new energy for growing communities - ecofys … energy for growing communities 7 preface the...
TRANSCRIPT
Almere
Ajaccio
Viladecans
Milton Keynes
New energy for growing communitiesThe cRRescendo sustainable building project
Read how leading EU municipalities made a significant step towards zero-carbon urban communities in turbulent economic times.
Emil ter Horst, Caspar Noach, Leendert Verhoef and Vera Haaksma
Almere
Ajaccio
Viladecans
Milton Keynes
New energy for growing communitiesThe cRRescendo sustainable building project
Emil ter Horst, Caspar Noach, Leendert Verhoef and Vera Haaksma
2
Almere
Ajaccio
Viladecans
Milton Keynes
New energy for growing communitiesThe cRRescendo sustainable building project
Emil ter Horst, Caspar Noach, Leendert Verhoef and Vera Haaksma
ISBN 9789082257601 | Horisun, Utrecht
Download: www.cRRescendo.net or www.horisun.com
4 cRRescendo
EC CONCERTO programme
cRRescendo is the largest sustainable building project,
that has been supported by the CONCERTO programme
of the European Union.
In a fast moving and developing modern world, energy
is a core factor of our daily life. We have become
dependent on the availability of energy, which has to
be produced in a sustainable and efficient manner.
The CONCERTO programme has supported local
communities in demonstrating actions that are both
sustainable and energy efficient. Increasing the use
of renewable energy sources and promoting energy
efficiency is not an easy task. The CONCERTO projects
aim to demonstrate the breakthroughs that can
be achieved by a fully integrated approach in high
performing communities.
The goals of CONCERTO (2005, 2007, 2010) were to
inspire an innovative energy policy on a European
level and to contribute towards creating an energy
independent Europe based on a vision of environmental,
social and economic sustainability. Now (2014) the
Smart Cities & Communities calls within Europe’s new
HORIZON2020 programme succeed the successful
CONCERTO programme. Having a closer look though
at the cRRescendo projects especially in Almere and
Milton Keynes, we see that CONCERTO has indeed
inspired these cities to compose the prelude to such a
smart city.
The municipalities Almere, Milton Keynes, Ajaccio and
Viladecans together with their partners and observers
completed these large, new, complex projects. These
municipalities reached new milestones and fulfilled
their ambitions in fantastic new or refurbished urban
environments. The results and lessons learned are
available to be shared with you. You are welcome to visit
our CONCERTO communities.
Emil ter Horst,
Horisun
Coordinator cRRescendo
Disclaimer: “The European Commission support for the production of this publication does not constitute endorsement of the contents which reflects the views only of the authors, and the Commission cannot be held responsible for any use which may be made of the information contained therein.”
new energy for growing communities 5
Recommendation It is a pleasure for me to recommend this book to you.
The European cRRescendo project and the lessons
learnt described in this book are close to my heart.
I came to Almere 10 years ago.
Before that time I lived for a long time in Friesland,
where I fell in love with the typical Dutch panoramic
flat and wet pastures. Here in the province of Flevoland
I experience the same feeling for this polder landscape.
With views reaching to the horizon. Here in Almere my
family and I built our own sustainable dream house.
Almere is a new-town handmade by pioneers in the new
polder of Flevoland just decades ago. As a spin-off we
saw Europe’s youngest nature reserve emerge just in the
shadow of Almere: the Oostvaardersplassen, sometimes
nicknamed as the “Serengeti behind the dikes”.
In Almere en Flevoland one can have the best of
two worlds. You can live in the countryside near the
city or you can live in the city near the countryside.
cRRescendo has shown us now clearly that a smart
sustainable city needs this countryside (that my city
is blessed with) in order to achieve the future goal of a
zero-energy community.
As president of the Council of European Municipalities
and Regions I am proud that in the cRRescendo project
Almere and her twin city Milton Keynes, the Catalan
new-town Viladecans and the beautiful capital of
Corsica, Ajaccio, were the founding fathers of this
important project. But I am even more pleased by the
dissemination that is taken so serious in the project.
During the project already to the observer cities
Misterbianco, Sofia and San de Senart, but now the
results are shared with all European cities.
Just as in my own sustainable building experience I
was happy to learn so much from others who did the
same job before us, in the same way I am sure the
lessons learnt in cRRescendo will pave the way for other
European cities, north, south, east or west.
As Mayor I can tell you that though the cRRescendo
project formally has ended, it lives on in our cities. The
ideas have been embedded in our local policies, while
new projects in all four cities are on the way exceeding
the high ambitions of cRRescendo, sometimes even
by far. The concept of a smart sustainable city is
unstoppable.
In Almere the cRRescendo “icon” demonstrations
showed our citizens the road towards a zero-energy
city in 2025. Under the heading Growing Green Cities,
this “green” road may now be even accelerated by the
Floriade, hosted by Almere in 2022.
And finally, if you enjoyed the book, feel free to visit us:
the surprising near-carbon-free socially sustainable
Almere Columbuskwartier, the pleasant low-carbon
Vizion building in Milton Keynes, the sturdy energy-
positive community center in Ajaccio or the inspiring
smart school in Viladecans. They have been visited
by many people and delegations already but are still
waiting for you.
Annemarie Jorritsma, Mayor of the city of Almere.
President of the association of Netherlands municipalities (VNG). President of the Council of European Municipalities and Regions (CEMR)
Left: Dissemination is taken serious in cRRescendo
Right: Icon projects such as the future Floriade will pave the way for a zero-energy smart Almere in 2022
6 cRRescendo
new energy for growing communities 7
Preface
The cRRescendo project is about the sustainable
building of 3,290 houses, 75,093 square meters of public
and commercial buildings, 1,099 kWp solar PV panels,
8,337 square meters of solar hot water collectors in four
European cities and last-but-not-least carbon-saving
district-heating systems installed in two cities. There
was an overall carbon saving by cRRescendo of almost
30%, while this percentage more than doubles when the
effect of the district-heating in Almere is included.
The project shows how the Municipalities Almere (NL),
Milton Keynes (UK), Ajaccio (Corsica, FR) and Viladecans
(ES) have made a significant step towards zero-carbon
communities in turbulent economic times.
These cities overcame the bureaucratic hurdles,
introduced modern low carbon energy production
technologies and set new energy-saving standards
for the built environment. They worked with vision,
ambition, perseverance, know-how, and bravery. They
woke up the building industry. The cRRescendo project
also demonstrates how best to meet the citizens’ wishes
of living in comfortable, energy efficient homes in a
healthy and clean environment.
Despite concessions to the original ambition (due to the
recession) the project kept its promise to pave the way
towards a complete sustainable city after 2020.
Developing new and innovative neighbourhoods at this
scale is a local challenge of international importance,
and therefore supported by the European CONCERTO
programme.
The results are both visible and embedded in the
local community: in paradigm changing iconic
urban developments and game changing new ways
of producing energy; in lasting changes among
stakeholders in the building sector and integral
sustainable policies in our cities. But above all inspiring
urban environments have been built, while new projects
underway have surpassed even our ambitions.
It was an adventure for us to unravel impacts and
success factors. It was hard work to filter through the
project management system, with all the changes in
contracts, objectives, and people. And then there was a
mountain of information and a sea of deliverables.
This book will guide you through all aspects of the
development and the results of Europe’s largest urban
sustainable building project.
You can experience the content on three levels. The first
level and main structure concerns the chapters on the 4
cities: the design, implementation and users’ experience
of eco-buildings and low-carbon power plants. The
second level on spread pages in-between the chapters
will guide you through overlapping themes such as the
research, training and dissemination. The third level
addresses general lessons or specific quotes and tips of
key staff in doing their job. You will find these echoes of
10 years’ co-operation often in the margin or indicated
with an exclamation mark. [!]
We believe, to remain in the imagery of the CONCERTO
programme, that the achievements by cRRescendo
form a nice symphony. We invite you to play along with
the song lines in the book. Absorb the useful lessons
and the tools you deem fit, combine them with your
own tunes, and become even more sustainable than the
cRRescendo project.
Emil ter Horst, Caspar Noach, Leendert Verhoef and
Vera Haaksma (clock wise)
The power of heatMilton Keynes
2.1 Milton Keynes – the scene 32
2.2 A suite of sustainable projects 33
2.3 Vizion – iconic building as an urban landscape 35
2.4 Office of tomorrow - The Pinnacle 36
2.5 Combined heat and power generation 39
2.6 PV power plant on former bus station 42
2.7 Moving forward 44
Sustainable renovationAjaccio
3.1 Ajaccio – the scene 48
3.2 A suite of projects 50
3.3 Performance – occupant behaviour 54
3.4 Moving forward 551
2
3
Frame: Economics needs Replication 58
Towards zero carbon cityAlmere
1.1 Almere – a New Town 14
1.2 Opportunity for sustainability 15
— Sustainability: a matter of “Principles” 16
1.3 Mobilising civil servants, stakeholders and inhabitants 17
1.4 Almere Solar Island for a low-carbon district heating 20
1.5 A solar PV power plant dispersed over Columbuskwartier 22
— The certification scheme “Solar House” 23
1.6 Ecohouses and private commissioning in Noorderplassen West 26
1.7 Research on sustainability 26
1.8 Towards smart energy-neutral in 2025 28
Frame: From observer to doer 30
PreludeEC CONCERTO Program 04
Recommendation 05
Preface 07
Bridging the recession - cRRescendo summary 10
Frame: Sharing local learnings 46
learning
designing
connecting
inspiring
building
giving
AnnexesAnnex I
Realised cRRescendo projects 92
Annex II
People behind the projects 98
Annex III
Solar potential in Europe 100
Paving the wayViladecans
4.1 Viladecans – the scene 62
4.2 Delivering eco-buildings 64
4.3 Solar energy in Viladecans 67
4.4 Overcoming barriers – stepping forward 69
New energy for growing communitiesResults, lessons and recommendations
6.1 Four cRRescendo cities 84
6.2 Diversity of projects in the different communities 86
6.3 EU policy lessons 87
6.4 Local policy and project level lessons 88
6.5 The building sector lessons 89
6.6 Bridging recessions 90
4
5
6
The discovery of a sustainable communityColumbuskwartier
5.1 A learning history 74
5.2 The district Almere Poort 75
5.3 From simple idea to detailed plan 76
5.4 Getting a grip on sustainability 78
— Managing Columbus’ egg 81
Frame: Empowering the community 82
Frame: Checking the ambition 71
Frame: Sharing local learnings 46
10 cRRescendo
A turbulent decade: 2003-2012
The preparation of the cRRescendo project started in
2003. It was not the most ambitious project when it was
accepted in CONCERTO. But it promised to be impactful,
not only due to its size, but also due to the ambitious
smaller projects inside the project: the so-called
icons of sustainability. cRRescendo was embedded
in a completely new kind of policy, an integral way of
looking at sustainability. Policy inspired by the cradle-
to-cradle ideas.
Now, a decade later cRRescendo turned out to be
recession-proof, being one of the CONCERTO projects
with substantial impact.
cRRescendo is led by 4 main cities with 11 local partners.
The cities of Milton-Keynes (England, UK), Viladecans
(Catalonia, Spain) and Almere (Netherlands) are sub-
metropolitan New Towns while Ajaccio is the historical
capital of Corsica (France). There were three so-called
observer cities, Misterbianco (Sicily, Italy), Sofia
(Bulgaria) and San-de Senart (France), entitled to learn
from the results.
The cities are nicely dispersed over Europe, with
similarities and differences.
In the beginning the project was well on track, but in
2007 it became clear that the crisis in the American
mortgage market was also causing project developers
Bridging the recession cRRescendo summary
to be cautious in Europe. Nevertheless, first realizations
in Almere and Milton Keynes had started.
Through 2008 cRRescendo developments continued
in all four cities. In Almere many eco-houses had been
delivered and the building of Solar Houses had started.
In Milton Keynes the CHP had been realized. In Ajaccio
the renovation of houses was delayed. In Viladecans
the Daycare Centre was at the last stage of realization.
The building of houses in Viladecans was delayed and it
became clear that the recession had arrived in Europe,
especially in Spain.
At the end of 2008, the housing market crisis had a
deeper impact on the demos in UK than previously
thought. Since then the housing crisis became a global
financial crisis, with substantial consequences for
cRRescendo, especially in Milton Keynes and Viladecans.
It was promising that the urban development in Almere
and renovation activities in Ajaccio nevertheless had
continued as planned. In Almere the recession simply
arrived later.
cRRescendo convinced “Brussels” that only with a
substantial amendment was it still possible to realize
the original ambitions, while a prolongation of the
project was accepted to accommodate this. Alternative
demonstrations have been developed in the cities to
compensate for the possible loss of ambition in the
original project.
The world changed quite a bit from 2003-2012, with
02000
Dawn of the solar age
2003
CO2-neutral Sun City in Heerhugowaard: precursor to CONCERTO and cRRescendo.
2004
The German Feed-in Tariff boosts the PV market to a global cumulative installed capacity just above 1 GWp. The price for PV modules is 3€/Wp. China starts first PV mass production.
2005
started in 2005 and co-funded over € 175 Million to 58 cities in 22 projects in 23 countries.
2006
With 75% of the PV Market in Europe (heavily subsidized) the price does not go down enough in 2006, while cheap production in China is attracted.
4 €/Wp
2
0
2000 2006 2012
11bridging the recession
the mortgage crisis, financial crisis and real estate
crisis followed by economic downturn. However due to
the re-scoping cRRescendo could be still successfully
realised with the same overall high ambition.
In that same decade we also saw enormous
technological changes: in energy efficiency measures, in
renewable energy especially PV solar energy technology,
while last but not least the concept of smarting the
energy grid and smarting the city gained a foothold.
It was not possible to sail through these times and at
the same time contribute to those needed changes
to the max. As the sky was not the limit anymore,
the larger demonstrations were carried out realistic
ambitious, while the project’s overall ambition was
kept high or even higher in smaller icon projects. As the
price of PV solar energy was reduced drastically, this
promising technology for the built environment could
be kept easily “on-board”, while the concept of a smart
community could not be adopted overnight, but will be
explored in the decade beyond the project (2013-2022).
4 cRRescendo communities
Now, at the end of cRRescendo 10,000 people live in
modern, comfortable, healthy and energy efficient
homes due to the well-orchestrated sustainable
developments of the metropolitan areas of Almere,
Milton Keynes, Ajaccio and Viladecans.
In Almere (NL) two “Energy Rich” districts are part of
the cRRescendo project. In Almere the total reduction
in conventional energy consumption is 31%, in which
the high carbon reduction due to cogeneration in both
communities and green electricity in Columbuskwartier
is NOT included.
About 2000 new dwellings have been built in three
“Energy Rich” classes:
- eco-houses, built at least 10% more energy efficient
than the building standard;
- solar houses, with an energy performance 25% better
than standard;
- passive houses, having an energy performance 50%
better than standard.
Most cRRescendo dwellings in the district
Noorderplassen West are eco-houses. In this area some
private dwellings have PV systems, but the major solar
contribution is achieved by the Almere Solar Island
(opened June 2010).
For the first time homes in the Netherlands are heated
collectively with locally-generated solar energy. The
Almere Solar Island is an icon in the Almere landscape.
The way the island works is simple: water in the solar
collectors is heated by the sun. The heated water is
pumped directly into the low-carbon district heating
network that supplies heating and hot tap water to the
residential district Noorderplassen West. The Almere
Solar Island is the fourth largest solar collector field in
the world.
In the second cRRescendo district, Columbuskwartier,
about 500 solar houses and 103 passive houses have
been built. On these and other houses and buildings
in the district a total of 600 kWp PV panels have been
installed.
In realising its ambitious objectives, the heat for the
1,000 homes of Columbuskwartier comes from the
Diemen “Combined Heat and Power” (CHP) plant on
the other side of lake IJmeer. The connection of all
dwellings and buildings of the spanning district Poort
to the district heating system is fed by this CHP system.
A new pipeline connection from the “Diemen” plant
goes through the IJ-lake to Almere. The overall energy
supply is obtaining a 93% CO2 reduction not only for
Columbuskwartier but for the whole Poort district. In
support of that the energy company NUON is required
to deliver only green electricity in the Poort district.
Milton Keynes (UK) is centrally located in the UK, 70
miles North West of London. In Milton Keynes the total
reduction in conventional energy consumption is 30%,
in which the reduction due to the CHP is included (the
share linked to cRRescendo buildings).
The local programme, where a holistic approach to
urban design has been adopted, includes four separate
developments:
- Combined Heat and Power (CHP) with private wire
network;
- Enhanced building fabric in a residential and a non-
residential building;
- A large 165 kWp Photovoltaics (PV) system.
A successful component of the Milton Keynes project
has been the delivery of the CHP engine, connecting via
2007
Europe was leading the global PV production (4GWp) only in 2007.
The IPCC and Al Gore have jointly won the 2007 Nobel Peace Prize.
2008
In Almere Columbuskwartier first houses are completed.
The U.S. Mortgage Crisis becomes a international financial crisis and is followed by a EU house-building crisis especially in Spain and the UK.
The huge world PV market share in Spain collapsed from 41% in 2008 to 1% in 2009.
Europe
China
Japan
Rest World
2009
Completion of the Pinnacle office and Vizion residential buildings in Milton Keynes
2010
Completion of the two Almere communities and the Solar Island.
12 cRRescendo
a private wire network up to many buildings in the city
centre. In 2012, the BREEAM “Excellent” rated Network
Rail Headquarters “Quadrant” development, comprising
38,000 sq.m. connected to the CHP system in Central
Milton Keynes. This expansion is a good indicator of the
confidence now being shown in the ability of the CHP to
deliver cost effective heat and power.
The Vizion complex is a high quality vertical mixed-
use development, which is loved by residents. The
development (2009) contains 441 apartments and
townhouses but also includes a large Sainsbury’s store
of approximately 10,000 m²and another 4,100 m2
commercial and retail units. The enhanced building
fabric was applied to raise the standard of the building
and its thermal characteristics far beyond national
standards. Heat, cooling and electricity are supplied by
the above CHP system.
The same applies to the Pinnacle, a high-quality
office with an element of mixed-use. The building is
performing well for the occupants. It is the first BREEAM
“Excellent” rated office development in Milton Keynes
and a winner of an Office Development Award for
Sustainable Achievement. The Pinnacle accommodates
three commercial offices and several smaller retail
units, with over 19,000-m2 commercial space.
Finally, the former bus station was settled on as the
most appropriate site for the PV installation. In total,
825 panels, made of polycrystalline silicon, were
installed on the roof. The installation had to respect
the architectural integrity of the existing building. As
a consequence, the PV arrays have been installed at an
angle of 5°. The electricity produced is delivered free of
charge to a youth community interest company which
uses the building.
By the end of 2003, the community of Ajaccio (Corsica,
FR) decided to answer the call for projects of the
“CONCERTO” programme. Until then the city had little
awareness for the environmental approach, but this
changed with the cRRescendo contract in August 2005.
It is from this date that Ajaccio’s understanding and
involvement grew towards more conscious politics on
the environmental issue. Ajaccio became more aware of
the need to reduce public energy consumption as well as
the energy use of social buildings tenants.
Public buildings like schools, which are part of the urban
renewal project in priority areas, are henceforth built in
compliance with High Environmental Quality Standards
(HQE, France), aiming at “zero” energy consumption, or
even better as for the (to be built) “Maison de quartier
des Cannes”, a positive energy building, producing more
electricity than what it will use.
At the same time, taking advantage of the National
Programme for Urban Renewal (since 2007), social
landlords were able to rehabilitate an ageing housing
stock by undergoing money saving and energy saving/
producing building improvements.
The refurbishment of social (rented) housing stock
(419 apartments) was the key element of cRRescendo’s
activities in Ajaccio. Also a surface of 346 m2 of solar
collectors has been installed on social housing buildings
and will produce hot water for 223 apartments. In the
Ajaccio demonstrations the reduction in conventional
energy consumption is about 20%.
Viladecans (ES) is a coastal community, located 12
kilometres from Barcelona.
In the frame of cRRescendo, due to the recession only
five public buildings have been built or refurbished (day
care centre, youth cultural centre, historical cultural
centre, sports building and municipal building).
The city is committed to reducing CO2 emissions,
elaborated in 1996 the Agenda 21 and joined in 1997
“Barcelona network of towns towards sustainability”.
In addition, Viladecans has signed the Declaration of
Vilafranca on preventing climate change in 2005. This
initiative is covering the whole Barcelona province.
Finally, Viladecans has signed its adhesion to the
Covenant of Mayors in 2008. The Viladecans’ Council is
elaborating its Action Plan for Sustainable Energy that
contains 143 specific actions for this purpose.
In the coming years, the municipality will finalise the
installation of 1 MW of photovoltaic panels in the city
(up to 342 kW of them are part of cRRescendo project)
and (as soon as the recession is over) will build 2.000
new dwellings in a new eco-district called Llevant.
New energy for growing communities
cRRescendo, with the full project title “Combined
Rational and Renewable Energy Strategies in Cities, for
Existing and New Dwellings to ensure Optimal quality
of life”, has been carried out very successfully, despite
the crisis and thanks to the perseverance of the four
2011
The price of PV is 1€/Wp. Global PV production is 35 GWp/year. China leading solar producing country.
2012
Total cumulative installed PV solar capacity is just above 100 GWp with 70% in Europe.
2013
Start of Horizon2020 / Smart Cities & communities programme to prepare smart zero-energy urban communities in 2020 and beyond.
2014
Since the recession in Europe has slowed down the building of houses, we see in so many cities a latent wish or need for sustainable projects, but more integral than ever before. The future city must not be only carbon-neutral, but also smart and social. The pipeline is full and the political will is there. Energy and ICT technologies to realize a smart zero-energy city are becoming very affordable. E.g. the price of PV has fallen in one decade by a factor of 8. There are promising years to come.
Europe
China
US
Rest World
Europe
China
Japan
Rest World
13bridging the recession
cities and flexibility of the CONCERTO programme
management.
The main impact of cRRescendo is that it paved the
way in all four cities to make a transition towards a
smart zero-energy society within the coming decade.
We showed that cross -Europe learning works well
for both the main cities and the observer cities, if well
orchestrated. We also have to accept that the solutions
for different parts of Europe often differ from each other
or at least need a local “translation”.
During the project a strong political wind arose in
Almere to adopt an integral (ecological and socio-
economical) sustainability policy, leading to a smart
zero-carbon city in 2025 or earlier. To do so things
need to change quickly, all while trying to maintain
citizen and potential stakeholder involvement. The
disadvantage that the cRRescendo project was
easily overtaken by future developments has been
compensated by high-ambition icon inner projects. The
combination of this and the larger scale of cRRescendo
as a whole give maximum impact for replication. The
large number of visitors from all across Europe and
beyond confirms that this idea has worked well.
Milton Keynes eventually realized large ambitious but
realistic projects, with low-energy buildings and a
paradigm changing Combined Heat Power plant (CHP),
that are easy to replicate on short-term. Due to the
recession the ambition was downsized, leading to a
hesitation by the founding fathers to showcase the
results. But the economic cases were so strong that
(also due to the co-operation the private sector) the
impact of a strong replication throughout the UK is
easily shown anyway.
Ajaccio could benefit from the lessons learned in the
project but also from other French cities in other
CONCERTO projects. Renovation is firstly tackled,
while Ajaccio jumped on the train of sustainability. For
Ajaccio the time was just right (increasing sustainability
standards, conjuncture, politics and house markets
in France). The main impact on Corsica is the growing
drive from lagging behind on sustainability to being
there at the very forefront in France.
Viladecans was forced to focus on training, education
and showcasing sustainable community buildings and
PV solar energy. Despite the recession a strong policy
back up remained; there is a latency of projects as soon
as the economy recovers. Also Viladecans benefits from
the lessons learned in cRRescendo especially for the
future ambitious eco-district Llevant.
As aimed, cRRescendo integrates a major share of
sustainability into over 3,150 new and existing homes
and their energy infrastructure in order to demonstrate
the possibility, feasibility and most importantly to
meet the citizens’ wish to live in a comfortable energy
efficient home in a healthy and clean environment.
The cooperation between the cities within the
EU CONCERTO programme not only showcases
the successful integration of poly-generation and
renewable energy into a large number of ecobuildings,
but also provides the tools for a successful reprise in
these towns, the observer communities and many other
cities in Europe, in an ever swelling cRRescendo.
But the outreach goes beyond that. The project as a
whole has withstood the building crisis of 2008-”10
because the recession impacted the four cities very
differently.
cRRescendo showed that it was still possible to do in
the middle of the crisis a substantial step in energy
reduction: with energy efficiency & renewable energy
… in new & renovated districts … in growing &
modern communities … and in north & south Europe.
It is now convincingly prooved that a zero-carbon
community is possible anywhere in Europe in 2020, as
this is simply just one step away from cRRescendo.
The demonstrations are described in further detail in
the following chapters, while spread pages in-between
chapters will guide you through the extensive research,
training and dissemination.
This chapter “0” continues with a summary of results
and lessons learned in chapter 6 (page 84)
2015
Planned completion of the Maison de quartier des Cannes in Ajaccio. This community building will produce more energy than it will use: with a solar roof, an urban windturbine and more.
2018
PV solar will be the cheapest source of electricity in the world. The annual PV production will be above 300 GWp while the price of produced energy will be lower than €0.05/kWh. SolarGIS © 2013 GeoModel Solar ›
2020
signatories aim to meet and exceed the European Union
20% CO2 reduction objective by 2020. Viladecans, Milton Keynes and Almere are part of the 5,883 signatories representing 189,148,547 inhabitants (2014). A huge statement by the EU cities & citizens !!!
2022
Almere stands for “Growing Green Cities” and wants to be a zero-energy city in the year of the Floriade World Expo.
2025
Every city & community to be ‘smart’ & energy-neutral as soon as posible!
14 new energy for growing communities
1.1 Almere – a New Town
Almere, a New Town with over 190,000 inhabitants,
situated east of Amsterdam, is expected to grow to
350,000 in 2030. From its inception in 1975, the city
committed itself to sustainable development. For
example: the majority of homes in Almere were already
connected to district heating since the beginning. In
2005, plans were made to build 2,700 new sustainable
homes with accompanying schools, offices and stores in
the district Noorderplassen West and to build 1,000 new
sustainable homes and accompanying schools in the
community Columbuskwartier in district Almere Poort.
About 2,000 of these houses and buildings were
brought into the framework of the cRRescendo project.
A greener energy supply for the area needed to be
developed as well.
The planning of the projects was initiated in 1997 for
Noorderplassen West, and in 1998 for Almere Poort.
Plans needed to include an approach for the whole
energy infrastructure, which was done separately for
both districts.
Nieuw Flevolands Peil was an important initiative
helping to make the principles of sustainable
development more practical. It was a regional
Towards a zero carbon cityAlmere
1.1 Almere – a New Town
1.2 Opportunity for sustainability
— Sustainability: a matter of “Principles”
1.3 Mobilising civil servants, stakeholders and inhabitants
1.4 Almere Solar Island for a low-carbon district heating
1.5 A solar PV power plant dispersed over Columbuskwartier
— The certification scheme “Solar House”
1.6 Ecohouses and private commissioning in Noorderplassen West
1.7 Research on sustainability
1.8 Towards smart energy-neutral in 2025
1
District Noorderplassen West with the Almere Solar Island
towards a zero carbon city 15
public programme describing actions on
sustainability for the province of Flevoland.
This grass root programme had a clear
influence on the ambitions of Almere in the
beginning of the project.
1.2 Opportunity for sustainability
One step better: in Noorderplassen West,
the main goal was to reduce the energy
demand by 10% with simple interventions in
an otherwise conventional way of building
without higher costs. However, the energy
supply had to have 50% lower carbon
emissions than a conventional new-built
district.
