Minutes of the 75th meeting of the Committee Constituted for Deciding the Consent under Orange Category, held on 03.09.2008 in the Conference Room of Chairman, DPCC.
The following persons attended the meeting:
1. Sh. J. K Dadoo, Chairman DPCC2. Sh. S.K.Gupta, Head Chemical Engineering Deptt. ,IIT Delhi 3. Sh. B. Kumar, SEE, DPCC4. Sh. M. Dwarakanth, SSO, Dept. of Env,. GNCTD.5. EEs of CMC – I, II & III.6. AEE of PGRC.7. AEEs and JEE of CMC – I, II & III.
Sh. K. Mahesh, Member Secretary, DPCC could not attend the meeting.
Following decisions were taken in the said meeting:-
Agenda Item No.1- Personal hearings of (i) Shoppers' Stop, Plot no 10, Shivaji Place, Rajouri Garden, Delhi (ii) Aditya Infracon (P) Ltd , at Plot no 8 Jasola District New Delhi (iii) Pankaj Buildwell, Sec-12 Dwarka, New Delhi (iv) ABW Infrastructure Ltd 208-210, Rectangle -I , D-4, Saket Dist Centre, New Delhi (v) Manish Buildwell Pvt. Ltd., Plot No 8, Sector-12, Dwarka , New Delhi (vi) Aman Hospitality Pvt. Ltd., (construction of '5 Star Hotel'), CBD Shahdara, Delhi (vii) R.C. Sood & Co. Pvt. Ltd. Proposed Shopping Mall at 10, Shivaji Palace, District centre, Raja Garden, Delhi, (viii) Vishal Retail Ltd., A-18, B Block, Mihan Co-Operative Society, Mathura Road, New Delhi (ix) Sabka Bazar (A unit of Home Store India Pvt. Ltd.), C-/10, GF, Janakpuri, New Delhi-58 (x) Galleria Property Management Services Pvt. Ltd at DT City Center, Block A, Community Center, Shalimar Bagh, Delhi
(i) Shoppers' Stop, Plot no 10, Shivaji Place, Rajouri Garden, Delhi
The unit did not come for personal hearing but sent an application saying that some leased area is part of the area mentioned in Environmental Clearance of R.C. Sood & Co. Pvt. Ltd.. They have also said that the application for Environmental Clearance of R.C. Sood & Co. Pvt. Ltd. mentions waste water generation of 72 KLD which includes the waste water generated by them. Also STP for this waste water treatment has the capacity of 80 KLD which covers both units. Since the unit is putting the onus of liability on the sub lesser i.e. R.C. Sood & Co. Pvt. Ltd., real facts can be ascertained only when both the parties are called for personal hearing together. Issue notice to both the parties for personal hearing on 17.09.2008 at 5.15 PM without waiting for minutes.
(ii) Aditya Infracon (P) Ltd , at Plot no 8 Jasola District New Delhi
The unit came for personal hearing but wants its Chief Engineer to be present since he is not familiar with the case. The Chief Engineer is reportedly sick as per their letter and 15 days time has been sought. Call for personal hearing on 17.09.2008 at 5.30 PM.
iii) Pankaj Buildwell, Sec-12 Dwarka, New Delhi
The unit came for personal hearing today. Unit claims that there are three small plots of 135 sqm each for which built up area as per the inspection report is 1593 sqm. According to the unit, there is no effluent discharged and there are no food courts proposed and it is only an office complex. The unit also claims that it has no D.G. Sets and no bore well. Let the unit file its application for Consent to Establish and the case will be considered in the CMC on 30.09.2008.
iv) ABW Infrastructure Ltd 208-210, Rectangle -I , D-4, Saket Dist Centre, New Delhi
The unit came personal hearing but wants its Chief Engineer to be present since he is not familiar with the case. The Chief Engineer is reportedly sick as per their letter and 15 days time has been sought. Call for personal hearing on 17.09.2008 at 5.45 PM.
v) Manish Buildwell Pvt. Ltd., Plot No 8, Sector-12, Dwarka , New Delhi
The unit came for personal hearing today. Unit claims that there are four small plots of 135 sqm each for which built up area as per the inspection report is 2160 sqm. According to the unit, there is no effluent discharged and there are no food courts proposed and it is only an office complex. The unit also claims that it has no D.G. Sets and no bore well. Let the unit file its application for Consent to Establish and the case will be considered in the CMC on 30.09.2008.
vi) Aman Hospitality Pvt. Ltd., (construction of '5 Star Hotel'), CBD Shahdara, Delhi
The unit came for personal hearing today. It has built up area of 91,000 sqm approximately and has started construction by way of excavation since 09.06.2008. It has applied for Consent to Establish and obtained Environmental Clearance on 08.07.2008. The total project cost of Rs. 866 crores. As per the SIT inspection, excavation work is in progress and fugitive emissions were noted for which SIT observed that concrete road would be required. Total water consumption is 1050 KLD as per the affidavit of the unit and the sewage quantity is expected to be 555 KLD.
Unit claims that it has not done any environmental pollution and it is a building for Common Wealth Projects which DDA has given a clearance for excavation. Unit was indicated that excavation causes maximum air pollution and, therefore, no authority other than the State Pollution Control Board or the MOEF can decide such matters since these are governed by law and Supreme Court orders. The unit sought time to file the item-wise compliance affidavit within 15 days. Time allowed till the CMC on 17.09.2008. The unit was also informed that the similarly situated circumstances units have been asked to pay damage of 10 % of ½ % of the project cost, which in present case amounts to Rs. 43 Lakhs and equivalent
amount of Bank Guarantee valid for three years. If the unit submits the same by 17.09.2008, Consent to Establish may be issued at the same time. Call for personal hearing on 17.09.2008 at 6.00 PM.
vii) R.C. Sood & Co. Pvt. Ltd. Proposed Shopping Mall at 10, Shivaji Palace, District centre, Raja Garden, Delhi
The unit did not come for personal hearing but sent a letter saying that he has received a notice of hearing on 02.09.2008. The concerned staff who handles the case, has prior engagements and therefore adjournment is sought. Call for personal hearing on 17.09.2008 at 5.15 PM without waiting for minutes.
viii) Vishal Retail Ltd., A-18, B Block, Mohan Co-Operative Society, Mathura Road, New Delhi
The unit came for personal hearing today. It was apprised of the need for payment of water cess whether by the unit or by its landlord expeditiously. It was also indicated to the unit that he needs to apply for Consent to Establish and provide the following:-
(a) CGWA clearance for the bore-well.(b) ETP for 16.8 KLD of trade effluent discharge.(c) Provide oil & grease trap/treatment system for the trade effluent
generated from restaurants.(d) Proper flooring and sheds are required at oil storage area at ground &
top floor in order to avoid leakage / spillage of water contamination. Waste oil needs to be handled properly / managed properly.
(e) Total project cost be submitted.
This data may be filed before 30.09.2008. Call for personal hearing on 30.09.2008 at 5.00 PM.
The unit was indicated that since it has been operating without Consent to Establish and Consent to Operate it would have to pay damages of 1 % of the project cost and Bank Guarantee of 2 % of the project cost valid for three years. The unit agreed to revert on this matter within two weeks.
The unit also informed that for water cess payment he requires one month time for its other 13 cases. Since this is a matter involving a resolution between the landlord and the tenant, cases listed of these units on 17.09.2008 may be transferred to 30.09.2008 and unit will file full compliance of the each case by 30.09.2008. In these 13 cases, due to non submission of some information required by our earlier letter, notices of closure have been issued. The unit represented by Mr. Narayan says that he received these letters after the date of the CMC meeting. The unit is therefore required to submit replies to the points raised in the SCN in all these 13 cases by 30.09.2008. Copy of the minutes of this unit may be handed over to Mr. Narayan tomorrow since Mr. Narayan apprehends personal retribution.
ix) Sabka Bazar (A unit of Home Store India Pvt. Ltd.), C-/10, GF, Janakpuri, New Delhi-58
The unit did not come for personal hearing today. Issue a letter to the unit to submit its comments on the complaint and the PGRC inspection report. Call on 30.09.2008.
x) Galleria Property Management Services Pvt. Ltd at DT City Center, Block A, Community Center, Shalimar Bagh, Delhi
The unit has filed the reply seeking time within office hours. Call for personal hearing on 17.09.2008 at 5.00 PM.
Agenda Item No.2- Special reference cases.
Decisions taken with respect to this agenda item are tabulated and annexed as Annexure – 1.
Agenda Item No. 3- PGRC cases.
Decisions taken with respect to this agenda item are tabulated and annexed as Annexure – 2.
Agenda Item No.4- Shopping Mall cases
Decisions taken with respect to this agenda item are tabulated and annexed as Annexure – 3.
Agenda Item No.5- Construction Projects cases
Decisions taken with respect to this agenda item are tabulated and annexed as Annexure – 4.
Agenda Item No.6- Cases of Wazirpur Industrial Area
Decisions taken with respect to this agenda item are tabulated and annexed as Annexure –5. Due to paucity of time, remaining cases of this agenda will be taken up in the next CMC meeting along with other WIA cases to be held on 30.09.2008.
Agenda Item No. 7- A representation received from DSIDC regarding extremely low pH discharged by the Industries at WIA
Due to paucity of time, Committee has decided to take up this agenda in the CMC meeting to be held on 30.09.2008.
Table Agenda Item No 1 :-M/s RMP International, A-51, Okhla Industrial Area, Phase-I, New Delhi-20
Unit has applied for renewal of consent on 24.05.2007 under Green category. During inspection on 08.01.2008, it was found that unit is operating with oil fired boiler and washing activity. Therefore, unit falls
under orange category and renewal of consent was refused on 26.02.2008 with Show Cause Notice u/s 31(A) of Air Act and 33(A) of Water Act.
In view of the above, unit may be asked to apply for Consent to Establish under Orange category. Call on 30.09.2008
Table Agenda Item No 2 : M/s Purearth Infrastructure Ltd, 20, Manohar lal Khurana Marg, New Delhi - 6
Call on 17.09.2008.
Table Agenda Item No 3 : M/s Hotel Queen Road Pvt. Ltd., 19, Ashoka Road, Connaught Place, New Delhi-01
Administrative decision read out and ratified. Call on 10.09.2008.
Table Agenda Item No 4 : M/s Carlos Elec Industries, 54, C-7, Rama Road, Najafgarh Road Indl. Area, New Delhi
Send him a copy of the High Court order and ask him to comply with it and respond. Call on 30.09.2008.
Table Agenda Item No 5 : M/s Bhawani Enterprises, D-21/6, Okhla Industrial Area, Phase-II, New Delhi
Call on 30.09.2008.
Meeting ended with thanks to the Chair.
Sl.No Name of the unit Activity Earlier Decision, if any ATR/Remarks Decision on 03.09.2008 Next Date
1 Samara India P LtdB - 18, Mayapuri Ind Area, Ph - I, New Delhi - 64
Automobile service station
11.06.2008The unit has filed reply and saying that it has not received many of the letters of DPCC and denied many of the findings of the inspection of DPCC. Unit be given a final reminder to file Bank Guarantee or face closure. Call on 25.06.2008. 25.06.2008While the unit has filed the Bank Guarantee, it has not filed the affidavit w.r.t. correction of the deficiencies. Ask him to do so. Call on 31.07.2008. 31.07.2008This was taken as a table agenda in view of the directions of CMC dated 25.06.2008. The unit has filed a Bank Guarantee and affidavit stating correction of the deficiencies. Unit may be asked to file Adequacy Report of ETP. Call on 03.09.2008.
Letter issued on 07.08.2008 for submitting adequacy report of ETP.No reply received so far.
Issue last and final reminder to submit adequacy report by 07.10.2008. Call on 7.10.2008.
2 Jhankar Banquet & Restaurant, Asiad Tower,
Khelgaon, New Delhi-110049
Banquet Halls 01.5.2008The file is not complete and without the note sheet. Concerned CMC to ensure file to be complete in all respects and put up on 14.05.2008. 13.5.2008Since an adverse inspection report of 24.10.2007 is on record, it will be in the fitness of things, the concerned CMC inspect the unit and submit the report in CMC on 10.06.2008. 11.06.2008The unit has to install hood & suction arrangement along with ducting on all LPG Chullas and provide a stack of minimum height of 30 feet. Ask the unit to file Consent to Establish application. Call on 11.07.2008. 11.07.2008Final Reminder be issued. Call on 06.08.2008. 06.08.2008Consent to Establish granted. Call on 03.09.2008.
Unit has obtained CTO on 08.10.2001 (valid upto 30.09.2004).CTE applied on 28.12.2007 vide I.D. No. 24608CTO applied on 26.02.2008 vide I.D. No. 25029As per CMC decision dated 06.08.2008, CTE issued on 19.08.2008.
Issue Consent to Operate. Call on 07.10.2008 for authorization.
3 Samara AutoMax Pvt. Ltd.A-17, Mayapuri Ind Area, Phase - I, New Delhi - 64
Automobile Service Station
11.07.2008The unit has filed an affidavit saying it will not use the ground water. Let him shut the borewell , show proof of drawing municipal water and file adequacy report of ETP. Call on 06.08.2008. 06.08.2008Let us wait for adequacy report to be filed. If there is any ground water drawl that must be closed down and confirmed to CMC Call on 03.09.2008.
Unit applied for Consent to Establish.Letter issued on 14.08.2008 regarding submission of adequacy report and closed down borewell.No reply received so far.
Issue last and final reminder to submit adequacy report by 07.10.2008. Call on 7.10.2008.
4 Mansfield Conveyors P LtdS - 77, Badli Indl estate, Delhi - 42
Safety/toughned glass
01.05.2008The unit must clarify the capacity of the oven. Call on 03.06.2008. 29.05.2008Consent to Establish will be granted if he files permission from Central Ground Water Authority for ground water drawl. Call on 03.07.2008 for documentary proof. 17.07.2008Insist on CGWA permission. Call on 06.08.2008. 06.08.2008Wait for reply. Call on 03.09.2008.
Unit was issued CTO on 20.8.04 valid up to 31.8.07.Applied for CTO (Renewal) on 27.8.07.Applied for CTE in March 2008 vide ID No. 25104Letter issued on 18.06.2008 regarding permission from CGWA for ground water drawl.Reply received on 01.07.2008 Ground water consumption indicated in the consent form is 1000 lt/day.As per CMC decision dated 17.07.2008, letter issued on 24.07.2008Submitted a copy of NOC from CGWA.
Consnt to Establish granted.
5 Vinayak International, A-115, Wazirpur Industrial Area
Mfg. of S.S. Utensils with buffing and polishing
17.07.2008Ask the unit to file Bank Guarantee of Rs. 1 Lakh under Air Act. Call on 06.08.2008. 06.08.2008Copy of the letter be pasted on the premises.Call on 03.09.2008.
Appied for CTE on 16.11.2007 vide I.D. No. 24218.Production capacity : 4000 Pc/day (as per affidavit)Unit has submitted a representation on 10.06.2008 & requested to issue CTE.As per CMC decision dated 17.07.2008, letter issued.Returned back undelievered & the same was delievered personally.Unit submitted Bg for Rs. 1 lakh under Air Act, 1981 on 01.9.08
SIT to inspect and report. Call on 30.09.2008.
6 Durga Enterprises, A-19, Wazirpur Industrial Area
Re-rolling of S.S. Sheets
06.08.2008If M/s Durga Enterprises files an affidavit that it will not undertake any pollution activity, Committee will consider its application for Consent to Establish. Call on 03.09.2008.
Letter issued.CTE obtained on 15.10.2004 vide consent order no. 11852 valid upto 27.09.2005.Applied for CTO 15.10.2005 vide I.D. No. 13391.Again aplied for CTE on 02.07.2008 vide I.D. No. 26256.Reply along with affidavit received on 02.09.2008. Unit has informed that they will not carried out any polluiton activity in future.
Issue Consent to Establish.
7 Mc-Donold Restaurant, West Punjabi Bagh
Restaurant 17.07.2008The unit has given contradictory data about waste water generation in the affidavit and Consent to Establish . Unit has also not filed the cash penalty & Bank Guarantee. Call for personal hearing on 20.08.2008 at 5.00 PM. 20.08.2008In view of the request for deferment, unit may be called for personal hearing on 28.08.2008 at 5.00 PM. 28.08.2008 The unit came for personal hearing today. It seeks one month time to do certain experiments for installation of ETP. The record of the unit shows that it has given contradictory data w.r.t. waste water discharge in the affidavit and the application for Consent to Establish. The unit is directed to comply with all previous directions issued by DPCC within 07 days i.e. by 03.09.2008. Call on 03.09.2008.
No reply received. Call for personal hearing on 30.09.2008 at 5.15 PM and for submission of all required documents.
1 Vikas Machine Tools22/7, Gali no.12, Anand Parbat Indl. Area New Delhi-5
Manufacturing of Industrial Knives
Decision on 18.06.2008: No case decided by the CMC will go to ALO for vetting. Draft order will prepared and will either be approved by MS or by chairman. If crucial legal matter is involved, DPCC counsel be consulted. Notice for closure be issued without waiting for minutes and also ask unit to file BG. Call on 18.07.08.Decision on 13.08.08:-Cases of PGRC are to be put up Administratively
Notice u/s 31(A) of the Air Act, issued on 19.06.08. The unit has already applied for CTE on 16.06.08. and submitted BG of Rs.1 lakh on 04.07.08. As decided in CMC meeting on 13.08.08, the file was put up administratively and it was decided to put up in CMC meeting to be held on 03.09.08.Earlier,closure direction u/s 31(A) of the Air Act was issued on 18.07.07
Call on 07.10.2008
2 Complaint Case M/s M.S. Metal 456-466, Gali No 8, Shambhu Nath compound, Friends Colony Industrial Area, Shahadara
Copper Melting
Decision on 18.06.08:-Ask the unit to file CTE. Call on 18.07.08.Decision on 13.08.08:-Cases of PGRC are to be put up Administratively.
Reminder issued on 02.07.08. Unit has applied for CTE on 16.07.08.The unit was again inspected by trainee engineers on 13.08.08 with reference to the public complaints. Following were observed during inspection :-(i). ECS installed and found in working condition.(ii). DG Set of 62.5KVA installed with accoustic enclosure and stack height 10 feet above roof level.(iii). Unit is complying with Hazardous waste rules.(iv). Applied for CTE.(v). Submitted BG of Rs.50,000.As decided in CMC on 13.08.08, the file was put up administratively and it was decided to put up in CMC meeting to be held on 03.09.08.
Issue Consent to Establish.
3 Complaint Case M/s Bansal Wire Industries Ltd/ Vishwaman Industries, 456-466, Gali No 8, Shambhu Nath compound, Friends Colony Industrial Area, Shahadara
Mfg. of G.I. Wire, M. S. Wire & S. S. Wire
Decision on 18.06.08:- Issue final reminder for BG. Call on 18.07.08.
Decision on 13.08.08:-Cases of PGRC are to be put up Administratively.
Reminder issued on 02.07.08. The unit submitted its reply on 16.07.08 and informed that they have already closed the factory and enclosed a copy of letter submitted to BSES Yamuna Power Limited for disconnetion or removal of connection. The unit requested to waive them from deposit the BG. The unit has submitted one more letter alongwith an affidavit that the unit has been closed and requested for cancellation of consent & authorization application. Applied for renewal of consent under Orange Category on 21.06.07 which is pending. Application for authorization under HW Rules applied on 13.07.06 which is pending. As decided in CMC meeting on 13.08.08, the file was put up administratively and it was decided to put up in CMC meeting to be held on 03.09.08.
In view of the PGRC inspection report, consent and authorization both are refused due to closure of the unit.
4 Complaint Case 1) M/s Veer Industries, Plot No. 48 (421-F), Gali no. 8, Friends Colony;2) M/s Shanti Nath Industries, Plot No. 48A, Gali no. 8, Friends Colony
Copper wire drawing and super enamelling
Decision on 25.06.08 : (1) M/s Veer Industry New PGRC engineer may inspect and confirm the facts of the case. (2) Santi Nath Industry Ask the test report and submit in the CMC on 31.07.08.
Decision on 13.08.08:-Cases of PGRC are to be put up Administratively.
(1) An inspection was carried out on 11.08.08 by trainee engineers (M/s Veer Industries).During inspection following was observed :-(a). No DG set was found there.(b). Hazardous waste is stored in a leak proof container with labeeling but not kept in an isolated area.
(c) Applied for CTE. (d) Bank Guarantee of Rs. 50000/- submitted.
(2) M/s Shanti Nath Industries Letter issued on 08.07.08 for test reports of Stack & D.G. sets. The unit submitted Stack monitoring report and Noise monitoring report on 29.07.08. Parameters found within limit.
M/s Veer Indutries for the deficiencies found by PGRC team, affidavit for compliance may be taken.
M/s Shanti Nath Inds : SIT to inspect and report. Call on 07.10.2008.
5 Complaint against industrial units Plot No.23, Badli Industral Area (a). Subhash jain ( Ankit Entrprises) Plot no.23, IInd floor, Ph-II, Badli Indl. Area (b). Dharmendra Yadav ( J.K. Entrprises) , Plot no.23, FF, Phase-II, Badli Industrial Area
(a). Mfg. of Polythene Tubes (b). Teflon Coating on iron (Press) Parts
Decision on 18.06.08:- (a) Issue final reminder for BG. (b) Issue final reminder for reply.Call on 18.07.08. Decision on 13.08.08:- Cases of PGRC are to be put up Administratively.
(a). Reminder issued to Sh. Subhash Jain ( Ankit Entrprises) on 02.07.08 to submit BG. Reply received. Requested to withdraw the clause of BG as the unit /Prop. is not in position to submit the same. As decided in CMC meeting on 13.08.08, the file was put up administratively and as approved, reminder letter issued for submission of Bank Guarantee on 03.09.08.As approved, the file is to be put up in CMC meeting to be held on 03.09.08 for ratification.
(b). Reminder issued to Sh. Dharmendra (J.K. Entrprises) on 02.07.08 to submit CTE. The unit has applied for CTE. The unit has already submiited BG of Rs. 1 lakh as approved on file. Case for ratification.As decided in CMC meeting on 13.08.08, the file was put up administratively and as approved CTE issued on 03.09.08. As approved, the file is to be put up in CMC meeting to be held on 03.09.08 for ratification.
Ratified by CMC.
6 Haldiram Mfg. Co. Pvt. Ltd., B-I/ F-10 &12, MCIE, New Delhi-44
Mfg.of Sweets & Namkeen
Decision on 25.06.08: Call for the test reports of both units and report in CMC on 31.07.08 Decision on 13.08.08:- Cases of PGRC are to be put up Administratively.
Both the units applied for renewal of Consent in the orange category on 24.07.08 and 25.07.08 along with test reports.As decided in CMC meeting on 13.08.08, the file was put up administratively. As approved, the file is to be put up in CMC meeting to be held on 03.09.08.
Issue renewal of consent to operate. File may be sent back to concerned CMC and consent order to be issued by concerned CMC.
7 Haldiram Marketing Pvt. Ltd., B-1/ H-8, Mohan Cooperative Industrial Area, New Delhi-44
Mfg.of Sweets and Outlet
Decision on 23.04.08:- No further action. Decision on 25.06.08( In case of M/s Halidarm Mfg. Co. Pvt. Ltd., B-I/ F-10 &12, MCIE, New Delhi-44 ): Call for the test reports of both units and report in CMC on 31.07.08Decision on 13.08.08:-Cases of PGRC are to be put up Administratively.
Both the units applied for renewal of Consent in the orange category on 24.07.08 and 25.07.08 along with test reports.As decided in CMC meeting on 13.08.08, the file was put up administratively. As approved, the file is to be put up in CMC meeting to be held on 03.09.08.
Issue renewal of consent to operate. File may be sent back to concerned CMC and consent order to be issued by concerned CMC.
8 Complaint against 1)H.No. WP 553 Village Wazirpur2)A-68, GF, Wazirpur Industrial Area3) B-25 Group, Wazirpur Indl. Area.
1) Unit closed.For (2) & (3) As approved in file, to be inspected by SIT. As Complaint was w.r.t. Wazirpur Indl. Area. Complaint in original has been sent to SIT on 16.05.08.
SIT inspection found ETP non functional, no hazardous waste management being practiced and bypass of all effluent into the sewer. Issue closure u/s 5 of EPA quoting Supreme Court order & u/s 33(A) of the Water Act Action to be taken by CMC-II, file may be transferred to CMC-II.
TOTAL NO
CMC S. No of
CMC
S. No.
Ref.
No
Name & Address
Date of EC accorded by MOEF
Status of application for CTE
Bult Up Area
Water / Waste Water details
Total Project Cost
Date of Commissioning
Earlier Decisions
ATR/REMARKS
Decision on 03.09.2008
Next Date
Earlier Decisions
Office Address
Status of EC Issued /Pending/Not Applied
Status of application for CTE
Date of Commissing as per application/ affidavit
I.D.No Date of Receipt of CTE
Decision on 26.06.2008
Decision on 25.06.08008
Decision on 18.06.2008
Decision on 11.07.2008
Decision on 24.07.08 Next
date(Old
)
1 1 1 1 SA-1
Campion Properties Ltd (Shoping Centre At ex Hotel Ranjit Site, Maharaja Ranjit Singh Marg)
22-04-08 Granted 14.5.08
30556sqm
145KLD\Dis-58.8(STP)
80crores
21.05.2008Ask the unit to file compliance affidavit item-wise of the Environmental Clearance conditions. Send appropriate reply to MOEF about the penalty and Bank Guarantee after showing to Chairman. Call on 25.06.2008. 25.06.2008Ask the unit to file application for authorization under HWM Rules. Also ask the unit to file permission from CGWA for ground
Letter issued on 08.07.2008 & 12.08.2008Unit has applied for authorization under HWM Rules. The unit has informed that it has applied on 21.07.2008 for permision for ground water drawl to CGWA.
Call on 07.10.2008 for CGWA permission.
07.10
10.03.2008Let him submit environmental clearance. Case to be taken up in April, 2008. 17.04.2008Call for personal hearing on 30.04.2008 at 7.00 PM. 30.04.2008The unit has admittedly completed 70 % of the structure in terms of built up area. The unit has been directed to stop construction by MOEF in Feb. 2008 and only
Campion Properties Ltd Vijaya Building, 5Th Floor, Barakhambha Road, Delhi-110001
P A End of the 2008
23420 39272 Ask the unit to file application for authorization under HWM Rules. Also ask the unit to file permission from CGWA for ground water drawl. Call on 31.07.2008.
31.07
water drawl. Call on 31.07.2008. 31.07.2008Issue reminder. Call on 03.09.2008.
after that the unit has got Environmental Clearance in April, 2008, applied for Consent to Establish on 07.09.2007 and the construction has been started on 17.05.2007 and applied for Environmental Clearance on 01.08.2007. The unit appears to have scant regard for environmental laws as it started its construction even before applying for Consent to
Establish and Environmental Clearance. MOEF while granting the Environmental Clearance has directed the unit to take Consent to Establish from DPCC, file it before MOEF and only then they will get permission for starting construction.In view of the above, the unit is required to pay 0.5 % of the estimated structural construction and 0.5 % as Bank Guarantee. Here the
total project cost will be taken on pro-rata basis as about 70 % of the structural construction has been completed which comes to about Rs. 56 Crores. The unit is therefore required to pay Rs. 25 Lakh as cash penalty and Rs. 25 Lakh as Bank Guarantee rounding to the nearest 5 lakh. The unit seeks time till 01.05.2008 to give its response. Call on 01.05.2008 at 6.00 PM.
01.05.2008The unit has agreed to the CMC condition and given a letter to the effect that it will file penalty and Bank Guarantee of Rs. 25 Lakh each by 14.05.2008. Call on 14.05.2008. 14.05.2008As instructed, M/s Campion Properties Limited has filed cash penalty of Rs. 25 Lakhs in the form of demand draft and Bank Guarantee of Rs. 25 Lakhs and
complied with CMC decision of 30.04.2008.In view of the above, the Consent to Establish should be issued to the unit tomorrow morning positively. 21.05.2008Ask the unit to file compliance affidavit item-wise of the Environmental Clearance conditions. Send appropriate reply to MOEF about the penalty and Bank Guarantee after showing to
Chairman. Call on 25.06.2008. 25.06.2008Ask the unit to file application for authorization under HWM Rules. Also ask the unit to file permission from CGWA for ground water drawl. Call on 31.07.2008. 31.07.2008Issue reminder. Call on 03.09.2008. 03.09.2008Call on 07.10.2008 for CGWA permission.
5 1 5 2 SA-5
Structural Fabricators Pvt Ltd (Anant Raj Agencies P ltd ) Commercial Complex at 67 Najafgarh Road, Kirti Nagar
08.07.2008
Granted 22.4.08
266878.13Sqm
MCD-248 KLD / 198 KLD (STP)
40 Crores
Dec----2008
28.5.08Call on 03.07.2008 for submission of a copy of Environmental Clearance.
31.07.2008Ask the unit to file itemwise compliance of Environmental Clearance conditions. Call on 20.08.2008. 20.08.2008Call on 03.09.2008.
The unit has submitted compliance of Environmental Clearance.
Ask the unit to submit compliance on affidavit. Call on 07.10.2008
07.10
11.04.2008The unit was given personal hearing and he agreed to pay the cash penalty of Rs. 5 lakh. Bank guarantee to be waived off, in case the project proponent files a proof of paying penalty to M.C.D. before 23/04/08. If the unit does so, then ‘Consent to Establish’ to be granted with a copy to Additional Secretary, MOE&F. 17.04.2008
Structural Fabricators Pvt Ltd,A.R.A Centre , E-2, Jhandewalan Ext, New Delhi-55
P A 39295
22497 18-07-07
04.07
Call on 23.04.2008.BG submitted. Accordingly, Consent to Establish issued. 28.5.08Call on 03.07.2008 for submission of a copy of Environmental Clearance. 31.07.2008Ask the unit to file itemwise compliance of Environmental Clearance conditions. Call on 20.08.2008. 20.08.2008Call on 03.09.200
8. 03.09.2008Ask the unit to submit compliance on affidavit. Call on 07.10.2008
6 1 6 3 SA-6
West End Mall, Janak puri Disrict Centre, New Delhi
Pending with MOE&F
Not Applied
15000Sqm in I/R
30KLD in I/R
44 Crores
15.5.08 11.07.2008Cash penalty filed.Let the unit file Bank Guarantee by 17.07.2008. Call on 17.07.2008. 24.07.2008Unit has submitted Bank Guarantee of Rs. 40 Lakhs during the CMC meeting and seeks time to submit remaining Bank Guarantee of Rs. 60
The unit has submitted a letter on 27.08.2008 stating that the EC is pending with MOEF.
Call on 07.10.2008.
07.10
10.3.2008Notice of environmental clearance may be issued immediately and this case will be taken up on 25.03.2008 for confirmation of Consent to Estabish & environmental clearance. Affidavit for date of construction and completion & architectu
West End Mall,M/s P. P. Buildwell Pvt. Ltd, Plot no 108, North Ex-Mall , Sec-9, Rohini,New Delhi
NO N _ _ _ Subsequent to the decision of the Committee on 11.06.2008 to issue closure order, the unit had represented that he was not prepared
Cash penalty filed.Let the unit file Bank Guarantee by 17.07.2008. Call on 17.07.2008.
Unit has submitted Bank Guarantee of Rs. 40 Lakhs during the CMC meeting and seeks time to submit remaining Bank
31.07
Lakhs. Time allowed upto 31.07.2008. Call on 31.07.2008. 31.07.2008Since damages and BG filed, Consent to Establish issued and directions for closure revoked. The unit may be asked to file Environmental Clearance soon. Call on 03.09.2008.
ral drawing may also be asked by 25.3.08. 03.4.08Take up on 10.04.2008. 17.04.2008Since unit has not responded for Consent to Establish and Environmental Clearance, MS to inspect and report on 30.04.2008. 01.05.2008The inspection of the unit by MS indicates following:(a) Consent to Establish
for 11.06.2008 to make his submissions and therefore he asked for another personal hearing. This letter was replied asking him to appear before the Committee today at 5.00 PM. Unfortu
Guarantee of Rs. 60 Lakhs. Time allowed upto 31.07.2008. Call on 31.07.2008.
not applied.(b) Claims Environmental Clearance not required as built up area without basements is 15000 sqm. For a plot size of 5507 sqm. (c) Total cost of the project is Rs. 45 crores.(d) ETP with 35 KLD capacity installed.(e) Three D.G. Sets proposed to be installed. (f) There are nine food courts sanctioned in the plan and the construction is over.
nately, the unit intends to avoid availing this opportunity and has tried to delay the mater when it was absolutely clear to the unit that the Committee is going out of its way to accomm
In view of the above, and complete violations of both Consent to Establish & Environmental Clearance, notice u/s 31(A) of the Air Act and u/s 33(A) of the Water Act for closure of the unit may be issued immediately bringing out all the deficiencies noted by MS during inspection. A copy of the letter may be sent to Addl. Secretary, MOEF, Director, BSES, CEO, DJB &
odate him. Such red herrings are not to be taken cognizance of by the Committee, and therefore the Committee confirms the earlier order which may be served to him by special messenge
Commissioner, MCD. This notice must be issued positively by 05.05.2008. To be drafted and signed by MS. 21.05.2008Call on 28.05.2008 with full details. Let concerned EE to research and submit all data to CMC on 28.5.2008 28.5.08The unit has not filed any reply to the SCN for closure. This is a first case where the unit appears to
r after approval of minutes by 23rd June, 2008.
be defiant. The EE concerned confirms that notice was validly served to the unit. In view of the above, MS is authorized to speak to the senior official in the unit and ask him to either file his reply by 29.05.2008 or appear before the Committee on 29.05.2008 failing which the unit will be effectively closed through SDM. 29.5.08it was informed today by MS in
pursuance of CMC minutes of 28.05.2008 to file its reply or appear before the Committee. The unit failed to do so. The Committee unanimously feels that this is the fit case for closure, but there is a little doubt on erroneous statement of built up area which must be cross checked and mentioned in the closure order. MS will get the calculation done through School of Planning Architect
ure and submit file before CMC on 11.06.2008. 11.6.2008The unit came for personal hearing today and stated that it has filed Consent to Establish and the Environmental Clearance applications. The unit pleaded ignorance about not filing these applications earlier, despite the fact in another case, it has filed to Consent to Establish application in August,
2007. The unit also claimed in its affidavit that the construction will end in 2010 whereas during the inspection by MS it was found almost complete and the unit confirmed this in the personal hearing. The representative was consistent that it had applied for Consent to Establish and Environmental Clearance and should be treated in similar fashion compared to units in similar
situation. This is a clear case whereby the unit has completed its construction without applying for Consent to Establish and Environmental Clearance. The unit gives the impression that it can manage its permission at its own free will. In such a situation, the Committee is of the view that closure orders may be confirmed to the unit with disconnection of power
and water supply for non compliance of environmental legislation i.e. EIA notification and provisions of the Air & Water Acts. All the deficiencies noted during the inspection and all other acts of omission and commission must be brought out in the detailed closure order. Draft closure order may be shown to the Chairman, DPCC by 16.06.2008 before issue. Call on
25.06.2008. 18.06.2008Subsequent to the decision of the Committee on 11.06.2008 to issue closure order, the unit had represented that he was not prepared for 11.06.2008 to make his submissions and therefore he asked for another personal hearing. This letter was replied asking him to appear before the Committee today at 5.00 PM. Unfortunately, the unit intends to
avoid availing this opportunity and has tried to delay the mater when it was absolutely clear to the unit that the Committee is going out of its way to accommodate him. Such red herrings are not to be taken cognizance of by the Committee, and therefore the Committee confirms the earlier order which may be served to him by special messenger after approval of minutes
by 23rd June, 2008. 27.06.2008The unit pleaded before MS on 26.06.2008 that it had been duped by his partners and architect and pressed for a personal hearing before the Committee. MS brought this information to the knowledge of the Committee and therefore he was allowed a personal hearing today.
In the personal hearing, the unit stated
again that it was totally ignorant about the environmental conditions and clearances and was duped by his architect and partners. The unit also pleaded that it had taken a loan of Rs. 13 crores by mortgaging the mall and therefore a very lenient view may be taken. The Committee deliberated on this matter over an hour and finally decided that the unit may be allowed
to comply with a cash penalty of 1 % of the project cost i.e. Rs. 50 Lakh and 3 % of the project cost i.e. Rs. 1.5 crores as Bank Guarantee by 11.07.2008 and the compliance must be filed in the CMC on 11.07.2008. If he does so, the closure orders will stand withdrawn and the Consent to Establish will be granted to the unit. Subsequently, a separate letter will be
addressed to Addl. Secretary, MOEF indicating the sequence of events and the levying of final cash penalty & Bank Guarantee on the unit. The unit has agreed to the same and filed a written undertaking to this effect. Call on 11.07.2008. As per SIT report, unit be asked to correct all deficiencies and update all systems to control air & water pollution including rainwater harvesting, water treatment &
recycling, solar water heating, compositing, greening & stack height for D.G. Set(s). 07.07.2008The unit was called for personal hearing today as a special case. In the last hearing, the unit was directed to pay Rs. 50 Lakhs as a cash penalty and Rs. 1.5 crores as a Bank Guarantee making a total of 4 % of the project cost. On that day, the project proponent was repeatedl
y requesting for Bank Guarantee of Rs. 1 crores instead of Rs. 1.5 crores. Today again he has made a request and in the interest of justice and to ensure fair treatment to all similarly placed cases the Committee felt that the Bank Guarantee can be reduced from Rs. 1.5 crores to Rs. 1 crores making a total of 1 % of the project cost as cash penalty and 2 % of the project cost as
Bank Guarantee i.e. 3 % in all. The validity of the Bank Guarantee should be for three years.
This may be communicated to the project proponent to be filed by 11.07.2008 without fail as per his own request in the CMC on 27.06.2008. 11.07.2008Cash penalty filed.Let the unit file Bank Guarantee by 17.07.2008. Call on 17.07.2008. 24.07.200
8Unit has submitted Bank Guarantee of Rs. 40 Lakhs during the CMC meeting and seeks time to submit remaining Bank Guarantee of Rs. 60 Lakhs. Time allowed upto 31.07.2008. Call on 31.07.2008. 31.07.2008Since damages and BG filed, Consent to Establish issued and directions for closure revoked. The unit may be asked to file Environm
ental Clearance soon. Call on 03.09.2008. 03.09.2008Call on 07.10.2008.
21 1 21 4 SA-21
PVR Naraina, Naraina, Delhi
Not submitted
Not submit
ted
_ _ _ _ 31.07.2008 The unit came for personal hearing today. It runs 8 cinema halls in Delhi and the situation is as follows:(a) In 3 cinema halls, the unit draws ground water, therefore it requires permission from CGWA.(b) In 3 cinema halls, the waste water discharge is more
Letter issued on 12.08.2008No reply received.
Reminder to comply with directions of CMC dated 31.07.2008 by 30.09.2008. Call on 30.09.2008.
30.09
01.05.2008A letter from Ex. Engineer (Karol Bagh Zone), MCD indicated that PVR Naraina was a shopping mall in Naraina Indl Area. Since there are other PVRs also, MS may issue a letter to PVR head office asking the following:(a) Built up area.(b) Waste water
PVR Naraina, Naraina, Delhi - 28
Call for personal hearing on 31.07.2008 at 7.00 PM with details of all the PVRs along with details of built up area, details of
31.07
PH
than 10 KLD, unit must file the details of trade effluent and domestic sewage separately out of this total waste discharges of 10 KLD. This information must be filed by way of affidavit.(c) The unit has D.G. Sets in 5 out of the 8 cinema halls for which stack height from roof has not been indicated. This may be provided.(d) Two D.G. Sets do not have the acoustic enclosures, which
discharge & water drawl source.(c) D.G. Sets with stack height with acoustic enclosure. 28.5.08No reply has been received from the unit. The Committee felt that in view of the large sewage discharge and the waste water discharge from numerous restaurants, MS may once again write to CMD, PVR to provide the required information for all the PVRs in Delhi. Call on 25.06.200
ground water drawl & its permission from CGWA, waste water discharge & its treatment and details of D.G. Set(s).
are mandatory to be installed. Since both air & water pollution possibility exists from the D.G. Sets and waste water generation, unit must file separate Consent to Establish applications for all the 8 cinema halls. Call on 03.09.2008 for compliance of the above.
8. 26.06.2008Call for personal hearing on 31.07.2008 at 7.00 PM with details of all the PVRs along with details of built up area, details of ground water drawl & its permission from CGWA, waste water discharge & its treatment and details of D.G. Set(s). 31.07.2008 The unit came for personal hearing today. It runs 8 cinema
halls in Delhi and the situation is as follows:
(a) In 3 cinema halls, the unit draws ground water, therefore it requires permission from CGWA.(b) In 3 cinema halls, the waste water discharge is more than 10 KLD, unit must file the details of trade effluent and domestic sewage separately out of this total waste discharges of 10 KLD. This information must be filed
by way of affidavit.(c) The unit has D.G. Sets in 5 out of the 8 cinema halls for which stack height from roof has not been indicated. This may be provided.(d) Two D.G. Sets do not have the acoustic enclosures, which are mandatory to be installed.
Since both air & water pollution possibility exists from the D.G. Sets and waste water generation, unit must file separate Consent
to Establish applications for all the 8 cinema halls. Call on 03.09.2008 for compliance of the above. 03.09.2008Reminder to comply with directions of CMC dated 31.07.2008 by 30.09.2008. Call on 30.09.2008.
37 2 9 5 SB-9
Genious Promoters And Developers Pvt. Ltd. Constructed Shop N Park Mall, CBD Ground, Near Karkardooma Court, Delhi-92
_ Applied For Consent to Establish on 12.6.08
13.08.2008Revoke the closure order and issue Consent to Establish.
Closure directions revoked and CTE issued.
No action. NA 11.03.2008Ask him to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date
Genious Promoters & Developers Pvt Ltd, (BPTP Group) M – 11, Middle Circle, Connaught Circus,
N _ _ _ In response to the closure notice, unit has filed its reply indicating that
17.07
of construction & date of completion. Approved architectural drawing may also be filed by 25.3.2008.Case to be put up on 25.03.2008. 03.04.2008The unit appears to be cleverly avoiding the arms of environmental laws. Direct him to appear before the committee on 17.04.2008 at 5.30 PM. 17.04.2008Take up on
New Delhi – 110 001
it had completed the plinth area of the plot before 7th July, 2004. The unit has filed an application for CTE and the affidavit attached with it does not indicate any ground water drawl. It sho
17.04.2008. 23.04.2008Sh. Birender Singh, General Manager (Legal), BPTP Ltd., 5th & 6th Floor, DCM Building, 16, Barakhamba Road, Connaught Place, New Delhi-110001 came for personal hearing and appears to be unaware of most of the operational and legal details of the mall which has been constructed without Consent to Establish.
ws waste water discharge of 29 KLD for which unit has proposed an STP. The unit has also indicated two D.G. Sets but the affidavit is silent on acoustic enclosure. The unit may be calle
The said mall was constructed by them and at present, the premises has been given on lease to India Bulls. Since the mall does not require Environmental Clearance as the built up area is less than 20,000 sq.mts, opportunity is being given to the unit to file Consent to Establish application immediately and the case will be heard on 01.05.2008. 01.05.200
d for personal hearing at 6.00 PM on 11.07.2008.
8The unit has not applied for Consent to Establish today and seeks time. Since the next meeting on 14.05.2008, unit may file its Consent to Establish application and the case will be discussed and decided on that day. 23.5.08Issue notice for closure as unit is running without Consent to Establish and without furnishing waste
water discharge details. Call on 18.06.2008. 18.06.2008In response to the closure notice, unit has filed its reply indicating that it had completed the plinth area of the plot before 7th July, 2004. The unit has filed an application for CTE and the affidavit attached with it does not indicate any ground water drawl. It shows waste
water discharge of 29 KLD for which unit has proposed an STP. The unit has also indicated two D.G. Sets but the affidavit is silent on acoustic enclosure. The unit may be called for personal hearing at 6.00 PM on 11.07.2008. 11.07.2008The unit came for personal hearing today against the notice of closure issued on 30.05.2008 and reconsidered on
18.06.2008 for a personal hearing. The unit claims that its superior are in Singapore / Hongkong therefore it needs another four days to consult them.
In a similar case which was represented by the same gentleman Sh. B. Singh who appeared in this case and in similar circumstances the said unit had paid a cash penalty of 1.5 % of the project
cost and Bank Guarantee of 1.5 % of the project cost and also withdrawn his case from the Hon’ble High Court. In this case, the unit has been discharging 29 KLD of waste water without any treatment facility since July, 2005 when it came into operation after getting the completion certificate. This is a serious violation of the Water Act and calls for
immediate closure of the unit u/s 33(A) the Water Act 1974.
However, since the unit claims that his owners will be back over the weekend, the Committee restrains itself from passing the order till Monday giving a chance to the unit to pay the damages of 1.5 % of project cost of Rs. 28.59 Crores as cash penalty and Bank
Guarantee of 1.5 % of the project cost of Rs. 28.59 Crores valid for three years, by Monday itself. If he fails to do so confirmation of closure order will be delivered with a copy to BSES Yamuna and DJB before closing hours of 14.07.2008 i.e. 5.00 PM positively. This order will not wait for the minutes to be issued, since today is the Friday and already
six weeks time have been given to the unit since issuance of closure notice as against the mandatory two weeks time. The status of the sequence of events may be brought administratively on file by end of 14.07.2008. Call on 17.07.2008. 13.08.2008Revoke the closure order and issue Consent to Establish. 03.09.2008
No action.
74 3 1 6 SC-1
Select City Walk (Shopping Mall) at Plot No. A-3 & P-1B, District Center, Saket, Delhi by Galleria Properties Management Services Pvt Ltd
14.02.07 29.04.05
24174.66 sq. mtr.
MCD-697000 lit/day GW-NIL DIS-300000 lit/day
350 crore
feb.2005. 28.5.08Brief CMC in the last week of July meeting of CMC. 31.07.2008Call on 03.09.2008. Meanwhile affidavit to be filed ,be put up administratively latest by 04.08.2008.
Affidavit has been filed on 28.08.2008.Next Date of Hearing is 02.09.2008.
Call on 07.10.2008
07.10
11.03.2008In this case, the unit was given Environmental Clearance on 14.02.2007 but DPCC was directed by MOEF to take legal action against the unit for starting construction before obtaining Environmental Clearance dated 14.02.2007. Unit has also filed an affidavit which does not give an item-wise compliance of all the Environm
Select City Walk,101-103 , Kanchaenjunga, 18, Barakhamba Road, New Delhi-01
YES D _ 13810 29-04-05
31.07
ental Clearance conditions.
The unit may, therefore, be asked to file an affidavit indicating item-wise compliance of all Environmental Clearance conditions in the construction and operation phase, date of start of construction and date of completion. Copy of approved architectural drawing and copy of completion certificate may also be filed, case to come up in CMC
April, 2008 when he will be given an opportunity of being heard also. 17.04.2008Call for personal hearing on 30.04.2008 at 7.30 PM. 30.04.2008The unit came for personal hearing with an advocate. Since, this is a personal hearing given to the unit, no advocates / consultants have been allowed in such hearings in CMC. Therefore
, the advocate was asked to leave and the proceedings were taken up. The unit was found to be violating the environmental laws and the letter has been issued by MoEF to Chairman, DPCC on 14.03.2007 to initiate legal action against the unit under the provisions of EPA. In the personal hearing today, the unit was apprised of this letter and was given
an opportuni
ty of hearing. The unit represented by Sh. Sanjeev Manchanda, General Manger, Finance stated that they have been trying to comply with all the environmental legislations and that the Ministry’s regional office has been inspecting their premises. The unit also represented that the violation of environmental legislations may be condoned.
In view of the clear letter of
legal action written by the MOEF in March, 2007, for which a clarification was sought by the DPCC in May, 2007, which was not replied by the MOEF so far clearly establishes that the original order of the Ministry stands.
In view of the above, legal action against the unit may be initiated. The draft prosecution order may be shown to the Chairman on 02.05.2008 before
issue. Despite repeated reminders/ cautioning and clear directions, Chairman found important matters which have a bearing on the entire functioning of DPCC have not been shown administratively on file to him. Explanation of concerned EE (CMC) be sought with in 48 hours by MS and put up. 28.5.08Brief CMC in the last week of
July meeting of CMC. 31.07.2008Call on 03.09.2008. Meanwhile affidavit to be filed ,be put up administratively latest by 04.08.2008. 03.09.2008Call on 07.10.2008
93 3 20 7 SC-20
Ambience Developer Pvt. Ltd, Plot No. 2, Vasant Kunj Mall, Vasant Kunj
27/01/2006
39787 42000 sq m
MCD-77 KLD GW-nil Discharge-152.4 kg/day
40.92 crore and paid to DDA-352.98 crore
NA 13.08.2008 The unit came for personal hearing today. It raised various issues including the fact that it does not consider itself to be a wilful defaulter, and it does not feel that it
Notice issued on 21.08.2008No reply received till date.
The unit has filed some details required vide our minutes of CMC dated 13.08.208 and sought two weeks time to file the adequacy report. Time allowed till 17.09.2008. Call for personal
17.09 PH
11.03.2008Unit has applied for Consent to Establish on 12.05.2006 and Environmental Clearance granted on 27.11.2006. Compliance condition
Ambience Developer Pvt. Ltd, Ambience Developers, A-4, Green Park, New Delhi
YES D _ 18193 39056 Call for personal hearing on 31.07.2008 at 5.30 PM.
31.07
PH
should pay any damages and that it has invested a large amount in the project and the damages should not be calculated on the basis of cost of the land and project. Perusal of the SIT report indicates several deficiencies w.r.t compliance of EIA conditions which have not been fulfilled. These may be indicated to the unit by way of notice for immediate correction. Secondly, it has not filed the six
hearing on 17.09.2008 at 6.15 PM. In the meantime, the replies to the points raised by the unit may be examined on file and brought in the unit brief.
s not given itemwise. Ask him fresh affidavit indicating date of start of construction & date of completion, item-wise compliance of Environmental Clearance conditions and approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008This case file will be shown to Chairman administratively on
monthly monitoring reports required vide Environmental Clearance conditions. It must submit the six monthly reports within this month. Thirdly, the adequacy reports that the unit has submitted are not from an empanelled consultant of DPCC, it may be directed to file these reports from an empanelled consultants of DPCC which are mentioned on the website of DPCC. Call on 03.09.200
21.04.2008. 28.5.08Ask SIT to inspect and submit a comprehensive report by 11.06.2008. Call on 11.06.2008. 25.06.2008Call for personal hearing on 31.07.2008 at 5.30 PM. 31.07.2008 The unit came for personal hearing today. Air & Noise monitoring of the D.G. Set(s) and adequacy report of STP to be submitted before 20.08.2008. Call on 12.08.200
8. 8 at 5.30 PM for personal hearing. 13.08.2008 The unit came for personal hearing today. It raised various issues including the fact that it does not consider itself to be a wilful defaulter, and it does not feel that it should pay any damages and that it has invested a large amount in the project and the damages should not be calculated on the basis of cost of the land
and project. Perusal of the SIT report indicates several deficiencies w.r.t compliance of EIA conditions which have not been fulfilled. These may be indicated to the unit by way of notice for immediate correction. Secondly, it has not filed the six monthly monitoring reports required vide Environmental Clearance conditions. It must submit the six monthly reports within this
month. Thirdly, the adequacy reports that the unit has submitted are not from an empanelled consultant of DPCC, it may be directed to file these reports from an empanelled consultants of DPCC which are mentioned on the website of DPCC. Call on 03.09.2008. 03.09.2008The unit has filed some details required vide our minutes of CMC dated 13.08.208
and sought two weeks time to file the adequacy report. Time allowed till 17.09.2008. Call for personal hearing on 17.09.2008 at 6.15 PM. In the meantime, the replies to the points raised by the unit may be examined on file and brought in the unit brief.
95 3 22 8 SC-22
Beverly Park Maintenance Service Ltd at Plot No. 3, Vasant Kunj Mall, Vasant Kunj,
22/01/2007
28960 sq m
MCD-517 KLD GW-nil DIS.-125 KLD
358 crore
31/03/2007
13.08.2008 The unit came for personal hearing today and explained that since the matter is sub-judice, the
As per decision taken in CMC on 13.08.2008, Air and noise monitoirng has been
File examining the air, water & noise monitoring report be submitted administratively.
A 11.03.2008Unit has applied for Consent to Establish on 25.09.2007 and Environm
Beverly Park Maintenance Service Ltd,DLF Centre,
9th Floor, Sansad Marg,
YES A Jan. 2008
23625 25-09-07
A 28 page reply has been received from the unit in resp
04.07
Delhi matTer should be taken up in the Court. MS, DPCC has objected to this since there is no stay in the matter and the court has directed not to take any precipitate action without giving 10 days notice / time. MS, DPCC feels that in the public interest air, water & noise monitoring report must be undertaken before any further decision is taken. Let DPCC do the air, water & noise
carried out. No water monitoring has been carried out because STP was under installation as per SS(Water).
ental granted on 24.11.2006. Environmental Clearance has been received in DPCC dated 15.01.2007. It is obvious that he started the construction before the Environmental Clearance. He has filed an affidavit indicating item-wise compliance the Environmental Clearance conditions. He may be asked an affidavit indicating date of start of construction and date of completio
New Delhi-01
onse to the notice for closure issued by DPCC. MS may draft an appropriate counter to all the points raised by the units and then submit to CMC on 04.07.2008 for taking a decision in this
monitoring in the next 15 days. Call on 03.09.2008.
n and approved architectural drawing. Case will be taken up in April, 2008 CMC for personal hearing. 17.04.2008Call for personal hearing on 14.05.2008 at 5.30 PM 14.05.2008The unit was given an opportunity for hearing today. It was not prepared to comply with the penalty and Bank Guarantee conditions totalling one percent of the total project
case.
cost. The Committee deliberated very carefully on this mater for over two hours and there was some difference of opinion. The matter was left for decision on 21.5.2008 CMC. 21.05.2008Case of Beverly Park Maintenance Service Ltd at Plot No. 3, Vasant Kunj Mall, Vasant Kunj, Delhi was brought up by MS on account of court case in
the High Court today. MS to do the following : (a) Ask SIT to inspect and report before the CMC meeting on 23.05.2008. 23.5.08In view of the several adverse deficiencies noted by the SIT in this case, a carefully drafted notice for closure incorporating all the above deficiencies should be formally shown to Chairman and issued immediately. Call
on 11.06.2008. 26.06.2008A 28 page reply has been received from the unit in response to the notice for closure issued by DPCC. MS may draft an appropriate counter to all the points raised by the units and then submit to CMC on 04.07.2008 for taking a decision in this case. 13.08.2008 The unit came for personal hearing today and explained that since the matter
is sub-judice, the matTer should be taken up in the Court. MS, DPCC has objected to this since there is no stay in the matter and the court has directed not to take any precipitate action without giving 10 days notice / time. MS, DPCC feels that in the public interest air, water & noise monitoring report must be undertaken before any further decision is taken. Let
DPCC do the air, water & noise monitoring in the next 15 days. Call on 03.09.2008. 03.09.2008File examining the air, water & noise monitoring report be submitted administratively.
96 3 23 9 SC-23
Regency Park Management Services Private Ltd. at Plot No. 4, Vasant Kunj Mall, Vasant Kunj, Delhi
24/11/2006
25/9/2007
59731.663 sq m
MCD-287 KLD GW-nil DIS-76 KLD
250 CRORE
15/7/2008 13.08.2008The unit came for personal hearing today and explained that since the matter is sub-judice, the mater should be taken up in the Court. MS, DPCC has
File is under submission.
File is under submission to Higher Authorities.
A 11.03.2008Unit has applied for Consent to Establish on 25.09.2007 and Environmental granted on 24.11.2006. Environmental Clearance
Regency Park Management Services Private Ltd,DLF Centre, 9th Floor, Sansad Marg, New Delhi-01
YES A Jan. 2008
23627 25-09-07
A 28 page reply has been received from the unit in response to the notice for closure issue
12.08
objected to this and since there is no stay in the matter. MS, DPCC feels that in the interest of comprehensive order, air, water & noise monitoring report must be undertaken before any further decision is taken. Let DPCC do the air, water & noise monitoring in the next 15 days. Call on 03.09.2008. 28.08.2008Call on 03.09.2008
has been received in DPCC dated 15.01.2007. It is obvious that he started the construction before the Environmental Clearance. He has filed an affidavit indicating item-wise compliance the Environmental Clearance conditions. He may be asked an affidavit indicating date of start of construction and date of completion and approved architectural drawing. Case will be taken up in
d by DPCC. MS may draft an appropriate counter to all the points raised by the units and then submit to CMC on 04.07.2008 for taking a decision in this case.
April, 2008 CMC for personal hearing. 17.04.2008Call for personal hearing on 14.05.2008 at 6.00 PM 14.05.2008The unit was given an opportunity for hearing today. It was not prepared to comply with the penalty and Bank Guarantee conditions totalling one percent of the total project cost. The Committee deliberated very carefully on this mater for
over two hours and there was some difference of opinion. The matter was left for decision on 21.5.2008 CMC. 21.05.2008Case of Regency Park Management Services Private Ltd. at Plot No. 4, Vasant Kunj Mall, Vasant Kunj, Delhi was brought up by MS on account of court case in the High Court today. MS to do the following :
(a) Get a copy of court order through inspection of file by 22.5.2008.(b) Ask SIT to inspect and report before the CMC meeting on 23.05.2008. 23.5.08In view of the several adverse deficiencies noted by the SIT in this case, a carefully drafted notice for closure incorporating all the above deficiencies should be formally shown to Chairman and issued
immediately. Call on 11.06.2008. 26.06.2008A 28 page reply has been received from the unit in response to the notice for closure issued by DPCC. MS may draft an appropriate counter to all the points raised by the units and then submit to CMC on 04.07.2008 for taking a decision in this case. 24.07.2008The unit came for personal hearing today. Since
DPCC is required to file its counter affidavit in the Hon’ble High Court in this case, it is in the process of doing so. Call on 12.08.2008. 13.08.2008The unit came for personal hearing today and explained that since the matter is sub-judice, the mater should be taken up in the Court. MS, DPCC has objected to this and since there is no stay in the matter. MS, DPCC
feels that in the interest of comprehensive order, air, water & noise monitoring report must be undertaken before any further decision is taken. Let DPCC do the air, water & noise monitoring in the next 15 days. Call on 03.09.2008. 28.08.2008Call on 03.09.2008 03.09.2008File is under submission to Higher Authorities.
102 3 29 10 SC- TSL Name not Not Letter Call for 30.0 TSL NO N _ _ _ Ask 31.0
29 Mall /Shopping Mall, Sec-04 Dwarka, New Delhi
included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
applied for consent to Establish
26.06.2008Ask the unit to file permission from CGWA for ground water draw & details of waste water discharge and its treatment. Also ask the unit to apply for Consent to Establish. Call on 31.07.2008. 31.07.2008Issue final reminder to comply with the decision of CMC meeting dated 26.06.2008. Call on 03.09.2008.
issued on 04.07.2008.Reply received on 22.08.2008 stating that they donnot come under the purview of section 21 & 22 of Air & Water Acts.
personal hearing on 30.09.2008 at 5.30 PM.
9 PH 11.03.2008Unit may be asked to apply for Consent to Establish and MS to inspect and report in April, 2008 CMC. 17.04.2008Ask the unit to apply for Consent to Establish by 21.05.2008. Take up on 21.05.2008. 28.5.08 As per the inspection report of MS, the built up area is 650 sqm with one bore-well but without any document
Mall /Shopping Mall,Trade Stone Ltd., A- 260, Okhla,
New Delhi.
the unit to file permission from CGWA for ground water draw & details of waste water discharge and its treatment. Also ask the unit to apply for Consent to Establish. Call on
7
ary permission from the CGWA. Details w.r.t. waste water discharge & D.G. Set are not available. Issue notice to the unit to provide the same and to file Consent to Establish. Call on 25.06.2008. 26.06.2008Ask the unit to file permission from CGWA for ground water draw & details of waste water discharge and its treatment. Also ask
31.07.2008.
the unit to apply for Consent to Establish. Call on 31.07.2008. 31.07.2008Issue final reminder to comply with the decision of CMC meeting dated 26.06.2008. Call on 03.09.2008. 03.09.2008Call for personal hearing on 30.09.2008 at 5.30 PM.
103 3 30 11 SC-30
TSL Mall /Shopping Mall, Sec-06 Dwarka, New Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
Not applied for consent to Establish
734.4 sq m /As per inspection report
9.0 CRORE
26.06.2008Ask the unit to file permission from CGWA for ground water draw & details of
Letter issued on 04.07.2008.Reply received on 22.08.2008 stating that
Call for personal hearing on 30.09.2008 at 5.45 PM. 30.0
9 PH
11.03.2008Unit may be asked to apply for Consent to Establish and MS to inspect
TSL Mall /Shopping Mall,Trade Stone Ltd., A- 260, Okhla,
NO N _ _ _ Ask the unit to file permission from CGWA for
31.07
waste water discharge and its treatment. Also ask the unit to apply for Consent to Establish. Call on 31.07.2008. 31.07.2008Issue final reminder to comply with the decision of CMC meeting dated 26.06.2008. Call on 03.09.2008.
they donnot come under the purview of section 21 & 22 of Air & Water Acts.
and report in April, 2008 CMC. 17.04.2008Ask the unit to apply for Consent to Establish by 21.05.2008. Take up on 21.05.2008. 28.5.08As per the inspection report of MS, the built up area is around 600 sqm and digging one bore-well but without any documentary permission from the CGWA. Details w.r.t. waste water discharge
New Delhi.
ground water draw & details of waste water discharge and its treatment. Also ask the unit to apply for Consent to Establish. Call on 31.07.2008.
& D.G. Set are not available. Issue notice to the unit to provide the same and to file Consent to Establish. Call on 25.06.2008. 26.06.2008Ask the unit to file permission from CGWA for ground water draw & details of waste water discharge and its treatment. Also ask the unit to apply for Consent to Establish. Call on 31.07.2008. 31.07.200
8Issue final reminder to comply with the decision of CMC meeting dated 26.06.2008. Call on 03.09.2008. 03.09.2008Call for personal hearing on 30.09.2008 at 5.45 PM.
115 3 42 12 SC-42
Amazon Enterprises, Plot No 1, Community Centre, Alaknanda, New Delhi
Pending with MOEF
Not applied
26.06.2008Call for personal hearing on 31.07.2008 at 6.00 PM. 31.07.2008 The unit came for personal hearing today. The unit has made an application to
Letter issued on 07.08.2008.Reply received on 19.08.2008
Call on 07.10.2008 for Environmental Clearance.
07.10
Letter for EC & CTE has been issued. 28.5.08SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 26.06.2008Call for personal hearing on
Amazon Enterprises, Plot No 1, Community Centre, Alaknanda, New Delhi
Call for personal hearing on 31.07.2008 at 6.00 PM.
31.07
PH
MOEF for Environmental Clearance. It has not made Consent to Establish application so far and the unit is advised to do so with immediate effect. Call on CMC on 03 September, 2008.
31.07.2008 at 6.00 PM. 31.07.2008 The unit came for personal hearing today. The unit has made an application to MOEF for Environmental Clearance. It has not made Consent to Establish application so far and the unit is advised to do so with immediate effect. Call on CMC on 03 September, 2008. 03.09.2008Call on 07.10.2008 for
Environmental Clearance.
116 3 43 13 SC-43
Construcion of Commercial Complex cum-multi level parking at plot no 13, Jasola, New Delhi
Pending with MOEF
Not applied
Letter for EC & CTE has been issued. 28.5.08SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 26.06.2008Call for personal hearing on 31.07.2008 at 6.30 PM. 31.07.2008The unit came for personal hearing today. The unit has made an application to MOEF for Environmental Clearance. It has not
Letter issued on 07.08.2008.Reply received on 19.08.2008
Call on 07.10.2008 for Environmental Clearance.
07.10
Letter for EC & CTE has been issued. 28.5.08SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 26.06.2008Call for personal hearing on 31.07.2008 at 6.30 PM. 31.07.2008The unit came for personal hearing today. The unit has made an application to MOEF for Environmental
Amazon Enterprises, Plot No 1, Community Centre, Alaknanda, New Delhi
Call for personal hearing on 31.07.2008 at 6.30 PM.
31.07
PH
made Consent to Establish application so far and the unit is advised to do so with immediate effect. Call on CMC on 03 September, 2008.
Clearance. It has not made Consent to Establish application so far and the unit is advised to do so with immediate effect. Call on CMC on 03 September, 2008. 03.09.2008Call on 07.10.2008 for Environmental Clearance.
18 1 18 14 SA-18
RG City Centre, Plot no 4, Motia Khan, Paharganj, New Delhi
Not submitted
Not submit
ted
3990 sqm
MCD : 10 KLD (in reply) /
GW : 20 KLD (as
per inspection report) / WW - 16
KLD without STP (as
per inspection
report)
Not reporte
d
29.05.2007
17.04.2008Issue notice to the unit to file Consent to Establish and Environmental Clearance along with an
As decided, a letter issued on 01.07.2008.The same is received back undelievered and reissue
17.09
17.04.2008Issue notice to the unit to file Consent to Establish and Environmental Clearance along with an
RG City Centre,Rajesh projects, RG Complex, DDA Communtiy Centre,Sec-14, Rohini,
_ _ _ (i) Ground water is 20 KLD without permission from CGWA
17.07
affidavit indicating date of start of construction & date of completion of construction and to submit approved architectural drawing and completion certificate. Call on 14.05.2008. 21.05.2008SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 18.06.2008(i) Ground water is 20 KLD without permission from CGWA for ground water
d on 09.07.2008.Unit has submitted reply on 18.07.2008
affidavit indicating date of start of construction & date of completion of construction and to submit approved architectural drawing and completion certificate. Call on 14.05.2008. 21.05.2008SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 18.06.2008(i) Ground water is 20 KLD without permission from CGWA for
Delhi for ground water drawl. (ii) Waste water generation is 16 KLD. No indication of its treatment.(iii) D.G. Sets of 125 KVA & 320 KVA with acoustic enclosure and adequate stac
drawl. (ii) Waste water generation is 16 KLD. No indication of its treatment.(iii) D.G. Sets of 125 KVA & 320 KVA with acoustic enclosure and adequate stack height.Ask the unit to file an application for Consent to Establish alonga with permission from CGWA for ground water drawl and above information. Call on 18.07.2008. 13.08.2008Issue fresh
ground water drawl. (ii) Waste water generation is 16 KLD. No indication of its treatment.(iii) D.G. Sets of 125 KVA & 320 KVA with acoustic enclosure and adequate stack height.
Ask the unit to file an application for Consent to Establish alonga with permission from CGWA for ground water drawl and above information. Call on 18.07.200
k height.
Ask the unit to file an application for Consent to Establish alonga with permission from CGWA for ground water drawl and above information. Call on 18.07.2008.
notice seeking information sought earlier.
8. 13.08.2008Issue fresh notice seeking information sought earlier.
46 2 18 15 SB-18
Galleria Property Management Services Pvt. Ltd at DT City Center, Block A, Communtiy Center, Shalimar Bagh, Delhi
15.01.2007
Applied
21.08.2008In reply to our show cause notice for closure, the unit has filed a detailed reply which must be examined on file and a final letter with a final decision on the matter be issued to the unit by 28.08.2008. This letter must be shown administratively to the Chairman, DPCC on 25.08.200
Notice for closure issued. Reply received.File submitted administratively for necessary decision and it was decided to place the same in today Committee meeting.
The unit has filed a detailed reply to the SCN dated 30.5.08 and sought a personal hearing. Rejoinder to the SCN is ready and should be issued immediately without waiting for the minutes. Call for personal hearing on 03.09.2008 at 8.15 PM for final order.
17.09 PH
11.03.2008The unit has applied for Consent to Establish and has also filed Environmental Clearance dated 15.01.2007. However, the construction of the said mall must have started before Environmental Clearance was given. He may therefore be asked to file an
Galleria Property Management Services Pvt. Ltd ,DLF Centre, 9th Floor, Sansad Marg, New Delhi-01
A 39448
23628 25-09-07
Proper well drafted reply has to be filed in the High Court which may be drafted and shown to Chairman by 30.06.2008.
Call on 24.07.2008 for compliance.
Reply to be filed in the court. Call on 06.08.2008.
06.08
8. Call on 28.08.2008. 28.08.2008The unit has filed a detailed reply to the SCN dated 30.5.08 and sought a personal hearing. Rejoinder to the SCN is ready and should be issued immediately without waiting for the minutes. Call for personal hearing on 03.09.2008 at 8.15 PM for final order.
affidavit indicating the date of start of construction of mall and copy of architectural drawing along with date of approval of architectural drawing and he will be given personal hearing in April, 2008 CMC to decide the case. 11.04.2008Call for personal hearing on 30.04.2008 at 5.30 PM. 30.04.2008The unit was asked to file an affidavit
indicating the date of start of construction which has not been done. Issue a final reminder for the same, failing which CMC will pass appropriate orders. The unit was given personal hearing time today but it failed to turn up. CMC is under no obligation to give the unit any further opportunity for personal hearing. 28.5.08Since the unit has not furnished the required
details asked by DPCC, SIT to inspect on 29.05.2008 and submit report to MS by evening for necessary action to be decided in CMC on 29.05.2008. 29.5.08The SIT report indicates several deficiencies, the most glaring of which is that the unit is drawing ground water through two bore-wells without any permission from CGWA. It has also not
complied with several conditions of Environmental Clearance. Issue notice for closure which should be served to the unit as the office opens tomorrow. 18.06.2008Proper well drafted reply has to be filed in the High Court which may be drafted and shown to Chairman by 30.06.2008. 11.07.2008Call on 24.07.2008 for complian
ce. 24.07.2008Reply to be filed in the court. Call on 06.08.2008. 13.08.2008Call for personal hearing on 20.08.2008 at 05.45 PM. 21.08.2008In reply to our show cause notice for closure, the unit has filed a detailed reply which must be examined on file and a final letter with a final decision on the matter be issued to the unit
by 28.08.2008. This letter must be shown administratively to the Chairman, DPCC on 25.08.2008. Call on 28.08.2008. 28.08.2008The unit has filed a detailed reply to the SCN dated 30.5.08 and sought a personal hearing. Rejoinder to the SCN is ready and should be issued immediately without waiting for the minutes. Call for personal hearing on
03.09.2008 at 8.15 PM for final order. 03.09.2008The unit has filed the reply seeking time within office hours. Call for personal hearing on 17.09.2008 at 5.00 PM.
81 3 8 16 SC-8
Aditya Infracon (P) Ltd , at Plot no 8 Jasola District New Delhi
Area < 20,000 sq. m
19906.801sq.m
MCD-212 KLD GW-Nil Dis-80 KLD
59.78 Crore
28.08.2008 The unit came for personal hearing today. The total project cost is Rs. 77.90 crores and the total effluent discharge is 80 KLD. STP / ETP is yet to be installed and the
Letter issued on 24.07.2008.No reply received till date. SIT report to be discused.
17.09 PH
11.03.2008Unit has applied for Consent to Establish on 07.05.2007 where he has reported the built up area more than 20,000 sqm whereas MOEF has allowed
Aditya Infracon (P) Ltd,64, Ground Floor, Poorvi Marg ,Vasant Vihar, New Delhi
P A Aug. 2007
21238 39268 CTE filed by the unit indicates built up area of 20356 sqm. However, MOEF understood this area to be 19906 sqm and therefore inform
Call on 25.06.2008 with architect's report.
31.07
SIT report has found certain other deficiencies which have been communicated to the unit. Unit is operating without Consent to Establish and Consent to Operate since January, 2008. The unit was informed that in similar cases, for violation of the provisions of Air and Water Acts, the Committee has levied the damages of 1 % of the project cost which comes out to Rs. 78 Lakhs and 2 % of
to unit not to file Environmental Clearance. This action is not comprehensible and contradictory to documents on file. Therefore, unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit
ed the unit that he does not require Environmental Clearance. However, inspection by IIT Surveyors on 18.06.2008 indicates that the total built up area is 20044.28 sqm nearly as indicated in the CTE. MS to put up a letter through Chairman to Addl. Secretary, MOEF indicating the
the project cost i.e. Rs. 1.56 crores as the Bank Guarantee valid for three years. The unit seeks time for few days. Call for personal hearing on 03.09.2008 at 5.15 PM. Since the IIT Survey indicates the built up area of more than 20,000 sqm, unit must apply for EC before the SEIAA which is being set up early next month.
to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Since lack of clarity of the built up area, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect
sequence of the event whereby the unit has tried to mislead MOEF and gain leniency on requirement of Environmental Clearance. This must be done without waiting from the minutes by 27.06.2008. the unit may also be called for personal hearing on 04.07.2008 at 6.30 PM.
who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-(a) Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report.
25.06.2008CTE filed by the unit indicates built up area of 20356 sqm. However, MOEF understood this area to be 19906 sqm and therefore informed the unit that he does not require Environmental Clearance. However, inspection by IIT Surveyors on 18.06.2008 indicates that the total built up area is 20044.28 sqm nearly as indicated in the CTE. MS to put up
a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead MOEF and gain leniency on requirement of Environmental Clearance. This must be done without waiting from the minutes by 27.06.2008. the unit may also be called for personal hearing on 04.07.2008 at 6.30 PM. 04.07.200
8 The unit came for personal hearing and claims that General Manager (Project) is not available, therefore, seeks postponement of the personal hearing. Time allowed. Call for personal hearing on 18.07.2008 at 7.45 PM. 17.07.2008The unit came for personal hearing today. It still believes that the total built up area is less than 20,000 sqm, therefore,
a copy of our letter written to Addl. Secretary, MOEF may be given to the unit immediately for filing the application for Environmental Clearance to MOEF. The IIT survey report indicates that the total built up is 20356 sqm. The unit used ground water during construction without CGWA clearance. If the unit is drawing any ground water from any source, it
must provide the permission from CGWA immediately. Unit has waste water generation of 212 KLD and no STP provided so far. The unit claims one of the floors is already operational. It is a great environmental damage if waste water of this magnitude is released in the drain without treating it in nasty manner. The unit must close down all its operation till the
STP is installed and run it as per the norms. Let the unit file a compliance report by 31.07.2008.
