 Nickel (Ni), ng/ m3
Annual* 20 20 - AAS/ICP method after sampling on
EPM 2000 or equivalent
filter paper
Source Anon 1996-97, National Ambient Air Quality Monitoring Series
NAQMS/a/1997-97, Central Pollution Control Board, Delhi.
*Average Arithmetic mean of minimum 104 measurements in a
year taken for a week 24 hourly at uniform interval.
** 24 hourly / 8hourly values should meet 98 percent of the
time in a year.
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-5
Pridhvi Envirotech (P) Ltd.
6.5 Water Quality Monitoring
The Physical and Chemical parameters recommended for
analysis for water quality relevant are pH, Total Solids, Total
Dissolved Solids, Total Suspended Solids, Oil and Grease, COD,
chloride, lead, zinc and cadmium. The location, duration, and
the pollution parameters to be monitored and the responsible
institutional arrangements are detailed in the environmental
monitoring Plan. The monitoring of the water quality is to be
carried out at all identified locations in accordance to the
Indian Standard Drinking Water Specification – IS 10500:1991
(State inTable 6.2)
Table 6.2
Indian Standard Drinking Water Specifications
IS: 10500:2012
Sl.
No
Substance or
Characteristi
cs
Require
ment
(Desira
ble
Limit)
Undesira
ble Effect
Outside
the
Desirable
Limit
Permiss
ible
Limit in
the
Absenc
e of
Alterna
te
Methods
of Test
(Ref. To
IS)
Remarks
ESSENTIAL CHARACTERISTICS
1 Colour, Hazen
units, Max
5 Above 5,
consumer
acceptanc
e
decreases
25 3025
(Part 4)
1983
Extended to
25 only i f
toxic
substance are
not suspected,
in absence of
alternate
sources
2 Odour Unobjec
tionable
- - 3025
(Parts 5)
1984
a)Test cold
and when
heated
b) Test at
several
di lutions
3 Taste Agreeab
le
- - 3025
(Parts
7&8)
1984
Test to be
conducted
only after
safety has
been
establ ished
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-6
Pridhvi Envirotech (P) Ltd.
4 Turbidity NTU,
Max
5 Above 5,
Consumer
acceptanc
e
decreases
10 3025
(Parts
10) 1984
-
5 pH Value 6.5 to
8.5
Beyond
this range,
the water
wi l l affect
the
mucous
membrane
and / or
water
supply
system
No
relaxati
on
3025
(Parts
11) 1984
-
6 Total hardness
(as CaCO3)
mg/1, Max
300 Encrustati
on in
water
supply
structure
and
adverse
effects on
domestic
use
600 3025
(Parts
21) 1983
-
7 Iron (as Fe)
mg/1, Max
0.3 Beyond
this l imit
taste/appe
rance are
affected,
has
adverse
effect on
domestic
uses and
water
supply6
structures,
and
promotes
iron
bacteria
1 32 of
3025:
1964
-
8 Chlorides (as
CI) mg/1, Max
250 Beyond
this l imit,
taste,
corrosion
and
palatabi l i t
y are
affected
1000 3025
(Part 32)
1988
-
9 Residual free
chlorine,
mg/1, Min
0.2 - - 3025
(Part 26)
1986
To be
appl icable
only when
water is
chlorinated.
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-7
Pridhvi Envirotech (P) Ltd.
Tested at
consumer end.
When
protection
against viral
infection is
required, i t
should be Min
0.5 mg/1
DESIRABLE CHARACTERISTICS
1 Dissolved
sol ids mg/1,
Max
500 Beyond
this
palatabi l i t
y
decreases
and may
cause
gastro
intestinal
irri tation
2000 3025
(Part 16)
1984
-
2 Calcium (as
Ca) mg/1, Max
75 Encrustati
on in
water
supply
structure
and
adverse
effects on
domestic
use
200 3025
(Part 40)
1991
-
3 Magnesium (as
Mg), mg/1,
Max
30 Encrustati
on to
water
supply
structure
and
adverse
effects on
domestic
use
100 16,33,34
of IS
3025:196
4
-
4 Copper (as
Cu), mg/1,
Max
0.05 Astringent
taste,
discolorati
on and
corrosion
of pipes,
fi tt ing and
utensi ls
wi l l be
caused
beyond
this
1.5 36 of
3025:196
4
-
5 Manganese (as
Mn), mg/1,
Max
0.1 Beyond
this l imit
taste/appe
arance are
0.3 35 of
3025:196
4
-
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-8
Pridhvi Envirotech (P) Ltd.
affected,
has
adverse
effects on
domestic
uses and
water
supply
structures
6 Sulphate (as
200 SO4),
mg/1, Max
200 Beyond
this
causes
gastro
intestinal
irri tation
when
magnesiu
m or
sodium
are
present
400 3025
(Part 24)
1996
May be
extended up
to 400
provided
(asMg) does
not exceed 30
7 Nitrate (as
NO2 ), mg/1,
Max
45 Beyond
this, may
cause
methaemo
globinemia
100 3025
(Part 34)
1998
-
8 F;iprode (as
F), mg/1, Max
1 Fluoride
may be
kept as
low as
possible.
High
fluoride
may cause
fluorosis
1.5 3025
(Part 23)
1964
-
9 Phenol ic
compounds
(As C6H5OH)
mg/1, Max
0.001 Beyond
this, i t
may cause
objectiona
ble taste
and odour
0.002 3025
(Part 54)
1964
-
10 Mercury (as
Hg), mg/1,
Max
0.001 Beyond
this, the
water
become
toxic
No
relaxati
on
(See
Note)
Mercury
ion
analyser
To be tested
when pol lution
is suspected
11 Cadmium (as
Cd), mg/1,
Max
0.01 Beyond
this, the
water
become
toxic
No
relaxati
on
(See
Note)
To be tested
when pol lution
is suspected
12 Selenium (as
Se), mg/1,
Max
0.01 Beyond
this, the
water
become
toxic
No
relaxati
on
3025
(Part 28)
1964
To be tested
when pol lution
is suspected
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-9
Pridhvi Envirotech (P) Ltd.
13 Arsenic (as
As), mg/1,
Max
0.05 Beyond
this, the
water
become
toxic
No
relaxati
on
3025
(Part 37)
1988
To be tested
when pol lution
is suspected
14 Cyanide (as
CN), mg/1,
Max
0.05 Beyond
this l imit,
the water
become
toxic
No
relaxati
on
3025
(Part 27)
1986
To be tested
when pol lution
is suspected
15 Lead (as Pb),
mg/1, Max
0.05 Beyond
this l imit,
the water
become
toxic
No
relaxati
on
(See
Note)
To be tested
when pol lution
is suspected
16 Zinc (as Zn),
mg/1, Max
5 Beyond
this l imit,
i t can
cause
astringent
taste and
an
opalescenc
e in water
15 39 of
3025:196
4
To be tested
when pol lution
is suspected
17 Anionic
detergents
(as MBAS),
mg/1, Max
0.2 Beyond
this l imit,
i t can
cause l ight
froth in
water
1 Methylen
e-blue
extractio
n method
To be tested
when pol lution
is suspected
18 Chromium (as
Cr6+), mg/1,
Max
0.05 May be
carcinogen
ic above
this l imit
No
relaxati
on
38 of
3025;
1964
To be tested
when pol lution
is suspected
19 Poly nuclear
aromatic
hydrocarbons
(as PAH)
mg/1, max
- May be
carcinogen
ic above
this l imit
- - -
20 Mineral oi l
mg/1, max
0.01 Beyond
this l imit
un-
desirable
taste and
odour
after
chlorinatio
n take
place
0.03 Gas
Chromato
graphic
method
-
21 Pesticides
mg/1, max
Absent Toxic 0.01 - -
22 Radioactive materials: 58 of
3025:196
4
-
23 Alpha
emitters
- - 0.1 - -
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-10
Pridhvi Envirotech (P) Ltd.
Bq/1, Max
24 Beta emitters
pci/1,
Naxmg/1, max
- - 1 - -
25 Aluminium (as
A1), mg/1,
Max
200 Beyond
this l imit
taste
become
unpleasant
600 13 of
3025:196
4
-
26 Aluminium (as
A1), mg/1,
Max
0.03 Cumulativ
e effect is
reported
to cause
dementia
0.2 31 of
3025:196
4
-
27 Boron, mg/1,
Max
1 - 5 29 of
3025:196
4
-
Source: Indian Standard Drinking Water specification-
I10500:1991
6.6 Noise Level Monitoring
The measurement for Monitoring noise levels would be carried
out at all designated locations in accordance to the Ambient
Noise Standards formulated by Central Pollution Control Board
(CPCB?) in 1989 (refer Table 6.3) Sound pressure levels would
be monitored on twenty-four hour basis. Noise should be
recorded at an “A” weighted frequency using a “slow time
response mode” of the measuring instrument. The location,
duration and the noise pollution parameters to be monitored
and the responsible institutional arrangements are detailed in
the Environmental Monitoring Plan.
Table 6.3 Noise Standards
Type Noise level for
Day Time Leq dB(A)
Noise level for
Night Time Leq dB(A)
Industrial area 75 70
Commercial area 65 55
Residential area 55 45
Silence zone 50 40
Day time - 6.00 am – 10.00 pm (15 hours) Night time – 10.00pm – 6.00 am (9 hours)
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-11
Pridhvi Envirotech (P) Ltd.
6.7 Environmental Monitoring plan
The monitoring plan along with the environmental parameters and the time frame is presented in the Table 6.4
Table 6.4
Environmental Monitoring Plan
S.
No Particulars
Monitoring
Frequency Standards
Duration
Of
Sampling
Important
monitoring
parameters
Institutional
responsibility
in M/s
DevashreeIspat
(P) Limited
In house
/Out source
Ambient Air Quality Monitoring
1 3 locations Once in a Quarter Air
(Prevention
and control
of Pollution)
Rules, CPCB,
1994
24hrs PM10, PM2.5, SO2, NOX
at 3 locations
and all specified
parameters of
National Ambient air
quality standards
once in a year at one
location
General Manager Through a
third party
laboratory
accredited to
MOEF/NABL
2 1 location in
nearby
village
(Male
ellikatta)
Once in a quarter 24 Hours PM10, PM2.5, SO2, NOX General Manager Through a
third party
laboratory
accredited to
MOEF/NABL
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-12
Pridhvi Envirotech (P) Ltd.
3 Work Place
Monitoring
Once in 3
months
Factory Act & Rules 8 hr RSPM & CO General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
Stack Emissions Monitoring
4 Stacks
Connected to
Induction
furnaces (1 Nos)
Once in a 3
months
Air (Prevention and
control of Pollution)
Rules, CPCB, 1994
Grab
samples
Particulate matter ,
SO2, &Nox as per the
recommended methods
of CPCB
General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
5 Stacks attached
DG Sets ( 3 Nos)
Once in 6
months
Air (Prevention and
control of Pollution)
Rules, CPCB, 1994
Grab
sample
PM, SO2 & NOX General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
6 Stacks attached to Re-heating
furnace ( One No)
As When Operated (
Once in a year)
Air (Prevention and
control of Pollution)
Rules, CPCB, 1994
Grab
sample
PM & NOX General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-13
Pridhvi Envirotech (P) Ltd.
Water Quality Monitoring
7 Ground water
3 locations
and surface
water 1
location
Pre and
post
monsoon
Surface water
standards as
per IS
2296:1982
Ground water
as per the IS
10500
standards
Grab As per state PCB specified
norms
General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
8 Treated Mill
water and
treated STP
water
Once in a
3 months
As per the PCB
specified
standards
Grab pH, TDS,SS, BOD, COD and
Oil & Grease chlorides/As
per state PCB specified
norms
General
Manager
In house
laboratory
Noise Quality Monitoring
9 Noise Levels
at 3 Locations
with in plant
site and 2
locations
outside the
plant site
Once in a
3 months
Noise standards
notified by
MOEF
Equivalent
noise levels
Equivalent Noise levels in
dB(A)
General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-14
Pridhvi Envirotech (P) Ltd.
Noise level in work place (
Rolling Mill and furnace
areas)
Once in every
month
Noise standards notified by
MOEF
Equivalent noise levels
Equivalent Noise levels in
dB(A)
General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
Soil
10 Soil – 3
locations ( one
in plant
location where
Slag is stored
and other 2 in
nearby
agricultural
lands)
Once in a
year
Threshold for
each
contaminant set
by IRIS
database of
USEPA until
national
standards are
promulgated
At productive
agricultural
lands in the
project
impact area
to be
identified by
the proponent
pH, EC, Ca, Mg,Potasium,
SodiumChlorides,Nitrates,
SulphatesCation Exchange
capacity
General
Manager
Through a
third party
laboratory
accredited to
MOEF/NABL
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-15
Pridhvi Envirotech (P) Ltd.
6.8 Responsibility of Monitoring and Reporting System
The overall responsibility of monitoring the above parameters
shall be lie with the Top Management of M/s. Devashree Ispat (P)
Ltd unit I. The environment division shall be responsible for
day to day monitoring of effluent, raw water and treated water
quality. The Ambient air quality, Stack emissions, soil, noise
and water quality shall be monitored by either third party or by
the Environment Management Division of M/s. Devashree Ispat (P)
Ltd unit I
Records shall be maintained for the analysis of raw effluents
and treated effluents, ambient air quality data, stack emissions
monitoring results, and noise levels. These records are not only
required for the statutory submission of the Pollution Control
Board authorities but also to assess the efficiencies of the
pollution control equipment as the objective of the project
proponent is not only compliance with statutory regulations,
but also a serious commitment towards clean environment.
Reporting system provides the necessary feedback for project
management to ensure quality of the works and that the
management plan in implementation. The rationale for a
reporting system is based on accountability to ensure that the
measures proposed as part of the Environmental Management
Plan get implemented in the project.
6.9 Environmental Monitoring Budget
The environmental budget for the various environmental
management measures in the EMP is detailed in Table 6.5 There
are several other environmental issues that have been
addressed as part of good engineering practices, the costs for
which have been accounted for in the Engineering Costs.
