lhc machine advisory committee , cern 12th june 2008

22
LHC Machine Advisory Committee, CERN 12th June 2008 Current Status of LHC Project and Upgrade Plan Lyn Evans

Upload: gwyn

Post on 19-Jan-2016

30 views

Category:

Documents


0 download

DESCRIPTION

Current Status of LHC Project and Upgrade Plan. Lyn Evans. LHC Machine Advisory Committee , CERN 12th June 2008. Summary LHC Cryogenics. Cooldown status. Sector 56. Sector 67. Sector 78. Sector 81. Cooldown status. Sector 12. Sector 23. Sector 34. Sector 45. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: LHC Machine Advisory Committee , CERN 12th June 2008

LHC Machine Advisory Committee, CERN 12th June 2008

Current Status of LHC Project and Upgrade PlanLyn Evans

Page 2: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Summary LHC Cryogenics

Page 3: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Cooldown status

Sector 56

Sector 67

Sector 78

Sector 81

Page 4: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Cooldown status

Sector 12

Sector 23

Sector 34

Sector 45

Page 5: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937 5

Re-training of dipoles in Sector 5-6

0

1

2

3150 3200 3250 3300 3350 3400 3450

Num

ber

of q

uenc

hes

Serial numbers of magnets

3536121

Page 6: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937 6

Quenches – Noell dipoles

3335 1 2 3 4 5 6 7

1 2 3 4 5 6 0

I (A) 11569 11814 12013 12245 12475 12727 12850

B (T) 8.13 8.30 8.43 8.59 8.75 8.91 9.00

Aper. D2 D1 D2 D1 D1 D1

Pole U U L U U U

Sect

Miits (MA^2s)

Spot (K)

3336 1 2 3 4 5 6

1 2 3 4 5 0

I (A) 10515 11971 12193 12440 12745 12850

B (T) 7.41 8.41 8.56 8.72 8.93 9.00

Aper. D2 D2 D2 D1 D1

Pole U U U U L

Sect S11 S02

Miits (MA^2s)

Spot (K)

3337 1 2

1 0

I (A) 10455 12850

B (T) 7.36 9.00

Aper. D1

Pole U

Sect

Miits (MA^2s)

Spot (K)

3338 1 2 3

1 2 0

I (A) 12180 12711 12850

B (T) 8.55 8.91 9.00

Aper. D2 D1

Pole U L

Sect

Miits (MA^2s)

Spot (K)

Page 7: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Ramp of 138 power converters to a current equivalent to 5.3 TeV (including all high current magnets realistic LHC optics )

19 February 2008,15:00commissioning team

Page 8: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Low-beta squeeze

Page 9: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937 9

Powering of inner triplet to nominal current

Page 10: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Schedule

The last sector (4-5) will be at 1.9 K by mid July.

First beam injected early August.

Colliding beams at 10 TeV early in October?

Page 11: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

LHC Upgrade

Unlike the Tevatron or LEP, the LHC already has all the attributes to go very quickly to design luminosity .

It is reasonably to assume that the machine will reach 1034 cm-2 s-1 on a 5-year timescale.

It is therefore necessary to plan an upgrade path now in order to be able to open the door to a factor of 4-5 improvement on the same timescale.

Page 12: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Peak Luminosity

Nb number of particles per bunch

nb number of bunches

fr revolution frequency

n normalised emittance

* beta value at Ip

F reduction factor due to crossing angle

Nb, n injector chain

* LHC insertion

F beam separation schemes

nb electron cloud effect

F*fnNN

41

L rbb

n

b

Page 13: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

LHC Upgrade-Phase I

Goal of “Phase I” upgrade: Enable focusing of the beams to b*=0.25 m in IP1 and IP5, and reliable operation of the LHC at double the operating luminosity on the horizon of the physics run in 2013.

Scope of “Phase I” upgrade:1. Upgrade of ATLAS and CMS experimental insertions. The interfaces

between the LHC and the experiments remain unchanged at 19 m.2. Replace the present triplets with wide aperture quadrupoles based on the

LHC dipole cables (Nb-Ti) cooled at 1.9 K.3. Upgrade the D1 separation dipole, TAS and collimation system so as to be

compatible with the inner triplet aperture.4. The cooling capacity of the cryogenic system and other main infrastructure

elements remain unchanged.5. Modifications of other insertion magnets (e.g. D2-Q4) and introduction of

other equipment in the insertions to the extent of available resources.

Page 14: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Participants and Milestones

Several departments are involved in the “Phase I” project:AT Department: low-beta quadrupoles and correctors, D1 separation dipoles, magnet testing, magnet protection and cold powering, vacuum equipment, QRL modifications.

AB Department: optics and performance, power converters, instrumentation, TAS and other beam-line absorbers, …

TS Department: cryostat support and alignment equipment, interfaces with the experiments, installation, design effort, …SLHC-PP collaborators.

