DOC. NO.: 56-00-41 REV. 01 PROJECT NO: E034.34E SH. 1 OF 103 AREA: Inspection & Expediting DESCRIPTION: Minimum Inspection requirements for Purchased Material REFERENCE SPEC. NO. - THIS DOCUMENT IS PROPRIETARY AND CONFIDENTIAL INFORMATION OF M&G GROUP AND ITS LICENSOR AND MAY BE USED ONLY WITH THEIR PRIOR WRITTEN CONSENT. REV. DESCRIPTION PREP'D. CKD. APPR’D. DATE 0 First issue MFL AA CR 04-Sept 2013 01 Final Issue. Revised after SEG comments where indicated MFL AA CR 11-Sept 2013 FILE NAME: E013-34E-56-00-41 rev 01 Minimum Inspection Requirement E013.34 E Minimum Inspection Requirements (ITP) for purchased Material M&G RESINS USA, LLC JUMBO PROJECT CORPUS CHRISTI, USA

Upload: hathien

Post on 07-Feb-2018

241 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO.: 56-00-41 REV. 01

PROJECT NO: E034.34E SH. 1 OF 103

AREA: Inspection & Expediting

DESCRIPTION: Minimum Inspection requirements for Purchased Material

REFERENCE SPEC. NO. - THIS DOCUMENT IS PROPRIETARY AND CONFIDENTIAL INFORMATION OF M&G GROUP AND ITS LICENSOR AND MAY BE USED ONLY WITH THEIR PRIOR WRITTEN CONSENT.

REV. DESCRIPTION PREP'D. CKD. APPR’D. DATE 0 First issue MFL AA CR 04-Sept 2013

01 Final Issue. Revised after SEG comments where indicated MFL AA CR 11-Sept 2013

FILE NAME: E013-34E-56-00-41 rev 01 Minimum Inspection Requirement

E013.34 E

Minimum Inspection Requirements (ITP) for purchased Material

M&G RESINS USA, LLC

JUMBO PROJECT

CORPUS CHRISTI, USA

Page 2: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 2 OF 103

R 01

TABLE OF CONTENTS

1 GENERAL ........................................... ............................................................................................... 4

1.1 SCOPE ............................................................................................................................................. 4

2 DEFINITIONS ..................................................................................................................................... 4

3 REFERENCE DOCUMENT ............................................................................................................... 5

4 QUALITY CLASS (CQ) / INSPECTION LEVEL ............. ................................................................... 5

4.1 SAMPLING INSPECTION ................................................................................................................ 6

5 ABBREVIATION ...................................... .......................................................................................... 6

6 INSPECTION AND TEST PLAN FOR EACH TYPE OF EQUIPMENT ............................................ 7

6.1 STEEL STRUCTURE ....................................................................................................................... 7

6.2 ANCHOR BOLTS .............................................................................................................................. 8

6.3 PRESSURE VESSEL ....................................................................................................................... 9

6.4 TRAY / COLUMN-INTERNALS ...................................................................................................... 11

6.5 SHELL AND TUBE HEAT EXCHANGER / GAS AND AIR PRE-HEATER ...................................... 12

6.6 AIR COOLED HEAT EXCHANGER ................................................................................................ 14

6.7 PLATE HEAT EXCHANGER .......................................................................................................... 16

6.8 ELECTRIC HEATER ....................................................................................................................... 18

6.9 PREFABRICATED ATMOSPHERIC TANK AT SHOP ................................................................... 19

6.10 SHOP FABRICATED STORAGE TANK ......................................................................................... 21

6.11 DEAERATOR / DESALTER ............................................................................................................ 23

6.12 API 610 CENTRIFUGAL PUMP ...................................................................................................... 24

6.13 RECIPROCATING, METERING, GEAR & DIAPHRAGM PUMPS ................................................. 27

6.14 GENERAL DUTY PUMPS INCLUDING BRINE PUMPS ............................................................... 29

6.15 CENTRIFUGAL COMPRESSOR ................................................................................................... 31

6.16 RECIPROCATING COMPRESSOR ............................................................................................... 33

6.17 AIR COMPRESSOR ....................................................................................................................... 34

6.18 FAN AND BLOWER ........................................................................................................................ 37

6.19 GAS TURBINE ................................................................................................................................ 38

6.20 STEAM TURBINE ........................................................................................................................... 40

6.21 LUBE OIL UNIT ............................................................................................................................... 42

6.22 FILTERS ......................................................................................................................................... 44

6.23 AGITATOR ..................................................................................................................................... 46

6.24 ELECTRIC HOIST .......................................................................................................................... 46

6.25 CRANE ........................................................................................................................................... 48

6.26 SILENCER ...................................................................................................................................... 49

6.27 IN-LINE STATIC MIXER ................................................................................................................. 50

6.28 FIRED HEATER .............................................................................................................................. 51

6.29 FLARE STACK ............................................................................................................................... 53

6.30 AUXILIARY BURNER ..................................................................................................................... 55

6.31 PACKAGED BOILER ...................................................................................................................... 56

6.32 CHEMICAL INJECTION & DOSING PACKAGE / ELECTROCHLORINATION PACKAGE ........... 59

6.33 REFRIGERANT UNIT ..................................................................................................................... 60

6.34 DESALINATION PACKAGES ......................................................................................................... 62

6.35 WATER POLISHING / REMINERALIZATION AND POTABLE WATER PACKAGE ...................... 65

6.36 FIRE FIGHTING SYSTEM .............................................................................................................. 68

6.37 EMERGENCY DIESEL GENERATOR ........................................................................................... 70

6.38 HVAC SYSTEM .............................................................................................................................. 72

Page 3: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 3 OF 103

R 01

6.39 PIPE ................................................................................................................................................ 74

6.40 SHOP FABRICATED PIPE ............................................................................................................. 75

6.41 FLANGE.......................................................................................................................................... 76

6.42 FITTING .......................................................................................................................................... 77

6.43 SPRING HANGER AND PIPE SUPPORT ...................................................................................... 78

6.44 ORDINARY TYPE VALVES (CASTING & FORGED) ..................................................................... 79

6.45 CRYOGENIC TYPE VALVES (CASTING & FORGED) .................................................................. 81

6.46 STRAINER ...................................................................................................................................... 83

6.47 EXPANSION JOINT ........................................................................................................................ 84

6.48 FLEXIBLE HOSE AND QUICK CONNECTOR ............................................................................... 85

6.49 LV SWITCHGEAR / MOTOR CONTROL CENTER (MCC) ............................................................ 86

6.50 UNINTERRUPTIBLE POWER SUPPLIES (UPS) .......................................................................... 88

6.51 INDUCTION MOTORS (LV & MV) .................................................................................................. 89

6.52 DRY TYPE TRANSFORMER ......................................................................................................... 91

6.53 OIL-IMMERSED TYPE TRANSFORMER ...................................................................................... 93

6.54 6KV SWITCHGEAR AND CONTROLGEAR ................................................................................... 95

6.55 33KV SWITCHGEAR ...................................................................................................................... 97

6.56 CABLES .......................................................................................................................................... 99

6.57 DISTRBUTION PANELS .............................................................................................................. 100

6.58 CONTROL VALVES/ESDV’S/BDV’S /ON-OFF VALVES ............................................................. 101

6.59 INSTRUMENT BULKS ................................................................................................................. 102

6.60 INSTRUMENT PRESSURE AND TEMPERATURE GAUGE ...................................................... 103

Page 4: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 4 OF 103

R 01

1 GENERAL

1.1 SCOPE This document covers the minimum general requirements of inspection and test activities to be performed for equipment and materials purchased, by the Contractor and/or the Owner or his nominated Third Party inspection Agency Inspector. These minimum general requirements of inspection shall be incorporated into the final ITP/QCP to be prepared by each Vendor and accepted by Contractor.

The assigned witness / hold points in ITP/QCP may be changed at Contractor's discretion during the course of the work to ensure the quality of equipment and materials.

The extent of inspection and test activities for the equipment and materials that are not covered by this document shall be highlighted to the CONTRACTOR and defined together with OWNER and LICENSORS prior to the start of fabrication.

If any conflict arises between this General Inspection Requirements for purchased Material and specification in the engineering requisition and/or purchase order, Vendor shall submit its deviation list to Contractor and through Contractor to Owner/Licensor for approval. However, if conflict arises between ITP and Data Sheets / Technical specifications, the latter shall prevail.

Relevant equipment specification numbers shall be reflected on each Final ITP/QCP to be prepared by each vendor.

2 DEFINITIONS

OWNER: M&G Resins Usa LLC.

CONTRACTOR: MGF,CII, SEG

MGF: M&G Finanziaria s.r.l

CSC: Chemtex Shanghai Chemical Engineering Company.

CII: Chemtex International Inc.

SEG: Sinopec Engineering Group ltd.

INSPECTOR: OWNER/CONTRACTOR's Inspector - employee or Agency Inspector

acting on behalf of OWNER / CONTRACTOR.

LICENSOR: TBD

VENDOR(S): means any person/firm or business which manufactures or supply

materials, equipment as required by a Purchase order.

PURCHASE ORDER: means the documents and attachments in which the order is described.

REQUISITION: means the documents where establishes the several technical, commercial and purchase conditions.

1

Page 5: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 5 OF 103

R 01

ITP/QCP: Inspection and Test Plan/Quality Control Plan prepared by Vendor.

MDR: Manufacturers Data Report

MOM: Minute of Meeting

MR: Material Requisition

NC/NCR: Non Conformity / Non Conformity Report

PL: Punch List

P/L: Packing List

PO: Purchase Order with relevant attachments

PPM: Project Procurement Manager

QC: Quality Control

PIM: Pre – Inspection Meeting

3 REFERENCE DOCUMENT

E013.34E-56-00-20 “Communication Plan” E013.34E-56-00-25 “Procurement Procedure” E013.34E-56-00-40 “QC Coordination Procedure with Suppliers” ….TBD.

4 QUALITY CLASS (CQ) / INSPECTION LEVEL Quality Class / Inspection Level are specified by the Technical Specification and shall be recalled into ITP front page. Equipment and Material shall be inspected by Contractor/OWNER within the limit of these level of inspection described below. CQ level 1: No contractor inspection. Review of inspection Reports and final documentation only. CQ level 2: Final Inspection prior to shipment. Issue of Inspection Release certificates and inspection including major tests. QC Level 3 Limited in process inspection and final inspection prior to shipment. Include as minimum Pre-Inspection Meeting, one or more in-process surveillance inspection visit as necessary. Witness of the major tests and tests specified in the data sheet for that type of equipment. Review of required documentation and issue of Inspection Release Certificate. QC Level 4 Progressive quality surveillance. Include Pre-Inspection Meeting, regular inspection visit are more frequent, based upon milestones as well as Witness/Hold points that are outlined in the

Page 6: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 6 OF 103

R 01

Pre-Inspection Meeting, approved ITP, data sheet. Witness of major tests, review of required documentations and issue of Inspection Release Certificate. Resident Inspector may be required to continuously monitoring the work in accordance with the ITP.

4.1 SAMPLING INSPECTION Where 10% of sampling inspection is called for valves, thermowell, bulks etc. it means that

10% or less of total ordered quantities of commodities. It is understood that in case the Purchase order for certain item of commodities is issued for

more than 2 times and/or the item of commodities is shipped on partial basis, the subsequent inspection may be waived at discretion of the Contractor/Owner/Licensors if previous inspections has been passed satisfactorily.

5 ABBREVIATION

Abbreviations used in this document are defined as follows:

R: Review of documents (including for example, radiograph films, Material certificate, etc.)

W: Witness - Application for inspection is required. The inspector will arrange to be present in ongoing process. Vendor will proceed to the next step if he is not present.

SW: Spot Witness – Application for inspection is required for initial operation for continuing of operation. The Inspector may witness in the specified activity at his discretion. Vendor can proceed to the next step if he is not present.

W+: Previous record may be reviewed H: Hold point - Application for inspection is required. Vendor shall not proceed with

work until inspector is present or written consent of inspector has been obtained. ITP/QCP: Inspection and Test plan/Quality Control Plan If required :means to be required

on the PO, Job Specification and/or applicable Codes and Standards.

NOTE: If not differently specified and agreed the “ Application for inspection” shall be sent to contactor (MGF) with and advance notice of 15 calendar days

Page 7: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 7 OF 103

R 01

6 INSPECTION AND TEST PLAN FOR EACH TYPE OF EQUIPME NT

6.1 STEEL STRUCTURE

COMMODITY: STEEL STRUCTURE (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

QC LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING, IF NECESSARY (DEPENDING ON

VOLUME) R R W W

2 MAIN MATERIAL IDENTIFICATION AND MATERIAL CERTIFICATES

REVIEW SW/R SW/R SW/R SW/R

3 WELDING PROCEDURE QUALIFICATION R R R R

4 WELDERS PERFORMANCE QUALIFICATION TEST R R R SW

5 CUTTING, SIZING, FIT-UP AND ASSEMBLY R R SW SW

6 NON-DESTRUCTIVE EXAMINATION (IF REQUIRED) R R SW SW

7 VISUAL&DIMENSIONAL INSPECTION R R SW SW

8 TRIAL ASSEMBLY INSPECTION (IF REQUIRED) R R SW SW

9 SURFACE PREPARATION INSPECTION (IF REQUIRED) R R SW SW

10 COATING INSPECTION (DRY FILM THICKNESS CHECK,

GALVANIZING etc.) SW SW SW W

11 MANUFACTURER’S DATA RECORDS R R R/W R/W

12 PRE-SHIPMENT INSPECTION R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1: VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 8: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 8 OF 103

R 01

6.2 ANCHOR BOLTS

COMMODITY: ANCHOR BOLTS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES R R R R

2 DIMENSIONAL AND VISUAL INSPECTION R R SW SW

3 COATING/PRESERVATION R R SW SW

4 MANUFACTURER’S DATA RECORDS R R R R/W

5 PRE-SHIPMENT INSPECTION R R SW SW

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1: VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 9: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 9 OF 103

R 01

6.3 PRESSURE VESSEL

COMMODITY: PRESSURE VESSEL /(Reactors, Columns, Drums) (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), COMPANY (O), TPI/TPIA AND SHALL BE INCORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES R R R R

3 CHECK OF DIMENSION, MARKING, SURFACE OF PLATE

(PRESSURE RETAINING PARTS) R R SW W

4

CHECK OF MARK WITH NAME OF TRADE MARK ONLY FOR

PRESSURE PARTS SUCH AS PIPE, FITTING, FLANGE, NOZZLE,

WELD CAP ETC.

