method boards - promatect 250t

Upload: anto-thoppil

Post on 05-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Method BOARDS - Promatect 250T

    1/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 1 of 11

    ACC/PJ1-FM D08

    Project:

    J14-15 COURTYARD OFFICES

    METHOD STATEMENT FORBOARD FIREPROOFING WORKS

    Supply and application of Fire Resistive Material

    PROMAT

    Promatect 250

    ATTACHMENTSNo Ref No Title

    APPROVAL HISTORY

    Issue/ Rev

    No

    Date Prepared By Reviewed by Approved by Description

    August 27,

    2011Project Engineer Project Manager Technical Director

  • 7/31/2019 Method BOARDS - Promatect 250T

    2/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 2 of 11

    ACC/PJ1-FM D08

    CONTENTS

    1.0 Scope2.0 Products

    3.0 Workmanship & method

    4.0 Site preparation

    5.0 Site precautions6.0 LEED Requirements

    7.0 Equipments

    8.0 Contact details for further information

  • 7/31/2019 Method BOARDS - Promatect 250T

    3/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 3 of 11

    ACC/PJ1-FM D08

    1. Scope

    1.1 Provide all labor, materials, equipment and services necessary for, andincidental to, the complete and proper installation of board fire resistive

    material Promat Promatect 250 to the structural steel main members in

    accordance with all applicable requirements of the Contract Documents

    based on the pre-determined material thickness as attached herewith, to

    upgrade the steel to achieve required fire resistance based on BS 476

    PART 20, 21 1987, against cellulosic fires.

    1.2 References

    Promatect 250 Product Data Sheet

    Promatect 250 CERTIFIRE Certificate of approval No CF 422

    Promatect 250 Technical and application Manuals

    Thermofires QAQC Procedures

    1.3 Responsibilities

    1.3.1 The Execution in Charge, who reports directly to The Operations

    Manager, will be responsible for the application of this Method Statement.

    1.3.2 The QA/QC Inspector / Site Engineers and Supervisors are responsible for

    direct implementation of all quality assurance and safety procedures who

    reports to the Execution InCharge.

    1.4 Quality Assurance

    1.4.1 Thermofire Middle East Limited will carry out work strictly in accordance

    with BS 476: PARTS 21 Standards as Tested & approved, with its

    expertise execution team in the installation of fire protection or similarmaterials.

    1.4.2 Thermofire (Middle East) Limited is an ISO 9001 2008 Certified

    Organization & is licensed and approved by the Civil Defense Directorate.

    1.4.3 Promat Promatect 250 will be applied to the steel main members by

    Thermofire Middle East Limited to the requisite pre determined thickness,strictly in accordance with manufacturers recommendations, based on

    Hp/A of the respective member, complies BS 476: PART 20, 21 1987 as

    Tested & approved.

  • 7/31/2019 Method BOARDS - Promatect 250T

    4/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 4 of 11

    ACC/PJ1-FM D08

    1.4.4 Applications to be carried out in accordance with the Certifires Test

    Certificates

    1.4.5 Thermofire (Middle East) Limited is an ISO 9001 2008 Certified

    Organization & is licensed and approved by the Civil Defense Directorate.

    1.4.6 Thermofire (Middle East) Limited is licensed and approved by the spray-

    applied fire resistive material manufacturerCafco International.

    1.4.7 Thermofire (Middle East) Limited is an International Contractor Member

    in FCIA - USA.

    1.4.8 Before proceeding with the fire protection work, approval of the proposed

    material & Method, shall be obtained from the Engineer/Client

    1.5 General Notes:

    1.5.1 All application / installation will be undertaken inaccordance with the Project Site Safety Plans

    1.5.2 Ensure all Personnel Protection Equipmentssuch as, coverall / Helmet / Face Mask / Goggles & Hand Gloves etc are

    used by the technicians.

    1.5.3 Avoid using hands to clean the surface, when the equipment

    is in motion.

    1.5.4 Precautions to be taken while working on scaffolding.

    1.5.5 All equipment / tools to be checked and approved before

    usage.

    1.5.6 All electric cables to be checked for live wires and in casethe same is not secured properly, male-female joints to be

    installed.

    1.5.7 Ensure erected/mobile scaffolding with staging is in good

    condition for safe working on the same.

    1.5.8 For all the work at heights where sufficient, correct working

    platform (which are to protect workers from fall) are not in

    place, requires fall arrest/restraint harness (to be worn).

    1.5.9 All access platforms to be erected and inspected by

    competent person

  • 7/31/2019 Method BOARDS - Promatect 250T

    5/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 5 of 11

    ACC/PJ1-FM D08

    1.5.10 Ensure all the tools are in good working condition for safe

    working.

    1.5.11 All power tools to be 220 Volts

    1.5.12 Follow the Site Safety Procedures strictly (to avoid

    accident/penalty by the Safety Engineer).

