learning resource material on irrigation engineering
TRANSCRIPT
LEARNING RESOURCE MATERIAL
ON
IRRIGATION ENGINEERING
(CET403)
UNDER EDUSAT PROGRAMME
SCTE&VT, BHUBANESWAR
ODISHA
Coordinator: Sri B. C. Sahu ,
Sr. Lecturer (Civil)
Govt. Polytechnic, Nabarangpur
Nodal Officer: Dr. P. K. Muduli,
Sr. Lecturer (Civil).
Govt. Polytechnic, Kendrapara
1
CONTENTS
Chapter
No.
Topic Name Page
No.
Prepared by
01 INTRODUCTION 2-6
Ms Amrapalli Sahoo,
Lecturer (Civil),
JES, Jarsuguda
02
HYDROLOGY
7-16
Sri Satyananda Sethi
Lecturer (Civil),
GP, Sambalpur
03
WATER REQUIREMENT OF CROPS 17-22
Smt. Sailaja Bhuyan,
Lecturer (Civil)
UGIE, Rourkela
04
FLOW IRRIGATION 23-32
Smt. Sailaja Bhuyan,
Lecturer (Civil)
UGIE, Rourkela
05
WATER LOGGING AND DRAINAGE
33-36
Sri D. K. Mohapatra
Lecturer (Civil)
ITT, Choudwar
06
DIVERSION HEAD WORKS AND
REGULATORY STRUCTURES
37-46
Sri Sudhakar Naik,
Lecturer (Civil)
GP, Gajapati
07
CROSS DRAINAGE WORKS
47-54
Sri Sanjeeb Meher
Lecturer (Civil)
GP, Sambalpur
08
DAMS
55-70
Sri D. Kura
Senior Lecturer (Civil)
JES, Jharsuguda
09
GROUND WATER HYDROLOGY 71-94
Dr. P. K. Mohanty
Principal,
ITI, Dhenkanal
2
CHAPTER -1
INTRODUCTION
Irrigation Practice in India can be traced to prehistoric times. Perhaps the earliest reference
to irrigation is given by the great sage, Narada who come to see the Emperor, Yudhishthhira, around
3150 B.C and asked “Are the farmers sturdy and prosperous? Ancient Hindu rulers took very keen
interest in construction of irrigation works. The account left by Megasthenese – the Greek
Ambassador of Sleukos Nikator to the court of Chandra Gupta Maurya also gives some idea about
irrigation in India around 300 B.C.
The Muslim rulers also took keen interest in constructing canals for irrigation. In the 14th
Century, Sultan Firoz Tughlaq constructed a number of canals from Sutlej and Yamuna rivers. Akbar
remodelled Firozshah canal in 16th
century and put it in use again. State controlled irrigation works
have begun to play a major role only in the last about 150-200 years. In the 19th
Century , the British
Raj was more concerned with the improvement of existing irrigation works than with building new
ones. Three important irrigation works – Western Yamuna Canal, Eastern Yamuna Canal and Cauvery
Delta System were remodelled and opened.
Perhaps the first hydro-electric work in India was undertaken in 1897 near Darjeeling. The
state of Mysore constructed in 1902, the Sivasamudram hydroelectric works with an installed
capacity of 4500 kW. After independence (1947) the government of India was concerned with the
need for food for a vastly growing population and irrigation was given a much needed impetus.
Nearly 27.2% of the total outlay in the first five year plan (1951-56) was set side for irrigation and
power. In second five year plan (1956-61) , 19% of the total outlay was used for irrigation and
power. In the third five year plan (1961-66), about 22% of the total outlay was spent on irrigation
and power development.
Types Of Irrigation :
Irrigation may broadly be classified into
1. Surface irrigation
2. Sub-surface irrigation
1. Surface Irrigation :
It can be classified into:
(a) Flow Irrigation
(b) Lift Irrigation
3
When the water is available at a higher level, and it is supplied to lower level, by the more
action of gravity, then it is called Flow Irrigation. But if the water is lifted up by some
mechanical or manual means, such as pumps, etc. and then supplied for irrigation , then it is
called Lift irrigation.
Flow irrigation can be further sub divided into:
(i) Perennial irrigation
(ii) Flood irrigation
Perennial Irrigation : In perennial system of irrigation, constant and continuous water
supply is assured to the crops in accordance with the requirements of the crops, throughout
the crop period. In this system of irrigation, water is supplied through storage canal head
works and canal distribution system.
When the water is directed into the canal by constructing a weir or a barrage across the river,
it is called Direct Irrigation. Ganga canal system is an example of this type of irrigation. But
if a dam is constructed across a river to store water during monsoons, so as to supply water in
the off-taking channels during periods of low flow, then it is termed as storage irrigation.
Flood Irrigation : This kind of irrigation , is sometimes called as inundation irrigation. In
this method of irrigation, soil is kept submerged and thoroughly flooded with water, so as to
cause thorough saturation of the land. The moisture soaked by the soil, when occasionally
supplemented by natural rainfall or minor watering, brings the crop to maturity.
(2) Sub-Surface Irrigation – It is termed as sub-surface irrigation, because in this type of
irrigation , water does not wet the soil surface. The underground water nourishes the plant
roots by capillarity. It may be divided into the following two types.
(a) Natural sub irrigation and
(b) Artificial sub-irrigation.
(a) Natural sub-irrigation – Leakage water from channels, etc goes underground, and
during passage through the sub soil, it may irrigate crops, sown on lower land , by capillarity.
Sometimes , leakage causes the water table to rise up, which helps in irrigation of crops by
capillarity. When underground irrigation is achieved, simply by natural processes, without
any additional extra efforts, it is called natural sub-irrigation.
(b) Artificial sub-irrigation – When a system of open jointed drains is artificially laid
below the soil, so as to supply water to the crops by capillarity, then it is known as artificial
sub-irrigation. It is a very costly process and hence adopted in India on a very small scale.
Sometimes irrigation water may be intentionally collected in some ditches near the fields, the
percolation water may then come up to the roots through capillarity.
4
Sources Of Irrigation Water :
There are various ways in which the irrigation water can be applied to the fields. Their main
classification is as follows :
(1) Free flooding
(2) Border flooding
(3) Check flooding
(4) Basin flooding
(5) Furrow irrigation method
(6) Sprinkler irrigation method
(7) Drip irrigation method
(1) Free flooding or Ordinary Flooding – In this method, ditches are excavated in the
field, and they may be either on the contour or up and down the slope. Water from
these ditches, flows across the field. After water leaves the ditches , no attempt is
made to control the flow by means of leaves. Etc. Since the movement of water is not
restricted, it is sometimes called wild flooding. Although the initial cost of land
preparation is low, labour requirements are usually high and water application
efficiency is also low. Wild flooding, is most suitable for close growing crops,
pastures, etc. particularly where the land is steep. Contour ditches called lateral or
subsidiary ditches. Are generally spaced at about 20 to 50 metres apart, depending
upon the slope, texture of soil, crops to be grown, etc. This method may be used on
rolling land where borders , checks, basins and furrows are not feasible.
(2) Border flooding – In this method, the land is devided into a number of strips,
separated by low leaves called borders. The land areas confined in each strip is of the
order of 10 to 20 metres in width and 100 to 400metres in length. To prevent water
from concentrating on either side of the border , the land should be levelled
perpendicular to the flow. Water is made to flow from the supply ditch into each strip.
The water flows slowly towards the lower end, and infiltrates into the soil as it
advances. When the advancing water reaches the lower end of the strip, the supply of
water to the strip is turned off. The supply ditch, also called irrigation stream, may
either be in the form of an earthen channel or a lined channel or an underground
concrete pipe having risers at intervals.
(3) Check Flooding – Check flooding is similar to ordinary flooding except that the water
is controlled by surrounding the check area with low and flat levees. Levees are
5
generally constructed along the contours, having vertical interval of about 5 to 10 cm.
These levees are connected with cross – levees at convenient places. The confined
plot area varies from 0.2 to 0.8 hectare. In check flooding, the check is filled with
water at a fairly high rate and allowed to stand until the water infiltrates. This method
is suitable for more permeable soils as well as for less permeable soils, thus reducing
the percolation losses. The water can also be held on the surface for a longer time in
case of less permeable soils, for assuring adequate penetration.
(4) Basin Flooding – This method is a special type of check flooding and is adopted
specially for orchard tress. One or more trees are generally placed in the basin and the
surface is flooded as in check method by ditch water.
(5) Furrow irrigation method – In flooding methods, described above, water covers the
entire surface while in furrow irrigation method only one-fifth to one-half of the land
surface is wetted by water. It therefore results in less evaporation, less pudding of soil
and permits cultivation sooner after irrigation. Furrows are narrow field ditches,
excavated between rows of plants and carry irrigation water through them. Spacing of
furrows is determined by the proper spacing of the plants. Furrows vary from 8 to 30
cm deep, and may be as much as 400 metres long. Excessive long furrows may result
in too much percolation near the upper end. And too little water near the down slope
and. Deep furrows are widely used for row crops. Small shallow furrows called
corrugations are particularly suitable for relatively irregular topography and close
growing crops such as meadows and small grains.
(6) Sprinkler irrigation method – In this farm water application method, water is applied
to the soil in the form of a spray through a network of pipes and pumps. It is a costly
process and widely used in U.S.A. It can be used for all types of soils and for widely
different topographic and slopes. It can be used for many crops, because it fulfils the
normal requirements of uniform distribution of water. This method possesses great
potentialities for irrigation areas. This method not only costly but requires a lot of
technicalities. Special steps have to be taken for preventing entry of silt and debris,
which are very harmful for the sprinkler equipments.
(7) Drip irrigation method – Drip irrigation also called trickle irrigation is the latest field
irrigation technique and is meant for adoption at places where there exists acute
scarcity of irrigation water and other salt problems. In this methods, water is slowly
and directly applied to the root zone of the plants, thereby minimising the losses by
evaporation and percolation. This system involves laying of a system of head, mains,
6
sub-mains, laterals and drop nozzles. Water oozes out of these small drip nozzles
uniformly and at a berry small rate, directly into the plant roots areas. The head
consists of a pump to lift water, so as to produce the desired pressure of about 2.5
atmosphere, for ensuring proper flow of water through the system. The lifted
irrigation water is passed through a fertiliser tank, so as to remove the suspended
particles from the water to avoid clogging of drip nozzles. The mains and sub mains
are the specially designed small sized pipes, made of flexible material like black PVC.
These are generally buried or laid on the ground. Their sizes should be sufficient to
carry the design discharge of the system.
7
CHAPTER -2
HYDROLOGY
Hydrological Cycle:-
The water of the universe always changes from one state to other under the effect of
the sun. The water from the surface source like lakes, rivers, oceans, etc. converts to vapour
by evaporation due to solar heat. The vapour goes on accumulating continuously in the
atmosphere. This vapour is again condensed due to the sudden fall of temperature and
pressure. Thus clouds are formed. These clouds again cause the precipitation (i.e. rainfall).
Some of the vapour is converted to ice at the peak of mountains. The ice again melts in
summer and flows as rivers to meet the sea or ocean. These processes of evaporation,
precipitation and melting of ice go on continuously like an endless chain and thus a balance is
maintained in the atmosphere. This phenomenon is known as hydrologic cycle.
Ch-2.2 Precipitation or Rain Fall and its Measurement:-
From the principle of hydrologic cycle we have seen that water goes on evaporation
continuously from the water surface on earth (e.g. river, lake, sea, ocean, etc), by the effect of
sun. The water vapour goes on collecting in the atmosphere up to a certain limit. When this
limit exceeds and temperature and pressure fall to certain value, the water vapour will get
condensed and thereby cloud is formed. Ultimately droplets are formed and returned to earth
in the form of rain, snowfall, hail, etc. This is known as rain fall or precipitation.
Types of Precipitation or Rain Fall:-
Depending upon the various atmospheric conditions the precipitation may be of the
following types:
The hydrograph is a general representation of the discharge of river (in cumec)
against the time (in hr or days). The discharge is plotted as ordinate (y
plotted as abscissa (x-axis) (see the figure)
During the dry season, there is only base f
runoff. This may be shown by a line which is approximately straight (not shown in the figure)
In rainy season, at the beginning of the rainfall there is only base flow (shown by the
line AB). After some period, w
infiltration) are fulfilled, the surface runoff stars and hence the discharge of river goes on
increasing. Hence the limb of the curve rises which is called rising limb (shown by line BC).
This line reaches to the peak value at ‘C’. Again when the rain stops, the flow in the river
decreases and the limb of the curve declines. This limb is known as recession limb (as shown
by the line CD). This discharge at the point C indicates the maximum discharge
discharge or flood discharge). The total area under the curve ABCDE indicates the total
runoff. But this run off includes the base flow and the direct runoff. So, to get the actual
runoff the base flow is to be ducted by separating it from tota
1) Cyclonic Precipitation:
This type of precipitation is caused by the difference of pressure within the air mass
on the surface of the earth. If low pressure is generated at some place the warm moist air
from the surrounding area rushes to the zo
moist air rises up with whirling motion and gets condensed at higher altitude and ultimately
heavy rain fall occurs.
This may be two types.
a) Frontal Precipitation
b) Non Frontal Precipitation
a) Frontal Precipitation:-
When the moving warm moist air mass is obstructed by the zone of cold air mass, the
warm moist air rises up (as it is lighter than cold air mass) to higher altitude where it gets
condensed and heavy rainfall occurs. This is known as Frontal
b) Non Frontal Precipitation:-
When the warm moist air mass rushes to the zone of low pressure from the
surrounding area, a pocket is formed and the warm moist air rises up like a chimney towards
8
graph is a general representation of the discharge of river (in cumec)
against the time (in hr or days). The discharge is plotted as ordinate (y-axis) and the time is
axis) (see the figure)
During the dry season, there is only base flow (i.e. ground water flow) but no surface
runoff. This may be shown by a line which is approximately straight (not shown in the figure)
In rainy season, at the beginning of the rainfall there is only base flow (shown by the
line AB). After some period, when the initial losses (like interception, evaporation and
infiltration) are fulfilled, the surface runoff stars and hence the discharge of river goes on
increasing. Hence the limb of the curve rises which is called rising limb (shown by line BC).
e reaches to the peak value at ‘C’. Again when the rain stops, the flow in the river
decreases and the limb of the curve declines. This limb is known as recession limb (as shown
by the line CD). This discharge at the point C indicates the maximum discharge
discharge or flood discharge). The total area under the curve ABCDE indicates the total
runoff. But this run off includes the base flow and the direct runoff. So, to get the actual
runoff the base flow is to be ducted by separating it from total area.
This type of precipitation is caused by the difference of pressure within the air mass
on the surface of the earth. If low pressure is generated at some place the warm moist air
from the surrounding area rushes to the zone of low pressure with violent force. The warm
moist air rises up with whirling motion and gets condensed at higher altitude and ultimately
Frontal Precipitation
Non Frontal Precipitation
When the moving warm moist air mass is obstructed by the zone of cold air mass, the
warm moist air rises up (as it is lighter than cold air mass) to higher altitude where it gets
condensed and heavy rainfall occurs. This is known as Frontal Precipitation.
When the warm moist air mass rushes to the zone of low pressure from the
surrounding area, a pocket is formed and the warm moist air rises up like a chimney towards
graph is a general representation of the discharge of river (in cumec)
axis) and the time is
low (i.e. ground water flow) but no surface
runoff. This may be shown by a line which is approximately straight (not shown in the figure)
In rainy season, at the beginning of the rainfall there is only base flow (shown by the
hen the initial losses (like interception, evaporation and
infiltration) are fulfilled, the surface runoff stars and hence the discharge of river goes on
increasing. Hence the limb of the curve rises which is called rising limb (shown by line BC).
e reaches to the peak value at ‘C’. Again when the rain stops, the flow in the river
decreases and the limb of the curve declines. This limb is known as recession limb (as shown
by the line CD). This discharge at the point C indicates the maximum discharge (i.e. peak
discharge or flood discharge). The total area under the curve ABCDE indicates the total
runoff. But this run off includes the base flow and the direct runoff. So, to get the actual
This type of precipitation is caused by the difference of pressure within the air mass
on the surface of the earth. If low pressure is generated at some place the warm moist air
ne of low pressure with violent force. The warm
moist air rises up with whirling motion and gets condensed at higher altitude and ultimately
When the moving warm moist air mass is obstructed by the zone of cold air mass, the
warm moist air rises up (as it is lighter than cold air mass) to higher altitude where it gets
When the warm moist air mass rushes to the zone of low pressure from the
surrounding area, a pocket is formed and the warm moist air rises up like a chimney towards
higher altitude. At higher altitude this
is known as Non Frontal Precipitation.
2) Convective Precipitation:
In tropical counties when on a particular hot day the ground surface gets heated
unequally, the warm air is lifted to high altitude
velocity, thus, the warm moist air mass is condensed at the high altitude causing heavy rain
fall. This is known as convective precipitation (see from the figure).
2) Orographic Precipitation:
The moving warm moist air when obstructed by some mountain rises up to high
altitude, it then gets condensed and precipitation occurs. This is known as orographic
precipitation (Figure).
Hyetograph:
The graphical representation of rain fall and run
prepared with intensity of rainfall (in cm/hr) as ordinate and time (in hrs) as abscissa. The
infiltration capacity curve is drawn on this graph to show the amount of infiltration loss
(shown by dotted portion). The upper portion indicat
hatched line).
The centroid of the effective rain fall is ascertained on the graph for determination of total
run-off at any specified period.
9
higher altitude. At higher altitude this air mass gets condensed and heavy rainfall occurs. This
is known as Non Frontal Precipitation.
In tropical counties when on a particular hot day the ground surface gets heated
unequally, the warm air is lifted to high altitude and the cooler air takes its place with high
velocity, thus, the warm moist air mass is condensed at the high altitude causing heavy rain
fall. This is known as convective precipitation (see from the figure).
moist air when obstructed by some mountain rises up to high
altitude, it then gets condensed and precipitation occurs. This is known as orographic
The graphical representation of rain fall and run-off is known as hyetograph. The graph is
prepared with intensity of rainfall (in cm/hr) as ordinate and time (in hrs) as abscissa. The
infiltration capacity curve is drawn on this graph to show the amount of infiltration loss
(shown by dotted portion). The upper portion indicates the effective rainfall (shown by
The centroid of the effective rain fall is ascertained on the graph for determination of total
air mass gets condensed and heavy rainfall occurs. This
In tropical counties when on a particular hot day the ground surface gets heated
and the cooler air takes its place with high
velocity, thus, the warm moist air mass is condensed at the high altitude causing heavy rain
moist air when obstructed by some mountain rises up to high
altitude, it then gets condensed and precipitation occurs. This is known as orographic
raph. The graph is
prepared with intensity of rainfall (in cm/hr) as ordinate and time (in hrs) as abscissa. The
infiltration capacity curve is drawn on this graph to show the amount of infiltration loss
es the effective rainfall (shown by
The centroid of the effective rain fall is ascertained on the graph for determination of total
2.3 Measurement of Rain Fall or Precipitation:
� The instrument which is us
Raingauge.
� The principle of raingauge is that the amount of rainfall in a small area will
represent the amount of rainfall in a large area provided the metrological
characteristics of both small and large ar
Types of Rainguese :-
1) Non-Recoding Type Raingauge (Non
2) Recording Type Raingauge (Automatic)
(i) Weighing Bucket Raingauge
(ii) Tipping Bucket Raingauge
(iii) Float Type Raingauge
1) Non-Recoding Type Raingauge:
Simon’s raingauge is a non
It consists of metal casing of diameter 127mm which is set on concrete foundation A glass
bottle of capacity about 100 mm of rain fall is placed within the casing. A funnel with brass
rim is placed on the top of the bottle. The arrangement is shown:
The rainfall is recorded at every 24 hours. Generally, the measurement is taken at
8.30am every day. In case of heavy rainfall the measurement should be taken 2 to 3 times
daily so that the bottle does not overflow. To measure the amount of rainfall the glass bottle
is taken off and the collected water is measured in a measuring glass, and recorded in the
raingauge record book. When the glass bottle is taken off and it is immediately replaced wi
new bottle of same capacity.
10
2.3 Measurement of Rain Fall or Precipitation:-
The instrument which is used to measure the amount of rainfall is known as
The principle of raingauge is that the amount of rainfall in a small area will
represent the amount of rainfall in a large area provided the metrological
characteristics of both small and large area are similar.
-
Recoding Type Raingauge (Non-Automatic)
Recording Type Raingauge (Automatic)
(i) Weighing Bucket Raingauge
(ii) Tipping Bucket Raingauge
(iii) Float Type Raingauge
Recoding Type Raingauge:
e is a non-recording type raingauge which is most commonly used.
It consists of metal casing of diameter 127mm which is set on concrete foundation A glass
bottle of capacity about 100 mm of rain fall is placed within the casing. A funnel with brass
s placed on the top of the bottle. The arrangement is shown:-
The rainfall is recorded at every 24 hours. Generally, the measurement is taken at
8.30am every day. In case of heavy rainfall the measurement should be taken 2 to 3 times
tle does not overflow. To measure the amount of rainfall the glass bottle
is taken off and the collected water is measured in a measuring glass, and recorded in the
raingauge record book. When the glass bottle is taken off and it is immediately replaced wi
ed to measure the amount of rainfall is known as
The principle of raingauge is that the amount of rainfall in a small area will
represent the amount of rainfall in a large area provided the metrological
recording type raingauge which is most commonly used.
