report @ cern-kek about lhc upgrades programs

20
Report @ CERN-KEK about LHC upgrades programs Lucio Rossi 14 December 2011

Upload: todd-moore

Post on 02-Jan-2016

21 views

Category:

Documents


0 download

DESCRIPTION

Report @ CERN-KEK about LHC upgrades programs. Lucio Rossi 14 December 2011. The path and goals: 3000 fb -1 – L peak < 5 10 34. Rad. damage. Tuning of the goal after summer. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Report @ CERN-KEK about LHC upgrades programs

Report @ CERN-KEK about LHC upgrades programs

Lucio Rossi

14 December 2011

Page 2: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 2

The path and goals: 3000 fb-1 – Lpeak< 5 1034

Rad.damage

Page 3: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 3

Tuning of the goal after summer

Efficiency is defined as the ratio between the annual luminosity target of 250 fb-1 over the potential luminosity that can be reached with an ideal cycle run time with no stop for 150 days: trun= tlev+tdec+tturn. The turnaround time after a beam dump is taken as 5 hours, tdecay is 3 h while tlev depends on the total beam current

Page 4: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 4

Cycle in the HL-LHC run20E+34 pile up

heat deposition in IR and DSother?

Levelling

Page 5: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 5

Possible evolution toward 3000 fb-1

Page 6: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 6

IR Magnets (triplet, D1, D2, MQ4, …) SC Crab Cavities, IR Collimation

Page 7: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 7

Other changes• Cryogenics• During LS2, a new refrigerator will be

installed at P4, to feed RF cavities and restore IR 5L

• Refrigerator 6.5 kW @ 4.5 K:• 4.5 kW + 0.25 kW (flash) + 0.12 kW

(thermal losses line & valve box) + 1.6 kW (contingency 33%)

• During LS3 new refrigerators for P1-P5• Warm compressor installed in surface.

Warm gas lines in Pit• Cold boxes installed in underground and

surface (if 2 K or 1.8 K options) • Distribution and transfer lines to

equipments (magnets, DFBs, crab-cavities ?, SCL ?, sector powering ?...)

Page 8: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 8

Other changes (list not exhaustive…)• R2E: whatever needed, see from experience

frome next years• P8• Removal of EPC and DFBX from tunnel to

surface via long SC links rated of 0.1-1 GW d.c.

Page 9: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 9

LIU – LHC Inj Upgrade (R. Garoby)LS2 (2018) and LS3 (2012-23)

• Linac4 (160 Mev H- vs. 50 MeV H of Linac2)Ready by mid 2014Connected 2015?Reliability, brilliance…

• PS Booster upgrade:from 1.4 GeV (800 Gev)to 2 GeV to reduce space ahrge at PS injectionIntensity gain : +65%Project launched;

• SPS reduction of impedencenew optics with low t (2615 GeV)new 200 MHz cavitiesreduction e-clouds by vaccum chamber coating (or scrubbing?)

Page 10: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 10

The HL composition, larger than FP7 HiLumi

WP1 Project Management and Technical Coordination

WP2 Accelerator Physics and Performance

WP3 Magnet Design

WP5 IR Collimation

WP6 Cold Powering

WP4 Crab Cavities

HiLumi LHC

WP7 Machine Protection

WP8 Collider-Experiment Interface

WP9 Cryogenics

WP10 Energy Deposition and shielding

WP11 11 tesla dipole two-in-one

WP12 Integration & (de)installation

Non-HiLumi LHC

HL-LHC Design Study

CollimationProject

Matching section and correctors

Beam Diagnostics

High Field Magnets R&D

HE-LHC Studies Hardware Commissioning

EuCARD2 WP10 on HTS dipoles

Page 11: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 11

Budget FP7 HiLumi and HL-LHC

Perfect score 15/15,

ALL request to EU

granted

Design in FP7 HiLumi

Extra effort for Design

R&D and proto

Industrialization & Construction TOT Industry

W1-WP6 27 10 50 200 287 160WP7-12 0 15 30 100 145 80Other 0 5 10 50 65 40TOT 27 30 90 350 497 280

Estimated cost for the the whole HL-LHC over 10 years in M€ (October 2010)

Page 12: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 12

3 days Collaboration Meeting at CERN 14-18 Nov (160 people)

Collaboration Board members/invited

Page 13: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 13

Page 14: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 14

Staff HiLumi Design Study, with 377 p-m by US Labs and 159 by KEK (Magnets, CC, AP)

Sum of pm Column Labels1 2 3 4 5 6 Grand Total

Row LabelsCERN 114 101 90 107 123.6 58 593.6CEA 24 48 6 78CNRS 40.8 40.8DESY 12 12INFN 67.2 44 22 133.2BINP 65 65CSIC 24 38 62EPFL 48 48RHUL 64 64SOTON 71 71STFC 28 31 59ULANC 70.5 70.5UNILIV 34.8 34.8UNIMAN 34.8 58 92.8KEK 19.2 72 68.5 159.7BNL 14.4 42 60 116.4FNAL 4 56.64 18 12 0 90.64LBNL 4 48 18 18 88ODU 48 48SLAC 4 14.4 16 0 34.4Grand Total 126 591.44 332 477.8 283.6 151 1961.84

