milestone 9 final report frankston arts precinct …...ceep1115 milestone 9 final report frankston...

58
CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government. The views expressed herein are not necessarily the views of the Commonwealth of Australia, and the Commonwealth does not accept responsibility for any information or advice contained herein.

Upload: others

Post on 17-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

 

 

 

 CEEP1115

Milestone9FinalReportFrankstonArtsPrecinctTrigeneration

This activity received funding from the Australian Government. 

The views expressed herein are not necessarily the views of the 

Commonwealth of Australia, and the Commonwealth does not accept 

responsibility for any information or advice contained herein. 

Page 2: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 2  

 

TABLE OF CONTENTS

ContentsDefinitions  4 

EXECUTIVE SUMMARY  5 

SITE OVERVIEW  7 

PROJECT ENERGY EFFICIENCY ACTIVITIES  9 

PROJECT OVERVIEW  10 

PROJECT OBJECTIVES  16 

Project Energy Efficiency Activities  17 

Trigeneration  23 

Ener‐G Co‐generation (CHP) system  23 

Absorption Chiller  27 

Switchboard – Central Control System  28 

Microgeneration  29 

BlueGen  31 

Yanmar  34 

Qnergy  38 

PROJECT DEMONSTRATION AND COMMUNICATIONS ACTIVITIES  39 

Thermal Comfort Guidelines  40 

Viewing Display area  41 

Real time energy display system  42 

Signage  45 

Community Energy Saving Workshops  47 

Flytower Projector Screen  49 

Community and Industry tours  50 

Fact Sheet / Tour notes  50 

Media  50 

OUTCOMES AND BENEFITS OF THE PROJECT  50 

Project Energy Efficiency Improvement Template  51 

Energy Efficiency savings to date  52 

Issues and challenges  53 

BUDGET  54 

PROJECT OPERATION, MECHANISMS AND PROCESSES  55 

CONCLUSION  56 

 

 

Page 3: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 3  

 

 

Frankston Arts Centre view from Cube 37 

   

Page 4: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 4  

 

DEFINITIONS 

BMS  Building Management System (HVAC, lighting controls) 

CEEP  Community Energy Efficiency Program (the Grant) 

CHP  Combined heat and power unit, also known as a cogeneration unit 

CO  Carbon Monoxide 

Cogen  Cogeneration system – gas powered generator that produces electricity and heat on site 

COP  The coefficient of performance or COP (sometimes CP) of a heat pump is a ratio of heating or cooling provided to electrical energy consumed. Higher COPs equate to lower operating costs. 

CTs  Current transformers 

FAC  Frankston Arts Centre 

FCC  Frankston City Council  

Fuel Cell  A fuel cell is a device that converts the chemical energy from a fuel into electricity through a chemical reaction with oxygen or another oxidizing agent 

Genset  The cogeneration unit 

GHG  Greenhouse gases 

HVAC  Heating Ventilation and Cooling System 

ISOQAR  ISOQAR is an accredited certification body. This means that ISOQAR is  accredited to audit organisations against a variety of ISO management  standards. On a day‐to‐day basis, this work is regulated by the ANSI‐ASQ  National Accreditation Board (ANAB).  

ISOQAR is an independent, third‐party certification body without affiliation to any other company or organization. It assesses a wide range of manufacturing and service organizations, both throughout the US and across many parts of the world. 

Microgen  Micro generators in the form of BlueGen, Yanmar and Qnergy systems 

MSB  Mechanical Switch Board 

NOx  Nitrous oxide 

Precinct  Frankston Arts Precinct including FAC, Library, Youth Resource Centre, Carpark and Cube 37 Gallery. Cube 37 was logistically unable to benefit from the trigen output at this stage.  

Redundancy  Can work independently of complimentary system (e.g. HVAC can run independently of Trigeneration system if required) 

SOFC (Solid Oxide Fuel Cell) 

A solid oxide fuel cell (or SOFC) is an electrochemical conversion device that produces electricity directly from oxidizing a fuel. Fuel cells are characterized by their electrolyte material; the SOFC has a solid oxide or ceramic, electrolyte. Advantages of this class of fuel cells include high efficiency, long‐term stability, fuel flexibility, low emissions, and relatively low cost. The largest disadvantage is the high operating temperature which results in longer start‐up times and mechanical and chemical compatibility issues 

Trigen  Trigeneration system – includes a cogeneration system and an absorption chiller 

Turnkey  A complete system, ready to go (turn the key) 

VSD  Variable Speed Drives 

 

Page 5: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 5  

 

EXECUTIVE SUMMARY 

 

The Frankston Arts Precinct trigeneration and microgeneration project showcases alternative energy and reduce 

carbon emissions for the Frankston Arts Precinct (the Precinct), which includes the Frankston Arts Centre (FAC); Cube 

37 Gallery, Library and Youth Resource Centre. During the project, it was ascertained that Cube 37 was deemed 

unviable to be connected to the trigeneration output at this stage.  

The main purpose of the project was to reduce greenhouse gas emissions. As Council’s highest energy user, the 

Frankston Arts Precinct’s energy use is also a significant contributor to Council’s overall greenhouse gas emissions. The 

Community Energy Efficiency Project aimed to help local government reduce greenhouse gas emissions. Additional 

benefits of the project will be ongoing operational savings and capacity building of the community by showcasing 

innovative alternative technologies in a local situation.  

As Frankston City Council’s highest energy user, the FAC contributes significantly to Council’s greenhouse gas 

emissions, energy usage and costs. The Precinct was identified in Council’s Alternative and Renewable Energy Study 

(Enhar, 2011) as a suitable candidate for trigeneration. Further studies included CarbonetiX 2009   Energy Efficiency 

audit and Recommendations, and Mito Energy Feasibility Study (2012).  

The project aims to reduce pressure on the electricity grid, particularly during peak times such as heatwaves, and 

reduce Council’s dependence on brown coal generated electricity which has a high carbon coefficient; and contribute 

towards Council’s Carbon Neutral 2025 target, alternative energy target and annual emissions targets of 12,254 to 

11,794 tonnes CO2‐e over the next few years. 

With the CEEP grant, Council was able to install a 120kW‐e trigeneration engine, thermal and absorption chiller, and 

three microgeneration units – BlueGen Fuel Cell, Yanmar internal combustion engine and a Qnergy sterling engine. 

Installations occurred in the latter part of 2014 and early 2015.  

Cogeneration is more efficient than sourcing electricity from brown coal due to the amount of grid losses with 

traditional electricity and the ability to capture waste heat from a cogeneration system and utilise it for both heating 

and cooling (trigeneration). Coupling Trigeneration (Cogeneration + chiller) with the microgeneration system (hot 

water) essentially creates “quad generation” in that there are four key outputs from the overall integrated systems: 

Electricity, Heating, Cooling and Hot water.  

A comprehensive communications strategy was implemented to advise and engage users on the works being done, to 

encourage behaviour change to support energy conservation initiatives, and embrace alternative electricity 

generation as an acceptable energy efficiency option.   

Overall objectives were to: 

Reduce energy consumption and GHG emissions of the building by 704 tonnes of CO2‐e per annum, 42% 

reduction in GHG emissions from grid energy demand and grid electricity savings of $41,270 

Contribute towards Council's Carbon Neutral 2025 target, alternative energy target and annual targets of 

11,794 tonnes CO2‐e by 2016/17.  

Future proof the precinct against climate change and blackouts/brownouts during heatwaves 

Showcase alternative energy sources in small and large scale with a world first comparison display of 

microgen systems 

Page 6: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 6  

 

A range of technologies were used to achieve the project objectives including: 

Trigeneration  

Absorption chiller 

BlueGen Fuel Cell 

Yanmar microgeneration system 

Qnergy sterling engine 

A range of communication and education activities supported the project and its promotion including:  

Development and implementation of the Heating and Cooling Policy, known as the Thermal Comfort 

Guidelines 

Installation of a real time energy display system  

Educational Projector show about the project 

Meetings, emails and briefings 

Councillor bulletins; Media Release about the project; Energy efficiency articles in local media/newsletters  

Sustainable Homes “Energy Busters” Workshops for the Frankston City community.  