Moreover, since environmental enhancements have not been
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
6-16
Pridhvi Envirotech (P) Ltd.
finalized at this stage, the table projects the typical costs unit
wise.
Table 6.5
Estimated Environmental Monitoring Budget
Component Item Frequency Unit Cost
(INR)
TotalCost/Year
(INR)
Air Stack monitoring ( 2 Furnace stacks)
Once in 3 months
2500 20,000
Stack Monitoring ( 3 DG Sets )
Once in 6 months
2500 15,000
AIR Ambient Air Quality at
locations specified in the monitoring plan In side
premises ( 3 Locations)
Once in a 3
months
4000 48,000
Ambient air quality at
locations in nearby
villages ( 1 location)
Quarterly 4000 16,000
Air Work place monitoring
( 4 locations)
Quarterly 2000 32,000
24,WATER
QUALITY
3 ground water samples
& one surface water
sample
Pre- Monsoon
& Post
Monsoon
3000 24,000
Wastewater (Treated
and Untreated effluent) ( In house)
Quarterly 2000 16,000
NOISE At Rolling Mill &
Induction furnace area ( 4 locations)
Once in a
month
500 24,000
At locations specified in
the monitoring plan ( 2 in house and 2 out side)
Quarterly 1000 16,000
SOIL At locations specified in the monitoring plan:1
near slag storage and two in adjacent Farmer
lands
Yearly 2000 6,000
Total 2,07,000
Chapter-7
OCCUPATIONAL HEALTH, RISK
ASSESSMENT
&
DISASTER MANAGEMENT
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-1
Pridhvi Envirotech (P) Ltd.
CHAPTER -7
OCCUPATIONAL HEALTH, RISK ASSESSMENT
& DISASTER MANAGEMENT
7.1 Risk Assessment
7.1.1 Hazards Relating to Foundries
Working with molten metal is always a safety hazard. Many accidents
occurred worldwide in steel melting industries. Primarily safety hazards
relating to Induction Furnace and Rolling Mill can be classified into 3
categories
Thermal hazards
Electrical hazards
Physical hazards
Use of proper personnel equipment, fire protection systems and continuous
training of people working in the shop floor are the only measures which
helps industries to avoid accidents.
7.1.2 Various possible Hazards & Emergencies from different
operations
M/S Devashree Ispat (P) Limited Unit I is currently having one Induction
Furnace, Rolling Mill and Coal Pulverizer. Apart from this material handling
operations are there in the raw material yard. Based on the type of
operations, the possible Hazards and Emergencies are identified and
mitigation measures are discussed below:
7.1.2.1 Induction Furnace
Induction Furnace produces heat using electricity. In that way Induction
Furnace is cleaner method of melting the charge. AC current flows through
coils made up of hollow copper tubes. The flowing current in induction coils
creates magnetic field and creates electrical current in the metal charge
thus by creating heat. This will help the metal to melt. The temperature in
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-2
Pridhvi Envirotech (P) Ltd.
the furnace reaches up to 1500oC to 1700oC. Refractory lining is provided
to the crucible.
Typical hazards relating to the Induction Furnace are
Feeding of wet or damp metal or empty gas cylinders scrap,
into the furnace as charge can cause explosion.
Lack of operator skill during sampling and addition of flux
materials can cause splashes and cause physical burn
injuries
Dropping of large pieces of metal into melting furnace from
overhead cranes causes splashes.
Coming into contact with electrical conductors, over-riding
safety interlock switches causes fatal electrical shocks.
Failure of cooling water circulation system can cause over
heating of magnetic coils and cause short circuits.
Metal charge is loaded into furnace using overhead crane by
magnets. During this process, possibility of charge coming
down abruptly which can cause physical injuries.
During the tilting of furnace for unloading of molten metal,
splashes may occur and can injure people.
Failure of refractory of furnace can cause serious spill of
molten metal in shop floor can cause serious injuries to
people.
7.1.2.2. Hot Billets Transfer from Unit III for Rolling Operations
Hot billets form the Continuous Casting Machine is sent back to Unit –I
through conveyor. Typical hazards identified relating to this activity is:
Serious burn injuries to people while transferring the
billets to the conveyor line.
Fall of hot billets from the conveyor line due to failure of conveyor
line can cause severe burn injuries to the people.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-3
Pridhvi Envirotech (P) Ltd.
Burn injuries may be caused due to physical contact of people with
hot billets while transferring to the Rolling Mill.
Physical hazards to the people working in the conveyor area from the
moving parts.
7.1.2.3. Hot Metal Transfer from Unit I to Unit III
Hot metal from Devashree Ispat (P) Ltd Unit-I will be transferred
to Devashree Ispat (P) Ltd Unit-III and fed to Continuous Casting
Machine by ladle transfer trolley. While handling and transferring
the hot metal from Unit - I can cause hazards related to physical
and burn injuries.
Typical hazards associated with these activities are
Serious burn injuries to people who are transferring the
hot metal from Induction Furnaces.
Spill of hot metal on ground which can cause severe burn injuries to
the people.
Burn injuries may be caused due to physical contact of people with
hot metal trolley.
During casting operation in Continuous Casting Machine, the flashes
may cause injuries to eyes. Eyes may also be affected by glare.
7.1.2.4 Rolling Mill
Rolling Mill constitutes of Re-heating Furnace and various rolling
passes apart from this the raw material being MS Billets is also
fed to rolling mill through conveyor. Here also the hot metal is
handled while rolling. Typical hazards associated with these
hazards are
Serious burn injuries to people who are loading hot billets
to roll stands.
In any rolling mill, there is a risk of trapping between the rolls
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-4
Pridhvi Envirotech (P) Ltd.
Severe injuries may be caused by shearing, cropping, trimming
and guillotine machines, unless the dangerous parts are securely
guarded.
Injuries may occur, especially in hot-rolling, if workers attempt to
cross roller conveyors at unauthorized points.
Accidents can occur while changing heavy rollers in the stands.
In hot-rolling, burns, eye injuries or other injuries may be caused by
flying mill scale and dust particles or by whipping of cable slings.
Eyes may also be affected by glare.
Cuts may occur when workers contact the edge of steel rods.
7.1.2.5 Consequential fires outside the premises
As can be seen from the above, most of the hazards relating to
Induction Furnace and continuous casting machines are related
to occupational hazards. The only hazard that can cause
problem surrounding public is consequential fires during fire
accidents. However there is no habitation nearby and
possibilities of consequential fires is not there .
7.2 Risk Mitigation Measures
Following Risk Mitigation Measures suggested to overcome the
risks identified
Periodical inspection of mechanical equipment, Hot metal
and Billet conveyors
Distance shall be maintained by operational staff while
charging scrap to furnace
Type of scrap charged shall be properly examined and any
pressure cylinders, chemical tins etc shall not be charged to
furnace
Tap holes should be checked regularly for damage and build-up of
Scale , to prevent molten metal splashes
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-5
Pridhvi Envirotech (P) Ltd.
A competent person should regularly inspect ladle buckets and their
supporting, locking and tipping mechanisms
Before each filling, the pouring of, or transport of slag ladles and their
related appliances should be visually inspected.
The hot metal conveyor crossing points shall be thoroughly enclosed
and heat shielded
Goggles, face shields, heat resistant aprons, gloves, safety
shoes, helmets shall be provided to the people working in
furnace and Continuous casting machine areas
Nose masks, gloves, shoes, helmets shall be provided to the
people working in the coal pulveriser area. All conveyors in
the coal crusher area shall be enclosed and suction points
shall be connected to bag filter to control fugitive emissions
Work force shall be continuously trained on operations,
hazards and safety measures
First aid boxes shall be maintained at all functional areas.
Eye washing fountain shall be installed in furnace and CCM
areas
People working in hot areas shall be provided rest for every
2 hours period to reduce fatigue due to heat and glare
Fluids like butter milk shall be supplied to work force during
summer period to reduce impact of heat on the body
Periodic mock drill shall be conducted
7.3 Emergency Equipment/facilities
At present M/s. Devashree Ispat Pvt Ltd Unit- I is having portable fire
extinguishers in Induction furnace area and rolling mill. Following
equipment are in place. Also few additional fire fighting equipment is
suggested as a part of this expansion plan and details are given below.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-6
Pridhvi Envirotech (P) Ltd.
Table 7.1 List of Existing fire Extinguishers
LIST OF FIRE EXTINGUISHERS IN UNIT - I (NEAR INDUCTION
FURNACE)
S.No. DESCRIPTION QTY LOCATION
1 6 Kg CO2 Trolley Mounted 1 No. Generator Room
2 10 Kg DCP Wall Mounted 2 Nos Under Furnace Room
3 10 Kg DCP Wall Mounted 1 No. Furnace Panel Room
4 Standby
9 Kg CO2 2 Nos Furnace Stores
4.5 Kg CO2
3
Nos. Furnace Stores
9 Kg DCP 3
Nos. Furnace Stores
6 Kg DCP 1 No. Furnace Stores
LIST OF FIRE EXTINGUISHERS IN UNIT - I (NEAR ROLLING MILL)
S.No. DESCRIPTION QTY LOCATION
1 9 Kg CO2 1 No. Panel Room
2 9 Kg DCP 1 No. O2 LPG & Diesel Godown
3 Standby
4.5 Kg CO2 2
Nos. Rolling Mill Stores
9 Kg DCP
2
Nos. Unfilled
Based on the existing emergency handling systems in the plant and keeping
in view of expansion activities, the following additional measures are
suggested
Table 7.2
List of Proposed Fire extinguishers and their location
S.No. Equipment/Facility Quantiy in No.s
Location
1 Wind Sock to provide the wind direction in emergencies
1 Rolling Mill Area
2 Fire Hydrant lines As
Required
From Water storage tank to
furnace and Rolling Mill area
3 Fire Hoses and Nozzles with
Housing
6 Furnace area-4 No.s
Rolling Mill area-2 No.s
4 10HP electrical Pump 1 Near Water Sump
5 Diesel operated Jockey Pump 1 Near Water Sump
6 Additional Fire Extinguishers (9Kg) in Furnace area DCP type
6 Induction Furnace area
7 CO2 Fire Extinguishers (4.5Kg) 4 Near Furnace Circuit room
8 CO2 Fire Extinguishers (4.5Kg) 4 at new DG sets area
9 DCP 9kg Fire Extinguishers 6 Rolling Mill
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-7
Pridhvi Envirotech (P) Ltd.
7.4 House Keeping
Good house keeping practices shall be adopted. Proper garbage
bins are provided at different areas of the plant. All roads are
swept and dirt is removed. Water sprinkling system is
established. Storm water drains shall be properly maintained and
dirt traps shall be established.
7.5 Occupational Safety and Health
The secondary steel making involves handling and processing of
sponge iron, metal scrap and ferro alloys like silica and
manganese. The steel making and processing may generate
fumes and dust, which can create health problems in the work
area to the employees. The occupational safety and health plan
shall follow the guidelines based on Factories Act , 1948 and shall
be finalized in consultation with the local factories inspectorate.
The occupational safety and health plan is prepared to identify
the hazards due to the operations and process, with the
mitigation measures. The mitigation measures are mainly
engineering controls, work room conditions, personal protective
equipment and training and education. The occupational hazards
and mitigation plan is presented in Table 7.3. The list of
personnel protective equipment is presented in Table 7.3
Table 7.3
Occupational hazards and mitigation plan Physical Hazards
Hazard Impact Mitigation
A. Physical Injuries due
to hot metal handling
Severe burn injuries a. Engineering Controls;
Splash curtains in Induction Furnace area
Proper design of Rolling Channels in
Rolling Mill area
b. Use of PPE shall be
made mandatory for
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-8
Pridhvi Envirotech (P) Ltd.
workers
B. Heat Stress Heat edema, Heat Rashes, Heat
Cramps, Heat Exhaustion, Heat
Stroke
a. Engineering Controls;
Rotation of employees working
in heat zones
Ventilation
b. Acclimatization
Training and Information
Intake of salts of K &
Na, Liquids regularly PPEs like Goggles,
Helmets, Heat resistant suits, Shoes
shall be mandatory in induction furnace
and re-rolling mill area
C Electrical
equipment handling
Shock, Serious or
fatal injury
Engineering controls
Isolation of systems
Tag Out Appropriate tool
selection Interlock systems
Safety protocols
Provision of PPE
D. Working at
Rolling Mill
Serious fatal injury Engineering Controls
Guards for conveyors
Interlocking
Systems Isolation
Maintenance Protocols
Appropriate Tool Selection
II. Training and Education
III. PPE: Helmets,
Heat resistant gloves, Shoes, Hot suits
E. Cranes and Hoists
Serious or Fatal injury
Engineering Controls ‘Operation cabin
isolation Two holding breaks
on hoist mechanism
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-9
Pridhvi Envirotech (P) Ltd.
Keep the crane
clean with out any loose materials and
tools
II.Obstruction
Clearance
III. Training and Education
E. Falling Objects
Serious or Fatal Injury
I. Engineering Controls Slip resistance
Flooring
Provisions of Platforms & Walk
ways Open mesh
platforms & Walkways
House keeping
Table 7.4 List of Personnel Protective Equipment
Industrial Safety Helmet
Molten metal resistant jackets and trousers
Zero power Plain goggles with cut type filters on both ends
Face shields or vented goggles
Welders equipment for eyes & face protection
Cylindrical type earplug
Ear Muffs
Dust Masks
Safety Belt/lime man’s safety belt Molten metal resistant gloves
Safety footwear insulated against heat
Canvas cum leather hand gloves with leather palm
Electrically tested electrical resistance hand gloves
Electrical safety shoes without steel toe and gum boots
7.5.1 Health Surveillance Plan
The health surveillance plan consists of medical checkup on
recruitment to ascertain the health status of the employees. The
data to be obtained includes.
Baseline health data such as height, weight and Vital statistics. A
detailed history of previous diseases and occupational exposures.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-10
Pridhvi Envirotech (P) Ltd.
The focus will be on previous lung problems and previous
exposure to lung toxins such as silica, asbestos, irritant gases
etc.,
Identification of personal habits (smoking, hygiene, alcohol
consumption, fingernail biting) that may be relevant to work.