Two steps better: in the South of
Columbuskwartier, the goal was to realise
an integral sustainable neighbourhood. Not
only from an environmental point of view,
but sustainable in many other ways. An
important goal for Columbuskwartier was to
reduce the energy demand of the houses
by more than 20% and to reduce the overall carbon
emissions by over 90%, in a cost-effective way. The
extra investment costs had to be earned back with cost
reductions, mainly by lower energy bills.
Three steps better: over 100 (passive) houses in the
North of Columbuskwartier have an approximately
50% lower energy demand than normal. With that the
project shows the way to build sustainable houses in a
cost-effective way in the future.
In both communities solar energy played an important
role.
The ambition level for buildings was set at 10%
energy savings in Noorderplassen West and 20%in
Columbuskwartier. In 2005 the urban development
process in Noorderplassen West was already rather
advanced, but a step of 10% was still achievable. The
Columbuskwartier however still had to be developed.
The project developers readily accepted the 20%
ambition, also because it was set relative to the familiar
Dutch national energy performance standard.
“Almere saw its growth, typical for
a New Town, as an opportunity
to build with a high ambition
level. cRRescendo enabled Almere
to increase that ambition in the
developments in Noorderplassen
West and Columbuskwartier. The
idea was to accomplish these
ambitions on the scale of a large
urban development. We have
successfully built houses that are
either 1, 2 or 3 steps more energy
efficient than required by the
building code.“
Emil ter Horst, cRRescendo project manager for Almere
The Columbuskwartier was developed with an integral
approach to sustainability. Besides energy savings
in buildings the development addressed the public
space and social aspects. Concurrently, the Dutch
energy agency (now www.RVO.nl) introduced a
certificate Zonnewoning (Solar House), which combines
sustainability and the indoor climate into practical,
easy-to-use guidelines. Caspar Noach (Ecofys): “We learned
that combining the Solar House certificate with a tender for
integral sustainability resulted in the most successful part of
cRRescendo: The development of the southern part of the area
Columbuskwartier known as The Marvel (De Verwondering).
However we also learned that the certificate was hardly known
among the house owners.”
The municipality of Almere anchored these ambitions
in legally binding, mutual agreements. Because
ambitions cannot be forced on project developers, a
good anticipation for what level of ambition would
be acceptable, was of key importance. The high tide
of continued (inter)national economic growth and
booming house markets in 2000-2005 allowed for
setting the ambitions high. And the builders, keen to
win the contract, set them even higher.
Eco-houses in Noorderplassen West
16 new energy for growing communities
Sustainability: a matter of “Principles”
The intended growth of
Almere in the coming
decades will take place
in an ecologically,
socially and economically
sustainable fashion.
The aim of the national
government, the provincial
government of Flevoland
and the municipality
Almere is to position
Almere as a national
laboratory for large-
scale implementation of
sustainable systems.
The joint desire is to turn Almere into an icon of
sustainability. This high ambition is reflected in the
winning bid for the organisation of the world famous
Floriade 2022, and in policy goals such as to reach
climate and energy neutrality for the whole city in 2025.
!Use tools to objectify sustainability
contributes to make ambitions real and
comprehensible. These range from simple
checklists to clearly defined goals.
To inspire everyone who contributes to the future of
the city, local politicians defined the Almere Principles
together with Cradle-to-Cradle champion William
McDonough. The Almere Principles were developed
parallel to the preparation and realisation of the
cRRescendo demonstrations in 2005-2008.
The ambition and mission behind the integral
sustainable Columbuskwartier were based on the same
corner stones and thereby Columbuskwartier was the
first neighbourhood built completely according to
the Almere Principles, even before they were formally
accepted by the council. The numerous delegations
from Netherlands, Europe and far abroad which visit the
neighbourhood prove that Columbuskwartier has given
us a good translation of the Almere Principles, showing
an interesting modern approach on how to realise an
integral sustainable urban concept into practice.
!Agreements on content do not alter the
process of development. Sustainable
quality can only be achieved through
(personal) involvement. It is not about
enforcing, but all about alluring and
connecting. The key is to connect parties that amplify
each other.
The Almere Principles
1. Cultivate diversity: To enrich the city, we acknowledge
diversity as a defining characteristic of robust ecological,
social and economic systems. By appraising and
stimulating diversity in all areas, we can ensure Almere
will continue to grow and thrive as a city rich in variety.
2. Connect place and context: To connect the city
we will strengthen and enhance its identity. Based on
its own strength and on mutual benefit, the city will
maintain active relationships with its surrounding
communities at large.
3. Combine city and nature: To give meaning to the city
we will consciously aim to bring about unique and lasting
combinations of the urban and natural fabric, and raise
awareness of human interconnectedness with nature.
4. Anticipate change: To honour the evolution of the city
we will incorporate generous flexibility and adaptability
in our plans and programs, in order to facilitate
unpredictable opportunities for future generations.
5. Continue innovation: To advance the city we will
encourage improved processes, technologies and
infrastructures, and we will support experimentation
and the exchange of knowledge.
6. Design healthy systems: We will utilize Cradle to
Cradle solutions, recognizing the interdependence, at all
scales, of ecological, social and economic health.
7. Empower people to make the city: Acknowledging
citizens to be the driving force in creating, keeping and
sustaining the city, we facilitate them in pursuing their
unique potential.
Cover of the book The Almere Principles
towards a zero carbon city 17
to build on their own: there were simply no single
plots available. Adri Duivesteijn stipulated that 35% of
the houses to be built should be allocated to private
commissioning.
During the first three years, communication was
mainly an internal process directed at the most relevant
stakeholders in the urban development. Though the
objectives of the project were described very well
in the project proposal, development of a large new
housing area takes over a decade from initiative until
commissioning. Once the development started and is
picking up speed, it is hard to stop or even change the
process. On the other hand a long running project must
provide space for new politics and changing realities.
Examples are the financial crisis of 2008 and the
recession since the start of the development.
Communication with (future) inhabitants is difficult in
new districts, and was also missing in the beginning.
Later on, the local environmental federation NMFF took
the responsibility for the communication together with
the municipality. How to communicate and interact
with citizens is something a New town had to learn, also
because houses are actually built before people moved
into the area. At first an “Explore Lab” platform was set up
for inhabitants to express their wishes and expectations
towards the architects and builders. This Explore Lab
evolved into the more successful platform “Sustainability
Lab”, which focused on knowledge transfer to the project
and to the employees of the municipality. More recently
it became DuurzaamAlmere.nl, a sustainability shop in
the centre of Almere City where citizens, municipality
and local businesses can really meet. When the focus
shifted to private commissioning the communication
towards the citizen improved a lot, also through the
successful “Kavelwinkel”, a shop selling lots.
In the final project year the communication focus
shifted again. From mainly internal communication
to stakeholders and instructions for citizens to more
general dissemination to Almere, the Netherlands and
Europe. Almere Solar Island and the Columbuskwartier
houses in The Marvel have become well-known and
attract many visitors from Almere, and other cities in the
Netherlands. In addition professional groups from abroad
come to visit almost weekly.
In parallel Almere’s ambitions on the policy level
were also rising. In 2007 the minister of Environment
imposed the condition that if Almere wanted to grow,
it had to do so in a sustainable way. This resulted in a
covenant between Almere and the national government
(Schaalsprong Almere). For the municipality Almere
this also led to the launch of the Almere Principles,
advertised by Alderman Adri Duivesteijn.
1.3 Mobilising civil servants, stakeholders and inhabitants
But it took time to learn how to make sustainability part
of the planning routines in a fast growing city. Tools
had to be developed and civil service officers had to
change their role. At first the project was not optimally
embedded in the organisation to make use of its full
potential. Alex van Oost, senior staff member Sustainable
Building and Energy at the department responsible for
environmental policy: “At the beginning we were struggling to
find a workable definition for sustainability, and how to make it
tangible. We lacked experience with an integral approach to the
complex definition of sustainability. What we were trying to do
had hardly been done on this scale before. We started to create a
context based on People, Planet and Prosperity. We determined
specific goals and ambitions, and worked these out in a detailed
sustainability matrix.
There were political changes as well. After a shift
in political power in 2006, the new alderman Adri
Duivesteijn initiated a paradigm shift in the way of
building. Conventionally, project developers would
build in batches of ten to hundreds of houses in the
Netherlands. For individual people, it was difficult
Schools (both buildings and education) were part of the project. Opening of the Clock House information centre for children.
18 new energy for growing communities
Name/typeNumber of Homes
Gross area per house m2
Measures Total Solar
Noorderplassen West
Eco Apartment 84 91 High insulation, EPC = 0.89 District heat
Eco House 1,462 176High insulation,EPC =0.89 district heat
Solar Apartment 48 137 High insulation, EPC = 0.72 District heat
Solar House 116 171 High insulation, EPC = 0.71 District heat
PV Systems on 3 Private Commissioning Houses n.a. n.a. PV Panels 9.9 kWp
Noorderplassen West 1,710 9.9 kWp
Columbuskwartier
Eco Apartment 114 86 High insulation, EPC = 0.8 District heat
Eco House 69 184 High insulation, EPC = 0.8 District heat
Solar Apartment 83 89
PV panels High insulation, EPC = 0.62, District heat
17 kWp
Solar House 342 140
High insulation, EPC = 0.6 PV panels on more than half of the homes District heat
325 kWp
Passive house 103 105
PV panels High insulation, EPC = 0.38, District heat
108 kWp
Carbon neutral house 1 225
PV panels High insulation, EPC = 0.03,Urban wind turbines
6.7 kWp
Columbuskwartier 712 457 kWp
Total All dwellings 2,422 271,786 466 kWp
Overview cRRescendo measures in residential buildings in Almere
towards a zero carbon city 19
Overview cRRescendo measures in non residential buildings in Almere
Name/type # functional units Realised Gross m2 Measures Solar
Noorderplassen West
Day care centre 5 1,382High insulation,District heat
Health centre 22 9,344High insulation,District heat
Shopping centre 11 1,757High insulation,District heat
Primary school 3 6,996High insulation. District heat, PV panels
47 kWp
PV on Sports accommodation
1 n.a. PV panels 45 kWp
Solar Island 1 n.a. Solar collectors 7,800 m2
Noorderplassen West 38 12,483 92 kWp7,800 m2
Columbuskwartier
Health centre 3 625 High insulation,District heat
Office 1 45 High insulation,District heat
Primary school 6 5,178 High insulation,District heat
Sports accommodation 1 1,071 High insulation,District heatPV panels
44 kWp
International School1
5,135 High insulation,District heatPV panels
26 kWp
PV on “Klokhuis” n.a. PV panels 1.4 kWp
PV on secondary school n.a. PV panels 23 kWp
PV on Community Disposal Centre
1 n.a. PV panels 37 kWp
Columbuskwartier 12 12,054 130 kWp
Total Non-residential 50 24,537 222 kWp 7,800 m2
20 new energy for growing communities
Panorama of Almere Solar Island (source: Panopictures.nl, J.A. Prins, 2010)
Solar Island, installation of (large surface) collectors
1.4 Almere Solar Island for a low-carbon district heating
Solar Island Noorderplassen West
District heating was already common practice in Almere
(40% lower carbon emissions than the reference). But in
Noorderplassen West the municipality wanted to go one
step further and reduce the CO2 emissions of the energy
supply by an additional 10% (to 50%). The initial idea was
to place a solar thermal system on individual homes
by the utility. However, potential project developers
opposed the idea of roofs owned by a utility. Consequently
centralized generation was considered and the Solar
Island was born. The plan was a large ground-based solar
thermal energy system feeding its heat into the district
heating system - not done anywhere else before. In 2003,
a location was found in the secondary space near the
ring road: an area not usable for housing due to noise
regulations. But the visibility to the public and thus the
potential exposure was excellent. This was to be the first
large-scale icon for sustainability in Almere.
Who should pay for this first-time innovation? The Solar
Island would increase the costs of district heating per
house by € 1,500. On top of the normal connection costs of
€ 3,500 that is quite a burden either for households or the
utility. The CONCERTO project could co-finance the Solar
Island, thus limiting the extra burden on households to a
few hundred Euro (€ 427) per home. But a more sustainable
energy supply should not become an excuse to build less
efficient houses. Antonin van de Bree, building expert of Ecofys:
“To avoid that the efficiency gain of the Solar Island would lead to
a lower insulation quality of the homes, its effect was excluded
from the applied energy performance calculation method.”
The additional ambition of a 10% lower energy demand
was enforced in one straight forward text line in every
developing contract for a specific site.
Solar Island commissioning and building
The building process of the Solar Island was delayed. Quite
late in the design process, it was discovered that feeding
the heat of the Solar Island into the city district heating
did not fit, due to counter pressure of this system. A new
design had to be made for the regulation system, with
heavier pumps.
Finally the Solar Island was put into operation, in June
2010. It consists of 7,800 m2 gross area (7,135 m2 net area)
of solar collectors. It delivered approx. 8,700 GJ per year
to the district heating in Almere in 2010-2011. From a
technical point of view this is very satisfactory: just above
specifications. From an economical point of view NUON
started with a financial loss. This was caused by a lower
amount of connections than anticipated in the business
case caused by delays in the building of houses due to the
financial crisis. The Solar Island has been replicated already
several times in Europe, clearly showing the economic
feasibility in general.
Emil ter Horst: “Meanwhile, the Solar Island has become an icon for
sustainability for Almere. It attracts visitors from all over the world,
because a solar heat installation connected to district heating is
unique. One advantage of the direct connection to district heating is
that all the solar heat produced can be utilised throughout the year.”
towards a zero carbon city 21
Long-distance district heating for Columbuskwartier
Tender for the energy supply
In 1999 the energy supply of Almere Poort was tendered.
An important criterion was to achieve a 50% or more
reduction in CO2 emissions compared to a reference
scenario based on gas heating. NUON won the tender with
an offer achieving a 93% CO2 reduction with a combination
of district heating, photovoltaics, and a biomass plant.
Consequently NUON was contracted to supply renewable
heat and green power to Almere Poort. The contract
specified the agreed performance levels but no specific
technologies.
Change of plan
In 2005, NUON proposed to change technologies,
because they had become owner of the Diemen
Power station. This is a large gas fired electric power
plant with excess heat used for district heating near
Amsterdam, and about 8 km away from Almere. A study
had shown it was feasible to transport the excess heat
by a pipeline through the IJmeer lake to the district-
heating network of Almere Poort. The municipality
endorsed this change, as Almere had gained insight
that a biomass plant in a living district might not be the
best solution due to possible air pollution and increased
traffic of supply trucks.
Both parties agreed upon an addendum to the contract
safeguarding the CO2 reduction from the original offer
in two ways. First, NUON will buy green electricity
certificates equivalent to what the cancelled biomass
plant would have produced during 30 years. And
The huge impressive red Heat Transfer Station in district Poort
Pipeline trajectory Almere Sustainable District Heating coming from Amsterdam, reaching the Heat Transfer Station
secondly, NUON implemented a flue gas heat recovery
system on the power plant, delivering 5 to 6 MW of
extra heat. Such a system can be added to an existing
plant without interruption of operation. The heat
recovery system proved financially beneficial as it
produces extra heat without extra energy/electricity
use. A new electric power plant (Diemen-34) has already
been constructed by NUON exploiting heat recovery
technology right from the start in 2012.
The final CO2-emission and renewable energy
performance goals for the energy supply in Almere
Poort contracted to NUON:
- 91% CO2-reduction with the supply of heat
- 100% CO2-reduction with the supply of electricity
- Resulting in an average of 93% CO2-emission
reduction compared to the emission of equivalent
newly built houses in 2000
- 10% of the total energy supply is to be generated by
renewable energy sources
Getting it done
Planning and especially obtaining the environmental
permits for the pipeline took a considerable amount of
time, because the trajectory runs through the IJmeer,
a lake area protected under the Natura 2000 law.
Construction started in 2011 and was completed in 2012
with the commissioning of the impressive red “Heat
Transfer Station”. The sustainable district heating was
realised without cRRescendo funds. In March 2012 the
first heat was delivered in Almere.
22 new energy for growing communities
1.5 A solar PV power plant dispersed over Columbuskwartier
In total almost 700 kWp of photovoltaic solar panels
were placed on approx. 500 houses and buildings in
the community. These buildings include the Passive
houses, the Solar Houses, a primary, secondary and
international school, two sports buildings and a waste
separation station. The systems were all architecturally
integrated in the houses but not always integrated in
the roofs.
The green electricity produced is connected behind the
meter, giving all profit to the owners and tenants of the
houses. NUON takes care of the maintenance of all PV
systems for the first ten years. Downside of this hassle-
free commitment of NUON and Almere, is that citizens
living below their sun roofs may not even notice their
solar system and may be less involved than hoped for.
Almere had two main reasons for (also) placing PV
systems on municipality-owned buildings in the
community. First, Almere wanted to show it’s own
commitment to sustainability to it’s citizens. Secondly,
Almere wanted to experiment with different concepts
of ownership, operation and maintenance.
The Solar House certificate had just been developed.
The municipality considered this certificate a robust
and manageable way to ensure their ambitions. Half of
the houses in Columbuskwartier would become Solar
Houses. The others would be lower ambition) Eco-
houses.
In 2004, a competition was launched to develop (the
south part of) the Columbuskwartier with high energy
ambitions and requirements on the sustainability
of the neighbourhood. Close to 600 houses in
Columbuskwartier were part of the tender.
The southern wing: The Marvel
The impressive showcase project The Marvel (Dutch:
De Verwondering) was realised by project developer
TBI-Koopmans, after they had won the tender for the
joint development with the municipality of the area.
On the drawing board the certified Solar Houses (see
inset in this chapter) and Eco-houses were intermixed
Solar Houses and beyond
and not separated into different blocks. During the
building phase this proved to be beneficial for the
overall energy-performance. TBI-Koopmans wanted
to make the design, building, and purchasing process
as uniform as possible. For instance; the same type of
glazing and insulation thickness was applied for both
types of homes. As a result, 190 of the Eco-Houses had
higher energy-performance than originally planned
and reached the ambition level of the 235 certified
Solar Houses. Finally a total of 580 houses were built,
of which 154 Eco-homes, 425 Solar Houses, and 1 CO2-
neutral house, all part of a socially and ecologically
integrated urban design.
Emil ter Horst: “The cRRescendo ambitions and timing fit well
with the realisation of the Columbus community. Attention
has been paid to the energy consumption of the homes, but
also to the liveability of the public space. Sustainability of the
neighbourhood was addressed in a broader sense than ever
before. A simple and beautiful example is that children can go
to school exclusively using roads not accessible to cars. Not only
safe but also leaving parents with their cars at home and thus
reducing collateral energy use. For me, The Marvel is the marble
in the Almere cRRescendo demonstration. But I would rather
let you discover that by listening to the people who should take
credit.”
See Chapter 5 (page 74) where the making of
The Marvel is elucidated
Be careful with the use of a certificate. In cRRescendo some certificates were hardly known among the house owners, while the certification process raise the costs of a house.
towards a zero carbon city 23
The certification scheme “Solar House”
The so-called Zonnewoning (Solar House) has played a
key role within The Marvel. It is a certification scheme
for sustainable dwellings launched by the Dutch
energy agency in 2005. The scheme focused on integral
sustainability while safeguarding a more comfortable
interior climate. Special characteristics of a Solar House are:
More energy efficient:
- An energy performance (EPC) 15% better than the legal
standard.
- Two renewable energy measures (solar power, solar
heat, heat pump, bio energy, or passive solar energy).
More comfortable to live in:
- The orientation (south) and large windows ensure
more daylight.
- The well aligned insulation and ventilation ensure a
healthy inner climate.
More sustainable:
- The use of sustainable building materials, and FSC-
certified wood.
- Special rules during the design to ensure the use of
sustainable techniques (besides materials).
For Almere the goal was to test whether this certificate
would work as an instrument to realise extra
sustainability. Secondly the certificate could work as a
communication instrument between builder and
end-user, to guarantee the quality of the house.
But where these two goals accomplished? The answer
is yes, and no. For the municipality the certificate
indeed offered an instrument that enabled them to
plan and verify a higher ambition level. But the role of
the certificate as a marketing instrument was simply
not successful. In practice the certificate was not able
to distinguish itself enough for future house owners
from other not-certified products. For the construction
companies the certification led to a loss in flexibility and
extra costs. Currently the certification body is therefore
not actively promoting the certificate anymore.
Technical challenges:
Due to the fact that district heating is standard in
Almere only two realistic renewable measures energy
remained: solar panels and passive solar energy. Project
developers however posed that this would lead to high
additional costs and very high percentages of glass
surface, because at least 33% of the gross heat demand
had to be provided through passive solar energy. An
Ecofys study showed that the amount was feasible by
applying two simple steps:
- Reducing the gross heat demand, automatically
rising the passive share towards the aimed 33%.
- Enlarging the glass surface using a higher G-value of
the glass (Solar Heat Gain), to increase the ability to
transmit the radiation of the sun.
The study shows results on the requirements for a Solar
House oriented south-east compared to a reference
house. It was concluded that a Solar House was feasible
by enlarging the glass surface by amounts that were
well manageable. Based on calculations made during
the discussion with the developers the additional costs
for a Solar House compared to a “standard house” were
between €5000 and €6000 for a terraced house and
€3500 and €4500 for a semi-detached or corner house
(excluding the costs for the PV-system which was fully
paid for by NUON). The final payback period is very
dependent of the inhabitants use pattern, but varied
between 13 and 17 years.
The main additional measures are:
- Better insulation of roof (20%), walls (15%) and glazing
(10%);
- A few extra square meters of glazing;
- Glazing with a G-value of 0.70;
- Sun screens (on when NW oriented);
- A different ventilation system;
- Low-temperature heating (instead of the standard
high-temperature);
- A 930 Wp PV system.Instructions for citizens must be laid down in a easy to understand manual
24 new energy for growing communities
Solar energy plays a key role in Columbuskwartier. These solar PV panels are on the roof of the Sports facility; with a nice view on the Passive houses in the upper right and the Heat Transfer Station (red) in the upper left.
The CO2- neutral house (Right).
Aerial view on the community Columbuskwartier (south) with the Almere ‘s most important showcase The Marvel (De Verwondering) during building
towards a zero carbon city 25
The northern wing: Passive houses
In the northern part of Columbuskwartier another
iconic showcase was born: an initiative to build 103
Passive Homes for the rental sector. These passive
houses were built by a joint development venture of
BAM Real Estate and Ballast Nedam. The development
was an initiative that had come up in parallel to
cRRescendo and was later embedded into cRRescendo.
The houses incorporate triple glazing, summer-night
ventilation shutters, very well insulated floors, walls
and roofs. The municipality of Almere and NUON
provided solar PV panels. Social Housing Corporation
De Goede Stede ordered and now rents out the homes.
They have been coaching the renters for energy-
efficient and comfortable use of their homes.
The sustainable measures to reach the ambition
level costed approximately € 20,000 extra per house,
excluding the costs for solar panels. Too costly to
put them on the market without financial support.
An additional difficulty in the rental market is that
hardly any raise of rents for higher energy efficiency
is accepted by low-income households. This is a
general problem in the social rental sector in the
Netherlands and in other EC countries, which has
lately gained attention. On top of that, the houses
Passive homes for the social rental sector (with 1 kWp PV solar panels per household on the roof).
Passive houses need a precise and careful construction. Triple HR glazing, extremely thick insulation and many more measures are standard.
had to be connected to district heating, due to the
contract between the municipality and utility NUON.
For a passive house a costly obligation: substantial
connection costs but a very low heat consumption,
which limits the earning back potential considerably.
In addition 38 Solar Houses and several Eco-houses were
developed in this northern part of Columbuskwartier by
the largest Dutch real estate developer Bouwfonds.
See also page 58 for Case: Serial-built “Passive Houses” in
the rental sector
26 new energy for growing communities
1.6 Ecohouses and private commissioning Noorderplassen West
In Noorderplassen West, ground contracts with project
developers with requirements on extra sustainability
(10%) had already been drawn up by the time the
cRRescendo contract was final. Vera Haaksma (Ecofys):
“Attempts to raise the ambitions, for instance by incorporating
Solar Houses, had to be done by convincing the project
developers. This turned out to be very difficult due to reluctance
towards innovations and a project and budget well on its way.
Ecofys showed the developers how building sustainabily is not
more expensive.”
The first one-third of the houses was allocated to
project developers mostly before the start of the
project. The other two-third of the homes in NPW
was not allocated until mid 2006. Early 2007, local
municipal elections shifted the political “colour” in the
municipality.
From 2007 onwards private commissioning became in
favour: most plots were sold to persons who developed
the houses themselves. The municipality made
external consultants available to assist the private
commissioners with the many issues they faced in the
building process. These consultants were also trained
on energy saving by Ecofys. Meetings were organised to
inform the consultants on energy issues and investing
in energy efficiency measures. The consultants
were instructed to raise the issues of energy costs
and sustainability in their contacts with private
commissioners.
An evaluation shows that private commissioning
results in larger and detached houses, which consume
Two examples of private commissioning in Almere-Poort, showing its diversity in a nutshell.
more energy in total, but have the same energy
performance per m2. As this type of commissioning
increases, this group needs extra attention. Almere
feared that it would be difficult to persuade people of
improving the energy efficiency of their own houses,
because building your own home requires people to pay
attention to many issues at the same time. For private
commissioners sustainability was still stimulated but
not mandatory. To our surprise the evaluation however
showed that some 200 privately commissioned houses
actually did comply with the ambitious cRRescendo
standards.
1.7 Research on sustainability
Almere Poort and the major part of the city of Almere
are heated by district heating, a major technology to
realise CO2 reductions for a municipality. Coupling
district heating to co-generation is a well-known
energy option in the Netherlands, leading to 40% CO2
reduction. The Almere Solar Island has demonstrated a
further reduction of CO2 by 10%. But what will be next in
the crusade to zero-carbon district heating? Geothermal
and biomass were studied. And how to generate
sufficient electric power besides the PV systems? Wind
energy and regeneration of combined heat and cold
for a zero-carbon district were investigated. All these
studies, not only for the district Poort but also for
future districts, were carried out under the cRRescendo
umbrella. Let’s have a look.
Geothermal energy
Almere wanted to look at the potential of low-
temperature geothermal energy. The geological
structure called the Slochteren Formation was
towards a zero carbon city 27
Almere Pampus windturbines nearby the Columbuskwartier community
investigated showing that geothermal energy can
be delivered to the district Nobelhorst, but not to
other existing districts as the distance to the relevant
geological layer becomes too large. In the Nobelhorst
district thousands of new houses will be built in the
years to come.
Biogas
Another interesting option is the potential of green
gas. In general, green gas can be directly used in homes
instead of natural gas. Six farmers in the area around
Almere are already producing biogas through a manure
fermentation process. Together with these farmers
and the province Flevoland, Almere conducted a study
to determine the current and potential production of
biogas and green gas in 2030. It turned out that the
farmers can deliver huge amounts of biogas or green
gas to the city of Almere. This gas can (amongst others)
be used in the district heating of Almere. The present
six biogas production plants are already producing 23
million m3 of biogas, sufficient for heating 9,000 houses
in Almere. The potential for 2030 is 115 million m3 of
biogas, sufficient to heat 45,000 houses.
Regeneration of Combined Heat and Cold in a water
protection area
Nobelhorst is Almere’s newest neighbourhood under
development with over 4,000 dwellings and a business
area of 500,000 m2. As it is intended to be carbon
neutral, Nobelhorst is an ideal candidate for learning
from the lessons from cRRescendo.
But the area has its restrictions, as it is situated
above a drinking water reservoir. Therefore, use of
the underground for heating and cooling purposes is
prohibited. Several research studies were conducted
to solve this issue, e.g. one in which a system was
studied to use the area 500 meter up north, beyond
the restricted area and another one in which only the
shallow system (10 meter below surface) was used.