R R SW W

5 WELDING PROCEDURE QUALIFICATION TEST R R R SW

6 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

7 TRANSFER OF MATERIAL IDENTIFICATION R R R SW

8 FIT-UP INSPECTION R R SW W

9 PRODUCTION WELD TEST (IF REQUIRED) R R SW SW

10 CLAD PLATE / OVERLAY WELD (IF REQUIRED) R R R SW

11 FERRITE CHECK OF WELD AND WELD OVERLAY (IF REQUIRED) R R SW SW

12 HARDNESS TEST (IF APPLICABLE) R R SW SW

13 LIQUID PENETRANT EXAMINATION AND/OR MAGNETIC

PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

14 ULTRASONIC EXAMINATION (IF REQUIRED) R R SW SW

15 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

16 POST WELD HEAT TREATMENT (IF REQUIRED) R R R SW

17 POSITIVE MATERIAL IDENTIFICATION (PMI)(IF APPLICABLE) R R SW SW

18 FERROXYL TEST (IF APPLICABLE) R R SW SW

DIMENSIONAL CHECK AND VISUAL INSPECTION

19 VISUAL&DIMENSIONAL CHECK OF HEADS AFTER FORMING R R R SW

20 OUT-OF ROUGNDNESS AND STRAIGHTNESS R R R SW

21 NOZZLE ORIENTATION AND PROJECTION R R R SW

Page 10: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 10 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

22 BASE PLATE AND TEMPLATE (VISUAL AND DIMENSION) R R SW SW

23 RATING, FACE TYPE, SIZE AND MARKING OF FLANGES R R SW SW

24 INTERNAL RING ELEVATION AND LEVEL R R SW W

25 OVERALL DIMENSION R SW W W

26 NAME PLATE CHECK R SW W W

27 TRAY AND INTERNAL DEVICE R R SW SW

28 GASKETS AND BOLTS R R R R

29 AIR LEAK TEST OF REINFORCING PAD R R SW SW

30 HYDROSTATIC TEST R R W H

31 DRAINING, DRYING, CLEALINESS CHECK (INTERNAL) R R W H

32 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

33 SPARA PART CHECK R R SW W

34 MANUFATURER’S DATA BOOK R R R/W R/H

35 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2 FILLING etc.) R W W W

Auxiliary Steel Structures

36 DIMENSIONAL CHECK R R SW SW

37 TRIAL FIT UP R R SW SW

Loading Spreading beam (if required)

38 NON-DESTRUCTIVE EXAMINATION R R R SW

39 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1: VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 11: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 11 OF 103

R 01

6.4 TRAY / COLUMN-INTERNALS

COMMODITY: TRAY / COLUMN-INTERNALS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES CHECK AND MATERIAL

IDENTIFICATION R R R/W R/W

3 WELDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

5 PMI, FERRITE, FERROYIL TEST (AS APPLICABLE) R R SW SW

6 LEAKAGE TEST & LIQUID MALDISTRIBUTION TEST OF GRAVITY

(IF REQUIRED) R R SW W

7 TRIAL ASSEMBLY INSPECTION R R SW W

8 DIMENSIONAL CHECK AND VISUAL INSPECTION (including

Marking) R SW SW SW

9 CHECK OF SURFACE TREATMENT (PICKLING&PASSIVATION

where applicable) R R SW SW

10 FERROXYL TEST (IF REQUIRED) R R SW SW

11 MANUFATURER’S DATA BOOK R R R R/W

12 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 12: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 12 OF 103

R 01

6.5 SHELL AND TUBE HEAT EXCHANGER / GAS AND AIR PRE-HEATER

COMMODITY: SHELL AND TUBE HEAT EXCHANGER / GAS AND AIR PRE-HEATER (NOT E1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), COMPANY (O), TPI/TPIA AND SHALL BE INCORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES AND MATERIAL IDENTIFICATION R R R/SW R/W

3 CHECK OF DIMENSION, MARKING, SURFACE OF PLATE

(PRESSURE RETAINING PARTS) R R SW W

4

CHECK OF MARK WITH NAME OF TRADE MARK ONLY FOR

PRESSURE PARTS SUCH AS PIPE, FITTING, FLANGE, NOZZLE,

WELD CAP ETC.

R R SW W

5 WELDING PROCEDURE QUALIFICATION TEST R R R R

6 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

7 TRANSFER OF MATERIAL IDENTIFICATION R R SW SW

8 FIT-UP INSPECTION R R SW SW

9 PRODUCTION TEST WELD (IF REQUIRED) R R R SW

10 CLAD PLATE / OVERLAY WELD (IF REQUIRED) R R SW SW

11 FERRITE CHECK OF WELD AND WELD OVERLAY (IF REQUIRED) R R SW SW

12 HARDNESS TEST (IF APPLICABLE) R R SW SW

13 LIQUID PENETRANT EXAMINATION AND/OR MAGNETIC

PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

14 ULTRASONIC EXAMINATION (IF REQUIRED) R R SW W

15 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

16 POST WELD HEAT TREATMENT (IF REQUIRED) R R R SW

17 POSITIVE MATERIAL IDENTIFICATION (PMI)(IF APPLICABLE) R R SW SW

18 FERROXYL TEST (IF APPLICABLE) R R SW SW

DIMENSIONAL CHECK AND VISUAL INSPECTION

19 VISUAL&DIMENSIONAL CHECK OF HEADS AFTER FORMING R R R SW

19 OUT-OF ROUGNDNESS AND STRAIGHTNESS R R R R

20 NOZZLE ORIENTATION AND PROJECTION R R R R

Page 13: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 13 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

21 BASE PLATE AND TEMPLATE VISUAL AND DIMENSION R R R SW

22 RATING, FACE TYPE, SIZE AND MARKING OF FLANGES R R R SW

23 EXPANSION BELOW (IF REQUIRED) R R SW SW

24 DIMENSION, FACE FINISH AND GROOVING OF TUBE SHEET R R SW W

25 BAFFLE DRILLED R R R R

26 INSPECTION OF TUBE EXPANDING AND TUBE WELDING R R SW SW

27 COMPLETE BUNBLE EXAMINATION R R W W

28 INSERTING OF TUBLE BUNDLE R R SW SW

29 OVERALL DIMENSION R SW SW W

30 NAME PLATE R R R R

31 GASKETS AND BOLTS R R R SW

32 AIR LEAK TEST OF REINFORCING PAD R R SW W

33 LEAK TEST FOR JOINT OF TUBE TO TUBE SHEET (IF

REQUIRED) R R W W

34 HYDROSTATIC TEST R R W H

35 PNEUMATIC TEST R R W H

36 DRAINING, DRYING, CLEALINESS CHECK (INTERNAL) R R W H

37 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

38 SPARA PART CHECK R R SW SW

39 MANUFATURER’S DATA BOOK R R R/W R/W

40 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2 FILLING etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 14: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 14 OF 103

R 01

6.6 AIR COOLED HEAT EXCHANGER

COMMODITY: AIR COOLED HEAT EXCHANGER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

TUBE BUNDLE

2 MATERIAL CERTIFICATES REVIEW AND MATERIAL

IDENTIFICATION R R R/W R/W

3 WELDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

5 FIT-UP CHECK R R R SW

6 PRODUCTION TEST COUPON AND MECHANICAL TEST (IF

REQUIRED) R R R R

7 TUBE TO TUBE SHEET WELDING CHECK R R SW SW

8 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

9 ULTRASONIC EXAMINATION (IF REQUIRED) R R SW WW

10 MAGNETIC PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

11 LIQUID PENETRANT TEST (IF REQUIRED) R R SW SW

12 POST WELD HEAT TREATMENT (IF REQUIRED) R R R SW

13 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

14 TUBE FINNING CHECK R R R R

15 HYDROSTATIC TEST R R W H

16 POSITIVE MATERIAL IDENTIFICATION (PMI), (IF APPLICABLE) R R SW SW

17 FERRITE CHECK (IF APPLICABLE) R R SW SW

18 CHECK OF FLANGE SURFACE FINISHING R R R SW

19 DRAINING, DRYING AND CLEANING CHECK R R W W

21 FINAL VISUAL AND DIMENSIONAL CHECK R R W W

22 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

Page 15: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 15 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

24 NAME PLATE CHECK R R R R

25 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2, Silica Gel , Vapor corrosion Inhibitor etc.) R R W H

FAN PART (Including hub and blades)

26 MATERIAL CERTIFICATES REVIEW AND MATERIAL

IDENTIFICATION R R SW SW

27 STATIC AND DINAMIC BALANCING TEST REPORTS R R R R

AXILIARY STEEL STRUCTURE

28 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

29 TRIAL FIT UP R R SW SW

ELECTRICAL MOTOR AND CONTROLPANEL

30 VISUAL AND DIMENSIONAL CHECK R R SW SW

31 REVIEW OF CERTITICATES R R R R

COMPLETE PACKAGE

32 RUN TEST AND PRE-ASSEMBLY AT SHOP R R W W

33 PACKAGE SUPPLY COMPLETION CHECK R W W W

34 MANUFATURER’S DATA BOOK R R R/W R/W

35 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2, Silica Gel , Vapor corrosion Inhibitor etc.) R W W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 16: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 16 OF 103

R 01

6.7 PLATE HEAT EXCHANGER

COMMODITY: PLATE HEAT EXCHANGER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW AND MATERIAL

IDENTIFICATION R R SW W

3 WELDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

5 FIT-UP CHECK R R R R

6 PRODUCTION TEST COUPON AND MECHANICAL TEST (IF

REQUIRED) R R R R

7 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

8 ULTRASONIC EXAMINATION (IF REQUIRED) R R R SW

9 MAGNETIC PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

10 LIQUID PENETRANT TEST (IF REQUIRED) R R W W

11 POST WELD HEAT TREATMENT (IF REQUIRED) R R R R

12 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

13 SHELL PLATE AND HEADS THCKNESS CHECK R R SW SW

14 HYDROSTATIC TEST R R W H

15 POSITIVE MATERIAL IDENTIFICATION (PMI), (IF APPLICABLE) R R SW SW

16 FERRITE CHECK (IF APPLICABLE) R R R SW

17 CHECK OF FLANGE SURFACE FINISHING R R SW SW

18 PNEUMATIC TEST (IF REQUIRED) R R SW SW

19 DRAINING, DRYING AND CLEANING CHECK R R SW SW

21 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

22 NAME PLATE CHECK R W W W

23 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2, Silica Gel , Vapor corrosion Inhibitor etc.) R W W H

Page 17: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 17 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

24 MANUFATURER’S DATA BOOK R R R/W R/W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 18: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 18 OF 103

R 01

6.8 ELECTRIC HEATER

COMMODITY: ELECTRIC HEATER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW AND MATERIAL

IDENTIFICATION R R SW SW

3 WELDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

5 NON DISTRUCTIVE EXAMINATION (IF REQUIRED) R R R SW

6 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

7 HYDROSTATIC TEST R R W H

8 CLEALINESS CHECK R R W W

9 FUNCTIONAL TEST FOR CONTROL PANEL R R SW SW

10 ELECTRICAL TEST R R SW SW

11 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R W W

12 MANUFATURER’S DATA BOOK R R R/W R/W

13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 19: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 19 OF 103

R 01

6.9 PREFABRICATED ATMOSPHERIC TANK AT SHOP

COMMODITY: PREFABRICATED ATMOSPHERIC TANK AT SHOP (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW R R R R

3 ULTRASONIC EXAMINATION FOR PLATE (IF REQUIRED) R R SW SW

4 CHECK OF DIMENSION, MARKING, SURFACE OF PLATE

(PRESSURE RETAINING PARTS) R R SW SW

5

CHECK OF MARK WITH NAME OF TRADE MARK ONLY FOR

PRESSURE PARTS SUCH AS PIPE, FITTING, FLANGE, NOZZLE,

WELD CAP ETC.

R R R SW

6 WELDING PROCEDURE QUALIFICATION TEST R R R R

7 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

8 PLATES ROLLING AND BEVELLING R R R SW

9 NDE OF BEVELS (Plates) R R SW SW

10 LIQUID PENETRANT EXAMINATION AND/OR MAGNETIC

PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

11 ULTRASONIC EXAMINATION (IF REQUIRED) R R R SW

12 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

13 POST WELD HEAT TREATMENT (IF REQUIRED) R R R R

14 HARDNESS TEST (IF APPLICABLE) R R R SW

15 POSITIVE MATERIAL IDENTIFICATION (IF APPLICABLE) R R R SW

16 FERRITE CHECK (IF APPLICABLE) R R SW SW

17 FERROXYL TEST (IF REQUIRED) R R SW SW

18 DIMENSIONAL CHECK AND VISUAL INSPECTION R SW W W

19 CLEANLINESS CHECK R R W W

20 COATING INSPECTION: STEEL PREPARATION AND PAINTING

(IF REQUIRED) R R SW SW

21 MANUFATURER’S DATA BOOK R R R/W R/W

22 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Page 20: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 20 OF 103

R 01

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 21: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 21 OF 103

R 01

6.10 SHOP FABRICATED STORAGE TANK

COMMODITY: SHOP FABRICATED STORAGE TANK (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES R R R R

3 ULTRASONIC EXAMINATION FOR PLATE (IF REQUIRED) R R R R

4 CHECK OF DIMENSION, MARKING, SURFACE OF PLATE

(PRESSURE RETAINING PARTS) R R R SW

5

CHECK OF MARK WITH NAME OF TRADE MARK ONLY FOR

PRESSURE PARTS SUCH AS PIPE, FITTING, FLANGE, NOZZLE,

WELD CAP ETC.

R R SW SW

6 WELDING PROCEDURE QUALIFICATION TEST R R R R

7 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

FOUNDATION RING TEMPLATE (Visual and dimensional

check) R R SW SW

8 PLATES ROLLING AND BEVELLING R R R SW

9 NDE OF BEVELS (Plates) R R SW SW

10 LIQUID PENETRANT EXAMINATION AND/OR MAGNETIC

PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

11 ULTRASONIC EXAMINATION (IF REQUIRED) R R SW SW

12 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

13 POST WELD HEAT TREATMENT (IF REQUIRED) R R R R

14 HARDNESS TEST (IF APPLICABLE) R R SW SW

15 POSITIVE MATERIAL IDENTIFICATION (IF APPLICABLE) R R SW SW

16 FERRITE CHECK (IF APPLICABLE) R R SW SW

17 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

18 AIR LEAK TEST OF REINFORCING PAD R R SW SW

19 HYDROSTATIC TEST R R W H

20 PNEUMATIC TEST (IF REQUIRED) R R SW SW

21 FERROXYL TEST (IF REQUIRED) R R SW SW

Page 22: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 22 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

22 DRAINING, DRYING AND CLEANING CHECK R R SW SW

23 VISUAL AND DIMENSIONAL EXAMINATIONS OF STEEL

STRUCTURES (stairways, platform, ect) R R R SW

24 TRIAL ASSEMBLY OF AUXILIARY STEEL STRUCTURES R R SW SW

25 COATING INSPECTION: STEEL PREPARATION AND PAINTING

(IF REQUIRED) R R SW SW

26 MANUFATURER’S DATA BOOK R R R/W R/W

27 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 23: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 23 OF 103

R 01

6.11 DEAERATOR / DESALTER

COMMODITY: DEAERATOR / DESALTER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES R R R R

3 CHECK OF DIMENSION, MARKING, SURFACE OF PLATE

(PRESSURE RETAINING PARTS) R R W W

4

CHECK OF MARK WITH NAME OF TRADE MARK ONLY FOR

PRESSURE PARTS SUCH AS PIPE, FITTING, FLANGE, NOZZLE,

WELD CAP ETC.

