NASHVILLE AREA MPO FY 2014-2017 TIP - ADOPTED DECEMBER 11, 2013
MULTI-COUNTY/REGIONAL
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description SR-109 relocation from Vaughn Rd west of I-65 to existing SR-109 east of I-65, new interchange at I-65and relocated SR-109/Vaughn Rd, & I-65 widening from south of new interchange to near the Kentuckystate line. SR-41 south of proposed SR-109 to near SR-259.
Proposed SR-109 relocation and new interchange at I-65 and the proposed relocated SR-109Location
Route I-65/SR-109 Prop/SR-41
$48,300,000.00Air Quality Status 107338.00TDOT PINNon-Exempt Project Cost
Multi-County 0.60 1053-240Regional Plan IDLengthCounty
TIP # 2006-416
TDOTLead AgencyInterchangeImprovement Type
I-65/SR-109 Prop/SR-41Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$700,000.00$6,300,000.00$7,000,000.00NHPPROW2014
$0.00$3,730,000.00$33,570,000.00$37,300,000.00NHPPCONSTRUCTION2014
$0.00$140,000.00$560,000.00$700,000.00STPROW2014
$0.00$400,000.00$1,600,000.00$2,000,000.00STPCONSTRUCTION2014
REVISION HISTORY
PROJECT NOTES
NHPP funds programmed at 90% federal share will be forcomponents of the project on the Interstate System (within theInterstate right-of-way)
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
58/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description ADA service capitalization. Complementary paratransit services within the Nashville-Davidson UZA using10% of annual formula apportionment.
RegionwideLocation
Route ADA Service Capitalization
$8,950,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-327Regional Plan IDLengthCounty
TIP # 2008-15-051
MPOLead AgencyTransit CapitalImprovement Type
ADA Service CapitalizationProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$223,750.00$223,750.00$1,790,000.00$2,237,500.00FTA 5307IMPLEMENTATION2014
$223,750.00$223,750.00$1,790,000.00$2,237,500.00FTA 5307IMPLEMENTATION2015
$223,750.00$223,750.00$1,790,000.00$2,237,500.00FTA 5307IMPLEMENTATION2016
$223,750.00$223,750.00$1,790,000.00$2,237,500.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
12/21/12 -This Project can be implemented within 12 monthsand project can be obligated within 12 months. MTA has anexperienced procurement and program management staff andis ready to begin procurement and deployment of the programtasks once the notice of award for this project has beengranted.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
59/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description See attachment 1 for a more comprehensive list of activities included but not limited for eligibility.
Regionwide - Nashville Area MPOLocation
Route Highway Safety Improvement Program (HSIP) Grouping
$8,000,000.00Air Quality Status 112112.00TDOT PINExempt Project Cost
Multi-County 0.00 1089-902Regional Plan IDLengthCounty
TIP # 2008-84-013
TDOTLead AgencySafetyImprovement Type
Highway Safety Improvement Program(HSIP) Grouping
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$200,000.00$1,800,000.00$2,000,000.00HSIPCONSTRUCTION2014
$0.00$200,000.00$1,800,000.00$2,000,000.00HSIPCONSTRUCTION2015
$0.00$200,000.00$1,800,000.00$2,000,000.00HSIPCONSTRUCTION2016
$0.00$200,000.00$1,800,000.00$2,000,000.00HSIPCONSTRUCTION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
60/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Administer, implement, operate and promote TDM-related programs including vanpools, employer/commuter outreach, ridesharing, etc.
RegionwideLocation
Route Regional Ridesharing & TDM Strategies - Program Administration
$3,783,700.00Air Quality Status 115232.00TDOT PINExempt Project Cost
Multi-County 0.00 1085-331Regional Plan IDLengthCounty
TIP # 2008-85-036
MPOLead AgencyTransit CapitalImprovement Type
Regional Ridesharing & TDM Strategies -Program Administration
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$312,500.00$0.00$1,250,000.00$1,562,500.00CMAQIMPLEMENTATION2014
$0.00$0.00$150,000.00$150,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
The 100% federal portion of the funding is for functions strictlyrelated to operations of vanpooling and carpooling.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
61/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Operation of and preventative maintenance for Music City Star Commuter Line East Corridor betweendowntown Nashville and the City of Lebanon.