The unit must also indicate having applied for Environmental Clearance to MOEF by 31.07.2008. Informed to the unit accordingly. Call on 31.07.2008. 31.07.2008SIT to inspect and report w.r.t. directions issued vide CMC meeting dated
17.07.2008. Call on 20.08.2008. 21.08.2008Call for personal hearing on 28.08.2008 at 6.30 PM. Meanwhile the deficiencies noted by the SIT may be communicated to the unit. Letter to be issued without waiting for minutes. 28.08.2008 The unit came for personal hearing today. The total project cost is Rs. 77.90 crores and the total effluent
discharge is 80 KLD. STP / ETP is yet to be installed and the SIT report has found certain other deficiencies which have been communicated to the unit. Unit is operating without Consent to Establish and Consent to Operate since January, 2008.
The unit was informed that in similar cases, for violation of the provisions of Air and Water Acts, the
Committee has levied the damages of 1 % of the project cost which comes out to Rs. 78 Lakhs and 2 % of the project cost i.e. Rs. 1.56 crores as the Bank Guarantee valid for three years. The unit seeks time for few days. Call for personal hearing on 03.09.2008 at 5.15 PM. Since the IIT Survey indicates the built up area of more than 20,000 sqm, unit must apply for EC before
the SEIAA which is being set up early next month. 03.09.2008The unit came for personal hearing but wants its Chief Engineer to be present since he is familiar with the case. The Chief Engineer is reportedly sick as per their letter and 15 days time has been sought. Call for personal hearing on 17.09.2008 at 5.30 PM.
91 3 18 17 SC-18
ABW Infrastructure Ltd 208-210, Rectangl
Area < 20,000 sq. m
39484 19815.567 sq m
MCD- 27.85 LPD GW- NIL DIS- 69.62
78.35 crore
proposed 28.08.2008The unit came for
Letter issued.No reply receive
17.09 PH
11.03.2008Issue final
ABW Infrastructure Ltd., 208-
NO N _ _ _ SIT inspect and report and IIT
31.07
SIT
e -I , D-4, Saket Dist Centre, New Delhi
KLD personal hearing today. The total project cost is Rs. 78.35 crores and the total effluent discharge is 69.6 KLD. STP / ETP is yet to be installed and the SIT report has found certain other deficiencies which have been communicated to the unit. Unit is operating without Consent to Establish and Consent to Operate since August, 2007. Trade effluent is being discharged without treatment
d.Inspection reports of SIT to be discussed.
letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.
210, Rectangle -I, D-4 Saket Distt Centre , New Delhi
Surveyors inspect and report. Call on 31.07.2008.
into the sewer. The unit was informed that in similar cases, for violation of the provisions of Air and Water Acts, the Committee has levied the damages of 1 % of the project cost which comes out to Rs. 78 Lakhs and 2 % of the project cost i.e. Rs. 1.56 crores as the Bank Guarantee valid for three years. The unit seeks time for few days. Call for personal hearing on 03.09.2008 at 5.45 PM. Since the IIT
Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 6.00 PM. 11.6.2008The unit came for personal hearing today. It is not clear, how many eateries exist and consequent quantity
Survey indicates the built up area of more than 20,000 sqm, unit must apply for EC before the SEIAA which is being set up early next month.
waste water generation will take place. It is also not clear about the total quantity of ground water drawl and the alternate sources of water for the mall. The CTE application indicates total waste water generation of 69 KLD which does not appear to be requirement only for offices. The unit confirms that it will get the required information and submit before
25.06.2008. The date of construction of the unit will also be confirmed before 25.06.2008. Call on 25.06.2008. 25.06.2008SIT inspect and report and IIT Surveyors inspect and report. Call on 31.07.2008. 31.07.2008SIT to inspect & report. Call on 20.08.2008. 21.08.2008SIT deficiencies may be communicated the unit. IIT Surveyor
to be deputed this week and report be submitted on 28.08.2008. Call for personal hearing on 28.08.2008 at 7.00 PM. 28.08.2008The unit came for personal hearing today. The total project cost is Rs. 78.35 crores and the total effluent discharge is 69.6 KLD. STP / ETP is yet to be installed and the SIT report has found certain other deficiencies which
have been communicated to the unit. Unit is operating without Consent to Establish and Consent to Operate since August, 2007. Trade effluent is being discharged without treatment into the sewer.
The unit was informed that in similar cases, for violation of the provisions of Air and Water Acts, the Committee has levied the damages of 1 % of the project
cost which comes out to Rs. 78 Lakhs and 2 % of the project cost i.e. Rs. 1.56 crores as the Bank Guarantee valid for three years. The unit seeks time for few days. Call for personal hearing on 03.09.2008 at 5.45 PM. Since the IIT Survey indicates the built up area of more than 20,000 sqm, unit must apply for EC before the SEIAA which is being set up early next month.
03.09.2008The unit came personal hearing but wants its Chief Engineer to be present since he is familiar with the case. The Chief Engineer is reportedly sick as per their letter and 15 days time has been sought. Call for personal hearing on 17.09.2008 at 5.45 PM.
3 1 3 18 SA-3
R.C.Sood & Co. Pvt.Ltd.Proposed Shopping Mall at 10, Shivaji Palace, District centre, Raja
26-03-08 11/09/06 27-02-07
11.6.2008SIT inspection report indicates that the unit has not complied with Environm
Submit this file administratively after examining all the requirements for Consen
17.09 PH
10.03.2008Ask the unit to file an affidavit indicating the date of construction & date
R.C.Sood & Co. Pvt.Ltd,S-1, American Plaza, International
P A Mid 2008
19289 20729
11/09/06 27-02-07
SIT inspection report indicates that the unit has
Issue fresh reminder. Call on 24.07.2008.
Call on 20.08.2008.
20.08
Garden, Delhi,
ental Clearance conditions and these deficiencies may be listed in the letter to the unit for compliance. Ask the unit to file permission from CGWA for ground water drawl. Call on 11.07.2008 11.07.2008Issue fresh reminder. Call on 24.07.2008. 24.07.2008Call on 20.08.2008. 21.08.2008The unit has filed item-wise compliance of EC conditions
t to Establish.
of completion, architectural drawing and completion certificate if received. 17.04.2008Issue reminder to the unit to file compliance affidavit of all Environmental Clearance conditions. Call on 14.05.2008, 21.05.2008SIT to inspect and submit a report by 03.06.2008. Call on 03.06.2008. 11.6.2008SIT inspection
Trade Tower,
Nehru Place, New Delhi-19
not complied with Environmental Clearance conditions and these deficiencies may be listed in the letter to the unit for compliance. Ask the unit to file permission from CGWA for grou
but has not filed the affidavit for correction of deficiencies noted by SIT. The unit may be asked to do so and called for personal hearing on 03.09.2008 at 7:00 PM.
report indicates that the unit has not complied with Environmental Clearance conditions and these deficiencies may be listed in the letter to the unit for compliance. Ask the unit to file permission from CGWA for ground water drawl. Call on 11.07.2008 11.07.2008Issue fresh reminder. Call on 24.07.2008. 24.07.2008Call on
nd water drawl. Call on 11.07.2008
20.08.2008. 21.08.2008The unit has filed item-wise compliance of EC conditions but has not filed the affidavit for correction of deficiencies noted by SIT. The unit may be asked to do so and called for personal hearing on 03.09.2008 at 7:00 PM. 03.09.2008The unit did not come for personal hearing but sent a letter saying that he has received a
notice of hearing on 02.09.2008. The concerned staff who handles the case, has prior engagements and therefore adjournment is sought. Call for personal hearing on 17.09.2008 at 5.15 PM without waiting for minutes.
10 1 10 19 SA-10
Shoppers' Stop, Plot no 10, Shivaji Place, Rajouri Garden, Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
Not submit
ted
26454Sqm
Issue letter to the unit to file environmental clearance & Consent to Establish. Also he may be asked to confirm why there are two applications from
As per CMC decision dated 31.07.2008, Chairman has given opportunity of personal hearing to the project proponent before
17.09 PH
Issue letter to the unit to file environmental clearance & Consent to Establish. Also he may be asked to confirm why there are two applications from
Shoppers' Stop,Eros Group,S-1, American Plaza, International Trade Tower,Nehru Place, New Delhi-19
NO N _ _ _ The unit has filed a detailed reply in response to the DPCC notice for closure
7.15
31.07
PH
two different firms for the same plot / site / complex. Case to be put up on 25.03.2008.Affidavit for date of construction and completion, architectural drawing & completion certificate may be filed by 25.3.08. 03.4.08Take up on 10.04.2008. 17.04.2008 CMC to inspect and report whether Shoppers' Stop qualifies as a separate unit for Environm
CMC on 20.08.2008.
two different firms for the same plot / site / complex. Case to be put up on 25.03.2008.Affidavit for date of construction and completion, architectural drawing & completion certificate may be filed by 25.3.08. 03.4.08Take up on 10.04.2008. 17.04.2008 CMC to inspect and report whether Shoppers' Stop qualifies as a separate
dated 28.05.2008. The following deficiencies are found in the reply:(i) The unit admits completion of mall without CTE.(ii) The unit has filed EC but not given an affidavit for item-
ental Clearance. Call on 14.05.2008. 21.05.2008Since the unit has not applied for Consent to Establish nor furnished Environmental Clearance, notice for closure may be issued immediately. Call on 11.06.2008 for updating CMC with unit's response to closure notice. 18.06.2008The unit has filed a detailed reply in response to the DPCC notice for
unit for Environmental Clearance. Call on 14.05.2008. 21.05.2008Since the unit has not applied for Consent to Establish nor furnished Environmental Clearance, notice for closure may be issued immediately. Call on 11.06.2008 for updating CMC with unit's response to closure notice. 18.06.2008The unit has filed a detailed
wise compliance which he must be asked to do immediately.(iii) The unit has not filed noise monitoring report of the two D.G. Sets.
(iv) The unit claims STP has been installed but unit has not
closure dated 28.05.2008. The following deficiencies are found in the reply:(i) The unit admits completion of mall without CTE.(ii) The unit has filed EC but not given an affidavit for item-wise compliance which he must be asked to do immediately.(iii) The unit has not filed noise monitoring report of the two D.G. Sets.
(iv) The unit claims STP has been installed
reply in response to the DPCC notice for closure dated 28.05.2008. The following deficiencies are found in the reply:(i) The unit admits completion of mall without CTE.(ii) The unit has filed EC but not given an affidavit for item-wise compliance which he must be asked to do immediately.(iii) The unit has not filed noise monitoring report of the two D.G. Sets.
(iv) The
filed the adequacy report. (v) The unit has drawn the ground water but unit has not filed the permission from CGWA for ground water drawl.(vi) The unit does not have adequate stack height
but unit has not filed the adequacy report. (v) The unit has drawn the ground water but unit has not filed the permission from CGWA for ground water drawl.(vi) The unit does not have adequate stack height for channelization arrangement.
In view of the above deficiencies, unit may be called for personal hearing on 7.30 PM on 11.07.2008. 11.07.2008 Issue
unit claims STP has been installed but unit has not filed the adequacy report. (v) The unit has drawn the ground water but unit has not filed the permission from CGWA for ground water drawl.(vi) The unit does not have adequate stack height for channelization arrangement.
In view of the above deficiencies, unit may be called for personal hearing on 7.30 PM on
for channelization arrangement.
In view of the above deficiencies, unit may be called for personal hearing on 7.30 PM on 11.07.2008.
final reminder for personal hearing on 24.07.2008. Call on 24.07.2008. 24.07.2008The unit came for personal hearing today. It has started its operation for a year now without getting Consent to Establish or even applying for Environmental Clearance. Apart from this, the unit has to file its noise monitoring report, confirmation of STP installation, CGWA clearance and
11.07.2008. 11.07.2008 Issue final reminder for personal hearing on 24.07.2008. Call on 24.07.2008. 24.07.2008The unit came for personal hearing today. It has started its operation for a year now without getting Consent to Establish or even applying for Environmental Clearance. Apart from this, the unit has to file its noise monitorin
adequate stack height for its channelization arrangement. The total project cost for the unit, since it is on lease, can be calculated for the purpose of damages, in terms of Rs. 19.6 Crores which it has incurred by way of furniture & fittings and Rs. 15 Crores which is the annual lease rent being paid to the developers. The project cost therefore comes about 34.6 cores. This is the case
g report, confirmation of STP installation, CGWA clearance and adequate stack height for its channelization arrangement. The total project cost for the unit, since it is on lease, can be calculated for the purpose of damages, in terms of Rs. 19.6 Crores which it has incurred by way of furniture & fittings and Rs. 15 Crores which is the annual lease rent being paid to
where environmental laws have been blatantly violated and in such cases, the Committee has levied damages in terms of cash penalty of 1.5 % of project cost and Bank Guarantee of 1.5 % of the project cost valid for three years, which comes to approx. Rs. 50 Lakhs each.
The unit seeks time to consult and get approval from its superiors. Time is allowed till 31.07.2008 on the
the developers. The project cost therefore comes about 34.6 cores. This is the case where environmental laws have been blatantly violated and in such cases, the Committee has levied damages in terms of cash penalty of 1.5 % of project cost and Bank Guarantee of 1.5 % of the project cost valid for three years, which comes to approx. Rs. 50 Lakhs each.
condition that the unit files Environmental Clearance application since it has gone into operation without even applying for Environmental Clearance which is a serious matter. Call on 31.07.2008 at 7.15 PM for personal hearing. 31.07.2008 The unit has asked for personal hearing before the Chairman, DPCC vide its letter dated 30.07.2008. Let him seek an appointment through
The unit seeks time to consult and get approval from its superiors. Time is allowed till 31.07.2008 on the condition that the unit files Environmental Clearance application since it has gone into operation without even applying for Environmental Clearance which is a serious matter. Call on 31.07.2008 at 7.15 PM for personal hearing. 31.07.2008 The unit has asked for
PS to Chairman. Time allowed for one week. Call on 06.08.2008. 21.08.2008The unit has sought time for adjournment for 15 days to furnish certain documents / information through it’s representation dated 20.08.08. Last and final opportunity to be given for personal hearing on 03.09.2008, at 5.00 PM.
personal hearing before the Chairman, DPCC vide its letter dated 30.07.2008. Let him seek an appointment through PS to Chairman. Time allowed for one week. Call on 06.08.2008. 21.08.2008The unit has sought time for adjournment for 15 days to furnish certain documents / information through it’s representation dated 20.08.08. Last and
final opportunity to be given for personal hearing on 03.09.2008, at 5.00 PM. 03.09.2008The unit did not come for personal hearing but sent an application saying that their some leased area is part of the area mentioned in Environmental Clearance of R.C. Sood & Co. Pvt. Ltd.. They have also said that the application for Environmental Clearance
of R.C. Sood & Co. Pvt. Ltd. mentions waste water generation of 72 KLD and states that the STP for this waste water treatment have the capacity of 80 KLD. Since the unit is putting the onus of liability on the sub lesser i.e. R.C. Sood & Co. Pvt. Ltd., real fact can be ascertained only when both the parties are called for personal hearing together. Issue notice to
both the parties for personal hearing on 17.09.2008 at 5.15 PM without waiting for minutes.
104 3 31 20 SC-31
Pankaj Group, Sec-12 Dwarka, New Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
Not applied for consent to Establish
531 sq m
aprox.40 lac /as per inspection report
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of constructi
30.09
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of
on and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008CMC to inspect and report by 21.05.2008. Take up on 21.05.2008. 28.5.08This unit has 3 plots of 135 sqm each of which has a built up area of 531 sqm this makes a total built up
start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008CMC to inspect and report by 21.05.2008. Take up on 21.05.2008. 28.5.08This unit has 3 plots of 135 sqm each of which has a built up area of 531 sqm
area of 1593. As per the inspection report of CMC officials, the built up area is 531 sqm with one bore-well but without any documentary permission from the CGWA,7.5 KVA D.G. Set without acoustic enclosure found. Details w.r.t. waste water discharge is not available. Issue notice to the unit to provide the same and file Consent to Establish. Call on 25.06.2008.CMC has
this makes a total built up area of 1593. As per the inspection report of CMC officials, the built up area is 531 sqm with one bore-well but without any documentary permission from the CGWA,7.5 KVA D.G. Set without acoustic enclosure found. Details w.r.t. waste water discharge is not available. Issue notice to the unit to provide the same and file Consent to Establish.
also reported that there are 04 plots of the same size in the adjoining area which implies the built up area of nearly 2000 sqm. No information on water source, water discharge and D.G. Sets are available. Issue notice by hand to Manish Group at the site to file the above details and application for Consent to Establish. Call on 25.06.2008. 26.06.2008Ask the
Call on 25.06.2008.CMC has also reported that there are 04 plots of the same size in the adjoining area which implies the built up area of nearly 2000 sqm. No information on water source, water discharge and D.G. Sets are available. Issue notice by hand to Manish Group at the site to file the above details and application for Consent to Establish. Call on 25.06.200
unit to file permission from CGWA for ground water draw & details of waste water discharge and its treatment. Details Ask the unit to confirm by when the acoustic enclosure & adequate stack with D.G. Set will be provided. Also ask the unit to apply for Consent to Establish. Letter may be issued to both the units namely Pankaj Buildwell & Manish Buildwell. Call on 31.07.2008.
8. 26.06.2008Ask the unit to file permission from CGWA for ground water draw & details of waste water discharge and its treatment. Details Ask the unit to confirm by when the acoustic enclosure & adequate stack with D.G. Set will be provided. Also ask the unit to apply for Consent to Establish. Letter may be issued to both the units namely
31.07.2008Call both the unit for personal hearing 20.08.2008 at 7.30 PM & 7.45 PM. 21.08.2008The unit seeks time for two weeks. Call for personal hearing on 03.09.2008, at 5.30 PM.
Pankaj Buildwell & Manish Buildwell. Call on 31.07.2008. 31.07.2008Call both the unit for personal hearing 20.08.2008 at 7.30 PM & 7.45 PM. 21.08.2008The unit seeks time for two weeks. Call for personal hearing on 03.09.2008, at 5.30 PM. 03.09.2008The unit came for personal hearing today. Unit claims that there are three
small plots of 135 sqm each for which built up area as per the inspection report is 1593 sqm. According to the unit, there is no effluent discharged and there are no food courts proposed and it is only office complex. The unit also claims that it has no D.G. Sets and no bore well. Let the unit file its application for Consent to Establish and the case will be considere
d in the CMC on 30.09.2008.
105 32 21 SC-32
Manish Buildwell Pvt. Ltd., Plot No 8, Sector-12, Dwarka , New Delhi
Not applied
Plot area 540 sqmBuilt up area 2160 sqm
21.08.2008The unit came for personal hearing today and claims that there is no waste water discharge and the shopping complex has a total built-up area of 2160 sqm. The unit claims that he is not drawing any ground water and not using any D.G. Set. The construction is however complete and finishing is being done. The unit claims for
30.09
21.08.2008The unit came for personal hearing today and claims that there is no waste water discharge and the shopping complex has a total built-up area of 2160 sqm. The unit claims that he is not drawing any ground water and not using any D.G. Set. The construction is however complete and finishing is being done. The unit
a lenient penalty in view of the small size of the plot and no water discharge and DG. Set. The Committee deliberated on the issue and decided to impose damages of Rs. 5 Lakh as cash penalty and Bank Guarantee of Rs. 10 Lakhs valid for three years. The unit seeks time to discuss it with remaining five directors. Call for personal hearing on 03.09.2008 at 6.00 PM. The unit must also file Consent to
claims for a lenient penalty in view of the small size of the plot and no water discharge and DG. Set. The Committee deliberated on the issue and decided to impose damages of Rs. 5 Lakh as cash penalty and Bank Guarantee of Rs. 10 Lakhs valid for three years. The unit seeks time to discuss it with remaining five directors. Call for personal hearing on 03.09.2008 at 6.00 PM. The unit must
Establish application before 03.09.2008.
also file Consent to Establish application before 03.09.2008. 03.09.2008The unit came for personal hearing today. Unit claims that there are four small plots of 135 sqm each for which built up area as per the inspection report is 2160 sqm. According to the unit, there is no effluent discharged and there are no food courts proposed and it is only office
complex. The unit also claims that it has no D.G. Sets and no bore well. Let the unit file its application for Consent to Establish and the case will be considered in the CMC on 30.09.2008.
114 3 41 22 SC-41
Vishal Retail Ltd., A-18, B Block, Mihan Co-Operative Society, Mathura Road, New Delhi
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit
Inspection report of SIT to be discussed.
30.09 PH
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the
31.07
SIT
form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore
height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.200
Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. SIT to inspect and report. Call on 31.07.2008.
the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT to inspect and report. Call on 20.08.2008.
8 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT to inspect and report.
21.08.2008Issue notice for personal hearing on 03.09.2008 at 7.30 PM as no ETP/STP, and 16.8 KLD discharge.
Call on 20.08.2008. 21.08.2008Issue notice for personal hearing on 03.09.2008 at 7.30 PM as no ETP/STP, and 16.8 KLD discharge.
03.09.2008The unit came for personal hearing today. It was apprised of the need for payment of water cess whether by the unit or by its landlord expeditiously. It was also indicated to the unit that he needs to
apply for Consent to Establish and provide the following:-
(a) CGWA clearance for the bore-well.(b) ETP for 16.8 KLD of trade effluent discharge.(c) Provide oil & grease trap/treatment system for the trade effluent generated from restaurants.(d) Proper flooring and sheds are required at oil storage area at ground & top floor in order
to avoid leakage / spillage of water contamination. Waste oil needs to be handled properly / managed properly. (e) Total project cost be submitted.
This data may be filed before 30.09.2008. Call for personal hearing on 30.09.2008 at 5.00 PM.
The unit was indicated that since it has been operating without Consent to Establish and Consent to
Operate it would have to pay damages of 1 % of the project cost and Bank Guarantee of 2 % of the project cost valid for three years. The unit agreed to revert on this matter within two weeks.
The unit also informed regarding water cess payment that he requires one month time for its other 13 cases. Since this is the matter involving the resolution
between the landlord and the tenants, cases listed of these units on 17.09.2008 may be transferred to 30.09.2008 and unit will file full compliance of the each case by 30.09.2008. In these 13 cases due to non submission of some information required by our earlier letter, notices of closure have been issued. The unit represented by Mr. Narayan says that he received these
letters after the date of the CMC meeting. The unit is therefore required to submit replies to the points raised in the SCN in all these 13 cases by 30.09.2008. Copy of the minutes of this unit may be handed over to Mr. Narayan tomorrow since Mr. Narayan apprehends personal retribution.
7 1 7 23 SA-7
Sonia Theater Pvt Ltd G-1, Community Centre, Vikas Puri New Delhi-18
Not submitted
Not submit
ted
3500 sqm
- Oct 01 Notice of environmental clearance may be issued immediately and this case will be taken up on
Letter for CTE issued on 28.5.08Reminder issued on 01.07.2
10.09
Notice of environmental clearance may be issued immediately and this case will be taken up
AEZ Square Mall ,AEZ Group,
707 - 712A, 7th Floor, Chiran
NO N _ _ _ The unit has filed its reply in response to our
17.07
(AEZ Sqaure)
25.03.2008 for confirmation of Consent to Estabish & environmental clearance. Affidavit for date of construction and completion & architectural drawing may also be asked by 25.3.08. 03.4.08Take up on 10.04.2008. 17.04.2008Since unit has not responded for Consent to Establish and Environmental Clearance, MS to inspect
008.Unit has submitted reply on 09.07.2008 but not applied for CTE. One unit namely M/s Mc Donold's family restaurant operating in the premises has applied for CTE.
on 25.03.2008 for confirmation of Consent to Estabish & environmental clearance. Affidavit for date of construction and completion & architectural drawing may also be asked by 25.3.08. 03.4.08Take up on 10.04.2008. 17.04.2008Since unit has not responded for Consent to Establish and Environmental Clearance
jiv Tower, 43, Nehru Place, New Delhi - 110019
letter dated 28.05.2008. However, the unit has not indicated details of ground water drawl and requisite permission, waste water discharge details and has also not applied for Consent
and report on 30.04.2008. 01.05.2008Call on 14.05.2008 with MS inspection report. 21.05.2008 The built up area is 3500 sqm but a lot of food shops exist. Ask the unit to file details of water drawn from DJB, waste water discharge details and apply for Consent to Establish. Call on 18.06.2008. 18.06.2008The unit has filed its reply in
, MS to inspect and report on 30.04.2008. 01.05.2008Call on 14.05.2008 with MS inspection report. 21.05.2008 The built up area is 3500 sqm but a lot of food shops exist. Ask the unit to file details of water drawn from DJB, waste water discharge details and apply for Consent to Establish. Call on 18.06.2008. 18.06.200
to Establish. It has confirmed that it has two food shops which must be generating a fair degree of waste water. The unit may be issued the final reminder to submit details of ground wate
response to our letter dated 28.05.2008. However, the unit has not indicated details of ground water drawl and requisite permission, waste water discharge details and has also not applied for Consent to Establish. It has confirmed that it has two food shops which must be generating a fair degree of waste water. The unit may be issued the final reminder to submit details of ground
8The unit has filed its reply in response to our letter dated 28.05.2008. However, the unit has not indicated details of ground water drawl and requisite permission, waste water discharge details and has also not applied for Consent to Establish. It has confirmed that it has two food shops which must be generating a fair degree of waste water. The unit may be
r drawl and its permission, waste water discharge and its treatment and Consent to Establish. If the unit fails to do so by 18.07.2008, it will be issued notice for closure.
water drawl and its permission, waste water discharge and its treatment and Consent to Establish. If the unit fails to do so by 18.07.2008, it will be issued notice for closure. 13.08.2008Issue notice to the second restaurant to apply for Consent to Establish. Call on 10.09.2008.
issued the final reminder to submit details of ground water drawl and its permission, waste water discharge and its treatment and Consent to Establish. If the unit fails to do so by 18.07.2008, it will be issued notice for closure. 13.08.2008Issue notice to the second restaurant to apply for Consent to Establish. Call on 10.09.2008.
14 1 14 24 SA-14
DLF LTD Proposed
Not submitted
Applied on
11.03.
Plot area is
76.3 KLD30.3 KLD (Municipa
80 Cr. May, 2010
17.04.2008
As decided, a
10.0
9
17.04.2008
DLF LTD, Execut
_ 25142 39755 (i) Fresh
17.0
7
multilevel parking Cum commercial complex, sarojni nagar
2008 3787.63sqmBuilt up area is 21887.9 Sqm
l Authority + 46 KLD recycled water) / WW : 48.4 KLD
The unit has not filed the Environmental Clearance which may be done expeditiously. Call on 14.05.2008. 21.05.2008Call on 23.05.2008. 23.05.2008Issue final reminder for submitting a copy of Environment Clearance. Ask SIT to inspect and report. Call on 03.06.2008. 18.06.2008(i) Fresh water is 30.3 KLD without
letter issued on 01.07.2008. Unit has submitted a reply on 10.07.2008, but silent on waste water discharge and D.G. Set. Unit has reported fresh water 30.3 KLD will be taken from NDMC. No ground water will be drawn for the project. Hence, permission from CGWA is not
The unit has not filed the Environmental Clearance which may be done expeditiously. Call on 14.05.2008. 21.05.2008Call on 23.05.2008. 23.05.2008Issue final reminder for submitting a copy of Environment Clearance. Ask SIT to inspect and report. Call on 03.06.2008. 18.06.2008(i) Fresh water is 30.3 KLD
ive Director (Retail ) of DLF Centre,
Sansad Marg, New Delhi
water is 30.3 KLD without permission from CGWA for ground water drawl. (ii) Waste water generation is 48.4 KLD.(iii) D.G. Sets of 750 KVA (2 nos.) and 500 KVA (2 nos.)
Ask
permission from CGWA for ground water drawl. (ii) Waste water generation is 48.4 KLD.(iii) D.G. Sets of 750 KVA (2 nos.) and 500 KVA (2 nos.)
Ask the unit to file the Environmental Clearance and permission from CGWA for ground water drawl. Call on 18.07.2008. 13.08.2008The unit was issued a letter for CGWA clearance, treatment of waste
applicable. EC is awaited.In response to a letter recevied from NDMC. A D.O. letter by MS to Sh. Vikram Dev Dutt, Secretary, NDMC has been issued on 01.08.2008.
without permission from CGWA for ground water drawl. (ii) Waste water generation is 48.4 KLD.(iii) D.G. Sets of 750 KVA (2 nos.) and 500 KVA (2 nos.)
Ask the unit to file the Environmental Clearance and permission from CGWA for ground water drawl. Call on 18.07.2008. 13.08.2008The unit was issued a letter for
the unit to file the Environmental Clearance and permission from CGWA for ground water drawl. Call on 18.07.2008.
water and stack height and acoustic enclosure with the D.G. Set(s). The unit has replied to this notice saying that no ground water will be used and fresh water will be taken from NDMC. It has also stated that EC is awaited. The unit is silent on waste water generation and its treatment and the D.G. Sets. On these two points, a fresh notice may be issued. Also ask the unit to expedite EIA. Call
CGWA clearance, treatment of waste water and stack height and acoustic enclosure with the D.G. Set(s). The unit has replied to this notice saying that no ground water will be used and fresh water will be taken from NDMC. It has also stated that EC is awaited. The unit is silent on waste water generation and its treatment and the D.G. Sets. On these two points, a fresh notice
on 10.09.2008.
may be issued. Also ask the unit to expedite EIA. Call on 10.09.2008.
15 1 15 25 SA-15
DLF LTD Proposed multilevel parking Cum commercial complex, Baba Kharak Singh Marg
Not submitted
Applied on
11.03.2008
Plot Area is 6085.5 sqm Built up area is 33, 633.28 Sqm
Water : 115.9 KLD (42.4 KLD
MCD + 73.5 KLD recycled treated
sewage) / WW :
77.4 KLD
130 Cr. May, 2010
17.04.2008The unit has not filed the Environmental Clearance which may be done expeditiously. Call on 14.05.2008. 21.05.2008Call on 23.05.2008. 23.05.2008Issue final reminder for submitting a copy of Environment Clearance. Ask SIT to inspect
As decided, a letter issued on 01.07.2008.Unit has submitted reply on 10.07.2008 but silent on waste water generation and D.G. Sets. Unit has reported fresh water of 30.3 KLD will be taken from NDMC. No ground
10.09
17.04.2008The unit has not filed the Environmental Clearance which may be done expeditiously. Call on 14.05.2008. 21.05.2008Call on 23.05.2008. 23.05.2008Issue final reminder for submitting a copy of Environment Clearance. Ask SIT
DLF LTD,Executive Director (Retail ) of DLF Centre, Sansad Marg, New Delhi
_ 25143 39755 (i) Fresh water is 42.4 KLD without permission from CGWA for ground water drawl. (ii) Waste water generation is 77.4 KLD.(iii) D.G. Sets
17.07
and report. Call on 03.06.2008. 18.06.2008(i) Fresh water is 42.4 KLD without permission from CGWA for ground water drawl. (ii) Waste water generation is 77.4 KLD.(iii) D.G. Sets of 750 KVA (2 nos.) and 500 KVA (2 nos.)
Ask the unit to file the Environmental Clearance and permission from CGWA for ground water drawl. Call on 18.07.200
water will be taken. Hence, permission from CGWA is not applicable. EC is awaited.
to inspect and report. Call on 03.06.2008. 18.06.2008(i) Fresh water is 42.4 KLD without permission from CGWA for ground water drawl. (ii) Waste water generation is 77.4 KLD.(iii) D.G. Sets of 750 KVA (2 nos.) and 500 KVA (2 nos.)
Ask the unit to file the Environmental Clearance and permission from CGWA for ground
of 750 KVA (2 nos.) and 500 KVA (2 nos.)
Ask the unit to file the Environmental Clearance and permission from CGWA for ground water drawl. Call on 18.07.2008.
8. 13.08.2008 The unit was issued a letter for CGWA clearance, treatment of waste water and stack height and acoustic enclosure with the D.G. Set(s). The unit has replied to this notice saying that no ground water will be used and fresh water will be taken from NDMC. It has also stated that EC is awaited. The unit is silent on waste water generation and its treatment and the
water drawl. Call on 18.07.2008. 13.08.2008 The unit was issued a letter for CGWA clearance, treatment of waste water and stack height and acoustic enclosure with the D.G. Set(s). The unit has replied to this notice saying that no ground water will be used and fresh water will be taken from NDMC. It has also stated that EC is awaited. The unit is silent
D.G. Sets. On these two points, a fresh notice may be issued. Also ask the unit to expedite EIA. Call on 10.09.2008.
on waste water generation and its treatment and the D.G. Sets. On these two points, a fresh notice may be issued. Also ask the unit to expedite EIA. Call on 10.09.2008.
17 1 17 26 SA-17
R G Complex, Plot no 2, Motia Khan, Paharganj, Delhi
Not submitted
Not submit
ted
3990 sqm
10 KLD Not reporte
d
20.07.06 17.04.2008Issue notice to the unit to file Consent to Establish and Environmental Clearance along with an affidavit indicating date of start of construction & date of completion of
As decided, a letter issued on 01.07.2008.The same is received back undelievered and reissued on 09.07.2008.Unit has submitted reply on
10.09
17.04.2008Issue notice to the unit to file Consent to Establish and Environmental Clearance along with an affidavit indicating date of start of construction & date of completion of
R G Complex,Rajesh projects, RG Complex, DDA Communtiy Centre,Sec-14, Rohini, Delhi
_ _ _ (i) Ground water is 20 KLD without permission from CGWA for ground water drawl. (ii) Was
17.07
construction and to submit approved architectural drawing and completion certificate. Call on 14.05.2008. 21.05.2008SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 18.06.2008(i) Ground water is 20 KLD without permission from CGWA for ground water drawl. (ii) Waste water generation is 16 KLD. No indication of its treatment.
18.07.2008
construction and to submit approved architectural drawing and completion certificate. Call on 14.05.2008. 21.05.2008SIT to inspect and report by 11.06.2008. Call on 11.06.2008. 18.06.2008(i) Ground water is 20 KLD without permission from CGWA for ground water drawl. (ii) Waste water generation is 16 KLD. No indication
te water generation is 16 KLD. No indication of its treatment.(iii) D.G. Sets of 50 KVA (3 nos) and 25 KVA (1 no.). Stack height of D.G. Set of 25 KVA is inadequate.
Ask the
(iii) D.G. Sets of 50 KVA (3 nos) and 25 KVA (1 no.). Stack height of D.G. Set of 25 KVA is inadequate.
Ask the unit to file an application for Consent to Establish alonga with permission from CGWA for ground water drawl and above information. Call on 18.07.2008. 13.08.2008The unit is challenging the notice issued for CGWA, treatment
of its treatment.(iii) D.G. Sets of 50 KVA (3 nos) and 25 KVA (1 no.). Stack height of D.G. Set of 25 KVA is inadequate.
Ask the unit to file an application for Consent to Establish alonga with permission from CGWA for ground water drawl and above information. Call on 18.07.2008. 13.08.2008The unit is challenging the
unit to file an application for Consent to Establish alonga with permission from CGWA for ground water drawl and above information. Call on 18.07.2008.
of waste water and deficiencies in D.G. Set. Issue fresh and final notice, failing which notice for closure will be issued. Call on 10.09.2008.
notice issued for CGWA, treatment of waste water and deficiencies in D.G. Set. Issue fresh and final notice, failing which notice for closure will be issued. Call on 10.09.2008.
33 2 5 27 SB-5
Star City Mayur Vihar, Ph-I, Delhi Noida Road, Delhi
Not accorded.
Not applied for consent to Establish
no detail provided
no detail provided
no detail provided
no detail provided
10.03.2008Ask him to file Consent to Establish & environmental clearance. Case to be put up on 25.03.2008. Issue fresh letter. 11.04.2008Call on 30.04.2008.
Notice issued. Reply received. But not applied for CTE.SIT inspection report to be discussed.
10.09
10.03.2008Ask him to file Consent to Establish & environmental clearance. Case to be put up on 25.03.2008. Issue fresh letter. 11.04.2008Call on 30.04.2008.
Star City,Mahatta Towers Pvt Ltd,54, B Block Community Centre, Janak Puri, New Delhi -58
N _ _ _ SIT to inspect and report. Call on 18.07.2008
17.07
SIT
01.05.2008A strong letter may be drafted by MS to counter the points raised by the unit in its letter dated 20.03.2008, reiterating the CMC decision to file the Consent to Establish application and a copy of the approved architectural plan and completion certificate. The provisions of the Air & Water Acts and the Noise Rules may be highlighted and the extent of waste water discharge
01.05.2008A strong letter may be drafted by MS to counter the points raised by the unit in its letter dated 20.03.2008, reiterating the CMC decision to file the Consent to Establish application and a copy of the approved architectural plan and completion certificate. The provisions of the Air & Water Acts and the Noise Rules may be highlighted and the extent of waste
and D.G. Sets status may also be asked to be furnished. If the unit fails to do so by 21.05.2008, CMC will be free to decide the case as per Environmental Laws. 23.5.08Call on 03.06.2008. 18.06.2008SIT to inspect and report. Call on 18.07.2008 13.08.2008Ask the unit to apply for Consent to Establish and correct of deficienci
water discharge and D.G. Sets status may also be asked to be furnished. If the unit fails to do so by 21.05.2008, CMC will be free to decide the case as per Environmental Laws. 23.5.08Call on 03.06.2008. 18.06.2008SIT to inspect and report. Call on 18.07.2008 13.08.2008Ask the unit to apply for Consent to Establish
es noted by SIT. Call on 10.09.2008.
and correct of deficiencies noted by SIT. Call on 10.09.2008.
36 2 8 28 SB-8
P.S.K. Distrcit Centre, Laxmi Nagar, Vikas Marg, Delhi, DSIDC Govt of NCT of Delhi
NA 15.01.2008
644 sq m
corporation and ground water, 3 KLD (WW)
70 lakhs
Feb 08 11.03.2008The unit appears to be a club with dining facilities. The unit may be asked to clarify whether they have installed ETP / STP. The unit may also be asked to clarify whether they have adequate stack height and acoustic enclosures with two D.G. Sets.
11.04.2008Time allowed till end
Letter issued on 03.06.2008. Reply awaited.
10.09
11.03.2008The unit appears to be a club with dining facilities. The unit may be asked to clarify whether they have installed ETP / STP. The unit may also be asked to clarify whether they have adequate stack height and acoustic enclosures with two D.G. Sets. 11.04.2008Time allowed
Delhi State Industrial and Infrastructure Development Corporation Ltd, N Block, Bombay Life Building,Connaught Circus,New Delhi - 1
N _ _ _ Call on 18.07.2008 with reply.
17.07
May, 2008 to install ETP. 28.5.08The unit must file the ETP report and noise monitoring report latest by 18.06.2008. Call on 18.06.2008. 18.06.2008Call on 18.07.2008 with reply. 13.08.2008Issue final reminder. Call on 10.09.2008.
till end May, 2008 to install ETP. 28.5.08The unit must file the ETP report and noise monitoring report latest by 18.06.2008. Call on 18.06.2008. 18.06.2008Call on 18.07.2008 with reply. 13.08.2008Issue final reminder. Call on 10.09.2008.
38 2 10 29 SB-10
Aditya Mall, CBD Ground, Near Karkardooma Court, Delhi-92
NA 30/05/08
12867.115
By tanker / 4(WW)
22 crores
1.4.06 11.03.2008Last and final reminder asking them to file Consent to
Notice for closure issued on 29.05.2008. Consent application
10.09
11.03.2008Last and final reminder asking them to file Consent to
M/s Aggarwal Associates,10, Rajdhani Enclave,Delhi -
N _ _ _ The SIT team was not allowed to fully inspect
06.08
Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion.Approved architectural drawing may also be filed by 25.3.2008. Case to be put up on 25.03.2008. 03.04.2008The unit appears to be cleverly avoiding the arms of environmental laws. Direct him to appear before the committee
received. Unit filed writ before Hon'ble HC. No stay granted.Analysis reprot of effluent received from DPCC laboratory. As per CMC decision dated 06.08.2008, Unit has submitted Rs. 20 Lakhs as cash penalty on 07.08.2008.
Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion.Approved architectural drawing may also be filed by 25.3.2008. Case to be put up on 25.03.2008. 03.04.2008The unit appears to be cleverly avoiding the arms of environmental laws. Direct him to appear
92 the premises despite the fact there is no stay from High Court. MS must therefore do the inspection himself. Call on 25.06.2008.
on 17.04.2008 at 6.00 PM. 11.04.2008Take up on 17.04.2008. 17.04.2008The unit appeared for personal hearing and the built up area is less than what is required for Environmental Clearance. However, the unit has not applied for Consent to Establish despite waste water generation and use of D.G. Sets. Unit is directed to apply for
before the committee on 17.04.2008 at 6.00 PM. 11.04.2008Take up on 17.04.2008. 17.04.2008The unit appeared for personal hearing and the built up area is less than what is required for Environmental Clearance. However, the unit has not applied for Consent to Establish despite waste water generation and use of D.G.
Consent to Establish within a week with all the necessary data. 28.5.08Issue notice for closure without waiting for minutes. Call on 18.06.2008. 18.06.2008The SIT team was not allowed to fully inspect the premises despite the fact there is no stay from High Court. MS must therefore do the inspection himself. Call on 25.06.2008.
Sets. Unit is directed to apply for Consent to Establish within a week with all the necessary data. 28.5.08Issue notice for closure without waiting for minutes. Call on 18.06.2008. 18.06.2008The SIT team was not allowed to fully inspect the premises despite the fact there is no stay from High Court. MS must therefore
25.06.2008In view of the fact brought out by MS, call the unit for personal hearing on 18.07.2008 at 6.00 PM. 17.07.2008The unit did not come for personal hearing but sent a clerk for seeking a date. The unit has already filed a case in the High Court but has not been granted stay. The inspection done by MS indicates a large number of deficiencies which are adequate
do the inspection himself. Call on 25.06.2008. 25.06.2008In view of the fact brought out by MS, call the unit for personal hearing on 18.07.2008 at 6.00 PM. 17.07.2008The unit did not come for personal hearing but sent a clerk for seeking a date. The unit has already filed a case in the High Court but has not been granted stay. The inspection done by
to warrant a notice for closure to prevent the environment from being affected adversely. The unit had approached both MS & Chairman and in the meeting with Chairman had indicated that he will withdraw the court case if a lenient view can be taken. Case may be called on 24.07.2008 to ascertain if the court case has been withdrawn. Call on 24.07.2008. 24.07.200
MS indicates a large number of deficiencies which are adequate to warrant a notice for closure to prevent the environment from being affected adversely. The unit had approached both MS & Chairman and in the meeting with Chairman had indicated that he will withdraw the court case if a lenient view can be taken. Case may be called on 24.07.2008 to ascertain
8The unit had gone to the High Court and had argued its case on 21.07.2008. It was not able to get a stay on the proceedings in DPCC from the Hon’ble High Court. Therefore, DPCC has the authority to take any action against the unit as it deems fit. Despite the above, the unit appeared before the CMC today and in its written letter wanted to know how and where it was covered in
if the court case has been withdrawn. Call on 24.07.2008. 24.07.2008The unit had gone to the High Court and had argued its case on 21.07.2008. It was not able to get a stay on the proceedings in DPCC from the Hon’ble High Court. Therefore, DPCC has the authority to take any action against the unit as it deems fit. Despite the above, the unit
the Orange category cases of DPCC. This was not acceptable to the Committee, because such issues had been raised by the unit in the Hon’ble High Court without any consequential benefit. The unit did not come before CMC with clean hands and after exercising all its legal options was trying to get relief. The Committee felt that the only relief that could be provided
appeared before the CMC today and in its written letter wanted to know how and where it was covered in the Orange category cases of DPCC. This was not acceptable to the Committee, because such issues had been raised by the unit in the Hon’ble High Court without any consequential benefit. The unit did not come before CMC with clean hands and
to the unit was to ask it to deposit 1.5 % of the total project cost by way of damages and 1.5 % of total project cost by way of Bank Guarantee valid for three years as has been done in similar cases where the malls come into operation without Consent to Establish. This comes to about Rs. 30 Lakhs each. If the unit is prepared to comply with these conditions, let it confirm by 06.08.200
after exercising all its legal options was trying to get relief. The Committee felt that the only relief that could be provided to the unit was to ask it to deposit 1.5 % of the total project cost by way of damages and 1.5 % of total project cost by way of Bank Guarantee valid for three years as has been done in similar cases where the malls come into operation without Consent to
8. Call on 06.08.2008. 31.07.2008The case was taken up as a table agenda item in view of the letter dated 25.07.2008, since the matter has already been disposed of by CMC on 24.07.2008 and minutes have been uploaded on the website, the matter is complete. Call on 06.08.2008. 06.08.08The unit appeared before Committee during the CMC meeting.
Establish. This comes to about Rs. 30 Lakhs each. If the unit is prepared to comply with these conditions, let it confirm by 06.08.2008. Call on 06.08.2008. 31.07.2008The case was taken up as a table agenda item in view of the letter dated 25.07.2008, since the matter has already been disposed of by CMC on 24.07.2008 and minutes have been uploaded on the website,
He has filed the representation before Hon’ble Chief Minister, which was received and shown to all the Committee members today. The Committee deliberated on the lenient view representation of the unit and decided that since it was a small unit and was running only one mall, the damages could be readjusted to 1 % of the total project cost and Bank Guarantee would be decided
the matter is complete. Call on 06.08.2008. 06.08.08The unit appeared before Committee during the CMC meeting. He has filed the representation before Hon’ble Chief Minister, which was received and shown to all the Committee members today. The Committee deliberated on the lenient view representation of the unit and decided that since it was a
only after the damages of Rs. 20 Lakhs is paid before 12.08.2008. Call on 12.08.2008 for a final decision. 13.08.2008Since the damages of Rs. 20 lakhs has been paid. The unit may be directed to submit Bank Guarantee of Rs. 40 Lakhs by 10.09.2008. Call on 10.09.2008.
small unit and was running only one mall, the damages could be readjusted to 1 % of the total project cost and Bank Guarantee would be decided only after the damages of Rs. 20 Lakhs is paid before 12.08.2008. Call on 12.08.2008 for a final decision. 13.08.2008Since the damages of Rs. 20 lakhs has been paid. The unit may be directed to submit Bank Guarantee of Rs. 40 Lakhs by 10.09.200
8. Call on 10.09.2008.
40 2 12 30 SB-12
Today Homes and InfrastructureLtd , Proposed Commercial Complex (North Gate obit plaza) at Gujaarawala Town area of Model Town-II, New Delhi
NA Not Applied For Consent to Establish, However had applied for NOC W.R.T EC on 24-08-06. The same has been forwrded to MOEF
18444.5(as per letter
)
160(MCD)/
74(WW)
57.84Cr.
2008 11.03.2008Ask the unit to file Environmental Clearance expeditiously. Affidavit for date of construction and completion, architectural drawing may be filed by April CMC. 11.04.2008Reminder may be issue to the unit to file a clear affidavit indicating date of construction and the total built up area as the building plan filed has some overwritin
Letter issued. Reply awaited.Inspection reprot of SIT will be discussed.
10.09
11.03.2008Ask the unit to file Environmental Clearance expeditiously. Affidavit for date of construction and completion, architectural drawing may be filed by April CMC. 11.04.2008Reminder may be issue to the unit to file a clear affidavit indicating date of construction and the total built up area as the
Today Homes and InfrastructureLtd, Satesman House, 8 th floor, Barakhamba Road, New Delhi - 01
D _ 19116 24-08-06
Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008.
17.07
SIT
g. Call on 30.04.2008. 01.05.2008Call on 14.05.2008. 23.5.2008Since unit claims built up area less than 20000 sqm, SIT to inspect specially on this point. Also on water drawl sources, waste water discharge in treatment and date of start of construction & date of completion of construction, details of D.G. Sets. Call on 18.06.2008.
building plan filed has some overwriting. Call on 30.04.2008. 01.05.2008Call on 14.05.2008. 23.5.2008Since unit claims built up area less than 20000 sqm, SIT to inspect specially on this point. Also on water drawl sources, waste water discharge in treatment and date of start of construction & date of completion of construction, details of D.G.
18.06.2008Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008. 13.08.2008Ask the unit to file correction of deficiencies noted by SIT. Call on 10.09.2008.
Sets. Call on 18.06.2008. 18.06.2008Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008. 13.08.2008Ask the unit to file correction of deficiencies noted by SIT. Call on 10.09.2008.
42 2 14 31 SB-14
Parsvnath Developers Ltd in construction with M/s OCL Ltd Commercial Complex
NA 18/03/08
2550.465 sq m
MCD-17 KLD
GW-NIL DIS.-7.68
KLD
5.9 crore
NA 11.03.2008Last and final reminder asking them to file Consent to Establish
Letter issued. Reply received on 29.07.2008 & informed that they have applied
10.09
11.03.2008Last and final reminder asking them to file Consent to Establish
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19,
N _ _ _ Time allowed till 18.07.2008.
17.07
at Pratap Nagar Metro
& environmental clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion. Unit will also file approved architectural drawing. Take up on 25.3.08. 03.04.2008Concerned CMC to inspect and report factually on 10.04.2008. 11.04.2008SIT will inspect and report by 30.04.2008. 01.05.200
for noise monitoring report of D.G. Sets.
& environmental clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion. Unit will also file approved architectural drawing. Take up on 25.3.08. 03.04.2008Concerned CMC to inspect and report factually on 10.04.2008. 11.04.2008SIT will inspect and report by 30.04.2008.
Barakhamba Road,New Delhi - 1
8SIT inspection confirms the claim of the unit that Environmental Clearance is not required. However, two D.G Sets were found in operational and Consent to Establish application indicates waste water generation to the tune of approximately 7.5 KLD. Let the unit file the noise monitoring report of D.G. Sets. Call on 03.06.2008. 28.5.08Call on 03.06.2008.
01.05.2008SIT inspection confirms the claim of the unit that Environmental Clearance is not required. However, two D.G Sets were found in operational and Consent to Establish application indicates waste water generation to the tune of approximately 7.5 KLD. Let the unit file the noise monitoring report of D.G. Sets. Call on 03.06.2008. 28.5.08Call on
18.06.2008Time allowed till 18.07.2008. 13.08.2008Ask the unit to submit noise monitoring report by 10.09.2008.
03.06.2008. 18.06.2008Time allowed till 18.07.2008. 13.08.2008Ask the unit to submit noise monitoring report by 10.09.2008.
45 2 17 32 SB-17
Parsvnath Developers Ltd Commercial Project Azad Pur
Application delisted by MOEF from the pending list.
39728 48680.21
180(MCD) (Borewell present according to as per insp.) / 48(WW)
199Cr. 2008 11.03.2008Consent to Establish application filed and Environmental Clearance not yet granted. MOEF has directed to take action against the unit for starting the
Letter isued.Reply awaited.
10.09
11.03.2008Consent to Establish application filed and Environmental Clearance not yet granted. MOEF has directed to take action against the unit for starting the
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
A 2008 22283 39362 SIT to inspect and report by 11.07.2008. Call on 11.07.2008.
Issue reminder to Addl. Secretary, MOEF through Chairman, DPCC for response to our
06.08
construction work before issue of Environmental Clearance. An opportunity of being heard may be given to the unit on 25.03.2008 at 8.00 PM. Issue letter immediately without waiting for the minutes. 28.03.2008Inspection to be done by MS, SEE & EE. Letter be issued seeking a copy of EC and copy of change of land use. 11.04.2008The inspection of MS clearly shows
construction work before issue of Environmental Clearance. An opportunity of being heard may be given to the unit on 25.03.2008 at 8.00 PM. Issue letter immediately without waiting for the minutes. 28.03.2008Inspection to be done by MS, SEE & EE. Letter be issued seeking a copy of EC and copy of change of land use. 11.04.2008The
letter. Call on 06.08.2008.
built up of the plot falling under EIA notification. Issue personal hearing notice on 30.04.2008 at 5.00 PM. 30.04.2008The total built up area as per the inspection report is 48680.21 sqm. Out of this, the unit claims that approx. 35000 sqm is with the unit and remaining area is with DMRC. The unit claims that due to change of land use problem they have been asked not to
inspection of MS clearly shows built up of the plot falling under EIA notification. Issue personal hearing notice on 30.04.2008 at 5.00 PM. 30.04.2008The total built up area as per the inspection report is 48680.21 sqm. Out of this, the unit claims that approx. 35000 sqm is with the unit and remaining area is with DMRC. The unit claims that due to change of land
undertake the said construction.
MOEF in its wisdom has already directed DPCC to take action against the unit under EPAct, 1986. This implies that MOEF is clear of the unit’s applicability for EIA. However, since the issue of change of land use has arisen, it would be appropriate to ask the unit to file an affidavit from the MD or the Director
use problem they have been asked not to undertake the said construction.
MOEF in its wisdom has already directed DPCC to take action against the unit under EPAct, 1986. This implies that MOEF is clear of the unit’s applicability for EIA. However, since the issue of change of land use has arisen, it would be appropriate to ask the unit to
(Projects), DMRC clearly indicating the extent of built up area which is going to the unit and the area which is going to remain with the DMRC. This affidavit may be filed before 21.05.2008 and the case may be put up for personal hearing on 21.05.2008. 21.05.2008The unit did not appear for personal hearing today. It was decided to ask MS to write to Additional
file an affidavit from the MD or the Director (Projects), DMRC clearly indicating the extent of built up area which is going to the unit and the area which is going to remain with the DMRC. This affidavit may be filed before 21.05.2008 and the case may be put up for personal hearing on 21.05.2008. 21.05.2008The unit did not appear for personal hearing
Secretary,MOEF enclosing both the letters of MOEF in which they have asked for action in one and delisting the case in the other. Call on 25.06.2008. 25.06.2008SIT to inspect and report by 11.07.2008. Call on 11.07.2008. 11.07.2008Issue reminder to Addl. Secretary, MOEF through Chairman, DPCC for response to our letter. Call on 06.08.2008.
today. It was decided to ask MS to write to Additional Secretary,MOEF enclosing both the letters of MOEF in which they have asked for action in one and delisting the case in the other. Call on 25.06.2008. 25.06.2008SIT to inspect and report by 11.07.2008. Call on 11.07.2008. 11.07.2008Issue reminder to Addl. Secretary, MOEF through Chairman
13.08.2008Ask the unit to correct the deficiencies noted by SIT. MS to check about the letter written about delisting of the case from the EIA Cell. Call on 10.09.2008.
, DPCC for response to our letter. Call on 06.08.2008. 13.08.2008Ask the unit to correct the deficiencies noted by SIT. MS to check about the letter written about delisting of the case from the EIA Cell. Call on 10.09.2008.
50 2 22 33 SB-22
North Square Mall , F-1,2,3 Netaji Subhash Place, Pitampura, Near T.V.Tower, New Delhi
exempted from EC
10342.96 (as per inspection
18(MCD)/ 14.4(WW)
40.76 cr.
june,06 11.03.2008Unit claims that it is not covered under EIA notification. Ask him to file an affidavit
Letter issued.Reply received. Water analysi report received from DPCC laboratory & stated
10.09
11.03.2008Unit claims that it is not covered under EIA notification. Ask him to file an
M/s Suncity Developers, N-49, I Floor, Connaught Place, New Delhi - 01.
A 38869
24681 39630 Dr. Nandita, Sr. Scientist (Water) must be directed to do the water monitoring as require
17.07
for date of start of construction and copy of the approved architectural drawing. He must also file completion certificate from the concerned public authority by April CMC.. 11.04.2008SIT to inspect. Case to be taken up on 14.05.2008. 21.05.2008Inspection report indicates waste water discharge of 14.4 KLD without any ETP. Also the unit is
that ETP/STP is very much required to treat waste water generated by the Mall.
affidavit for date of start of construction and copy of the approved architectural drawing. He must also file completion certificate from the concerned public authority by April CMC.. 11.04.2008SIT to inspect. Case to be taken up on 14.05.2008. 21.05.2008Inspection report indicates waste water discharge of 14.4 KLD without any ETP. Also the
d by CMC meeting dated 03.06.2008. Call on 18.07.2008.
taking ground water through bore-well and has not filed clearance from CGWB. No rain water harvesting structure was also seen. Call the unit for personal hearing on 03.06.2008. 03.06.2008The unit was called for personal hearing today and attended the same. The unit has agreed to do the following by 25.06.208:-
(a) Self assessment of water cess to be done and
unit is taking ground water through bore-well and has not filed clearance from CGWB. No rain water harvesting structure was also seen. Call the unit for personal hearing on 03.06.2008. 03.06.2008The unit was called for personal hearing today and attended the same. The unit has agreed to do the following by 25.06.208:-
(a) Self
deposited in DPCC.(b) Stack height of DG sets to be raised to appropriate level.(c) DPCC to do a water monitoring of waste water and confirm whether ETP / STP is required within 10 days and thereafter by 25.06.2008 the unit will confirm by when ETP / STP will be installed as found necessary through the water monitoring report. (d) The unit will file the permission from Central Ground
assessment of water cess to be done and deposited in DPCC.(b) Stack height of DG sets to be raised to appropriate level.(c) DPCC to do a water monitoring of waste water and confirm whether ETP / STP is required within 10 days and thereafter by 25.06.2008 the unit will confirm by when ETP / STP will be installed as found necessary through the water monitoring report. (d) The unit will
Water Authority for drawl of ground water. 25.06.2008Dr. Nandita, Sr. Scientist (Water) must be directed to do the water monitoring as required by CMC meeting dated 03.06.2008. Call on 18.07.2008. 13.08.2008 Inform the unit that the STP is required. Let the unit install STP and confirm by 10.09.2008. Call on 10.09.2008.
file the permission from Central Ground Water Authority for drawl of ground water. 25.06.2008Dr. Nandita, Sr. Scientist (Water) must be directed to do the water monitoring as required by CMC meeting dated 03.06.2008. Call on 18.07.2008. 13.08.2008 Inform the unit that the STP is required. Let the unit install STP and confirm by
10.09.2008. Call on 10.09.2008.
54 2 26 34 SB-26
Jackson Buildwell, V3S Ring Road Mall, at 1B-3, Sector -1o, Rohini.
16/04/08 23/10/07
MCD-206 KLD GW-NIL DIS.-70 KLD
170 crore
11.03.2008Unit has filed Consent to Establish on 23.10.2007 & Environmental Clearance not yet filed. The unit is reportedly under construction without Environmental Clearance. Unit may be asked to file an affidavit indicating start of construction, likely date of completion of construction and approved architectural drawing.
CTE issued. Call in July 2008.Letter issued.Reply received.
10.09
11.03.2008Unit has filed Consent to Establish on 23.10.2007 & Environmental Clearance not yet filed. The unit is reportedly under construction without Environmental Clearance. Unit may be asked to file an affidavit indicating start of construction, likely date of completion of construction and approved architectural
Jackson Buildwell, B - 1, Udyog Nagar, Peera Garhi Chowk, Rohtak Road, New Delhi - 41.
A 200 9
24006 23/10/07
Ask the unit to submit permission from CGWA for ground water drawl and latest status on EC compliance. Call on 06.08.2008.
06.08
Case to be taken up in April, 2008. 11.04.2008Call for personal hearing on 30.04.2008 at 6.30 PM. 30.04.2008The unit had filed an application for Consent to Establish on 23.10.2007 and application for Environmental Clearance on 26.06.2007 and started construction in Feb, 2008 and received Environmental Clearance on 16.04.2008.
drawing. Case to be taken up in April, 2008. 11.04.2008Call for personal hearing on 30.04.2008 at 6.30 PM. 30.04.2008The unit had filed an application for Consent to Establish on 23.10.2007 and application for Environmental Clearance on 26.06.2007 and started construction in Feb, 2008 and received Environmental Clearance
Between start of construction and today the unit admits about 20 % of completion of the construction which amounts to about Rs. 34 Crore on total investment of Rs. 170 Crores. Since the unit has shown scant regard for compliance of environmental laws, the unit may be asked to file a cash penalty of 0.5 % of the project cost of Rs. 15 Lakh and 0.5 %
as Bank Guarantee which
on 16.04.2008. Between start of construction and today the unit admits about 20 % of completion of the construction which amounts to about Rs. 34 Crore on total investment of Rs. 170 Crores. Since the unit has shown scant regard for compliance of environmental laws, the unit may be asked to file a cash penalty of 0.5 % of the project cost of Rs. 15 Lakh and
comes to Rs. 15 Lakh each rounded to the nearest Rs. 5 lakh. The unit was indicated this quantum and has agreed to submit the same within a week. The unit has also filed a letter to this effect.
In view of the above, the unit may be issued Consent to Establish at the same time as they file the cash penalty of Rs. 15 Lakh and Bank Guarantee
of Rs. 15 Lakh valid for
0.5 % as Bank Guarantee which comes to Rs. 15 Lakh each rounded to the nearest Rs. 5 lakh. The unit was indicated this quantum and has agreed to submit the same within a week. The unit has also filed a letter to this effect.
In view of the above, the unit may be issued Consent to Establish at the same time as they file the cash penalty of Rs. 15
three years in assurance of compliance of all environmental laws. Call on 14.05.2008 for confirmation of compliance. 23.5.08Call in July, 2008. 11.07.2008Ask the unit to submit permission from CGWA for ground water drawl and latest status on EC compliance. Call on 06.08.2008. 13.08.2008Call on 10.09.2008.
Lakh and Bank Guarantee
of Rs. 15 Lakh valid for three years in assurance of compliance of all environmental laws. Call on 14.05.2008 for confirmation of compliance. 23.5.08Call in July, 2008. 11.07.2008Ask the unit to submit permission from CGWA for ground water drawl and latest status on EC compliance. Call
on 06.08.2008. 13.08.2008Call on 10.09.2008.
55 2 27 35 SB-27
Parsvnath Developers Ltd. Plot No 1B2, Twin District Centre, Sector-10, Rohini
EC obtained on 14.07.2008
25/02/08
35287.27 sq m
MCD-205 KLD GW-NIL DIS.-135 KLD
268.57 crore
July, 2010 11.04.2008Call for personal hearing on 30.04.2008 at 7.00 PM. 30.04.2008The unit has applied for Consent to Establish on 25.02.2008 and Environmental Clearance on 11.12.2007. Without getting either of them, the unit has started excavation and excavated
Cash penalty and BG not yet submitted. Letter submitted by the unit on 31.07.2008..
10.09
11.04.2008Call for personal hearing on 30.04.2008 at 7.00 PM. 30.04.2008The unit has applied for Consent to Establish on 25.02.2008 and Environmental Clearance on 11.12.2007. Without getting either of them, the unit has started excavation and
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
25009 25-02-2008
Call for personal hearing on 25.07.2008 at 5.30 PM.
06.08
more than 25000 cubic feet between March, 2008 and 1st week of April, 2008. Let the CMC inspect the unit to find out the total excavation done. Issue reminder to the unit to file a copy of Environmental Clearance immediately. Inform Addl. Secretary, MOEF about the minutes of this meeting. Call on 14.05.2008. 21.05.2008Total built up area is about 35000 sqm. Inspection report
excavated more than 25000 cubic feet between March, 2008 and 1st week of April, 2008. Let the CMC inspect the unit to find out the total excavation done. Issue reminder to the unit to file a copy of Environmental Clearance immediately. Inform Addl. Secretary, MOEF about the minutes of this meeting. Call on 14.05.2008. 21.05.2008Total built up area is about 35000
indicates excavation done to the extent of 26250 cubic meter. This information may be sent to Addl. Secretary, MOEF by MS asking whether any adverse order issued against them. Separately, unit may be asked to file Environmental Clearance urgently. Call on 11.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 5.30 PM. 24.07.2008
sqm. Inspection report indicates excavation done to the extent of 26250 cubic meter. This information may be sent to Addl. Secretary, MOEF by MS asking whether any adverse order issued against them. Separately, unit may be asked to file Environmental Clearance urgently. Call on 11.06.2008. 25.06.2008Call for personal hearing on 25.07.200
The unit came for personal hearing today. It has excavated without Environmental Clearance and Consent to Establish about 26250 cubic meters for the space of three basements which is approx. 1/3rd of the total construction to be done in terms of 6 floors yet to be taken up. The total waste water generation is 135 KLD and the unit has proposed STP with recycling of waste water
8 at 5.30 PM. 24.07.2008The unit came for personal hearing today. It has excavated without Environmental Clearance and Consent to Establish about 26250 cubic meters for the space of three basements which is approx. 1/3rd of the total construction to be done in terms of 6 floors yet to be taken up. The total waste water generation is 135 KLD and the unit has
facility. The total project cost is Rs. 268 Crores.
The Committee deliberated on the appropriate amount of damages for this unit and concluded that, since three basements related excavation has been done, 1/3rd of the cash penalty of 0.5 % of the project cost and 1/3rd of the Bank Guarantee of 0.5 % of the project cost valid for three years, amounting to Rs. 40 Lakhs each may be levied
proposed STP with recycling of waste water facility. The total project cost is Rs. 268 Crores.
The Committee deliberated on the appropriate amount of damages for this unit and concluded that, since three basements related excavation has been done, 1/3rd of the cash penalty of 0.5 % of the project cost and 1/3rd of the Bank Guarantee of 0.5 % of the project cost valid
on the unit. Unit seeks time for 10 days. If the unit files the Bank Guarantee and damages within 10 days or before 06.08.2008, Consent to Establish may be granted at the same time and action may be confirmed in the CMC on 06.08.2008. 13.08.2008Unit reply has been carefully considered by the committee and rejected. Issue a final reminder for submissio
for three years, amounting to Rs. 40 Lakhs each may be levied on the unit. Unit seeks time for 10 days. If the unit files the Bank Guarantee and damages within 10 days or before 06.08.2008, Consent to Establish may be granted at the same time and action may be confirmed in the CMC on 06.08.2008. 13.08.2008Unit reply has been carefully considered by the committe
n of damages and Bank Guarantee. Call on 10.09.2008.
e and rejected. Issue a final reminder for submission of damages and Bank Guarantee. Call on 10.09.2008.
57 2 29 36 SB-29
Sachdewa Buildcon, Plot No 17, Karkardooma, District Centre, near AGCR Colony, Delhi
_ Not applied
17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to
Letter issued. Reply received on 29.07.2008.
10.09
17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent
Sachdewa Buildcon, Plot No 17, Karkardooma, District Centre,
Near AGCR Colony, Delhi
Not known
The unit has replied in response to the letter of DPCC dated 29.05.2008 indicating that they have started commercial building as per
17.07
Establish, a copy of Environmental Clearance, affidavit indicating date of start of construction, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008.
18.06.2008The unit has replied in response to the letter of DPCC dated
to Establish, a copy of Environmental Clearance, affidavit indicating date of start of construction, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008.
18.06.2008The unit has replied in response to the
DDA sanction. The unit may be asked to file the following details:(i) Permission from CGWA for ground water drawl. (ii) Waste water generation & its treatment.(iii) Details of
29.05.2008 indicating that they have started commercial building as per DDA sanction. The unit may be asked to file the following details:(i) Permission from CGWA for ground water drawl. (ii) Waste water generation & its treatment.(iii) Details of D.G. Sets along with information w.r.t. stack height and acoustic enclosure.Call on 18.07.2008. 13.08.2008
letter of DPCC dated 29.05.2008 indicating that they have started commercial building as per DDA sanction. The unit may be asked to file the following details:(i) Permission from CGWA for ground water drawl. (ii) Waste water generation & its treatment.(iii) Details of D.G. Sets along with information w.r.t. stack height and acoustic enclosure.
D.G. Sets along with information w.r.t. stack height and acoustic enclosure.Call on 18.07.2008.
The unit has filed the reply which does not answer the notice. Issue final reminder for appropriate reply. Call on 10.09.2008.
Call on 18.07.2008. 13.08.2008The unit has filed the reply which does not answer the notice. Issue final reminder for appropriate reply. Call on 10.09.2008.
79 3 6 37 SC-6
DLF Commercial Developers Ltd (Construction of proposed Commercial & Retail Centre at Plot no 10 & 11 Jasola New Delhi
16/05/07 08.02.2007
28970.78 sq m
MCD-563 KLD DIS.-NIL GW-NIL
320.63 crore
JAN. 2008
11.03.2008The unit has applied for Consent to Establish and has also filed Environmental Clearance dated 17.05.2007. However, the construction of the said mall
Inspection is to be carried out by SIT.
10.09
11.03.2008The unit has applied for Consent to Establish and has also filed Environmental Clearance dated 17.05.2007. However, the construction of the said mall
DLF Commercial Developers Ltd,DLF Centre,
9th Floor, Sansad Marg, New Delhi-01
YES A Jan. 2008
20622 39296 Call for personal hearing on 25.07.2008 at 7.30 PM.
12.08
must have started before Environmental Clearance was given. He may be therefore asked an affidavit indicating the date of start of construction of mall and copy of approved architectural drawing along with date of approval of architectural drawing and he will be given personal hearing in April, 2008 CMC to decide the case. 17.04.2008Issue reminder to the unit
must have started before Environmental Clearance was given. He may be therefore asked an affidavit indicating the date of start of construction of mall and copy of approved architectural drawing along with date of approval of architectural drawing and he will be given personal hearing in April, 2008 CMC to decide the case. 17.04.2008Issue reminder
to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08SIT to inspect & report on 10 conditions and on Environmental Clearance conditions. Call on 11.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 7.30 PM. 24.07.2008The unit came for personal hearing today. Since DPCC is required to file its counter affidavit
to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08SIT to inspect & report on 10 conditions and on Environmental Clearance conditions. Call on 11.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 7.30 PM. 24.07.2008The unit came for personal hearing today. Since DPCC is required to file its
in the Hon’ble High Court in this case, it is in the process of doing so. Call on 12.08.2008. 13.08.2008Ask the unit to correct the deficiencies noted by SIT. Call on 10.09.2008.
counter affidavit in the Hon’ble High Court in this case, it is in the process of doing so. Call on 12.08.2008. 13.08.2008Ask the unit to correct the deficiencies noted by SIT. Call on 10.09.2008.
90 3 17 38 SC-17
Ansal Plaza , HUDCO Place, Khel Gaon Marg Andrews Ganj, New Delhi-49
Came up prior to the EIA Notification as gathered from the Internet.
Not applied for consent to Establish
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things :
Letter issued to Ansal Plaza on 29.07.2008.Also letter issued to HUDCO, Indian Oil, Karnataka Bhawan and
10.09
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five
Ansal Plaza,Ansal Properties & Infrastructure Ltd., 115, Ansal Bhawan, 16, K. G. Marg, New Delhi.
D N _ _ _ Call for personal hearing on 25.07.2008 at 8.00 PM
12.08
1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on
Habitate Service Centre.No reply received.
things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing
14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 5.30 PM. 11.6.2008The unit appeared for personal hearing today. It has also filed an application saying that HUDCO has signed an agreement to sublease in 1995 and the total built up area of M/s Ansal Plaza is about 14,700 sqm. The unit has also claimed that HUDCO is responsible for the
documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 5.30 PM. 11.6.2008The unit appeared for personal hearing today. It has also filed an application saying that HUDCO has signed an agreement to sublease in 1995 and the total built up area of M/s Ansal Plaza is about 14,700 sqm. The unit has also
maintenance and external services in the entire area. When questioned about the air emissions and waste water generation from the eating places in Ansal Plaza, the representatives of the unit were not familiar with the details. It was not also clear about the total number of D.G. Sets and whether these D.G. Sets have acoustic enclosures. In view of the above, SIT may inspect the premises
claimed that HUDCO is responsible for the maintenance and external services in the entire area. When questioned about the air emissions and waste water generation from the eating places in Ansal Plaza, the representatives of the unit were not familiar with the details. It was not also clear about the total number of D.G. Sets and whether these D.G. Sets have acoustic enclosure
by 25.06.2008. Call on 25.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 8.00 PM 24.07.2008The unit came for personal hearing today and putting the entire responsibility on HUDCO who is their lesser for creation and treatment of 48 KD of waste water. The SIT report indicates built up area is 14,700 sqm with waste water of 48 KLD and
s. In view of the above, SIT may inspect the premises by 25.06.2008. Call on 25.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 8.00 PM 24.07.2008The unit came for personal hearing today and putting the entire responsibility on HUDCO who is their lesser for creation and treatment of 48 KD of waste water. The SIT
without any ETP/STP. It also indicates one D.G. Set without acoustic enclosure. It shows five restaurants in operation with the total seating capacity of 350 odd seats.
The two crucial issues of lack of treatment facility of waste water generated by them, and for operating without Consent to Establish for nine years does not appear to be understood by the unit despite
report indicates built up area is 14,700 sqm with waste water of 48 KLD and without any ETP/STP. It also indicates one D.G. Set without acoustic enclosure. It shows five restaurants in operation with the total seating capacity of 350 odd seats.
The two crucial issues of lack of treatment facility of waste water generated by them, and for operating without Consent
repeated clarifications. The unit still wants to take cover of Consent to Establish issued to HUDCO in 2000 which clearly indicates waste water generation of much lesser magnitude than what is done by Ansal Plaza alone.
Therefore, a carefully drafted communication has to be issued to the unit indicating the deficiencies pointed out by SIT, incorporating why the Consent
to Establish for nine years does not appear to be understood by the unit despite repeated clarifications. The unit still wants to take cover of Consent to Establish issued to HUDCO in 2000 which clearly indicates waste water generation of much lesser magnitude than what is done by Ansal Plaza alone.