In the Netherlands dwellings happen to have a larger
demand for heat than cold. Therefore one normally
needs to regenerate the soil in residential areas where
underground heat and cold is deployed. The heat can
be delivered for example by a nearby existing biogas
cogeneration unit. Another possibility is to combine
residential with business areas and to deliver “cold” to
the business area.
Wind energy potential
In 2011 and 2012 research has been done on how
much wind energy can be deployed in Almere. These
wind energy options relate directly to the energy
supply contract for Almere Poort and therefore to
Columbuskwartier: NUON must provide 100% green
electricity. The feasibility study showed that 10 existing
1.65 MW windmills of Almere Pampus can provide this.
Now, but also in the future (when the district grows), as
the turbines can be replaced in the future by larger ones.
The energy supply contract for the Poort district also
requires that 10% of sustainable energy has to be
produced locally, which is not yet achieved by the 689
kWp solar PV panels within the cRRescendo project.
New wind turbines in the area are an option. From
technical, environmental and landscape point of view
a lot is possible with large wind turbines in Almere.
Smaller urban turbines are also an option, but because
substantial power is needed, the emphasis will be on
large turbines.
Although some conflicts with the existing provincial
and national policy have to be solved, over 100 MW of
new wind power can be located in Almere. Partly on
municipal grounds and partly on private ground. If so,
wind can contribute up to 25% of the sustainable energy
production for an energy-neutral Almere in 2025.
Studies show that acceptance of wind turbines near
housing depends largely on adequate information and
the possibility for inhabitants to profit financially.
Therefore, the municipality must facilitate financial
participation. Lately also options and choices for bottom-
up initiatives to participate have been studied with very
28 new energy for growing communities
interesting results. The so-called “Deals for Sustainable
Almere 2012-2014” (September 2012) are important
municipal policy statements on wind energy.
New solar PV business models
In Almere (cRRescendo) hundreds of houses
and several other municipality-owned
buildings have been equipped with solar PV
panels. Almere is experimenting and preparing
new business models for PV. In the so-called
“Company”on” model (in Dutch: Bedrijf-Zoekt-
Buur), company-owned solar panels are
installed on the roof of an employee, a client,
or a neighbour. The model combines a tax
deduction opportunity for the company with
delivering high-value electricity at consumer
tariff level. The inhabitant gets a solar system
free of investment and pays an annual fee to the
company for the consumption of the renewable
energy. A similar model was developed placing company-
owned solar panels on local government buildings.
The model has been tested in Amsterdam with school
buildings.
For and with the community
With the Almere Principles in mind, Almere wants to
develop to a sustainable city not only on a ecological
base, but also socio-economically. We think that our
people make the city: the residents of the CONCERTO
communities are the driving force for creating sustainable
communities and , and the Almere’s citizens in general
eventually for a smart sustainable city. In the project
we have put great effort in informing our citizens and
involving them. From the youngest child to the most senior
citizen, or again referring to the “Principles” from Cradle to
Cradle.
1.8 Towards smart energy-neutral in 2025
Masterplan Energy Almere
A major result of cRRescendo research and the adoption
of the lessons-learnt for Almere is the Masterplan
Energy Almere 2.0 (MEA). The successful Solar Island in
Noorderplassen West, the Passive Houses and the Solar
Houses in Columbuskwartier fostered the belief that
Almere might become energy-neutral. In 2011 the MEA
study was commissioned by the province of Flevoland,
as part of the collective quest with the national and
local authority to double the city’s housing capacity
and increasing its quality (= “Almere 2.0”). The target of
energy-neutrality from 2025 onwards and iconic measures
for the short term (2012-2014) were undersigned by
Almere, Flevoland and the Ministry of Infrastructure and
Environment in September 2012.
On-going studies on wind energy, solar panel boosting,
a greener heating network and geothermal energy were
integrated in this study. The target of energy neutrality
in the municipality is allowed to be partly obtained with
renewable energy capacity in the surrounding province.
The baseline scenario to 2025 showed that with a
growth of 50,000 households, generic trends in energy
consumption lead to an autonomous energy consumption
of 9,8 PJ. This is partly covered by 1,84 PJ locally produced
sustainable energy, mainly due to market penetration of
solar panels.
The energy vision of Almere for 2025 consists of
4 elements:
- extra energy savings
- exchange of energy
- shifts in energy carriers (gas to electricity)
- local and regional production of Sustainable energy
Within reasonable constraints, 20% extra energy savings
and energy exchange can be deployed, leading to 1 PJ of
end-use reduction. A total of 3.9 PJ/yr can be produced
with wind, solar, biomass and geothermal capacity within
the city boundaries. The remaining 4.9 PJ can be achieved
in the surroundings using wind, biogas and geothermal
capacity. Thus, 44% of the net energy consumption can
be produced within city boundaries and 56% from the
surroundings. Realisation will require large investments
but also creates jobs.
“So now even people with little
capital can get solar panels. We
made interesting business cases for
both the company and the resident.”
Anne Marie van Osch, cRRescendo project manager sustainable energy Almere
Alderman Ben Scholten planting a tree at the opening of the Passive Houses
towards a zero carbon city 29
20102025baseline
2025MEA 2.0
2025 MEA 2.0+surr
End-use (PJ) 7.2 9.8 8.8 8.8
Sustainable production (PJ) 0.65 1.84 3.9 8.8
Reduction CO2 (kton/year) 90 232 414 800
Net CO2-emissions (kton/year) 560 656 386 0
Local investments (M€) 1,167 1,745
New jobs in person years 3,823 4,866
Policy changes
On European level, implementation of sustainable
energy requires a level playing field, combined with
temporary incentives. In Almere some fundamental
regional policy changes are required as well for this
energy transition to succeed, such as:
- the provincial policy on wind energy is to be revised
- expanding legal and financial options for solar power
- consider a regional sustainable energy organisation.
Several business cases have been selected, based on
their energy potential and their expected feasibility.
In these the combination of public and commercial
parties, pension funds and specific banks (public private
partnerships) allow for a lower, and socially responsible
rate of return. (e.g 5%). The presence of a willing and
financially solid municipality is essential to achieve and
finance this energy transition.
Regional networks
Almere is working closely in a network of 35 other
local governments and the provinces of Flevoland and
Noord-Holland in the Amsterdam Metropolitan Area
(Metropool Regio Amsterdam). This region wants to be
energy neutral in 2040, using only renewable energy
and no fossil fuels. Jointly, studies are conducted and
working conferences for aldermen are held. Also in this
network cRRescendo houses en demonstrations in
Almere are used as a guiding example.
Beyond cRRescendo: the making of the Floriade 2022 Immediately after the project end date of cRRescendo,
in September 2012, the Dutch Horticultural Council
(NTR) announced that Almere is chosen to organize the
7th edition of the Floriade. The themes of the Floriade
2022: greening, feeding, energising and healthying the
city, align perfectly with local, national and European
issues. Almere as a growing city wants to create a
“smart” green city where energy is generated, rather
than used alone. She wants to achieve a circular
economy where waste is transformed into raw
material in closed and sustainable cycles. And a bio
based economy, so a revolutionary transition from an
economy that runs on fossil fuels to an economy that
runs on biomass.
Scenarios baseline and MEA 2.0 and MEA 2.0+surr
Almere Floriade 2022 will be parrallelled by the most ambitious urban development and will pave the way towards an energy and carbon neutral Almere in 2022
30 new energy for growing communities
A special concept within CONCERTO projects is the presence of associated partners
or so-called observers (often municipalities) in the consortium that carries out the
project. cRRescendo adopted this concept as a primary means to disseminate lessons
to other municipalities in Europe.
When the project kicked off, observers were easily interested to actively participate in
cRRescendo. Peer reviews and excursions to best practice communities were well attended
and inspiring for both observing and the four core municipalities.
However, during cRRescendo’s third to fifth years, it became harder to interest the observers.
There simply was not enough direct gain from the project for observers to allocate substantial
human resources. Eventually, we were able to attract the observers’ attention again by
demonstrating the results of the projects in four main cities, and by showing ways to increase
their own direct gain in the project.
Looking back we can see a clear positive impact of cRRescendo on the observing communities.
For instance new EU project proposals by observers reach higher quality levels. During our
evaluation it was interesting to learn what results of cRRescendo can be applied to other cities
in general and to the observers in particular, and what results may need tuning to the specific
constraints of another community or region.
Misterbianco (Sicily), Italy
Misterbianco is an important commercial
centre in the north-western part of Catania
on Sicily. Its population of 50,000 inhabitants
is spread out over a vast area. Suburbs occupy
half of its surface while commercial facilities
occupy 30%. In sustainable development,
Misterbianco takes into account two different
autonomous developments:
- the growth of the suburbs and;
- the stagnation of the historic centre.
The main renewable energy source in the
Misterbianco territory is solar energy for
electric energy with photovoltaic systems and
for thermal energy through solar collectors.
Misterbianco wants to become one of the
first solarised cities on Sicily. To achieve this
main medium-term goal a great commitment
on the short term is required:
1. Installation of about 4,000 m² of
photovoltaic panels on the roofs of urban
buildings;
2. Installation of about 6,000 m² of solar hot
water collectors;
3. Reduction by 10% of the energy demand in
the commercial area.
Sergio Campanella: “We were stimulated by
cRRescendo from the start to present the
EU state-of-the-art in Misterbianco and to
prepare a Local Action Plan. Preparation of
this continuous plan and the dissemination
of results afterwards were subsidized by
the EC, but for the realisation of the actions
a much larger investment was done by the
Misterbianco community.”
Four cRRescendo actions were applied in
Misterbianco:
A. Realisation of PV and thermal solar plants
in public structures
B. Citizen sensitisation
C. Interventions towards families
D. Interventions for saving energy in public
lighting
From observer to doer
towards a zero carbon city 31
Sofia, Bulgaria
Our largest observer community is Sofia,
capital of Bulgaria. Sofia carried out several
detailed surveys, for example on the
“Possibilities for the Use of Renewable Energy
Sources and Energy Saving Technologies
in Municipal Buildings”. In addition a pilot
in a central (“Vazrajdane”) and a peripheral
(“Vrabnitsa”) district of Sofia was performed.
An activity with direct impact was the
Zapiska project. The main objectives
of this research were: establishing a
complete programme for the utilization of
hydrothermal resources on the territory
of Sofia, rehabilitating all municipal
baths buildings, and refurbishing their
environment. This Zapiska research included
the assessment of hydrothermal potential as
well as the environmental impact.
The realization of the refurbishment
programme is warranted by grants to Sofia
from Bulgaria’s Ministry of Environment and
Water.
Nadia Nikolova: ”Sofia has been an observer right
from the start. One of the main practical benefits
of this relationship was that Sofia became a main
partner in a more recent CONCERTO-II project
STACCATO. Sofia was introduced to STACCATO by
cRRescendo partner Ecofys.”
Two important sustainable developments
have followed the implementation of
cRRescendo in Sofia. First, investments
directed at reduction of energy consumption
were realized at nine schools in nine districts.
Repairs and refurbishment of the school
buildings will result in 53% lower energy costs
because of a decreased energy consumption
by 3,823 MWh. Second, the Mayor of Sofia
has become involved in the Covenant of
Mayors, a European cooperation committed
to increasing energy efficiency and the use of
renewable sources.
San de Sénart, France
The community of Sénart comprises of 10
towns and villages, with 110,000 inhabitants.
Sénart is located 35 km southeast of Paris. It is
the youngest of the new towns surrounding
Paris, and is still growing rapidly.
San de Sénart has intensified the
participation in the final period of
cRRescendo, when it became possible to
combine cRRescendo actions with their own
plans: the Local Housing Programme and
the Sustainable Energy Action Plan. Sénart
undertook two main actions.
The successful conference “Sustainable
development and social housing
refurbishment”, in 2007, involved most
of Sénart’s social housing organisations.
Afterwards, these social house owners
measured the energy performance in
housings. Results were shocking. Since
then, social householders quickly became
innovative, have undertaken actions to
refurbish 15% of the investigated housings
and to make energy improvement works on
54%, up to 2015.
Nathalie Dupont: “We learned that monitoring is
important, a new way of thinking for us. This might
be a stimulant for future building programs. One of
our local partners, the housing corporation Relais
Jeunes 77, intends to build a residence for young
people in 2014. Installing monitoring systems in
these residences could be a way for them to watch
energy and water consumption in accommodations
they manage.”
Together with social owner Relais Jeunes 77,
Sénart developed an interactive tool, called
“Max & Soraya learn eco-friendly behaviour”,
to raise young people eco-awareness and
behaviour. The “Max & Soraya” movies are
broadcasted on the Sénart website.
32 new energy for growing communities
2.1 Milton Keynes – the scene
UK’s largest new town
Milton Keynes is situated midway between Birmingham
and London. It is the largest urban development project
ever undertaken in the UK – a “new town” - with an
expected eventual population of about 250,000 people,
primarily built to accommodate the growth of the London
area. The City was designated in 1967 at which time the
area’s population was approximately 40,000. From the
1970’s through to the 1990’s Milton Keynes established
itself as Britain’s fastest growing urban area and has
remained one of the fastest growing areas up to the
present day. The City has evolved as a major regional
centre. Currently approximately 210,000 live in the new
city. Almere and Milton Keynes are so-called Twin Towns.
Milton Keynes Development Corporation
The early development of the city was the responsibility
of Milton Keynes Development Corporation, which was
established by the central government. The Master Plan
for Milton Keynes was published in 1970. It was devised
as a strategic framework capable of responding to
changing needs, rather than a town map or a “blue-
print.” Six guiding principles were identified, one
of which addresses sustainability: “Efficient and
imaginative use of resources.”
The power of heat Milton Keynes
2.1 Milton Keynes – the scene
2.2 A suite of sustainable projects
2.3 Vizion – iconic building as an urban landscape
2.4 Office of tomorrow - The Pinnacle
2.5 Combined heat and power generation
2.6 PV power plant on former bus station
2.7 Moving forward
2
Central Milton Keynes
the power of heat 33
The Master Plan also recognised the close
connection between transport systems and
the arrangement of land uses and the need
to consider these two fundamental elements
together. A unique “grid” pattern of main
roads - intersecting at approximately 1 km
intervals - stimulates dispersed land uses
throughout the City. The dispersal of homes
and jobs allows for an even distribution of
traffic.
The Development Corporation put in place
much of the city’s infrastructure and oversaw
its rapid and large-scale growth during the
1970’s and 1980’s. When the Corporation was
eventually wound up in 1992 its remaining
land and property assets were transferred
to the Commission for the New Towns
and, subsequently, its successor English
Partnerships, the National Regeneration
Agency.
2.2 A suite of sustainable projects
Central Milton Keynes was designated as the “city centre”
and an exception to the principle of dispersed land uses.
It was envisaged that Central Milton Keynes should
contain a substantial shopping centre, cultural and
leisure activities/facilities, housing and offices to serve
the population of the new city and the surrounding area.
With at its heart a sustainable residential quarter.
Embracing Sustainable excellence
The objectives of the CONCERTO programme resonate
directly with the challenges faced by Milton Keynes
as it matures into a significant regional centre. There
was a good “fit” between the emerging vision for the
“The ambitious CONCERTO projects
have created nation-wide exposure
for Milton Keynes and made a
huge difference to the communities
where these projects are based.
Milton Keynes now benefits from
sustainability pathfinder status
and we are pleased the HCA has
been able to support partners to
boost the town’s growth potential
as a destination of choice for urban,
environmentally-conscious citizens.”
Margaret Allen, Executive Director, HCA Midlands.
municipality and the realisation of ambitious projects:
the physical deliverables associated with cRRescendo/
CONCERTO. Projects and policy in unison!
The UK Government under the Sustainable Communities
Plan designated Milton Keynes as a “Growth Area” in
2003, and subsequently in the Milton Keynes & South
Midlands Sub-Regional Strategy. A long-term vision was,
therefore, developed to guide the proposed expansion of
Milton Keynes.
Jeremy Draper, Senior Practitioner, Environment Team, Milton
Keynes Council: “The Milton Keynes Local Plan, adopted in 2005,
included an ambitious sustainable construction policy (known
as Policy D4), stipulating that all new development above a
certain size must be ‘carbon neutral’ or offset its emissions
within the city, incorporate renewable energy technologies to
deliver a 10% reduction in CO2, feature water conservation and
drainage technologies, and use sustainable building materials
and minimise waste.” At the time of its introduction
this policy was seen as “pushing the boundary” in
terms of reducing the resource consumption of new
development and achieving zero carbon growth.
The aspiration of developing MK into a ‘showcase low
carbon city” was later articulated in the Low Carbon
Prospectus (NHBC Foundation, 2010). Jeremy Draper: “The
prospectus presents a vision for reducing the environmental
impact of buildings and transport through a wide range of
initiatives involving a diverse range of stakeholder groups.”
The cRRescendo initiative
Four separate developments with ambitions beyond
standard regulations were realised in Milton
Keynes within the cRRescendo project: the
Vizion, the Pinnacle, a Combined Heat and
Power plant, and a large PV system.
Jeremy Draper and Jon Muncaster (Senior Urban Designer,
English Partnerships) concur: “the CONCERTO programme has
been instrumental to achieving the sustainability and quality of
these projects.”
The developments cover production and use of heat, cold,
and power and demonstrate sustainable consumption
in domestic and commercial use. The commercial use
consists of office and shops/retail. Two of the projects
achieved national exposure in the UK.
!Eco-buildings and combined heat and power plant in Central Milton Keynes, the 165 kWp PV system is located on the old bus station near the station just west of this area
34 new energy for growing communities
Vizion Apartments with award-winning Roof Garden landscaping
Vizion - inner courtyard (Left)Vizion - streetview (Right)
the power of heat 35
2.3 Vizion – iconic building as an urban landscape
The Vizion complex is a high quality vertical mixed-
use development by Abbeygate Developments Ltd.
The English Partnerships competition winning design
by q2 Architects is a vibrant high density mixed-use
development which not only creates a landmark
for Central Milton Keynes but also addresses the
city’s sustainable development objectives. It was
completed in April 2009. The development contains
441 apartments and townhouses, a large Sainsbury’s
store of approximately 10,000 m2 and another 4,100
m2 commercial and retail units. The 441 residential
units are distributed over 14 blocks totalling 26,887 m2.
Buildings gradually step up in height from 4 to 12 storeys,
providing active frontages to the existing streets,
increasing connectivity to adjacent areas and providing
non-obtrusive security by maximising sight lines to the
main footpath routes.
An Enhanced Building Fabric (EBF) was deployed to raise
the standard of the building thermal characteristics
beyond national regulatory requirements. Better
insulation of walls, roofs and windows, and less air
changes per hour were applied. These building thermal
characteristics of the apartment blocks were based
upon the cRRescendo Specifications. In addition,
water saving fittings were applied throughout to
reduce demand for hot water. Jon Muncaster: “Our initial
plans were much more distinguishing with respect to the
national regulations of 2001. But as we encountered delays,
and regulations were sharpened in 2003 and 2005, the lead
evaporated partly. A strange effect of time.”
All buildings are designed with advanced energy
performance, to meet BREEAM “Excellent” and Eco-
Homes “Very Good” ratings. The electricity and heating
are supplied by the CHP system. Residential units have
large balconies, which also provide solar shading. A
pleasant open streetscape is maintained by providing
two levels of basement parking below the main
buildings.
How do residents perceive their Vizion apartment? Are
they aware of the energy measures? Partly, seems to
be the answer. A questionnaire was distributed to the
inhabitants, and 28 replies were received.
36% of the respondents were aware that their
apartment block was connected to a combined heat
and power plant, and 43% that it was specially designed
for less heating and fitted with efficient lighting and
Landscaped courtyard Vizion
36 new energy for growing communities
appliances. However, regardless whether people were
aware of the measures implemented two-thirds are
actually happy with it.
John Piggott, Associate Director, Arup: “Many prospective
residents are nervous about taking heat and power from a CHP
scheme (which is still an unusual arrangement in the UK). They
prefer dealing with a big utility company that they recognise.
Hence the “anonymity” of the energy supplies in Milton Keynes
is actually a real positive outcome. Many sustainability projects
in the early 2000s were making “statements” that sometimes
backfired if the costs went up or the technology did not deliver.
Milton Keynes is a refreshing change because it is low-key and it
just works.”
The design and layout, daylight through windows,
and the general comfort of their flats are rated at the
highest level by two-third. One third of respondents
also conveyed the highest degree of satisfaction with
the heating and level of humidity in their homes. These
are partially due to the energy measures, as many other
physical elements of the apartments (e.g., layout, day-
lighting), which are in effect there.
High quality landscaped courtyards are a major feature
of Vizion. The 0.5 ha large, “green roof” of the Sainsbury’s
store doubles as a magnificent podium garden for
residents. Frosts, landscape gardeners, won a Bali award
for the garden landscaping in 2009 for these landscaped
communal gardens and pocket park with play facilities.
In a Sustainable Project Appraisal Routine assessment
undertaken by Arup in 2012, the site selection, facilities
management and energy and water use indicators were
all scored as “best practice.” These achievements are
considerable and represent real successes for the scheme.
This development was a significant milestone for the
city centre. It was the first scheme to respond to the new
Development Framework for Central Milton Keynes. The
design and quality of this scheme are very visible, and set
a “benchmark” for future development. The sustainability
measures are invisible - quite ironic considering the
name of the building. The Vizion is an icon, as name
and content coincide perfectly; a landmark for Central
Milton Keynes and answers to the city’s sustainable
development objectives.
2.4 Office of tomorrow - The Pinnacle
The Pinnacle, developed by Hampton Brook, is a
high-quality office scheme incorporating an element
of mixed-use. The design has attracted leading
companies such as Deloitte and Touche. It is the first
BREEAM “Excellent” rated office development in Milton
Keynes using the Building Research Establishment
Environmental Assessment Method, with an A
rating Energy Performance Certificate. It was winner
of an Office Development Award for Sustainable
Achievement. The Pinnacle accommodates three
commercial offices and several smaller retail units, with
over 19,000-m2 commercial space.
The enhanced building fabric was applied to raise the
standard of the building and the thermal characteristics
beyond regulatory requirements. The CONCERTO
standard of insulation was used as a basis for these
offices. Heat, cold and electricity are supplied by the
CHP system.
The Pinnacle uses more energy than was targeted, but
there are good reasons for this. John Piggott (Arup):
“Generally, office space is more utilised now than a few years
ago, as businesses are tending to put more people into the same
space, to get better value for money from their real estate.
Combined with the constant rise in the use of IT, this means that
office space is using more energy. The energy used per employee
is not increasing. So maybe we need to rethink our metrics in
future.”
The Pinnacle Commercial Offices
the power of heat 37
The Pinnacle Commercial Offices
How do occupants feel about the building? Overall,
survey data (Oxford University / HCA) show that the
building is performing well for the occupants. A quarter
knows the building was connected to a combined
heat and power network. Approximately half knows
the building was designed to be energy efficient and
half of the respondents said they thought the building
was performing efficiently. Only thermal comfort lags
behind, as one-quarter claims their work productivity
is reduced by the environmental conditions in this
building (e.g. thermal, lighting, acoustics). Ruth
Wharton (USEA): “We expected negative responses because
of a resentments against the landlord. But overall, responses
were moderate. Nevertheless the comments called for
implementation of improvements.”
38 new energy for growing communities
Name (Residential) Measures Number of homes Gross area per house m2
The Vizion (14 blocks)
District heating with Combined Heat and Power
441 61
High insulation
Non-residential Name Measures Buildings / functions Realised Gross m2
The Pinnacle
District heating/cooling with CHP
Office building A 9,010
Office building B 7,396
High insulation
Office building C 1,875
Small retail units 955
The Vizion District heating with CHP
Supermarket 10,000
10 retail units 3,000
Commercial office space 1,100
Total 33,336
Name (Power plants)Installed (kW)
Production (MWh/year) Measures
Energy Station (Combined Heat and Power System) 12,224
Heat: 13,277Electr.: 15,632
Two engines (of 3.07 MWth and 3.04 MWe each)
Connected to 925 residential units (Vizion: 441 and the Hub: 484)
Connected to commercial spaces Vizion and office building the Pinnacle
Photovoltaic Power Plant 165 92 825 panels of 200 Wp each
Total 12,389 15,724 (Electr.) + 13,277 (Heat)
Overview cRRescendo Eco-buildings, renewable energy, and polygeneration in Milton Keynes
the power of heat 39
2.5 Combined heat and power generation
What it is
Combined Heat and Power (CHP) operates on the
principle of using waste heat of electric power
generation. The heat produced is channelled to heat and
cool buildings and/or provide domestic hot water. In
conventional power plants heat is being wasted, leading
to efficiencies (in the UK) of maximum 60%. In contrast,
Combined heat & power plants can achieve an efficiency
of over 80%. CHP systems are generally most efficient
when there is a mix of demand: residential, retail,
schools/colleges and/or businesses. This mix creates
a more constant need for heat day and night. A CHP is
generally connected to the mains power grid for back up
electricity and the opportunity to sell “excess” electricity
back to the grid.
Steady growth of demand
In 2007, Thameswey Central Milton Keynes Ltd. was
established to construct and operate a Combined
Heat and Power station, to deliver district heating and
electricity via a private wire network to newly developed
areas in Central Milton Keynes. The Energy Station is
located on Avebury Boulevard. Jeremy Draper: “During
design and planning process an objection came up regarding
the 80 m high chimneys, which was thought to spoil the
skyline. But after completion and inclusion in between the
buildings, they proved to be barely visible.”
A 3.04 MWe and 3.07 MWth Combined Heat and Power
(CHP) system was built as part of cRRescendo. A second
engine, of the same size, was added in 2009 to facilitate
expansion of the system (not part of the cRRescendo
project). This increased the total capacity to 6.08 MWe
and 6.14 MWth. At the heart of the station are two CHP
units that are fuelled by natural gas and have an electrical
output of 3.04 MWe each. The area served currently has a
radius of about 1.5 km, and the total area served is 90.000
m2.
But not all buildings were connected from the start.
Rather, a steady growth of connections was realized over
a few years. Initially, in 2007, “the Hub” (a development
comprising 484 apartments, 30 shops and offices) and
the Vizion buildings (with 441 apartments, commercial
outlets and a large Sainsbury store) were connected. Two
years later, the office building Pinnacle was connected.
This required expansion of the Energy Station with the
second engine, maintaining spare capacity for future
residential /commercial development in the west end of
Central Milton Keynes.
CHP is selected by forward-looking organisations as a reliable heating and cooling technology
Energy Station & chimneys
See also page 59 for Case:
Investing in CHP
40 new energy for growing communities
!Jeremy Draper: “The CHP plant is barely
noticed anymore. I believe an engineer is
successful if it works and nobody notices.
So in my opinion this has been a very
successful project.”
The spare capacity proved valuable, because in 2012,
the Network Rail Headquarters the “Quadrant”
development was connected to the CMK CHP system.
The “Quadrant” development, comprising 38,000 m2
will provide accommodation for approximately 3,000
Network Rail staff. Paul Hammond, Area Manager, MK Land
Team, HCA: This expansion to the Network Rail headquarters
is a strong vote of confidence in the CHP to deliver cost
effective heat and power. They wanted to be associated with
us, a forward looking community, and we of course wanted
those high-value jobs in our town.” The Quadrant is located
outside the original CHP project development area,
and therefore, there was no obligation for the client
to connect to the district CHP system; the decision
for Network Rail to connect to CHP was made on a
comparison, which involved the other energy solutions.
But some negotiation was done: Jeremy Draper: “Instead of
full conformance to the D4 policy, it was agreed to do something
special and to achieve BREEAM Excellent.”