R R W W

5 WELDING PROCEDURE QUALIFICATION TEST R R SW SW

6 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R SW SW

7 TRANSFER OF MATERIAL IDENTIFICATION R R SW SW

8 FIT-UP INSPECTION R R SW W

9 PRODUCTION WELD TEST (IF REQUIRED) R R W W

10 CLAD PLATE / OVERLAY WELD (IF REQUIRED R R W W

11 FERRITE CHECK OF WELD AND WELD OVERLAY (IF REQUIRED) R R SW SW

12 HARDNESS TEST (IF APPLICABLE) R R SW SW

13 LIQUID PENETRANT EXAMINATION AND/OR MAGNETIC

PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

14 ULTRASONIC EXAMINATION (IF REQUIRED) R R SW SW

15 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R W W FILM

REVIEW

16 POST WELD HEAT TREATMENT (IF REQUIRED) R R SW W

17 POSITIVE MATERIAL IDENTIFICATION (PMI)(IF APPLICABLE) R R SW SW

18 FERROXYL TEST (IF APPLICABLE) R R SW W

DIMENSIONAL CHECK AND VISUAL INSPECTION

19 VISUAL&DIMENSIONAL CHECK OF HEADS AFTER FORMING R R SW SW

20 OUT-OF ROUGNDNESS AND STRAIGHTNESS R R SW SW

21 NOZZLE ORIENTATION AND PROJECTION R R SW W

Page 24: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 24 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

22 BASE PLATE AND TEMPLATE R R SW W

23 RATING, FACE TYPE, SIZE AND MARKING OF FLANGES R R SW SW

24 INTERNAL RING ELEVATION AND LEVEL R R SW SW

25 OVERALL DIMENSION R R W W

26 NAME PLATE R R W W

27 TRAY AND INTERNAL DEVICE R R SW W

28 GASKETS AND BOLTS R R SW W

29 AIR LEAK TEST OF REINFORCING PAD R R W W

30 HYDROSTATIC TEST R R W H

31 DRAINING, DRYING, CLEALINESS CHECK (INTERNAL) R R W W

32 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R W W

33 SPARE PART CHECK R R SW W

34 MANUFATURER’S DATA BOOK R R R/W R/W

35 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2 FILLING etc.) R W W H

Auxiliary Steel Structures

36 DIMENSIONAL CHECK R R SW SW

37 TRIAL FIT UP R R SW W

Loading Spreading beam (if required)

38 NON-DESTRUCTIVE EXAMINATION R R SW SW

39 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

6.12 API 610 CENTRIFUGAL PUMP

COMMODITY: API 610 CENTRIFUGAL PUMP (NOTE 1, 2, 3, 4, 5)

Page 25: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 25 OF 103

R 01

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES (Casing, cover, impeller, shaft,

diffuser(s), mechanical seal(s)) R R R R 5

3 RADIOGRAPHIC TEST (RT) FOR CONNECTION WELDS R R W W FILM

REVIEW

4 PT ON MACHINED SURFACE (impellers and casing) R R SW W

5 IF BARREL TYPE, NDE ON BARRELS AS PER TYPE AND

FABRICATION R R W W

6 HARDNESS TEST FOR WELD (WHERE REQUESTED) R R SW SW

7 HYDROSTATIC TEST (CASING AND PRESSURE CONTAINING

PARTS) R R W H

8 BALANCING OF IMPELLER AND/OR ROTOR R R W H

9 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R SW W 4

10 NPHS TEST (AS PER DATA SHEET) R R W W 3

11

PERFORMANCE TEST OF ASSEMBLED UNIT (Power, capacity,

head check, bearing temp. check, vibration, corrected curve

check by speed&specific gravity, sound level test, inspection

of hydrodynamic bearing after test)

R R W W 2

12 MECHANICAL RUNNING TEST FOR 4 H (IF REQUIRED) R R W W

13

VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) INCLUDING SEAL FLUSHING/COOLING SYSTEM AND

SKID ASSEMBLY

R W W H

14 NAME PLATE DATA CHECK R R W W

15 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R W W

16 MANUFATURER’S DATA BOOK R R R/W R/W

17 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R R W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. EACH PUMP SHALL BE GIVEN A PERFORMANCE TEST AT THE SHOP, BUT FOR IDENTICAL ONES, THE WITNESS IS TO BE PERFORMED ONE (1) SET DESIGNATED BY THE INSPECTOR

Page 26: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 26 OF 103

R 01

AND THE TEST OF PUMPS WITH RATED POWER OF LESS THAN 30KW SHALL BE IN ACCORDANCE WITH THE OTHER PROJECT SPECIFICATIONS.

3. NPSH SUPPRESSION TEST SHALL BE CARRIED OUT IN ACCORDANCE WITH THE STANDARD OF HYDRAULIC INSTITUTE STANDARD (LATEST EDITION).

4. ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS PER “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50

5. MATERIAL CERTIFICATE TYPE 3.1 FOR CASING, IMPELLER, AND SHAFT, TYPE 2.2 FOR ALL OTHER PARTS.

Page 27: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 27 OF 103

R 01

6.13 RECIPROCATING, METERING, GEAR & DIAPHRAGM PUMPS

COMMODITY: RECIPROCATING, METERING, GEAR & DIAPHRAGM PUMPS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES (Casing, plunger, diaphragm, ball) R R R R 5

3 NON DISTRUCTIVE EXAMINATION (IF REQUIRED, connection,

weld, casing, etc.) R R SW SW

4 PT ON MACHINED SURFACE R R SW SW

5 HYDROSTATIC TEST (CASING AND PRESSURE CONTAINING

PARTS) R R W H

6

PERFORMANCE TEST OF ASSEMBLED UNIT (Power, capacity,

head check, bearing temp. check, vibration, corrected curve

check by speed&specific gravity, sound level test, inspection

of hydrodynamic bearing after test)

R R W H 2

7 MECHANICAL RUNNING TEST FOR 4 H (IF REQUIRED) R R W H 2

8 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R W W 4

9

VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) INCLUDING SEAL FLUSHING/COOLING SYSTEM AND

SKID ASSEMBLY

R W W W

10 NAME PLATE DATA CHECK R W W W 3

11 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

12 MANUFATURER’S DATA BOOK R R R/W R/W

13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. EACH PUMP SHALL BE GIVEN A PERFORMANCE TEST AT THE SHOP, BUT FOR IDENTICAL ONES, THE WITNESS IS TO BE PERFORMED ONE (1) SET DESIGNATED BY THE INSPECTOR AND THE TEST OF PUMPS WITH RATED POWER OF LESS THAN 30KW SHALL BE IN ACCORDANCE WITH THE OTHER PROJECT SPECIFICATIONS.

3. NPSH SUPPRESSION TEST SHALL BE CARRIED OUT IN ACCORDANCE WITH THE STANDARD OF HYDRAULIC INSTITUTE STANDARD (LATEST EDITION).

Page 28: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 28 OF 103

R 01

4. ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS PER “ITP “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

5. MATERIAL CERTIFICATE TYPE 3.1 FOR CASING, IMPELLER, AND SHAFT, TYPE 2.2 FOR ALL OTHER PARTS.

Page 29: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 29 OF 103

R 01

6.14 GENERAL DUTY PUMPS INCLUDING BRINE PUMPS

COMMODITY: GENERAL DUTY PUMPS INCLUDING BRINE PUMPS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES (Casing, impeller and shaft) R R R R 5

3 NON DISTRUCTIVE EXAMINATION (IF REQUIRED) R R SW SW

4 PT ON MACHINED SURFACE R R SW SW

5 HYDROSTATIC TEST (CASING AND PRESSURE CONTAINING

PARTS) R R W H

6

PERFORMANCE TEST OF ASSEMBLED UNIT (Power, capacity,

head check, bearing temp. check, vibration, corrected curve

check by speed&specific gravity, sound level test, inspection

of hydrodynamic bearing after test)

R R W H 2

7 MECHANICAL RUNNING TEST FOR 4 H (IF REQUIRED) R R W H 2

8 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R W W 4

9

VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) INCLUDING SEAL FLUSHING/COOLING SYSTEM AND

SKID ASSEMBLY

R R W W

10 NAME PLATE DATA CHECK R W W W 3

11 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

12 MANUFATURER’S DATA BOOK R R R/W R/W

13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R R W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. EACH PUMP SHALL BE GIVEN A PERFORMANCE TEST AT THE SHOP, BUT FOR IDENTICAL ONES, THE WITNESS IS TO BE PERFORMED ONE (1) SET DESIGNATED BY THE INSPECTOR AND THE TEST OF PUMPS WITH RATED POWER OF LESS THAN 30KW SHALL BE IN ACCORDANCE WITH THE OTHER PROJECT SPECIFICATIONS.

3. NPSH SUPPRESSION TEST SHALL BE CARRIED OUT IN ACCORDANCE WITH THE STANDARD OF HYDRAULIC INSTITUTE STANDARD (LATEST EDITION).

4 ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS PER “ITP TESTED AS PER “ITP “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

Page 30: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 30 OF 103

R 01

5. MATERIAL CERTIFICATE TYPE 3.1 FOR CASING, IMPELLER, AND SHAFT, TYPE 2.2 FOR ALL OTHER PARTS.

Page 31: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 31 OF 103

R 01

6.15 CENTRIFUGAL COMPRESSOR

COMMODITY: CENTRIFUGAL COMPRESSOR (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES (Casing, impeller, shaft, bull gear

IGV R R R R

3 CHECK OF WELDING BOOK R R R R

4

UT ON SHAFT after RAW MACHINING, PT ON FINISHED

SHAFT. MT or PT on WELDED PART (Impeller or casing) UT/PT

on FORGED IMPELLER, BULL GEAR,

R R W W

5 HARDNESS TEST FOR WELD (WHERE REQUESTED) R R SW SW

6 HYDROSTATIC TEST (CASING AND PRESSURE CONTAINING

PARTS) R R W H

7

HIGH SPEED BALANCING OF IMPELLER AND/OR ROTOR.

MECHANICAL and ELECTRICAL RUN-OUT, OVERSPEED TEST;

PT AFTER OVERSPEED TEST

R R W W

8 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R W W 4

9

PERFORMANCE TEST OF ASSEMBLED UNIT (Power, capacity,

head check, bearing temp. check, vibration, corrected curve

check by speed&specific gravity, sound level test, inspection

of hydrodynamic bearing after test)

R R W H

10 MECHANICAL RUNNING TEST FOR 4 H (IF REQUIRED) R R W H 3

11 POST INSPECTION AFTER TEST RUN (OPTIONAL) R R W W 2

12 LUBE OIL/GAUGE BOARD R R SW SW

13 COMBINED JOB DRIVER & FULL LOAD TEST (IF REQUIRED) R R W H

14 GEAR TEST (IF REQUIRED) R R W W

15 DYNAMIC BALANCE TEST FOR SPARE ROTOR (OPTIONAL) R R W W

16 SPARE ROTOR MECHANICAL TEST R R W W

17 OVERSPEED TEST FOR SPARE ROTOR R R W W

18

VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) INCLUDING SEAL FLUSHING/COOLING SYSTEM AND

SKID ASSEMBLY

R R W H

19 NAME PLATE DATA CHECK R W W W

20 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R W W

Page 32: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 32 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

21 MANUFATURER’S DATA BOOK R R W/R W/R

22 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R R W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. THE WITNESS TEST SHALL BE CARRIED OUT FOR ALL COMPRESSORS AT THE SHOP.

3. EACH COMPRESSOR TYPE SHALL BE CARRIED OUT A PERFORMANCE TEST AT THE SHOP, BUT FOR IDENTICAL ONES, THE WITNESS IS TO BE PERFORMED ONE (1) SET FOR EACH TYPE

4. ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS PER “ITP TESTED AS PER “ITP “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

Page 33: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 33 OF 103

R 01

6.16 RECIPROCATING COMPRESSOR

COMMODITY: RECIPROCATING COMPRESSOR (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2

MATERIAL CERTIFICATES (CRANKCASE, DISTANCE PIECE(S),

CYLINDER(S), CRANKSHAFT, PISTONS, CNNECTIN ROODS,

PISTON ROD, CROSS HEAD, HEAD X PIN, BOLTING)

R R R R

3 CHECK OF WELDING BOOK R R R R

4 NDE(S) (to be defined in ITP) on CONNECTING RODS,

CYLINDERS, CRANKCASE,CRANKSHAFT R R W W

5 RT OF BUTT JOINTS (GAS PIPING) R R W W FILM

REVIEW

6 UT OF CRANK SHAFT, PISTONS&PISTON ROD R R W W

7 HARDNESS TEST FOR WELD (WHERE REQUESTED) AND DE-

BOUNDING TEST ON HARDENED SURFACES OF PISTON RODS R R W W

8 HYDROSTATIC TEST CYLINDERS AND PRESSURE CONTAINING

PARTS. R R W H

9 HELIUM, PRESSURE TEST OF CYLINDERS (IF REQUIRED) R R W H

10 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R W W 3

11 BAR OVER TETS INCLUDING VERTICAL AND HORIZONTAL

PISTON RUN OUT R R W W

12 VOLUME CLEARANCE CHECK R R W W

13 VALVE LEAKAGE TEST R R W W

14

MECHANICAL RUNNING TEST FOR (4 hrs. min.) WITH JOB

LUBE OIL AND COOLING WATER UNIT. Strip down after test

with pistons/bearings/crank-bearings/big-end bearing check

Measurement of RPM,VIBRATION SOUND NOISE LEVEL, LUBE

OIL TEMP. PRESSURE AND CLEARANCE

R R W H

15 FIT UP INSPECTION OF PULSATION DEVICES&ASSOCIATED

GAS PIPING R R SW SW

16 LUBE OIL CONSOLE RUN TEST R R W W

17 COOLING WATER CONSOLE RUN TEST R R W W

18 CYLINDER JACKET WATER HYDRO TEST R R W W

19 FUNCTION TEST OF CONTROL SYSTEM R R W W

20 INTEGRATION TEST OF CONTROL SYSTEM R R W W

Page 34: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 34 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

21 COMBINED JOB DRIVER & FULL LOAD TEST/PERFORMANCE

TEST R R W H 2

22

PRESSURE VESSELS, HEAT EXCHANGERS, FILTERS, LUBE OIL,

WATER COOLING UNIT, INTERCONNECTING PIPING,

CONTROL PANNEL A GAUGE BOARD (SEE RELEVANT

PARAGRAPH)

- - - -

23

VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) INCLUDING SEAL FLUSHING/COOLING SYSTEM AND

SKID ASSEMBLY

R R W H

24 NAME PLATE DATA CHECK R R W W

25 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R W W

26 PACKAGE COMPLETION CHECK R W W W

27 MANUFATURER’S DATA BOOK R R R/W R/W

28 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R R W H

LUBE OI L UNIT-See relevant paragraph - - - -

COOLING WATER UNIT -See relevant paragraph - - - -

PRESSURE VESSEL, HEAT EXCHANGER ect-See relevant

paragraph - - - -

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. EACH COMPRESSOR TYPE SHALL BE GIVEN A PERFORMANCEL RUN TEST AT THE SHOP, BUT FOR IDENTICAL ONES, THE WITNESS IS TO BE PERFORMED ONE (1) SET FOR EACH TYPE

3. ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS PER “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

6.17 AIR COMPRESSOR

COMMODITY: AIR COMPRESSOR (NOTE 1)

Page 35: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 35 OF 103

R 01

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES (casing shaft ect.) R R R R

3 CHECK OF WELDING BOOK R R R R

4 NDE OF CASING (IF REQUIERED) R R SW W

5

UT ON SHAFT after RAW MACHINING, PT ON FINISHED

SHAFT. MT or PT on WELDED PART (Impeller or casing) UT/PT

on FORGED IMPELLER, BULL GEAR,

R R W W

6 HYDROSTATIC TEST (CASING AND PRESSURE CONTAINING

PARTS) R R W H

7 BALANCING OF IMPELLERS AND/OR ROTORS R R W H

8 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R W W 4

9

MECHANICAL RUNNING TEST FOR (4 hrs. min.)