It consists of metal casing of diameter 127mm which is set on concrete foundation A glass
bottle of capacity about 100 mm of rain fall is placed within the casing. A funnel with brass
The rainfall is recorded at every 24 hours. Generally, the measurement is taken at
8.30am every day. In case of heavy rainfall the measurement should be taken 2 to 3 times
tle does not overflow. To measure the amount of rainfall the glass bottle
is taken off and the collected water is measured in a measuring glass, and recorded in the
raingauge record book. When the glass bottle is taken off and it is immediately replaced with
Figure: Simon’s Rain Gauge
2) Recoding Type Raingauge:
In this type of raingauge, the amount of rainfall is automatically recorded on a graph
proper by some mechanical device (see figure). Here, no person is required for
amount of rainfall from the container in which the rain water is collected. The recording type
raingauge may be three types.
Types of Recoding Type Raingauges:
(i) Weighing Bucket Raingauge:
bucket which is placed on pan. The pan is again fitted with some weighing mechanism. A
pencil arm is pivoted with the weighing mechanism in such a way that the movement of the
bucket can be traced by a pencil on the moving recording drum. So, when the wate
collected in the bucket the increasing weight of water is transmitted through the pencil which
traces a curve on the recording drum.the rain gauge produces a grph of cumulative rain
versus time and hence it is some time called Integrating raingau
mass curve of rain fall.
11
Figure: Simon’s Rain Gauge
In this type of raingauge, the amount of rainfall is automatically recorded on a graph
proper by some mechanical device (see figure). Here, no person is required for measuring the
amount of rainfall from the container in which the rain water is collected. The recording type
Types of Recoding Type Raingauges:-
(i) Weighing Bucket Raingauge: - This type of raingauge consists of a receiving
bucket which is placed on pan. The pan is again fitted with some weighing mechanism. A
pencil arm is pivoted with the weighing mechanism in such a way that the movement of the
bucket can be traced by a pencil on the moving recording drum. So, when the wate
collected in the bucket the increasing weight of water is transmitted through the pencil which
traces a curve on the recording drum.the rain gauge produces a grph of cumulative rain
versus time and hence it is some time called Integrating raingauge. The graph is known as the
In this type of raingauge, the amount of rainfall is automatically recorded on a graph
measuring the
amount of rainfall from the container in which the rain water is collected. The recording type
This type of raingauge consists of a receiving
bucket which is placed on pan. The pan is again fitted with some weighing mechanism. A
pencil arm is pivoted with the weighing mechanism in such a way that the movement of the
bucket can be traced by a pencil on the moving recording drum. So, when the water is
collected in the bucket the increasing weight of water is transmitted through the pencil which
traces a curve on the recording drum.the rain gauge produces a grph of cumulative rain-fall
ge. The graph is known as the
Figure :Weighing Bucket Rain Gauge
(ii) Tipping Bucket Raingauge :
in which the rain water is initially collected. The rain water then passes t
fitted to the circular collector and gets collected in two compartment tipping bucket pivoted
below the funnel. (figure).
When 0.25 mm rain water is collected in one bucket then it tips and discharges the
water in a reservoir kept below the
the funnel and the rain-water goes on collecting in it. When the requisite amount of rainwater
is collected, it also tips and discharges the water in the reservoir. In this way, a circular
motion is generated by the buckets. This circular motion is transmitted to a pen or pencil
which traces a wave like curve on the sheet mounted on a revolving drum. The total rainfall
may be ascertained from the graph. There is an opening with stopcock at bottom of
reservoir for discharging the collected rainwater. Sometimes a measuring glass is provided to
verify the results shown by the graph.
12
Figure :Weighing Bucket Rain Gauge
(ii) Tipping Bucket Raingauge :-It consists of a circular collector of diameter 30 cm
in which the rain water is initially collected. The rain water then passes through a funnel
fitted to the circular collector and gets collected in two compartment tipping bucket pivoted
When 0.25 mm rain water is collected in one bucket then it tips and discharges the
water in a reservoir kept below the buckets. At the same time the other bucket s comes below
water goes on collecting in it. When the requisite amount of rainwater
is collected, it also tips and discharges the water in the reservoir. In this way, a circular
generated by the buckets. This circular motion is transmitted to a pen or pencil
which traces a wave like curve on the sheet mounted on a revolving drum. The total rainfall
may be ascertained from the graph. There is an opening with stopcock at bottom of
reservoir for discharging the collected rainwater. Sometimes a measuring glass is provided to
verify the results shown by the graph.
It consists of a circular collector of diameter 30 cm
hrough a funnel
fitted to the circular collector and gets collected in two compartment tipping bucket pivoted
When 0.25 mm rain water is collected in one bucket then it tips and discharges the
buckets. At the same time the other bucket s comes below
water goes on collecting in it. When the requisite amount of rainwater
is collected, it also tips and discharges the water in the reservoir. In this way, a circular
generated by the buckets. This circular motion is transmitted to a pen or pencil
which traces a wave like curve on the sheet mounted on a revolving drum. The total rainfall
may be ascertained from the graph. There is an opening with stopcock at bottom of the
reservoir for discharging the collected rainwater. Sometimes a measuring glass is provided to
Figure :
(ii) Float Type Raingauge :
rectangular container and rotating recording drum is drum is provided at the another end. The
rain water enters the container through the funnel. A float is provided within the container
which rises up as the rain water gets collected there. The float
contains a pen arm for recoding the amount of rainfall on the graph paper dropped on the
recording drum. It consists of a siphon which starts functioning when the float rises to some
definite height and the container goes on emptyi
Selection of Site for Raingauge Station:
while selecting a site for rain gauge station.
a) The site should be on level ground and on open space. It should never be sloping
ground.
b) The site should be such that the distance between the gauge station and the objects
(like tree, building etc) should be atleast twice the height of the objects.
c) In hilly area, where absolutely level ground is not available, the site should be so
selected that the station may
d) The site should be easily accessible to the observer.
e) The site should be well protected from cattles by wire fencing.
13
Figure :- Tipping Bucket Raingauge
(ii) Float Type Raingauge :-In this type rain gauge a funnel is provided at one en
rectangular container and rotating recording drum is drum is provided at the another end. The
rain water enters the container through the funnel. A float is provided within the container
which rises up as the rain water gets collected there. The float consists of a rod which
contains a pen arm for recoding the amount of rainfall on the graph paper dropped on the
recording drum. It consists of a siphon which starts functioning when the float rises to some
definite height and the container goes on emptying gradually
Selection of Site for Raingauge Station:- The following points should be considered
while selecting a site for rain gauge station.
The site should be on level ground and on open space. It should never be sloping
uch that the distance between the gauge station and the objects
(like tree, building etc) should be atleast twice the height of the objects.
In hilly area, where absolutely level ground is not available, the site should be so
selected that the station may be well shielded from high wind.
The site should be easily accessible to the observer.
The site should be well protected from cattles by wire fencing.
In this type rain gauge a funnel is provided at one end of
rectangular container and rotating recording drum is drum is provided at the another end. The
rain water enters the container through the funnel. A float is provided within the container
consists of a rod which
contains a pen arm for recoding the amount of rainfall on the graph paper dropped on the
recording drum. It consists of a siphon which starts functioning when the float rises to some
The following points should be considered
The site should be on level ground and on open space. It should never be sloping
uch that the distance between the gauge station and the objects
In hilly area, where absolutely level ground is not available, the site should be so
14
Ch-2.4
Run-off:-
Runoff or Surface run-off in hydrology, the quantity of water discharged in surface
streams. Runoff includes not only the waters that travel over the land surface and through
channels to reach a stream but also interflow, the water that infiltrates the soil surface and
travels by means of gravity toward a stream channel (always above the main groundwater
level) and eventually empties into the channel. Runoff also includes ground water that is
discharged into a stream; stream flow that is composed entirely of groundwater is termed
base flow, or fair-weather runoff, and it occurs where a stream channel intersects the water
table.
The total Runoff is equal to the Total precipitation less the losses caused by
evapotranspiration (loss to the atmosphere from soil surfaces and plant leaves), storage (as in
temporary ponds) and other such abstractions.
Catchment Area:-A hydrological catchment is defined as the area of land point (usually the
sea). A hydrological catchment can vary widely in size and other characteristics such as
height above sea level, slope, geology and land use, and may contain different combination of
freshwater bodies (surface water and ground water) and coastal waters.
Estimation of Flood Discharge:-
The flood discharge may be estimated by the below mentioned methods.
(a) Dicken’s Formula
Q= C X A 3/4
Where Q= Discharge in cumec
A= Catchment area in sq. km
C= a constant depending upon the factors affecting flood discharge
** An average value of C considered as 11.5
(b) Ryve’s Formula
Q= C X A 2/3
Where Q= Discharge in cumec
A= Catchment area in sq. km
C= a constant
** An average value of C considered as 6.8
Ch-2.5
Hydrograph:-
The hydrograph is a graphical representation of the discharge of river (in cumec) against the
time (in hr or days). The discharge is plotted as ordinate (y-axis) and the time is plotted as
abscissa (x-axis).
During the dry season, there is only base flow (i.e. ground flow) but no surface runoff. This
may be shown by a line which is approximately straight (not shown in the figure).
In rainy season, at the beginning of the rainfall there is only base flow (shown by the line
AB). After some period, when the initial losses (like interception, evaporation and
infiltration) are fulfilled, the surface runoff starts and hence the discharge of river goes
increasing. Hence the limb of the curve rises which i
BC). This line reaches to the peak value at ‘C’. Again when the rain stops, the flow in the
river decreases and the limb of te curve declines. This limb is known as recession limb (as
shown by the line CD). The disch
(i.epeak discharge or flood discharge). The total area under the curve ABCDE indicates the
total runoff. But this run off includes the base flow and the direct runoff. So, to get the actual
runoff the base flow is to be deducted by separating it from total area.
Unit Hydrograph:-
A unit hydrograph may be defined as a hydrograph which is obtained from one cm of
effective rainfall (i.e. run-off) for unit duration. Here, effective rainfall means the rainf
excess (i.e. run-off) which directly flows to the river or stream. The unit duration is the period
during which the effective rainfall is assumed to be uniformly distributed. The unit duration
may be considered as 1 hr, 2 hr, 3 hr, 4 hr, …. Etc. as for
prepared for as effective rainfall of one cm lasting for 2 hrs, then it is known as 2 hr. unit
hydrograph, for the duration of 3 hrs it known as 3 hr unit hydrograph )as sowon in the figure
15
increasing. Hence the limb of the curve rises which is called rising limb (shown by the line
BC). This line reaches to the peak value at ‘C’. Again when the rain stops, the flow in the
river decreases and the limb of te curve declines. This limb is known as recession limb (as
shown by the line CD). The discharge at the point C indicates the maximum discharge
(i.epeak discharge or flood discharge). The total area under the curve ABCDE indicates the
total runoff. But this run off includes the base flow and the direct runoff. So, to get the actual
e flow is to be deducted by separating it from total area.
A unit hydrograph may be defined as a hydrograph which is obtained from one cm of
off) for unit duration. Here, effective rainfall means the rainf
off) which directly flows to the river or stream. The unit duration is the period
during which the effective rainfall is assumed to be uniformly distributed. The unit duration
may be considered as 1 hr, 2 hr, 3 hr, 4 hr, …. Etc. as for example, if a hydrograph is
prepared for as effective rainfall of one cm lasting for 2 hrs, then it is known as 2 hr. unit
hydrograph, for the duration of 3 hrs it known as 3 hr unit hydrograph )as sowon in the figure
s called rising limb (shown by the line
BC). This line reaches to the peak value at ‘C’. Again when the rain stops, the flow in the
river decreases and the limb of te curve declines. This limb is known as recession limb (as
arge at the point C indicates the maximum discharge
(i.epeak discharge or flood discharge). The total area under the curve ABCDE indicates the
total runoff. But this run off includes the base flow and the direct runoff. So, to get the actual
A unit hydrograph may be defined as a hydrograph which is obtained from one cm of
off) for unit duration. Here, effective rainfall means the rainfall
off) which directly flows to the river or stream. The unit duration is the period
during which the effective rainfall is assumed to be uniformly distributed. The unit duration
example, if a hydrograph is
prepared for as effective rainfall of one cm lasting for 2 hrs, then it is known as 2 hr. unit
hydrograph, for the duration of 3 hrs it known as 3 hr unit hydrograph )as sowon in the figure
16
Concept of Unit Hydrograph: - The unit hydrograph theory is based on the conception that
if two identical storms occur on a drainage basin with identical condition, then unit
hydrograph of runoff from the two storms may be expected as same. This conception of unit
hydrograph was first given by L.K. Sherman in 1932.
CHAPTER 3
17
CHAPTER-3
WATER REQUIREMENTS OF CROPS
3.1 CROP SEASONS:-
The period during which some particular types of crops can be grown every year on the same
land is known as crop seasons. The following are the main crop seasons.
• Kharif season: - this seasons ranges from June to October. The crops are sown in the
very beginning of monsoon and harvested at the end of autumn. Ex- rice, millet, jute,
groundnut, etc.
• Rabi seasons: - this season ranges from October to March. The crops are sown in the
very beginning of winter & harvested at the end of spring. Ex- wheat, gram, mustard,
onion, etc.
3.2 DUTY:-
• The duty of water is defined as number of hectares that can be irrigated by constant
supply of water at the rate of one cumec throughout the base period.
• It is expressed in hectares/cumec.
• It is denoted by ”D”.
• The duties of some common crops are
Crop duty in hectares/cumec
Rice 900
Wheat 1800
Cotton 1400
Sugarcane 800
DELTA:-
• Each crop requires certain amount of water per hectare for its maturity. It is the total
amount of water supplied to the crop(from 1st watering to last watering) is stored on
the land without loss, then there will be a thick layer of water standing on the land.
This depth of water layer is known as delta.
• It is denoted by ∆.
• It is expressed in cm.
Kharif crop Delta in cm
18
Rice 125
Maize 45
Ground nut 30
Millet 30
Rabi crop delta in cm
Wheat 40
Mustard 45
Gram 30
Potato 75
BASE:-
• Base period is the whole period from irrigation water first watering for preparation of
the ground for planting the crop to its last watering before harvesting.
• It is denoted by “B”.
• It is expressed in days.
Crop Base in days
Rice 120
Wheat 120
Maize 100
Cotton 200
Sugarcane 320
Relation between base duty and delta:-
Let ,
D =duty of water in hectares/cumec
B =base in days,
∆ =delta in m
From definition, one cumec of water flowing continuously for “B” days gives a depth of
water ∆ over an area D hectares. That is
1 cumec for B days gives ∆ over D/B hectares
1 cumec for 1 days gives ∆ over D/B hectares
1 cumec-day =D/B*∆ hectare-meter
Again, 1 cumec-days = 1*24*60*60=86400m
Problem 1:- a channel is to be designed for irrigating 5000 hectares in kharif crop &
4000 hectares in rabi crop. The wa
cm, respectively. The kor period for kharif is 3 weeks & for rabi is 4weeks.
Determine the discharge of the channel for which it is to be designed.
Solution:-
∆=8.64B/D
Discharge for kharif crop:
∆=60cm=0.60m
B=3weeks=21days
Duty=(8.64*21)/0.60=302.4 hectares/cumec
Area to be irrigated =5000 hectares
Required discharge of channel=5000/302.4=16.53cumec
Discharge for rabi crop:-
∆=25cm=0.25m
B=4weeks=28 days
Duty=(8.64*28)/0.25=967.68 hectares/cumec
Area to be irrigated =4000 hectares
Required discharge of channel=4000/967.68=4.13cumec
19
days = 1*24*60*60=86400m3
a channel is to be designed for irrigating 5000 hectares in kharif crop &
4000 hectares in rabi crop. The water requirement for kharif & rabi are 60 cm & 25
cm, respectively. The kor period for kharif is 3 weeks & for rabi is 4weeks.
Determine the discharge of the channel for which it is to be designed.
Discharge for kharif crop:-
Duty=(8.64*21)/0.60=302.4 hectares/cumec
Area to be irrigated =5000 hectares
Required discharge of channel=5000/302.4=16.53cumec
Duty=(8.64*28)/0.25=967.68 hectares/cumec
be irrigated =4000 hectares
Required discharge of channel=4000/967.68=4.13cumec
a channel is to be designed for irrigating 5000 hectares in kharif crop &
ter requirement for kharif & rabi are 60 cm & 25
cm, respectively. The kor period for kharif is 3 weeks & for rabi is 4weeks.
20
Problem 2:- the command area of a channel 4000 hectares. The intensity of irrigation
of a crop is 70%. The crop requires 60 cm of water in 15 days, when the effective
rainfall is recorded as a 15cm during that period. Find,
a) the duty at the head of field.
b) the duty at the head of field.
c) The head discharge at the head of channel.
Assume total losses as 15%.
Solution:-
Depth of water required =60 cm
Effective rain fall =15cm
Depth of irrigation water = 60-15=45cm
Delta =45cm=0.45m, B = 15days
From relation, ∆ =(8.64*B)/D
Duty D = (8.64*15)/0.45 =288 hectares/cumec
a) So, duty at the head of field =288 ha/cumec. Due to the losses of water the
duty at the head of the channel will be reduced. here losses are 15%.
b) So, the duty at the head of channel = 288*(85/100) =244.80 hect/cumec.
c) Total area under crop =4000 * (70/100) =2800 hect
The discharge at the head of channel = 2800/244.8=11.438 cumec.
3.3 GROSS COMMAND AREA:-
The whole area enclosed between an imaginary boundary line which can be included
in an irrigation project for supplying water to agricultural land by the networks of
canal is known as gross command area. It includes both the culturable & unculturable
area.
unculturable area:-
the area where the agriculture cannot be done & crop cannot be grown is known as
unculturable area.
culturable area:-
the area where the agriculture can be done satisfactory is known as culturable area
CULTURABLE COMMAND AREA:-
21
The total area within an irrigation project where the cultivation can be done & crops
can be grown is known as culturable command area. again c.c.a may be of two
categories.
a) Culturable cultivated area:- it is the area within c.c.a where the cultivation
has been actually done at present.
b) Culturable uncultivated area:- it is the area within c.c.a where the
cultivation is possible but is not being cultivated at present due to some
reasons.
INTENSITY OF IRRIGATION:-
• The total culturable command area may not be cultivated at the same time in a
year due to various reasons. Some area may remains vacant every year. Again
various crops may be cultivated in the culuturable command area. So, The
intensity of irrigation may be defined as a ratio of cultivated land for a
particular crop to the total culturable command area.
• It is expressed as a percentage of c.c.a.
FIELD CAPACITY:-
The field capacity is defined as the amount of maximum moisture that can be held by
the soil against gravity.
PERMANENT WILTING POINT:-
It is defined as the amount of moisture held by soil which cannot be extracted by the
roots for transpiration. At this point the wilting of the plant occurs. It is also expressed
in percentage.
FREQUENCY OF IRRIGATION
The irrigation water is applied to the field to raise the moisture content of the soil up
to its field capacity. The application of water is then stopped. The water content also
reduces gradually due to transpiration and evaporation. If the moisture content is
dropped below the requisite amount, the growth of the plants gets disturbed. So the
moisture content requires to the immediately replenished by irrigation and it should
22
be raised to the field capacity. The frequency of irrigation should be worked out in
advance so that it can be applied in proper intervals.
a. The frequency of irrigation may be ascertained by the following expressions,
Dw=�� × �
�� × �F − M�
where, Dw = Depth of water to be applied in each watering;
d = Depth of root zone
Ws= Unit wt. of soil;
Ww = Unit wt. of water;
Fc = Field capacity;
M0 = Optimum moisture content.
b. fw = ��
��
Where. fw = Frequency of watering;
Dw = Depth of water to be applied in each watering;
Cu = Daily consumptive use of water.
23
CHAPTER 4
FLOW IRRIGATION
DEFINATION:-
The irrigation system in which the water flows under gravity from the source to
agricultural land is known as flow irrigation
PERENNIAL IRRIGATION:-
• In this irrigation water is available throught the year. Hydraulic structures are
necessary across the river for raising the water level.
• Large area can be included under this system
• Negligible silting takes place in the canal bed
TYPES OF CANAL:-
1. BASED ON THE PURPOSE:-
Based on the purpose of service, the canals are 4 types
a) Irrigation canal:-the canal which is constructed to carry water from the source to the
agricultural land for the purpose of irrigation is known as irrigation canal.
b) Navigation canal:-the canal which is constructed for the purpose of inland navigation
is known as navigation canal.
c) Power canal:-the canal which is constructed to supply water with very high force to
the hydroelectric power station for the purpose of moving turbine to generate electric
power is known as power canal.
d) Feeder canal:- the canal which is constructed to feed another canal or river for the
purpose of irrigation or navigation is known as feeder canal
2. BASED ON THE NATURE OF SUPPLY:-
Based on the nature of supply the canal are 2 types
a) Inundation canal:- the canal which is excavated from the banks of the inundation
river to carry the water to agricultural land in rainy season only is known as
inundation canal.
b) Perennial canal:-the canal which can supply water to the agricultural land
throughout the year is known as perennial canal.