Energy performance outcome monitoring will commence once the system is completely operational in April.  

A range of social benefits are already apparent with improved energy efficiency awareness and positive feedback from 

community workshops. Staff awareness of energy usage of the precinct has also improved, and staff knowledge of the 

emerging technologies and energy efficiency options for Council facilities has also resulted from their involvement 

with the project.   

Council encountered issues with timing and budget due to the technical complexities of the project, and the 

outsourcing of project management for part of the project. This caused several delays and required Council to 

contribute additional funding. A Deed of Variation and several milestone extensions were granted to assist with this. 

The project was over‐budget due to costs coming in higher than estimated at the time of applying for the CEEP grant 

(many tenderers up to double). CPI increases from the grant being written to being awarded and delivered also 

impacted the budget. 

The initial project budget was $1,011,241 with $486,035 being contributed by the Australian Government. The total 

project cost was $1,079,221 with Council making up the additional $67,980. Once grant funds have been received, the 

budget breakdown will be: 

Total project (preliminary figures): $1,079,221 = Australian Government $486,035 + Council contribution $593,186. 

   

Page 7: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 7  

 

SITE OVERVIEW 

The Frankston Arts Centre is a landmark theatre and art gallery located on Davey Street Frankston, Victoria.  

 

The Centre provides community access with workshops, exhibitions, shows, conferences and expos, and youth art 

projects running throughout the year. It plays host to a number of major performances, including regular shows by the 

Melbourne Symphony Orchestra and Victorian Opera, and is a tour venue for the Melbourne International Film 

Festival, Opera Australia and a number of national theatre companies.  

The Centre houses an 800 seat theatre boasting the second largest proscenium arch stage in Victoria, a 60 line fly 

tower and state of the art technical and staking equipment.  

Page 8: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 8  

 

 

Above: Frankston Arts Precinct. Below: Frankston Arts Centre floorplan 

 

   

Page 9: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 9  

 

Below: the 800 seat theatre 

 

PROJECT ENERGY EFFICIENCY ACTIVITIES 

Frankston City Council prepared this project to install a trigeneration system, based on recommendations from the 

Entura Alternative and Renewable Energy Study for Frankston City Council.  

After an intensive engineering review process, the final plant consisted of: 

ENER‐G E‐125 gas generator (Trigen unit) with Rated electrical output 124 kW and Rated heat output 200 

kW. Maximum fuel consumption at rated capacity 36 Nm3/hr 

Shuangliang Eco‐Energy Co. Ltd absorption chiller RXZ(92/84)‐14(12/8)(29.5/35)H2 with Rated thermal 

output 135 kW cooling capacity and coefficient of performance of 0.75  

BlueGen micro‐generator Rated electrical output 1.5 kWe, rated heat output 0.61 kW, maximum fuel 

consumption at rated capacity 9.5 MJ/hr 

Yanmar Micro CHP 3.9kW lean‐burn Miller Cycle engine 

Qnergy external combustion 7.5kW Stirling engine 

Customised Real time energy display system 

This was coupled with the communications program referred to in this document.  

 

 

 

 

Page 10: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 10  

 

Below: ENER‐G Cogeneration system – standard enclosure and internals.  

 

Below: Shuangliang Absorption Chiller Illustration 

 

PROJECT OVERVIEW 

This innovative, high profile project will set the 'jewel in the crown' for investing in best practice and cutting edge 

alternative technology for Melbourne. It will provide a showcase demonstration site for best practice on‐site 

decentralised efficient energy supply, in line with smart grid onsite generation opportunities. Trigeneration and micro 

generation fuel cell technology fits in with the 'big picture' smart grid vision currently being explored by Jemena and 

United Energy. The microgeneration component has been designed to be replicated in residential urban 

developments and other facilities.  

The project creates functional and feasible electricity demand reduction for the Arts Precinct, and is intended to be 

displayed in a way that does not interfere with the access to the Arts Centre when in use when tours are run, such as 

the display board will be located in the public access foyer area and the microgeneration is intended to be placed 

behind a glass wall for easy tour access but not obstructive. The vision is intended to not only inspire other 

organisations to explore cutting edge high tech solutions to reducing emissions, but engage with the entire 

community such that school students may be inspired to pursue a future in science and engineering from gaining an 

understanding of high tech sustainability solutions.  

Page 11: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 11  

 

The Precinct was selected as it is Council's highest energy user. The site has previously undergone extensive energy 

efficient retrofits to reduce energy usage (4.5% reduction in the last quarter compared with the same time in the 

previous year).  

The Precinct also has a high public profile and is the perfect opportunity to 'showcase' a trigeneration system to the 

public, other councils and large organisations who could benefit from replicating the project. 

The Frankston Arts Centre is a significant consumer of energy, consuming approximately 1.2GWh of coal fired grid 

electricity and 3,374 GJ of natural gas annually (2011/12).  

These two energy sources are subject to a range of external economic, environmental and reliability pressures and 

risks, including: 

Increased pressure on the aging grid infrastructure leading to brown outs and blackouts, impacting our 

community’s most vulnerable citizens 

Revenue loss from electricity interruptions 

Significant increases in power supply costs 

Low efficiency conversion and use of grid power sources 

Overall social responsibility to reduce Council’s carbon footprint and contribution to climate change, which is 

already impacting the Frankston municipality through coastal erosion and storm surge, increased heatwaves 

and average temperatures, impacts on wildlife and native vegetation, and increased droughts and flooding 

events.  

On average, the FAC operates between 9am and 5pm on weekdays and weekends, as well as afterhours shows and 

events. Based on this energy use profile, it was recommended by consulting engineers on the project to operate the 

trigeneration system 15 hours a day, five to seven days a week.  

The proposed trigeneration plant was designed to provide Council with greater control over the site’s energy supply, 

reduce pressure on the grid during peak times and heatwaves, and improve reliability of operations through 

guarantees of supplies and redundancy. It will also assist the stabilisation of energy costs and a higher conversion 

efficiency of energy used. It will make significant reductions to both Frankston City Council’s carbon emissions, but 

Australia’s as well.  

Project Stages 

Feasibility (pre‐grant): 

Precinct was identified in Council’s Alternative and Renewable Energy Study (Enhar, 2011) 

CarbonetiX 2009 ‐ Energy efficiency audit and recommendations 

Mito Energy Feasibility Study (2012) including preliminary concept design and preliminary cost benefit 

Grant application 

Design: 

Detailed system design and sizing both cogeneration unity and absorption chiller to fit the Precinct’s electrical 

and thermal requirements 

Detailed design for hydraulic circuits for integration with existing heating water systems 

Complete detailed design of the system’s electrical circuits for integration into the main switchboard inclusive 

of electrical schematics for energy authority approvals 

Page 12: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 12  

 

Complete electrical and gas regulatory submissions and approvals 

Civil Works: 

Construct a plant room structure with large roller doors on either side for housing the trigeneration system. 

Plant room 4m wide, 7.5m long, 2.5m high and bolted to concrete roof 

Complete penetrations through the roof for cogeneration unit exhaust system, ventilation system and 

cooling tower 

Obtain development approvals for all related civil works 

Design and install roof reinforcement (unplanned variation) 

Install chiller and cogeneration unit (trigen) 

Mechanical: 

Complete all gas and water pipework, installation of pumps, valves and heat exchangers, ducting and 

ventilation and assembly of the cogeneration system as described in drawings 

Disconnect plumbing services from old chiller plant on roof plant room and assist in removal by crane 

operator 

Crane plant to roof area and position all trigeneration plant 

Supply and install vertical pipe support posts to clip relevant plumbing services to within plant area 

Plumb in new natural gas supply line from existing. Connect new gas fitting line to tri‐generator with isolator 

OPSO regulator and tested to current gas regulations 

Supply and install all plumbing between the cogeneration unit, absorption chiller and cooling tower including 

all heat exchanges and pumps 

Supply and installation of 20mm cold water supply to new cooling tower from existing 25mm supply in plant 

area 

Assemble and erect flue with silencer, supply and install a flue support bracket 

Plumb in 65mm chilled waste lines from absorption chiller and connect to existing building chiller system on 

the roof plant area 

Supply and install new 50mm copper heating hot water flow and return lines from PXH1 heat exchanger and 

cut into the building heating hot water return line. Full insulation of all lines. 