How different from ten years ago. In 2000, in the UK,
experience with CHP and confidence in District Heading
were minimal, because of the imprinted history of bad
projects of the 1950’s and 1960’s. Jon Muncaster:
“The common opinion was: CHP won’t work in this country.
But there was an initiative in Woking for CHP in central town
offices. A visit there made us enthusiastic.” The Chairman
of the Board of Development Corporation suggested
bidding for European money. Jeremy Draper: “This EU
funding made the project financially attractive enough
to go ahead.”
The lesson here is that with modern technology
and management, and with a long-term vision to
exploitation, prejudices can be countered: CHP proves
competitive. The CHP Energy Station has become a
nation-wide example of good practice. Jeremy Draper:
“Our example helped solve the chicken-and-egg problem
around CHP. Without the confidence of an existing scheme, no
one ventured into it. And with no new examples, the prejudice
against it remained alive. Now, project developers are much
more positive towards it. Now the Energy station’s management
is looking for opportunities to expand towards the shopping
centre and the skiing-hall.”Energy flows in the Energy Centre
gas in (boiler, CHP)
100%
generationlosses
32%
elec.
37% elec.
29 %
elec. export 3%
elec. lost 5%
heat
31%
heat
25%
heat lost 6%
heat used other area’s 19%
elec. used other area’s 29%
heat cRRescendo 6%
elec. cRRescendo 9%
ele
c. im
po
rt 9
%
the power of heat 41
CHP Performance
Taking all flows into account and generation losses
and including electricity import and export, of the
energy flows can be constructed, for instance in a
Sankey Diagram. It unveils the flows and losses that
occur in between the production and the consumption
of electricity and heat and including import and
export of electricity. 38% of the primary energy in the
gas is converted to electricity that can be used for
consumption (including export) and that 25% of the
heat is converted to useful heat for consumption.
Balancing the energy
How do the 4 projects (CHP, Vizion apartments,
Pinnacle offices, and PV) now balance in energy?
The majority of the electricity (86%) and heat (97%)
consumed stems from the CHP plant. It is mainly
used in the private wire system and district heating is
delivered from the CHP engines. There are interesting
opportunities for improvement, but here we focus on
the overall balance.
Energy balance cRResendo project
production
heat
electricity
heat
consumption
electricity
Pinnacle
Pinnacle absorption cooling
Vizion
The Hub
CHP
imports, exports, losses
boiler
The electrical generation efficiency of the CHP was
37% and the thermal efficiency was found to be 30%.
This corresponds to manufacturer’s nominal electrical
efficiency of 42% and thermal efficiency of 43%,
considering the degree of over-sizing of the central plant
to accommodate future expansion. With one of the
machines often all that is required to meet the demand,
and partly operating on part load for significant periods.
And overall 30% of primary energy is saved in Milton
Keynes thanks to cRRescendo. Close to the target of
38%. The reduction in primary energy is partly due to the
increased efficiency of the buildings and partly due to the
CHP. The difference compared to the CONCERTO target is
mainly caused by two effects: a larger energy consumption
of commercial sites e.g. due to large glass surfaces and
high occupation levels in offices, and because the CHP is
operating at partial load, which will improve in the future.
It can be concluded that, on one hand, significant
savings have been achieved. On the other hand, there is
still potential for improvement.
42 new energy for growing communities
2.6 PV power plant on former bus station
The search for a site
One of the objectives was to develop a “renewable
energy” component in the Sustainable Residential
Quarter in Central Milton Keynes (CMK). Because this
West End development had to be postponed due to
adverse economic conditions an alternative strategy
had to be adopted. In November 2009 the Milton Keynes
Partnership Senior Management Team approved to
install a photovoltaic (PV) array of 165kw in the Centre.
But where to put it?
Most appealing was to incorporate the PV on the Vizion
or Pinnacle. These had already been completed and
negotiations involving the developers and occupiers
ultimately ended unsuccessfully. Another option was a
ring-fenced “ground-level” PV installation on a vacant
site. This option had the advantage of flexibility:
when development of the site took place, the PV
installation could be removed and then “lifted” into
the roof design. However, the costs associated with
ground level location (such as security) and removal and
re-installation at some future date, and the anticipated
disturbance of energy production during a potentially
lengthy relocation period made it unfeasible.
Excellent location
Finally, the former bus station - a property in HCA
freehold ownership - was settled on as the most
appropriate site for the PV installation. It is an
excellent location: a two-storey building with a large
flat, overhanging roof area, open to the sky and not
overshadowed from any direction by any development
or structure. Following a competitive tender process,
the PV installation - one of the largest “retro-fitted” roof
based arrays in the UK to date - was completed in March
2012. In total, 825 panels, made of polycrystalline silicon,
were installed. A mini weather station monitors the
ambient air temperature on the roof. A maintenance
and operation contract between the HCA and the
installing contractor was agreed.
Architectural and roof integrity
One principal planning issue and one technical issue
literally posed “boundary conditions” to the PV system.
The installation had to respect the “architectural
integrity” of the existing building. As a consequence,
and to make the array acceptable in planning (i.e.
development control) terms, the PV arrays have
been installed at an angle of 5°. This slightly reduces
operational output and thus income. The roof of the
bus station had been renewed not long before and
installation of the PV array had therefore not, been
anticipated. The new roof membrane could not be
punctured to facilitate the installation of the PV array.
Consequently, a bespoke engineering design had to be
devised for the supporting “steels” to create a suspended
roof frame, increasing cost.
Electricity sales
The output from the PV is continuously monitored
through a web portal and the energy and carbon data
are prominently displayed at the building entrance. The
first half-year period February - August 2012 showed
that the PV array had generated 92.5 MWh of electricity,
saving 49 tonnes of carbon. The electricity produced is
delivered free of charge to a youth community interest
company. The PV operator sells the excess to energy
company Good Energy. The electricity that is exported
to the grid is monitored and metered on a half-hourly
basis by metering company Stark Energy.
Persistence (time was not on our side)
Ambitious, subsidized projects always are challenging
because application deadlines put pressure on decision
making whereas the waiting time and negotiations
to get approval cost much time. In Milton Keynes, this
played a major role in the final project choice during the
negotiation phase with the EC in 2005/2006. During the
course of this time, numbers of apartments went down,
but the ambitions rose considerably. Brad Hook, United
Sustainable Energy Agency: “And with time, national regulations
changed. Now we even have a feed-in tariff for PV.” Two major
time consuming factors have contributed to the drastic changes:
subsidy negotiations and the financial crisis.
Negotiating subsidy application
Due to the long time period between the submission
of the original bid in December 2003 and completion
of the contract with the EC in July 2005, commercial
and programme pressures forced some of the early
developers to start on site before the CONCERTO
contract and its requirements were finally agreed
the power of heat 43
PV Installation on former Bus Station, Central Milton Keynes (upper left)
Inverter room PV system (right)
Secondary steelwork structure elevates the PV panels and protects the waterproof roof membrane (lower left)
with the EC. Jon Muncaster: “The result of this was that a
significant portion of the planned developments “the Hub”
in cRRescendo had already been designed and planned by the
time the cRRescendo contract came around. By then, it did not
have sufficient ambition to qualify as cRRescendo development
anymore. As PV panels were planned to be installed on the
original buildings, this also jeopardised the renewable energy
contribution to the project.”
!The flexibility shown by the EC towards
the CONCERTO contract to be revised and
extended was very supportive for
achieving physical deliverables. The
unprecedented economic downturn had a
significant adverse impact on the UK development and
construction industry. This flexibility was also critical to
other European consortium partners. The flexibility
shown by developers of, then, recently completed
schemes was also critical in helping to achieve the
required physical outputs. A search for replacement
projects commenced.
Global financial crisis
The global financial crisis developed since 2007 severely
affected the UK housing market. Results for cRRescendo
were that progress in negotiations for including other
building developments first slowed down and at a later
stage it turned out that the new building plans were
unviable altogether. Jon Muncaster: “The plan was to develop
a “community” in the form of the Sustainable Residential Quarter
located in Central Milton Keynes, centred on the West End Phase
1. This plan was a dramatic leap in quality, with for instance air
tightness unknown in the UK. However, this scheme, comprising
650 homes and a 420 place combined school, stalled when
the global “credit crunch” / banking crisis resulted in economic
downturn. There were too many apartment developments in
preparation.” This has led to the withdrawal of (building
4 Phase 1) / (West End Phase 1) which included the
primary school intended to meet the needs of the larger
community.
Re-Development
So: an empty portfolio. Jon Muncaster: “But we kept
committed to the contract, Milton Keynes could delve into its
array of development plans. The practicality of including an
off-site anaerobic digestion plant was investigated, (fuelled by
kitchen and garden waste) to produce biogas for the CHP unit.
This was not viable for financial reasons.” The Anaerobic
digestion plant is being built, but the gas generated will
be used for a variety of local uses, including replacing
liquid fuels used for waste collection vehicles.
The CONCERTO contract was re-negotiated to
incorporate two previously planned schemes in Vizion
and Pinnacle, including the connection of them to
the Combined Heat & Power (CHP) plant. The CHP
was enlarged to 3 MWe, from the original 1,4 MWe.
44 new energy for growing communities
Fortunately, the Pinnacle building already incorporated
absorption chillers in the basement, prepared for CHP
connection.
For the incorporation of renewable energy, in Milton
Keynes PV solar energy, it took longer to find a solution.
Paul Hammond: “Finally, the roof of the former bus stations was
found to be suitable for installing 165 kWp of PV panels. The
bus station functions as a home for a community interest group
which helps young people. It is located just across the road west
of the original cRRescendo project area and south-west of The
Pinnacle.”
This resulted in a smaller and less centralised project
than anticipated, but still with significant savings over
business as usual. And a close-knit suite of projects:
CHP, offices, dwellings, and PV plant. Thanks to
persistence on many sides. And everybody agrees, these
have been realised because of cRRescendo.
National/local partnering
!The primary stakeholders have been
English Partnerships/HCA and Milton
Keynes Council, with planning and
development powers, showing political
commitment and financial commitment and
owning land interests. The positive dynamic between EP/
HCA and MKC illustrates how organisations working to
different national and local “drivers”, and assisted by the
valuable input of other consortium partners, effectively
combined to realise common sustainable development
objectives through the cRRescendo programme. A good
“connect” was established with other partners [e.g. Arup,
ECIOU, NEF and USEA] who have been principally
concerned with providing technical input, monitoring
outputs, undertaking research and associated report
production. The influence of MKC principally derives from
a combination its political power [e.g. local democratic
mandate] and statutory planning responsibilities; to
include “plan making” and “development control.”
2.7 Moving forward
Milton Keynes has joined numerous ambitious national
and international initiatives and networks. Jeremy
Draper: “We signed the Nottingham Declaration on Climate
Change, agreed in the frame of the LSP Local Area Agreement
on a carbon reduction target of 12% by 2019, and joined the EU
Covenant of Mayors, which required cuts in carbon emissions by
at least 20% by 2020.” Eventually the “Low Carbon Living
Strategy and Action Plan” was published by the Council in
2010, with the aim to target an overall carbon emission
reduction of 40% per person, and to place Milton Keynes
at the forefront of low carbon living, nationally and
internationally.
Spreading the word
The cRRescendo projects were highlighted and promoted
at the Low Carbon Living Seminar, held at Stadium: MK,
in December 2011. A further workshop was held with
stakeholders and cRRescendo partners in June 2012 to
disseminate information about the recently completed
PV installation.
Ian Byrne, Deputy Director, National Energy Foundation: “A
major benefit of the scheme has been to showcase the ability
of designers and developers to meet a benchmark with the low
energy requirements of the project, in the heart of a developing
city.”
This provides evidence that developers, in conjunction
with city planners can affect the market for low energy
housing and offices.
Development power and land interests
English Partnerships/HCA assumed “lead partner”
status in the Milton Keynes cRRescendo consortium
as a consequence of its planning & development
role and its ability to provide investment. The
designation of Milton Keynes as a “Growth Area” in the
Sustainable Communities Plan (ODPM, 2003) led to
the establishment of the Milton Keynes Partnership
(MKP) local delivery vehicle; a sub-committee of English
Land ownership is of great help to municipalities in ambition setting and maintaining
the power of heat 45
Partnership for implementation support for the physical
elements of the project (i.e. development). From the
Agency’s perspective, the initiative was corporately
driven. EP’s/HCA’s National Consultancy Unit
championed involvement in the project, negotiated the
associated contracts, and subsequently managed and
co-ordinated the European element of the project (e.g.
“City Co-ordinator” role and EU grant claim).
Basically, HCA had significant land interests in Milton
Keynes. The Agency owned in excess of 550 hectares of
land in Milton Keynes. This ownership included some
strategic land parcels in Central Milton Keynes, which
became the focus for cRRescendo/CONCERTO related
developments. As a consequence of its land ownership
HCA was also able to produce development briefs for
its sites which sought to “raise the bar” in terms of the
design and sustainability of development.
Involving the architect
With regard to securing planning permission for the
PV installation, commissioning the involvement of
the architect who had originally designed the former
bus station in CMK was, in hindsight, very beneficial
since this arguably expedited both achievement of the
required planning consent and, indeed, subsequent
installation of the PV array in accordance with the
West-End 1 development plan (not yet realised)
Retrofitting a building with solar energy can be a balancing act. The original architect can help find the equilibrium
project timeframe. Paul Hammond: “The “retro-fit” PV
installation represented a compromise between, on the one
hand, planning, building and technical constraints and, on the
other hand, the aspiration to reduce carbon emissions through
the delivery of a renewable energy system. Having the original
architect on board helped pave the way and find acceptable
solutions.” This compromise may have resulted in a
more costly - and marginally “sub-optimal” - PV array.
Nevertheless, the installation successfully fulfilled the
cRRescendo/CONCERTO renewable energy objective
whilst also addressing a variety of policy and technical
requirements.
Moving forward
It is clear that Milton Keynes has the capability to
develop low-carbon buildings. And moving on is needed.
New, more advanced policies are under development,
and the first “carbon-negative” building, a school, is
on the drawing board. Jeremy Draper: “Maybe we did not
publicise our achievements as much as we could have but we
are still proud of the powerful combination of forward looking
policies and projects generated by cRRescendo.”
46 new energy for growing communities
To support learning across projects the EC organised CONCERTO+ Premium activities.
In the European events in Brussels, our partners very much appreciated learning about
the results from other CONCERTO projects. In the national events, where more partners
attended due to less travel time, they appreciated talking in their own language about the
CONCERTO communities in their own country. Both were evaluated as key dissemination
actions.
Environmental education is a learning process that increases people’s knowledge and
awareness about the environment and associated challenges. It develops the necessary skills
and expertise to address the challenges, and fosters attitudes, motivations, and commitments
to make informed decisions and take responsible action (UNESCO, Tbilisi Declaration, 1978).
Energy education is a subset of environmental education. It focuses on increasing public
knowledge about the impacts of energy production and consumption. Energy training, on the
other hand, is a much more intensive process than education. It focuses on building skills for
experts interested in working in the field.
cRRescendo’s final dissemination activity was the successful cRRescendo ConfeRRence,
Step by step towards a carbon neutral built environment, held in October 2011 in the city of
Almere. 126 participants listened to high-level presentations and involved in lively discussions
on the results and impact of the project. All aiming to convince stakeholders that large scale
climate-neutral building is possible in the foreseeable future (2020). The proceedings can be
downloaded from www.cRRescendo.net.
Energy Rich activities to involve Almere residents
Communication experts advised that the
name cRRescendo would not resonate
enough with the local community. Therefore
the name Energy Rich (EnergieRijk in Dutch)
was invented. Under Energy Rich various
activities were organized for residents of the
communities and Almere in general:
- Opening festivities
- Open days
- Photo contest
- Treasure Hunts
- Educational activities
- Out-of-school events like
in the community
information centre Klokhuis
(opening by Queen Maxima, see picture).
After the delivery of Solar or Passive houses,
instructions were given to residents on how
to use their sustainable house or PV system.
Almere developed a sustainability training
and toolbox for residents who want to build
their own houses. These Private Contractors
are a new phenomenon in the Netherlands.
This toolbox included a voucher for free
professional advice on sustainable building.
In addition to residents, training was also
provided to professional target groups.
Training activities differed from sharing
general knowledge and lessons learned, to
very practical ones like on how to build energy
efficient houses or how to advise private
contractors on sustainable building.
Sharing local learnings
towards a zero carbon city 47
Enduring impact through Milton Keynes professionals
Milton Keynes has given priority to the training
of professional stakeholders and target groups
(although involved residents have also been
reached). Throughout the duration of the
project, training courses for design teams, PV
specialist installers, and building managers
have been offered. The project was closed in the
Low Carbon Living conference and exhibition
in 2011, highlighting the contribution of
cRRescendo.
The aim of almost zero-carbon buildings
could not be maintained due to the recession.
This resulted in disappointment for those
professionals involved from the very beginning.
Professionals more recently involved are on
the contrary very satisfied. They see that the
four developments are excellent examples for
stakeholders to replicate in a world in which the
sky is not the limit anymore.
Three demonstrations already have significant
impact on the development of building in both
Milton Keynes and the UK - some of them have
even shifted paradigms:
- The cogeneration heat/power plant is
followed throughout the UK;
- The ambitious Pinnacle office building was
followed by the NetworkRail headquarter in
Milton Keynes;
- The residential block Vizion is planned to be
copied just across the road;
- The Vizion residence is very popular among
residents despite the crisis.
Intensifying communication between stakeholders in Ajaccio
With regard to sustainable development, Corsica
was lagging behind other regions in France at
start of the cRRescendo project. To prepare the
refurbishment activities it was necessary for
the different stakeholders to work together. In
Ajaccio we learned that (to be equally successful
and timely realised) a refurbishment project
needs to be further prepared than a new building
project. A refurbishment is more complicated
in decision-making, and the residents that are
involved are not always willing or able to pay for
the improvement, even when it is economically
feasible.
As a result of cRRescendo, engineers and
architects in Corsica learned to communicate.
The municipality and the housing corporation
started to interact, and developers and residents
learned to understand each other. Excursions
to other cities of France and Europe (e.g. by
the mayor and professionals) stimulated the
conceptualisation of a more sustainable Ajaccio
and other parts of the island via a covenant
between 20 mayors on Corsica.
In the first cRRescendo training for architects
and decision makers it was concluded that
there was a severe lack of knowledge on the
island. In March 2012, to solve this Ademe gave
an in-depth training on the environmental
quality of buildings to about 20 architects.
Subsequently Ademe organized information
sessions in six micro-regions of Corsica, attended
by 25 professionals each, about the new thermal
regulation for new building called RT 2012.
Education for a sustainable future in Viladecans
From the cRRescendo cities Viladecans was
hit hardest by the economic recession and had
the greatest change between planned and
realised activities. Therefore, more efforts
were directed to general and professional
education for establishing the basis for future
sustainable development.
Over a four-year period, more than 1,000
children participated in 29 energy education
workshops.
These workshops ranged in topic from solar
kitchens, photovoltaic energy, solar thermal
energy to energy efficiency.
In addition 44 adults received training,
distributed across three different courses:
- A solar thermal and photovoltaic
installations course for unemployed people
from the building sector;
- Two full week courses on the assembly and
maintenance of solar thermal collectors;
- A full week course on the assembly and
maintenance of solar photovoltaic panels.
Viladecans also did substantial public
outreach and awareness activities. The
activities varied from a mobile municipal
office for informing citizens and a sustainable
house for the general public, to brochures
about the sustainable developments and
workshops for over 200 children (Solar Sports
Cars and Penguins Against Climate Change).
48 new energy for growing communities
3.1 Ajaccio – the scene
Ancient historic capital
Ajaccio is the ancient capital of Corsica with
65,000 inhabitants covering 82 km2. Ajaccio
is located on the Mediterranean coast with a
lively marina. The historical centre consists
mainly of old buildings. Since 2004, it falls
under the “Protection of Architectural, Urban
and Landscape Heritage”. The buildings
in the town centre as well as the suburb
areas are energy inefficient. Expansions
around the centre contain many 1960’s
apartment buildings, many in urgent need
of renewing. In 2002, a significant urban
renewal programme was started by the
City of Ajaccio, together with ADEME.
The programme includes several energy
measures.
!Facing the technological and financial
challenges of the more sustainable renewal
programme, Ajaccio decided to explore
international co-operation options.
Fast adoption of sustainability
At the launch of CONCERTO Ajaccio became more aware
of the need to reduce public energy consumption as well
as the energy use of social buildings tenants. The steps
towards a better quality of life, and with greater respect
of the environment were gradually set up. Virginie Bollini,
cRRescendo project manager at Ademe: “Until the early 2000’s
the city had little awareness for an environmental approach
towards buildings. Through the inception of the cRRescendo
project Ajaccio’s understanding and involvement grew towards
more conscious politics on the environmental issue.” The
ambitions of Ajaccio increased during the course of
the project. Virginie Bollini: “In 2005 approx. 300 apartment
refurbishments were planned whereas now more than 425 have
been realised.”
Sustainable renovation Ajaccio
33.1 Ajaccio – the scene
3.2 A suite of projects
3.3 Performance – occupant behaviour
3.4 Moving forward
“We have changed the way we
renovate. And rather than tackling
single buildings, we are now
developing ideas for “eco-quartiers”.
We will be moving strongly towards
a smart low-carbon city. With the
experience built up and our iconic
energy-positive building, we are
confident to get there.”
Simon Renucci, Mayor Ajaccio
sustainable renovation 49
Ajaccio
The fast growing environmental awareness was
enormously aided by the international project.
Virginie Bollini: “Discussions and exchanges with cRRescendo
partners, Almere in the Netherlands; Milton Keynes in the
United Kingdom and Viladecans in Spain, helped by sharing
experiences. The annual meetings enabled us to observe the
different approaches implemented in other parts of Europe.”
At the same time, the French National Programme
for Urban Renewal (Ajaccio belongs to since 2007)
enabled social landlords to rehabilitate their ageing
housing stock by implementing money-saving and
energy saving or even energy-producing building
improvements. Virginie Bollini: “In 2003, at the start of our
project, the French national regulation was not as ambitious as
the CONCERTO energy requirements. The national regulation
on energy efficiency was sharpened in 2006 and 2009 and now
supersedes CONCERTO requirements for new-built, but still
there are no regulations for refurbishments.”
As new large scale
urban developments are
multi-year projects even
ambitious requirements
may be surpassed
by new regulations,
lowering the possibility
to serve as an exemplar
project for a longer
period. Integration of
an extra high-ambition
“Icon” project in the
developments, will
extend this exemplar
role.
Ground plan of Ajaccio with cRRescendo developments
50 new energy for growing communities
The building and technical companies developed along
similar lines, but not automatically. Virginie Bollini: “In the
beginning it was hard to find specialists. And the slow tender
process for the Energy Positive building and the industry status
according to the CERC survey, inspired Ademe to organise an
architect training course on Corsica. The first in 2010, and the
second in 2012.” As a result, 20 professionals from the
industry gained knowledge on environmental quality.
But even here hurdles occurred: the small size of most
enterprises (typical only several employees) led to the
issue that they cannot miss the workable hours “lost” on
training.
3.2 A suite of projects
Ajaccio set out to implement a suite of projects:
refurbishments and new developments (demolish and
build) with and without solar energy installations, in
the ancient centre and in the 1960’s expansions. In that
way, a wide-ranging experience would be gained fast
on a variety of buildings and procedures. This proved
a sensible approach: each development had its own
peculiarities and pitfalls, and different stakeholders
influencing progress and quality.
The refurbishments should serve a dual purpose: reduce
CO2 emissions in the atmosphere and reduce the rent for
tenants by lower service costs. Virginie Bollini: “A domestic
hot water system fed by solar thermal collectors rather than
gas fired boilers and better building insulation were expected to
reduce the use of heating in winter.”
The new buildings offered the opportunity to engage in
high ambitions. In Ajaccio, public buildings like schools
which are part of the urban renewal project in priority
areas, are built in compliance with High Environmental
Quality Standards (HQE, France) aiming at zero energy
consumption. Even more ambitious is the “iconic”
Maison de quartier des Cannes, which is developed
under cRRescendo and will be built in 2014. The new
building is an “energy-positive” building, which will
produce more electricity than it consumes.
Old centre solar systems - cancelled due to roof restrictions
Refurbishments on buildings located in the old
centre are eligible for interventions financed by the
“Programmed operation for the improvement of the
housing environment”. In particular the installation
of solar thermal collectors and photovoltaic panels
are eligible. The Housing Rehabilitation Programme
was launched by Ajaccio city in 2006 to increase
refurbishment within the city. Denis Bravi, project manager
at Ajaccio Municipality mentions: “Our first idea was to work
on 10 buildings situated in the old centre of the town. The
Municipality began searching for buildings in need of heavy
refurbishing, and more specifically on roof works, in order to
install solar thermal systems on these roofs. It was easy at start
to find willing owners in the old centre.”
But later three different problems emerged:
- The heritage protection rules specify that roof works
can only be carried out if not visible from public space,
i.e. from the pavements. This limits the use of solar
systems.
- Most streets in the historical centre are orientated
East-West and have facetted roofs with different
heights that create a lot of shading. Those facing
south are often visible from the street and thus
forbidden for use.
- In narrow streets there is often shading from buildings
on the other side.
Shadow casting in old city centre
See also page 60 for Case:
Refurbishment for social
owners: another cup of
tea
sustainable renovation 51
Residential NameNumber of homes
Gross area per house (m2)
Measures Solar
Rue de la Porta (1 new building)
8 75
Solar PV panels
5,5 kWp12 m2
Solar collectors
High energy performance building envelop
Monte e Mare (2 renovated buildings)
91 70
Solar collectors
98 m2
Refurbishment heating system
St Paul (2 renovated buildings)
52 70
Solar collectors
94 m2
Improved ventilation, heating and lighting system
Improved roof insulation
Installation of Casa system
St Jean 2 (4 renovated buildings)
196 117
Improved ventilation, heating and lighting system
Double-glazed windows
Insulation of exterior walls and roof
Pietralba 2 (10 renovated buildings)
80 87
Improved ventilation, heating and lighting system
142 m2
Solar collectors
Double-glazed windows
Insulation of exterior walls, floor, and roof
Installation of Casa system
Total dwellings 427
Office buildingsName
Number of buildings
Planned Gross m2 Measures Solar
Les Cannes, new public service building (construction 2014)
1 1,000
Solar panels
200 m2
Urban wind turbines
Ambitious specifications for insulation and ventilation resulting in an energy positive building
Total office buildings 1 1,000
Overview cRRescendo Eco-buildings, and renewable energy in Ajaccio
52 new energy for growing communities
Renovated building St. Jean
Renovated building Pietralba
Renovated building St. Paul
With these restrictions much fewer buildings then
expected were identified and none were refurbished.
This highlights the important difference between new
development and refurbishment projects. In the latter
the current inhabitants are the main decision makers and
very diverse. In addition the situation of each building may
differ and plays an important role.
New area refurbishments finally successful
In the new areas of Ajaccio a renovation project was
initiated in a zone defined as the French Sensitive Urban
Areas. In total 419 homes were renovated spread over 19
buildings named: Monte e Mare, St Paul buildings, St Jean-
2, and Pietralba-2 buildings.
Part of the renovation plan was the introduction of solar
thermal collectors. For this technique an issue arose
regarding the ownership of the dwellings. A social owner:
“If Isupport the cost of the works, I have no return on investment if
I cannot raise the rent, as the benefits go to the tenants saving on
their energy bills.”
The municipality rapidly realised the unfairness of the
distribution of the benefits between private flats owners
and social tenants. Therefore the strategy was changed.