History will be sufficiently detailed, complete physical
examination with special attention to respiratory, fatigue, chest
X-ray, Blood tests and urine tests.
The employees shall have annual Medical Check-up with special
attention to respiratory, fatigue, dermal, audiometry tests
depending on the areas they are working in the plant. The
health records shall be maintained by M/s. Devashree Ispat (P)
Ltd Unit-I, Personnel Department.
7.5.2 First Aid center
A First Aid Center is in place in Devashree Ispat (P) Ltd Unit-I.
In house trained first aiders maintain the first aid center.
Adequate medicines are made available in the first aid center. I t
is suggested to provide stretcher, Oxygen breathing equipment
in first aid center.
24x7 an emergency vehicle is made available at site to shift
people in case of any accident. Local ambulance services are also
available in the area under Arogyasree program.
7.5.3 Tie up with Local Hospitals
Government Hospital and Private Nursing Homes are available in
Shadnagar town. It is suggested to have tie-up with the local
hospitals for treating any emergency accident case of workers at
the hospitals.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-11
Pridhvi Envirotech (P) Ltd.
7.6 Disaster Management Plan
This Disaster Management Plan (DMP) has been designed based on the
range, scales and effects of "Major Generic Hazards" described in the Risk
Assessment Report just mentioned and on their typical behaviors predicted
therein. The DMP addresses the range of thermal and mechanical impacts
of these major hazards so that potential harm to people onsite and off-site,
plant and environment can be reduced to a practicable minimum. The
scenarios of loss of containment are credible worst cases to which this DMP
is linked.
The emergency plan envisaged will be designed to intercept full range of
hazards specific to steel melt shops. In particular, the DMP will be designed
and conducted to mitigate those losses of containment situations, which
have potentials to escalate into major perils.
Emergency medical aids to those who might be affected by incident heat
radiation flux, electrical shocks, physical injuries will be inherent in the
basic capabilities. The most important capability of this DMP will be the
required speed of response to intercept a developing emergency in good
time so that disasters such as explosion, major fire etc. are never allowed
to happen.
7.7 Disaster Control Philosophy
The emergency control philosophy of the plant is in line with its normal
operational controls. The emergency control room will be the existing
administrative office, which will employ Distributed Control System (DCS).
All emergency operations will be directed from the Emergency Control
Room.
The principal strategy of DMP of the plant is "Prevention" of identified major
hazards. The "Identification" of the hazards will employ one or more of the
techniques e.g. Hazard and Operability Study (HAZOP), accident
consequence analysis etc. The Project Authority will be committed to this
strategy right from the conceptual stage of the plant so that the objective
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-12
Pridhvi Envirotech (P) Ltd.
of prevention can have ample opportunities to mature and be realized in
practice
The DMP or Emergency Preparedness Plan (EPP) will consist of:
A. On-site Emergency Plan
B. Off-site Emergency Plan
Disaster Management Plan preparation under the headlines of On-site
Emergency Plan and Off-site Emergency Plan is in consonance with the
guidelines laid by the Ministry of Environment and Forests (MOEF), Govt of
India "Occupier" of the facility is responsible for the development of the On-
site Emergency Plan as per the guidelines given by the Government,. The
Off-site Emergency Plan should be developed by the Government (District
Authorities).
7.8 On-Site Emergency Plan
The objective of the On-site Emergency Plan should be to make maximum
use of the combined resources of the plant and the outside service to
o Effect the rescue and treatment of casualties
o Safeguard other personnel in the premises
o Minimize damage to property and environment
o Initially contain and ultimately bring the incident under control
o Secure the safe rehabilitation of affected people
o Provide authoritative information to the authorities and news
media
o Preserve relevant records and equipment for the subsequent
enquiry
o into the cause and circumstances of emergency
7.8.1 Action Plan
The Action Plan consists of:
o Identification of Key Personnel
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-13
Pridhvi Envirotech (P) Ltd.
o Defining responsibilities of Key Personnel
o Designating Emergency Control Centres and Assembly Points
o Declaration of Emergency
o Sending All Clear Signal
o Defining actions to be taken by non-key personnel during
emergency
7.8.2 Key Personnel & Teams
The actions necessary in an emergency will clearly depend upon the
surrounding circumstances. Nevertheless, it is imperative that the required
actions are initiated and directed by nominated people, each having
specified responsibilities as part of co-ordinate plan. the following table
summarizes the rolls and responsibilities of key personnel identified by
M/s.Devashree Ispat (P) Ltd Unit-I.
Table 7.5
Rolls and Responsibilities of Key Personnel Identified By M/S. Devshree Ispat Pvt Ltd Unit-I.
S.No. Designation Person
Nominated
Responsibilities
1 Site Controller
(SC)
Plant manager Overall in-charge and
decision maker during emergencies
Receives communication on
emergencies and declare emergencies in the plant
Deploy adequate manpower and other resources to
control the emergencies
Declare normal status after
handling the emergency Communicate with top
management during and after the emergency
2 Incidental
Controller (IC)
Shift In-Charge Receives communication on
emergencies and communicate the same to
the plant manager Rush to the place of
emergency and assess the
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-14
Pridhvi Envirotech (P) Ltd.
magnitude of emergency
and deploy emergency teams to handle the
emergencies Shut down the plant
operations and restrict the movement of people and
material from and to the plant
Take the attendance from the rolls and alert the
rescue teams for rescue of
the people trapped Supervise the emergency
activity at the site and provide the feedback to the
plant manager from time to time
3 Liaison and Communication
Officer (LCO)
EHS Manager Receives communication on emergencies and
communicate the same to
the nearby plants and other government agencies such
as Fire Tenders, Ambulances and nearby
Hospitals Guide the external and
other rescue agencies to the plant site
Send the injured people to the nearby hospitals by
company vehicles and ambulances
Record the emergency situation and rescue
operation details to submit
to the top management and government agencies as
required
4 Fire and Security Officer (FSO)
Security In-Charge
On hearing of emergency entry of people and material
into the plant is controlled Take the attendance and
visitors list and count the people at the assembly
point and give feed back to
the incident controller
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-15
Pridhvi Envirotech (P) Ltd.
Coordinate the fire control
and rescue operations in the plant
5 Trained
personnel in fire
and other emergency
Ten People
nominated
covering all shifts
Take the necessary fire
extinguishers and other
emergency equipment Start the fire control
activities using fire hydrant lines and fire extinguishers
6 Rescue and first
aiders
Ten People
nominated covering all
shifts
Take the necessary rescue
equipment such as ropes self-breathing equipment
fire suits etc. to the incident site
Participating in the rescue
operations along with other outside agencies
Provide first aid to the injured people and shift
them the nearest hospitals
7.8.3 Emergency Control Centre
The Emergency Control Centre will be the focal point in case of an
emergency from where the operations to handle the emergency are
directed and coordinated.
It will control site activities.
Emergency management measures in this case have been proposed to
carry out from single control Centre designated as Main Control Centre
(MCC).
MCC is the place from which messages to outside agencies will be sent
other helps for the management of emergency will be arranged.
It will be located office of Plant Manager. Following facilities would be
available in the MCC:
P&T phones, mobile phones, intercoms, and wireless
Fax and telex
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-16
Pridhvi Envirotech (P) Ltd.
Site map
Location of water sump, fire hoses and fire extinguishers available at
site
Internal telephone directories
District telephone directories
Emergency lights
Requisite sets of personal protective equipment such as gloves,
gumboots and aprons, self breathing equipment
MCC will be furnished with call out list of key persons, fire, safety, first aid,
medical, security, police and district administrative authorities. MCC will
also contain safety data pertaining to all hazardous materials likely to cause
emergency and well-defined procedures of fire fighting, rescue operations,
first aid etc.
7.8.4 Assembly Point
In an emergency, it will certainly be necessary to evacuate personnel from
affected areas and as precautionary measure, to further evacuate non-
essential workers, in the first instance, from areas likely to be affected,
should the emergency escalate. The evacuation will be effected on getting
necessary message from I.e. On evacuation, employees would be directed
to a predetermined safe place called Assembly Point.
Proposed Location: Area near FG stock yard shall be emergency point in
M/s.Devashree Ispat (P) Ltd Unit -I.
7.8.5 Emergency Management Training
The Key Personnel would undergo special courses on disaster management.
This may preferably be in-plant training. The Managers, Senior Officers and
Staff would undergo a course on the use of personal protective equipment.
The Key Personnel belonging to various Teams would undergo special
courses as per their expected nature of work at the time of emergency.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-17
Pridhvi Envirotech (P) Ltd.
The plant management should conduct familiarization program to outside
agencies like district fire services to make them familiar with the plant
layout and other aspects, which will be helpful to them during an
emergency.
7.8.6 Mock Drills
It is imperative that the procedures laid in this Plan are put to the test by
conducting Mock Drills. To avoid any lethality, the emergency response
time would be clocked below 2 minutes during the mock drill.
1st Step: Test the effectiveness of communication system
2nd Step: Test the speed of mobilization of the plant emergency teams
3rd Step: Test the effectiveness of search, rescue and treatment of
casualties
4th Step: Test emergency isolation and shut down and remedial measures
taken on the system
5th Step: Conduct a full rehearsal of all the actions to be taken during an
emergency
It is suggested to make mock drill once in 6 months time in M/s. Devashree
Ispat (P) Ltd
7.8.7 Incident recording and revision of Disaster Management Plan
Every incident/accident in Devashree Ispat (P) Ltd Unit-I shall be recorded
by safety & environmental officer. Root cause analysis and corrective
actions shall be taken by responsible I/C of area and shall be reviewed by
top management in safety committee meeting once in two months time.
The Disaster Management Plan would be periodically revised based on
accident / incidents and experience gained from the mock drills.
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
7-18
Pridhvi Envirotech (P) Ltd.
7.9 Off site Emergency Plan
As this is a steel melting unit, the emergency situations will be
limited to plant premises. As there is considerable distance
between the habitation and the operation areas of the plant,
there is no possibility of emergencies resulting outside. Hence no
specific off-site emergency plan is not suggested. However as
and when district authorities and fire & emergency services
authorities ask for any specific information, same shall be
submitted by M/s. Devashree Ispat (P) Ltd Unit-1. Also the unit
will participate in any off-site mock drill programs conducted by
District officials in the area.
Chapter-8
PROJECT BENEFITS
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
8-1
Pridhvi Envirotech (P) Ltd.
CHAPTER-8
PROJECT BENEFITS
This chapter describes about benefits of the project on improvements in the
physical infrastructure, social infrastructure, employment potential and
other tangible benefits.
8.1 Employment Opportunity
Currently the total employees working in the plant are 325 people.
The proposed expansion project is likely to provide employment to
additional 120 people. The preference will be given to local population for
employment as per the qualifications of people; this will increase the
employmnt opportunity in the surrounding area.
Secondary jobs and indirect employment are also bound to be generated to
provide day-to-day needs and services to the work force and industrial
activity. This will also increase the demand for essential daily utilities in the
local market. The employed people will be benefited financially. This
financial gain will increase their standard of living.
8.2 Likely Indirect Employment Opportunities
The industry requires higher quantities of raw materials and procures from
various sources. This will enhance the employment opportunities at the
source. Apart from this additional employment will be generated in the
transport sector for increased material transportation.
The industry generates nearly 7000 tons of slag per year after expansion.
Slag is crushed in-house and crushed material can be used for manufacture
of bricks by mixing it with cement motor. The management is ready to
encourage local people to provide technology and resources to take this as
downstream unit. This will increase employment opportunities
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
8-2
Pridhvi Envirotech (P) Ltd.
8.3 Environmental Social Responsibility (ESR) & Socio-Economic
Development
The unit is aware of the obligations towards the society and to fulfill the
social obligations, unit will employ semi-skilled and skilled labor from the
nearby villages for the proposed project as far as possible. Unit will also
helps to generate indirect employment in the nearby villages by appointing
local contractors during construction phase as well as during operation
phase. After proposed project, unit will make provision of fund every year
towards CER activities in nearby villages. The various CER activities
identified and planned at present are described below;
Augment water supply for near by Maleellikatta village(Under Ellikatta
panchayat)
Contribute to neighborhood under swach Bharat program and
Telgananaku haritharharam project
A budget of Rs.9.5 Lakhs is proposed as per the corporate environmental
responsibility by the company towards these activities over a period of next
5 years.
As per the Companies Act, CSR funds will be allocated on the profits.
8.4 Direct Revenue Earning To the National and State Exchequer
The proposed project will also contribute revenue to the Central & State
exchequer in the form GST & Corporate taxes etc. Indirect contribution to
the Central & State exchequer will be there due to Income by way of
registration of trucks, payment of road tax, income tax from individual as
well as taxes from associated units. Thus, the proposed project will
contribute to state and central exchequer which will help in developing the
area. Development with sustainable approach is the goal of the industry to
maintain good environment.
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
8-3
Pridhvi Envirotech (P) Ltd.
8.5 Other Intangible Benefits
The proposed project will have many employment & trade opportunities
with the initiation of expansion activities. Thus, these considerable
employment & trade opportunities will eventually result in appreciable
economic benefits to the local people & businesses/contractors. At present
the raw materials & finished goods are moved by trucks which provides
indirect employment to people engaged in this sector. With increase in
capacity, unit’s contribution to growth of service sector shall increase.
Rain water harvesting is done for groundwater recharging that will improve
the ground water table in the area. Green drive in the area will give a
pleasant look and improves biodiversity of the area.
Chapter – 9
ENVIRONMENT COST BENEFIT
ANALYSIS
M/s. Devashree Ispat (P) Limited Unit-I Draft EIA Report
9-1
Pridhvi Envirotech (P) Ltd.
CHAPTER – 9
ENVIRONMENT COST BENEFIT ANALYSIS
There is no specific aspect recommended in the TOR on this.
Chapter-10
ENVIRONMENT MANAGEMENT PLAN
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-1
Pridhvi Envirotech (P) Ltd.
CHAPTER-10
ENVIRONMENT MANAGEMENT PLAN
This chapter outlines the Environmental Management Plan for the project,
budget provisions, institutional arrangements for implementation and
monitoring of the EMP.
