method boards - promatect 250t
TRANSCRIPT
-
7/31/2019 Method BOARDS - Promatect 250T
1/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 1 of 11
ACC/PJ1-FM D08
Project:
J14-15 COURTYARD OFFICES
METHOD STATEMENT FORBOARD FIREPROOFING WORKS
Supply and application of Fire Resistive Material
PROMAT
Promatect 250
ATTACHMENTSNo Ref No Title
APPROVAL HISTORY
Issue/ Rev
No
Date Prepared By Reviewed by Approved by Description
August 27,
2011Project Engineer Project Manager Technical Director
-
7/31/2019 Method BOARDS - Promatect 250T
2/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 2 of 11
ACC/PJ1-FM D08
CONTENTS
1.0 Scope2.0 Products
3.0 Workmanship & method
4.0 Site preparation
5.0 Site precautions6.0 LEED Requirements
7.0 Equipments
8.0 Contact details for further information
-
7/31/2019 Method BOARDS - Promatect 250T
3/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 3 of 11
ACC/PJ1-FM D08
1. Scope
1.1 Provide all labor, materials, equipment and services necessary for, andincidental to, the complete and proper installation of board fire resistive
material Promat Promatect 250 to the structural steel main members in
accordance with all applicable requirements of the Contract Documents
based on the pre-determined material thickness as attached herewith, to
upgrade the steel to achieve required fire resistance based on BS 476
PART 20, 21 1987, against cellulosic fires.
1.2 References
Promatect 250 Product Data Sheet
Promatect 250 CERTIFIRE Certificate of approval No CF 422
Promatect 250 Technical and application Manuals
Thermofires QAQC Procedures
1.3 Responsibilities
1.3.1 The Execution in Charge, who reports directly to The Operations
Manager, will be responsible for the application of this Method Statement.
1.3.2 The QA/QC Inspector / Site Engineers and Supervisors are responsible for
direct implementation of all quality assurance and safety procedures who
reports to the Execution InCharge.
1.4 Quality Assurance
1.4.1 Thermofire Middle East Limited will carry out work strictly in accordance
with BS 476: PARTS 21 Standards as Tested & approved, with its
expertise execution team in the installation of fire protection or similarmaterials.
1.4.2 Thermofire (Middle East) Limited is an ISO 9001 2008 Certified
Organization & is licensed and approved by the Civil Defense Directorate.
1.4.3 Promat Promatect 250 will be applied to the steel main members by
Thermofire Middle East Limited to the requisite pre determined thickness,strictly in accordance with manufacturers recommendations, based on
Hp/A of the respective member, complies BS 476: PART 20, 21 1987 as
Tested & approved.
-
7/31/2019 Method BOARDS - Promatect 250T
4/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 4 of 11
ACC/PJ1-FM D08
1.4.4 Applications to be carried out in accordance with the Certifires Test
Certificates
1.4.5 Thermofire (Middle East) Limited is an ISO 9001 2008 Certified
Organization & is licensed and approved by the Civil Defense Directorate.
1.4.6 Thermofire (Middle East) Limited is licensed and approved by the spray-
applied fire resistive material manufacturerCafco International.
1.4.7 Thermofire (Middle East) Limited is an International Contractor Member
in FCIA - USA.
1.4.8 Before proceeding with the fire protection work, approval of the proposed
material & Method, shall be obtained from the Engineer/Client
1.5 General Notes:
1.5.1 All application / installation will be undertaken inaccordance with the Project Site Safety Plans
1.5.2 Ensure all Personnel Protection Equipmentssuch as, coverall / Helmet / Face Mask / Goggles & Hand Gloves etc are
used by the technicians.
1.5.3 Avoid using hands to clean the surface, when the equipment
is in motion.
1.5.4 Precautions to be taken while working on scaffolding.
1.5.5 All equipment / tools to be checked and approved before
usage.
1.5.6 All electric cables to be checked for live wires and in casethe same is not secured properly, male-female joints to be
installed.
1.5.7 Ensure erected/mobile scaffolding with staging is in good
condition for safe working on the same.
1.5.8 For all the work at heights where sufficient, correct working
platform (which are to protect workers from fall) are not in
place, requires fall arrest/restraint harness (to be worn).
1.5.9 All access platforms to be erected and inspected by
competent person
-
7/31/2019 Method BOARDS - Promatect 250T
5/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 5 of 11
ACC/PJ1-FM D08
1.5.10 Ensure all the tools are in good working condition for safe
working.
1.5.11 All power tools to be 220 Volts
1.5.12 Follow the Site Safety Procedures strictly (to avoid
accident/penalty by the Safety Engineer).
1.5.13 In case of emergency contact Safety Officer at site
immediately and inform office.
