Page 1: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

NANC Report

Number Oversight Working Group(NOWG)

January 22, 2003

Co-Chairs:

Karen Mulberry, WorldCom

Jim Castagna, Verizon

Page 2: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 2

Summary

• PAS Forecasting Work Around Recommendation

• PA Change Order Recommendations

• 2002 NANPA Performance Survey Status

• 2002 NANPA PIP Status

• Meeting Schedule

• Attachments - Tracking Documents - PAS Work Around Letter- PA Change Order Recommendations- Table of NANPA Complaints- NOWG Project Status Table

Page 3: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 3

PAS Forecasting Work Around Recommendation

• NANC 11-19-2002 Action Item:NOWG will consider feasibility of “work arounds” so that carriers can obtain number blocks if request exceeds PAS forecast.

– Considered the feasibility of “work-arounds” that would allow service providers (SPs) the ability to be assigned blocks by PAS even if the quantity of blocks requested exceeds the SP’s PAS forecast.

– Work-around focused on eliminating the need for an SP to provide the “on the spot” forecast currently required by PAS when the quantity of blocks requested exceeds the embedded PAS forecast.

– The NOWG was unable to identify a work-around that could be implemented by SPs. However, the NOWG did identify a solution that may be easily implemented by NeuStar in the short term.

• Recommendation:PAS should override and auto-update the SP’s embedded forecast for the current month based upon the actual number of blocks requested and should discontinue the present practice of informing the applicant “Resource Request Denied: Requesting more blocks than forecasted for OCN (XXXX).” PAS would continue to employ its existing logic for pool replenishment, which appears to be triggered by forecasts and not by block assignments.

Page 4: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 4

PA Change Order Recommendations

• Developed template format for change order analysis.

• Reviewed pending PA Change Orders and prepared recommendations for the FCC.

• Recommendations forwarded to the FCC and NANC Chair on December 6, 2002

• Eight Recommendations completed.

Page 5: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 5

2002 NANPA Performance Survey Status

• Survey response deadline extended to January 15th.

• Respondents tabulated to date:Industry and Other 146

Regulatory Agencies 27

• Timeline: 1-23 NANPA Operational Review - Washington

DC

1-28/30 NANPA Operational Review - Concord CA

2-24/28 Data analysis and report development

March Final Report to NANC

Page 6: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 6

2002 NANPA Performance Improvement Plan Status

PIP 1 - Code Administration System (CAS)

1. Analysis and recommendations gathered from CAS Users Survey - Suspended pending resolution of identified issues.

2. Program to increase CAS usage - Completed

3. Data discrepancies (LERG, CAS, NRUF) - Investigating solutions to correct differences.

4. Reconcile CAS capabilities with Lockheed proposal - Suspended by new requirements

PIP 2 - NANPA Web Site

Completed

PIP 3 - Code Administration

Completed

Page 7: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 7

Status NANPA 2001-2002Performance Improvement Plan

PIP 4 - Relief Planning

Completed

PIP 5 - NRUF

1. Revised exhaust projection posted to NANPA web site - Ongoing

2. Update NRUF Job Aide - Completed

3. NRUF data proactively provided to State Commissions - Ongoing

PIP 6 - Measurements

1. NRUF performance measurements added - Completed

PIP 7 - General1. Leadership on numbering issues - Ongoing

2. Distribute and explain FCC directives regarding number administration - Ongoing

Page 8: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 8

Upcoming Meeting Schedule

Dates Time Meeting Details January 21 2003

9am to 5pm NOWG Face-to-Face Meeting Washington DC

January 23 2003

9am to 5pm

NANPA Operational Review in Washington DC

January 24 2003

9am to 5pm NOWG Face-to-Face Meeting Washington DC

January 28-30 2003

9am to 5pm

NANPA Operational Review in Concord CA

February 24-28 2003

9am to 5pm

WG Face-to-Face meeting in Denver CO

March 10 & 14 2003

2 to 5 pm EST

NOWG Conference Calls

March 18 2003

9am to 5pm

NOWG Face-to-Face Meeting Washington DC

Contact either of the Co-Chairs for complete meeting or conference call details

WG meeting records and documents posted on the NANC Chair web site

Page 9: NANC Report Number Oversight Working Group (NOWG) January 22, 2003 Co-Chairs: Karen Mulberry, WorldCom Jim Castagna, Verizon

01/22/2003 NOWG NANC Report 9

Attachments - Tracking Documents

• PAS Forecasting Work Around Recommendation Letter

• PA Change Order Recommendations (#6, #10, #11, #12, #13, #14, #15, #16)

• PA Change Order Tracking Summary

• Table of NANPA Complaints

• NOWG Project Table - tracking WG Activities/Timelines