10.1 Introduction
Environmental Protection is an issue that no organization can neglect and
hope to survive. The by- products of civilization are being dumped upon the
environment to a degree that the environment finds difficult to assimilate.
The key to success of the integrated approach to pollution prevention and
control is the management and operation of the organization. Effective
committed management delivers a successful industry. As total
commitment to the environment, not just for compliance with legal or
regulatory compliance will be the essence of environment management of
an industry. Many companies have recognized the benefits of implementing
an effective environmental management system.
Environmental management Plan can be effectively implemented to
mitigate the pollution levels by observing the following;
Pollution will be prevented or reduced at the source,
Pollution that cannot be prevented will be recycled in an
environmentally safe manner,
Pollution that cannot be prevented or recycled will be treated in
environmentally safe manner.
Disposal and other releases into the environment will be used “only
as a last resort” and will be conducted in an environmentally safe
manner.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-2
Pridhvi Envirotech (P) Ltd.
The management plan is drawn in consultation with the project proponents
with reference to various potential impacts monitored, identified and
predicted in the previous chapters. And the necessary measures to be taken
for the mitigation and control of the same presented, various pollution
control measures adopted which are present and the proposed additional
measures identified for adoption are discussed in this chapter.
Review of the process is the essential component of Environmental
management Plan.
10.2 The Project Location
The proposed project is to be located over the existing premises
at Sy.Nos.458,459 and 460, Elikatta (V), Farooqnagar (M), Rangareddy
District, Telangana State.
The project site is located between Lattitudes N 17059’22.0’’ E
78o24’55.6’’ and N 17059’14.6’’ E 78o24’53.0’’.
10.3 Site Sensitivity:
The nearest human settlement from the site is at Male
Elikatta village located at a distance of 0.6 km in South East
direction.
Total number of villages in 10 KM radius of the site is 75
and the total population in 10 KM radius is 1,38,080.
Nearest town is Shadnagar is at a distance of 7.15 KM with a
population of around 45675.
Rangampalli Cheruvu is at 1.29 Km from SW Direction and
Beemavaram nallah at 8.4 Km from South west direction.
ZP High school is in Shadnagar which is about 7.20 KM away
from the site.
One primary health center & Anganwadi School in Elikatta
village.
Mysuram Kammadhanam Reserve forest is at a distance of
9.07 km in South East direction.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-3
Pridhvi Envirotech (P) Ltd.
The major road access to the site is NH-44 which is at a
distance of 7.20 KM on the East. Shadnagar to Pargi Road is
adjacent to the plant site which connects to National Highway.
The nearest railway station is Shadnagar Railway station at a
distance of 7.15 km from the site in the East direction.
There are no sanctuaries, ecologically sensitive areas or
national parks with in 10 km radius of the site.
Indian Remote sensing agency, data receiving and analysis
center is located near Shadnagar area.
Sri Ramalingeswara Swami Temple at Rameswaram built in the 19th
Century is an important religious place in the study area.
10.4 MAJOR FINDINGS OF THE EIA
An EIA was conducted as per the broader guidelines of TOR issued to the
project and based on current deficiencies in the running plant, the major
findings of the EIA study & Impacts of the project on environment due to
the expansion activity are presented below
10.4.1 Impact on Physical Resources
Expansion activities of the plant requires few natural resources like
sand, sub grade & aggregate, and materials produced from natural
resources like bricks, cement and steel. The material shall be drawn from
local sources, and the lead distances range from 1- 100 km. The impacts
on physical resources of sand will be irreversible while bricks will be
brought from kilns. The material requirement of steel, cement etc. will
be purchased from manufacturers with in state.
There will be marginal impacts on physical resources as regards the
availability and procurement of construction material are anticipated
due to the project.
10.4.2 Impacts on Air Quality
Impacts on air quality during construction stage are likely to be due to
operation of construction yards, material transport on trucks and
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-4
Pridhvi Envirotech (P) Ltd.
fugitive emissions from the construction site. During operational stage
the following air emission sources are identified
Air emissions from Induction Furnace
Air emissions from DG sets (standby)
Air emissions from Re-heating Furnace (standby)
Air emissions from Coal Pulverizer
Fugitive emissions from vehicle movement
Fugitive emissions from storage and handling of slag waste
Emissions are quantified and given in chapter 2 and Chapter 4. Modelling
results are presented in chapter 4 which indicates slight increase in PM
10, PM 2.5, SO2 and NOx. Bag filters are installed for controlling dust
emissions from Induction Furnace. Adequate stack height is maintained
as per CPCB norms for both Induction Furance and DG Sets for safe
dispersion of emissions. The Re-heating Furnace is kept as standby and
will be used only in case of failure of Conveyor. Coal Pulverizer Unit is
provided with bag filter system to control dust emissions.
10.4.2.1 Measures for fugitive emission control
Slag generated from the plant if transferred to Unit III where Slag
Crusher is established.
Proper storage of crushed slag is recommended under shed with water
sprinklers.
To avoid the dust from roads, it is suggested to provide water sprinklers
for wetting of roads.
10.4.3 Impact on Water Resources
The main source of water is by tankers from nearby villages. The fresh
water requirement would be 145 KLD and Recycled water from cooling
towers would be 98 KLD both put together would be 243.0 KLD total water
requirement.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-5
Pridhvi Envirotech (P) Ltd.
10.4.3.1 Pollution Control Measure
It is proposed to treat and re-use the cooling water from the mill sections
and recycle the furnace cooling water directly and completely
It is suggested to treat the domestic sewage also in STP and re-use for
gardening purpose
10.4.3.2 Water Conservation Measures
Project site is in semi-arid region and receives about 833 mm rainfall.
Water is scarce and is required to adopt all possible methods to conserve
the resource. All the possible methods of Reduce, Recycle and Reuse of
water shall have to be implemented along with the minimization of waste
generation in the process.
In order to reduce consumption of fresh water the following options will
have to be adopted at every stage.
(1) Leakages from taps and pipe joints will have to be avoided.
(2) Care should be taken to avoid accidental leakages and spillages.
(3) Cooling towers shall be maintained to avoid any leakages.
(4) Cooling water make up shall be measured to detect any line
leakages.
10.5 RAIN WATER HARVESTING AND RECHARGE METHODS
Fresh Water is elixir of life. It is not only required for life’s survival and
sustenance, but also its availability plays a vital role in the prosperity and in
all the processes of modern day development. Fresh water, once in
abundance is gradually becoming scarce. Population growth, increased
demand has necessitated to conserve fresh water resources and also to
protect the environment.
With a little effort, naturally falling precipitated rain water can be collected
and stored for its use in subsequent periods. Every environmentally
conscious citizen should realize the importance of rain water harvesting. It
is an enlightened self-interest of an individual to save the money and
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-6
Pridhvi Envirotech (P) Ltd.
resources spent for getting equivalent amount of fresh water from
elsewhere.
In the Project Site, rainwater harvesting methodology comprises of two
components (A) the roof top rain water collection from the buildings, (B)
overland flow collection from open areas within the project premises.
Collected rainwater can be stored suitably for its use in subsequent periods
or used simultaneously.
Harvested rain water can either be used directly; a part or full can be
utilized simultaneously for artificial recharge of ground water source.
harvested rain water can be fruitfully utilised for augmenting the source.
10.5.1 Ground Water Recharge Requirements- Site Conditions:
In any environment to take-up ground water recharge, either any one or
more of the following conditions are necessary in the Site
10.5.2 Ground water Exploitation:
Ground water draft in any basin / water-shed should be limited to the long
term average annual recharge. Where the draft exceeds the replenish-able
recharge, the resources dwindle, water levels fall steeply, wells gets dried
up and aquifers also lose their inherent storage capacity. In such situation
it is desirable to adopt sustainable development strategy and management
of the available resource by adopting artificial recharge techniques.
However the area where plant is located is considered as safe zone for
ground water exploitation
10.5.3 Rain Water Harvesting Plans:
10.5.3.1 Open areas Over- land Flow:
The plant consists of Mills, Open areas, Greenbelt, Buildings and Utilities.
The normal annual rainfall is about 800 mm. At about 60% of surface
storm flow from the rainfall, the anticipated overland flow is from 480 mm
rainfall. The volume of storm water likely to leave the Plant Site is not
advisable to collect the same.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-7
Pridhvi Envirotech (P) Ltd.
10.5.3.2 Roof top Rain Water Collection
It is suggested to provide roof top rain water collection system for the RCC
roof buildings. Precipitated rain water on the Roof top may be connected to
storage reservoir/tank placed on the ground having a control valve in
between to wash off initial rainfall water associated with dust / impurities.
The stored water may be used for washing machines / vehicles toilet
purposes. Currently the plant had developed a rain water pond within the
plant premises and storing and using this water for industrial uses.
10.5.3.3 Road top/paved areas Rain Water Collection
Rain water from the road top paved areas and also in the open areas may
be diverted and stored in the lined ponds constructed within the Green belt
area. Rain water collected and stored in the lined Reservoirs / Ponds may
be used for green belt development during dry spells.
10.5.4 Ground Water Recharge Structures
10.5.4.1 Project Site
There is an unlined surface water collection pond at the entrance gate in
the North-East, of dimensions 47m X 23m with average depth of 4m to
harvest over land flow of road top and open area rainfall surface runoff. The
stored water of about 4000 m3 shall be available for Ground Water
recharge. It is likely to fill a minimum of 6 times during monsoon rains.
Considering 50% water stored shall go in to storage of aquifer horizons at
depth, nearly 12000 m3 gets added annually from the pond.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-8
Pridhvi Envirotech (P) Ltd.
Figure 10.1 Rainfall Harvesting Pond existing in the plant
10.6 Impact on Soil
The impacts on soil primarily come from slag waste handling and Mill waste
handling processes. It is suggested to provide a proper concrete plat form for
draining out the Mill waste removed from settling tanks of mill cooling water
sump. Also it is suggested to provide covered storage both for Mill waste and
crushed slag waste until they are disposed off.
10.7 Impact on Land use
The existing project is spread over 42997.14 Sq. M or 10.62 acres of land.
Out of this 2.72 Acres is utilized for constructions and 3.00 acres is utilized
for Green Belt area. The remaining area comprises roads and open area.
Additional Land requirement for the proposed expansion would be 1.0 Acre
for expansion of Rolling Mill and stock yards. It is proposed to add an
additional green belt of 0.54 acres with expansion activities. This land will
be utilized from existing open areas.
Thus there is no need for acquisition of additional land for project. As the
plant area is under industrial use, there is no need for change of land use
There will not be any impact on land use of the area as a whole.
Plant Site R W H Pond Plant Site R W H Pond
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-9
Pridhvi Envirotech (P) Ltd.
10.8 Impacts on Noise Quality
Impacts on noise quality during construction stage will be significant.
Hence the construction is proposed only during daytime, construction
workers will be provided with protection equipment to guard against the
noise impacts.
The impacts during occupation stage will be noise from DG Sets and
Rolling Mill activities. Acoustic enclosures are proposed to meet noise
standards near DG Sets. The impact of noise from Rolling Mill will be
limited to site boundaries as there is considerable distance between plant
boundary and Rolling Mill. All the mill workers shall be provided
personnel protective equipment.
Extensive green belt on the boundaries proposed will further reduce
impact of noise on outside environment.
10.9 Impact on Flora
The project site and its surroundings do not form a habitat to any
endangered flora. The project will enhance the aesthetics of the site due
to the provision additional green belt. Currently the unit is having a
greenery of 3.0 Acres. As a part of expansion activity it is proposed to
add additional green belt area 3.54 acres to the existing green belt. The
total area of green belt after expansion would be 33 % of the total area.
Further as a part of commitment towards eco development program, the
management is planning plantation of around 250 trees in the nearby
public areas as a part of “Telanganaku HaritaHaram” project of the state
Government. Thus overall impact on flora would be positive.
10.10 Impact on Fauna
As there are no endangered species of wild life in and around the project
site, it is likely to have minimal impact. The avifauna will find abode on
the trees proposed to be planted. This would enhance the aesthetics of
the area.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-10
Pridhvi Envirotech (P) Ltd.
10.11 Impact on Road Network
The road infrastructure available at present can meet the demand. The
development in combination with this project activity will have marginal
impact. The site is well connected to NH 44 Banglore way which is at
about 7 KM from the site. The site adjacent to Shadnagar – Pargi Road.
It is anticipated that there will be an addition of 60 PCU units/day after
expansion which is insignificant compared to carrying capacity of road.
10.12 Impact on Power Distribution:
Power is required for operating the Induction Furnace, Rolling Mill, Bag
Filters ID Fan, Cooling Towers etc., and for general lighting in the plant.
Presently the connected load of 8.5 MVA is being sourced from TSSPDCL.
The total power requirement after expansion will be approximately 11.0
MVA and the additional power required will be sourced from TSSPDCL.
10.13 ENVIRONMENT MANAGEMENT MEASURES PROPOSED
A description of the various management measures during the various
stages of the project is provided in the table below
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-11
Pridhvi Envirotech (P) Ltd.
Table 10.1
Environmental Impacts and mitigation measures
Environmental
Issues/Impacts
Enhancement/ Mitigation
Measures Management Action
CONSTRUCTION PHASE
Dust generation
due to construction
activities
Roads in the construction area
will be sprinkled with water to
reduce the raising of dust. Stocking of construction materials
would be minimized Plantation measures will be
improved
Plantation will be improved
Horticulturists to identify the
species. Supervising consultants/
contractor to ensure the water sprinkling
Exhaust gases from construction machinery
and transportation of materials
Vehicle and equipment maintenance.
PUC for all transport Vehicles.
Avoidance of idling of equipment.
Contractors to be educated and superv i s ing consu l tan t to
ensure the same.
Sedimentation of
storm water during rainy season
Avoiding stockpiles of materials
near natural drains. Provision of filter fence
Provision of storm water drains wherever possible before the
beginning of construction.
Storm water drains will be planned
along with construction plan Proper traps will be planned to avoid
sediments reaching storm water drains
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-12
Pridhvi Envirotech (P) Ltd.
Alteration of
Drainage
Storm water drains to follow the
natural course as far as possible. Storm water drains to have a
min. water velocity of 1m/s and a max. 3 m/s.
