LIU-SPS RF Power upgrade [email protected] | 09 December 2015

Upload: gilbert-snow

Post on 18-Jan-2018

233 views

Category:

Documents


0 download

DESCRIPTION

2016 Challenges – 200 MHz  Drivers Complete the demonstrators tests, launch the series production (150 units per year over the next two years)  Finals Design review, Demonstrator Site Acceptance Tests before end of November 2016 and validation for the two series transmitters  Building BAF3 Integration of all services, water cooling, HVAC, Electrical network and RF power control room  Integration RF coaxial lines construction, tests and validation, preparation for EYETS installation from BAF3 to LSS3 at the entrance of the tunnel  Cavities and FPC (Fundamental Power Coupler) Two spare sections fully re-assembled and vacuum tested, four pre-series FPC for medium power tests, HOMS feedthroughs construction and test of 100 units

TRANSCRIPT

Page 1: LIU-SPS RF Power upgrade | 09 December 2015

LIU-SPS RF Power [email protected] | 09 December 2015

Page 2: LIU-SPS RF Power upgrade | 09 December 2015

2015 Highlights – 200 MHz Drivers

Deep tests of the demonstrators, RF transistors soldering difficulties, controls non conformities, still ongoing

FinalsSSPA option selected, contract under preparation (should be signed before Xmas), 400 V mains network by CERN’s team

Building BAF3Bare building completed, ground floor with resine, crane installed and validated

IntegrationRF coaxial lines re-designed (specific flanges, specific ceramics, specific supporting systems), RF path defined and almost fully validated

Cavities and FPC (Fundamental Power Coupler)All cavity mechanical drawings reverse engineered, one spare section fully re-assembled, FPC new concept (coaxial with ceramic without inner line, first time world wide)

A lot has been done

Page 3: LIU-SPS RF Power upgrade | 09 December 2015

2016 Challenges – 200 MHz Drivers

Complete the demonstrators tests, launch the series production (150 units per year over the next two years)

FinalsDesign review, Demonstrator Site Acceptance Tests before end of November 2016 and validation for the two series transmitters

Building BAF3Integration of all services, water cooling, HVAC, Electrical network and RF power control room

IntegrationRF coaxial lines construction, tests and validation, preparation for EYETS installation from BAF3 to LSS3 at the entrance of the tunnel

Cavities and FPC (Fundamental Power Coupler)Two spare sections fully re-assembled and vacuum tested, four pre-series FPC for medium power tests, HOMS feedthroughs construction and test of 100 units

Still a lot to be done

Page 4: LIU-SPS RF Power upgrade | 09 December 2015

2015 Highlights – 800 MHz

IOT#2 & IOT#3 electrical mains instabilities understoodForce mains network and control mains network will be separated during YETS

Two power systems 100 % available at full power all along the year Solution for spares found after company bankrupt

Mitigation with contractor, free spares instead of penalties Fully learnt and understood IOT’s behavior

New grid cleaning process to avoid grid contamination due to vaporization of barium, inducing emissivity loss and shortening tube lifetime, thermal characterization of SSPA drivers

A lot has been learnt

Page 5: LIU-SPS RF Power upgrade | 09 December 2015

2016 Challenges – 800 MHz

DriversNew units with better thermal and power characteristics

IOTsLifetime management (currently 9000 to 13000 hours), spare tubes management

TransmittersFirst maintenance scheme to be defined

Spare cavity & spare FPCThird cavity under construction to be a spare, new FPC design and four pre-series construction, resonant ring for FPC tests

Still a lot to learn

Page 6: LIU-SPS RF Power upgrade | 09 December 2015

2015 Highlights – HBWD Strip line kickers

Two units in the SPS (one with final version feedthroughs, one to be exchanged), all feedthroughs delivered, third kicker prepared and ready for installation

Slotted line kickersDesign under progress, first 3D model and 2D drawings completed, components ordered and partially delivered

2016 Challenges – HBWD Strip line kickers

Two final version units in the SPS during YETS, third kicker as spare in lab with the same feedthroughs

Slotted line kickers (if FTEC granted)Construction of one prototype for measurements in lab, preparation for installation during EYETS (very challenging) or during following YETS (more realistic)

Under completion