3. BASED ON DISCHARGE:-
According to discharge capacity the canals are
24
a) Main canal:-the large canal which is taken directly from the diversion head work or
from the storage to supply water to the network of the small canal is known as main
canal.
b) Branch canal:-the branch canals are taken from either side of the main canal at
suitable points so that the whole command area can be covered by the network
c) Distributory channel:- these channels are taken from the branch canals to supply
water to different sectors.
d) Field channel:- these channels are taken from the outlets of the distributory channel
by the cultivators to supply water to their own lands.
4. BASED ON ALLIGNMENT:-
Depending upon the alignment the canal are following types
a) Ridge or water shed canal:- the canal which is aligned along the ridge line is known
as ridge canal.
b) Contour canal:- the canal which is aligned approximately parallel to the contour
lines is known as contour canal.
c) Side slope canal:-the canal which is aligned approximately at right angle to the
contour lines is known as side slope canal.
CANAL SECTION
TERMS RELATED TO CANAL SECTION:
1. Canal bank
2. Berm
3. Hydraulic gradient
4. Counter berm
5. Free board
6. Side slope
7. Service road or inspection road
8. Dowel or Dowla
9. Borrow pit
10. Spoil bank
11. Land width
25
canal section
CANAL BANK:
The canal bank is necessary to retain water in the canal to the full supply
level. According to different site conditions the bank of the canals are two types..
(a) Canal bank in cutting :
The banks are constructed on both side of the canal to provide only a
inspection load. The side slope will be 1.5:1 or 2:1 according to the nature of soil.
(b) Canal bank in full banking:
Both canal banks are constructed above the ground level. The height of
the bank will be high and the section will be large due to hydraulic gradient.
BERM:
The distance between toe of the bank and the top edge of the cutting is called
berm.
The berm is provided for following reasons:
(a) To protect the bank from erosion.
(b) To provide a space for widening the canal section in future if necessary.
(c) To protect the bank from sliding down towards the canal section.
(d) The silt deposition on the berm makes an impervious lining.
(e) If necessary borrow pit can be excavated on the berm.
The width of the berm varies from D to 2D.where D is the full supply level
HYDRAULIC GRADIENT:
When water is retained by the canal bank, the seepage occurs through the body of the
bank. Due to the resistance of soil, the saturation line forms a sloping line which may pass
through countryside of the bank. The sloping line is known as hydraulic gradient.
26
SOIL H.G Clayey soil 1:4
Sandy soil 1:6
Alluvial soil 1:5
COUNTER BERM:
When the water is retain by a canal bank the hydraulic gradient line passes through the
body of the bank. The gradient should not intersect the outer side of the bank. It should pass
through the base and a minimum cover of 0.5m should always be maintained. It may occur
that the hydraulic gradient line intersect the outer side of the bank in that case a projection is
provided on the bank to obtain minimum cover. This projection is known as counter berm.
FREE BOARD:
It is the distance between the full supply level and top of the bank. The amount of free
board varies from 0.6 m to 0.75 m.
It is provided for the following reasons
(a) To keep a sufficient margin so that the canal water does not overtop the bank.
(b) To keep the saturation gradient much below the top of the bank
SIDE SLOPE:
The side slope of the canal bank and canal section depends upon the angle of repose
of the soil existing on side. So to determine the side slope of different sections the soil
sample should be collected from the site and should be tested in the soil testing laboratory.
Permissible side slope for some soil
Types of soil Side slope in cutting Side slope in banking
Clayey soil 1:1 1 ½:1
Alluvial soil 1:1 2:1
Sandy loam 1 ½:1 2:1
Sandy soil 2:1 3:1
SERVICE ROAD:
The road is provided on the top of the canal bank for inspection and maintenance
work is known as service road or inspection road. For main canal the service road are
provided on both side of the bank but for branch canal the road is provided on the bank only.
The width of the service road for main canal varies from 3-4 m. But finally these roads serve
the purpose of communication between different villages.
DOWEL:
27
The protective small embankment which is provided on the canal side of the service
road for safety of the vehicles playing on it is known as dowel or dowla. The top width is
generally 0.5m and the height above the road level is about 0.5m.
SPOIL BANK:
When the canal is constructed in pool cutting the excavated earth may not be sufficient
for forming the bank. In such case the extra earth is deposited in the form of small bank
which is known as spoil bank. The spoil banks are provided on one side or both side of the
canal bank depending upon the quantity of extra earth and available space. The spoil bank
are not continuous sufficient space are left between the adjacent spoil banks for proper
drainage.
BORROWPIT:
When the canal is constructed in practically cutting and partial banking, the
excavated earth may not be sufficient for forming the required bank. In such case, the extra
earth required for the construction of banks is taken from some pits which are known as
borrow pits. The borrow pit may be inside or outside of the canal. The maximum depth
should be 1m. The excavation is done in a no of borrow pit living a gap between them. The
gap is generally half of the length of each borrow pit.
LAND WIDTH:
The total land width required for construction of canal depends upon the nature of site
condition. Such as fully in cutting of fully in banking or partially in cutting and partially in
banking. To determine the total width the following dimension should be added.
(a) Top width of the canal.
(b) Twice the berm width.
(c) Twice the bottom width of banks.
(d) A margin of one meter from the heel of the bank on both sides.
(e) Width of the external borrow pit if any
(f) A margin of 0.5m from the outer edge of borrow pit on both sides, if external
borrow pit becomes necessary.
BALANCING DEPTH:
If the quantity of excavated earth can be fully utilized when making the bank on both
side then that canal section is known as economical section. The depth of cutting for the idle
condition is known as balancing depth.
SKETCHES OF DIFFERENT CANAL CROSS-SECTION:-
Canal in full cutting:-
28
canal in partially cutting & partially banking:-
canal in fully bankin:-
CANAL LINING
OBJECTS OF CANAL LINING:
(a) To control seepage.
(b) To prevent water logging.
(c) To increase the capacity of canal.
(d) To increase the command area.
(e) To protect the canal from damage by flood.
(f) To control the growth of weeds.
ADVANTAGES OF CANAL LINING:
(a) It reduces the loss of water due to seepage and hence the duty is enhanced.
(b) It controls the water logging and hence the bad effects of water logging are eliminated.
(c) It provides smooth surface and hence the velocity of flow can be increased.
29
(d) Due to increased velocity the discharge capacity of a canal is also increased.
(e) Due to increased velocity, the evaporation loss also be reduced.
(f) It eliminates the effect of scouring in the canal bed.
(g) The increased velocity eliminates the possibility of silting in the canal bed.
(h) It controls the growth of weeds along the canal sides and bed.
(i) It provides the stable section of the canal.
(j) It reduces the requirement of land width for the canal, because smaller section of the
canal can produce greater discharge.
(k) It prevents the sub soil salt to come in contact with the canal water.
(l) It reduces the maintenance cost of canals.
DISADVANTAGES:
(a) The initial cost of canal lining is very high
(b) It take too much time to complete the project work
(c) It involves much difficulties for repairing of damaged section of line
(d) It becomes difficult if the outlet are required to be shifted or new outlet are requred to
be provided
TYPES OF LINING:
The following are the types of lining according to their site condition
(1) Cement concrete lining
(2) Pre-cast concrete lining
(3) Cement mortar lining
(4) Lime concrete lining
(5) Brick lining
(6) Boulder lining
(7) Shot crete lining
(8) Asphalt lining
(9) Bentonite and clay lining
(10) Soil-cement lining
1. CEMENT CONCRETE LINING :
30
This type of lining is recommended for canal in full banking. It is widely
accepted as best impervious lining. The velocity of flow may be kept above 2.3 m/sec. It can
eliminate completely growth of weeds.
Following are the steps for cement concrete lining…..
(A) Preparation of sub-grade :
The subgrade is prepared by ramming the surface properly with a layer of
sand(about 15cm) . then a slurry of cement and sand (1:3) is spread uniformly over
the prepared bed.
(B) Laying of concrete :
The cement concrete of grade M15 is spread uniformly according to desire
thickness (100-150mm). after laying the concrete is tapped until the slurry comes on
the top . then the curing is done for two weeks..
2. PRE-CAST CONCRETE LINING :
The lining is recommended for the canal in full banking. It consist of pre
cast concrete slabs of size (60cm*60cm*5cm) which are set along the canal bank and
bed with cement mortar (1:6). A network of 6mm dia. rod is provided in the slab with
spacing 10cm centre of centre. Expansion joints are also provided. The slabs are set in
the following sequence,
(a) The sub grade is prepared by properly ramming the soil with a layer of sand.
(b) The slabs are stacked as per estimate along the course of the canal.
(c) The curing is done for a week.
3. CEMENT MORTAR LINING
This type of lining is recommended for the canal fully in cutting where
hard soil or clayey soil is available. The thickness of cement mortar(1:4) is generally
2.5cm. This lining is impervious, but is not durable. The curing should be done
properly.
4. LIME CONCRETE LINING
When hydraulic lime, surkhi and brick ballast are available in plenty along the
course of the canal or in the vicinity of the irrigation project, then the lining of the
canal may be made by the lime concrete of proportion 1:1:6. The thickness of
concrete varies from 150mm to 225mm and the curing should be done for longer
period. This lining is less durable then the cement concrete lining.
31
5. BRICK LINING
This lining is prepared by double layer brick flat soling laid with cement
mortar (1:6) over the compacted sub grade. The first class bricks should be
recommended for the work. The curing should be done properly. The lining is
preferred for following reasons
(a) The lining is economical
(b) Work can be done very quickly
(c) Repair work can be done easily
(d) Brick can be manufactured from the excavated earth near the site
DISADVANTAGES
(a) It is completely impervious
(b) It has low resistance against erosion
(c) It is not so much durable
6. BOULDER LINING
In hilly areas where the boulders are available in plenty, this type of
lining is generally recommended. The boulders are laid in single or double layer
maintaining the slope of the banks and the level of the canal. The lining is very
durable and impervious. But the transporting cost of material is very high. So ,it
cannot be recommended for all cases.
7. SHOT CRETE LINING
In this system, the cement mortar is directly applied on the sub grade
by equipment known as cement gun. The mortar is termed as shot crete and the lining
is known as shot crete lining. The process is also known as guniting, as a gun is used
for laying the mortar. The line is done in two ways..
(A) By dry mix :
A mixture of cement and moist sand is prepared and loaded in the
cement gun. Then it is forced through the nozzle of the gun with the help of
compressed air. The mortar spreads over the sub grade to a thickness which
varies from 2.5 cm to 5 cm.
(B) By wet mix :
32
The mixture of cement ,sand and water is prepared according to the
approved consistency. The mixture is loaded in the gun and forced on the
sub-grade… This type of lining is very costly and is not durable.
8. ASPHALT LINING
This lining is prepared by spraying asphalt at a very high
temperature (about150’) on the subgrade to a thick varies from 3mm to 6mm. the hot
asphalt when becomes cold forms a water proof membrane over the sub grade. This
membrane is covered with a layer of earth and gravel. The lining is very cheap
9. BENTONITE AND CLAY LINING
A mixture of benotite and clay are mixed to gather to form a sticky
mass. The mass is spread over the sub-grade to form an impervious membrane which
is effective in controlling the seepage of water, but it cannot control the growth of
weeds. This lining is recommended for small channels.
10. SOIL-CEMENT LINING
This lining is prepared with a mixture of soil and cement. The usual
quantity of cement is10 percent of the weight of dry soil. The soil and cement are
thoroughly mixed to get an uniform texture. The mixture is laid on the surface of the
sub-grade and it is made thoroughly compact. The lining is efficient to control the
seepage of water, but it cannot control the growth of weeds. So this is recommended
for small channels only.
SELECTION OF TYPES OF LINING :
(A) Imperviousness
(B) Smoothness
(C) Durability
(D) Economy
(E) Sitecondition
(F) Life of project
33
CHAPTER-5
WATER LOGGING
Definition:-
In the agricultural land, when the soil pores within the root zone of the crops
get saturated with the sub soil water , the air circulation inside the soil pores gets totally
stopped . This phenomenon is called as water logging.
The water logging makes the soil alkaline in character and the fertility of the
land is totally destroyed and the yield crops gets reduced.
Due to heavy rain fall for a longer period or due to continuous percolation of
the water from the canals, the water table gets raised near the surface of the soil. Then by
capillary action then the water rises to the root zone of the crops and goes on saturating
soil.
Causes of the Water Logging:-
The Following are the main causes of the water Logging.:-
� Over Irrigation:-In inundation irrigation since there is no controlling system of water
supply it may cause over irrigation. The excess water percolates and remains stored
within the root zone of the crops. Again in perennial irrigation system if water is
supplied more than its required. This excess water is responsible for water logging.
� Seepage from Canals:-In unlined canal system ,the water percolates through the
bank of the canals and get collected in low lying area along course of the canal and
thus water table gets raised. This seepage more in case of canal in banking.
� Inadequate Surface Drainage:- When the rainfall is heavy and there is no proper
provision of surface drainage then the water gets collected and submerges in the
vast area. When this condition continues for a longer period the water table is
raised.
� Obstruction in natural water courses:-If the bridges and the culverts are constructed
across a water courses with the opening with insufficient discharge capacity the
upstream area gets flooded and this causes water logging.
34
� Obstruction in sub soil drainage:- If some impermeable stratum exists in a lower
depth below the ground surface then the movement of the subsoil water gets
obstructed and causes the water logging in the area.
� Nature of the Soil:- The soil of low permeability like Black cotton soil does not allow
the water to percolate through it So, in case of over irrigation or flood the water
retains in this type of land and causes water logging.
� Seepage from reservoir:- If the reservoir basin consists of permeable zones cracks
and fissures which are not detected during the construction of dam, these may
cause seepage of the water. This subsoil water will move towards the low lying areas
causes the water logging.
� Incorrect method of cultivation:- if the agricultural land is not well leveled and there
is no arrangement of surplus for the water to flow out then it will create the pools of
the stagnant water leading to water logging.
� Poor irrigation Management:- If the main canal is kept or long period unnecessarily
without computing the total water requirement of the crops then this leads to the
over irrigation which may causes water logging.
� Excessive rainfall :- If the rainfall is excessive and water gets no time to get drained
off completely then a pool of stagnant water leading to water logging.
� Topography of the land:- If the agricultural land is flat i.e with no country slope and
consists of depression or undulation then this leads to water logging.
� Occasional Flood:- If an area gets affected by flood every year and there is no
proper drainage system the water table gets raised and this causes water logging.
Effects of Water logging:-
The following effects of the water logging.
� Stalinization of the Soil:- Due to the water logging the dissolved salts like
sodium carbonate, sodium chloride and sodium sulphate come to the surface of the
soil. When the water evaporates from the surface,the salts are deposited there. This
process is known as Stalinization of the soil. Excessive concentration of the salt
makes the land alkaline, it does not allow the plant to strive and thus the yield of the
crop is reduced.
� Lack of Aeration:- The crops required some nutrients for the growth which are
supplied some bacteria and some micro organism by breaking the complex
nitrogenous compound into simple compounds which are consumed by the plants
for the growths. But the bacteria required the oxygen for their life and activity.
When the aeration of the soil is stopped by the water logging these bacteria cannot
35
survive without oxygen and the fertility of the land is lost which results in reduction
of yield.
� Fall of Soil Temperature:-Due to the water logging the soil temperature is
lowered. At low temperature of the soil the activity of the bacteria becomes very
slow and consequently the plant do not get requisite amount of food in time. Thus
the growth of the plant is hampered and the yield is reduced.
� Growth of weeds and aquatic plants:-Due to the water logging the
agricultural land is converted to marshy land and the weeds and the aquatic plants
are grown in plenty. This plants consume the soil food in advance and thus the crops
gets destroyed.
� Disease of the crops:-Due to the low temperature and poor aeration the crops
gets some disease which may destroy the crops or reduce the yield.
� Difficulty in cultivation:-In water logged area it is very difficult to carry out the
operation of cultivation such as tilling, ploughing etc.
� Restriction of the root Growth:-When the water table rises near to root zone
the soil gets saturated .The growth of the root is confirmed only to the top layer of
the soil. So, the crops cannot be matured properly and the yield is reduced.
Control of Water Logging:-
The following measures may be taken to control the water logging.
Prevention of Percolation from Canals:- The irrigation canals should be lined
with impervious lining to prevent the percolation through the bed and banks of the
canals. Thus the water logging may be controlled. Intercepting the drains may be
provided along the course of the irrigation canals in place where percolation of
water is detected.
Prevention of Percolation from Reservoirs:-During the construction of dam
the geological survey should be conducted on the reservoir basin to detect the zone
permeable formation through which may percolate. These zones should be treated
properly to prevent the seepage .If afterwards it is found that there is still leakage of
water through some zone then sheet piling should be done to prevent the leakage.
Economical use of water:- If water is used economically then it may control the
water logging and the yields crops may be high. So, the special training should be
given to the cultivators to release the benefits of economical use of water.
Control of Intensity of Irrigation:- The intensity of irrigation may cause the
water logging so it may be controlled in a planned way so that there is no possibility
of water logging in a particular area.
36
Fixing of Crop pattern:- Soil survey should be conducted to fix the crop pattern.
The crops having high rate of evapotranspiration should be recommended for the
area susceptible to water logging.
Providing Drainage System:- Suitable drainage system should be provided in
the low lying area so that the rain water does not stand for long period
Improvement of natural Drainage:- Sometimes the natural drainage may be
completely silted up or obstructed by weeds aquatic plants etc. The effected section
of the drainage should be improved by excavating and clearing the obstruction.
Pumping of Ground Water:- A no. of open wells or tube wells are constructed
in water logged area and the ground water is pumped out until the water table goes
down to a safe level.
Construction of Sump Wells:- Sump wells may be constructed with in the water
logged area and they help to collect the surface water. The water from the slump
wells may be pumped to the irrigable lands or may be discharged to any river.
DIVERSION HEAD WORKS AND REGULATORY STRUCTURES
Introduction
Any hydraulic structure which supplies water to the off
headwork. Head work may be divided into two classes such as:
(a) Diversion Head Work and (b) Storage Head Work
(a) Diversion Head
required supply into the canal from the river.
(b) Storage Head Work :
the river. It stores water during the period of excess supplies in the river &
releases it when demand overtakes available supplies.
Necessity of Diversion Head Work :
(1) The necessity of diversion head works in the irrigation projects is to divert the river
water into the canal and a constant and continuous water supply is ensured into
canal even during the periods of low flow.
(2) It controls the silt entry into the canal.
(3) It raises the water level in the river so that the commanded area can be increased.
(4) It reduces fluctuations in the level of supply in the river.
(5) It regulates the intake of water into the canal.
(6) It stores water for tiding over small periods of short supplies.
General layout and different part of a Diversion Head Work
37
CHAPTER- 6
N HEAD WORKS AND REGULATORY STRUCTURES
Any hydraulic structure which supplies water to the off-taking canal is called a
headwork. Head work may be divided into two classes such as:
Diversion Head Work and (b) Storage Head Work
Diversion Head Work : A diversion head work is that which divert the
required supply into the canal from the river.
Storage Head Work :A storage head work is the construction of a dam across
the river. It stores water during the period of excess supplies in the river &
eleases it when demand overtakes available supplies.
Necessity of Diversion Head Work :
The necessity of diversion head works in the irrigation projects is to divert the river
water into the canal and a constant and continuous water supply is ensured into
canal even during the periods of low flow.
It controls the silt entry into the canal.
It raises the water level in the river so that the commanded area can be increased.
It reduces fluctuations in the level of supply in the river.
ake of water into the canal.
It stores water for tiding over small periods of short supplies.
General layout and different part of a Diversion Head Work
N HEAD WORKS AND REGULATORY STRUCTURES
taking canal is called a
A diversion head work is that which divert the
A storage head work is the construction of a dam across
the river. It stores water during the period of excess supplies in the river &
The necessity of diversion head works in the irrigation projects is to divert the river
water into the canal and a constant and continuous water supply is ensured into the
It raises the water level in the river so that the commanded area can be increased.
38
( Fig.1Layout of a diversion head work)
Divide Wall :A divide wall is constructed parallel to the direction of flow of river to separate
the weir section and the under sluices section to avoid across flows. If there are under sluices
at both the sided, there are 2 divide walls.
Scouring sluices : Provide adjacent to the canal head regulator should be able to pass fair
weather flow for which the crest shutters on the weir proper need not be dropped.
Fish Ladder : A passage provided adjacent to the divide wall on the weir side for the fish to
travel from up stream to down stream and vice versa. Fish migrate upstream or down stream
in search of food or to rich their spreading places.
Guide Banks : Guide Banks are provided on either side of the diversion head work for a
smooth approach and to prevent the river from outflanking.
Marginal bunds : Marginal bunds are provided on either side of the river up stream of
diversion head works to protect the land and property which is likely to be submerged during
ponding of water in floods.
Head regulators : A canal head regulator is provided at the head of the canal off taking from
the diversion headwork. It regulates the supply of water into the canal, controls the entry silt
into the canal and prevents the entry of river flood into canal.
A diversion head work is further divided in to two parts:
(a) Weir :
� The weir is a solid obstruction put across the river to raise its water level and
divert the water in to the canal.
� Here the water level is raised up to the required height and the surplus water is
allowed to flow over the weir.
� Generally it is constructed across an inundation river. Weirs are commonly used
to alter the flow of rivers to prevent flooding, measure discharge and help render
rivers navigable.
� If a weir also stores water for tiding over small periods of short supplies, it is
called a storage weir.
� The main difference between a storage weir and a dam is only in height and the
duration for which the storage is stored. A dam stores the supply for a
comparatively longer duration.
(b)Barrage :
� The function of barrage is s
effected by the gates alone.