Min. width of 0.6 meters and depth based on the gradient
Storm water inspection pits shall be provided to check water
quality
Architects in consultation with
sanitary engineering consultants. Supervision consultant to ensure
the same.
Water Consumption Water conservation measures
during construction.
Sub contractors to be educated on
water conservation measures.
Pollution from
construction workers
Provision of toilets connected to
septic tank followed by soak pit. Proper availability of drinking
water. Proper Sanitation practices.
No labor camps required at the site
as local labour will be employed
Soil Erosion
Silt fence to ensure silt does not
enter storm water drains. Side slopes will be kept flatter
wherever possible, and in case of steeper slopes it is mulched.
Supervision consultant to ensure the
same in consultation with project authorities.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-13
Pridhvi Envirotech (P) Ltd.
Contamination of Soil Vehicle washing and machinery
washing to be avoided in site. Parking of vehicles and
maintenance of vehicles to be avoided in site.
Disposal of solid wastes by construction workers to be made
in garbage bins only.
Sub-contractors and Project
authorities should ensure. Designate the parking areas
Provision of Garbage bin by project authorities and arrangements to be
for disposal of the same.
Natural Resource
consumption
Identify sand availability from
government-authorized locations
Use of robotic sand to maximum extent possible.
use bricks made from coal ash and slag produced from the
plant
The design consultation with
project authorities and supervision consultants must identify the
suppliers.
Noise Pollution from heavy machinery, and
transportation.
Noise causing activities to be conducted during daytime.
Maintenance of equipment and vehicles to mitigate noise
generation.
Inclusion of appropriate clauses in construction contracts; monitoring
of compliance during construction and proper administration of
contracts. Locating the construction
equipments in consultation with project authorities and supervision
consultants.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-14
Pridhvi Envirotech (P) Ltd.
Construction debris •Construction debris to be used for aggregate and or sub grade purpose in the case of RCC
•recyclable metals to be collected and sold to recyclers
•avoidance of excess inventory of materials.
Provision of waste disposal site for
waste from construction and storage yard.
Supervision consultant in consultation with the sub-contractors
Inclusion of appropriate clauses in construction contracts; monitoring of
compliance during construction and proper administration of contracts
OCCUPATION STAGE
Dust Generation from material transport
vehicles
Maintenance of roads by way of sweeping.
Water sprinkling on roads Plantation.
Horticulturist should ensure avenue plantation
The Plant management should ensure maintenance of avenue
plantation.
Emissions from
Induction furnaces
• Establishment & Continuous
operation of high efficiency Bag Filters
• Provision of primary and
secondary ducts for induction furnaces
• Use of good grade scrap Maintenance of bag filters
Availability of spare bags Stack heights as per the CPCB
Norms Periodical monitoring of
emissions
Upgrading the existing Bag Filters to
meet higher capacity furnace and provide adequate ID fans to suck the
dust from furnace area during
operations
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-15
Pridhvi Envirotech (P) Ltd.
Emissions from coal
pulveriser
• Enclose the conveyor systems
thoroughly • Provide bag filter with suction
points to extract dust generated at transfer points
• Provide shed for storage of coal • Provide water sprinklers in coal
storage area
To be maintained by management of
M/s. Devashree Ispat (P) Ltd Uniut-I
Emissions from DG
sets
• Enclose the DG sets with
acoustic enclosures • Provide enough stack height as
per the CPCB norms • Maintain DG sets as per the
manufacturers recommendation
To be maintained by management of
M/s. Devashree Ispat (P) Ltd Unit-I
Waste Water Management
The cooling water from Rolling Mill and Induction Furnace shall
be pre-treated to remove oil & grease and suspended solids and
recycled back. Domestic waste water shall be
treated in STP and re-used for gardening.
Proper up keep of primary treatment plant is responsibility of
operational management of M/s. Devashree Ispat (P) Ltd Unit-I
Records of influent and treated effluent quality and quantity
should be maintained by the plant management as per the monitoring
plan specified
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-16
Pridhvi Envirotech (P) Ltd.
Storm water
Management
Storm water drains will be
maintained periodically before monsoon.
Accidental discharges spillages will not be allowed to join storm
water drains. Roads, pavements and other
surfaces are swept regularly. Storm water quality shall be
monitored regularly and records shall be maintained
• Storm water drain system and
recharge pond provided by M/s.Devashree Ispat (P) Ltd Unit-I
and will be maintained properly
Water Conservation
Measures .
Water conservation measures to
be adopted to reduce resource consumption
Water consumption for various uses shall be measured and
records shall be maintained
Rain water conservation shall be done by re-charge pit existing at
the entrance of the plant
M/s. Devashree Ispat (P) Ltd Unit-I
shall conduct regular training classes on water conservation
measures M/s. Devashree Ispat (P) Ltd shall
maintain the rain water recharge
pond
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-17
Pridhvi Envirotech (P) Ltd.
Solid & Hazardous
Wastes
Solid waste/garbage to be
collected in green and blue dustbins.
The biodegradable wastes to be removed everyday while the
recyclable wastes to be removed once a week.
Slag waste shall be used for land filling
Proper storage of slag and mill waste shall be done
Waste oil generated from Rolling
Mill and DG sets shall be filtered and re-used for lubrication
purpose Waste generated from Coal
Pulverizer Unit ( If operated ) shall be reused
• Plant authorities and
Environment team shall be responsible for proper handling,
accounting storing & Disposal of solid waste and maintenance of
records
Noise Levels Noise levels due to traffic will increase in the area and the
mitigation measures like maintaining greenery
Noise levels from DG sets to be mitigated by the provision of
acoustic enclosures.
Noise from Rolling mill operations
Plant authorities shall ensure development and maintenance of
greenery PPE shall be provided to work force
working in the high noise areas Noise levels shall be measured as
per the monitoring plan
Audiometry tests shall be carried
out for those people exposed to
high noise levels
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-18
Pridhvi Envirotech (P) Ltd.
Traffic Control &
Parking
Provision of parking facilities for
trucks carrying raw materials and FG goods
Traffic and road safety signals to be provided in the plant premises
The plant management must
ensure proper parking of vehicles carrying raw materials in
designated areas only Cleaning operations of trucks shall
not be allowed in plant premises or nearby water bodies
Contractors shall be educated on this by M/s. Devashree Ispat (P)
Ltd Unit-I
Flora The impacts on flora are due to
air pollution from furnace, DG sets and other fugitive dust shall
be mitigated by developing greenery
The flora of the site shall
increase with the greening program.
•The Project authorities M/s.
Devashree Ispat (P) Ltd Unit-I management to ensure greening
the open space.
Energy Conservation
The energy conservation measures for operation of
various equipment and pumps shall be ensured
Energy efficient lighting shall be ensured
Use of solar street lighting is suggested
The Architect shall ensure the codes are implemented in the
design drawings and working drawings.
Use of LED lights, Electronic Ballast, and ON/OFF sensors, etc.
All Pumps, Motors and mechanical equipment shall be maintained
regularly
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-19
Pridhvi Envirotech (P) Ltd.
Fire Safety Provision of fire safety measures
as per the fire safety regulations.
The plant management must
provide necessary emergency equipment outlined in chapter 7
Regular mock drills shall be done by team
Worker Safety Personal protective equipment
shall be provided to all employees working in furnace
and rolling mill areas Regular health checkup shall be
done as per the norms and
records shall be maintained Display of Safety warnings in
rolling mill and induction furnace area
Periodic breaks shall be given to people working in hot areas of
furnace and rolling mill Periodic audit of electrical
installations shall be carried out Emergency vehicle shall be
available at site 24x7
M/s. Devashree Ispat (P) Ltd shall
provide training to all employees regularly on safety
EHS teams shall be made responsible on accident and
incident reporting system
All safety equipment shall be examined at regular intervals
Management actions shall be initiated based on health checkup
records The work force shall ensure wearing
of safety gadgets always in the factory premises
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-20
Pridhvi Envirotech (P) Ltd.
10.14 Green Belt Development
It is well known that trees help to reduce various types of pollution.
Development of a green belt with selected plant species in and around the
proposed project site reduces the intensity to pollution as well as improves
the aesthetics. Hence species selection is very important. The direction,
distance between the plants, maintaining the survival rate etc are keen for
greenbelt. The number of species and their size (individual numbers)
depends on the budget and available space. Efforts will be taken for
strengthening the existing greenbelt like replacing the exotic tree species
with local & indigenous tree species in the project site.
Green Belt is recommended as one of the major components of
Environmental Management Plan. Out of the total area 10.62 acres of land,
green belt is proposed to develop in 3.54 acres (33%). Proper attention
and management is required to maintain the survival rate of the planted
species. The existing greenbelt tree species will not be disturbed. A large
variety of other plant species suggested under the green belt plan and
around 15 lakhs financial budget is proposed to develop the habitat. The
species can be selected as per the availability of greenbelt area. Following
guidelines has been suggested & shall be followed by the company for
future operations of greenbelt development & maintenance.
As per the present project activities, it is recommended to raise the
following plant species. These species can be also available near the forest
department nurseries.
Among the various native plant species evaluated during the research
studies Pongamia pinnata and Azadiracta indica are identified as keystone
species which is coming under the excellent category.
Small herbs, grass verities, climbers and other ornamental and flowering
plants can also be raised as per the availability near the paths and
corridors of the existing buildings. Certain plants are also recommended to
raise in the buffer zone as per the budget availability.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-21
Pridhvi Envirotech (P) Ltd.
Care shall be taken to plant ample trees along the road side, boundary wall
as well as within the plant premises. It shall enable proper balance of
atmosphere both outside the campus by absorbing noise and gaseous
pollutants of the road side movement of vehicles and also absorption of
noise and emissions within the premises of the plant.
Company shall follow the following five year comprehensive
Company shall follow the following five year comprehensive greenbelt
development program after that the company shall keep following
the prevailing practices of greenbelt management.
Company shall maintain all necessary facilities for irrigation of
greenbelt in good condition and necessary maintenance of irrigation
facilities shall be done regularly.
Company shall regularly assess survival rate of planted trees & shrub
and if required necessary re‐plantation shall be done to ensure
healthy & dense greenbelt area in proposed premises.
For re‐plantation, if required, company shall acquire saplings from
local private/government (Forest & Other) nursery.
Company shall do fertilization as required for healthy & dense
greenbelt development.
Management Period
The properly designed greenbelt area, irrigation facilities, sapling storage &
maintenance area and storage for greenbelt development resources/tools
etc. shall be provided in construction phase prior to commissioning of plant
operation. The necessary structural maintenance shall be done throughout
the extent of operation phase. The greenbelt development guidelines and
five year program shall be initiated with inception of construction phase of
project and shall be implemented & practiced as routine throughout the
project life.
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-22
Pridhvi Envirotech (P) Ltd.
Budgetary Provision
Considered in capital & recurring cost for Ecological Conservation &
Protection.
Responsible Authority
Project Proponent, Project Manager, Accounting Head/Manager, Site Officer
& Engineers, Contractors.
Table 10.2 List of Trees recommended for Green Belt
SNo Botanical Name Common Name
Preferre
d site of planting
No
1 Polyalthia longifolia
(Sonn.) Thwaites
Indian mast tree A1 20
2 Azadirachta indica
A.Juss.
Neem A1 10
3 Leucaena leucocephala (Lam.) de Wit Jabarichettu
A1 20
4 Terminalia catappa L. Baadam A1 5
5 Thespesia populnea (L.)
Ganga Raavi A1 2
6 Tecoma stans (L.) Juss. ex Kunth
Patcha turai A2 10
7 Vitex negundo L. Vaavili A2 5
8 Pongamia pinnata (L.) Pierre
Kanuga A2 10
9 Cascabela thevetia (L.) Pacha ganneru A2 15
10 Melaleuca citrina (Curtis)
Crimson bottle brush
A2 2
11 Nerium odoratum Lam. Ganneru A3, B 10
12 Bauhinia purpurea L. Are A3 5
13 Caryota urens L. Fish tail palm B 10
14 Roystonea regia
(Kunth) O.F.Cook
Royal palm B 10
15 Plumeria alba L. Deva ganneru C 5
16 Ixora coccinea L. Ramabanam C 5
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-23
Pridhvi Envirotech (P) Ltd.
Preferred site of planting codes:
A1: Tall trees towards boundary wall
A2: Medium sized trees next row to A1 species
A3: Small trees next row to A2 species
B: Near entrance gate and paths
C: Garden centre and space provided for plantation
Table 10.3 List of Ornamental herbs and shrubs within the greenbelt area
(recommended for aesthetic value):
SNo Botanical Name Common Name Habit Preferred site
of planting No
1 Acalypha hispida Shrub Next row to Hedges
5
2 Plumaria pudica Tree Garden Centre 5
3 Tabernaemontana divaricata
Nandivardhanam Shrub Garden Centre 4
4 Caesalpinia pulcherrima
Ratnagandhi Shrub Next row to Hedges
3
5 Allamanda schottii
compacta
Hedge Towards paths 100
6 Begonia
semperflorens
Hedge Towards paths 10
7 Caladium hortulanum
Fancy Leaved Caladium
Hedge Towards paths 10
8 Euphorbia geraldii Kiss Me Quick Herb Near Corridor 10
9 Catharanthus rosea
Vinca Ordinary Herb Near Paths 100
10 Crinum asiaticum Blood Lily Herb Near Corridor 10
11 Crossandra
undulaefolia lutea
Crossandra
Yellow
Herb Near Corridor 10
12 Eranthemum purpureum
Kodia Purple Leaves
Hedge Towards paths 10
13 Gerbera jamesonii Transvaal Daisy Herb Near Corridor 10
14 Lantana camara erecta
Lantana Red Shrub Next row to Hedges
10
15 Kalanchoe tubiflora Chandelier Plant Herb Near Corridor 100
16 Buddleja davidii Butterfly bush Shrub Next row to Hedges
10
17 Asystasia gangetica
Creeping foxglove
Hedge Near Paths 100
18 Bauhinia Scarlet Climbin
g shrub
Entrance to
Garden
5
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-24
Pridhvi Envirotech (P) Ltd.
