inspection test plan itp v3
TRANSCRIPT
-
8/22/2019 Inspection Test Plan ITP v3
1/22
Footer10/29/2012
Updated: October 19, 2012
Inspection & Test Plan (ITP) presentation for suppliers to FMC Technologies, Norway
QRL-0010001 FMC Standard Administration Requirements:
- Revision P, released August 19, 2011- Appendix F Quality Requirements, section 1.5 & 1.6
-
8/22/2019 Inspection Test Plan ITP v3
2/22
Learning Objectives
2
Why and when FMC require an Inspection & Test Plan(ITP).
What the requirements are.
The responsibilities of issue, review and handling.
Why and when FMC require intervention points.
The different types of intervention codes.
Notification requirements content & communication.
-
8/22/2019 Inspection Test Plan ITP v3
3/22
Purpose
3
Inspection & Test Plan is a basis for verifying conformity withspecified contractual requirements.
For FMC and the Supplier to establish and agree upon the
following prior to production start;
Quality Control activities
Interventions for the Supplier, FMC, FMCs customer
and/or Third Party
Intervention points allow the parties to go into different steps
in the production process to assure the quality.
-
8/22/2019 Inspection Test Plan ITP v3
4/22
When is ITP applicable
The requirement for ITP is listed in the DocumentRequirement List (DRL), Supplier Document Requirements
(SDR) / Manufacturing Information Requirements (MIR).
Typically for Products with Special Processes (e.g.
bending, welding, nondestructive examination (NDE),
forging, castings) There will be Intervention points on all ITPs
Product-, Project-, and Supplier Criticality decides the
level of intervention
4
-
8/22/2019 Inspection Test Plan ITP v3
5/22
What
ITP is listing the sequence of activities, and shall as a minimuminclude:
All important production processes in all phases of production.
All examinations, inspections and tests to be performed with
reference to applicable inspection and test procedures, and
type of verifying document. Location of activity.
Suppliers Intervention activities (witness, hold, etc).
Interventions columns for FMC, 3rd party and Customer.
Health, Safety & Environment (HSE) intervention point prior to
critical tests, if any. Pre-Production Meeting (PPM) to preferably be an activity in
the ITP.
5
-
8/22/2019 Inspection Test Plan ITP v3
6/22
Kick Off vs. Pre-Production Meeting (PPM)
Kick Off Meeting (Pre-Award Meeting): To ensure that the Supplierbase their work on the correct input and that the commercial and
technical requirements are understood.
FMC procurement responsible for meeting, without FMC customer.
Pre-Production Meeting (PPM): To determine whether the Supplier isready to start production.
Supplier to call for meeting, FMC responsible for documenting the
findings, often with FMC customer.
All clarifications between FMC and supplier shall be done prior to PPM.
6
-
8/22/2019 Inspection Test Plan ITP v3
7/22
Responsibilities; issue & handling
ITP shall be uniquely identified and revision controlled documents toensure proper communication of the latest requirements.
Supplier shall issue ITP 2WAO (weeks after order) for FMC review
and approval
FMC responsible to forward to FMC Customer for review if required
Subcontractors ITPs:The level of review and approval of subcontractors ITPs shall be based on the
product and Supplier complexity, and communicated to the Supplier, by either;
Kick off or PPM (ref also PPM check list LST60069359)
other written instructions from FMC
ITPs shall be listed on the SMDR (Supplier Master DocumentRegister)
If any change in manufacturing process on an ongoing ITP, the ITP
shall be revised and resubmitted to FMC for review and approval.
7
-
8/22/2019 Inspection Test Plan ITP v3
8/22
Responsibilities; Review
8
FMC responsible Quality personnel shall review
FMC to review and return document to Supplier within twenty (20)
Business Days, or longer if the document shall be reviewed by FMC
Customer as the case may be.
For every review cycle (revision) the supplier will receive a DR-4
document (Design Review) from FMC.
The DR-4 document will have an Approval Status Code and may
have comments for action or information.
If comments, Supplier shall re-submit updated document within
10 Business Days. (if not otherwise agreed in the contract)
-
8/22/2019 Inspection Test Plan ITP v3
9/22
Responsibilities; Review
9
The Approval Status Code and the DR reference shallimmediately be recorded in the SMDR by the supplier.