Pressure test all new services to current regulations 

Supply and install 15mm auto air bleeds at high points of the system and drain valves where required.  

Pipe Extension: 

Plumb in new 50mm 10Kpa copper natural gas supply line from existing gas meter room to serve new plant 

room only 

Extend through the building and connect to tri generator with required valving and marking 

Electrical: 

Page 13: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 13  

 

Design and install all associated electrical engineering 

Supply and install main power feeder XLPE cables and earth (95mm) from genset to MSB 

Supply and install communications cables from genset to MSB 

Install and connect power modulation cable 

 Supply and install current transformers to MSB 

Supply and install all wiring to cogeneration unit control panel 

Supply and install all wiring to trigeneration control board 

Supply and install all wiring to trigeneration switch board 

Supply and install 16mm 4 core and supply to trigeneration switch board 

All labelling as required 

Commissioning of installation 

Installation of Microgen units: 

Relocate hot water services 

Supply and install power feed for sub switchboard in ground floor carpark 

Supply and install power circuit outlets 

Connect microgen units to supply with separate isolators 

Supply and install communications cable area for internet connection 

Integrate microgens mechanically with site’s existing systems 

Installation of the real time energy performance monitoring system 

Below: View of the Frankston Arts Precinct from Playne Street, showing the Library on the left, Arts Centre and 

Flytower in the centre, and Youth Resource Centre and Conference rooms to the right.  

Page 14: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 14  

 

 

 

Data Analysis: 

In order to optimise the trigeneration system, sizing was critical to the success of the project. Appropriate selection of 

the equipment allows integrating with the building’s electrical and thermal profile. This process helps to improve the 

efficiency, longevity and maximises potential financial savings of the cogeneration plant. If the unit is undersized then 

the maximum benefit is not being achieved. If oversized, the unit will frequently modulate, significantly increasing 

maintenance costs or rejecting too much thermal energy, reducing efficiency of the unit.  

Note: Data is based primarily on the Frankston Arts Centre as the highest energy user of the Frankston Arts Precinct. 

Data analysis and ground proofing of infrastructure deemed that Cube37 should not be connected to the trigeneration 

system. In the future, excess heat from the system may be used at Cube37 if infrastructure allows.  

Below: Daily analysis of maximum, minimum and average load profile 

 

The FAC’s peak electrical load is 440kW and the average electrical consumption is 213kW. 

Page 15: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 15  

 

 

The graphs are based on interval data of half hour electrical demand, over 15 hours a day, 5 days a week. The graph 

represents instantaneous electricity as a curve (blue line) with electricity consumption on the vertical axis and reading 

number on the horizontal axis with these readings reordered from highest to lowest in order to illustrate: 

Total electrical consumption (total area under the curve) 

Peak consumption (left hand side of the curve) 

Base load of the site and the amount of power supplied by the cogeneration system.  

The green line represents the cogeneration electrical production. The amount of demand that can be satisfied by the 

cogeneration system is represented by the area under the green curve. The red line indicates the new load profile of 

the FAC after installing the complete trigeneration system due to chiller offset. The cogeneration line drops off at low 

electricity demand as the unit will not be operated at less than 50% of its rated capacity.  

3D schematic of location (Illustrated below) 

The trigeneration system is located on the roof level 

plant room of the FAC. The layout is demonstrated 

below. The entire trigeneration system is located 

between the Powerpax adiabatic chiller (bottom left 

box) and the building ventilation outlet (top right box).  

The positioning was extremely tight as the plant room 

is limited for space. The diagram below shows the 

cogeneration unit (long white unit – top right), 

absorption chiller (blue unit – bottom right), Cooling 

tower (white cube with wide exhaust on left hand 

side), pumps, piping and heat exchangers. All of these 

items had to fit where the existing York chiller was 

located prior to removal for the project.  

Number of readings (sorted) 

Page 16: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 16  

 

PROJECT OBJECTIVES  

Frankston City Council’s project aimed to improve the energy efficiency of the Frankston Arts Precinct. The anticipated 

outcomes from this project included a reduction in energy expenditure, pressure on the grid, air pollution and 

greenhouse gas emissions. Additional project outcomes included the trial of innovative technology in a world first trial 

to demonstrate the infrastructure side by side to encourage the adoption of improved energy management practices 

within councils, organisations and the broader community. 

Additional benefits were to provide better services for the community facility by reducing pressure on the grid leading 

to brown outs and black outs, minimising energy consumption and costs to manage the impacts of the carbon price 

and rising energy costs compared with business as usual, build knowledge and capacity of the energy services and 

construction industry around the microgeneration demonstration trial site, support competitive Australian energy 

efficiency technology and equipment manufacturers, in particular BlueGEN, and of course to contribute to the 

national effort to reduce greenhouse gas emissions. 

The primary objectives of the project were to:  

Reduce energy consumption and GHG emissions of the building by 704 tonnes of CO2‐e per annum, 42% 

reduction in GHG emissions from grid energy demand and grid electricity savings of $41,270 

Contribute towards Council's Carbon Neutral 2025 target, alternative energy target and annual greenhouse 

target of 11,794 tonnes CO2‐e by 2016/17 

Future proof the Precinct against climate change and blackouts/brownouts during heatwaves 

Showcase alternative energy sources in small and large scale with a world first comparison display of 

microgen systems  

The broader project objectives were to showcase alternative energy and reduce carbon emissions for the Frankston 

Arts Precinct, which includes the Frankston Arts Centre, Cube 37 Gallery, Library and Youth Resource Centre. As 

Council’s highest energy user, the FAC contributes significantly to Council’s greenhouse gas emissions, and contribute 

towards our Carbon Neutral 2025 target, alternative energy target and annual greenhouse gas emissions targets of 

12,254 to 11,794 tonnes CO2‐e in the next few years. 

The Precinct was identified in Council’s Alternative and Renewable Energy Study (Enhar, 2011) as a suitable candidate 

for trigeneration. Further studies included CarbonetiX 2009 ‐ Energy efficiency audit and recommendations, and Mito 

Energy Feasibility study (2012).  

The project aimed also to reduce pressure on the electricity grid, particularly during peak times such as heatwaves, 

and reduce Council’s dependence on brown coal generated electricity which has a high carbon coefficient.  

With the CEEP grant, Council was able to install a trigeneration system including absorption chiller, and showcase 

three micro generation units in a world first comparison trial, consisting if a BlueGen fuel cell, a Yanmar engine and a 

Qnergy Stirling unit.  

A comprehensive communications strategy was implemented to advise and engage users on the works being done, to 

encourage behaviour change to support energy conservation initiatives, and embrace alternative electricity 

generation as an acceptable energy efficiency option.   

Project overview: 

Utilise the gas‐fired trigeneration plant to power the facility, as well as provide heating and cooling. This will 

significantly reduce the amount of electricity required to run the facility.  

In order to showcase the trigeneration and high efficiency fuel cell system to the community, they will be 

incorporated into the regular tours of the Arts Centre that are currently run.   

Page 17: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 17  

 

Installation of the trigeneration and microgeneration plant aims to reduce electricity use and greenhouse gas 

emissions in the Precinct by the following: 

Tri‐generation system potential savings evaluation: 

Estimated Net annual cost savings $34,772 ex GST 

Estimated Simple payback (excluding annualised maintenance costs) 14.4 years 

Estimated GHG Savings 622 CO2–e tonnes per annum 

Estimated GHG percentage saving 34% (against 2011/12 emissions generated by the Precinct) 

Micro‐generator potential savings evaluation: 

Estimated Net annual cost savings $6,498 ex GST 

Estimated GHG Savings 82 CO2–e tonnes per annum 

Estimated GHG percentage saving 4% (against 2011/12 emissions generated by the Precinct) 

This equates to total savings of: 

Estimated Net annual cost savings $41,270 ex GST 

Estimated GHG Savings 704 CO2–e tonnes per annum (electricity only – excludes gas emissions) 

Estimated GHG percentage saving 38% (against 2011/12 total Precinct emissions) – electricity only 

Anticipated outcomes: 

a) Deliver strong investment returns through future cost savings, reduced impact of uncontrolled external 

electricity price increases, greater efficiency and increased monitoring and scrutiny of energy production and 

consumption. 

b) Encourage more generalised improved energy management within the Precinct by creating awareness of 

energy efficiency initiatives by recording and reporting energy demand reductions and efficiency 

improvements. 

c) Expand the community’s understanding of the potential for energy efficiency and CO2 abatement 

improvement opportunities. Create awareness of the cost savings that could be derived along with the 

reduced CO2 emissions through implementation of energy efficient technology and alternative energy.  