19 Ixora coccinea jungle flame Shrub Next row to Hedges
5
20 Pennisetum
clandestinum
Lawn Grass Grass Rest of all LS
Table 10.4 Avenue plantation for Road side and pond side (recommended):
(For each 1 ha)
S.No. Botanical name Importance No. of
trees
Area
in ha.
1 Ficus benghalensis Shade and a
source of food for birds
100 0.1
2 Ficus racemosa Edible fruits 50 0.05
3 Ficus religiosa Shade and a source of food for
birds
50 0.05
4 Ailanthus triphysa Shade 50 0.05
5 Azadirachta indica A.Juss. Shade 50 0.05
6 Albizia amara Shade 50 0.05
7 Butea monosperma (Lam.) Taub.
Shade 50 0.05
8 Alstonia scholaris Shade 100 0.1
9 Bauhiniapurpurea Shade and flowers 100 0.1
10 Tecomastans Shade and flowers 50 0.05
11 Tectonagrandis Shade and Wood 50 0.05
12 Pongamia pinnata (L.) Pierre
Shade and wood 50 0.05
13 Terminaliabellarica Shade and fruits 50 0.05
14 Peltophorum pterocarpum Shade 100 0.1
15 Samania saman Shade, timber and
fruits are a good live stock feed.
100 0.1
Table 10.5 Proposed financial Budget for the Green belt development (Rs in
Lakhs)
S.No Component First
year
Second
year
Third
year
Fourth
year
Fifth
year Total
1 Plant seeds/
saplings
2.0 1.0 1.0 - - 4.0
2 Gardeners Cost 2.0 2.0 2.0 2.0 2.0 10.0
3 Fertilizers and
Miscellaneous cost
0.20 0.20 0.20 0.20 0.20 1.0
Grand Total 4.2 3.2 3.2 2.2 2.2 15.0
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-25
Pridhvi Envirotech (P) Ltd.
10.15 Environment Management Cell
The industry shall have an Environment Management Wing
supervised by the Plant Head. The organizational chart for
Environmental Management is presented in figure 10.2.
Fig 10.2 Organizational Chart for Environmental
Management
Records shall be maintained for the analysis of raw effluents and
treated effluents, ambient air quality data, Stack emissions
monitoring results, micro-meteorological data and noise levels.
These records are not only requires for the perusal of the
pollution control board authorities but also to derive at the
efficiencies of the pollution control equipment as the objective of
the project proponent is not only compliance with statutory
regulations, but also a serious commitment towards clean
environment.
The industry shall regularly maintain the records as per the
hazardous waste regulations & shall apply for the renewal of
consents for air and water and renewal of authorization for the
Hazardous waste.
Environment &
Safety Officer
Maintenance
Head
Operators
2 Nos
2 Workers
Instrumentation
Technician 1 Nos
Plant Head
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-26
Pridhvi Envirotech (P) Ltd.
10.16 REPORTING SYSTEM & MONITORING SYSTEM
Reporting system provides the necessary feedback for project management
to ensure quality of the works and that the program is on schedule. The
rationale for a reporting system is based on accountability to ensure the
measures proposed as part of the Environment Management Plan get
implemented in the project.
The reporting system will operate linearly with the contractor who is at the
lowest rung of the implementation system reporting to the Supervision
Consultant, who in turn shall report to the top management of M/s.
Devashree Ispat (P) Ltd Unit – I. Every month, implementation of EMP
shall be reviewed by top management during implementation stage and
thereafter during operational stage.
10.17 Corporate Environmental Responsibility
The project proponents have been contributing to the socio-economic
development in the area as part of the Corporate Environmental
Responsibility (CER). Company is providing sustainable livelihoods through
direct and indirect employment the company.
Towards improvement of social infrastructure in the nearby villages it is
proposed to implement following CER activities for the next 5 years period.
Table 10.6 Budget for CER Activities
Activity Year wise Budgets (Rs. Lakhs)
1 2 3 4 5 Total
Augmentation water facilities in the nearby
Maleellikatta village
3.0 1.0 0.5 0.5 0.5 5.5
Contributing to
neighbourhood cleanliness under
“Swachh Bharat” mission &
Telanganaku Harithaharam projects
2.0 1.0 1.0 -- -- 4.0
Total 5.0 2.0 1.5 0.5 0.5 9.5
M/s. Devashree Ispat (P) Ltd Unit I Draft EIA Report
10-27
Pridhvi Envirotech (P) Ltd.
10.18 ENVIRONMENTAL MANAGEMENT BUDGET
The environmental budget of Rs. 0.75 Crores is allocated for the various
environmental management measures proposed in the EMP is detailed in
table 8.4 there are several other environmental issues that have been
addressed as part of good engineering practices, the costs for which has
been accounted for in the Engineering Costs & presented in the table
below.
Table 10.7 Environmental Budgets for Project
S.No Description Capital Cost in
Rs. Lakhs
Recurring Cost in Rs.
Lakhs/Annum
1 Air Pollution Control Establishment of bag
filter for furnace
36.0 6.0
2 Water Pollution Control Primary treatment plant
of mill cooling water
10.0 2.0
3
Storm Water
management & Rain water harvesting
structures
5.0 1.0
4 Solid Waste Management & dust
prevention measures
4.0 1.0
5 Noise Pollution Control 3.0 1.0
6
Environmental
Monitoring & Management
-- 2.5
7 Occupational health 3.0 1.0
8 Fire Safety 11.0 1.0
9 Green belt & open area
development 3.0 3.0
Total 75.0 19.0
Chapter – 11
PROJECT SUMMARY AND
CONCLUSIONS
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
11-1
Pridhvi Envirotech (P) Ltd.
CHAPTER - 11
PROJECT SUMMARY AND CONCLUSIONS
M/s. Devashree Ispat (P) Ltd Unit-I situated near Shadnagar – Pargi Road,
at Sy.Nos:458, 459 and 460, Ellikatta (Vil), Farooq Nagar (M), Rangareddy
District (Formerly Mahaboobnagar District), Telangana State is
manufacturing Thermo Mechanically Treated (TMT) Bars in their plant
spread over 10.62 Ac.
Now the project proposes to expand the production capacity by upgrading
the capacities of Induction Furnace from 100 TPD to 200 TPD and that of
the Rolling Mill from 300 TPD to 800 TPD, for increasing the production
capacity of MS Billets from current level of 30,000 TPA to 70,000 TPA &
TMT Bars from 90,000 TPA to 2,80,000 TPA.
Overall Environmental Impacts
The proposed expansion activity primarily create impact on air environment
due to emissions from induction furnaces, Re-heating furnace and
additional DG sets. The water requirements of the project need to be met
through private tankers, and it can create a depletion of natural ground
water resources. Both these aspects are adequately addressed in
environmental management plan. As a part of this project, additional green
belt of 0.54 acres is proposed in the EMP plan. Various other measures of
handling of wastes, occupational health & Safety, Fire safety measures are
incorporated in the EMP. Total Budget for implementation of EMP is
estimated at Rs. 75 lakhs with recurring expenditure of Rs. 19 lakhs.
Conclusions
Industrialization is most essential for our country and society as it creates
employment and revenue. There is gap between demand and supply of
Steel in the country which is most essential input for infrastructure
development. Next 10 years will see rapid growth in this sector and
proposed expansion of M/s. Devashree Ispat (P) Ltd Unit-I will help to meet
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
11-2
Pridhvi Envirotech (P) Ltd.
the demand within the country. This will support the concept of Make in
India.
Out of the total investment for expansion of Rs. 5.75 crores, Rs.0.75 Crores
is proposed to implement the EMP plan which is about 13.04% of overall
investment of expansion. There will be an additional direct and indirect
employment for 120 people from the expansion activities thus by helps un-
employed youth to get livelihood from the project.
Apart from this an amount of Rs. 9.5 Lakhs proposed to be allotted for
corporate Environmental responsibility activities over next 5 years period in
the nearby village .
As adequate safeguards are proposed to tackle any adverse environmental
impacts from the project supported by budget commitments in the project,
this project is viable financially and sustainable from environment point of
view.
Chapter- 12
DISCLOSURE OF CONSULTANTS
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
12-1
Pridhvi Envirotech (P) Ltd.
CHAPTER - 12
DISCLOSURE OF CONSULTANTS
Name of the project : M/s. Devashree Ispat (P) Ltd Unit-I
Environmental coordinator : Mr. P.Venkata Raju
EIA Consultant Organization : Pridhvi Envirotech (P) Limited
Contact Information : # 184/C, 4th Floor, Lawn house,
Vengalrao Nagar, Hyderabad-500038
Phone : 040-40179770, 9849023662
E-mail : [email protected]
Website : www.pridhvienviro.com
Status of Accreditation with
QCI/NABET
: S.No 119, List of Accredited EIA
Consultant Organizations (Alphabetically)
/ Rev.66A, 15thJune 2018, published by QCI/NABET
Laboratory Engaged in EIA Project
: Lawn Enviro Associates
Status of Laboratory : MoEF Accreditation S.O.857(E), dated
26th February 2018
Company Profile
PridhviEnvirotech (P) Limited was established by professionals in the field of
environment with nearly 25 years of experience with clear vision to serve
customers in the field of environment.
Accredited by National Accreditation Board for Education and Training
(NABET) under Quality Council of India as consultant for preparation of
Environmental Impact Assessments for new and existing industries,
PridhviEnvirotech (P) Limited provides the following services
Provide complete and one stop consultancy to get Environmental
clearances from MOEF and Pollution Control Board for proposed and
changed products
Provide complete assistance to industry by conducting legal gap
analysis and advise actions to be taken
Conduct EIA and EMP reports
Provide assistance to industries to prepare and get CFE/CFO from
Pollution control Board
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
12-2
Pridhvi Envirotech (P) Ltd.
Periodical monitoring of effluents/emissions/Hazardous Wastes from
MOEF approved laboratory
Provide assistance to industries to help them in case of legal hearings
and submission of technical replies in case of any legal notices
Provide liaison services to industries with PCB on any matter
Provide consultancy services in the area of implementation of ISO
14001 systems and OHSAS 18001
Provide consultancy services in design and execution of effluent
treatment plants
Provide consultancy services in hazardous waste handling and
disposal services
Waste mapping and audits and provide solutions for waste reduction
Provide training to personnel on environment and safety management
systems, legal requirements and other host of environmental ,
occupational Health and Safety issues
EIA Team members involved in the preparation of the EIA
Approved FAEs
S.No Name of the FAE Area of Expertise
1 P.V.Raju Environmental coordinator AQ/SHW
2 Dr.G.Pallavi WP
3 K.Santhosh LU
4 Dr.M.Veranna GEO/HG
5 P. Sivunnaidu SE
6 M. Raju AP
7 Ch. Chiranjeevi NV
8 I.SivaramaKrishna EB
9 G.Ramaswamy Reddy EB
10 K.Raji Reddy RH
Team Members
11 I.Radha Krishna Murthy Environmental
co-ordinator
12 Dr. G.Pallavi EB
13 R. Krishna Chaitanya SHW/WP/AQ
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
12-3
Pridhvi Envirotech (P) Ltd.
Declaration by the head of the Accredited Consultant Organization
I, P. Venkata Raju, hereby confirm that the above mentioned experts
prepared the EIA of “M/s. Devashree Ispat(P)Ltd Unit-I ”, I also confirm
that I shall be fully accountable for any misleading information mentioned
in this statement.
Name : P. Venkata Raju
Designation : Managing Director
M/s. Devashree Ispat (P) Ltd Unit-I Draft EIA Report
12-4
Pridhvi Envirotech (P) Ltd.