Downtown Nashville to Downtown LebanonLocation
Route Commuter Rail Capitalization and Preventative Maintenance
$10,912,500.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 32.00 1085-320Regional Plan IDLengthCounty
TIP # 2008-85-091
RTALead AgencyTransit CapitalImprovement Type
Commuter Rail Capitalization andPreventative Maintenance
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$171,250.00$171,250.00$1,370,000.00$1,712,500.00FTA 5307IMPLEMENTATION2014
$125,000.00$0.00$500,000.00$625,000.00U-STP (Flexed toFTA)
IMPLEMENTATION2014
$125,000.00$0.00$500,000.00$625,000.00U-STPIMPLEMENTATION2014
$202,500.00$202,500.00$1,620,000.00$2,025,000.00FTA 5307IMPLEMENTATION2015
$125,000.00$0.00$500,000.00$625,000.00U-STPIMPLEMENTATION2015
$265,000.00$265,000.00$2,120,000.00$2,650,000.00FTA 5307IMPLEMENTATION2016
$265,000.00$265,000.00$2,120,000.00$2,650,000.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
62/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Express bus service from Spring Hill, Franklin, and Brentwood to Nashville and return.
Williamson County & Davidson CountyLocation
Route Express Bus Service from Williamson County
$1,100,000.00Air Quality Status 115225.00TDOT PINExempt Project Cost
Multi-County 38.00 1085-322Regional Plan IDLengthCounty
TIP # 2009-85-012
RTALead AgencyTransit OperationsImprovement Type
Express Bus Service from WilliamsonCounty
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$60,000.00$0.00$240,000.00$300,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
63/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Operations and capitalize service contracts for operation of express bus service frequency in the area’sSoutheast Corridor for RTA’s Express Route 96: Nashville/Murfreesboro Relax & Ride.
Davidson County and Rutherford CountyLocation
Route SE Corridor Express Bus Service Expansion
$4,097,840.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 36.00 1085-319Regional Plan IDLengthCounty
TIP # 2009-85-018
RTALead AgencyTransit OperationsImprovement Type
SE Corridor Express Bus ServiceExpansion
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$90,000.00$90,000.00$720,000.00$900,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Murfreesboro FTA 5307
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
64/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Campaign to address transportation-related issues negatively impacting the air quality in MiddleTennessee.
RegionwideLocation
Route Clean Air Schools Anti-Idling Campaign and School Pooling Program
$398,025.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1089-345Regional Plan IDLengthCounty
TIP # 2011-69-122
Williamson County/TMAGroup
Lead AgencyAir QualityImprovement Type
Clean Air Schools Anti-Idling Campaignand School Pooling Program
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$24,400.00$0.00$97,600.00$122,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
The TMA Group is a non-profit organization doing business onbehalf of the Clean Air Partnership of Middle Tennessee.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
65/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Public education and outreach activities through cost-effective multi-media and promotional outlets toeducate the public in general and select audiences on how their actions can reduce transportation-related emissions and improve air quality
RegionwideLocation
Route Transportation-Related Air Quality Outreach Campaign
$428,100.00Air Quality Status 115216.00TDOT PINExempt Project Cost
Multi-County 0.00 1089-345Regional Plan IDLengthCounty
TIP # 2011-69-124
Williamson County/TMAGroup
Lead AgencyAir QualityImprovement Type
Transportation-Related Air QualityOutreach Campaign
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$26,960.00$0.00$107,840.00$134,800.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
The TMA Group is a non-profit organization doing business onbehalf of the Clean Air Partnership of Middle Tennessee.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
66/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description RTA utilizes CMAQ funds to provide for expansion of bus services
RegionwideLocation
Route Expansion of Regional Bus Services
$1,100,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-323Regional Plan IDLengthCounty
TIP # 2011-85-125
RTALead AgencyTransit OperationsImprovement Type
Expansion of Regional Bus ServicesProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$50,000.00$0.00$200,000.00$250,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
67/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Job Access and Reverse Commute (JARC) Program funds to expand the availability of publictransportation services to employment and career centers throughout the region.