Therefore, a carefully drafted communication has
to Establish of HUDCO is not applicable in their case and also highlighting the water act clearly indicating that the polluter is supposed to treat the polluted water before releasing it in the drain. This communication should be in the shape of letter to be sent by 29.07.2008 and must ask the unit to file an affidavit in its response within 14 days. Call on 12.08.2008.
to be issued to the unit indicating the deficiencies pointed out by SIT, incorporating why the Consent to Establish of HUDCO is not applicable in their case and also highlighting the water act clearly indicating that the polluter is supposed to treat the polluted water before releasing it in the drain. This communication should be in the shape of letter to be sent by
In addition to above, HUDCO’s consent issued in 2000 may be carefully studied and put up on file administratively to find out the jurisdiction its cover and the extent of air and water emission it covers for itself and it’s constituent units, by 12.08.2008. 13.08.2008Final reminder be issued to Ansal Plaza. Call on 10.09.2008.
29.07.2008 and must ask the unit to file an affidavit in its response within 14 days. Call on 12.08.2008. In addition to above, HUDCO’s consent issued in 2000 may be carefully studied and put up on file administratively to find out the jurisdiction its cover and the extent of air and water emission it covers for itself and it’s constituent units, by 12.08.2008. 13.08.200
8Final reminder be issued to Ansal Plaza. Call on 10.09.2008.
110 3 37 39 SC-37
Sothern Park, D-
2 District Center Saket, New Delhi
Not applied
Not applied
N.A N.A N.A N.A 17.04.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of
Inspection report of SIT to be discussed.
10.09
17.04.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and
Sothern Park,Taneja Developers & Infrastructure Ltd,
9, Kastur
ba Ghand
hi Marg, New Delhi-
01
_ _ The unit has not replied to the notice of DPCC letter dated 04.06.2008, SIT to inspect and report. Call on 31.07.2008.
31.07
SIT
construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 01.05.2008Call on 14.05.2008. 23.5.08Repeat dispatch of notice of 17.04.2008 by hand at the site. Call on 11.06.2008. 26.06.2008The unit has not replied to the notice of DPCC letter dated 04.06.200
completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 01.05.2008Call on 14.05.2008. 23.5.08Repeat dispatch of notice of 17.04.2008 by hand at the site. Call on 11.06.2008. 26.06.2008The unit has not replied to the notice of DPCC
8, SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT report has noted certain deficiencies which must be issued by way of the notice for correction. Call for personal hearing on 20.08.2008 at 8.00 PM. 21.08.2008The unit has been trying to avoid the notice of DPCC for a long time. It has not replied to the deficiencies pointed out by SIT. The CMC deliberate
letter dated 04.06.2008, SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT report has noted certain deficiencies which must be issued by way of the notice for correction. Call for personal hearing on 20.08.2008 at 8.00 PM. 21.08.2008The unit has been trying to avoid the notice of DPCC for a long time. It has not replied to the
d on the issue and felt that this is the fit case of notice for closure and the notice must be issued without waiting for the minutes. Call on 10.09.2008. Meanwhile, air, noise & water monitoring as per procedure may be conducted and the test reports be submitted on 10.09.2008.
deficiencies pointed out by SIT. The CMC deliberated on the issue and felt that this is the fit case of notice for closure and the notice must be issued without waiting for the minutes. Call on 10.09.2008. Meanwhile, air, noise & water monitoring as per procedure may be conducted and the test reports be submitted on 10.09.2008.
85 3 12 40 SC-12
Amazing Realtors Ltd (Office Complex &
Ec accorded by MOEF on 02.11.07.
05.09.2007
22880 sqm
MCD-150 KLD / GW - Nil / WW - 65 KLD
65 Cr. Oct, 2007 11.03.2008No action as of now.
Unit filed writ before Hon'ble High
11.12
11.03.2008No action as of now.
Amazing Realtors Ltd,F-38/2,
Y A 23388 39211
04.07
Shopping Mall Namely Splendor Forum)Plot no -3, DDA District Centre, Jasola
Check form the site of MOEF
17.04.2008Matter is under consultation at the highest levels. 28.5.08Move application through Sh. Prem Kumar, Advocate in the Supreme Court for enforcing the DPCC order and getting Delhi High Court order vacated. Call on 03.07.2008. 13.08.2008Call on 11.12.2008.
Court.Case was heard by the High Court on 04.8.08 and the same has been adjourned on 11.12.2008
17.04.2008Matter is under consultation at the highest levels. 28.5.08Move application through Sh. Prem Kumar, Advocate in the Supreme Court for enforcing the DPCC order and getting Delhi High Court order vacated. Call on 03.07.2008. 13.08.2008Call on 11.12.2008.
Ph-II, Okhla Industrial Area, New Delhi
12 1 12 41 SA-12
Vardhman Land Developers Private Limited Pushpanjali
Built up area is 18751.134 sqm.
12.12.2007
18815.529Sqm
125KLD(GW)/Domestic eff.-85KLD(STP)
44.14crores
25.3.04 Issue fresh letter for environmental clearance along with approved
Letter for adequacy report of STP and Affidav
17.09
Issue fresh letter for environmental clearance along with
Vardhman Land Developers Private Limited
D A Not Reported
24473 39428 Call the unit for personal hearing on 18.07.2008 at
31.07
Promoters Private Limited Construction of TDI Mall , Plot no 11, Shivaji Place, District Centre, Rajouri Garden, New Delhi
architectural drawing. Case to be put up on 25.03.2008. 03.4.08MS to study file and take up on 10.04.2008. 17.04.2008With comments of MS file be submitted administratively for decision on 21.04.2008. 21.05.2008The unit has 04 D.G. Sets. Ask the unit to file latest noise monitoring reports. Unit has 60 KLD STP in operation. Ask the
it about extent of construction issued on 28-05-08Reply received.
approved architectural drawing. Case to be put up on 25.03.2008. 03.4.08MS to study file and take up on 10.04.2008. 17.04.2008With comments of MS file be submitted administratively for decision on 21.04.2008. 21.05.2008The unit has 04 D.G. Sets. Ask the unit to file latest noise monitoring reports. Unit has 60 KLD
Pushpanjali Promoters Private Limited ,9, Kasturba Ghandhi Marg,New Delhi-01
8.00 PM indicating the documents still not provided.
unit to file adequacy report. Ask the unit to file an affidavit about the extent of construction done by the unit as on 07.07.2004 with supporting documents. Call on 25.06.2008. 25.06.2008Call the unit for personal hearing on 18.07.2008 at 8.00 PM indicating the documents still not provided. 17.07.2008The unit came for personal hearing today. It seeks 15 days time
STP in operation. Ask the unit to file adequacy report. Ask the unit to file an affidavit about the extent of construction done by the unit as on 07.07.2004 with supporting documents. Call on 25.06.2008. 25.06.2008Call the unit for personal hearing on 18.07.2008 at 8.00 PM indicating the documents still not provided. 17.07.2008The unit came for
to take the shopkeepers association on board for meeting on environmental legislations in the future. SIT report indicates groundwater drawl of 25 KLD without CGWA clearance Let the unit get the CGWA clearance by 31.07.2008 and the case will be heard on that day. Let the unit also file the noise monitoring report of D.G. Sets and the adequacy report of STP by 31.07.2008. Call on
personal hearing today. It seeks 15 days time to take the shopkeepers association on board for meeting on environmental legislations in the future. SIT report indicates groundwater drawl of 25 KLD without CGWA clearance Let the unit get the CGWA clearance by 31.07.2008 and the case will be heard on that day. Let the unit also file the noise monitoring report
31.07.2008. 31.07.2008 The unit has not come for personal hearing today and made a request to hear the case on 12.08.2008 where another case of the same company in the name of Brighways Housing & Land Development has been scheduled. Call for personal hearing on 12.08.2008 at 5.15 PM. 13.08.2008The unit has not attended the meeting and submitted
of D.G. Sets and the adequacy report of STP by 31.07.2008. Call on 31.07.2008. 31.07.2008 The unit has not come for personal hearing today and made a request to hear the case on 12.08.2008 where another case of the same company in the name of Brighways Housing & Land Development has been scheduled. Call for personal hearing on 12.08.2008 at 5.15 PM.
a representation requesting for postponement of the hearing. Call for personal hearing on 20.08.2008, at 09.30 as a last and final opportunity. 21.08.2008The unit came for personal hearing. This mall does not require Environmental Clearance but has been in operation without Consent to Establish for last one year. The total project cost is Rs. 44.14 crores. In similar
13.08.2008The unit has not attended the meeting and submitted a representation requesting for postponement of the hearing. Call for personal hearing on 20.08.2008, at 09.30 as a last and final opportunity. 21.08.2008The unit came for personal hearing. This mall does not require Environmental Clearance but has been in operation without
cases, the CMC has levied damages of 1 % of the project cost and 2 % of the project cost for Bank Guarantee which in present case comes to damages as cash penalty of Rs. 44 Lakhs and Bank Guarantee of Rs. 88 Lakhs. The aforesaid damages as cash penalty and Bank Guarantee valid for three years be filed by 17.09.2008. Call on 17.09.2008.
Consent to Establish for last one year. The total project cost is Rs. 44.14 crores. In similar cases, the CMC has levied damages of 1 % of the project cost and 2 % of the project cost for Bank Guarantee which in present case comes to damages as cash penalty of Rs. 44 Lakhs and Bank Guarantee of Rs. 88 Lakhs. The aforesaid damages as cash penalty and Bank Guarantee valid for three
years be filed by 17.09.2008. Call on 17.09.2008.
13 1 13 42 SA-13
Ess Cee & Associates (India)Pvt Ltd Construction of Paragon Mall , Cinema Plot no 2, District Centre, Shivaji Place, Near Raja Garden Crossing, New Delhi
Built up area is 5293.164 sqm.
12.2.07
15883.104 Sqm
75Kld/disp-
50Kld(STP)
41.44 11.1.05 Issue fresh letter for environmental clearance along with approved architectural drawing. Case to be put up on 25.03.2008. 03.4.08Sh. M. Dwarkanath, SSO to study file and take up on 10.04.2008. 17.04.2008Despite clear instructions, unit has not filed the completion certificate and may be directed to
Submit this file administratively after examining all the points communicated to the unit.
17.09
Issue fresh letter for environmental clearance along with approved architectural drawing. Case to be put up on 25.03.2008. 03.4.08Sh. M. Dwarkanath, SSO to study file and take up on 10.04.2008. 17.04.2008Despite clear instructions, unit has not filed the completion certificate
Ess Cee & Associates (India)Pvt Ltd,9, Kasturba Ghandhi Marg, New Delhi-02
D A Not Reported
24472 39428 The unit has filed a reply in response to the SCN dated 28.05.2008. The unit has not provided the information on CGWA clearance for ground water through bore
31.07
PH
do so immediately by 30.04.2008. File Environmental Clearance by 30.04.2008. Call on 30.04.2008. 01.05.2008SIT to inspect & report by 21.05.2008. 21.05.2008SIT to inspect and report by 23.05.2008. Call on 23.05.2008. 23.05.2008In view of the deficiencies found by the SIT w.r.t. drawl of ground water without permissio
and may be directed to do so immediately by 30.04.2008. File Environmental Clearance by 30.04.2008. Call on 30.04.2008. 01.05.2008SIT to inspect & report by 21.05.2008. 21.05.2008SIT to inspect and report by 23.05.2008. Call on 23.05.2008. 23.05.2008In view of the deficiencies found by the SIT w.r.t. drawl of ground
-well found by SIT. The unit claims that the STP fully functional although SIT did not find it so. The unit must file adequacy report immediately. The unit claims it will install the filter press for the
n, no treatment of waste water, non installation of Rain Water Harvesting Structure and release of sludge & waste water in the open drain, unit has clearly violated the provisions of the Water Act. The Committee felt that it is a fit case for issuing a notice for closure u/s 33(A) of the Water Act.
In view of the above, the properly drafted notice may be issued immediate
water without permission, no treatment of waste water, non installation of Rain Water Harvesting Structure and release of sludge & waste water in the open drain, unit has clearly violated the provisions of the Water Act. The Committee felt that it is a fit case for issuing a notice for closure u/s 33(A) of the Water Act.
In view of the above, the properly drafted
sludge and this must be confirmed soon. No Rain Water Harvesting Structure found by SIT although the unit claims to have provided one in terms of pit. Since there are several deficiencies
ly. Call on 18.06.2008. 18.06.2008The unit has filed a reply in response to the SCN dated 28.05.2008. The unit has not provided the information on CGWA clearance for ground water through bore-well found by SIT. The unit claims that the STP fully functional although SIT did not find it so. The unit must file adequacy report immediately. The
notice may be issued immediately. Call on 18.06.2008. 18.06.2008The unit has filed a reply in response to the SCN dated 28.05.2008. The unit has not provided the information on CGWA clearance for ground water through bore-well found by SIT. The unit claims that the STP fully functional although SIT did not find it so. The unit must
still, the unit may be called for personal hearing at 5.00 PM on 11.07.2008.
unit claims it will install the filter press for the sludge and this must be confirmed soon. No Rain Water Harvesting Structure found by SIT although the unit claims to have provided one in terms of pit. Since there are several deficiencies still, the unit may be called for personal hearing at 5.00 PM on 11.07.2008. 11.07.2008The unit came for
file adequacy report immediately. The unit claims it will install the filter press for the sludge and this must be confirmed soon. No Rain Water Harvesting Structure found by SIT although the unit claims to have provided one in terms of pit. Since there are several deficiencies still, the unit may be called for personal hearing at 5.00 PM on 11.07.2008.
personal hearing today. The unit has applied for CTE on 12.02.07, but never applied for the Environment Clearance .The unit claimed that it is not covered under the EIA notification in view of its built up area less than 20000 sq.mts.The SIT report indicates that the unit has completed its construction by 23.02.2007 . SIT also indicates that the unit is
11.07.2008The unit came for personal hearing today. The unit has applied for CTE on 12.02.07, but never applied for the Environment Clearance .The unit claimed that it is not covered under the EIA notification in view of its built up area less than 20000 sq.mts.The SIT report indicates that the unit has completed its construction by 23.02.200
drawing water from the ground and the total consumption of water is 75 KLD. The unit has not filed any CGWA clearance for this. The unit requested for time upto 17.07.2008 to consult its Board regarding payment of Cash Penalty and Bank Guarantee . If the unit files the cash penalty of 1.5 % of the project cost of Rs 41.44 Crores i.e. Rs. 60 Lakhs, and 1.5 % of the project cost as
7 . SIT also indicates that the unit is drawing water from the ground and the total consumption of water is 75 KLD. The unit has not filed any CGWA clearance for this. The unit requested for time upto 17.07.2008 to consult its Board regarding payment of Cash Penalty and Bank Guarantee . If the unit files the cash penalty of 1.5 % of the project cost of Rs 41.44
Bank Guarantee of another Rs. 60 Lakhs as has been stipulated in case where no Environmental Clearance and no Consent to Establish existed, by 17.07.2008, the case may be put up administratively for decision. Call on 17.07.2008. 17.07.2008The unit has filed a letter seeking 15 days time to consult the shopkeepers association as all the shops
Crores i.e. Rs. 60 Lakhs, and 1.5 % of the project cost as Bank Guarantee of another Rs. 60 Lakhs as has been stipulated in case where no Environmental Clearance and no Consent to Establish existed, by 17.07.2008, the case may be put up administratively for decision. Call on 17.07.2008. 17.07.2008The unit has filed a letter seeking 15 days time to
have been sold. Call on 31.07.2008 for personal hearing at 8.15 PM. 31.07.2008 The unit has filed a letter indicating that it has paid a total penalty of Rs. 4.44 crores to MCD along with details of such penalty. This penalty is mainly in the nature of composition fee which implies building construction without approval. In view of the large penalty already
consult the shopkeepers association as all the shops have been sold. Call on 31.07.2008 for personal hearing at 8.15 PM. 31.07.2008 The unit has filed a letter indicating that it has paid a total penalty of Rs. 4.44 crores to MCD along with details of such penalty. This penalty is mainly in the nature of composition fee which implies
paid to MCD and the similar case has been cleared by the CMC, the Committee deliberated on this issue and felt that the total damages of 3 % of the project cost for unit running without Consent to Establish / Environmental Clearance for certain period of time after completion should not be changed. However, the Committee felt that the unit should
building construction without approval. In view of the large penalty already paid to MCD and the similar case has been cleared by the CMC, the Committee deliberated on this issue and felt that the total damages of 3 % of the project cost for unit running without Consent to Establish / Environmental Clearance for certain period of
get some relief on account of the penalty already paid to MCD amounting to Rs. 4.44 crores. The Committee finally decided that the unit may be asked to pay damages of Rs. 20 Lakhs and Bank Guarantee of Rs. 1 crores valid for three years to comply with all environmental legislations. Call on 20.08.2008 for compliance. 21.08.2008Issue final
time after completion should not be changed. However, the Committee felt that the unit should get some relief on account of the penalty already paid to MCD amounting to Rs. 4.44 crores. The Committee finally decided that the unit may be asked to pay damages of Rs. 20 Lakhs and Bank Guarantee of Rs. 1 crores valid for three years to comply
reminder for compliance of letter dated 12.08.2008, failing which orders for closure will be issued. Call on 17.09.2008.
with all environmental legislations. Call on 20.08.2008 for compliance. 21.08.2008Issue final reminder for compliance of letter dated 12.08.2008, failing which orders for closure will be issued. Call on 17.09.2008.
23 1 23 43 SA-23
Vishal Retail Ltd., 1/1 Tilak Nagar, New Delhi
Not submitted
Not submit
ted
_ _ _ _ 01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New
_ _ MS may write to Vishal Retail Ltd. to confirm the Wat
31.07
with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14
and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two
Delhi-37
er Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm.Unit reports built up area 2818 sqm. It is silent on ground weat
malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm.Unit reports built up area 2818 sqm. It is silent on ground weater drawl and acoustic
details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm.Unit reports built up area 2818 sqm. It is silent on
er drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
24 1 24 44 SA-24
Vishal Retail Ltd., 156 out of Khadra No. 83/14, Village Hastsal, Colony
Not submitted
Not submit
ted
_ _ _ _ 01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitorin
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahip
_ _ MS may write to Vishal Retail Ltd. to conf
31.07
G-1 Block, Uttam Nagar, New Delhi
for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for
g reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administr
alpur Extn,New Delhi-37
irm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 4400 sq. feet It is silen
these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 4400 sq. feet It is silent
atively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up
t on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
area 4400 sq. feet It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
25 1 25 45 SA-25
Vishal Retail Ltd., Palmohan Plaza-39, Block- A,2
Not submitted
Not submit
ted
_ _ _ _ 01.05.2008Issue a letter to Vishal Retail Ltd. to file
As decided, letter issued on 19-08-08.Reply awaited
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to
Vishal Retail Ltd.,RZ-A-95&96, Road No-4,
_ _ MS may write to Vishal Retail
31.07
Rajouri Garden, New Delhi
a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed
. file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS
Gali no-09,Mahipalpur Extn,New Delhi-37
Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 4500 sq.
administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up
has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm.
feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
area 4500 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
Unit reports built up area 4500 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
26 1 26 46 SA-26
Vishal Retail Ltd., B-374, Meera
Not submitted
Not submit
ted
_ _ _ _ 01.05.2008Issue a letter to
As decided, letter issued on 19-
17.09
01.05.2008Issue a letter to
Vishal Retail Ltd.,RZ-A-95&96
_ _ MS may write to Vish
31.07
Bagh, Paschim Vihar, New Delhi
Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. According
08-08.Reply awaited.
Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge
, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
al Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up
ly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm.
figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before
area 10087 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
Unit reports built up area 10087 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
31.07.2008 and confirm. Unit reports built up area 10087 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
27 1 27 47 SA- Vishal Not Not _ _ _ _ As 17.0 Vishal _ _ MS 31.0
27 Retail Ltd., 2, Road No. 85, Club Road, Punjabi Bagh(W), New Delhi
submitted submitted
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste
decided, letter issued on 19-08-08.Reply awaited.
9 01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been
Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit
7
water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.05.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do
silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.05.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so
reports built up area 144 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
so before 31.07.2008 and confirm. Unit reports built up area 144 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 144 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on
17.09.2008
28 1 28 48 SA-28
Vishal Retail Ltd., 10209/10210, Padam Singh Road, karol Bagh, Delhi
Not submitted
Not submit
ted
_ _ _ _ 01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
_ _ MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and
31.07
been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.05.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not
provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.05.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping
confirm. Unit reports built up area 20000 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 20000 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre.
Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 20000 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008
Call on 17.09.2008
Issue notice for clousre. Call on 17.09.2008
29 2 1 49 SB-1
Paliwal Developers Ltd (DLF), Galleria shopping Mall Plot no 1 B Mayur Vihar
Formal order not provided. Only website reveals the project is clear on 06.06.2007.
08.02.2007
12324
139(MCD)+GW wil be used as supplmentry source./42(WW)
56.06Cr. /
106.12 Cr.
10.03.2008The website of MOE&F indicates environmental clearance cleared on 06.06.2007 whereas the affidavit says area less than 20,000 sq.mts and no environmental clearance required. If the environmental clearance has been given, let the unit file a copy of the environmental clearance and also the approved architectu
Call for personal hearing on 10.09.2008 at 8:00 PM.
17.09
10.03.2008The website of MOE&F indicates environmental clearance cleared on 06.06.2007 whereas the affidavit says area less than 20,000 sq.mts and no environmental clearance required. If the environmental clearance has been given, let the unit file a copy of the environmental clearance and also
Paliwal Developers Ltd (DLF), DLF Centre,
9th Floor, Sansad Marg, New Delhi-01
A 39052
20623 39121 Based on the SIT report, water flow chart may be asked from the unit and also the permission from CGWA for ground water drawl. With these two documents, ask the unit to come for personal hearing on 18.07.2008 at 6.30 PM.
20.08
ral plan and the completion certificate since the construction has been reportedly completed. 11.04.2008Unit claims that it is not covered by the EIA notification of September, 2006 and has been cleared by the MEOF through the website entry copy of which has been filed. Website entries are not admissible evidence of Environmental Clearance
the approved architectural plan and the completion certificate since the construction has been reportedly completed. 11.04.2008Unit claims that it is not covered by the EIA notification of September, 2006 and has been cleared by the MEOF through the website entry copy of which has been filed. Website entries are not admissibl
and the unit may be asked to file the formal Environmenal Clearance. Separately, MOEF may also be asked to clarify and send us the formal clearance.
Since Prof. Gutpa had inspected the nearby mall and seen this from outside with the observation that it appears to be covered by the EIA notification, the unit may also be asked to comply with our earlier directions of filing
e evidence of Environmental Clearance and the unit may be asked to file the formal Environmenal Clearance. Separately, MOEF may also be asked to clarify and send us the formal clearance.
Since Prof. Gutpa had inspected the nearby mall and seen this from outside with the observation that it appears to be covered by the EIA notificatio
the clear copy of building plans and completion certificate which will clearly establish the built up area and the applicability of EIA notifcation of September, 2006. Take up on 30.04.2008. 01.05.2008Call on 14.05.2008. 23.05.2008The unit has filed no details about water drawl. It has also not provided any details of the STP for 25 KLD. Let
n, the unit may also be asked to comply with our earlier directions of filing the clear copy of building plans and completion certificate
which will clearly establish the built up area and the applicability of EIA notifcation of September, 2006. Take up on 30.04.2008. 01.05.2008Call on 14.05.2008. 23.05.2008The unit has filed no details
the unit furnish an adequacy report of the STP. Let the unit also confirm on affidavit the date of start of construction & date of completion of construction. Call on 25.06.2008. 28.5.08Over and above the decision of the committee of 23.05.2008 committee felt that SIT should inspect and report to CMC on 25.06.2008. Call on 25.06.2008. 25.06.200
about water drawl. It has also not provided any details of the STP for 25 KLD. Let the unit furnish an adequacy report of the STP. Let the unit also confirm on affidavit the date of start of construction & date of completion of construction. Call on 25.06.2008. 28.5.08Over and above the decision of the committee of 23.05.2008 committee felt that SIT
8Based on the SIT report, water flow chart may be asked from the unit and also the permission from CGWA for ground water drawl. With these two documents, ask the unit to come for personal hearing on 18.07.2008 at 6.30 PM. 17.07.2008A letter has been received from DLF stating that the unit is busy w.r.t. presentations before Expert Appraisal Committees of MOEF,
should inspect and report to CMC on 25.06.2008. Call on 25.06.2008. 25.06.2008Based on the SIT report, water flow chart may be asked from the unit and also the permission from CGWA for ground water drawl. With these two documents, ask the unit to come for personal hearing on 18.07.2008 at 6.30 PM. 17.07.2008A letter has been
Tamil Nadu and Andhra Pradesh. He has, therefore, sought postponement of the personal hearing. The date of his preoccupation in his chart indicates that he is free on 24.07.2008 which is the next date of CMC meeting. Call on 24.07.2008 at 5.45 PM for personal hearing. 24.07.2008The unit came for personal hearing today. Technical points were discussed with the unit but
received from DLF stating that the unit is busy w.r.t. presentations before Expert Appraisal Committees of MOEF, Tamil Nadu and Andhra Pradesh. He has, therefore, sought postponement of the personal hearing. The date of his preoccupation in his chart indicates that he is free on 24.07.2008 which is the next date of CMC meeting. Call on 24.07.2008 at 5.45 PM for personal
the representative of the unit did not provide any details on the following counts:-
(a) Permission from CGWA for ground water drawl was not submitted.(b) Adequacy report of the ETP had not been provided.
The unit was therefore asked to submit these documents urgently to enable CMC to take appropriate action. Call on 20.08.2008.
hearing. 24.07.2008The unit came for personal hearing today. Technical points were discussed with the unit but the representative of the unit did not provide any details on the following counts:-
(a) Permission from CGWA for ground water drawl was not submitted.(b) Adequacy report of the ETP had not been provided.
20.08.2008The unit has not complied with the directions of CMC dated 24.07.2008. Issue final reminder to do so by 17.09.2008 and ensure that the mall does not commence its operation without Consent to Establish and Consent to Operate. If the unit does not comply with the DPCC directions, DPCC will be constraint to issue notice for closure. Call on 17.09.200
The unit was therefore asked to submit these documents urgently to enable CMC to take appropriate action. Call on 20.08.2008. 20.08.2008The unit has not complied with the directions of CMC dated 24.07.2008. Issue final reminder to do so by 17.09.2008 and ensure that the mall does not commence its operation without Consent to Establish and
8. Consent to Operate. If the unit does not comply with the DPCC directions, DPCC will be constraint to issue notice for closure. Call on 17.09.2008.
30 2 2 50 SB-2
Y.M.C Buildmore pvt ltd construction of Commercial Complex at plot no 12 Laxmi nagar Distt Centre (V3S Mall)
CTE issued
on 18.04.2008.Applied for CTO on
14.07.2008
39093.14 sq m
MCD-165 KLD GW-40 KLD DIS.-164 KLD
165 crore
10.03.2008Since an attested copy has been received from the MOEF saying action may be taken, this is a development over and above the Committee meeting decision on 05.02.2008. Like other cases an opportunit
Consent to establish issued Unit has applied for CTO on 14.07.2008 vide I.D. No. 26445 in the name of Gahoi Buildwell Ltd. (Commercial Complex). SIT
17.09
10.03.2008Since an attested copy has been received from the MOEF saying action may be taken, this is a development over and above the Committee meeting decision on 05.02.2008. Like other cases an opportuni
Y.M.C Buildmore Pvt Ltd , 701, Mercantile House 15 K.G Marg, New Delhi - 110001.
A 39326
21763 39244 Z
y of being heard may be given to the unit on 25.03.2008 at 5.00 PM. 28.03.2008Letter be issued seeking penalty and BG as was done in the first case i.e. M/s Splendor Forum. 11.04.200815 days elapsing on 19.04.2008. Take up on 23.04.2008. 17.04.2008A letter was received from M/s Y.M.C. Buildmore Pvt. Ltd. that he has filed a cash
report to be discussed.
ty of being heard may be given to the unit on 25.03.2008 at 5.00 PM. 28.03.2008Letter be issued seeking penalty and BG as was done in the first case i.e. M/s Splendor Forum. 11.04.200815 days elapsing on 19.04.2008. Take up on 23.04.2008. 17.04.2008A letter was received from M/s Y.M.C. Buildmore Pvt.
penalty of Rs. 80 Lakh and Bank Guarantee of Rs. 80 Lakh and despite clear order of CMC dated 28.03.2008, the Consent to Establish has not been issued by the concerned EE for which his written explanation may be submitted on file by MS on 21.04.2008. If the reply is not found satisfactory, an entry will be made in his ACR.
For not violating the CMC decisions, MS must once
Ltd. that he has filed a cash penalty of Rs. 80 Lakh and Bank Guarantee of Rs. 80 Lakh and despite clear order of CMC dated 28.03.2008, the Consent to Establish has not been issued by the concerned EE for which his written explanation may be submitted on file by MS on 21.04.2008. If the reply is not found satisfactory, an entry will be made in his ACR.
again issue a clear circular to all members of CMC.
In this case, EE will call the unit on 18.04.2008 and issue the Consent to Establish without fail and confirm the same on file.
Cash penalty & BG submitted. Accordinlgy, consent issued on 18.04.2008. 28.5.08No action. 31.07.2008Ask SIT to inspect w.r.t. construction phase
For not violating the CMC decisions, MS must once again issue a clear circular to all members of CMC.
In this case, EE will call the unit on 18.04.2008 and issue the Consent to Establish without fail and confirm the same on file.
Cash penalty & BG submitted. Accordinlgy, consent issued on 18.04.2008. 28.5.08No action.
& operation phase conditions of Environmental Clearance and for Consent to Operate application. Call on 20.08.2008. 21.08.2008SIT inspection has found certain deficiencies on the item-wise compliance of Environmental Clearance conditions. These deficiencies may be indicated to the unit for correction by 17.09.2008. Call on 17.09.2008.
31.07.2008Ask SIT to inspect w.r.t. construction phase & operation phase conditions of Environmental Clearance and for Consent to Operate application. Call on 20.08.2008. 21.08.2008SIT inspection has found certain deficiencies on the item-wise compliance of Environmental Clearance conditions. These deficiencies may be indicated to the unit
for correction by 17.09.2008. Call on 17.09.2008.
31 2 3 51 SB-3
Cross River Mall, 9B & 9 C, Central Business Shahdara, New Delhi-95
Not obtained
07.1.08
36109.67
By tanker
/71.2(ww)
121.76Cr.
2006 10.03.2008The unit claims it is not covered by the 2004 notification, but have not adduced any proof of such exemption. The unit may therefore be asked to file an affidavit adducing proof of his assertion.
The unit started construction in 2004 and did not bother to apply for CTE till 07.01.2008. In the same
BG of Rs. 2.7 crores and remaining cash peanlty of Rs. 35 Lakhs not yet deposited.
17.09
10.03.2008The unit claims it is not covered by the 2004 notification, but have not adduced any proof of such exemption. The unit may therefore be asked to file an affidavit adducing proof of his assertion.
The unit started construction in 2004 and did not bother to apply for CTE till 07.01.2008. In the same
Cross River Mall,STC Developers P Ltd, N-49, IST Floor, Connaught Place, New Delhi
A 38869
24680 39630 Noise monitoring report of one D.G. Set which was not filed be filed immediately. Call for personal hearing on 11.07.2008 at 5.30 PM.
17.07
affidavit unit may be asked to explain how and why he has failed to file the CTE application. Let the unit be given an opportunity of being heard on 25.03.2008 at 6.00 PM and the unit may be directed to file the above affidavit before that day. 03.04.2008The unit may be asked to file an affidavit with concrete proof that it had come upto the plinth level on 07.07.2004 and therefore was not
affidavit unit may be asked to explain how and why he has failed to file the CTE application. Let the unit be given an opportunity of being heard on 25.03.2008 at 6.00 PM and the unit may be directed to file the above affidavit before that day. 03.04.2008The unit may be asked to file an affidavit with concrete proof that it had come upto the plinth level on 07.07.2004 and
hit by the notification of MOEF dated 07.07.2004 regarding EIA.
MS may separately check with DDA the basis of the compounding fee to ascertain the extent of construction which corresponds to the compounding fee of Rs. 1.17 Lakh. Based on these documents and findings, a decision will be taken about this case in the CMC on 23.04.2008. 11.04.2008Call on
therefore was not hit by the notification of MOEF dated 07.07.2004 regarding EIA.
MS may separately check with DDA the basis of the compounding fee to ascertain the extent of construction which corresponds to the compounding fee of Rs. 1.17 Lakh. Based on these documents and findings, a decision will be taken about this case in the CMC on
23.04.2008 with response of our notice. 01.05.2008Reminder may be issued to DDA for their response. Consent to Establish has been applied and the waste water discharge is 71 KLD and 4 D.G. Sets are installed with capacity of 750 KVA. Call on 03.06.2008 with test reports of D.G. Sets. 28.5.08The unit has asked for 10 days time to submit noise monitorin
23.04.2008. 11.04.2008Call on 23.04.2008 with response of our notice. 01.05.2008Reminder may be issued to DDA for their response. Consent to Establish has been applied and the waste water discharge is 71 KLD and 4 D.G. Sets are installed with capacity of 750 KVA. Call on 03.06.2008 with test reports of D.G. Sets. 28.5.08
g reports of D.G. Sets. In the meantime the DDA report may also be pursued. Call on 18.06.2008. 18.06.2008Noise monitoring report of one D.G. Set which was not filed be filed immediately. Call for personal hearing on 11.07.2008 at 5.30 PM. 11.07.2008The unit came for personal hearing today. It has effluent discharge of 71
The unit has asked for 10 days time to submit noise monitoring reports of D.G. Sets. In the meantime the DDA report may also be pursued. Call on 18.06.2008. 18.06.2008Noise monitoring report of one D.G. Set which was not filed be filed immediately. Call for personal hearing on 11.07.2008 at 5.30 PM. 11.07.2008The unit came for
KLD which appears to be both trade effluent and domestic effluent in view of the number of food courts in mall. The unit has no sewage treatment facility at present and therefore prima-facie, it has been discharging 71 KLD effluent into the drain for the last two years since it was in operation and further two years when it was being constructed. In such
personal hearing today. It has effluent discharge of 71 KLD which appears to be both trade effluent and domestic effluent in view of the number of food courts in mall. The unit has no sewage treatment facility at present and therefore prima-facie, it has been discharging 71 KLD effluent into the drain for the last two years since it was in operation
cases where the unit has not taken Consent to Establish under Air Act and Water Act from Delhi Pollution Control Committee and built the whole mall and started operating it, the Committee in some recent cases has levied damages of 1 % of the total project cost as cash penalty and 2 % of the total project cost as Bank Guarantee. If the unit files this by 14.07.200
and further two years when it was being constructed. In such cases where the unit has not taken Consent to Establish under Air Act and Water Act from Delhi Pollution Control Committee and built the whole mall and started operating it, the Committee in some recent cases has levied damages of 1 % of the total project cost as cash penalty
8, the file may be submitted administratively for decision. If the unit does not file the cash penalty and Bank Guarantee by 14.07.2008, SIT will inspect the premises and submit the report by 17.07.2008. The affidavit filed by Sh. Satish Chand Jain on 07.01.2008 indicates the total project cost as Rs 121.76 Crores whereas the project report submitte
and 2 % of the total project cost as Bank Guarantee. If the unit files this by 14.07.2008, the file may be submitted administratively for decision. If the unit does not file the cash penalty and Bank Guarantee by 14.07.2008, SIT will inspect the premises and submit the report by 17.07.2008. The affidavit filed by Sh. Satish Chand Jain on
d by the unit through Perfect Solutions indicates the total project cost as 143.67 Crores. The unit will therefore have to file the said penalty on the following basis:-
(a) Submit proof of land cost from Land Owning Agency.(b) Submit proof of total construction cost including civil works, equipment cost and other miscellaneous accessories cost.
07.01.2008 indicates the total project cost as Rs 121.76 Crores whereas the project report submitted by the unit through Perfect Solutions indicates the total project cost as 143.67 Crores. The unit will therefore have to file the said penalty on the following basis:-
(a) Submit proof of land cost from Land Owning Agency.(b) Submit proof of
The project proponent has not filed supporting documents like Form “A” and any other documents to prove that construction was complete up to plinth level on 07.07.2004 and not submitted completion certificate. Call on 17.07.2008. 31.07.2008The unit appeared before CMC during the meeting. The unit claims total cost of the
total construction cost including civil works, equipment cost and other miscellaneous accessories cost.
The project proponent has not filed supporting documents like Form “A” and any other documents to prove that construction was complete up to plinth level on 07.07.2004 and not submitted completion certificate. Call on 17.07.200
project is Rs. 137 Crores and not Rs. 143.67 Crores since Rs. 6 Cores is on account of interest of the loan. The Committee accepts the figure of Rs. 137 Crores and calculates the damages of 1 % as Rs. 1.35 Crores rounding off to the nearest lakh. Similarly the Bank Guarantee of 2 % of the project cost, rounded off to the nearest lakh comes to Rs. 2.70 Cores. The unit
8. 31.07.2008The unit appeared before CMC during the meeting. The unit claims total cost of the project is Rs. 137 Crores and not Rs. 143.67 Crores since Rs. 6 Cores is on account of interest of the loan. The Committee accepts the figure of Rs. 137 Crores and calculates the damages of 1 % as Rs. 1.35 Crores rounding off to the
is allowed time upto 20.08.2008 to comply with these conditions. Call on 20.08.2008. 21.08.2008The unit has deposited Rs. 1 crore out of Rs. 1.35 crores total damages and no Bank Guarantee so far. It has already availed 40 days since 11.07.2008 and seeks time for another month for complying. Time allowed till 17.09.2008. Issue
nearest lakh. Similarly the Bank Guarantee of 2 % of the project cost, rounded off to the nearest lakh comes to Rs. 2.70 Cores. The unit is allowed time upto 20.08.2008 to comply with these conditions. Call on 20.08.2008. 21.08.2008The unit has deposited Rs. 1 crore out of Rs. 1.35 crores total damages and no Bank Guarantee so far.
final reminder for compliance. Call on 17.09.2008.
It has already availed 40 days since 11.07.2008 and seeks time for another month for complying. Time allowed till 17.09.2008. Issue final reminder for compliance. Call on 17.09.2008.
48 2 20 52 SB-20
Pragya Products Private Ltd, Construcion of Commercial Mall name Shop in Park at Plot no 2 Community Centre Blk B , Shalimar Bagh New Delhi ,
_ Original application dated 26/04/06 returned.
14884 (as informed)
20(GW)/ 16(WW)
40Cr. 2007.. 11.03.2008Ask him to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date
As per CMC decision dated 05.07.2008 & 07.07.2008, unit has filed cash penalty of Rs. 1 crore, BG of Rs. 1 crore and affidavit on
17.09
11.03.2008Ask him to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of constructi
Pragya Products Private Ltd, 63, Rama Marg, Najafgarh Road, New Delhi - 15.
N _ _ _ As soon as CTE is filed it should be placed in the CMC preferably on 24.07.2008.
Letter to the unit and MOEF be issued as approved on file. Call on 20.08.2008.
20.08
Pragya Products Private Ltd
of completion. Unit will also file approved architectural drawing. He must also file completion certificate from the concerned public authority by April CMC. 11.04.2008Issue a reminder to abide by the notice of 11.03.2008 fully, failing which the Committee will have to take further necessary action. 01.05.2008Call for Personal hearing on 14.05.200
07.07.2008 & 08.08.2008.As per approval of Chairman, closure directions dated 30.06.2008 have been revoked on 08.07.2008. Applied for CTE application.Letter issued.Reply awaited.
on & date of completion. Unit will also file approved architectural drawing. He must also file completion certificate from the concerned public authority by April CMC. 11.04.2008Issue a reminder to abide by the notice of 11.03.2008 fully, failing which the Committee will have to take further necessary action. 01.05.2008Call for Personal hearing
Call on 24.07.2008.
8 at 7.30 PM. 14.05.2008The unit appeared before the Committee today and filed some documents about the land cost, the completion certificate and some data about the floor area which is not in consonance with the MOEF record available with DPCC. The unit has neither filed the application for Consent to Establish nor appeared before MOEF to get the
on 14.05.2008 at 7.30 PM. 14.05.2008The unit appeared before the Committee today and filed some documents about the land cost, the completion certificate and some data about the floor area which is not in consonance with the MOEF record available with DPCC. The unit has neither filed the application for Consent to Establish nor appeared
Environmental Clearance and yet it started its construction as per its own admission in December, 2005 and completed in July, 2007 (letter of Sh. Rajeev Gupta, Sr. General Manger dated 31.03.2008). Therefore, a clear case of violation of all environmental legislations and smacks of total disregard for laws of the land.
The project total cost as per the record is Rs. 73.29
before MOEF to get the Environmental Clearance and yet it started its construction as per its own admission in December, 2005 and completed in July, 2007 (letter of Sh. Rajeev Gupta, Sr. General Manger dated 31.03.2008). Therefore, a clear case of violation of all environmental legislations and smacks of total disregard for laws of the land.
The project
crores. The unit seeks two days time to seek orders from its superior authorities about the penalty which can be imposed on the unit if at all DPCC decides not to close down the unit. Time allowed till 5.30 PM on 15.05.2008. 21.05.2008The unit represented by its General Manager (Legal), Sh. Birender Singh appeared and wanted a couple of days time as his directors
total cost as per the record is Rs. 73.29 crores. The unit seeks two days time to seek orders from its superior authorities about the penalty which can be imposed on the unit if at all DPCC decides not to close down the unit. Time allowed till 5.30 PM on 15.05.2008. 21.05.2008The unit represented by its General Manager (Legal), Sh. Birender Singh appeared
were not in town. In the last hearing on 15.05.2008, they had sought two days time but were given one week’s time as CMC meets only weekly. The representative had no clear directions from his bosses. The Committee deliberated on various options once again for over an hour and then gave a final offer of Rs. 6 crores as an upfront penalty in the form of Demand
and wanted a couple of days time as his directors were not in town. In the last hearing on 15.05.2008, they had sought two days time but were given one week’s time as CMC meets only weekly. The representative had no clear directions from his bosses. The Committee deliberated on various options once again for over an hour and then gave a final offer of
Draft to be filed within two days, failing which the Committee will take recourse as per law. Call on 23.05.2008. 23.05.2008The Committee deliberated on the proposed action against this unit for about one hour and decided to issue notice for closure immediately. The notice will incorporate the deficiencies found in inspection and monitoring report of waste
Rs. 6 crores as an upfront penalty in the form of Demand Draft to be filed within two days, failing which the Committee will take recourse as per law. Call on 23.05.2008. 23.05.2008The Committee deliberated on the proposed action against this unit for about one hour and decided to issue notice for closure immediately. The notice will
water status, noise & air pollution levels. Notice to be issued expeditiously. 11.6.2008The case of this unit, was taken up as a table agenda, being a major violator. The unit has replied and sought a personal hearing as it is not accepting the SIT report findings despite signature of the representative of the unit on the report. Call for personal hearing on 25.06.2008 at 5.00 PM.
incorporate the deficiencies found in inspection and monitoring report of waste water status, noise & air pollution levels. Notice to be issued expeditiously. 11.6.2008The case of this unit, was taken up as a table agenda, being a major violator. The unit has replied and sought a personal hearing as it is not accepting the SIT report findings despite signature of the
25.06.2008 Unit came for personal hearing today and claimed it had filed the complete Consent to Establish application and wanted to see DPCC’s file. The file was shown to him indicating when under what circumstances his Consent to Establish application was returned. Secondly, unit claimed that the inspection report was signed by its official who was ignorant
representative of the unit on the report. Call for personal hearing on 25.06.2008 at 5.00 PM. 25.06.2008 Unit came for personal hearing today and claimed it had filed the complete Consent to Establish application and wanted to see DPCC’s file. The file was shown to him indicating when under what circumstances his Consent to Establish application was
and that water and air testing should be done again by DPCC. The moment, the unit has signed the SIT report it loses its right to question it later and, therefore, the Committee did not agree with his suggestions. The unit then appealed for lenient penalty and after much deliberation, the Committee agreed to reduce the penalty to Rs. 3 crores and Bank Guarantee of Rs. 4 crores, failing which,
returned. Secondly, unit claimed that the inspection report was signed by its official who was ignorant and that water and air testing should be done again by DPCC. The moment, the unit has signed the SIT report it loses its right to question it later and, therefore, the Committee did not agree with his suggestions. The unit then appealed for lenient penalty and after much
appropriate action as per law will be taken. 11.07.2008As soon as CTE is filed it should be placed in the CMC preferably on 24.07.2008. Call on 24.07.2008. 24.07.2008Letter to the unit and MOEF be issued as approved on file. Call on 20.08.2008. 21.08.2008Call on 17.09.2008.
deliberation, the Committee agreed to reduce the penalty to Rs. 3 crores and Bank Guarantee of Rs. 4 crores, failing which, appropriate action as per law will be taken. 11.07.2008As soon as CTE is filed it should be placed in the CMC preferably on 24.07.2008. Call on 24.07.2008. 24.07.2008Letter to the unit and MOEF be issued as approved on file. Call on
20.08.2008. 21.08.2008Call on 17.09.2008.
49 2 21 53 SB-21
Mamram Majesty Mall , Plot no 2, Guru Harkishan Marg Road no 43, Pitampura New Delhi-83
_ 39692 4496.8
1.5(MCD)+8(GW)/ .5(WW)
10.7Cr. 39479 11.03.2008Unit claims that it is not covered under EIA notification. Ask him to file an affidavit for date of start of construction and copy of the approved architectural drawing. Unit may also be asked to file compliance of four conditions laid down by DDA. He must also file completion certificate
Letter issued on 08.07.2008Unit has submitted its reply on 22.07.2008 & informed that they have placed an order for noise monitoring of D.G. Set to DCE. As soon as they get it, the same will be submitted to DPCC. Unit
17.09
11.03.2008Unit claims that it is not covered under EIA notification. Ask him to file an affidavit for date of start of construction and copy of the approved architectural drawing. Unit may also be asked to file compliance of four conditions laid down by DDA. He must also file completio
Mamram Majesty Mall,
D-11, Udyog Nagar,
Peera Garhi, New Delhi - 41.
A 39479
24699 39692 Ask the unit operating the banquet hall in the name of M/s VNV at the same address to furnish the data required by CMC vide its meeting dated 21.05.2008. Call on 31.07.2008.
31.07
from the concerned public authority by April CMC. 11.04.2008SIT to inspect. Case to be taken up on 14.05.2008. 21.05.2008Unit has not given details of waste water discharge and the inspection report shows that the banquet hall of 200 seating capacity is running there necessitating an ETP. Two D.G. Sets are operating without acoustic enclosure.
has also requested to give one month time for the compliance of other formalities.
n certificate from the concerned public authority by April CMC. 11.04.2008SIT to inspect. Case to be taken up on 14.05.2008. 21.05.2008Unit has not given details of waste water discharge and the inspection report shows that the banquet hall of 200 seating capacity is running there necessitating an ETP. Two D.G. Sets are operating without
Ask the unit to do the following :(a) File the noise monitoring reports.(b) Install ETP and confirm.(c) Comply with a DDA condition of rain water harvesting.Call on 25.06.2008. 25.06.2008Ask the unit operating the banquet hall in the name of M/s VNV at the same address to furnish the data required by CMC vide its meeting dated 21.05.200
acoustic enclosure. Ask the unit to do the following :(a) File the noise monitoring reports.(b) Install ETP and confirm.(c) Comply with a DDA condition of rain water harvesting.Call on 25.06.2008. 25.06.2008Ask the unit operating the banquet hall in the name of M/s VNV at the same address to furnish the data required by CMC vide its meeting
8. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 6.30 PM. 21.08.2008The unit came for personal hearing today and pleaded for lenient view. The Committee deliberated on the issue and decided that he may be asked to file Bank Guarantee of Rs. 8 Lakhs valid for three years. Call on 17.09.2008.
Also ask M/S VNV which is
dated 21.05.2008. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 6.30 PM. 21.08.2008The unit came for personal hearing today and pleaded for lenient view. The Committee deliberated on the issue and decided that he may be asked to file Bank Guarantee of Rs. 8 Lakhs valid for three years. Call on 17.09.2008.
operating at the same address after buying the property from Mamram Majesty Mall ,to apply for Consent to Establish immediately. Call on 17.09.2008.
Also ask M/S VNV which is operating at the same address after buying the property from Mamram Majesty Mall ,to apply for Consent to Establish immediately. Call on 17.09.2008.
56 2 28 54 SB-28
Aggarwal Plaza (P) Ltd., Plot no 29 & 31, CBD Shahdara Commercial Complex, Shahdara, Delhi
Not obtained
18.06.2008
18000 (as per CTE)31000 (as per MOEF)
MCD - 40 KLD/ GW - 120 KLD / WW - 100 KLD
78.55 crores
Dec, 2008 17.04.2008Call on 14.05.2008. Also check if any adverse order was issued by MOEF. 21.05.2008The unit has a built up area of 31000 sqm and
Cash penalty & BG of Rs. 50 Lakh each submitted.Accordingly, CTE issued.
17.09
17.04.2008Call on 14.05.2008. Also check if any adverse order was issued by MOEF. 21.05.2008The unit has a built up area of 31000 sqm and
Aggarwal Plaza (P) Ltd, Plot no 29 & 31, CBD Shahdara Commercial Complex, Shahdara, Delhi
Not known
Based on SIT inspection, issue notice for closure without waiting for minutes by 27.06.2008. Call on 11.07.2008.
Call for personal hearing on 24.07.2008 at 8.15 PM.
20.08
proposed STP is 160 KLD capacity. Ask the unit to do the following :-(a) final reminder for Consent to Establish application.(b) Final reminder for Environmental Clearance.(c) Affidavit indicating date of start of construction, date of completion(d) Submit a copy of completion certificate, approved architcural drawing and details of DG sets.If the unit fails to
proposed STP is 160 KLD capacity. Ask the unit to do the following :-(a) final reminder for Consent to Establish application.(b) Final reminder for Environmental Clearance.(c) Affidavit indicating date of start of construction, date of completion(d) Submit a copy of completion certificate, approved architcural drawing and details of
comply with the same, notice for closure will be issued. Concerned CMC to ensure that the letter is personally delivered to the unit by 24.5.2008. Call on 11.06.2008.
28.5.08The total built up area proposed is 31,000 sqm and the unit has applied for Environmental Clearance and has the temerity to ask MOEF to postpone Environmental Clearance hearing
DG sets.If the unit fails to comply with the same, notice for closure will be issued. Concerned CMC to ensure that the letter is personally delivered to the unit by 24.5.2008. Call on 11.06.2008.
28.5.08The total built up area proposed is 31,000 sqm and the unit has applied for Environmental Clearance and has the temerity to ask MOEF to postpone
while he continues to construct. Unit has not applied for Consent to Establish. Let SIT to do an inspection and submit a report before CMC on 11.06.2008. Call on 11.06.2008. 25.06.2008Based on SIT inspection, issue notice for closure without waiting for minutes by 27.06.2008. Call on 11.07.2008. 11.07.2008Call for personal
Environmental Clearance hearing while he continues to construct. Unit has not applied for Consent to Establish. Let SIT to do an inspection and submit a report before CMC on 11.06.2008. Call on 11.06.2008. 25.06.2008Based on SIT inspection, issue notice for closure without waiting for minutes by 27.06.2008. Call on 11.07.2008.
hearing on 24.07.2008 at 8.15 PM. 24.07.2008 The unit came for personal hearing today. It has a built up area 31,000 sqm and project cost of Rs. 100 Crores on our record, which have been changed to Rs. 78 Crores at one place and built up area has been changed to 18,000 sqm. In reply to our SCN, the unit admits of built up area is 31000 sqm. The unit also states that he does not have
11.07.2008Call for personal hearing on 24.07.2008 at 8.15 PM. 24.07.2008 The unit came for personal hearing today. It has a built up area 31,000 sqm and project cost of Rs. 100 Crores on our record, which have been changed to Rs. 78 Crores at one place and built up area has been changed to 18,000 sqm. In reply to our SCN, the unit admits of built up area is 31000
CGWA clearance so far and has applied for the same. The unit does not have any STP for 160 KLD of waste water which it generates. The unit claims that it has requisite stack height of 6 meter although the SIT report says it is 3.5 meter. Unit is about to complete finishing work and structural wok is already completed.
The unit is clear blatant violator and it has not taken Environm
sqm. The unit also states that he does not have CGWA clearance so far and has applied for the same. The unit does not have any STP for 160 KLD of waste water which it generates. The unit claims that it has requisite stack height of 6 meter although the SIT report says it is 3.5 meter. Unit is about to complete finishing work and structural wok is already completed.
The unit is clear
ental Clearance or Consent to Establish and completed the entire hyper market. It does not have STP & ETP. In such a situation, with no extenuating circumstances the unit will have to pay damages at the same rate charged in similar cases i.e. 0.5 % of the project cost as cash penalty and 0.5 % of the project cost as Bank Guarantee as the stated project cost before the
blatant violator and it has not taken Environmental Clearance or Consent to Establish and completed the entire hyper market. It does not have STP & ETP. In such a situation, with no extenuating circumstances the unit will have to pay damages at the same rate charged in similar cases i.e. 0.5 % of the project cost as cash penalty and 0.5 % of the project cost as
MOEF is Rs. 100 cores, it comes to Rs. 50 Lakhs as cash penalty and Rs. 50 Lakhs as Bank Guarantee. The unit will apply for Environmental Clearance to MOEF and create STP. If, the unit complies with all the above four conditions by 31.08.2008, the file may be submitted in CMC on 20.08.2008 for a decision. 21.08.2008CMC order stands. While CTE has been
Bank Guarantee as the stated project cost before the MOEF is Rs. 100 cores, it comes to Rs. 50 Lakhs as cash penalty and Rs. 50 Lakhs as Bank Guarantee. The unit will apply for Environmental Clearance to MOEF and create STP. If, the unit complies with all the above four conditions by 31.08.2008, the file may be submitted in CMC on 20.08.2008 for a decision. 21.08.200
issued, ask the unit to set up STP and get the environmetal clearance from MOEF. Call on 17.09.2008.
8CMC order stands. While CTE has been issued, ask the unit to set up STP and get the environmetal clearance from MOEF. Call on 17.09.2008.
61 2 33 55 SB-33
Jaksons Developers Pvt. Ltd.,, Plot No 3B1, District Centre, Sector-10, Rohini, Delhi
08.07.2008
31/03/08
51393.57
231(MCD)+320(GW)/ 347(WW)
320 crores
2010 17.04.2008Ask him to submit Environmental Clearance. Separately check whether any adverse order was issued by MOEF. 23.5.08The reply of the unit has been perused. Ask him to file
Cash penalty & BG not yet submitted. However, unit has submitted a letter on 20.08.2008.
17.09
17.04.2008Ask him to submit Environmental Clearance. Separately check whether any adverse order was issued by MOEF. 23.5.08The reply of the unit has been perused. Ask him
Jaksons Developers Pvt. Ltd.,, 4th Flor, Vikas Surya Shoping Mall,
Plot No 1B, Mangalam Place, Secor-3, Rohini, Delhi
31-03-2008
Call for personal hearing on 25.07.2008 at 6.00 PM with full details of all information sought so far.
20.08
application for Consent to Establish, a copy of Environmental Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of plot area, builtup area, water drawl, waste water discharge, DG sets, noise monitoring reports of DG sets. Call for personal hearing on 03.06.2008 at 6.30
to file application for Consent to Establish, a copy of Environmental Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of plot area, builtup area, water drawl, waste water discharge, DG sets, noise monitoring reports of DG sets. Call for personal hearing
PM. 03.06.2008The unit has not appeared for personal hearing and sent a letter asking for 15-20 days time to file the required information. The record shows that Environmental Clearance has not been provided and in March, 2008 certain clarifications were raised by MOEF. The EIA Trainee will get the latest updated status from MOEF and also through the net.
on 03.06.2008 at 6.30 PM. 03.06.2008The unit has not appeared for personal hearing and sent a letter asking for 15-20 days time to file the required information. The record shows that Environmental Clearance has not been provided and in March, 2008 certain clarifications were raised by MOEF. The EIA Trainee will get the latest updated status from
The unit may be advised to file all the required documentation latest by 25.06.2008. Call on 25.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 6.00 PM with full details of all information sought so far. 24.07.2008The unit came for personal hearing today. The Environmental Clearance of the unit has been received on 15.07.2008. The unit has sewage
MOEF and also through the net. The unit may be advised to file all the required documentation latest by 25.06.2008. Call on 25.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 6.00 PM with full details of all information sought so far. 24.07.2008The unit came for personal hearing today. The Environmental Clearance of the unit has been
quantity of 347 KLD and has constructed equivalent of three basements and 15 floors are yet to be started which comes to about 16 % of the total area. Based on similar calculation done on damages, the unit requires to pay cash penalty of Rs. 25 Lakhs and Bank Guarantee of Rs. 25 Lakhs valid for three years by 20.08.2008. If the unit complies with the same, Consent to Establish may be
received on 15.07.2008. The unit has sewage quantity of 347 KLD and has constructed equivalent of three basements and 15 floors are yet to be started which comes to about 16 % of the total area. Based on similar calculation done on damages, the unit requires to pay cash penalty of Rs. 25 Lakhs and Bank Guarantee of Rs. 25 Lakhs valid for three years by 20.08.2008. If the unit
issued to the unit. Call on 20.08.2008. 21.08.2008The unit has represented against the damages and Bank Guarantee stating that it is a Common Wealth project. CMC has taken uniform decision for all projects including CWG projects and therefore no discrimination can be made in the eyes of law. Unit may be asked to comply with the CMC decision on
complies with the same, Consent to Establish may be issued to the unit. Call on 20.08.2008. 21.08.2008The unit has represented against the damages and Bank Guarantee stating that it is a Common Wealth project. CMC has taken uniform decision for all projects including CWG projects and therefore no discrimination can be made in the eyes of law. Unit
24.07.2008. and file the required damages and BG latest by 17.09.2008. Call on 17.09.2008.
may be asked to comply with the CMC decision on 24.07.2008. and file the required damages and BG latest by 17.09.2008. Call on 17.09.2008.
63 2 35 56 SB-35
Vishal Retail Ltd., A Block, plot no.1, Ground Floor, Ph-2, Opp. Satyawati College, Ashok Vihar, New Delhi
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008.
Vishal Retail Ltd.RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it
31.07
Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008.
28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.200
has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 2250 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let
26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 2250 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
8. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 2250 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on
the unit confirms the above by 31.07.2008. Call on 31.07.2008.
31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
64 2 36 57 SB-36
Vishal Retail Ltd., E-6 Outer Ring Road, Prashant Vihar, New Delhi
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.200
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping
31.07
8. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on
on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case
Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 4500 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the
18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 4500 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on
may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 4500 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above
D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
65 2 37 58 SB-37
Vishal Retail Ltd., D-2/21 Krishna Nagar, Delhi
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the
31.07
form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore
height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.200
Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 6000 sq. feet. It is silent on ground weater drawl and acoustic enclosur
the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 6000 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above
8 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 6000 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set. Let the
e with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
66 2 38 59 SB-38
Vishal Retail Ltd., E-367, Nirman Vihar, Vikas Marg, New Delhi-92
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid
31.07
and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on
enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter
for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 10400 sq. feet. It is silent on ground weater drawl and acou
27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 10400 sq. feet. It is silent on ground weater drawl and acoustic enclosure with the D.G. Set.
has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 10400 sq. feet. It is silent on ground weater drawl and acoustic
stic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
67 2 39 60 SB-39
Vishal Retail Ltd., FD-7 Pitampura, New Delhi
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-
MS may write to Vishal Retail Ltd. to confirm the Water
31.07
existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of
with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for
37 Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 18000 sq. feet. It is silent on ground weat
Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 18000 sq. feet. It is silent on ground weater drawl and
all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 18000 sq. feet. It is silent on
er drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
ground weater drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
75 3 2 61 SC-2
Metropolitan Mall (MGF developments Ltd.) at Plot No. A-2 & P1B, District Center,
15/5/2007 21/10/2005
34395 sq m
MCD- 280 KLD GW- nil Dis -100 KLD
101 crore
11.03.2008Unit has applied for Consent to Establish on 21.10.200
Cash penalty & Bank Guarantee submitted by the project proponent on
17.09
11.03.2008Unit has applied for Consent to Establish on 21.10.200
Metropolitan Mall (MGF developments Ltd.) ,17-B, Asaf Ali Road,
YES D 95% construction completed in September 2006
16793 21-10-05
Ask the unit to file compliance affidavit of Environmental Conditi
31.07
Saket, Delhi
5 and obtained Environmental Clearance on 15.05.2007. The unit may be asked to file an affidavit indicating item-wise compliance of all Environmental Clearance conditions in the construction and operation phase, date of start of construction and date of completion, copy of approved architectural drawing and copy of completion certificate may also be filed. In view of the DPCC inspection
24.06.2008 and CTE issued on 25.06.2008.Letter issued on 07.07.2008Compliance affidavit submitted by the project proponent on 30.7.08. SIT report to be discussed.
5 and obtained Environmental Clearance on 15.05.2007. The unit may be asked to file an affidavit indicating item-wise compliance of all Environmental Clearance conditions in the construction and operation phase, date of start of construction and date of completion, copy of approved architectural drawing and copy of completion certificate may also be filed. In view of the DPCC inspection
New Delhi-02
as observed during the Inspection
ons. Call on 31.07.2008.
report dated 19.09.2006, which found construction well before Environmental Clearance was granted, case to come up in CMC April, 2008 when he will be given an opportunity of being heard also. 17.04.2008Call for personal hearing on 30.04.2008 at 8.00 PM. 30.04.2008The unit was given a personal hearing and it was found that they were not prepared
report dated 19.09.2006, which found construction well before Environmental Clearance was granted, case to come up in CMC April, 2008 when he will be given an opportunity of being heard also. 17.04.2008Call for personal hearing on 30.04.2008 at 8.00 PM. 30.04.2008The unit was given a personal hearing and it was found that they were
with the factual information sought in the meeting. In view of the above, on their request, the personal hearing is re-scheduled for 6.30 PM on 01.05.2008. 01.05.2008The unit came to personal hearing on 30.04.2008 but failed to do so today. MS to draft a letter asking them for a proof of total cost of the project with separate figures of cost of land and cost of constructi
not prepared with the factual information sought in the meeting. In view of the above, on their request, the personal hearing is re-scheduled for 6.30 PM on 01.05.2008. 01.05.2008The unit came to personal hearing on 30.04.2008 but failed to do so today. MS to draft a letter asking them for a proof of total cost of the project with separate figures of
on. Call them for personal hearing with these details on 14.05.2008. 14.05.2008The unit was given personal hearing when it claimed its right of deemed consent for the application for Consent to Establish. The unit was clearly explained why this is not possible in view of the various documents yet to be supplied/submitted by the unit. The unit pleaded for one weeks
cost of land and cost of construction. Call them for personal hearing with these details on 14.05.2008. 14.05.2008The unit was given personal hearing when it claimed its right of deemed consent for the application for Consent to Establish. The unit was clearly explained why this is not possible in view of the various documents yet to be supplied/submitted by the
time and wanted a copy of our notice dated January, 2007. MS to give the unit a copy on 14.05.2008, if the unit files a copy of the Balance sheet and Memorandum of the Association of the company. Call on 21.06.2008. 28.5.08The unit has filed two letters. One on 14.05.2008 where it is willing to pay the penalty at a “bare minimum percentage”. In another letter dated 23.05.200
unit. The unit pleaded for one weeks time and wanted a copy of our notice dated January, 2007. MS to give the unit a copy on 14.05.2008, if the unit files a copy of the Balance sheet and Memorandum of the Association of the company. Call on 21.06.2008. 28.5.08The unit has filed two letters. One on 14.05.2008 where it is willing to pay the penalty at a “bare minimum percentag
8, the unit stated that it has taken necessary steps to abide by the law. Finally, it is again reiterating that it is willing to pay the penalty and the Bank Guarantee at a “very bare minimum percentage”.In view of the above, the unit may be given a personal hearing on 11.06.2008 at 7.00 PM. 11.6.08The unit during course of hearing has agreed in principle to file a cash penalty of 0.5 % and
e”. In another letter dated 23.05.2008, the unit stated that it has taken necessary steps to abide by the law. Finally, it is again reiterating that it is willing to pay the penalty and the Bank Guarantee at a “very bare minimum percentage”.In view of the above, the unit may be given a personal hearing on 11.06.2008 at 7.00 PM. 11.6.08The unit during course of hearing has
Bank Guarantee of same amount within a week from today. Call on 25.06.2008 with confirmation of the above. 25.06.2008Ask the unit to file compliance affidavit of Environmental Conditions. Call on 31.07.2008. 31.07.2008SIT to inspect and report. Call on 20.08.2008. 21.08.2008SIT inspection has found certain deficienci
agreed in principle to file a cash penalty of 0.5 % and Bank Guarantee of same amount within a week from today. Call on 25.06.2008 with confirmation of the above. 25.06.2008Ask the unit to file compliance affidavit of Environmental Conditions. Call on 31.07.2008. 31.07.2008SIT to inspect and report. Call on 20.08.2008.
es on the item-wise compliance of Environmental Clearance conditions. These deficiencies may be indicated to the unit for correction by 17.09.2008. Call on 17.09.2008.
21.08.2008SIT inspection has found certain deficiencies on the item-wise compliance of Environmental Clearance conditions. These deficiencies may be indicated to the unit for correction by 17.09.2008. Call on 17.09.2008.
77 3 4 62 SC-4
Omaxe Construction Ltd. (Construction of Commercial Complex) at Plot No 14, Jasola, Delhi
N A 28.09.2007
23000 sq m
MCD-I90 KLD GW-nil Discharge-56 KLD
78.57 crore
2007 11.03.2008Unit has applied for Consent to Establish on 28.09.2007. Environmental Clearance not filed but the informatio
Cash penalty & BG submitted.Accordingly, CTE issued.
17.09
11.03.2008Unit has applied for Consent to Establish on 28.09.2007. Environmental Clearance not filed but the informati
Omaxe Construction Ltd.,11, LSC, Kalkaji, New Delhi
D A 2007 19251 & 23704
7/9/2006 & 28-09-07
Call for personal hearing on 25.07.2008 at 7.00 PM with all the required information asked by CMC
Call on 25.06.2008 with architect's report.
20.08
n on the website of MOEF indicate that the Environmental Clearance application has rejected. Unit to file an affidavit with date of start of construction and likely date of completion, approved architectural drawing and completion certificate and reason for concealing the facts that Environmental Clearance application was rejected by MOEF. 17.04.2008
on on the website of MOEF indicate that the Environmental Clearance application has rejected. Unit to file an affidavit with date of start of construction and likely date of completion, approved architectural drawing and completion certificate and reason for concealing the facts that Environmental Clearance application was rejected by MOEF. 17.04.2008
meeting dated 23.05.2008.
Issue a reminder to the unit to file all the documents not filed despite CMC decision of 11.03.2008. Meanwhile, MS to inspect and submit report by 14.05.2008. Take up on 14.05.2008. 23.5.08Since lack of clarity of the built up area, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof. Desh
Issue a reminder to the unit to file all the documents not filed despite CMC decision of 11.03.2008. Meanwhile, MS to inspect and submit report by 14.05.2008. Take up on 14.05.2008. 23.5.08Since lack of clarity of the built up area, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof.
Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-(a) Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise monitorin
Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-(a) Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise
g of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report. 25.06.2008Call for personal hearing on 25.07.2008 at 7.00 PM with all the required information asked by CMC meeting dated 23.05.2008. 24.07.2008The unit came for personal hearing today. There is some confusion about the built up
monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report. 25.06.2008Call for personal hearing on 25.07.2008 at 7.00 PM with all the required information asked by CMC meeting dated 23.05.2008. 24.07.2008The unit came for personal hearing today. There is some confusion
area as the Consent to Establish shows approx. 11,000 sqm, Environmental Clearance shows approx. 18,000 sqm while the IIT Survey shows approx. 19, 000 sqm built up area. In any case the built up area is less than 20,000 sqm and Environmental Clearance is not required. The unit started construction in November, 2006 without taking Consent to Establish. The unit will be
about the built up area as the Consent to Establish shows approx. 11,000 sqm, Environmental Clearance shows approx. 18,000 sqm while the IIT Survey shows approx. 19, 000 sqm built up area. In any case the built up area is less than 20,000 sqm and Environmental Clearance is not required. The unit started construction in November, 2006 without taking
discharging 72 KLD of waste water and STP is yet to be commissioned.
In similar cases where construction has begun and almost completed before Consent to Establish, the damages of cash penalty and Bank Guarantee of 1 % of the total cost has been levied. The unit pleads that Environmental Clearance is not required, therefore, the cash penalty amount may be reduced
Consent to Establish. The unit will be discharging 72 KLD of waste water and STP is yet to be commissioned.
In similar cases where construction has begun and almost completed before Consent to Establish, the damages of cash penalty and Bank Guarantee of 1 % of the total cost has been levied. The unit pleads that Environmental Clearance is not
keeping the total 1 % of the project cost intact. The Committee deliberated on the issue and finally suggested a cash penalty of Rs. 15 Lakhs and Bank Guarantee of Rs. 60 Lakhs valid for three years. If the unit complies with this condition by 20.08.2008, Consent to Establish may be issued at the same time. Call on 20.08.2008. 21.08.2008While
required, therefore, the cash penalty amount may be reduced keeping the total 1 % of the project cost intact. The Committee deliberated on the issue and finally suggested a cash penalty of Rs. 15 Lakhs and Bank Guarantee of Rs. 60 Lakhs valid for three years. If the unit complies with this condition by 20.08.2008, Consent to Establish may be issued at the same time. Call
damages and Bank Guarantee have been filed and CTE have been issued. Unit may be asked to set up STP expeditiously. Call on 17.09.2008.
on 20.08.2008. 21.08.2008While damages and Bank Guarantee have been filed and CTE have been issued. Unit may be asked to set up STP expeditiously. Call on 17.09.2008.
80 3 7 63 SC-7
Laxmi Buildtech Pvt Ltd ,Plot no D-1 & P3-A Saket Place
39784 24/4/07
4650 sq m
MCD-181KLD GW-Nil Dis-72 KLD
173.88 Crore
11.03.2008Unit has applied for Consent to Establish on 24.04.2007 and Environmental Clearance granted on 31.01.2008. It is obvious that unit has started constructi
Reply received with regards to P.H dated 18-06-08.Letter issued in response to the reply submitted by the project proponent. SIT report
17.09
11.03.2008Unit has applied for Consent to Establish on 24.04.2007 and Environmental Clearance granted on 31.01.2008. It is obvious that unit has
Laxmi Buildtech Pvt Ltd ,H-33, Green Park Ext, ND-16
P A Jan. 2008
21114 24-04-07
The unit came for personal hearing and claimed that they are abiding by all the environment
04.07
on before Environmental Clearance was granted. Unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate and itemwise compliance of Environmental Clearance conditions. Case will be taken up in April, 2008 CMC. 17.04.2008Issue reminder to the unit to file the missing
to be discussed.
started construction before Environmental Clearance was granted. Unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate and itemwise compliance of Environmental Clearance conditions. Case will be taken up in April, 2008 CMC. 17.04.2008Issue reminder to the unit
al legislations. However, record shows that they started the construction before getting Environmental Clearance and Consent to Establish. In fact, Environmental Clearance was recei
documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 5.00 PM. 11.6.2008The unit came for personal hearing today and agreed that it has not created the requisite facilities for control of noise / air pollution and treatment of waste water. The unit has also filed a letter saying that it requires a week time for its owner to come
to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 5.00 PM. 11.6.2008The unit came for personal hearing today and agreed that it has not created the requisite facilities for control of noise / air pollution and treatment of waste water. The unit has also filed a letter saying that it requires a
ved after 09 months of start of construction. Still they do not have the Consent to Establish. The unit was asked to pay the required cash penalty i.e. Rs. 50 Lakhs and Bank Guarantee of
personally to explain its case. Call on 18.06.2008 at 8.00 PM for personal hearing of the owner Sh. Vinod Saluja. 18.06.2008The unit came for personal hearing and claimed that they are abiding by all the environmental legislations. However, record shows that they started the construction before getting Environmental Clearance and Consent to Establish. In fact, Environm
week time for its owner to come personally to explain its case. Call on 18.06.2008 at 8.00 PM for personal hearing of the owner Sh. Vinod Saluja. 18.06.2008The unit came for personal hearing and claimed that they are abiding by all the environmental legislations. However, record shows that they started the construction before getting Environmental Clearance
Rs. 1.2 crores valid for three years after much deliberation by the Committee to be complied by 30.06.2008. Call on 03.07.2008.
ental Clearance was received after 09 months of start of construction. Still they do not have the Consent to Establish. The unit was asked to pay the required cash penalty i.e. Rs. 50 Lakhs and Bank Guarantee of Rs. 1.2 crores valid for three years after much deliberation by the Committee, to be complied by 30.06.2008. On further insistent requests by the representative of the unit, the
and Consent to Establish. In fact, Environmental Clearance was received after 09 months of start of construction. Still they do not have the Consent to Establish. The unit was asked to pay the required cash penalty i.e. Rs. 50 Lakhs and Bank Guarantee of Rs. 1.2 crores valid for three years after much deliberation by the Committee, to be complied by 30.06.2008. On
cash penalty was further reduced by the Committee to Rs. 40 Lakhs and Bank Guarantee of Rs. 1.3 crores, to be complied by 30.06.2008. Call on 03.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting. 21.08.2008 Notice for closure be
further insistent requests by the representative of the unit, the cash penalty was further reduced by the Committee to Rs. 40 Lakhs and Bank Guarantee of Rs. 1.3 crores, to be complied by 30.06.2008. Call on 03.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC
issued indicating the deficiencies of SITreport. Call on 17.09.2008.
meeting. 21.08.2008 Notice for closure be issued indicating the deficiencies of SITreport. Call on 17.09.2008.