ANNEXUIRE –I
M/s. Devashree Ispat (P) Ltd Ambien t Air Quality Data
Location: Project site(AAQ1)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
4.12.2017 83.8 44.6 13.2 20.5 2
5.12.2017 80.3 39.2 13.5 19.4 2.1
11.12.2017 85.6 40.3 14.6 21 1.6
12.12.2017 83.2 41.4 12.4 20.3 2
18.12.2017 78.2 39.6 15.3 18.3 2.1
19.12.2017 75.4 40.2 16.2 17.4 1.7
25.12.2017 80.5 37.8 13.2 20.8 1.4
26.12.2017 77.2 41.3 12.4 17.4 1.5
2.1.2018 70.3 37.6 13.2 19.5 1.3
3.1.2018 79.2 40.2 15.2 18.5 2.2
9.1.2018 81.3 34.2 13.5 20.2 1.9
10.1.2018 82.5 40.2 15.2 17.3 2.2
16.1.2018 80.5 36.3 12.4 20.5 1.9
17.1.2018 79.2 41.2 14.5 21.4 1.7
23.1.2018 75.2 35.6 12.4 20.3 1.3
24.1.2018 69.3 30.4 11.6 18.4 1.5
5.2.2018 70.2 34.2 12.4 20.3 1.6
6.2.2018 72.3 37.3 13.5 17.4 1.9
12.2.2018 70.4 34.5 11.4 14.2 2.1
13.2.2018 72.1 38.7 12.7 15.8 1.7
19.2.2018 74.3 34.5 14.2 16.2 2.1
20.2.2018 72.5 36.2 15.1 18.5 1.8
26.2.2018 72.3 36.2 13.6 16.2 1.5
27.2.2017 82.3 32.5 16.2 17.4 2
Max 85.6 44.6 16.2 21.4 2.2
min 69.3 30.4 11.4 14.2 1.3
mean 77.0 37.7 13.7 18.6 1.8
98% 84.8 43.1 16.2 21.2 2.2
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Elikatta (AAQ2)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
4.12.2017 73.5 30.2 11.4 16.3 1.5
5.12.2017 69.3 27.4 10.5 17.3 1.3
11.12.2017 67.3 26.2 12.4 16.2 1.3
12.12.2017 70.3 30.2 13.2 15.3 1.1
18.12.2017 64.3 29.4 11.3 16.3 1.3
19.12.2017 62.3 28.4 12.4 14.2 1.4
25.12.2017 60.8 26.2 11.4 15.2 2.2
26.12.2017 69.1 27.4 10.4 13.5 1.4
2.1.2018 65.3 24.3 10.3 14.5 1.2
3.1.2018 62.3 26.3 12.4 16.3 1
9.1.2018 58.3 25.3 11.2 18.3 1.1
10.1.2018 67.2 23.5 10.4 14.1 1.4
16.1.2018 62.3 25.7 11.5 15.3 1.2
17.1.2018 59.2 26.7 13.2 18.3 1.3
23.1.2018 60.4 26.3 12.4 18.3 1.4
24.1.2018 54.2 25.2 14.2 14.2 1.2
5.2.2018 60.1 24.3 12.8 15.2 1.1
6.2.2018 57.2 23.2 12.3 13.9 1.1
12.2.2018 62.4 21.5 11.7 15.3 1.3
13.2.2018 58.2 23.5 13.2 12.3 1.3
19.2.2018 54.2 19.5 15.2 15.2 1.2
20.2.2018 57.2 20.4 11.2 13.2 1.4
26.2.2018 60.2 21.3 12.4 15.2 1.2
27.2.2017 58.2 19.4 10.7 13.1 1.1
Max 73.5 30.2 15.2 18.3 2.2
min 54.2 19.4 10.3 12.3 1.0
mean 62.2 25.1 12.0 15.3 1.3
98% 72.0 30.2 14.7 18.3 1.9
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Rangampalli(AAQ3)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
4.12.2017 64.3 24.3 13.5 16.3 1.3
5.12.2017 59.2 22.4 14.2 14.2 1.1
11.12.2017 62.3 25.3 15.2 13.5 1.2
12.12.2017 57.3 19.8 12.3 14.2 1.4
18.12.2017 62.1 23.2 10.6 15.2 1.1
19.12.2017 58.3 28.4 15.2 15.2 1.3
25.12.2017 61.4 29.4 12.3 13.2 1.1
26.12.2017 63.2 30.5 10.4 14.2 1
2.1.2018 60.6 28.3 9.8 16.3 1.4
3.1.2018 59.8 21.2 11.4 13.4 1.2
9.1.2018 57.3 19.4 10.2 14.6 1.3
10.1.2018 61.4 20.2 11.5 15.2 1.4
16.1.2018 58.9 21.5 12.5 14.2 1.2
17.1.2018 61.2 20.5 10.7 16.2 1.2
23.1.2018 59.8 18.5 11.3 13.5 1.1
24.1.2018 57.2 20.6 10.7 14.2 1.4
5.2.2018 54.3 21.4 12.4 15.2 1.2
6.2.2018 60.3 19.5 10.5 16.7 1.3
12.2.2018 57.4 17.4 11.4 15.2 1.2
13.2.2018 63.2 19.4 13.2 13.6 1.2
19.2.2018 61.2 20.4 12.4 15.2 1.1
20.2.2018 63.2 21.4 10.5 14.3 1.2
26.2.2018 58.5 20.6 11.4 17.3 1.2
27.2.2017 61.3 21.4 10.7 15.2 1.3
Max 64.3 30.5 15.2 17.3 1.4
min 54.3 17.4 9.8 13.2 1.0
mean 60.2 22.3 11.8 14.8 1.2
98% 63.8 30.0 15.2 17.0 1.4
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Chaulapalli (AAQ4)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
4.12.2017 65.2 26.7 13.5 13.5 1.2
5.12.2017 67.2 21.4 14.2 14.2 1.3
11.12.2017 63.4 24.6 11.3 15.2 1.1
12.12.2017 58.3 27.4 12.4 17.3 1
18.12.2017 56.4 23.5 10.6 14.2 1.1
19.12.2017 52.3 20.7 13.2 13.9 1.2
25.12.2017 50.8 26.4 15.2 14.2 1.4
26.12.2017 56.3 23.5 14.2 12.5 1.2
2.1.2018 50.6 24.2 13.2 11.6 1.2
3.1.2018 52.3 25.2 14.2 12.6 1
9.1.2018 52.3 27.3 12.4 15.2 1.3
10.1.2018 54.6 23.2 11.3 14.2 1.2
16.1.2018 55.6 22.6 14.7 16.3 1.2
17.1.2018 52.5 19.5 13.2 14.3 1.3
23.1.2018 55.7 20.3 11.5 12.6 1.4
24.1.2018 56.7 21.4 13.2 15.1 1.1
5.2.2018 53.4 18.4 12.4 13.2 1.3
6.2.2018 60.4 23.2 12.4 14.1 1.2
12.2.2018 61.3 22.5 10.3 13.5 1.2
13.2.2018 52.3 20.6 13.2 14.2 1.3
19.2.2018 55.4 23.3 10.4 12.8 1.3
20.2.2018 58.4 21.2 14.2 13.2 1.1
26.2.2018 57.5 20.6 12.4 11.4 1.4
27.2.2017 54.3 21.5 12.3 13.2 1.2
Max 67.2 27.4 15.2 17.3 1.4
min 50.6 18.4 10.3 11.4 1.0
mean 56.4 22.9 12.7 13.9 1.2
98% 66.3 27.4 15.0 16.8 1.4
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Mughalgidda(AAQ5)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
6.12.2017 65.3 23.4 11.4 17.3 1.3
7.12.2017 58.3 26.3 13.2 15.2 1.5
13.12.2017 55.3 22.2 15.2 14.2 1.7
14.12.2017 45.3 26.3 12.4 16.2 1.3
20.12.2017 53.5 21.5 11.9 18.3 1.7
21.12.2017 55.3 19.5 10.6 15.2 1.5
27.12.2017 57.5 23.5 11.4 13.7 1.3
28.12.2017 58.5 26.3 12.5 15.2 1.7
5.1.2018 53.2 22.4 13.2 15.2 1.4
6.1.2018 58.5 20.5 10.4 16.2 1.2
12.1.2018 61.2 23.5 12.5 14.2 1.3
13.1.2018 58.3 27.4 15.2 15.2 1.4
19.1.2018 60.3 19.4 11.5 16.3 1.5
20.1.2018 57.3 23.2 12.6 17.2 1.3
26.1.2018 53.2 21.3 13.2 14.2 1.1
27.1.2018 51.2 20.5 14.6 15.2 1.5
7.2.2018 49.2 22.4 12.5 14.2 1.4
8.2.2018 51.2 26.2 13.7 15.2 1.2
14.2.2018 50.3 23.5 11.9 16.2 1.2
15.2.2018 52.1 22.4 12.4 15.2 1.2
21.2.2018 52.5 20.6 13.6 13.9 1.1
22.2.2018 49.2 21.4 12.5 14.2 1.4
27.2.2018 50.2 24.2 14.2 12.5 1.2
28.2.2018 55.3 25.3 11.7 15.2 1.1
Max 65.3 27.4 15.2 18.3 1.7
min 45.3 19.4 10.4 12.5 1.1
mean 54.7 23.1 12.7 15.2 1.3
98% 63.4 26.9 15.2 17.8 1.7
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Antanam (AAQ6)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
6.12.2017 62.3 23.4 13.54 16.1 1.2
7.12.2017 60.2 21.2 14.2 15.2 1.2
13.12.2017 59.3 19.6 12.5 13.5 1.3
14.12.2017 60.3 22.5 12.4 14.2 1.4
20.12.2017 58.3 21.4 10.9 16.2 1.2
21.12.2017 52.3 18.7 12.2 14.2 1.1
27.12.2017 55.7 21.5 11.4 13.2 1.5
28.12.2017 54.2 22.4 12.5 14.7 1.2
5.1.2018 57.3 24.5 14.3 17.3 1.2
6.1.2018 53.4 28.4 12.6 14.2 1.4
12.1.2018 56.7 18.9 11.8 13.7 1.3
13.1.2018 53.4 21.2 12.4 16.2 1.3
19.1.2018 55.6 19.3 15.2 14.6 1.1
20.1.2018 53.4 21.3 12.5 15.2 1.5
26.1.2018 52.3 22.5 14.2 16.3 1.6
27.1.2018 52.4 23.1 13.2 14.3 1.2
7.2.2018 50.2 22.6 15.2 15.7 1.4
8.2.2018 51.2 24.2 13.2 13.5 1.5
14.2.2018 50.3 25.2 12.6 15.7 1.3
15.2.2018 52.3 21.4 12.4 14.6 1.2
21.2.2018 50.3 24.3 10.5 16.2 1.5
22.2.2018 51.3 26.2 13.2 13.6 1.2
27.2.2018 53.2 21.4 12.4 14.8 1
28.2.2018 55.2 22.5 13.6 15.2 1.1
Max 62.3 28.4 15.2 17.3 1.6
min 50.2 18.7 10.5 13.2 1.0
mean 54.6 22.4 12.9 14.9 1.3
98% 61.4 27.4 15.2 16.8 1.6
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Shadnagar(AAQ7)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
6.12.2017 63.2 19.5 12.3 17.2 1.4
7.12.2017 59.3 21.2 10.5 15.2 1.1
13.12.2017 57 20.6 11.4 14.2 2
14.12.2017 54.3 18.4 11.4 15.3 2.1
20.12.2017 50.3 19.5 12 13.2 2.1
21.12.2017 51.5 20.4 10.6 15.3 2.4
27.12.2017 52.3 22.4 13.2 14.6 2.3
28.12.2017 53.4 23.2 11.3 15.2 1.9
5.1.2018 49.7 22.6 12.4 13.7 2
6.1.2018 51.3 20.6 11.5 12.5 1.8
12.1.2018 52.3 18.4 13.5 15.2 2.2
13.1.2018 54.6 21.4 10.8 14.6 1.9
19.1.2018 57.4 26.4 12.4 14.2 0.18
20.1.2018 52.3 21.4 13.2 17.2 1.3
26.1.2018 54.3 20.5 12.5 14.2 1.7
27.1.2018 53.2 23.4 14.3 12.5 2.1
7.2.2018 49.6 21.4 12.4 14.6 2.2
8.2.2018 50.3 20.5 13.6 15.2 1.9
14.2.2018 52.3 19.5 12.4 13.5 2.1
15.2.2018 53.2 22.3 12.7 16.1 2.3
21.2.2018 60.2 24.2 14.2 14.5 2.4
22.2.2018 53.4 25.2 12.4 15.1 1.8
27.2.2018 51.2 19.4 14.6 15.2 1.6
28.2.2018 57.4 18.3 12.4 13.6 1.4
Max 63.2 26.4 14.6 17.2 2.4
min 49.6 18.3 10.5 12.5 0.2
mean 53.9 21.3 12.4 14.7 1.8
98% 61.8 25.8 14.5 17.2 2.4
M/s. Devashree Ispat (P) Ltd
Ambien t Air Quality Data
Location: Pidkiryla(AAQ8)
PM10
(µg/m3)
PM 2.5
( µg/m3)
SO2
( µg/m3)
NOx
(µg/m3)
CO
(ppm)
6.12.2017 58.3 22.3 13.5 16.3 1.4
7.12.2017 52.3 20.4 14.2 14.2 1.3
13.12.2017 50.3 18.9 13.2 13.6 1.3
14.12.2017 52.3 22.3 14.2 16.3 1.3
20.12.2017 53.6 20.4 12.4 11.2 1.5
21.12.2017 51.4 23.4 12.5 12.7 1.3
27.12.2017 58.3 19.4 13.2 17.3 1.9
28.12.2017 54.3 19.3 10.2 14.2 1.3
5.1.2018 60.2 20.4 9.4 12.4 1.4
6.1.2018 58.4 21.4 10 16.3 1.5
12.1.2018 52.3 20.5 9.5 16.3 1.3
13.1.2018 50.6 21.4 11.2 15.3 1.3
19.1.2018 49.3 23.5 12.3 14.7 1.4
20.1.2018 52.3 19.3 10.6 14.2 1.6
26.1.2018 53.6 18.6 10.3 13.8 1.3
27.1.2018 50.6 19.5 12.4 12.5 1.2
7.2.2018 51.4 20.4 11.4 14.2 1.5
8.2.2018 49.5 18.4 10.5 16.2 1.2
14.2.2018 50.2 20.5 11.2 13.6 1.3
15.2.2018 51.4 16.3 10.8 13.2 1.2
21.2.2018 53.2 16.3 13.2 13.5 1.4
22.2.2018 55.7 16.3 13.2 15.2 1.3
27.2.2018 50.7 22.4 10.7 15.2 1
28.2.2018 51.4 19.3 11.3 13.6 1.1
Max 60.2 23.5 14.2 17.3 1.9
min 49.3 16.3 9.4 11.2 1.0
mean 53.0 20.0 11.7 14.4 1.3
98% 59.4 23.5 14.2 16.8 1.8
ANNEXUIRE –II
SEIA study of M/s Devashree Ispat (P) Ltd Unit-I, at Sy. Nos- 458, 459 and 460, Ellikatta (Vi), Farooq Nagar (M), Rangareddy District, Telangana State
VITAL STATISTICS OF SURVEY VILLAGESAS PER CENSUS – 2011
Sl. No.