Nashville-Davidson Urbanized AreaLocation
Route
$4,291,368.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-504Regional Plan IDLengthCounty
TIP # 2011-85-147
MPOLead AgencyTransit OperationsImprovement Type
Job Access and Reverse CommuteProgram (Grouping)
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$100,000.00$100,000.00$800,000.00$1,000,000.00FTA 5307IMPLEMENTATION2014
$4,137.00$4,137.00$33,094.00$41,368.00FTA 5316 (JARC)IMPLEMENTATION2014
$100,000.00$100,000.00$800,000.00$1,000,000.00FTA 5307IMPLEMENTATION2015
$100,000.00$100,000.00$800,000.00$1,000,000.00FTA 5307IMPLEMENTATION2016
$100,000.00$100,000.00$800,000.00$1,000,000.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
68/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Purchase new vehicles and provide funding for seat guarantees for vanpools
RegionwideLocation
Route Regional Vanpool Start-Up Program (New Vehicles & Seat Guarantee)
$1,999,500.00Air Quality Status 115231.00TDOT PINExempt Project Cost
Multi-County 0.00 1085-326Regional Plan IDLengthCounty
TIP # 2011-85-154
MPOLead AgencyTransit CapitalImprovement Type
Regional Vanpool Start-Up Program (NewVehicles & Seat Guarantee)
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$0.00$1,333,000.00$1,333,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
69/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description 5-years of program funds to be awarded through competitive call-for-projects within 6-months of TIPadoption.
Regionwide (Nashville-Davidson UZA)Location
Route Regional Transit Projects with U-STP
$6,250.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-501Regional Plan IDLengthCounty
TIP # 2011-85-5555
MPOLead AgencyTransit CapitalImprovement Type
Regional Transit Projects with U-STPProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$1,250.00$0.00$5,000.00$6,250.00U-STPIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
70/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description 5-years of program funds for regional coordination of bicycle and pedestrian planning activities andcompetitive grants to be awarded through call-for-projects following the adoption of the TIP.
Regionwide (Nashville-Davidson UZA)Location
Route Regional Non-Motorized Projects with U-STP
$84,259.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1086-601Regional Plan IDLengthCounty
TIP # 2011-86-6666
MPOLead AgencyMulti-Modal UpgradesImprovement Type
Regional Non-Motorized Projects with U-STP
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$16,852.00$0.00$67,407.00$84,259.00U-STPIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
71/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description 5-years of program funds to be awarded through competitive call-for-projects within 6-months of TIPadoption.
Regionwide (Nashville-Davidson UZA)Location
Route Regional ITS & System Management Projects with U-STP
$38,750.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1087-701Regional Plan IDLengthCounty
TIP # 2011-89-9999
MPOLead AgencyITSImprovement Type
Regional ITS & System ManagementProjects with U-STP
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$7,750.00$0.00$31,000.00$38,750.00U-STPIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
72/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Pilot project at select large employers in the area to enhance awareness and communications regardingthe availability and accessibility of alternative transportation options for workers by utilizing transportationtechnologies
RegionwideLocation
Route
$320,000.00Air Quality Status 117132.00TDOT PINExempt Project Cost
Multi-County 0.00 1085-331Regional Plan IDLengthCounty
TIP # 2012-85-178
Williamson County/TMAGroup
Lead AgencyEducation & OutreachImprovement Type
Communicating Dynamic AlternativeTransportation Options at EmployerWorksites
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$44,200.00$0.00$176,800.00$221,000.00CMAQIMPLEMENTATION2014
$19,200.00$0.00$76,800.00$96,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
73/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Provide new and expanded bus service to Sumner County and communities. Service will include moredirect express trips, additional service hours, and potential new park and ride opportunities
Several routes between Nashville and GallatinLocation
Route NE Corridor Regional Express Bus Service
$900,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 29.00 1085-323Regional Plan IDLengthCounty
TIP # 2012-85-180
RTALead AgencyTransit OperationsImprovement Type
NE Corridor Regional Express Bus ServiceProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$30,000.00$30,000.00$240,000.00$300,000.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
74/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Install CCTV cameras, dynamic message signs and other equipment to expand the smartway in Davidsonand Rutherford counties.