1.5.14 Any works at height operative to wear harness and the
Harness to be inspected prior to use
1.5.15 Please refer to the risk assessment attached herewith forMitigation control to eliminate or reduce the risk of the
above from occurring.
1.6.16 All operatives to be inducted prior to commencing works.
1.5.17 All operatives to have the method statement and risk
assessment briefed to them in a language they understand
and they will sign their acceptance of its conditions.
1.6 Submittals
1.6.1 Submit Manufacturer's Material Data Sheets of Promat Promatect
250 to show material compliance with Project Specifications
1.7 Delivery, Storage and Handling
1.7.1 Promat Promatect 250 should be protected from rain and directsunlight, and maintained at a temperature between 10C and 48 C
during shipping and storage and protected from frost and freezing
temperatures until ready for use.
1.8 Sample
1.8.1 A sample areas of Promat Promatect 250 to be installed to thestructural steel as specified to avail approval prior to the
commencement of the Fireproofing Works.
2. Products
2.1 Acceptable Manufactures. The spray-applied fire resistive material shall
be manufactured under the PROMAT/CAFCO
brand name, byauthorized producers.
-
7/31/2019 Method BOARDS - Promatect 250T
6/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 6 of 11
ACC/PJ1-FM D08
2.2 Materials
2.2.1 Materials shall be Promat Promatect 250Boards for the fire
protection of structural steel (for exposed areas) and shall be
installed, to the requisite pre determined thickness and segregation
to upgrade the steel to achieve the required fire resistance based on
BS 476 PART 20, 21 1987 as Tested & approved, against
cellulosic fires
3. Workmanship (Preparation)
3.1 Site Preparation
3.1.1 Prior to installation of Promat Promatect 250 the Cafco Approved
Applicator should ensure that adequate services and site conditions
are present for the application process. These requirements will
include some or all of the following:
o Powero
Ventilationo Watero Scaffoldo Maskingo Lightingo Waste disposal
3.2 Sub-Strata:
3.2.1 Any cleaning of surfaces to receive fire protection shall be the
responsibility of the General Contractor or Steel Erector.
3.2.2 Clips, hangers, supports, sleeves and other attachments to the
substrate are to be placed by others prior to the application of fire
resistive materials.
3.2.3 The installation of ducts, piping, conduit or other suspended
equipment shall not take place until the application of fire resistivematerials is complete in an area.
3.5 Installation Instructions:
-
7/31/2019 Method BOARDS - Promatect 250T
7/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 7 of 11
ACC/PJ1-FM D08
Application technique
For four-sided column casings Promatect 250 soldiers are wedged between the flanges
at the top and bottom of the column.
The soldiers are 120mm wide x casing thickness. The boards are fixed to the soldiers
and to each other using steel staples, 50mm long x 12.5mm wide x 1.6mm thick, at
150mm centres.
The end staples are located nominally 40mm from the corner of the board. Soldiers maybe fitted behind board joints as an option. Cover strips are not required over joints in the
boards covering the flanges. Board to board joints on adjacent sides are staggered by at
least 530mm.
For single layer boards 12 or 15mm thick the length of the staples may be reduced to
35mm.
For three-sided beam casings the fixing method is the same except that the soldiers arerequired to be fitted at the ends of the beam and at maximum 1250mm centres and the
soffit board is fitted between the side boards. Soldiers must coincide with board joints.
For double-layer casings, the first layer is the thicker of the two layers and is fixed as a
single layer casing. The outer layer is then secured through the first layer into the
soldiers and to each other using staples, 50mm long, at 150mm centres. Board joints are
staggered between layers by at least 530mm.
On steel sections up to 400mm deep, the soldiers may be cut in half, with the cut
sloping by 5mm from side to side, and the two parts tapped together to wedge the
soldier in position. For steel sections deeper than 400mm and up to 686mm deep, each
soldier is strengthened using a Promatect 250 stiffener to form a T-shaped soldier. Thestiffener is the same thickness as the standard soldier and is wedged between the
flanges. The standard soldier is stapled to the outer edge of the stiffener to form the T-
shaped soldier.
For steel sections deeper than 686mm and up to 1.0m deep, each soldier is strengthened
using a Promatect 250 stiffener to form a T-shaped soldier. The stiffener is glued and
stapled to the soldier using Vicubond adhesive. The stiffener is the same thickness asthe standard soldier.
-
7/31/2019 Method BOARDS - Promatect 250T
8/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 8 of 11
ACC/PJ1-FM D08
The T-shaped soldiers are glued in position in the steel section using Vicubond adhesive
and the Promatect 250 facing boards stapled to the T-shaped soldiers, as per the
standard fixing recommendations.