Ajaccio approached the social owners to also take part in
the cRRescendo project, resulting in a lower investment
due to European subsidy. Denis Bravi: “Several meetings were
organised with co-owners of private buildings, in order to study
the feasibility to install thermal solar systems on roofs with them.
Both collective private housing and houses owned by a housing
association were then equipped in particular with solar collectors
for domestic hot water.”
There also was a plan to install solar (PV) panels on all the
buildings (119 homes) of the community St Jean 1. This was
feasible with the feed-in tariff for electricity in 2009 of
0.44 €/kWh. Unfortunately the feed-in tariff was lowered
to 0.12 €/kWh by 2011. This lower feed-in tariff made the
panels completely unfeasible for the building owners.
! Because the buildings of Saint Paul were
already better than other buildings in the
area, the extra effort to insulate the walls,
ground floor and windows turned out to be
not feasible for the building owners. It was decided to
concentrate on the measures that had the highest effect
on the savings for the inhabitants, such as roof insulation
and a solar hot water system.
sustainable renovation 53
New apartments in heritage area built to high standards
The unsafe and unhealthy apartment building in the city
at Rue de la Porta 3, owned by a housing association had
to be replaced. It was agreed to demolish and rebuild
it according to the French High Environmental Quality
Standards (National regulations for green buildings in
France). Denis Bravi: “Then local interest groups successfully
campaigned to ensure to conserve the architectural heritage.
One of the outcomes: solar panels were only acceptable when
not facing the public street, i.e. facing the courtyard.”
The new apartment building is made in Siporex – a
first for a 4-storey building in Corsica. Siporex is a
lightweight concrete. It is available as blocks and pre-
cast reinforced units for floors, roofs, and walls. This
material has a high energy performance.
New building in city centre,
Rue de La Porta
The roof was designed with a south orientation to the
sun with no visual impact from the street, and was
equipped with solar systems. No less than 3 different
solar systems were mounted. A solar thermal system (12
m²) was installed to produce hot water for sanitary use.
Two air-type solar collectors were installed on the upper
part of the south front wall of the staircase. They reheat
and ventilate the building’s staircase, minimising heat
loss between the landing doors and the common parts.
And finally 32.5 m²of photovoltaic panels were installed
to produce electricity, the sale of which will cover part
of the extra cost incurred by achieving the so called High
Environmental Quality Standards. Virginie Bollini: “The
heritage rules unfortunately led to partial shading of the system
during certain daytimes.”
Evolution of an “energy-positive” building
The 1000 m2 public building “La Maison de quartier
des Cannes” was developed on land made available by
demolishing an older building in the middle of the “Les
Cannes” district. Originally it was planned to reach
the High Environmental Quality Standards. Virginie
Bollini: “In 2010 a call for tender was launched by ADEME on
a regional level for architects to design an exemplar building,
with ambitious specifications. The winning architects conceived
an “energy-positive” building: It will produce more energy
than it needs, because it is fitted with 200 m² of photovoltaic
panels. A great, but realistic design. This extremely high result
for the public building would not be possible without the
cooperation and exchanges with Almere and Milton Keynes in
the cRRescendo project.”
! Thanks to the ambitious specifications of
the competition to select an architect the
objective of a zero energy building,
producing the total of its needs in energy,
has established itself as a realistic solution.
Realising the ambitious plans of the winning architect
proved more difficult than anticipated. Its originality,
specifics and its innovativeness as the first building of
this type in Corsica made the discussions, drawing up
of the requirements, and the consultation procedures
for contractors a rather long venture. The construction
tender went out included in a Corsica-wide call for
several energy-efficient buildings. Twenty subscribers
developed plans. These plans did not contain feasible
plans for the zero energy building. Virginie Bollini: “Ajaccio’s
54 new energy for growing communities
Energy-Positive building remained on the loose for over a year.
Therefore Ajaccio had to launch a new specific tender procedure,
with more success.”
It shows that visionary ambitions can be adhered to,
and ambitions can be increased rather than downsized!
Although substantially delayed, the public office
building will be built in 2014 and is more advanced than
initially envisioned. Denis Bravi: “We learned from other
cRRescendo cities, we set high ambitions for the architect, and
we gave the architect the freedom to choose how to realise these
ambitions. Corsica needs buildings like these.”
Solar energy systems – thermal and electric
Solar thermal hot water systems and one solar PV
systems were mounted on part of the buildings, for a
total of 346 m2 respectively 5,5 kWp.
3.3 Performance – occupant behaviour
Combine social and technical monitoring
Both national regulation and CONCERTO standards
calculate energy performance using building
parameters, but do not account for occupancy. It is
well known that occupant behaviour and occupancy
numbers are very influential on the energy bill. The
extent of that effect is shown in the monitoring results
Solar thermal system Ajaccio, Pietralba
Energy-positive public services building
Combine technical and social monitoring, to understand data and take appropriate action
sustainable renovation 55
of Ajaccio. Virginie Bollini: “We think it is better to combine
technical and social monitoring and do it with a locally known
partner. Interventions on energy behaviour should be taken after
starting the monitoring.”
Heating on demand
In Monte e Mare, the heat consumption was measured
with sensors and data loggers. Heat consumption
varied enormously from one apartment to another,
with the highest consumption 10 times that of the
lowest. These differences may be due to a variation
in set temperature, the duration of heating, varying
occupancy, and ventilation preferences. One poorer
inhabitant is very clear on his heating strategy: “When I don”t
have money, I just switch the heating off, whether it’s cold or
not.”
Public servants learning to conserve energy
How do occupants influence the performance of
public office buildings in the St. Jean area? Reference
monitoring values are available for a similar office
building in the area. The measured consumption in
the reference situation is much higher than one would
expect, the electricity consumption as well as the heat
consumption. Virginie Bollini: “Inspection of the building
during the monitoring period revealed several things. First,
during daytime lights are on: not all window shutters were
opened during the day, and the light is not switched off after
use in the toilet. Second, computers were not switched to low-
energy mode during lunch break, and third many devices remain
on standby at all the time (computers, printers, DVD players),
explaining the high night-time consumption (20% of the day-
time peak).”
Risk perception and money saving
Solar hot water systems concern a technology for which
Corsica has a reasonably well-developed industry
compared with other regions of France. That does not
mean that solar thermal technology is fully normalised
across Corsican society, while some actors associate
risks with the technology because it is still relatively
unknown. The perception of risk for maintenance has
even led to the creation of a new service charge for
residents in the Monte e Mare apartment building.
Some residents fear now that the system which they
had been told would save them money on energy bills
may see them actually becoming worse off overall.
A resident survey on people’s general understanding
and familiarity with sustainable technology pointed out
several interesting issues, such as the anxiety regarding
the risk and regulation associated with the Legionella
bacterium in solar hot water systems. But like one
inhabitant puts it: “I don”t know how it works but I save
money with the collectors.”
3.4 Moving forward
The Corsican building industry
In 2011, the French national network of Construction
Economics Groups (Cellules Economiques Regionales
de la Construction, CERC) surveyed industry
representatives in 30 French employment districts,
including Ajaccio District and Southern Corsica. It
gives a comparative snapshot of the construction
industry in economic activity in two sectors: low-
energy construction and installation of renewable
energy technologies. The survey focused in particular
on the needs for new competences among building
and renewable energy professionals in the short- to
medium-term.
Large variation in electricity use for heating, 10 households, Monte e Mare
1 2 3 4 5 6 7 8 9 10
80
70
60
50
40
30
20
10
0
households
annual heating energy (kWh/m2/year
56 new energy for growing communities
Organise regional dissemination and showcase the feasibility and attractiveness of your eco-buildings.
In France, construction accounts on average for
10% of the economy, but the Ajaccio district scores
substantially above average: 13% and in Southern
Corsica even 16%. Spending on low-energy and low-
impact buildings in Southern Corsica takes 13% of all
construction budgets, lower than the national median
of 16%, and half of the highest-spending districts (25%) in
France.
Low-energy refurbishment projects are clearly an
underdeveloped competence on Corsica during our
project. Another study however shows that Corsica has
a higher number of solar thermal installation companies
per capita compared to the France, and a somewhat
developed PV industry.
! But change comes fast: early 2011, in
Corsica there were no labelled low energy
buildings. Now an impressive 86 projects
are seeking the relevant so called BBC
(Bâtiment Basse Consommation) approval.
Virginie Bollini: “Ajaccio’s cRRescendo project and the architect
training course have certainly contributed to this development.”
Spreading the word
The cRRescendo funding has been used to add funds
to larger budgets, such that renewable energy and
energy-efficient “extras” have been incorporated into
larger projects – either renovations of existing buildings
or construction of new buildings. For the apartment
building renovation in St. Paul, the proportion of
CONCERTO funds relative to the total was 2.1% of
the total capital budget. However, the impact of
cRRescendo may prove to be greater than the financial
contribution.
! The interest in the Mayor’s office in now
developing an entire neighbourhood to be
more sustainable should be seen in the
context of Ajaccio winning the status of
project partner on the cRRescendo project.
Virginie Bollini: “Now, the Mayors are convinced they can
change the way we renovate. They take action and actively
spread that believe around. And rather than tackling single
buildings, we are now developing ideas for “eco-quartiers”,
districts involving 200-500 homes within the Agenda 21
programme”.
One impact of having Ajaccio associated with a
prestigious EU-funded programme may prove to be a
stronger commitment to sustainable development in
general among the local politicians and government
officials. And Ajaccio sets an example and spreads the
word. Virginie Bollini: “In the greater Ajaccio area, the 10
-municipality Commune d”Aglomeration de Pays Ajaccio, now
officially adheres to the objective to reduce greenhouse gas
emissions.” And Ajaccio’s renovations form showcases on
the feasibility of those.
Solar thermal collector field aside a residential building
sustainable renovation 57
58 new energy for growing communities
Economics needs replication
The measures implemented in the cRRescendo project are substantial, and costs are
considerable. Are these costs earned back in a reasonable time period? And how about
replication? No easy questions to answer. On these pages we analyse four cases: new
passive homes, a CHP plant, refurbishment for social housing, and a smart school.
Serial-built Passive Houses in the rental sector (Almere)
Many see passive houses as a solution to
tackle the problems of ever rising energy
bills, scarcity of energy resources and
climate change in the housing sector.
Within Columbuskwartier the developer
AM (supported by many others) realized
a project with 103 passive houses for the
Urban Housing foundation Goede Stede. This
project was innovative and unique (in the
Netherlands) because the houses were built
on a large scale and in a serial way, instead
of being a (single) pilot case. A standardised
building process forms the basis of this
concept with the possibility to still create a
large variation of houses.
The focus was on optimising the technology;
economic optimisation would follow
afterwards. In the design phase the comfort
and energy costs of the occupant played a
decisive role. Through the project a reference
was created towards serial energy neutral
houses.
At the start of the project the total additional
costs were estimated to be €12,000 per
house, consisting of €6,000 for the building
construction, and €6,000 for other costs
like installations. The costs for solar PV
were not included (but paid by NUON and
cRRescendo subsidy) and the payback period
was estimated on 30 years. In practice
these costs however turned out to be higher
than expected due to specific incidental
reasons: €20,500 per house. Especially the
construction costs turned out to be much
higher at €16,000 per house.
However it is expected that through
repetition and market development costs can
be considerably reduced to €7,000, consisting
of €4,500 for construction and €2,500 for
other costs. These other costs will by then
only be caused by additional material use (e.g.
for insulation), but not for building activities.
Through this the payback time could drop to
15 to 20 years in the short term. On the longer
term payback times of below 10 years could
be possible, considering the fact that building
standards will increase as well.
Project developer AM (BAM) foresees
the following actions for a full market
introduction:
- Creating a communication plan about the
passive house for inhabitants;
- Initiating further product development
including the industrialisation of
components to reduce the work on the
building ground. This should lead to quality
improvements, and cost reductions.
- Striving to a large degree of standardisation
in the production of passive houses, leading
to high quality levels, with room for choice.
The knowledge which AM has built up
during this project has already been used
for the development of a very energy
efficient apartment complex (Kotmanpark in
Enschede, the Netherlands). In recent years
several other serial passive house concepts
have been realized.
Passive building is a generic term for a way of
building aiming at a healthy and comfortable
inner climate without traditional heating
or cooling systems. The energy demand for
heating and cooling needs to be maximized
on 15 kWh per square meter of living space
per year. Furthermore there are demands
for the total primary energy demand for all
households appliances, hot water and cooling
per year (120 kWh/m2). Renewable energy
sources are used to fill in the remaining
energy need. Through this a passive house
has an energy saving of approximately 80%
compared to a regular new house.
towards a zero carbon city 59
Investing in CHP (Milton Keynes)
The MK Combined Heat and Power (CHP)
plant, delivered by Thameswey Ltd, plays a
central role within the Milton Keynes demo
project. Using a pioneering approach by
working on a large scale with residential,
commercial and retail developers the first
multi-phase multi-developer CHP system of
its type in the UK came to be. A system that
now successfully provides energy to over
45,500m2 of commercial and retail space and
929 residential units. But how did this capital
intensive project come to be?
Core to the business case of the CHP plant
is the Project Development Agreement
(“PDA”), between Thamesway and the Homes
and Communities Agency (HCA). It gives
Thamesway the exclusive right to supply
heat and power to all developments within a
defined area in Central Milton Keynes (CMK),
but only for a competitive price. Developers
in this area are required to enter into a Phase
Project Development Agreement (PPDA)
which commit them to use the CHP system as
long as it is financially viable for both parties:
1 Connection costs paid by developers to
Thameswey must equal to the avoided costs
(compared to traditional heat and power).
2 A reasonable rate of return on the equity
investments of Thamesway. It is understood
that in this specific pilot this rate of return is
12%, and that the majority of the investment
in the scheme is debt funded.
3 HCA can gap fund the project if it falls short
of being financially viable.
Gap Funding
The CHP plant was constructed in 2007 and
was able to successfully supply power and
heat to the Hub and Vizion developments,
without any gap funding requirement. In
2009 however this situation changed when
Thameswey was contractually committed
to provide heat and power to the B3.2N
(Pinnacle) office development. Although
calculations indicated that CO2 savings of
400t/year could be expected, one of the
key issues were the infrastructural costs
for the expansion of the existing system
for Pinnacle but also for other future
developments. The upfront investment costs
were higher due to the extended distance
to Pinnacle, and the additional advanced
infrastructure required (a new sub-station
and high-voltage ring main) to facilitated the
connection of future development in CMK (to
reach the full capacity of Energy Station 1).
Studies indicated that an additional capital
contribution of around 6% for Pinnacle alone,
and 30% of the total expansion investments
were needed to make the scheme viable.
Overall, looking to the total CHP system,
it is understood that the total private
investment to date in the CHP systems is
roughly £20 million. This comprises the
investment of Thameswey and the developer
payments (avoided costs). Additionally /HCA’s
contribution is understood to be roughly
of £3m which is about 13% of the total costs
of delivering the CHP. However with the
assistance of government agency funding
the infrastructure is now effectively “future
proofed”, and in addition this sum is repayable
to the Agency if/when Thameswey exceed the
target rate of return in the future. In practice
the economic climate has resulted in a
delayed development of the area (not as many
consumers as anticipated yet). Therefore
Thamesway’s current ROI is lower than
expected: just above 5% compared with the
targeted 12%. However the position of Milton
Keynes as one of the fastest centres of growth
in the UK means that the long-term outlook
remains positive.
Successful repetition in the UK
Overall the CHP demo has been a success: the
system proved to be technically sound but
also (on the longer run) economically viable. It
is therefore viewed as an exemplar project for
others, and one with serious follow-up from
local up to national level:
- In 2012, after cRRescendo, the BREEAM
“Excellent” rated Network Rail development
called Quadrant, comprising 38,000 sq.m.
was connected to the CMK CHP system.
The Quadrant had no obligation to connect
to the district CHP system, and made a
comparison with other, competing, energy
providers. This voluntary expansion is a
good indicator of the confidence in the CHP
business case.
- Thameswey also has an increasing number
of local Councils that approach them for
consultancy or joint ventures.
- And in recent years CHP projects is seen as a
popular low carbon measure across the UK.
Foto left: CHP plant in Milton Keynesis based on a Jenbacher cogeneration unit
Foto right: Network Rail’s Quadrant building: 38,000 sq.m. office space connected to CHP in 2012
60 new energy for growing communities
Refurbishment for social owners: another cup of tea (Ajaccio)
Different than in all other cRRescendo
communities in Ajaccio the focus was on
refurbishment instead of new developments.
In refurbishments projects a new stakeholder
comes into play: the current inhabitant. It
turned out that the development process
in Ajaccio was intrinsically slower and the
outcomes were less predictable. In addition
we saw that the recession that hit Viladecans
and Milton-Keynes so hard, had a lower
impact on the refurbishment in Ajaccio.
During this project we however learned
refurbishment not only radically changes
the decision making process, but also
the business case behind additional
improvements relating energy efficiency. An
additional challenge was that renovations
were planned in relatively low-income areas
of Ajaccio. A first issue that arose was that,
regardless many information meetings, we
were not able to convince the private owners
to commit themselves in doing part of the
investment, even when pay back periods were
low.
In Ajaccio the solution was found through
the introduction of two social house owners
in Corsica: Erilia and OPH Sud (Office Public
de l”Habitat). OPH is the territorial company
for social housing in the south of Corsica. Its
rents are about twice lower than standards
(about €5.- per square meter), and owns 1700
social homes rented to modest families, of
which a part was in need of renovation. The
solution was however not easy as the benefits
of energy savings end up with the tenants’
trough lower energy bills, and the fact that
raising rents based on energy savings is not
allowed in France.
Regardless the lack of a solid business case,
OPH (and Erilia) however was strongly inclined
to improve the quality of life and reduce the
energy costs of their tenants. Thanks to a
combination of this ambition and additional
support from the municipality and the
cRRescendo project for the most ambitious
measures, it proved possible to find sufficient
funds for making the very substantial
investments.
For OPH the total investments for the three
main projects (St Jean 2, Pietralba 2 and Saint
Paul) added up to €10.4 million! In addition over
€155,000.- was spend on technical research
and feasibility studies to create the plans for
these projects. The table below summarizes
the measures.
The renovation measures were implemented
based upon the tenant’s request. Besides the
buildings themselves, a lot of effort was done
by the city and the social landlords to improve
the surroundings and public space in the area.
One of these efforts includes creating family
gardens for the inhabitants to interact and
grow their own food. This combination has
finally led to very positive feedback and high
satisfaction levels among the tenants.
Measures St Jean 2 (4 buildings, 196 homes)
Pietralba 2(10 buildings, 80 homes)
Saint Paul(52 apartments)
Total investment costs €4.9 million €3.5 million €2 million
Insulation of the exterior walls (regulation: 0.5 W/m2K) 0.32 [W/m2K] 0.32 [W/m2K] No works
Improvement of roof insulation (regulation: 0.4 W/m2K) 0.28 [W/m2K] 0.28 [W/m2K] 0.33 [W/m2K]
Insulation of the Ground floors (regulation: 0.5 W/m2K) No works 0.37 [W/m2K] No works
Installation of efficient lighting 12% savings 12% savings 15% savings
Replacement of the entry doors Yes Yes Yes
Installation of mechanical ventilation 1.4 air changes/hr 1.4 air changes/hr 1.4 air changes/hr
Double glazed windows, including window shading 1.81 [W/m2K] 1.81 [W/m2K] No works
New heating system (savings include insulation) 15% savings 40% savings 15% savings
Installation of a solar hot water system No works 60% savings 60% savings
towards a zero carbon city 61
A smart school is cool (Viladecans)
“An important milestone for the city and the
neighbourhood”: words spoken by Mayor
Carlos Ruiz of Viladecans in November 2011.
In September 2012 the New Primary School
CEIP Nova Escola Ponent opened her doors
in the West District of Viladecans City. New
generation smart devices and energy systems
(like light sensors, digital whiteboards, fibre
optic cable, and PV) make the school, built as
part of cRRescendo, the first “Smart School”
in the municipality and a model for other
buildings in the city!
State of the art energy system
Thanks to the modern lighting and heating
systems, and other “smart” devices the school
was awarded with the maximum energy
efficiency building certificate by ICAEN
(Catalan Institute of Energy). The school
makes use of energy efficient lighting systems
(Fluorescent lighting, high efficiency light
bulbs and LED), and the rooms and toilets
have presence sensors for saving energy when
the rooms are unattended. Within the class
rooms, sensors detect the light intensity
(luminosity) coming from the windows and
adapt the intensity of the lights.
Regarding heating, a high-efficiency
condensing boiler is used combined with
thermostatic valves at all radiators. The
ventilation system is designed to recover 50%
of the energy from the air going out from the
classrooms. And in addition 650 m2 of solar
panels producing 125,000 kWh, and 9 solar
thermal collectors ensure the school is 70%
self-sufficient regarding electricity and 64%
for hot water.
The building design has been created with
energy efficiency criteria in mind with
features like ventilated walls and roofs, high
efficiency glazing, measures to prevent
thermal bridges, and the use of passive solar
energy in the building construction. There
is no need for cooling thanks to the clever
building design. Building materials have been
chosen consciously and according to the
latest rules and norms. The annual energy
consumption is calculated to be 608 MWh/
year, meaning 124 kWh/m2. The annual CO2
emissions are calculated to be 52 tCO2/year,
meaning 10 kg CO2/m2.
Applied measure Value
Clay Façade U = 0.48 W/m2K
Concrete Facade U = 0.46 W/m2K
Zinc Façade U = 0.18 W/m2K
Roof U = 0.28 W/m2K
Floor U = 0.48 W/m2K
GlazingU = 1.70 W/m2KSolar factor (G value) = 0.58
Heating system High efficiency boiler
Ventilation system Heat recovery (balanced)
Hot water 9 solar collectors (23.5 m2)
Renewable energy 394 PV-panels (94.56 kWp)
A smart new management model
The school serves as experimental example
of a new energy management model for
other facilities in the city. Currently, the
city is working on installing a new online
energy management system for the energy
consumption of all the municipal buildings.
This system will allow the real time tracking
of all energy flows for each municipal
building, or area. This information can be
used to set up corrective actions, manage the
energy demand/consumption patterns and
thus the required energy, spot moments of
excess and shortage of energy, etc.
62 new energy for growing communities
4.1 Viladecans – the scene
Growth between nature and infrastructure
Viladecans is a mid-sized Spanish town of 20 km2 with
over 65,000 inhabitants; a city located 15 km from
Barcelona and its Sea Port. Barcelona Airport is nearby,
and a significant part (16%) of the airport infrastructure
belongs to the city area. Besides the infrastructural
connections (airport, sea port, national highways, and
a major railway), almost half of the municipal area is
environmentally protected. This double claim makes
the area complex when it comes to implementation,
coordination and management of development
plans, such as a protection plan for aquifers. Still, the
Local Dwelling Plan anticipates a growth to 73,000
inhabitants in 2020.
The existing homes in the town are fairly energy-
inefficient, e.g.: only half of dwellings have double glass
in windows, few have solar thermal panels (just 2% of
dwellings have them), and 79% of the dwellings have
little or no efficient light bulbs. But people are getting
more energy conscious: regarding electrical appliances:
80% say they try to choose an A label (see also:
www.cRRescendo.net).
Committing to sustainability
Carmen Pérez Figueras, head of the department of International
relations in Viladecans and City Coordinator in the cRRescendo
project: “Energy saving and climate change is an important
subject for the city. The awareness of the city regarding
this subject is high. Over the period 1999-2010, this was
substantiated by municipal policies and by joining external
sustainability networks.” The first relevant policy
measure was the approval of Agenda 21 already in
1999. A Municipal Environmental Action Program for
2003-2007 was approved in 2004 and the city signed
Paving the wayViladecans
44.1 Viladecans – the scene
4.2 Delivering eco-buildings
4.3 Solar energy in Viladecans
4.4 Overcoming barriers – stepping forward
paving the way 63
the “Vilafranca Declaration” for preventing
Climate Change in 2005. In addition, the
Municipal Assembly for Environment and
Sustainability was constituted on the 12th of
July 2005 and the Municipal Law for Solar
Energy was approved on the 23rd of April
2005.
The municipality enlisted in the European
Covenant of Mayors in 2008. Raquel Millán
Lopez ( 2013), cRRescendo project manager
for Viladecans: “This participation partly was
resulting from Viladecans’ involvement in the
cRRescendo project.” In 2009 the mandatory
Sustainable Energy Action Plan of Viladecans
was approved by the Covenant’s office. The
main objective of this plan was to reduce the
City Council’s own emissions by 20% in 2020
compared to 2005. Carmen Pérez: “Under these
substantial national and international frameworks,
the city started planning new developments
in a sustainable way, with high ambitions. In
Viladecans a shift from socio-economic to technical
projects was eminent and European support was needed.”
Ambitious extension plans
And so the sustainable showcase the “Llevant Partial
Plan” was initiated. The plan involved 2,100 dwellings
and included renewable energy, rational use of energy,
community development as well as other sustainability
criteria (water saving, wastes, biodiversity, etc.).
It was approved in 2007 by the Territorial Planning
Department of the Regional Government of Catalonia.
Carmen Pérez: “Such a ground-breaking eco-district required
substantial research. An energy concept had to be developed,
the set up of a tender procedure necessitated legislation studies,
and energy calculations for sustainable solutions were initiated.
Sometimes with remarkable findings.”
!A poly generation heat and power plant
combined with district heating may be
less feasible in the Spanish climate
compared to Northern Europe. In this
study this was due to a smaller demand for
space heating and a short heating period per year. A
high temperature grid (e.g. 70ºC) supplying both space
heat and hot tap water may be the most attractive. And
to supply the substantial demand for cold in summer,
cooling by absorption cooling machines in the building
“Ten years ago, we were a standard
modern Spanish town, now we are a
city smarting our way towards low
carbon society. The large ambitious
European project with renewable
and rational use of energy we
participated in, paved the way in our
municipality. And it pays to do so:
our business districts are still filling
up and our citizens love to live and
work in our town.”
Carles Ruiz Novella, Mayor Viladecans
blocks is an interesting energy option to investigate.
Raquel and Carmen: “Everything was in place. But the housing
and financial crisis, which started in 2007, hit Spain and
Viladecans hard. The private building sector in Spain dropped
into a very deep crisis. Regretfully, we had to postpone further
developments.”
Noblesse oblige
But by then, sustainability had been firmly internalised
in the council, and mayors were standing up for it. And
Viladecans had its international network obligations in
the European CONCERTO project cRRescendo. Carmen
Pérez: “Noblesse oblige. For instance, the Covenant obliges the
municipality to obtain an “A” energy label certificate for all new
public buildings.”
In 2009 the Municipality had to rationalise its plans
for cRRescendo and directed all the efforts towards
public buildings, such as theatres, sports facilities,
and libraries, and solar energy. These buildings then
demonstrate sustainability to visitors and occupants in
practice, and show that the Council puts money where
its mouth is. Carmen Pérez: “When the recession is over, the
project has changed the future way of building in Viladecans: it
will be clearly more sustainable than before.”
Viladecans centre
64 new energy for growing communities
Being in a European project was stimulating. Raquel
Millán: “The other cities in cRRescendo Almere, Milton Keynes
and Ajaccio were inspiring examples how to adapt to changes
and how to layout new districts.” But at least as helpful
were the other ambitious CONCERTO developments
in Spain (Zaragoza and Tudela). Raquel Millán: “Exchange
of experience and colleague help was very valuable. As were
the national (so-called CONCERTO+) meetings for exchanging
knowledge.”
Viladecans became convinced that sustainability
is a multi-variable multi-level theme. To that end,
a management tool has been developed and is
currently in operation. Raquel Millán: “The effective Project
Co-ordination Committee of the cRRescendo management
structure was adopted in Viladecans. Internal Co-ordination
Committees were installed to improve transversal co-operation.