� It consists of a number of large gates that can be opened or closed to control the
amount of water passing through the structure and thus regulate and stabilise river
water.
� No solid obstruction is put across the river. The crest level in the barrage is kept at a
low level. During the floods the gates are raised to clear off the high flood level,
enabling the high flood to pass downstream with minimum afflux. When the flood
recedes, the gates are lowered and the flow is obstructed, thus raising the water level
to the upstream of the barrage.
� Due to this, there is less silting and better control over the levels.
39
main difference between a storage weir and a dam is only in height and the
duration for which the storage is stored. A dam stores the supply for a
comparatively longer duration.
(fig.2 Vertical drop wier)
The function of barrage is similar to that of a weir but the heading up of water is
effected by the gates alone.
It consists of a number of large gates that can be opened or closed to control the
amount of water passing through the structure and thus regulate and stabilise river
No solid obstruction is put across the river. The crest level in the barrage is kept at a
low level. During the floods the gates are raised to clear off the high flood level,
enabling the high flood to pass downstream with minimum afflux. When the flood
recedes, the gates are lowered and the flow is obstructed, thus raising the water level
to the upstream of the barrage.
Due to this, there is less silting and better control over the levels.
main difference between a storage weir and a dam is only in height and the
duration for which the storage is stored. A dam stores the supply for a
imilar to that of a weir but the heading up of water is
It consists of a number of large gates that can be opened or closed to control the
amount of water passing through the structure and thus regulate and stabilise river
No solid obstruction is put across the river. The crest level in the barrage is kept at a
low level. During the floods the gates are raised to clear off the high flood level,
enabling the high flood to pass downstream with minimum afflux. When the flood
recedes, the gates are lowered and the flow is obstructed, thus raising the water level
40
(fig.3 barrage)
Differences between Weir and Barrage :
Barrage Weir
� Low set crest
� Gated over entire length
� Gates are of greater height
� Gates are raised clear off the high
floods
� Perfect control on river flow
� Longer construction period
� Costly structure
� Silt removal is done through
under sluices
� High set crest
� Shutters in part length
� Shutters are of smaller height
� Shutters are dropped to pass
floods
� No control of river in low floods
� Shorter construction period
� Relatively cheaper structure
� No means for silt disposal
Functions of Regulatory structures :
A regulatory structure is provided at the head of the off- taking canal and serves the
following functions.
(1) It regulates the supply of water entering the canal.
(2) It controls the entry of silt in the canal.
(3) It prevents the river floods from entering the canal.
Head Regulators and Cross regulators :
Head regulators and cross regulators regulate the supplies of the off-taking channel
and parent channel respectively. The distributary head regulator is provided at the head of the
distributary and controls the supply entering the distributary. A cross regulator is provided
41
on the main canal at the down stream of the off-take to head up the water level and to enable
the off-taking channel to draw the required supply.
Functions of distributary head regulators :
(1) These regulate orcontrol the supplies to the off-taking canal.
(2) To control silt entry into the off-take canal.
(3) To serve as a meter for measuring discharge.
Functions of cross regulators :
(1) To effectively control the entire canal irrigation system.
(2) When the water level in the main channel is low, it helps is heading up water on the
up stream and to feed the off-take channels to their full demand in rotation.
Falls :
Irrigation canals are constructed with some permissible bed slopes so that there is no
silting or scouring in the canal bed. But it is not always possible to run the canal at the
desired bed slope throughout the alignment due to the fluctuating nature of the country slope.
Generally the slope of the natural ground surface is not uniform through the
alignment. Sometimes the ground surface may be steep and sometimes it may be very
irregular with abrupt change of grade.
In this case “ a vertical drop is constructed across a canal to lower down its water
level and destroy the surplus energy liberated from the falling water which may otherwise
scour the bed and banks of the canal. This is done to avoid unnecessary huge earth work in
filling. Such vertical drops are known as Canal falls or Falls simply.”
Types of Falls :
The followings are the different types of canal falls.
(I) Ogee fall : In this type of falls, an ogee curve ( a combination of convex and
concave curve ) is provided for carrying the canal water from higher level to
lower level. This fall is recommended when the natural ground surface suddenly
changes to a steeper slope along the alignment of the canal. The fall consists of a
concrete vertical wall and concrete bed.
42
(fig.4 Ogee fall)
(II) Rapid fall : The Rapid fall is suitable when the slope of the natural ground
surface is even and long. It consists of a long slopping glacis with longitudinal
slope which varies 1 in vertical to 10 – 20 in horizontal. Curtain walls are
provided on the upstream and downstream side of the slopping glacis. The sloping
bed is provided with rubble masonry. The masonry surface is finishes with rich
cement mortar (1:2).
(Fig.5 Rapid Fall)
(III) Stepped fall : Stepped fall consists of a series of vertical drops in the form of
steps. This fall is suitable in places where the sloping ground is very long and
requires long glacis to connect the higher bed level with lower bed level. This fall
is practically a modification of the rapid fall. The sloping glacis is divided into a
number of drops so that the following water may not cause any dmage to the canal
bed. Brick walls are provided at each of the drops.
43
(Fig.6 Stepped Fall)
(IV) Trapezoidal North Fall :In this type of fall a body wall is constructed acroos the
canal. The body wall consists of several trapezoidal notches between the side piers
and the intermediate pier or piers. The sills of the notches are kept at the upstream
bed level of the canal.
(Fig.7 Trapezoidal notch fall)
(V) Glacis type fall :The glacis type fall utilised the standing wave phenomenon for
dissipation of energy. The glacis fall may be straight glacis or parabolic glacis
type.
Energy dissipaters :
The water flowing over the spillway acquires a lot of kinetic energy by the time it
reaches near the toe of the spillway. The arrangement is made to dissipate the huge kinetic
energy and the velocity of water is reduced on the downstream side near the toe of the dam.
This arrangement is known as energy dissipaters.
44
Canal Outlets :-
An outlet is a small structure which admits water from the distributing channel to a
water course or field channel. Thus, an outlet is a sort of head regulator for the field channel
delivering water to the irrigation fields.
Types of Outlets :-
Outlets may be classified as 3 types :
(1) Non modular outlet
(2) Semi- module or Flexible Module
(3) Rigid module.
1) Non modular outlet :-A non modular outlet is the one in which the discharge
depends upon the difference in level between the water levels in the distributing
channel and water course. The discharge through such an outlet varies in wide limits
with the fluctuations of the water levels in the distributing and field channels. The
common examples under this category are : Submerged pipe outlet, masonry sluice
and Orifices.
2) Semi module or Flexible module :- A flexible outlet or Semi module outlets the one
in which the discharge is affected by the fluctuations in the water level of the
discharging channel while the fluctuations in the water levels of the field channel do
not have any effect on its discharge.
Example:- Pipe Outlet, Kennedy’s gauge outlet, Pipe cum open flume outlet etc.
3) Rigid Module :- A rigid module is the one which maintains constant discharge,
within limits, irrespective of the fluctuations in water levels in the distributing channel
or field channel. Example : Gibb’s Rigid module.
CANAL ESCAPES :-
Canal escapes is defined as an channel meant for the removal of surplus or excess
water from the canal into nearby drainage. The function served by canal escape are :
(i) Safety valve to protect the canal against possible damage by flooding.
(ii) Emptying of the canal reach, below the escape, for silt or weed removal, repairs
and maintenance.
(iii) Periodical flushing off the silt prone head of a canal through the escape.
45
(Fig.8 Canal escape)
Depending upon the purpose, there can be 3 types of escapes such as :
a) Canal scouring escapes
b) Surplus escapes
c) Tail escapes
Canal scouring escapes :- The scouring escape is constructed for the purpose of scouring off
excess silt from time to time. Escapes are also constructed to dispose off excess supplies of
the parent channel. Excess supplies in the canal take place either during heavy rains or due to
the closure of canal outlet by the farmers. In that case, the escapes save the down stream
section of the canal from overflow of banks.
(Fig.9 Scouring Escape)
Surplus escape :- A canal surplus escape may be weir type, with the crest of weir wall at
F.S.L. of parent bed level.
46
Tail escape :- A tail escape is required F.S.L. at tail end. The structure is weir type with its
crest level at the required F.S.L. of canal at its tail end.
47
CHAPTER-7
CROSS DRAINAGE WORKS
A Cross drainage works is a structure carrying the discharge from a natural stream
across a Canal intercepting the stream.
OR
Canal comes across obstruction like rivers, natural drains, and other canals. The various
types of structure that ate built to carry the canal water across the above mentioned
obstructions or vice versa are called cross drainage works. � There are many different factors involved in selection of a specific type of cross drainage
works and in selection of a suitable site for cross drainage works. It is generally very
costly item & should be avoided by � Diverting one stream into another. � Changing the alignment of the canal, so that it crosses below the junction of two
streams.
NECESSITY OF CROSS DRAINAGE WORKS The following factors justify the necessity of cross drainage works. (a) At the crossing point, the water of the canal and the drainage get intermixed, So for
the smooth running of the canal with its design discharge, the cross drainage works
are required. (b) The site condition of the crossing point may be such that without any suitable
structure, the water of the canal and drainage cannot be diverted to their natural
directions. So, the cross drainage works must be provided to maintain their natural
direction of flow.
(c) The water shed canals do not cross natural drainage. But in actual orientation of the
canal network, this ideal condition may not be available and the obstacles like natural
drainages may be present across the canal. So, the cross- drainage works must be
provided for running the irrigation system.
48
TYPES OF CROSS- DRAINAGE WORKS
The drainage water intercepting the canal can be disposed of in either of the following
ways. (1) By passing the canal over the drainage. The structures that fall under this type are:-
(a) An Aqueduct.
(b) Syphon aqueduct. (2) By Passing the canal below the drainage. The structures that fall under this type are :
(a) Super passage
(b) Canal Syphon or syphon super passage. (3) By passing the drain through the canal, so that the canal water and drainage water are
allowed to intermingle with each other.
Following are the structures under this type of cross- drainage works:
(a) Level crossing.
(b) Inlet and outlet.
PROPER SITE FOR DAINAGE CROSSING The site selected for the cross. Drainage works should have the following main
characteristics. (1) It should be such that it requires minimum disturbance regarding the approach and tail
reaches of the drainage channel. (2) Suitable foundation soil should be available at reasonable depth. (3) Sufficient headway is available for the super structure of the aqueduct over the H.F.L.
of the natural stream. (4) Suitable existing topography, geological and hydraulic conditions for cross drainage
works at reasonable costs.
49
AQUEDUCT
The hydraulic structure in which the irrigation canal is taken over the drainage is known as
an aqueduct.
When the HFL of the drain is sufficiently be
structure is known as aqueduct. In this type of work, the canal water is taken across the
drainage in a trough supported an piers. An aqueduct is just like a bridge except that instead
of carrying a road or a railway, it carries a canal on its top. The advantage of such
arrangement is that the canal, running perennially, is above the ground and is open to
inspection.
An aqueduct is provided when sufficient level difference is available between the
canal and natural drainage, and canal bed level is sufficiently higher than the torrent level.
Generally the canal is in the shape of a rectangular trough and sometimes may be
trapezoidal section, which is constructed with R.C.C. The section of the trough is designed as
per the full supply level of the canal. The height & section of piers are designed according to
the highest flood level and velocity of flow of the drainage. The piers constructed may be
R.C.C., stone masonry or brick masonry. According to the availability
type of foundation provided. The bed & banks of drainage is protected by boulder pitching.
In case of the syphon aqueduct, the HFL of the drain is much higher above the canal
bed, and water runs under syphonic action through the aqueduct barrels or tunnels. Here the
sloping apron provided on both sides of the crossing. The apron may be constructed by
cement concert or stone pitching. The section of the drainage below the canal trough is
constructed with P.C.C. in the form of tunnel or barrels. This tunnel acts as a syphon. Cut
50
he hydraulic structure in which the irrigation canal is taken over the drainage is known as
OR
When the HFL of the drain is sufficiently below the bottom under gravity, such type of
structure is known as aqueduct. In this type of work, the canal water is taken across the
drainage in a trough supported an piers. An aqueduct is just like a bridge except that instead
way, it carries a canal on its top. The advantage of such
arrangement is that the canal, running perennially, is above the ground and is open to
An aqueduct is provided when sufficient level difference is available between the
l drainage, and canal bed level is sufficiently higher than the torrent level.
Generally the canal is in the shape of a rectangular trough and sometimes may be
trapezoidal section, which is constructed with R.C.C. The section of the trough is designed as
per the full supply level of the canal. The height & section of piers are designed according to
the highest flood level and velocity of flow of the drainage. The piers constructed may be
R.C.C., stone masonry or brick masonry. According to the availability of soil, the depth &
type of foundation provided. The bed & banks of drainage is protected by boulder pitching.
SYPHON AQUEDUCT
In case of the syphon aqueduct, the HFL of the drain is much higher above the canal
s under syphonic action through the aqueduct barrels or tunnels. Here the
sloping apron provided on both sides of the crossing. The apron may be constructed by
cement concert or stone pitching. The section of the drainage below the canal trough is
ted with P.C.C. in the form of tunnel or barrels. This tunnel acts as a syphon. Cut
he hydraulic structure in which the irrigation canal is taken over the drainage is known as
low the bottom under gravity, such type of
structure is known as aqueduct. In this type of work, the canal water is taken across the
drainage in a trough supported an piers. An aqueduct is just like a bridge except that instead
way, it carries a canal on its top. The advantage of such
arrangement is that the canal, running perennially, is above the ground and is open to
An aqueduct is provided when sufficient level difference is available between the
l drainage, and canal bed level is sufficiently higher than the torrent level.
Generally the canal is in the shape of a rectangular trough and sometimes may be
trapezoidal section, which is constructed with R.C.C. The section of the trough is designed as
per the full supply level of the canal. The height & section of piers are designed according to
the highest flood level and velocity of flow of the drainage. The piers constructed may be
of soil, the depth &
type of foundation provided. The bed & banks of drainage is protected by boulder pitching.
In case of the syphon aqueduct, the HFL of the drain is much higher above the canal
s under syphonic action through the aqueduct barrels or tunnels. Here the
sloping apron provided on both sides of the crossing. The apron may be constructed by
cement concert or stone pitching. The section of the drainage below the canal trough is
ted with P.C.C. in the form of tunnel or barrels. This tunnel acts as a syphon. Cut-off
walls are provided on both sides of the apron to prevent scouring diring heavy flood. Also
boulder pitching should be provided on the u/s and d/s of the cut
The hydraulic structure in which the drainage is passing over the irrigation canal is
known as super passage. It is reverse of an aqueduct. A super passage is similar to an
aqueduct, except in this case the drain
The FSL of the canal is lower than the underside of the trough carrying drainage
water. Thus the canal water runs under the gravity. The drainage is taken through a
rectangular or trapezoidal trough of channel which is constructed on t
piers. The section of the drainage trough depends on the high flood discharge. A free board of
about 1.5 m. should be provided for safety. The trough should be constructed of R.C.C. The
bed & banks of the canal below the drainage troug
or lining with concrete slabs.
SYPHON SUPER PASSAGE/ CANAL SYPHON/ SYPHON
51
walls are provided on both sides of the apron to prevent scouring diring heavy flood. Also
boulder pitching should be provided on the u/s and d/s of the cut-off wall.
SUPER PASSAGE
The hydraulic structure in which the drainage is passing over the irrigation canal is
known as super passage. It is reverse of an aqueduct. A super passage is similar to an
aqueduct, except in this case the drain is over the canal.
The FSL of the canal is lower than the underside of the trough carrying drainage
water. Thus the canal water runs under the gravity. The drainage is taken through a
rectangular or trapezoidal trough of channel which is constructed on the deck supported by
piers. The section of the drainage trough depends on the high flood discharge. A free board of
about 1.5 m. should be provided for safety. The trough should be constructed of R.C.C. The
bed & banks of the canal below the drainage trough should be protected by boulder pitching
SYPHON SUPER PASSAGE/ CANAL SYPHON/ SYPHON
walls are provided on both sides of the apron to prevent scouring diring heavy flood. Also
The hydraulic structure in which the drainage is passing over the irrigation canal is
known as super passage. It is reverse of an aqueduct. A super passage is similar to an
The FSL of the canal is lower than the underside of the trough carrying drainage
water. Thus the canal water runs under the gravity. The drainage is taken through a
he deck supported by
piers. The section of the drainage trough depends on the high flood discharge. A free board of
about 1.5 m. should be provided for safety. The trough should be constructed of R.C.C. The
h should be protected by boulder pitching
SYPHON SUPER PASSAGE/ CANAL SYPHON/ SYPHON
If the FSL of the canal is sufficiently above the bed level of the drainage trough, so that the
canal flows under syphonic action unde
a siphon super passage.
This structure is reverse of an syphon aqueduct. The section of the trough is designed
according to high flood discharge. The canal bed is lowered and a ramp is provided at th
entry & exit, so that the trouble of silting is minimized. The sloping apron may be
constructed with stone pitching or concert slabs. The section of the canal below the ttough is
constructed with cement concrete in the form of tunnel ehich acts as siphon
provided on u/s & d/s of the sloping apron to minimize scouring affect during high flood.
In this type of cross drainage work, the canal water and drain water are allowed to
intermingle with each other. A level crossing
huge drainage (Such as a stream or a river) approach each other practically at the same level.
In this type of work, the drainage water is passed into the canal & then taken out at
the opposite bank. The work consists of
I. Construction of crest, with its top at the FSL of the canal, at the u/s junction
with the canal.
II. Provision of the head regulator across the drainage at its d/s junction with the
canal.
III. A cross regulator across the cana A regulator at the end of the incoming canal is also sometimes required.
When the drainage does not carry any water, its regulator is closed while the cross
regulator of the canal is kept open so that the canal f
52
f the FSL of the canal is sufficiently above the bed level of the drainage trough, so that the
canal flows under syphonic action under the trough, the structure is known as canal syphon or
This structure is reverse of an syphon aqueduct. The section of the trough is designed
according to high flood discharge. The canal bed is lowered and a ramp is provided at th
entry & exit, so that the trouble of silting is minimized. The sloping apron may be
constructed with stone pitching or concert slabs. The section of the canal below the ttough is
constructed with cement concrete in the form of tunnel ehich acts as siphon. Cut
provided on u/s & d/s of the sloping apron to minimize scouring affect during high flood.
LEVEL CROSSING
In this type of cross drainage work, the canal water and drain water are allowed to
intermingle with each other. A level crossing is generally provided when a large canal and
huge drainage (Such as a stream or a river) approach each other practically at the same level.
In this type of work, the drainage water is passed into the canal & then taken out at
pposite bank. The work consists of
Construction of crest, with its top at the FSL of the canal, at the u/s junction
Provision of the head regulator across the drainage at its d/s junction with the
A cross regulator across the canal at its d/s junction with the drainage.
A regulator at the end of the incoming canal is also sometimes required.
When the drainage does not carry any water, its regulator is closed while the cross
regulator of the canal is kept open so that the canal flows without any interruption. During
f the FSL of the canal is sufficiently above the bed level of the drainage trough, so that the
r the trough, the structure is known as canal syphon or
This structure is reverse of an syphon aqueduct. The section of the trough is designed
according to high flood discharge. The canal bed is lowered and a ramp is provided at the
entry & exit, so that the trouble of silting is minimized. The sloping apron may be
constructed with stone pitching or concert slabs. The section of the canal below the ttough is
. Cut-off walls are
provided on u/s & d/s of the sloping apron to minimize scouring affect during high flood.
In this type of cross drainage work, the canal water and drain water are allowed to
is generally provided when a large canal and
huge drainage (Such as a stream or a river) approach each other practically at the same level.
In this type of work, the drainage water is passed into the canal & then taken out at
Construction of crest, with its top at the FSL of the canal, at the u/s junction
Provision of the head regulator across the drainage at its d/s junction with the
l at its d/s junction with the drainage.
When the drainage does not carry any water, its regulator is closed while the cross-
lows without any interruption. During
the floods, however, the drainage regulator is opened so that the flood discharge, after
spilling over the crest & mixing with the canal water, passes through it to the downstream of
the drainage.
In Case of crossing of a small irrigation channel with a small drainage, no hydraulic
structure is constructed, because, the discharged of the drainage and the channel are
practically low and these can be easily tackled by easy sy
arrangement. In this system an inlet is provided in the channel bank simply by open cut and
the drainage water is allowed to join the channel. Then at a suitable point on the downstream
side of the channel an outlet is provided b
is allowed to flow through a leading channel towards the original course of the drainage. At
the points of inlet the bed and banks of the drainage are protected by stone pitching. The bed
and banks of the irrigation channel between inlet and outlet points should also be protected
by stone pitching.
SELECTION OF SUITABLE TYPE OF CROSS
According to the relative bed levels of the canal and the river or drainage, the types
of cross drainage works are generally selected. However, in actual field, such ideal
conditions may not be available and the choice would then depends on following points: (a) The crossing should be at right angles to each other. (b) Availability of funds. (c) Suitability of soil for embankment. (d) Position of water table and availability of dewatering equipments.