83 3 10 64 SC-10
Fargo Estate Pvt Ltd C-2 District Centre Saket, New Delhi
N A 24/10/08
10100 sq m
MCD- 49.5 KLD GW-nil Discharge-7000 l/day
46,30,12,260
N A 11.03.2008Unit has applied for Consent to Establish on 04.06.2007. Unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate. Case will
Letter issued on 30.05.2008.Reply received on 20.06.2008.Inspection has been carried out by SIT on 22.07.2008. Matter is to be discussed.
17.09
11.03.2008Unit has applied for Consent to Establish on 04.06.2007. Unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate. Case
Fargo Estate Pvt Ltd,43, Community Centre,
New Friends Colony, Delhi
D A 1.8.2006
21660 39178 SIT to inspect and report by 25.07.2008. Call on 25.07.2008.
Call on 31.07.2008.
31.07
be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08The unit may be asked to file details of water drawl sources, details of ETP for kitchen waste water and steps taken for control of air pollution during excavation. Call on 11.06.2008. 25.06.2008
will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08The unit may be asked to file details of water drawl sources, details of ETP for kitchen waste water and steps taken for control of air pollution during excavation. Call on 11.06.2008.
SIT to inspect and report by 25.07.2008. Call on 25.07.2008. 24.07.2008Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 7.00 PM. Meanwhile issue letter for deficiencies noted by SIT for compliance by 20.08.2008. 21.08.2008The unit came for personal hearing today. It pleads ignorance of procedure of the
25.06.2008SIT to inspect and report by 25.07.2008. Call on 25.07.2008. 24.07.2008Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 7.00 PM. Meanwhile issue letter for deficiencies noted by SIT for compliance by 20.08.2008. 21.08.2008The unit came for personal hearing today. It pleads
Consent to Establish and also confirmed that the mall has been in operation since April, 2007 and has about 100 shops. Effluent discharge is 58.4 KLD and the ETP was not functioning at the time of inspection. The project cost is Rs. 46.3 crores. The unit does not have CGWA clearance. In a similar case, CMC had levied damages of 1.5 % of project cost as cash penalty
ignorance of procedure of the Consent to Establish and also confirmed that the mall has been in operation since April, 2007 and has about 100 shops. Effluent discharge is 58.4 KLD and the ETP was not functioning at the time of inspection. The project cost is Rs. 46.3 crores. The unit does not have CGWA clearance. In a similar case, CMC had levied damages of 1.5 %
and the same amount for Bank Guarantee. The unit claims that it is a smaller Mall and does not require Environmental Clearance and therefore a lenient view will be taken. The Committee deliberated on the issue and decided that damages of 1 % of the project cost as cash penalty amounting Rs. 45 Lakhs and 2 % of the project cost as Bank Guarantee amounting Rs. 90 Lakhs valid for
of project cost as cash penalty and the same amount for Bank Guarantee. The unit claims that it is a smaller Mall and does not require Environmental Clearance and therefore a lenient view will be taken. The Committee deliberated on the issue and decided that damages of 1 % of the project cost as cash penalty amounting Rs. 45 Lakhs and 2 % of the project cost as
three years be submitted by 17.09.2008. The unit may also apply for Consent to Operate and authorization under HWM Rules. Call on 17.09.08.
Bank Guarantee amounting Rs. 90 Lakhs valid for three years be submitted by 17.09.2008. The unit may also apply for Consent to Operate and authorization under HWM Rules. Call on 17.09.08.
87 3 14 65 SC-14
DLF Universal Ltd. Construction of Commercial Complex name DLF Court Yard at Plot No. A4 & P-1A, Saket Place, New Delhi-17
15-01-07 Applied for consent to Establish on 25-09-07
11.03.2008Unit has applied for Consent to Establish on 25.09.2007 and Environmental granted on 15.01.2007. It is obvious that he started the constructi
Unit filed writ before Hon'ble High Court.Case was heard by the High Court on 04.8.08 and the same has been adjourned on
17.09
11.03.2008Unit has applied for Consent to Establish on 25.09.2007 and Environmental granted on 15.01.2007. It is obvious that he started
DLF Universal Ltd.,DLF Centre,
9th Floor, Sansad Marg, New Delhi-01
YES A Jan. 2008
23629 25-09-07
MS to brief the counsel in this case who is doing majority of the mall cases. Call
17.07
on before the Environmental Clearance. He has filed an affidavit indicating item-wise compliance the Environmental Clearance conditions. He may be asked an affidavit indicating date of start of construction and date of completion and architectural drawing and compliance certificate. DPCC inspection indicating start of construction much before the Environmental Clearance. Unit may
11.12.2008SIT inspection report dated 01.08.2008 to be discussed.
the construction before the Environmental Clearance. He has filed an affidavit indicating item-wise compliance the Environmental Clearance conditions. He may be asked an affidavit indicating date of start of construction and date of completion and architectural drawing and compliance certificate. DPCC inspection indicating start of construction much before the Environmental
on 18.07.2008.
be given an opportunity of being heard in 25.03.2008 at 6.30 PM. 17.04.2008Take up on 23.04.2008. 28.5.08Call on 18.06.2008. 18.06.2008MS to brief the counsel in this case who is doing majority of the mall cases. Call on 18.07.2008. 31.07.2008Learned counsel of DPCC has informed that in the case of DLF
Clearance. Unit may be given an opportunity of being heard in 25.03.2008 at 6.30 PM. 17.04.2008Take up on 23.04.2008. 28.5.08Call on 18.06.2008. 18.06.2008MS to brief the counsel in this case who is doing majority of the mall cases. Call on 18.07.2008. 31.07.2008Learned counsel of DPCC has
Universal at Plot No. A4 & P-1A, Saket Place, New Delhi-17 and immediate inspection under the Air & Water Acts must be done. SIT to be directed to do the inspection on 01.08.2008 and submit the file by 1st August administratively without fail. SIT to be informed today without waiting from the minutes so that the work is completed by tomorrow. This matter is listed before the
informed that in the case of DLF Universal at Plot No. A4 & P-1A, Saket Place, New Delhi-17 and immediate inspection under the Air & Water Acts must be done. SIT to be directed to do the inspection on 01.08.2008 and submit the file by 1st August administratively without fail. SIT to be informed today without waiting from the minutes so that the work is complete
Court on 04.08.2008 and hence the urgency. Call on 20.8.2008. 21.08.2008SIT inspection and deficiencies found may be indicated to the unit through a notice for correction. Call on 17.09.2008.
d by tomorrow. This matter is listed before the Court on 04.08.2008 and hence the urgency. Call on 20.8.2008. 21.08.2008SIT inspection and deficiencies found may be indicated to the unit through a notice for correction. Call on 17.09.2008.
88 3 15 66 SC-15
Brightways Housing & Land Development, Construction of Office Cum Shopping Mall at Plot no 7 Distt Centre
Pending with MoEF
39093 21096.513 sq m
source of water not mentioned /ground water-- nil discharge--70KLD
66 crore
proposed 11.03.2008Unit has applied for Consent to Establish on 01.11.2007. Unit not replied to DPCC
A letter received from MOEF on 30.06.2008 stating that project proponent has to apply fresh
17.09
11.03.2008Unit has applied for Consent to Establish on 01.11.2007. Unit not replied to DPCC
Brightways Housing & Land Development, M-39, IIND Floor, Opp Super Bazar, Connaught
P A 31.3.2008
24087 39093 SIT report indicates one borewell without permission from CG
31.07
PH
Jasola New Delhi
letter to file Environmental Clearance. He may be asked for submitting Environmental Clearnce and an affidavit indicating date of start of construction and date of completion, approved architectural drawing & completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing document
application for environmental clearance.
letter to file Environmental Clearance. He may be asked for submitting Environmental Clearnce and an affidavit indicating date of start of construction and date of completion, approved architectural drawing & completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing
Place, New Delhi
WA. It also indicates waste wager generation of 70 KLD and STP of 60 KLD under construction. As regards Environmental Clearance, the net indicates that MOEF has postpone
s by 14.05.2008. Check net for any adverse decision of MOEF. Call on 14.05.2008. 23.5.08SIT to inspect & report by 18.06.2008. Call on 18.06.2008 18.06.2008SIT report indicates one borewell without permission from CGWA. It also indicates waste wager generation of 70 KLD and STP of 60 KLD under construction. As regards Environmental
documents by 14.05.2008. Check net for any adverse decision of MOEF. Call on 14.05.2008. 23.5.08SIT to inspect & report by 18.06.2008. Call on 18.06.2008 18.06.2008SIT report indicates one borewell without permission from CGWA. It also indicates waste wager generation of 70 KLD and STP of 60 KLD under construction. As regards
d the hearing in this case.
Ask the unit to file the permission from CGWA for borewell and Environmental Clearance immediately. Call for personal hearing at 6.30 PM on 11.07.2008.
Clearance, the net indicates that MOEF has postponed the hearing in this case. Ask the unit to file the permission from CGWA for borewell and Environmental Clearance immediately. Call for personal hearing at 6.30 PM on 11.07.2008. 11.07.2008The unit has a total built up area of more than 20,000 sqm and requires an Environmental Clearance.
Environmental Clearance, the net indicates that MOEF has postponed the hearing in this case. Ask the unit to file the permission from CGWA for borewell and Environmental Clearance immediately. Call for personal hearing at 6.30 PM on 11.07.2008. 11.07.2008The unit has a total built up area of more than 20,000 sqm and requires an Environm
The SIT report indicates that the unit has completed its construction by June, 2007 and is awaiting the completion certificate. SIT also indicates that the unit is drawing water from the ground and the total consumption of water as per the CTE is 206 KLD. The unit has not filed any CGWA clearance for this. Additionally, the unit is showing a discharge of 70 KLD vide
ental Clearance. The SIT report indicates that the unit has completed its construction by June, 2007 and is awaiting the completion certificate. SIT also indicates that the unit is drawing water from the ground and the total consumption of water as per the CTE is 206 KLD. The unit has not filed any CGWA clearance for this. Additionally, the unit is showing a discharge
its CTE application. For consumption of 206 KLD as per the norms, the discharge should be in the range of 160 KLD. The unit has not provided any facility for treatment of waste water so far and claims to be constructing an STP of 60 KLD which is any case would be grossly insufficient to treat the waste water.
As regard the stack height of D.G. Set of 1500 KVA the unit needs to raise it as per
of 70 KLD vide its CTE application. For consumption of 206 KLD as per the norms, the discharge should be in the range of 160 KLD. The unit has not provided any facility for treatment of waste water so far and claims to be constructing an STP of 60 KLD which is any case would be grossly insufficient to treat the waste water.
As regard the stack height of D.G. Set of 1500
appropriate norms.
The project cost is claimed to be Rs. 66 Crores whereas MOEF has adjudged it to be Rs. 100 crores. The unit requested for time up to 17.07.2008 to consult its Board. If the unit files the cash penalty of 1.5 % of the project cost i.e. Rs. 1.5 crores and 1.5 % of the project cost as Bank Guarantee of another Rs. 1.5 Crores as has been stipulated in similarly placed
KVA the unit needs to raise it as per appropriate norms.
The project cost is claimed to be Rs. 66 Crores whereas MOEF has adjudged it to be Rs. 100 crores. The unit requested for time up to 17.07.2008 to consult its Board. If the unit files the cash penalty of 1.5 % of the project cost i.e. Rs. 1.5 crores and 1.5 % of the project cost as Bank Guarantee of another Rs. 1.5
unit recently where no Environmental Clearance and no Consent to Establish existed, by 17.07.2008, the case may be put administratively for decision. Call on 17.07.2008. 17.07.2008The unit has filed a letter seeking 15 days time to consult the shopkeepers association as all the shops have been sold. Meanwhile, the unit has been delisted by MOEF and the
Crores as has been stipulated in similarly placed unit recently where no Environmental Clearance and no Consent to Establish existed, by 17.07.2008, the case may be put administratively for decision. Call on 17.07.2008. 17.07.2008The unit has filed a letter seeking 15 days time to consult the shopkeepers association as all the shops have been
mater will have to be taken up through a D.O. letter to Addl. Secretary, MOEF with a copy to Secretary, MOEF, Govt. of India stating that in such cases delisting is not the correct option and action should be proposed against the unit for violating and continuous violation of EPA. Call on 31.07.2008 for personal hearing at 8.30 PM. 31.07.2008 Call for personal hearing on 12.08.2008 at 5.00
sold. Meanwhile, the unit has been delisted by MOEF and the mater will have to be taken up through a D.O. letter to Addl. Secretary, MOEF with a copy to Secretary, MOEF, Govt. of India stating that in such cases delisting is not the correct option and action should be proposed against the unit for violating and continuous violation of EPA. Call on 31.07.2008 for
PM. 13.08.2008The unit has not attended the meeting and submitted a representation requesting for postponement of the hearing. Call for personal hearing on 20.08.2008, at 09.15 PM as a last and final opportunity. 21.08.2008The unit came for personal hearing. It has filed a letter saying that he has paid penalty of Rs. 28 Lakhs to DDA as
personal hearing at 8.30 PM. 31.07.2008 Call for personal hearing on 12.08.2008 at 5.00 PM. 13.08.2008The unit has not attended the meeting and submitted a representation requesting for postponement of the hearing. Call for personal hearing on 20.08.2008, at 09.15 PM as a last and final opportunity. 21.08.2008
compounding fees for construction without sanction. The unit therefore claimed a lenient view in the matter. The Committee deliberated on the issue and felt that the damages as cash penalty be reduced to 1 % of the project cost and Bank Guarantee of 2 % of the project cost as in similar cases. Unit be asked to file damages of Rs. 1 crores and Bank Guarantee of Rs. 2 crores
The unit came for personal hearing. It has filed a letter saying that he has paid penalty of Rs. 28 Lakhs to DDA as compounding fees for construction without sanction. The unit therefore claimed a lenient view in the matter. The Committee deliberated on the issue and felt that the damages as cash penalty be reduced to 1 % of the project cost and Bank Guarantee
valid for three years by 17.09.2008. Call on 17.09.2008.
of 2 % of the project cost as in similar cases. Unit be asked to file damages of Rs. 1 crores and Bank Guarantee of Rs. 2 crores valid for three years by 17.09.2008. Call on 17.09.2008.
92 3 19 67 SC-19
Aditya Infracon (P) Ltd , at Plot no 5 Jasola District New Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
19991 sq m
MCD-110000 LPD GW-120000 LPD DIS- 80000 LPD
63 crore
11.03.2008Unit has applied for Consent to Establish on 01.10.2007 wherein he claims built up area less than 20000 sqm . Ask him an affidavit indicating date of start of
Letter issued on 24-07-08. No reply received.
17.09
11.03.2008Unit has applied for Consent to Establish on 01.10.2007 wherein he claims built up area less than 20000 sqm . Ask him an affidavit indicating date of start of
Aditya Infra Developers (P) Ltd,Commercial Building 271/11, Udyog Vihar, Gurgaon
NO A Mar. 2008
23717 39092 CTE filed by the unit indicate built up area of 19991 sqm. However, inspection by IIT Surveyors on 18.06.2008 indicates that the total built up
Call on 25.06.2008 with measurement.
20.08
construction and date of completion and approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008MS to inspect and report by 14.05.2008. Take up on 14.05.2008. 23.5.08Since lack of clarity of the built up area, as reported by the unit, it requires a professional architect to
construction and date of completion and approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008MS to inspect and report by 14.05.2008. Take up on 14.05.2008. 23.5.08Since lack of clarity of the built up area, as reported by the unit, it requires a professional architect
area is 20323.92 sqm. MS to put up a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead in order to avoid applicability of Environmental Clearance. The unit may also be called for personal hearing on
measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-(a) Ground water drawl, if any, with permission.(b) Installation of STP with
to measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-(a) Ground water drawl, if any, with permission.(b) Installation of STP
04.07.2008 at 7.00 PM.
adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with measurement. 25.06.2008CTE filed by the unit indicate built up area of 19991 sqm. However, inspection by IIT Surveyors on 18.06.2008 indicates that the total built up area is 20323.92 sqm. MS
with adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with measurement. 25.06.2008CTE filed by the unit indicate built up area of 19991 sqm. However, inspection by IIT Surveyors on 18.06.2008 indicates that the total built up area is 20323.92
to put up a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead in order to avoid applicability of Environmental Clearance. The unit may also be called for personal hearing on 04.07.2008 at 7.00 PM. 04.07.2008 Letter has been received regarding postponement of the personal hearing. Request allowed.
sqm. MS to put up a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead in order to avoid applicability of Environmental Clearance. The unit may also be called for personal hearing on 04.07.2008 at 7.00 PM. 04.07.2008 Letter has been received regarding postponement of the personal
Call for personal hearing on 18.07.2008 at 8.15 PM. 17.07.2008The unit came for personal hearing today. It still believes that the total built up area is less than 20,000 sqm, therefore, a copy of our letter written to Addl. Secretary, MOEF may be given to the unit immediately for filing the application for Environmental Clearance to MOEF. The IIT survey report indicates that the
hearing. Request allowed. Call for personal hearing on 18.07.2008 at 8.15 PM. 17.07.2008The unit came for personal hearing today. It still believes that the total built up area is less than 20,000 sqm, therefore, a copy of our letter written to Addl. Secretary, MOEF may be given to the unit immediately for filing the application for Environmental Clearance to MOEF. The IIT
total built up is 20323 sqm. The Consent to Establish application indicates ground water drawl of 120 KLD without CGWA clearance. This must be obtained immediately. It also talks about waste water generation of 80 KLD. Total water consumption recorded in CTE is 230 LD for which 80 % should be the waste water generation i.e. about 180 KLD.
survey report indicates that the total built up is 20323 sqm. The Consent to Establish application indicates ground water drawl of 120 KLD without CGWA clearance. This must be obtained immediately. It also talks about waste water generation of 80 KLD. Total water consumption recorded in CTE is 230 LD for which 80 % should be the waste
The unit however has installed an STP of only 80 KLD. The unit must file an adequacy report of the same and also clarify the difference through an affidavit. The unit must also file the noise monitoring report of the D.G. Set(s). Call on 20.08.2008 for compliance of the above including the application of Environmental Clearance. Informed to the unit accordingly. 21.08.2008
water generation i.e. about 180 KLD. The unit however has installed an STP of only 80 KLD. The unit must file an adequacy report of the same and also clarify the difference through an affidavit. The unit must also file the noise monitoring report of the D.G. Set(s). Call on 20.08.2008 for compliance of the above including the application of Environmental Clearance.
Issue final reminder for information on CGWA permission and Environmental Clearance. Call on 17.09.2008
Informed to the unit accordingly. 21.08.2008Issue final reminder for information on CGWA permission and Environmental Clearance. Call on 17.09.2008
94 3 21 68 SC-21
M/s Suncity Project Pvt. Ltd.Vasant Square Mall Construction Project Pocket 5, Vasant Kunj, Delhi
22/1/2007 28960 sq m-/
MCD-355 KLD GW- Proposed Did- nil
175 crores
proposed Dec 2007
11.03.2008Unit has applied for Consent to Establish on 04.07.2007 and Environmental Clearance granted on 22.01.2007. Compliance conditions not given itemwise. Ask him
BG of Rs. 75 Lakh submitted.Unit has submitted a letter requesting to grant one month time to submit cash penalty of Rs. 75 Lakh.
17.09
11.03.2008Unit has applied for Consent to Establish on 04.07.2007 and Environmental Clearance granted on 22.01.2007. Compliance conditions not given
M/s Suncity Project Pvt. Ltd.,N-49, Ist Floor, Connaught Place, New Delhi-110001
YES A Dec. 2007
22181 39179 SIT report found several deficiencies in the compliance conditions of the Environmental Clearanc
31.07
PH
fresh affidavit indicating date of start of construction & date of completion, item-wise compliance of Environmental Clearance conditions and approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008.
itemwise. Ask him fresh affidavit indicating date of start of construction & date of completion, item-wise compliance of Environmental Clearance conditions and approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.200
e. Call for personal hearing at 5.30 PM on 18.07.2008
23.5.08SIT to inspect & report by 18.06.2008. Call on 18.06.2008 18.06.2008SIT report found several deficiencies in the compliance conditions of the Environmental Clearance. Call for personal hearing at 5.30 PM on 18.07.2008 17.07.2008The unit could not come for personal hearing since the General Manger is hospitalized. SIT report found
8. Call on 14.05.2008. 23.5.08SIT to inspect & report by 18.06.2008. Call on 18.06.2008 18.06.2008SIT report found several deficiencies in the compliance conditions of the Environmental Clearance. Call for personal hearing at 5.30 PM on 18.07.2008 17.07.2008The unit could not come for personal hearing since the General Manger is
several deficiencies which may be communicated to the unit for correction by 31.07.2008. The unit has proposed an STP of 100 KLD while the premises is more or less complete. Unit may be asked to confirm by when STP will be ready. Call on 31.07.2008 at 5.00 PM for personal hearing. 31.07.2008 The unit came for personal hearing today. It is almost on the verge of completion and claims to
hospitalized. SIT report found several deficiencies which may be communicated to the unit for correction by 31.07.2008. The unit has proposed an STP of 100 KLD while the premises is more or less complete. Unit may be asked to confirm by when STP will be ready. Call on 31.07.2008 at 5.00 PM for personal hearing. 31.07.2008 The unit came for personal hearing today. It
have installed the STP and filed the adequacy report. The adequacy report is OK. However, the unit has the total water consumption of 400 KLD and discharge of nearly 100 KLD. The STP capacity is also of 100 KLD. SIT report has found certain discrepancies which have been corrected. The unit claims that the bore well at the site has not been used for drawing ground water. Air monitoring report is also in the
is almost on the verge of completion and claims to have installed the STP and filed the adequacy report. The adequacy report is OK. However, the unit has the total water consumption of 400 KLD and discharge of nearly 100 KLD. The STP capacity is also of 100 KLD. SIT report has found certain discrepancies which have been corrected. The unit claims that the bore well at the site
file and the same is OK. In view of the above, since the unit has completed the construction without Consent to Establish but has installed the STP, the Committee felt that instead of 0.5 % of the total project cost of Rs. 175 Crores which comes to of Rs. 87 Lakhs as damages and Bank Guarantee of Rs. 87 Lakhs, ends of justice will be met, if the damages are reduced to Rs. 75
has not been used for drawing ground water. Air monitoring report is also in the file and the same is OK. In view of the above, since the unit has completed the construction without Consent to Establish but has installed the STP, the Committee felt that instead of 0.5 % of the total project cost of Rs. 175 Crores which comes to of Rs. 87 Lakhs as damages and Bank Guarantee of Rs. 87
Lakhs and Bank Guarantee of equivalent amount valid for three years. These conditions are to be complied with by 20.08.2008. Call on 20.08.2008. 21.08.2008The unit has filed BG of Rs. 75 Lakhs which is not in appropriate proforma. It must be returned to the unit for resubmission in a proper form. The BG should include (a) the value of the BG (b) the time
Lakhs, ends of justice will be met, if the damages are reduced to Rs. 75 Lakhs and Bank Guarantee of equivalent amount valid for three years. These conditions are to be complied with by 20.08.2008. Call on 20.08.2008. 21.08.2008The unit has filed BG of Rs. 75 Lakhs which is not in appropriate proforma. It must be returned to the unit for resubmission in a proper
period of three years for which it is valid (c) the cause of validity i.e. compliance to all evironemental legislation valid for city of Dehi.The unit seeks time of one month for submission of cash penalty of Rs. 75 lakh. Time granted upto 17.09.2008.
form. The BG should include (a) the value of the BG (b) the time period of three years for which it is valid (c) the cause of validity i.e. compliance to all evironemental legislation valid for city of Dehi.The unit seeks time of one month for submission of cash penalty of Rs. 75 lakh. Time granted upto 17.09.2008.
112 3 39 69 SC-39
Vishal Retail Ltd., RZ-6, Part of
_ Not applie
d
01.05.2008Issue a letter to
Inspection report of SIT to be
17.09
01.05.2008Issue a letter to
Vishal Retail Ltd.,RZ-A-95&96
MS may write to Vish
31.07
SIT
Rect No 19 Killa No. 1/2/1, 10, 1/2/2 Rect No. 18 Killa No. 7/3, 5/2 & 6, Laxmi Garden, Village Nazafgarh.
Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. According
discussed.
Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge
, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
al Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. SIT to inspect and
ly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm.
figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before
report. Call on 31.07.2008.
SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT to inspect and report. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
31.07.2008 and confirm. SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT to inspect and report. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
113 3 40 70 SC-40
Vishal Retail Ltd., Mahipalpur Crossing Near Bikaner Sweets Mahipalpur, New Delhi
_ Not applie
d
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence of
As decided, letter issued on 19-08-08.Reply awaited.
17.09
01.05.2008Issue a letter to Vishal Retail Ltd. to file a noise monitoring reports for all D.G. Sets and along with existence
Vishal Retail Ltd.,RZ-A-95&96, Road No-4, Gali no-09,Mahipalpur Extn,New Delhi-37
MS may write to Vishal Retail Ltd. to confirm the Water Cess amo
31.07
acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of Vishal. This letter
of acoustic enclosures and stack height in affidavit form. Call on 03.06.2008. 28.5.08Unit had replied giving details of acoustic enclosure of the D.G. Sets, but no information on the stack height has been provided. It had also been silent on waste water discharge figures. Accordingly, MS has been directed administratively to ask for these two details for all the 14 malls of
unt paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 12500 sq. feet. It is silent on ground weater draw
has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 12500 sq. feet. It is silent on ground weater drawl and acoustic enclosure
Vishal. This letter has gone on 27.05.2008 and therefore the case may be called on 18.06.2008. 26.06.2008MS may write to Vishal Retail Ltd. to confirm the Water Cess amount paid for all the Shopping Malls. If, it has not paid so far the unit must do so before 31.07.2008 and confirm. Unit reports built up area 12500 sq. feet. It is silent on ground weater
l and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008.
with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
drawl and acoustic enclosure with the D.G. Set. Let the unit confirms the above by 31.07.2008. Call on 31.07.2008. 31.07.2008Reminder for reply by 20.08.2008. Call on 20.08.2008. 21.08.2008Issue notice for clousre. Call on 17.09.2008
117 3 44 71 SC-44
Construction of commercial building at Plot No 2, City Centre, Sector-13, Dwarka by M/s
13/05/2008
15260 sqm
MCD-38 KLD GW-77 KLD WW-Nil KLD
144.73 crores
31.07.2008The unit appeared before CMC during the meeting and requested for early hearing.
17.09
31.07.2008The unit appeared before CMC during the meeting and requested for early hearing.
Nettles Farms Pvt. Ltd.
Call on 06.08.2008 at 6.00 PM for personal hearing. 06.08.08The unit came for personal hearing today and assured that it will file the documents asked vide letter dated 06.06.2008 within a week. Call for personal hearing on 20.08.2008 at 6.45 PM. 21.08.2008The unit came for personal hearing today. It has a total built up area of 15216 sqm of which the basement is nearly 9600 sqm
Call on 06.08.2008 at 6.00 PM for personal hearing. 06.08.08The unit came for personal hearing today and assured that it will file the documents asked vide letter dated 06.06.2008 within a week. Call for personal hearing on 20.08.2008 at 6.45 PM. 21.08.2008The unit came for personal hearing today. It has a total built up area of 15216 sqm of which the basement is nearly
and ground + three floors of 6500 sqm. The unit has done complete excavation and according to the SIT report laid the foundation. The total project cost is Rs. 144 crores. The unit has filed the affidavit and other details sought vide CMC meeting held on 18.06.2008. The Committee deliberated on the issue and felt that no construction has been done on the
9600 sqm and ground + three floors of 6500 sqm. The unit has done complete excavation and according to the SIT report laid the foundation. The total project cost is Rs. 144 crores. The unit has filed the affidavit and other details sought vide CMC meeting held on 18.06.2008. The Committee deliberated on the issue and felt that no constructi
premises since last four months. The unit claims that in a similar case CMC had levied damages of 10 % of 1/2 % of the project cost as cash penalty, and equivalent amount as Bank Guarantee and a similar equation may be applied for this unit. The Committee deliberated on the issue and felt that the ends of justice will be met if the damages of cash penalty of Rs. 10 Lakhs and Bank Guarantee
on has been done on the premises since last four months. The unit claims that in a similar case CMC had levied damages of 10 % of 1/2 % of the project cost as cash penalty, and equivalent amount as Bank Guarantee and a similar equation may be applied for this unit. The Committee deliberated on the issue and felt that the ends of justice will be met if the damages of cash
of Rs. 10 Lakhs valid for three years is levied. To be complied with by 17.09.2008. Call on 17.09.2008.
penalty of Rs. 10 Lakhs and Bank Guarantee of Rs. 10 Lakhs valid for three years is levied. To be complied with by 17.09.2008. Call on 17.09.2008.
4 1 4 72 SA-4
Naman Buildcon Ltd Proposed Commercial Complex Namely Pacific Mall at Khyala New Delhi
19.5.08 24-05-07
42438.58Sqm
375KLD/250KLD(STP)in EC
65crores
10.03.2008Prosecution proceedings have been inordinately delayed which is unwarranted. Prosecution must be launched by tomorrow positively without waiting for the minutes to be issued since this has already been
As decided in CMC, a letter to DMRC along with copy of letter received from MOEF on 03.07.2008The next date of hearing is 20.10.2008.
20.10
10.03.2008Prosecution proceedings have been inordinately delayed which is unwarranted. Prosecution must be launched by tomorrow positively without waiting for the minutes to be issued since this
Naman Buildcon Ltd,Pacific 3rd Floor, Plot no 1, Site IV Sahibabad Industrial Area, Ghaziabad (U.P)
P A 40148
21488 24-05-07
Send the copy of MoEF's letter to DMRC. Call on 18.07.2008.
18.07
decided. Explanation of the concerned Cells for 40 day delay may be placed on file and submit with the remarks of MS to me in two days along with confirmation of the prosecution having been undertaken in the relevant court. It is once again reiterated to all the CMC Incharges that once the CMC Committee takes a decision, any delay / alterations / with holding / tampering with the decision
has already been decided. Explanation of the concerned Cells for 40 day delay may be placed on file and submit with the remarks of MS to me in two days along with confirmation of the prosecution having been undertaken in the relevant court. It is once again reiterated to all the CMC Incharges that once the CMC Committee takes a decision, any delay / alterations / with
will not be accepted under any circumstances. This is to ensure the sanctity of the Committee which spends hours in taking the decisions. 17.04.2008`The latest Court proceedings may be indicated against this unit on 14.05.2008. MS will ensure that in all cases of prosecution, an updated status in the Court will become part of the agenda in CMC. The copy of the prosecution
holding / tampering with the decision will not be accepted under any circumstances. This is to ensure the sanctity of the Committee which spends hours in taking the decisions. 17.04.2008`The latest Court proceedings may be indicated against this unit on 14.05.2008. MS will ensure that in all cases of prosecution, an updated status in the Court will become part of the
documents filed by DPCC should also be sent to DJB, NDPL & MCD by MS under his signatures. 21.05.2008There appears to be a rather long date in this prosecution case which in the first place was delayed by 40 days in the process of filing the prosecution. Let Sh. Prem Kumar, Advocate in the panel of DPCC, file an application for early hearing in this case so that the
agenda in CMC. The copy of the prosecution documents filed by DPCC should also be sent to DJB, NDPL & MCD by MS under his signatures. 21.05.2008There appears to be a rather long date in this prosecution case which in the first place was delayed by 40 days in the process of filing the prosecution. Let Sh. Prem Kumar, Advocate in the panel of
prosecution proceedings become meaningful. 18.06.2008Send the copy of MoEF's letter to DMRC. Call on 18.07.2008. 13.08.2008Call on 20.10.2008.
DPCC, file an application for early hearing in this case so that the prosecution proceedings become meaningful. 18.06.2008Send the copy of MoEF's letter to DMRC. Call on 18.07.2008. 13.08.2008Call on 20.10.2008.
11 1 11 73 SA-11
S.S. Co-Build Pvt. Ltd. proposed shopping mall "Capitol City Mall", BG-1 & BG-2, Paschim Vihar, New
Built up area : 13571.94 sqm
Applied on
03.07.2008
13571.9 sqm
MCD : 14 KLD / MCD
Sewer : 10 KLD
136.50 Cr.
2009 Ask him to file Consent to Establish & environmental clearance. Also ask the unit to file an affidavit indicating
Directions for closure issued on 24.06.2008.Unit has applied in the name of S.S.Co
10.09 PH
Ask him to file Consent to Establish & environmental clearance. Also ask the unit to file an affidavit indicating
Capitol City Mall,M/s Naresh Aggarwal Properties & Developers (P) Ltd.,
NO N _ _ _ In this case there is no Consent to Establish, no Environment
17.07
Delhi. the date of construction & date of completion.Approved architectural drawing may also be filed by 25.3.2008. Case to be put up on 25.03.2008. 03.4.08Take up on 10.04.2008. 17.04.2008Issue reminder to the unit to file all the documents required vide CMC decision of 03.04.2008. If he fails to file the documents by 30.04.2008, the unit will be
Build Pvt. Ltd. for CTE on 03.07.2008.
the date of construction & date of completion.Approved architectural drawing may also be filed by 25.3.2008. Case to be put up on 25.03.2008. 03.4.08Take up on 10.04.2008. 17.04.2008Issue reminder to the unit to file all the documents required vide CMC decision of 03.04.2008. If he fails to file the documents by
28, Apra Plaza, Pitam Pura, Delhi.
al Clearance and there is a full-fledged SIT report with all the deficiencies. The unit has not replied to notice for closure and therefore the closure orders are confirmed with directions to disc
proceeded against as per the Environmental Laws of the Land. Reminder should be issued to both the office address and mall address. 01.05.2008Since the unit has not replied to any of the letters issued on the directions of CMC, the unit may be asked to come up on personal hearing on 14.05.2008 at 8.00 PM with all the relevant documents. 14.05.2008SIT to
30.04.2008, the unit will be proceeded against as per the Environmental Laws of the Land. Reminder should be issued to both the office address and mall address. 01.05.2008Since the unit has not replied to any of the letters issued on the directions of CMC, the unit may be asked to come up on personal hearing on 14.05.2008 at 8.00 PM with all the relevant documents.
onnect water / power supply. This closure order must be served by Monday i.e. 23.06.2008 without waiting for the minutes. Draft order may be shown to the Chairman befo
inspect this unit on 14.05.2008 and this case will also be taken up in the special CMC meeting convened on 15.05.2008 for deciding the case of Shop in Park by Pragya Products Private Ltd at Plot No. 2, Community Centre, Block B , Shalimar Bagh, Delhi. 15.5.08though it is not liable for Environmental Clearance since the built up area is less than 20000 sqm, is trying to
14.05.2008SIT to inspect this unit on 14.05.2008 and this case will also be taken up in the special CMC meeting convened on 15.05.2008 for deciding the case of Shop in Park by Pragya Products Private Ltd at Plot No. 2, Community Centre, Block B , Shalimar Bagh, Delhi. 15.5.08though it is not liable for Environmental Clearance since the built up
re issue. Call on 18.07.2008.
evade the law and therefore the Committee felt that it is appropriate to issue notice for closure u/s 31(A) of the Air Act, 1981 and u/s 33(A) of the Water Act, 1974 to the unit for non compliance of the Air & Water Acts provisions. The notice may be drafted and shown to the chairman on 19.05.2008. The notice may be issued to both the addresses recorded in the inspection report
area is less than 20000 sqm, is trying to evade the law and therefore the Committee felt that it is appropriate to issue notice for closure u/s 31(A) of the Air Act, 1981 and u/s 33(A) of the Water Act, 1974 to the unit for non compliance of the Air & Water Acts provisions. The notice may be drafted and shown to the chairman on 19.05.2008. The notice may be issued to both the
giving 15 days time. Call on 03.06.2008. 28.5.08Call on 11.06.2008. 18.06.2008In this case there is no Consent to Establish, no Environmental Clearance and there is a full-fledged SIT report with all the deficiencies. The unit has not replied to notice for closure and therefore the closure orders are confirmed with directions to disconnec
addresses recorded in the inspection report giving 15 days time. Call on 03.06.2008. 28.5.08Call on 11.06.2008. 18.06.2008In this case there is no Consent to Establish, no Environmental Clearance and there is a full-fledged SIT report with all the deficiencies. The unit has not replied to notice for closure and therefore the closure
t water / power supply. This closure order must be served by Monday i.e. 23.06.2008 without waiting for the minutes. Draft order may be shown to the Chairman before issue. Call on 18.07.2008. 13.08.2008Call for personal hearing on 10.9.2008 at 5.00 PM.
orders are confirmed with directions to disconnect water / power supply. This closure order must be served by Monday i.e. 23.06.2008 without waiting for the minutes. Draft order may be shown to the Chairman before issue. Call on 18.07.2008. 13.08.2008Call for personal hearing on 10.9.2008 at 5.00 PM.
19 1 19 74 SA-19
CTC Mall, 3, Najafgarh Road, New
2552.96Sqm
28.5.08
2552.96Sqm/in reply
-
1500LD(municpal)
/discharge-800LD(no
77800000Rs
Dec----2008
17.04.2008 Issue notice for
As decided, a letter issued
10.09 PH
17.04.2008 Issue notice for
CTC Mall,Chhabra Tradin
_ _ Call on 06.08.2008.
06.08
Delhi 2043Sqm
STP) filing Consent to Establish and Environmental Clearance on 03.04.2008 giving four weeks time. Call on 30.04.2008. 01.05.2008SIT to inspect to check built up area, waste water discharge and D.G.Sets connection. Call on 21.05.2008. 21.05.2008SIT to inspect and report by 23.05.2008. Call on 23.05.2008.
on 13.06.2008, unit has submitted a letter and requested for 45 days time for installation of STP.
filing Consent to Establish and Environmental Clearance on 03.04.2008 giving four weeks time. Call on 30.04.2008. 01.05.2008SIT to inspect to check built up area, waste water discharge and D.G.Sets connection. Call on 21.05.2008. 21.05.2008SIT to inspect and report by 23.05.2008. Call on 23.05.2008.
g CompanyLtd, 920, station Road, Near Mewa Hotel, Chandni Chowk, Delhi-06
23.05.2008In view of the SIT report and the deficiencies found therein, unit may be called for personal hearing on 03.06.2008 at 6.00 PM. 03.06.2008The unit came for personal hearing today . The unit has agreed to do the following:-
(a) The unit has to file the permission from the Central Ground Water Authority for ground water drawl. (b) The inspection report
23.05.2008In view of the SIT report and the deficiencies found therein, unit may be called for personal hearing on 03.06.2008 at 6.00 PM. 03.06.2008The unit came for personal hearing today . The unit has agreed to do the following:-
(a) The unit has to file the permission from the Central Ground Water Authority for ground water
shows waste water generation of 4.8 KLD without any substantiation as of now how it is being treated. The unit is advised to install mini STP for treatment of this sewage water. (c) Our record shows lease agreement between erstwhile industry and this unit that the premises should be used for factory purpose. Let the unit file the building plan and completion certificate
drawl. (b) The inspection report shows waste water generation of 4.8 KLD without any substantiation as of now how it is being treated. The unit is advised to install mini STP for treatment of this sewage water. (c) Our record shows lease agreement between erstwhile industry and this unit that the premises should be used for factory purpose. Let the unit file the building
from DDA/ MCD. Call on 11.07.2008. 11.07.2008Call on 06.08.2008. 13.08.2008Call for personal hearing on 10.9.2008 at 5.30 PM.
plan and completion certificate from DDA/ MCD. Call on 11.07.2008. 11.07.2008Call on 06.08.2008. 13.08.2008Call for personal hearing on 10.9.2008 at 5.30 PM.
35 2 7 75 SB-7
Rishab Ipex Mall, I.P Extension, Near Max Balaji Hospital Delhi
NA 27/03/08
666.52
2(borewell)/ 1.6(WW)
10Cr. 11.03.2008Ask him to apply for Consent to Establish. MS to inspect. Case to come up on 25.03.2008. 17.03.2008Ask both
Letter issued on 01.07.2008. Reply received.
10.09 PH
11.03.2008Ask him to apply for Consent to Establish. MS to inspect. Case to come up on 25.03.2008. 17.03.2008Ask both
Rishab Ipex Mall, Rishab Build Con Pvt Ltd, Plot No 16, Community Centre,
Karkardooma
Delhi - 92
N _ 25322 27-03-08
Issue final reminder failing which notice for closure order be issued. Call on 18.0
17.07
the porjects to apply for CTE. Inform about the deficiencies found during the inspection for correction. 11.04.2008The unit was inspected by MS. In view of violation of stack height provisions, the unit may be asked to correct the deficiencies and file a Bank Guarantee of Rupees One Lakh under Air Act by 30.04.2008. 01.05.2008Call on 14.05.2008.
the porjects to apply for CTE. Inform about the deficiencies found during the inspection for correction. 11.04.2008The unit was inspected by MS. In view of violation of stack height provisions, the unit may be asked to correct the deficiencies and file a Bank Guarantee of Rupees One Lakh under Air Act by 30.04.2008. 01.05.2008Call on 14.05.2008.
7.2008.
23.5.08Issue reminder for Bank Guarantee to be filed within 15 days. Call on 11.06.2008. 18.06.2008Issue final reminder failing which notice for closure order be issued. Call on 18.07.2008. 13.08.2008BG will not be waived. Call for personal hearing on 10.09.2008, at 06.00 PM
23.5.08Issue reminder for Bank Guarantee to be filed within 15 days. Call on 11.06.2008. 18.06.2008Issue final reminder failing which notice for closure order be issued. Call on 18.07.2008. 13.08.2008BG will not be waived. Call for personal hearing on 10.09.2008, at 06.00 PM
97 3 24 76 SC-24
Eros Metro Mall, Sec-14, Dwarka , New
Area < 20,000 sq. m
02.05.2008
14491.761 sq m
MCD-105 KLD GW-NIL DIS- 48 KLD
132.68 crore
2010 11.03.2008Issue final letter. Unit has
Reply received on 03.07.2008 with
10.09 PH
11.03.2008Issue final letter.
Eros Metro Mall,Eros Group, S-1,
NO N _ _ _
04.07
Delhi not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April,
regards to personal hearing dated 25.06.2008 stating his inability to pay cash penalty & BG of Rs. 50 Lakhs respectively.Also, a reply received on 18.07.208.
Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will
American Plaza, International Trade Tower, Nehru Place, New Delhi-19
2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 6.30 PM. 11.6.08The unit came for personal hearing today. The built up area is approx. 15,500 sqm and construction not yet started as the building plans are yet to be cleared by DDA. Unit will
be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 11.06.2008 at 6.30 PM. 11.6.08The unit came for personal hearing today. The built up area is approx. 15,500 sqm and construction not yet started as the building
install STP of 50 KLD and 2 D.G. Sets with acoustic enclosures and requisite stack height. The unit will file clarification on how excavation would be done to ensure air pollution is checked. Unit will also confirm when the building plans will be approved, so that the DDA building plan conditions can be checked by DPCC before Consent to Establish application is considered. Call on
plans are yet to be cleared by DDA. Unit will install STP of 50 KLD and 2 D.G. Sets with acoustic enclosures and requisite stack height. The unit will file clarification on how excavation would be done to ensure air pollution is checked. Unit will also confirm when the building plans will be approved, so that the DDA building plan conditions can be checked by DPCC before
25.06.2008. 25.06.2008This case was taken up as a table agenda because of the personal appearance of Sh. Deepak Gupta, General Manger - Commercial. The unit has filed application saying that as regard the excavation plan, they will use 55,00 cubic meter of earth for back filling and rest will be shifted from the site. As regard the building plans approval, it is yet to be
Consent to Establish application is considered. Call on 25.06.2008. 25.06.2008This case was taken up as a table agenda because of the personal appearance of Sh. Deepak Gupta, General Manger - Commercial. The unit has filed application saying that as regard the excavation plan, they will use 55,00 cubic meter of earth for back filling and rest will be shifted
received from DDA. The unit admits that it has excavated earth to the extent of approx. 19,584 cubic meters.
The unit pleaded for leniency of the cash penalty in view of the fact that it had not done any construction but only excavation work. The Committee deliberated on this issue and decided that a final figure of cash penalty of Rs. 50 Lakhs and Bank
from the site. As regard the building plans approval, it is yet to be received from DDA. The unit admits that it has excavated earth to the extent of approx. 19,584 cubic meters.
The unit pleaded for leniency of the cash penalty in view of the fact that it had not done any construction but only excavation work. The Committee deliberated on this issue and decided
Guarantee of Rs. 50 Lakhs would be appropriate. The unit can now file the letter of agreement in this regard by 03.07.2008 and submit the same as early as possible to get its Consent to Establish but not later than 18.07.2008. Call on 04.07.2008. 13.08.2008Call for personal hearing on 10.09.2008, at 06.30 PM.
that a final figure of cash penalty of Rs. 50 Lakhs and Bank Guarantee of Rs. 50 Lakhs would be appropriate. The unit can now file the letter of agreement in this regard by 03.07.2008 and submit the same as early as possible to get its Consent to Establish but not later than 18.07.2008. Call on 04.07.2008. 13.08.2008Call for personal hearing on
10.09.2008, at 06.30 PM.
2 1 2 77 SA-2
G.P. S Developers & Contractors Pvt Ltd , West Gate Mall, 4,5 & 6 Shivaji Place District Center, Rajagarden
39177 Consent to Establish/ NOC valid upto 23-04-07 vide Consent No.- 14249
10728Sqm
10Kld(MCD),120KLD(G.W)/
45crores(72crores Gross)
04.09.08 10.03.2008Let him submit the copy of environmental clearance. Let the unit clarify on affidavit when it started the construction and what is the date of completion. A letter may be sent from Chairman, DPCC to Addl. Secretary, MoE&F highlighting the fact that environmental clearance given by MoE&F are seldom received by Secretary(Env.) or
As decided in CMC meeting dated 11.07.2008, reminder was issued on 23.07.2008.Unit has submitted revised itemwise compliance affidavit and copy of letter addressed to MS, CGWA.
10.09
SIT
10.03.2008Let him submit the copy of environmental clearance. Let the unit clarify on affidavit when it started the construction and what is the date of completion. A letter may be sent from Chairman, DPCC to Addl. Secretary, MoE&F highlighting the fact that environmental clearance given by MoE&F are seldom received
G.P. S Developers & Contractors Pvt Ltd The Statesman House,
8th Floor, Barakhamba Road, New Delhi - 110001.
Y D Not Reported
14067 13-05-05
The unit has not filed an appropriate affidavit and may be directed to file item-wise compliance in a shape of proper affidavit. The unit may also be asked to file permission
Final reminder for CGWA and item-wise affidavit. Call on 06.08.2008.
06.08
MS, DPCC and therefore decisions by DPCC are getting delayed. Addl. Secretary may be requested to send all the copies of environmental clearances issued in 2007 & 2008. 17.04.2008Issue reminder on the previous lines for compliance urgently. Call on 14.05.2008, 21.05.2008The unit has filed Environmental Clearance of 04.05.2007 on
by Secretary(Env.) or MS, DPCC and therefore decisions by DPCC are getting delayed. Addl. Secretary may be requested to send all the copies of environmental clearances issued in 2007 & 2008. 17.04.2008Issue reminder on the previous lines for compliance urgently. Call on 14.05.2008, 21.05.2008The unit has filed Environmental
from CGWA for ground water drawl. Call on 11.07.2008.
15.05.2008. Ask the unit to file compliance affidavit of all the Environmental Clearance conditions, item-wise, along with a fresh Consent to Establish application from the date the previous one expired. Unit may also confirm when it completed its construction and whether it is operating as a mall and from what date. Copy of DPCC letter may be sent to Addl. Secretary, MOEF to confirm whether
Clearance of 04.05.2007 on 15.05.2008. Ask the unit to file compliance affidavit of all the Environmental Clearance conditions, item-wise, along with a fresh Consent to Establish application from the date the previous one expired. Unit may also confirm when it completed its construction and whether it is operating as a mall and from what date. Copy of
any adverse order has been passed against the unit. Letter to be signed by MS. Call on 03.06.2008. 11.6.2008The unit has not filed an appropriate affidavit and may be directed to file item-wise compliance in a shape of proper affidavit. The unit may also be asked to file permission from CGWA for ground water drawl. Call on 11.07.2008. 11.07.2008
DPCC letter may be sent to Addl. Secretary, MOEF to confirm whether any adverse order has been passed against the unit. Letter to be signed by MS. Call on 03.06.2008. 11.6.2008The unit has not filed an appropriate affidavit and may be directed to file item-wise compliance in a shape of proper affidavit. The unit may also be asked to file permission from CGWA for
Final reminder for CGWA and item-wise affidavit. Call on 06.08.2008. 13.08.2008SIT to inspect & report. Call on 10.09.2008
ground water drawl. Call on 11.07.2008. 11.07.2008Final reminder for CGWA and item-wise affidavit. Call on 06.08.2008. 13.08.2008SIT to inspect & report. Call on 10.09.2008
22 1 22 78 SA-22
Office & Commercial mall at 27, K.G. Marg, Delhi by Parsvnath Developers Ltd.
Built up area 16783 sqm
16.06.2008
16783 sqn
MCD - 81.4 KLD / WW / 36 KLD(No STP)
244 crores
2010 Letter issued seeking Consent to Establisha, copy of Environmental Clearance, details of D.G. Sets, built up area & generation of waste water.
Letter issued for required information / dsocuments.Applied for CTE on 16.06.2008 vide I.D. No. 26072.
10.09
SIT
Letter issued seeking Consent to Establisha, copy of Environmental Clearance, details of D.G. Sets, built up area & generation of waste water.
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
04.07
28.5.08The unit in its reply has stated that the proposed built up area will be less than 20,000 sqm and it will apply for CTE at the appropriate time. However, press report indicates the total plot area of more than 5,000 sqm and total investment of nearly Rs. 300 crores. The unit may therefore be asked to file the following documents:1. Affidavit indicating date of start of constructi
Specific Reply not submitted but application for CTE submited on 16-06-08.
28.5.08The unit in its reply has stated that the proposed built up area will be less than 20,000 sqm and it will apply for CTE at the appropriate time. However, press report indicates the total plot area of more than 5,000 sqm and total investment of nearly Rs. 300 crores. The unit may therefore be asked to file the following documents:1. Affidavit indicating date of
on and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission for water drawl. 6. Deatils of waste water discharge 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Application for Consent to Establish. 11.Copy of Environmental ClearanceCall on 03.07.2008. 13.08.2008SIT to
start of construction and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission for water drawl. 6. Deatils of waste water discharge 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Application for Consent to Establish. 11.Copy of Environmental ClearanceCall on 03.07.2008. 13.08.200
inspect and report. Call on 10.09.2008
8SIT to inspect and report. Call on 10.09.2008
58 2 30 79 SB-30
Nippun Builders & Development (P) Ltd., Karkardooma, District Centre, near AGCR Colony, Delhi
_ Not applied
_ _ _ _
17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit
Letter issued on 01.07.2008. Reply awaited.
10.09
SIT 17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance
Nippun Builders & Development (P) Ltd., Karkardooma, District Centre,
Near AGCR Colony, Delhi
Not known
The unit has filed CTE wherein he has indicated ground water drawl of 13.5 KLD without any CGWA permission. It also indicates waste water generatio
17.07
indicating date of start of construction, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008The unit has filed CTE wherein he has indicated ground water drawl of 13.5 KLD without any CGWA permissio
, affidavit indicating date of start of construction, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008The unit has filed CTE wherein he has indicated ground water drawl of 13.5 KLD without
n of 8.5 KLD without mentioning any treatment of this waste water. It has also shown one D.G. Set with acoustic enclosure but without adequate stack height. Ask the unit to file the detai
n. It also indicates waste water generation of 8.5 KLD without mentioning any treatment of this waste water. It has also shown one D.G. Set with acoustic enclosure but without adequate stack height. Ask the unit to file the details by 18.07.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
any CGWA permission. It also indicates waste water generation of 8.5 KLD without mentioning any treatment of this waste water. It has also shown one D.G. Set with acoustic enclosure but without adequate stack height. Ask the unit to file the details by 18.07.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
ls by 18.07.2008.
60 2 32 80 SB-32
Jindal Biochem
_ Not applie
New Engine
10.09
Jindal Bioche
Not kno
One of
17.07
(P) Ltd., Karkardooma, District Centre, near AGCR Colony, Delhi
d 17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit indicating date of start of construction, date of completion,a copy of completion
er of CMC visited the area and get the correct address. Accordingly, notice reissued at correct address.Reply received.
SIT 17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit indicating date of start of construction, date of completion,a copy of
m (P) Ltd., Karkardooma, District Centre,
Near AGCR Colony, Delhi
wn the new Engineer of CMC will visit the area and get the correct address and notice will be reissued by next week. Call on 18.07.2008.
certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008One of the new Engineer of CMC will visit the area and get the correct address and notice will be reissued by next week. Call on 18.07.2008. 13.08.2008SIT to inspect and report.
completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008One of the new Engineer of CMC will visit the area and get the correct address and notice will be reissued by next week. Call on 18.07.2008. 13.08.200
Call on 10.09.2008.
8SIT to inspect and report. Call on 10.09.2008.
68 2 40 81 SB-40
T. R. Sawhney Heritage Mall,Secotor - 23, Rohini, Delhi - 85
NA Applied on 21.5.2008
1190 8(GW)no permission frim CGWA/ 3(WW)
4.67Cr. 28.5.08The built up area is 1190 sqm and the unit is drawing 8 KLD of water from the ground without permission from CGWA. The unit is also discharging 3 KLD of water with only an oil & grease trap. The unit has also one DG. Set of 125 KVA of which details have not been provided. Unit may be asked to file
Letter issued & returned back undelievered. Hence personaly delievered.Reply received on 16.07.2008..
10.09
SIT
28.5.08The built up area is 1190 sqm and the unit is drawing 8 KLD of water from the ground without permission from CGWA. The unit is also discharging 3 KLD of water with only an oil & grease trap. The unit has also one DG. Set of 125 KVA of which details have not been provided. Unit may be asked to file
T. R. Sawhney Heritage Mall,Secotor - 23, Rohini, Delhi - 85
Issue final reminder on the documents asked for. Call on 18.07.2008
17.07
permission from CGWA for drawing ground water, waste water treatment details and D.G. Sets details. Call on 18.06.2008. 18.06.2008Issue final reminder on the documents asked for. Call on 18.07.2008 13.08.2008SIT to inspect and report. Call on 10.09.2008.
permission from CGWA for drawing ground water, waste water treatment details and D.G. Sets details. Call on 18.06.2008. 18.06.2008Issue final reminder on the documents asked for. Call on 18.07.2008 13.08.2008SIT to inspect and report. Call on 10.09.2008.
72 2 44 82 SB-44
Prithvi Sound Products Company (P) Ltd.
_ 08.08.2008
8058.89 sqm
MCD - 34.7 KLD / GW - Not mentioned / WW - 31
40.01 Cr.
2008 13.08.2008SIT to inspect and
Applied for CTE on 08.08.2008 vide
10.09
SIT
13.08.2008SIT to inspect and
(KLJ Tower North), Plot No B-5, District Centre, Wazirpur, Delhi
KLD / STP - 40 KLD
report. Call on 10.09.2008.
I.D. No. 26909.
report. Call on 10.09.2008.
76 3 3 83 SC-3
India Coloniser Pvt.Ltd (const. of Commercial Complex at M-6 Plaza NHCC Jasola)
Area < 20,000 sq. m
Not Applied For Consent to Establish, However had applied for NOC W.R.T EC on 23-05-06
19650.72 sq m
MCD-220 KLD GW-NIL DIS 38 KLD
72.18 crore
11.03.2008Unit to file Environmental Clearance, an affidavit indicating date of start of construction and likely date of completion and approved architectural drawing and copy of completion certificate may also be filed. In view of the violation of the Water & Air Act found by
Letter issued on 07.08.2008No reply received.
10.09
SIT
11.03.2008Unit to file Environmental Clearance, an affidavit indicating date of start of construction and likely date of completion and approved architectural drawing and copy of completion certificate may also be filed. In view of the violation of the Water & Air Act found by
India Coloniser Pvt.Ltd ,229, Ph-III, Okhla Industrial Area, New Delhi-20
NO D 10.6.2007
18268 23-05-06
Call for personal hearing on 25.07.2008 at 6.30 PM with all the required information asked by CMC meeting dated 23.05.2008.
Call on 25.06.2008 with architect's report.
5.45 31.07
PH
DPCC, unit will be given an opportunity of being heard in April, 2008 CMC. 17.04.2008Issue a reminder to the unit to file all the documents not filed despite CMC decision of 11.03.2008. Meanwhile, MS to inspect and submit report by 14.05.2008. Take up on 14.05.2008. 23.5.08Since the built up area is about 400 sqm less than the requireme
DPCC, unit will be given an opportunity of being heard in April, 2008 CMC. 17.04.2008Issue a reminder to the unit to file all the documents not filed despite CMC decision of 11.03.2008. Meanwhile, MS to inspect and submit report by 14.05.2008. Take up on 14.05.2008. 23.5.08Since the built up area is about 400 sqm less than the
nt for EC, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-(a)
requirement for EC, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-
Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report. 25.06.2008Call for personal hearing on 25.07.2008 at 6.30 PM with all the required information asked by CMC
(a) Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report. 25.06.2008Call for personal hearing on 25.07.2008 at 6.30 PM with all the required informati
meeting dated 23.05.2008. 24.07.2008The unit came for personal hearing today. Instead of answering the three points raised by the DPCC, the unit is trying to circumvent its omissions & commissions and not even supplying the required data asked for. The record clearly indicates the waste water discharge of 38 KLD and the unit is completely silent on the STP which it
on asked by CMC meeting dated 23.05.2008. 24.07.2008The unit came for personal hearing today. Instead of answering the three points raised by the DPCC, the unit is trying to circumvent its omissions & commissions and not even supplying the required data asked for. The record clearly indicates the waste water discharge of 38 KLD and the unit is completel
was directed to install. The unit is discharging the entire waste water of 38 KLD into the drain without bothering about the provisions of the Water Act. The unit has also stated that its director is not well and seeks adjournment. The unit is allowed time upto 31.07.2008 to file an affidavit to three points raised by CMC vide its decision dated 23.05.2008 and come for personal
y silent on the STP which it was directed to install. The unit is discharging the entire waste water of 38 KLD into the drain without bothering about the provisions of the Water Act. The unit has also stated that its director is not well and seeks adjournment. The unit is allowed time upto 31.07.2008 to file an affidavit to three points raised by CMC vide its decision
hearing on 31.07.2008 at 5.45 PM with the affidavit. 31.07.2008The unit came for personal hearing today. It has claimed that the ground water was drawn from the nearby well for the construction purpose only and now the water is utilized only from DJB supply. As regards effluent discharge, the Consent to Establish application shows 38 KLD of trade
dated 23.05.2008 and come for personal hearing on 31.07.2008 at 5.45 PM with the affidavit. 31.07.2008The unit came for personal hearing today. It has claimed that the ground water was drawn from the nearby well for the construction purpose only and now the water is utilized only from DJB supply. As regards effluent discharge, the Consent
effluent while the unit claims that the proposed shops and food courts have not been constructed and therefore it is only household sewage which is connected to the DJB sewage line. This fact is being substantiated by the DJB. The unit may be asked to file water monitoring report and noise monitoring of the D.G. Set(s) by 12.08.2008 along with an affidavit. Call on 12.08.2008.
to Establish application shows 38 KLD of trade effluent while the unit claims that the proposed shops and food courts have not been constructed and therefore it is only household sewage which is connected to the DJB sewage line. This fact is being substantiated by the DJB. The unit may be asked to file water monitoring report and noise monitoring of the D.G. Set(s) by 12.08.200
13.08.2008SIT to inspect and report. Call on 10.09.2008.
8 along with an affidavit. Call on 12.08.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
89 3 16 84 SC-16
National Building Construction Corporation Ltd (NBCC) Construction of Community Centre Cum Commercial Complex at Sec-5, Pushp Vihar, New Delhi
14/3/2007 29/10/2007
39169 sq m
MCD-280 KLD GW -NIL DIS- 96000 LPD
100crore
11.03.2008Unit may be asked an affidavit indicating date of start of construction and date of completion and approved architectural drawing, , itemwise compliance of Environmentalf Clearance conditions. Case will be taken up in April,
Letter issued on 01.07.2008 by MS.Reply received on 18.07.2008 alonga with affidavit, architectural drawing and other details.
10.09
SIT
11.03.2008Unit may be asked an affidavit indicating date of start of construction and date of completion and approved architectural drawing, , itemwise compliance of Environmentalf Clearance conditions. Case will be taken up in April,
National Building Construction Corporation Ltd (NBCC) ,NBCC Bhawan, Lodhi Road, New Delhi
Y A Dec. 2007
24043 29-10-07
MS to remind MD again. Call on 18.07.2008.
17.07
2008 CMC. 17.04.2008Issue notice to file compliance affidavit of all the conditions of Environmental Clearance with special reference to the conditions of construction phase which is now in operation. Issue reminder seeking missing documents also. Call on 14.05.2008. 23.5.08Issue reminder to MD by MS. Call on 18.06.2008.
2008 CMC. 17.04.2008Issue notice to file compliance affidavit of all the conditions of Environmental Clearance with special reference to the conditions of construction phase which is now in operation. Issue reminder seeking missing documents also. Call on 14.05.2008. 23.5.08Issue reminder to MD by MS. Call on 18.06.2008.
18.06.2008MS to remind MD again. Call on 18.07.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
18.06.2008MS to remind MD again. Call on 18.07.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
106 3 33 85 SC-33
H.l Group, Sec-11, Dwarka , New Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
Not applied for consent to Establish
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environm
Letter isued on 01.07.2008 as decided in the hearing on 18.06.2008.Reply received on 17.07.2008.
10.09
SIT
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2.
H.l Group,Home Linker Pvt. Ltd., (H. L. Group), 2nd Floor, H. L. Square, Sector - 5, Dwaraka, New Delhi - 75.
NO N _ _ _ The unit is not very clear about the total quantity of water drawn and the total quantity of waste water
17.07
ental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal
Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008.
that will be generated. This data may be provided to the Committee by 18.07.2008. Data on D.G. Set to be installed with acoustic enclosure and stack height may also be asked for.
hearing on 18.06.2008 at 5.00 PM. 18.06.2008The unit is not very clear about the total quantity of water drawn and the total quantity of waste water that will be generated. This data may be provided to the Committee by 18.07.2008. Data on D.G. Set to be installed with acoustic enclosure and stack height may also be asked for. 13.08.2008SIT to inspect and
23.5.08Call for personal hearing on 18.06.2008 at 5.00 PM. 18.06.2008The unit is not very clear about the total quantity of water drawn and the total quantity of waste water that will be generated. This data may be provided to the Committee by 18.07.2008. Data on D.G. Set to be installed with acoustic enclosure and stack height may also be asked
report. Call on 10.09.2008.
for. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
108 3 35 86 SC-35
Parvsanath Developers Ltd Commercial Project At Welcome Metro Station
Pending with MOEF check from site of MOEF.
39329 371178 sq m
MCD- 517 KLD GW-NIL DIS-133 KLD
80 crore
2008 11.03.2008Unit has applied for Consent to Establish on 09.04.2007. Website of MOEFindicates that MOEF has directed stoppage of construction. Let the unit file an affidavit indicating date of start of construction and completion of construction,
Letter isued on 06-06-08 Reply received on 25-06-08 with regards to compliance of EC condition. But it is not proper.
10.09
SIT
11.03.2008Unit has applied for Consent to Establish on 09.04.2007. Website of MOEFindicates that MOEF has directed stoppage of construction. Let the unit file an affidavit indicating date of start of construction and completion of construction,
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
P A 2008 21012 39329 04.07
approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008 Call on 23.04.2008. 23.04.2008The representative of Parvsanath Developers Ltd also raised the issue of payment of cash penalty and BG for Commercial Project at Welcome Metro Station and the unit has given a
approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008 Call on 23.04.2008. 23.04.2008The representative of Parvsanath Developers Ltd also raised the issue of payment of cash penalty and BG for Commercial Project at Welcome Metro Station and the unit has
letter saying that they have erroneously given a figure of 40 % of construction last time on 11.4.2008. The actual construction is only about 20 %. The unit however has no document to substantiate its claim. The unit is allowed time to file an appropriate clear & correct document along with the photographs by 30.04.2008. Case to come up on 30.04.2008. 30.04.2008
given a letter saying that they have erroneously given a figure of 40 % of construction last time on 11.4.2008. The actual construction is only about 20 %. The unit however has no document to substantiate its claim. The unit is allowed time to file an appropriate clear & correct document along with the photographs by 30.04.2008. Case to come up on 30.04.2008.
The unit was asked in the last CMC meeting to submit documentary proof of extent of construction. Instead of that unit has filed a certificate from Charted Accountant stating that Rs. 14.6 Crores worth of expenditure has been incurred. CMC cannot decide and give relief on account of expenditure incurred when the unit had clearly admitted that 40 % of the construction has been
30.04.2008The unit was asked in the last CMC meeting to submit documentary proof of extent of construction. Instead of that unit has filed a certificate from Charted Accountant stating that Rs. 14.6 Crores worth of expenditure has been incurred. CMC cannot decide and give relief on account of expenditure incurred when the unit had clearly admitted that 40 % of the
completed.
In view of the above, the earlier order of CMC dated 11.04.2008 is reiterated and the formal letter may be issued to the unit by tomorrow without waiting for the minutes for compliance by 14.05.2008. 28.5.08The unit has been issued CTE on the basis of the CMC decision of 30.04.2008 wherein it was decided that CTE will be issued to
construction has been completed.
In view of the above, the earlier order of CMC dated 11.04.2008 is reiterated and the formal letter may be issued to the unit by tomorrow without waiting for the minutes for compliance by 14.05.2008. 28.5.08The unit has been issued CTE on the basis of the CMC decision of 30.04.2008 wherein it was decided
the unit if it pays the cash penalty & Bank Guarantee. This has been done and CTE was issued. Unit be asked to file compliance of Environmental Clearance conditions through an affidavit by 01.07.2008 & 01.01.2009. Call on 03.07.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
that CTE will be issued to the unit if it pays the cash penalty & Bank Guarantee. This has been done and CTE was issued. Unit be asked to file compliance of Environmental Clearance conditions through an affidavit by 01.07.2008 & 01.01.2009. Call on 03.07.2008. 13.08.2008SIT to inspect and report. Call on 10.09.2008.
41 2 13 87 SB-13
Parsvnath Developers Ltd in construction with M/s OCL Ltd Construction of Integrated Station Building and commercial development at Inderlok Metro
NA Not applied for consent to Establish
16555(as per
letter)
Not provided
Not provide
d
Not provided
11.03.2008Last and final reminder asking them to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion. Unit will also file approved architectural drawing. Take up on 25.3.2008. 03.04.2008The unit appears to be cleverly avoiding the arms of
Letter issued. Reply received on 29.07.2008Inspection reprot of SIT will be discussed.
A 11.03.2008Last and final reminder asking them to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion. Unit will also file approved architectural drawing. Take up on 25.3.2008. 03.04.2008The unit appears to be cleverly avoiding
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
N _ _ _ Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008.
17.07
SIT
environmental laws. Direct him to appear before the committee on 17.04.2008 at 6.30 PM 11.04.2008Take up on 17.04.2008. 23.04.2008The personal hearing was attended by Sh. Sandeep Mukherjee, Sr. Manager (Strategic Planning).The unit claims that it is only a tenant in the DMRC property and therefore has no role to
the arms of environmental laws. Direct him to appear before the committee on 17.04.2008 at 6.30 PM 11.04.2008Take up on 17.04.2008. 23.04.2008The personal hearing was attended by Sh. Sandeep Mukherjee, Sr. Manager (Strategic Planning).The unit claims that it is only a tenant in the DMRC property and therefore
play with respect to any adherence to environmental legislations. The unit has filed a letter saying that the commercial space has been concessioned to them and has been constructed by DMRC.
Clause (E) of the concession agreement filed by the unit states “ DMRC proposed to grant to a selected person a concession to develop, procure, finance, construct, manage, maintain
has no role to play with respect to any adherence to environmental legislations. The unit has filed a letter saying that the commercial space has been concessioned to them and has been constructed by DMRC.
Clause (E) of the concession agreement filed by the unit states “ DMRC proposed to grant to a selected person a concession to develop, procure, finance,
and licence the use of the built up spaces and facilities in the Specified Area for specified purposes (the Project authorized to be undertaken is hereinafter call the ‘Project’)”
In view of the above, the status of the unit is not that of a tenant by any logical method of analysis and requires them to file the Consent to Establish application along with details of D.G. Sets
construct, manage, maintain and licence the use of the built up spaces and facilities in the Specified Area for specified purposes (the Project authorized to be undertaken is hereinafter call the ‘Project’)”
In view of the above, the status of the unit is not that of a tenant by any logical method of analysis and requires them to file the Consent to Establish applicatio
and waste water discharge. This must be done by 14.05.2008. The case be taken up in CMC meeting on 14.5.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit indicating date of start of construction, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating
n along with details of D.G. Sets and waste water discharge. This must be done by 14.05.2008. The case be taken up in CMC meeting on 14.5.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit indicating date of start of construction, date of completion,a copy of completio
plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next
n certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted
CMC meeting.
administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
47 2 19 88 SB-19
Parsvnath Developers Ltd in construction with M/s OCL Ltd Construction of Integrated Station Building and commercial development at Netaji Subhash Place Metro
Applied on 17.04.2008
22/04/08
29074.55
108.95(MCD)/ 71.2(WW) (STP)
147.1Cr.
11.03.2008Ask him to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion. Unit will also file approved architectural drawing by April CMC. 11.04.2008Call for
Letter issued on 01.07.2008. Reply received on 07.07.2008SIT report to be discussed.
A 11.03.2008Ask him to file Consent to Establish & Environmental Clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion. Unit will also file approved architectural drawing by April CMC. 11.04.2008
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
N _ _ _ Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008.
17.07
personal hearing on 30.04.2008 at 6.00 PM. 30.04.2008In this case, applications for Consent to Establish and Environmental Clearance have been filed. The total built up area is going to be 29074.55 sqm. The unit claims, it has not started construction and is awaiting Environmental Clearance. Take up on 21.05.2008 with a copy of Environmental Clearance.
Call for personal hearing on 30.04.2008 at 6.00 PM. 30.04.2008In this case, applications for Consent to Establish and Environmental Clearance have been filed. The total built up area is going to be 29074.55 sqm. The unit claims, it has not started construction and is awaiting Environmental Clearance. Take up on 21.05.2008 with a copy of Environmental
21.05.2008Unit to file Environmental Clearance. Call on 18.06.2008. 18.06.2008Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in
Clearance. 21.05.2008Unit to file Environmental Clearance. Call on 18.06.2008. 18.06.2008Issue final reminder to file documents. Meanwhile SIT to inspect and report by 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be
the next CMC meeting.
ratified in the next CMC meeting.
69 2 41 89 SB-41
Amtrac Automotive India Pvt. Ltd. 3A Wazirpur Indl Area, Near Deep Hyundai Service Centre, Delhi-52
_ not applied
18273 sq feet(as reported)
Borewell not reported
not reported
25.06.2008SIT to inspect and report by 04.07.2008. Call on 04.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
As directed by Chairman, notice were issued and same were returned back undelivered. Notice delivered on 02.06.2008. Reply awaited. Report of SIT to be discused.
A
25.06.2008SIT to inspect and report by 04.07.2008. Call on 04.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
SIT to inspect and report by 04.07.2008. Call on 04.07.2008.
04.07
SIT
70 2 42 90 SB-42
Commercial cum Multiplex Project by Yogi Raj Promoters Pvt. Ltd. Plot No SU,
19.06.2008
88938.06 sqm
MCD - 116 KLD / GW - Stand By / WW - 244 KLD(STP Proposed)
440 crores
October, 2008
28.5.08Call on 03.06.2008. 25.06.2008SIT to inspect
Inspection report of SIT will be discussed.
A 28.5.08Call on 03.06.2008. 25.06.2008SIT to inspect
Emaar MGF Land Limited,ECE House,28, Kasturbha
SIT to inspect and report by 18.07.2008. Call on 18.07.2008.
17.07
SIT
Sector-22, Rohini
and report by 18.07.2008. Call on 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
and report by 18.07.2008. Call on 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
Gandhi Marg,New Delhi - 1
71 2 43 91 SB-43
Gold souk mallplot no.1,sharda niketan opp.crescent public school, saraswati vihar
_ Not Applied
Not reported
MCD-6 KLD (borewell+DJB) GW-NIL DIS.-5 KLD
not reported
not reported
25.06.2008SIT to inspect and report by 18.07.2008. Call on 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted
Inspection report of SIT will be discussed.
A 25.06.2008SIT to inspect and report by 18.07.2008. Call on 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted
SIT to inspect and report by 18.07.2008. Call on 18.07.2008.
17.07
SIT
administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
78 3 5 92 SC-5
Lifestyle Building Pvt. Ltd. (construction of Commercial Complex at Plot NO 4, Jasola, Delhi
31/10/2007
Not Applied For Consent to Establish, However had applied for NOC W.R.T EC on 13-09-06 . The same has been forwarded to MOEF
26898.25 sq m
MCD-192 KLD GW- NIL DIS- NIL STP PROPOSED-100 KLD
70 CRORE
11.03.2008Unit has applied for Consent to Establish on 13.09.2006 and Environmental Clearance received on 25.02.2008. It is obvious that unit has started construction before Environmental Clearance was granted. Unit to file an affidavit with date of start of constructi
Inspection report of SIT will be discussed.