I-24 in Davidson & Rutherford countiesLocation
Route
$9,000,000.00Air Quality Status 115549.00TDOT PINExempt Project Cost
Multi-County 14.00 ConsistentRegional Plan IDLengthCounty
TIP # 2012-87-192
TDOTLead AgencyITSImprovement Type
I-24E Smartway ExpansionProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$900,000.00$8,100,000.00$9,000,000.00NHPPCONSTRUCTION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
75/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Install CCTV and dynamic message boards on I-65.
I-65 from Exit 96 to Exit 108 in Davidson, Robertson and Sumner countiesLocation
Route I-65 ITS
$2,200,000.00Air Quality Status 117228.00TDOT PINExempt Project Cost
Multi-County 12.00 ConsistentRegional Plan IDLengthCounty
TIP # 2012-87-193
TDOTLead AgencyITSImprovement Type
I-65 ITSProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$5,000.00$45,000.00$50,000.00NHPPPE-D2014
$0.00$10,000.00$90,000.00$100,000.00NHPPROW2014
$0.00$200,000.00$1,800,000.00$2,000,000.00NHPPCONSTRUCTION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
76/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Improve the regional transportation infrastructure that is shared between the jurisdictionsof the City ofBrentwood and Metro Nashville using the tools of enhanced traffic signal coordination.
Several roads in south Davidson County and north Williamson County.Location
Route Several routes in south Nashville and north Brentwood.
$382,500.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1087-701Regional Plan IDLengthCounty
TIP # 2013-87-217
BrentwoodLead AgencyITSImprovement Type
Regional Traffic Management Study andSignal Optimization Plan
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$11,250.00$0.00$45,000.00$56,250.00U-STPPE-N2014
$43,750.00$0.00$175,000.00$218,750.00U-STPPE-D2014
$21,500.00$0.00$86,000.00$107,500.00U-STPROW, UTILITIES2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
77/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description A study for the implementation of future commuter rail service between Clarksville and Nashville.
Nashville Region Northwest Corridor between Nashville and ClarksvilleLocation
Route Nashville I-24 corridor
$500,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 45.00 ConsistentRegional Plan IDLengthCounty
TIP # 2013-89-204
RTALead AgencyPlanningImprovement Type
Northwest Corridor Transit StudyProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$50,000.00$50,000.00$400,000.00$500,000.00FTA 5307PLANNING2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
78/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Reconstruct and widen
Nolensville Road south of Burkitt Road to near SR-24 (Old Hickory Blvd)Location
Route SR-11 (US-31A)
$52,000,000.00Air Quality Status 105766.00TDOT PINNon-Exempt Project Cost
Multi-County 4.40 1012-185Regional Plan IDLengthCounty
TIP # 2014-82-049
TDOTLead AgencyRoad WideningImprovement Type
Franklin Road (SR-11/US-31A)Reconstruction & Widening
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$2,140,000.00$8,560,000.00$10,700,000.00NHPPROW2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
79/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Purchase and/or Rehab of locomotive(s) and rail cars for use on Music City Star service. Prepare andpaint exterior of passenger cars to cover rusted areas and improve image of service. Paint recentlypurchased locomotive to match paint scheme of current equipment. Rehab interiors of 30+ year oldequipment used on Music City Star service.