So, by virtue of the cRRescendo partnership example, a Smart
City Directors Committee has been formed with decision-
making powers, formalised in the internal procedures. In
this committee, politicians, mayors, and area directors and
department managers participate.”
4.2 Delivering eco-buildings
Getting it done
Institutionally, the cRRescendo project was integrated
in the Viladecans’ Bureau for Urban Renewal towards
Sustainability. During the preparation phase all
cRRescendo criteria were incorporated in the
public tenders for builders and the constraints for
the architectural designs. During the preparation
and realisation the Council was assisted by the two
municipal-owned Enterprises VIMED (development
of the Llevant sector) and VIGIP (PV development);
this is a common logistic construction in Spain.
These enterprises can operate with less bureaucratic
constraints in developing projects.
The period between preparation and submission of the
cRRescendo proposal at the end of 2003, and the final
contract in august 2005 took longer than expected.
This caused that some of the buildings planned to be
sustainable to fall out of scope and sometimes were
built in the conventional way. For example construction
of Day Care Centre La Marina had already started before
2005.
See also Milton Keynes (page 42-43): negotiating subsidy
applications
! In addition the final subsidy conditions
did not all match Viladecans expectations.
Raquel Millán: “It turned out that the subsidy
available was much less than expected (30 €/m2
Time plays a large role in subsidized projects. Be prepared to deal with delays and financial re-arrangements.
Viladecans Llevant development plan (postponed)
paving the way 65
For infants, culture, associations, sports, and students…
The Council developed 3 new high-quality public (non-
residential) buildings and refurbished 2 other buildings.
And, as part of a larger plan for installing 1MW of
photovoltaic panels, Viladecans installed 238 kWp of
solar PV panels and 191m2 of solar thermal collectors
during cRRescendo. All were developed for users sharing
a future oriented character, such as: day care centres,
cultural centres, sport clubs, and school buildings.
instead of the submitted 100€/m2). Some criteria of the
CONCERTO programme, for instance the U-values, should
be considered differently in warm countries, as heating is only
limited to a small part of the year and cooling is predominant.”
Raquel Millán: “Around 2005, it was difficult to find some of
the energy-friendly building materials as they were not widely
commercialised in Spain. For example, at first it was difficult to
find the optimum double-glazing windows for La Pineda Day
Care. But ambitious projects like cRRescendo create the demand
for this kind of products. Nowadays it is common to find such
kind of materials in Spain.”
Office BuildingsName
Number of Buildings
TypeRealised Gross Area (m2)
Measures Solar PV (kWp)/Thermal (m2)
Day care Centre La Pineda 1 New Building 1,144
Solar collectors
12.5 m2
Passive solar energy
High insulation of roof, floor and windows
High efficient lighting and cooling
Can Xic Youth Centre 1 Renovation 765
Solar PV panels
6 kWp
High insulation
Sport Facilities building 1 New Building 1.512
Solar collectors
156 m2
High insulation
Cultural Centre – Auditorium Pablo Picasso
1 Renovation 821 High insulation
School CEIP Ponent 1 New Building 4,982
PV panels
95 kWp
22.5 m2Solar collectors
Very high insulation (label A)
La Marina Park 0 New Pergola Solar PV Panels 16 kWp
Atrium Sports and Theatre centre
1 Existing buildings Solar PV Panels 94 kWp
Cubic Conference Centre 1 Existing buildings Solar PV Panels 23 kWp
Municipal Library 1 Existing building Solar PV Panels 4.9 kWp
Total 8 9,224238 kWp191 m2
Overview cRRescendo Eco-buildings, and renewable energy in Viladecans
66 new energy for growing communities
Solar thermal hot water installations on facilities building Soccer field “Torre Roja”.(right)
Day-care centre la Pineda (left)
Youth Cultural centre “Can Xic” (left)
Day-Care Centre “La Pineda”
La Pineda is a new day-care centre hosting about 100
children. La Pineda is the first demonstration building
in Viladecans, taken into use on 1st of October 2008.
Insulation, efficient windows, solar hot water systems,
high efficiency lighting and cooling are installed. And
the building makes better use of passive solar energy.
The teachers say they feel very good in this comfortable,
modern building.
Youth Cultural Centre “Can Xic”
Can Xic is a refurbished country house with a cultural
destination. It offers workshops, courses and adjacent
office space and multifunctional spaces for music, arts,
etc. In May 2009 Can Xic has opened up with graffiti
competitions, table tennis, Wii matches, break-dance
shows and concerts.
Sport Facilities Building - Football Field Torre Roja
This Sport Facilities Building is a new building,
inaugurated on the 24th January 2010. The 100 square
meters of solar thermal panels cover 80% of the hot
water needs, such as showers.
Cultural Centre – Auditorium Pablo Picasso
The Auditorium Pable Picasso was refurbished in 10
months by 11 previously unemployed people. It is a
historical building from the beginning of 20th century
designed by Josep Canaleta, a pupil of Antoni Gaudí.
Originally it was an abattoir, which was reconverted
into a cultural centre during the 1980’s. The centre hosts
31 cultural associations. There is an auditorium with
theatre facilities and seating capacity for 157 people and
a small exhibition room. It was inaugurated on the 27th
of February 2011.
Primary School - Ponent
The new Primary School CEIP Nova Escola Ponent
(West School) contains a ground floor and two more
floors with 40 classrooms, one gym, one dining hall
with kitchen, a library, and a room for the parents
association. The building is 4,982 m2 and the plot
is 8,000 m2. It is now fully in function, hosting 650
students. This building has obtained the “A” energy
performance qualification according to the CALENER
and LIDER programs. A high efficiency condensing boiler
with thermostatic valves, and a ventilation system with
Cultural Center Pablo Picasso (right)
paving the way 67
heat recovery is installed. And in addition 94.5 kWp solar
photovoltaic panels for producing electricity, and 9 solar
thermal collectors are installed to provide for 64% of the
schools hot water consumption.
See also page 61 for Case: A smart school is cool
4.3 Solar energy in Viladecans
The original goal was to install 342 kWp of solar PV
(for electricity) and 191 m2 of solar thermal panels (for
hot water). All solar thermal panels and a large part of
the solar PV panels were finally installed. Raquel Millán:
“We counted on finance from the national subsidy schemes
for photovoltaic energy in Spain. But these decreased by 70%
between 2004-2008. Therefore it is not as interesting for a
private company to invest in a solar energy plant anymore. This
also meant that the last PV installation had to be totally paid by
our partner VIGIP. This seriously affected the implementation of
PV in the frame of the cRRescendo Project.”
So far, 239kW of solar PV has been installed (2/3 of
what was planned) on 6 locations, with panels facing
southeast, south or southwest. The installations are
functioning conform to their specifications. Most PV
installations are mounted on buildings.
One exception: In La Marina Park, about 125 m2 of solar
PV is installed on a steel superstructure, including 96
panels (170 Wp each).
Several Wi-Fi spots are installed on outdoor PV-shelters,
which were created near a public sports field. On
the long run the municipality is still committed to
implementing a total 1 MW of PV in the city.
Solar panels on sport and theatre centre
68 new energy for growing communities
Sustainability fair
Training professionals in Viladecans on solar PV installation and maintenance (left)
Solar powered pergola servicing Wi-Fi hot spots (right)
Solar panels on municipal library
paving the way 69
4.4 Overcoming barriers – stepping forward
Performance in La Pineda affected by day-care users
The point of view from the occupants is enlightening.
As one teacher puts it: “La Pineda is a modern, comfortable, and
nice building. These are the really important criteria to judge
my working place.” She is obviously satisfied. Raquel Millán:
“But we were curious how the buildings perform energetically,
and executed a monitoring programme.”
Some preliminary results:
In day-care centre La Pineda, the heat consumption
seems to be much larger than CONCERTO specified, and
even larger than the national regulation. This is largely
due to high heat consumption in the winter months.
In addition the solar collector hot water yield was
substantially lower than expected. Should we conclude
that the performance is very poor? Not yet. First it is
important to take into account that there were start-up
problems with solar hot water provision. Due to liquid
losses in the primary circuit the collector had been out of
order for a while.
Second, inhabitants, occupants and visitors influence
performance. For example: Raquel Millán: “During evening
parents” gatherings, the parents adjusted the thermostat
settings to make it more comfortable, and these were not reset
for a longer period.” Carmen Pérez adds: “In a day care centre,
where children under one year old are taken care of, will require
substantial higher temperatures, maybe not taken into account
in the specifications.”
!It is obvious the energy installations
should be fully operational, and without
growing pains before starting the
monitoring period. And occupant behaviour
should be factored into the comparison
between calculated and measured performance.
The financial crisis
Despite the financial crisis, which interfered with the
project, considerable work has been done. Raquel Millán:
“The financial and housing crisis hit us hard. Financial setbacks
were multiple: Higher construction and land costs which
reduced profitability. Lack of tax incentives and subsidies for
sustainability in Spain. Reduced CONCERTO eligible costs for
construction (€/m2), and changed Spanish law regarding PV.”
Manage and improve the energy behaviour of all users of your eco-buildings.
Most of these setbacks are nation-wide.
The intervention by the municipality was to step
in as a back-up developer. Thus the majority of the
investments have been directly made by the municipality
and its municipal enterprises. The private sector has
not participated in financing. Raquel Millán: “The good
thing of such a deep crisis is that it forces you to rethink your
plans thoroughly and select the strongest.” We observe
from experience that any large long-term project will
encounter financial and conjuncture barriers along the
way.
Harness indigenous technologies
Raquel Millán: “Some sustainable building criteria, suitable for
Nordic countries, are not applicable or implementable in Southern
countries. And southern countries still have access to traditional
“indigenous” construction methods which have evolved as the
most effective in the climatic conditions.”
!An example is rainwater collection and
re-use instead of draining it. In Spain
rainwater collection is still common
practice, but in northern countries an
almost forgotten skill. In Almere’s
Columbuskwartier it is reintroduced. An interesting
balance should be found between the attractiveness of
technological advanced solutions versus traditional tools.
Can modern low-carbon technologies be combined
better with the traditional practices? Carmen Pérez: “We
think that if you want to change the future, you first have to look
at the past. This was also shown in the soccer stadium. With a
passive design which shades the building in summertime, the
cooling demand was substantially reduced.”
Catalyst for the future
Main benefit of this project is that the municipal
mentality has changed. At all levels. Raquel Millán:
“Becoming a smart energy city is not a question anymore, but a
belief – a true paradigm shift.” But why did the Council not
advertise its accomplishments with grand openings
of the buildings? Because of professional pride. Raquel
Millán: “We are still disappointed and remorseful that we had to
postpone so many plans. But it may turn out for good. We are
better geared for large-scale developments. We are now preparing
a re-development of the smart low-carbon Llevante development.
As such, cRRescendo has been an important catalyst and enabler
for a low-energy community.”
70 new energy for growing communities
towards a zero carbon city 71
Checking the ambition
The monitoring in cRRescendo was aimed at assessing the community level benefits of
integrating renewable energy sources (RES) as well as energy efficiency (EE) techniques
in the cRRescendo communities. On the following pages a selection of relevant
monitoring results will be discussed. The full monitoring results can be found on our project
website: www.cRRescendo.net.
Solar energy in cRRescendoThe Almere Solar Island, a large field with
520 coupled solar thermal collectors (7,800
m2), supplies renewable heat to the primary
district heating grid of Almere which acts
as an unlimited storage. The water flow,
temperature readings and irradiation were
recorded every 5 seconds from May 2010 to
June 2012. The results indicate that the Solar
Island annually converts 32% of the energy
received from the sun (irradiation) to heat. The
total yield of the Solar Island is between 8,440
and 8,930 GJ for a normal year, leading to a
yield per net m2 of 1.18-1.25 GJ. For comparison,
individual collectors typically have a yield of 1.1-
1.4 GJ per m2. So (within the error margin) this
specific Solar Island system already performs
equal to individual collectors without having
profited from its future learning curve yet.
Solar island (page 20)
For the solar hot water collectors in Ajaccio
(Rue de la Porta), it can be concluded that the
solar hot water production (in the first year
only) performs less than anticipated: 10 kWh/
m2 instead of the anticipated 15 kWh/m2 floor
area. Other locations such as Monte Mare
and St. Paul performed somewhat better 11-13
kWh/m2.
Buildings in Columbuskwartier are equipped
with a large number of small PV-systems
equipped with CIS solar cells from Wurth
Solar (CIS75-modules). CIS cells are thin-
film cells with a bit lower efficiency than
crystalline Silicon cells. It is the first time
these cells are used at this scale in Holland.
About 80 systems are monitored. The
annual monitored yield is 60-65 kWh/m2,
and the occupants themselves use most
of the electricity (>95%). The monitoring
also revealed several defects, which must
be solved by the supplier. Apart from these
defect systems, the average measured yield
has dropped in 2014 to 70% of the theoretical
calculated yield (72% in the beginning), which
was and still is too low.
The monitoring of solar PV systems in Milton
Keynes and Viladecans started late, leading
to a (too) short monitoring period. More
data will become available later. In Milton
Keynes the 165 kWp PV system, installed on
the old bus station, comprises of 825 panels,
of 200 Wp each. The output was continuously
monitored through a web portal and an
energy and carbon meter is prominently
displayed at the community centre. Data
acquired in the first half year of operation
(February-August) showed a production of
92.5 MWh. In Viladecans, 239 kWp of PV has
been installed, and for 117 kWp 8 months of
monitoring data were available. The results
for both cities indicate the systems perform
as expected.
Pv in MK (page 42/43)
Pv in Viladecans (page 67)
Ecobuildings in cRRescendoThe Ecobuildings can be roughly divided
in in three energy efficiency performance
levels above the level that is obliged by law or
building code. In Almere these houses were
for example called Eco-Houses, Solar Houses
and Passive Houses: with a 10%, 25% or 50%
higher energy performance. In Milton Keynes
all dwellings and buildings belong to the mid-
level ambition or higher, while in Ajaccio and
Viladecans the ambition level is spread over
the low and the mid performance level. But in
Ajaccio cRRescendo’s most ambitious (energy
positive) building is being built after the end
date of the project.
Noorderplassen West annual energy use
Calculated energy use
Regulation Concerto specs
Measured use
2010-2014
140
120
100
80
60
40
20
0
kWh/m2.a
72 new energy for growing communities
Almere and Viladecans:
“The first year monitoring effect”
In Almere a large amount of monitoring data
was collected of about 700 dwellings for
two consecutive years, including detailed
(monthly or real-time) results for about
100 dwellings. In Viladecans monitoring
data were limited. But still 8 months of
monitoring results were available at the end
of cRRescendo, while monitoring continues.
The monitoring results presented in the
figures on the average final energy demand
in the Almere communities shows that the
buildings in both Noorderplassen West and
Columbuskwartier in average have been
built according to the specs promised to
CONCERTO. When looking at the measured
energy consumption (real behaviour) an
interesting effect appears:
- In Noorderplassen West monitoring results
are in line with the expectations (see title
box).
- In Columbuskwartier however the
results improve a bit from the first to the
second monitoring year, with possibly an
underperformance in the first year.
This may be due to the fact that half of the
houses in Columbuskwartier had only been
commissioned just before the monitoring
started. In Noorderplassen West most houses
were delivered earlier. This supports the
recommendation not to base any conclusions
on the first year of monitoring directly after
realisation.
In Viladecans both the newly built Day
care centre La Pineda, and the refurbished
Cultural Centre Can Xic have been built
according to the CONCERTO specifications,
and show a large improvement over national
regulation. Monitoring data, only from the
preferrably “not to be used” first year, show
that Can Xic performs in line with the upfront
expectation, while energy use in La Pineda is
significantly higher. A possible explanation is
Annual energy use La Pineda
Columbuskwartier: Annual energy use
National
regulation
Planned Realised
CONCERTO
specification140
120
100
80
60
40
20
0
-20kW
h/m
2.a
Calculated use: Measured use:
2010-2011 2011-2012 2012-2014
Hot water demand (Space) Heating demand Electricity demand RE electricity production
Cooling demand SHW heat production
Annual energy use newly built and Can Xic - refurbishment
Planned Realised Planned Realised
160
140
120
100
80
60
40
20
0
-20
-40
160
140
120
100
80
60
40
20
0
-20
-40
Measured use Measured use
that this is due to the fact that Can Xic was a
refurbishment project, and that the “first year
monitoring effect” is only a problem for newly
built developments.
!To ensure a sufficient and high
quality data set at least a two
year monitoring period is
needed.
Variation of consumption in Ajaccio and Milton
Keynes
In Ajaccio, reference monitoring was
done for the re-built apartments in Rue
de la Porta in the historic city centre. In
addition, a measurement programme
was set up to measure SHW yield, hot tap
water consumption and heat consumption.
Unfortunately, due to hiccups during the
start-up only a limited part of the collected
data could be used for the analyses.
kW
h/m
2.a
kW
h/m
2.a
National
regulation
CONCERTO
specification
Calculated use:
National
regulation
CONCERTO
specification
Calculated use:
towards a zero carbon city 73
What was striking from the reference
monitoring of the old building was that
electricity consumption showed a huge
spread from apartment to apartment.
A similar picture was found during the
monitoring of the monthly electricity
consumption of 40 individual apartments
in Milton Keynes, and even more extreme
variations were observed in the heat use after
renovation for 15 monitored households in
Monte e Mare, Ajaccio.
Monte e Mare and Pinnacle – The real story behind
the results
In Monte e Mare measured heating
consumption and solar hot water
production were available. The solar hot
water production is reasonably in line with
expectations. The heat consumption seems
much lower than expected. However, it
turns out that the national averages and
expected 15% improvement in efficiency
from the national average (the CONCERTO
specification) is far away from being a
realistic picture of the situation before
renovation. The national average is for the
whole of France, while Ajaccio is situated in
one of the warmest areas in France.
Annual energy use in Monte e Mare - residential
Planned Realised
160
140
120
100
80
60
40
20
0
-20
-40
Planned Realised
Annual energy use in the Vizion buildings – residential
250
200
150
100
50
0
-50
Vizion Apartment Monthly Heat Consumption in kWh/m2
Based on 40 apartments
25.00
20.00
15.00
10.00
5.00
0.00
He
at
in k
Wh
/m2
Months
Aug - 10 Sep - 10 Oct - 10 Nov - 10 Dec - 10 Jan - 11 Feb - 11 Mar - 11
For Pinnacle, in Milton Keynes, the calculated
results are in line with the predefined
CONCERTO targets. However the measured
actual heat and electricity demand were
higher, while only 50% of the office and
retail areas were occupied. Full occupation
would at least further increase the electricity
use. Analysis of the profile of electricity
however showed that the night-time demand
rarely falls below 50% of the daytime peak,
indicating that a lot of equipment and/or
lighting is not turned off. Finally, zooming in
to the monthly totals shows strikingly that
both significant cooling and heating takes
place year round.
Combined Heat & Power plant and Vizion
building at par
The electrical generation efficiency for the
CHP was found to be 37% while thermal
efficiency was 30%. This corresponds to
manufacturer’s nominal efficiency levels of
42% (electrical) and 43% (thermal). There is a
degree of over-sizing of the central plant to
accommodate future expansion. So, often,
only one of the machines is required to meet
the demand, operating on part load for
significant periods.
The figure on the average final energy
consumption in the new Vizion residential
buildings shows the heat, hot water and
electricity demand are all found to be at
par with CONCERTO targets and shows a
tremendous reduction compared to the valid
national regulation.
kW
h/m
2.a
kW
h/m
2.a
National
regulation
CONCERTO
specification
Calculated use:
National
regulation
CONCERTO
specification
Calculated use:
Measured use
Measured use
74 new energy for growing communities
5
5.1 A learning history
Almere planning
Almere, as a young city, has been consciously planned
for the past forty years and is still developing today
notwithstanding the recession. It has been – and
still is – a continuous process of brainstorming,
designing, construction, experience and change.
Columbuskwartier, a neighbourhood in the new Almere
Poort district, is part of that process.
The discovery of a sustainable community Columbuskwartier Almere
5.1 A learning history
5.2 The district Almere Poort
5.3 From simple idea to detailed plan
5.4 Getting a grip on sustainability
— Managing Columbus’ egg
The neighbourhood, as well as the district, is
remarkable in many ways for both the city of Almere and
the Netherlands. Sustainability was taken into account
in all life cycle phases (development, realisation, use,
and maintenance).
A learning history with partners
The development has been very instructive, both in
terms of content and process. This motivated the
intensive evaluation of the effectiveness and successes
This chapter is based on “Columbuskwartier, de ontdekking van een duurzame wijk”, DuurzaamheidsLab, Gemeente Almere, May 2009.
the discovery of a sustainable community 75
of the sustainable development tools used
in Columbuskwartier. For instance with a
multi-actor analysis and a Learning History,
in cooperation with the Dutch national
innovation programme for building (PSI-
Bouw), public-private partnerships such
as the regional Nieuw Flevolands Peil, and
The Netherlands Organisation of Applied
Scientific Research TNO. The evaluation
showed that already during the preparation
phase a stage for parties to meet and initiate
new development projects in Almere was
born. The evaluation also showed that real
estate developer TBI/Koopmans was the
most important private stakeholder.
5.2 The district Almere Poort
Quality and sustainability
Almere Poort is the city’s fourth major
development area after (Almere) Haven,
Stad and Buiten. These earlier built districts
have provided Almere with large quantities
of houses but little diversity. In developing
Almere Poort the goals were driven by quality
instead of quantity and the desire to give
Almere a more urban feel. The 1999 Structural
Plan Almere Poort assigned sustainability as key in
future development. Columbuskwartier was designated
to become the most sustainable neighbourhood within
the district Poort.
From sandy lowland to a lively district
The area used to be sandy reclaimed land from the
IJsselmeer (IJ-lake). Now it has transformed into an
attractive and highly varied area. People can live, work
and do sports, right at the waterfront. It is transforming
into an urban area with ample space, and opportunities
for recreation, relaxation, and for a rich, fulfilling life.
Almere Poort consists of four residential areas, several
business parks, and a centrally located public park,
surrounded by water and green areas. By developing
the coastal zone, Almere is aiming itself towards the
waterfront. Residences as well as catering and options
for leisure will be constructed alongside the IJ-Lake. The
area is turning into the beach town of the Amsterdam’s
metropolitan area. A newly assembled dune area will
complement the current polder landscape.
All four residential neighbourhoods have their
own characteristics: Europakwartier will offer
modern, urban living. Columbuskwartier will be a
comfortable, suburban and very sustainable residential
neighbourhood. Homeruskwartier will consist of many
private (individual) developmental projects, while
Olympiakwartier will offer city centre facilities.
From a sustainable district to the most sustainable
neighbourhood
The focus on sustainability was chosen when Almere
Poort was very first planned. For the initial plans, an
Environmental Impact Report was made, to point out
the Most Eco-friendly Alternative from the different
scenarios for the area’s development - on the basis
of value to future generations. This Eco-friendly
Alternative proved sufficiently strong, and was
accepted by the city council as the preferential choice.
“The Columbuskwartier is Almere’s
most important showcase in the
cRRescendo project. In anticipation
of the Almere Principles - which
were published in 2008 - renewable
energy sources were explored and
sustainability was implemented
way beyond the conventional
ecological concepts. Almere Poort
and Columbuskwartier or more
specifically the community The
Marvel in Columbuskwartier South
is as sustainable as you can get on
the district and community level
anno 2012. It is well worth to be
discovered.”
Emil ter Horst, cRRescendo project manager for Almere
Urban design plan of Columbuskwartier (2005)
76 new energy for growing communities
Based on this Eco-Alternative the residential
neighbourhoods and business parks of Poort were
developed. Each neighbourhood was studied to evaluate
sustainable options. Al improvements have been
established on environment themes like energy, noise,
water, and ecology. An excellent example is the energy
supply to Almere Poort: a >90% reduction in carbon
dioxide emission has been reached.
Almere Poort overview map
In 1999, the plan for the Almere Poort area was to realize a
very versatile area with approximately 10,000 residences,
300-400,000 m2 floor space for offices, and 115 hectare of
business area for 20,000 jobs. Approximately 80 hectare
was planned for sport and leisure activities, and 35
hectare for other public facilities. In 2005, Almere Poort
Business Plan described how to enrich the original urban
development plan. This new structural plan influenced
the final design of Columbuskwartier. A truly integral
approach to sustainability was born for the first time in
Europe at this scale.
5.3 From ambitious idea to detailed integral sustainable urban plan
In contrast to traditional renewable projects and policy
which look at separate environmental factors, the
development of Columbuskwartier took an integral
approach: sustainable development of an urban
community along the entire spectrum of ecological,
physical, social and economic factors. The key question
was: how to interpret the concept of sustainability
factually, spatially and methodically.
Sustainable ingredients / building materials / elements
A municipal project team was given the assignment
to work out this key question. The first essential
step was to define sustainability. The internationally
recognized definition of sustainability interpreted with
the Triple-P Approach provided a useful framework to
realise and further refine this concept. With this the
step to concrete spatial developments specific to the
local situation however could not be made yet. Global
Overview of the development The Marvel, from final design to realized
the discovery of a sustainable community 77
concepts like climate change, pollution, quality of
life and future prospects, did not mobilise sufficient
support on its own. Therefore the project team
developed a list of more applicable definitions including
an array of options for spatial or physical ingredients.
And the list would cover all aspects of sustainability.
Describing environmental aspects was already
challenging, but this certainly also counted for
describing the social and economic aspects of
sustainability. Engaging external expertise did lead to
better understanding, but still no progress to municipal
practice was made. Alex van Oost, senior staff member
Sustainable Building and Energy at the department responsible
for environmental policy: “A special task was to elaborate on
the socially-sustainable character of the district, the “People”
part. Research on lifestyle and daily activity schedules
made us focus on the combination of work, family care and
household management. Another goal was to build houses
to accommodate people of all ages and lifestyles. We paid
special attention to design public spaces according to criteria
of interactional experience, safety as well as attractiveness.
Physical and ecological sustainability are necessary conditions
for social sustainability. Consequently, we set goals for
sustainable construction techniques, use of energy and water,
ecological aspects and noise reduction. Creating a visibly
sustainable district was a special item of attention.”
Sustainability Compass
In the years 2005-2008 it became very clear that integral
sustainable city planning does not happen overnight.
Bicycle path; cars can not enter the inside of the neighbourhood
Open rainwater system creates semi-private terraces at the front side of the dwellings, in close contact with the public space
78 new energy for growing communities
Knowledge instruments and tools for sustainable urban
planning such as the National Package (1999) and local
Blueprints for Sustainable Building were inadequate.
The project needed its own practical and flexible
supporting tools that would provide full information
from the very start of city plan development projects
and could adjust to specific needs during the process.
This firstly resulted in a sustainability matrix, much
like a reference document. The matrix subdivides
sustainability in three dimensions: People, Planet and
Prosperity. Within each of these dimensions, spatial
aspects relevant for sustainable city planning were
listed categorically. The matrix was used for the first
time in the development plan for Columbuskwartier.
Later it helped in the assessment of the tenders for the
southern part of the district.
This method was further developed together
with the Saxion College, leading to a prototype
for the Sustainability Compass. Insights from the
Columbuskwartier planning process were absorbed
into the Compass and validated in practice, thereby
creating a solid instrument applicable in Almere’s
context. Alex van Oost: “We were literally learning on the job.
The Sustainability Compass became an important supportive
instrument. It gives us insight into technical realization,
investments and management aspects of various ambitions.
It facilitates efficient and results-oriented working within the
project team. It not just describes ideas and ambition levels,
it shows how to achieve them and gives insight into costs and
benefits.”
