lee williams, aurecon - wiggins island coal terminal – design case study
DESCRIPTION
Lee Williams, Principal Bulk Materials Handling Engineer, Aurecon delivered this presentation at the 10th Annual Bulk Materials Handling conference 2013. This conference is an expert led forum on the engineering behind the latest expansions and upgrades of bulk materials facilities. It also evaluates the latest engineering feats that are creating record levels of throughput whilst minimising downtime. For more information on this conference, please vist http://www.informa.com.au/bmh2014TRANSCRIPT
Wiggins Island Coal Export Terminal
BMH presentation – 4 June 2013
Wharf
Rail receival
Stockyard
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
Wiggins Island Coal Export terminal
Presentation 4 June 2013
Design Case Study
• Basic overview of terminal
• Design brief and response
– Terminal capacity
– Automation
– Equipment selection and innovation
– Environmental considerations
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
Site overview - 3D fly through
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
Basic WICET facility facts
• Terminal throughput 27 Mtpa
• Rail receival
– Automated rail receival station with wagon vibrator
– Bottom dump wagons
– Unloading rate up to 8250tph via belt feeder
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Stockyard
– Dedicated storage facility with approximately 1.6Mt of
on ground storage
– Stacking via automated bridge stacker with dozer
push reclaim onto tunnel conveyors
– Stacking rate up to
8250tph, reclaim 6900tph
– Blending from multiple
coal stockpiles on
shiploading
– 1200T surge bin
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Offshore
– 2km long jetty conveyor to offshore wharf
– Loading rate 8250tph
– Long travelling, luffing shiploader
– Vessel size 40,000dwt to 220,000dwt
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Design brief
– Stage 1 capacity of 27 Mtpa expanding in stages to 70+ Mtpa
– Dedicated storage facility with high blending capability
– Highly automated design
– High level of reliability
– Design for a range of coal types – some poor handleability
expected
– Leading environmental controls and solutions
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
– Initial handling rates and equipment selected with
static modelling and previous experience benchmark
– Once basic design complete, equipment selection
and sizing was confirmed by application of a dynamic
simulation model
Shipping queue vs Throughput
Base Case
Shipping queue vs Throughput
Sensitivity analysis
CAPACITY
27Mtpa 27Mtpa
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Dedicated storage with high blending capability
– 70% of blended product with up to 5 way blending required
– Terminal with multiple drawdown points and dozer discharge
allowed maximum flexibility for blending operations
– Dedicated storage requirement of approximately 6% of
yearly throughput
BLENDING CAPABILITY
Tunnel cross section
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Rail receival
– Automated readers and tags on wagons
– Automated triggers to discharge coal
– Train speed feedback to loco drivers
– Wagon vibrator to assist discharge of sticky coals
– Volumetric control of feed rate to maximise conveyor fill
independent of density
HIGHLY AUTOMATED SOLUTION
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Stockyard and stacking operations
– Automated stacker able to stack to a pre-defined area with a
selected stacking pattern with minimal operator intervention
– Dust suppression sprays which operate automatically with
input from the Bureau of Meteorology
– Coal tracking system on unloading operations so a “gap” can
be placed between batches based on stacker repositioning
time (Important for remote rail receival site)
HIGHLY AUTOMATED SOLUTION
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Reclaiming operations and shiploading
– Automated reclaim feeder control to maintain load
rate accuracy
– Shiploader designed to be capable of remote tele-
operation as a first step towards future automation
– Wharf is designed to be retro-fitted with Moormaster
automated mooring system which eliminates rope
handling on the wharf
HIGHLY AUTOMATED SOLUTION
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Belt conveyors/feeders are based on proven designs. Idler
selection and spacing optimised. Low rolling resistance covers
used widely. Extensive dynamic modelling undertaken
– Feeders (Rail receival and surge bin) 3200mm
– Overland conveyor 1800mm, 6.9m/s, horizontal curve
– Yard conveyors 2000mm, 6m/s
– Shiploader 2200mm, 6m/s
EQUIPMENT SELECTION AND INNOVATION
Rail receival section OC1 start tensions
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Stacker design undertaken by Aurecon’s experienced
machine designers
• Subject to extensive internal and external reviews and risk
assessments
• Fully automated, articulated machine
• Multi layer skew control and protection system
EQUIPMENT SELECTION AND INNOVATION
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
260m OVERALL
•Stacker over
Suncorp Stadium
•Each leg within
+/-200mm at travel
speed of 30m/min
Photo courtesy of Google
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Shiploader design undertaken by Aurecon’s machine
design team. Designed in tandem with the wharf
• Lightweight shiploader design to reduce loading on wharf
and allow a relatively lightweight wharf structure
EQUIPMENT SELECTION AND INNOVATION
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
EQUIPMENT SELECTION AND INNOVATION
• 3D modelling used in the design process to maximise the
feedback from operators. Good interaction during HAZOPs
and safety reviews
• Multi discipline formal and informal walk throughs were
undertaken regularly to ensure client requirements were
met
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Noise
– Conveyors incorporate low noise idlers with tight
tolerances on roundness and balance
– Tight tolerances on allowable noise generated from
individual drives and motors. Factory testing
– Drives generally located at ground level to minimise
the effective noise travel length
– Directional alert sirens incorporated on travelling
equipment to direct sound to the hazardous areas
only and limit any unnecessary leakage to surrounds
LEADING ENVIRONMENTAL CONTROLS
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Dust
– Dust collection system for the rail receival hopper
– Moisture analysers and water addition system on the
unloading stream to complement DEM moisture levels
– Partial enclosure of most elevated conveyors
– Dust suppression sprays at conveyor transfer points
– Full coverage stockyard water sprays with a control link
to the Bureau of Meteorology (BOM) to allow pre-
emptive actions to be taken
– Telescopic chutes on
stacker discharge
LEADING ENVIRONMENTAL CONTROLS
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
LEADING ENVIRONMENTAL CONTROLS
• Dust (Cont’d)
– Real time dust monitoring around the stockyard and
rail receival with captured data used on a daily basis
to improve dust management practices
– Moisture analyser and water addition system on the
shiploading stream
– Vegetation buffer around the site to reduce wind
effects as well as provide a visual barrier
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Spillage
– Multiple scraper belt cleaning with belt washing
– Solid floors in elevated gallery sections
– Solid floors along length of jetty conveyor
– Capture trays under the wharf conveyor
– Shiploader capture controls
– Overall offshore slurry capture and return system
LEADING ENVIRONMENTAL CONTROLS
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
• Stockyard equipment progress
Gantry structure progress
Bridge stacker
progress
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
FUTURE PROOFING THE DESIGN
• Capacity – Future expansion planning is underway
– Terminal is designed for future upgrades with minimal
operational interruptions
• Automation – Rail receival automation is already good
– Opportunities in the stockyard for dozer remote operation
– Opportunities on shiploading for remote operation and some
degree of automation
• Environmental controls – Performance will be monitored with the continuous monitors
– Further opportunities may arise but will largely depend on coal
properties
Wiggins Island Coal Export Terminal – BMH 2013
BMH 2013 BMH 2013
THANK YOU