report @ cern-kek about lhc upgrades programs
DESCRIPTION
Report @ CERN-KEK about LHC upgrades programs. Lucio Rossi 14 December 2011. The path and goals: 3000 fb -1 – L peak < 5 10 34. Rad. damage. Tuning of the goal after summer. - PowerPoint PPT PresentationTRANSCRIPT
Report @ CERN-KEK about LHC upgrades programs
Lucio Rossi
14 December 2011
LRossi@CERN-KEK Dec2011 2
The path and goals: 3000 fb-1 – Lpeak< 5 1034
Rad.damage
LRossi@CERN-KEK Dec2011 3
Tuning of the goal after summer
Efficiency is defined as the ratio between the annual luminosity target of 250 fb-1 over the potential luminosity that can be reached with an ideal cycle run time with no stop for 150 days: trun= tlev+tdec+tturn. The turnaround time after a beam dump is taken as 5 hours, tdecay is 3 h while tlev depends on the total beam current
LRossi@CERN-KEK Dec2011 4
Cycle in the HL-LHC run20E+34 pile up
heat deposition in IR and DSother?
Levelling
LRossi@CERN-KEK Dec2011 5
Possible evolution toward 3000 fb-1
LRossi@CERN-KEK Dec2011 6
IR Magnets (triplet, D1, D2, MQ4, …) SC Crab Cavities, IR Collimation
LRossi@CERN-KEK Dec2011 7
Other changes• Cryogenics• During LS2, a new refrigerator will be
installed at P4, to feed RF cavities and restore IR 5L
• Refrigerator 6.5 kW @ 4.5 K:• 4.5 kW + 0.25 kW (flash) + 0.12 kW
(thermal losses line & valve box) + 1.6 kW (contingency 33%)
• During LS3 new refrigerators for P1-P5• Warm compressor installed in surface.
Warm gas lines in Pit• Cold boxes installed in underground and
surface (if 2 K or 1.8 K options) • Distribution and transfer lines to
equipments (magnets, DFBs, crab-cavities ?, SCL ?, sector powering ?...)
LRossi@CERN-KEK Dec2011 8
Other changes (list not exhaustive…)• R2E: whatever needed, see from experience
frome next years• P8• Removal of EPC and DFBX from tunnel to
surface via long SC links rated of 0.1-1 GW d.c.
LRossi@CERN-KEK Dec2011 9
LIU – LHC Inj Upgrade (R. Garoby)LS2 (2018) and LS3 (2012-23)
• Linac4 (160 Mev H- vs. 50 MeV H of Linac2)Ready by mid 2014Connected 2015?Reliability, brilliance…
• PS Booster upgrade:from 1.4 GeV (800 Gev)to 2 GeV to reduce space ahrge at PS injectionIntensity gain : +65%Project launched;
• SPS reduction of impedencenew optics with low t (2615 GeV)new 200 MHz cavitiesreduction e-clouds by vaccum chamber coating (or scrubbing?)
LRossi@CERN-KEK Dec2011 10
The HL composition, larger than FP7 HiLumi
WP1 Project Management and Technical Coordination
WP2 Accelerator Physics and Performance
WP3 Magnet Design
WP5 IR Collimation
WP6 Cold Powering
WP4 Crab Cavities
HiLumi LHC
WP7 Machine Protection
WP8 Collider-Experiment Interface
WP9 Cryogenics
WP10 Energy Deposition and shielding
WP11 11 tesla dipole two-in-one
WP12 Integration & (de)installation
Non-HiLumi LHC
HL-LHC Design Study
CollimationProject
Matching section and correctors
Beam Diagnostics
High Field Magnets R&D
HE-LHC Studies Hardware Commissioning
EuCARD2 WP10 on HTS dipoles
LRossi@CERN-KEK Dec2011 11
Budget FP7 HiLumi and HL-LHC
Perfect score 15/15,
ALL request to EU
granted
Design in FP7 HiLumi
Extra effort for Design
R&D and proto
Industrialization & Construction TOT Industry
W1-WP6 27 10 50 200 287 160WP7-12 0 15 30 100 145 80Other 0 5 10 50 65 40TOT 27 30 90 350 497 280
Estimated cost for the the whole HL-LHC over 10 years in M€ (October 2010)
LRossi@CERN-KEK Dec2011 12
3 days Collaboration Meeting at CERN 14-18 Nov (160 people)
Collaboration Board members/invited
LRossi@CERN-KEK Dec2011 13
LRossi@CERN-KEK Dec2011 14
Staff HiLumi Design Study, with 377 p-m by US Labs and 159 by KEK (Magnets, CC, AP)
Sum of pm Column Labels1 2 3 4 5 6 Grand Total