53
the floods, however, the drainage regulator is opened so that the flood discharge, after
spilling over the crest & mixing with the canal water, passes through it to the downstream of
INLET & OUTLET
In Case of crossing of a small irrigation channel with a small drainage, no hydraulic
structure is constructed, because, the discharged of the drainage and the channel are
practically low and these can be easily tackled by easy system like inlet and outlet
arrangement. In this system an inlet is provided in the channel bank simply by open cut and
the drainage water is allowed to join the channel. Then at a suitable point on the downstream
side of the channel an outlet is provided by open cut and the water from the irrigation channel
is allowed to flow through a leading channel towards the original course of the drainage. At
the points of inlet the bed and banks of the drainage are protected by stone pitching. The bed
e irrigation channel between inlet and outlet points should also be protected
SELECTION OF SUITABLE TYPE OF CROSS- DRAINAGE WORKS
According to the relative bed levels of the canal and the river or drainage, the types
works are generally selected. However, in actual field, such ideal
conditions may not be available and the choice would then depends on following points:
The crossing should be at right angles to each other.
l for embankment.
Position of water table and availability of dewatering equipments.
the floods, however, the drainage regulator is opened so that the flood discharge, after
spilling over the crest & mixing with the canal water, passes through it to the downstream of
In Case of crossing of a small irrigation channel with a small drainage, no hydraulic
structure is constructed, because, the discharged of the drainage and the channel are
stem like inlet and outlet
arrangement. In this system an inlet is provided in the channel bank simply by open cut and
the drainage water is allowed to join the channel. Then at a suitable point on the downstream
y open cut and the water from the irrigation channel
is allowed to flow through a leading channel towards the original course of the drainage. At
the points of inlet the bed and banks of the drainage are protected by stone pitching. The bed
e irrigation channel between inlet and outlet points should also be protected
DRAINAGE WORKS
According to the relative bed levels of the canal and the river or drainage, the types
works are generally selected. However, in actual field, such ideal
conditions may not be available and the choice would then depends on following points:-
54
(e) Well defined c/s of the canal or river or drainage should be available.
(1) Availability of suitable foundation:-
For the construction of cross drainage works suitable foundation is required. By
boring test, if suitable foundation is not available, then the type cross drainage works
should be selected according to site condition. (2) Economical Consideration:-
The cost of construction of cross drainage works should be justified with respect to
the project cost and overall benefits of the project. So, the type of works should be
selected considering the economical point of view. (3) Discharge of the Drainage:-
Practically, the discharge of the drainage is very uncertain in rainy season. So, the
structure should be carefully selected so that it may not be destroyed due to
unexpected heavy discharge of the river or drainage. (4) Construction Problems:-
Different types of constructional problems may arise at the site such as sub-soil water,
construction materials, communication, availability of land, etc. So, the type of works
should be selected according to the site condition.
55
CHAPTER-8
DAM
8.1 INTRODUCTION
A dam is a hydraulic structure of fairly impervious material built across a river
to create a reservoir on its upstream side for impounding water for various purposes.
It is suitable in hilly region where a deep gorge section is available for the strange
reservoir. These purposes may be Irrigation, Hydro-power, Water-supply, Flood
Control, Navigation, Fishing and Recreation. Dams may be built to meet the one of
the above purposes or they may be constructed fulfilling more than one. As such, it
can be classified as: Single-purpose and Multipurpose Dam.
The dam is meant for serving multipurpose functions such as,
(a) Irrigation,(b)Hydroelectric power generation, (c)Flood control, (d)Water supply,
(e) Fishery, (f) Recreation.
Weir and Barrage are also impervious barriers across the river. Which are
suitable in plain terrain but not in hilly region. The purpose of weir is only to raise the
water level to some desired height and the purpose of barrage is to adjust the water
level at different levels when required. These to hydraulic structures are suitable for
irrigation only.
DIFFEREENT PARTS & TEREMELOGY OF DAMS:-
� Crest: The top of the dam structure. These may in some cases be used for
providing a roadway or walkway over the dam.
� Parapet walls: Low Protective walls on either side of the roadway or walkway on
the crest.
� Heel: Portion of structure in contact with ground or river-bed at upstream side.
� Toe: Portion of structure in contact with ground or river-bed at downstream side.
� Spillway: It is the arrangement made (kind of passage) near the top of structure
for the passage of surplus/ excessive water from the reservoir.
� Abutments: The valley slopes on either side of the dam wall to which the left &
right end of dam are fixed to.
� Gallery: Level or gently sloping tunnel like passage (small room like space) at
transverse or longitudinal within the dam with drain on floor for seepage water.
These are generally provided for having space for drilling grout holes and
drainage holes. These may also be used to accommodate the instrumentation for
studying the performance of dam.
� Sluice way: Opening in the structure near the base, provided to clear the silt
accumulation in the reservoir.
o Illustration of dam-parts in a typical cross section
� Free board: The space between the highest level of water in the reservoir and the
top of the structure.
� Dead Storage level: Level of permanent storage below which the water will not
be withdrawn.
� Diversion Tunnel: Tunnel constructed to divert or change the directi
to bypass the dam construction site. The hydraulic structures are built while the
river flows through the diversion tunnel.
SELECTION OF SITE FOR DAM
While selecting the site for a dam, the following points should be considered.
� Good rocky foundation should be available at the dam site. The nature of the
foundation soil should be examined by suitable method of soil exploration.
� The river valley should be narrow and well defined so that the length of the dam
may be short as far as possible.
� Site should be in deep gorge section of the valley so that large capacity storage
can be formed with minimum surface area and minimum length of dam.
� Valuable property and valuable land should not be submerged due to the
construction of dam.
o The proposed
sediment. If unavoidable, the sources of sediments should be located and
necessary measures should be recommended to arrest the sediment.
� The site should be easily accessible by road or railway f
construction materials, equipment’s, etc.
� The construction materials should be available in the vicinity of the dam site.
56
: Opening in the structure near the base, provided to clear the silt
accumulation in the reservoir.
parts in a typical cross section (click the image to view it clearly)
: The space between the highest level of water in the reservoir and the
: Level of permanent storage below which the water will not
: Tunnel constructed to divert or change the directi
to bypass the dam construction site. The hydraulic structures are built while the
river flows through the diversion tunnel.
SELECTION OF SITE FOR DAM
While selecting the site for a dam, the following points should be considered.
oundation should be available at the dam site. The nature of the
foundation soil should be examined by suitable method of soil exploration.
The river valley should be narrow and well defined so that the length of the dam
may be short as far as possible.
Site should be in deep gorge section of the valley so that large capacity storage
can be formed with minimum surface area and minimum length of dam.
Valuable property and valuable land should not be submerged due to the
The proposed river or its tributaries should not carry large quantity of
sediment. If unavoidable, the sources of sediments should be located and
necessary measures should be recommended to arrest the sediment.
The site should be easily accessible by road or railway for the transport of
construction materials, equipment’s, etc.
The construction materials should be available in the vicinity of the dam site.
: Opening in the structure near the base, provided to clear the silt
to view it clearly)
: The space between the highest level of water in the reservoir and the
: Level of permanent storage below which the water will not
: Tunnel constructed to divert or change the direction of water
to bypass the dam construction site. The hydraulic structures are built while the
While selecting the site for a dam, the following points should be considered.
oundation should be available at the dam site. The nature of the
foundation soil should be examined by suitable method of soil exploration.
The river valley should be narrow and well defined so that the length of the dam
Site should be in deep gorge section of the valley so that large capacity storage
can be formed with minimum surface area and minimum length of dam.
Valuable property and valuable land should not be submerged due to the
river or its tributaries should not carry large quantity of
sediment. If unavoidable, the sources of sediments should be located and
necessary measures should be recommended to arrest the sediment.
or the transport of
The construction materials should be available in the vicinity of the dam site.
57
� Sufficient space should be available near the site for the construction of labour
colony, godowns and staff quarters for the personnel associated with the
constructional activities.
� The basin should be free from cracks, fissures, etc. to avoid percolation loss. It is
done by physical verification and other observations, If unavoidable, the area
should be located and necessary measures should be recommended to make the
area leak-proof.
� From the rainfall records in the catchment area or empirical formulae the
maximum discharge of the river should be ascertained whether the required
quantity of water shall be available or not.
INVESTIGATION WORKS FOR DAM SITE
The following investigation works should be done before final selection of dam site
and the preparation of the project report.
1. Preliminary Survey: the preliminary survey involves the following steps.
(a) Reconnaissance survey : the reconnaissance survey should be conducted for
the dam site and surrounding area to gather information regarding the natural
features of the area, nature of dam site, location of labour colony and staff
quarters, stack yard, dodowns, etc. the nature of the land and the localities in
the basin area should also be recorded. And index map should be prepared.
(b) Topographical survey: A topographical map is to be prepared for the
proposed project area by traverse surveying. The traverse survey may be
conducted any suitable method depending on the nature of the area.
(c) Contour Survey: A contour map should be prepared for the basin area to
determine the capacity of the reservoir.
(d) Contour Survey: longitudinal leveling and cross-sectional leveling should be
done at the dam site at least one km upstream and downstream of the proposed
centerline of the dam. This is done to select the most suitable dam site.
2. Geological Survey: the geological survey involves the following steps
a. Soil Survey: To work the nature of the foundation at the dam site. Soil
exploration should be done by suitable method. The sub-soil formation should
be thoroughly studied to determine the type of foundation for the dam.
b. Study of formation in basin area: Soil exploration should be done at
different spot in the basin area to ascertain the nature of sub-soil. This is done
to calculate the probable percolation loss.
c. Study of source of Sediment: The sources of sediments carried by the river
or its tributaries should be studied and located. If slips or areas of loose soil
58
with mica particles are found, then the stabilization of those areas should be
done.
3. Hydrological Survey: It involves the following steps:
a. Gauge and discharge site: The gauge and discharge stations should be
established near the dam site to record the discharge of the river throughout
the year.
b. Site analysis: In rainy season the river carries heavy silt or sediment. The
analysis of the silt should be carried out throughout the season for some
specific period to determine grade of silt. This is done to ascertain the possible
sedimentation in the reservoir and thus suitable methods can be employed to
reduce the sedimentation.
4. Communication Survey: The route survey for the possible communication of
the dam site the nearest highway or railway station should be done. It involves the
preparation of longitudinal section and cross-sections along the proposed
alignment. It is done to estimate the cost of construction of this connecting road or
railway lie. The possible route for telephone communication and electrical
connections should also be located.
5. Construction Materials Survey: The availability of construction materials like
stone, sand, etc. should be located in the topographical map of the concerned
district or state. The possible route for carrying these materials should also be
located in the map.
6. Compensation Report: A detailed report should be prepared for the
compensation which is likely to be paid by the government during the
implementation of the project. This will include the dam site, area of labour
colony and staff quarters, area required for stack yards and godowns, valuable
lands and properties that may be submerged by the reservoir, etc.
7. Project Report: The project involves the following steps:
a. Design and estimate of dam and other allied structures.
b. Detailed drawings of dam section with foundation and other buildings or
structures.
c. Detailed estimate for the road or railway communication.
d. Comprehensive report for compensation.
e. The project is forwarded to the higher authority with recommendation for
approval.
f. The project is forward to the higher authority with recommendation for
approval.
59
CLASSIFICATION OF DAMS:
Dams can be classified in number of ways. But most usual ways of classification i.e.
types of dams are mentioned below:
Based on the functions of dams, it can be classified as follows:
1. Storage dams: They are constructed to store water during the rainy season when
there is a large flow in the river. Many small dams impound the spring runoff for
later use in dry summers. Storage dams may also provide a water supply, or
improved habitat for fish and wildlife. They may store water for hydroelectric
power generation, irrigation or for a flood control project. Storage dams are the
most common type of dams and in general the dam means a storage dam unless
qualified otherwise.
2. Diversion dams: A diversion dam is constructed for the purpose of diverting
water of the river into an off-taking canal (or a conduit). They provide sufficient
pressure for pushing water into ditches, canals, or other conveyance systems. Such
shorter dams are used for irrigation, and for diversion from a stream to a distant
storage reservoir. It is usually of low height and has a small storage reservoir on
its upstream. The diversion dam is a sort of storage weir which also diverts water
and has a small storage. Sometimes, the terms weirs and diversion dams are used
synonymously.
3. Detention dams: Detention dams are constructed for flood control. A detention
dam retards the flow in the river on its downstream during floods by storing some
flood water. Thus the effect of sudden floods is reduced to some extent. The water
retained in the reservoir is later released gradually at a controlled rate according to
the carrying capacity of the channel downstream of the detention dam. Thus the
area downstream of the dam is protected against flood.
4. Debris dams: A debris dam is constructed to retain debris such as sand, gravel,
and drift wood flowing in the river with water. The water after passing over a
debris dam is relatively clear.
5. Coffer dams: It is an enclosure constructed around the construction site to
exclude water so that the construction can be done in dry. A coffer dam is thus a
temporary dam constructed for facilitating construction. These structure are
usually constructed on the upstream of the main dam to divert water into a
diversion tunnel (or channel) during the construction of the dam. When the flow in
the river during construction of hydraulic structures is not much, the site is usually
enclosed by the coffer dam and pumped dry. Sometimes a coffer dam on the
downstream of the dam is also required.
Based on structure and design, dams can be classified as follows:
1. Gravity Dams: A gravity dam is a massive sized dam fabricated from concret
stone masonry. They are designed to hold back large volumes of water. By using
concrete, the weight of the dam is actually able to resist the horizontal thrust of water
pushing against it. This is why it is called a gravity dam. Gravity essentially ho
dam down to the ground, stopping water from toppling it over.
a. b. Types of dam
i. Gravity dams are well suited forblocking rivers in wide valleys or
narrow gorge ways. Since gravity dams must rely on their own weight
to hold back water, it is necessary
foundation ofbedrock.
Examples of Gravity dam: Grand Coulee Dam (USA), Nagarjuna
Sagar (India) and Itaipu
is the largest in the world).
2. Earth Dams: An earth dam is made of earth (
successive layers of earth, using the most impervious materials to form a core and
placing more permeable substances on the upstream and downstream sides. A facing
of crushed stone prevents erosion by wind or rain, and an am
concrete, protects against catastrophic washout should the water overtop the dam.
Earth dam resists the forces exerted upon it mainly due to shear strength of the soil.
Although the weight of the structure also helps in resisting t
behavior of an earth dam is entirely different from that of a gravity dam. The earth
dams are usually built in wide valleys having flat slopes at flanks (abutments).The
foundation requirements are less stringent than those of grav
can be built at the sites where the foundations are less strong. They can be built on all
types of foundations. However, the height of the dam will depend upon the strength of
the foundation material.
Examples of earthfill dam: Ron
60
Based on structure and design, dams can be classified as follows:
: A gravity dam is a massive sized dam fabricated from concret
stone masonry. They are designed to hold back large volumes of water. By using
concrete, the weight of the dam is actually able to resist the horizontal thrust of water
pushing against it. This is why it is called a gravity dam. Gravity essentially ho
dam down to the ground, stopping water from toppling it over.
Gravity dams are well suited forblocking rivers in wide valleys or
narrow gorge ways. Since gravity dams must rely on their own weight
to hold back water, it is necessary that they are built on a solid
foundation ofbedrock.
Examples of Gravity dam: Grand Coulee Dam (USA), Nagarjuna
Sagar (India) and Itaipu Dam (It lies Between Brazil and Paraguay and
is the largest in the world).
: An earth dam is made of earth (or soil) built up by compacting
successive layers of earth, using the most impervious materials to form a core and
placing more permeable substances on the upstream and downstream sides. A facing
of crushed stone prevents erosion by wind or rain, and an ample spillway, usually of
concrete, protects against catastrophic washout should the water overtop the dam.
Earth dam resists the forces exerted upon it mainly due to shear strength of the soil.
Although the weight of the structure also helps in resisting the forces, the structural
behavior of an earth dam is entirely different from that of a gravity dam. The earth
dams are usually built in wide valleys having flat slopes at flanks (abutments).The
foundation requirements are less stringent than those of gravity dams, and hence they
can be built at the sites where the foundations are less strong. They can be built on all
types of foundations. However, the height of the dam will depend upon the strength of
the foundation material.
Examples of earthfill dam: Rongunsky dam (Russia) and New Cornelia Dam (USA).
: A gravity dam is a massive sized dam fabricated from concrete or
stone masonry. They are designed to hold back large volumes of water. By using
concrete, the weight of the dam is actually able to resist the horizontal thrust of water
pushing against it. This is why it is called a gravity dam. Gravity essentially holds the
Gravity dams are well suited forblocking rivers in wide valleys or
narrow gorge ways. Since gravity dams must rely on their own weight
that they are built on a solid
foundation ofbedrock.
Examples of Gravity dam: Grand Coulee Dam (USA), Nagarjuna
Dam (It lies Between Brazil and Paraguay and
or soil) built up by compacting
successive layers of earth, using the most impervious materials to form a core and
placing more permeable substances on the upstream and downstream sides. A facing
ple spillway, usually of
concrete, protects against catastrophic washout should the water overtop the dam.
Earth dam resists the forces exerted upon it mainly due to shear strength of the soil.
he forces, the structural
behavior of an earth dam is entirely different from that of a gravity dam. The earth
dams are usually built in wide valleys having flat slopes at flanks (abutments).The
ity dams, and hence they
can be built at the sites where the foundations are less strong. They can be built on all
types of foundations. However, the height of the dam will depend upon the strength of
the foundation material.
gunsky dam (Russia) and New Cornelia Dam (USA).
61
3. Rockfill Dams: A rockfill dam is built of rock fragments and boulders of large size.
An impervious membrane is placed on the rockfill on the upstream side to reduce the
seepage through the dam. The membrane is usually made of cement concrete or
asphaltic concrete.
a. b. Mohale Dam, Lesotho, Africa
In early rockfill dams, steel and timber membrane were also used, but now
they are obsolete. A dry rubble cushion is placed between the rockfill and the
membrane for the distribution of water load and for providing a support to the
membrane. Sometimes, the rockfill dams have an impervious earth core in the middle
to check the seepage instead of an impervious upstream membrane. The earth core is
placed against a dumped rockfill. It is necessary to provide adequate filters between
the earth core and the rockfill on the upstream and downstream sides of the core so
that the soil particles are not carried by water and piping does not occur. The side
slopes of rockfill are usually kept equal to the angle of repose of rock, which is
usually taken as 1.4:1 (or 1.3:1). Rockfill dams require foundation stronger than those
for earth dams.
Examples of rockfill dam: Mica Dam (Canada) and Chicoasen Dam (Mexico).
4. Arch Dams: An arch dam is curved in plan, with its convexity towards the upstream
side. They transfer the water pressure and other forces mainly to the abutments by
arch action.
Hoover dam (USA)
62
An arch dam is quite suitable for narrow canyons with strong flanks which are
capable of resisting the thrust produced by the arch action. The section of an arch dam
is approximately triangular like a gravity dam but the section is comparatively
thinner. The arch dam may have a single curvature or double curvature in the vertical
plane. Generally, the arch dams of double curvature are more economical and are
used in practice.
Examples of Arch dam: Hoover Dam (USA) and Idukki Dam (India).
5. Buttress Dams: Buttress dams are of three types : (i) Deck type, (ii) Multiple-arch
type, and (iii) Massive-head type. A deck type buttress dam consists of a sloping deck
supported by buttresses. Buttresses are triangular concrete walls which transmit the
water pressure from the deck slab to the foundation. Buttresses are compression
members. Buttresses are typically spaced across the dam site every 6 to 30 metre,
depending upon the size and design of the dam. Buttress dams are sometimes called
hollow dams because the buttresses do not form a solid wall stretching across a river
valley.The deck is usually a reinforced concrete slab supported between the
buttresses, which are usually equally spaced
.
In a multiple-arch type buttress dam the deck slab is replaced by horizontal arches
supported by buttresses. The arches are usually of small span and made of concrete. In
a massive-head type buttress dam, there is no deck slab. Instead of the deck, the
upstream edges of the buttresses are flared to form massive heads which span the
distance between the buttresses. The buttress dams require less concrete than gravity
dams. But they are not necessarily cheaper than the gravity dams because of extra cost
of form work, reinforcement and more skilled labor. The foundation requirements of a
buttress are usually less stringent than those in a gravity dam.
Examples of Buttress type: Bartlett dam (USA) and The Daniel-Johnson Dam
(Canada).
6. Steel Dams: Dams: A steel dam consists of a steel framework, with a steel skin plate
on its upstream face. Steel dams are generally of two types: (i) Direct-strutted, and (ii)
Cantilever type . In direct strutted steel dams, the water pressure is transmitted
directly to the foundation through inclined struts. In a cantilever type steel dam, there
is a bent supporting the upper part of the deck, which is formed into a cantilever truss.
This arrangement introduces a tensile force in the deck girder which can be taken care
of by anchoring it into the foundation at the upstream toe. Hovey suggested that
tension at the upstream toe may be reduced by flattening the slopes of the lower struts
in the bent.
However, it would require heavier sections struts for Another alternative to reduce
tension is to frame together the entire bent rigidly so that the moment due to the
weight of the water on the lower part of the deck is utilized to o
induced in the cantilever. This arrangement would, however, require bracing and this
will increase the cost. These are quite costly and are subjected to corrosion. These
dams are almost obsolete. Steel dams are sometimes used as temporary
during the construction of the permanent one. Steel coffer dams are supplemented
with timber or earthfill on the inner side to make them water tight. The area between
the coffer dams is dewatered so that the construction may be done in dry for
permanent dam.
Examples of Steel type: Redridge Steel Dam (USA) and Ashfork
Dam (USA).