Project Energy Efficiency Activities   

The technologies used were selected as they were the leading products on the market at the time of undertaking the project, offering great ‘bang for buck’ and long term energy savings without compromising on quality.   The technologies selected were also to showcase emerging technology in microgeneration, which can be demonstrated and replicated on small and large scales, offering excellent community and industry engagement opportunities and a world‐first trial to run the three different units side by side for comparison.    Cogeneration is more efficient that sourcing electricity from brown coal due to the amount of grid losses with traditional electricity and the ability to capture waste heat from a cogeneration system and utilise it for both heating and cooling (trigeneration). Coupling Trigeneration (Cogeneration + chiller) with the microgeneration system (hot water) essentially creates “quad generation” in that there are 4 key outputs from the overall integrated systems: Electricity, Heating, Cooling and Hot water.  

Page 18: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 18  

 

   

  How combined Trigen and Microgen works  

   Estimated System Outputs 

Page 19: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 19  

 

Assuming the tri‐generation system runs for 15 hours per day, 5 days a week: 

Annual kWh produced – Cogeneration  476,160 kW of electricity 

Annual kWh produced Microgen  5760 kW of electricity 

Annual CHW produced  576,000 kW of cooling 

Annual HHW produced  768,000 kW of hot water 

Estimated system carbon offset KgCO2‐e/annum  524 tonnes (704 tonnes excluding gas emissions) 

Annual carbon offset micro Gen KgCO2‐e  66 tonnes 

Annual electricity consumed (kWh)  15,936kW 

Annual oil consumed (Litres)  Negligible 

Annual gas consumed (GJ)  5294.59 GJ 

 

The System  

The equipment that makes the trigeneration system operate is a CHP (cogeneration) unit, an absorption chiller, two 

heat exchangers (a heating heat exchanger and a heat rejection plate heat exchanger) as well as associated pumps 

and control valves. In addition 3 microgeneration units were installed to supply further electricity and hot water to the 

site, without the large carbon emissions.  

 

Below: Single line diagram of the trigeneration system 

 

 

 

 

 

 

Page 20: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 20  

 

Below: Trigeneration system schematics 

 

Daily operations 

The cogeneration unit is primarily operated on a time clock for 15 hours a day (7am to 10pm daily) which reflects the 

high peak and shoulder electrical tariffs on weekdays.  

The unit can be operational from 50‐100% of its capacity. When the system fires up, it synchronises with the grid and 

takes over the electrical feed of the centre through a parallel grid connection. If the load on the centre is above the 

amount supplied by the cogeneration and microgeneration units, the additional electricity required is imported from 

the grid. If the load on the centre drops below 50% of the capacity of the cogeneration unit, the unit unloads power to 

the grid and the grid takes up the excess load of the building.  

The cogeneration system can also be remotely started or stopped by the Building Management System (BMS) and a 

manual on/off control within the cogeneration unit. These systems gradually unload the electricity off the generator 

to a final system stop. This is known as a soft stop. The system also has a hard stop, or emergency stop, for when the 

emergency stop button is pushed, or if a serious error or fault signal from the engine is detected. If this occurs, the 

Page 21: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 21  

 

generator circuit breaker (GCB) is instantly opened allowing the generator to slow to a stop. In this instance the 

building is powered from the grid.  

All other components of the trigeneration system rely on the cogeneration unit being operational.  

The trigeneration component consists of the cogeneration unit, chiller, pump and switchboard. Other components 

include: 

Component  Description 

CHP unit  ENER‐G 125 indoor with standard enclosure rated at 70dBA at 1m (free field) and included ventilation fan integrated to top of unit 

Air‐fuel ratio controller  Controls the air‐fuel mix that enters the engine to ensure clean and efficient combustion 

Catalyst  Reduces NOx levels below 250mg/m3 according to NSW Office of Environment and Heritage (OEH) regulations. Treats exhaust gas to reduce CO and NOx emissions in conjunction with air‐fuel ratio controller 

Exhaust silencers  Residential grade low noise primary and secondary stainless steel exhaust silencers 

Ventilation air outlet attenuator 1D 

Reduces noise produced by ventilation fans on top of the unit 

Gas meter and temperature compensated 

Measures the volume of gas consumed by the CHP unit – pressure and temperature compensated 

Heat meter  Measures total thermal energy rejected – allows performance auditing 

Electrical meter  Measures gross electrical output  

Secondary water pump  Standard fixed speed, single head secondary water pump 

 

 

Page 22: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 22  

 

    

Page 23: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 23  

 

Trigeneration 

Ener‐G Co‐generation (CHP) system 

Ener‐G is Europe’s leading supplier of cogeneration systems from 4kWe up to 10MW.  ENER‐G have manufactured over 2500 Cogeneration units to date which are operating in 11 countries across the globe in a wide range of sectors such as: Hospitals, Leisure Centres, Food and Beverages, Aquatic Centres, Museums, Hotels, Schools, Universities, Manufactures, Commercial Buildings and Agricultural sectors.  This system is manufactured in the United Kingdom.  The unit can be run on: 

Natural Gas 

Biogas 

Vegetable gas 

Landfill Gas 

Mining Gas 

Propane 

Biodiesel 

Pure plant oil (PPO) 

 

 

Specifications of the Frankston Arts Precinct genset are: 

Unit designation  ENER‐G 125 

Electrical output  125kW (e) 

Heat output  200kW (th)  

Fuel type  Natural gas 

Voltage  400V 3 Phase 50 Hz 

Electrical efficiency at 100%  34.3% 

Thermal efficiency at 100%  55.4% 

Total efficiency  89.7% 

Page 24: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 24  

 

Expected lifespan  20 years 

 

ENER‐G cogeneration systems reached the marketplace in 1984 and are built using high end technology. The unit has 

a sophisticated externally monitored control system, managing the engine, air charge, hot water, oil level and fuel 

supply, with the ability to diagnose faults and malfunctions as they occur.  

The quality management system of ENER‐G Combined Power has been approved by ISOQAR, to the standard of 

ISO9001:2008 including the design, manufacture and service of Combined Heat and Power units for hotels, hospitals, 

leisure centres and industrial applications.  

How it works 

 

 

Page 25: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 25  

 

 

Below: 3D views of the trigeneration plant showing positioning and shelter structure 

 

Monitoring and Reporting 

An integral part of every Cogeneration system is the patented on‐board control system. The system monitors and 

Page 26: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 26  

 

manages the CHP unit and is programmed to optimise its operation to suit the demands of the site. From a client’s 

perspective, the Cogeneration unit is simply ‘fit and forget’. 

 

Logistics ‐ Challenges 

Site access was difficult, in location, size and structure.  

Unplanned structural reinforcements were necessary at a cost of $36,714 to support the weight of the unit.  

The footprint of the plant room is also very tight, resulting in other modifications being required, and very careful 

planning of plant layout.  

Equipment had to be craned up onto the plant room which required a large crane, access from a neighbouring 

property, and ideal weather conditions to conduct the lift safely. In all, several lifts were completed, including 

removing the old chiller, lifting the new chiller, lifting the tri‐gen unit, all wiring, pipes and connections, and finally a 

shelter had to be constructed and lifted to protect the unit from the coastal conditions (salt spray).  

Below: Aerial view of positioning of trigeneration system.  

 

 

 

 

Page 27: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 27  

 

Below: Thermal System Logic – detailed mechanical schematic for Frankston Arts Precinct.  