Row LabelsCERN 114 101 90 107 123.6 58 593.6CEA 24 48 6 78CNRS 40.8 40.8DESY 12 12INFN 67.2 44 22 133.2BINP 65 65CSIC 24 38 62EPFL 48 48RHUL 64 64SOTON 71 71STFC 28 31 59ULANC 70.5 70.5UNILIV 34.8 34.8UNIMAN 34.8 58 92.8KEK 19.2 72 68.5 159.7BNL 14.4 42 60 116.4FNAL 4 56.64 18 12 0 90.64LBNL 4 48 18 18 88ODU 48 48SLAC 4 14.4 16 0 34.4Grand Total 126 591.44 332 477.8 283.6 151 1961.84
163 FTE-y
LRossi@CERN-KEK Dec2011 15
New baseline to follow the new EU strategy for HEP! Goal: HL-LHC approved by 2013
CB of 17 Nov 2011 , message from President of Council, Prof. Spiro:PDR needed in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013)
Need to fix choice earlier
LRossi@CERN-KEK Dec2011 16
Malta Workshop14-16 October 2010HE-LHC @ 33 TeV c.o.m
0
20
40
60
80
0 20 40 60 80 100 120
y (m
m)
x (mm)
HTS
HTS
Nb3Snlow j
Nb-Ti
Nb-TiNb3Snlow j
Nb3Snlow j
Nb3Snhigh j
Nb3Snhigh j
Nb3Snhigh j
Nb3Snhigh j
Material N. turns Coil fraction Peak field Joverall (A/mm2) Nb-Ti 41 27% 8 380 Nb3Sn (high Jc) 55 37% 13 380 Nb3Sn (Low Jc) 30 20% 15 190 HTS 24 16% 20.5 380
Magnet design: very challanging but not impossible. 300 mm inter-beamMultiple powering in the same magnet (and more sectioning for energy)Work for 4 years to assess HTS for 2X20T to open the way to 16.5 T/beam .Otherwise limit field to 15.5 T for 2x13 TeVHigher INJ energy is desirable (2xSPS)
The synchrotron light is not a stopper by operating the beam screen at 60 K. The beam stability looks « easier » than LHC thanks to dumping time.Collimation is possibly not more difficult than HL-LHC. Reaching 2x1034 appears reasonable.The big challenge, after main magnet technology, is beam handling for INJ & beam dump: new kicker technology is needed since we cannot make twice more room for LHC kickers.
LRossi@CERN-KEK Dec2011 17
EC - FP7 EuCARD2 joint research activity• WP10 : Future Magnets : 2013-2016.• 5 T HTS Dipole Magnets
40 mm bore Accelerator Quality• To be tested as insert in existing 13 T magnet• KEK and Univ. of Kyoto (and 5 US labs & Univ) declared
associate collaborators. Interest in YBCO technology.Beneficiary Total
Person-Months
Total Personnel
direct costs
Total Personnel
indirect costs
Total Sub-contracting
cost
Total Consumable
and prototype
direct costs
Total Travel direct costs
Total Material and
travel indirect costs
Total direct costs
Toal indirect costs
Total costs(direct
+indirect)
Total EC requested
funding
CERN 120 1,129,740 677,844 - 800,000 71,000 522,600 2,000,740 1,200,444 3,201,183 346,385 CEA 54 321,278 202,405 - 160,000 20,000 - 501,278 202,405 703,683 315,805 INPG 43 141,384 84,830 - 12,000 8,000 12,000 161,384 96,830 258,214 101,672 INFN 39 144,495 86,697 - 130,000 14,000 86,400 288,495 173,097 461,592 181,752 KIT 16 94,224 100,800 - 80,000 10,000 - 184,224 100,800 285,024 116,061 SOTON 16 89,680 79,815 - 40,000 10,000 - 139,680 79,815 219,495 87,998 UNIGE 12 109,872 65,923 - 50,000 4,000 32,400 163,872 98,323 262,195 103,239 UT 20 131,580 78,948 - 50,000 8,000 34,800 189,580 113,748 303,328 119,435 BHTS 38 223,782 304,344 - 150,000 4,000 - 377,782 304,344 682,126 238,003 TUT 8 37,757 22,654 - - 12,000 7,200 49,757 29,854 79,612 31,347 DTI 10 66,687 46,681 - 20,000 6,000 - 92,687 46,681 139,368 58,393 TOTAL: 376 2,490,479 1,750,942 - 1,492,000 167,000 695,400 4,149,479 2,446,342 6,595,820 1,700,091
LRossi@CERN-KEK Dec2011 18
What is the possibile for HE-LHC?
2005 2010 2015 2020 2025 2030 2035
US 16 T small dipole
EuCARD 13 T large dipole+
18 T small insert
US 13 T Quads FP7-HiLumi
US NbSn-HTS development
15-20 T dip final proto &
Industrialization
Final delivery Magnets HE-LHC
HE-LHC start-up
HE-LHC preliminary
study
HTS for HE-LHC:
yes.or.no
LARP 11 T long quadEuCARD
R&D
Industry contracts, start
constrution
US basic programs and
LARP R&DEU FP6-CARE-NED
EuCARD2 full bore
dipole HTS
15-20 T R&D dipole
models and prototypes
LRossi@CERN-KEK Dec2011 19
HiLumi (and HE) LHC : the best use of the (renovated) existing infrastructure
LHeC ?