7. Timber Dams: Main load
wood, primarily coniferous varieties such as pine and fir. Timber dams
small heads (2-4 m or, rarely, 4
of the apron they are divided into pile, crib, pile
63
of by anchoring it into the foundation at the upstream toe. Hovey suggested that
tension at the upstream toe may be reduced by flattening the slopes of the lower struts
.
However, it would require heavier sections struts for Another alternative to reduce
tension is to frame together the entire bent rigidly so that the moment due to the
weight of the water on the lower part of the deck is utilized to offset the moment
induced in the cantilever. This arrangement would, however, require bracing and this
will increase the cost. These are quite costly and are subjected to corrosion. These
dams are almost obsolete. Steel dams are sometimes used as temporary
during the construction of the permanent one. Steel coffer dams are supplemented
with timber or earthfill on the inner side to make them water tight. The area between
the coffer dams is dewatered so that the construction may be done in dry for
permanent dam.
Examples of Steel type: Redridge Steel Dam (USA) and Ashfork-Bainbridge Steel
: Main load-carrying structural elements of timber dam are made of
wood, primarily coniferous varieties such as pine and fir. Timber dams
4 m or, rarely, 4-8 m) and usually have sluices; according to the design
of the apron they are divided into pile, crib, pile-crib, and buttressed dams.
of by anchoring it into the foundation at the upstream toe. Hovey suggested that
tension at the upstream toe may be reduced by flattening the slopes of the lower struts
However, it would require heavier sections struts for Another alternative to reduce
tension is to frame together the entire bent rigidly so that the moment due to the
ffset the moment
induced in the cantilever. This arrangement would, however, require bracing and this
will increase the cost. These are quite costly and are subjected to corrosion. These
dams are almost obsolete. Steel dams are sometimes used as temporary coffer dams
during the construction of the permanent one. Steel coffer dams are supplemented
with timber or earthfill on the inner side to make them water tight. The area between
the coffer dams is dewatered so that the construction may be done in dry for the
permanent dam.
Bainbridge Steel
carrying structural elements of timber dam are made of
are made for
8 m) and usually have sluices; according to the design
crib, and buttressed dams.
64
Timber dam
The openings of timber dams are restricted by abutments; where the sluice is very
long it is divided into several openings by intermediate supports: piers, buttresses, and
posts. The openings are covered by wooden shields, usually several in a row one
above the other. Simple hoists—permanent or mobile winches—are used to raise and
lower the shields.
8. Rubber Dams: A symbol of sophistication and simple and efficient design, this most
recent type of dam uses huge cylindrical shells made of special synthetic rubber and
inflated by either compressed air or pressurized water. Rubber dams offer ease of
construction, operation and decommissioning in tight schedules.
a. b. These can be deflated when pressure is released and hence, even the crest level
can be controlled to some extent. Surplus waters would simply overflow the
inflated shell. They need extreme care in design and erection and are limited to
small projects.
EARTHEN DAM
Earthen dams are constructed purely by earth work in trapezoidal section.
These are most economical and suitable for weak foundation. Earthen dams are
classified as follows:-
65
Based on Method of Construction
Rolled fill Dam:
In this method, the dam is constructed in successive layers of earth by
mechanical compaction. The selected soil is transported from borrow pits and laid on
the dam section, to layers of about 45 cm. The layers are thoroughly compacted by
rollers of recommended weight and type. When the compaction of one layer is fully
achieved, the next layer is laid and compacted in the usual way. The designed dam
section hence is completed layer by layer.
Hydraulic Fill Dam:
In this method, the dam section is constructed with the help of water.
Sufficient water is poured in the borrow pit and by plugging thoroughly, slurry is
formed. This slurry is transported to the dam site by pipe line and discharged near the
upstream and downstream faces of the dam. The coarser material gets deposited near
the face and the finer material move towards the centre and gets deposit there. Thus
the dam section is formed with faces of coarse material and central core is of
impervious materials like clay and silt. In this case, compaction is not necessary.
Semi-Hydraulic Fill Dam:
In this method the selected earth is transported from the borrowpit and
dumped within the section of the dam, as done in the case of rolled fill dam. While
dumping no water is used. But, after dumping the water jet is forced on the dumped
earth. Due to the action of water the finer materials move towards the centre of the
dam and an impervious core is formed with fine materials like clay. The outside body
is formed by coarse material, In this case also compaction is not necessary.
66
Homogeneous Type Dam:
This type of dam is constructed purely with earth in trapezoidal section having
the side slopes according to the angle of repose of the soil. The top width and height
deponents on the depth of water to be retained and the gradient of the seepage line.
The phreatic line (top level of seepage line) should pass well within the body of the
dam. This type of dam is completely pervious. The upstream face of the dam is
protected by stone pitching. Now-a- days, the earthen dam is modified by providing
horizontal drainage blanket or rock toe.
Zoned Type Dam:
This type of dam consists of several materials. The impervious core is made of puddle
clay and the outer previous shell is constructed with the mixture of earth, sand, gravel,
etc. the core is trapezoidal in section and its width depends on the seepage
characteristics of the soil mixture on the upstream side. The core is extended below
the both sides of the impervious core to control the seepage. The transition filter is
made of gravel and coarse sand. The upstream face of the dam is protected by stone
pitching.
Diaphragm Type Dam:
In this type of dam, a thin impervious core of diaphragm is provided which may
consist of puddle clay or cement concrete or bituminous concrete. The upstream and
downstream body of the dam is constructed with pervious shell which consists of the
mixture of soil, sand, gravel, etc. the thickness of the core is generally less than 3m. A
blanket of stones is provided on the toe of the dam for the drainage of the seepage
water without damaging the base of the dam. The upstream face is protected by stone
pitching. The side slope of the dam should be decided according to the angle of repose
of the soil mixture.
CAUSES OF FAILURE OF EARTHEN DAM
The failure of the earthen dam may be caused due to the reasons.
1. Hydraulic Failure : this type of failure may be caused by:
a. Overtopping: If the actual flood discharge is much is much more than the
estimated flood discharge or the fee board is kept insufficient or there is
settlement of the dam or the capacity of spill way is insufficient, then it results in
the overtopping of the dam. During the overtopping the crest of the dam may be
washed out and the dam may collapse.
b. Erosion: If the stone of the upstream side is insufficient, then the upstream face
may be damaged by erosion due to wave action. The downstream side also may be
damaged by tail water, rainwater, etc. The toe of the dam may also get damaged
by the water flowing through the spill ways.
67
c. Seepage Failure : this type of failure may be caused by:
d. Piping of undermining: Due to the continuous seepage flow through the body of
the dam and through the sub-soil below the dam, the downstream side gets eroded
or wshed out and a hollow pipe like groove is formed which extends gradually
towards the upstream through the base of the dam. This phenomenon is known as
piping or undermining. This effect weakens the dam and ultimately causes failure
of the dam.
e. Sloughing: the crumbling of the tow of the dam is known as sloughing. When the
reservoir runs full, for a longer time, the downstream base of the dam remains
saturated. Due to the force of the seepage water the toe of the dam goes on
crumbling gradually. Ultimately the base of the dam collapses.
f. Structural Failure : This type failure may be caused by
g. Sliding of the side slopes : Sometimes, it is found that the side slope of the dam
slides down to form some steeper slope. The dam goes on depressing gradually
and then overtopping occurs which leads to the failure of the dam.
h. Damage by burrowing animals: due to earthquake cracks may develop on the
body of the dam and the dam may eventually Collapse.
SOLID GRAVITY DAM
The solid gravity dam may be constructed with rubble masonry or concrete. The
rubble masonry is done according to the shape of the dam with rich cement mortar.
The upstream and downstream face are finished with rich cement mortar. Non-a-days,
concrete gravity dams are preferred, because they can be easily constructed by laying
concrete, layer by layer with construction joints. But good rocky foundation must be
available to bear the enormous weight of the dam. The distance between the heel and
toe is considered as the base width. It depends, on the height of the dam. Again, the
height depends on the nature of foundation. If good rocky foundation is available, the
height may be above 200 m. If hard foundation is not available, the height of the dam
should be limited to about 20m. The upstream and downstream base of dam is made
sloping. The horizontal trace (or line) passing through the upstream top edge is known
as axis of the dam or the base line. The layout of the dam is done corresponding to
this base line. Drainage gallery is provided at the base of the dam. Spill ways are
provided at the full reservoir level to allow the surplus water to flow to the
downstream. The solid gravity dam resists all the forces acting on it by its self-weight.
FORCES ACTING ON GRAVITY DAM.
1. Weight of the dam.
2. Water pressure
68
3. Uplift pressure.
4. Pressure due to earthquake
5. Ice pressure
6. Wave pressure
7. Silt Pressure
8. Wind Pressure
Following are the modes of failure of a Gravity Dam:
1.Overturning
2.Sliding
3. Compression or Crushing
4. Tension
SPILLWAYS:
Spillways are structures constructed to provide safe release of flood waters
from a dam to a downstream are, normally the river on which the dam has been
constructed.
Every reservoir has a certain capacity to store water. If the reservoir is full and
flood waters enter the same, the reservoir level will go up and may eventually result in
over-topping of the dam. To avoid this situation, the flood has to be passed to the
downstream and this is done by providing a spillway which draws water from the top
of the reservoir. A spillway can be a part of the dam or separate from it.
Spillways can be controlled or uncontrolled. A controlled spillway is provided
with gates which can be raised or lowered. Controlled spillways have certain
advantages as will be clear from the discussion that follows. When a reservoir is full,
its water level will be the same as the crest level of the spillway.
This is the normal reservoir level. If a flood enters the reservoir at this time,
the water level will start going up and simultaneously water will start flowing out
through the spillway. The rise in water level in the reservoir will continue for some
time and so will the discharge over the spillway. After reaching a maximum, the
69
reservoir level will come down and eventually come back to the normal reservoir
level.
The top of the dam will have to be higher than the maximum reservoir level
corresponding to the design flood for the spillway, while the effective storage
available is only up to the normal reservoir level. The storage available between the
maximum reservoir level and the normal reservoir level is called the surcharge storage
and is only a temporary storage in uncontrolled spillways. Thus for a given height of
the dam, part of the storage - the surcharge storage is not being utilized. In a
controlled spillway, water can be stored even above the spillway crest level by
keeping the gates closed. The gates can be opened when a flood has to be passed.
Parameters considered in Designing Spillways
Thus controlled spillways allow more storage for the same height of the dam. Many
parameters need consideration in designing a spillway. These include:
1. The inflow design flood hydro-graph
2. The type of spillway to be provided and its capacity
3. The hydraulic and structural design of various components and
4. The energy dissipation downstream of the spillway.
The topography, hydrology, hydraulics, geology and economic considerations all have
a bearing on these decisions. For a given inflow flood hydro graph, the maximum rise
in the reservoir level depends on the discharge characteristics of the spillway crest and
its size and can be obtained by flood routing. Trial with different sizes can then help
in getting the optimum combination.
Types of Spillways - Classification of Spillways
There are different types of spillways that can be provided depending on the
suitability of site and other parameters. Generally a spillway consists of a control
structure, a conveyance channel and a terminal structure, but the former two may be
combined in the same for certain types. The more common types are briefly described
below.
Ogee Spillway
The Ogee spillway is generally provided in rigid dams and forms a part of the main
dam itself if sufficient length is available. The crest of the spillway is shaped to
conform to the lower nappe of a water sheet flowing over an aerated sharp crested
weir.
Chute (Trough) Spillway
In this type of spillway, the water, after flowing over a short crest or other kind of
control structure, is carried by an open channel (called the "chute" or "trough") to the
70
downstream side of the river. The control structure is generally normal to the
conveyance channel. The channel is constructed in excavation with stable side slopes
and invariably lined. The flow through the channel is super-critical. The spillway can
be provided close to the dam or at a suitable saddle away from the dam where site
conditions permit.
Side Channel Spillway
Side channel spillways are located just upstream and to the side of the dam. The water
after flowing over a crest enters a side channel which is nearly parallel to the crest.
This is then carried by a chute to the downstream side. Sometimes a tunnel may be
used instead of a chute.
Shaft (Morning Glory or Glory hole) Spillway
This type of spillway utilizes a crest circular in plan, the flow over which is carried by
a vertical or sloping tunnel on to a horizontal tunnel nearly at the stream bed level and
eventually to the downstream side. The diversion tunnels constructed during the dam
construction can be used as the horizontal conduit in many cases.
Siphon Spillway
As the name indicates, this spillway works on the principle of a siphon. A hood
provided over a conventional spillway forms a conduit. With the rise in reservoir level
water starts flowing over the crest as in an "ogee" spillway. The flowing water
however, entrains air and once all the air in the crest area is removed, siphon action
starts. Under this condition, the discharge takes place at a much larger head. The
spillway thus has a larger discharging capacity. The inlet end of the hood is generally
kept below the reservoir level to prevent floating debris from entering the conduit.
This may cause the reservoir to be drawn down below the normal level before the
siphon action breaks and therefore arrangement for de-priming the siphon at the
normal reservoir level is provided.
71
CHAPTER-9
GROUND WATER AND ITS DEVELOPMENT
9.1 Occurrence of Ground Water: The rainfall that percolates below the ground surface, passes through the voids of the
rocks, and joins the watertable. These voids are generally inter-connected, permitting the
movement of the ground water. But in some rocks, they may be isolated, and thus, preventing
the movement of water between the interstices. Hence, it is evident that the mode of
occurrence of ground water depends largely upon the type of formation, and hence upon the
geology of the area.
In fact, all the materials of variable porosity (or interstices) near the upper portion of
the earth’s crust can be considered as a potential storage place for ground water, and hence
might be called as the ground water reservoir. The volume of water contained in the ground
water reservoir in any localized area, i.e. the water storage capacity of the ground water is
dependent upon (i) the porosity of the rocks; (ii) the rate at which water is added to it by
infiltration, transpiration, seepage to surface courses, and withdrawn by man.
Ground Water Yield(Quantity of Ground water):
The interstices present in the given formation get filled up with water during the
process of ground-water replenishment. If all these voids are completely filled with water,
then it is known as saturated formation. The water contained in these voids is drained by
digging wells under the action of ‘gravity-drainage’ (explained later. When these saturated
formations are drained under the action of ‘gravity drainage’, it is found that the volume of
water so drained is less than the volume of the void space as indicated by its porosity. This is
because of the fact, that the entire water contained in these voids cannot be drained out by
mere force of gravity. Some of the water is being retained by these interstices due to their
molecular attraction. The water so retained is known as pellicular water.
Specific Yield:
The volume of ground-water extracted by gravity-drainage from a saturated water
bearing material is known as the yield, and when it is expressed as ratio of the volume of the
total material drained, then it is known as specific field.
100dewateredor drained material theof volumeTotal
drainagegravity by obtained water of volume. ×=∴ yieldSp
72
1.4 Specific retention or Field Capacity:
On the other hand, the quantity of water retained by the material against the pull of
gravity is termed as specific retention or field capacity, and this is also expressed as
percentage of the total volume of the material drained.
100 drained material theof volumeTotal
drainagegravity against held water of volume×=capacityfieldortentionSpecificre
It is evident that the sum of the specific yield and specific retention is equal to its porosity.
1.5 Specific Retention of different Kinds of Formations:
As has been said earlier, the specific retention is the amount of the water held between
the grains due to molecular attraction. This film of water is thus held by molecular adhesion
on the walls of the interstices. Therefore, the amount of this water will depend upon the total
interstitial surface in the rock. If the total interstitial surface is more, the specific retention
will be more and vice versa.
Now, if the effective size of the grains decreases, the surface area between the
interstices will increase, leading to, more specific retention and less specific yield.
It, therefore, follows that, in fine soils like clay, the specific retention would be more,
and hence, such soils would result in very small specific yields.
The reverse is also true when the grain size increases; the interstitial surface area
reduces, and , therefore, sp. Retention reduces and hence sp. Yield increases. It, therefore,
follow that in large particle soils like coarse gravels, the specific retention would be small and
it would result in large specific yields.
This conclusion is very important from practical stand point, because it follows from
this that a water bearing formation of coarse gravel would supply large quantities of water to
wells, whereas, clay formations although saturated and of high porosity, would be of little
ably upon the type of neighboring formations.
Aquifers and Their Types:
A permeable stratum or a geological formation of permeable material, which is
capable of yielding appreciable quantities of ground water under gravity, is known as aquifer.
The term ‘appreciable quantity’ is relative, depending upon the availability of the ground
water. In the regions, where ground
materials containing very less quantities of water may be classified as Principal aquifers.
When an aquifer is obtained by a confined bed of impervious material, then this
confined bed of overburden is called as aquiclude, as shown in Fig. 9.1
The amount of water yielded by a well excavated through an aquifer, depends on
many factors, some of which, such as well diameter, are inherent in the well itself. But all
other things being equal, the permeability and the thickness of the aquifer are the m
important.
Aquifer very in depth, lateral extend, and thickness; but in general, all aquifer fall into
one of the two categories, i.e.,
1. Unconfined or Non-artesian aquifers; and
2. Confined or Artesian aquifer.
Unconfined Aquifer or Non-artesian aquifers:
The top most water bearing stratum having no confined impermeable over burden
(i.e., aquiclude) lying over it, is known as an unconfined aquifer or non
(Refer Fig. 9.2)
73
A permeable stratum or a geological formation of permeable material, which is
ppreciable quantities of ground water under gravity, is known as aquifer.
The term ‘appreciable quantity’ is relative, depending upon the availability of the ground
water. In the regions, where ground-water is available with great difficult, even fine
materials containing very less quantities of water may be classified as Principal aquifers.
When an aquifer is obtained by a confined bed of impervious material, then this
confined bed of overburden is called as aquiclude, as shown in Fig. 9.1
he amount of water yielded by a well excavated through an aquifer, depends on
many factors, some of which, such as well diameter, are inherent in the well itself. But all
other things being equal, the permeability and the thickness of the aquifer are the m
Aquifer very in depth, lateral extend, and thickness; but in general, all aquifer fall into
artesian aquifers; and
Confined or Artesian aquifer.
artesian aquifers:
The top most water bearing stratum having no confined impermeable over burden
(i.e., aquiclude) lying over it, is known as an unconfined aquifer or non-artesian aquifer
A permeable stratum or a geological formation of permeable material, which is
ppreciable quantities of ground water under gravity, is known as aquifer.
The term ‘appreciable quantity’ is relative, depending upon the availability of the ground
water is available with great difficult, even fine-grained
materials containing very less quantities of water may be classified as Principal aquifers.
When an aquifer is obtained by a confined bed of impervious material, then this
he amount of water yielded by a well excavated through an aquifer, depends on
many factors, some of which, such as well diameter, are inherent in the well itself. But all
other things being equal, the permeability and the thickness of the aquifer are the most
Aquifer very in depth, lateral extend, and thickness; but in general, all aquifer fall into
The top most water bearing stratum having no confined impermeable over burden
artesian aquifer
The ordinary gravity wells of 2 to 5 m diameter, which are con
from the top most water bearing strata, i.e., from the unconfined aquifers, are known as
unconfined or non-artesian wells. The water levels in these wells will be equal to the level of
the watertable. Such well are, therefore, also kn
Confined Aquifers or Artesian Aquifers:
When an aquifer is confined on its upper and under surface, by impervious rock
formations (i.e., aquicludes), and is also broadly inclined so as to expose the aquifer
somewhere to the catchments area at a higher level for the creation of sufficient dydraulic
head, it is called a confined aquifer or an artesian aquifer. A well excavated through such an
aquifer, yields water than often flows out automatically, under the hydrostatic press
may thus, even rise or gush out of surface for a reasonable height. However, where the
ground profile is high , the water may remain well below the ground level. The former type
of artesian wells, where after is gushing out automatically, are call
The level to which water will rise in an artesian well is determined by the highest
point on the aquifer, from where it is fed from
74
The ordinary gravity wells of 2 to 5 m diameter, which are constructed to gap water
from the top most water bearing strata, i.e., from the unconfined aquifers, are known as
artesian wells. The water levels in these wells will be equal to the level of
the watertable. Such well are, therefore, also known as wells or gravity wells.
Confined Aquifers or Artesian Aquifers:
When an aquifer is confined on its upper and under surface, by impervious rock
formations (i.e., aquicludes), and is also broadly inclined so as to expose the aquifer
catchments area at a higher level for the creation of sufficient dydraulic
head, it is called a confined aquifer or an artesian aquifer. A well excavated through such an
aquifer, yields water than often flows out automatically, under the hydrostatic press
may thus, even rise or gush out of surface for a reasonable height. However, where the
ground profile is high , the water may remain well below the ground level. The former type
of artesian wells, where after is gushing out automatically, are called flowing wells.
The level to which water will rise in an artesian well is determined by the highest
point on the aquifer, from where it is fed from
structed to gap water
from the top most water bearing strata, i.e., from the unconfined aquifers, are known as
artesian wells. The water levels in these wells will be equal to the level of
When an aquifer is confined on its upper and under surface, by impervious rock
formations (i.e., aquicludes), and is also broadly inclined so as to expose the aquifer
catchments area at a higher level for the creation of sufficient dydraulic
head, it is called a confined aquifer or an artesian aquifer. A well excavated through such an
aquifer, yields water than often flows out automatically, under the hydrostatic pressure, and
may thus, even rise or gush out of surface for a reasonable height. However, where the
ground profile is high , the water may remain well below the ground level. The former type
ed flowing wells.