Measurement of RPM,VIBRATION SOUND NOISE LEVEL, LUBE

OIL TEMP. PRESSURE AND CLEARANCE

R R W H 2

10 MECHANICAL RUNNING TEST FOR SPARE STAGES (IF

REQUIRED) R R W W

11

PERFORMANCE TEST (IF REQUIRED)

-RPM CHECK /POWER CHECK

-CAP.PRESS SORGE POIT CHECK

-LUBE OIL TEMP/PRESS BEARING TEMP. CHECK

-CORRECTED CURVE CHECK

R R W H 3

12 COMPLETE UNIT TEST WITH NO LOAD (IF REQUIRED) R R W W

13 BEARING AND SEAL CHECK AFTER TEST RUN (IF REQUIRED) R R W W

14 NAME PLATE DATA CHECK R R W W

15 SPECIAL TOOL CHECK R R SW SW

16 CLEANLINESS CHECK R R W W

17

AUXILIARY EQUIPMENT

-OIL PUMPS, OIL FILTER, OIL COOLER, SEAL OIL TRAP,

ACCUMULATOR

R R W W

18 CONTROL PANEL FUNTIONAL TEST R R W W

19 INTEGRATION TEST OF CONTROL SYSTEM ALONG WITH PCS R R W W

20 VISUAL & DIMENSIONAL CHECK OF COMPLETE ASSEMBLY

(with P&ID check and marking) R W W W

21 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

22 PACKAGE COMPLETION CHECK R W W W

Page 36: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 36 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

23 MANUFATURER’S DATA BOOK R R R/W R/W

24 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. ALL COMPRESSORS SHALL BE PERFORMED A MECHANICAL RUN TEST BY VENDOR AT THE SHOP, THE WITNESS IS TO BE CONDUCTED ALL OVER COMPRESSORS.

3 EACH COMPRESSOR TYPE SHALL BE GIVEN A PERFORMANCE TEST AT THE SHOP, BUT FOR IDENTICAL ONES, THE WITNESS IS TO BE PER SET EACH TYPE.

4 ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

Page 37: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 37 OF 103

R 01

6.18 FAN AND BLOWER

COMMODITY: FAN AND BLOWER (NOTE 1 & 2)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES (Casing, impeller, shaft) R R R R

3 CHECK OF WELDING BOOK R R R R

4 UT ON SHAFT after RAW MACHINING, PT ON FINISHED SHAFT R R W W

5 MT or PT on welded part (IMPELLER , SASING) R R SW W

6 HYDROSTATIC TEST or LEAKAGE TEST AS APPLICABLE

(CASING AND PRESSURE CONTAINING PARTS) R R W H

7 BALANCING OF IMPELLER AND/OR ROTOR. R R W H

8 ROUTINE/TYPE TEST FOR MV OR HV ELECTRIC MOTORS R R W W

9

MECHANICAL RUNNING/PERFORMANCE TEST OF ASSEMBLED

UNIT (Power, capacity, head check, bearing temp. check,

vibration, corrected curve check by speed&specific gravity,

sound level test, inspection of hydrodynamic bearing after

test)

R R W H

10

VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) INCLUDING SEAL FLUSHING/COOLING SYSTEM AND

SKID ASSEMBLY

R W W W

11 NAME PLATE DATA CHECK R W W W

12 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

13 MANUFATURER’S DATA BOOK R R R/W R/W

14 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

2. EACH FAN&BLOWER SHALL BE GIVEN A MECHANICAL RUN&PERFORMANCE TEST AT THE SHOP, BUT FOR IDENTICAL ONES THE WITNESS IS TO BE PERFORMED ONE (1) SET DESIGNATE BY INSPECTOR

3. ELECTRICAL MOTOR DRIVERS SHALL BE TESTED AS PER “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

Page 38: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 38 OF 103

R 01

6.19 GAS TURBINE

COMMODITY: GAS TURBINE (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2

MATERIAL CERTIFICATES for main components (casing, inlet

valve casing, shaft, blades, wheels, exhaust casing, bolting,

diaphragms, bearing housing etc.)

R R R R

3 CHECK OF WELDING BOOK R R R R

4

RT or UT (as appl.) ON CASING, NOZZLES AND CRITICAL

AREAS. RT/UT ON WELDS CASING AND CASING TO NOZZLE

WELDS (as applicable)

R R SW SW

5 MT on 100% CASING AS RAW AND DIAPHRAMS AS RAW R R SW SW

6 PT ON 100% MACHINED PARTS OF CASING R R SW SW

7 UT ON SHAFTS AS RAW MATERIAL.PT ON FINISHED SHAFT R R R SW

8 HEAT STABILITY TEST R R SW SW

9 MT ON BLADES. MT ON WHEELS (as applicable) R R SW SW

10 MT ON 100% WELDS OF EXHAUST CASING (LP CASING) R R SW SW

11 HYDROSTATIC PRESSURE TEST ON HP, MP, & LP CASING R R W H

12 UT ON 100% OF BOLTING. R R SW SW

13 ROTOR BALANCING TEST (LOW SPEED AND HIGH SPEED) R R W W

14 SPIN TEST OF ROTOR (OVER SPEED) R R W W

15 MECHANICAL AND ELECTRICAL RUN OUT OF ROTOR R R W W

16 UT ON WHITEMETAL OF BABBITED BEARINGS R R SW SW

17 MECHANICAL RUNNING TETS OF BARE SHAFT TURBINE R R W H

18 PERFORMANCE TEST (IF APPLICABLE) R R W H

19 BEARING INSPECTION AFTER MTor PT ON SURFACE OF

WHITEMETAL OF BABBITED BEARINGS R R SW W

20 LUBE OIL UNIT /GAUGE BOARD –-See relevant paragraph - - - -

21 INTEGRATION TEST OF CONTROL SYSTEM ALONG WITH PCS R R W W

22 CONTROL PANEL FUNCTIONAL TEST R R W W

Page 39: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 39 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

23 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R W W

24 VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) SKID ASSEMBLY. SUPPLY COMPLEATION CHECK R W W W

25 NAME PLATE DATA CHECK R W W W

26 MANUFATURER’S DATA BOOK R R R/W R/W

27 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 40: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 40 OF 103

R 01

6.20 STEAM TURBINE

COMMODITY: STEAM TURBINE (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2

MATERIAL CERTIFICATES for main components (casing, inlet

valve casing, shaft, blades, wheels, steam valves, exhaust

casing, bolting, diaphragms, bearing housing etc.)

R R R R

3 CHECK OF WELDING BOOK R R R R

4

RT or UT (as appl.) ON CASING, NOZZLES AND CRITICAL

AREAS. RT/UT ON WELDS CASING AND CASING TO NOZZLE

WELDS (as applicable)

R R SW SW

5 MT on 100% CASING AS RAW AND DIAPHRAMS AS RAW R R SW SW

6 PT ON 100% MACHINED PARTS OF CASING R R SW SW

7 UT ON SHAFTS AS RAW MATERIAL.PT ON FINISHED SHAFT R R SW SW

8 HEAT STABILITY TEST R R SW SW

9 MT BLADES. MT ON WHEELS (as applicable) R R SW SW

10 MT ON 100% WELDS OF EXHAUST CASING (LP CASING) R R SW W

11 HYDROSTATIC PRESSURE TEST ON HP, MP, & LP CASING R R W H

12 UT ON 100% OF BOLTING. UT&PT on 100% steam VALVES

STELLITE OVERLAY R R SW SW

13 HYDROSATIC PRESSURE TEST OF STEAM CHEST CASING AND

STEAM PIPE. R R SW SW

14 ROTOR BALANCING TEST (LOW SPEED AND HIGH SPEED) R R W W

15 SPIN TEST OF ROTOR (OVER SPEED) R R W W

16 MECHANICAL AND ELECTRICAL RUN OUT OF ROTOR R R W W

17 UT ON WHITEMETAL OF BABBITED BEARINGS R R SW SW

18 MECHANICAL RUNNING TEST OF BARE SHAFT TURBINE R R W H

19 PERFORMANCE TEST (IF APPLICABLE) R R W H

20 GOVERNOR FUNCTIONAL TEST (if required) R R W W

21 BEARING INSPECTION AFTER MRT. PT ON SURFACE OF

WHITEMETAL OF BABBITED BEARINGS R R SW SW

22 LUBE OIL UNIT /GAUGE BOARD – See relevant paragraph - - - -

Page 41: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 41 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

23 INTEGRATION TEST OF CONTROL SYSTEM ALONG WITH PCS R R W W

24 CONTROL PANEL FUNCTIONAL TEST R R SW W

25 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

26 VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) SKID ASSEMBLY. SUPPLY COMPLEATION CHECK R W W W

27 NAME PLATE DATA CHECK R W W W

28 MANUFATURER’S DATA BOOK R R R/W R/W

29 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

.

Page 42: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 42 OF 103

R 01

6.21 LUBE OIL UNIT

COMMODITY: LUBE OIL UNIT (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

OIL PUMPS

2 MATERIAL TEST CERTIFICATES REVIEW (CASING, COVER,

IMPELLER, ROTOR, SHAFT) R R R R

3 HYDROSTATIC TEST OF CASING ANC COVER R R R W

4 PERFORMANCE TEST R R SW W

ELECTRIC MOTOR

5 MATERIAL TEST CERTIFICATES REVIEW (ROTOR, SHAFT) R R R R

6 TYPE TEST CERTIFICATES R R R R

7 ROUTINE TEST CERTIFICATE R R R W

8 ATEX CERTIFICATE R R R R

OIL TWIN FILTER

9 MATERIAL TEST CERTIFICATES REVIEW (ROTOR, SHAFT) R R R R

10 RWVIEW OF WELDING BOOK R R R R

11 NDE (IF REQUIRED) R R SW W

12 HYDROSTATIC TEST R R SW SW

13 HEAT EXCHANGER (SEE RELEVAT PARAGRAPH) - - - -

OIL TANK

14 MATERIAL TEST CERTIFICATES REVIEW FOR MAIN MATERIAL R R R R

15 LEAKAGE TEST R R SW SW

SAVETY VALVES AND INSTRUMENTATION

16 -SEE RELEVAN PARAGHAPH - - - -

ASSEMBLED UNIT

17 FUNCTIONAL TEST AS PER API 614 R R SW W

18 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

Page 43: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 43 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

19 VISUAL & DIMENSIONAL CHECK (with P&ID check and

marking) SKID ASSEMBLY. SUPPLY COMPLEATION CHECK R W W H

20 NAME PLATE DATA CHECK R W W W

21 MANUFATURER’S DATA BOOK R R R/W R/W

22 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 44: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 44 OF 103

R 01

6.22 FILTERS

COMMODITY: FILTERS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES R R R R

3 MAIN MATERIAL INDENTIFICATION (Plates, nozzles, forgings,

flanges, consumables) /Material certificates check and review R R SW W

4 TRANSFER OF MATERIAL IDENTIFICATION R R SW SW

5 WELDING PROCEDURE QUALIFICATION TEST R R R R

6 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

7 FOUNDATION RING TEMPLATE (Visual and dimensional check ) R R SW SW

8 FIT-UP INSPECTION R R R R

9 PRODUCTION WELD TEST (IF REQUIRED) R R R SW

10 CLAD PLATE / OVERLAY WELD (IF REQUIRED R R SW SW

11 FERRITE CHECK OF WELD AND WELD OVERLAY (IF REQUIRED) R R SW SW

12 HARDNESS TEST (IF APPLICABLE) R R SW SW

13 LIQUID PENETRANT EXAMINATION AND/OR MAGNETIC

PARTICLE EXAMINATION (IF REQUIRED) R R SW SW

14 ULTRASONIC EXAMINATION (IF REQUIRED) R R SW SW

15 RADIOGRAPHIC EXAMINATION (IF REQUIRED) R R R R FILM

REVIEW

16 POST WELD HEAT TREATMENT (IF REQUIRED) R R R SW

17 POSITIVE MATERIAL IDENTIFICATION (PMI)(IF APPLICABLE) R R SW SW

18 FERROXYL TEST (IF APPLICABLE) R R SW SW

DIMENSIONAL CHECK AND VISUAL INSPECTION

19 VISUAL&DIMENSIONAL CHECK OF HEADS AFTER FORMING R R R SW

20 OUT-OF ROUGNDNESS AND STRAIGHTNESS R R R R

21 NOZZLE ORIENTATION AND PROJECTION R R SW SW

22 RATING, FACE TYPE, SIZE AND MARKING OF FLANGES R R SW SW

Page 45: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 45 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

23 INTERNAL RING ELEVATION AND LEVEL R R SW SW

24 OVERALL DIMENSION R R SW W

25 NAME PLATE R R W W

26 TRAY AND INTERNAL DEVICE R R SW W

27 GASKETS AND BOLTS R R SW SW

28 AIR LEAK TEST OF REINFORCING PAD R R SW SW

29 HYDROSTATIC TEST R R W H

30 DRAINING, DRYING, CLEALINESS CHECK (INTERNAL) R R W H

31 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

32 SPARE PART CHECK R R SW W

33 MANUFATURER’S DATA BOOK R R R/W R/W

34 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION, N2 FILLING etc.) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 46: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 46 OF 103

R 01

6.23 AGITATOR

COMMODITY: AGITATOR (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2

MAIN MATERIAL INDENTIFICATION (driver shaft, impeller,

blades, gear or gear reducer, flanges, consumables) /Material

certificates check and review

R R SW W

3 WELDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER'S/OPERATOR'S PERFORMANCE QUALIFICATION TEST R R R R

5 HARDNESS TEST (IF APPLICABLE) R R SW SW

6 UT ON SHAFT AND PT /MT ON MACHINED SURFACES R R R SW

7 POST WELD HEAT TREATMENT (IF REQUIRED) R R R R

8 NDE EXAMINATION (IF REQUIRED) R R SW SW

9 POSITIVE MATERIAL IDENTIFICATION (PMI)(IF APPLICABLE) R R SW SW

10 FERROXYL TEST (IF APPLICABLE) R R SW SW

11

MECHANICAL RUN TEST (in water or AIR as per data sheet)

-vibration and noise level check

-RPM check

-Bearing temperature check

R R W H

12 FINAL VISUAL&DIMENSIONAL CHECK R SW W W

13 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

14 SPARE PART CHECK R R SW SW

15 MOTOR AND GEAR REDUCER TEST RECORDS. R R R R

16 MANUFATURER’S DATA BOOK R R R/W R/W

17 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

6.24 ELECTRIC HOIST

Page 47: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 47 OF 103

R 01

COMMODITY: ELECTRIC HOIST (NOTE 1 & 2)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

3 MATERIAL CERTIFICATES (girder, hook, wire ect) REVIEW AND

MAIN MATERIAL IDENTIFICATION R R SW W

4 NDE EXAMINATION (IF REQUIRED) R R SW SW

5

MECHANICAL/FUNCTIONAL TEST

-LOAD TEST

-BREAK TEST

-OPERATION TEST

R R W H

6 FINAL VISUAL&DIMENSIONAL CHECK R R W W

7 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

8 SPARE PART CHECK R R SW SW

9 MOTOR AND GEAR REDUCER TEST RECORDS. R R R R

10 MANUFATURER’S DATA BOOK R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

2. EACH HOIST SHALL BE GIVEN A MECHANICAL RUN & LOAD TEST AT THE SHOP, BUT FOR IDENTICAL ONE, THE WITNESS IS TO BE PERFORMED ONE (1) SET DESIGNATED BY INSPECTOR.

Page 48: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 48 OF 103

R 01

6.25 CRANE

COMMODITY: CRANE (NOTE 1,2,3)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

3 MATERIAL CERTIFICATES (girder, crab, hook, wire ect)

REVIEW AND MAIN MATERIAL IDENTIFICATION R R SW W

4 WENDING PROCEDURE QUALIFICATION TEST R R R R

5 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

6 NDE EXAMINATION (IF REQUIRED) R R SW SW

7

MECHANICAL/FUNCTIONAL TEST

-LOAD TEST

-BREAK TEST

-OPERATION TEST

R R W H

8 FINAL VISUAL&DIMENSIONAL CHECK R R W H

9 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

10 SPARE PART CHECK R R SW SW

11 MOTOR TEST RECORDS. R R R R

12 MANUFATURER’S DATA BOOK R R R/W R/W

13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

2. EACH HOIST SHALL BE GIVEN A MECHANICAL RUN & LOAD TEST AT THE SHOP, BUT FOR IDENTICAL ONE, THE WITNESS IS TO BE PERFORMED ONE (1) SET DESIGNATED BY INSPECTOR.

