may 2017, american university of sharjah - hilti · 2020. 11. 18. · rebar presentation 9 2....

22
1 www.hilti.com Rebar Presentation Post installed rebar design May 2017, American University of Sharjah

Upload: others

Post on 19-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

1www.hilti.com Rebar Presentation

Post installed rebar design

May 2017, American University of Sharjah

Page 2: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

2www.hilti.com Rebar Presentation

Agenda

• Scope and applications

• Available design methods

• How to transfer moments to an existing slab?

Frame node design

• How to optimize the design?

Take the maximum power of the chemical

• Questions

Page 3: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

3www.hilti.com Rebar Presentation

New concrete

Old concrete

Post-installed rebar

Existing

reinforcement

Steel plate

Concrete

HIT-RE 500 V3 HIT-RE 500 V3

Anchor

The same product has different features if

used for anchor applications or for post-

installed rebar applications

Page 4: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

4www.hilti.com Rebar Presentation

Missing or misplaced rebars

Necessary for:

- Missing bars due to

mistakes on the

jobsite

- Change in the design

of the structure

Additional rebars

Necessary for:

- Correction of the

general architecture

- Required additional

bars for additional

strength

3 Main needs for post-installation of rebars:

Post-installation scope and applications

Alternative construction method

Necessary for:

- Fixing of Staircases

- Stiffner Columns

- Replacing couplers and

other time consuming

applications

Page 5: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

5www.hilti.com Rebar Presentation

Extension of slabs, balconies & stairs

Connections of new slabs

Close openings / slab enlargement

Balcony extension

Staircase connection

Example of applications

Post installed rebars gives the flexibility required for new constructions and

allow easier renovation

Page 6: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

6www.hilti.com Rebar Presentation

Extension of columns, beams & walls

Example of applications

Connections of new columns

Connection of beams

Reservoirs extension

Wall extension

Post installed rebars gives the flexibility required for new constructions and

allow easier renovation

Page 7: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

7www.hilti.com Rebar Presentation

Agenda

• Scope and applications

• Available design methods

• How to transfer moments to an existing slab?

Frame node design

• How to optimize the design?

Take the maximum power of the chemical

• Questions

Page 8: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

8www.hilti.com Rebar Presentation

Design method that should be avoided

(safety risk)

1. 10/12/15… x diameter embedment

• Basic / Simplistic design method

• Small concrete covers are not considered

• Splitting and concrete cone failure modes are

ignored

• Simultaneous behavior of rebars is not taken

into consideration

Datasheets and tables should be avoided in all post-installation fixings

Page 9: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

9www.hilti.com Rebar Presentation

2. Design of Rebar as an Anchor (ETAG 001 – Annex C)

Design method that can be used

(not recommended)

• Load acting on rebar is transferred to the

concrete

• Rebar resists both Shear and Tension

forces

• Takes into account the concrete cone

failure

• Spacing and edge distance will often

make anchor design impossible for

rebars (As per ETA values of Spacing

and Edge Distances on Anchor Theory)

Page 10: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

10www.hilti.com Rebar Presentation

The correct design method for post-installed

rebars

3. Eurocode 2 Part 1 (EN 1992 – 1)

• The logic is that post-installed rebars will work the same way as a

straight cast-in bar.

• The requirements to be able to design according to EC2 is to have a

rebar ETA TR023.

• The failure modes possible to occur are all ductile, concrete cone is

impossible to occur.

We can calculate as per EC2 the embedment length using the following:

𝑙𝑏,𝑟𝑞𝑑 =∅

4∙𝜎𝑠𝑑𝑓𝑏𝑑

𝑙𝑏𝑑 = 𝑙𝑏,𝑟𝑞𝑑 ∙ 𝛼1 ∙ 𝛼2 ∙ 𝛼3 ∙ 𝛼4 ∙ 𝛼5

Page 11: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

11www.hilti.com Rebar Presentation

Load is transferred from the post installed rebar

to the existing rebars

Unlike the Anchor Theory, the load is transferred from the new rebars to the

existing rebars through the concrete

Page 12: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

12www.hilti.com Rebar Presentation

The rebar is designed only to take pure tension

If we have a shear loading on a concrete member fastened on a

roughened surface, using a strut-and-tie model allows us to see the

shear load into a pure tension.

