inspection test plan itp v3

Upload: luis-gabriel-bautista

Post on 08-Aug-2018

304 views

Category:

Documents


6 download

TRANSCRIPT

  • 8/22/2019 Inspection Test Plan ITP v3

    1/22

    Footer10/29/2012

    Updated: October 19, 2012

    Inspection & Test Plan (ITP) presentation for suppliers to FMC Technologies, Norway

    QRL-0010001 FMC Standard Administration Requirements:

    - Revision P, released August 19, 2011- Appendix F Quality Requirements, section 1.5 & 1.6

  • 8/22/2019 Inspection Test Plan ITP v3

    2/22

    Learning Objectives

    2

    Why and when FMC require an Inspection & Test Plan(ITP).

    What the requirements are.

    The responsibilities of issue, review and handling.

    Why and when FMC require intervention points.

    The different types of intervention codes.

    Notification requirements content & communication.

  • 8/22/2019 Inspection Test Plan ITP v3

    3/22

    Purpose

    3

    Inspection & Test Plan is a basis for verifying conformity withspecified contractual requirements.

    For FMC and the Supplier to establish and agree upon the

    following prior to production start;

    Quality Control activities

    Interventions for the Supplier, FMC, FMCs customer

    and/or Third Party

    Intervention points allow the parties to go into different steps

    in the production process to assure the quality.

  • 8/22/2019 Inspection Test Plan ITP v3

    4/22

    When is ITP applicable

    The requirement for ITP is listed in the DocumentRequirement List (DRL), Supplier Document Requirements

    (SDR) / Manufacturing Information Requirements (MIR).

    Typically for Products with Special Processes (e.g.

    bending, welding, nondestructive examination (NDE),

    forging, castings) There will be Intervention points on all ITPs

    Product-, Project-, and Supplier Criticality decides the

    level of intervention

    4

  • 8/22/2019 Inspection Test Plan ITP v3

    5/22

    What

    ITP is listing the sequence of activities, and shall as a minimuminclude:

    All important production processes in all phases of production.

    All examinations, inspections and tests to be performed with

    reference to applicable inspection and test procedures, and

    type of verifying document. Location of activity.

    Suppliers Intervention activities (witness, hold, etc).

    Interventions columns for FMC, 3rd party and Customer.

    Health, Safety & Environment (HSE) intervention point prior to

    critical tests, if any. Pre-Production Meeting (PPM) to preferably be an activity in

    the ITP.

    5

  • 8/22/2019 Inspection Test Plan ITP v3

    6/22

    Kick Off vs. Pre-Production Meeting (PPM)

    Kick Off Meeting (Pre-Award Meeting): To ensure that the Supplierbase their work on the correct input and that the commercial and

    technical requirements are understood.

    FMC procurement responsible for meeting, without FMC customer.

    Pre-Production Meeting (PPM): To determine whether the Supplier isready to start production.

    Supplier to call for meeting, FMC responsible for documenting the

    findings, often with FMC customer.

    All clarifications between FMC and supplier shall be done prior to PPM.

    6

  • 8/22/2019 Inspection Test Plan ITP v3

    7/22

    Responsibilities; issue & handling

    ITP shall be uniquely identified and revision controlled documents toensure proper communication of the latest requirements.

    Supplier shall issue ITP 2WAO (weeks after order) for FMC review

    and approval

    FMC responsible to forward to FMC Customer for review if required

    Subcontractors ITPs:The level of review and approval of subcontractors ITPs shall be based on the

    product and Supplier complexity, and communicated to the Supplier, by either;

    Kick off or PPM (ref also PPM check list LST60069359)

    other written instructions from FMC

    ITPs shall be listed on the SMDR (Supplier Master DocumentRegister)

    If any change in manufacturing process on an ongoing ITP, the ITP

    shall be revised and resubmitted to FMC for review and approval.

    7

  • 8/22/2019 Inspection Test Plan ITP v3

    8/22

    Responsibilities; Review

    8

    FMC responsible Quality personnel shall review

    FMC to review and return document to Supplier within twenty (20)

    Business Days, or longer if the document shall be reviewed by FMC

    Customer as the case may be.

    For every review cycle (revision) the supplier will receive a DR-4

    document (Design Review) from FMC.

    The DR-4 document will have an Approval Status Code and may

    have comments for action or information.

    If comments, Supplier shall re-submit updated document within

    10 Business Days. (if not otherwise agreed in the contract)

  • 8/22/2019 Inspection Test Plan ITP v3

    9/22

    Responsibilities; Review

    9

    The Approval Status Code and the DR reference shallimmediately be recorded in the SMDR by the supplier.