Alternatively, for steel sections up to 1.2m deep, the framed casing arrangement may be
used, as detailed below.
The application technique for four-sided beam casings is the same as for three-sided
beam casings with the addition of the board protection on top of the beam, fitted
between the side boards.
Promatect 250 board
As an alternative to using Promatect 250 soldiers, for steel sections up to 686mm deep,
the side boards may be secured using continuous galvanised steel angles, 32mm x
18mm x 0.8mm thick, or equivalent. The angles are fastened to the steel beam or
column with minimum M4 steel screws at 500mm maximum centres. The boards are
fastened to the angles with steel drywall screws at 200mm nominal centres.
Board to board side panel joints are backed with Promatect 250 cover strips, 120mm
wide x 15mm thick, fastened with staples.
3 and 4-sided framed casing to deep web beams greater than 686mm deep
The construction of the framed casings for deep web beams greater than 686mm deep is
shown in Figure 1.
Framing:
32mm x 52mm x 32mm x 0.5mm steel channel fixed to the underside of the top flanges
and the upper side of the bottom flanges of the steel beam. Vertical steel channels,
32mm x 52mm x 32mm x 0.5mm, are fitted into the horizontal channels at 1250mmcentres.
Fixings:
Channel to flange: shot fired 3.7mm x 16mm steel nails (Hilti ENK 16 S12 or
equivalent) or selftapping 9.5mm x No.8 panhead screws at 500mm maximum centres.
Board to channels: No. 8 countersunk self-tapping hardened steel or dry wall screws atnominal
200mm centres. Screw length should allow minimum of 10mm penetration through the
channel.
-
7/31/2019 Method BOARDS - Promatect 250T
9/11
-
7/31/2019 Method BOARDS - Promatect 250T
10/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 10 of 11
ACC/PJ1-FM D08
Board to channels: No. 8 countersunk self-tapping hardened steel or dry wall screws at
nominal 200mm centres. Screw length should allow minimum of 10mm penetration
through the channel.
Board to board: steel staples, 50mm long x 12.5mm wide x 1.6mm thick, at 150mm
centres.
The end staples are located nominally 40mm from the corner of the board. Board to
board joints on adjacent sides are staggered by at least 530mm. For single layer boards
12 or 15mm thick the length of the staples may be reduced to 35mm.
Cover strips:
Promatect 250 internal cover strips, 100mm wide x minimum thickness of the side
panels, at the position of vertical board joints in the Promatect 250 side panels. The side
panels are fastened to the cover strips, on both sides of the joint, with steel staples,
50mm long x 12.5mm wide x 1.6mm thick, at 150mm centres. The soffit panels are
fitted between the side panels and fastened with steel staples, 50mm long x 12.5mm
wide x 1.6mm thick, at 150mm centres. For single layer boards 12 or 15mm thick thelength of the staples may be reduced to 35mm.
Through Penetrations:
All through penetration gaps shall be treated as per the approved independent
firestopping designs
4 Precautions
4.1 Sufficient cross ventilation
4.2 All personal protection equipments to be warned by all technicians.
4.3 All works to be carried out in a closed environment4.4 Risk factor: standard risk factors apply to this product like material
going in to the eyes or being swallowed; as such please avoid the
same. Hence use safety glass, etc.
5 LEED Requirements:
5.1 Construction Waste Management: Waste generated during the
process will be segregated and placed in the appropriate recycling
skips in the waste collection area.
-
7/31/2019 Method BOARDS - Promatect 250T
11/11
Project: J14/ J15 Courtyard Offices
Document No:TMEL.MS.09/J1376/2-1
METHOD STATEMENT FOR(BOARD FIREPROOFING WORKS)
Promatect 250
Rev-01Date: March 07, 2012
Page No. 11 of 11
ACC/PJ1-FM D08
5.2 Construction IAQ Management: Indoor Air Quality Management
Plan requirements will be implemented and adhered to during the
process of works.
5.3 Low Emitting Materials: All sealant, adhesive, coats or paintings
used will be from the approved material submittals complying with
the LEED requirements on VOC content.
6. Equipments:
Airless Spray MachineHeavy Duty Electrical Hand Mixer
7. Contact Details for Further Information:
Thermofire (Middle East) Limited
(An ISO 9001:2008 Certified Company)
Post Box No: 113566, Dubai Tel: +971 4 2809894, Fax: +971 4 2809897
Post Box No: 127339, Abu Dhabi, T: +971 2 6741955 F: +971 2 6741952Post Box No: 47529, Doha - Qatar, T: +974 44 154 711, F: +974 44 154 712
E-mail: [email protected], www.thermofire.com
End of section
mailto:[email protected]://www.thermofire.com/http://www.thermofire.com/mailto:[email protected]