Milestones:Conceptual Design Report mid 2008Technical Design Report mid 2009Model quadrupole end 2009Pre-series quadrupole 2010String test 2012Installation shutdown 2013

Page 15: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

CERN accelerator complex

Page 16: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Upgrade of the Injector Chain

parameters icrelativist classical :

raccelerato theof radiusmean :

emittances e transversnormalized :

nchprotons/bu ofnumber :with

,

2,

R

N

RNQ

YX

b

YX

bSC

1. Lack of reliability:

Ageing accelerators (PS is 48 years old !) operating far beyond initial parameters

need for new accelerators designed for the needs of SLHC

2. Main performance limitation:

Excessive incoherent space chargetune spreads DQSC at injection in thePSB (50 MeV) and PS (1.4 GeV) becauseof the high required beam brightness N/e*.

need to increase the injection energy in the synchrotrons

• Increase injection energy in the PSB from 50 to 160 MeV kinetic• Increase injection energy in the SPS from 25 to 50 GeV kinetic• Design the PS successor (PS2) with an acceptable space charge effect for the

maximum beam envisaged for SLHC: => injection energy of 4 GeV

Page 17: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

LPSPL: Low Power Superconducting Proton Linac (4 GeV)

PS2: High Energy PS(~ 5 to 50 GeV – 0.3 Hz)

SPS+: Superconducting SPS(50 to1000 GeV)

SLHC: “Superluminosity” LHC(up to 1035 cm-2s-1)

DLHC: “Double energy” LHC(1 to ~14 TeV)

Proton flux / Beam power

Upgrade components

PSB

SPSSPS+

Linac4

LPSPL

PS

LHC / SLHC DLHC

Out

put

ener

gy

160 MeV

1.4 GeV4 GeV

26 GeV50 GeV

450 GeV1 TeV

7 TeV~ 14 TeV

Linac250 MeV

PS2

Page 18: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Layout of the new injectors

SPS

PS2

SPL

Linac4

PS

Page 19: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Stage 1: Linac4

• Direct benefits of the new linacStop of Linac2:

• End of recurrent problems with Linac2 (vacuum leaks, etc.)• End of use of obsolete RF triodes (hard to get + expensive)

Higher performance:• Space charge decreased by a factor of 2 in the PSB

=> potential to double the beam brightness and fill the PS with the LHC beam in a single pulse,=> easier handling of high intensity. Potential to double the intensity per pulse.

• Low loss injection process (Charge exchange instead of betatron stacking)• High flexibility for painting in the transverse and longitudinal planes (high speed

chopper at 3 MeV in Linac4)First step towards the SPL:

• Linac4 will provide beam for commissioning LPSPL + PS2 without disturbing physics.

• Benefits for users of the PSBGood match between space charge limits at injection in the PSB and PS

=> for LHC, no more long flat bottom at PS injection + shorter flat bottom at SPS injection: easier/ more reliable operation / potential for ultimate beam from the PS

More intensity per pulse available for PSB beam users (ISOLDE) – up to 2´

More PSB cycles available for other uses than LHC

Page 20: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

Stage 2: LPSPL + PS2

• Direct benefits of the LPSPL + PS2Stop of PSB and PS:

• End of recurrent problems (damaged magnets in the PS, etc.)• End of maintenance of equipment with multiple layers of modifications• End of operation of old accelerators at their maximum capability• Safer operation at higher proton flux (adequate shielding and collimation)

Higher performance:• Capability to deliver 2.2´ the ultimate beam for LHC to the SPS

=> potential to prepare the SPS for supplying the beam required for the SLHC,• Higher injection energy in the SPS + higher intensity and brightness

=> easier handling of high intensity. Potential to increase the intensity per pulse.First step towards the SPL:

• Linac4 will provide beam for commissioning LPSPL + PS2 without disturbing physics.

• Benefits for users of the LPSPL and PS2More than 50 % of the LPSPL pulses will be available (not needed by PS2)

=> New nuclear physics experiments – extension of ISOLDE (if no EURISOL)…Upgraded characteristics of the PS2 beam wrt the PS (energy and flux)Potential for a higher proton flux from the SPS

Page 21: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

For SPL A comparison of the frequency chosen for SPL (704 MHz) compared with

Project X (1400 MHz), which is also intended to develop the technology for ILC.

A very clear conclusion was made that the lower frequency is superior if one does not want to limit future beam intensity.

For PS2 A comparison was made of a classical FODO lattice with transition

crossing compared with a more complex lattice giving an imaginary and therefore avoiding transition crossing.

It was clear that the second option is far superior if one does not want to build in intensity limitations for future generations. It requires some R&D on a 40 MHz cavity with 1 octave tuning range.

The choice of superconducting (super ferric) or conventional magnets can be made once the detailed lattice design is fixed.

Recent Reviews

T

Page 22: LHC Machine Advisory Committee , CERN 12th June 2008

L. Evans – EDMS Document 926937

CDR 2

Planning …

Linac4 approval

3 MeV test place ready

SPL & PS2 approvalStart for Physics