Downtown Nashville to Downtown Lebanon.Location
Route Purchase and/or rehab Locomotive and rail cars
$2,075,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-320Regional Plan IDLengthCounty
TIP # 2014-85-012
RTALead AgencyTransit CapitalImprovement Type
Purchase and/or rehab Locomotive and railcars
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$62,500.00$62,500.00$500,000.00$625,000.00FTA 5307IMPLEMENTATION2015
$31,250.00$31,250.00$250,000.00$312,500.00FTA 5307IMPLEMENTATION2016
$113,750.00$113,750.00$910,000.00$1,137,500.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
12/28/12 -Projects can be implemented within 12 months andproject can be obligated within 12 months. RTA has anexperienced procurement and program management staff andis ready to begin procurement and deployment of the programtasks once the notice of award for this project has beengranted. RTA has previous success with completing largercapital projects with the use of federal funds. There are nooutstanding legal issues that would make this a high-riskproject to implement quickly.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
80/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Purchase land/ building/equipment for new maintenance facility to allow RTA to effectively maintaincurrent and future service levels.
TBDLocation
Route Storage and Maintenance Yard for Music City Star Railcars
$500,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-320Regional Plan IDLengthCounty
TIP # 2014-85-013
RTALead AgencyTransit CapitalImprovement Type
Storage and Maintenance Yard for MusicCity Star Railcars
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$12,500.00$12,500.00$100,000.00$125,000.00FTA 5307IMPLEMENTATION2015
REVISION HISTORY
PROJECT NOTES
12/28/12 - RTA currently leases a maintenance facility fromNashville and Eastern Railroad.Milestone 1: Final Design andConstruction Plans - 60 days from grant award.Milestone 2:Project Out for Bid - 75 days from grant award.Milestone 3:Contract Awarded - 90 days from grant awardMilestone 4:Begin Construction - 120 days from grant award.Milestone 5:Complete Construction - 365 days from grant award.Sitelocation, preliminary engineering, environmental analysis,design, building and procurement of equipment will be themajor stages of this project.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
81/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Create a network of Park and Ride Lots to improve mobility across Region to promote regional rideshareand transit access.
RegionwideLocation
Route Regional Park & Ride
$2,750,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-329Regional Plan IDLengthCounty
TIP # 2014-85-014
Williamson County/TMAGroup
Lead AgencyTransit CapitalImprovement Type
Regional Park & RideProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$37,500.00$0.00$150,000.00$187,500.00FTA 5307IMPLEMENTATION2014
$62,500.00$0.00$250,000.00$312,500.00FTA 5307IMPLEMENTATION2015
$450,000.00$0.00$1,800,000.00$2,250,000.00FTA 5307IMPLEMENTATION2016
REVISION HISTORY
PROJECT NOTES
1/2/13 -Demand Study: Identify demand on corridors - Q1, Q22014.Site Proposals: Recommendations on sites, preliminarybudgets, project design - Q4 2014, Q1 2015.Final design andproject execution: Lease alternatives executed. marketing andmanaging of leased locations. Final design, final budgets forconstruction of future sites - Q4 2015.Construction of Site 1:Facility constructed and opened for public use - Fiscal2016.Construction of Site 2: Facility constructed and openedfor public use - Fiscal 2017.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
82/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Replace Vanpool Vehicles that have met FTA Useful Life Criteria.
RegionwideLocation
Route Vanpool Vehicle Replacements
$2,590,500.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-330Regional Plan IDLengthCounty
TIP # 2014-85-015
MPOLead AgencyTransit CapitalImprovement Type
Vanpool Vehicle ReplacementsProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$54,560.00$54,560.00$436,480.00$545,600.00FTA 5307IMPLEMENTATION2014
$52,800.00$52,800.00$422,400.00$528,000.00FTA 5307IMPLEMENTATION2015
$50,050.00$50,050.00$400,400.00$500,500.00FTA 5307IMPLEMENTATION2016
$101,640.00$101,640.00$813,120.00$1,016,400.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
FGC 1/2/13 - This project relates to TIP #2011-85-155 -Regional Vanpool Program - Vehicle Replacement (VanpoolVeh. replacement grouping managed by MPO).