3. ELECTRICAL MOTORS SHALL BE TESTED PER “ITP INDUCTION MOTOR (LV& MV)” PARA 6.50.

Page 49: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 49 OF 103

R 01

6.26 SILENCER

COMMODITY: SILENCER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R SW W

2 WENDING PROCEDURE QUALIFICATION TEST R R R R

3 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

4 NDE EXAMINATION (IF REQUIRED) R R SW SW

5 OUTLINE VISUAL&DIMENSIONAL CHECK R R SW W

6 HYDROSTATIC TEST R R W H

7 PMI, FERROXYL test (IF specified in data sheet) R R SW SW

8 FINAL VISUAL&DIMENSIONAL CHECK R R SW W

9 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

10 MANUFATURER’S DATA BOOK R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 50: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 50 OF 103

R 01

6.27 IN-LINE STATIC MIXER

COMMODITY: IN-LINE STATIC MIXER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW (Boby , mixing element ect.) R R R R

2 WENDING PROCEDURE QUALIFICATION TEST R R R R

3 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

4 NDE EXAMINATION (IF REQUIRED) R R R SW

5 OUTLINE VISUAL&DIMENSIONAL CHECK W R SW W

6 HYDROSTATIC TEST R R W H

7 PMI, FERROXYL test (IF specified in data sheet) R R SW SW

8 FINAL VISUAL&DIMENSIONAL CHECK W R SW W

9 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

10 MANUFATURER’S DATA BOOK W/R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) W W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 51: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 51 OF 103

R 01

6.28 FIRED HEATER

COMMODITY: FIRED HEATER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

PRESSURE PARTS (COILS AND RETURN BEND)

2 MATERIAL CERTIFICATES REVIEW AND MAIN MATERIAL

IDENTIFICATION R R W W

3 WENDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

5 FIT-UP INSPECTION R R SW SW

6 NDE EXAMINATION R R SW SW

7 POST WELD HEAT TREATMENT R R R SW

8 HARDNESS TEST R R SW SW

9 VISUAL&DIMENSIONAL CHECK R R SW SW

10 HYDROSTATIC TEST R R W H

11 PMI, FERROXYL test (IF specified in data sheet) R R SW SW

HEATER CASING&STRUCTURE INCLUDING AIR.DUCT

12 MATERIAL CERTIFICATES AND MAIN MATERIAL

IDENTIFICATION R R SW SW

13 NDE EXAMINATION R R SW SW

14 VISUAL AND DIMENSIONAL CHECK R R SW W

15 TRIAL ASSEMBLY (IF REQUIRED) R R SW W

16 SHOP APPLIED CASTABLE REFRACTORY

17 REFRACTORY MATERIAL CERTIFICATES R R R R

18 VISUAL INSPECTION AFTER APPLICATION R R SW SW

18 HAMMERING TEST R R SW SW

20 CURING TEST RECORDS R R R R

Page 52: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 52 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

BURNERS

21 FIRING TEST (IF REQUIRED) R R SW W

22 VISUAL AND DIMENSIONAL INSPECTION R R W W

SOOT BLOWER

23 FUNCTIONAL TEST R R SW SW

DAMPER

24 OPERATION TEST R R SW SW

AIR PRE-HEATER

25 AIR LEAK TEST R R SW SW

CONTROL PANEL

26 LOGIC TEST (SEQUENCE TEST) R R SW SW

27 CONTROL SYSTEM R R SW SW

28 FUNCTIONAL AND PERFORMANCE TEST (INCLUDING BMS) AT

SITE R R W W

CAST TUBE SUPPORT

29 MATERIAL CERTIFICATES R R R R

30 DIMENSIONAL AND VISUAL CHECK R R SW SW

COMPLETE PACKAGE

31 FINAL VISUAL&DIMENSIONAL CHECK R R W W

32 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

33 MANUFATURER’S DATA BOOK R R R/W R/W

34 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 53: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 53 OF 103

R 01

6.29 FLARE STACK

COMMODITY: FLARE STACK (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW(plates, forgings, flanges,

flare tip, burners, ect ) AND MATERIAL IDENTIFICATION R R SW W

3 WENDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

STACK RISERS

5 FIT-UP INSPECTION R R SW SW

6 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

7 POST WELD HEAT TREATMENT R R R SW

8 NDE EXAMINATION (TO BE DETTAILED IN THE ITP) R R SW SW

9 TRIAL ASSEMBLY INSPECTION R R SW SW

GUY ROPES WITH PLATFORM AND LADDERS

10 MATERIAL TEST CERTIFICATES REVIEW R R R R

11 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

12 NDE EXAMINATION (TO BE DETTAILED IN THE ITP) R R SW SW

13 TRIAL ASSEMBLING (IF REQUIRED) R R SW SW

UTILITY AND HEADER PIPING

14 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

15 NDE EXAMINATION (TO BE DETTAILED IN THE ITP) R R SW SW

16 HYDROSTATIC TEST (IF REQUIRED) R R W H

FLAME FRONT GENERATOR PANEL

17 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

ELECTRICAL AND INSTRUMENTATION

18 CERTIFICATION REVIEW (INCLUDING CALIBRATION AND EX

CERTICATES) R R R R

Page 54: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 54 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

COMPLETE PACKAGE

19 PMI, FERROXYL test (IF specified in data sheet) R R SW SW

20 FINAL VISUAL&DIMENSIONAL CHECK R SW W W

21 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

22 MANUFATURER’S DATA BOOK R R R/W R/W

23 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

KO DRUM /pressure vessel

24 see relevant ITP for for pressure vessel - - - -

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 55: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 55 OF 103

R 01

6.30 AUXILIARY BURNER

COMMODITY: AUXILIARY BURNER (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R R R

2 FINAL VISUAL&DIMENSIONAL CHECK R R SW W

3 FUNCTIONAL TEST R R W H

4 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

5 MANUFATURER’S DATA BOOK R R R/W R/W

6 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 56: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 56 OF 103

R 01

6.31 PACKAGED BOILER

COMMODITY: PACKAGED BOILER (NOTEs 1-2-3-4-5-6-7)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

PRESSURE PARTS (STEAM DRUM)

2 MATERIAL IDENTIFICATION &TEST CERTIFICATES REVIEW

(plates, tube, pipe, forgings, welding consumable) R R W W

3 WENDING PROCEDURE QUALIFICATION TEST R R R R

4 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

5 FIT-UP INSPECTION R R SW SW 1

6 DISH HEADS INSPECTION R R SW SW 2

7 VISUAL AND IMENSINAL CHECK OF WELDS R R SW SW

8 PIPE TO STEAM DRUM (Check of expanding &/or welds) R R SW SW

9 NDE EXAMINATION R R SW SW 3-7

10 POST WELD HEAT TREATMENT R R R SW 4

11 HARDNESS TEST R R SW SW 5

12 VISUAL&DIMENSIONAL CHECK R R W W 6

13 HYDROSTATIC TEST R R W H

14 PMI, FERROXYL test (IF specified in data sheet) R R W W

BOILER WALLS

15 PRESSURE PARTS-Material identification/certification review R R SW SW

16 PIPE FINNING R R R SW

17 NDE (PT) on pipe welds R R SW SW 7

18 CHECK OF MARKING R R SW SW

BOILER CASING

19 MATERIAL IDENTIFICATION /CERTIFICATION REVIEW R R SW SW

20 NDE EXAMINATION R R SW SW 7

Page 57: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 57 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

21 VISUAL AND DIMENSIONAL CHECK R R SW SW

22 TRIAL ASSEMBLY (IF REQUIRED) R R SW W

STEEL STRUCTURES

23 DIMENSIONAL AND VISUAL INSPECTION R R SW SW

24 NDE EXAMINATION R R SW SW 7

25 TRIAL FIT-UP INSPECTION (on random basis) R R SW W

SHOP APPLIED CASTABLE REFRACTORY

26 REFRACTORY MATERIAL CERTIFICATES R R R R

27 VISUAL INSPECTION AFTER APPLICATION R R SW SW

28 HAMMERING TEST R R SW W

29 CURING TEST RECORDS R R R R

BURNERS

20 FIRING TEST (IF REQUIRED) R R SW W

21 DIMENSIONAL CHECK R R W W

22 VISUAL INSPECTION R R W W

CAST TUBE SUPPORT

23

24 MATERIAL CERTIFICATES R R R R

25 DIMENSIONAL AND VISUAL CHECK R R SW SW

AUXILIARIES

26 FD/ID FAN R R W W

27 ELECTRICAL MOTORS R R W W

28 AIR PRE HEATERS R R W W

29 VALVES R R SW W

30 PIPING R R SW W

31 ELECTICAL AND INSTRUMENTATION R R W W

32 PEFORMANCE/MECHANICAL RUNNING TEST OF FANS AND

BLOWER R R W H

33 CONTROL SYSTEM (EXCLUDING BMS) PERFORMANCE AND FUNCTION TEST OF ELECTRICAL & INSTRUMENTATION EQUIPMENT

R R SW W

Page 58: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 58 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

STACK

34 MATERIAL TEST CERTIFICATES REVIEW&MATERIAL

IDENTIFICATION R R SW SW

35 WENDING PROCEDURE QUALIFICATION TEST R R R R

36 WELDER OPERATOR’S PERFORMANCE QUALIFICATION TEST R R R R

37 VISUAL AND DIMENSIONAL CHECK OF WELDS R R SW SW

38 FOUNDATION TEMPLATE VISUAL AND DIMENSIONAL CHECK R R SW SW

39 NDE EXAMINATION R R SW SW 7

40 POST WELD HEAT TREATMENT R R R SW

41 VISUAL&DIMENSIONAL CHECK R R W W

42 TRIAL ASSEMBLY R R W W

43 PLATFORM AND LADDERS TRIAL FIT UP R R W W

REFRACTORY

44 MATERIAL VERIFICATION R R R R

45 ANCHOR WELDING CHECK (Hammer test e Bend Test) R R R SW

46 INSTALLATION CHECK (if applicable) R R SW W

47 DIMENSIONAL CHECK AND VISUAL INSPECTION R R W W

GENERAL (Valid for packaged Boiler)

48 VISUAL&DIMENSIONAL CHECK (with P&ID check and

marking), supply completion check R R W W

49 PMI, FERROXYL test (IF specified in data sheet) R R SW SW

50 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

51 MANUFATURER’S DATA BOOK R R R/W R/W

52 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE (1) : at least n.1 fit-up for every main weld joint shall be monitored by Contractor. NOTE (2) : Receiving inspection of Dish Heads shall be included in case of dish heads are at sub- vendor scope. NOTE (3) : All coil welds in contact with the Flue Gases or Stainless Steel, Low Allow steel material shall be 100% x-ray

tested. NOTE (4) : Contractor inspector shall witness the furnace preparation check and take sign of the PWHT after start of the

operation and make the review of PWHT chart at its completion. NOTE (5) : Hardness test after PWHT shall be performed on weld metal and Heat Affected Zone (HAZ).

Page 59: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 59 OF 103

R 01

NOTE (6) : internal inspection included. NOTE (7) : NDE extension is given by the Technical Specification / contract Specification/Applicable codes

6.32 CHEMICAL INJECTION & DOSING PACKAGE / ELECTROCHLORINATION PACKAGE

COMMODITY: CHEMICAL INJECTION & DOSING PACKAGE / ELECTROCHLORINATION PACKAGE (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW &MAIN MATERIAL

IDENTIFICATION R R SW W

3

HYDROSTATIC TEST

-Vessel

-Heat Exchanger

-Pump Casing ect

R R W H

4 WATER FILLING TEST FOR STORAGE&DOSSING TANK R R W H

5 OUTLINE DIMENSIONAL AND VISUAL INSPECTION R R W W

6 MOTOR TEST RECORDS (NO LOAD TEST) R R R R

7 INSPECTION AND TEST RECORDS OF PRESSURE VESSEL AND

HEAT EXCHANGER R R R R

AGITATOR/PUMPS/FAN

8

-Balance Test

-No load mechanical running test

R R SW SW

9 VISUAL AND DIMENSIONAL INSPECTION OF SKID

ASSEMBLING AND LOOSE PART R SW W W

10 SPARE PARTS CHECK R R SW SW

11 TEST RECORDS OF AUXILIARY EQUIPMENT& INSTRUMENTS R R R R

12 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

13 MANUFATURER’S DATA BOOK R R R/W R/W

14 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 60: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 60 OF 103

R 01

6.33 REFRIGERANT UNIT

COMMODITY: REFRIGERANT UNIT (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW&MAIN MATERIAL

IDENTIFICATION R R SW W

3 WELDERS/WELDING OPERATOR’S PERFORMANCE

QUALIFICATION TEST R R R R

4 WPS/PQR R R R R

5 NON DISTRUCTIVE EXAMINATION (IF REQUIRED) R R SW SW

6 PMI (IF REQUIRED) R R SW SW

COMPRESSOR

7 OIL PIPING SYSTEM LEAK TEST R R SW SW

8 DYNAMIC BALANCING TEST RECORD FOR ROTOR R R R R

9 MECHANICAL RUNNING TEST R R W H

10 VIBRATION CHECK R R SW W

11 CLEANING INSPECTION R R W W

PRESSURE VESSEL AND HEAT EXCHANGER

12 INSPECTION AND TEST RECORD R R R R

13 CLEANLINESS CHECK R R SW W

COMPLETE PACKAGE

14 FUNCTIONAL TEST OF SYSTEM (IF APPLICABLE) R R W W

15 MOTOR NO LOAD TEST CERTIFICATE R R R R

16 PIPING – NDE EXAMINATION R R SW SW

17

INSTRUMENT AND CONTROL PANEL

-FUNCTIONAL TEST

-CALIBRATION TEST

R R SW SW

18 VISUAL AND DIMENSIONAL INSPECTION OF SKID

ASSEMBLING AND LOOSE PART R R W W

Page 61: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 61 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

19 SPARE PARTS CHECK R R SW SW

20 TEST RECORDS OF AUXILIARY EQUIPMENT& INSTRUMENTS R R R R

21 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW SW

22 MANUFATURER’S DATA BOOK R R R/W R/W

23 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 62: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 62 OF 103