 

Heat generated and captured as a result of electrical production is a product of the engine jacket water heat, the 

exhaust’s heat and the oil’s heat. These three heat sources are captured, isolated with heat exchangers and passed 

onto the trigeneration system’s secondary circuit.  

Absorption Chiller 

An absorption chiller is a refrigerator that uses a heat source (e.g., 

Cogeneration System, Solar, Natural Gas, Biogas) to provide the 

energy needed to drive the cooling system.  

The waste hot water from the cogeneration system is transferred to 

an absorption chiller – thus creating tri (three) generated outputs 

from co (two) generated outputs.  

The absorption chiller uses waste heat to create cooling thereby 

reducing the requirement of using a standard chiller to create the 

same amount of cooling with additional grid electricity.  

Shuangliang chillers have 40% of the market share in China and 

around 15% worldwide. More than 20,000 Shuangliang chillers are in operation around the globe, resulting in 

significant energy savings equivalent to saving 22.5 million tonnes of coal, 57.6 million tonnes of CO2 and 85,000 

tonnes of SO2 – the equivalent of planting 160,000ha of forest every year.  

Features of Shuangliang absorption chillers: 

Over 20,000 in operation worldwide 

15% of world market share 

Waste, steam or hot water fired 

Highest COP 

Lower energy consumption  

Page 28: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 28  

 

Double sealed mechanical vacuum 

Auto purging system 

Auto de‐crystallisation system  

Insulated  

 

Switchboard – Central Control System 

A dedicated central control system was installed with the unit. Below is the design for the central control system. The 

board controls when all the units start and stop, and provides a central point of operational control and monitoring.  

Below: trigeneration control board schematics 

 

“Smart” controllers 

The trigeneration electrical board is programmed to sense that the cogeneration unit is operational. After a 30 minute 

time delay to stabilise system temperatures and to allow a current flow of water in the chilled water system, a signal is 

sent to the chiller to allow it to become operational.  

The electrical signal from the chiller for the condenser water pump also initiates the cooling tower to operate. Once 

the chiller has received the pump interlock signals, the chiller begins to open the hot water 3 way valve and adjusts it 

according to the inlet temperature of the chilled water. The chiller also controls a number of pumps including a 

refrigerant pump, an automatic vacuum pump and one VSD solution pump according to the pressure in the 

generator/compressor system.   

Unless stopped, the chiller will continue running and modulating the hot water input until it loses any of the original 

signals, which will cause the shutdown sequence to begin.  

   

Page 29: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 29  

 

Below: trigeneration control board 

 

Heat system 

The heating circuit set adds heat to the building’s heating circuit prior to the heated water returning to the building’s 

boilers, thereby reducing the gas requirement of the boilers.  

A low head loss plate heat exchanger was added to the boiler return water line through the use of 2 x 3 way diversions 

and a high flow balancing valve.  

A temperature probe in the water line from the heat exchanger was installed to allow an automatic set point of 70 

degrees, which is not impacted by variations in the flow rate or intake temperature into the heat exchanger. At this 

temperature, the boiler should not need to fire at all.  

Heat rejection system 

The heat rejection system operates with its own pre‐set control system which maintains the maximum temperature of 

80 degrees back into the cogeneration system.  

Secondary water pump 

The secondary water pump is controlled and operated by the cogeneration unit. The pump is a temperature 

controlled VSD pump with a target cogeneration outlet temperature of 90 degrees. The system allows both the 

absorption chiller and the heating system equal priority, while still providing the absorption chiller with the hottest 

available water, further increasing the efficiency and effectiveness of the system.  

Microgeneration 

Advice from consulting engineers altered the original scope of the project. Initially, a bank of five BlueGens was to be 

used to showcase Australian alternative technology suitable for domestic and commercial applications.  

Page 30: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 30  

 

However with BlueGen closing its Australian manufacturing (research and development remains in Australia) and the 

emergence of successful applications of alternative microgeneration plant of Qnergy and Yanmar, a proposal to 

showcase these three different microgeneration systems in a world first side‐by‐side comparison was proposed.  

The table below compares the various parameters and efficiencies of the three different units: 

  BLUEGEN  QNERGY  YANMAR 

Country of Origin  Australia/UK  Israel/USA  Japan 

Technology  Solid Oxide Fuel Cell (chemical conversion of predominately CH4 derived from natural gas) 

Stirling Engine (external combustion engine using a variety of fuels) 

Internal combustion (predominately natural gas) 

Electrical Power Output – Maximum 

1.5kW  3.5kW or 7.5kW  3.9kW / 10kW  

Thermal Power Output – Maximum 

0.61kW  14kW or 30kW  8.38 kW / 17.3 kW 

Electrical Efficiency (max)  60%  LHV  20% LHV  26.7% / 30.7%  

Thermal Efficiency (max)  25%   83% LHV  57.8% / 53.3 

System Efficiency (max)  85% LHV  103% LHV  (95% HHV)  84.5% / 84% 

Specific Gas Consumption/kWe 

6.33 MJ/kWe/Hr  18.30 MJ/kWe/Hr  13.33 MJ/kWh/Hr 

Specific Gas Consumption/kW total 

4.50 MJ/kW/Hr  3.65 MJ/kW/Hr  4.22 MJ/kWh/Hr 

Outlet water temp  deg C  65   80  65 / 70  

Sounds level @ 1 meter  47 dB(A)  50 dB(A)  51 dB(A) / 54 dB(A)  

Start‐up time (to operating temp) 

25 hours  15 mins  5 mins 

Shut‐down time  72 hours  3 mins  3 mins 

Lifetime  10‐15 years  >60,000 hours  Unknown 

Scheduled maintenance and service 

Regular maintenance ‐ filters and gas de‐sulphuriser (6‐12 months).  Major maintenance  ‐ fuel cell stack  

None required  Every 10,000 hours 

Weight  195kg  200kg (7.5kW)  410kg / 790kg 

Approx. Cost Per Unit (excluding installation) 

$30,000 (for purchase of 5 units) 

$19,000 / $25,000  $30,000 / $40,000 

$/kWe  $20,000  $5,400 / $3,333  $7,600 / $4,000 

$/kW total  $14,200  $1,085 / $666  $1,730 / $1,465 

Advantages  Highest electrical efficiency 

Very quiet 

Lowest electrical specific gas consumption 

 

Lowest price per kW; Highest overall efficiency; Very quiet 

Lowest maintenance 

Lowest overall specific gas consumption 

Highest (most useful) 

Moderate price per kW 

Shortest start‐up/ramp time 

 

Page 31: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 31  

 

  BLUEGEN  QNERGY  YANMAR 

output water temp  

 

Disadvantages  Longest start‐up/ramp time  

Highest price per kW 

 

Lowest electrical efficiency 

Unknown  

 

These units will be compared over the coming year to build a case study on the different features and suitability for 

different applications.  

Below: Location of microgen, hot water and viewing area (prior to construction) 

BlueGen 

The BlueGEN unit converts natural gas to electricity and heats 

hot water, via a chemical reaction, not combustion. 

BlueGen® is the world's most efficient, small‐scale electricity 

generator, delivering up to 60 per cent electrical efficiency. 

At peak efficiency, BlueGen delivers approximately 13,000 

kilowatt‐hours of low‐emission electricity per year. That's 

more than enough for the average home. 

Optional waste heat from BlueGen can be recovered to 

provide 200 litres of domestic hot water per day. This 

increases total efficiency to approximately 85 per cent. 

Installable inside or outside, BlueGen is virtually silent. It has a 

wide operating range and can be used to balance electricity 

from intermittent renewable sources such as solar and wind. 

BlueGen uses fuel cell technology in the form of solid oxide 

fuel cell (or SOFC). SOFC is an electrochemical conversion 

device that produces electricity directly from oxidizing a fuel. 

Fuel cells are characterized by their electrolyte material; the SOFC has a solid oxide or ceramic, electrolyte. 

Advantages of this class of fuel cells include high efficiency, long‐term stability, fuel flexibility, low emissions, and 

relatively low cost. The largest disadvantage is the high operating temperature which results in longer start‐up times 

and mechanical and chemical compatibility issues. 