1/2/13 -Based on mileage as of November 1, 2012, TMAestimates the following schedule for replacement ofvehicles:YEAR 1 - 2014 16 Vehicles.YEAR 2 – 2015 15Vehicles.YEAR 3 – 2016 14 Vehicles.YEAR 4 – 2017 28Vehicles.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
83/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Study, procurement and installation of Positive Train Control technology along RTA’s Music City Star lineand any future rail lines.
Regionwide - Music City Star and any future rail lines.Location
Route Positive Train Control
$19,750,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-85-022
RTALead AgencyTransit CapitalImprovement Type
Positive Train ControlProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$612,500.00$612,500.00$4,900,000.00$6,125,000.00FTA 5307IMPLEMENTATION2015
$487,500.00$487,500.00$3,900,000.00$4,875,000.00FTA 5307IMPLEMENTATION2016
REVISION HISTORY
PROJECT NOTES
1/31/13 -The first phase of this project will be the initialconsultant study of the best ways to implement PTC followedby procurement and installation of the technology. Projectscan be implemented within 12 months and project can beobligated within 12 months. RTA has an experiencedprocurement and program management staff and is ready tobegin procurement and deployment of the program tasks oncethe notice of award for this project has been granted. RTA hasprevious success with completing larger capital projects withthe use of federal funds. There are no outstanding legalissues that would make this a high-risk project to implementquickly.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
84/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Purchase of miscellaneous support equipment for commuter rail. Purchase of schedule display racks,shelters, benches, and associated sidewalk infrastructure, commuter rail signs, flags.
Music City Star commuter rail line between Nashville and Lebanon.Location
Route Music City Star Passenger Amenities
$100,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 32.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-85-023
RTALead AgencyTransit CapitalImprovement Type
Music City Star Miscellaneous SupportEquipment & Passenger Amenities
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$2,500.00$2,500.00$20,000.00$25,000.00FTA 5307IMPLEMENTATION2014
$2,500.00$2,500.00$20,000.00$25,000.00FTA 5307IMPLEMENTATION2015
$2,500.00$2,500.00$20,000.00$25,000.00FTA 5307IMPLEMENTATION2016
$2,500.00$2,500.00$20,000.00$25,000.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
1/31/13 -Projects can be implemented within 12 months andproject can be obligated within 12 months. RTA has anexperienced procurement and program management staff andis ready to begin procurement and deployment of the programtasks once the notice of award for this project has beengranted. RTA has previous success with completing largercapital projects with the use of federal funds. There are nooutstanding legal issues that would make this a high-riskproject to implement quickly.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
85/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Purchase of spare parts to rebuild and replace parts and equipment for the commuter rail.
Music City Star commuter rail line between Nashville and LebanonLocation
Route Spare parts for stock
$600,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-85-024
RTALead AgencyTransit CapitalImprovement Type
Spare parts for stockProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$15,000.00$15,000.00$120,000.00$150,000.00FTA 5307IMPLEMENTATION2015
$15,000.00$15,000.00$120,000.00$150,000.00FTA 5307IMPLEMENTATION2016
$30,000.00$30,000.00$240,000.00$300,000.00FTA 5307IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
1/31/13 -Projects can be implemented within 12 months andproject can be obligated within 12 months. RTA has anexperienced procurement and program management staff andis ready to begin procurement and deployment of the programtasks once the notice of award for this project has beengranted. RTA has previous success with completing largercapital projects with the use of federal funds. There are nooutstanding legal issues that would make this a high-riskproject to implement quickly.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
86/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description This program is intended to enhance mobility for seniors and persons with disabilities by providing fundsfor programs to serve the special needs of transit-dependent populationsbeyond traditional publictransportation services and Americans with Disabilities Act (ADA) complementary paratransit services.