Category/ Area
Name
Mandal Locational
Direction
from Proje
ct Site
Distance from
Project Site
(Km Aerial)
Total House
Holdes
Total Populat
ion
Males Females
SC ST Average
Literacy
(%)
Villageswithin 0-2 Km Distance from the Site
1
Maleellik
atta
Farooqn
agar SE 0.6Km Under Elikatta Revenue Population Data is Same
2 Elikatta
Farooqn
agar E 0.87 Km 665 2806 1365 1441 437 21 48.8
3
Rangamp
alle
Farooqn
agar SW 1.4 Km Under Mogalgidda Revenue Population Data is Same
Sub Total - I 665 2806 1365 1441 437 21 48.8
Villages in 2-5 Km Distance from the Site
4
Kurvagu
dem Shabad N 2.5 Km Under Hajipalle Revenue Population Data is Same
5
Pallagad
daTanda
Farooqn
agar SW 2.5 Km Under Kishannagar Revenue Population Data is Same
6 Mogalgid Farooqn NW 2.6 Km 1044 4778 2379 2399 630 15 56.6
da agar
7
Mahama
dallguda
Farooqn
agar NE 2.6 Km Under Farooq Nagar Revenue Population Data is Same
8
Sardarna
gar Shabad NE 2.7 Km Under Hajipalle Revenue Population Data is Same
9
Kishanna
gar
Farooqn
agar SE 3.0 Km 893 3784 1884 1900 814 912 49.7
10
Bapanna
guttaTan
da
Farooqn
agar SE 3.3 Km Under Kishannagar Revenue Population Data is Same
11 Kakloor Shabad NE 3.4 Km 1151 4954 2511 2443 1036 5 57.2
12
Errabirdg
aTanda
Farooqn
agar SW 3.4 Km Under Kishannagar Revenue Population Data is Same
13
Rangedh
am
Farooqn
agar NW 3.7 Km Under Mogalgidda Revenue Population Data is Same
14
Rangasa
mudram
(Yellamp
alle)
Farooqn
agar NW 4.0 Km 172 776 393 383 80 0 50.8
15 Hajipalle
Farooqn
agar SE 4.2 Km 188 795 390 405 215 0 56.7
16
Duntikun
ta
Farooqn
agar SW 4.6 Km Under Kandivanam Revenue Population Data is Same
17
Chowlap
alle
Farooqn
agar SW 4.6 Km 661 2950 1517 1433 366 706 56.3
18
Bodampa
hed Shabad NW 4.6 Km Under Manmarri Revenue Population Data is Same
19
Rasumall
agudem(
Mhamad
Farooqn
agar NE 4.8 Km Under Elikatta Revenue Population Data is Same
haliguda)
20
Farooqna
gar
(Shadna
gar)
Farooqn
agar E 5.0 Km 10328 45675 23328 22347 2840 1081 70.6
21
Allisabgu
da
Farooqn
agar NW 5.0 Km 168 619 319 300 246 0 63.8
Sub Total - II 14605 64331 32721 31610 6227 2719 66.1
Villages in 5-10 Km Distance from the Site
22
Anantha
waram Shabad N 5.1 Km 250 1085 541 544 460 0 52.7
23
Appared
diguda Shabad NW 5.4 Km Under Manmarri Revenue Population Data is Same
24
Perlagud
a
Farooqna
gar SW 5.7 Km Under Chowlapalle Revenue Population Data is Same
25
Pullappa
guda Kondurg SW 5.7 Km Under Chinnayelkicherla Revenue Population Data is Same
26
Doddigad
daTanda
Farooqna
gar SE 6.0 Km Under Kishannagar Revenue Population Data is Same
27
Patelkunt
a
Farooqna
gar SW 6.0 Km Under Chinchode Revenue Population Data is Same
28
Nagulapa
lle
Farooqna
gar NE 6.2 Km 536 2088 1057 1031 676 6 52.6
29 Vittyal
Farooqna
gar S 6.2 Km 452 1970 981 989 335 472 40.6
30
Kummari
guda
Farooqna
gar SW 6.3 Km Under Bheemaram Revenue Population Data is Same
31 Manmarri Shabad NW 6.4 Km 866 3758 1915 1843 708 0 53.1
32
Chinnaye
lkicherla Kondurg SW 6.6 Km 373 1693 858 835 257 743 38.5
33
PeddaYel
kicherla Kondurg W 6.7 Km 985 4674 2283 2391 997 650 42.1
34 Annaram
Farooqna
gar SE 6.7 Km 384 1616 827 789 391 295 53.0
35
Kesavara
m Shabad NE 6.8 Km 251 1100 563 537 80 47 53.2
36
Kandivan
am
Farooqna
gar SW 6.8 Km 293 1317 684 633 195 267 48.4
37
Sriranga
pur Kondurg NW 6.9 Km 216 905 464 441 240 0 46.9
38
Rangapu
r Shabad NE 7.0 Km 3 15 7 8 0 0 13.3
39
Ramesh
waram
Farooqna
gar SE 7.2 Km Under Chilkamarri (Chelka) Revenue Population Data is Same
40
Devunipa
lli
Farooqna
gar SW 7.1 Km Under Bheemaram Revenue Population Data is Same
41
Nareddig
uda Shabad N 7.2 Km Under Shabad Revenue Population Data is Same
42
Chinchod
e
Farooqna
gar SW 7.2 Km 1322 5445 2787 2658 858 924 43.3
43
Gollagud
a
Farooqna
gar SE 7.3 Km Under Annaram Revenue Population Data is Same
44
Llgonddg
uda Shabad NW 7.3 Km
Under Shabad Revenue Population Data is Same 45
Mirampu
r Shabad NW 7.4 Km
46 Kaziguda
Farooqna
gar SE 7.8 Km Under Annaram Revenue Population Data is Same
47 Solipur
Farooqna
gar SE 7.9 Km 419 1778 899 879 325 129 60.5
48
Venkatre
ddipalli
Farooqna
gar SW 8.0 Km Under Kamsanpalle Revenue Population Data is Same
49
Kamsanp
alle
Farooqna
gar SW 8.1 Km 608 2705 1405 1300 406 642 36.8
50
Edulapall
e Nandigam NE 8.1 Km 320 1467 761 706 458 9 47.6
51
Chattanp
alle
Farooqna
gar SE 8.2 Km 1665 6978 3486 3492 1110 536 60.6
52
Rangare
ddiguda
Farooqna
gar SW 8.2 Km Under Bheemaram Revenue Population Data is Same
53
Lingared
dyguda
Farooqna
gar NE 8.3 Km Under Chattanpalle Revenue Population Data is Same
54
Ramchan
drapur Kondurg NW 8.4 Km Under Mahadevpoor Revenue Population Data is Same
55
Jogamm
aguda
Farooqna
gar SE 8.6 Km 141 578 293 285 10 149 41.5
56
Mahadev
poor Kondurg NW 8.7 Km 367 1551 770 781 541 16 50.2
57
Pulsomar
di Kondurg W 8.7 Km Under Mahadevpoor Revenue Population Data is Same
58
Angoligu
ndlaTand
a
Farooqna
gar SW 8.8 Km Under Bheemaram Revenue Population Data is Same
59
Bhiramp
alle Kondurg NW 8.8 Km 216 915 473 442 260 30 37.9
60 Raikal
Farooqna
gar SE 8.9 Km 478 2170 1139 1031 504 357 53.3
61
Parvatha
pur Kondurg SW 9.0 Km 272 1109 546 563 180 0 49.4
62 Ayyawar Farooqna SW 9.0 Km Under Bheemaram Revenue Population Data is Same
upalli gar
63
Cherlagu
da Shabad NW 9.0 Km Under Shabad Revenue Population Data is Same
64
Srinivasu
laguda Nandigam NE 9.1 Km Under Mamidipalle Revenue Population Data is Same
65
Kummari
guda Shabad N 9.1 Km Under Shabad Revenue Population Data is Same
66
Antaredd
iguda Nandigam NE 9.2 Km Under Mamidipalle Revenue Population Data is Same
67
Patelgud
am Shabad N 9.4 Km Under Shabad Revenue Population Data is Same
68 Shabad Shabad N 9.4 Km 3511 14927 7614 7313 3596 196 54.4
69
Nasisaba
d Nandigam NE 9.4 Km Under Mamidipalle Revenue Population Data is Same
70
Motighan
puram Balanagar SE 9.5 Km 1002 4367 2276 2091 565 1395 40.1
71
Chilkama
rri
(Chelka)
Farooqna
gar SE 9.6 Km 425 1680 847 833 231 13 49.4
72
Mamidip
alle Nandigam NE 9.6 Km 870 3687 1854 1833 753 13 52.5
73
Gangadh
arPalli Balanagar SE 9.8 Km Under Motighanpuram Revenue Population Data is Same
74
Masjid
Mamidip
alli Nandigam NE 9.8 Km Under Mamidipalle Revenue Population Data is Same
75
Bheemar
am
Farooqna
gar SW 9.9 Km 285 1365 696 669 206 519 44.5
Sub Total - III 16510 70943 36026 34917 14342 7408 49.7
Grand Total 31780 138080 70112 67968 21006 10148 57.3
Source : 2011 Census Data
NA: Data Not Available separately as the habitation/village is not a census unit.
ANNEXUIRE –III
LIST OF FAUNA & THEIR CONSERVATION STATUS
Checklist of Mammalian species in the Study Area
(* indicates Primary data)
Scientific Name Common Name Family I - WPA
Funambuluspalmarum Three striped palm squirrel*
Sciuridae
Bendicotabengalensis Indian mole rat Muridae
Bendicotaindica Bandicoot rat Muridae
Mus booduga Little Indian Field
mouse
Muridae
Mus musculus House Mouse Muridae
Rattusrattus House rat Muridae
Herpestesjavanicus Common Indian Mongoose*
Herpestidae Schedule II Part II
Mucacamulata* Common Langur LC Part-II of
sch-II
List of AVES either spotted or reported or recorded from the study
area. (* indicates Primary data)
Technical Name Local name I - WPA
Acridotherestristicus Common myna* Sch-IV
Aegithinatiphia Iora Sch-IV
Alcedoatthis Common Kingfisher Sch-IV
Anasacuta Common Teal Sch-IV
Bubulcus ibis Cattle Egret* Sch-IV
Columbus livibus Rock Pigeon* Sch-IV
Corvuscorvus Jungle crow Sch-IV
Corvussplendens House crow* Sch-V
Egrettagarzetta Little Egret Sch-IV
Eudynamisscolopaceus Koel Sch-IV
Gallinulachlorpus Moore hen* Sch-IV
Gallus gallus Red Jungle fowl Sch-IV
Haliasturindus Brahmny kite Sch-IV
Hierococysvarius Common Hawk Cuckoo Sch-IV
Lobvanellaindicus Redwattled Lapwing* Sch-IV
Megalaimamerulinus Indian Cuckoo Sch-IV
Meropsleschenaulti Chestnut headed Bee
Eater*
Sch-IV
Meropsorinetalis Common Bee Eater* Sch-IV
Milvus migrans Pariah kite Sch-IV
Milyusmigrans Common Kite* Sch-IV
Technical Name Local name I - WPA
Motacillacinerea Grey wagtail* Sch-IV
Motacillamaderaspatens
is
Large pied wagtail Sch-IV
Oriolusoriolus Indian Oriole* Sch-IV
Oriolusxanthornus Black Headed Oriole Sch-IV
Passer domisticus House Sparrow* Sch-IV
Temenuchuspagodarum Brahmny Myna* Sch-IV
Tephrodornisondiceraia
nus
Common Wood shrike Sch-IV
Turdoidesstriatus White headed babler* Sch-IV
Bayabaya Golden sparrow Sch-IV
List of Reptiles either spotted or reported from the study area. (*
indicates Primary data)
S. Scientific Name Common Name IUCN IWP
1. Ahaetullanasutus Green whip snake LC
2. Najanaja Indian Cobra LC II
3. Viperarusselli Russel Viper LR II
4. Dendrelaphistristis Tree Snake LC
5. Ptyasmucosus Common Rat snake LC II
6. Amphiesmastolata Buffstripedkeelback LC
7. Trimeresurusgramineu Green pit viper LC IV
8. Typhlopshypomethes Common blind snake LC IV
9. Enhydrisenhydris Common Smooth Water LC
10. Varanusbengalensis Common Indian monitor LR II
11. Chamaeleon zelanicus Chameleon* VU II
12. Mabuyacarinata Common Skink* LC
13. Calotesrouxi Forest Calottes* LC
14. Calotes versicolor Common garden lizard* LC
15. Hemimidactylusbrooki House gecko* LC
16. Hemidactylusforenatu Southern House Gecko LC
List of Amphibians either spotted or reported from the study area.
S. Scientific Name Common Name IUCN IWPA
1. Bufomelanosticus Common toad LC Sch-IV
2. Rana hexadactyla Commn green LC Sch-IV
3. Rana leptodactyla Small forg LC Sch-IV
4. Rana tigrina Bullfrog LC Sch-IV
5. Rhacophorus Common Tree LC Sch-IV
List of Butterflies either spotted or reported from the study area.
(* indicates Primary data)
Scientific Name Common Name Status
Acraea violae Tawny Coster*
Danauschrysippuschrysippus Plain Tiger *
Danausgenutiagenutia Striped Tiger*
Euploea core core Common Crow* Sch- IV
Phalantaphalanthaphalantha Common Leopard*
Precis lemoniaslemonias Lemon Pansy*
Precis orithyaocyale Blue Pansy *
Chiladeslaius Lime Blue*
Evereslacturnussyntala Indian Cupid *
Freyeriatrochylus Grass Jewel*
Jamidescelenoaelianus Common Cerulean *
TarucusnaraKollar Rounded Pierrot*
Colotisetrida Small or Little Orange Tip*
Colotis eucharis eucharis Plain Orange Tip*
Catopsiliapomona Common Emigrant*
Euremahecabesimulata Common Grass Yellow*
Papiliodemoleus Lime Butterfly*
Papiliopolytespolytes Common Mormon*
Papiliopolytesstichius Common Mormon *
List of fishes either spotted or reported from the study area. LC
means Least Concern (list taken from secondary data)
S.No Scientific Name Family IUCN Status
1 Clariasbatrachus Clariidae LC
2 Osteobramacotio Cyprinidae LC
3 Labeorohita Cyprinidae LC
4 Chela laubuca Cyprinidae LC
5 Salmostomabacaila Cyprinidae LC
6 Chela cachius Cyprinidae LC
7 Amblypharyngodonmola Cyprinidae LC
8 Tor mussulah Cyprinidae LC
9 Rohteeogilbii Cyprinidae LC
10 Puntius filamentosus Cyprinidae LC
11 Cirrhinusfulungee Cyprinidae LC
12 Cirrhinusreba Cyprinidae LC
13 Catlacatla Cyprinidae LC
14 Garramullya Cyprinidae LC
15 Crossocheiluslatius Cyprinidae LC
16 Notopterusnotopterus Notopteridae LC
17 Pangasiuspangasius Pangasiidae LC
18 Wallago attu Siluridae LC
19 Ompokbimaculatus Siluridae LC
20 Nangraitchkeea Sisoridae LC
21 Bagariusbagarius Sisoridae LC
22 Glyptothoraxlonah Sisoridae LC