   

Page 32: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 32  

 

Below: How an SOFC works inside a BlueGen unit 

 

 

 

 

 

 

   

CH4 

CO2  N 

Page 33: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 33  

 

 

Below: Schematic of how the overall BlueGen system works 

 

Simons Green Energy proposed BlueGen units supplied by Ceramic Fuel Cells, an Australian based company (at the 

time) and a world leader in commercialising Solid Oxide Fuel Cell (SOFC) technology to generate efficient, low 

emission electricity from widely available gas and natural fuels.  

 

Page 34: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 34  

 

BlueGen features 

 

Yanmar 

YANMAR Energy System Co., Ltd. is the world’s largest manufacturer of Micro Cogeneration, also called Micro 

Combined Heat and Power.  Yanmar’s long experience and technical mastery of engine manufacturing has provided 

the base for the precise manufacture of a range of small, economic and efficient energy systems. 

YANMAR Micro CHP or cogeneration units generate electricity and heat from natural gas or biogas utilising a lean‐

burn Miller cycle engine with waste heat recovery.  The unit is housed in an acoustically attenuated enclosure suitable 

for all‐weather conditions. The system includes remote monitoring and diagnostics for optimal performance.  The 

YANMAR Micro CHP range includes 5kW, 10kW and 25kW units that can be “daisy‐chained” for increased output and 

will load follow to suit any sites instantaneous electricity demand. 

What is Yanmar 

The YANMAR engine is a gas powered generator producing electricity with half the emissions of electricity from coal.  

Yanmar Micro Cogeneration Packages (CP) are small footprint cogeneration units that generate electricity and hot 

water using gas.  

This high efficiency typically leads to lower energy costs and reduced CO2 emissions compared to remotely generated 

electricity from the power grid. Yanmar has a low operating noise and a range of output classes, individual CP units 

can be used in a huge range of smaller applications, and for higher power applications multiple units can be controlled 

Page 35: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 35  

 

together as a higher output system using the Yanmar System Controller.  

Yanmar has a blackout start option that can provide a higher level of power security. 

Below: A YANMAR unit 

 

   

Page 36: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 36  

 

Below: our Yanmar unit in situ 

 

Below: Yanmar serial plate 

 

 

Page 37: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 37  

 

How Yanmar works 

Energy from gas drives a gas‐engine, the engine then drives electricity generator. During operation heat from the gas 

engine is reclaimed and used to supply hot water from the unit. 

 

Yanmar uses asynchronous power generation so that the unit can be operated at the best point for efficiency, 

reliability and long‐life independently of the external power supply frequency. Connection to external power supply 

networks is made using inverters which gives great flexibility and simplifies connection of the unit. 

 

Key benefits 

Reduces overall energy and production costs 

Turns naturally occurring methane from effluent into usable energy 

Produces alternative electricity for site consumption 

Produces alternative heat ideal for other thermal requirements 

Remote monitoring and diagnostics 

10,000 running hours between scheduled maintenance with up to 15 year project life 

 

Page 38: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 38  

 

  

History of Yanmar 

Yanmar Energy System is part of the YANMAR group of companies, first founded in 1912 in Japan to produce gas 

engines.  Over the century, YANMAR expanded its engine manufacturing from small to large scale gas and diesel 

power engines for various applications including seagoing vessels, construction equipment, industrial and agricultural 

equipment, air conditioning and  generator sets. 

Since early 1900s, YANMAR has enjoyed constant product development and global expansion, including new 

production facilities in Asia, Europe and America in the 1990s. With an annual turnover of $470 million and over 

16,600 staff in offices around the world, YANMAR has become the leading manufacturer of small Cogeneration energy 

systems.  

Fuel sources 

Natural Gas 

Propane 

Biogas 

Qnergy 

The 7.5 kWe Qnergy's Free Piston Stirling Engine (FPSE) concept, offers high performance, almost zero maintenance 

and unsurpassed reliability. 

The external combustion engine produces electricity while transforming all of the remaining thermal power into 

useable heat.  

As an external combustion engine, they may utilise multiple fuel sources. 

 

Below left: Qnergy unit in casing; right: Stirling engine 

Page 39: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 39  

 

 

PROJECT DEMONSTRATION AND COMMUNICATIONS ACTIVITIES   

The project’s activities were intended to demonstrate and communicate alternative energy and energy efficiency 

activities and their effectiveness.  

Key stakeholders were internal staff in regards to the installations and day to day contact with the technologies. The 

broader community was seen as a stakeholder in demonstrating responsible spend of public funding, and the 

educational opportunities to inspire the community to think about their own energy efficiency opportunities.  

This was done in a number of ways.  

Internal Stakeholders (Staff) 

The following tools were used for staff engagement and education: 

Development and implementation of the Heating and Cooling Policy, known as the Thermal Comfort 

Guidelines 

Installation of a real time energy display system  

Meetings, emails and briefings 

Councillor bulletins 

 

External Stakeholders (Community) 

The following tools were used for community engagement and education about energy efficiency in general, and 

about the project: 

Energy efficiency articles in EnviroNews newsletter (Council’s monthly environment newsletter to 3000+ 

residents) 

Media Release about the project 

Energy efficiency articles in Frankston City News (Council’s quarterly newspaper that is delivered to every 

household in the municipality) 

Sustainable Homes “Energy Busters” Workshops and handouts (general) 

Further detail about the activities is below.  

Page 40: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 40  

 

  

Thermal Comfort Guidelines 

Thermal comfort guidelines were adapted for the Arts Precinct from existing guidelines written for office 

accommodation.   

The purpose of the guidelines is: 

To reduce energy consumption by agreeing on summer and winter set points for heating and cooling 

To increase efficiency through set guidelines 

To clarify processes in managing HVAC temperatures.  

   

Frankston City Council has successfully secured two energy efficiency grants under the 

Federal Government's Community Energy Efficiency Program (CEEP). 

  

Frankston City Council Arts Precinct Tri‐Generation and Microgeneration Project ‐  

Installation of a tri‐generation system to replace the heating and air conditioning and hot 

water systems. Total project cost $1,011,241; CEEP Funding granted $486,035. 

 

The project aims to achieve savings of: 

•  Net annual cost savings $41,270 

•  GHG Savings 704 CO2‐e tonnes per annum 

•  GHG percentage saving 42% (against current total Precinct emissions) 

 

This innovative, high profile project will showcase trigeneration and micro generation fuel 

cell technology. The trigeneration system will use a gas‐powered generator to generate 

electricity and recover heat for the facility’s heating and cooling without relying on coal 

generated electricity. 

 

The Frankston Arts Precinct has been selected for this project as it is Council's highest 

energy user. The site has previously undergone extensive energy efficient retrofits to 

reduce energy usage (4.5% reduction in the last quarter compared with the same time in 

the previous year).  

~ Councillor Bulletin 

Page 41: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 41  

 

Thermal Comfort Guidelines highlights: 

Frankston Arts Precinct Thermal and Ventilation Comfort Parameters 1. warm water temperature ranges. Optimum: 23 ‐ 25 0C. Acceptable: 20 ‐ 26 0C. 

2. cool weather temperature ranges. Optimum: 19 ‐22 0C. Acceptable  18 ‐ 24 0C  

3. room temperature is to be measured & controlled between 1.2 – 1.6 metres from floor level in accordance with industry guidelines 

4. optimum humidity range 40 ‐ 60% 

5. minimum recommended fresh air rate 10 litres per second (l/s) per person or 10 l/s per 10 m2 for mechanical ventilation systems 

6. optimum air movement 0.1 ‐ 0.5 m/s (naturally ventilated), 0.1 ‐ 0.2 m/s (air‐conditioned) 

NOTE: Council has adopted an optimum warm weather temperature range of 23 ‐ 25 0C and optimum cool weather 

temperature range of 19 – 22 0C as a balance of comfort and economy.  

Warm and cool weather can change on a day to day basis which is why the terms ‘warm season’ and ‘cool season’ 

have been avoided.  

Attached: Thermal comfort guidelines document.  