Nashville-Davidson Urbanized AreaLocation
Route
$3,324,643.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-85-025
MPOLead AgencyTransit CapitalImprovement Type
Enhanced Mobility of Seniors & Individualswith Disabilities (Grouping)
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$83,834.00$83,834.00$670,673.00$838,341.00FTA 5310IMPLEMENTATION2014
$81,890.00$81,890.00$655,121.00$818,901.00FTA 5310IMPLEMENTATION2015
$82,873.00$82,873.00$662,983.00$828,729.00FTA 5310IMPLEMENTATION2016
$83,867.00$83,867.00$670,938.00$838,672.00FTA 5310IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
87/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Capital funding to replace, rehabilitate and purchase buses and related equipment and to construct bus-related facilities.
Regionwide: Nashville-Davidson Urbanized AreaLocation
Route
$2,520,112.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-85-028
MPOLead AgencyTransit CapitalImprovement Type
Bus & Bus Facilities (Grouping) - Nashville-Davidson UZA
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$61,880.00$61,880.00$495,040.00$618,800.00FTA 5339IMPLEMENTATION2014
$62,623.00$62,623.00$500,980.00$626,226.00FTA 5339IMPLEMENTATION2015
$63,374.00$63,374.00$506,992.00$633,740.00FTA 5339IMPLEMENTATION2016
$64,135.00$64,135.00$513,076.00$641,346.00FTA 5339IMPLEMENTATION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
88/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description 4-years of program funds to be awarded through competitive call-for-projects within 6-months of TIPadoption. Projects must meet federal STP requirements and improves or expand infrastructure toaccommodate existing or future transit service or promote or implement various other transportationdemand management strategies such as ridesharing, telecommuting, etc. Funding may be used toconduct transit alternatives analyses for regionally significant transit projects, implement a stand-alonetransit project, or supplement an existing project to ensure the inclusion of the appropriate transitaccommodations.
Regionwide (Nashville-Davidson UZA)Location
Route MPO Mass Transit Program
$4,716,217.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1085-501Regional Plan IDLengthCounty
TIP # 2014-85-5555
MPOLead AgencyTransit CapitalImprovement Type
MPO Mass Transit ProgramProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$83,374.00$0.00$333,496.00$416,870.00M-STPPE, ROW,CONSTRUCTION
2014
$859,880.00$0.00$3,439,521.00$4,299,401.00U-STPPE, ROW,CONSTRUCTION
2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
89/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description 4-years of program funds for regional coordination of bicycle and pedestrian planning activities to beawarded through competitive call-for-projects within 6-months of TIP adoption. Projects must advanceregional initiatives to improve the availability, safety, and convenience of active forms of transportation.Funding could be used to implement a stand-alone project or supplement an existing project to ensure theinclusion of non-motorized modes (e.g., adding sidewalks to a road widening project).
Regionwide (Nashville-Davidson UZA)Location
Route MPO Active Transportation Program
$15,199,407.24Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1086-601Regional Plan IDLengthCounty
TIP # 2014-86-6666
MPOLead AgencyMulti-Modal UpgradesImprovement Type
MPO Active Transportation ProgramProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$125,061.00$0.00$500,244.00$625,305.00M-STPPE, ROW,CONSTRUCTION
2014
$650,000.00$0.00$2,600,000.00$3,250,000.00U-ALTPE, ROW,CONSTRUCTION
2014
$1,289,820.45$0.00$5,159,281.79$6,449,102.24U-STPPE, ROW,CONSTRUCTION
2014
$325,000.00$0.00$1,300,000.00$1,625,000.00U-ALTPE, ROW,CONSTRUCTION
2015
$325,000.00$0.00$1,300,000.00$1,625,000.00U-ALTPE, ROW,CONSTRUCTION
2016
$325,000.00$0.00$1,300,000.00$1,625,000.00U-ALTPE, ROW,CONSTRUCTION
2017
REVISION HISTORY
PROJECT NOTES
U-ALT = Nashville-Davidson Urbanized Area TransportationAlternatives Program.
FY 2014 includes two years worth of funding.
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
90/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description Expansion of the Nashville ITS Smartway system in Davidson and Rutherford counties.