Meanwhile the Compass has evolved into a web-
based computer tool linked to the widely used Dutch
Sustainability Profile of a Location. This instrument
helps to determine sustainable ambitions and puts a
figure to sustainable achievements of a district. The
Cascade Park close to Columbuskwartier was designed
in 2007 using both instruments.
5.4 Getting a grip on sustainability
The city Council was focused on developing social
sustainability. The project team spent much attention
on researching the options for spatial city planning in
relation to daily life, life style and consumer-directed
construction. This research formed the basis for items
like social cohesion, quality of life, social security and
child friendliness. The KinderPath is a concrete and
unique result, which became the social backbone of the
neighbourhood.
Until then, it was common practice to combine
technical, schematic and financial aspects with
spatial aspects to create a detailed blueprint plan
of areal division. That was also the initial set-up for
Columbuskwartier. However, in search of quality and
innovation, the Council decided to pioneer along a
different line. A framework plan was developed, in
which only a spatial framework was laid out, in which
construction sites could later be filled in. The framework
served to create cohesion between construction sites.
Subareas were merely given a scheme and a set of basic
rules for further elaboration. This way the Council
intended to allow the market to bring forth more quality
and creativity. The framework approach was a turning
point. It served as a valuable basis for achieving the
degree of sustainability in Columbuskwartier.
Solar Houses and Eco-houses called The Playery, artist impression and reality
the discovery of a sustainable community 79
Tendering and co-creation in the southern part
However, much had happened before all of this. Almere
decided on a tender procedure in order to attract
appropriate partners. Former Alderman Arie Willem
Bijl expected the market to bring in much knowledge
and creativity, and believed that tendering would be
the best method to stimulate this. Alex van Oost: “I have
always believed in the call for tenders to raise knowledge and
stimulate creativity. To give developers a set of criteria as
well as a certain amount of freedom in their designs was a
breakthrough for the project. In assessing their designs, just 10
out of 100 points were scored for sustainability. At that time
it was the best feasible. But things have changed. Take the
Cascade Park. In the design contest for housing development
no less than 50% of the score is based on a vision on sustainable
construction. We”re evolving! Ultimately almost all concepts
submitted for Columbuskwartier were of high quality, and
better than I had expected. Despite the low number of points
Solar Houses for house-owners around the KinderPath
KinderPath through the community with unique playgrounds (left)
More SolarHouses at the outside of the community, where cars may park (right)
80 new energy for growing communities
that could be granted, all plans focused on the sustainability
criteria. It was clear to me our sustainable ambitions stimulated
the market.”
Traditional but ambitious development in the northern part
In Almere Poort, three styles of urban development
were explored, differing in content and process: firstly
tendering and co-creation in the southern part of
Columbuskwartier. In the northern part there was room
for conventional ambitious development as well as
private (individual) contracting (relatively new for the
Netherlands).
In the northern part building areas were awarded to
project developers that had construction contracts in
other parts of Almere Poort as compensation for halted
projects elsewhere in Almere.
This resulted in a plan with over 100 Passive Homes.
Emil ter Horst: “The ambition in the southern part of
Columbuskwartier clearly stimulated the Passive houses – an
initiative of BAM – to go significantly beyond the quality level
we had set in the south.” Construction of this large number
of very low-energy houses in one project in the rented
sector was new in the Netherlands. But the level of
integral sustainability obtained in the southern part
The Marvel, was not achieved.
See also chapter 1 (page 14)
EC subsidy as an enabler for quality and persistence
The European grant for the cRRescendo project within
the CONCERTO programme proved of great value.
The grant was elaborated into a binding contract in
2005. This contract became part of the development
plan, which later became of critical importance to
safeguard the physical sustainability ambitions of
Columbuskwartier. The subsidy we received financially
supported our sustainability ambitions, for instance
to the many solar-powered houses. But European
recognition made the project position with the
city Council stronger, and also showed developers
we had something real to offer. In other projects in
Almere Poort, the ambitions were downscaled during
implementation, but not in the Columbuskwartier!
Looking back, success has many fathers. What and/
or who balanced “the Egg of Columbus” so successfully
through time? All success factors could have killed the
project if they had not been in place: the call for tender,
the arbitration, the new Alderman Adri Duivesteyn
continuing this specific urban development, the
inspiring staff members, or the subsidy from the EC. Or
was it the unique ambition of the real estate developer?
Jos Ensink, project manager at TBI/Koopmans. “For me it is
clear that the municipal project leader Aleida Winkelman is the
most important factor for the overall success of the project.
Ambitions are easily put on paper by a municipality at the
start and promises are easily made by a developer. But during
implementation ambitions are easily lost when they have to be
translated from the patient paper to the much harder practice.
Aleida Winkelman took the time to understand our problems
during implementation. She went for advise to municipality staff
for solving problems which emerged, and used her power when
it was needed. It was an excellent example of co-development by
municipality and real estate developer. Without her persistent
attention and skills from the very beginning until the first
delivery of houses in 2008, the integral sustainable quality of
The Marvel would have been much lower.”
People making the city in Columbuskwartier
Children showing their sustainable wishes in Columbus’ Egg
the discovery of a sustainable community 81
Managing Columbus’ Egg
Aleida Winkelman-van Doornum, Municipal project
manager Columbuskwartier (2003- 2008), Almere:
Columbus’ Egg
“In Columbuskwartier, we wanted to attain the most
extensive level of sustainability. A true community of the
future. At first no one in the project team found a solution
for The Egg of Columbus. We had high ambitions, but we
lacked the specific expert knowledge required to clarify
the broadly defined ambitions. And we could not easily
attract this knowledge from elsewhere. What we wanted
had never before been done in our country. Especially our
broad definition of sustainability proved to be an issue. We
were not looking for technical and architectural aspects
alone; we wanted to make a neighbourhood that would
be sustainable on a social level too. What is that? And how
were we going to make that visible and objective?”
! Make your ambitions concrete and
objective.
People, Planet, Prosperity
“We did better after taking the People, Planet, Prosperity
concept on board. This directly led to e.g. the idea for
the KinderPath: a safe and carless trail providing access
to residences, schools and facilities. The trail enables
residents to easily combine daily tasks such as care
and work, and will in fact be crossing the heart of the
neighbourhood passing by many meeting points and
playgrounds.”
! Think about the reward you offer in the
tender process to commercial businesses.
Our second-round reward amounted to
20,000 euro for each plan. Looking back, this
may have been too little compensation for high-quality
plans.
Call for tenders
“To us this was a whole new way of thinking. We were
used to design public areas ourselves, and make detailed
plans of land subdivision. Now all we could do was list
the conditions and leave the rest to external parties.
How much freedom were we willing to give tender
participators? Eventually we settled for the golden mean.
For example we listed the minimal numbers of new
residences and the percentage of social housing, but not
the division of dwellings across price segments.”
Much interest
“Eventually, the tender procedure went smoothly.
We raised much interest among all national major
development and housing corporations to register
for the procedure’s quality selection phase. Based on
predetermined criteria such as solvency and previous
projects (references), we selected five corporations for the
second phase of the procedure to work out an actual plan.”
High quality
“This resulted in a broad range of plans, all of high quality.
We predefined a scoring system in which criteria for
quality made up half of the score. Within these quality
criteria, we did not prioritize one specific aspect. This also
applied to sustainability, which in our opinion already was
the basis for the development plan of Columbuskwartier.
Ultimately, this decision turned against us when we
compared the final scores for all plans: they scored close
to each other. At first, the plan by TBI/Koopmans did
not win but seemed a good second choice. We had our
doubts about the financial support for TBI’s excellent plan
for public areas containing large numbers of exceptional
public elements. When TBI questioned our appraisal
and asked the arbitrator, they were granted right: it was
not our responsibility to pass judgment on the financial
support.
Although the arbitration procedure resulted in a delay, TBI
Bouw/Koopmans and Almere ultimately worked together
well and intensively. The developer wished to frequently
consult with us about the specific implementation.
Looking back, I found this very satisfactory.”
To repeat the success
“Now you can walk around the community. And you can
feel that especially The Marvel and its public areas are truly
exceptional.” Citizens express their enthusiasm as well:
“This is different than other Almere districts! Without the
call for tenders, we might not have been able to achieve
these optimal quality and sustainability aspects while
maintaining to offer buyers and tenants reasonable
prices. In the end, the city has saved time and money on
planning and arranging and subdividing land.”
Looking back, success has many fathers but, according to most stakeholders in the development process, only one mother: the understanding, solving but persistent project manager for the neighbourhood Aleida Winkelman.
82 new energy for growing communities
Empowering the community
Socio-economics
From a cRRescendo perspective, the
CONCERTO indicators had a poor fit with
most of the local projects. Nevertheless,
cRRescendo cities contributed information
on 87.5% of the CONCERTO indicators. On
the other hand many of the most relevant
issues of local interest during cRRescendo on
education, public events, and information on
the policy context were not well covered by
CONCERTO.
Almere is one of the cities that successfully
hired a local social research partner that
undertook independent research and
activities interactively with the central social
research coordinator. The local partner,
NMFF, did an excellent job of engaging the
public in the cRRescendo areas. In particular,
there were a number of creative activities
directed toward engaging children in the
renewable and efficient attributes of their
neighbourhoods. The full list of social
research related documents prepared by
NMFF are outlined in the dedicated Final
Social Research Report.
Milton Keynes also successfully hired a local
social research partner that undertook
independent research and activities
interactively with the central social research
coordinator. The local social partner, USEA,
carried out a number of social research
projects in close cooperation with the social
research coordinator Oxford University.
Together, these entities developed surveys
for the residents in the Vizion apartment
building, the occupants in the Pinnacle office
building, and the participants in a workshop
on the solar PV array. In addition, Oxford
University did a stakeholder analysis.
The social research in Ajaccio covers relevant
initiatives and priorities in relation to housing,
construction, energy efficiency and micro
generation – both at the French national level
and in terms of Corsica as an island in its own
right. Additional resident surveys focused on
people’s general understanding and familiarity
with technology, rather than on their response
Social & Policy Context
Direct Education and Training
Public Engagement Activities
Occupant Surveys
Stakeholder Interviews
Ajaccio üüü ü ü ü ü
Almere ü üü üüü üü üü
Milton Keynes üü ü üüü ü
Viladecans üüü üü ü
Distribution and magnitude of cRRescendo social research methods and results
For socio-economic research and monitoring a number of indicators were originally
proposed by the uniquely integral EC CONCERTO programme. These indicators served as
a general frame in which ideally research in each project was supposed to conform. Eight
issues were distinguished. In some of these areas, the goal was to find the percentage of people
(predominantly households) reacting positively to the CONCERTO measures.
Social dimension:
1 Degree of satisfaction / acceptance by inhabitants / tenants /
2 owners Level of information & direct participation
3 Active/proactive tenants behaviour
Environmental dimension:
4 Improvement of CONCERTO district environment and internal comfort level
Economic dimension:
5 Economic-ecologic cost effectiveness
6 Increase in local control of energy supply / local energy production due to CONCERTO measures
7 Stimulation of local economy
8 Pay Back Period (Investor side)
towards a zero carbon city 83
to having technology installed in their own
homes.
The Council of Viladecans commissioned an
extensive energy awareness and behaviour
research performed by unemployed people,
covering a large proportion of the inhabitants
in the entire city. Furthermore in a poll 330
interviews were collected in dwellings.
Questions focussed on surface area, number
of occupants, heating, cooling, water, lighting,
electrical appliances, kitchen, renewable
energies, and invoices. The analysis of the
interviews was done by Agencia d”Ecologia
Urbana. Finally, surveys were done to
dwellings built before 1976.
In the second half of 2010, 10.000 interviews
on energy consumption associated with
different kinds of urbanism and building
typologies were performed, while in
another study the water, gas and electricity
consumption of all public buildings of the
Viladecans Municipality was analysed.
As an illustrative example the survey in the
office building in Milton Keynes is elucidated
below.
Occupant Survey Pinnacle Building
In summer 2012, 130 staff members working
in the Pinnacle building were invited to
participate in a web-based survey about their
workspace. Of the 130 potential respondents,
83 completed online surveys were received
(64% response rate). The survey contained
a total of 79 questions, 57 of which were
displayed to all participants and 22 only
revealed depending upon the answers to
certain questions.
The standard survey included questions
on the following key aspects of the indoor
environment:
- Office Layout
- Office Furnishings
- Thermal Comfort
- Air Quality
- Lighting
- Acoustic Quality
- Cleanliness and Maintenance
- General Comments
An additional section about energy was also
included asking whether occupants were
aware and supportive of different aspects of
the cRRescendo measures. Overall, the survey
data show that the building is performing
well, except in the area of thermal comfort and
acoustical quality.
The majority (74%) of the respondents (as in
the Vizion resident survey) did not know the
building was connected to a combined heat
and power network. Similarly, more than half
(54%) did not know the building was designed
to be energy efficient. Nevertheless, 58% of the
respondents said they thought the building
was performing efficiently.
Overview
The table on the left shows the different social
research strategies pursued in each partner
city, with check marks indicating the type,
and the magnitude and relative success of the
effort devoted to different strategies. All cities
did more than one form of social research,
although each city tended to concentrate its
efforts in one area. Depending on the type of
research, some cities did more vigorous work
or produced more rigorous results than others.
More on socio-economic research can be
found in the community chapters of this book.
In addition the socio-economic work is also
well summarised in the downloadable and
elaborate cRRescendo Evaluation Report.
Satisfaction in Core Survey Categories
Graph showing the percentage of satisfied responses for each category in Milton Keynes
General Satisfaction Building (79%)
Thermal Comfort (30%)
Office Layout (62%)
Office Furnischings (75%)
Lighting (64%)
Acoustic Quality (30%)
Air Quality (44%)
Cleanliness and Maintenance (61%)
84 cRRescendo
6.1 Four cRRescendo cities
In Almere over 2000 dwellings have been built within
cRRescendo. Homes have been built in three efficiency
categories: “eco”, “solar” and “passive”. Monitoring
results show that overall the performance of the homes
is well in line with the expectations. For Eco Houses
the heat consumption tends to be even lower than
specified, because they were brought up to the same
insulation level as the Solar Houses. In addition, the
Solar Island has been built, producing enough heat for
the tap water needs for some 1000 households. The
yield is 1.2 GJ/m2, which is equal to that of individual
collectors.
New energy for growing communities Results, lessons and recommendations
66.1 Four cRRescendo cities
6.2 Diversity of projects in the different communities
6.3 EU policy lessons
6.4 Local policy and project level lessons
6.5 The building sector lessons
6.6 Bridging recessions
Based on the monitoring results collected in the first
monitoring year, the Almere cRRescendo project has
saved 31% (14 GWh) of primary energy compared to
a business as usual situation. The number does not
include high carbon reduction (up to over 90%) due to
cogeneration in Almere and by green electricity in the
community Columbuskwartier. The floor area of the
homes ended up larger than originally anticipated.
This happened especially in NPW and to the largest
extent in the areas where private commissioners built
their houses. Such effects could cause the total energy
demand for homes to keep rising, despite a substantial
increase in efficiency.
new energy for growing communities 85
In Milton Keynes a new apartment building with 441
apartments and a new commercial building have been
built. In addition, a 3 MWe combined heat and power
generation plant is now in operation. The apartments
perform in line with CONCERTO specifications, but
the commercial buildings consume substantially more
electricity as well as heat. The CHP is performing at
a lower efficiency level than foreseen due to larger
periods of partial load operation than foreseen.
Nonetheless, based on the monitoring results to date,
30% primary energy (5.8 GWhprim) has been saved in
the project compared to business as usual. This includes
the reduction due to the CHP and to the PV-system on
the bus station that has been built in the fall of 2011.
In Ajaccio mostly refurbishment of apartment buildings,
in total some 420 apartments, has taken place. The
most ambitious building, the new public service office
building unfortunately is being built after the project.
Based on monitoring results of 30% of the refurbished
apartments, 0.1 GWhprim savings have been achieved
for these apartments. For 12% of the apartments overall
heat and solar hot water measurements were done. It
can be concluded that 30% of the heat was supplied by
renewable energy.
In Viladecans two public service buildings have been
newly built and two buildings have been refurbished.
One municipal technical service building is still to be
built. Preliminary results of monitoring of the four
buildings show mixed performances, varying from
5% increase in primary energy consumption of day
care centre la Pineda to 25% reduction for refurbished
Cultural Center Pablo Picasso. The PV-system (117 kWp)
performs according to expectations.
Based on the monitoring results to date: 0.5 GWhprim
primary energy has been saved in the project. These
savings are primarily due to the 117 kWp PV-system.
Solar Houses next to the kid-friendly KinderPath in Almere (left)
The popular Vizion residence showing the path towards a zero-carbon future in Milton Keynes (right)
It was not without a struggle but cRRescendo finally opened the minds for sustainability in Ajaccio (left)
PV solar energy illuminates at night the football facilities building Torre Roja in Viladecans (right)
86 cRRescendo
6.2 Diversity of projects in the different communities
For Almere, project primary energy savings are
substantial both in % as in GWhprim, primarily
achieved by increasing efficiency in buildings but also a
significant portion in renewable heat.
For Milton Keynes savings are considerable both in % as
in GWhprim, to a modest extent by increasing efficiency
in buildings and to a large extent by efficient generation
of heat and electricity by the CHP.
For Ajaccio, projected primary energy savings compared
to business as usual are comparatively modest but
nonetheless significant, based on efficiency measures
as well as renewable energy, both heat and electricity.
For Viladecans, the percentage of primary energy
savings is huge in % and modest in GWhprim, primarily
achieved by renewable electricity and to a modest
extent by efficiency measures, simply because the
number of solar PV systems are large compared with the
cRRescendo buildings.
It is interesting to note that electricity is becoming the
largest share of primary energy in buildings. For the
services sector this was already the case in the reference
situation, but with efficient buildings this is now also
the case for residential buildings, even in northern
climates like the Netherlands and the UK.
The most efficient homes built are the passive homes in
Almere, with a total final energy consumption of about
70 kWh/m2. The most efficient non-residential building
is refurbished Cultural Center Can Amat in Viladecans,
with (based on preliminary data) a total final energy
consumption of more than 90 kWh/m2.
For three out of five non-residential buildings
monitored consumption turned out to be significantly
Overview of cRRescendo as built up to 2012
Almere Milton Keynes Ajaccio Viladecans
Number of homes built / improved
2093 new single family dwellings and 329 apartments
441 new apartments419 apartments refurbished and 8 apartments newly built
-
Number of other buildings realised
Several schools, day care and healthcare centres combined 31,533 m2 of space (53 units)
commercial buildings combined 33,336 m2 of space
1000 m2 of public office building to be realised in 2014
3 new public service buildings 2 refurbished public service buildings total of 9,224 m2
Renewable energy realised
7135 m2 nett/ 7800 m2
gross Solar Island, 689 kWp PV
165 kWp PV346 m2 solar collectors, 5.5 kWp PV
191 m2 solar collectors, 239 kWp PV
Polygeneration realisedCity district heating extended and improved to low-carbon
3042 kWe CHP - -
Approximate measured primary energy savings
14 GWh (31%)* 5.8 GWh (30%) 0.11 GWh 0.5 GWh
Approximate energy from RES
12% heat in 1st; 20% electricity in 2nd community2
3% of electricity23% of heat;Electricity not measured
100% of electricity
* without primary energy saving by cogeneration; 100% green electricity not taken into account.
new energy for growing communities 87
larger than expected. Even though discrepancies could
be caused by something as basic as operational hours,
it clearly shows the need to monitor, understand and
manage the consumption in non-residential buildings.
6.3 EU Policy lessons
Complex project management
cRRescendo has been a long (7 years) and complex
project which proved to be an enormous task to manage.
Furthermore many partners mention that the project
has also been heavy in an administrative way, creating
a lot of overhead costs. On the other hand we should
also see that this project delivered many great results
that without the support of CONCERTO would never
have been there. The amount of knowledge sharing and
learning was high.
Another lesson learned during this project was that
refurbishment projects with a high ambition are actually
even more difficult than new construction projects,
as the interests of the existing occupants need to be
incorporated and respected.
Recommendations for future projects:
- Definitely continue with similar CONCERTO
programmes, but consider to reduce:
- the amount of partners/communities per project
- the amount of deliverables/reports
- The overall coordinator had too little effective
instruments to steer all partners
Financial project management
Within cRRescendo the so-called “Clause 41” has turned
out to be one of the most important drivers for success.
Without this clause it would have been necessary for all
commercial/building parties to disclose their financial
accounts and keep separate administrative accounts.
Furthermore the exact calculation of the “additional
costs” of sustainability is an impossible task. Clause
41 enabled parties to claim their costs based on actual
performance. A disadvantage of this instrument is that
the financing/subsidy for the commercial realisation
partners only comes in at a very late stage in the project.
At that stage the money does not give that extra push in
the right direction anymore for which it was intended.
Recommendations for future projects:
Find ways for ways to finance realisation work earlier in the
process, without increasing the risk of bad performance.
Knowledge sharing
Knowledge sharing, an important topic within
cRRescendo, has known some downs, but definitely
contributed to the success of the project. During the
project we have learned that partners and stakeholders
are “open” for receiving new knowledge at certain
(specific) moments, but that it also worked out
differently than anticipated before when writing the
contract.
Recommendations for future projects:
- Focus the knowledge sharing in future projects
around the start and end date of the project. At the
start the EC could demand all partners to take note of
the current state of affairs and best practices in the
participating countries/the EU. And at the end of the
project the focus could be on dissemination of results
and lessons learned.
- Reserve a specific and separate budget for
dissemination for AFTER the moment the project is
fully finalized. We recommend to provide this budget
through a separate application.
- For monitoring we recommend the same approach.
So separate specific time and budget for thorough
monitoring research AFTER the main project is
finalised. This allows the technical partner to collect
enough high quality data and focus on high quality
analyses. Furthermore and just as important the
monitoring research in cRRescendo has proved that
construction projects and (new) house owners need
some time to settle: monitoring data becomes more
stable and reliable after the first year.
- Try to base the knowledge sharing in future project on
a more scientific basis.
Knowledge sharing between EC projects
The work of CONCERTO Plus and later Premium has
been very useful. This counts for the reports, but
especially for the meetings that were organised for
exchange of CONCERTO projects.
The transfer from the CONCERTO Plus to the CONCERTO
Premium organisation could have been planned
better in advance as this inevitably lead to loss of
knowledge. The EU wide activities with meetings in
Brussels and the overall monitoring are perceived as
very useful. Additionally the regional events organised
by CONCERTO Plus in the first years were also very
informative. Unfortunately these events were not
organised anymore by the CONCERTO Premium.
There is not a single EU-wide harmonised solution for success, but knowledge transfer within EU projects has proven to be very valuable to speed up energy transition in other cities.
88 cRRescendo
Recommendations for future projects:
- Organise both knowledge sharing on EU level and on a
more regional level.
- Reintroduce the regional CONCERTO Plus/Premium
meetings.
Observer cities
The cooperation with the participating Observer cities
has also been one with ups and downs, but finally with
good results. It was difficult to keep the Observers
interested throughout the whole project. This may be
caused by the length (7 years!) of the project. Lessons
learned from this are that every partner/Observer needs
an own specific interest in order to actively participate
during the whole running time of the project.
Eventually, we were able to attract the observers’
attention again by demonstrating the results of the
projects in four main cities in the fifth and sixth year,
and by showing ways to increase their own direct gain
in the project.
Recommendations for future projects:
- Keep on involving other cities through the “Observer”
construction in future projects.
- At kick-off observers can be active in peer-reviewing
and excursions to example communities. The special
connection does lead to results in future projects and
policy that would not happen otherwise.
- During the mid of the project the Observers’ attention
must be drawn by special dedicated sessions and
presentations during the annual project meetings.
- Use instruments to revive the interest at the end
when results and lessons learnt become available.
Cherish Diversity
We have learned within this project that there is no such
thing as one blueprint or approach for all communities.
The main reason for this is that the local situation,
policies, laws, economy, and cultures often differ too
much to be truly comparable. But is this an issue, and
does this mean we cannot learn from each other? The
answer is: no but we have to be realistic.
When the CONCERTO initiative was prepared in
2003, the vision was based on a more harmonised
ideal of paving the way to an energy neutral Europe.
The practise of CONCERTO has however given us an
extremely important, but large cookbook with a large
palette of colourful solutions for every corner of Europe.
Recommendation for future projects:
- Acknowledge the fact that these types of projects
inherently contain a lot of differences and that not
one harmonised solution or approach provides a
guarantee for success.
6.4 Local policy and project level lessons
Translating EU demands and international differences to
successful local projects
A fundamental problem for projects like cRRescendo is
how to translate complex EU requirements to the local
practice without having to many risks.
Within cRRescendo, e.g. to minimise risks payments
were only made after a certain activity was already
finished; but at this late moment the direct added value
to the building process is unfortunately lower. Project
developers have told us that they sometimes got the
feeling that the (big) contribution they made to the
success of the project was not always balanced with the
financial support received. Recommendations for future
projects:
- For next projects we recommend to work out a
detailed plan about the flow of money throughout
the project directly at the start of the project. And
make sure this plan integrates the interests of all
participants, is fair and is understood by all partners.
- Project finance can be made simpler by using very
straightforward rules like: a partner will get this
amount of money as soon as a specific set of criteria is
met.
Communication and dissemination
It has a great value for a project to have one (or more)
real icons for sustainability. This can create both local
acquaintance and involvement of the local community,
and also national or even international awareness of the
project. Furthermore such an icon can also be a good
tool for showing your vision behind the project.
In Almere for example the Solar Island has been such an
icon. It has attracted a lot of attention and visitors to
the Almere project, both national as international.
We also learned that good communication moments
arise when physical milestones (such as “first stone/
pole”, completion of the building, etc.) are reached. These
need to be celebrated, so the communication plan could
be built around these moments. Furthermore we learned
that locally people seem to be open for communication,
Be aware of the difference between new construction (address building companies!) and renovation projects (address house occupants!) when selecting the most appropriate instruments to reach your goal.
new energy for growing communities 89
The Almere Solar Island is used for communication to the local community. European astronaut Wubbo Ockels ( 2014) has inaugurated the innovative system and joins the festivity together with Alderman Steunenberg
only on the moments the information affects/benefits
them directly. Recommendations for future projects:
- Include icons for sustainability in future projects as
they draw the necessary attention both to the icon
itself, but also to related project activities in the
neighbourhood.
- Set up a clear communication plan up front in which
communication moments are smartly chosen (for
example around “milestone moments”).
- It is important to secure the participation of the city
mayors.
Ensure sufficient knowledge on municipal level
This project has proved (in all communities, and observer
cities) that an active local government is key for success.
The successes realized within cRRescendo would not
have been possible without the input of the local politics.
But on the other hand it became clear that to reach this
a lot of (technical and social) knowledge was necessary.
An example is the process of negotiating large contracts
with project developers. Here there is a great need of
skilled local civil servants. Another successful example
was the internal sustainability-lab in Almere with
technical expertise which can be called in on the fly at
projects all over the city.
Recommendation for future projects:
- Ensure sufficient knowledge on municipal level.
Effective local (performance based) instruments
We have seen several successful examples like a local
“carbon offset fund”, “ground quotes”, a “performance
based tender competition”, etc. A key success factor in
these local instruments was the use of performance
based factors in the process, instead of building
prescriptions.
The decision making process within renovation
projects is very different and more complicated than
for new construction projects. In renovation projects
often a majority vote is needed to accept the proposed
renovation plans. In renovations the amount of subsidy
can directly influence the decision of the inhabitant. In
new construction projects subsidies are less effective,
than in renovation situations. In fact they only matter
in higher ambition projects, as the costs are then
substantially higher.