163 FTE-y

Page 15: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 15

New baseline to follow the new EU strategy for HEP! Goal: HL-LHC approved by 2013

CB of 17 Nov 2011 , message from President of Council, Prof. Spiro:PDR needed in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013)

Need to fix choice earlier

Page 16: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 16

Malta Workshop14-16 October 2010HE-LHC @ 33 TeV c.o.m

0

20

40

60

80

0 20 40 60 80 100 120

y (m

m)

x (mm)

HTS

HTS

Nb3Snlow j

Nb-Ti

Nb-TiNb3Snlow j

Nb3Snlow j

Nb3Snhigh j

Nb3Snhigh j

Nb3Snhigh j

Nb3Snhigh j

Material N. turns Coil fraction Peak field Joverall (A/mm2) Nb-Ti 41 27% 8 380 Nb3Sn (high Jc) 55 37% 13 380 Nb3Sn (Low Jc) 30 20% 15 190 HTS 24 16% 20.5 380

Magnet design: very challanging but not impossible. 300 mm inter-beamMultiple powering in the same magnet (and more sectioning for energy)Work for 4 years to assess HTS for 2X20T to open the way to 16.5 T/beam .Otherwise limit field to 15.5 T for 2x13 TeVHigher INJ energy is desirable (2xSPS)

The synchrotron light is not a stopper by operating the beam screen at 60 K. The beam stability looks « easier » than LHC thanks to dumping time.Collimation is possibly not more difficult than HL-LHC. Reaching 2x1034 appears reasonable.The big challenge, after main magnet technology, is beam handling for INJ & beam dump: new kicker technology is needed since we cannot make twice more room for LHC kickers.

Page 17: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 17

EC - FP7 EuCARD2 joint research activity• WP10 : Future Magnets : 2013-2016.• 5 T HTS Dipole Magnets

40 mm bore Accelerator Quality• To be tested as insert in existing 13 T magnet• KEK and Univ. of Kyoto (and 5 US labs & Univ) declared

associate collaborators. Interest in YBCO technology.Beneficiary Total

Person-Months

Total Personnel

direct costs

Total Personnel

indirect costs

Total Sub-contracting

cost

Total Consumable

and prototype

direct costs

Total Travel direct costs

Total Material and

travel indirect costs

Total direct costs

Toal indirect costs

Total costs(direct

+indirect)

Total EC requested

funding

CERN 120 1,129,740 677,844 - 800,000 71,000 522,600 2,000,740 1,200,444 3,201,183 346,385 CEA 54 321,278 202,405 - 160,000 20,000 - 501,278 202,405 703,683 315,805 INPG 43 141,384 84,830 - 12,000 8,000 12,000 161,384 96,830 258,214 101,672 INFN 39 144,495 86,697 - 130,000 14,000 86,400 288,495 173,097 461,592 181,752 KIT 16 94,224 100,800 - 80,000 10,000 - 184,224 100,800 285,024 116,061 SOTON 16 89,680 79,815 - 40,000 10,000 - 139,680 79,815 219,495 87,998 UNIGE 12 109,872 65,923 - 50,000 4,000 32,400 163,872 98,323 262,195 103,239 UT 20 131,580 78,948 - 50,000 8,000 34,800 189,580 113,748 303,328 119,435 BHTS 38 223,782 304,344 - 150,000 4,000 - 377,782 304,344 682,126 238,003 TUT 8 37,757 22,654 - - 12,000 7,200 49,757 29,854 79,612 31,347 DTI 10 66,687 46,681 - 20,000 6,000 - 92,687 46,681 139,368 58,393 TOTAL: 376 2,490,479 1,750,942 - 1,492,000 167,000 695,400 4,149,479 2,446,342 6,595,820 1,700,091

Page 18: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 18

What is the possibile for HE-LHC?

2005 2010 2015 2020 2025 2030 2035

US 16 T small dipole

EuCARD 13 T large dipole+

18 T small insert

US 13 T Quads FP7-HiLumi

US NbSn-HTS development

15-20 T dip final proto &

Industrialization

Final delivery Magnets HE-LHC

HE-LHC start-up

HE-LHC preliminary

study

HTS for HE-LHC:

yes.or.no

LARP 11 T long quadEuCARD

R&D

Industry contracts, start

constrution

US basic programs and

LARP R&DEU FP6-CARE-NED

EuCARD2 full bore

dipole HTS

15-20 T R&D dipole

models and prototypes

Page 19: Report @ CERN-KEK about LHC upgrades programs

LRossi@CERN-KEK Dec2011 19

HiLumi (and HE) LHC : the best use of the (renovated) existing infrastructure

LHeC ?

Page 20: Report @ CERN-KEK about LHC upgrades programs