I-65 in Davidson & Williamson countiesLocation
Route I-65 South Smartway Expansion
$7,200,000.00Air Quality Status 115547.00TDOT PINExempt Project Cost
Multi-County 14.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-87-048
TDOTLead AgencyITSImprovement Type
I-65 South Smartway ExpansionProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$700,000.00$6,300,000.00$7,000,000.00NHPPCONSTRUCTION2014
$0.00$10,000.00$90,000.00$100,000.00NHPPROW, UTILITIES2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
91/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description See attachment 1 for a more comprehensive list of activities included but not limited for eligibility.
Nashville MPO Planning AreaLocation
Route National Highway Performance Program (NHPP) Grouping
$28,000,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-89-046
TDOTLead AgencyRoad UpgradesImprovement Type
National Highway Performance Program(NHPP) Grouping
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$1,400,000.00$5,600,000.00$7,000,000.00NHPPCONSTRUCTION2014
$0.00$1,400,000.00$5,600,000.00$7,000,000.00NHPPCONSTRUCTION2015
$0.00$1,400,000.00$5,600,000.00$7,000,000.00NHPPCONSTRUCTION2016
$0.00$1,400,000.00$5,600,000.00$7,000,000.00NHPPCONSTRUCTION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
92/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description See attachment 1 for a more comprehensive list of activities included but not limited for eligibility.
Regionwide - Nashville Area MPOLocation
Route Surface Transportation Program (STP) Grouping
$12,000,000.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-89-047
TDOTLead AgencyRoad UpgradesImprovement Type
Surface Transportation Program (STP)Grouping
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$0.00$600,000.00$2,400,000.00$3,000,000.00STPCONSTRUCTION2014
$0.00$600,000.00$2,400,000.00$3,000,000.00STPCONSTRUCTION2015
$0.00$600,000.00$2,400,000.00$3,000,000.00STPCONSTRUCTION2016
$0.00$600,000.00$2,400,000.00$3,000,000.00STPCONSTRUCTION2017
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
93/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description See attachment 1 for a more comprehensive list of activities included but not limited for eligibility.
Regionwide - Nashville Area MPOLocation
Route PM 2.5 Diesel Emission Reduction Strategies Grouping
$3,584,085.00Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 ConsistentRegional Plan IDLengthCounty
TIP # 2014-89-050
TDOTLead AgencyAir QualityImprovement Type
PM 2.5 Diesel Emission ReductionStrategies Grouping
Project Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$716,817.00$0.00$2,867,268.00$3,584,085.00CMAQIMPLEMENTATION2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017
94/191Page
NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Description 4-years of program funds to be awarded through competitive call-for-projects within 6-months of TIPadoption. Projects must meet federal STP requirements and also improve the operations of the regionalroadway or transit systems without adding lane-mile capacity for motorized or non-motorized vehicles.The program is intended to fund low-cost solutions aimed at improving traffic flow and safety alongcongested corridors and at intersection bottlenecks. Projects must incorporate some degree of ITS toinclude signage/wayfinding, traffic control/ signalization, traveler information, or information management.
Regionwide (Nashville-Davidson UZA)Location
Route MPO ITS/Ops Program
$2,358,135.75Air Quality Status TDOT PINExempt Project Cost
Multi-County 0.00 1087-701Regional Plan IDLengthCounty
TIP # 2014-89-9999
MPOLead AgencyITSImprovement Type
MPO ITS/Ops ProgramProject Name
Local fundsState FundsFederal FundsTotal FundsFunding TypeType of WorkFiscal Year
$41,687.00$0.00$166,748.00$208,435.00M-STPPE, ROW,CONSTRUCTION
2014
$429,940.15$0.00$1,719,760.60$2,149,700.75U-STPPE, ROW,CONSTRUCTION
2014
REVISION HISTORY
PROJECT NOTES
Printed on
Nashville Area Metropolitan Planning Organization
Wednesday, December 11, 2013
Transportation Improvement Program for FYs 2014-2017