Another success approach considering the instruments
was aim for gradual and manageable improvements
in energy performance. By setting targets that are
one step higher than (but not way beyond) the current
practice it proved to be possible reach great results, but
also without high additional costs or house prices. This
approach also ensures that effective scale up possibilities
exist while already proven technologies are used which
can benefit quickly from economies of scales and
connected price drops.
Recommendations for future projects:
- Make a conscious choice for effective local instruments
to reach your goal. In our experience a performance
based element within this instrument can be an
important and effective ingredient.
- Be aware of the difference between new construction
and renovation projects when selecting the most
appropriate instruments to reach your goal. Incentives
in a renovation project need to focus directly on the
(many) occupants of the houses, while instruments in
a new to be built development can address mainly the
real estate developers and building companies.
- Include (performance based) goals that are a step
ahead of the current practice, but still manageable to
ensure a (cost) efficient execution and scale up.
- Financial instruments can be very effective, but be
aware of possible unwanted side effects, and keep it
simple to avoid difficulties during execution.
6.5 The building sector lessons
Involvement of local building partners
Because the building partners are the ones actually
realising the project, their positive contribution is vital
90 cRRescendo
for the project success. At the start of cRRescendo it was
the intention to involve the local building companies
directly into the European project by making them
partners. In practice the companies couldn”t or didn”t
want to satisfy the accompanying demands like the
needed insight into their accounting systems and the
yearly reporting requirements. This was comprehensible
from their perspective, but also caused that they
were less involved within the project. In general the
building companies want a level playing field and clear
agreements with the municipality. Financial incentives
are only helpful in developments with very high
ambitions.
During cRRescendo we learned that the optimal mode
for cooperation between companies and the municipality
differs with the level of ambition of the project:
- For relatively straightforward projects where the
ambition is one step higher than the current practice,
and when there is a good instrument to verify it (e.g.
the current building code) the project can best be
arranged through a straightforward contract with the
municipality. Incentives that are given must be effective
at the start of the project. A good example is a reduction
of the ground price.
- Projects with a high ambition, the icon projects, are
often much more innovative and therefore much less
predictable. The building party can best be involved
in the project as a (real) project partner with its own
budget/subsidy, giving the needed flexibility. But if the
ambitions are not met, the partner will not get paid.
- Finally for projects in between (two steps ahead on
current practice) the cooperation could be more in the
form of a coproduction between the municipality and
the project developer. These types of projects also need a
larger scale (than the icons) to have impact, and this type
of cooperation helps the parties to share risk together.
Some of the most successful parts of the cRRescendo
projects were the result of close co-development
between the municipality and the project developers.
Recommendations for future projects:
- At the start of the project work on a way to give the
building companies a clear and determining role within
the project.
- Set up of the cooperation level based on ambition of the
project. The higher the ambition of the project developer
the more decisive he can be during the realization.
6.6 Bridging recessions
After 7 years of hard work cRRescendo has delivered not
only bricks and stones, installations, and monitoring
data, but also a lot of knowledge and lessons learned for
future projects.
The lessons and recommendations have been
summarized along the levels described before. It was only
possible to draw such a set of conclusions because we
took our research and studies serious.
Ecofys, Ademe and the University of Oxford have
developed standardised methods to monitor the
technical and non-technical issues of the project, in
order to be able to improve future replications of the
cRRescendo concept. Only sometimes the results were of
limited use; e.g. when partners were pressed for time so
the monitoring was performed during less than one year
(and therefore not really useful).
Equal important to cRRescendo were professional
training activities and dissemination: both internal
(between the four partner communities) and external
(to associate communities and broad European level)
dissemination.
cRRescendo had a final dissemination activity in the
successful “cRRescendo ConfeRRence, Step by step
towards a carbon neutral built environment”, held in
October 2011 in the city of Almere. The final conference
was for a broad range of target groups (authorities,
researchers, builders, project developers, architects,
etc.) and the proceedings can be found on:
www.cRRescendo.net
We are proud that we were successful in engaging
the public in the cRRescendo communities and the
stakeholders in the local markets. Outreach to other
citizens and local politics was such that we believe
that crossing the recessions a new latent strong wish
originated for going all the way to a carbon free society
as soon as possible. This strong commitment also calls
opposing forces, true, but they are not strong enough
to stop it. This is the new promise in the air at the end
of the recession: what a difference with 2003 when we
started and everything was still so expensive and almost
experimental.
This chapter continues on page 10
A municipality can set up the cooperation and agreement based on the level of ambition of the project. The higher the ambition of the project the more decisive the project developer can be during realization.
towards a zero carbon city 91
Annex IRealised cRRescendo projects p92 - p97
Annex IIPeople behind the projects p98 - p99
Annex IIISolar Potential in Europep100 - p101
92 new energy for growing communities
Name
Photo
Community
Area description
Type built
Number of homes/buildings
Total gross area (m2)
Average area per house (m2)
Measures in buildings
Energy certificate
Generation of renewable power or heat
Solar thermal (m2) / pv (kWp)
Remarks
Name
Photo
Community
Area description
Type built
Number of homes/buildings
Total gross area (m2)
Average area per house (m2)
Measures in buildings
Energy certificate
Generation of renewable power or heat
Solar thermal (m2) / pv (kWp)
Remarks
Alm
ere
Alm
ere
Almere Solar Island Eco-apartments Solar Apartments Eco-houses
Noorderplassen West Columbuskwartier Columbuskwartier Columbuskwartier
New-built district New-built district New-built district New-built district
Solar Thermal Plant New Ecohouse (apartment) New Solar House (apartment)New Ecohouse (single family dwelling)
(Service building) 114 83 69
9,756 7,385 12,704
86 89 184
High insulation High insulation High insulation
EPC 0.8 EPC 0.62/ Cert. ZonneWoning EPC < 0.8
Solar Thermal Collectors (Output = 8.400-9.400 GJ/yr)
District heating based on waste heat
PV panels on less than half of the apartments, District heating based on waste heat
PV panels on half of the houses, District heating based on waste heat
7.800 m2 17 kWp in total
Solar thermal plant is directly connected to the district heating system of Almere.
Apartments with PV are certified Solar Houses (all apartments fulfil the BEST table for solar houses).
Health centre Office building Schools
Columbuskwartier Columbuskwartier Columbuskwartier
New-built district New-built district New-built district
Health Centre Office New primary schools
3 functional units 1 6 functional units
625 45 5,178
High insulation High insulation High insulation
District heating based on waste heat
District heating based on waste heat
District heating based on waste heat
Sports accommodation
Columbuskwartier
New-built district
Sports Accomodation
1
1,071
High insulation
PV solar plant, District heating based on waste heat
44 kWp
cRRescendo 93
De Verwondering Eco-apartments Solar Apartments Eco-houses
Columbuskwartier Noorderplassen West Noorderplassen West Noorderplassen West
New-built district New-built district New-built district New-built district
New Solar House (single family dwelling)
Eco Apartment Solar Apartment Eco House
342 84 48 1,462
47,993 7,685 6,586 257,551
140 91 137 176
High insulation High insulation High insulation High insulation
EPC 0.6; Cert. ZonneWoning EPC 0.89 EPC 0.72 EPC 0.89
PV panels on more than half of the houses, District heating based on waste heat
District heating based on Solar Island and waste heat
District heating based on Solar Island and waste heat
District heating based on Solar Island and waste heat
325 kWp in total
The majority of the houses are certified Solar Houses (all houses fulfil the BEST table for solar houses).
Apartments are not certified Solar Houses but fulfil the BEST table for solar houses.
Solar Houses
Noorderplassen West
New-built district
Solar House
116
19,815
171
High insulation
EPC 0.71 / None
District heating based on Solar Island and waste heat
Houses are not certified Solar Houses but fulfil there quirements for solar houses.
Day-care centre Health centre Shopping centre
Noorderplassen West Noorderplassen West Noorderplassen West
New-built district New-built district New-built district
Child Day-care facilities New health accomodations New shops
5 functional units 22 functional units 11 functional units
1,382 9,344 1,757
High insulation High insulation High insulation
District heating based on Solar Island and waste heat
District heating based on Solar Island and waste heat
District heating based on Solar Island and waste heat
Rented Passive Houses Goede Steede
Columbuskwartier
New-built district
New Passive Houses
103
10,815
105
Extreme high insulation, Triple glazing, Balanced ventilation with heat recovery
EPC 0.38/equal to Passive House
PV panels, District heating based on waste heat
108 kWp in total
First serial built passive house project in the rental sector in the Netherlands.
CO2 Neutral House
Columbuskwartier
New-built district
CO2 neutral house
1
225
225
Extreme high insulation, Triple glazing, Balanced ventilation with heat recovery
EPC 0.03
PV panels, District heating based on
waste heat, Small wind turbines
6,7 kWp
PV has been architecually integrated in the building façade.
94 new energy for growing communities
Milto
n K
eyn
es
Name
Photo
Community
Area description
Type built
Number of homes/buildings
Total gross area (m2)
Average area per house (m2)
Measures in buildings
Energy certificate
Generation of renewable power or heat
CHP (MW) / pv (kWp)
Remarks
Alm
ere
Name
Photo
Community
Area description
Type built
Number of homes/buildings
Total gross area (m2)
Average area per house (m2)
Measures in buildings
Energy certificate
Generation of renewable power or heat
Solar thermal (m2) / pv (kWp)
Remarks
International School Almere Dependance De Windwijzer
CascadePark-Poort Noorderplassen West
New-built district New-built district
New secondary school New primary school
1 1
5,135 961
High insulation High insulation
PV panels, District heating based on waste heat
District heating based on Solar Island and waste heat
26 kWp
CHP Thameswey Vizion Residential Sainsbury’s supermarket Vizion Retail
Central Milton Keynes Central Milton Keynes C4.1 (Vizion) Central Milton Keynes C4.1 (Vizion) Central Milton Keynes C4.1 (Vizion)
New-built district New-built district New-built district New-built district
Combined heat and power plant Residential building Supermarket Small retail stores
(Service building) 441 homes in 14 blocks 1 10
26,887 10.000 3.000
61
High insulation High insulation High insulation
EcoHomes “Very Good” / BREEAM “Excellent”
BREEAM “Excellent” BREEAM “Excellent”
3,04 MWe and 3,07 MW
th
District heating (and electricity) based on the CHP plant.
District heating (and electricity) based on the CHP plant.
District heating (and electricity) based on the CHP plant.
6.1 MW in total
A similar engine was added in 2009 increasing the capacity to 6.08 MW
e and 6.14 MW
th.
The “green roof” of the Sainsbury’s creates a podium garden for residents.
Primary schools
Noorderplassen West
New-built district
New primary schools
2
6,035
Unknown, only PV panels are part of cRRescendo project.
PV panels on main building De
Windwijzer, District heating based
on Solar Island and waste heat
47 kWp
Private contractors & other
Noorderplassen West and Poort
New-built district
Private Commissioned & other
Sustainable measures were not mandatory. Only PV panels are part of cRRescendo project.
EPC < 0.80
PV panels on 3 houses, District heating based on waste heat
9.9 kWp on 3 houses
Although not mandatory around 200 houses complied with the ambitious cRRescendo standards.
cRRescendo 95
Vizion Offices Pinnacle Pinnacle Retail PV Bus Station
Central Milton Keynes C4.1 (Vizion) Central Milton Keynes B3.2 (Pinnacle) Central Milton Keynes B3.2 (Pinnacle) Central Milton Keynes
New-built district New-built district New-built district Existing district
Commercial office space Office Small retail stores Roof integrated solar plant
1 3 Several (1)
1.100 18,281 955
High insulation High insulation High insulation
BREEAM “Excellent” EPC “A” / BREEAM “Excelent” EPC “A” / BREEAM “Excelent”
District heating (and electricity) based on the CHP plant.
District heat District heatPV solar plant on the flat roof of the previous bus station.
165 kWp
The installation had to respect the “architectural integrity” of the existing building.
Community Disposal Centre Sports facility Fanny Blankers Koen KlokHuis Groenhorst College
District Almere Poort Almere Noord West Columbuskwartier District Almere Poort
New-built district Existing community building New-built district New-built district
PV on municipality recycling station
PV on sports facility PV on educational centre PV on new secondary school
1 1 1 1
Unknown, only PV panels are part of cRRescendo project.
Unknown, only PV panels are part of cRRescendo project.
Unknown, only PV panels are part of cRRescendo project.
Unknown, only PV panels are part of cRRescendo project.
PV solar plant, District heating based on waste heat
PV solar plant, District heating based on waste heat
PV panels, Small wind turbine,
District heating based on waste heat
PV panels, District heating based on waste heat
37 kWp 45 kWp 1,4 kWp 23 kWp
The KlokHuis facility has also been used for dissemination and education.
96 new energy for growing communities
Vilad
ecan
s
Name
Photo
Community
Area description
Type built
Number of homes/buildings
Total gross area (m2)
Average area per house (m2)
Measures in buildings
Energy certificate
Generation of renewable power or heat
Solar thermal (m2) / pv (kWp)
Remarks
Aja
ccio
Name
Photo
Community
Area description
Type built
Number of homes/buildings
Total gross area (m2)
Average area per house (m2)
Measures in buildings
Energy certificate
Generation of renewable power or heat
Solar thermal (m2) / pv (kWp)
Remarks
Rue de la Porte Monte e Mare St. Paul Les Cannes
Historical Centre Urban renovation area Urban renovation area Urban renovation area
Existing district Existing district Existing district Existing district
New building apartments Refurbishment Refurbishment New office building (to be built)
8 homes in 1 building 92 homes in 2 buildings 52 homes in 2 buildings 1
602 6,370 3,637 1,000
75 70 70
High energy performance level of the building envelop
Refurbishment heating systemImproved ventilation, heating and lighting system, Roof insulation, Casa system
Ambitious specifications for insulation and ventilation
“Energy-positive”
PV panels, Solar thermal collectors Solar thermal collectors Solar thermal collectors PV panels, Small wind turbines
12 m2 and 5.5 kWp 98 m2 94 m2 20 kWp
An unsafe and unhealthy social rented building was demolished and replaced.
Build in a sensitive urban zone with high public housing, unemployment, and a low education level.
Build in a sensitive urban zone with high public housing, unemployment, and a low education level.
This energy positive building is developed within but built after the cRRescendo project period.
La Pineda Can Xic Torre Roja Pablo Picasso
Existing district Existing district Recreation area Existing district
New building day-care centre Renovated Youth Centre New sports facility building Renocated cultural centre
1 1 1 1
1,144 765 1,512 821
High insulation of roof, floor and windows, High efficient lighting and cooling
High insulation High insulation High insulation
Passive solar energy, Solar thermal collectors
PV panels Solar thermal collectors
12.5 m2 6 kWp 156 m2
cRRescendo 97
St. Jean 2 Pietralba
Urban renovation area Urban renovation area
Existing district Existing district
Refurbishment Refurbishment
196 homes in 4 buildings 80 homes in 10 buildings
22,904 6,985
117 87
Improved ventilation, heating and lighting system, Insulation of roof, walls and windows, Casa system.
Improved ventilation, heating and lighting system, Insulation of roof, floor, walls and windows.
Solar thermal collectors
142 m2
Build in a sensitive urban zone with high public housing, unemployment, and a low education level.
Build in a sensitive urban zone with high public housing, unemployment, and a low education level.
CEIP Ponent La Marina Park Atrium Cubic Municipal Library
Existing district Existing harbour area Existing district Existing district Existing building
New school building PV on new pergola PV on sports and theatre centre PV on conference centre PV on municipal library
1 0 1 1 1
4,982
Very high insulation
Calener / Lider Energy Label A
PV panels, Solar thermal collectors PV panels PV panels PV panels PV panels
22.5 m2 and 95 kWp 16 kWp 94 kWp 23 kWp 4.9 kWp
Smart devices like digital whiteboards, make this first Solar Smart School a model for other municipal buildings.
98 new energy for growing communities
Netherlands
Gemeente Almere
Ivo Booijnk
Adri Duivesteijn
Emil ter Horst
Annemarie Jorritsma,
Jack Laddé
Erwin Lindeijer
Jeroen Lubbers
Alex van Oost
Anne Marie van Osch
Sander Post
Linda Prins-van Essen
Marijke Quist
Ben Scholten
Tilly Stassen
Edwin van der Wel
Aleida Winkelman
Ecofys
Kathrin Braun
Antonin van de Bree
Pim van Gennip
Maarten Graveland
Vera Haaksma
Edith Molenbroek
Caspar Noach
Lou Ramaekers
Bart van der Ree
Nesen Surmeli
NUON
Gerrit Daalmeijer
Henkjan Marsman
Charlie de Ruiter
Frank de Vries
NMFF
Robert Atkins
Kim Boerboom
Vera Dam
United Kingdom
Milton Keynes Council
Martin Davies
Jeremy Draper
Geoff Snelson
Annex IIPeople behind the projects
The cRRescendo project was realised with the input and efforts of many individuals and
organisations. Mentioned here are the people from project partners. They are listed
alphabetically at the affiliation during their involvement.
HCA (formerly English Partnerships)
Steve Ball
Alan Bates
Allison DeMarco
Ian Duncan
Stan Farmer
Sue Green
Paul Hammond
Anthony Leney
Caroline Madden
Jon Muncaster
Andrew Pearson
Emyr Poole
Muhammad Rafique
Ann Seipp
cRRescendo 99
Paul Van Geete
Richard Watkins
NEF / USEA
Ian Byrne
Brad Hook
Ruth Wharton
Arup
Rupert Blackstone
Malcolm Heath
Chris Trott
John Piggott
Barry Austin
Oxford University - Environmental Change
Institute
Brenda Boardman
Sarah Darby
Nick Eyre
Kathryn Janda
Anu Jogesh
Gavin Killip
Pernille Schillerup
France
Ajaccio Municipality
Christine Bernardini
Denis Bravi
Frédéric Debortoli
ADEME
Virginie Bollini
ADEME DR Corse
Philippe Istria
Alexis Milano
Corsican Regional Authority
Loic Chastanet
Maria Guidicelli
Marie-Dominique Paoli
François Noël Rossi
Thierry Souchard
Spain
Viladecans City Council
M. Arcos
A. Chaves
I. Fabró
E. Galisteo
M. Jarque
Raquel Millán Lopez
Carmen Pérez Figueras
X. Roig
J. Rodríguez
C. Ruiz,
C. Sainz
E. Serra
VIMED
I. Marin
S. Presmanes
J. Regalado
VIGIP
J. Crespo
J. Giner
SaAs Sabaté Asociados Arquitectura y
Sostenibilidad
J. Sabaté
Observers cities
SAN de Senart
Jerome Bourgis
Nathalie Dupont
Frederique Vinay
Sofia , Bulgaria
Nadia Nikolova
Silvia Savkova
Misterbianco, Sicily, Italy
Sergio Campanella
Mariangela Torrisi
In loving memory of Raquel Millan Lopez ( 2013),
a driving force in Viladecans to the cRRescendo
project and main Catalan contributor to this book.
cRRescendo 101
Roma
BucureştiLjubljana
Bern
Budapest
BratislavaWien
Paris
Luxembourg
Praha
Bruxelles/Brussel
Valletta
Athínai
Lisboa
Madrid
Warszawa
AmsterdamBerlin
Dublin
Vilnius
København
Rīga
Stockholm
TallinnOslo
Helsinki
Sofia
Zagreb
London
San Marino
Reykjavík
Tiranë
Sarajevo
Minsk
Podgorica
Skopje
Belgrade
Kyiv
Chişinău
Vaduz
Andorra la Vella
Nicosia
Tunis
Ankara
Dimashq
Rabat
Moscow
Amman
Bayrut
T'Bilisi
El Djazaïr
Jerusalem
60°E50°E40°E
30°E
30°E
20°E
20°E
10°E
10°E
0°
0°
10°W
10°W20°W30°W
60°N
60°N
50°N
50°N
40°N
40°N
JointResearch Centre
[kWh/m2]
[kWh/kWpeak] Yearly sum of solar electricity generated by optimally-inclined1kWpsystem with a performance ratio of 0.75
http://re.jrc.ec.europa.eu/pvigs/cmaps/mapinfo.htmGrid resolution (enhanced by terrain) Map projection
Data description:
Authors:
Legal notice: Neither the European Commission nor any personacting on behalf of the Commission is responsible for the use
which might be made of this publication.The boundaries and names shown on this map do not imply official
endorsement or acceptance by the European Commission.
www.eea.europa.euwww.gvm.jrc.it/glc2000
www2.jpl.nasa.gov/srtm/http://epp.eurostat.ec.europa.eu/
www.geonames.orgwww.naturalearthdata.com
0 100 200 300 400 500km
Ancillary data sources:
In collaboration with:
PV output: difference between fixed optimum angle and one-axistracking system
Optimum inclination of PV modules to maximize yearly energy yield
Optimumangle [°]
Comparison of global irradiation in urban areas per country
www.cmsaf.eu
520222426283032343638404244464850
750 900 1050 1200 1350 1500600<450 >1650
Gain in output [%]
>50
40
30
<20
Annex III Solar Potential in Europe
102 new energy for growing communities
cRRescendo 103
vimed vigip
104 new energy for growing communities
Colophon
Authors
Emil ter Horst, Caspar Noach, Leendert Verhoef and
Vera Haaksma
Source material
Paul Hammond, Raquel Millán Lopez, Virginie Bollini and
all partners. Chapter 5 is based on “Columbuskwartier, de
ontdekking van een duurzame wijk”, Almere, May 2009, with
texts from Connie Franssen, Berthilde Lammertink and
Alex van Oost.
Graphic design
Blik grafisch ontwerp, Utrecht, www.klikopblik.nl
Printing
Schorel Drukkerij, Spijk, www.schorel.net
Picture creditsFront side: Almere The Marvel/De Verwondering, Solar Houses
in the social rented sector around the KinderPath and the
SunDial (photo: Koopmans Bouwgroep).
Page 2: Almere The Marvel/De Verwondering, Solar Houses
with PV in the façade with view on the CO2 neutral house by Han
van Zwieten (photo: Koopmans Bouwgroep).
Page 6: Milton Keynes, Vizion Apartments with Roof Garden
landscaping on the roof of the Sainsbury’s supermarket
(photo: Homes and Communities Agency).
Page 57: Ajaccio, Refurbishment and energy saving measures for
social housing on Corsica (photo: Ville de Ajacio).
Page 70: Viladecans, The first primary “Smart School” CEIP Nova
Escola Ponent (photo: Ajuntament de Viladecans).
Page 100 (left): Almere Columbuskwartier, PV solar panels
being installed (photo: TBI-Koopmans).
Page 102: Almere Noorderplassen West, The iconic Solar Island
(photo: Gemeente Almere).
Back side & page 100-101: Photovoltaic Solar Electricity
Potential in European Countries (Thomas Huld, Irene Pinedo-
Pascua, JRC, European Commission, 2012, in collaboration with
www.cmsaf.eu). Legal notice: Neither the European Commission
nor any person acting on behalf of the Commission is responsible
for the use which might be made of this publication. The
boundaries and names shown on this map do not imply official
endorsement or acceptance by the European Commission.
Other photography: TBI-Koopmans, Horisun, J.A. Prins
(www.panopictures.nl) and all cRRescendo partners.
GlossaryBREEAM = (Building Research Establishment Environmental
Assessment Methodology) = is a certification method for the
sustainability and energy performance of a building
CHP = cogeneration of heat and power (electric energy).
CIS = Cupper Indium Selenide: is a type of PV solar cell.
CMK = Central Milton Keynes
EPC = (Energy Performance Coefficient) = the standard building
code certification method for assessing the energy performance
of a building in the NL
GJ = 278 kWh
GWhprim = unit for saved primary energy (in kWh or in PJ)
kWp = kiloWattpeak: is the standardised nominal power of a solar
system and equals more or less the (maximum) power a PV system
or unit produces when the sun is at noon (solar radiation
1000 W/m2 @ 25 degrees Celcius temperature)
MK = Milton Keynes
MWe = electric power expressed in 1000’s kW’s.
MWth = idem for thermal power (heat)
Polygeneration = almost equal as CHP: to generate more than one
source of energy, e.g. heat and power.
PV solar energy = photovoltaic solar energy or electricity directly
produced by solar cells from sun light.
SHW = Solar Hot Water energy technology
Zero-carbon = a concept for a community of producing just as
much carbon by using energy (e.g. on a yearly base) as that the
community is saving by producing renewable energy or biomass.
Zero-energy = more or less idem for energy
Editor in chief
Emil ter Horst (Horisun, on behalf of Almere)
Editor
Caspar Noach (Ecofys)
Affiliations, financial support and contact
European Commission: www.CONCERTO.eu
Municipality Almere: www.almere.nl
HCA: www.homesandcommunities.co.uk
Contact:
For more info and download: www.cRRescendo.net
Publisher
Horisun Renewable Energy Strategies, Utrecht, www.horisun.nl
ISBN 9789082257601 | © Almere, 2014
Roma
BucureştiLjubljana
Bern
Budapest
BratislavaWien
Paris
Luxembourg
Praha
Bruxelles/Brussel
Valletta
Athínai
Lisboa
Madrid
Warszawa
AmsterdamBerlin
Dublin
Vilnius
København
Rīga
Stockholm
TallinnOslo
Helsinki
Sofia
Zagreb
London
San Marino
Reykjavík
Tiranë
Sarajevo
Minsk
Podgorica
Skopje
Belgrade
Kyiv
Chişinău
Vaduz
Andorra la Vella
Nicosia
Tunis
Ankara
Dimashq
Rabat
Moscow
Amman
Bayrut
T'Bilisi
El Djazaïr
Jerusalem
60°E50°E40°E
30°E
30°E
20°E
20°E
10°E
10°E
0°
0°
10°W
10°W20°W30°W60
°N
60°N
50°N
50°N
40°N
40°N
JointResearch Centre
[kWh/m2]
[kWh/kWpeak] Yearly sum of solar electricity generated by optimally-inclined1kWpsystem with a performance ratio of 0.75
http://re.jrc.ec.europa.eu/pvigs/cmaps/mapinfo.htmGrid resolution (enhanced by terrain) Map projection
Data description:
Authors:
Legal notice: Neither the European Commission nor any personacting on behalf of the Commission is responsible for the use
which might be made of this publication.The boundaries and names shown on this map do not imply official
endorsement or acceptance by the European Commission.
www.eea.europa.euwww.gvm.jrc.it/glc2000
www2.jpl.nasa.gov/srtm/http://epp.eurostat.ec.europa.eu/
www.geonames.orgwww.naturalearthdata.com
0 100 200 300 400 500km
Ancillary data sources:
In collaboration with:
PV output: difference between fixed optimum angle and one-axistracking system
Optimum inclination of PV modules to maximize yearly energy yield
Optimumangle [°]
Comparison of global irradiation in urban areas per country
www.cmsaf.eu
520222426283032343638404244464850
750 900 1050 1200 1350 1500600<450 >1650
Gain in output [%]
>50
40
30
<20
Milton KeynesA first CHP and the ambitious Vizion & Pinnacle buildings have been replicated in the market and are the stepping stones to the development of large near-zero carbon integrated smart neighbourhoods
AlmereFrom a quantity driven urban planning through the Solar Island and a healthy near-zero-carbon sustainable community now to a zero-energy Smart City in 2022
AjaccioFrom lacking behind on sustainability through over 400 energy saving refurbished houses now to energy positive building at the French forefront
ViladecansEducation and showcasing sustainable community buildings and PV solar energy during the recession paves the way to the ambitious eco-district Llevant
San de Sénart
Misterbianco
Brussels
Sofia
CONCERTO inspires an innovative energy policy and contributes towards an energy independent Europe based on environmental, social and economic sustainability
New energy for growing communities
ISBN 9789082257601 | Horisun, Utrecht