The level to which water will rise in an artesian well is determined by the highest
75
The rains falling in the catchments (i.e., by discharge). However, the water will not
rise to this full height, because the friction of the water moving through the aquifer uses up
some of the energy.
The question whether it will be a flowing artesian well or a non-flowing artesian well
depends upon the topography of the area, and is not the inherent property of the artesian
aquifer. In fact, if the pressure surface lies above the ground surface, the well will be a
flowing artesian well, whereas, if the pressure surface is below the ground surface, the well
will be artesian but non-flowing, and will require a pump to bring water to the surface, as
shown in Fig.9.3. Such non-flowing artesian wells are sometimes called as sub-artesian wells.
Perched Aquifers:
Perched aquifer is a special case which is sometimes found to occur within an
unconfined aquifer.
If within the zone of saturation, an impervious deposit below a pervious deposit is
found to support a body of saturated materials, then this body of saturated materials which is
a kind of aquifer is known as perched aquifer. The top surface of the water held in the
perched aquifer is known as perched water table. This is shown in Fig. 9.4.
Wells
A water well is a hole usually vertical, excavated in the eared for brining ground
water to the surface. The wells may be classify into two types:
1. Open wells; and
2. Tube wells.
Open Wells or Dug Wells.
Smaller amount of ground water has been utilized from ancient times by open wells.
Open wells are generally open masonry wells having comparatively bigger diameters, and are
suitable for low discharges of the order of 18 cubic maters per hour (i.e. about 0.005 cumecs).
The diameter of than 20 m in depth. The walls of an open well may be built of precast
concrete rings or in brick or stone masonry, the thickness generally varies from 0.05 to 0.75
m, according to the depth of the well.
The yield of an open well is limited because such wells can be excavated only to a
limited depth where the ground water storage is also limited.
Moreover, in such a well the water, the water can be withdrawn only at the critical
velocity for the soil. Higher velocities cannot be permitted as that may lead to disturbance of
soil grains and consequent subsidence of well lining in the hollow so formed. The limit
placed
On velocity , therefore, also limits the maximum possible safe
One of the recent methods used to improve the yield of an open well is to put in a 8 to
10 cm diameter bore hole in the centre of the well, so as to tap the additional water from an
aquifer or from fissures in the rock. If a c
as to support the open masonry well, a bore hole can be made in its centre so as to reach the
76
The yield of an open well is limited because such wells can be excavated only to a
limited depth where the ground water storage is also limited.
Moreover, in such a well the water, the water can be withdrawn only at the critical
elocity for the soil. Higher velocities cannot be permitted as that may lead to disturbance of
soil grains and consequent subsidence of well lining in the hollow so formed. The limit
On velocity , therefore, also limits the maximum possible safe dis-charge of an open well.
One of the recent methods used to improve the yield of an open well is to put in a 8 to
10 cm diameter bore hole in the centre of the well, so as to tap the additional water from an
aquifer or from fissures in the rock. If a clay or kankar layer is available at a smaller depth so
as to support the open masonry well, a bore hole can be made in its centre so as to reach the
The yield of an open well is limited because such wells can be excavated only to a
Moreover, in such a well the water, the water can be withdrawn only at the critical
elocity for the soil. Higher velocities cannot be permitted as that may lead to disturbance of
soil grains and consequent subsidence of well lining in the hollow so formed. The limit
charge of an open well.
One of the recent methods used to improve the yield of an open well is to put in a 8 to
10 cm diameter bore hole in the centre of the well, so as to tap the additional water from an
lay or kankar layer is available at a smaller depth so
as to support the open masonry well, a bore hole can be made in its centre so as to reach the
sand strata. Such an arrangement will not only give a structural support to the open well but
will also considerably increase its yield. Depending upon the availability of such a provision,
the open wells may be classified into the following two types :
(a) Shallow wells; and
(b) Deep wells.
Shallow wells are those which rest in a pervious stratum and draw their suppli
the surrounding materials. On the other hand, a deep well is one which rests on an impervious
‘mota’ layer and draws its supply from the pervious formation lying below the mota layer,
through a bore hole made into the ‘mota’ layer, as shown in Fig
also sometimes known as “Matbarwa” or “Magasan”, referes to a layer of clay, cemented
sand,
kankar or other hard materials, which are often found lying a few metres below the
watertable in the sub-soil. The names are
the watertable. The main advantage of such a mota layer lies in giving structural support to
the open well resting on its surface. It is useful for unlined and partly lined wells, and is
indispensable for a heavy masonry well which would not remain stable under steady use
without such a support. The mota layer is generally found throughout the indo
These mote layer may either be continuous or may be localized, and are generally found in
different thicknesses and depths at different places.
77
sand strata. Such an arrangement will not only give a structural support to the open well but
siderably increase its yield. Depending upon the availability of such a provision,
the open wells may be classified into the following two types :
Shallow wells are those which rest in a pervious stratum and draw their suppli
the surrounding materials. On the other hand, a deep well is one which rests on an impervious
‘mota’ layer and draws its supply from the pervious formation lying below the mota layer,
through a bore hole made into the ‘mota’ layer, as shown in Fig. 4016. The term “Mota layer”
also sometimes known as “Matbarwa” or “Magasan”, referes to a layer of clay, cemented
kankar or other hard materials, which are often found lying a few metres below the
soil. The names are not applied to layers of hard material lying above
the watertable. The main advantage of such a mota layer lies in giving structural support to
the open well resting on its surface. It is useful for unlined and partly lined wells, and is
a heavy masonry well which would not remain stable under steady use
without such a support. The mota layer is generally found throughout the indo-Gangtic plain.
These mote layer may either be continuous or may be localized, and are generally found in
erent thicknesses and depths at different places.
sand strata. Such an arrangement will not only give a structural support to the open well but
siderably increase its yield. Depending upon the availability of such a provision,
Shallow wells are those which rest in a pervious stratum and draw their suppliers from
the surrounding materials. On the other hand, a deep well is one which rests on an impervious
‘mota’ layer and draws its supply from the pervious formation lying below the mota layer,
. 4016. The term “Mota layer”
also sometimes known as “Matbarwa” or “Magasan”, referes to a layer of clay, cemented
kankar or other hard materials, which are often found lying a few metres below the
not applied to layers of hard material lying above
the watertable. The main advantage of such a mota layer lies in giving structural support to
the open well resting on its surface. It is useful for unlined and partly lined wells, and is
a heavy masonry well which would not remain stable under steady use
Gangtic plain.
These mote layer may either be continuous or may be localized, and are generally found in
The nomenclature of shallow and deep wells is purely technical and has nothing to do
with the actual depth of the well. A “shallow well” might be having more depth than a “deep
well”.
Since a shallow well draws water from the topmost water bearing stratum, its water is
liable to be contaminated by the rain water percolating in the vicinity and may take with it
minerals or organic matters such as decomposing animals and plants, etc. The water in a deep
well, on the other hand, is not liable to get such impurities and infections. Secondly, the
pervious formations below the mota layer generally contain greater discharge and greater
supplies can be obtained from a deep well as compared to those from a shallow wel
Water is generally drawn from dug or open wells by means of a bucket and a rope.
However, due to the possible surface contamination of water in an uncovered well and also
the individual buckets adding contamination to water, such open wells have been co
many parts of India and fitted with hand pumps (Fig. 4" 15).
2.1 Cavity Formation in Wells.
withdrawn. The water level in such a well will obviously be the same as is the static
watertable outside the well. Now, if a discharge is withdrawn from this well at a constant
rate, the level in the well will go down and stabilise at a lower level than that of the outside
watertable. The head difference between these two levels is called depression head (Fig.
4.17). Under the influence of this head difference, water enters the well from outside so as to
fill
the gap created by withdrawn water. As the water from the surrounding soil travels towards
the well, there is a gradual loss of head, and water surf
same discharge is passing through reducing soil areas as it approaches the well, there is a
gradual increase in flow velocity towards the well. Now according to Darcy's law, this
velocity can gradually increase only if
the water surface will fall gently in the beginning and will fall more and more rapidly as it
78
The nomenclature of shallow and deep wells is purely technical and has nothing to do
with the actual depth of the well. A “shallow well” might be having more depth than a “deep
raws water from the topmost water bearing stratum, its water is
liable to be contaminated by the rain water percolating in the vicinity and may take with it
minerals or organic matters such as decomposing animals and plants, etc. The water in a deep
on the other hand, is not liable to get such impurities and infections. Secondly, the
pervious formations below the mota layer generally contain greater discharge and greater
supplies can be obtained from a deep well as compared to those from a shallow wel
Water is generally drawn from dug or open wells by means of a bucket and a rope.
However, due to the possible surface contamination of water in an uncovered well and also
the individual buckets adding contamination to water, such open wells have been co
many parts of India and fitted with hand pumps (Fig. 4" 15).
Cavity Formation in Wells. Consider a well from which no water is being
withdrawn. The water level in such a well will obviously be the same as is the static
e well. Now, if a discharge is withdrawn from this well at a constant
rate, the level in the well will go down and stabilise at a lower level than that of the outside
watertable. The head difference between these two levels is called depression head (Fig.
4.17). Under the influence of this head difference, water enters the well from outside so as to
the gap created by withdrawn water. As the water from the surrounding soil travels towards
the well, there is a gradual loss of head, and water surface drops towards the well. Since the
same discharge is passing through reducing soil areas as it approaches the well, there is a
gradual increase in flow velocity towards the well. Now according to Darcy's law, this
velocity can gradually increase only if the hydraulic gradient gets gradually increased. Hence,
the water surface will fall gently in the beginning and will fall more and more rapidly as it
The nomenclature of shallow and deep wells is purely technical and has nothing to do
with the actual depth of the well. A “shallow well” might be having more depth than a “deep
raws water from the topmost water bearing stratum, its water is
liable to be contaminated by the rain water percolating in the vicinity and may take with it
minerals or organic matters such as decomposing animals and plants, etc. The water in a deep
on the other hand, is not liable to get such impurities and infections. Secondly, the
pervious formations below the mota layer generally contain greater discharge and greater
supplies can be obtained from a deep well as compared to those from a shallow well.
Water is generally drawn from dug or open wells by means of a bucket and a rope.
However, due to the possible surface contamination of water in an uncovered well and also
the individual buckets adding contamination to water, such open wells have been covered in
Consider a well from which no water is being
withdrawn. The water level in such a well will obviously be the same as is the static
e well. Now, if a discharge is withdrawn from this well at a constant
rate, the level in the well will go down and stabilise at a lower level than that of the outside
watertable. The head difference between these two levels is called depression head (Fig.
4.17). Under the influence of this head difference, water enters the well from outside so as to
the gap created by withdrawn water. As the water from the surrounding soil travels towards
ace drops towards the well. Since the
same discharge is passing through reducing soil areas as it approaches the well, there is a
gradual increase in flow velocity towards the well. Now according to Darcy's law, this
the hydraulic gradient gets gradually increased. Hence,
the water surface will fall gently in the beginning and will fall more and more rapidly as it
79
approaches the well. The surface of water-table surrounding the well, therefore, takes up a
curved shape and is called Cone of Depression. At a certain distance from the well, there is
no appreciable depression of watertable. This distance from, the central line of the well is
called radius of influence of the well.
The velocity of percolating water into the well depends upon the depression head. If
more amount of water is withdrawn from the well and thereby increasing the depression
head, higher flow velocities will prevail in the vicinity of the well. Thus, at a certain rate of
withdrawal, it is very much possible that the flow velocity may exceed the critical velocity
for the soil, thereby causing the soil particles to lift up. As more and more sand particles are
lifted, a hollow is created in the bottom of the well, resulting in increased effective area, so
that ultimately, the velocity falls below the critical value and then no further sand goes out of
the well.
As pointed out earlier, the formation of such hollows beneath the wells is dangerous
in shallow wells, because there is always a danger of subsidence of the well lining. The
maximum rate of withdrawal from such wells is, therefore, limited.
In case of deep well resting on mota layer, the cavity or hollow formation below the
bore hole (Fig. 4'16) is not dangerous, because the well lining remains supported on the mota
layer. Hence, a hollow, much larger in area than the cross-sectional area of the well, may
safely form in deep wells, and thereby giving higher yields. In a shallow well of an equivalent
yield, the well area will have to be increased equal to the area of the cavity under the deep
well, which would make it costlier.
2.2 Construction of Open Wells. From the construction point of view, the open wells
may be classified into the following three types :
Type I. Wells with an impervious lining, such as masonry lining, and generally resting on a
mota layer.
Type II. Wells with a pervious lining, such as dry brick or stone lining, and fed through the
pores in the lining.
Type III. No lining at all, i.e., a Kachha well.
Type I. Wells with impervious lining. They provide the most stable and useful type of wells
for obtaining water supplies. For constructing such a well, a pit is first of all excavated,
generally by hand tools, up to the soft moist soil. Masonry lining is then built up on a kerb
upto a few metres above the ground level. A "kerb" is a circular ring of R.C.C., timber or
steel having a cutting edge at the bottom and a flat top, wide enough to support the thickness
80
of well lining called "steining". The kerb is then descended into the pit by loading the
masonry by sand bags, etc. As excavation proceeds below the kerb, the masonry sinks down.
As the masonry sinks down, it is further built up at top. To ensure vertical sinking, plum bobs
are suspended around the well steinning, and if the well starts tilting, it may be corrected by
adjusting the loads or by removing the soil from below the kerb which may be causing the
tilt. The well lining (steinning) is generally reinforced with vertical steel bars.
After the well has gone up to the watertable, further excavation and sinking may be
done either by continuously removing the water through pumps, etc., or the excavation may
be carried out from top by Jhams. A Jham is a self-closing bucket which is tied to a rope and
worked up and down over a pulley. When the Jham is thrown into the well, its jaws strike the
bottom of the well, dislodging some of the soil materials. As the Jham is pulled up, the soil
cuttings get retained but the water oozes out. The sinking is continued till the mota layer is
reached. A smaller diameter bore hole is then made through the mota layer in the centre of
the well, which is generally protected by a timber lining.
Sometimes, when mota layer is not available, shallow wells may be sunk as described
above upto a required depth, and partly filled with gravel or broken ballast. This will function
as a niter through which water will percolate and enter the well but the sand particles will be
prevented from rising up.
In a pucca well, lined with an impervious lining on its sides, the flow is not radial.
The water enters only from the bottom and the flow becomes spherical when once the cavity
has been formed at the bottom.
Type II. Wells with pervious lining. In this type of wells, dry brick or stone lining is used on
the sides of the well. No mortar or binding material is used. The water, thus enters from the
sides, through the pores in the lining. The flow is, therefore, radial. Such wells are generally
plugged at the bottom by means of concrete. If the bottom is not plugged, the flow pattern
will be a combination of radial flow and a spherical flow. Such wells are generally suitable in
strata as of gravel or coarse sand. The pervious lining may have to be sorrounded by gravel,
etc., when such a well is constructed in finer soils, so as to prevent the entry of sand into the
well along with the seeping water.
Type III. Kachha wells. These are temporary wells of very-shallow depths, and are generally
constructed by cultivators for irrigation supplies in their fields. Such wells can be constructed
in hard soils, where the well walls can stand vertically without any support. They can,
therefore, be constructed only where the water-table is very near to the ground. Though they
81
are very cheap and useful, yet they collapse after some time, and may sometimes prove to be
dangerous.
2.3 Yield of an Open Well. The yield of an open well can be determined with the help
of theoretical methods, with practical methods, or by carrying out a practical test and then
calculating it from the observations. This third method is useful for calculating the yields of
open wells as well as that of tube-wells penetrating through confined aquifers.
(1) Theoretical method. If a well is penetrated through the aquifer, water will rush into it
with a velocity V. If A is the area of the aquifer opening into the well, then
Q=AV
where V=vK, where v is the actual flow velocity and V is the velocity with which water
rushes into the well and is constant.
Q=K.A.v
where K is a constant depending upon the soil and is known as permeability constant.
In the above equation, the velocity of ground water flow (v) can be found by using Slichter's
or Hazen's formula or by actual measurements by chemical or electrical methods.
A, the area of the aquifer, and can be found by knowing the •diameter of the well and
the depth of porous strata.
K, the constant can be found by studying the sample of the soil in the laboratory.
Knowing v, A and K, the discharge can be easily calculated.
2.3 Tube-wells.
The discharge from an open well is generally limited to 3 to 6 litres/sec. Mechanical
pumping of small discharges available in open wells is not econofnical. To obtain large
discharge mechanically, tubewell, which is a long pipe or a tube, is bored or drilled deep into
the ground, intercepting one or more water bearing stratum. The discharge of an open well is
smaller, because : (0 open wells can tap only the topmost or at the most the next lower water
bearing stratum. O'O water from open wells can be withdrawn only at velocity equal to or
smaller than the critical velocity for the soil, so as to avoid the danger of well subsidence. But
in the tube wells, larger discharges can be obtained by getting a larger velocity as well as a
larger cross-sectional area of the water bearing stratum. Since, we have an enormous storage
of ground water in India, the tubewells provide excellent means for providing water supplies,
although they are generally used for irrigation.
2.4 Tube-Wells in Alluvial Soil. Most of our land, especially the entire area from
Himalayas to Vindhya mountains (such as the Indo-Gangetic plain), coastal areas, Narmada
valley, etc., consist of deep alluvial soils. The subsoil water slowly penetrates and is stored in
82
the porous sand and gravel beds which are extensively found in India, except that in the
desert areas. Tube-wells can be easily installed in such soils and are very useful for irrigation.
It is in this context that the tube-wells are assuming greater and greater importance for
tapping out ground water resources, especially in alluviums.
Deep tube-wells are generally constructed by Government and are called State tube-
wells The depth of such wells, generally vary from 50 to 500 m, and may yield as high as 200
litres/sec. The general average yield from the standard tube-wells is of the order of 40 to 45
litr. s/sec. A 300 m deep tube-well has been constructed at Allahabad (UP.) at the edge of
river Gauges, and is yielding at about 140 litres/sec. Trie diameter of the hole is 0"6 m upto
60 m depth, and then 0'56 m below 60 m. The diameter of the strainer is 0'25 m, and
drawdown is 10 m. Tnere are about 20,000 ■deep tube wells in our country, and every year
about 1,500 such wells are being added.
Besides deep tube-wells, shallow tube-wells are also constructed by cultivators. Their
depths generally vary from 20 to 40 m or so, and may yield as high as 15 litres/sec, if located
at proper places. Each well iirigates about 8 hectares. There are about 10 lakh shallow tube-
wells in India, and every year about 1'5 lakh such wells are being added
2.5 Tube-wells in Hard Rocky Soils. It is very difficult to construct a tube-well
irrigation system in rocky areas. Therefore, in rocky areas, tube-wells or open wells are
resorted to, only when, there are no other alternate sources of water. Hence, in rocky areas,
only isolated holes of 10 to 15 cm diameter may sometimes be drilled using down the hole
rigs. Only wells in alluviums have been treated here.
2.6 Various Types of Tube-wells. Tube-wells are generally of the following types :
(1) Strainer wells ;
(2) Cavity wells ;
(3) Slotted wells ; and
(4) Perforated pipe wells.
Out of these four types, the first type, i.e., the strainer wells •are the most important
and widely used in India, while the last type, i.e., perforated pipe wells are not of much
importance, as they have not been used in India to any appreciable extent. The first three
important types of tube-wells are described below :
(1) Strainer Type Tube-wells. As pointed out earlier, a strainer well is the most
important of all the types of tube-wells, and has been extensively and widely used in our
country. So much so that whenever we refer to a 'tube-well', we generally mean a strainer
type of a'iube-well'. All the state tube
tube-well construction got started in 1931, are exclusively of this type.
In this type of a well, a strainer or a screen is placed against the water bearing stratum.
The strainer is generally constructed of a wire screen wrapped round a slotted or perforat
pipe with a small annular space between the two. The wire screen prevents sand particles
from entering the tube-well. The water, therefore, enters the well pipe through the fine mesh
(i.e., the screen) and the sand particles of size larger than the si
from entering the pipe. This reduces the danger of sand removal and hence, larger flow
velocities can be permitted. Moreover, the strainer penetrates into a number of water bearing
strata, and thus* does not depend only on one
pipe is made to have the cross-sectional area of its openings equal to that in the wire screen,
so that no change of velocity occurs between the two. The annular space between the pipe
and the screen is required, otherwise the wires of the screen part of the of the opening of the
pipe.
The strainer type of tube
because in that case, the size of the screen opening will have to be considerably reduced,
which may result in chocking of the strainer, and if the screen openings are kept bigger, the
well will start discharging sand.
The boring for such a well is generally carried out by a "casing pipe of about 5 to 10
cm larger than the diameter of the well pipe. Thus, for a 15 cm diameter well, a bore hole of
20 to 25 cm diameter shall be drilled. After boring the hole, the well pipe assembly which is
partly in ordinary plain pipe (called blind pipe) and partly of strainer pipe, is lowered into th
83
well'. All the state tube-wells constructed in U.P., from where the technique of
well construction got started in 1931, are exclusively of this type.
In this type of a well, a strainer or a screen is placed against the water bearing stratum.