    1.5.13 In case of emergency contact Safety Officer at site

    immediately and inform office.

    1.5.14 Any works at height operative to wear harness and the

    Harness to be inspected prior to use

    1.5.15 Please refer to the risk assessment attached herewith forMitigation control to eliminate or reduce the risk of the

    above from occurring.

    1.6.16 All operatives to be inducted prior to commencing works.

    1.5.17 All operatives to have the method statement and risk

    assessment briefed to them in a language they understand

    and they will sign their acceptance of its conditions.

    1.6 Submittals

    1.6.1 Submit Manufacturer's Material Data Sheets of Promat Promatect

    250 to show material compliance with Project Specifications

    1.7 Delivery, Storage and Handling

    1.7.1 Promat Promatect 250 should be protected from rain and directsunlight, and maintained at a temperature between 10C and 48 C

    during shipping and storage and protected from frost and freezing

    temperatures until ready for use.

    1.8 Sample

    1.8.1 A sample areas of Promat Promatect 250 to be installed to thestructural steel as specified to avail approval prior to the

    commencement of the Fireproofing Works.

    2. Products

    2.1 Acceptable Manufactures. The spray-applied fire resistive material shall

    be manufactured under the PROMAT/CAFCO

    brand name, byauthorized producers.

  • 7/31/2019 Method BOARDS - Promatect 250T

    6/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 6 of 11

    ACC/PJ1-FM D08

    2.2 Materials

    2.2.1 Materials shall be Promat Promatect 250Boards for the fire

    protection of structural steel (for exposed areas) and shall be

    installed, to the requisite pre determined thickness and segregation

    to upgrade the steel to achieve the required fire resistance based on

    BS 476 PART 20, 21 1987 as Tested & approved, against

    cellulosic fires

    3. Workmanship (Preparation)

    3.1 Site Preparation

    3.1.1 Prior to installation of Promat Promatect 250 the Cafco Approved

    Applicator should ensure that adequate services and site conditions

    are present for the application process. These requirements will

    include some or all of the following:

    o Powero

    Ventilationo Watero Scaffoldo Maskingo Lightingo Waste disposal

    3.2 Sub-Strata:

    3.2.1 Any cleaning of surfaces to receive fire protection shall be the

    responsibility of the General Contractor or Steel Erector.

    3.2.2 Clips, hangers, supports, sleeves and other attachments to the

    substrate are to be placed by others prior to the application of fire

    resistive materials.

    3.2.3 The installation of ducts, piping, conduit or other suspended

    equipment shall not take place until the application of fire resistivematerials is complete in an area.

    3.5 Installation Instructions:

  • 7/31/2019 Method BOARDS - Promatect 250T

    7/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 7 of 11

    ACC/PJ1-FM D08

    Application technique

    For four-sided column casings Promatect 250 soldiers are wedged between the flanges

    at the top and bottom of the column.

    The soldiers are 120mm wide x casing thickness. The boards are fixed to the soldiers

    and to each other using steel staples, 50mm long x 12.5mm wide x 1.6mm thick, at

    150mm centres.

    The end staples are located nominally 40mm from the corner of the board. Soldiers maybe fitted behind board joints as an option. Cover strips are not required over joints in the

    boards covering the flanges. Board to board joints on adjacent sides are staggered by at

    least 530mm.

    For single layer boards 12 or 15mm thick the length of the staples may be reduced to

    35mm.

    For three-sided beam casings the fixing method is the same except that the soldiers arerequired to be fitted at the ends of the beam and at maximum 1250mm centres and the

    soffit board is fitted between the side boards. Soldiers must coincide with board joints.

    For double-layer casings, the first layer is the thicker of the two layers and is fixed as a

    single layer casing. The outer layer is then secured through the first layer into the

    soldiers and to each other using staples, 50mm long, at 150mm centres. Board joints are

    staggered between layers by at least 530mm.

    On steel sections up to 400mm deep, the soldiers may be cut in half, with the cut

    sloping by 5mm from side to side, and the two parts tapped together to wedge the

    soldier in position. For steel sections deeper than 400mm and up to 686mm deep, each

    soldier is strengthened using a Promatect 250 stiffener to form a T-shaped soldier. Thestiffener is the same thickness as the standard soldier and is wedged between the

    flanges. The standard soldier is stapled to the outer edge of the stiffener to form the T-

    shaped soldier.

    For steel sections deeper than 686mm and up to 1.0m deep, each soldier is strengthened

    using a Promatect 250 stiffener to form a T-shaped soldier. The stiffener is glued and

    stapled to the soldier using Vicubond adhesive. The stiffener is the same thickness asthe standard soldier.

  • 7/31/2019 Method BOARDS - Promatect 250T

    8/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 8 of 11

    ACC/PJ1-FM D08

    The T-shaped soldiers are glued in position in the steel section using Vicubond adhesive

    and the Promatect 250 facing boards stapled to the T-shaped soldiers, as per the

    standard fixing recommendations.