    Approval Status Codes:

    1 Accepted with no comments2 Accepted with comments incorporated. Revise and resubmit.

    2x Document returned before the customer's final approval/comments. Hold next

    revision of the document until receipt of FMC final comments, or document is

    given approval status code 1.

    3 Rejected

    4 Information

  • 8/22/2019 Inspection Test Plan ITP v3

    10/22

    Example (non complex part, page 1 of 1)

    10

  • 8/22/2019 Inspection Test Plan ITP v3

    11/22

    Example (complex part, page 1 of 2)

    11

  • 8/22/2019 Inspection Test Plan ITP v3

    12/22

    Example (complex part, page 2 of 2)

    12

  • 8/22/2019 Inspection Test Plan ITP v3

    13/22

    Intervention Codes

    13

    R = Review:

    Documentation and records shall be available for verification at any time by

    FMC/Customer representative.

    M = Monitor:

    Activity will proceed as scheduled, without advance notification, but is

    subject to FMC/Customer witness as and when required. Monitor activities

    are intended for process verification, not product inspection.

  • 8/22/2019 Inspection Test Plan ITP v3

    14/22

    Intervention Codes

    14

    W = Witness:

    A critical step in manufacturing or testing where it is desirable that FMC

    and/or Customer representative participates in the inspection / process

    activity of the material / equipment in order to ascertain that the product for

    delivery complies with the specified requirements. Formal advance

    notification shall be given. The step can proceed with or without the

    presence of FMC and/or Customer representative after the designated timehas passed.

    H = Hold:

    A critical step in manufacturing and testing where it is essentialthat FMC

    and/or Customer representative participates in the inspection /processactivity of the material / equipment in order to ascertain that the product for

    delivery complies with the specified requirements. Formal advance

    notification shall be given . The step shall not proceed without the presence

    of FMC and/or Customer representative, or without a written statement

    giving a waiver.

  • 8/22/2019 Inspection Test Plan ITP v3

    15/22

    Notification of Witness/Hold points - Content

    Supplier may use their own format, but it shall as a minimuminclude:

    FMC Purchase Order ref, Part Number & Serial Number (quantity)

    Part description

    Date & Time for activity

    Duration

    Supplier ITP doc number with reference to activity

    Procedure document number and revision

    Location for activity

    Contact persons

    15

  • 8/22/2019 Inspection Test Plan ITP v3

    16/22

    Notification Format

    16

  • 8/22/2019 Inspection Test Plan ITP v3

    17/22

    Notify

    All notifications to FMC Kongsberg (including updates) shallbe sent to: [email protected] E-mail subject: FMC Project code & name, PO number (but not limited to)

    Copy relevant personnel, such as Commercial point of contact and

    Quality resource

    Notification time shall be minimum 10 business days unless

    otherwise formally agreed.

    17

    mailto:[email protected]:[email protected]
  • 8/22/2019 Inspection Test Plan ITP v3

    18/22

    ITP Notification Process (1 of 2)

    18

  • 8/22/2019 Inspection Test Plan ITP v3

    19/22

    ITP Notification Process (2 of 2)

    19

  • 8/22/2019 Inspection Test Plan ITP v3

    20/22

    Be aware

    Recurring problems:

    Documentation is a bottle neck Internally in FMC

    FMC Customer

    Contact FMC purchaser if delay in documents

    ITPs and notifications

    wrong / misspelled Purchase Order Number or Part Number several cases of copy-paste

    If several Part Numbers (PN) are included in one ITP

    Be very clear on which procedure belongs to which PN

    Multiple ITPs for one PO if the manufacturing steps are different

    20

  • 8/22/2019 Inspection Test Plan ITP v3

    21/22

    Be aware continue

    FMC is working on methods to inform about required interventionpoints at PO award.

    For BP projects requirements for intervention will be included in the

    Part Report (DBI). Include those on first revision of ITP.

    Notifications

    Any special agreements with FMC or Customer (shorter notification

    time, document approvals etc) shall be clearly stated in the

    notification.

    An email shall only contain notifications for one project.

    21

  • 8/22/2019 Inspection Test Plan ITP v3

    22/22

    Summary

    Where to find out if we require an ITP for the Part? Where to find out the required content of an ITP?

    When shall the ITP intervention points be agreed?

    When do the supplier need to update and resubmit ITP?

    When shall the notifications be sent to FMC?

    To whom shall the notifications be sent?

    22