R 01

6.34 DESALINATION PACKAGES

COMMODITY: DESALINATION PACKAGES (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 VESSEL/HEAT EXCHANGER

2.1 MATERIAL TEST CERTIFICATES REVIEW (PLATES, PIPE,

FORGINGS, FLANGES) AND MATERIAL IDENTIFICATION R R SW W

2.2 WELDERS/WELDING OPERATOR’S PERFORMANCE

QUALIFICATION TEST R R R R

2.3 WPS/PQR R R R R

2.3 FORMED HEADS NDE TEST REPORT REVIEW R R R R

2.4 FORMED HEADS VISUAL AND DIMENSIONAL CHECK R R SW SW

2.5 RT for all butt welds R R R R FIL

REVIEW

2.6 MT or PT for all welds and temporary welded area after

ground off R R R SW

2.7 PWHT R R R SW

2.8 VISUAL AND DIMENSIONAL CHECK OF COMPLETE VESSEL R R W W

2.9 FLANGES FINISCHING VISUAL AND ROUGNESS CHECK R R SW SW

2.10 HYDROSTATIC PRESSURE TEST R R W H

2.11 DRYING, DRAINING, CLEANING CHECK R R W W

2.12 SURFACE PREPARATION AND COATING INSPECTION R R SW SW

3 STORAGE /MIXING /DOSING TANKS

3.1 MATERIAL TEST CERTIFICATES REVIEW (PLATES, PIPE,

FORGINGS, FLANGES) AND MAIN MATERIAL IDENTIFICATION R R SW SW

3.2 WELDERS/WELDING OPERATOR’S PERFORMANCE

QUALIFICATION TEST R R R R

3.3 WPS/PQR R R R R

3.4 NDE EXAMINATION R R SW SW

3.5 VISUAL AND DIMENSIONAL CHECK OF COMPLETE TANK R R W W

3.6 HYDROSTATIC TEST/WATER FILLING TEST R R W H

Page 63: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 63 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

3.7 PMI (IF REQUIRED) R R SW SW

4 CENTRIFUGAL/RECIPROCATING PUMPS

4.1 MATERIAL CERTIFICATES CHECK R R R R

4.2 HYDROSTATIC TEST (PRESSURE CONTAINING PARTS) R R SW SW

4.3 MECHANICAL RUNNING/PERFORMANCE TEST R R SW SW

4.4 VISUAL AND DIMENSIONAL CHECK (PUMP+MOTOR) R R SW SW

4.5 PMI (IF REQUIRED) R R SW SW

4.6 FLANGE SURFACE FINISHING/ROUGNESS CHECK R R SW SW

4.7 CHECK OF SPARE PART AND ACCESSORIES R R SW SW

5 MIXER AGITATOR

5.1 MATERIAL TEST CERTIFICATES REVIEW R R R R

5.2 DYNAMIC BALANCE TEST R R R SW

5.3 MECHANICAL RUNNIG TEST R R SW SW

5.4 VISUAL AND DIMENSIONAL CHECK R R W W

5.5 MOTOR TYPE TEST R R R R

6 MOTORS

6.1 VISUAL AND DIMENTSIONAL CHECK R R SW SW

6.2 ROUTINE TEST CERTIFICATES R R R R

6.3 TYPE TEST CERTIFICATES R R R R

6.4 MARKING CHECK R R SW W

7 INSTRUMENTATION

7.1 PANELS

(Dimension, functional test ) R R SW W

7.2

FIELD INSTRUMENT INCLUDING CONTROL AND SHUTT-OFF

VALVES.

(Material certificates, calibration certificates, hydro test,

functional test )

R R SW SW

7.3 SAFETY RELIEF VALVES

(Material test certificates, hydrostatic test reports,) R R SW SW

8 PIPING

8.1 MATERIAL CERTIFICATES REVIEW R R R R

8.2 VISUAL AND DIMENSIONAL CHECK R R SW SW

Page 64: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 64 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

8.3 NDE OF WELDING R R SW SW

8.4 HYDROSTATIC PRESSURE TEST R R SW W

9 GENERAL (COMPLETE SKYD)

9.1 VISUAL&DIMENSIONAL CHECK (with P&ID check e marking),

supply completion check R R W W

9.2 TIE IN VISUAL AND DIMENSIONAL CHECK R R W W

9.3 SUPPLY COMPLETION CHECK AND FAT TEST R R W H

9.4 ELECTRICAL CABLING CONTINUITY CHECK R R SW W

9.5 TUBING ROUTING CHECK R R SW W

9.6 LEAK TEST OF TUBING AND PIPING R R SW SW

9.7 TAGGING AND MARKING CHECK R R SW SW

9.8 MT ON LIFTING LUGS R R SW SW

9.9 NDE ON STEEL STRUCTURE R R SW SW

9.10 SPARE PARTS CHECK R R SW SW

9.11 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

9.12 MANUFATURER’S DATA BOOK R R R/W R/W

9.13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 65: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 65 OF 103

R 01

6.35 WATER POLISHING / REMINERALIZATION AND POTABLE WATER PACKAGE

COMMODITY: WATER POLISHING / REMINERALIZATION AND POTABLE WATER PACKAG E (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 VESSEL/HEAT EXCHANGER

2.1 MATERIAL TEST CERTIFICATES REVIEW (PLATES, PIPE,

FORGINGS, FLANGES) AND MATERIAL IDENTIFICATION R R SW W

2.2 WELDERS/WELDING OPERATOR’S PERFORMANCE

QUALIFICATION TEST R R R R

2.3 WPS/PQR R R R R

2.3 FORMED HEADS NDE TEST REPORT REVIEW R R R R

2.4 FORMED HEADS VISUAL AND DIMENSIONAL CHECK R R SW SW

2.5 RT for all butt welds R R R R FILM

REVIEW

2.6 MT or PT for all welds and temporary welded area after

ground off R R R SW

2.7 PWHT R R R R

2.8 VISUAL AND DIMENSIONAL CHECK OF COMPLETE VESSEL R R W W

2.9 FLANGES FINISCHING VISUAL AND ROUGNESS CHECK R R SW SW

2.10 HYDROSTATIC PRESSURE TEST R R W H

2.11 DRYING, DRAINING, CLEANING CHECK R R W W

2.12 SURFACE PREPARATION AND COATING INSPECTION R R SW SW

3 STORAGE /MIXING /DOSING TANKS

3.1 MATERIAL TEST CERTIFICATES REVIEW (PLATES, PIPE,

FORGINGS, FLANGES) AND MAIN MATERIAL IDENTIFICATION R R SW SW

3.2 WELDERS/WELDING OPERATOR’S PERFORMANCE

QUALIFICATION TEST R R R R

3.3 WPS/PQR R R R R

3.4 NDE EXAMINATION R R SW SW

3.5 VISUAL AND DIMENSIONAL CHECK OF COMPLETE TANK R R SW W

3.6 HYDROSTATIC TEST/WATER FILLING TEST R R W H

3.7 PMI (IF REQUIRED) R R SW SW

Page 66: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 66 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

4 CENTRIFUGAL/RECIPROCATING PUMPS

4.1 MATERIAL CERTIFICATES CHECK R R R R

4.2 HYDROSTATIC CHECK FOR PRESSURE CONTAINING PARTS R R R SW

4.3 MECHANICAL RUNNING/PERFORMANCE TEST R R R SW

4.4 VISUAL AND DIMENSIONAL CHECK (PUMP+MOTOR) R R SW SW

4.5 PMI (IF REQUIRED) R R SW SW

4.6 FLANGE SURFACE FINISHING/ROUGNESS CHECK R R SW SW

4.7 CHECK OF SPARE PART AND ACCESSORIES R R SW SW

5 MIXER AGITATOR

5.1 MATERIAL TEST CERTIFICATES CHECK R R R R

5.2 DYNAMIC BALANCE TEST R R R SW

5.3 MECHANICAL RUNNIG TEST R R R SW

5.4 VISUAL AND DIMENSIONAL CHECK R R W W

5.5 MOTOR TYPE TEST R R R R

6 MOTORS

6.1 VISUAL AND DIMENTSIONAL CHECK R R SW W

6.2 ROUTINE TEST CERTIFICATES R R R R

6.3 TYPE TEST CERTIFICATES R R R R

6.4 MARKING CHECK R R SW W

7 INSTRUMENTATION

7.1 PANELS

(Dimension, functional test ) R R SW W

7.2

FIELD INSTRUMENT INCLUDING CONTROL AND SHUTT-OFF

VALVES.

(Material certificates, calibration certificates, hydro test,

functional test )

R R SW SW

7.3 SAFETY RELIEF VALVES

(Material test certificates, hydrostatic test reports,) R R SW SW

8 PIPING

8.1 MATERIAL CERTIFICATES REVIEW R R R R

8.2 VISUAL AND DIMENSIONAL CHECK R R SW SW

8.3 NDE OF WELDING R R SW SW

Page 67: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 67 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

8.4 HYDROSTATIC PRESSURE TEST R R SW SW

9 GENERAL (COMPLETE SKYD)

9.1 VISUAL&DIMENSIONAL CHECK (with P&ID check e marking),

supply completion check R R W W

9.2 TIE IN DIMENSIONAL CHECK R R SW W

9.3 SUPPLY COMPLETION CHECK AND FAT TEST R R SW W

9.4 ELECTRICAL CABLING CONTINUITY CHECK R R SW SW

9.5 TUBING ROUTING CHECK R R SW SW

9.6 LEAK TEST OF TUBING AND PIPING R R SW SW

9.7 TAGGING AND MARKING CHECK R R SW SW

9.8 MT ON LIFTING LUGS R R SW SW

9.9 NDE ON STEEL STRUCTURES R R SW SW

9.10 SPARE PARTS CHECK R R SW W

9.11 COATING INSPECTION: STEEL PREPARATION AND PAINTING R R SW W

9.12 MANUFATURER’S DATA BOOK R R R/W R/W

9.13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 68: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 68 OF 103

R 01

6.36 FIRE FIGHTING SYSTEM

COMMODITY: FIRE FIGHTING SYSTEM (NOTE 1 &2)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

CO2/CLEAN AGENT PACKAGE SYSTEM

2 ELECTRICAL TEST R R R R

3 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

4 SEQUENCE AND FUNCTIONAL TEST R R SW SW

5 CERTIFICATION REVIEW R R R R

DELUGE SYSTEM (VALVES W/SPRAY NOZZLES)

6 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

7 PRESSURE TEST R R SW SW

8 FUNCTIONAL TEST R R SW SW

9 ELECTRICAL TEST R R SW SW

10 CERTIFICATION REVIEW R R R R

SPRINKLER SYSTEM (ALARM VALVE WITH SPRINKLER

NOZZLE)

11 DIMENSION CHECK AND VISUAL INSPECTION R R R R

12 PRESSURE TEST R R R R

13 ELECTRICAL TEST R R R R

FIRE FIGHTING EQUIPMENT (Hydrant, post indicating valve

monitor)

14 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

15 HYDROSTATIC TEST R R R R

16 CERTIFICATION REVIEW R R R R

FIRE FIGHTING EQUIPMENT (Cabinet, /hose house, hose

reel, PIV, ect)

17 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

Page 69: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 69 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

18 CERTIFICATION REVIEW R R R R

MISCELLANEOUS (Fire extinguishers, breathing apparatus,

safety shower, eyewash etc.)

19 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

20 FUNCTIONAL TEST R R SW SW

21 CERTIFICATION REVIEW R R R R

GENERAL

22 MANUFATURER’S DATA BOOK R R R/W R/W

23 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

2. SAMPLING INSPECTION WIL BE APPLIED FOR 10% IN QUANTITIES OF EACH ITEM OF COMMODITIES

Page 70: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 70 OF 103

R 01

6.37 EMERGENCY DIESEL GENERATOR

COMMODITY: EMERGENCY DIESEL GENERATOR (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

DIESEL ENGINE

2 MATERIAL MILL TEST CERTIFICATES FOR MAIN PARTS

(crankshaft, cylinder, piston ect.) R R R R

3 VISUAL AND DIMENSIONAL INSPECTION AT ASSEMBLED

CONDITION R R SW W

4 STARTING SYSTEM TEST, OVERSPEED TRIP DEVICE TEST R R W W

5 HYDROSTATIC TEST OF FUEL LINE AND COOLING WATER TEST R R R SW

6

PERFORMANCE TEST AND MECHANICAL RUNNING TEST WITH

GENERATOR AND AUXILIARY SYSTEM (measurement of sound

level and vibration during running test)

R R W H

7 STANDARD (MFR) SHOP TEST R R R SW

GENERATOR SET

8 MATERIAL MILL TEST CERTIFICATES REVIEW (ROTOR SHAFT

AND MAIN COMPONENTS) R R SW SW

9 DYNAMIC BALANCE TEST OF GENERATOR ROTOR R R R SW

10 MEASURAMENT OF WINDING RESISTANCE R R SW W

11 CLEARANCE TEST RECORD R R R R

12 NO LOAD TEST R R SW W

13 THREE PHASE SHORT CIRCUIT TEST R R SW W

14 CALCULATION OF LOSSES AND CONVENTIONAL EFFICIENCY R R R R

15 TEMPERATURE RISE TEST R R SW W

16 INSULATION RESISTANCE TEST R R SW W

17 HIGH VOLTAGE TEST R R SW W

18 CALCULATION WAVE- FORM DEVIATION FACTOR R R R R

19 MEASUREMENT OF SHAFT VOLTAGE. R R SW SW

20 MEASUREMENT OF VIBRATION. R R SW SW

Page 71: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 71 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

21 COMBINE TEST WITH EXCITATION SYSTEM. R R SW W

22 COMBINE TEST ON AVR (automatic voltage regulation) AND MANUAL CONTROLLER. R R SW W

23 MEASUREMENT OF REACTANCE. R R SW W

24 TYPE TEST (CERTIFICATE ONLY) R R R R

25 POST TEST INSPECTION, IF REQUIRED. R R SW W

26 VISUAL AND DIMENSIONAL INSPECTION OF OIL SYSTEM R R W W

27 FULL LOAD TEST, IF REQUIRED R R SW W

28 FUNCTION TEST OF CONTROL PANEL AND INSTRUMENTS. R R SW W

29 FUNCTION TEST OF PROTECTION RELAY. R R SW W

30 FUNCTION TEST OF GENERATOR ASSEMBLY R R W W

GENERAL

31 VISUAL AND DIMENSIONAL INSPECTION OF COMPLETE PACKAGE R R W W

32 NAME PLATE, TAGGING AND MARKING. R R W W

33 MANUFATURER’S DATA BOOK R R R/W R

34 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 72: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 72 OF 103

R 01

6.38 HVAC SYSTEM

COMMODITY: HVAC SYSTEM (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

QC LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

AIR COOLED CONDENSING UNIT / AIR COOLED WATER CHILLER

2 MATERIAL MILL TEST CERTIFICATES FOR MAIN PARTS R R R R

3 VISUAL AND DIMENSIONAL INSPECTION AT ASSEMBLED

CONDITION R R SW W

4 PERFORMANCE TEST RECORDS R R R R

AIR HANDLING UNIT, PUMP, FAN, & BLAST PROOF VALVE

6 OUTLINE DIMENSION CHECK AND VISUAL INSPECTION R R W W

PERFORMANCE TEST RECORDS R R R R

7 STANDARD (MFR) SHOP TEST R R SW SW

CONTROL PANEL AND WIRING

8 MATERIAL TEST CERTIFICATES R R R R

9 OUTLINE DIMENSION CHECK AND VISUAL INSPECTION R R SW SW

10 INSULATION RESISTANCE TEST R R SW SW

11 DIELECTRIC TEST R R SW SW

12 SEQUENCE/ FUNCTION CHECK R R SW W

13 HVAC CONTROL SYSTEM FUNCTION TEST R R SW W

MISCELLANEOUS ITEMS FOR HVAC SYSTEM

15 MATERIAL TEST CERTIFICATES R R R R

16 OUTLINE DIMENSION CHECK AND VISUAL INSPECTION R R W W

GENERAL

17 SURFACE PREPARATION/PAINTING INSPECTION R R SW SW

18 NAME PLATE, TAGGING AND MARKING. R R W W

Page 73: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 73 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

QC LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

19 MANUFACTURER’S DATA BOOK R R R/W R/W

20 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

Page 74: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 74 OF 103

R 01

6.39 PIPE

COMMODITY: PIPE (NOTE 1,2 & 3)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

QC LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 WPS/PQR R R R R

3 POST WELD HEAT TRATMENT (IF REQUIRED) R R SW SW

4 NDE (IF REQUIRED) R R R R

5 HYDROSTATIC TEST (IF REQUIRED) R R R R

6 DIMENSIONAL CHECK AND VISUAL INSPECTION (ESPECIALLY,

ROUNDNESS CHECK) R R SW SW

7 HARNESS TEST (IF REQUIRED) R R SW SW

8 IMPACT TEST (IF REQUIRED) R R SW SW

9 HIC TEST (IF REQUIRED) R R SW SW

10 PMI (IF REQUIRED) R R SW SW

11 ADDITIONAL MECHANICAL AND CHEMICAL TEST (IF

REQUIRED) R R SW W

12 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW SW

13 MARKING CHECK R R SW SW

14 MANUFACTURER’S DATA BOOK R R R/W R/W

15 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. 100% INSPECTION WILL BE CARRIED OUT ONLY FOR CARBON STEEL PIPE 26” AND OVER, OR SUBJECT TO NACE REQ’T, OR LOW ALLOY (Cr-Mo) AND STAINLESS STEEL PIPE 10” AND OVER.

