mochovce unit 3 & 4 full-scope simulator project key points and successes

16
Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes [email protected]

Upload: gse-systems-inc

Post on 27-Jul-2015

74 views

Category:

Technology


1 download

TRANSCRIPT

Mochovce Unit 3 & 4 Full-Scope Simulator Project Key Points and Successes

[email protected]

2

Two New Units at Mochovce

• Modern power plant consisting of four Soviet VVER 440/V-213:– Units 1 & 2 operated since 1998

and 2000– Units 3 & 4 to be started up in

2014 and 2015

• Owner: Slovenské elektrárne and Enel

• Primarily modern Siemens controls and a modern control room with a traditional plant design.

3

Project Objective

High fidelity full-scope simulator:– All new system models and controls– New control room panels including emergency control

room– Siemens and other vendors sub-contractor to GSE– Simulator delivery critical to new plant schedule (critical

path) – Plant controls still in development as simulator was

being constructed

4

Simulator Applications

The simulator was successfully used for the following purposes:

– Verification and validation of the operational and emergency procedures

– Verification and testing of the DCS system to identifying control deficiencies to the main project • This has helped the main project schedule and costs

significantly!

– Training the new operators and preparing them for operating the main unit

5

3rd Party Integrated Software

The simulator integrated many third party new and complex technologies:

– Siemens /Areva DCS, BUP, Instrumentation and Control (I&C)

(T2000/T3000)-Virtual control with Stimulated interface

– Invelt/Skoda Turbine Control System (TCS) – Stimulated

– Skoda Reactor Rod Control System (RRCS) – Stimulated

– Rolls Royce Ex-core system – Stimulated

– SNIIP In-core system – Stimulated

– ZAT Electrical Distribution/Synchronization system – ED

Stimulated & Sync Simulated

– EnergoData Dispatching Center – Stimulated

– SafeCo Fire Detection and Protection System – Stimulated

6

Mochovce 3/4 Simulator Network Layout

7

Simulator Control Room

8

Simulator Control Room

9

Simulator Control Room

10

Simulation Software Tool Set

JADE Modeling Tool Set– JTopmeret: Two Phase Flow Network Modeling– JControl: Functional Block Control Modeling– JLogic: Schematic Logic Modeling– JElectric: Electrical Network Modeling– Theatre: Thermal hydraulics model– Remark: Reactor core neutronics model

JADE Instructor Station– JStation: Instructor/Operator Station

JADE Graphic User Interface (GUI)– JDesigner: Simulation Drawing Editor– JEditor: Object / Icon Editor

SimExec: Multi-User Real-time Executive

11

Core/TH Implementation

Neutronics Model– REMARK

• dimensional coarse mesh, two (or four) energy groups, time-dependent, diffusion model

– 349 fuel assemblies – 16 axial nodes– Core nodalization size is 349x16

or 5,584 nodes

Thermohydraulics Model– Theatre code– 5 equation model with drift flux– Using RELAP5 flow regimes and

properties– 350 nodes

12

JTOPMERET

Two phase, 6 equations, multi-component, non-thermal equilibrium model

High fidelity modeling tool designed for BOP

– Main steam – Feed water– CVCS– Containment, etc.

JTOPMERET has been implemented in over 50 full scope simulators.

Used to model All BOP fluid systems

12

13

Model Fidelity and Detail

New build plants with Digital I&C and control rooms allow the operator to see much more detail than older analog plants.

– Models must have a much more detailed scope of simulation.– Interface allow for trending and alarming of these systems and therefor

the fidelity of the models must support. – Older simulators could get by with less model definition as much was

hidden from the operator.

The value of the simulator as an engineering resource to the construction project means that more fidelity is required.

– Predictive models are needed, not “tuned” to match– Virtual and stimulated DCS allow for virtual commissioning and SAE

• Need real control algorithms

14

Project Challenges

Plant under construction, build simulator parallel with plant, DCS database availability and changes.

• Need to integrate changes and run automated test to validate logic• Many times new logic was not complete or ready for test• Customer relied on GSE team to test new controls for sim and new plant.

Integrate the simulator with third party vendors complex and new technologies.

• Third party tools• Each had its own issues (IC, communications, displays)

– Size and complexity of the project with unique features DCS, BUP and third party systems

– Location of the project • The project was performed in three locations: United States, Germany and

Slovakia • Created difficulties for providing resources and transportation of the

expensive equipment.

15

Project Result

The simulator project was started in March 2009.

Schedule was delayed/extended as major change was made to control room design.

Successfully completed on time in December 2013 – On-time delivery– On-budget delivery– Customer provided letter of commendation for the team

and the simulator.