LESSONS LEARNT FROM
A PILOT PROJECT FOR
PMMR IN TANZANIA
By; Eng Chrispianus B Ako,Director of Projects - TANROADS
TABLE OF CONTENT1. Overview of PMMR
Pilot Project2. Lessons learnt3. Way forward
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
�1,010 km of unpaved roads in three different regions
� 6 contract packages- Initial plan was about 300km per package - later reduced to about 100 - 200 km per package
Scope of Pilot project
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
�Works performed included;- Initial Rehabilitation – paid based on output- Maintenance Works – fixed lump sum per month- Emergency Works - as instructed
Scope of Pilot project
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
� started in 2007 and completed in 2012
� 6 Local Contractor executed the Works
�3 local Firms supervised the works
�1 International firm conducted training and facilitation
� Contractors were responsible to plan what do, where to do, how to do and when to do in order to meet performance criteria.
Implementation arrangement
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
� Supervision consultant were responsible for- assessing contractor’s compliance every month and
certify payments accordingly- quality control for rehabilitation works and
emergency Works- Inspecting road condition and notify Contractor on
defects
Implementation arrangement
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
Performance CriteriaService level Fair
< 50 VpdGood50-100 vpd
V. Good>100 vpd
Accessibility All year All year All year
Travel speed (km/h) 40 50 60
Road User Comfort: Max Rut depth ( cm) 10 7.0 5.0
Max. area for single degradation (m2) 1 1 0.5
Max cumulative degradation per km (m2) 100 80 50
Max. corrugation amplitude (cm) 5 3.5 2.5
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
Time table of compliance
Usability TrafficSpeed
Road UserComfort
Durability
Very Good Month 3 Month 8 Month 6 Month 14
Good Month 3 Month 8 Month 10 Month 17
Fair Month 3 Month 8 Month 11 Month 19
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Overview of Pilot Project
� Value for Money
� Reduced Overhead to the Agency
� Timely attendance of emergency Works
� Comparatively lower costs
Expected Benefits of PMMR
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Lessons learnt
1. Select roads which are in maintainable state
2. Design of rehabilitation Works should not be done by Contractors
3. Use simplified performance criteria
eg Measure roughness instead of various distress,
4. Select few but effective service quality levels
eg use GOOD instead of GOOD and FAIR
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Lessons learnt
5. Identify and apportion risks properly.
- risk of traffic increase - Employer
- risk of overloading - Employer
- land acquisition - Contractor
6. Clarity on contract Documents
- conditions of Contracts
- specifications
1st AfDB Transport Forum26-27 Novembre 2015 Abidjan
Lessons learnt
7. Undertake adequate training for the prospective bidders
8. Select contractors with Technical and financial capability
9. Give adequate time for bid preparation
10. Provide training/ awareness to Agency staff
11.Provide awareness to societies along project area