2. EXCEPT FOR ITEMS SPECIFIED IN NOTE-1, CONTRACTOR INSPECTION WILL BE CARRIED OUT AT RANDOM AT LEAST 10% OF THE TOTAL ORDERED QUANTITIES OF COMMODITIES.

3. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 75: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 75 OF 103

R 01

6.40 SHOP FABRICATED PIPE

COMMODITY: SHOP FABRICATED PIPE (NOTE 1,2 & 3)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W W

2 MATERIAL TEST CERTIFICATES R R R R

3 WPS/PQR R R R R

4 POST WELD HEAT TRATMENT (IF REQUIRED) R R SW SW

5 NDE (IF REQUIRED) R R SW SW

6 HYDROSTATIC TEST (IF REQUIRED) R R SW W

7 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

8 HARNESS TEST (IF REQUIRED) R R SW SW

9 IMPACT TEST (IF REQUIRED) R R SW SW

10 HIC TEST (IF REQUIRED) R R SW SW

11 PMI (IF REQUIRED) R R SW SW

12 ADDITIONAL MECHANICAL AND CHEMICAL TEST (IF

REQUIRED) R R SW W

13 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

14 MARKING CHECK R R SW SW

15 MANUFACTURER’S DATA BOOK R R R/W R/W

16 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. 100% INSPECTION WILL BE CARRIED OUT ONLY FOR CARBON STEEL PIPE 26” AND OVER, OR SUBJECT TO NACE REQ’T, OR LOW ALLOY (Cr-Mo) AND STAINLESS STEEL PIPE 10” AND OVER.

2. EXCEPT FOR ITEMS SPECIFIED IN NOTE-1, CONTRACTOR INSPECTION WILL BE CARRIED OUT AT RANDOM AT LEAST 10% OF THE TOTAL ORDERED QUANTITIES OF COMMODITIES.

3. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 76: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 76 OF 103

R 01

6.41 FLANGE

COMMODITY: FLANGE (NOTE 1,2 & 3

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 WPS/PQR R R R R

3 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

4 NDE (IF REQUIRED) R R R SW

5 HARNESS TEST, IMPACT TEST, PMI. (IF REQUIRED) R R R SW

6 ADDITIONAL MECHANICAL TEST AND CHEMICAL TEST (IF

REQUIRED) R R SW SW

7 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

8 MARKING CHECK R R SW W

9 MANUFACTURER’S DATA BOOK R R R/W R/W

10 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. 100% INSPECTION WILL BE CARRIED OUT ONLY FOR CARBON STEEL PIPE 26” AND OVER, OR SUBJECT TO NACE REQ’T, OR LOW ALLOY (Cr-Mo) AND STAINLESS STEEL PIPE 10” AND OVER.

2. EXCEPT FOR ITEMS SPECIFIED IN NOTE-1, CONTRACTOR INSPECTION WILL BE CARRIED OUT AT RANDOM AT LEAST 10% OF THE TOTAL ORDERED QUANTITIES OF COMMODITIES.

3. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 77: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 77 OF 103

R 01

6.42 FITTING

COMMODITY: FITTING (NOTE 1,2 & 3)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 WPS/PQR R R R R

3 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

4 NDE (IF REQUIRED) R R R SW

5 HARNESS TEST, IMPACT TEST, PMI. (IF REQUIRED) R R SW SW

6 ADDITIONAL MECHANICAL TEST AND CHEMICAL TEST (IF

REQUIRED) R R SW SW

7 DIMENSIONAL CHECK AND VISUAL INSPECTION R SW SW SW

8 MARKING CHECK R R SW SW

9 SURFACE PREPARATION/PAINTING INSPECTION REPORTS R R R R

10 MANUFACTURER’S DATA BOOK R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. 100% INSPECTION WILL BE CARRIED OUT ONLY FOR CARBON STEEL FITTINGS 26” AND OVER, OR SUBJECT TO NACE REQ’T, OR LOW ALLOY (Cr-Mo) AND STAINLESS STEEL PIPE 10” AND OVER.

2. EXCEPT FOR ITEMS SPECIFIED IN NOTE-1, CONTRACTOR INSPECTION WILL BE CARRIED OUT AT RANDOM AT LEAST 10% OF THE TOTAL ORDERED QUANTITIES OF COMMODITIES.

3. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 78: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 78 OF 103

R 01

6.43 SPRING HANGER AND PIPE SUPPORT

COMMODITY: SPRING HANGER AND PIPE SUPPORT (NOTE 1 &2)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 WPS/PQR R R R R

3 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

4 NDE (IF REQUIRED) R R SW SW

5 HARNESS TEST, IMPACT TEST, PMI. (IF REQUIRED) R R SW SW

6 FUNCTIONAL TEST (CONSTANT AND VARIABLE SPRING) R R SW SW

7 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

8 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

9 MARKING CHECK R R W W

10 MANUFACTURER’S DATA BOOK R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. UNLESS OTHERWISE SPECIFIED, CONTRCTOR INSPECTION WILL BE CARRIED OUT AT RANDOM FOR ATLEAST 10% OF THE TOTAL ORDERED QUANTITIES AND COMMODITIES.

2. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 79: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 79 OF 103

R 01

6.44 ORDINARY TYPE VALVES (CASTING & FORGED)

COMMODITY: ORDINARY TYPE VALVES (CASTING & FORGED) note 1-2-3-4-5

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL TEST CERTIFICATES FOR MAIN COMPONENT R R R R

3 WPS/PQR R R R R

4 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

5 NDE (IF REQUIRED) R R SW SW

6 HARNESS TEST, IMPACT TEST, PMI. (IF REQUIRED) R R SW SW

7 ADDITIONAL MECHANICAL TEST AND CHEMICAL TEST (IF

REQUIRED) R R SW SW

8 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

9 PRESSURE TEST & SEAT LEAK TEST R R W H

10 OPERATIONAL TEST R R SW SW

11 MARKING CHECK R R SW SW

12 SURFACE PREPARATION/PAINTING INSPECTION REPORTS R R SW W

13 MANUFACTURER’S DATA BOOK R R R/W R/W

14 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW SW W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. 100% INSPECTION OF CAST OR FORGED CS VALVES FOR COLD SERVICE, SOUR SERVICE AND ALL CAST VALVES CLASS 600 LBS AND ABOVE.

2. 100 % INSPECTION OF ALLOY AND STAINLESS STEEL VALVES 12” AND ABOVE.

3. AT LEAST 10 % INSPECTION WILL BE CONDUCTED FOR THE OTHER SERVICES AND COMMODITIES (CAST IRON, BRASS, ALUMINIUM AND OTHER NON-FERROUS OR NON-METALLIC VALVES) EXCEPT FOR ITEMS SPECIFIED IN NOTE 1 & 2.

4. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

5. BALL VALVE TEST SHALL INCLUDE, TESTING OF SEAT RELIEF DESIGN EFFECTIVENESS.

Page 80: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 80 OF 103

R 01

Valve Category Minimum Sample Size

(% of Item)

All manual and actuated on-off valves NPS 2 and smaller 10%

Manual and actuated valve on-off, 2<valves<14 NPS and less than ASME Class 600

25%

All manual and actuated on-off valves NPS 14 and above

All manual and actuated on off valves > 2” and ASME Class 600 and above 100%

All high value/process critical/severe service control valves 100%

All other control valves 10%

Severe Service: - Valves with noise control trim, anti-cavitation trim, high pressure (>= 600 ASME Class)

Process Critical –Valves as deemed critical by contractor and specified in the data sheet.

Page 81: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 81 OF 103

R 01

6.45 CRYOGENIC TYPE VALVES (CASTING & FORGED)

COMMODITY: CRYOGENIC TYPE VALVES (CASTING & FORGED) note 1-2-3

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL TEST CERTIFICATES FOR MAIN COMPONENT R R R R

3 WPS/PQR R R R R

4 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

5 CRYOGENICT TEST (IF REQUIRED) R R SW SW

6 NDE (IF REQUIRED) R R SW SW

7 IMPACT TEST R R SW SW

8 HARNESS TEST, PMI. (IF REQUIRED) R R SW SW

9 ADDITIONAL MECHANICAL TEST AND CHEMICAL TEST (IF

REQUIRED) R R SW SW

10 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW SW

11 PRESSURE TEST & SEAT LEAK TEST R R W H

12 OPERATIONAL TEST R R W W

13 MARKING CHECK R R W W

14 SURFACE PREPARATION/PAINTING INSPECTION REPORTS R R SW W

15 MANUFACTURER’S DATA BOOK R R R/W R/W

16 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. 100% INSPECTION OF CAST OR FORGED CS VALVES FOR COLD SERVICE, SOUR SERVICE AND ALL CAST VALVES CLASS 600 LBS AND ABOVE.

2. AT LEAST 10 % INSPECTION WILL BE CONDUCTED FOR THE OTHER SERVICES AND COMMODITIES (CAST IRON, BRASS, ALUMINIUM AND OTHER NON-FERROUS OR NON-METALLIC VALVES) EXCEPT FOR ITEMS SPECIFIED IN NOTE 1 & 2.

3. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 82: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 82 OF 103

R 01

Valve Category Minimum Sample Size

(% of Item)

All manual and actuated on-off valves NPS 2 and smaller 10%

Manual and actuated valve on-off, 2<valves<14 NPS and less than ASME Class 600

25%

All manual and actuated on-off valves NPS 14 and above

All manual and actuated on off valves > 2” and ASME Class 600 and above 100%

All high value/process critical/severe service control valves 100%

All other control valves 10%

Severe Service: - Valves with noise control trim, anti-cavitation trim, high pressure (>= 600 ASME Class)

Process Critical –Valves as deemed critical by contractor and specified in the data sheet.

Page 83: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 83 OF 103

R 01

6.46 STRAINER

COMMODITY: STRAINER (NOTE 1 & 2)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 WPS/PQR R R R R

3 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

4 NDE (IF REQUIRED) R R R SW

5 HARNESS TEST, IMPACT TEST, PMI. (IF REQUIRED) R R SW SW

6 PRESSURE TEST R R SW W

7 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

8 MARKING CHECK R R SW W

9 SURFACE PREPARATION/PAINTING INSPECTION REPORTS R R SW SW

10 MANUFACTURER’S DATA BOOK R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. UNLESS OTHERWISE SPECIFIED, CONTRACTOR INSPECTION WILL BE CARRIED OUT AT RANDOM AT LEST 10% OF THE TOTAL ORDERED QUANTITIES OF COMMODITIES.

2. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 84: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 84 OF 103

R 01

6.47 EXPANSION JOINT

COMMODITY: EXPANSION JOINT (NOTE 1,2 & 3)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

QC LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 WPS/PQR R R R R

3 POST WELD HEAT TRATMENT (IF REQUIRED) R R R R

4 NDE (IF REQUIRED) R R SW SW

5 HARNESS TEST, IMPACT TEST, PMI. (IF REQUIRED) R R SW SW

6 PRESSURE TEST R R SW W

7 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

8 MARKING CHECK R R W W

9 SURFACE PREPARATION/PAINTING INSPECTION REPORTS R R SW SW

10 MANUFACTURER’S DATA BOOK R R R/W R/W

11 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. CONTRACTOR INSPECTION AT SHOP WILL BE CARRIED OUT ONY FOR EXPANSION JOINT 4” AND OVER.

2. VENDOR INSPECTION WILL BE FINAL FOR THE OTHER COMMODITIES EXCEPT FOR ITEMS SPECIFIED IN NOTE 1.

3. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 85: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 85 OF 103

R 01

6.48 FLEXIBLE HOSE AND QUICK CONNECTOR

COMMODITY: FLEXIBLE HOSE AND QUICK CONNECTOR (NOTE 1,2,3&4)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL TEST CERTIFICATES R R R R

2 PRESSURE TEST R R SW SW

3 DIMENSIONAL CHECK AND VISUAL INSPECTION R R SW W

4 MARKING CHECK R R SW W

5 MANUFACTURER’S DATA BOOK R R R/W R/W

6 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. CONTRACTOR INSPECTION AT SHOP WILL BE CARRIED OUT ONY FOR FLEXIBLE HOSE 4” AND OVER.

2. VENDOR INSPECTION WILL BE FINAL FOR THE OTHER COMMODITIES EXCEPT FOR ITEMS SPECIFIED IN NOTE 1.

3. UNLESS OTHERWISE SPECIFIED, CONTRACTOR INSPECTION WILL BE CARRIED OUT AT RANDOM AT LEAST 10% OF THE TOTAL ORDERED QUANTITIES OF COMMODITIES.

4. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 86: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 86 OF 103

R 01

6.49 LV SWITCHGEAR / MOTOR CONTROL CENTER (MCC)

COMMODITY: LV SWITCHGEAR / MOTOR CONTROL CENTER (MCC) (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL TEST CERTIFICATES R R R R

ROUTINE TEST AND SPECIFIC TEST

3 TEMPERATURE RISE CHECK R R W W

4 SHORT CIRCUIT WITHSTAND TEST R R W W

5 MECHANICAL INTER LOCK TEST R R W W

6 MAIN CIRCUIT RESISTANCE MEASUREMENT R R W W

7 AUXILIARY CIRCUIT VOLATGE TEST R R W W

8 DIELECTRIC TEST R R W W

9 OPERATION AND INJECTION TESTS OF PROTECTIVE RELAYS R R W W

10 MECHANICAL OPERATION TEST R R W W

11 OPERATION SEQUENCE AND FUNCTIONAL TEST OF ALL

EQUIPMENT AND CIRCUIT R R W H

12 INSTRUMENT CALIBRATION AND SETTING R R R R

13 CABLING AND WIRING CHECK R R W W

14 EARTHING LOOP CHECK OF INSTRUMENTS R R W W

15 ROUTINE TEST CERTIFICATES REVIEW FOR MAIN

COMPONENTS R R R R

16 OTHER TEST IN ACCORDANCE TO IEC R R R R

17 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW SW

18 DIMENSIONAL CHECK AND VISUAL INSPECTION R R W W

19 MARKING CHECK R R W W

20 MANUFACTURER’S DATA BOOK R R R/W R/W

21 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W W

Page 87: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 87 OF 103

R 01

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 88: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 88 OF 103

R 01

6.50 UNINTERRUPTIBLE POWER SUPPLIES (UPS)

COMMODITY: UNINTERRUPTIBLE POWER SUPPLIES (UPS) (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R R R

2 VISUAL&DIMENSIONAL INSPECTION R R W W

3 INSULATION RESISTANCE TEST R R SW SW

4 TEMPERATURE RISE TEST R R SW W

5 OPERATION TEST R R SW W

6 AC OUTPUT CHARACTERISTIC TEST R R SW W

7 POWER FREQUENCY VOLTAGE WITHSTAND TEST R R SW W

8 EFFEICIENCY AND INPUT POWER FACTOR TEST R R SW SW

9 OTHER INSPECTION/TEST STIPULATED IN THE PO SPECIFICATION, IF ANY

R R W W

10 MANUFACTURER’S DATA RECORDS R R R R

11 MARKING CHECK R SW W W

12 MANUFACTURER’S DATA BOOK R R R/W R/W

13 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 89: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 89 OF 103

R 01

6.51 INDUCTION MOTORS (LV & MV)

COMMODITY: INDUCTION MOTORS (LV & MV) (note 1,2,3,4)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW R R R R

3 VISUAL&DIMENSIONAL INSPECTION R R W W

4 INSULATION RESISTANCE TEST R R W W

5 DIELECTRIC STRENGTH TEST R R W W

6 TEMPERATURE RISE TEST R R W W

7 NO-LOAD TEST R R W W

8 LOCKED ROTOR TEST R R W W

9 HIGH-VOLTAGE TEST R R W W

10 MEASUREMENT OF VIBRATION R R W W

11 MEASUREMENT OF NOISE R R W W

12 MEASUREMENT OF WINDING RESISTANCE R R W W

13 MEASUREMENT OF SHAFT VOLTAGE R R W W

14 HEATER TEST R R SW SW

15 FUNCTIONAL AND PERFORMANCE TEST (FAT) R R W H

16 OTHER INSPECTION/TEST STIPULATED IN THE P.O. SPECIFICATION, IF ANY. R R W W

17 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

18 MARKING CHECK R R W W

19 MANUFACTURER’S DATA BOOK R R R/W R/W

20 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

Page 90: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 90 OF 103

R 01

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

2 NO WITNESS INSPECTION IS REQUIRED FOR INDUCTION MOTOR LESS THAN 1000V, ONLY REVIEW OF INSPECTION AND TEST RECORDS.

3 ROUTINE AND TYPE TEST CERTIFICATES FOR MOTORS SHALL BE SUBMIITTED BY VENDOR. 4 STARTING TORQUE/SPEED CHECK BY COMPARING TORQUE SPEED CURVE OF LOAD WITH

TORQUE SPEED CURVE OF MOTOR AT 75% OF RATED VOLTAGE. (FOR LOW VOLTAGE MOTORS OVER 75KW RATING.)

Page 91: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 91 OF 103

R 01

6.52 DRY TYPE TRANSFORMER

COMMODITY: DRY TYPE TRANSFORMER (NOTE 1-2-3-4)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW R R R R

3 VISUAL&DIMENSIONAL INSPECTION R R W W

4 INSULATION RESISTANCE TEST R R SW W

5 MEASUREMENT OF WINDING RESISTANCE R R W W

6 MEASUREMENT OF VOLTAGE RATIO R R W W

7 MEASUREMENT OF NO-LOAD LOSS AND CURRENT R R W W

8 MEASUREMENT OF SHORT-CIRCUIT IMPEDANCE AND LOAD LOSS R R W W

9 TEMPERATURE RISE TEST R R W W

10 DIELECTRIC RESISTANCE TEST R R W W

11 INDUCED OVER VOLTAGE WITHSTAND TEST R R W W

12 SEPARATE –SOURCE VOLTAGE WITHSTAND TEST R R W W

13 MEASUREMENT OF NOISE LEVEL R R W W

14 SHORT CIRCUIT TEST R R W W

15 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

16 MARKING CHECK R R W W

17 MANUFACTURER’S DATA BOOK R R R/W R/W

18 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

2 ALL TRANSFORMERS ABOVE 1000KVA SHALL BE TESTED INDIPENDENT OF VOLTAGE

RANGE

Page 92: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 92 OF 103

R 01

3 TEMPERATURE RISE TEST SHALL BE MADE ON THE UNIT OF EACH TRANSFORMER SIZE 4 EQUIPMENT SHALL BE COMPLETELY SHOP-ASSEMBLED IN ORDER TO VERIFY THE

SPECIFIED FUNCTION AT SHOP ACCORDING TO DESIGN DATA, AND TO CHECK THE ELECTRICAL SYSTEAM. DISASSEMBLED PARTS MUST BE CLEARLY MATCH-MARKED FOR FIELD RE-ASSEMBLING.

Page 93: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 93 OF 103

R 01

6.53 OIL-IMMERSED TYPE TRANSFORMER

COMMODITY: OIL-IMMERSED TYPE TRANSFORMER (NOTE1-2-3-4-5-6)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW R R R R

3 VISUAL&DIMENSIONAL INSPECTION R R W W

4 INSULATION RESISTANCE TEST R R W W

5 MEASURAMENT OF WINDING RESISTANCE. R R W W

6 MEASUREMENT OF VOLTAGE RATIO R R W W

7 MEASUREMENT OF NO-LOAD LOSS AND CURRENT R R W W

8 MEASUREMENT OF SHORT-CIRCUIT IMPEDANCE AND LOAD LOSS R R W W

9 DIELECTRIC RESISTANCE TEST R R W W

10 TEST ON-LOAD TAP – CHANGERS, WHERE APPROPRIATE

R R W W

11 SEPARATE –SOURCE VOLTAGE WITHSTAND TEST R R W W

12 TEMPERATURE RISE TEST R R W W

13 TYPE TEST RECORDS (Impulse test, measurement of zero-sequence impedance, thermal ability to withstand short circuit, short circuit test)

R R R R

14 CONTROL PANEL TEST R R W W

15 INDUCED OVERVOLTAGE WITHSTAND TEST R R W W

16 ASSEMBLING/DISASSEMBLING R R W W

17 INSTRUMENT CALIBRATION R R R R

18 CURRENT TRANSFORMER TEST R R W W

19 PROTECTION DEVICES R R W W

20 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

21 MARKING CHECK R R W W

22 MANUFACTURER’S DATA BOOK R R R/W R/W

23 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Page 94: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 94 OF 103

R 01

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORD AS REQUIRED.

2. NO WITNESSED INSPECTION IS REQUIRED FOR TRANSFORMER LESS THAN 1000V, ONLY REVIEW OF INSPECTION AND TEST RECORDS.

3. RECORDS FOR ON-LOAD TAP CHANGER TO BE SUBMITTED.

4. ALL TRANSFORMERS ABOVE 1000KVA SHALL BE TESTED INDEPENDENT OF VOLTAGE RANGE.

5. TEMPERATURE RISE TEST SHALL BE MADE ON THE UNIT OF EACH TRANSFORMER SIZE.

6. THE EQUIPMENT SHALL BE COMPLETELY SHOP-ASSEMBLED IN ORDER TO VERIFY THE

SPECIFIED FUNCTION AT SHOP ACCORDING TO DESIGN DATA, AND TO CHECK THE ELECTRICAL SYSTEM. DISASSEMBLED PARTS MUST BE CLEARLY MATCH-MARKED FOR FIELD RE-ASSEMBLING.

Page 95: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 95 OF 103

R 01

6.54 6KV SWITCHGEAR AND CONTROLGEAR

COMMODITY: 6kV SWITCHGEAR AND CONTROLGEAR (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R R R

2 VISUAL&DIMENSIONAL INSPECTION R R SW W

ROUTINE TEST &SPECIFIC TEST

3 SHORT CIRCUIT WITHSTAND TEST R R W W

4 INSULATION RESISTANCE TEST R R SW SW

5 TEMPERATURE RISE TEST R R SW SW

6 MECHANICAL INTERLOCK TEST R R W W

7 SHORT CIRCUIT WITHSTAND TEST R R W W

8 FREQUENCY VOLTAGE TEST R R W W

9 MAIN CIRCUIT RESISTANT MEASUREMENT R R W W

10 AUXILIARY CIRCUIT VOLTAGE TESTS R R W W

11 DIELECTRIC TESTS R R W W

12 OPERATION AND INJECTION TESTS OF PROTECTIVE RELAYS R R W W

13 INSTRUMENT CALIBRATION AND SETTING R R R R

14 MECHANICAL OPERATION TESTS R R W W

15 OPERATION AND FUNCTIONAL TESTS OF ALL EQUIPMENT AND CIRCUIT R R W W

16 CHECK OF WIRING R R R R

17 INTERCHANGEABILITY OF BREAKERS R R R R

18 OTHER TESTS IN ACCORDANCE WITH IEC R R SW SW

19 EARTHING LOOP CHECK OF INSTRUMENT R R SW SW

20 REVIEW ROUTINE TEST OF MAIN COMPONENT’S R R R R

21 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW SW

Page 96: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 96 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

22 MARKING CHECK R R W W

23 MANUFACTURER’S DATA BOOK R R R/W R/W

24 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 97: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 97 OF 103

R 01

6.55 33KV SWITCHGEAR

COMMODITY: 33kV SWITCHGEAR (NOTE 1) THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

1 PRE-INSPECTION MEETING R R W H

2 MATERIAL CERTIFICATES REVIEW R R R R

3 VISUAL&DIMENSIONAL INSPECTION R R W W

ROUTINE TEST &SPECIFIC TEST

4 SHORT CIRCUIT WITHSTAND TEST R R W W

5 INSULATION RESISTANCE TEST R R W W

6 TEMPERATURE RISE TEST R R W W

7 MECHANICAL INTERLOCK TEST R R W W

8 SHORT CIRCUIT WITHSTAND TEST R R W W

9 FREQUENCY VOLTAGE TEST R R W W

10 MAIN CIRCUIT RESISTANT MEASUREMENT R R W W

11 AUXILIARY CIRCUIT VOLTAGE TESTS R R W W

12 DIELECTRIC TESTS R R W W

13 OPERATION AND INJECTION TESTS OF PROTECTIVE RELAYS R R W W

14 INSTRUMENT CALIBRATION AND SETTING R R R R

15 MECHANICAL OPERATION TESTS R R W W

16 OPERATION AND FUNCTIONAL TESTS OF ALL EQUIPMENT AND CIRCUIT R R W H

17 CHECK OF WIRING R R SW SW

18 INTERCHANGEABILITY OF BREAKERS R R W W

19 OTHER TESTS IN ACCORDANCE WITH IEC R R SW SW

20 EARTHING LOOP CHECK OF INSTRUMENT R R W W

21 REVIEW ROUTINE TEST OF MAIN COMPONENT’S R R R R

22 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

Page 98: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 98 OF 103

R 01

INSPECTION ACTIVITY DESCRIPTION

INSPECTION BY NOTE

CQ1 CQ2 CQ3 CQ4

23 MANUFACTURER’S DATA RECORDS R R R/W R/W

24 MARKING CHECK R W W W

26 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORDS AS REQUIRED.

Page 99: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 99 OF 103

R 01

6.56 CABLES

COMMODITY: CABLES (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R R R

2 VISUAL&DIMENSIONAL INSPECTION R R SW SW

3 INSULATION RESISTANCE TEST R R R R

4 HIGH VOLATGE TEST R R SW SW

5 CONDUCTOR RESISTANCE MEASUREMENT R R SW SW

6 MARKING CHECK R R SW W

7 MANUFACTURER’S DATA BOOK R R R/W R/W

8 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R SW W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORD AS REQUIRED.

Page 100: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 100 OF 103

R 01

6.57 DISTRBUTION PANELS

COMMODITY: DISTRBUTION PANELS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R R R

2 VISUAL&DIMENSIONAL INSPECTION R R W W

3 INSULATION RESISTANCE TEST R R SW SW

4 HIGH VOLTAGE TEST R R W W

5 FUNCTIONAL TEST R R W H

6 MARKING CHECK R R W W

7 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

8 MANUFACTURER’S DATA BOOK R R R/W R/W

9 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER’S DATA RECORD AS REQUIRED.

Page 101: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 101 OF 103

R 01

6.58 CONTROL VALVES/ESDV’S/BDV’S /ON-OFF VALVES

COMMODITY: CONTROL VALVES/ESDV’S/BDV’S /ON-OFF VALVES (NOTE 1)

(ESDV: Emergency Shut down valves)

(BDV : Blow down valves)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

VALVE

1 PRE INSPECTION MEETING R R W W

2 MATERIAL CERTIFICATES REVIEW R R R R

3 NON DISTRUCTIVE TESTING (IF SPECIFIED) R R SW W

4 PRESSURE TEST/TIGHTNESS TEST R R W H

5 SEAT LEAKAGE TEST R R W H

6 PARTIAL STROKE TEST R R W H

7 PERFORMANCE TEST INCLUDING OPEN/CLOSE CHECK R R SW W

8 PMI (IF REQUIRED) R R SW SW

ACTUATOR

9 DIMENSONAL AND VISUAL INSPECTION R R SW W

10 FUNCTIONAL TEST R R SW SW

11 CHECK OF SPARE PARTS AND SPECIAL TOOLS IF REQUIRED R R SW SW

12 MARKING CHECK R R SW W

GENERAL

13 CHECK NAME AND TAG PLATE R R W W

14 SURFACE PREPARATION/PAINTING INSPECTION REPORTS

R R SW W

15 MANUFACTURER’S DATA BOOK R R R/W R/W

16 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W H

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

Page 102: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 102 OF 103

R 01

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED

6.59 INSTRUMENT BULKS

COMMODITY: INSTRUMENT BULKS (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW R R R R

2 DIMENSIONAL CHECK /VISUAL INSPECTION R R SW W

3 CALIBRATION CHECK R R R R

4 MARKING CHECK R R SW SW

5 SURFACE PREPARATION/PAINTING INSPECTION REPORTS (IF APPLICABLE) R R R R

6 MANUFACTURER’S DATA BOOK R R R/W R/W

7 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.

Page 103: Minimum Inspection Requirements (ITP) for purchased …beecroftconstruction.com/Plans/MG-Control-Room/04_QA_QC/E013-34… · Minimum Inspection Requirements (ITP) for purchased Material

DOC. NO 56-00-41 REV 01 SHEET 103 OF 103

R 01

6.60 INSTRUMENT PRESSURE AND TEMPERATURE GAUGE

COMMODITY: INSTRUMENT AND TEMPERATURE GAUGE (NOTE 1)

THIS ITP INDICATES MINIMUM EXTENT OF INSPECTION TO BE PERFORMED BY CONTRACTOR (C), OWNER (O), TPI/TPIA AND SHALL BE IN CORPORATED INTO VENDOR/SUB-VENDOR’S ITP/QCP.

INSPECTION ACTIVITY DESCRIPTION

CQ LEVEL NOTE

CQ1 CQ2 CQ3 CQ4

1 MATERIAL CERTIFICATES REVIEW (wetted parts, accessories) R R R R

2 DIMENSIONAL CHECK /VISUAL INSPECTION R R W W

3 DYE PENETRANT TEST (PT) (IF required) R R SW SW

4 CALIBRATION CHECK R R R R

5 MARKING CHECK R R SW W

6 SURFACE PREPARATION/PAINTING INSPECTION REPORTS (IF APPLICABLE) R R R R

7 MANUFACTURER’S DATA BOOK R R R/W R/W

8 PRE SHIPMENT INSPECTION (PACKING, MARKING,

PRESERVATION,) R W W W

Legenda : H – HOLD POINT / W – WITNESS POINT / R – REVIEW POINT / Y – REQUIRED

N – NOT REQUIRED / SW – SPOT WITNESS / M – MONITORING

NOTE 1. VENDOR SHALL SUBMIT MANUFACTURER'S DATA RECORDS AS REQUIRED.