A 11.03.2008Unit has applied for Consent to Establish on 13.09.2006 and Environmental Clearance received on 25.02.2008. It is obvious that unit has started construction before Environmental Clearance was granted. Unit to file an affidavit with date of start of
Lifestyle Building Pvt. Ltd.,3, Munirka Marg, Vasant Vihar, Delhi
Y D 6.6.2007
19309 13-09-06
SIT to inspect and report by 18.07.2008.
17.07
SIT
on and date of completion, approved architectural drawing and completion certificate and itemwise compliance of Environmental Clearance conditions. 17.04.2008Issue reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08In view of no response of the unit, issue notice for closure under Air & water
construction and date of completion, approved architectural drawing and completion certificate and itemwise compliance of Environmental Clearance conditions. 17.04.2008Issue reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08In view of no response of the unit, issue notice for closure under Air
Acts. Call on 18.06.2008. 18.06.2008SIT to inspect and report by 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
& water Acts. Call on 18.06.2008. 18.06.2008SIT to inspect and report by 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
84 3 11 93 SC-11
Sprit Global Pvt Ltd Commercial Complex Plot no 9 Jasola District Centre
N A 16/07/08
19948.637 sq m
MCD-151 KLD GW-bore well proposed Discharge-45 KLD STP-50KLD capacity
54.56 crore
2008 11.03.2008Unit has applied for Consent to Establish on 16.07.2007. Unit
Letter issued on 03.05.2008No reply received.Inspection report
A
11.03.2008Unit has applied for Consent to Establish on 16.07.2007. Unit
Sprit Global Pvt Ltd,J-1906, Chitranjan Park, New Delhi-
D A July 2007/ 2008
22457 16-07-07
CTE filed by the unit indicate built up area of 19991 sqm. However, inspecti
Call on 25.06.2008 with architect's report.
31.07
SIT
claims that he is less than 20,000 sqm. Unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Since lack of
of SIT to be discussed.
claims that he is less than 20,000 sqm. Unit to file an affidavit with date of start of construction and date of completion, approved architectural drawing and completion certificate. Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Since
19 on by IIT Surveyors on 19.06.2008 indicates that the total built up area is 20420.56 sqm. MS to put up a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead in order to avoid applicability of Environmental Clearan
clarity of the built up area, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following documents :-
lack of clarity of the built up area, as reported by the unit, it requires a professional architect to measure and confirm. MS will speak to Prof. Desh Bandhu of the Environmental wing of School of Planning & Architecture and hire the services of a good Junior Architect who will go with MS and confirm the built up area. The unit may also be asked to file the following
ce. The unit may also be called for personal hearing on 04.07.2008 at 7.30 PM.
(a) Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report. 25.06.2008CTE filed by the unit indicate built up area of 19991 sqm. However, inspection
documents :-(a) Ground water drawl, if any, with permission.(b) Installation of STP with adequacy report for waste water discharge.(c) Noise monitoring of D.G. Sets.Call on 18.06.2008 with all details above. 18.06.2008Call on 25.06.2008 with architect's report. 25.06.2008CTE filed by the unit indicate built up area of 19991 sqm.
by IIT Surveyors on 19.06.2008 indicates that the total built up area is 20420.56 sqm. MS to put up a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead in order to avoid applicability of Environmental Clearance. The unit may also be called for personal hearing on 04.07.2008 at 7.30 PM. 04.07.2008
However, inspection by IIT Surveyors on 19.06.2008 indicates that the total built up area is 20420.56 sqm. MS to put up a letter through Chairman to Addl. Secretary, MOEF indicating the sequence of the event whereby the unit has tried to mislead in order to avoid applicability of Environmental Clearance. The unit may also be called for personal hearing on 04.07.2008 at 7.30
The unit came for personal hearing today. It claims that it has applied for Environmental Clearance to MOEF. While it is yet to receive approval and has had a couple of hearings in the MOEF. It is, therefore, clear the built up area is more than 20,000 sqm, the unit also admits that about 18,000 sqm out of 20,000 sqm is complete as on today without Environmental Clearance and
PM. 04.07.2008The unit came for personal hearing today. It claims that it has applied for Environmental Clearance to MOEF. While it is yet to receive approval and has had a couple of hearings in the MOEF. It is, therefore, clear the built up area is more than 20,000 sqm, the unit also admits that about 18,000 sqm out of 20,000 sqm is complete as on today without
Consent to Establish. The unit is allowed time upto 31.07.2008 to file Environmental Clearance. In the meantime, SIT to inspect and report by 31.07.2008. Latest status of Environmental Clearance may be cheeked by EIA Trainee from MOEF with due authorization from MS and the CMC will also check it through the internet. 31.07.2008SIT to inspect and report on
Environmental Clearance and Consent to Establish. The unit is allowed time upto 31.07.2008 to file Environmental Clearance. In the meantime, SIT to inspect and report by 31.07.2008. Latest status of Environmental Clearance may be cheeked by EIA Trainee from MOEF with due authorization from MS and the CMC will also check it through the internet. 31.07.2008
12.08.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
SIT to inspect and report on 12.08.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
86 3 13 94 SC-13
DLF Retail Developers Ltd. (Construction of Shopping Complex named as DLF South Court at Plot No A1 & P2B, Saket Place, Saket, New
15/01/07 25/09/07
34871.72 sq m
MCD-400 KLD GW-NIL DIS-NIL
245.35 crore
11.03.2008Unit has applied for Consent to Establish on 25.09.2007 and Environmental granted on 15.01.2007. EC has been received in DPCC
Inspection is to be carried out by SIT.
A
11.03.2008Unit has applied for Consent to Establish on 25.09.2007 and Environmental granted on 15.01.2007. EC has been received
DLF Retail Developers Ltd., DLF Centre,
Sansad Marg, New Delhi-01
YES A Jan. 2008
23626 25-09-07
Call for personal hearing on 31.07.2008 at 5.00 PM
12.08
Delhi ) dated 15.01.2007. It is obvious that he started the construction before the EC. He has filed an affidavit indicating item-wise compliance the EC conditions. He may be asked an affidavit indicating date of start of construction and date of completion and approved architectural drawing and completion certificate if received. Case will be taken up in April, 2008 CMC.
in DPCC dated 15.01.2007. It is obvious that he started the construction before the EC. He has filed an affidavit indicating item-wise compliance the EC conditions. He may be asked an affidavit indicating date of start of construction and date of completion and approved architectural drawing and completion certificate if received. Case will be taken up in April, 2008
17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08SIT to inspect & report by 18.06.2008. Call on 18.06.2008 28.5.08SIT to inspect & report on 10 conditions and on Environmental Clearance conditions. Call on 11.06.2008. 25.06.2008Call for personal hearing on 31.07.2008 at 5.00 PM
CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08SIT to inspect & report by 18.06.2008. Call on 18.06.2008 28.5.08SIT to inspect & report on 10 conditions and on Environmental Clearance conditions. Call on 11.06.2008. 25.06.2008Call for personal hearing
24.07.2008The unit came for personal hearing today. Since DPCC is required to file its counter affidavit in the Hon’ble High Court in this case, it is in the process of doing so. Call on 12.08.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
on 31.07.2008 at 5.00 PM 24.07.2008The unit came for personal hearing today. Since DPCC is required to file its counter affidavit in the Hon’ble High Court in this case, it is in the process of doing so. Call on 12.08.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in
the next CMC meeting.
98 3 25 95 SC-25
Manish Buildwell Pvt. Ltd., Plot No 2, LSC, Sec-22 Dwarka , New Delhi
Built up area : 8485.75 sqm
24.06.2008
8485.75 sqm
MCD- 73 KLD / WW-57 KLD (STP)
66,94,71,101 crores
2010 11.03.2008Unit may be asked to file the following four things : 1. Consent to Establish.2. Affidavit indicating date of start of construction and completion of construction.3. Approved architectural drawing.4. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final
Inspection report of SIT will be discussed.
A 11.03.2008Unit may be asked to file the following four things : 1. Consent to Establish.2. Affidavit indicating date of start of construction and completion of construction.3. Approved architectural drawing.4. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008
Manish Buildwell Pvt. Ltd. S-1, 2nd Floor Usha Chamber, 37-38, Central Market, Ashok Vihar, Delhi - 52
NO N _ _ _ SIT to inspect and report. Call on 18.07.2008
17.07
reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Issue notice for closure. Call on 18.06.2008. 18.06.2008SIT to inspect and report. Call on 18.07.2008 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next
Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Issue notice for closure. Call on 18.06.2008. 18.06.2008SIT to inspect and report. Call on 18.07.2008 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be
CMC meeting.
ratified in the next CMC meeting.
99 3 26 96 SC-26
Vardhman Group, Sec-7 Dwarka, New Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
Not applied for consent to Establish
11.03.2008Ask him to apply fresh Consent to Establish on the ground that a mall would generate effluent and huge D.G. Set which pollutes the air & create noise. Also ask him to file an affdaivt indicating date of start of construction & date of completion of construction, approved architectural drawing and completio
Inspection report of SIT will be discussed.File in with Legal Cell for taking necessary action at their end.
A 11.03.2008Ask him to apply fresh Consent to Establish on the ground that a mall would generate effluent and huge D.G. Set which pollutes the air & create noise. Also ask him to file an affdaivt indicating date of start of construction & date of completion of construction, approved architectural drawing and
Vardhman Group,Vardhman Land Developers (P) Ltd., G-9, Vardhman Trade Centre,
DDA Building, Nehru Place, Delhi - 19.
NO N _ _ _ 04.07
SIT
n certficate. Case will be taken up in April, 2008. 17.04.2008File being studied administratively for appropriate action on the court case. 28.5.08Call on 29.5.08 29.5.08In 04 Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get
completion certficate. Case will be taken up in April, 2008. 17.04.2008File being studied administratively for appropriate action on the court case. 28.5.08Call on 29.5.08 29.5.08In 04 Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean
stay. DPCC through SIT must get the fresh inspection done focusing on whether the projects fall within the notification of 07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed
hands and managed to get stay. DPCC through SIT must get the fresh inspection done focusing on whether the projects fall within the notification of 07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the constructi
on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate from DDA for sector-23 is dated 04.12.2006. The earlier inspection reports have not been signed at the site by the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Due to want of
on has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate from DDA for sector-23 is dated 04.12.2006. The earlier inspection reports have not been signed at the site by the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of
time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
ATR on 03.7.08. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
100 3 27 97 SC-27
Vardhman Group, Sec-19 Dwarka, New Delhi
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
Not applied for consent to Establish
11.03.2008Ask him to apply fresh Consent to Establish on the ground that a mall would generate effluent and huge D.G. Set which pollutes the air & create noise. Also ask him to file
Inspection report of SIT will be discussed.File in with Legal Cell for taking necessary action at their end.
A 11.03.2008Ask him to apply fresh Consent to Establish on the ground that a mall would generate effluent and huge D.G. Set which pollutes the air & create noise. Also ask
Vardhman Group,Vardhman Land Developers (P) Ltd., G-9, Vardhman Trade Centre, DDA Building, Nehru Place, Delhi - 19.
NO N _ _ _ 04.07
SIT
an affdaivt indicating date of start of construction & date of completion of construction, approved architectural drawing and completion certficate. Case will be taken up in April, 2008. 17.04.2008File being studied administratively for appropriate action on the court case. 28.5.08Call on 29.5.08 29.5.08In 04 Vardhman cases, 3
him to file an affdaivt indicating date of start of construction & date of completion of construction, approved architectural drawing and completion certficate. Case will be taken up in April, 2008. 17.04.2008File being studied administratively for appropriate action on the court case. 28.5.08Call on 29.5.08 29.5.08In 04
projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get stay. DPCC through SIT must get the fresh inspection done focusing on whether the projects fall within the notification of 07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as
Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get stay. DPCC through SIT must get the fresh inspection done focusing on whether the projects fall within the notification of 07.07.2004 with reference to the project investment (b) waste
building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate from DDA for sector-23 is dated 04.12.2006. The earlier inspection reports have not been signed at the site by the official present of the project proponent
water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate from DDA for sector-23 is dated 04.12.2006. The earlier inspection reports have not been signed at the site by
s. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
101 3 28 98 SC-28
Vardhman Group, Sec-23 Dwarka, New Delhi
Name not included in the list of Ecs accorded/pending
Not applied for consent to Establi
11.03.2008Ask him to apply fresh
Inspection report of SIT will be discuss
A
11.03.2008Ask him to apply fresh
Vardhman Group,Vardhman Land
NO N _ _ _ 04.07
SIT
with MOEF(as provided by MOEF)
sh Consent to Establish on the ground that a mall would generate effluent and huge D.G. Set which pollutes the air & create noise. Also ask him to file an affdaivt indicating date of start of construction & date of completion of construction, approved architectural drawing and completion certficate. Case will be taken up in April, 2008. 17.04.2008
ed.File in with Legal Cell for taking necessary action at their end.
Consent to Establish on the ground that a mall would generate effluent and huge D.G. Set which pollutes the air & create noise. Also ask him to file an affdaivt indicating date of start of construction & date of completion of construction, approved architectural drawing and completion certficate. Case will be taken up in April, 2008. 17.04.200
Developers (P) Ltd., G-9, Vardhman Trade Centre,
DDA Building, Nehru Place, Delhi - 19.
File being studied administratively for appropriate action on the court case. 28.5.08Call on 29.5.08 29.5.08In 04 Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get stay. DPCC through SIT must get the fresh inspection done focusing on
8File being studied administratively for appropriate action on the court case. 28.5.08Call on 29.5.08 29.5.08In 04 Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get stay. DPCC through SIT must get the fresh inspection
whether the projects fall within the notification of 07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate
done focusing on whether the projects fall within the notification of 07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-
from DDA for sector-23 is dated 04.12.2006. The earlier inspection reports have not been signed at the site by the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision
7 & 19 and occupancy certificate from DDA for sector-23 is dated 04.12.2006. The earlier inspection reports have not been signed at the site by the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Due to want of time, SIT report may be
to be ratified in the next CMC meeting.
submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
107 3 34 99 SC-34
Parsvnath Developers Ltd in construction with M/s OCL Ltd Commercial Complex at Seelampur Metro
Name not included in the list of Ecs accorded/pending with MOEF(as provided by MOEF)
18/3/2008
89342 sq m
MCD- GW-NIL DIS-344 cu.m
120.33 crore
proposed 11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of constructi
Inspection report of SIT will be discussed.
A 11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
NO N _ _ _ The unit came for personal hearing today. Since Consent to Establish and Environmental Clearance have been filed and no construction has
17.07
SIT
on and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 18.06.2008 at 5.30 PM. 18.06.2008The unit
start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Call for personal hearing on 18.06.2008 at 5.30
been started, case may be taken up on 18.07.2008. Meanwhile SIT to inspect and report. Call on 18.07.2008.
came for personal hearing today. Since Consent to Establish and Environmental Clearance have been filed and no construction has been started, case may be taken up on 18.07.2008. Meanwhile SIT to inspect and report. Call on 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear
PM. 18.06.2008The unit came for personal hearing today. Since Consent to Establish and Environmental Clearance have been filed and no construction has been started, case may be taken up on 18.07.2008. Meanwhile SIT to inspect and report. Call on 18.07.2008. 13.08.2008Due to want of time, SIT report may be submitted
decision to be ratified in the next CMC meeting.
administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
109 3 36 100
SC-36
Parsvnath Developers Ltd in construction with M/s OCL Ltd Construction of Commercial Complex at Shahdara Metro
Not applied for consent to Establish
11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of construction and
Inspection report of SIT will be discussed.
A 11.03.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things : 1. Consent to Establish.2. Environmental Clearance.3. Affidavit indicating date of start of
Parsvnath Developers Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
D N _ _ _ SIT to inspect and report. Call on 18.07.2008
17.07
SIT
completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008
Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Issue notice for closure. Call on 18.06.2008. 18.06.2008SIT to
construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.Case will be taken up in April, 2008 CMC. 17.04.2008
Issue final reminder to the unit to file the missing documents by 14.05.2008. Call on 14.05.2008. 23.5.08Issue notice for closure. Call on 18.06.2008.
inspect and report. Call on 18.07.2008 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
18.06.2008SIT to inspect and report. Call on 18.07.2008 13.08.2008Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting.
8 1 8 101
SA-8
Sewa International Fashion Ltd. (City Square Mall), Plot No 7, Shivaji Place, Rajouri Garden, Delhi
Built up area Plot No 7 : 10794.61 sqm Plot No 8 : 11791.6 sqm
Applied for Consent to Establish in two different names for plot no 7 & 8
Built up area Plot No 7 : 10794.61 sqm Plot No 8 : 11791.6 sqm
Plot No 7 : 100 KLDPlot No 8 : 69.2 Kld
Plot No 7 : 25.8 Cr.Plot No 8 : 21.07 Cr.
Plot No 7 : Dec, 2005Plot No 8 : Dec, 2005
The unit may be asked to apply for environmental clearance, since the same unit is setting up two adjacent malls which will be construed
NA
The unit may be asked to apply for environmental clearance, since the same unit is setting up two adjacent malls which will be construed
as one mall unless otherwise clearly justified. Affidavit for date of construction and completion, architectural drawing & completion certificate may be filed by 25.3.08. 03.4.08Let SEE study the file and take up on 10.04.2008. 17.04.2008While the unit has filed the affidavit, it has not filed completion certificate and the unit may be issued a
as one mall unless otherwise clearly justified. Affidavit for date of construction and completion, architectural drawing & completion certificate may be filed by 25.3.08. 03.4.08Let SEE study the file and take up on 10.04.2008. 17.04.2008While the unit has filed the affidavit, it has not filed completion certificate and the unit may
reminder to do so within 15 days. Call on 14.05.2008. 21.05.2008The unit has two malls adjacent to each other and the total built up area exceeds 20000 sqm. Let SIT to inspect and report by 03.06.2008. Call on 03.06.2008. 18.06.2008In view of the fact that there is no clarity on whether plot no 7 & 8 are distinct, call for personal hearing at 7.00 PM
be issued a reminder to do so within 15 days. Call on 14.05.2008. 21.05.2008The unit has two malls adjacent to each other and the total built up area exceeds 20000 sqm. Let SIT to inspect and report by 03.06.2008. Call on 03.06.2008. 18.06.2008In view of the fact that there is no clarity on whether plot no 7 & 8 are distinct, call for personal
on 11.07.2008. 11.07.2008The unit came for personal hearing today. It has very cleverly tried to conceal the facts that two plots are different while it runs similar entity for both the plots thereby united it in terms of pollution and its treatment. The unit is in operation since September, 2005 without Consent to Establish and without Environmental
hearing at 7.00 PM on 11.07.2008. 11.07.2008The unit came for personal hearing today. It has very cleverly tried to conceal the facts that two plots are different while it runs similar entity for both the plots thereby united it in terms of pollution and its treatment. The unit is in operation since September, 2005 without Consent to Establish and without
Clearance which it should have taken. Since the waste water discharge whether taken singly or jointly is more than 50000 litres / day therefore it was covered under EIA notification dated 07.07.2004 thereby requiring to obtain Environmental Clearance from MOEF. The combined built up area is more than 26000 sqm therefore MS, DPCC may write to Addl. Secretary, MOEF for calling the
Environmental Clearance which it should have taken. Since the waste water discharge whether taken singly or jointly is more than 50000 litres / day therefore it was covered under EIA notification dated 07.07.2004 thereby requiring to obtain Environmental Clearance from MOEF. The combined built up area is more than 26000 sqm therefore MS, DPCC may write
unit for submission of application under the EIA notifications, as this is an attempt to nullify the law through clever means. The management of the two plots is the same hand though the ownership of the plot may be in different hands. The Committee feels that end of justice will be met if a cash penalty of 1 % of the project cost and Bank Guarantee of 2 % of the project cost is deposited for the
to Addl. Secretary, MOEF for calling the unit for submission of application under the EIA notifications, as this is an attempt to nullify the law through clever means. The management of the two plots is the same hand though the ownership of the plot may be in different hands. The Committee feels that end of justice will be met if a cash penalty of 1 % of
projects on both plots i.e. Plot No 7 & Plot No 8. The representative came for the hearing gave the undertaking for depositing the same by 17.07.2008 for both the projects. If the units do so, Consent to Establish be issued to both the units and reported in CMC on 17.07.2008. Call on 17.07.2008. 17.07.2008 During the course of CMC meeting, the unit filed a
the project cost and Bank Guarantee of 2 % of the project cost is deposited for the projects on both plots i.e. Plot No 7 & Plot No 8. The representative came for the hearing gave the undertaking for depositing the same by 17.07.2008 for both the projects. If the units do so, Consent to Establish be issued to both the units and reported in CMC on 17.07.2008. Call on
cash penalty of Rs. 25.80 Lakhs in one case (plot no 7) and Rs. 21.07 for another case (plot no 8) to comply with the decision of CMC in its meeting dated 11.07.2008. The unit says that he will file Bank Guarantee in 03-04 days. If, the unit files the Bank Guarantee before the next CMC, Consent to Establish may be issued at the same time. Call on 24.07.2008 for compliance report.
17.07.2008. 17.07.2008 During the course of CMC meeting, the unit filed a cash penalty of Rs. 25.80 Lakhs in one case (plot no 7) and Rs. 21.07 for another case (plot no 8) to comply with the decision of CMC in its meeting dated 11.07.2008. The unit says that he will file Bank Guarantee in 03-04 days. If, the unit files the Bank Guarantee before the next CMC, Consent
24.07.2008File to be dealt with administratively as submitted.
13.08.2008No action.
to Establish may be issued at the same time. Call on 24.07.2008 for compliance report. 24.07.2008File to be dealt with administratively as submitted. 13.08.2008No action.
9 9 102
SA-9
Discovery State Pvt. Ltd. (City Square Mall), Plot No 8, Shivaji Place, Rajouri Garden, Delhi
Built up area Plot No 7 : 10794.61 sqm Plot No 8 : 11791.6 sqm
Applied for Consent to Establish in two different names for plot no 7 & 8
Built up area Plot No 7 : 10794.61 sqm Plot No 8 : 11791.6 sqm
Plot No 7 : 100 KLDPlot No 8 : 69.2 Kld
Plot No 7 : 25.8 Cr.Plot No 8 : 21.07 Cr.
Plot No 7 : Dec, 2005Plot No 8 : Dec, 2005
The unit may be asked to apply for environmental clearance, since the same unit is setting up two adjacent malls which will be construed as one mall unless otherwise clearly
NA The unit may be asked to apply for environmental clearance, since the same unit is setting up two adjacent malls which will be construed as one mall unless otherwise clearly
justified. Affidavit for date of construction and completion, architectural drawing & completion certificate may be filed by 25.3.08. 03.4.08Let SEE study the file and take up on 10.04.2008. 17.04.2008While the unit has filed the affidavit, it has not filed completion certificate and the unit may be issued a reminder to do so within 15 days. Call on
justified. Affidavit for date of construction and completion, architectural drawing & completion certificate may be filed by 25.3.08. 03.4.08Let SEE study the file and take up on 10.04.2008. 17.04.2008While the unit has filed the affidavit, it has not filed completion certificate and the unit may be issued a reminder to do so within 15
14.05.2008. 21.05.2008The unit has two malls adjacent to each other and the total built up area exceeds 20000 sqm. Let SIT to inspect and report by 03.06.2008. Call on 03.06.2008. 18.06.2008In view of the fact that there is no clarity on whether plot no 7 & 8 are distinct, call for personal hearing at 7.00 PM on 11.07.2008. 11.07.200
days. Call on 14.05.2008. 21.05.2008The unit has two malls adjacent to each other and the total built up area exceeds 20000 sqm. Let SIT to inspect and report by 03.06.2008. Call on 03.06.2008. 18.06.2008In view of the fact that there is no clarity on whether plot no 7 & 8 are distinct, call for personal hearing at 7.00 PM on 11.07.2008.
8The unit came for personal hearing today. It has very cleverly tried to conceal the facts that two plots are different while it runs similar entity for both the plots thereby united it in terms of pollution and its treatment. The unit is in operation since September, 2005 without Consent to Establish and without Environmental Clearance which it should have taken.
11.07.2008The unit came for personal hearing today. It has very cleverly tried to conceal the facts that two plots are different while it runs similar entity for both the plots thereby united it in terms of pollution and its treatment. The unit is in operation since September, 2005 without Consent to Establish and without Environmental Clearance which it should
Since the waste water discharge whether taken singly or jointly is more than 50000 litres / day therefore it was covered under EIA notification dated 07.07.2004 thereby requiring to obtain Environmental Clearance from MOEF. The combined built up area is more than 26000 sqm therefore MS, DPCC may write to Addl. Secretary, MOEF for calling the unit for submission of application under
have taken. Since the waste water discharge whether taken singly or jointly is more than 50000 litres / day therefore it was covered under EIA notification dated 07.07.2004 thereby requiring to obtain Environmental Clearance from MOEF. The combined built up area is more than 26000 sqm therefore MS, DPCC may write to Addl. Secretary, MOEF for calling
the EIA notifications, as this is an attempt to nullify the law through clever means. The management of the two plots is the same hand though the ownership of the plot may be in different hands. The Committee feels that end of justice will be met if a cash penalty of 1 % of the project cost and Bank Guarantee of 2 % of the project cost is deposited for the projects on both plots i.e. Plot No 7 & Plot No
the unit for submission of application under the EIA notifications, as this is an attempt to nullify the law through clever means. The management of the two plots is the same hand though the ownership of the plot may be in different hands. The Committee feels that end of justice will be met if a cash penalty of 1 % of the project cost and Bank Guarantee
8. The representative came for the hearing gave the undertaking for depositing the same by 17.07.2008 for both the projects. If the units do so, Consent to Establish be issued to both the units and reported in CMC on 17.07.2008. Call on 17.07.2008. 17.07.2008 During the course of CMC meeting, the unit filed a cash penalty of Rs. 25.80 Lakhs in one case
of 2 % of the project cost is deposited for the projects on both plots i.e. Plot No 7 & Plot No 8. The representative came for the hearing gave the undertaking for depositing the same by 17.07.2008 for both the projects. If the units do so, Consent to Establish be issued to both the units and reported in CMC on 17.07.2008. Call on 17.07.2008. 17.07.2008
(plot no 7) and Rs. 21.07 for another case (plot no 8) to comply with the decision of CMC in its meeting dated 11.07.2008. The unit says that he will file Bank Guarantee in 03-04 days. If, the unit files the Bank Guarantee before the next CMC, Consent to Establish may be issued at the same time. Call on 24.07.2008 for compliance report. 24.07.2008File to be dealt with
During the course of CMC meeting, the unit filed a cash penalty of Rs. 25.80 Lakhs in one case (plot no 7) and Rs. 21.07 for another case (plot no 8) to comply with the decision of CMC in its meeting dated 11.07.2008. The unit says that he will file Bank Guarantee in 03-04 days. If, the unit files the Bank Guarantee before the next CMC, Consent to Establish may be issued at the same
administratively as submitted.
13.08.2008No action.
time. Call on 24.07.2008 for compliance report. 24.07.2008File to be dealt with administratively as submitted. 13.08.2008No action.
20 1 20 103
SA-20
Magestic Agrotech Pvt Ltd,Commercial Building at Plot No. A, Block A, Community Centre, Vikaspuri, New Delhi
13.06.2008
13.05.2008
_ 17.04.2008Ask the unit to file the Consent to Establish and Environmental Clearance. Call on 14.05.2008. 21.05.2008SIT to inspect and report on MOEF direction to stop constructi
Unit has deposited cash penalty of Rs. 20 Lakhs and BG of Rs. 20 Lakhs on 23.07.2008. Chairman, DPCC has directed to issue CTE and confirm in
NA 17.04.2008Ask the unit to file the Consent to Establish and Environmental Clearance. Call on 14.05.2008. 21.05.2008SIT to inspect and report on MOEF direction to stop constructi
Magestic Agrotech Pvt Ltd,Commercial Building,Plot No. A-3, Mohan Co-operative Industry Area, Mathura Road, New delhi-44
The EIA Trainee will get the order from MOEF dated 02.04.2008 against this unit with due authorization
(i) One borewell found at site without permission from CGWA for ground water drawl. (ii) Waste wate
No action.
Z
on. Call on 03.06.2008. 18.06.2008(i) One borewell found at site without permission from CGWA for ground water drawl. (ii) Waste water generation is 3.2 KLD. No indication of its treatment.(iii) D.G. Sets of 62 KVA & 125 KVA with acoustic enclosure and inadequate stack height and 3rd D.G. Set of 125 KVA is without acoustic enclosure and without adequate
CMC on 24.07.2008. Acordingly, CTE has been issued.
on. Call on 03.06.2008. 18.06.2008(i) One borewell found at site without permission from CGWA for ground water drawl. (ii) Waste water generation is 3.2 KLD. No indication of its treatment.(iii) D.G. Sets of 62 KVA & 125 KVA with acoustic enclosure and inadequate stack height and 3rd D.G. Set of 125 KVA is without acoustic enclosure and
by MS. Call for personal hearing on 11.07.2008 at 8.00 PM.
r generation is 3.2 KLD. No indication of its treatment.(iii) D.G. Sets of 62 KVA & 125 KVA with acoustic enclosure and inadequate stack height and 3rd D.G. Set of 125 KV
stack height.
Call for personal hearing at 8.00 PM on 11.07.2008. 26.06.2008The EIA Trainee will get the order from MOEF dated 02.04.2008 against this unit with due authorization by MS. Call for personal hearing on 11.07.2008 at 8.00 PM. 11.07.2008The unit came for personal hearing today. The cost of the project is Rs 320 Crores.
without adequate stack height.
Call for personal hearing at 8.00 PM on 11.07.2008. 26.06.2008The EIA Trainee will get the order from MOEF dated 02.04.2008 against this unit with due authorization by MS. Call for personal hearing on 11.07.2008 at 8.00 PM. 11.07.2008The unit came for personal hearing today. The cost of the
A is without acoustic enclosure and without adequate stack height.
Call for personal hearing at 8.00 PM on 11.07.2008.
The unit has carried out excavation work equivalent to the 10 % of the total construction work. Taking precedence of the decision taken in the past in the similarly placed cases, pro rata cash penalty of 10 % of the 0.5 % of the project cost i.e. Rs. 20 Lakhs and equivalent amount as Bank Guarantee valid for three years may be deposited by 24.07.2008. Call on 24.07.2008.
project is Rs 320 Crores. The unit has carried out excavation work equivalent to the 10 % of the total construction work. Taking precedence of the decision taken in the past in the similarly placed cases, pro rata cash penalty of 10 % of the 0.5 % of the project cost i.e. Rs. 20 Lakhs and equivalent amount as Bank Guarantee valid for three years may be deposited by 24.07.200
24.07.2008No action.
8. Call on 24.07.2008. 24.07.2008No action.
34 2 6 104
SB-6
Gahoi Build Well Ltd Proposed Commercial Complex name East Centre Mall at Plot no 10 Laxmi Nagar District Centre
N.A 24/03/08
5189.19 (as per inspection
95 KLD(GW)/70(WW)
31 Crores
2006 -2008
10.03.2008Ask him to file Consent to Establish & environmental clearance. Case to be put up on 25.03.2008. Issue fresh letter.Affidavit for date of construction and completion, architectural drawing & completion certificate if received may be filed. 03.4.2008Unit be inspected
Cash penalty and BG submitted. Accordingly, consent isued.
NA 10.03.2008Ask him to file Consent to Establish & environmental clearance. Case to be put up on 25.03.2008. Issue fresh letter.Affidavit for date of construction and completion, architectural drawing & completion certificate if received may be filed. 03.4.2008
Gahoi Build Well Ltd., 701, Mercantile House,
15, KG Marg, New Delhi - 1
N _ 25284 24-03-08
(i) No permission from CGWA for ground water drawl. (ii) Waste water generation is 70 KLD. (iii) D.G. Sets of 500 KVA, 380 KVA & 250 KV
31.07
by CMC and put up on 10.4.2008. 11.04.2008SIT will inspect and report by 30.04.2008. 01.05.2008The SIT report clarifies that the built up area is about 5000 sqm and therefore does not require Environmental Clearance. However, the unit has applied for Consent to Establish and SIT report talks about three D.G. Sets with proper
Unit be inspected by CMC and put up on 10.4.2008. 11.04.2008SIT will inspect and report by 30.04.2008. 01.05.2008The SIT report clarifies that the built up area is about 5000 sqm and therefore does not require Environmental Clearance. However, the unit has applied for Consent to Establish and SIT report talks
A with acoustic enclosure.
Call for personal hearing at 5.00 PM on 18.07.2008.
stack height and inbuilt acoustic enclosure. However, SIT is silent on waste water discharge. The Consent to Establish application shows waste water discharge of 70 KLD.
In view of the above let the unit file an adequacy report and payment of water cess details. Call on 03.06.2008. 28.5.08Since water source & waste water discharge details are
about three D.G. Sets with proper stack height and inbuilt acoustic enclosure. However, SIT is silent on waste water discharge. The Consent to Establish application shows waste water discharge of 70 KLD.
In view of the above let the unit file an adequacy report and payment of water cess details. Call on 03.06.2008. 28.5.08Since
not available. Unit may be asked to file these along with the adequacy report and payment of water cess. Issue notice without waiting for minutes. Call on 03.06.2008. 18.06.2008(i) No permission from CGWA for ground water drawl. (ii) Waste water generation is 70 KLD. (iii) D.G. Sets of 500 KVA, 380 KVA & 250 KVA with acoustic enclosure.
Call for
water source & waste water discharge details are not available. Unit may be asked to file these along with the adequacy report and payment of water cess. Issue notice without waiting for minutes. Call on 03.06.2008. 18.06.2008(i) No permission from CGWA for ground water drawl. (ii) Waste water generation is 70 KLD. (iii) D.G. Sets of
personal hearing at 5.00 PM on 18.07.2008. 17.07.2008 The unit came for personal hearing today. It has been sourcing ground water for more than two years without CGWA clearance. The adequacy report also indicates that the standards are not being met w.r.t. TSS & BOD. The unit has also filed wrong affidavit w.r.t effluent discharge and filing of Consent to Establish.
500 KVA, 380 KVA & 250 KVA with acoustic enclosure.
Call for personal hearing at 5.00 PM on 18.07.2008. 17.07.2008 The unit came for personal hearing today. It has been sourcing ground water for more than two years without CGWA clearance. The adequacy report also indicates that the standards are not being met w.r.t. TSS & BOD. The unit has also
In view of the above, the unit is directed to pay damages of 0.5 % of project cost as cash penalty & 0.5 % of project cost as Bank Guarantee valid for three years. To be complied by 31.07.2008. Call on 31.07.2008. 31.07.2008Unit has asked for one month time. Call on 20.08.2008. 17.09.2008No action.
filed wrong affidavit w.r.t effluent discharge and filing of Consent to Establish.
In view of the above, the unit is directed to pay damages of 0.5 % of project cost as cash penalty & 0.5 % of project cost as Bank Guarantee valid for three years. To be complied by 31.07.2008. Call on 31.07.2008. 31.07.2008Unit has asked for one month
time. Call on 20.08.2008. 17.09.2008No action.
39 2 11 105
SB-11
MGF Developers Ltd Proposed Commercial Mall Namely MGF City Mall at Khyberpass, New Delhi
29.02.2007
21/10/05
48216.481
200(MCD)+696(GW)/ 225(WW)
125Cr. 11.03.2008Unit has filed both Environmental Clearance and application for Consent to Establish. The unit may be asked to file item-wise compliance of all the conditions of Environmental Clearance in the construction phase and the operation phase in the form of an affidavit. Affidavit for date of
As per decision of CMC dated 17.07.2008, unit has submitted Rs. 6 Lakhs as cash peanlty & Rs. 6 Lakhs as Bank Guarante on 24.07.2008 and requested for 2-3 days time for submision of fresh CTE application along with
NA 11.03.2008Unit has filed both Environmental Clearance and application for Consent to Establish. The unit may be asked to file item-wise compliance of all the conditions of Environmental Clearance in the construction phase and the operation phase in the form of an affidavit. Affidavit
MGF Developers Limited ,17-B, MGF House, Asaf Ali Road, New Delhi-02
D _ 16794 21-10-05
Call for personal hearing on 18.07.2008 at 7.30 PM.
Consent to Establish to be issued as soon as it files the original Consent to Establish application without fee. Call on 31.07.2008.
31.07
construction and completion, architectural drawing may also be filed by 31.3.08. Take up in April CMC. 11.04.2008Reminder may be issued to the unit to file a clear affidavit of date of start of construction and compliance of the construction phase conditions so far. Call on 30.04.2008. 01.05.2008Call on 14.05.2008. 23.5.08The complianc
required documents without consent fee as decided by the Committee. As decided in CMC meeting dated 31.07.2008, CTE issued.
for date of construction and completion, architectural drawing may also be filed by 31.3.08. Take up in April CMC. 11.04.2008Reminder may be issued to the unit to file a clear affidavit of date of start of construction and compliance of the construction phase conditions so far. Call on 30.04.2008. 01.05.2008Call on 14.05.2008.
e affidavit of Environmental Clearance conditions is not proper and does not indicate anything about construction phase compliance. Issue notice to the unit to file an affidavit indicating date of start of construction & date of completion of construction. Also an affidavit item-wise compliance in terms of what has been done by the unit w.r.t. Environmental Clearance conditions during the
23.5.08The compliance affidavit of Environmental Clearance conditions is not proper and does not indicate anything about construction phase compliance. Issue notice to the unit to file an affidavit indicating date of start of construction & date of completion of construction. Also an affidavit item-wise compliance in terms of what has been done by the unit w.r.t. Environm
construction phase be sought. The unit may also be asked to indicate source of water drawl with permission, treatment of waste water details and whether STP has been installed. If so, adequacy report may be filed. Details of D.G. Set with stack height also not provided. Issue notice to the unit on the above lines. Call on 25.06.2008. 25.06.2008Call for
ental Clearance conditions during the construction phase be sought. The unit may also be asked to indicate source of water drawl with permission, treatment of waste water details and whether STP has been installed. If so, adequacy report may be filed. Details of D.G. Set with stack height also not provided. Issue notice to the unit on the above lines. Call on
personal hearing on 18.07.2008 at 7.30 PM. 17.07.2008The unit came for personal hearing today. The cost of the project is Rs 125 Crores. The unit has carried out excavation work. Cash penalty of 10 % of the 0.5 % of the project cost i.e. Rs. 6 Lakhs and equivalent amount as Bank Guarantee valid for three years may be deposited by the unit by 24.07.2008. Call on
25.06.2008. 25.06.2008Call for personal hearing on 18.07.2008 at 7.30 PM. 17.07.2008The unit came for personal hearing today. The cost of the project is Rs 125 Crores. The unit has carried out excavation work. Cash penalty of 10 % of the 0.5 % of the project cost i.e. Rs. 6 Lakhs and equivalent amount as Bank Guarantee valid for
24.07.2008. 24.07.2008Consent to Establish to be issued as soon as it files the original Consent to Establish application without fee. Call on 31.07.2008. 31.07.2008Ask the unit to file copy of the project report which is required with the Conent to Establish application if not available on the file. Issue Consent to Establish immediately. Call on
three years may be deposited by the unit by 24.07.2008. Call on 24.07.2008. 24.07.2008Consent to Establish to be issued as soon as it files the original Consent to Establish application without fee. Call on 31.07.2008. 31.07.2008Ask the unit to file copy of the project report which is required with the Conent to Establish application if not
12.08.2008. 13.08.2008No action.
available on the file. Issue Consent to Establish immediately. Call on 12.08.2008. 13.08.2008No action.
43 2 15 106
SB-15
Omaxe Ltd. at Netaji Subhash Place, New Delhi
39390 28/09/07
31219.85
165(MCD) /135 (WW)
113.78Cr.
2007 11.03.2008Consent to Establish and Environmental Clearance filed. Date of completion mentioned in the Consent to Establish is 2007. Unit may be asked to file an affidavit indicating item-wise compliance of Environmental
BG & Penalty submittedAccordingly, consent issued.
NA 11.03.2008Consent to Establish and Environmental Clearance filed. Date of completion mentioned in the Consent to Establish is 2007. Unit may be asked to file an affidavit indicating item-wise compliance of Environmental
Omaxe Construction Ltd, 7,L.S.C Kalkaji New Delhi 110019
A 2007 18237 & 23705
18-05-06 & 28-09-07
Call for personal hearing on 25.07.2008 at 5.00 PM.
Call on 25.06.2008.
20.08
Clearance conditions in the construction phase and the operation phase. Take up in CMC in April, 2008.Affidavit for date of construction and completion, architectural drawing may be filed by April CMC 11.04.2008The unit has not filed a clear affidavit indicating item-wise conditions of construction phase mentioned in the Environmental Clearance. Reminder may be
Clearance conditions in the construction phase and the operation phase. Take up in CMC in April, 2008.Affidavit for date of construction and completion, architectural drawing may be filed by April CMC 11.04.2008The unit has not filed a clear affidavit indicating item-wise conditions of construction phase mentioned in the Environmental Clearance. Reminder
issued to the unit to do so by 30.04.2008. 01.05.2008Call for Personal hearing on 14.05.2008 at 7.00 PM. 14.05.2008SIT to inspect this unit on 14.05.2008 and this case will also be taken up in the special CMC meeting convened on 15.05.2008 for deciding the case of M/s Shop in Park by Pragya Products Private Ltd at Plot No. 2, Community Centre,
may be issued to the unit to do so by 30.04.2008. 01.05.2008Call for Personal hearing on 14.05.2008 at 7.00 PM. 14.05.2008SIT to inspect this unit on 14.05.2008 and this case will also be taken up in the special CMC meeting convened on 15.05.2008 for deciding the case of M/s Shop in Park by Pragya Products Private Ltd at Plot No.
Block B , Shalimar Bagh, Delhi. 15.5.08The Committee felt that despite Environmental Clearance the unit has not complied with the construction phase conditions and has taken the Environmental Clearance as a certificate for forgetting the environmental laws. In such circumstances the only way to bring the unit to book is to issue a notice for closure u/s 31(A) of the Air Act, 1981
2, Community Centre, Block B , Shalimar Bagh, Delhi. 15.5.08The Committee felt that despite Environmental Clearance the unit has not complied with the construction phase conditions and has taken the Environmental Clearance as a certificate for forgetting the environmental laws. In such circumstances the only way to bring the unit to book is to issue a notice for closure
and u/s 33(A) of the Water Act, 1974, giving 15 days time to comply. This letter may be drafted and shown to the Chairman on 19.05.2008 before issue. Call on 03.06.2008. 28.5.08Call on 11.06.2008. 18.06.2008Call on 25.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 5.00 PM. 24.07.2008The unit
u/s 31(A) of the Air Act, 1981 and u/s 33(A) of the Water Act, 1974, giving 15 days time to comply. This letter may be drafted and shown to the Chairman on 19.05.2008 before issue. Call on 03.06.2008. 28.5.08Call on 11.06.2008. 18.06.2008Call on 25.06.2008. 25.06.2008Call for personal hearing on 25.07.2008 at 5.00
came for personal hearing today. It has a total water consumption of 165 KLD and waste water generation of 135 KLD. At the time of inspection on 14.05.2008, the unit had not created the STP facility and had not installed the rain water harvesting structure and solar water heating & lighting system. The unit has done construction upto 12th floor without having Consent to Establish
PM. 24.07.2008The unit came for personal hearing today. It has a total water consumption of 165 KLD and waste water generation of 135 KLD. At the time of inspection on 14.05.2008, the unit had not created the STP facility and had not installed the rain water harvesting structure and solar water heating & lighting system. The unit has done construction upto
as required by the Environmental Clearance conditions imposed by MOEF. Unit also had not placed on record approval from Forest Department as required by the Environmental Clearance condition. It is clear that the unit started the construction much before it got the Environment Clearance i.e. 07 months prior to the Environment Clearance dated 11.04.2007. Further,
12th floor without having Consent to Establish as required by the Environmental Clearance conditions imposed by MOEF. Unit also had not placed on record approval from Forest Department as required by the Environmental Clearance condition. It is clear that the unit started the construction much before it got the Environment Clearance i.e. 07 months prior to
it has constructed the premises upto 12th floor without taking Consent to Establish.
In view of the above, DPCC was constrained to issue closure notice to the firm and in response to that, unit has come for personal hearing and claims that it will install the STP, rainwater harvesting structure and solar water system only after the construction is completed. Unit also
the Environment Clearance dated 11.04.2007. Further, it has constructed the premises upto 12th floor without taking Consent to Establish.
In view of the above, DPCC was constrained to issue closure notice to the firm and in response to that, unit has come for personal hearing and claims that it will install the STP, rainwater harvesting
claims that forest clearance is not required. The unit was advised to pay the required damages of 0.5 % of the project cost as cash penalty and 0.5 % of the project cost as Bank Guarantee valid for three years. This comes to about Rs. 55 Lakhs each. The unit claims that it requires approval of the Board for this purpose and seeks time upto 31.08.2008. Since the next CMC is
structure and solar water system only after the construction is completed. Unit also claims that forest clearance is not required. The unit was advised to pay the required damages of 0.5 % of the project cost as cash penalty and 0.5 % of the project cost as Bank Guarantee valid for three years. This comes to about Rs. 55 Lakhs each. The unit claims that it requires
scheduled on 20.08.2008, time allowed upto 20.08.2008. If the unit files the damages and Bank Guarantee by that time, Consent to Establish may be issued at the same time. It has been brought to the notice of the Committee that the old application for the Consent to Establish which was forwarded to MOEF is still shown in our record even though the new application dated 28.09.200
approval of the Board for this purpose and seeks time upto 31.08.2008. Since the next CMC is scheduled on 20.08.2008, time allowed upto 20.08.2008. If the unit files the damages and Bank Guarantee by that time, Consent to Establish may be issued at the same time. It has been brought to the notice of the Committee that the old application for the Consent to Establish
7, in original, has been filed. The validity of the old application, therefore, loses meaning. If conditions are complied with, Consent to Establish may be issued against the original application of September, 2007. Call on 20.08.2008. 21.08.2008No action.
which was forwarded to MOEF is still shown in our record even though the new application dated 28.09.2007, in original, has been filed. The validity of the old application, therefore, loses meaning. If conditions are complied with, Consent to Establish may be issued against the original application of September, 2007. Call on 20.08.2008.
21.08.2008No action.
44 2 16 107
SB-16
Upaj Buildcon Pvt Ltd Construction of Parking and Commercial Building at Sec-10 Rohini
CTE issued on 11.04.200
8.
21063.50 sq m
MCD-10.1 KLD GW-NIL DIS.-8 KLD
55.62 crore
NA 11.03.2008The unit applied for Consent to Establish and also filed Environmental Clearance. Further, MOEF has directed action against the unit for completing construction before Environmental Clearance was granted. An opportunity of being heard may be given to the unit on 25.03.2008 at 7.00 PM. Issue letter
CTE granted on 11/04/08
NA 11.03.2008The unit applied for Consent to Establish and also filed Environmental Clearance. Further, MOEF has directed action against the unit for completing construction before Environmental Clearance was granted. An opportunity of being heard may be given to the unit on 25.03.2008 at 7.00
Upaj Buildcon Pvt Ltd , 1 B1 , Twin Distt Centre Sec-10, RohiniNew Delhi - 85
A 39600
21748 39392 NA
immediately without waiting for the minutes. 03.04.2008Issue CTE if the unit submits a BG of Rs. Twenty Five Lakhs at tahe same time. 11.04.2008Complied. Consent to Establish issued. 28.5.08No action.
PM. Issue letter immediately without waiting for the minutes. 03.04.2008Issue CTE if the unit submits a BG of Rs. Twenty Five Lakhs at tahe same time. 11.04.2008Complied. Consent to Establish issued. 28.5.08No action.
51 2 23 108
SB-23
Mamram Magic Mall , Plot no 4, CS/0CF Sec-24 Ph-III Rohini, New Delhi-85
_ 39692 888.62 sq m
MCD-1500 L/D GW-8 KLD DIS.-500 L/D
7.99 crore
11.03.2008MS to inspect and report in April, 2008. 11.04.2008Call for personal
CTE granted on 23/05/08
NA
11.03.2008MS to inspect and report in April, 2008. 11.04.2008Call for personal
Mamram Majesty Mall,
D-11, Udyog Nagar,
Peera Garhi, New Delhi -
A 2008 24700 39692 NA
hearing on 14.05.2008 at 5.00 PM. 14.05.2008The unit appeared for the personal hearing and pleaded that it s a small unit and is not covered by Environmental Clearance. It also pleaded ignorance of Air & Water Acts and therefore applied for the same when instructed by DPCC. The unit pleaded for lenient treatment and has agreed in writing to submit Bank Guarantee of Rupees
hearing on 14.05.2008 at 5.00 PM. 14.05.2008The unit appeared for the personal hearing and pleaded that it s a small unit and is not covered by Environmental Clearance. It also pleaded ignorance of Air & Water Acts and therefore applied for the same when instructed by DPCC. The unit pleaded for lenient treatment and has agreed in writing to submit Bank
41.
Five Lakhs. The Committee feels that since the unit is small and has accepted the mistake of not having filed the Consent to Establish application in time, the unit may be allowed to file a Bank Guarantee of 1 % of project cost which comes about Rupees Eight Lakh. Since, DPCC has rounded of such Bank Guarantees to the nearest Five Lakh, the unit is allowed to
Guarantee of Rupees Five Lakhs. The Committee feels that since the unit is small and has accepted the mistake of not having filed the Consent to Establish application in time, the unit may be allowed to file a Bank Guarantee of 1 % of project cost which comes about Rupees Eight Lakh. Since, DPCC has rounded of such Bank Guarantees to the nearest
file, a Bank Guarantee of Rupees Five Lakh only, before 28.05.2008. If it does so, the Consent to Establish be issued to him at the same time and report to CMC on 28.05.2008. 28.5.08No action.
Five Lakh, the unit is allowed to file, a Bank Guarantee of Rupees Five Lakh only, before 28.05.2008. If it does so, the Consent to Establish be issued to him at the same time and report to CMC on 28.05.2008. 28.5.08No action.
53 2 25 109
SB-25
Jaksons Buildwell Private Ltd, Construcion of Commercial Mall name V3S Ring Road Mall at Plot no 21 Mangla
29.02.2008
31/03/08
51393.57 sq m
MCD-231 KLD GW-320 KLD DIS.-347 KLD
48 crore
N.A 11.03.2008Unit has filed Consent to Establish on 23.10.2007 & obtained EC on 29.02.2008. Website
CTE issued.
NA 11.03.2008Unit has filed Consent to Establish on 23.10.2007 & obtained EC on 29.02.2008. Website
Jaksons Buildwell Private Ltd, , B-1, Udyog Nagar,
Peere Ghari Chowk, Rohtak Road,
A 2008 24007 23-10-07
NA
m Place, Sec-03, Rohini, New Delhi
reveals that MOEF has directed the unit to stop construction. It is obvious that the unit has started construction much before Consent to Establish & EC. Unit may be asked to file an affidavit indicating start of construction, likely date of completion of construction and approved architectural drawing and item-wise compliance of conditions laid down in Environmental
reveals that MOEF has directed the unit to stop construction. It is obvious that the unit has started construction much before Consent to Establish & EC. Unit may be asked to file an affidavit indicating start of construction, likely date of completion of construction and approved architectural drawing and item-wise compliance of conditions laid down in Environmental
New Delhi-41
Clearance. Case to be taken up in April, 2008. 03.04.2008Personal hearing accorded unit was asked to submit penalty & BG by 10.04.2008. 11.04.2008No action. 28.5.08No action.
Clearance. Case to be taken up in April, 2008. 03.04.2008Personal hearing accorded unit was asked to submit penalty & BG by 10.04.2008. 11.04.2008No action. 28.5.08No action.
62 2 34 110
SB-34
Aggarwal Prestige Mall, Plot No 2, Road No 44, Facility Centre, Rani Bagh Road, Pitampura
Built up area :
7324.12 sqm
24.06.2008
7324.12
MCD-25 KLD / GW - 33 KLD / WW - 19.5 KLD (STP)
36.36 crores
2005 11.04.2008Let the Special Inspection Team do an inspection and submit a report by 30.04.2008. This case may be listed with the rest of
As per CMC decision, unit has submitted cash penalty of Rs. 5 Lakh and BG of Rs. 25 Lakhs on 11.07.2008. Accord
NA
11.04.2008Let the Special Inspection Team do an inspection and submit a report by 30.04.2008. This case may be listed with the rest of
Prestige Builtwell Pvt Ltd ,1001 10th floor, millenium tower, Netaji subash palace,Delhi-34
Call for personal hearing on 04.07.2008 at 5.30 PM
17.07
mall cases with effect from this meeting itself and be called on 30.04.2008. 01.05.2008SIT inspection report indicates that the complaint of Bansal Jewellers is correct and excavated soil has been dumped in front of the shop in a space belonging into DDA. The height of the soil dumped is approx. 2 meters. The SIT report also indicates that excavated soil has been dumped
ingy, CTE & revocation of closure directions issued.Letter received on 21.07.2008 regarding to refund the cash penalty and Bank Guarantee.
mall cases with effect from this meeting itself and be called on 30.04.2008. 01.05.2008SIT inspection report indicates that the complaint of Bansal Jewellers is correct and excavated soil has been dumped in front of the shop in a space belonging into DDA. The height of the soil dumped is approx. 2 meters. The SIT report also indicates that excavated
by Aggarwal Prestige Mall as a result of which Bansal Jewellers is facing acute problem for last six months.
In view of the above, issue notice to Aggarwal Prestige Mall under section 31(A) of the Air Act, 1981, to stop all excavation immediately and to confirm within one week. Case to be submitted on file administratively by 09.05.2008. This notice be issued without waiting the
soil has been dumped by Aggarwal Prestige Mall as a result of which Bansal Jewellers is facing acute problem for last six months.
In view of the above, issue notice to Aggarwal Prestige Mall under section 31(A) of the Air Act, 1981, to stop all excavation immediately and to confirm within one week. Case to be submitted on file administratively by 09.05.200
minutes. 23.5.08The reply of the unit has been perused. Ask him to file application for Consent to Establish, a copy of Environmental Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of plot area, builtup area, water drawl, waste water discharge, DG sets, noise
8. This notice be issued without waiting the minutes. 23.5.08The reply of the unit has been perused. Ask him to file application for Consent to Establish, a copy of Environmental Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of plot area, builtup area,
monitoring reports of DG sets. Call on 25.06.2008. 25.06.2008Call for personal hearing on 04.07.2008 at 5.30 PM 04.07.2008The unit appeared for personal hearing today and pleaded for lesser penalty for violation of the Air Act, which it has already committed. The unit will be discharging 25 KLD trade effluent and 20 KLD domestic
water drawl, waste water discharge, DG sets, noise monitoring reports of DG sets. Call on 25.06.2008. 25.06.2008Call for personal hearing on 04.07.2008 at 5.30 PM 04.07.2008The unit appeared for personal hearing today and pleaded for lesser penalty for violation of the Air Act, which it has already committed. The unit will
effluent and it will have three DG Sets.
In view of the pubic compliant received against the unit, the case of the unit was considered by Committee. In view of the fact that it has stopped excavation work on the directions of DPCC, the Committee felt that interests of justice will be met if Bank Guarantee of Rs. 25 Lakhs valid for three years and cash penalty of Rs. 5 Lakhs is imposed on the
be discharging 25 KLD trade effluent and 20 KLD domestic effluent and it will have three DG Sets.
In view of the pubic compliant received against the unit, the case of the unit was considered by Committee. In view of the fact that it has stopped excavation work on the directions of DPCC, the Committee felt that interests of justice will be met if Bank Guarantee of Rs. 25
unit in order to make up the 01 % of the total project cost. Unit has agreed to do so. If, unit complies with these conditions, Consent to Establish may be granted & the closure orders may be revoked. Call on 18.07.2008. 13.08.2008No action.
Lakhs valid for three years and cash penalty of Rs. 5 Lakhs is imposed on the unit in order to make up the 01 % of the total project cost. Unit has agreed to do so. If, unit complies with these conditions, Consent to Establish may be granted & the closure orders may be revoked. Call on 18.07.2008. 13.08.2008No action.
73 2 45 111
SB-45
Unitech Amusem
28.9.07 Applied
18751.08
MCD-214GW-200
217.88 Cr
2007 CTE and
CTE and
NA
CTE and
NA
ent Parks LtdSector - 10, Rohini,Delhi - 85
WW-20 CTO issued.
CTO issued.
CTO issued.
82 3 9 112
SC-9
Shantiniketan Buildwell Ltd. (Proposed Office Cum Commercial cum Complex At Plot D-3, P-3, B , Saket)
16/10/2007
29/05/08
16616 sq. m
MCD-145 KLD GW-nil Discharge-70 KLD
70 crore
Aug.2008 11.03.2008Since an attested copy has been received from the MOEF saying action may be taken, this is a development over and above the committee meeting decision on 30.01.2008. Like other cases an opportunity of being heard may be given to the unit on 25.03.2008 at 7.30 PM. He may be asked to bring
NA 11.03.2008Since an attested copy has been received from the MOEF saying action may be taken, this is a development over and above the committee meeting decision on 30.01.2008. Like other cases an opportunity of being heard may be given to the unit on 25.03.2008 at 7.30 PM. He may be
Shantiniketan Buildwell Ltd.,6, Community Centre,
Saket, New Delhi-17
YES A May 2008/Aug. 2008
21557 29-05-07
NA
approved architectural drawing & completion certifciate.
17.04.2008No action. 28.5.08No action
asked to bring approved architectural drawing & completion certifciate. 17.04.2008No action. 28.5.08No action
111 3 38 113
SC-38
Construction of commercial building at Plot No 1, City Centre, Sector-13, Dwarka by M/s Nettles Farms Pvt. Ltd.
EC not submitted.
13/05/2008
44005.4 sq m
MCD-9 KLD GW-168 KLD DIS-68 KLD
296.84 crore
17.04.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things by 30.04.2008.: 1. Consent to Establish.2.
Unit has submitted BG of Rs. 2.2 crores & cash penalty of Rs. 75 Lakhs.CTE issued on 08.07.2008.
NA 17.04.2008Issue final letter. Unit has not filed Environmental Clearance and Consent to Establish. Unit may be asked to file the following five things by 30.04.2008.: 1. Consent to Establish.
Nettles Farms Pvt Ltd, 11th Floor, Gopal Das Bhaan,
Barakhamba Road, New Delhi
_ The unit came for personal hearing today. It is yet to receive the Environmental Clearance and has applied
04.07
Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.
Call for personal hearing on 30.04.2008 at 8.30 PM. 30.04.2008The unit has neither filed Environmental Clearance nor Consent to Establish and other
2. Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate. Call for personal hearing on 30.04.2008 at 8.30 PM. 30.04.2008The unit has neither filed Environmental Clearance nor Consent to
for Consent to Establish. As advised by MOEF, the unit has stopped the excavation work after reaching the three basement levels. The unit has verbally assured that total project cost is Rs.
five documents instructed to be filed on 17.04.2008. Also the unit came for personal hearing today as directed. It appears logical that the unit is trying to evade the arms of law. In such a situation CMC cannot wait indefinitely and therefore unanimously feels that the following course of action should be taken:-
(a) Issue notice for closure u/s 31(A) of the Air Act, 1981 & u/s
Establish and other five documents instructed to be filed on 17.04.2008. Also the unit came for personal hearing today as directed. It appears logical that the unit is trying to evade the arms of law. In such a situation CMC cannot wait indefinitely and therefore unanimously feels that the following course of action should be taken:-
(a) Issue notice for closure u/s 31(A) of the Air
296 crore and it is willing to file a cash penalty of Rs. 75 Lakhs and the remaining amount of Rs. 2.2 crores by way of Bank Guarantee by 30.06.2008. The unit also says that
33(A) of the Water Act, 1974.(b) SIT may be asked to inspect the premises and report by 14.05.2008.
Call on 14.05.2008. 28.5.08The unit in its reply claims it had no knowledge of the personal hearing granted to the unit on 30.04.2008. It also claims that it has applied for Environmental Clearance which will be granted shortly. The unit also states that it has
Act, 1981 & u/s 33(A) of the Water Act, 1974.(b) SIT may be asked to inspect the premises and report by 14.05.2008.
Call on 14.05.2008. 28.5.08The unit in its reply claims it had no knowledge of the personal hearing granted to the unit on 30.04.2008. It also claims that it has applied for Environmental Clearance which will be granted
since it requires Board approval, a formal letter will be filed by 20.06.2008.
If the letter in compliance is filed by 20.06.2008 and the compliance is done by 30th June, 2008, file may
applied for Consent to Establish for both the plots. Beyond this, it has filed no other information which was required vide CMC decision dated 17.04.2008. Unit may be called for final hearing on 18.06.2008 at 6.00 PM along with the following documents:-1. Affidavit indicating date of start of construction and date of completion. 2. Completion certificate. 3. Approved
shortly. The unit also states that it has applied for Consent to Establish for both the plots. Beyond this, it has filed no other information which was required vide CMC decision dated 17.04.2008. Unit may be called for final hearing on 18.06.2008 at 6.00 PM along with the following documents:-1. Affidavit indicating date of start of construction and date of completio
be moved administratively for confirmation. Call on 03.07.2008.
architectural drawing. 4. details of water drawl. 5. Permission for water drawl. 6. Deatils of waste water discharge and 7. Details of D.G. Sets. 18.06.2008The unit came for personal hearing today. It is yet to receive the Environmental Clearance and has applied for Consent to Establish. As advised by MOEF, the unit has stopped the excavatio
n. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission for water drawl. 6. Deatils of waste water discharge and 7. Details of D.G. Sets. 18.06.2008The unit came for personal hearing today. It is yet to receive the Environmental Clearance and has applied for Consent to Establish. As advised by
n work after reaching the three basement levels. The unit has verbally assured that total project cost is Rs. 296 crore and it is willing to file a cash penalty of Rs. 75 Lakhs and the remaining amount of Rs. 2.2 crores by way of Bank Guarantee by 30.06.2008. The unit also says that since it requires Board approval, a formal letter will be filed by 20.06.2008.
If the letter in
MOEF, the unit has stopped the excavation work after reaching the three basement levels. The unit has verbally assured that total project cost is Rs. 296 crore and it is willing to file a cash penalty of Rs. 75 Lakhs and the remaining amount of Rs. 2.2 crores by way of Bank Guarantee by 30.06.2008. The unit also says that since it requires Board approval, a formal letter will be filed
compliance is filed by 20.06.2008 and the compliance is done by 30th June, 2008, file may be moved administratively for confirmation. Call on 03.07.2008. 13.08.2008No action.
by 20.06.2008.
If the letter in compliance is filed by 20.06.2008 and the compliance is done by 30th June, 2008, file may be moved administratively for confirmation. Call on 03.07.2008. 13.08.2008No action.
52 2 24 114
SB-24
North Ex Mall , Sec-9, Near Kadambiri C.G.H.S Rohini New Delhi-85
_ Not applied for consent to Establish
11.03.2008Unit is not responded to three letters issued by DPCC. He is given last and final opportunity to appear
Decision of CMC communicated to legal cell for necessary action. Legal Cell has already taken
OCT
11.03.2008Unit is not responded to three letters issued by DPCC. He is given last and final opportunity to
PP Buildwell Pvt Ltd, Sec-9, Near Kadambiri C.G.H.S Rohini
New Delhi-
N _ _ _ Call on 31.07.2008.
31.07
before the Committee on 17.03.2008 at 6.00 PM, failing, which the case will be decided ex-parte. 25.3.2008Prosecution be done by 28.3.2008 11.04.2008Inform MOEF about the summons issued by the Court. 23.5.08Sh. Prem Kumar to file an application for early hearing along with an order of Supreme Court relating to Andhra Pradesh State Pollution Control
action. Case was heard on 30.07.2008. Next date of hearing 20.10.2008.
appear before the Committee on 17.03.2008 at 6.00 PM, failing, which the case will be decided ex-parte. 25.3.2008Prosecution be done by 28.3.2008 11.04.2008Inform MOEF about the summons issued by the Court.
23.5.08Sh. Prem Kumar to file an application for early hearing along with an order of Supreme Court relating to Andhra Pradesh
85
Board referred to by Sh. Khwaja, Addl. Secretary, MOEF in the meeting of CPCB. Call on 25.06.2008. 25.06.2008Call on 31.07.2008. 31.07.2008Call in CMC in October after court hearing.
State Pollution Control Board referred to by Sh. Khwaja, Addl. Secretary, MOEF in the meeting of CPCB. Call on 25.06.2008. 25.06.2008Call on 31.07.2008. 31.07.2008Call in CMC in October after court hearing.
16 1 16 115
SA-16
Vardhman Plaza, Plot no 3, Motia , Khan, Paharganj, Delhi
Not submitted
Not submit
ted
_ _ _ _ 17.04.2008Issue notice to the unit to file Consent to Establish and Environmental Clearance along with
The file is with Legal Cell as a reply to be filed in court.
Sep
17.04.2008Issue notice to the unit to file Consent to Establish and Environmental Clearance along
Vardhman Plaza,Vardhman Trade centre,DDA Complex, Nehru Place,New Delhi-19
_ _ _ 04.07
SIT
an affidavit indicating date of start of construction & date of completion of construction and to submit approved architectural drawing and completion certificate. Call on 14.05.2008. 21.05.2008Since the unit has not filed Consent to Establish and not indicated details of waste water discharge and D.G. Set details, issue notice for closure. Call on
with an affidavit indicating date of start of construction & date of completion of construction and to submit approved architectural drawing and completion certificate. Call on 14.05.2008. 21.05.2008Since the unit has not filed Consent to Establish and not indicated details of waste water discharge and D.G. Set details, issue notice for closure. Call on
11.06.2008 with unit's response to closure notice.. 29.5.08In 04 Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get stay. DPCC through SIT must get the fresh inspection done focusing on whether the projects fall within the notification of
11.06.2008 with unit's response to closure notice.. 29.5.08In 04 Vardhman cases, 3 projects in Dwaraka and one project in Motia Khan, the Committee is of the view that the units have gone to the Court with unclean hands and managed to get stay. DPCC through SIT must get the fresh inspection done focusing on whether the projects fall within the notificatio
07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate from DDA for sector-23 is dated 04.12.2006. The earlier
n of 07.07.2004 with reference to the project investment (b) waste water discharge of 50 KLD as building plans were sanctioned on 22.02.2005, 04.08.2005, 15.02.2005 & 25.11.2003 and the construction has already been completed on 09.11.2006, 25.06.2007 on plot of Sector-7 & 19 and occupancy certificate from DDA for sector-23 is dated
inspection reports have not been signed at the site by the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Sh. Prem Kumar to handle this case in future. Call after court hearing in September, 2008.
04.12.2006. The earlier inspection reports have not been signed at the site by the official present of the project proponents. Therefore, SIT inspection may be conducted on the above said points. Inform CMC of ATR on 03.7.08. 13.08.2008Sh. Prem Kumar to handle this case in future. Call after court hearing in September, 2008.
32 2 4 116
SB-4
Parsvnath Developers Ltd
Not obtained
25/02/08
29642.57
55(DJB)+113(GW/TANKER
153.67Cr.
10.03.2008Ask him
As decided by CMC
This will be agenda item no 1 in the
Z
10.03.2008Ask him
Parsvnath Developers
yes _ 25010 25-02-08
Call for personal hearing
SIT to inspect
20.08
PH
in collabration with M/s OCL Ltd Construction of Integrated Station Building and Commercial development at Games Village,Near Akshardham Temple, Delhi
)/ 49.5(WW)
to file environmental clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion and approved architectural drawing. 11.04.2008Issue reminder without waiting for minutes. Call on 30.04.2008. 01.05.2008The unit has claimed that it does not require any approval and clearance for any developm
on 21.08.2008, copy of minutes sent to Member Secretary of SEIAA for necessary action.Unit submitted a letter.
SEIAA in its first meeting.
to file environmental clearance. Also ask the unit to file an affidavit indicating the date of construction & date of completion and approved architectural drawing. 11.04.2008Issue reminder without waiting for minutes. Call on 30.04.2008. 01.05.2008The unit has claimed that it does not require any approval and clearance for any
Ltd , 6th Floor, Arunachal Building 19, Barakhamba Road,New Delhi - 1
on 18.07.2008 at 7.00 PM
and report by 25.06.2008.
ent within the Akshardham Station of DMRC. It has therefore not filed any of the documents required by the CMC in its meetings on 10.03.2008, 11.03.2008 & 11.04.2008.
Perusal of the concession agreement shows that excluding the metro the total area exceeds 20000 sqm and therefore Environmental Clearance is required. This is also borne out of the
development within the Akshardham Station of DMRC. It has therefore not filed any of the documents required by the CMC in its meetings on 10.03.2008, 11.03.2008 & 11.04.2008.
Perusal of the concession agreement shows that excluding the metro the total area exceeds 20000 sqm and therefore Environmental Clearance is required. This is
fact that case is listed for Environmental Clearance hearing on 03.05.2008 as indicated by MOEF's letter in the file dated 16.04.2008. Therefore, the unit is not stating the correct position and once again directed to file all the documents required by CMC meeting minutes dated 11.03.2008 & 11.04.2008. If the unit fails to do so by 14.05.2008, CMC will be free to decide the case as per
also borne out of the fact that case is listed for Environmental Clearance hearing on 03.05.2008 as indicated by MOEF's letter in the file dated 16.04.2008. Therefore, the unit is not stating the correct position and once again directed to file all the documents required by CMC meeting minutes dated 11.03.2008 & 11.04.2008. If the unit fails to do so by
Environmental Laws. 23.05.2008Since there is no information about construction activity, and since no Environmental Clearance is available, SIT to inspect and report by 18.06.2008. Call on 18.06.2008. 18.06.2008SIT to inspect and report by 25.06.2008. 25.06.2008Call for personal hearing on 18.07.2008 at 7.00 PM
14.05.2008, CMC will be free to decide the case as per Environmental Laws. 23.05.2008Since there is no information about construction activity, and since no Environmental Clearance is available, SIT to inspect and report by 18.06.2008. Call on 18.06.2008. 18.06.2008SIT to inspect and report by 25.06.2008.
17.07.2008The unit was called for personal hearing today but he has written a letter seeking postponement due to outstation commitments. The SIT inspection report indicates the following:-
(a) D.G. Sets do not have adequate stack height.(b) 40 KLD of waste water generation without a separate STP.(c) One bore-well exists for which CGWA
25.06.2008Call for personal hearing on 18.07.2008 at 7.00 PM 17.07.2008The unit was called for personal hearing today but he has written a letter seeking postponement due to outstation commitments. The SIT inspection report indicates the following:-
(a) D.G. Sets do not have adequate stack height.(b) 40 KLD of waste water
clearance is required.(d) Environmental Clearance has not yet been granted.(e) The entire 20000 sqm has been constructed which includes the area of the mall also. The unit may be asked to file the EC immediately and correct the deficiencies noted by the SIT. Call for personal hearing on 20.08.2008 at 5.30 PM. 21.08.2008The unit came for personal hearing
generation without a separate STP.(c) One bore-well exists for which CGWA clearance is required.(d) Environmental Clearance has not yet been granted.(e) The entire 20000 sqm has been constructed which includes the area of the mall also.
The unit may be asked to file the EC immediately and correct the deficiencies noted by the SIT. Call for personal
today. It claims that it had submitted an application to the MOEF for withdrawal of the Environmental Clearance application on the ground that DMRC is the parent company building this integrated station-cum-commercial complex. Their proposal for withdrawal has been accepted by the MOEF without assigning any reason. In the personal hearing today, the unit repeatedly
hearing on 20.08.2008 at 5.30 PM. 21.08.2008The unit came for personal hearing today. It claims that it had submitted an application to the MOEF for withdrawal of the Environmental Clearance application on the ground that DMRC is the parent company building this integrated station-cum-commercial complex. Their proposal for withdrawal has
emphasized that the DMRC is above all environmental laws and it has such a mandate from the Govt. of India. It does not stand to reason that DMRC, which is the promoter of the metro rail and moves trains for the welfare of the people, can exercise power under EPA to exempt itself from Environmental Clearance for a commercial project being undertaken within its
been accepted by the MOEF without assigning any reason. In the personal hearing today, the unit repeatedly emphasized that the DMRC is above all environmental laws and it has such a mandate from the Govt. of India. It does not stand to reason that DMRC, which is the promoter of the metro rail and moves trains for the welfare of the people, can
premises, attracting the basic provisions of the EIA notification. The Committee feels that this is not an appropriate way of exempting the unit which is likely to create air, water and noise emissions substantially on a built-up area of nearly 29000 sqm. Since the State EIA Committee has been notified by the MOEF, this matter be placed as a first item on the agenda in the first meeting of State EIA Committe
exercise power under EPA to exempt itself from Environmental Clearance for a commercial project being undertaken within its premises, attracting the basic provisions of the EIA notification. The Committee feels that this is not an appropriate way of exempting the unit which is likely to create air, water and noise emissions substantially on a built-up area of nearly 29000 sqm.
e. The SIT inspection report must be placed before the State EIA Committee and the Committee may be requested to visit the site since the unit claims that no construction has been done on the commercial complex, whereas SIT report says that the entire 29000 sqm which includes the commercial complex ,has been constructed.
The unit has filed Consent to Establish
Since the State EIA Committee has been notified by the MOEF, this matter be placed as a first item on the agenda in the first meeting of State EIA Committee. The SIT inspection report must be placed before the State EIA Committee and the Committee may be requested to visit the site since the unit claims that no construction has been done on the commercial complex,
application which will be considered only after the matter of Environmental Clearance, will be decided by the State EIA Committee. Call on 17.09.2008. 28.08.2008This will be agenda item no 1 in the SEIAA in its first meeting.
whereas SIT report says that the entire 29000 sqm which includes the commercial complex ,has been constructed.