 

Viewing Display area 

A viewing display area was constructed to serve as a community education/communications point for the systems. 

This allows high visibility of the microgeneration units, signage and real time energy display monitor for the general 

public at any time, and is the focal point of the technical tour.  

Below: Construction of the Viewing Display area 

 

Page 42: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 42  

 

Below: The completed Viewing Display area prior to signage installation 

 

 

 

Real time energy display system  

A Real Time Energy Display System was developed by Simon’s Green Energy. It is linked to the monitoring systems of 

the generators, and shows how much electricity has been generated, kg of CO2 avoided and financial savings from the 

system. It is set up as a series of web pages and scrolls through the various screens, allowing the flexibility to modify 

the information being displayed to incorporate videos and static images.  

Screenshots of the system under development are below.  

Page 43: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 43  

 

 

 

 

Page 44: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 44  

 

 

 

   

Page 45: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 45  

 

Signage 

Signage was developed to show the community the information about the systems in the viewing Display area.  

Below: Microgeneration signs *NB: DRAFT only – still being refined 

 

 

Page 46: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 46  

 

 

 

 

 

Page 47: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 47  

 

Community Energy Saving Workshops 

Sustainable Homes “Energy Busters” Workshops to educate and empower the community to understand energy use 

in their own homes, and give them low cost projects to tackle to improve thermal efficiency (general). The following 

workshops were held: 

Date  Location  Presenter  Number of participants 

August 2012  Langwarrin Community Centre 

Ella Boyen, Climate change officer 

October 2012  Karingal PLACE  Ella Boyen, Climate change officer 

31 

March 2013  Frankston Library  Ella Boyen, Climate change officer 

22 May 2013  Lyrebird Community Centre Carrum Downs 

Ella Boyen, Climate change officer 

10 

27 July 2013  Frankston South  Ella Boyen, Climate change officer 

30 

12 Mar 2014  Frankston Library  Ella Boyen, Climate change officer 

21 

17 May 2014  Mahogany Neighbourhood Centre 

Ella Boyen, Climate change officer 

12 

August 2014  43 Davey Street  Ella Boyen, Climate change officer 

86 

September 2014  Seniors Week  Ella Boyen, Climate change officer 

30 

17 Oct 2014  Frankston Library  Ella Boyen, Climate change officer 

18 

November 2014  Belvedere Community Centre 

Ella Boyen, Climate change officer 

14 

 

   

Page 48: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 48  

 

 

Below and Attached: Promotion in EnviroNews 

 

 

 

 

Page 49: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 49  

 

 

 

Below: Screenshots of the some of the slides from the community energy education sessions 

    

    

    

 

Flytower Projector Screen 

The flytower of the FAC has had an outdoor projector installed, in order to educate and engage with the community.  

This screen will be used for promotion of tours and education around the Trigeneration project.  

Below is an example of how items look when projected onto the flytower, followed by the slides developed to 

Page 50: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 50  

 

promote the trigeneration project to the community.  

See attached ‘Media’ supporting documentation for slideshow of Trigeneration for the display.  

Community and Industry tours 

Community tours will be conducted in the coming 12 months to showcase the technology to generate community 

interest in alternative energy, and will be coupled with future energy efficiency workshops. 

Industry tours will be conducted in the coming 12 months to showcase the technology as a case study for other large 

facilities such as hospitals and universities.  

A fact sheet / technical tour notes have been developed as supporting documentation.  

Fact Sheet / Tour notes 

Tour notes in the form of a fact sheet were developed to supplement the industry and community tours.  

Attachment: Fact Sheet and tour notes *NB: DRAFT only – still being refined 

Media 

Key media utilised was Frankston City News (delivered to every house in the municipality) and EnviroNews, emailed to 

over 3000 subscribed residents.  

Below are examples of media communications that have been released to the general public on the project and also 

promoting workshops.  

Attachment: Media clippings ‐ Frankston City News (FCN) clippings 

OUTCOMES AND BENEFITS OF THE PROJECT 

Post implementation evaluation of the project is important to gauge whether the project’s objectives have been 

achieved. Energy consumption, emissions, demand and cost data will be compared pre and post installation of the 

system.  

Page 51: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 51  

 

This data is independently verifiable as the system is internal to the site and comparisons can be assessed through the 

reduction in grid sourced electricity and an increase in natural gas consumption for the site.  

An important benefit of the project is the reduction of pressure on the aging infrastructure of the electricity grid, leading to a higher frequency of black outs and brown outs, impacting the most vulnerable people in our community.  Data from the Bureau of Meteorology and CSIRO show that Melbourne’s weather patterns are changing, with increased frequency and duration of days over 35 degrees. This particularly affects infants, the elderly, and the sick. In reducing pressure from the grid, the Frankston Arts Precinct not only will no longer contribute the brown outs during heatwaves, but potentially provide a refuge for these vulnerable citizens during these times.  

 

Energy metering will be monitored in detail for an initial four week performance analysis period, and then quarterly 

thereafter. Ongoing energy consumption comparisons will be undertaken through the energy monitoring software 

installed as a part of the project, as well and billing and interval data.   

Benefits of the system will be reported internal and to industry and the community to create awareness and 

community support. Reporting of benefits will include statements of cost saving and financial returns where 

applicable, reduction in grid supplied electricity, CO2 abated based on comparative efficiency of grid versus on site 

electricity production and consumption.  

As final commissioning is still underway, Council is yet to receive post implementation data. Comprehensive 

monitoring will be undertaken over the coming 12 months and into the future to assess the successes of the project 

and quantify savings.  

 

Project Energy Efficiency Improvement Template 

PROJECT TITLE   Arts Precinct Tri‐Generation and Microgeneration  PROJECT ID  CEEP1115 

FUNDING RECIPIENT  Frankston City Council  DATE  20 Jan 2015 

   

Name of Building, Facility or Site 1 

Frankston Arts Precinct 

Location (address)  35 Davey Street, Frankston, VIC 3199 

Type of building, facility or site 

Public Building – Theatre, Exhibition, Dining and Library 

Activity Type and Measure  Install Trigeneration and Microgeneration 

Energy Efficiency Estimate Method 

The method used to provide the estimates is based on the 2012 Arts Precinct Cogeneration Feasibility Study with third party verification from an energy consultant.  

Energy efficiency outcomes will be assessed based on the energy savings, greenhouse savings, and electricty cost savings achieved. These will be measured with reference to the IPMVP (International Performance Monitoring and Verification Protocol). 

Date  7 November 2012  20 Jan 2015 

Baseline Energy Usage 

1,333,033 kWh per annum (Arts Precinct 

electricity only) 

Greenhouse gas emissions = 1,843,115 kg CO2e (electricity only), 1,972,771 kg CO2e 

TBA 

Page 52: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 52  

 

(electricity + gas)

Baseline Energy Efficiency 

Arts Precinct 1,333,033 kWh x 3.6 factor / 

18,743m2 = 256 MJ per m2 pa (electricity 

only) 

Arts Precinct 1,333,033 kWh x 3.6 factor / 18,743m2, = 436 MJ per m2 pa (electricity + gas) 

TBA 

Energy Efficiency Improvement 

Electricity only 

Reduction of 546,114 kWh x 3.6 / 18,743m2 

= 105 per m2 pa therefore new Energy 

Efficiency = 151.1 MJ per m2 pa 

Reduction of 703 tonnes CO2 equivalent 

per annum 

Electricity + Gas 

Factoring in estimated increase in gas 

usage, reduction of (546,114 kWh x 3.6) + 

increase of 3,499GJ / 18,743m2 = increase 

of 187 per m2 pa therefore new Energy 

Efficiency = 622.8 MJ per m2 pa 

This however still equates to a reduction of 380 tonnes CO2 equivalent per annum 

Electricity only 

TBA  

Electricity + Gas 

TBA 

Reporting Data (Measuring Energy Efficiency and Additional Data) 

A total area of 18,743 m2 and 60 staff and 

up to 800 occupants 

50 per cent average operational occupancy 

level 

Daily hours of operation: 8am to 11pm 

Building construction date 1994‐5 

A total area of 18,743 m2 and 60 staff and 

up to 800 occupants 

50 per cent average operational occupancy 

level 

Daily hours of operation: 8am to 11pm 

Building construction date 1994‐5 

     

Cost of Activity ex GST  $1,011,240  $1,079,221 Preliminary Final spend 

Estimated Cost Savings  $41,270 per annum  *See annual estimation below: 

 

*Estimated annual savings by year 

2015‐16  2016‐17  2017‐18  2018‐19  2019‐20  2020‐21  2021‐22  2022‐23  2023‐24 

$20,263  $23,449  $26,961  $31,541  $36,656  $42,363  $51,642  $62,039  $67,162 

 

Energy Efficiency savings to date 

Energy efficiency savings to date cannot yet be quantified as the system is still in its final stages of commissioning. This 

report will be updated with available data once the system is commissioned, and intensively monitored for the first 12 

months and then on a quarterly basis. This data can be made available to the Department of Industry. 