Approval Status Codes:
1 Accepted with no comments2 Accepted with comments incorporated. Revise and resubmit.
2x Document returned before the customer's final approval/comments. Hold next
revision of the document until receipt of FMC final comments, or document is
given approval status code 1.
3 Rejected
4 Information
-
8/22/2019 Inspection Test Plan ITP v3
10/22
Example (non complex part, page 1 of 1)
10
-
8/22/2019 Inspection Test Plan ITP v3
11/22
Example (complex part, page 1 of 2)
11
-
8/22/2019 Inspection Test Plan ITP v3
12/22
Example (complex part, page 2 of 2)
12
-
8/22/2019 Inspection Test Plan ITP v3
13/22
Intervention Codes
13
R = Review:
Documentation and records shall be available for verification at any time by
FMC/Customer representative.
M = Monitor:
Activity will proceed as scheduled, without advance notification, but is
subject to FMC/Customer witness as and when required. Monitor activities
are intended for process verification, not product inspection.
-
8/22/2019 Inspection Test Plan ITP v3
14/22
Intervention Codes
14
W = Witness:
A critical step in manufacturing or testing where it is desirable that FMC
and/or Customer representative participates in the inspection / process
activity of the material / equipment in order to ascertain that the product for
delivery complies with the specified requirements. Formal advance
notification shall be given. The step can proceed with or without the
presence of FMC and/or Customer representative after the designated timehas passed.
H = Hold:
A critical step in manufacturing and testing where it is essentialthat FMC
and/or Customer representative participates in the inspection /processactivity of the material / equipment in order to ascertain that the product for
delivery complies with the specified requirements. Formal advance
notification shall be given . The step shall not proceed without the presence
of FMC and/or Customer representative, or without a written statement
giving a waiver.
-
8/22/2019 Inspection Test Plan ITP v3
15/22
Notification of Witness/Hold points - Content
Supplier may use their own format, but it shall as a minimuminclude:
FMC Purchase Order ref, Part Number & Serial Number (quantity)
Part description
Date & Time for activity
Duration
Supplier ITP doc number with reference to activity
Procedure document number and revision
Location for activity
Contact persons
15
-
8/22/2019 Inspection Test Plan ITP v3
16/22
Notification Format
16
-
8/22/2019 Inspection Test Plan ITP v3
17/22
Notify
All notifications to FMC Kongsberg (including updates) shallbe sent to: [email protected] E-mail subject: FMC Project code & name, PO number (but not limited to)
Copy relevant personnel, such as Commercial point of contact and
Quality resource
Notification time shall be minimum 10 business days unless
otherwise formally agreed.
17
mailto:[email protected]:[email protected] -
8/22/2019 Inspection Test Plan ITP v3
18/22
ITP Notification Process (1 of 2)
18
-
8/22/2019 Inspection Test Plan ITP v3
19/22
ITP Notification Process (2 of 2)
19
-
8/22/2019 Inspection Test Plan ITP v3
20/22
Be aware
Recurring problems:
Documentation is a bottle neck Internally in FMC
FMC Customer
Contact FMC purchaser if delay in documents
ITPs and notifications
wrong / misspelled Purchase Order Number or Part Number several cases of copy-paste
If several Part Numbers (PN) are included in one ITP
Be very clear on which procedure belongs to which PN
Multiple ITPs for one PO if the manufacturing steps are different
20
-
8/22/2019 Inspection Test Plan ITP v3
21/22
Be aware continue
FMC is working on methods to inform about required interventionpoints at PO award.
For BP projects requirements for intervention will be included in the
Part Report (DBI). Include those on first revision of ITP.
Notifications
Any special agreements with FMC or Customer (shorter notification
time, document approvals etc) shall be clearly stated in the
notification.
An email shall only contain notifications for one project.
21
-
8/22/2019 Inspection Test Plan ITP v3
22/22
Summary
Where to find out if we require an ITP for the Part? Where to find out the required content of an ITP?
When shall the ITP intervention points be agreed?
When do the supplier need to update and resubmit ITP?
When shall the notifications be sent to FMC?
To whom shall the notifications be sent?
22