The unit has filed Consent to Establish application which will be considered only after the matter of Environmental Clearance, will be decided by the State EIA Committee. Call on 17.09.2008. 28.08.2008This will be agenda item no 1
in the SEIAA in its first meeting.
59 2 31 117
SB-31
Tirupati Construction Well (P) Ltd., Karkardooma, CBD, Delhi
_ Not applied
17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit indicating date of start of constructi
New Engineer of CMC visited the area. However, the address of the said unit was not traced out.Letter issued.Letter returned back undelievered.
Z 17.04.2008Issue notice asking the unit to apply for Consent to Establish & submit a copy of Environmental Clearance by 14.05.2008. Take up on 14.05.2008. 21.05.2008Ask the unit to file application for Consent to Establish, a copy of Environmental Clearance, affidavit indicating date of start of
Tirupati Construction Well (P) Ltd., Karkardooma, CBD,
Delhi
Not known
M/s Tirupati Construction as per SIT report is in the name of Indus Hotel and Spa at Plot No 11, CBD, Shahdara. The built up area proposed is more than 20000 Sqm but it does not have Environmental Clearance. Unit has already excavat
One of the new Engineer of CMC will visit the area and get the correct address and notice will be reissued by next week. Call on 18.07.2008.
Z 31.0
7
on, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008One of the new Engineer of CMC will visit the area and get the correct address and notice will be reissued by next week. Call on 18.07.2008.
construction, date of completion,a copy of completion certificate, approved architcural drawing, affidavit indicating plot area, built up area, details about waste water discharge and D.G. Sets. Call on 18.06.2008. 18.06.2008One of the new Engineer of CMC will visit the area and get the correct address and notice will be reissued by next
ed substantially (70 % ) without Consent to Establish and Environmental Clearance. Call the units for personal hearing on 04.07.2008 at 6.00 PM. Since information about Tiruputi has come from BSES efforts must be made through BSES, to get the exact address of the unit by concer
25.06.2008M/s Tirupati Construction as per SIT report is in the name of Indus Hotel and Spa at Plot No 11, CBD, Shahdara. The built up area proposed is more than 20000 Sqm but it does not have Environmental Clearance. Unit has already excavated substantially (70 % ) without Consent to Establish and Environmental Clearance. Call the units for personal hearing on 04.07.200
week. Call on 18.07.2008. 25.06.2008M/s Tirupati Construction as per SIT report is in the name of Indus Hotel and Spa at Plot No 11, CBD, Shahdara. The built up area proposed is more than 20000 Sqm but it does not have Environmental Clearance. Unit has already excavated substantially (70 % ) without Consent to Establish and Environmental
ned EE. Call on 04.07.2008.
8 at 6.00 PM. Since information about Tiruputi has come from BSES efforts must be made through BSES, to get the exact address of the unit by concerned EE. Call on 04.07.2008. 04.07.2008It appears Tirupati Construction Well (P) Ltd. is similar to Anush Finlease and Construction P Ltd, therefore, till further clarifications are received, both the units are to be
Clearance. Call the units for personal hearing on 04.07.2008 at 6.00 PM. Since information about Tiruputi has come from BSES efforts must be made through BSES, to get the exact address of the unit by concerned EE. Call on 04.07.2008. 04.07.2008It appears Tirupati Construction Well (P) Ltd. is similar to Anush Finlease and Construction P Ltd, therefore,
treated as one.
till further clarifications are received, both the units are to be treated as one.
TOTAL SL NO CMC
S. No of
CMCS.No Ref.
No
Name & Address
Name & Address
Date of EC accorded by MOEF
Bult Up Area
Water / Waste Water details
Total Project Cost
Date of Commis-sioning
Earlier Decisions
ATR/Remarks
Decision on 03.09.2008 Next
Date
Earlier decisions
Decision on 27.06.2008
Decision on 26.06.2008
Decision on 03.06.08
Decision on 24.07.08
Next date(Old)
4 1 4 1 A-4
MCD, Civic Center at J.N. Marg, Delhi
18-07-2007
04-08-05 1,16,755 Sqm
MCD--610.5 KLD & GW-- 541.8 KLD/ 488
789.41 crores
30-06-05 26.06.2008Reminder will be issued by MS to file compliance
The unit has submitted itemwise
Examine the compliance letter and put up in CMC on
07.10
18.02.2008Consent to Establish will be
Reminder will be issued by MS to file compliance affidavit of
Reminder will be issued by MS to file complia
Call on 11.07.2008.
31.07
KLD affidavit of Environmental Clearance conditions. Call on 31.07.2008. 31.07.2008MS to speak to Engineer Incharge of Civic Centre for reply. Call on 03.09.2008.
compliance report on 20.08.2008. However, itemwise compliance of EC conditions has not submitted on affidavit.
07.10.2008.
pending till EIA clearance is obtained.
17.3.2008MS to speak. Take up in April, 2008. 23.04.2008Issue letter to MCD as decided in CMC on 17.04.2008. 03.6.08Call on 11.07.2008. 26.06.2008Reminder will be issued by MS to file compliance affidavit of Environm
Environmental Clearance conditions. Call on 31.07.2008.
nce affidavit of Environmental Clearance conditions. Call on 31.07.2008.
ental Clearance conditions. Call on 31.07.2008. 31.07.2008MS to speak to Engineer Incharge of Civic Centre for reply. Call on 03.09.2008.
87 3 21 2 C-21
DLF Ltd., Group Housing Society at E Block, G.K-II
_ 14-5-2007
10733 metre square
MCD-1095./4KLD,GW-Nil, Waste water discharge-24.73 KLD
26.755 crore
Feb,2009 26.06.2008MS to study reply. Call on 11.07.2008. 31.07.2008 The unit came for personal hearing today. Since the matter is before the Court and the counter affidavit is being filed. Case to be taken up in CMC on 03
Counter affidavit has ben filed on 18.08.2008,Next date of hearing is 19.09.2008.
Call on 30.09.2008
30.09 23.04.2008Let the unit file an affidavit of previous directions regarding date of start of construction and date of completion by 14.05.2008. Call on 14.05.2008.
MS to study reply. Call on 11.07.2008.
MS to study reply. Call on 11.07.2008.
Issue notice for closure indicating the deficiencies observed by SIT. Call on 25.06.2008.
11.07
September, 2008.
13.05.2008SIT to inspect with special reference to waste water discharge and installation of D.G. Set and report to CMC by 03.06.2008. Unit may also be asked to clarify the waste water discharge figures which differ from their letter dated 21.02.2008 and their CTE application dated 17.04.2007. Call on 03.06.2008.
28.05.2008Decision of CMC dated 13.05.2008 will stand. 03.6.08Issue notice for closure indicating the deficiencies observed by SIT. Call on 25.06.2008. 26.06.2008MS to study reply. Call on 11.07.2008. 31.07.2008 The unit came for personal hearing today. Since the matter is
before the Court and the counter affidavit is being filed. Case to be taken up in CMC on 03 September, 2008.
89 3 23 3 C-23
IFFCO Sadan , C-1, District Centre Saket, Saket, New Delhi
Not applicable
18.06.2008
17912 DJ - 45 KLD / GW - Nil / WW - 5 KLD
86.455 crores
Apr-06 26.06.2008Unit to file details of water drawl including from ground water along with CGWA permission. Unit may also file details of waste water discharge and its treatment. Call on 31.07.2008. 31.07.2008Final reminder. Call on 03.09.2008.
Letter issued on 07.08.2008.No reply received so far.
Issue reminder. Call on 07.10.2008.
07.10 18.02.2008Ask the unit to apply for Consent to Establish. Also ask the previous EE to file his explanation on whose orders notice was issued. 17.3.2008MS to speak and also check
Unit to file details of water drawl including from ground water along with CGWA permission. Unit may also file details of waste water discharge and its treatment. Call on 31.07.2008.
Unit to file details of water drawl including from ground water along with CGWA permission. Unit may also file details of waste water discharge and its treatment. Call on
Time allowed. Call on 25.06.2008
31.07
from MOEF for Environmental Clearance. Take up in April, 2008. 23.04.2008Fresh reminder for Consent to Establish & Environmental Clearance. Call on 21.05.2008. 03.6..08Time allowed. Call on 25.06.2008 26.06.2008Unit to file details of water drawl
31.07.2008.
including from ground water along with CGWA permission. Unit may also file details of waste water discharge and its treatment. Call on 31.07.2008. 31.07.2008Final reminder. Call on 03.09.2008.
104 3 38 4 C-38
NBCC Commercial Centre, Plot NO 2, Community Centre, Phase-I, Okhla
_ 13.03.2008
25991 sqm
DJB - 339 Lt/dayGW - NilWW - Nil(STP proposed)
190 crores
Jan, 2009
26.06.2008Ask the unit to submit the following documents :-1. Affidavit indicating date of start of construction
Letter issued on 07.08.2008 for submitting EC.No reply
Issue reminder. Call on 07.10.2008.
07.10
26.06.2008Ask the unit to submit the following documents :-1. Affidavit indicating
Ask the unit to submit the following documents :-1. Affidavit indicating date of start of construction and date of
Ask the unit to submit the following documents :-1. Affidavit indicating date of start of
31.07
and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission from CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on 31.07.2008.
31.07.2008Ask the unit to file Enviornmental Clearance.
received so far.
date of start of construction and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission from CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on
completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission from CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on 31.07.2008.
construction and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission from CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearanc
Call on 03.09.2008.
31.07.2008. 31.07.2008Ask the unit to file Enviornmental Clearance. Call on 03.09.2008.
e. Call on 31.07.2008.
105 3 39 5 C-39
DMRC, I.T.Park, Block No 3, Shastri Nagar, Delhi
_ 05.06.2008
38841 sqm
MCD - NilGW - 288.7 KLDWW - Nil (STP proposed)
90 crores
April, 2010
26.06.2008Ask the unit to submit the following documents :-1. Affidavit indicating date of start of construction and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission from
Letter issued.Reply received.
Call for personal hearing 07.10.2008 at 5.00 PM.
07.10 PH
26.06.2008Ask the unit to submit the following documents :-1. Affidavit indicating date of start of construction and date of completion. 2. Completion certificate. 3. Approved architectural
Ask the unit to submit the following documents :-1. Affidavit indicating date of start of construction and date of completion. 2. Completion certificate. 3. Approved architectural drawing. 4. details of water drawl. 5. Permission from CGWA for
Ask the unit to submit the following documents :-1. Affidavit indicating date of start of construction and date of completion. 2. Completion certificate. 3. Approved architectural drawing.
31.07
CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on 31.07.2008.
31.07.2008Final reminder be issued. Call on 03.09.2008.
drawing. 4. details of water drawl. 5. Permission from CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on 31.07.2008. 31.07.2008Final reminder be issued. Call on 03.09.2008.
ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on 31.07.2008.
4. details of water drawl. 5. Permission from CGWA for ground water drawl. 6. Deatils of waste water & its treatment. 7. Details of D.G. Sets.8. Plot area. 9. Builtup Area. 10. Copy of Environmental Clearance. Call on 31.07.2008.
107 3 41 6 C-41
Indian Oil Corporation Ltd., Bijwasan Hook up of Mathura – Jalandhar Pipeline with Tikrikalan
24.06.2008
27.06.2008The unit has applied for Consent to Establish on 24.06.2008 vide I.D. No 26149. Ask the unit to submit the following documents by 31.07.2008:-(i) Affidavit indicating date of start of construction and date of completion. (ii) Completion certificate. (iii) Approved architectural drawing. (iv) Details of water drawl. (v) Permission from CGWA for ground water drawl. (vi) Details of
Letter issued.Reply received.
Ask the unit to file CGWA clearance. EE, CMC to check if EIA applicable. Compliance on rain water harvesting, composting and greening plan be sought. Call on 07.10.2008.
07.10 27.06.2008The unit has applied for Consent to Establish on 24.06.2008 vide I.D. No 26149. Ask the unit to submit the following documents by 31.07.2008:-(i) Affidavit indicating date of start of construction and date of completion. (ii) Completion certificate. (iii) Approved architectural
31.07
waste water & its treatment, and recyling. (vii) Details of D.G. Sets.(viii) Plot area. (ix) Built up Area. (x) Copy of Environmental Clearance. (xi) Solar water heating, rain water harvesting, composting & greening plan.Call on 31.07.2008.
31.07.2008Final reminder be issued. Call on 03.09.2008.
drawing. (iv) Details of water drawl. (v) Permission from CGWA for ground water drawl. (vi) Details of waste water & its treatment, and recyling. (vii) Details of D.G. Sets.(viii) Plot area. (ix) Built up Area. (x) Copy of Environmental Clearance. (xi) Solar water heating, rain water harvesting, composting &
greening plan.Call on 31.07.2008. 31.07.2008Final reminder be issued. Call on 03.09.2008.
96 3 30 7 C-30
Construction of Internal Data Center Building, at Greater Kailash-I, New Delhi
_ 29-1-2008
183000 Sq. metre
MCD-Quantity not mentioned, GW-Nil, Discharge-1560 KLD
300 Crore
Not mentioned
31.07.2008SIT report indicates no construction started. Consent to Establish application is not complete as the project report has not been filed. Ask the unit to file project report. Call on 03.09.2008. 13.08.2008The case of M/s Internal Data Center Building, at Greater
Letter issued on 07.08.2008.Reply along with project report on 11.07.2008.
10.09 23.04.2008Ask him to apply for Consent to Establish. Call on 21.05.2008. 03.6.08SIT to inspect and report. Call on 11.07.2008 31.07.2008SIT report indicates
SIT to inspect and report. Call on 11.07.2008
11.07 SIT
Kailash-I, New Delhi was taken up as Table Agenda Item. Due to want of time, SIT report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting. 28.08.2008Issue Consent to Establish.
no construction started. Consent to Establish application is not complete as the project report has not been filed. Ask the unit to file project report. Call on 03.09.2008. 13.08.2008The case of M/s Internal Data Center Building, at Greater Kailash-I, New Delhi was taken up as Table Agenda Item. Due to want of time, SIT
report may be submitted administratively by the SIT team for clear decision to be ratified in the next CMC meeting. 28.08.2008Issue Consent to Establish.
13 1 13 8 A-13
Hotel Queen Road Pvt. Ltd., 19, Ashoka Road, Connaught Place, New Delhi-01
Not applied
Granted on 01.06.2006
36.21 Sqm in Application & 20991Sqm in Reply
255 65.50 crores
___ 31.07.2008Unit has applied for authorization under HWM Rules. However, it is silent on three other directions given on 18.06.2008 (a) solar water heating system (b) CGWA permission
Letter issued.Reply received & requesting for extension of time.Applied for authorization under HWM Rules.
10.09 01.05.2008In response to the letter issued on 22.04.2008, the unit has not filed Environmental Clearance and claims that they have renovated
The unit has filed a reply claiming that it is out of the ambit of EIA because it completed its construction by 2004 before the notification came. It has
17.07
(c) Compliance Building code of BEE . Call on 03.09.2008. Meanwhile, Chairman, DPCC will inspect the premises since reply may have to be sent to VIP whose reference has come. 21.08.2008Nobody turned up for the hearing. File be submitted to the Chairman . Inspection by the Chairman along with SIT official to be conducted.
ITDC hotel and there was no change in architectural drawing and therefore it did not apply for Environmental Clearance. The unit has also not filed an affidavit indicating date of start of construction but has confirmed that the unit is not yet operational. The unit has also not filed architectural drawing and the completion
applied for Consent to Establish and confirms that it will follow the other laws like HWM Rules, Noise Rules, Solar water Heating, Rain Water Harvesting System.The claim of the unit that it completed construction by 2004 does not appear to be tenable because the hotel is yet to start its
certificate. MS may draft a letter to the unit reiterating the requirements of above documents and clearly specifying that the since the built up area is more than 20000 sqm it requires MOEF’s Environmental Clearance immediately. A copy of the letter may be sent to Addl. Secretary, MOEF & Joint Secretary, Hotels Ministry of
operations and could not be suspending the operations for 04 years without any significant reason. The Committee feels the unit should be called for personal hearing where it will submit all the clarifications the Committee members raise. Call on 11.06.2008 at 5.15 PM. Meanwhile, the unit may be asked
Tourism, Govt. of India.MS to clarify that the Consent to Establish cannot be renewed till the unit files Environmental Clearance. Finally, the unit may be issued a letter on the lines of Lodhi Hotel requiring it to comply with all the environmental legislations listed in the letter. Show the letter to Chairman administratively
to file clarification on the extent of ground water drawl and the permission for the same. It may also be asked to file its water cess returns from May, 2003 when it became applicable.
before issue. Call on 21.05.2008. 03.6.08The unit has filed a reply claiming that it is out of the ambit of EIA because it completed its construction by 2004 before the notification came. It has applied for Consent to Establish and confirms that it will follow the other laws like HWM Rules, Noise Rules,
Solar water Heating, Rain Water Harvesting System.The claim of the unit that it completed construction by 2004 does not appear to be tenable because the hotel is yet to start its operations and could not be suspending the operations for 04 years without any significant reason. The Committee feels the unit should be
called for personal hearing where it will submit all the clarifications the Committee members raise. Call on 11.06.2008 at 5.15 PM. Meanwhile, the unit may be asked to file clarification on the extent of ground water drawl and the permission for the same. It may also be asked to file its water cess returns from May, 2003
when it became applicable.
11.6.08The unit appeared for personal hearing. The representative of the unit, who appeared for the hearing, seeks 10 days time to check with his superiors and respond to the penalty of 1 % of the project cost. Call on 18.06.2008 at 7.30 PM for personal hearing and final order.
18.06.2008The unit came for personal hearing today. Since the unit had not started its operation till September, 2006 after renovation, the Committee feels that the unit being a large hotel with 440 rooms, will require the clearance from MOEF as per EIA notification dated 14.09.2006. The unit must therefore apply for
the same.
Unit has confirmed to DPCC that it will apply for authorization under HWM Rules. This must be done immediately. The unit has also confirmed that it will install Rain Water Harvesting Structure and Solar Water Heating System and this must be confirmed by 18.07.2008. The unit has filed its applicatio
n for renewal of consent. Since the unit claims that STP is working, adequacy report may be filed by 18.07.2008. The Building Code of BEE is also applicable and compliance of this must be confirmed by 18.07.2008. The unit in its application of 2007 indicates ground water drawl of 180 KLD, the unit must file the appropria
te permission from CGWA for this purpose. Call on 18.07.2008. 31.07.2008Unit has applied for authorization under HWM Rules. However, it is silent on three other directions given on 18.06.2008 (a) solar water heating system (b) CGWA permission (c) Compliance Building code of BEE . Call on 03.09.200
8. Meanwhile, Chairman, DPCC will inspect the premises since reply may have to be sent to VIP whose reference has come.
21.08.2008Nobody turned up for the hearing. File be submitted to the Chairman . Inspection by the Chairman along with SIT official to be conducted. 03.09.200
8Administrative decision read out and ratified. Call on 10.09.2008.
74 3 8 9 C-8 Maruti Udyog Limited , Plot No. 1 Vasant Kunj Mall, Vasant Kunj, New Delhi
29-11-06 13.04.2005
24567.5 sqm
MCD - 49.03 KLD / 37.2 KLD
90 crores
Oct-08 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
17.3.2008Take up in April, 2008. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. 23.04.2008Draft letters seeking
Unit has deposited cash penalty and BG of Rs. 45 Lakhs on 23.07.2008.
NA 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. 17.3.2008Take up in April, 2008. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of
Call for personal hearing on 31.07.2008 at 8.30 PM.
Call for personal hearing on 31.07.2008 at 8.30 PM.
SIT to inspect and report. Call on 11.06.2008
Since the unit has complied with decision of CMC meeting dated 17.07.2008, Consent to Establish has been issued.
Z
clarification have been put up which will be corrected and issued. 03.6.08SIT to inspect and report. Call on 11.06.2008 26.06.2008Call for personal hearing on 31.07.2008 at 8.30 PM. 17.07.2008The unit came for personal hearing. The unit started construction in March, 2006 about 8 months before grant of Environmental Clearance. The unit is almost at the verged
construction. 23.04.2008Draft letters seeking clarification have been put up which will be corrected and issued. 03.6.08SIT to inspect and report. Call on 11.06.2008 26.06.2008Call for personal hearing on 31.07.2008 at 8.30 PM. 17.07.2008The unit came for personal
of completion without obtaining Consent to Establish. The unit has total water consumption and discharge of 49 KLD which will be fully treated through an STP. Total project cost is Rs. 90 crores and considering that in similarly placed cases damages of 0.5 % of the project cost as cash penalty and 0.5 % of the project cost as Bank Guarantee has been taken, unit may be asked to do the same which amounts to Rs. 45
hearing. The unit started construction in March, 2006 about 8 months before grant of Environmental Clearance. The unit is almost at the verged of completion without obtaining Consent to Establish. The unit has total water consumption and discharge of 49 KLD which will be fully treated through an STP. Total project cost is Rs.
Lakhs as cash penalty and Rs. 45 Lakhs as Bank Guarantee valid for 3 years for complying with all environmental legislations applicable in the city. If, the unit complies these conditions before 24.07.2008, Consent to Establish may be granted to them at the same time and the compliance report will be filed before CMC on 24.07.2008. Call on 24.07.2008. 24.07.2008Since the unit has complied
90 crores and considering that in similarly placed cases damages of 0.5 % of the project cost as cash penalty and 0.5 % of the project cost as Bank Guarantee has been taken, unit may be asked to do the same which amounts to Rs. 45 Lakhs as cash penalty and Rs. 45 Lakhs as Bank Guarantee valid for 3 years for complyin
with decision of CMC meeting dated 17.07.2008, Consent to Establish has been issued.
g with all environmental legislations applicable in the city. If, the unit complies these conditions before 24.07.2008, Consent to Establish may be granted to them at the same time and the compliance report will be filed before CMC on 24.07.2008. Call on 24.07.2008. 24.07.2008Since the unit has complied with
decision of CMC meeting dated 17.07.2008, Consent to Establish has been issued.
44 2 15 10 B-15
Aman Hospitality Pvt. Ltd., (construction of '5 Star Hotel'), CBD Shahdara, Delhi
08.07.2008
04.04.2008
91, 444 Sqm
886 KLD in EC /615 KLD (STP)
866 Crores
__ 23.04.2008Reminder for taking up on 21.05.2008. 03.6.08Issue notice for closure for not applying for Consent to Establish. Call on 25.06.2008. 26.06.2008SIT to inspect and report. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 9.00 PM.
Applied for CTE on 04.04.2008 vide I.D. No. 25422.EC issued by MOEF on 08.07.2008.SIT report to be discussed.Unit has submitted a letter on 14.07.
17.09 PH
23.04.2008Reminder for taking up on 21.05.2008. 03.6.08Issue notice for closure for not applying for Consent to Establish. Call on 25.06.2008. 26.06.2008SIT to inspect and report. Call on
SIT to inspect and report. Call on 31.07.2008.
SIT to inspect and report. Call on 31.07.2008.
Issue notice for closure for not applying for Consent to Establish. Call on 25.06.2008.
31.07 SIT
Also ask item wise compliance affidavit for Environmental Clearance conditions before 20.08.2008. Proper fact sheet based on SIT report may be prepared.
2008 & requested to grant CTE as it is commonwealth games project and is required to be complted within a specific time fram.
31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 9.00 PM. Also ask item wise compliance affidavit for Environmental Clearance conditions before 20.08.2008. Proper fact sheet based on SIT report may be prepared. 21.08.2008The unit came for personal hearing and pleaded that its
Chairman is out of station. Call for personal hearing on 03.09.2008, at 6.30 PM. 03.09.2008The unit came for personal hearing today. It has built up area of 91,000 sqm approximately and has started construction by way of excavation since 09.06.2008. It has applied for Consent to Establish and obtained Environm
ental Clearance on 08.07.2008. The total project cost of Rs. 866 crores. As per the SIT inspection, excavation work is in progress and fugitive emissions were noted for which SIT observed that the concreted road would be required. Total water consumption is 1050 KLD as per the affidavit of the unit and
the sewage quantity is expected to be 555 KLD.
Unit claims that it has not done any environmental pollution and it is a building for Common Wealth Projects which DDA has given a clearance for excavation. Unit was indicated that excavation causes maximum air pollution and, therefore, no authority
other than the State Pollution Control Board or the MOEF can decide such matters since these are governed by Supreme Court orders. The unit sought time to file the item-wise compliance affidavit within 15 days. Time allowed till the CMC on 17.09.2008. The unit was also informed that the similarly situated circumsta
nces units have been asked to pay damage of 10 % of ½ % of the project cost,which in presnt case amounts to Rs. 43 Lakhs and equivalent amount of Bank Guarantee valid for three years. If the unit submits the same by 17.09.2008, Consent to Establish may be issued at the same time. Call for personal hearing on
17.09.2008 at 6.00 PM.
12 1 12 11 A-12
Tirupati Infraprojects Private Limited,
"Indus Hotel & Spa" Plot No. - D, Paschim Vihar Dist Centre, New Delhi
04.06.2008
24-04-08 __ __ __ __ 23.04.2008Issue notice to file Consent to Establish and environmental clearance by 14.05.2008. Call on 14.05.2008. 13.05.2008Unit has not yet filed Environmental Clearance as its case was discussed on 13.03.2008 and various documentary submissions were required by MOEF. In order to be sure about the factual information, SIT may be
Letter issued on 27.5.08.Reply awaited.SIT inspection report to be discussed.
10.09 23.04.2008Issue notice to file Consent to Establish and environmental clearance by 14.05.2008. Call on 14.05.2008. 13.05.2008Unit has not yet filed Environmental Clearance as its case was discussed on 13.03.2008 and various documentary submissions were
Call for personal hearing on 31.07.2008 at 7.30 PM. Meanwhile, item-wise Environmental Clearance conditions be filed by the unit.
Call for personal hearing on 31.07.2008 at 7.30 PM. Meanwhile, item-wise Environmental Clearance conditions be filed by the unit.
Take up on 11.06.2008.
31.07 PH
asked to inspect the premises and report by 10.06.2008. Call on 11.06.2008. Meanwhile, unit may be asked to submit a copy of Environmental Clearance once again. 03.6.08Take up on 11.06.2008. 26.06.2008Call for personal hearing on 31.07.2008 at 7.30 PM. Meanwhile, item-wise Environmental Clearance conditions be filed by the unit. 31.07.2008 The unit did not come for
required by MOEF. In order to be sure about the factual information, SIT may be asked to inspect the premises and report by 10.06.2008. Call on 11.06.2008. Meanwhile, unit may be asked to submit a copy of Environmental Clearance once again. 03.6.08Take up on 11.06.2008. 26.06.2008Call for
personal hearing today and it has not filed the compliance affidavit on conditions of Environmental Clearance. Issue notice & final reminder for filing item-wise Environmental Clearance conditions. Also the deficiencies noted by the SIT may also be listed in the notice. Call for personal hearing on 20.08.2008 at 6.00 PM.
personal hearing on 31.07.2008 at 7.30 PM. Meanwhile, item-wise Environmental Clearance conditions be filed by the unit. 31.07.2008 The unit did not come for personal hearing today and it has not filed the compliance affidavit on conditions of Environmental Clearance. Issue notice & final reminder for filing
item-wise Environmental Clearance conditions. Also the deficiencies noted by the SIT may also be listed in the notice. Call for personal hearing on 20.08.2008 at 6.00 PM. 21.08.2008The unit came for personal hearing today. It claims that due to ignorance of law they had started the construction without
taking the Consent to Establish. They were also under the impression that DDA clearance and the fact that this is a Common Wealth Project and is being monitored by DDA is enough to start the construction. The CMC had taken up this case earlier and it was found on 31.07.2008 that the unit did not come for personal hearing on 09.07.200
8 & 31.07.2008. The unit was therefore asked to file a compliance affidavit on the Environmental Clearance conditions. The Special Inspection Team(SIT) inspected the premises on 10.06.2008 and the deficiencies noted by the SIT were also indicated to the unit on 14.08.2008. The unit has not filed item-wise complian
ce of Environmental Clearance conditions through an affidavit, and has filed a simple letter in reply to the letter dated 14.08.2008 stating that they have removed one of the D.G. Sets and raised the stack height of the other. They have mentioned about two proposed rain water harvesting systems, green belt and have confirmed that no bore well
has been dug at the hotel site. The unit has also confirmed that the total built up area of about 70000 sqm is divided into three parts. Basement of 30000 sqm, ground & other floors covering about 40000 sqm. The entire excavation of three basements have been completed. Applying logic in terms of pollution created, approx. 40 % area has been
covered. Unit seeks time to consult its remaining Directors on the issue of imposition of damages and Bank Guarantee. Call for personal hearing on 28.08.2008, at 5.15 PM and the unit must file affidavit for item-wise compliance of Environment Clearance’s conditions before the personal hearing. 28.08.2008The unit
came for personal hearing today. It sought lenient view for payment for damages and Bank Guarantee on the lines of some similar cases decided by this Committee. It also highlighted that the High Level Committee of the Government had enabled the hotel site owners to start the excavation work and seek the required clearances
urgently.The Committee deliberated on the issue for about an hour and gave several options to the project proponent. Finally the Committee decided that 10 % of ½ % of the project cost of Rs. 475 crores i.e. Rs. 24 Lakhs may be taken as damages and equivalent amount as Bank Guarantee valid for three years. The unit has to file
these two by 10.09.2008. As soon as the damages and Bank Guarantee are paid, Consent to Establish should be issued at the same time. Call on 10.09.2008.
1 1 1 12 A-1
Controller & Audit General (C& AG) Office Complex at Pocket 9, Deen Dayal Upadhyay Marg, New Delhi Rouse Avenue
31-08-06 CTE issued and valid upto 04.03.2008
13,942.842 Sqm
MCD--97 KLD / 25,600 KLD / 71.25 KLD
66.6811 crores
Nov-07 17.3.2008No action. 03.6.08Ask the unit to file the itemwise compliance of Environmental Clearance conditions. Call on 11.07.2008.
As decided, a letter was issued on 13.06.2008Reply awaited.
10.09
17.3.2008No action. 03.6.08Ask the unit to file the itemwise compliance of Environmental Clearance conditions. Call on 11.07.2008.
Ask the unit to file the itemwise compliance of Environmental Clearance conditions. Call on 11.07.2008.
11.07
2 1 2 13 A-2
Ex. Engineer, CPWD (Construction of residential flats), Pocket-6 of Rouse Avenue Complex, Along DDU Marg
07-10-07 Applied on 20-07-06
56,951 Sqm in EC 6290.72 sqm in CTE
MCD-430 MLD / 344 MLD
83 crores in Affidavit & 125.35 crores in EC
2008 18.02.2008Ask him to submit the EIA clearance. 17.3.2008MS to speak. Take up in April, 2008. 23.04.2008MS to follow up. Call on 21.05.2008. 03.6.08Ask the unit to file the itemwise compliance of Environmental Clearance conditions. Call on 11.07.2008.
As decided, a letter was issued on 13.06.2008Reply awaited.
10.09
18.02.2008Ask him to submit the EIA clearance.
17.3.2008MS to speak. Take up in April, 2008. 23.04.2008MS to follow up. Call on 21.05.2008. 03.6.08Ask the unit to file the itemwise compliance of Environmental Clearance conditions. Call on 11.07.2008.
Ask the unit to file the itemwise compliance of Environmental Clearance conditions. Call on 11.07.2008.
11.07
3 1 3 14 A-3
Construction of Office Building (MOEA) by CPWD (Jawahar Lal Nehru Bhawan, Plot No 23-D, Maulana Azad Road, New Delhi)
22-12-06 CTE issued on 28-02-08
58,285 Sqm
MCD-160 KLD/ 120 KLD (STP)
147 crores
Jun-07 18.02.2008Consent to Estabish granted. 17.3.2008No action. 03.6.08The Environmental Clearance clearly specifies a six monthly monitoring report to be submitted to DPCC. Ask the unit to file the report by 11.07.2008. Call on 11.07.2008.
As decided a letter was issued on 13.06.2008Reply received stating six monthly report will be submitted in July, 2008. The same is awaited.
10.09
18.02.2008Consent to Estabish granted. 17.3.2008No action. 03.6.08The Environmental Clearance clearly specifies a six monthly monitoring report to be submitted to DPCC. Ask the unit to file the report by 11.07.2008. Call on 11.07.2008.
The Environmental Clearance clearly specifies a six monthly monitoring report to be submitted to DPCC. Ask the unit to file the report by 11.07.2008. Call on 11.07.2008.
11.07
5 1 5 15 A-5
Executive Engineer, CPWD ,
10-04-07 Applied on 21.05.2008
139294 sqm
MCD 667 KLD/trade effluent (185
124.80 crores
Dec, 2008
18.02.2008Ask him to apply for fresh Consent to
The unit has made contradictor
10.09
18.02.2008Ask him to apply for fresh
MS to speak to DG, CPWD to submit EC and
11.07
Const. of General Pool Housing at Dev Nagar
KLD) & domestic effluent (553 KLD) as per affidavit
Establish. 17.3.2008MS to speak. Take up in April, 2008. 23.04.2008Call on 21.05.2008 03.6.08MS to speak to DG, CPWD to submit EC and CTE application expeditiously. Call on 11.07.2008.
y statement regarding trade effluent discharge in affidavit.Unit has not reported in column no. 16 of application form regarding treatment facility.
Consent to Establish.
17.3.2008MS to speak. Take up in April, 2008. 23.04.2008Call on 21.05.2008 03.6.08MS to speak to DG, CPWD to submit EC and CTE application expeditiously. Call on 11.07.2008.
CTE application expeditiously. Call on 11.07.2008.
6 1 6 16 A-6
Central Bureau of Investigation,Construction OF
16.10.2007
05-05-08 57,320 Sqm
MCD 220 KLD / 204 KLD (STP of 225
137 crores Exculuding Land Cost in
2008 18.02.2008 Ask him to apply for fresh Consent to Establish.
As decided, a letter was issued on
10.09
18.02.2008 Ask him to apply for fresh Consent
The Environmental Clearance clearly specifies a six
11.07
CBI Building at Plot no 5 b, CGO Complex, Lodhi Raod, New Delhi
KLD capacity)
CTE application 130 crores in EC..
17.3.2008MS to speak. Take up in April, 2008. 23.04.2008Issue Consent to Establish and ask the unit to file item-wise compliance of environmental clearance conditions through an affidavit. 03.6.08The Environmental Clearance clearly specifies a six monthly monitoring report to be submitted to DPCC. Ask the unit to file the report by 11.07.2008. Call on
13.06.2008Reply awaited.
to Establish.
17.3.2008MS to speak. Take up in April, 2008. 23.04.2008Issue Consent to Establish and ask the unit to file item-wise compliance of environmental clearance conditions through an affidavit. 03.6.08The Environmental Clearance clearly specifies a six monthly
monthly monitoring report to be submitted to DPCC. Ask the unit to file the report by 11.07.2008. Call on 11.07.2008.
11.07.2008. monitoring report to be submitted to DPCC. Ask the unit to file the report by 11.07.2008. Call on 11.07.2008.
8 1 8 17 A-8 DMRC , Construction of operation control centre (Metro Bhawan ) of Delhi Metro Rail Corporation Ltd at Fire Brigade, Lane Connaught Place, New Delhi
01.04.2008
Applied on 1/4/2008
26,723.66 Sqm as per EC26,000 as per CTE
MCD 252 KLD / 33.6 KLD (NDMC)
90 crores
June, 2008
17.3.2008Give opportunity of being heard to DMRC on 03.04.2008 at 5.00 PM. 23.04.2008Let the unit file item-wise compliance of environmental clearance conditions through an affidavit by 21.05.2008. Take up on 21.05.2008. 30.04.2008This case
Unit has submitted itemwise compliance affidavit. A letter from MOEF has also ben received, it will be discussed.
10.09 17.3.2008Give opportunity of being heard to DMRC on 03.04.2008 at 5.00 PM. 23.04.2008Let the unit file item-wise compliance of environmental clearance conditions through an affidavit by
Since the unit has not replied, a D.O. letter may be sent from Chairman to Addl. Secretary, MOEF regarding the earlier clarifications. A letter may also be sent from
11.07
was taken up and Sh. C.P. Singh of DMRC was given a personal hearing who claims that the MRTS projects were covered in the draft notification of MOEF which was finally excluded in the notification dated 14.09.2006. The argument is not tenable and it was decided to prosecute the unit under EPA, 1986. Draft order of prosecution be prepared by MS and shown to Chairman before filing the same. As a matter
21.05.2008. Take up on 21.05.2008. 30.04.2008This case was taken up and Sh. C.P. Singh of DMRC was given a personal hearing who claims that the MRTS projects were covered in the draft notification of MOEF which was finally excluded in the notification dated 14.09.2006. The argument is not tenable
MS, DPCC to, CMD, DMRC asking for item-wise compliance of Environmental Clearance conditions. Call on 11.07.2008.
of abundant precaution, a final clarification from addl. Secretary, MoEF, GOI may be taken before start of proceedings to be 100 % sure of the contentions of Sh. CP Singh, since Metro is serving a large public purpose. 03.6.08Since the unit has not replied, a D.O. letter may be sent from Chairman to Addl. Secretary, MOEF regarding the earlier clarifications. A letter may also be sent from MS, DPCC to, CMD,
and it was decided to prosecute the unit under EPA, 1986. Draft order of prosecution be prepared by MS and shown to Chairman
before filing the same. As a matter of abundant precaution, a final clarification from addl. Secretary, MoEF, GOI may be taken before start of proceedings to be 100 % sure of the contentio
DMRC asking for item-wise compliance of Environmental Clearance conditions. Call on 11.07.2008.
ns of Sh. CP Singh, since Metro is serving a large public purpose. 03.6.08Since the unit has not replied, a D.O. letter may be sent from Chairman to Addl. Secretary, MOEF regarding the earlier clarifications. A letter may also be sent from MS, DPCC to, CMD, DMRC asking for item-wise compliance of Environmental Clearance
conditions. Call on 11.07.2008.
9 1 9 18 A-9 Piccadily Hotel at District Center, Janakpuri, Delhi
21-05-07 CTE issued on 25.07.2008
34067.31 Sqm in EC & 22689.31 Sqm in Application
MCD 300 KLD GW 240 KLD / 340 KLD
84 crores in Application & 88 crores in EC
__ 23.05.2008
In the last CMC meeting where the case of M/s Piccadily Hotel was taken on 15.05.2008 and the Committee had decided to issue a letter to comply with the directions of the Committee’s decision dated 17.03.2008, otherwise action will be taken against it. Before this letter could be issued the unit approached Delhi Govt. and sought lenient
Unit has submitted a penalty of Rs. 20 Lakh, the case was reviewed in CMC and accordingly a letter has been issued for submission of BG of Rs. 60
10.09 23.05.2008 In the last CMC meeting where the case of M/s Piccadily Hotel was taken on 15.05.2008 and the Committee had decided to issue a letter to comply with the directions of the Committee’s decision dated 17.03.2008, otherwise action will be taken against it. Before this letter could be
Call on 04.07.2008.
Call on 04.07.2008.
MS reports that the unit has confirmed that it will file the Bank Guarantee soon since the MD is out of the country. Call on 11.06.2008 for filling the Bank Guarantee
4.07
action. The unit was clearly informed by the Delhi Govt. that it will have to comply with the orders of CMC. On 21.05.2008, the unit has filed a letter to MS, DPCC enclosing a draft of Rs. 20 Lakh and saying that this is the maximum that the unit is able to pay since it is incurring heavy financial losses every day. Unit also requested the Committee to issue Consent to Establish. In view of
Lakhs.BG not submitted. Letter for the same issued on 26.06.2008.BG of Rs. 60 Lakhs submitted.CTE issued.
issued the unit approached Delhi Govt. and sought lenient action. The unit was clearly informed by the Delhi Govt. that it will have to comply with the orders of CMC. On 21.05.2008, the unit has filed a letter to MS, DPCC enclosing a draft of Rs. 20 Lakh and saying that this is the maximum that the unit is able to pay since
the submissions made by the project proponent vide letter dated 07.05.2008. It has submitted the permission from CGWA for boring three tube-wells. Further, it has also submitted a copy of inspection report of MOEF dated 07.01.2008 which appears to be satisfactory. The Committee therefore deliberated and felt that ends of justice will be met if the earlier 0.5 % of the total project cost as cash
it is incurring heavy financial losses every day. Unit also requested the Committee to issue Consent to Establish. In view of the submissions made by the project proponent vide letter dated 07.05.2008. It has submitted the permission from CGWA for boring three tube-wells. Further, it has also submitted a copy of inspection report
penalty as directed vide letter dated 17.03.2008 may be reduced to Rs. 20 Lakh, but the Bank Guarantee may be raised by Rs. 20 Lakh and the total Bank Guarantee of Rs. 60 Lakh valid for three years may be paid by the unit within 01 week as promised to MS on 22.05.2008. If this Bank Guarantee is filed within a week as an assurance that the all environmental legislation will be complied
of MOEF dated 07.01.2008 which appears to be satisfactory. The Committee therefore deliberated and felt that ends of justice will be met if the earlier 0.5 % of the total project cost as cash penalty as directed vide letter dated 17.03.2008 may be reduced to Rs. 20 Lakh, but the Bank Guarantee may be raised by Rs. 20 Lakh and the total Bank
with for the next three years, the unit may be issued Consent to Establish, as it would have been complied with the basic committee’s condition of furnishing 1 % of the total project cost in terms of cash penalty & Bank Guarantee. The result may be reported to CMC on 03.06.2008. 03.6.08MS reports that the unit has confirmed that it will file the Bank Guarantee soon since the MD is out of the country.
Guarantee of Rs. 60 Lakh valid for three years may be paid by the unit within 01 week as promised to MS on 22.05.2008. If this Bank Guarantee is filed within a week as an assurance
that the all environmental legislation will be complied with for the next three years, the unit may be issued Consent to Establish, as it would
Call on 11.06.2008 for filling the Bank Guarantee 26.06.2008Call on 04.07.2008.
have been complied with the basic committee’s condition of furnishing 1 % of the total project cost in terms of cash penalty & Bank Guarantee. The result may be reported to CMC on 03.06.2008. 03.6.08MS reports that the unit has confirmed that it will file the Bank Guarantee soon since the MD is out
of the country. Call on 11.06.2008 for filling the Bank Guarantee 26.06.2008Call on 04.07.2008.
11 1 11 19 A-11
Parsvnath landmark developers Pvt. Ltd Construction of Residential Complex at Subhash Nagar
Built up area 19928.954 sqm
26-03-07
10759.4 Sqm in Application & 19,928.954 Sqm in Reply given to DPCC
MCD 114.34 KLD / 85.1 KLD (STP)
12,77,69,739 crores
2009 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed on their application by MoE&F.
17.3.2008Unit be asked to
Spoken.IIT report is to be discussed.
10.09 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed on their
MS to speak to Sh. Naresh, Addl. Commisioner, MCD. This unit will also be cross checked for built up area by the team of SPA or IIT, Delhi. Call on 11.07.2008.
11.07
submit an affidavit indicating date of start of construction & date of completion, approved architectural drawing & completion certificate, if received. 23.04.2008Since the unit is trying to avoid the EC by showing himself only 77 sqm short of the norms, MS may write to Addl. Commissioner (Engineering), MCD to confirm the actual built up area proposed in the building plan. Call on 21.5.2008.
application by MoE&F.
17.3.2008Unit be asked to submit an affidavit indicating date of start of construction & date of completion, approved architectural drawing & completion certificate, if received. 23.04.2008Since the unit is trying to avoid the EC by showing himself only 77 sqm short of the
03.6.08MS to speak to Sh. Naresh, Addl. Commisioner, MCD. This unit will also be cross checked for built up area by the team of SPA or IIT, Delhi. Call on 11.07.2008.
norms, MS may write to Addl. Commissioner (Engineering), MCD to confirm the actual built up area proposed in the building plan. Call on 21.5.2008. 03.6.08MS to speak to Sh. Naresh, Addl. Commisioner, MCD. This unit will also be cross checked for built up area by the team of SPA or IIT, Delhi.
Call on 11.07.2008.
15 1 15 20 A-15
BES Buildcon Pvt. Ltd., Swatantra Bharat Mills Complex, Plot No 15, Najafgarh Road, Delhi
Pending with MOE&F
24.06.2008
850401 sqm
MCD - 2195 KLD / WW - 3129 KLD (STP)
1684.61
Crores
2010 03.6.2008The unit
says that it will apply
for Consent to Establish
within a week and it
has filed revised
application for
Environmental
Clearance with MOEF
on 28.04.2008.
Ask the unit to file
Environmental
Clearance & Consent to Establish expeditiously. The unit
may be asked to file clarification
on the extent of ground
water drawl and the
permission for the
Notice u/s 25/26 of Water Act and u/s 21/22 of Air Act was isued on 30.04.2008 for CTE.Reply received on 13.05.2008.Applied for CTE on 24.06.2008
10.09 03.6.2008The unit says that
it will apply for Consent
to Establish within a
week and it has filed
revised applicatio
n for Environm
ental Clearance
with MOEF on 28.04.200
8. Ask the unit to
file Environm
ental Clearance
& Consent
to Establish expeditiously. The unit may be asked
to file clarificati
Call on 04.07.2008 after inspection by Chairman, DPCC with Sh. M. Dwarkanath, SSO.In view of the very large scope of the project of 20 acres and cost involvement of nearly Rs. 1700 crores.
The unit says that it will apply for Consent to Establish within a week and it has filed revised application for Environmental Clearance with MOEF on 28.04.2008. Ask the unit to file Environmental Clearance & Consent to Establis
4.07
same. It may also be asked to file
its water cess returns
when it became
applicable.
27.06.2008Call on
04.07.2008 after
inspection by
Chairman, DPCC with
Sh. M. Dwarkanath
, SSO.In view of the very
large scope of the
project of 20 acres and cost
involvement of nearly Rs. 1700 crores.
vide I.D. No. 26156. Inspection conducted by Chairman, DPCC and Sh. Dwarkanath, SSO on 30.06.2008 and inspection report to be discused.
on on the extent of ground water
drawl and the
permission for the same. It may also be asked to file its
water cess
returns when it became
applicable.
27.06.2008
Call on 04.07.200
8 after inspectio
n by Chairman, DPCC with Sh.
M. Dwarkanath, SSO.In view of the
very large scope of
the project of 20 acres and cost
h expeditiously. The unit may be asked to file clarification on the extent of ground water drawl and the permission for the same. It may also be asked to file its water cess returns when it became applicable.
involvement of
nearly Rs. 1700
crores.
17 1 17 21 A-17
G.M. Northern Railway, Head Quarters, Ministry of Railway, Baroda House, New Delhi-110001
Pending with MOE&F
Not applied.
__ __ __ __ 03.6.08The unit has
replied saying that
the redevelopment of New
Delhi Railway Station is
under planning stage and
no construction
has been taken up so far. They will apply
for Consent to Establish as soon as
the Environmen
tal Clearance
is received. The unit may be
asked to file clarification
on the extent of ground
A letter was issued on 13.06.2008Reply awaited.
10.09 03.6.08The unit
has replied saying that the
redevelopment of
New Delhi
Railway Station is
under planning stage and
no constructi
on has been
taken up so far.
They will apply for Consent
to Establish as soon as
the Environm
ental Clearance
is received. The unit
The unit has replied saying that the redevelopment of New Delhi Railway Station is under planning stage and no construction has been taken up so far. They will apply for Consent to Establish as soon as the
11.07
water drawl and the
permission for the
same. In view of the above, call
on 11.07.2008.
may be asked to
file clarification on the extent of ground water
drawl and the
permission for the same. In view of
the above, call on
11.07.2008.
Environmental Clearance is received. The unit may be asked to file clarification on the extent of ground water drawl and the permission for the same. In view of the above, call on 11.07.2008.
18 1 18 22 A-18
Delhi Cricket Association, Frozeshah Kotla, Delhi Gate,
Not applied
Not applied
__ __ __ __ 03.6.2008Issue reminder and also the unit may be asked to
A reminder was issued on 13.06.2008
10.09 03.6.2008Issue reminder and also the unit may be
Issue reminder and also the unit may be asked to file
11.07
Delhi-110002
file clarification on the extent of ground water drawl and the permission for the same. It may also be asked to file its water cess returns from May, 2003 when it became applicable. Reminder to be sent to site address in the name of Secretary, DDCA. Call on 11.07.2008
Reply awaited.
asked to file clarification on the extent of ground water drawl and the permission for the same. It may also be asked to file its water cess returns from May, 2003 when it became applicable. Reminder to be sent to site address in the name of Secretary, DDCA.
clarification on the extent of ground water drawl and the permission for the same. It may also be asked to file its water cess returns from May, 2003 when it became applicable. Reminder to be sent to site address in the name of Secretary, DDCA.
Call on 11.07.2008
Call on 11.07.2008
22 1 22 23 A-22
DLF I.T. Park, 15, Shivaji Marg, Delhi
Applied on 21.05.2008
Applied on 13.06.2008
430789.322 sqm
MCD-1262 KLDGW - NilWW - 2471 KLD(STP Proposed)
916.63 crores
Dec-10 27.06.2008Call on 04.07.2008 after inspection by Chairman, DPCC with Sh. M. Dwarkanath, SSO.In view of the very large scope of the project of 10 acres and cost involvement of nearly Rs. 1000 crores.
Applied for CTE on 13.06.2008 vide I.D. No. 26056. Inspection conducted by Chairman, DPCC and Sh. Dwarkanath on 30.06.2008 and inspection report to be discused.
10.09
27.06.2008Call on 04.07.2008 after inspection by Chairman, DPCC with Sh. M. Dwarkanath, SSO.In view of the very large scope of the project of 10 acres and cost involvement of nearly Rs. 1000 crores.
Call on 04.07.2008 after inspection by Chairman, DPCC with Sh. M. Dwarkanath, SSO.In view of the very large scope of the project of 10 acres and cost involvement of nearly Rs. 1000 crores.
4.07
23 1 23 24 A-23
Construction of Bakkarwala Housing
03.06.2008DDA has filed Consent to
Letter issued.Reply awaite
10.09
03.06.2008DDA has filed
11.07
Complex by DDA
Establish application for Bakkarwala Housing Complex. Since the built up area is more than 20000 sqm, ask the unit to apply for EC in MOEF expeditiously. Call on 11.07.2008.
d. Consent to Establish application for Bakkarwala Housing Complex. Since the built up area is more than 20000 sqm, ask the unit to apply for EC in MOEF expeditiously. Call on 11.07.2008.
24 1 24 25 A-24
Construction of office complex "Anupam Tower Complex", 23-A, Najfgarh Road Indl. Area, New Delhi by M/s
_ Not applied
_ _ _ _ Chairman, DPCC & Sh. Dwarkanath, SSO visited the area on 28.06.2008 w.r.t. BES Build
10.09
BPTP Ltd.
con Pvt. Ltd., 15, Shivaji Marg & DLF I.T. Park, 15, Shivaji Marg, Delhi. During the inspection, this unit was noticed.Notice for CTE issued on 08.07.2008.Reply awaited.
25 1 25 26 A-25
Genger Rail Yatri Niwas (Roots Corporation Ltd.), Rail Yatri Niwas, New Delhi Railway Station, Gate No 2, Ajmeri Gate Side
_ Applied on 15.07.2008
4842.456 sqm
MCD : 20
KLD / GW : 30 KLD /
45 KLD (STP)
1013.97
Lakhs
July, 2008
Applied for CTE on 15.07.2008.Unit has informed about waste water discharge is Nil in application form, however, 50 lt/day mentioned in the affidavit.Unit has also informed about stack height of D.G. Set above roof
10.09
of building is N.A however, there is no information mentioned in the affidavit..
31 2 2 27 B-2 General Pool Office Complex
__ Not applied
__ __ __ __ 18.02.2008Ask the unit to apply for Consent to Establish. Also ask them to file EIA clearance.
17.3.2008MS to speak to the concerned authority. Take up in April, 2008. 23.04.2008Fresh letter at correct address be
Reminder issued on 12.06.2008.Letter received from DDA regarding correct address.
10.09 18.02.2008Ask the unit to apply for Consent to Establish. Also ask them to file EIA clearance. 17.3.2008MS to speak to the concerned authority. Take up in April,
Send reminder. Call on 11.07.2008.
11.07
sent. 03.6.08Send reminder. Call on 11.07.2008.
2008. 23.04.2008Fresh letter at correct address be sent. 03.6.08Send reminder. Call on 11.07.2008.
32 2 3 28 B-3 Negolice India Ltd. Construction of Residential Complex named "VVictoria Gardens" at Ring Road, Azadpur, New Delhi
16-05-07 23-05-07
1,00,676.12 Sqm
MCD 517 KLD / 413 KLD (STP)
106.70 crores
2007 18.02.2008Ask the unit to file EIA clearance immediately. 17.3.2008Unit be asked to submit item-wise compliance of conditions laid down in Environmental Clearance and date of start of construction
Letter issued on 12.06.2008.Reply received on 15.07.2008
10.09 18.02.2008Ask the unit to file EIA clearance immediately.
17.3.2008Unit be asked to submit item-wise compliance of conditions laid down in Environmental Clearance
Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. Call on 11.07.2008
11.07
& date of completion through an affidavit. Take up in April 2008. 23.04.2008Let the unit file the forest clearance and let him comply with STP condition of MOEF rather than becoming a judge in his own case. All other conditions not mentioned in the compliance affidavit must also be done by 14.05.2008. Call on 14.05.2008.
13.05.2008In view of the fact that time was allowed upto
and date of start of construction & date of completion through an affidavit. Take up in April 2008. 23.04.2008Let the unit file the forest clearance and let him comply with STP condition of MOEF rather than becoming a judge in his own case. All other conditions not mentioned in the compliance affidavit must also be done
14.05.208, unit may be informed to file the documents not later than 20.05.2008. Letter may be issued without waiting for minutes. Call on 23.5.2008. 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. Call on 11.07.2008
by 14.05.2008. Call on 14.05.2008. 13.05.2008In view of the fact that time was allowed upto 14.05.208, unit may be informed to file the documents not later than 20.05.2008. Letter may be issued without waiting for minutes. Call on 23.5.2008. 03.6.08Ask the unit to file details of waste water
discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. Call on 11.07.2008
33 2 4 29 B-4 The Executive Engineer, Building Project Division, P.W.D Govt of NCT Delhi for construction of Lawyers Chambers at District Court Complex, Rohini
09-03-07 26.06.2008
24,194.708 Sqm
127 KLD /Day
(MCD - 88 KLD & GW -
39 KLD /
WW - 80 KLD
66 crores
Dec-10 18.02.2008Ask the unit to apply for Consent to Establish. Also affidavit complying with EIA conditions.
17.3.2008MS to speak to the concerned authority. Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response.
Reminder isued.Applied for CTE on 26.06.2008
10.09 18.02.2008Ask the unit to apply for Consent to Establish. Also affidavit complying with EIA conditions. 17.3.2008MS to speak to the concerned authority. Take up in April, 2008.
Issue reminder. Call on 11.07.2008.
11.07
03.6.08Issue reminder. Call on 11.07.2008.
23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
34 2 5 30 B-5 DDA , New Construction Project of a Housing Complex for economically weaker section at siraspur in Delhi
Pending with Moef
Not applied
1,20,100sqm
3766KLD in EC
121 crores
__ 18.02.2008Ask the unit to apply for Consent to Establish. Also ask them to file EIA clearance.
17.3.2008MS to speak to the concerned authority. Take up in April, 2008. 23.04.2008The minutes of the meeting of MOEF and other relevant
Letter issued to CE, North Zone, DDA on 13.06.08 seeking application for CTE and a copy of EC. Reply recei
10.09 18.02.2008Ask the unit to apply for Consent to Establish. Also ask them to file EIA clearance.
17.3.2008MS to speak to the concerned authority. Take up in April, 2008.
Issue reminder. Call on 11.07.2008.
11.07
papers may be sent by MS to the concerned Chief Engineer to clarify the issue. 03.6.08Issue reminder. Call on 11.07.2008.
ved. 23.04.2008The minutes of the meeting of MOEF and other relevant papers may be sent by MS to the concerned Chief Engineer to clarify the issue. 03.6.08Issue reminder. Call on 11.07.2008.
35 2 6 31 B-6
Indian Institute of Information Technology Campus of Indraprastha University at Surajmal Vihar, Shahdar
16-01-08 17-03-08 87,112.5 sqm
MCD 170 KLD GW 80 KLD /190 KLD
65.82 crores
__ 18.02.2008The explanation of concerned EE must be called for why the decision given on the file has not been implemented. Ask the unit to
Letter issued on 13.06.2008.Reply awaited.
10.09
18.02.2008The explanation of concerned EE must be called for why the decision given on the file has not been
Environmental Clearance has been filed. But for item-wise compliance, unit says that
11.07
a apply for Consent to Establish immediately. 17.3.2008Unit be asked to submit item-wise compliance of conditions laid down in Environmental Clearance through an affidavit and MS to speak to Registrar w.r.t. applying for Consent to Establish.Take up in April 2008. 23.04.2008Compliance affidavit by 21.05.2008. Call on 21.5.2008. 03.6.08Environmental Clearance
implemented. Ask the unit to apply for Consent to Establish immediately.
17.3.2008Unit be asked to submit item-wise compliance of conditions laid down in Environmental Clearance through an affidavit and MS to speak to Registrar w.r.t. applying for Consent to Establish.Take up in April 2008.
construction yet to be started and it will be filed. Call on 11.07.2008.
has been filed. But for item-wise compliance, unit says that construction yet to be started and it will be filed. Call on 11.07.2008.
23.04.2008Compliance affidavit by 21.05.2008. Call on 21.5.2008. 03.6.08Environmental Clearance has been filed. But for item-wise compliance, unit says that construction yet to be started and it will be filed. Call on 11.07.2008.
37 2 8 32 B-8 Residential Complex near Rithala Metro Station by A.P. Real Estates
Pending with Moef
30-08-07 29,889.65 Sqm
MCD 221 KLD/ 170 KLD (STP)
93.28 Crores
2008 18.02.2008Ask the unit to file EIA clearance.
17.3.2008MS may write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response.. 03.6.08Call for personal hearing on 11.06.2008 at 7.45 PM. 11.6.2008The unit was called for personal hearing today. He claims no construction taken place
Affidavit not yet been submitted by the unit as directed by CMC during the personal hearing on 11.7.2008
10.09 18.02.2008Ask the unit to file EIA clearance. 17.3.2008MS may write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response.. 03.6.08Call for personal hearing on 11.06.2008 at 7.45 PM. 11.6.2008The unit was
Call for personal hearing on 11.07.2008 at 8.30 PM.
Call on 27.06.2008.
Call for personal hearing on 11.06.2008 at 7.45 PM.
6.08
so far. The internet download of MOEF indicates that certain clarifications have been sought and Environmental Clearance is yet to be given to the unit. SIT may inspect and report on all points relating to Air, Water & Noise pollution, Green Building concept and efficient waste management practices. Unit may also be asked to file permission from CGWA for ground water drawl. Call on 25.06.2008.
called for personal hearing today. He claims no construction taken place so far. The internet download of MOEF indicates that certain clarifications have been sought and Environmental Clearance is yet to be given to the unit. SIT may inspect and report on all points relating to Air, Water & Noise pollution, Green Building concept and
26.06.2008Call on 27.06.2008. 27.06.2008Call for personal hearing on 11.07.2008 at 8.30 PM. 11.07.2008 The unit came for personal hearing today. Since it has not done any construction so far and since it is yet to get the building plan clearances, it may be prudent to wait for the Environmental Clearance first before decision on Consent to Establish. However, in the meantime unit be directed to
efficient waste management practices. Unit may also be asked to file permission from CGWA for ground water drawl. Call on 25.06.2008. 26.06.2008Call on 27.06.2008. 27.06.2008Call for personal hearing on 11.07.2008 at 8.30 PM. 11.07.2008 The unit came for personal
file an affidavit saying it will not start any construction till it gets the Environmental Clearance. Call on 06.08.2008.
hearing today. Since it has not done any construction so far and since it is yet to get the building plan clearances, it may be prudent to wait for the Environmental Clearance first before decision on Consent to Establish. However, in the meantime unit be directed to file an affidavit saying it will not start any construction till it gets the
Environmental Clearance. Call on 06.08.2008.
38 2 9 33 B-9 Executive Enmgineer ( C) Building Projects Division, Proposed Maharaja Agrasen College,Delhi University, Village Dallupura, Vasundhara Enclave, Delhi
__ 11-12-07 20, 217.6 Sqm
__ / 117 KLD (STP)
38 Crores
Dec----07
18.02.2008Not discussed in the CMC meeting dt 18.02.08 17.3.2008MS to speak . Take up in April, 2008. 23.04.2008 Unit may be asked to submit sanctioned building plan by 21.05.2008. Call on 21.05.2008. 03.6.08Issue reminder for submission of a copy of Environmental Clearance,
Letter issued on 12.06.2008.Same is returned back undelievered.
10.09 18.02.2008Not discussed in the CMC meeting dt 18.02.08
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008 Unit may be asked to submit sanctioned building plan by 21.05.2008. Call on 21.05.2008. 03.6.08Issue
Issue reminder for submission of a copy of Environmental Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of
11.07
an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets . Call on 11.07.2008.
reminder for submission of a copy of Environmental Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water
builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets . Call on 11.07.2008.
Authority, water cess payment as per Water Cess Act, 1977, DG sets . Call on 11.07.2008.
39 2 10 34 B-10
Hilton Garden Inn,Plot No. 1 B - 4, Twin District CentreSec - 10, Rohini, Delhi - 85
16-04-08 02-08-08 29, 884.21 Sqm
MCD 253 KLD / 258 KLD (STP)
110.46 Crores
JUNE -----2010
18.02.2008Not discussed in the CMC meeting dt 18.02.08
MS may write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008MS to remind Addl. Secretary, MOEF about the Environmental Clearance of the unit.
Letter isued.Reply received.
10.09 18.02.2008Not discussed in the CMC meeting dt 18.02.08
MS may write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008MS to remind Addl. Secretary,
The unit has filed item-wise compliance affidavit which is not complete. Ask the unit to file the affidavit on the remaining items & also to file an affidavit indicating date of start of
11.07
03.6.08The unit has filed item-wise compliance affidavit which is not complete. Ask the unit to file the affidavit on the remaining items & also to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground
MOEF about the Environmental Clearance of the unit. 03.6.08The unit has filed item-wise compliance affidavit which is not complete. Ask the unit to file the affidavit on the remaining items & also to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved
construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per
Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008.
architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008.
Water Cess Act, 1977, DG sets. Call on 11.07.2008.
40 2 11 35 B-11
Executive Enmgineer Rohini Project Division - 13 proposed the
Not applied
18-01-08 76160 Sqm
MCD 634.1 KLD / 539 KLD (STP)
62.37 Crores
March-----2010
18.02.2008Not discussed in the CMC meeting dt 18.02.08
MS may write to MOEF to
Letter issued on 8.5.08 and 19.06.2008 to MoE
10.09
18.02.2008Not discussed in the CMC meeting dt 18.02.08
Issue reminder. Call on 11.07.2008.
11.07
Construction of HIG Multistoried HousesSec - 29, Rohini, Phase - IV,Delhi - 85
find out the status of EIA clearance. Take up in April, 2008. 23.04.2008MS to remind Addl. Secretary, MOEF about the Environmental Clearance of the unit. 03.6.08Issue reminder. Call on 11.07.2008.
F.Reply awaited.
MS may write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008MS to remind Addl. Secretary, MOEF about the Environmental Clearance of the unit. 03.6.08Issue reminder. Call on 11.07.2008.
41 2 12 36 B-12
Executive Engineer,Rohini Project Division - 9,
Pending with Moef
12-10-07 53600 Sqm
1117 KLD / 950(STP RITHALA) KLD
108 Crores
__ 18.02.2008Not discussed in the CMC meeting dt 18.02.08
MS may
Letter issued on 8.5.08 and 19.06.2008
10.09
18.02.2008Not discussed in the CMC meeting dt
Issue reminder. Call on 11.07.2008.
11.07
proposed the Construction of Slum houses near STP, Sector - 26, Phase - IV, Rohini,Delhi - 85
write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008MS to remind Addl. Secretary, MOEF about the Environmental Clearance of the unit. 03.6.08Issue reminder. Call on 11.07.2008.
to MoEF.Reply awaited.
18.02.08
MS may write to MOEF to find out the status of EIA clearance. Take up in April, 2008. 23.04.2008MS to remind Addl. Secretary, MOEF about the Environmental Clearance of the unit. 03.6.08Issue reminder. Call on 11.07.2008.
42 2 13 37 B-13
Construction of Zonal Development Plan of Narela Sector-A-1 to A-4 Narela Sub City Narela, Delhi Development Authority
Pending with Moef
Not applied
__ 18, 149KLD IN EC / 10 MLD (STP)
146.9 Crores
__ 23.04.2008Send notice to concerned Chief Engineer, DDA for compliance. 03.6.08Issue reminder. Call on 11.07.2008.
Notice issued to DDA.Reply received on 30.05.2008. However, not applied for CTE.Minutes of the EAC meeting of MoEF is placed on file.Reminder issued on 18.06.2008.Letter received on 30.06.2008 from DDA regard
10.09 23.04.2008Send notice to concerned Chief Engineer, DDA for compliance. 03.6.08Issue reminder. Call on 11.07.2008.
Issue reminder. Call on 11.07.2008.
11.07
ing the new address for correspondence.
45 2 16 38 B-16
Delhi Administration Staff Quarters at Shalimar Bagh being constructed by PWD
17.06.2008
26.06.2008
45,560.716 Sqm
253 KLD / MCD - 135 KLD / WW- 190 KLD / Day
54 Crores
__ 23.04.2008MS to speak to Engineer in Chief about Consent to Establish application after revealing to him the directions of MOEF. Call on 21.5.2008 03.6.08Issue reminder. Call on 11.07.2008.
Letter issued.Application for CTE received on 26.06.2008. However, letter received from MOEF for take necessary action under EPA.
10.09
23.04.2008MS to speak to Engineer in Chief about Consent to Establish application after revealing to him the directions of MOEF. Call on 21.5.2008 03.6.08Issue reminder. Call on 11.07.2008.
Issue reminder. Call on 11.07.2008.
11.07
47 2 18 39 B-18
Rugby Stadium and Multipurpose Hall
Pending with Moef
Applied for CTE on 12.6.08.
9549 sqm + 20280 sqm
240 KLD / MCD-
240 KLD / STP
224 crores
Nov, 2009
01.05.2008This case is listed in MOEF for discussion
Letter issued.Applied for CTE.
10.09 01.05.2008This case is listed in MOEF
Issue reminder. Call on 11.07.2008.
11.07
North Campus,Delhi University,Delhi
proposed on 02.05.2008. Call on 14.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
for discussion on 02.05.2008. Call on 14.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
48 2 19 40 B-19
Brilliant Buildtech Private Ltd, Shalimar Bagh District Centre NC-NW
Built up area is
19111.14 Sqm
16-05-08 19111.14 Sqm
MCD 143.38 KLD / 74.63 KLD (STP)
110 Crores
Sept---2009
03.6.08Ask the unit to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot
Letter isued.Reply along with approved architectural drawing of the projet received on 30.06.2008.
10.09 03.6.08Ask the unit to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details
Ask the unit to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of
11.07
area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. This unit will also be cross checked for built up area by the team of SPA or IIT, Delhi. Call on 11.07.2008.
of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. This unit will also be cross checked for built up area by the team of SPA or IIT,
builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. This unit will also be cross checked for built up area by the team of SPA or
Delhi. Call on 11.07.2008.
IIT, Delhi. Call on 11.07.2008.
50 2 21 41 B-21
Executive Engineer, Provisional Division PWD (B& R) Civil Line, Gurgaon Poposed Construcion of Housing Complex at Plot no1 Near Single Pur Village, Shalimar bagh , Delhi-81
Built up area is
17065.59 Sqm
Not applied.
17065.59 Sqm
__ __ 2009 03.6.08Ask the unit to file application fro Consent to Establish, a copy of Environmnetal Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground
Notice issued on 23.05.2008 & 12.06.2008 for CTE.Neither reply submitted nor applied for CTE.
10.09 03.6.08Ask the unit to file application fro Consent to Establish, a copy of Environmnetal Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area,
Ask the unit to file application fro Consent to Establish, a copy of Environmnetal Clearance, an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste
11.07
Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008.
waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008.
water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008.
51 2 22 42 B-22
Construction of HIG Flats at Mukherjee Nagar by DDA
18.06.2008A letter received from MOEF for taking action under EPA against HIG Flats at Mukherjee Nagar. A well drafted letter may be put up by MS to Vice Chairman, DDA by 25.06.2008.
Letter issued to Engineer (Member), North Division-3 on 01.07.2008 and copy sent to UD.
10.09 18.06.2008A letter received from MOEF for taking action under EPA against HIG Flats at Mukherjee Nagar. A well drafted
Z
Reply awaited from DDA. However, a letter received from Urban Development.
letter may be put up by MS to Vice Chairman, DDA by 25.06.2008.
52 2 23 43 B-23
Construction of Anand Vihar Railway Station at Anand Vihar
03.06.2008The issue of Anand Vihar Railway Station was taken up by the Committee and it was decided to issue notice to GM, Northern Railway for applying for Consent to Establish for Anand Vihar Railway Station.
Notice issued.Reply received.
10.09 03.06.2008The issue of Anand Vihar Railway Station was taken up by the Committee and it was decided to issue notice to GM, Northern Railway for applying for Consent to Establish for Anand
Z
Vihar Railway Station.
54 2 25 44 B-25
Construction of Hotel at Plot No. 12, Mangalam Place, Rohini, N.Delhi by M/s Star Realty Private Limited,M - 75, Greater Kailash, Part - I, New Delhi - 48
Obtained on 30.7.08
Not Applied
24389.62 91 KLDSTP-82 KLD
225 Cr Copy of EC dated 30.7.08 received from MoEF, GOI on 05.08.08.
10.09
67 3 1 45 C-1 UGC Campus, Pocket 7 Sector B Vasant Kunj, Nelson Mandela Road, Delhi
Obtained on
30.7.08
Applied 18.02.2008Ask the unit to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has
Letter issued on 12.06.2008Reply received on 18.06.2008 & 31.07
10.09 18.02.2008Ask the unit to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest
Issue reminder. Call on 11.07.2008.
11.07
been passed on their application by MoE&F.
Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
.2008Obtained EC on 30.07.2008..
status of the unit and whether any order has been passed on their application by MoE&F. Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
68 3 2 46 C-2 Delhi Judicial Academy, National Law School ad National Institute of Mediation & Concilat
22-01-07 Applied 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
17.3.2008MS to speak .
Letter issued on 12.06.2008No reply received.
10.09 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
Issue reminder. Call on 11.07.2008.
11.07
ion , Sector 14, Dwarka Phase-I, New Delhi
Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
69 3 3 47 C-3 Redevelopment of Netaji Nagar(Part) and Moti Nagar(East), New Delhi, Ministry of Urban Dwevelopment, Govt. of India, Nirman Bhawan, New
21-03-07 Applied 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Issue CTE
Letter issued. Unit has submitted compliance affidavit of Environment Clear
10.09 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. 17.3.2008MS to speak . Take up in April,
Call on 11.07.2008.
11.07
Delhi and ask them to comply with the conditions of Environmental Clearance which have not yet been done. Call on 21.5.2008. 03.6.08Call on 11.07.2008.
ance on 26.05.2008..
2008. 23.04.2008Issue CTE and ask them to comply with the conditions of Environmental Clearance which have not yet been done. Call on 21.5.2008. 03.6.08Call on 11.07.2008.
73 3 7 48 C-7
Jasmine Projects Private Ltd. , Plot No. 1 Vasant Kunj Mall, Vasant Kunj
28-11-06 15.05.06 21367.68 sqm
MCD-28.5 KLD / 22.8 KLD
90 crores
Mar-07 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
17.3.2008Take up in April, 2008.
Letter isued on 12.06.2008Reply received on 26.06.2008
10.09
18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
Issue reminder for compliance affidavit and also to file details of waste water discharge, D.G.
11.07
Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. 23.04.2008Draft letters seeking clarification have been put up which will be corrected and issued. 03.6.08Issue reminder for compliance affidavit and also to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as
along with affidavit on 09.07.2008 regarding energy conservation. But no compliance affidavit of EC submitted.
17.3.2008Take up in April, 2008. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. 23.04.2008Draft letters seeking clarification have been put up which will be corrected and issued. 03.6.08Issue reminder for compliance affidavit and also
Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008.
per Cess Act. Call on 11.07.2008.
to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008.
75 3 9 49 C-9 DMRC , IT Park, Shastri Park, GT Road
20-12-06 03.03.2006
38,841 sqm
GW - 288.75 KLD / 110 KLD
73 crores
2007 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
17.3.2008Take up in April, 2008. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of
Letter issued on 12.06.2008No reply received.
10.09 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. 17.3.2008Take up in April, 2008. Ask the unit to submit an affidavit w.r.t. date
Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008
11.07
construction. 23.04.2008Ask the unit to file fresh affidavit clearly indicating what conditions under each of the three phases have been complied with, date of start of construction & date of completion of construction & approved architectural drawing. Call on 21.5.2008. 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess
of start of construction and likely date of completion of construction. 23.04.2008Ask the unit to file fresh affidavit clearly indicating what conditions under each of the three phases have been complied with, date of start of construction & date of completion of construction & approved architectural drawing. Call on 21.5.2008
payment as per Cess Act. Call on 11.07.2008
. 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008
77 3 11 50 C-11
CPWD, Construction of general pool office Accomodation, Phase-II , Pushpa Bhawan, Pushp Vihar, Delhi
06-05-07 Not applied
88.742metre square
NA NA 18.02.2008 Ask the unit to apply for Consent to Establish. Also ask them to file an affidavit for compliance of EIA clearance conditions. 17.3.2008MS to
Letter issued on 12.06.2008Reply received on 24.06.2008.