Engineers have suggested that the system may have greater economics if run for greater than 15 hours a day. The 

Page 53: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 53  

 

operation hours will be set as 15 hours a day in the initial period and then reviewed to determine if greater savings 

can be achieved through longer operating hours.  

Issues and challenges 

Council encountered issues with timing and budget due to the technical complexities of the project, and the 

outsourcing of project management for part of the project. This caused several delays and required Council to 

contribute additional funding. A Deed of Variation and several milestone extensions were granted to assist with this. 

United Energy has also experienced delays due to staffing issues beyond their control, which has slowed down the 

approvals process. Delays were also caused by the technical nature of the project, structural issues with the plant 

room, and time taken by the contractor to obtain building permits.  

The project was over‐budget due to costs coming in higher than estimated at the time of applying for the CEEP grant 

(many tenders up to double), and with CPI increases from the grant being written to being awarded and delivered, this 

also impacted the budget. With Frankston City Council contributing extra funds, Council was still able to meet all the 

CEEP deliverables. 

The initial project budget was $1,011,241 with $486,035 being contributed by the Department of Industry. The total 

project cost was $1,079,221. Council has made up the overspend with an additional $67,980.  

The project lacked continuity and momentum until the time of tender award, when project management was brought 

in‐house and began running smoothly, to the credit of the project manager in charge.  

Finally, future gas supply charges have been flagged as a challenge. Predictions are that gas costs will rise significantly, 

and Council may need to explore biogas and other sources to mitigate this cost.  

Targets 

It is too early to determine if targets will be met, as the system is not yet fully commissioned at the time of the 

preparation of this report, however preliminary modelling suggests that the infrastructure will meet the targets, and 

operations hours will be reviewed for the greatest efficiencies and saving.  

Other Benefits 

Capacity building of Council staff and contractors has occurred due to the technical nature of the project. Staff have a 

much greater awareness of the complexities of managing a project of this nature, the structural implications and the 

United Energy approvals requirements.  

Further benefits will be seen once the showcase microgeneration trial is in full operation, as the trial will identify 

technologies that can assist industry to explore bespoke alternative energy models for their facilities.  

   

Page 54: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 54  

 

Cost benefits (predicted) 

 

Community impact 

Community awareness of energy efficiency continues to rise as a result of regular workshops and communication.  

The Energy Busters workshops offered the best evaluation opportunity as they are conducted face to face and 

evaluation forms are handed out at every session. Feedback from the community on the workshops and Council’s 

activities has been extremely positive to date.  

BUDGET 

The initial project budget was: 

  Department Funding  Frankston City Council Funding 

Total Project 

CEEP Budget  $486,035  $525,206  $1,011,241 

Frankston City Council has contributed an additional $67,980 to bring total Council contribution to $593,186 to 

compensate for the recent increases in cost.  

Due to being over budget, the actual spend (preliminary figures) was: 

  Department Funding  Frankston City Council Funding 

Total Project 

Actual  $486,035  $593,186  $1,079,221 

 

The project was over budget due to costs coming in higher than estimated at the time of applying for the CEEP grant, 

Page 55: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 55  

 

CPI increases from the grant being submitted to award of tender and project delivery.  

The nature of the technology itself created many budget issues, in such a rapidly evolving industry. Council was 

originally going to issue separate tenders for design (D) and construct (C), but due to a range of timing factors and 

advice from industry engineers, bundled D&C together. This had benefits in both improving time frames, and reduced 

financial and corporate risk of one contractor being accountable for the entire project. It also ensured that equipment 

specified was readily available or able to be constructed within the timeframe.   

The project management and administration funds were used to outsource project management, and were expended 

well before project completion as they were grossly underestimated in using a project management firm rather than 

assigning a staff member for the project. The allocation of reporting and administration time was also greatly under‐

estimated, as negotiations, deeds of variation, financial administration and reporting requirements were often 

detailed and time consuming.  

Another challenge with the budget was the delay relating to payment of invoices, as acceptance of Milestone reports 

was sometimes a lengthy process.  

PROJECT OPERATION, MECHANISMS AND PROCESSES 

The project management was initiated internally, then outsourced, and again brought back internally, which proved to 

be the best model for the project in the long term. The benefits of internal project management were clear, as it gave 

Council greater control over the project at a lower cost. The benefits of outsourcing project management were in the 

expertise and risk management, however with highly capable staff and technical consultants advising on the project 

proved that Council was able to manage risk to the same degree from within.  

The complex and multidisciplinary project also provided excellent professional development for the Project Manager 

and Project working group, who now have a much greater understanding of the technical aspects of trigeneration 

from mechanical, civil, structural, electrical and hydraulic requirements.  

External organisations were involved in the construction phase in order to ensure qualified builders; electricians; 

plumbers etc. were used throughout the project.  

Ideally the project should be reported on by Project Manager, as the one individual would then manage all the 

budgetary requirements, grant requirements, contract and project requirements and internal reporting requirements 

well as Milestone reporting. 

Resources were grossly underestimated at the time of submitting the grant application for such a complex project. 

Learnings from this project include: 

Increasing the lead time for approvals – both internal and external. 

Reporting time – allocate sufficient time for the background work that goes into compiling and interpreting 

data, budgets and deliverables for milestone reporting, and not just the time taken to write up the report. 

Increasing the overall project time frame – the tendering process is lengthy, and due to the technical nature 

of the project, additional time was required to source information and equipment.  

Increase time allocated to gain electricity distributor approvals and building permits. 

Despite the benefits of outsourcing project management, internal project management proved to be the 

most cost effective and efficient. 

All stakeholders and contractors need to be closely managed in order to keep the project on track and 

prevent timelines slipping. Delays can have a snowball effect as a minor delay in an approval or equipment 

has a flow on effect of delaying further approvals, as well as commissioning, delaying data comparison. 

Page 56: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 56  

 

United Energy (the distributor) had significant delays in grid approval, due to staff shortages beyond their 

control.  

External project management costs were not factored in during the scoping stage and had an impact on the 

overall budget. This needs to be decided at budgeting stage of the project in the future. Learnings from this 

project demonstrated that managing projects internally are more efficient and cost effective.  

CONCLUSION 

Frankston City Council is grateful for the assistance from the Department of Industry in providing the Community 

Energy Efficiency Project.  

Whilst the full savings cannot yet be quantified, the project is proving to be a jewel demonstration site for trial and 

comparison of alternative energy, particularly in a non‐aquatic centre.  

The project had a number of challenges, including lengthy approvals processes in Canberra, changes to requirements 

around milestones and invoicing, difficulties with external project management and underestimation of time and 

budget. It is positive to see the project now near completion, and Council is enjoying the positive feedback from staff 

and the community.  

Some highlights from the communications program are the development of signs, tour notes and the projector screen 

presentation which will heighten awareness of energy efficiency in the town centre.  

 

 

   

Page 57: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 57  

 

   

DECLARATION  

 

 

 

 

 

 

 

   

Page 58: Milestone 9 Final Report Frankston Arts Precinct …...CEEP1115 Milestone 9 Final Report Frankston Arts Precinct Trigeneration This activity received funding from the Australian Government

 

CEEP1115 Frankston City Council Final Report (Milestone 9) Page | 58