    Alternatively, for steel sections up to 1.2m deep, the framed casing arrangement may be

    used, as detailed below.

    The application technique for four-sided beam casings is the same as for three-sided

    beam casings with the addition of the board protection on top of the beam, fitted

    between the side boards.

    Promatect 250 board

    As an alternative to using Promatect 250 soldiers, for steel sections up to 686mm deep,

    the side boards may be secured using continuous galvanised steel angles, 32mm x

    18mm x 0.8mm thick, or equivalent. The angles are fastened to the steel beam or

    column with minimum M4 steel screws at 500mm maximum centres. The boards are

    fastened to the angles with steel drywall screws at 200mm nominal centres.

    Board to board side panel joints are backed with Promatect 250 cover strips, 120mm

    wide x 15mm thick, fastened with staples.

    3 and 4-sided framed casing to deep web beams greater than 686mm deep

    The construction of the framed casings for deep web beams greater than 686mm deep is

    shown in Figure 1.

    Framing:

    32mm x 52mm x 32mm x 0.5mm steel channel fixed to the underside of the top flanges

    and the upper side of the bottom flanges of the steel beam. Vertical steel channels,

    32mm x 52mm x 32mm x 0.5mm, are fitted into the horizontal channels at 1250mmcentres.

    Fixings:

    Channel to flange: shot fired 3.7mm x 16mm steel nails (Hilti ENK 16 S12 or

    equivalent) or selftapping 9.5mm x No.8 panhead screws at 500mm maximum centres.

    Board to channels: No. 8 countersunk self-tapping hardened steel or dry wall screws atnominal

    200mm centres. Screw length should allow minimum of 10mm penetration through the

    channel.

  • 7/31/2019 Method BOARDS - Promatect 250T

    9/11

  • 7/31/2019 Method BOARDS - Promatect 250T

    10/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 10 of 11

    ACC/PJ1-FM D08

    Board to channels: No. 8 countersunk self-tapping hardened steel or dry wall screws at

    nominal 200mm centres. Screw length should allow minimum of 10mm penetration

    through the channel.

    Board to board: steel staples, 50mm long x 12.5mm wide x 1.6mm thick, at 150mm

    centres.

    The end staples are located nominally 40mm from the corner of the board. Board to

    board joints on adjacent sides are staggered by at least 530mm. For single layer boards

    12 or 15mm thick the length of the staples may be reduced to 35mm.

    Cover strips:

    Promatect 250 internal cover strips, 100mm wide x minimum thickness of the side

    panels, at the position of vertical board joints in the Promatect 250 side panels. The side

    panels are fastened to the cover strips, on both sides of the joint, with steel staples,

    50mm long x 12.5mm wide x 1.6mm thick, at 150mm centres. The soffit panels are

    fitted between the side panels and fastened with steel staples, 50mm long x 12.5mm

    wide x 1.6mm thick, at 150mm centres. For single layer boards 12 or 15mm thick thelength of the staples may be reduced to 35mm.

    Through Penetrations:

    All through penetration gaps shall be treated as per the approved independent

    firestopping designs

    4 Precautions

    4.1 Sufficient cross ventilation

    4.2 All personal protection equipments to be warned by all technicians.

    4.3 All works to be carried out in a closed environment4.4 Risk factor: standard risk factors apply to this product like material

    going in to the eyes or being swallowed; as such please avoid the

    same. Hence use safety glass, etc.

    5 LEED Requirements:

    5.1 Construction Waste Management: Waste generated during the

    process will be segregated and placed in the appropriate recycling

    skips in the waste collection area.

  • 7/31/2019 Method BOARDS - Promatect 250T

    11/11

    Project: J14/ J15 Courtyard Offices

    Document No:TMEL.MS.09/J1376/2-1

    METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)

    Promatect 250

    Rev-01Date: March 07, 2012

    Page No. 11 of 11

    ACC/PJ1-FM D08

    5.2 Construction IAQ Management: Indoor Air Quality Management

    Plan requirements will be implemented and adhered to during the

    process of works.

    5.3 Low Emitting Materials: All sealant, adhesive, coats or paintings

    used will be from the approved material submittals complying with

    the LEED requirements on VOC content.

    6. Equipments:

    Airless Spray MachineHeavy Duty Electrical Hand Mixer

    7. Contact Details for Further Information:

    Thermofire (Middle East) Limited

    (An ISO 9001:2008 Certified Company)

    Post Box No: 113566, Dubai Tel: +971 4 2809894, Fax: +971 4 2809897

    Post Box No: 127339, Abu Dhabi, T: +971 2 6741955 F: +971 2 6741952Post Box No: 47529, Doha - Qatar, T: +974 44 154 711, F: +974 44 154 712

    E-mail: [email protected], www.thermofire.com

    End of section

    mailto:[email protected]://www.thermofire.com/http://www.thermofire.com/mailto:[email protected]