10.09 18.02.2008 Ask the unit to apply for Consent to Establish. Also ask them to file an affidavit for compliance of EIA clearance conditions.
Issue reminder. Call on 11.07.2008.
11.07
speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
78 3 12 51 C-12
National Small Industries Corporation Ltd , Okhla Industrial Estate, New Delhi
_ 19-10-2007
17987.94metre square
GW-104KLD, Discharge-51KLD
87 crore
2009 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed
Letter issued on 12.06.2008No reply received.
10.09 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of
Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per
11.07
on their application by MoE&F.
17.3.2008MS to speak to MOEF. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as
the unit and whether any order has been passed on their application by MoE&F.
17.3.2008MS to speak to MOEF. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response.
Cess Act. Call on 11.07.2008
per Cess Act. Call on 11.07.2008
03.6.08Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008
80 3 14 52 C-14
DDA LIG Houses , Molar Bandh, New Delhi
_ 12-04-07 33465metre square
MCD-Quanitiy not mentioned, GW-Nil, Waste Water Discharge-NA
38 Crores
Not mentioned
18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed
Letter isued on 12.06.2008Reply received on 20.06.2008 stating environmental
10.09 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of
Issue reminder. Call on 11.07.2008.
11.07
on their application by MoE&F.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
clearance will be cleared by MOEF very soon.
the unit and whether any order has been passed on their application by MoE&F.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
81 3 15 53 C-15
Guru Gobind Singh Indraprastha University, Sector
02-12-07 13-6-6 88694Sq,. Metre
MCD-550 KLD, GW-Nil, Discharge-104 KLD
163.24 crore
2008 18.02.2008Unit may be asked to file an affidavit for compliance of EIA
Letter issued on 12.06.2008Com
10.09
18.02.2008Unit may be asked to file an affidavit for
Issue last reminder. Call on 11.07.2008.
11.07
16 Dwarka, New Delhi
clearance conditions.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. Let the unit download the proforma from the net. 03.6.08Issue last reminder. Call on 11.07.2008.
pliance affidavit of EC submitted.
compliance of EIA clearance conditions. 17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. Let the unit download the proforma from the net. 03.6.08Issue last reminder. Call on 11.07.2008.
82 3 16 54 C-16
Uppal Housing Pvt. Ltd , Mehrauli Road, Village Chandahaula, Tehsil Hauz Khas, New Delhi
_ 26-4-07 49559.22 Sq. metre
MCD-227 KLD, GW-Nil, Discharge-104 KLD
110.884 Crore
17.3.2008MS to speak to MOEF. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. Take up in April, 2008. 23.04.2008Call on 14.05.2008 with response. 13.05.2008The unit has not complied with the directions of CMC of 17.03.2008 despite two opportunities. EE to check on the net if any adverse order has
Letter issued on 28-5-2008.
No reply received so for. Letter issued to project proponent on 01-07-08. Also a letter issue to DC South on 01-07-08. Reply received from the project proponent on 01-07-08.
No reply
10.09 17.3.2008MS to speak to MOEF. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. Take up in April, 2008. 23.04.2008Call on 14.05.2008 with response. 13.05.2008The unit has not complied with the directions of CMC of 17.03.200
Call for personal hearing on 18.06.2008 at 7.00 PM with all the documents asked so far.
17.07
been passed against the unit by MOEF and also there is any further developments in MOEF in this case. Unit may be issued a final reminder to file EC and the documents required by DPCC by 03.06.2008 failing which action as per environmental legislations will be taken against the unit. 03.6.08Call for personal hearing on 18.06.2008 at 7.00 PM with all the documents asked so far.
received from DC(South).
8 despite two opportunities. EE to check on the net if any adverse order has been passed against the unit by MOEF and also there is any further developments in MOEF in this case. Unit may be issued a final reminder to file EC and the documents required by DPCC by 03.06.2008 failing which action as per environmental legislations will be
18.06.2008In the letter of MOEF dated 21.05.2008, MOEF has asked for DDA permission to construct on agriculture land. The unit claims that the land is not agricultural but extended ‘Abadi’. Let the unit file a copy of Khatauni which will clearly indicate whether the land is actually extended Abadi. A letter may also be written to Dy. Commissioner (South) by MS for a separate confirmatio
taken against the unit. 03.6.08Call for personal hearing on 18.06.2008 at 7.00 PM with all the documents asked so far. 18.06.2008In the letter of MOEF dated 21.05.2008, MOEF has asked for DDA permission to construct on agriculture land. The unit claims that the land is not agricultural but extended
n on whether group housing can be allowed on this plot. Call on 18.07.2008.
‘Abadi’. Let the unit file a copy of Khatauni which will clearly indicate whether the land is actually extended Abadi. A letter may also be written to Dy. Commissioner (South) by MS for a separate confirmation on whether group housing can be allowed on this plot. Call on 18.07.2008.
84 3 18 55 C-18
DLF Ltd. , Block W, Greater Kailash, New Delhi
26-12-07 03-08-07 23281.258 Sq. Metre
MCD-155.72 KLD, GW-Nil, Discharge-44.61 KLD
53.19 crore
may,2008
23.04.2008Ask the unit to file affidavit indicating date of start of construction and completion of construction and also to submit completion certificate. Call on 21.05.2008. 28.05.2008The unit vide its consent application is showing water drawl of 1.55 Lakh litres per day and waste water discharge upto 80 % of the same. The unit must file authorization from local body for such a huge drawl of
MS has to study and same is to be reported to CMC. Also reply received from the project proponent.
10.09 23.04.2008Ask the unit to file affidavit indicating date of start of construction and completion of construction and also to submit completion certificate. Call on 21.05.2008. 28.05.2008The unit vide its consent application is showing water drawl of 1.55 Lakh litres per day and waste water discharge
The unit has filed a detailed reply which MS has to study. Case is to be taken up in CMC on 11.07.2008.
The unit has filed a detailed reply which MS has to study. Case is to be taken up in CMC on 11.07.2008.
Call on 18.06.2008.
11.07
water and its professional treatment so that only treated effluent enters the drain. SIT while inspecting will devote specific attention to these two points along with D.G Sets details and their impact. As regard the item-wise compliance affidavit filed by the unit, SIT will also cross check what is stated there and submit its report on 18.06.2008. Call on 18.06.2008. 03.6.08Call on 18.06.2008.
upto 80 % of the same. The unit must file authorization from local body for such a huge drawl of water and its professional treatment so that only treated effluent enters the drain. SIT while inspecting will devote specific attention to these two points along with D.G Sets details and their impact. As regard the item-wise
26.06.2008The unit has filed a detailed reply which MS has to study. Case is to be taken up in CMC on 11.07.2008.
compliance affidavit filed by the unit, SIT will also cross check what is stated there and submit its report on 18.06.2008. Call on 18.06.2008. 03.6.08Call on 18.06.2008. 26.06.2008The unit has filed a detailed reply which MS has to study. Case is to be taken up in CMC on 11.07.2008.
85 3 19 56 C-19
Construction of General Pool Accomodation at Vasant Vihar
_ Not applied
18.02.2008Ask the unit to apply for afresh Consent to Establish. Also ask them to file EIA clearance.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 14.05.2008 reminding about Consent to Establish and Environmental Clearance. 13.05.2008MS to speak CPWD and ensure that application for Consent to Establish and a copy
Letter isued on 13.06.2008 for CTE & EC.No reply received.
10.09 18.02.2008Ask the unit to apply for afresh Consent to Establish. Also ask them to file EIA clearance.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 14.05.2008 reminding about Consent to Establish and Environmental Clearance. 13.05.200
Issue reminder. Call on 11.07.2008.
11.07
of Environmental Clearance are filed by 10.06.2008. Call on 10.06.2008. 03.6.08Issue reminder. Call on 11.07.2008.
8MS to speak CPWD and ensure that application for Consent to Establish and a copy of Environmental Clearance are filed by 10.06.2008. Call on 10.06.2008. 03.6.08Issue reminder. Call on 11.07.2008.
86 3 20 57 C-20
Redevelopment of GPRA , Aliganj, Jorbagh
_ Not applied
NA NA NA NA 18.02.2008Ask the unit to apply for afresh Consent to Establish. Also ask them to file EIA
Letter isued on 13.06.2008No reply received.
10.09
18.02.2008Ask the unit to apply for afresh Consent to Establish.
Issue reminder. Call on 11.07.2008.
11.07
clearance.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
Also ask them to file EIA clearance.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
88 3 22 58 C-22
Squash and Badminton Stadium, Sri Fort Complex
_ Not applied
NA NA NA NA 18.02.2008Ask the unit to apply for Consent to Establish. Also ask the previous EE to file his explanation on whose orders notice was issued.
Letter issued on 12.06.2008No reply received.
10.09 18.02.2008Ask the unit to apply for Consent to Establish. Also ask the previous EE to file his explanati
Issue reminder. Call on 11.07.2008.
11.07
17.3.2008MS to check from MOEF for Environmental Clearance. Take up in April, 2008. 23.04.2008Ask him to apply for Consent to Establish. Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
on on whose orders notice was issued.
17.3.2008MS to check from MOEF for Environmental Clearance. Take up in April, 2008. 23.04.2008Ask him to apply for Consent to Establish. Call on 21.05.2008. 03.6.08Issue reminder. Call on 11.07.2008.
90 3 24 59 C-24
IRCON International Limited , Plot No. C-4 District Centre, Saket, New Delhi
_ 06-03-08 16206metre square
MCD-Nil, GW-Nil,purchased from outside, Waste water discharge-35000LPD
75 crore
Not Available
18.02.2008Ask the unit to apply for EIA clearance.
17.3.2008MS to speak to concerned authority. Take up in April, 2008. 23.04.2008MS to write to the MD asking him to submit 1. Consent to Establish application.2. Copy of Environmental Clearance.3. Affidavit indicating date of start of construction and completion of construction.4. Approved architectura
Letter issued on 12.06.2008Reply received on 20.06.2008 & 02.07.2008
10.09 18.02.2008Ask the unit to apply for EIA clearance.
17.3.2008MS to speak to concerned authority. Take up in April, 2008. 23.04.2008MS to write to the MD asking him to submit 1. Consent to Establish application.2. Copy of Environmental Clearance.3.
Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008
11.07
l drawing.5. Completion certificate.6. Water discharge details. Call on 21.05.2008. 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 11.07.2008
Affidavit indicating date of start of construction and completion of construction.4. Approved architectural drawing.5. Completion certificate.6. Water discharge details. Call on 21.05.2008. 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, details, ground water and water cess
payment as per Cess Act. Call on 11.07.2008
91 3 25 60 C-25
I.G.I.B. , CRRI Campus, Mathura Road, New Delhi
_ Not applied
23413.38 M2
MCD-58KLD, GW-NIL, Waste Water-46KLD
46.26 Crore
2010 18.02.2008Ask the unit to apply for Consent to Establish. Also ask the previous EE to file his explanation on whose orders notice was issued.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
Letter issued on 12.06.2008No reply received.
10.09 18.02.2008Ask the unit to apply for Consent to Establish. Also ask the previous EE to file his explanation on whose orders notice was issued.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on
Issue reminder. Call on 11.07.2008.
11.07
21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
92 3 26 61 C-26
General Pool Office accomodation at INA, New Delhi-23
06-05-07 Applied 7073.34M2
MCD-Nil, GW-68.4KLD, Waste Water-55 KLD
84 Crore
Jan,2008 18.02.2008Unit may be asked to file an affidavit for compliance of EIA clearance conditions.
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
Letter issued on 12.06.2008Reply received on 08.07.2008.
10.09 18.02.2008Unit may be asked to file an affidavit for compliance of EIA clearance conditions. 17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue
Issue reminder. Call on 11.07.2008.
11.07
reminder. Call on 11.07.2008.
93 3 27 62 C-27
Construction of International Convention Centre, Sector-24, Dwarka, New Delhi
_ Applied 18300 metre square
MCD-DJB, GW-Nil, Waste water-15,60,000 LPD
3000 Crore
Not Available
18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed on their application by MoE&F.
17.3.2008MS to speak . Take up in April, 2008.
23.04.2008Call on 21.05.2008 with response.
Letter issued on 12.06.2008Reply received on 25.06.2008 with Environment Clearnce
10.09 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed on their application by MoE&F.
17.3.2008MS to speak . Take up in April,
Issue reminder. Call on 11.07.2008.
11.07
03.6.08Issue reminder. Call on 11.07.2008.
2008. 23.04.2008Call on 21.05.2008 with response. 03.6.08Issue reminder. Call on 11.07.2008.
95 3 29 63 C-29
Todays Hotel (New Delhi) Pvt. Ltd., Plot No. 1 Okhla Community CENTER, Delhi-110020
Accorded
22-3-2007
34382 metre square
MCD-250 KLD, GW-Nil, Waste water discharge-90 KLD
113.86 crore
2008 23.04.2008Ask for an affidavit giving itemwise compliance of conditions of Environmental Clearance and check for any adverse order by MOEF. Call on 21.05.2008. 03.6.08Ask the unit to submit itemwise compliance
Letter issued on 12.06.2008Reply received on 25.06.2008 with full facts.
10.09 23.04.2008Ask for an affidavit giving itemwise compliance of conditions of Environmental Clearance and check for any adverse order by MOEF. Call on 21.05.2008. 03.6.08Ask the
Ask the unit to submit itemwise compliance affidavit and an affidavit indicating date of start of construction & date of completion, completion certificate,
11.07
affidavit and an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets and information w.r.t. boiler sought vide letter dated 24.01.2008. Call on
unit to submit itemwise compliance affidavit and an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water
approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets and information w.r.t.
11.07.2008 cess payment as per Water Cess Act, 1977, DG sets and information w.r.t. boiler sought vide letter dated 24.01.2008. Call on 11.07.2008
boiler sought vide letter dated 24.01.2008. Call on 11.07.2008
97 3 31 64 C-31
Army Welfare Housing Organization, Construction of residential project at plot No. 15, Sector 22, Dwarka, New Delhi
19-7-7 13.06.2008
28640.72 Sq. Metre
DJB-285 KLD / GW - Nil / Trade effluent - 205 KLD
25 crores
2010 23.04.2008Reminder for Consent to Establish and itemwise compliance of Environmental Clearance conditions through an affidavit. Call on 21.05.2008. 03.6.08MS to write to DG of Army Welfare Organizatio
Letter issued on 13.06.2008.Applied for CTE only on 13.06.2008.No EC compliance affida
10.09 23.04.2008Reminder for Consent to Establish and itemwise compliance of Environmental Clearance conditions through an affidavit. Call on 21.05.2008. 03.6.08
MS to write to DG of Army Welfare Organization for Consent to Establish and itemwise compliance. Call on 11.07.2008
11.07
n for Consent to Establish and itemwise compliance. Call on 11.07.2008
vit submitted.
MS to write to DG of Army Welfare Organization for Consent to Establish and itemwise compliance. Call on 11.07.2008
98 3 32 65 C-32
Army Welfare Housing Organization, Construction of residential project at plot No. 16, Sector 23, Dwarka, New Delhi
Not known
13.06.2008
44004 sqm
DJB-436 KLD / GW-Nil / Trade effuent - 314 KLD
40 crores
2010 23.04.2008Reminder for Consent to Establish and itemwise compliance of Environmental Clearance conditions through an affidavit. Call on 21.05.2008. 03.6.08MS to write to DG of Army Welfare Organizatio
Letter issued on 13.06.2008Applied for CTE.EC not applied.
10.09 23.04.2008Reminder for Consent to Establish and itemwise compliance of Environmental Clearance conditions through an affidavit. Call on 21.05.2008. 03.6.08
MS to write to DG of Army Welfare Organization for Consent to Establish and copy of Environmental Clearance. Call on 11.07.2008
11.07
n for Consent to Establish and copy of Environmental Clearance. Call on 11.07.2008
MS to write to DG of Army Welfare Organization for Consent to Establish and copy of Environmental Clearance. Call on 11.07.2008
102 3 36 66 C-36
Construction of modern Inter State Bus terminal (ISBT) at Sarai kale Khan, New Delhi by M/s Executive Engineer, Building Project Division, New Delhi.
_ Not applied.
NA NA NA NA 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 03.6.08Issue reminder to MD, DIMTS to file Consent to Establish &
Letter issued on 12.06.2008No reply received.
10.09 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 03.6.08Issue reminder
Issue reminder to MD, DIMTS to file Consent to Establish & Environmental Clearance. Call on 11.07.2008
11.07
Environmental Clearance. Call on 11.07.2008
to MD, DIMTS to file Consent to Establish & Environmental Clearance. Call on 11.07.2008
103 3 37 67 C-37
Construction of Integrated Freight Complex at Sector 25 & 26, Dwarka Sub City, Phase-II, North West District., NCT of Delhi by M/s Delhi State Industrial and Infrastructure Development Corpora
_ Not applied.
NA NA NA NA 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 03.6.08MS to remind MD, DSIIDC to file Consent to Establish & Environmental Clearance. Call on 11.07.2008
Letter issued on 12.06.2008Reply received on 29.07.2008.
10.09 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 03.6.08MS to remind MD, DSIIDC to file Consent to
MS to remind MD, DSIIDC to file Consent to Establish & Environmental Clearance. Call on 11.07.2008
11.07
tion Ltd. Establish & Environmental Clearance. Call on 11.07.2008
109 3 43 68 C-43
Marc Hotel, Mahipalpur by M/s Dee Marks Hotel & Resorts
17.03.2008Issue a letter asking the unit to apply for Consent to Establish.
Letter issued on 02.04.2008No reply received.
10.09
17.03.2008Issue a letter asking the unit to apply for Consent to Establish.
Z
118 CW 52 69 CW-8
Table Tennis Sports Complex, yamuna Sports Complex
24-01-07 jointly for Rugby Stadium also
05-05-08 19500 Sqm in EC , 13527 in application
MCD 75 KLD AND GW 125 KLD / 160 KLD IN MCD Sewer
140 Crore
s
2008 01.05.2008Issue fresh reminder to file Consent to Establish. Call on 03.06.2008. 03.6.08Ask the unit to file item-wise complian
Letter issued.Reply received.
10.09 01.05.2008Issue fresh reminder to file Consent to Establish. Call on 03.06.2008. 03.6.08Ask the unit to file
Ask the unit to file item-wise compliance affidavit. Call on 11.07.2008.
11.07
ce affidavit. Call on 11.07.2008.
item-wise compliance affidavit. Call on 11.07.2008.
26 26 70 A-26
M/s D.J. Infrastructure Developers (P) Ltd, 201, Surya Kiran Building, K.G Marg, New Delhi
_ Not applied
_ _ _ _ 10.09 06.08.2008CMC-I indicates that 01 out of the 5 sites is already in the CMC list and four other are not. CMC-I to issue notice to four sites at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.200
8. This must be done without waiting for the minutes.
27 27 71 A-27
M/s ACG Hospitality Pvt Ltd, GL-13, Kocha Tower, Jail road, New Delhi proposed Hotel at IA, Sub Distt Centre, Hari Nagar , New Delhi.
_ Not applied
_ _ _ _ 10.09 06.08.2008CMC-I indicates that 01 out of the 5 sites is already in the CMC list and four other are not. CMC-I to issue notice to four sites at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be
done without waiting for the minutes.
28 28 72 A-28
M/s DG Estate (P) Ltd, A-1/14, Paschim Vihar, Main Rohtak Road, New Delhi- 63 Proposed Hotel at IB, Sub Distt. Centre, Hari Nagar
_ Not applied
_ _ _ _ 10.09 06.08.2008CMC-I indicates that 01 out of the 5 sites is already in the CMC list and four other are not. CMC-I to issue notice to four sites at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be done without
waiting for the minutes.
29 29 73 A-29
M/s S.Chand & Co. Ltd 7361, Ram Nagar, Qutab Road New Delhi , Proposed Hotel at IC, Sub Distt. Centre, Hari Nagar, New Delhi
_ Not applied
_ _ _ _ 10.09 06.08.2008CMC-I indicates that 01 out of the 5 sites is already in the CMC list and four other are not. CMC-I to issue notice to four sites at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be done without waiting for the
minutes. 55 26 74 B-
26Construction of Hotel at CBD Shahdara Mahagun Hotels Pvt. Ltd., C-215, Vivek Vihar, Delhi-95
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be done without waiting
for the minutes.
56 27 75 B-27
Construction of Hotel at Kondli Gharoli Dr. Fresh I.T Park Pvt Ltd B-1/E24, Mohan Co-operative Industrial Estate, Mathura Road, New Delhi.
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be done without
waiting for the minutes.
57 28 76 B-28
Construction of Hotel at 4A District Center Mayur Vihar, IFCI Ltd., IFCI Tower, 61, Nehru Place, New Delhi-110019
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be done
without waiting for the minutes.
58 29 77 B-29
Construction of Hotel at 4B-Mayur Vihar ,Antarctica Properties Co. Ltd., SV-12-13, Bhakaji Cama Place, New Delhi
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This must be
done without waiting for the minutes.
59 30 78 B-30
Construction of Hotel at Community Center Vivek Vihar Kunal Foods Products Pvt. Ltd., G-59, Aggarwal City Plaza, Plot No.17, Mangalam Place, Sec-3, Rohini, Delhi-85
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.2008. This
must be done without waiting for the minutes.
60 31 79 B-31
Construction of Hotel at Community Center Vivek Vihar Perfect Learning Pvt.Ltd. A-12, Swasthya Vihar, Vikas Marg, Delhi-92
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by 10.09.200
8. This must be done without waiting for the minutes.
61 32 80 B-32
Construction of Hotel at Community Center Anand Vihar Best View Properties Ltd. C/o Eldew Infrastructure & Properties Ltd. SV-12-13, Bhikaji Cama Place, New Delhi
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance by
10.09.2008. This must be done without waiting for the minutes.
62 33 81 B-33
Construction of Hotel at 6A-Community Center Mandavali Fazalpur Spirit Hotels & Resorts Pvt. Ltd., 59, Pkt-2, Jasola, New Delhi
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental Clearance
by 10.09.2008. This must be done without waiting for the minutes.
63 34 82 B-34
Construction of Hotel at 6B-Community Center Mandavali Fazalpur SS Infrastructure F-109, Aditya Arcade, Community Centre, Preet Vihar, Delhi-92
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environmental
Clearance by 10.09.2008. This must be done without waiting for the minutes.
64 35 83 B-35
Construction of Hotel at 6C-Community Center Mandavali Fazalpur Indo Green International 313-315, Vikas Deep Building, Laxmi Nagar District Centre, Delhi-92
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and Environm
ental Clearance by 10.09.2008. This must be done without waiting for the minutes.
65 36 84 B-36
Construction of Hotel at Uday Estate Pvt. Ltd. 6, Alipur Road, Ganpati Apptt Civil Lines, Delhi-54
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish and
Environmental Clearance by 10.09.2008. This must be done without waiting for the minutes.
66 37 85 B-37
Construction of Hotel at A-1, Community Centre, Pitampura, Delhi by M/s Sita Kiran Inn Pvt. Ltd., 88-C, Civil Lines, Bareily (UP)
10.09 06.08.2008CMC-II indicates that 10 out of the 20 sites are already in the CMC list and ten other are not on record of DPCC. CMC-II to issue notice to ten sites, at their address given in the DDA list for applying Consent to Establish
and Environmental Clearance by 10.09.2008. This must be done without waiting for the minutes.
83 3 17 86 C-17
Metro Park , Dwarka Morh, Najafgarh
17-05-07 19-6-2008
36828.604 Sq. Metre
MCD-340 KLD, GW-Nil, Discharge-224 KLD
164.90 crore
2008 13.05.2008The unit has filed an affidavit giving item-wise compliance of some of the conditions but not complied with the directions issued vide DPCC letter dated 02.05.2008, based on CMC decision of 23.04.2008. The unit may be given a final reminder to
SIT inspection report to be discussed.Reply received on 04.08.2008
Let the unit seek the Forest Department clearance as trees may be cut, since SIT report indicates there are 6 trees located in the complex. Call on 17.09.2008.
17.09 17.3.2008Take up in April, 2008. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. 23.04.2008Ask the unit to file the copy of forest
SIT to inspect and report. Call on 11.07.2008
11.07 SIT
file the required documents or face closure by 20.5.2008. This may be issued without waiting minutes. 03.6.08SIT to inspect and report. Call on 11.07.2008
clearance and seek affidavit of previous directions. Call on 14.05.2008. 13.05.2008The unit has filed an affidavit giving item-wise compliance of some of the conditions but not complied with the directions issued vide DPCC letter dated 02.05.2008, based on CMC decision of 23.04.2008. The unit may be given
a final reminder to file the required documents or face closure by 20.5.2008. This may be issued without waiting minutes. 03.6.08SIT to inspect and report. Call on 11.07.2008 28.08.2008Let the unit seek the Forest Department clearance as trees may be cut, since SIT report indicates there are 6 trees
located in the complex. Call on 17.09.2008.
46 2 17 87 B-17
Anush Finlease and Construction P Ltd,, Proposed Indus Hotel & SpaPlot No. - 11, CBD, Shahdara, Delhi - 92
08.07.2008
24-04-08 29,121.91 Sqm
264 KLD in EC / 175 KLD (STP)
160 Crores
2008 23.04.2008Issue notice for Consent to Establish and Environmental Clearance without waiting for minutes. Check on MOEF website for any adverse order. Call on 30.04.2008. 13.05.2008Unit has not yet filed Environmental Clearance as its case was discussed on 13.03.2008 and various documentary submissions
Applied for CTE on 24.4.08.EC issued by MOEF on 08.07.2008.Notice for closure issued on 28.07.2008
17.09 23.04.2008Issue notice for Consent to Establish and Environmental Clearance without waiting for minutes. Check on MOEF website for any adverse order. Call on 30.04.2008. 13.05.2008Unit has not yet filed Environmental Clearance as its case
As per decision of CMC dated 25.06.2008.
As per decision of CMC dated 25.06.2008.
Issue reminder for Environmental Clearance and ask the unit to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water
31.07
were required by MOEF. In order to be sure about the factual information, SIT may be asked to inspect the premises and report by 10.06.2008. Call on 11.06.2008. Meanwhile, unit may be asked to submit a copy of Environmental Clearance once again.
03.6.08Issue reminder for Environmental Clearance and ask the unit to file an affidavit indicating date of start of construction
was discussed on 13.03.2008 and various documentary submissions were required by MOEF. In order to be sure about the factual information, SIT may be asked to inspect the premises and report by 10.06.2008. Call on 11.06.2008. Meanwhile, unit may be asked to submit a copy of Environmental Clearance once again.
drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008.
& date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008. 26.06.2008As per decision of CMC dated 25.06.2008. 04.07.2008The unit was called for personal
03.6.08Issue reminder for Environmental Clearance and ask the unit to file an affidavit indicating date of start of construction & date of completion, completion certificate, approved architectural drawing, details of builtup area, plot area, waste water discharge, ground water drawl, permission from
hearing and has not appeared before the Committee today. It appears, it is violating the instructions of DPCC after violation of the Air Act & Water Act, as indicated by the findings of the SIT report. The total built up area is about 29000 sqm. The unit may be issued notice for closure. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 8.30 PM.
Central Ground Water Authority, water cess payment as per Water Cess Act, 1977, DG sets. Call on 11.07.2008. 26.06.2008As per decision of CMC dated 25.06.2008. 04.07.2008The unit was called for personal hearing and has not appeared before the Committee today. It appears, it is violating
the instructions of DPCC after violation of the Air Act & Water Act, as indicated by the findings of the SIT report. The total built up area is about 29000 sqm. The unit may be issued notice for closure. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 8.30 PM. 21.08.2008
The unit came for personal hearing today. It claims that due to ignorance of law they had started the construction without taking the Consent to Establish. They were also under the impression that DDA clearance and the fact that this is a Common Wealth Project and being monitored by DDA, is enough to start the constructi
on. The unit has also confirmed that the total built up area nearly of 29000 sqm. By the logic in terms of pollution approx. 50 % area has been covered. Unit seeks time to consult its remaining Directors on the issue of imposition of damages and Bank Guarantee. Call for personal hearing on 28.08.2008, at 5.30 PM and unit must file affidavit
for item wise compliance of Environment Clearance’s conditions before personal hearing. 28.08.2008 The unit came for personal hearing today. It sought lenient view in the payment for damages and Bank Guarantee on the lines of some similar cases decided by this Committee where only excavation work
had been completed. It also highlighted that the High Level Committee of the Government had enabled the hotel site owners to start the excavation work and seek the required clearances urgently.
The Committee deliberated on the issue for about an hour and gave several options to the project proponent. Finally the
Committee decided that 10 % of ½ % of the project cost of Rs. 160 crores i.e. Rs. 8 Lakhs may be taken as damages and equivalent amount as Bank Guarantee valid for three years. The unit has to file these two by 17.09.2008. As soon as the damages and Bank Guarantee are paid, Consent to Establish should be issued at the same
time. Call on 17.09.2008.
100 3 34 88 C-34
Construction of Indus Hotel & Spa at Plot No. 4, Sector-13, Dwarka, New Delhi by M/s Divine Infracon Pvt. Ltd.
EC obtained
24-4-8 65303.7 metre square
MCD-230KLD, GW-Nil, Discharge-234KLD
457.2 crore
2010 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 03.6.08Issue reminder for Environmental Clearance. Call on 11.07.2008
Letter issued on 12.06.2008.EC received.
17.09 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 03.6.08Issue reminder for Environmental Clearance. Call on 11.07.2008 21.08.2008The representative of the units
Issue reminder for Environmental Clearance. Call on 11.07.2008
11.07
Devine Infracon Pvt. Ltd. & Tirupati Infra Project Pvt. Ltd., in Dwarka appeared before CMC and claimed that both the units have filed Consent to Establish. Concerned CMC ie CMC III to check and bring these cases for personal hearing on 28.08.2008 at 5.45 PM and 6.00 PM respectively. 28.08.2008 The unit came for
personal hearing today. It sought lenient view in the payment for damages and Bank Guarantee on the lines of some similar cases decided by this Committee where only excavation work had been completed. It also highlighted that the High Level Committee of the Government had enabled the hotel site owners to start the excavatio
n work and seek the required clearances urgently.
The Committee deliberated on the issue for about an hour and gave several options to the project proponent. Finally the Committee decided that 10 % of ½ % of the project cost of Rs. 457.20 crores i.e. Rs. 23 Lakhs may be taken as damages and equivalen
t amount as Bank Guarantee valid for three years. The unit has to file these two by 17.09.2008. As soon as the damages and Bank Guarantee are paid, Consent to Establish should be issued at the same time. Call on 17.09.2008.
101 3 35 89 C-35
Construction of Indus Hotel & Spa at Plot No. 3, Sector-10, Dwarka, New Delhi by
Pending with MOEF
24-4-8 55550.17 metre square
MCD-183KLD, GW-Nil, Discharge-172KLD
407.188 crore
2011 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance.
Letter issued on 12.06.2008EC received from MOE
17.09
23.04.2008Ask the unit to submit an application for Consent to Establish and a
Issue reminder for Environmental Clearance. Call on 11.07.2008
11.07
M/s Tirupati Buildings and Offices Pvt. Ltd.
Call on 21.05.2008. 03.6.08Issue reminder for Environmental Clearance. Call on 11.07.2008
F on 08.07.2008.
copy of Environmental Clearance. Call on 21.05.2008. 03.6.08Issue reminder for Environmental Clearance. Call on 11.07.2008 21.08.2008The representative of the units Devine Infracon Pvt. Ltd. & Tirupati Infra Project Pvt. Ltd., in Dwarka appeared before CMC and claimed that both the units
have filed Consent to Establish. Concerned CMC ie CMC III to check and bring these cases for personal hearing on 28.08.2008 at 5.45 PM and 6.00 PM respectively. 28.08.2008 The unit came for personal hearing today. It sought lenient view in the payment for damages and Bank Guarantee on the lines of some similar
cases decided by this Committee where only excavation work had been completed. It also highlighted that the High Level Committee of the Government had enabled the hotel site owners to start the excavation work and seek the required clearances urgently. The Committee deliberated on the issue for about an hour and
gave several options to the project proponent. Finally the Committee decided that 10 % of ½ % of the project cost of Rs. 407.88 crores i.e. Rs. 20 Lakhs may be taken as damages and equivalent amount as Bank Guarantee valid for three years. The unit has to file these two by 17.09.2008. As soon as the damages and Bank
Guarantee are paid, Consent to Establish should be issued at the same time. Call on 17.09.2008.
16 1 16 90 A-16
D.D. Properties Pvt., Plot No 68 & 68/1, Najafgarh Road, Delhi
Pending with MOE&F
Not applied.
__ __ __ __ 03.6.08Call on
18.06.2008. 26.06.2008
SIT to inspect and report. Call
on 31.07.2008.
31.07.2008
Call for personal
hearing on 20.08.2008 at 8.15 PM.
A proper fact sheet
be prepared based on the SIT
report for confronting
the unit. The name
of Structural
Inspection report of SIT to be disucussed.
17.09 03.6.08Call on
18.06.2008.
26.06.2008
SIT to inspect
and report. Call on
31.07.2008.
31.07.2008
Call for personal hearing
on 20.08.2008 at 8.15 PM. A proper
fact sheet be
prepared
SIT to inspect and report. Call on 31.07.2008.
SIT to inspect and report. Call on 31.07.2008.
Call on 18.06.2008.
31.07 SIT
Fabricators is already in our list and so no need
to take cognizance
of SIT report.
based on the SIT
report for confronti
ng the unit. The name of
Structural Fabricato
rs is already in
our list and so no need to
take cognizance of SIT report.
21.08.200
8The unit came for personal hearing today. It claims
that it is going to
change its applicatio
n for Environm
ental Clearance in view of the latest notificati
on of MPD. It has not
applied for
Consent to
Establish and will
do so within a month as soon as decision is taken. The unit
has a proposed built up area of 30000
sqm and total
project cost is Rs. 60 crores approximately. Let the unit
file Consent
to Establish and make amendme
nts for Environm
ental Clearance
and confirm the same in writing to DPCC
by 17.09.2008. Call on 17.09.200
8. 20 1 20 91 A-
20Bharat Sanchar Nigam Ltd., CTO Project, ARA Centre, Jhandewalan, Delhi
Structural Fabricators Pvt Ltd (Anant Raj Agencies P ltd ) Commercial Complex at 67 Najafgarh Road, Kirti Nagar
25-04-08 13655.1 Sqm
MCD-35 KLD And GW 30 KLD / 40 (STP)
48.42crores
31-07-07 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. 27.06.2008SIT to inspect and report. Call on 31.07.2008. 31.07.2008SIT report indicates drawl of ground
As decided a letter issued on 12-08-08. Reply Awaited.
The unit may be communicated the deficiencies noted by SIT and the water sampling done by DPCC and deficiencies of noise monitoring report along with CGWA clearance . Unit to file response by 17.09.2008. Call on 17.09.2008.
17.09 03.6.08Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. 27.06.2008SIT to inspect and report. Call on 31.07.2008.
SIT to inspect and report. Call on 31.07.2008.
Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act.
31.07 SIT
water without CGWA permission. Ask the unit to file water cess payment details and CGWA clearance. Call on 20.08.2008.
31.07.2008SIT report indicates drawl of ground water without CGWA permission. Ask the unit to file water cess payment details and CGWA clearance. Call on 20.08.2008. 21.08.2008The unit may be communicated the deficiencies noted by SIT and the
water sampling done by DPCC and deficiencies of noise monitoring report along with CGWA clearance . Unit to file response by 17.09.2008. Call on 17.09.2008.
43 2 14 92 B-14
Asrani Inns and Resorts Pvt. Ltd., (construction of 'JMJ' Hotel'), Wazirpur District Centre, Delhi
08.07.2008
Applied for CTE on 10.6.08
59, 478.244 Sqm
457 KLD IN EC/ 260 KLD (STP)
235 Crores
__ 23.04.2008Reminder for taking up on 21.05.2008. 03.6.08Issue notice for closure for not applying for Consent to Establish. Call on
Notice for closure issued on 14.06.2008.EC issued by MOEF on 08.07.2008.
17.09
23.04.2008Reminder for taking up on 21.05.2008. 03.6.08Issue notice for closure for not applying
SIT to inspect and report. Call on 31.07.2008.
SIT to inspect and report. Call on 31.07.2008.
Issue notice for closure for not applying for Consent to Establish. Call on 25.06.2008.
31.07 SIT
25.06.2008. 26.06.2008SIT to inspect and report. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 8.45 PM. Meanwhile itemwise compliance affidavit for Environment Clearance conditions must be filed.
SIT report to be discussed.
for Consent to Establish. Call on 25.06.2008. 26.06.2008SIT to inspect and report. Call on 31.07.2008. 31.07.2008Call for personal hearing on 20.08.2008 at 8.45 PM. Meanwhile itemwise compliance affidavit for Environment Clearance conditions must be filed.
21.08.2008The unit came for personal hearing today. Against the total built up area of 59000 sqm the basement covers 30000 sqm , ground and other floors covers 29000 sqm. The unit has excavated the entire area and is in the process of building first basement. In effect 50 % of the area has been affected by pollution during excavatio
n. The unit has total project cost of Rs. 235 crores and sewage quantity of 256 KLD.
In similar cases CMC has levied damages in proportion to the area which has been exposed to pollution which in this case comes to 50 % of 0.5 % of the project cost. This amount to damages of Rs. 58 Lakhs and Bank Guarante
e of Rs. 58 Lakhs valid for three years. The unit agrees to file the same by 17.09.2008. Call on 17.09.2008.
110 3 44 93 C-44
Group Housing Complex at Vasant Kunj by Delhi Development Authority
31.07.2008MS to write to Engineer Member, DDA for Consent to Establish. MS to enclose the copy of MOEF letter to Engineer Member, DDA for his response. Call on 20.08.2008.
Letter issued on 11-08-08
No reply received.
Issue reminder. Call on 17.09.2008.
17.09 31.07.2008MS to write to Engineer Member, DDA for Consent to Establish. MS to enclose the copy of MOEF letter to Engineer Member, DDA for his response. Call on 20.08.2008. 21.08.2008
Z
Issue reminder. Call on 17.09.2008.
79 3 13 94 C-13
The Mira , 1 & 2 Ishwar Nagar, New Delhi
Not Required(Letter from MoEF dated 9.07.2007)
Applied 14838metre square
MCD-Nil, GW-Quanitity not mention, Waste Water Discharge-100 KLD
30 crore
2006 26.06.2008As requested time allowed to file the complete documents by 31.07.2008 including ground water drawl and its permission from CGWA. Call on 31.07.2008. 31.07.2008Final reminder to be issued without waiting for minutes. Call on 20.08.2008.
Letter isued on 04-08-08
Reply received on 11-08-08
Call for personal hearing on 10.09.2008 at 8:00 PM.
10.09 PH
18.02.2008Inspect and report on 29.02.2008. 17.3.2008Take up in April, 2008. 23.04.2008Draft letter will be put up and issued this week. 03.6.2008Issue reminder to file complete affidavit on all the points raised vide our letter dated
As requested time allowed to file the complete documents by 31.07.2008 including ground water drawl and its permission from CGWA. Call on 31.07.2008.
As requested time allowed to file the complete documents by 31.07.2008 including ground water drawl and its permission from CGWA. Call on 31.07.2008.
Issue reminder to file complete affidavit on all the points raised vide our letter dated 28.04.2008 and also to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess
31.07
28.04.2008 and also to file details of waste water discharge, D.G. Set, details, ground water and water cess payment as per Cess Act. Call on 25.06.2008. 26.06.2008As requested time allowed to file the complete documents by 31.07.2008 including ground water drawl and its permission from CGWA. Call on
Act. Call on 25.06.2008.
31.07.2008. 31.07.2008Final reminder to be issued without waiting for minutes. Call on 20.08.2008. 21.08.2008Call for personal hearing on 10.09.2008 at 8:00 PM.
106 3 40 95 C-40
Construction of IT Towers (Office Cum Reatil Complex) at F-79-80, Okhla, Phase-I, New Delhi by Mohan
23.06.2008
54316.89 sqm
MCD-92.2 KLDGW - NilWW - 180.3 KLD(STP Proposed)
102.2 crores
October, 2010
27.06.2008Ask the unit to submit the following documents by 31.07.2008:-(i) Affidavit indicating date of start of construction
Letter issued on 11.07.2008.Reply received on 31-07-08.
Call for personal hearing on 10.09.2008 at 7.30 PM.
10.09 PH
27.06.2008Ask the unit to submit the following documents by 31.07.2008:-(i) Affidavit indicating
Ask the unit to submit the following documents by 31.07.2008:-(i) Affidavit indicating date of start of construction and date
31.07
Machines Ltd., DLF Centre, Sansad Marg, New Delhi
and date of completion.
(ii) Completion certificate. (iii) Approved architectural drawing. (iv) Details of water drawl. (v) Permission from CGWA for ground water drawl. (vi) Details of waste water & its treatment. (vii)Details of D.G. Sets including the information of the acoustic enclosure & stack height.(viii) Copy of Environmental Clearance. (ix) Floor wise built
date of start of construction and date of completion. (ii) Completion certificate. (iii) Approved architectural drawing. (iv) Details of water drawl. (v) Permission from CGWA for ground water drawl. (vi) Details of waste water & its treatment.
(vii)Details of D.G. Sets including the
of completion.
(ii) Completion certificate. (iii) Approved architectural drawing. (iv) Details of water drawl. (v) Permission from CGWA for ground water drawl. (vi) Details of waste water & its treatment. (vii)Details of D.G. Sets including the information of the acoustic enclosure & stack height.(viii) Copy of Environmental Clearance. (ix) Floor
up area.(x) Built up area of basement.(xi) Built up are calculation drawing of each floor and basement.Call on 31.07.2008. 31.07.2008Final reminder be issued. Call on 20.08.2008.
information of the acoustic enclosure & stack height.(viii) Copy of Environmental Clearance. (ix) Floor wise built up area.(x) Built up area of basement.(xi) Built up are calculation drawing of each floor and basement.Call on 31.07.2008. 31.07.2008Final reminder be issued. Call on 20.08.2008. 21.08.2008Call for
wise built up area.(x) Built up area of basement.(xi) Built up are calculation drawing of each floor and basement.Call on 31.07.2008.
personal hearing on 10.09.2008 at 7.30 PM.
14 1 14 96 A-14
Hotel Leelaventure LimitedAfrica Avenue, Chanakya Puri, New Delhi
13.06.2008
06-03-08 39,194.98 Sqm
MCD - 125
KLD / GW - 80 KLD /
218 KLD
306 crores
Mar-10 23.4.2008Issue a reminder to both the addresses to file Consent to Establish and environmental clearance by 30.04.2008. Call on 30.04.2008. 01.05.2008Since the letter was issued by DPCC on 29.04.2008, call on 14.05.2008 with all the documents mentioned in the DPCC letter. 03.6.08The unit has filed the
SIT inspection report to be discussed.
10.09 SIT
23.4.2008Issue a reminder to both the addresses to file Consent to Establish and environmental clearance by 30.04.2008. Call on 30.04.2008. 01.05.2008Since the letter was issued by DPCC on 29.04.2008, call on 14.05.2008 with all the documents mentione
SIT to inspect and report. Call on 11.07.2008.
SIT to inspect and report. Call on 11.07.2008.
The unit has filed the Consent to Establish application but not filed the Environmental Clearance so far. MOEF has raised 12 clarifications in its meeting held on 03.04.2008. The total cost of the
11.07 SIT
Consent to Establish application but not filed the Environmental Clearance so far. MOEF has raised 12 clarifications in its meeting held on 03.04.2008. The total cost of the project is Rs. 611 crores for land & Rs. 306 crores for construction making a total of Rs. 917 crores. The unit may be asked to file clarification on the extent of ground water drawl and the permission for the same and it may be asked to
d in the DPCC letter. 03.6.08The unit has filed the Consent to Establish application but not filed the Environmental Clearance so far. MOEF has raised 12 clarifications in its meeting held on 03.04.2008. The total cost of the project is Rs. 611 crores for land & Rs. 306 crores for construction making a total of Rs. 917 crores.
project is Rs. 611 crores for land & Rs. 306 crores for construction making a total of Rs. 917 crores. The unit may be asked to file clarification on the extent of ground water drawl and the permission for the same and it may be asked to expedite
expedite the submission of copy of Environmental Clearance. Call on 25.06.2008. 26.06.2008SIT to inspect and report. Call on 11.07.2008.
The unit may be asked to file clarification on the extent of ground water drawl and the permission for the same and it may be asked to expedite the submission of copy of Environmental Clearance. Call on 25.06.2008. 26.06.2008SIT to inspect and report. Call on 11.07.2008.
the submission of copy of Environmental Clearance. Call on 25.06.2008.
49 2 20 97 B-20
Shalimar Social Club Society
Built up area is 3450 Sqm
21-05-08 3450 Sqm
MCD .8 KLD & GW .4 KLD /
7.44 Crores
June ----2008
03.6.08SIT to inspect and
SIT report to be discus
10.09 SIT
03.6.08SIT to inspect
SIT to inspect and report.
11.07 SIT
(REGD.)
1.8 KLD (Oil and Grease Trap)
report. Call on 11.07.2008
sed.Letter received on 10.07.2008.
and report. Call on 11.07.2008
Call on 11.07.2008
53 2 24 98 B-24
Omkara Developers (P) Ltd. (Mangalam Paradise), Plot No 8, Manglam Place, Sector -03, Rohini, Delhi
11.07.2008
This case of mall was taken up as table agenda .The mall does not require Environmental Clearance. SIT to inspect and report. Call on 06.08.2008.
SIT report to be discussed.
10.09 SIT
11.07.2008
This case of mall was taken up as table agenda .The mall does not require Environmental Clearance. SIT to inspect and report. Call on 06.08.2008.
6.08 SIT
70 3 4 99 C-4 Cabinet Secretariate Biuilding , Plot No. 5A, CGO Complex, Lodhi Road, New Delhi
29-12-06 Applied 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions.
SIT inspection report to be discussed.
10.09 SIT
18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA condition
SIT to inspect and report. Call on 11.07.2008
11.07 SIT
17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08SIT to inspect and report. Call on 11.07.2008
s. 17.3.2008MS to speak . Take up in April, 2008. 23.04.2008Call on 21.05.2008. 03.6.08SIT to inspect and report. Call on 11.07.2008
76 3 10 100 C-10
Shanti Hospitality Private Ltd , Shanti Ananda Delhi, National Highway-8, Delhi
Pending with MOEF
20.03.2006
7850 sqm (in EC)
GW - 420 KLD / 250 KLD (STP)
79.14 crores
Apr.-06 18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any
SIT inspection report to be discussed.
10.09 SIT
18.02.2008Ask him to file EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain
SIT to inspect and report. Call on 11.07.2008
11.07 SIT
order has been passed on their application by MoE&F.
17.3.2008MS to speak to MOEF. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. Take up in April, 2008. 23.04.2008MS to inspect and report. Call on 21.05.2008. 03.6.08SIT to inspect and report. Call on 11.07.2008
the latest status of the unit and whether any order has been passed on their application by MoE&F.
17.3.2008MS to speak to MOEF. Ask the unit to submit an affidavit w.r.t. date of start of construction and likely date of completion of construction. Take up in April, 2008. 23.04.2008MS to inspect
and report. Call on 21.05.2008. 03.6.08SIT to inspect and report. Call on 11.07.2008
94 3 28 101 C-28
M/s Kenneth Builders & Developers Pvt. Ltd., Maa Anandmayi MARG, Tehkhand, Delhi
_ 30-5-2008
100730 Metre square for EWS+165000 metre square for free sales unit
MCD-2965KLD, GW-Nil, Waste waster discharge- 2668.5KLD
23.04.2008Issue fresh letter with all the requirements of Consent to Establish and Environmental Clearance and ensure it is delievered at the correct address. Call on 21.05.2008. 03.6.08Ask DCF (South) to confirm whether
Letter issued to DCF(South) on 13.06.2008. Also a letter isued to Sh. Bharat Bhushan (Director), MOEF on 26.06
17.09 PH
23.04.2008Issue fresh letter with all the requirements of Consent to Establish and Environmental Clearance and ensure it is delievered at the correct address. Call on 21.05.2008.
Ask DCF (South) to confirm whether they have given the forest clearance. Call on 11.07.2008.
11.07
they have given the forest clearance. Call on 11.07.2008.
.2008
.Reply received from DCF (South) & MOEF.
03.6.08Ask DCF (South) to confirm whether they have given the forest clearance. Call on 11.07.2008. 21.08.2008The unit has sought an adjournment for three weeks for appropriate presentation of their case in CMC. Call for personal hearing on 17.09.2008, at 5.00 PM.
7 1 7 102 A-7 DLF Limted, Construction of Office Complex at DLF Centre Sansad marg
R.C.Sood & Co. Pvt.Ltd.Proposed Shopping Mall at 10, Shivaji Palace, District centre, Raja Garden, Delhi,
26-03-08 18,553.8 Sqm
MCD 13.33 KLD GW--61.17 KLD / 34 KLD
3,04,163,477 crores
1991 26.06.2008The unit has not filed confirmation of payment of the water cess amount from 2003 to 2008 as directed by DPCC vide letter dated 13.06.2008. Unit may be directed to do so by 31.07.2008 without fail. The unit may be also asked permission from CGWA for ground water drawl. Call on 31.07.2008. 31.07.2008Reminder to be issued. Call on 20.08.2008.
As decided, reminder issued on 13-08-08. Reply awaited.
Submit this file administratively after examining all the requirements for Consent to Establish.
A 18.02.2008Ask him to submit EIA clearance of MoE&F first. Also ask him to apply for Consent to Establish.
17.3.2008Take up in April, 2008. 23.04.2008There is no provision in law to provide Consent to Operate directly without Consent to Establish. Let the unit,
The unit has not filed confirmation of payment of the water cess amount from 2003 to 2008 as directed by DPCC vide letter dated 13.06.2008. Unit may be directed to do so by 31.07.2008 without fail. The unit may be also asked permission from CGWA for ground water drawl. Call on 31.07.2008.
The unit has not filed confirmation of payment of the water cess amount from 2003 to 2008 as directed by DPCC vide letter dated 13.06.2008. Unit may be directed to do so by 31.07.2008 without fail. The unit may be also asked permission from CGWA for ground water drawl. Call on 31.07.20
The unit is required to file the water cess amount from May, 2003 when it became applicable. Since the unit falls under the self assessment category, it maybe directed to file water cess amount, from May, 2003 to May, 2008.The unit also
31.07
therefore, file application for Consent to Establish and self assessed cess by 21.05.2008. 03.6.08The unit is required to file the water cess amount from May, 2003 when it became applicable. Since the unit falls under the self assessment category, it maybe directed to file water cess amount,
08. draws ground water and has not filed permission from CGWA. Ask the unit to file the same before 25.06.2008. Call on 25.06.2008.
from May, 2003 to May, 2008.The unit also draws ground water and has not filed permission from CGWA. Ask the unit to file the same before 25.06.2008. Call on 25.06.2008. 26.06.2008The unit has not filed confirmation of payment of the water cess amount from 2003 to 2008 as directed
by DPCC vide letter dated 13.06.2008. Unit may be directed to do so by 31.07.2008 without fail. The unit may be also asked permission from CGWA for ground water drawl. Call on 31.07.2008. 31.07.2008Reminder to be issued. Call on 20.08.2008. 21.08.2008Submit this file administratively
after examining all the requirements for Consent to Establish.
36 2 7 103 B-7 Parsvnath landmark developers Pvt. Ltd (La Tropicana) at Magazine Road, Khber Pass, Civil Line, New Delhi
07-02-07 22-05-06 22717.18 Sqm
MCD 465 KLD / 261KLD(STP)
476.69 Crores
2009 03.6.08SIT to inspect and report. Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. Call on 25.06.2008. 26.06.2008Call for personal hearing on 31.07.2008 at 8.00 PM. 31.07.2008 The unit came for personal hearing today. SIT
Notice issued on 04.08.2008Reply awaited.
Submit this file administratively after examining all the points communicated to the unit.
A 18.02.2008Ask the unit to file the EIA clearance. Separately a copy of this letter may be sent to Addl. Secretary, MoE&F to ascertain the latest status of the unit and whether any order has been passed on their application by MoE&F.
Call for personal hearing on 31.07.2008 at 8.00 PM.
Call for personal hearing on 31.07.2008 at 8.00 PM.
SIT to inspect and report. Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. Call on 25.06.2008.
31.07 PH
has inspected the unit w.r.t. all the Environmental Clearance conditions and found several deficiencies. A notice may be issued to the unit indicating all the deficiencies. The unit claims that it has one D.G. Set and SIT report finds two D.G. Sets out of which one is without acoustic enclosure. Issue this notice without waiting for the minutes. Call on 20.08.2008.
17.3.2008Unit be asked to submit item-wise compliance of conditions laid down in Environmental Clearance and date of start of construction & date of completion through an affidavit. 23.04.2008MS to inspect and report. Call on 14.05.2008. 13.05.2008Since MS needs some more time to inspect,
call on 21.05.2008. 03.6.08SIT to inspect and report. Ask the unit to file details of waste water discharge, D.G. Set, ground water drawl and water cess payment as per Cess Act. Call on 25.06.2008. 26.06.2008Call for personal hearing on 31.07.2008 at 8.00 PM. 31.07.2008
The unit came for personal hearing today. SIT has inspected the unit w.r.t. all the Environmental Clearance conditions and found several deficiencies. A notice may be issued to the unit indicating all the deficiencies. The unit claims that it has one D.G. Set and SIT report finds two D.G. Sets out of which one is without acoustic
enclosure. Issue this notice without waiting for the minutes. Call on 20.08.2008. 21.08.2008Submit this file administratively after examining all the points communicated to the unit.
10 1 10 104 A-10
Hindustan Petroleum Corporation Ltd. (HPCL), Mundra-Delhi Pipeline Project, Haryana Border to Tikri Kalan
20-06-05 Granted 06-05-08
__ __ 1534.84 crores
__ 18.02.2008The unit has requested for extension of the Consent to Establish since DDA is yet to grant them land at Tikrikalan Village. Let the unit file a formal extension application along with consent fee. This may be considered in the next CMC on 29.02.2008.
17.3.2008Take up in April, 2008. 23.04.2008Extended for three years from 24.01.2008. 03.6.08No action.
In the CMC Orange Meeting Dated 18-02-08 it was decided that unit should file a formal extension application alongwith consent fee. Accordingly unit was issued a
NA 18.02.2008The unit has requested for extension of the Consent to Establish since DDA is yet to grant them land at Tikrikalan Village. Let the unit file a formal extension application along with consent fee. This may be considered in the next CMC on 29.02.2008. 17.3.2008Take up in April, 2008.
No action.
NA
letter on 28-02-08. Unit has submitted a reply alongwith a banker cheque for Rs 7,800 against Consent fee for three years and has requested for extending the
23.04.2008Extended for three years from 24.01.2008. 03.6.08No action.
validity of consent to establish by a period of three years upto 24-01-11. The unit has also mentioned that Additional Secretary to LG Delhi has written a letter to DDA advising it
to acquire land for HPCL.at Tikri Kalan.Validity of CTE has been extended for further three years i.e. 23.01.2011.
19 1 19 105 A-19
P.P. Buildwell,Constrcuion of Conventional Center , District Center, Janak
Not applied
Applied __ __ __ __ 03.6.08The unit has sent a letter saying that the Director is out of station and therefore they could not appear on
Unit has deposited cash penalty of Rs. 6 Lakhs and BG
NA
03.6.08The unit has sent a letter saying that the Director is out of station and therefore
SIT to inspect and report and also personal heraing on 27.06.2008 at 6.00
The unit has sent a letter saying that the Director is out of station and therefore they could not
Unit has deposited Bank Guarantee of Rs. 6 Lakhs during the
31.07
Puri, Delhi
29.05.208. It has sought a time for 15 days. Call on 11.06.2008 at 7.30 PM for personal hearing, indicating in the letter that if he fails to appear the action as per law will be taken. 11.6.2008The unit was called for personal hearing and it confirmed that entire construction is completed and Consent to Establish has not been applied for. Ask SIT to inspect and report on 25.06.2008. 26.06.2008SIT to
of Rs. 6 Lakhs. Accordingly, CTE issued.
they could not appear on 29.05.208. It has sought a time for 15 days. Call on 11.06.2008 at 7.30 PM for personal hearing, indicating in the letter that if he fails to appear the action as per law will be taken. 11.6.2008The unit was called for personal hearing and it confirmed that entire construction is completed and Consent to Establish
PM. appear on 29.05.208. It has sought a time for 15 days. Call on 11.06.2008 at 7.30 PM for personal hearing, indicating in the letter that if he fails to appear the action as per law will be taken.
CMC meeting. Consent to Establish to be issued. Confirm on 31.07.2008.
inspect and report and also personal heraing on 27.06.2008 at 6.00 PM. 27.06.2008Personal hearing in this case deferred for 11.07.2008 at 8.15 PM, due to want of time. 11.07.2008The unit came for personal hearing today. SIT inspection indicates total built up area of 4434 sqm and completion of construction work and external finishing. Interior finishing work is in progress. The total
has not been applied for. Ask SIT to inspect and report on 25.06.2008. 26.06.2008SIT to inspect and report and also personal heraing on 27.06.2008 at 6.00 PM. 27.06.2008Personal hearing in this case deferred for 11.07.2008 at 8.15 PM, due to want of time. 11.07.2008The unit came for
project cost is Rs. 12.87 Crores. The completion certificate was obtained on 30.05.2008.
Since the case does not require Environmental Clearance, and since the building has been constructed without Consent to Establish, the unit may be asked to file 0.5 % of the project cost as cash penalty and the same amount as Bank Guarantee which comes to Rs. 6 Lakhs as cash penalty and Rs. 6 Lakhs as Bank Guarantee
personal hearing today. SIT inspection indicates total built up area of 4434 sqm and completion of construction work and external finishing. Interior finishing work is in progress. The total project cost is Rs. 12.87 Crores. The completion certificate was obtained on 30.05.2008. Since the case does not require Environm
valid for three years to be filed by 24.07.2008. Call on 24.07.2008. 24.07.2008Unit has deposited Bank Guarantee of Rs. 6 Lakhs during the CMC meeting. Consent to Establish to be issued. Confirm on 31.07.2008. 31.07.2008No action.
ental Clearance, and since the building has been constructed without Consent to Establish, the unit may be asked to file 0.5 % of the project cost as cash penalty and the same amount as Bank Guarantee which comes to Rs. 6 Lakhs as cash penalty and Rs. 6 Lakhs as Bank Guarantee valid for three years to be filed by
24.07.2008. Call on 24.07.2008. 24.07.2008Unit has deposited Bank Guarantee of Rs. 6 Lakhs during the CMC meeting. Consent to Establish to be issued. Confirm on 31.07.2008. 31.07.2008No action.
30 2 1 106 B-1
Construction of proposed Hotel "Crown Plaze" at Plot No. 13-A, 13 B District
6/6/2007 & 16-07-07
Granted 08-04-08
50,702 Sqm
MCD 270 KLD / 252 KLD (STP)
22.50 crores
2009 18.02.2008Prof. Gupta to inspect on 01.03.2008. EE, CMC-II to accompany him during
No action.
NA
18.02.2008Prof. Gupta to inspect on 01.03.2008. EE, CMC-II to
No action.
NA
Centre, Mayur Vihar, New Delhi-110096
the inspection. Inspection report to be filed during ATR meeting of these cases in March 2008. 17.3.2008In view of the fact that date of construction of the unit was not made clear even during the inspection, and in view of the fact that the basement construction was started sometime before the Consent to Establish application and Environmental Clearance was received, an opportunity of being
accompany him during the inspection. Inspection report to be filed during ATR meeting of these cases in March 2008.
17.3.2008In view of the fact that date of construction of the unit was not made clear even during the inspection, and in view of the fact that the basement construction was started sometime before the Consent to
heard may be granted to the unit on 25.03.2008 at 4.30 PM.
03.4.08Personal hearing accorded. Asked to submit pealty, BG and separate CTE applications by 10.4.08 23.04.2008No action. 03.6.08No action.
Establish application and Environmental Clearance was received, an opportunity of being heard may be granted to the unit on 25.03.2008 at 4.30 PM. 03.4.08Personal hearing accorded. Asked to submit pealty, BG and separate CTE applications by 10.4.08 23.04.2008No action. 03.6.08
No action.
71 3 5 107 C-5
ONGC Ltd., Plot No.5B, Vasant Kunj, Phase-II, New Delhi
28-11-06 Granted 02.04.08
46,900 sq. mtr
MCD 484 KLD/285kld(STP)
450 cr in EC
07-Jun 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. Each unit must specify what is the exact activity on each of the two plots.
17.3.2008Consent to Establish granted. 23.04.2008No action. 03.6.08No action.
NA
18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. Each unit must specify what is the exact activity on each of the two plots.
17.3.2008Consent to Establish granted. 23.04.2008No action. 03.6.08No action.
No action.
NA
72 3 6 108 C-6
ONGC Videsh Ltd. , Plot 5A Vasant Kunj, Phase-II, New Delhi
Granted 02.04.08
46,900 Sq. mtr
MCD 484 KLD/285kld(STP)
220.71 Crore
Jun-07 18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. Each unit must specify what is the exact activity on each of the two plots.
17.3.2008Consent to Establish granted. 23.04.2008No action. 03.6.08No action.
NA
18.02.2008Ask the unit to submit an affidavit seeking itemwise compliance of EIA conditions. Each unit must specify what is the exact activity on each of the two plots. 17.3.2008Consent to Establish granted. 23.04.2008No action. 03.6.08No action.
No action.
NA
99 3 33 109 C-33
Construction of 5 star Hotel project at Plot No. 15 and 15 A, Non-Heirachial Commercial Complex, Jasola, Delhi by M/s Emmar MGF Land Pvt. Ltd.
EC obtained
05-01-08 71693.80 metre square
MCD-262KLD, GW-Nil, Discharge-236 KLD
779 crore
2010 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 13.05.2008Ask the unit to file application for Consent to Establish immediately and also itemwise compliance affidavit on 26 conditions under construction phase and 03 general conditions. This may be done by 11.06.2008. Call on 11.06.2008. 03.6.08
Cash penalty & BG of Rs. 39 lakhs each submitted by the project on 30.7.08. CTE issued as decided by CMC on 17.7.08.
NA 23.04.2008Ask the unit to submit an application for Consent to Establish and a copy of Environmental Clearance. Call on 21.05.2008. 13.05.2008Ask the unit to file application for Consent to Establish immediately and also itemwise compliance affidavit on 26 conditions under constructi
Call for personal hearing on 18.07.2008 at 8.30 PM.
Call for personal hearing on 18.07.2008 at 8.30 PM.
SIT to inspect and report. Call on 11.06.2008
31.07
SIT to inspect and report. Call on 11.06.2008 26.06.2008Call for personal hearing on 18.07.2008 at 8.30 PM. 17.07.2008The unit came for personal hearing today. The cost of the project is Rs 779 Crores. SIT report indicates excavation going on and completed upto 10 meters below ground level.
In view of the above, cash penalty of 10 % of the 0.5 % of the project
on phase and 03 general conditions. This may be done by 11.06.2008. Call on 11.06.2008. 03.6.08SIT to inspect and report. Call on 11.06.2008 26.06.2008Call for personal hearing on 18.07.2008 at 8.30 PM. 17.07.2008The unit came for personal hearing today. The cost of the project is
cost i.e. Rs. 39 Lakhs and equivalent amount as Bank Guarantee valid for three years may be deposited by the unit by 31.07.2008. Call on 31.07.2008. 31.07.2008No action.
Rs 779 Crores. SIT report indicates excavation going on and completed upto 10 meters below ground level.
In view of the above, cash penalty of 10 % of the 0.5 % of the project cost i.e. Rs. 39 Lakhs and equivalent amount as Bank Guarantee valid for three years may be deposited by the unit by 31.07.2008. Call on
31.07.2008. 31.07.2008No action.
108 3 42 110 C-42
Indian Oil Corporation Ltd, Mathura Jalndhar Pipeline, Bijwasan, Delhi
_ 16.06.2008
32760 sqm (Plot area)
MCD- Nil / GW - 1 KLD / WW - Nil
27.12 crores
July, 2009
31.07.2008Consent to Establish granted.
Applied for CTE on 16.06.2008 vide I.D. No. 26082.
NA
31.07.2008Consent to Establish granted.
Z
111 CW 45 111 CW-1
Dr. Karni Singh Shooting Range(Upgradation, Renovation & New Construction), Tuglakabad, New Delhi
Having EC from MoEF
17-9-2007
89000 metre square
MCD-Nil, GW-100KLD, Discharge-80 KLd
30 2007 01.05.2008Issue Consent to Establish. 03.6.08No action.
Consent to Establish issued.
NA
01.05.2008Issue Consent to Establish. 03.6.08No action.
No action.
NA
112 CW 46 112 CW-2
Major Dhyan Chand Nationa
YES Applied 01.05.2008
Consent to Establish
NA 01.05.2008
No action.
NA
l Stadium (Remodelling & Upgradation), Near India Gate, New Delhi
Issue Consent to Establish. 03.6.08No action.
issued.
Issue Consent to Establish. 03.6.08No action.
113 CW 47 113 CW-3
Jawaharlal Nehru Stadium (Upgradation, Renovation & New Construction), Jawaharlal Nehru Sports Complex, New Delhi
YES Applied 01.05.2008Issue Consent to Establish. 03.6.08No action.
Consent to Establish issued.
NA
01.05.2008Issue Consent to Establish. 03.6.08No action.
No action.
NA
114 CW 48 114 CW-4
Dr. S.P. Mukherjee Swimming Complex(Upgradation,
YES Applied 01.05.2008Issue Consent to Establish.
Consent to Establish issued.
NA 01.05.2008Issue Consent to Establish.
No action.
NA
Renovation & New Construction),Talkatora, New Delhi
03.6.08No action.
03.6.08No action.
115 CW 49 115 CW-5
Indira Gandhi Stadium Complex, I.G. Stadium I.P.Estate, New Delhi
YES Applied 01.05.2008Issue Consent to Establish. 03.6.08No action.
Consent to Establish issued.
NA
01.05.2008Issue Consent to Establish. 03.6.08No action.
No action.
NA
116 CW 50 116 CW-6
Commonwealth Village, Near Akshardham Temple
14-12-06 13-09-06 2,27,640 Sqm
MCD 3010 KLD during Games and 1225 KLD after games / 2408 KLD during Games and 980 KLD after Games
850 Crores
2007 01.05.2008Ask for itemwise compliance of all conditions laid down by MoEF, GOI in the Environmental Clearance in the
Letter issued on 08.07.2008.Reply received on 16.07.2008 & informed that where Common Wealth
NA
01.05.2008Ask for itemwise compliance of all conditions laid down by MoEF, GOI in the Environ
Issue reminder. Call on 31.07.2008.
Issue reminder. Call on 31.07.2008.
Ask the unit to file ground water drawl figures and permission from CGWA. Call on 18.06.2008. Issue letter in this case without waiting for
31.07
form of an affidavit. Call on 03.06.2008 03.6.08Ask the unit to file ground water drawl figures and permission from CGWA. Call on 18.06.2008. Issue letter in this case without waiting for minutes. 26.06.2008Issue reminder. Call on 31.07.2008. 31.07.200
Games Village is developed, does not fall under the noitifed area. Hence, no permission is sought from CGWA.
mental Clearance in the form of an affidavit. Call on 03.06.2008 03.6.08Ask the unit to file ground water drawl figures and permission from CGWA. Call on 18.06.2008. Issue letter in this case without waiting for minutes. 26.06.2008
minutes.
8Since all the Environmental Clearance conditons are being complied with except six monthly moniotirng report to be sent to DPCC, the unit is granted Consent to Establish with clear direction that six monthly monitoring report must be submitted to DPCC without any delay. This Consent to
Issue reminder. Call on 31.07.2008. 31.07.2008Since all the Environmental Clearance conditons are being complied with except six monthly moniotirng report to be sent to DPCC, the unit is granted Consent to Establish with clear
Establish may be sent to Commissioner, Common Wealth Games , DDA without waiting for minutes.
direction that six monthly monitoring report must be submitted to DPCC without any delay. This Consent to Establish may be sent to Commissioner, Common Wealth Games , DDA without waiting for minutes.
117 CW 51 117 CW-7
Thyagrajan Sports Comple
Copy of EC not enclosed.
11-05-07 30539metre sqyare
MCD-DJB, GW-Nil, Waste
97.45 crore
Not mentioned
01.05.2008Time
CTE issued.
NA
01.05.2008Time
Call on 11.07.2008
Z
x, Thyagaraj Nagar, New Delhi
water-3500 LPD
allowed till 03.06.2008. 03.6.08Call on 11.07.2008 26.06.2008Consent to Establish granted.
allowed till 03.06.2008. 03.6.08Call on 11.07.2008 26.06.2008Consent to Establish granted.
21 1 21 118 A-21
Purearth Infrastructure Ltd20, Manohar lal Khurana Marg,New Delhi - 6
Applied CTE issued on 14.07.2008
217439 sqm
MCD: 926 KLD / 787.1 KLD (STP)
302 Cr.
2011 04.07.2008The unit has not started construction for Plaza -IV as directed by DPCC. The unit has applied for Environmental Clearance in MOEF and has stated that the case is listed for hearing on 17.07.2008. The limited
Case was discussed in CMC meeting held on 04.07.2008. As decided, unit has deposited cash penalty of Rs. 1 crore
The letter of the MoEF and a detailed case background may be put up before SEIAA Committee in its first meeting.
17.09 28.05.2008(i) The unit has not replied to the point whether only flatted factory will be built or residential / commercial complex will also be built. Issue
Call on 18.06.2008.
11.07
matter before DPCC is the violation of the Air & Water Acts so far. The Consent Management Committee has taken an impartial view in all such matters and imposed a penalty of 0.5 % of cash and 0.5 % by way of Bank Guarantee of the total project cost of Rs. 302 crores. The unit pleads that it has not started construction for Plaza-IV, which accounts for 50 % of the built up area. The unit also confirms that it will submit the
and BG of Rs. 2 crores.CTE issued.A letter received from MOEF wherein MOEF has directed to DPCC to take necessary action u/s 5 of EP Act as the unit has started the construction before obtaining EC.
notice to the unit to confirm the same. (ii) Unit has shown 40 % completion in Plaza-I, 10 % in Plaza-2, 60 % in Plaza-3 and no construction in Plaza-4. The Committee of the view that the unit should not undertake any construction in Plaza-4 till Environmental Clearance is obtained.
The Committee after
penalty and Bank Guarantee before 11.07.2008, if the Committee can consider the non construction in Plaza-IV in their calculations. The Committee deliberated on this matter and finally decided to impose a cash penalty of Rs. 1 crore and Bank Guarantee of Rs. 2 crores valid for three years for not violating any of the environmental legislations applicable in Govt. of Delhi. If, this is
deliberation has decided to call the unit for personal hearing on 18.06.2008 at 6.30 PM for further course of action. 03.6.08Call on 18.06.2008. 18.06.2008The unit did not come for personal hearing but filed a letter stating that the Directors are abroad and the opportunity may be given in 1st week of July, 2008.
complied with by 11.07.2008, unit may be issued Consent to Establish at the time of filing of the cash penalty
& Bank Guarantee. Call on 11.07.2008.
Call on 03.07.2008 for personal hearing at 5.00 PM. 04.07.2008The unit has not started construction for Plaza -IV as directed by DPCC. The unit has applied for Environmental Clearance in MOEF and has stated that the case is listed for hearing on 17.07.2008. The limited matter before DPCC is the
violation of the Air & Water Acts so far. The Consent Management Committee has taken an impartial view in all such matters and imposed a penalty of 0.5 % of cash and 0.5 % by way of Bank Guarantee of the total project cost of Rs. 302 crores. The unit pleads that it has not started construction for Plaza-IV, which accounts for 50 %
of the built up area. The unit also confirms that it will submit the penalty and Bank Guarantee before 11.07.2008, if the Committee can consider the non construction in Plaza-IV in their calculations.
The Committee deliberated on this matter and finally decided to impose a cash penalty of Rs. 1 crore and Bank
Guarantee of Rs. 2 crores valid for three years for not violating any of the environmental legislations applicable in Govt. of Delhi. If, this is complied with by 11.07.2008, unit may be issued Consent to Establish at the time of filing of the cash penalty & Bank Guarantee. Call on 11.07.2008. 28.08.2008The letter
of the MoEF and a detailed case background may be put up before SEIAA Committee in its first meeting. 03.09.2008Call on 17.09.2008.
Sl. No
Name of Industry / Unit
Address Activity Production figure
BG Submitted
CTE status
Consent Status
Status of authorization
Earlier Decisions
ATR for 03.09.2008
Decision on 03.09.2008
Coading Tag Call on ATR for 06.08.2008
Decision on 06.08.2008
1 Arihant Industries
A-101/1 A Re-rolling & Pickling
800-900 Kg/day (as per inspection report)
BG of Rs. 3 Lakhs submitted on 28.09.2007.
CTE obtained on 04.03.2008 vide consent order no. 18454 (valid upto 03.03.2009)
CTO on 06.08.2007.
06.08.2007. 24.04.2008SIT to inspect in June, 2008. 29.05.2008Call on 03.07.2008 06.08.2008Consent to Establish granted.
CTE already issued. Hence, CTE not issued again.
Ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and also to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
2 MM 30.10.08 SIT inspection report to be discussed.
Consent to Establish granted.