This is coming from Eurocode 2 (as per EN 1992-1-1:2004) and is required for

any rebar application (cast-in as well as post-installed)

Pure shear

application

Only tension is

acting on the rebars !

Roughened

surface

Page 13: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

13www.hilti.com Rebar Presentation

Two failure possibilities are considered by EC2

formulation

Rebar close to

the edge

Rebar away

from the edge

Page 14: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

14www.hilti.com Rebar Presentation

M

V

N

Moment resisting nodes are in practice not

possible according to EC2/TR023 approach

M

V

N

N

Hilti provides a solution following the philosophy of EC2

Overlap joint for rebar connections of

slabs and beamsOverlap joint at a foundation of a

column or wall

Components stressed primarily in

compression

End anchoring of slabs or beams

(simply supported)

Components subjected to bending

moment and compression

Covered

by TR 023

Covered

by TR 023

Covered

by TR 023, but not

feasible with

post-installed rebars

NOT covered

by TR 023 but highly

requested by specifiers

Covered

by TR 023

5-10% of all design cases

45-55% of all design cases

35-45% of all design

cases

In 35-45% of all design cases EC2/TR023

does not provide a solution

~ 0% of all design cases

Page 15: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

15www.hilti.com Rebar Presentation

Agenda

• Scope and applications

• Available design methods

• How to transfer moments to an existing slab?

Frame node design

• How to optimize the design?

Take the maximum power of the chemical

• Questions

Page 16: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

16www.hilti.com Rebar Presentation

For some applications, moment transfer is

required for post-installed rebars

Hilti provides a strut and tie model for moment resisting node with straight bars

θ > 30°

θ

The force flow in the frame node

(Hilti research with Technical University of Munich and the American

University of Beirut ).

The strut and tie model is developed for straight bars

(Hilti research), showing that this application can also be

designed according to EC2 approach.

Compressive strut

Tests Finite Element Analysis Strut and tie model

Only the main struts are shown

Page 17: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

17www.hilti.com Rebar Presentation

M1

V1

N1

M1

V1

N1

C

M1

V1

N1

M1

V1

N1

C

Together with TU Munich and AUB, Hilti has

developed strut and tie model for straight bars

Page 18: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

18www.hilti.com Rebar Presentation

Agenda

• Scope and applications

• Available design methods

• How to transfer moments to an existing slab?

Frame node design

• How to optimize the design?

Take the maximum power of the chemical

• Questions

Page 19: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

19www.hilti.com Rebar Presentation

With large concrete cover post-installed rebar is

stronger than cast-in

© University of Stuttgart

Page 20: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

20www.hilti.com Rebar Presentation

Eurocode 2: a2=1-0.15∙(cd/f-1)

bond strength depending on cover: fbd,cover = fbd/a2

scxcy

EC2 limited by

a2,min = 0.7

Extension for post-

installed rebars with large

concrete cover (product

dependent) limited by the

bond strength of adhesive. Inclination derived from internal

tests

We know from our 30 years anchoring experience that

our chemicals have a higher bond strength than

concrete

1 2 3 4 5 62

2.5

3

3.5

4

4.5

5

5.5

6

(Confinement or concrete cover)

Uti

lizab

le b

on

d s

tren

gth

fb

d[

N/m

m2]

cd /Φ

We are able to use more of the capacity of the mortars as soon as we are above cd/Ø > 3

Page 21: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

21www.hilti.com Rebar Presentation

By doing these internal tests we were able to

provide and optimize a solution for all cases on

the jobsite

M45-55% of all design

cases

5-10% of all design

cases

35-45% of all

design cases

No solution according to EC2!

Length reduction in

some cases, only

Length reduction

Length reduction

Design solution

Hilti provides:

Not realistic case

End anchoring of slabs or beams, designed

as simply supportedOverlap joint at a foundation of a column or

wall

Rebar connection for components stressed

primarly in compression

Overlap joint for rebar connections of slabs

and beams

Rebar connection for components subjected

to bending moment

Page 22: May 2017, American University of Sharjah - Hilti · 2020. 11. 18. · Rebar Presentation 9 2. Design of Rebar as an Anchor (ETAG 001 –Annex C) Design method that can be used (not

22www.hilti.com Rebar Presentation

Agenda

• Scope and applications

• Available design methods

• How to transfer moments to an existing slab?

Frame node design

• How to optimize the design?

Take the maximum power of the chemical

• Questions