2 Gupta Enterprises
B-47/2, Group
Annealing, Re-Rolling & Pickling of SS Sheets.
01 tonne (as per inspection report)
BG submitted on 21.11.2007
CTE on 21.11.2007 vide I.D. No. 24275.
CTO was valid up to 30.9.2005.CTO(R)
Applied for authorization on 26.07.2006 vide I.D. No. 2948.
29.05.2008Ask the unit to file new adequacy
Letter issued.Replies received on 30.06.2008
Last and final reminder for submission of CGWA clearance
5 MM 30.10.2008
Letter issued.Replies received on 30.06.2008 & 01.07.2008AR not
Call on 03.09.2008.
28.09.2007.
report, permission from Central Ground Water Authority for ground water drawl and affidavit for correction of deficiencies noted during the inspection by SIT. 06.08.2008Call on 03.09.2008.
& 01.07.2008AR not submitted.Unit has informed that they have submitted the fee to GGS Univesity. As soon as they get the AR, the same will be submitted.Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, same will be submitted.Affidavit submitted.
and adequacy report of ETP. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
submitted.Unit has informed that they have submitted the fee to GGS Univesity. As soon as they get the AR, the same will be submitted.Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, same will be submitted.Affidavit submitted.
3 Rana Motors Pvt. Ltd.
A-3 Service Station
25-30 cars (as per inspection report)
BG of Rs. Three Lakh submitted on 22.11.2007
CTE on 15.01.2008 vide I.D. No. 24752.
CTO refused on 09.10.2007. CTO
Refused on 09.10.2007. Applied on 23.01.2008 vide I.D. No.
29.05.2008Ask the unit to file permission
Letter issued.Reply received on
Call on 30.10.20008
30.10.
30.10. Letter issued.Reply received on 27.06.2008Affidavit along with
Call on 03.09.2008.
on 24.08.2006 vide I.D. No. 19123.
4469. from Central Ground Water Authority for ground water drawl and affidavit for correction of deficiencies noted during the inspection by SIT. 06.08.2008Call on 03.09.2008.
27.06.2008Affidavit along with photographs submitted.Permission from CGWA not submitted. Unit has informed that they have approched to CGWA fro permission of ground water drawl.
photographs submitted.Permission from CGWA not submitted. Unit has informed that they have approched to CGWA fro permission of ground water drawl.
4 Sahil Mohit & Co.
B-85 Re-rolling & Pickling
10 tonnes / month (as per inspection report)
BG of Rs. Three Lakh submitted on 24.12.2007
CTE on 13.2.2008 with ID No. 24929
CTO on 09.11.2004 vide I.D. No. 12091.
Applied for renewal of authorization on 18.08.2006 vide I.D. No. 3365.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008.
Letter issued.Reply received on 01.07.2008Permssion from CGWA not submitted. Unit has submitted a copy of application which has filed to CGWA for permission for ground water drawl.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010,
4 MM 30.10.2008
Letter issued.Reply received on 01.07.2008Permssion from CGWA not submitted. Unit has submitted a copy of application which has filed to CGWA for permission for ground water drawl.
Call on 03.09.2008.
which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
5 Scorpion Iron Steel Pvt. Ltd.
A- 135 Manufacturing of utensils involving Buffing
2 tonnes / day (as per affidavit)
BG submitted on 26.09.2007.
CTE obtained on 04.03.2008 vide consent order no. 18453 (valid upto 03.03.2009)
CTO revoked on 09.08.2007
Not applicable
29.05.2008Ask the unit to file affidavit for correction of deficiencies noted during the inspection by SIT, failing which Bank Guarantee will be forfeited. 06.08.2008Consent to Establish granted.
CTE already issued. Hence, CTE not issued again.
No action. NA Letter issued.Reply along with photographs received on 01.07.2008Affidavit submitted.
Consent to Establish granted.
6 Shiv Shakti Industries
A-84/1 Re-Rolling & Pickling of S.S.Sheets
1 T/Day as per affidavit.
BG of Rs. Three Lakh submitted on 23.10.2007.
CTE issued as decided in CMC meeting dated 26.02.200
CTO(R) applied on 12.10.2006
Authorization issued as decided in CMC meeting dated 26.02.2008.
29.05.2008Ask the unit to file permission from Central
Letter issued.Reply received on 30.06.2008Permissio
Call on 30.09.2008 with SIT report.
SIT 30.09 Letter issued.Reply received on 30.06.2008Permission from CGWA submitted. Affidavit
SIT to inspect on pH and report. Call on 03.09.2008.
8. Ground Water Authority for ground water drawl and affidavit for correction of deficiencies noted during the inspection by SIT, failing which Bank Guarantee will be forfeited. 06.08.2008SIT to inspect on pH and report. Call on 03.09.2008.
n from CGWA submitted. Affidavit submitted.SIT report to be discussed.
submitted.
7(a) Shri Sai Enterprises
B-27/2, Group
Pickling 1 Tonne/day as per affidavit.
BG of Rs. Three Lakh submitted on 31.12.2007.
CTE issued as decided in CMC meeting dated 26.02.2008.
CTO (Re) applied on 05.10.2007 vide ID No. 23785
Revocation of authorization on 01.10.2007
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl and affidavit for correction of deficiencies noted during the inspection by SIT, failing which Bank Guarantee will be forfeited. Notice for closure to Ankit for Consent to
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will subit the same.Affidavit submitted.
Call on 03.09.2008.
Establish. 06.08.2008Call on 03.09.2008.
subit the same.Affidavit submitted.
under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
7(b) Ankit Exim Pvt. Ltd.,
B-27/2, Group
Re-rolling and annealing of S.S. Sheets at ground floor & utensils cutting at 1st floor
CTE on 05.06.2008 vide I.D. No. 25985.
06.08.2008Ask the unit to file clearcut details about stack height and acosutic enclosure of D.G. Set. Call on 03.09.2008
Letter issued on 18.08.2008.Reply received on 25.08.2008 and given the details . Installed accoustic enclosure.
Issue Consent to Esstablish.
CTE Notice for closure issued.Reply received on 03.07.2008. Unit has informed that they have applied for CTE on 05.06.2008 vide I.D. No. 25985.
Ask the unit to file clearcut details about stack height and acosutic enclosure of D.G. Set. Call on 03.09.2008
8(a) Avtar Refrigeraton Industries
C-57/1 Re-Rolling & Pickling of S.S.Sheets
2-3 tonne (as per inspection report)
BG of Rs. Three Lakh submitted on 03.01.2008
CTE obtained on 05.01.2004. Valid upto 05.01.2005. CTO refused on 07.08.2007 vide refusal no. 1646..
CTE obtained on 05.01.2004. Valid upto 05.01.2005. CTO refused on 07.08.2007 vide refusal no. 1646..
Refused on 07.08.2007.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. Issue notice for closure to three units found by SIT
Letter issued.Reply received on 29.07.2008.No permission from CGWA submitted. Unit has informed that they
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is
4 MM 30.10.2008
Letter issued.Reply received on 29.07.2008.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be
Call on 03.09.2008.
06.08.2008Call on 03.09.2008.
have applied for permission to CGWA. As and when the permission will come the same will be submitted.
within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
submitted.
8(b) New Goel Steel
C-57/1, 1st Floor
Circle cutting
CTE on 29.08.2008 vide I.D. No. 27131
CTO on 07.08.2007 vide I.D. No. 23029 under Green category
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Reply received on 03.07.2008. Unit has informed that they have applied for CTO, under green category on 07.08.2007 vide I.D. No. 23029.
Shift to Green Committee.
8(c) Hans International
C-57/1, 2nd Floor
Bearing Trading
06.08.2008Call on 03.09.2008
Notice for closure issued.Reply received
Remove from this list.
remove
Notice for closure issued.Reply received on 03.07.2008. Unit has
Call on 03.09.2008
on 03.07.2008. Unit has informed that they are engaged in activity of trading only. No mfg. activity take place. They have only office at the second floor like banks, or shops and donot have any D.G. Set. Being a trader, they are not covered under pollution type activity and requested to withdraw the notice.
informed that they are engaged in activity of trading only. No mfg. activity take place. They have only office at the second floor like banks, or shops and donot have any D.G. Set. Being a trader, they are not covered under pollution type activity and requested to withdraw the notice.
8(d) Neeraj KumarNeeraj Enterprises
C-57/1, 2nd Floor
Assembling of washbasin part
CTE on 19.06.2008 vide I.D. No. 26115 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Reply received on 03.07.2008. Unit has informed that they have applied for CTE on 19.06.2008 vide I.D. No.
Shift to Green Committee.
26115 under Green category.As per CMC (Green) decision dated 18.07.2008, CTE granted.
9 Parmod Steel
C-54, GateNo.5
Pickling and Cold Re Rolling of S.S.Sheets
1 tons (as per inspection report)
Submitted on 25.02.2008
Obtained CTE on 21.9.2005 valid up to 20.9.06
CTO applied on 20.12.2006
Applied for auth on 20.12.06 with ID No. 4178.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will subit the same.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will subit the same.
Call on 03.09.2008
present activity. Call on 30.09.2008.
10 Brij Mohan Ram Mohan
A-86/2 Pickling & Re- Rolling of SS sheet
1 tonne/day (as per inspection report)
Submitted valid up to 06.02.2010 for 3 lakhs
CTE on 27.09.2007 vide I.D. No. 23668.
CTO obtained. Valid upto 30.09.2008.Revoked on 09.2.07
Refused on 09.02.2007
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Reply received on 27.06.2008Permission from CGWA not submitted. Unit has informed that they have applied to CGWA, as soon as they get the permission, the same will be submitted to DPCC.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on
4 MM 30.10.2008
Letter issued.Reply received on 27.06.2008Permission from CGWA not submitted. Unit has informed that they have applied to CGWA, as soon as they get the permission, the same will be submitted to DPCC.
Call on 03.09.2008
30.09.2008.11 Dham
Dyeing & Bleaching Mills
B-63/2 Dyeing , Bleaching and processing of hosiery fabrics
400 Kg (as per inspection report)
Submitted valid up to 06.02.2010 for 3 lakhs BG forfeited as decided by CMC on 24.4.08.
CTE on 18.09.2007 vide I.D. No. 23543.
CTO refused on 13.9.07
Auth refused on 13.9.07
29.05.2008Call on 03.07.2008 with reply of notice issued to the unit earlier. 06.08.2008BG forfeiture decision will not be revoked. Unit to ensure pH within norms and ETP fully functional & operational. Inform the unit accordingly. Call on 03.09.2008.
Letter issued.Reply received on 01.09.2008. Unit has informed that pH will be under norms and ETP is fully equiped and OK and also requested to revoke the decision of forfeiture of BG.
Ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms. Call on 30.09.2008.
1 MM 30.09 Notice issued.Reply received on 03.06.2008.
BG forfeiture decision will not be revoked. Unit to ensure pH within norms and ETP fully functional & operational. Inform the unit accordingly. Call on 03.09.2008.
12 R.J. Enterprises
A-112 Pickling and Cold Re-Rolling of S.S Sheets
750 kg/day as per affidavit.
Submitted on 25.02.2008
CTE on 14.12.2007 vide I.D. No 24493
CTO dt 03.10.06 refused on 18.08.2007 vide refusal no. 1667.
Refused on 18.08.2007.
29.05.2008As SIT observed that pH as 2, forfeit Bank Guarantee under all the three acts. Inform unit accordingly. 06.08.2008SIT report has been checked. The unit needs to construct fresh flooring
Letter issued.Reply along with affidavit & photographs received on 26.08.2008. Unit has informed that they have constructed fresh floring so as to collect all effluents genrated
Ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and also to submit an action plan for stoppage of the activity before 07.02.2010, which falls under
2 MM 30.10.2008
Bank forfeited under all three acts.Unit has submtted its reply and case was taken up CMC on 25.06.2008 and decided to reinspect the unit by SIT.Unit submitted letter requesting for revival of BGs forfeited earlier.
SIT report has been checked. The unit needs to construct fresh flooring and slope of the floor should be towards effluent collection tank. Let the unit do this and confirm it through an affidavit. Call on 03.09.2008.
and slope of the floor should be towards effluent collection tank. Let the unit do this and confirm it through an affidavit. Call on 03.09.2008.
into colleciton tank and requested to revoke the forfeiture of BG.
negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
13(a) Rishabh Steel
C-59/2 Pickling of SS Sheets
2.0-2.5 tonnes (as per inspection report)
Submitted valid up to 06.02.2010 for 3 lakhs
CTE on 22.10.2007 vide I.D. No. 23992.
Applied on 08.11.2007 vide I.D. No. 4416.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. Issue notice for closure to M/s Jai Chand for not applying for Consent to Establish. 06.08.2008Ask the unit to file adequacy report of ETP. Call on 03.09.2008
Letter issued.Reply received on 01.09.2008AR of ETP submitted on 01.09.2008.
Ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and also to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-
2 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will subit the same.A complaint received from Sinter Kings Virmani (P) Ltd. against the unit on 13.06.2008 and requested to the instruct the unit to take proper corrective measures to
Ask the unit to file adequacy report of ETP. Call on 03.09.2008
2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
stop the acid leakage into its premises.Also, a complaint received from Samajwati Andoolan Suraksha against the unit (listed at Sl. No 16 out of 26 cases).
13(b) Jai Chand C-59/2, 1st & 2nd Floor
Mfg of S.S. Utensils
CTE on 07.07.2008 vide I.D. No. 26331.
CTO obtained on 19.04.2004 vide consent order no. 10175 (valid upto 16.03.2007) CTO(R) on 14.03.2007 vide I.D. No. 20846
06.08.2008Confirm closure. Call on 03.09.2008
Unit has already submitted CTE. Hence, closure directions not issued.
Ask the unit to file Bank Guarantee of Rs. 1 Lakh under Air Act for not starting buffing activity.
Notice for closure issued.No reply received.
Confirm closure. Call on 03.09.2008
14(a) S. K. Steels B-58, Group
Pickling 30 tonnes / month (as per inspection report)
Submitted on 25.02.2008
CTE on 31.12.2007 vide I.D. No. 24612.
CTO applied on 16.3.2005 vide ID No. 13018.
Applied on 29.8.06 for renewal.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. Issue notice for closure to two new units found by SIT during their
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will submit
Call on 03.09.2008
inspection. 06.08.2008Call on 03.09.2008
the application for permission to CGWA. As soon as they get the permission, they will submit the same.
within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
the same.
14(b) R.K. Steel Ground Floor, B-58, Group
Re-rolling Applied for CTE on 09.07.2008 vide I.D. No. 26373.
CTO obtained on 26.06.2003 vide consent order no. 6079 (valid upto 13.08.2005)CTO(R) on 15.11.2006 vide consent order no.
06.08.2008Confirm closure. Call on 03.09.2008 for ATR.
Unit has already submitted CTE. Hence, closure directions not issued.CTO obtained on 26.06.2003 vide consent order no. 6079 (valid upto 13.08.2005
No action. NA Notice for closure issued on 20.06.2008.No reply received.
Confirm closure. Call on 03.09.2008 for ATR.
17624 (valid upto 13.08.2009)
)CTO(R) on 15.11.2006 vide consent order no. 17624 (valid upto 13.08.2009)Applied for CTE on 09.07.2008 vide I.D. No. 26373.
14(c) P.K. Steel 1st Floor, B-58, Group
Trading of S.S. Utensils
CTE on 09.07.2008 vide I.D. No. 26374 under Green category.
CTO(R) on 25.07.2007 vide I.D. No. 22803 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
No action. NA Notice for closure issued on 20.06.2008.Applied for CTE on 09.07.2008 vide I.D. No. 26374 under Green category.As per CMC (Green) decision dated 18.07.2008, CTE granted.
Shift to Green Committee.
15 Swaroop Industries
B-9, Group
Pickling of S.S.Sheets
BG of Rs. 50000 each under Air & Water Act only instead of Rs. 1 Lakh under each of the three acts.
CTE on 21.09.2007 vide I.D. No. 23597.
_
Applied on 04.02.2005 vide I.D. No. 2306.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008
Ask the unit to file full
Letter issued.Reply received on 02.09.2008. Unit has informed that as per hon'ble court that the unit first get consent for the last one
Refuse Consent to Establish. Call on 30.09.2008.
ref 30.09 Letter issued.Reply received on 02.07.2008Permission from CGWA not submitted. Unit has informed that they have filed an application to CGWA.Unit has submitted BG of Rs. 50000 under Air Act
Ask the unit to file full Bank Guarantee and confirm. Call on 03.09.2008
Bank Guarantee and confirm. Call on 03.09.2008
year so unit is not operated for the last one year. As unit is not doing any activity how he can submit the BG and requested to issue revocation letter and consent so they can start unit and full fill requirement i.e. BG.
& Water Act instead of Rs. One Lakh under Air Act, Water Act and HWM Rules asked vide letter dated 18.12.2007
16 A.V. Metal A-72/2 Re-rolling and pickling of SS sheets
8 MT/month Not sought CTE on 13.11.2007 vide ID No. 24193
_ _ 24.04.2008SIT to inspect & report by 28.05.2008. 29.05.2008Call on 03.07.2008 06.08.2008Based on SIT report, issue fresh notice for closure. Call on 03.09.2008
Notice for closure issued.No reply received.
Call on 30.09.2008
30.09
30.09 Unit has suubmitted a letter on 22.05.2008 & informed that they are facing critical problems and closed down its activity last one year. They have rectified all the deficiencies found during the inspection and requested to allow to operating its unit.SIT inspected the unit.SLP filed by DPCC dismissed by
Based on SIT report, issue fresh notice for closure. Call on 03.09.2008
Hon'ble SC.17 Ajit Nath
Alloys (P) Ltd.
C- 60/1 Manufacturing of SS utensils (including buffing)
250-300 Kg (as per inspection report)
BG of Rs. 50000 under
Air Act submitted.
CTE on 13.08.2007 vide I.D.No. 23112 under Orange category.CTE under Green category on 21.9.07
Not applicable
29.05.2008Call on 03.06.2008 06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift CTE under Green category issued and as per decision of CMC meeting dated 03.06.2008, decision of CMC was intimated to Legal Cell for filing the application to High Court.Application filed before Hon'ble HC
Shift to Green Committee.
18 Baba Steels A- 14 (Backside)
Pickling (unit found closed &locked from outside .Unit non operational)
Not Mentioned
BG not submitted.
CTE on 28.11.07 vide ID No. 24342
CTO refused on 18.08.2007 vide refusal no. 1659.
Applied for renewal on 18.08.2006 vide I.D. No. 3351.
29.05.2008Issue closure directions u/s 31(A) of the Air Act, 1981 and u/s 33(A) of the Water Act, 1974, as the unit has not submitted Bank Guarantee inspite of issuing SCN for the same. 06.08.2008Ask the unit to file an affidavit that it has actually closed down the unit. Call on 03.09.2008.
Letter issued.No reply received.
Refuse Consent to Establish. Seek compliance from discom agencies. Call on 30.10.2008
ref + com
30.10.2008
Closure direcitons issued.Replies received on 19.06.2008 & 30.06.2008BG not submitted. Unit has informed that they have stopped pickling activity and removed all the equipments related to pickling activity and requested to withdraw the notice.Unit has also informed on 30.06.2008 that they are not operating unit for the last 15
Ask the unit to file an affidavit that it has actually closed down the unit. Call on 03.09.2008.
months and requested to withdraw the notice.NDPL has informed that no industry exists at site.
19 Bhalla Hosiery Factory
B-40, Group
Re-rolling & Pickling
S.S Sheet (as per inspection report)
BG not submitted.
CTE on 18.09.2007 vide I.D. No. 23542.
CTO refused on 09.08.2007 vide refusal no. 1655. CTO on 21.08.2007 vide I.D. No. 23212.
_ 29.05.2008Issue notice for clousre based on SIT inspection. 06.08.2008SIT to inspect after 02 months. Call in CMC of WIA in October, 2008
Call on 07.10.2008 with SIT report.
SIT 7.1 As per approval on file, unit was directed to file BG of Rs. One Lakh each under three acts.Letter issued.Reply along with affidavit received on 16.07.2008 & stated that we are not enagaged in polluting activity and the same was verified by SIT, therefore, does not require to submit BG.
SIT to inspect after 02 months. Call in CMC of WIA in October, 2008
20 Gee Aar Industries
A-9/3 Mfg A cotton thread, Mercerizing, and Bleaching.
400-450 Kg (as per inspection report)
Not sought CTE on 28.12.200
7 vide I.D. No. 24606.
CTO refused on 30.11.2007
Refused on 30.11.2007
29.05.2008Reminder for compliance. 06.08.2008Issue reminder.Call on 03.09.2008
Reminder issued.No compliance report received.
Refuse Consent to Establish. Seek compliance from discom agencies. Call on 30.10.2008
ref + com
30.10.2008
Reminder issued.No compliance report received.
Issue reminder.Call on 03.09.2008
21 Hari Ram C-40/3 Pickling of SS Sheets
500-600 Kg / day (as per affidavit)
BG of Rs. 75000 under Air, Water
Acts & HWM Rules
CTE on 31.12.2007 vide I.D. No. 24620.
CTO refused on 09.12.2005.
Applied for renewal on 18.08.2006 vide I.D. No. 3367.
29.05.2008Ask the unit to file permission from Central Ground Water
Letter issued.Replies issued on 27.06.2008 & 29.07.2008
Last and final reminder for submission of CGWA clearance. Also ask the
4 MM 30.10.2008
Letter issued.Replies issued on 27.06.2008 & 29.07.2008.No permission from CGWA submitted.
Call on 03.09.2008
Authority for ground water drawl. 06.08.2008Call on 03.09.2008
.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be submitted.
unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be submitted.
22 Hariom Industries
C- 60/3 Manufacturing of SS utensils (involving buffing)
200 Pcs per day as per affidavit
BG submitted.
CTE on 20.9.2007 vide ID No. 23580
Only CTE applied
Not applicable
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl.
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted.
Last and final reminder for submission of CGWA clearance. Call on 30.10.2008.
3 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have approched to
Call on 03.09.2008
06.08.2008Call on 03.09.2008
Unit has informed that they have approched to CGWA. As soon as they get the permission, they will subit the same.Noise moniotirng report of D.G. Set submitted.
CGWA. As soon as they get the permission, they will subit the same.Noise moniotirng report of D.G. Set submitted.
23 Parasmani Steel Job Works
B-33/3, Group
Re-rolling & Pickling
1 tonne/day (as per inspection report)
BG not submitted.
CTE on 11.09.2007 vide I.D. No. 23462.
29.05.2008Issue notice for clsoure. 06.08.2008Issue final reminder for filling Bank Guarantee by 03.09.2008, failing which closure order will be issued.
Final reminder issued.Reply received on 02.09.2008. Unit has informed that unit is not operational because of bad work scenario in the market of S.S. Re-rolling(no work at present in the market) so they are not in position to submit the BG and requested to give at
Last and final reminder for submission of Bank Guarantee. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-
6 MM 30.10.2008
Notice for closure issued.Reply received. Unit has requested to allow more time to submit BG.
Issue final reminder for filling Bank Guarantee by 03.09.2008, failing which closure order will be issued.
least 3 months time to submit the BG.
2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
24 Shakti Industries
C-9/4 Re-Rolling and Pickling of SS Sheets.
300 Kg (as per inspection report)
BG of Rs. 50000
submitted.
CTE on 14.12.07
CTO valid up to 01.8.05.Applied for CTO(R) on 08.10.2007 vide I.D. No. 23808.
_ 29.05.2008Issue notice for clsoure. 06.08.2008Issue final notice for Bank Guarantee of Rs. 50,000 under Air Act to be filed by 03.09.2008, failing which closure order will be confirmed.
Final notice issued.Reply received on 02.09.2008BG submitted on 02.09.2008.
Call on 30.10.2008
30.09
30.09 Notice for closure issued.Reply received on 07.07.2008. Unit has informed that there is no hazardous waste generation as the activity of the unit is cold re-rolling of S.S.Sheet (dry unit). Unit has also informed that unit is closed since 1st November, 2007.Unit has also informed that to allow the time upto 31.12.2008 to submit BG as unit is not operating since 1st November, 2007.
Issue final notice for Bank Guarantee of Rs. 50,000 under Air Act to be filed by 03.09.2008, failing which closure order will be confirmed.
25 Vishal C-55/1 Re-Rolling 2.5 Tonnes BG of Rs. 1.5 CTE on CTO Letter Last and 4 MM 30.10.200 Letter issued. Call on 03.09.2008
Industries & Pickling of S.S.Sheets
per month
Lakhs submitted.
10.09.2007 vide I.D. No. 23442.
refused on 20.07.2007 vide I.D. No. 22638.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
issued.Reply submitted on 04.08.2008.Permission from CGWA not submitted.Unit has informed that they have submitted an application for permission to CGWA (copy enclosed).
final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
8 Reply submitted on 04.08.2008.Permission from CGWA not submitted.Unit has informed that they have submitted an application for permission to CGWA (copy enclosed).
26 Goyal Enterprises
B-7, Group
Pickling & Re- Rolling of SS sheet
1 tonne (as per inspection report)
BG of Rs. Three Lakh submitted on 24.10.2007.
CTO(R) obtained. Valid upto
CTO(R) obtained. Valid upto
Authorization issued.
29.05.2008Ask the unit to file
Authorization already issued. Hence, no
Ask the unit to confirm through an affidavit that
2 MM 30.10.2008
Letter issued.Reply received on 25.06.2008Permission
Authorization under HWM Rules granted.
11.08.2008.
11.08.2008.
permission from Central Ground Water Authority for ground water drawl. 06.08.2008Authorization under HWM Rules granted.
authorization issued.
it is discharging its effluents whose pH is within the norms and also to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
from CGWA submitted.
27(a) Hari Ram Babu Lal
B-63 Pickling , Annealing & Re- Rolling of SS sheet
20 tonnes (as per inspection report)
BG of Rupees Two Lakh submitted on 29.10.2007
CTE on 14.03.2008 vide I.D. No. 25202
CTO(R) obtained. Valid upto 01.08.2008. CTO on 04.10.2006 vide I.D. No. 19489.
Applied on 04.10.2006 vide I.D. No. 3759
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. Issue notice for closure to two new units
SIT report to be discussed.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging
4 MM 30.10.2008
Letter issued.Reply received on 29.07.2008.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the
SIT to inspect and report. Call on 03.09.2008
found by SIT for not applying for Consent to Establish. 06.08.2008SIT to inspect and report. Call on 03.09.2008
its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
permission will come the same will be submitted.
27(b) Ashish Industries
B-63, Ground Floor
R-rolling of S.S. Sheets
CTE on 07.07.2008 vide I.D. No. 26320.
06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008 with SIT report.
SIT 30.09 Notice for closure issued.Reply received. Unit has informed that they have obtained valid consent and also applied for CTE on 07.07.2008 vide I.D. No. 26320.
SIT to inspect and report. Call on 03.09.2008
27(c) Saurabh Industries
B-63, Ground Floor
Re-rolling of S.S. Sheets
CTE on 07.07.2008 vide I.D. No.
06.08.2008SIT to inspect and report.
SIT report to be discussed.
Call on 30.09.2008 with SIT report.
SIT 30.09 Notice for closure issued.Reply received. Unit has
SIT to inspect and report. Call on 03.09.2008
26321. Call on 03.09.2008
informed that they have obtained valid consent and also applied for CTE on 07.07.2008 vide I.D. No. 26321.
28 S.K. Enterprises
A-126/1 Pickling, Annealing & Re- Rolling of SS sheet
2.5 tonnes (as per inspection report)
BG submitted on 08.10.2007
Not applied/obtained
CTO ( Renewal) obtained. Valid upto 26.7.2008.
Applied for renewal of authorization on 03.08.2006 vide I.D. No. 3110.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Replies issued on 27.06.2008 & 29.07.2008.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be submitted.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to
4 MM 30.10.2008
Letter issued.Replies issued on 27.06.2008 & 29.07.2008.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be submitted.
Call on 03.09.2008
closure of present activity. Call on 30.10.2008.
29 Parkash Re-Rolling Works
A-131, Group
Re-rolling and pickling of SS sheets
2.5 tonnes (as per inspection report)
BG of Rs. 3 Lakhs submitted.
CTE on 26.05.2008 vide I.D. No. 25838.
CTO refused on 18.08.2007 vide refusal no. 1661..
Applied for authorization on 25.06.2008 vide I.D No. 4606.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008SIT to inspect and report. Call on 03.09.2008
Letter issued.Replies received on 27.06.2008 & 18.08.2008.No permission from CGWA submitted. Unit has requested to allow 30 to 45 days time to file the permission from CGWA.Unit has submitted a letter on 18.08.2008 & informed that they have shut down the industrial activity of pickling for some time (temporarily) due to non availability
Call on 30.09.2008 with SIT report.
SIT 30.09 Letter issued.Reply issued on 27.06.2008.No permission from CGWA submitted. Unit has requested to allow 30 to 45 days time to file the permission from CGWA.
SIT to inspect and report. Call on 03.09.2008
of raw material for pickling. At present, He has engaged in the actiivty of cold re-rolling.SIT report to be discussed.
30 Prem Dyeing
A- 13 Dyeing (Premises found closed, unit not operating)
Not Mentioned
unit closed Not applied/obtained
CTO(R) on 09.04.2007 vide I.D. No. 21011.
29.05.2008Reminder for compliance. 06.08.2008Issue reminder for compliance report. Call on 03.09.2008
Reminder issued .No compliance report received.
Reminder for compliance. Call on 30.10.2008
com 30.1 Reminder issued .No compliance report received.
Issue reminder for compliance report. Call on 03.09.2008
31 (a) Bhagwati Steels
B-28/4 Pickling, Annealing & Re-Rolling of SS sheet
500 Kg/day (as per inspection report)
Revalidated BG of Rs. Three Lakh submitted on 19.03.2007
Applied for CTE on 20.03.2008 vide I.D. No. 25278.
CTO on 25.07.2005.
Renewal of authorization on 12.07.2006 vide I.D. No. 2758.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. Issue notice for closure to new unit found by SIT for not applying for Consent to Establish. 06.08.2008SIT to inspect
SIT report to be discussed.
Forfeit Bank Guarantee under all the three Acts and inform the unit accordingly. Call on 30.09.2008 for ATR.
Z 30.09.2008
Letter issued.Reply received on 03.07.2008.Permission from CGWA submitted.
SIT to inspect and report. Call on 03.09.2008
and report. Call on 03.09.2008
31 (b) Anil HandaRaj Industries
B-28/4, 1st Floor
Mfg. of S.S. Utensils
CTE on 07.07.2008 vide I.D. No. 26333 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Reply received on 08.07.2008. Unit has informed that the unit name is M/s Raj Industries in lieu of Anil Hand and they have applied for CTE on 07.07.2008 vide I.D. No. 26333.As per CMC (Green) decision dated 18.07.2008, SIT to Iinspect and report.
Shift to Green Committee.
32 Ganpati Rolling Mill
A-98/6 Pickling & Re- Rolling of SS sheet
2-3 tonne (as per inspection report)
Revalidated BG of Rs. Three Lakh submitted on 29.10.2007
CTE on 11.03.2008 vide I.D. No. 25151.
CTO(R) on 16.05.2007 vide I.D. No. 21335
Applied for renewal of authorization on 18.08.2006 vide I.D No. 3353
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008 with SIT report.
SIT 30.09 Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will submit the same.
SIT to inspect and report. Call on 03.09.2008
33(a) Kusum Steel Co.
C-57 Re-rolling & Pickling
4-5 tonne (as per inspection)
BG of Rs. Three Lakh submitted on 23.08.2007
CTE on 11.04.2008 vide I.D. No. 25487.
CTO on 11.01.2005 vide I.D. No. 12421.
Applied for renewal of authorization on 11.01.2005 vide I.D. No. 2265.
29.05.2008Bank Guarantee forfeited,
Letter issued.No reply received.SIT report to be
Ask the unit to correct the deficiencies noted by SIT through an affidavit and
Z MM 30.10.2008
Bank Guarantee forfeited under each of the three Acts. Unit has submitted its
Decision of forfeiture of Bank Guarantees will not be revoked. SIT to inspect and report. Call on 03.09.2008.
under all the three acts, on account of SIT inspection.Issue notice for cloure to new unit for not applying for Consent to Establish 06.08.2008Decision of forfeiture of Bank Guarantees will not be revoked. SIT to inspect and report. Call on 03.09.2008.
discussed. to submit Bank Guarantee of Rs. 01 Lakh under Water Act valid upto 06.02.2010. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and also to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
replies along with photographs on 03.06.2008 & 06.06.2008 & informed that they have rectified all the deficiencies and requested to send SIT for reinspection.
33(b) Shyam Steel
C-57, 1st Floor
Circle cutting
06.08.2008Notice be pasted on the premises. Call on 03.09.2008
Notice pasted.No reply received.
Call on 30.09.2008
30.09
30.09 Notice for closure issued on 20.06.2008.Notice for closure returned back undelievered.
Notice be pasted on the premises. Call on 03.09.2008
34 Metal Fabricators
A-85/3 Pickling, Annealing & Re- Rolling of SS sheet
30 tonnes / month (as per inspection report)
Revalidated BG submitted on 29.10.2007
Applied for CTE on 20.03.2008 vide I.D. No. 25279.
CTO on 24.01.2005 vide I.D. No. 12494
Applied on 20.09.2006 vide I.D. No. 3637
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have approched to CGWA. As soon as they get the permission, they will subit the same.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have approched to CGWA. As soon as they get the permission, they will subit the same.
Call on 03.09.2008
present activity. Call on 30.10.2008.
35 Mitul Industries
A-124 Pickling, Annealing & Re-Rolling of SS sheet
1.5 tonnes (as per affidavit)
Extension letter for BG submitted on 01.10.2007.BG revalidated up to 06.02.2010.
CTE granted vide CMC decision dated 24.04.2008
CTO(R) on 01.08.2005 vide I.D. No. 15868.
Applied for renewal of authorization on 09.12.2006 vide I.D. No. 3248.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Reply received on 27.06.2008Permission from CGWA not submitted. Unit has informed that they have applied to CGWA, as soon as they get the permission, the same will be submitted to DPCC.Undit has submitted a letter on 01.09.2008 and informed that they are operating ETP on regular basis and discharging the effuent wel within limit of pH
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on
4 MM 30.10.2008
Letter issued.Reply received on 27.06.2008Permission from CGWA not submitted. Unit has informed that they have applied to CGWA, as soon as they get the permission, the same will be submitted to DPCC.
Call on 03.09.2008
7. 30.10.2008.36 Pooja
Rolling Mills
A-90/1, Group
Pickling & Re- Rolling of SS sheet
1-1.25 tonne (as per inspection report)
Revalided BG of Rs. Three Lakh submitted on 29.10.2007
Applied for CTE on 18.03.2008 vide I.D. No. 25220.
CTO(R) on 30.01.2006 vide I.D. No. 17616.
Applied for renewal of authorization on 01.08.2006 vide I.D. No. 3030.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008SIT to inspect and report. Call on 03.09.2008
Unit has submitted a letter along with affidavit on 12.08.2008 and informed that they have stopped pickling & reorlling activity and ther is no such type of unit. I were on rent so I had handed over the premise to the landlord. Unit has again submitted a letter on 29.08.2008 and informed that they have stopped pickling activity and started other activity for S.S. Circle cutting which is totally dry unit.
Call on 30.09.2008 with SIT report.
SIT 30.09 Letter issued.Reply received on 23.06.2008Permission from CGWA submitted.
SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
37 Rahul Udyog
A- 96 / 1A Annealing, Re-Rolling & Pickling of S.S.Sheets
2-2.5 tonnes (as per inspection report)
BG of Rs. Three Lakh submitted on 15.10.2007.
CTE on 01.01.2008 vide I.D. No. 24632.
CTO applied on 29.3.2005 vide ID No. 13253
Applied on 28.03.2005 vide I.D. No. 2367.
29.05.2008Ask the unit to file adequacy report and permission from Central Ground Water Authority for ground water drawl. 06.08.2008Forfeit Bank Guarantees under three Acts/Rules submitted by the unit. Call on 03.09.2008
Bank Guarantee forfeited.
Ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and also to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
2 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have approched to CGWA. As soon as they get the permission, they will subit the same.
Forfeit Bank Guarantees under three Acts/Rules submitted by the unit. Call on 03.09.2008
38 Raj Overseas
C- 60/1 Annealing , re-rolling and pickling of SS sheets and manufacturin
3 tonnes/day (as per affidavit)
BG of Rs. Three Lakh submitted on 31.12.2007.
CTE granted vide CMC decision dated
CTO on 01.06.2007.
Applied on 01.06.2007
29.05.2008Ask the unit to file permission from Central
SIT report to be discussed.
Forfeit Bank Guarantee under all the three Acts and inform the unit
Z 30.10.2008
Letter issued.Reply submitted on 04.08.2008.Permission from CGWA
SIT to inspect and report. Call on 03.09.2008
g of utensils ( including buffing)
24.04.2008
Ground Water Authority for ground water drawl. 06.08.2008SIT to inspect and report. Call on 03.09.2008
accordingly. Call on 30.10.2008 for ATR.
not submitted.Unit has informed that they have submitted an application for permission to CGWA (copy enclosed).
39 Satish Kumar
B-70/2 Annealing of SS sheet
150 tonnes / month (as per raw material list) 60 sqm(plot area)
Revalidated BG of Rs. 50,000 submitted.BG of Rs. 50000 under Air Act submitted on 22.05.2008.
CTE on 25.04.2008 vide I.D. No. 25583
CTO on 31.01.2006 vide I.D. No. 17629.
Not applicable
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008 with SIT report.
SIT 30.09 Letter issued.Reply received on 27.06.2008Permission from CGWA not submitted. Unit has informed that the activity of the unit is annealing which is dry activity so does not require to take permisson from CGWA.
SIT to inspect and report. Call on 03.09.2008
40 Shriram Rolling Mill
A-93/14 Pickling & Re- Rolling of SS sheet
2-3 tonne (as per inspection report)
Revalidated BG of Rs. Three Lakh submitted on 29.10.2007
Applied for CTE on 25.03.2008 vide I.D. No. 25299.
CTO on 01.06.2006 vide I.D. No. 18355
Applied on 01.06.2007 vide I.D. No. 2655.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will submit the same.
Call on 03.09.2008
As soon as they get the permission, they will submit the same.
of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
41(a) Vinayak Industires
C-36/1 Re- Rolling & Pickling of SS sheet
375 - 500 kg/day
BG of Rs. Three Lakh subitted 29.10.2007.
CTE on 18.03.2008 vide I.D. No. 25226
CTO applied on 02.8.02 and 25.6.04CTO valid up to 24.6.07.CTO(R) on 11.06.2007 vide I.D. No. 21775.
Applied on 23.12.2003 & 25.04.2005 vide I.D. No. 192 & 2387 respectively.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. Issue notice for closure to two new units found by SIT for not applying for Consent to Establish. 06.08.2008Call on 03.09.2008
Letter issued.Reply on 29.07.2008.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before
4 MM 30.10.2008
Letter issued.Reply on 29.07.2008.No permission from CGWA submitted. Unit has informed that they have applied for permission to CGWA. As and when the permission will come the same will be submitted.
Call on 03.09.2008
submitted. 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
41(b) Jaina Steel C-36/1, Basement
Mfg. of S.S. Utnsils without buffing
06.08.2008Notice to be pasted on the premises. Call on 03.09.2008
Notice for closure issued on 20.06.2008.Notice for closure returned back undelievered.Notice pasted.M/s Vinayak Inds has submitted a letter on 01.09.2008 and informed that M/s Jain Steels has left the premises and there
Ask the unit to submit Bank Guarantee of Rs. 1 Lakh under Air Act, 1981 valid upto 06.02.2010 for not to start buffing activity. Call on 30.09.2008
MM 30.09.2008
Notice for closure issued on 20.06.2008.Notice for closure returned back undelievered.
Notice to be pasted on the premises. Call on 03.09.2008
is no such unit exists and also informed that they have rented this premise to new tenant who will apply CTE in day or two in DPCC.
41(c) Auto Plast C-36/1, Ground Floor
CTO obtained on 27.10.2007(valid upto 07.10.2007)
06.08.2008Notice to be pasted on the premises. Call on 03.09.2008
Notice for closure issued on 20.06.2008.Notice for closure returned back undelievered.Notice pasted.M/s Auto Plast has submitted a letter on 01.09.2008 and informed that M/s Auto Plast has left the premises and there is no such unit exists and also informed that they have rented this
Call on 30.09.2008 for new tenants.
Z 30.09 Notice for closure issued on 20.06.2008.Notice for closure returned back undelievered.
Notice to be pasted on the premises. Call on 03.09.2008
premise to new tenant who will apply CTE in day or two in DPCC.
42 (a) Rajkumar Hosiery
A-128, Group
Dyeing , Bleaching and processing of hosiery clothes
300 Kg (as per inspection report)
BG not submitted.
CTE on 13.08.2008 vide ID No. 26951 under Green category for the activity of cutting of hosiery, farbic / cloth.
CTO applied on 26.7.02CTO renewal applied on 30.9.05
Applied for renewal on 02.8.06 vide Id No.3077
28.08.2008The unit moved the Delhi High Court on 27.08.2008 and the Hon’ble High Court directed that the electricity and water connection is to be restored immediately as it stood already disconnected on 24.08.2008. His application for Consent to Establish under Green category may be disposed off by CMC(Green). W.r.t. the other units located in the same premises namely (i) M/s Somdutt, the unit has already
Court order and fact sheet are yet to be received. Hence, letter for revocation not issued and CTE application to be considered by CMC(Green) Committee. .
Call on 30.09.2008
30.09
30.09 Findings of SIT inspection to be discussed
Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.SIT found four other units, details of which are as follows:-(i) J.P. Steel engaged in S.S. Sheet pressing job.(ii) Somdutt engaged in lathe machine works.(iii) Suresh Kumar engaged in plastic footwear.(iv) Sushil Kumar Goel engaged in circle cutting.Issue notice for closure to all the four units for not applying for for Consent to Establish.
applied under the Green category and the same may be disposed off in the CMC (Green) meeting (ii) M/s Suresh Kumar located at ground floor has already applied for CTE under Orange category, the same may be taken up in next CMC(Orange) of WIA on 03.09.2008 (iii) M/s Sushil Goel has applied under the Green category and his application may be considered by the CMC(Green). (iv) M/s A.K. Metal has not applied for Consent to Establish, he may be asked by way of notice to apply for Consent to Establish. (v)
M/s J.P. Steel, the unit has already applied for Consent to Establish under Green category and the same may be disposed off in the CMC(Green) meeting.
42 (b) J.P. Steel A-128, Group
CTE under Green category on 14.08.2008 vide I.D. No 26971
Notice for closure issued.Applied for CTE under Green category on 14.08.2008 vide I.D. No 26971. The same was to be considered by CMC(Green) Committee.
Remove from this list as the activity falls under Green category.
shift
42 (c) Somdutt A-128, Group
CTE under Green category on 14.08.2008 vide I.D. No 26973
Notice for closure issued.Applied for CTE under Green category on 14.08.2008 vide I.D. No 26973. The same
Remove from this list as the activity falls under Green category.
shift
was to be considered by CMC(Green) Committee.
42 (d) Suresh Kumar
A-128, Group
CTE on 14.08.2008 vide I.D. No 26969.
Notice for closure issued.Applied for CTE on 14.08.2008 vide I.D. No 26969
Call on 30.09.2008
30.09
30.09
42 (e) Sushil Kumar Goel
A-128, Group
CTE under Green category on 14.08.2008 vide I.D. No 26972.
Notice for closure issued.Applied for CTE under Green category on 14.08.2008 vide I.D. No 26972. The same was to be considered by CMC(Green) Committee.
Remove from this list as the activity falls under Green category.
shift
43 Sh. Gaurav(Proprietor of pickling unit )
C-55/1 (back side portion )
Pickling of S.S.Sheets
Not Mentioned
BG of Rs. 3 Lakhs submitted.
CTE on 21.05.2008 vide I.D.No. 25789.
CTO applied.
Not applied. 29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl.
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission
Call on 03.09.2008
06.08.2008Call on 03.09.2008
Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will submit the same.
it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
to CGWA. As soon as they get the permission, they will subit the same.
44 A.N. Steel Industries
A-95 Re-Rolling of S.S.Sheets(Pickling stopped)
15 tonnes / month (as per inspection report)
Not sought
Not applied/obtained
Refused on 31.07.2006
29.05.2008Reminder for compliance. 06.08.2008Issue reminder for compliance report. Call on 03.09.2008
Reminder for compliance issued.No reply received.
Reminder for compliance. Call on 30.10.2008
com 30.1 Reminder for compliance issued.No reply received.
Issue reminder for compliance report. Call on 03.09.2008
45(a) Abhinandan Steel
A-124, II & III Floor,
Manufacturing of steel utensils
200-300 kg/day (as per
Not applied/obtained
CTO revoked on
Not applicable
29.05.2008
Letter for disconnection of
Seek compliance. Call on
com 30.1 Since unit is closed, issue letter for disconnection of
(involving buffing)
inspection report)
09.08.2007 vide revocation no. 1651.
Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
power / water supply & disconnection of MCD licence issued.
30.10.2008 power/water supply & cancellation of MCD licence to the unit.File be closed.
45(b) Adhinath Works
A-124, 2nd & 3rd Floor
Bank Guarantee of Rs 01 Lakh under Air Act submitted
CTE on 26.11.2007 vide I.D. No 24319.
06.08.2008Ask the unit to file Consent to Establish application.Call on 03.09.2008
Letter issued.Applied for CTE on 26.11.2007 vide I.D. No 24319.Repy received on 02.09.2008. Unit has informed that they have applied for CTE for mfg. of utensils and requested to withdraw the notice
Call on 30.09.2008
30.09
30.09 Letter issued.Reply received on 01.07.2008Permssion from CGWA not submitted. Unit has informed that they do not have any bore well connection and requested to withdraw the notice.
Ask the unit to file Consent to Establish application.Call on 03.09.2008
and issue the consent.
46 Jain Udyog B-41, Group
Re-rolling & Pickling
Not Mentioned
Not sought CTE refused on 29.11.07
CTE refused on 29.11.07
Not applied. 29.05.2008No pickling observed. Call on 03.07.2008 for final decision. 06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Ask the unit to submit an affidavit for removal of dismantled equipment & machinery. Call on 30.09.2008
MM 30.09.2008
Unit has submitted a letter on 03.06.2008 & informed that they have closed down the pickling activity and rquested to treat old consent application or any other such doucments as null and void.A complaint received from Samajwati Andoolan Suraksha against the unit (listed at Sl. No 17 out of 26 cases).
SIT to inspect and report. Call on 03.09.2008
47 Laxmi Chand Hosiery Factory
A-97/ 2 Buffing on S.S.Utensils(knitting of socks is also being carried out)
_ BG of Rs. 50000 under Air Act.
CTE on 28.05.2008 vide I.D. No. 25870
CTO on 25.07.2007 vide I.D. No. 22799 under Green Category.
_ 29.05.2008BG and CTE submitted. Call on 03.07.2008 for final decision. 06.08.2008Ask the unit to file permission from CGWA for ground water drawl.
Letter issued.Unit has submitted a letter on 27.08.2008 & informed that they have applied for ground water drawl to CGWA.Unit has approched to Finance Commissio
Call on 30.09.2008 with all the facts.
Z 30.09 Letter issued. Reply received on 28.05.2008.Bank Guarantee submitted on 27.05.2008.Applied for CTE on 28.05.2008 vide I.D. No. 25870
Ask the unit to file permission from CGWA for ground water drawl.
ner and stay was granted.Next DOH is 05.09.2008.
48(a) Laxmi Rolling Mills
A-90/3, Group
Pickling & Re- Rolling of SS sheet
2-3 tonne (as per inspection report)
Revalided BG submitted on 29.10.2007
CTE on 18.03.2008 vide I.D. No. 25233
CTO on 12.03.2003 vide I.D. No. 7956. Unit depsited the fee for further three years on 17.08.2006 as sought by DPCC.
Applied for renewal of authorization on 07.08.2006 vide I.D. No. 3179.
29.05.2008unit found closed. Issue notice for closure to new two units for not applying for Consent to Establish. 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.SIT to inspect new unit namely M/s Laxmi Rolling Industries.
CMC on 28.8.08 has decided to get the unit inspected by the SIT.
Call on 30.09.2008 with SIT report.
SIT 30.09 Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.SIT to inspect new unit namely M/s Laxmi Rolling Industries.
48(b) Chawla Polymer
A-90, Group Ground Foor
Mfg. of safety boot
CTE on 11.03.2008 vide I.D. No. 25150.
06.08.2008Call on 03.09.2008
Notice for closure issued.Applied for CTE on 11.03.2008 vide I.D. No. 25150.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Applied for CTE on 11.03.2008 vide I.D. No. 25150.
Call on 03.09.2008
48(c) Acme Safety
A-90, Group, 1st & 2nd Foor
Mfg. of safety belt, torch, jacket
06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Issue Consent to Esstablish.
CTE Notice for closure issued.Notice returned back undelievered.
SIT to inspect and report. Call on 03.09.2008
49 Mittal Dyeing and Processing Mills
A-94/1 Dyeing , Bleaching and processing of hosiery clothes
1000 Kg (as per inspection report)
BG not submitted
CTE on 26.03.2008 vide I.D. No. 25319 under Green Category
CTO valid up to 28.11.2003CTO(R) applied on 22.3.2005
Applied for renewal on 01.08.2006 vide I.D. No. 3027.
29.05.2008SIT to inspect & report. Call on 03.7.08 06.08.2008Final reminder for submission of Bank Guarantee, failing which unit will be closed down. Call on 03.09.2008.
Reminder issued.Unit has submitted a letter on 28.08.2008 and informed that they have closed the polluting activity. At present, he is engaged in green activity for which he has applied for CTE and requested to grant CTE.
Refuse consent under Orange category. Transfer to Green Committee.
shift SIT report to be discussed.
Final reminder for submission of Bank Guarantee, failing which unit will be closed down. Call on 03.09.2008.
50 Rafiq Electroplating
C- 59/2 Unit shifted.(Premises found vacant.)
Not Mentioned
Not sought Not applied/obtained
CTO refused on 07.08.2007 vide refusal no. 1643.
Refused on 07.08.2007.
29.05.2008Reminder for compliance. 06.08.2008Issue reminder for compliance report. Call on 03.09.2008
Reminder issued.No compliance report received.
Seek compliance. Call on 30.09.2008
com 30.09 Reminder issued.No compliance report received.
Issue reminder for compliance report. Call on 03.09.2008
51 Sh. Paras and Sh. Mohd. Latif & (M/s Krishna Metal
A-40 Steel Rolling Annealing Re -Rolling & Pickling
10-15 Kg/month (as per inspection report)
BG of Rs. 3 Lakhs submitted on 06.08.2008
Applied for CTE on 24.03.2008 vide I.D. No.
CTO obained. Expired on 02.12.2007.
Applied for renewal of authorization on 18.08.2006 vide I.D. No. 3355.
29.05.2008Ask the unit to file permission
Letter issued.Replies received on 30.06.2008
Last and final reminder for submission of CGWA clearance.
4 MM 30.10.2008
Letter issued.Replies received on 30.06.2008, 01.07.2008 & 06.08.2008
Call on 03.09.2008
Industries) 25290. CTO(R) on 04.04.2008 vide I.D. No. 25417.
from Central Ground Water Authority for ground water drawl, affidavit for correction of deficiencies observed by SIT and to submit Bank Guarantee for Rs. 1 lakh each under Water Act, Air Act and HWM Rules. 06.08.2008Call on 03.09.2008
, 01.07.2008 & 06.08.2008Permission from CGWA not submitted. Unit has informed that they have applied to CGWA for permission (copy enclosed).Affidavit submitted.BG submitted on 06.08.2008.
Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
Permission from CGWA not submitted. Unit has informed that they have applied to CGWA for permission (copy enclosed).Affidavit submitted.BG submitted on 06.08.2008.
52 Shiv Industires
B-7 (Back side), Group
Re-Rolling & Pickling of S.S.Sheets (Presently unit is not in operation)
1 tonne (as per affidavit)
Not Sought Not applied/obtained
CTO was valid up to 06.6.07.CTO(R) on 11.07.2007 vide I.D. No.
Applied for renewal of authorization on 09.08.2006 vide I.D. No. 3245.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water
Final reminder issued.BG not submitted.Permission from CGWA not
Last and final reminder for submission of CGWA clearance and Bank Guarantee. Also ask the
7 MM 30.09.2008
Letter issued.Reply received on 27.06.2008Permission from CGWA not submitted. Unit has informed that they have
No reduction in Bank Guarantee amount. Final reminder for Bank Guarantee & permission from CGWA, failing which unit be closed down.
22316. drawl, affidavit for correction of deficiencies observed by SIT and to submit Bank Guarantee for Rs. 1 lakh each under Water Act, Air Act and HWM Rules. 06.08.2008No reduction in Bank Guarantee amount. Final reminder for Bank Guarantee & permission from CGWA, failing which unit be closed down.
submitted.Reply received on 28.08.2008. Unit has informed that it is very small and production capacity of the unit is 500 Kg/day which was also verified by the Inspecting Officer and requested to grant two months time for submision of BG and also infomed that he has rectified all the deficiencies directed by the Inspecting officer.
unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
approached to concerned to file permission.Affidavit submitted.BG not submitted. Unit has requested to reduce the amount of BG as the production capacity was very small i.e. 500 Kg/day which was also verified by the Inspecting Officer during the inspection.
53 Shree Krishna Enterprises
Shed no. 75 (DSIDC Sheds)
Rolling. Pickling proposed.
15-20 tonnes / month (as per affidavit)
BG of Rs. 75000 each under Air, Water Acts & HWM Rules
CTE on 28.05.2008 vide I.D. No. 25859
Refused on 09.08.2007 vide refusal no. 1659.
Refused on 09.08.2007.
29.05.2008Ask the unit to file permission from Central Ground Water Authority for
Letter issued.Unit has submitted a letter on 18.08.2008 & informed
Last and final reminder for submission of CGWA clearance. Also ask the unit to
4 MM 30.10.2008
Letter issued.Reply issued on 27.06.2008.No permission from CGWA submitted. Unit has requested to
Call on 03.09.2008
ground water drawl. 06.08.2008Call on 03.09.2008
that they have shut down the industrial activity of pickling since past three months and at present he is engaged only in the activity of cold re-rolling.No permission from CGWA submitted. Unit has submitted a letter on 18.08.2008 & informed that they have applied to CGWA for permission for ground water drawl.
confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.09.2008.
allow 30 to 45 days time to file the permission from CGWA.
54 Vardhman Impex
A-38 Re-rolling and pickling of SS sheets
3 tonnes (as per inspection report)
BG not submitted.
CTE on 18.03.2008 vide I.D. No. 25217.CTE on 21.05.2008 vide I.D.No. 25791 (M/s
CTO refused on 18.08.2007 vide refusal no. 1660.
_ 29.05.2008Call on 03.7.2008 for final decision. 06.08.2008No reduction in Bank Guarantee amount. Final
Letter issued. Reply received on 22.05.2008 & 01.09.2008.BG not submitted.
Last and final reminder for submission of Bank Guarantee. Also ask the unit to confirm through an affidavit that
Z SIT + MM
30.10.2008
Letter issued. Reply received on 22.05.2008.BG not submitted. Unit has stated its reply that they have stopped the pickling activity and
No reduction in Bank Guarantee amount. Final reminder for Bank Guarantee , failing which unit will be closed down.
Saurabh Steel Udyog).
reminder for Bank Guarantee , failing which unit will be closed down.
SIT to inspect both units and report. Call on 03.09.2008
M/s Saurabh Steel Udyog : Unit has submitted a letter on 21.05.2008 & informed that there is no unit in the name of M/s Rakesh Kumar at the said premises.Unit has again submitted a letter on 28.05.2008 & informed that they have placed order for canopy. As soon as canopy install, they will submit the noise monitoring report.Applied for CTE on 21.05.2008 vide I.D.No. 25791.
it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Also SIT to inspection and reprot. Call on 30.09.2008.
informed to DPCC vide letter dated 23.08.2007 and the same was observed during the inspection on 24.04.2008 and they have applied for consent for the activity of cold re-rolling and requested to waive off the order of submission of BG and withdraw the notice.M/s Saurabh Steel Udyog : Unit has submitted a letter on 21.05.2008 & informed that there is no unit in the name of M/s Rakesh Kumar at the said premises.Unit has again submitted a letter on 28.05.2008 & informed that they have placed order for canopy. As soon as canopy install, they will submit the noise monitoring report.
SIT to inspect both units and report. Call on 03.09.2008
M/s Rakesh Kumar : Unit has neither applied for CTE and nor submitted any reply.Letter issued.BG not submitted.SIT report to be discussed.
Applied for CTE on 21.05.2008 vide I.D.No. 25791.M/s Rakesh Kumar : Unit has neither applied for CTE and nor submitted any reply.
55(a) Vardhman Metal
B-50, Group
Pickling 4 T/day as per adequacy report
Not Sought CTE on 28.02.2008 vide I.D. No. 25059.
CTO on 21.07.2004 vide I.D. No. 11088.
Applied on 29.08.2007 vide I.D. No. 3426.
29.05.2008Unit found closed. Call on 03.07.2008.Issue notice for closure to Ramanand Gupta & Swagat Steel for not applying for Consent to Establish . 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
Decision to disconnect electricity/water supply to be reveiwed.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an
4 MM 30.10.2008
Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
55(b) Swagat Steel
Ground Floor, B-50, Group
Annealing CTE on 01.07.2008 vide I.D. No. 26235
06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Applied for CTE on 01.07.2008 vide I.D. No. 26235.
SIT to inspect and report. Call on 03.09.2008
55(c) Ramanand Gupta
B-50, Group, 2nd Floor
Acid Battery Recyling
CTE on 03.06.2008 vide I.D. No. 25960.
06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Applied for CTE on 03.06.2008 vide I.D. No. 25960.
SIT to inspect and report. Call on 03.09.2008
56 Vijay Industries
B-71 Annealing & Pickling
_ BG of Rs. 3 Lakhs submitted.
CTE on 15.04.2008 vide I.D. No. 25519
CTO applied on 02.5.2005.
Applied on 27.4.05 vide ID No. 2390
29.05.2008Ask the unit to file permission from Central Ground Water Authority for ground water drawl. 06.08.2008Call on 03.09.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan
4 MM 30.10.2008
Letter issued.Reply received on 30.06.2008Permission from CGWA not submitted. Unit has informed that they have filed the application for permission to CGWA. As soon as they get the permission, they will submit the same.
Call on 03.09.2008
to CGWA. As soon as they get the permission, they will submit the same.
for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
57 W.C. Steel B-70/2 Pickling of SS sheet
1.5 Tonnes per ady as per List of raw materials
Not Sought Not applied/obtained
CTO refused on 19.09.2007
Refused on 19.09.2007
29.05.2008Reminder for compliance. 06.08.2008Issue reminder for compliance report. Call on 03.09.2008
Reminder issued.No compliance report received.
Seek complinace. Call on 30.09.2008.
com 30.09 Reminder issued.No compliance report received.
Issue reminder for compliance report. Call on 03.09.2008
58 R. K. HosieryA-69
A-69, Group
Dyeing and bleaching of cotton hosiery fabric.
Not Mentioned
Not sought CTE under Green
Category on
14.12.2007 vide
I.D. No. 24494.
CTO (R) obtained. Valid upto 29.11.2007
Applied for renewal of authorization on 02.08.2006 vide I.D. No. 3067.
29.05.2008Let Green Committee decide. 06.08.2008SIT to inspect and report. Call on
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Case was taken up by CMC(Green) on 06.06.2008 & it was decided to again resubmit in CMC(Orange) to take decision for storage of
SIT to inspect and report. Call on 03.09.2008
03.09.2008 hazardous waste.
59 R.N. Gupta & Co.
A-125 Pickling & Annealing of SS sheet
30 tonnes / month (as per inspection report)
Not sought CTE under Green category on 17.1.08 vide ID No. 24773.
CTO refused on 08.01.2007 vide refusal no. 1578.
Refused on 05.01.2007.
29.05.2008SIT to inspect and report. Call on 11.06.2008.
04.07.2008 In view of the order of Finance Commissioner, the case was taken up as a table agenda today. Since the file is with SIT, case may be taken up 11.07.2008. 11.07.2008Since Finance Commissioner order says de-seal and inspect, SIT will coordinate with SDM, de-seal, inspect and reseal and submit report by 06.08.2008. 06.08.2008SIT to inspect and report. Call on 29.08.2008
SIT report to be discussed.
STI to put up the file administratively. Call on 30.09.2008.
SIT 30.09.2008
SIT inspection report to be discussed.
SIT to inspect and report. Call on 29.08.2008
60(a) Bhagwati A-101/5 unit closed Not unit closed unit _ _ Letter for Seek com 30.09 Since unit is closed,
Industries Mentioned closed 29.05.2008M/s Bhagwati Industries was found closed by SIT. Issue notice for closure to other units found by SIT. 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
disconnection of power / water supply & disconnection of MCD licence issued.
complinace. Call on 30.09.2008.
issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
60(b) Kanwar Sina
A-101/5, Ground Foor
Mf.g of Iron Base
CTE on 01.10.2007 vide I.D. No. 23728 under Green category(M/s Paras Electricals (India)
06.08.2008Notice to be pasted on the premises. Call on 03.09.2008
Notice pasted.M/s Paras Electricals (India) has submitted a letter on 27.08.2008 & informed that no unit in the name of M/s Kanwar Sain who is the landlord of the premises. At present M/s Paras Electrical
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.No reply received.
Notice to be pasted on the premises. Call on 03.09.2008
(India) is operating engaged in the activity of turning and threading of iron base plate for which he has applied for CTE under Green category.
60(c) S.K. Polymers
A-101/5, Ground Foor
Mfg. of Pet Bottles
CTE on 28.08.2008 vide I.D. No. 27118
06.08.2008Notice to be pasted on the premises. Call on 03.09.2008
Notice pasted.Applied for CTE on 28.08.2008 vide I.D. No. 27118
Call on 30.09.2008
30.09
30.09 Notice for closure issued.No reply received.
Notice to be pasted on the premises. Call on 03.09.2008
61 Durga Industries
A-100/2 unit closed Not Mentioned
unit closed unit closed
_ _ 29.05.2008Call on 03.07.2008 06.08.2008SIT to inpect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 SIT to inpect and report. Call on 03.09.2008
62(a) Ganesh A-79, Group
Unit Closed Unit closed. unit closed unit closed
_ _ 29.05.2008Issue notice for closure to
Call on 30.09.2008
NA Call on 03.09.2008
all six units. Call on 03.07.2008. 06.08.2008Call on 03.09.2008
62(b) Vardhman S. Industries
A-79, Basement, Group
Mfg. of S.S. Utensils
CTE on 04.07.2008 vide I.D .No 26288 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Unit has applied for CTE under Green category on 04.07.2008 vide I.D. No. 26288.As per CMC (Green) decision dated 18.07.2008, CTE granted without buffing.
Shift to Green Committee.
62(c) Jain Enterprises
A-79, Ground Floor, Group
Mfg. of motorcycle brake parts
CTE on 04.07.2008 vide I.D .No 26289 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Unit has applied for CTE under Green category on 04.07.2008 vide I.D. No. 26289.As per CMC (Green) decision dated 18.07.2008, CTE granted.
Shift to Green Committee.
62(d) Mishra Hosiery
A-79, 1st Floor, Group
Mfg. of Socks
CTE on 04.07.2008 vide I.D. No. 26301 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Applied for CTE on 04.07.2008 vide I.D. No. 26301 under Green category.As per CMC (Green) decision dated
Shift to Green Committee.
18.07.2008, CTE granted.
62(e) Anju Impex A-79, 2nd Floor, Group
Mfg. of S.S. Modular Kitchen Set (wire basket)
CTE on 04.07.2008 vide I.D .No 26291 under Green category.
06.08.2008Shift to Green Committee.
Shifted to Green Committee.
Remove from this list as the activity falls under Green category.
shift Notice for closure issued.Unit has applied for CTE under Green category on 04.07.2008 vide I.D. No. 26291.As per CMC (Green) decision dated 18.07.2008, CTE granted.
Shift to Green Committee.
62(f) Dhatu Spectro
A-79, 3rd Floor, Group
Metal Checking (analysis work)
CTE on 04.07.2008 vide I.D .No 26290 under Green category.
06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Unit has applied for CTE under Green category on 04.07.2008 vide I.D. No. 26290.As per CMC (Green) decision dated 18.07.2008, "Shift to Orange Committee".
SIT to inspect and report. Call on 03.09.2008
62(g) ETS Engineering
A-79, Ground Floor, Group
Zinc Casting (Pressure Die Casting)
CTE on 04.07.2008 vide I.D .No 26287
06.08.2008SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Applied for CTE on 04.07.2008 vide I.D .No 26287
SIT to inspect and report. Call on 03.09.2008
63 Ganpati Industries
B-27/2, Group
Unit does not exist.
Unit does not exist.
Not sought Unit does not exist.
Unit does not exist.
Unit does not exist.
29.05.2008No action. 06.08.2008No action.
No action. No action. NA No action. No action.
64 K.C. Steel B-31, Group
Buffing on S.S. Utensils.
200 Kg (as per inspection report)
Not sought Premises vacant.
Revocation of consent on 09.08.200
Not applicable
29.05.2008Reminder for compliance. 06.08.2008
Reminder issued.No compliance report
Reminder for compliance. Call on 30.10.2008
com 30.1 Reminder issued.No compliance report received.
Issue reminder for compliance report. Call on 03.09.2008
7. Issue reminder for compliance report. Call on 03.09.2008
received.
65 Kirti Industries
A-100/1 unit closed Not Mentioned
unit closed Unit found closed by SIT
Unit found closed by SIT
_ 29.05.2008Call on 03.07.2008Shift King Steel to Green Committee. 06.08.2008No action by this committee.
No action. No action. NA No action by this committee.
66 Manoj Steel Industries
B-5, Group
unit closed and shifted.
Not Mentioned
unit closed unit closed and shifted.
_ _ 29.05.2008No action. 06.08.2008No action.
No action. No action. NA No action. No action.
67 Om Steel Rolling Works
A-96/10 No Indl Activity observed(Premises is being used for godown & One Transport Company exists)
Activity Obsersved (as per Inspection Report)
_ CTO refused on 18.08.2007 vide refusal no. 16640.
29.05.2008No industrial activity found by SIT. Call on 03.07.2008. 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the
Letter for disconnection of power / water supply & disconnection of MCD licence issued.
Seek complinace. Call on 30.09.2008.
com 30.09 Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
unit.File be closed.
68 Rajinder C- 60/2 (Backside portion)
Manufacturing of Hinges (including pickling activity)
Unit does not exist.
Unit does not exist.
Unit does not exist.
Unit does not exist.
Unit does not exist.
29.05.2008Shift (i) & (ii) to Green Category. Other units i.e. (iii) & (iv) call on 03.07.2008. Issue notice for closure to (v) unit who have not applied for CTE 06.08.2008SIT to inspect all five units. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued to (v) Rattan Singh & Sons.Applied for CTE on 30.05.2008 vide I.D. No. 25903
SIT to inspect all five units. Call on 03.09.2008
69(a) Sobti Associates
B-78 Pickling (unit found closed / site found vacant)
Unit closed. Not sought Unit closed.
CTO refused on 06.08.2007 vide I.D. No. 1638
Unit closed. 29.05.2008Sobti closed.Issue notice for closure to Vidya Inds , Cellco India & Dinesh. 06.08.2008 SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 SIT to inspect and report. Call on 03.09.2008
69(b) Vidya Inds B-78 Applied CTE on 20.09.2007 vide I.D. No. 23573
Applied for authorization on 07.07.2008 vide I.D. No. 4616.
06.08.2008 SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Reply received on 07.07.2008. Unit has applied for authorization under HWM
SIT to inspect and report. Call on 03.09.2008
Rules.Unit has applied CTE on 20.09.2007 vide I.D. No. 23573
69(c) Cellco India
B-78 06.08.2008 SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.Reply received on 07.07.2008. Unit has informed that they are engaged in trading of synthetic leather and no need to apply CTE as informed by Enquiry Coutner.
SIT to inspect and report. Call on 03.09.2008
69(d) Dinesh B-78 06.08.2008 SIT to inspect and report. Call on 03.09.2008
SIT report to be discussed.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.No reply received.
SIT to inspect and report. Call on 03.09.2008
70 Sun Flower Steel Industries
A-81/1 Unit closed & shifted.No Indl Activity observed. Premises found vacant
Not Mentioned
unit closed Unit closed
_ _ 29.05.2008Call on 03.07.2008 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
Letter for disconnection of power / water supply & disconnection of MCD licence issued.
Seek complinace. Call on 30.09.2008.
com 30.09 Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
71(a) Swastik Enterprises
B-63 Pickling of SS sheets (Unit found
Not Mentioned
unit closed Unit closed
_ _ 29.05.2008
Letter for disconnection of
Seek complinace. Call on
com 30.09 SIT report to be discussed.
Since unit is closed, issue letter for disconnection of
closed, Pickling not found at site)
SIT to inspect & report. 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
Issue notice for closure to (i) Ashiksh Industries (ii) Surabh Industries for not applying for Consent to Establish.
power / water supply & disconnection of MCD licence issued.M/s Sourabh Industries has submitted a letter on 27.08.2008 M/s Swastik Enterprises is no more exists at the said addres.
30.09.2008. power/water supply & cancellation of MCD licence to the unit.File be closed.
Issue notice for closure to (i) Ashiksh Industries (ii) Surabh Industries for not applying for Consent to Establish.
71(b) Ashish Industries
B-63 Cold Re-rolling without pickling
CTE on 07.07.2008 vide I.D. no 26320
CTO(R) obtained on 20.04.2006 vide I.D. No. 14128 (valid upto 01.08.2008).CTO(R) on 16.07.2008 vide I.D. No. 26495.
Notice issued.CTO(R) obtained on 20.04.2006 vide I.D. No. 14128 (valid upto 01.08.2008).Applied for CTO(R) on 16.07.2008 vide I.D. No. 26495.Applied CTE on 07.07.2008
Call on 30.09.2008
30.09
30.09
vide I.D. no 26320
71(c) Surabh Industries
B-63 Cold Re-rolling without pickling
CTE on 07.07.2008 vide I.D. no 26321
CTO(R) obtained on 20.04.2006 vide I.D. No. 14129 (valid upto 01.08.2008).CTO(R) on 24.07.2008 vide I.D. No. 26717.
Notice issued.CTO(R) obtained on 20.04.2006 vide I.D. No. 14129 (valid upto 01.08.2008).Applied CTO(R) on 24.07.2008 vide I.D. No. 26717.Applied CTE on 07.07.2008 vide I.D. no 26321
Call on 30.09.2008
30.09
30.09
72(a) Sh. Charat / Sadanand (Proprietor of pickling unit )
C-55/1 (front portion )
Pickling of S.S.Sheets
BG not submitted.
_ 29.05.2008Issue final reminder for submission of BG to first two units for considering their CTE applications. Issue notice for closure for Shriram Inds. 06.08.2008Since unit is closed, issue letter for disconnection of power/water supply & cancellation
Letter for disconnection of power / water supply & disconnection of MCD licence issued.
Seek complinace. Call on 30.09.2008.
com 30.09 Since unit is closed, issue letter for disconnection of power/water supply & cancellation of MCD licence to the unit.File be closed.
of MCD licence to the unit.File be closed.
72(b) Shree Metal C-55/1, 1st Floor
Circle cutting
BG of Rs. One Lakh under Air Act submitted.
CTE on 27.05.2008 vide I.D. NO. 25831 under Green category
06.08.2008Ask the unit to file CGWA permission.Call on 03.09.2008
Letter issued.No reply received.
Remove from this list as the activity falls under Green category.
shift Letter issued.Bank Guarantee of Rs. One Lakh under Air Act submitted.
Ask the unit to file CGWA permission.Call on 03.09.2008
72(c) Suraj Industries
C-55/1 Pickling of S.S. Sheets
Rs. 75000 under each of three acts
CTE on 26.05.2008 vide I.D. No. 25839
06.08.2008Ask the unit to file CGWA permission.Call on 03.09.2008
Letter issued.No reply received.
Last and final reminder for submission of CGWA clearance. Also ask the unit to confirm through an affidavit that it is discharging its effluents whose pH is within the norms and to submit an action plan for stoppage of the activity before 07.02.2010, which falls under negative list as per MPD-2021 and an action plan for new proposed activity in conformity
4 MM 30.10.2008
Letter issued.Bank Guarantee of Rs. 75000 under each of three acts submitted.
Ask the unit to file CGWA permission.Call on 03.09.2008
with MPD-2021 on the vacant plot due to closure of present activity. Call on 30.10.2008.
72(d) Shriram Inds
Ground Floor (front portion)
Steel Rerolling
CTE on 13.08.2008 vide ID No. 26950
06.08.2008Notice to be pasted on the premises. Call on 03.09.2008
Notice for closure issued.No reply received.Notice pasted.No reply received.
Call on 30.09.2008
30.09
30.09 Notice for closure issued.No reply received.
Notice to be pasted on the premises. Call on 03.09.2008
73 Sterling Auto Engineering
B-69/1 Manufacturing of piston rings (involving electroplating, grinding and buffing)
Pistion Rings (as per Inspection Report)
Not Sought _ _ 29.05.2008Reminder for compliance from MCD & DJB. 06.08.2008Issue reminder for compliance report. Call on 03.09.2008
Reminder issued.No compliance report received.Unit has filed a write before High Court.
Seek complinace. Call on 30.09.2008.
com 30.09 Reminder issued.No compliance report received.Unit has filed a write before High Court.
Issue reminder for compliance report. Call on 03.09.2008