The strainer is generally constructed of a wire screen wrapped round a slotted or perforat
pipe with a small annular space between the two. The wire screen prevents sand particles
well. The water, therefore, enters the well pipe through the fine mesh
(i.e., the screen) and the sand particles of size larger than the size of the mesh, are kept away
from entering the pipe. This reduces the danger of sand removal and hence, larger flow
velocities can be permitted. Moreover, the strainer penetrates into a number of water bearing
strata, and thus* does not depend only on one or two strata for the well supplies. The slotted
sectional area of its openings equal to that in the wire screen,
so that no change of velocity occurs between the two. The annular space between the pipe
uired, otherwise the wires of the screen part of the of the opening of the
The strainer type of tube-well is generally unsuitable for very fine sandy strata,
because in that case, the size of the screen opening will have to be considerably reduced,
which may result in chocking of the strainer, and if the screen openings are kept bigger, the
The boring for such a well is generally carried out by a "casing pipe of about 5 to 10
f the well pipe. Thus, for a 15 cm diameter well, a bore hole of
20 to 25 cm diameter shall be drilled. After boring the hole, the well pipe assembly which is
partly in ordinary plain pipe (called blind pipe) and partly of strainer pipe, is lowered into th
wells constructed in U.P., from where the technique of
In this type of a well, a strainer or a screen is placed against the water bearing stratum.
The strainer is generally constructed of a wire screen wrapped round a slotted or perforated
pipe with a small annular space between the two. The wire screen prevents sand particles
well. The water, therefore, enters the well pipe through the fine mesh
ze of the mesh, are kept away
from entering the pipe. This reduces the danger of sand removal and hence, larger flow
velocities can be permitted. Moreover, the strainer penetrates into a number of water bearing
or two strata for the well supplies. The slotted
sectional area of its openings equal to that in the wire screen,
so that no change of velocity occurs between the two. The annular space between the pipe
uired, otherwise the wires of the screen part of the of the opening of the
well is generally unsuitable for very fine sandy strata,
because in that case, the size of the screen opening will have to be considerably reduced,
which may result in chocking of the strainer, and if the screen openings are kept bigger, the
The boring for such a well is generally carried out by a "casing pipe of about 5 to 10
f the well pipe. Thus, for a 15 cm diameter well, a bore hole of
20 to 25 cm diameter shall be drilled. After boring the hole, the well pipe assembly which is
partly in ordinary plain pipe (called blind pipe) and partly of strainer pipe, is lowered into the
bore hole. The lengths of blind pipe and strainer pipe are so adjusted that the blind pipe rests
against the aquicludes, while the strainer rests against the aquifers, as shown in Fig 4'19. At
bottom, a short blind pipe is provided, so as to permit settl
passed through the strainer. The well is generally plugged at bottom by cement concrete.
Abyssinia tube-well is a special type of strainer well, in which the diameter of the well pipe is
kept equal to 3'8 cm (l^T) and the st
(i.e., 4 to 5 feet).
(2) Cavity Type Tube-wells.
their supplies from the bottom, and not from the sides. Since the water is drawn from the
bottom, only one particular aquifer can be tapped. Thus, the principle behind a cavity
tube-well is essentially similar to that of a deep open well, with the only difference that
whereas an open deep well taps the first aquifer, just below the mota layer,
need not do SO;, and may even tap the lower stratum, as shown in Fig. 4'20.
A cavity type tube-well essentially consists of a pipe bored through the soil and
resting on the bottom of a strong clay layer. A cavity is for
from the aquifer enters the well pipe through this cavity, as shown in Fig. 4'20. In the initial
stages of pumping, fine sand comes out with water, and consequently, a hollow or a cavity is
formed. As the spherical area of t
84
bore hole. The lengths of blind pipe and strainer pipe are so adjusted that the blind pipe rests
against the aquicludes, while the strainer rests against the aquifers, as shown in Fig 4'19. At
bottom, a short blind pipe is provided, so as to permit settlement of any sand particles, if
passed through the strainer. The well is generally plugged at bottom by cement concrete.
well is a special type of strainer well, in which the diameter of the well pipe is
kept equal to 3'8 cm (l^T) and the strainer is provided only for a length of about 1.2 to l.5m
wells. They are those which do not utilise strainers and draw
their supplies from the bottom, and not from the sides. Since the water is drawn from the
om, only one particular aquifer can be tapped. Thus, the principle behind a cavity
well is essentially similar to that of a deep open well, with the only difference that
whereas an open deep well taps the first aquifer, just below the mota layer, a cavity tube
need not do SO;, and may even tap the lower stratum, as shown in Fig. 4'20.
well essentially consists of a pipe bored through the soil and
resting on the bottom of a strong clay layer. A cavity is formed at the bottom and the water
from the aquifer enters the well pipe through this cavity, as shown in Fig. 4'20. In the initial
stages of pumping, fine sand comes out with water, and consequently, a hollow or a cavity is
formed. As the spherical area of the cavity increases outwards, the radial critical velocity
bore hole. The lengths of blind pipe and strainer pipe are so adjusted that the blind pipe rests
against the aquicludes, while the strainer rests against the aquifers, as shown in Fig 4'19. At
ement of any sand particles, if
passed through the strainer. The well is generally plugged at bottom by cement concrete.
well is a special type of strainer well, in which the diameter of the well pipe is
rainer is provided only for a length of about 1.2 to l.5m
They are those which do not utilise strainers and draw
their supplies from the bottom, and not from the sides. Since the water is drawn from the
om, only one particular aquifer can be tapped. Thus, the principle behind a cavity-type
well is essentially similar to that of a deep open well, with the only difference that
a cavity tube-well
well essentially consists of a pipe bored through the soil and
med at the bottom and the water
from the aquifer enters the well pipe through this cavity, as shown in Fig. 4'20. In the initial
stages of pumping, fine sand comes out with water, and consequently, a hollow or a cavity is
he cavity increases outwards, the radial critical velocity
decreases for the same discharge, thus redut Yg the flow velocity and consequently stopping
the entry of sand. Hence, the flow in the beginning is sandy, but becomes clear with the
passage of time.
The essential difference in the flow pattern of a strainer well and a cavity well is that
whereas in a strainer well, the flow is radial, the flow in a cavity well is spherical. Also, in a
strainer well, the area of flow is increased by increasing the l
cavity well, the area of flow is increased by enlarging the size of the cavity. The cavity
formed with a certain discharge enlarges in size if an increased discharge is pumped out.
(3) Slotted Type Tube
available even at deep depths of 75 to 100 m, so as to obtain the required discharge from a
strainer well, and if a suitable strong clay roof is not available for a cavity well, a slotted well
is adopted, provided at least one good stratum having sufficient amount of water is available.
A slotted well essentially consists of a slotted wrought iron pipe, penetrating a highly
pervious confined aquifer (Fig. 4.21). The size of slots may be 25 mmX3mmatl0 to 12 mm
spacing. In order to prevent the entry of fine sand
particles into the pipe, the pipe is surrounded by a mixture of gravel and bajri. This mixture is
called shrouding and is poured from the top into the annular space between the strainer and
85
decreases for the same discharge, thus redut Yg the flow velocity and consequently stopping
the entry of sand. Hence, the flow in the beginning is sandy, but becomes clear with the
The essential difference in the flow pattern of a strainer well and a cavity well is that
whereas in a strainer well, the flow is radial, the flow in a cavity well is spherical. Also, in a
strainer well, the area of flow is increased by increasing the length of strainer pipe, while in a
cavity well, the area of flow is increased by enlarging the size of the cavity. The cavity
formed with a certain discharge enlarges in size if an increased discharge is pumped out.
(3) Slotted Type Tube-wells. If sufficient depth of water bearing strata is not
available even at deep depths of 75 to 100 m, so as to obtain the required discharge from a
strainer well, and if a suitable strong clay roof is not available for a cavity well, a slotted well
t least one good stratum having sufficient amount of water is available.
A slotted well essentially consists of a slotted wrought iron pipe, penetrating a highly
pervious confined aquifer (Fig. 4.21). The size of slots may be 25 mmX3mmatl0 to 12 mm
. In order to prevent the entry of fine sand
particles into the pipe, the pipe is surrounded by a mixture of gravel and bajri. This mixture is
called shrouding and is poured from the top into the annular space between the strainer and
decreases for the same discharge, thus redut Yg the flow velocity and consequently stopping
the entry of sand. Hence, the flow in the beginning is sandy, but becomes clear with the
The essential difference in the flow pattern of a strainer well and a cavity well is that
whereas in a strainer well, the flow is radial, the flow in a cavity well is spherical. Also, in a
ength of strainer pipe, while in a
cavity well, the area of flow is increased by enlarging the size of the cavity. The cavity
formed with a certain discharge enlarges in size if an increased discharge is pumped out.
ent depth of water bearing strata is not
available even at deep depths of 75 to 100 m, so as to obtain the required discharge from a
strainer well, and if a suitable strong clay roof is not available for a cavity well, a slotted well
t least one good stratum having sufficient amount of water is available.
A slotted well essentially consists of a slotted wrought iron pipe, penetrating a highly
pervious confined aquifer (Fig. 4.21). The size of slots may be 25 mmX3mmatl0 to 12 mm
particles into the pipe, the pipe is surrounded by a mixture of gravel and bajri. This mixture is
called shrouding and is poured from the top into the annular space between the strainer and
86
the casing pipe before withdrawing the casing pipe. The tube-well is developed by pumping
water with an air compressor or with a bigger capacity pumping set. In the process of
developing such a tube-well, water is drawn at a high rate, causing high flow velocities and
consequent removal of appreciable quantities of fine sand. Shrouding is continuously fed
through the annular space, so as to fill up the space of removed sand particles. The process is
continued till the sand-free water is obtained.
The diameter of the bore hole or casing pipe is generally kept more than that of a
strainer type of tube-well. For example, a casing pipe of about 40 cm diameter is required for
a well pipe of 15 cm diameter.
The essential difference between a strainer well and a slotted well are :
(i) A strainer well uses a 'strainer' for preventing sand entry in the water, whereas a
slotted well uses a gravel 'shrouding' for this purpose.
(ii) A strainer well can tap one or more strata, whereas a slotted well can tap only one
stratum.
2.6 Methods for Drilling Tube-wells. Deep and high capacity wells are constructed by
drilling. Various different techniques are employed in drilling the well hole. Different
techniques have comparative advantages and disadvantages over each other, depending upon
the type of formation to be drilled. Therefore, each well should be treated as an individual
project, and one particular method adopted, depending upon its suitability. Some of the
drilling methods, common'y used, are described below:
(I) Standard method or Cable tool method. This method of drilling the well hole is also
known as percussion drilling ; because in this method, the well hole is made by percussion,
(i.e., by hammering and cutting). This method is very useful for cutting consolidated rocks
from soft clay to hardest rocks, and is generally unsuitable in loose formations, such as
unconsolidated sand and gravel or for quick sands. This method becomes ineffective in loose
materials, because the loose material slumps and caves around the drilling bit. The drill bit
has a chisel sharp edge, which breaks the rocks by impact when alternately lifted and-
dropped. This drilling bit is connected at the lowest end of the entire’ falling and rising
arrangement' known as String of tools. [Refer Figs. 4'2 (a) and (b)]. From top to bottom, the
string of tools consists of a rope socket, a set of jars, a drill stem, and the drilling bit.
Tools are made of steel and are joined with tapered box and pin screw joints. The
entire assembly weighs several tonnes. The most important tool of the entire assembly is the
drilling bit (or drill) as it does the actual rock cutting. The drill stem is the long steel bar
which adds weight and length to the drill, so that it can cut rapidly and vertically.
The set of jars have no dir
they stick in the hole. A rope or a cable is fastened at the upper end to the rope socket and to
a dead man (or a heavy weight) at the lower end.
The entire assembly of tools is suspended from an
beam, etc. This assembly, known as drilling rig, in turn, is generally mointed on a truck, so as
to make it easily portable. The mast should be sufficiently high, so as to allow the longest of
tools to be hoisted.
87
The set of jars have no direct effect on the drilling. They only loosen the tools when
they stick in the hole. A rope or a cable is fastened at the upper end to the rope socket and to
a dead man (or a heavy weight) at the lower end.
The entire assembly of tools is suspended from an assembly of a mast and a walking
beam, etc. This assembly, known as drilling rig, in turn, is generally mointed on a truck, so as
to make it easily portable. The mast should be sufficiently high, so as to allow the longest of
ect effect on the drilling. They only loosen the tools when
they stick in the hole. A rope or a cable is fastened at the upper end to the rope socket and to
assembly of a mast and a walking
beam, etc. This assembly, known as drilling rig, in turn, is generally mointed on a truck, so as
to make it easily portable. The mast should be sufficiently high, so as to allow the longest of
88
As the drilling proceeds, the tools make 40 to 60 strokes per minute, from a height of 0'4 to 1
m. Water is sometimes added in the hole, so as to form a paste with the cuttings, thus
reducing friction on the falling bit. After the bit has cut 1 to 2 m through a formation, the
string of tools is lifted out, and the hole is cleaned and cleared of the cuttings by means of a
bailer. The process is known as bailing out the hole.
A bailer essentially consists o
When lowered into the well, the valve permits the cuttings to enter the bailer but prevents
them from escaping the bailer. After it is filled with cuttings, it is lifted up to the surface and
emptied.
In unconsolidated formations, casing should be driven down and maintained near the
bottom of the hole to avoid caving. Casing is driven down by means of drive clamps fastened
to the drill stem. The up and down motion of the tools, striking the top of
protected by a drive head, sinks the casing. On the bottom of the casing, a drive shoe is
fastened to protect the casing, as it is being driven.
(2) Hydraulic rotary or Direct rotary method.
and is especially useful in unconsolidated formations. The method involves a continuously
rotating hollow bit, through which a mixture of clay and water or mud is forced. The bit
cuttings are carried up in the hole by the rising mud. No casing is required during drilli
because the mud itself makes a lining on the walls of the hole, which prevents caving.
The drill bit is connected to a hollow steel rod (or drill stem), which, in turn, is
connected at the top to a square rod, known as the Kelley [Refer Fig. 4'23 (a)].
rotated by a rotating
89
As the drilling proceeds, the tools make 40 to 60 strokes per minute, from a height of 0'4 to 1
m. Water is sometimes added in the hole, so as to form a paste with the cuttings, thus
the falling bit. After the bit has cut 1 to 2 m through a formation, the
string of tools is lifted out, and the hole is cleaned and cleared of the cuttings by means of a
bailer. The process is known as bailing out the hole.
A bailer essentially consists of a pipe with a valve at the bottom and a ring at the top.
When lowered into the well, the valve permits the cuttings to enter the bailer but prevents
them from escaping the bailer. After it is filled with cuttings, it is lifted up to the surface and
In unconsolidated formations, casing should be driven down and maintained near the
bottom of the hole to avoid caving. Casing is driven down by means of drive clamps fastened
to the drill stem. The up and down motion of the tools, striking the top of
protected by a drive head, sinks the casing. On the bottom of the casing, a drive shoe is
fastened to protect the casing, as it is being driven.
Hydraulic rotary or Direct rotary method. This is the fastest method of drilling,
ally useful in unconsolidated formations. The method involves a continuously
rotating hollow bit, through which a mixture of clay and water or mud is forced. The bit
cuttings are carried up in the hole by the rising mud. No casing is required during drilli
because the mud itself makes a lining on the walls of the hole, which prevents caving.
The drill bit is connected to a hollow steel rod (or drill stem), which, in turn, is
connected at the top to a square rod, known as the Kelley [Refer Fig. 4'23 (a)].
As the drilling proceeds, the tools make 40 to 60 strokes per minute, from a height of 0'4 to 1
m. Water is sometimes added in the hole, so as to form a paste with the cuttings, thus
the falling bit. After the bit has cut 1 to 2 m through a formation, the
string of tools is lifted out, and the hole is cleaned and cleared of the cuttings by means of a
f a pipe with a valve at the bottom and a ring at the top.
When lowered into the well, the valve permits the cuttings to enter the bailer but prevents
them from escaping the bailer. After it is filled with cuttings, it is lifted up to the surface and
In unconsolidated formations, casing should be driven down and maintained near the
bottom of the hole to avoid caving. Casing is driven down by means of drive clamps fastened
to the drill stem. The up and down motion of the tools, striking the top of the casing,
protected by a drive head, sinks the casing. On the bottom of the casing, a drive shoe is
This is the fastest method of drilling,
ally useful in unconsolidated formations. The method involves a continuously
rotating hollow bit, through which a mixture of clay and water or mud is forced. The bit
cuttings are carried up in the hole by the rising mud. No casing is required during drilling,
because the mud itself makes a lining on the walls of the hole, which prevents caving.
The drill bit is connected to a hollow steel rod (or drill stem), which, in turn, is
connected at the top to a square rod, known as the Kelley [Refer Fig. 4'23 (a)]. The drill is
table which fits closely around the Kelley, and allows the drill rod to slide down, as the hole
progresses.
The drilling rig, such as shown Fig. 4'23 (b), consists of a mast, a rotating table, a
pump for forcing the mud, a hoist and the engine. The mud, after it emerges out of the hole, is
carried to & tank where the cuttings settle out, and the mud can be repumped into the hole.
After the drilling is completed, the casing is lowered into t
in the well-walls during mud pumping, is removed by washing it with water. Water
containing some chemicals like sodium hexametaphosphate is forced through the drill rod,
and the washings come out through the perforations of the
level is completed, the bit is raised and the process repeated.
(3) Reverse Rotary method or Jetting method
method is known as Reverse Rotary method. This is gaining popularity day by
useful for making large wells (diameter up to 1'2 m. app.) in unconsolidated formations.
This method is also known as jetting method. The tool consists of a hollow drill, a drill pipe,
and water swivel. In this method, the cuttings are
called drill pipe. The equipment consists of a mast or a derrick, a centrifugal pump, and
necessary water and power casing.
90
table which fits closely around the Kelley, and allows the drill rod to slide down, as the hole
The drilling rig, such as shown Fig. 4'23 (b), consists of a mast, a rotating table, a
ing the mud, a hoist and the engine. The mud, after it emerges out of the hole, is
carried to & tank where the cuttings settle out, and the mud can be repumped into the hole.
After the drilling is completed, the casing is lowered into the hole. The clay, deposited
walls during mud pumping, is removed by washing it with water. Water
containing some chemicals like sodium hexametaphosphate is forced through the drill rod,
and the washings come out through the perforations of the casing When the washing at one
level is completed, the bit is raised and the process repeated.
Reverse Rotary method or Jetting method. A modification of the hydraulic rotary
method is known as Reverse Rotary method. This is gaining popularity day by day. It is quite
useful for making large wells (diameter up to 1'2 m. app.) in unconsolidated formations.
This method is also known as jetting method. The tool consists of a hollow drill, a drill pipe,
and water swivel. In this method, the cuttings are removed by water through a suction pipe
called drill pipe. The equipment consists of a mast or a derrick, a centrifugal pump, and
necessary water and power casing.
table which fits closely around the Kelley, and allows the drill rod to slide down, as the hole
The drilling rig, such as shown Fig. 4'23 (b), consists of a mast, a rotating table, a
ing the mud, a hoist and the engine. The mud, after it emerges out of the hole, is
carried to & tank where the cuttings settle out, and the mud can be repumped into the hole.
he hole. The clay, deposited
walls during mud pumping, is removed by washing it with water. Water
containing some chemicals like sodium hexametaphosphate is forced through the drill rod,
casing When the washing at one
. A modification of the hydraulic rotary
day. It is quite
useful for making large wells (diameter up to 1'2 m. app.) in unconsolidated formations.
This method is also known as jetting method. The tool consists of a hollow drill, a drill pipe,
removed by water through a suction pipe
called drill pipe. The equipment consists of a mast or a derrick, a centrifugal pump, and
The hole is driven by pumping water under pressure through
churned up and down.
The walls of the hole are supported by hydrostatic pressure acting against a film of
fine grained material deposited on the walls by the drilling water. Cuttings are removed by
water ; and after the mixture (water + cuttings) comes out to the surface, it is passed through
a settling tank (Refer Fig. 4'24).
The sand settles out here, but the fine grained particles are recalculated, so as to help
in stabilising the walls. Casing and cleaning of the walls, etc. i
rotary method.
91
The hole is driven by pumping water under pressure through the drill bit, while it is
The walls of the hole are supported by hydrostatic pressure acting against a film of
fine grained material deposited on the walls by the drilling water. Cuttings are removed by
water + cuttings) comes out to the surface, it is passed through
The sand settles out here, but the fine grained particles are recalculated, so as to help
in stabilising the walls. Casing and cleaning of the walls, etc. is the same as in the hydraulic
the drill bit, while it is
The walls of the hole are supported by hydrostatic pressure acting against a film of
fine grained material deposited on the walls by the drilling water. Cuttings are removed by
water + cuttings) comes out to the surface, it is passed through
The sand settles out here, but the fine grained particles are recalculated, so as to help
s the same as in the hydraulic
92
Comparison of Cable Tool and Hydraulic Rotary methods.
Advantages of Cable Tool Method are given below :
1. A more accurate sample of the formation can be obtained.
2. Lesser amount of water is required during drilling operations.
3. Cable tool rig is lighter and easy to transport.
4. Very useful for consolidated rocks and less useful for loose formations.
5. For shallow-wells, in unconsolidated materials too, it comes out to be cheaper.
Advantages of Hydraulic Rotary Method are given below :
1. Can be used for larger holes up to 1'5 m diameter.
2. Can be best used for drilling test holes, because the hole can be abandoned with
minimum cost.
3. Rotary drilled hole can be gravel packed, which increases its specific capacity, and
keeps the fine particles away, thus causing less sand trouble.
4. Casing is to be driven only after the hole completion, and hence, can be set at any
desired depth.
5. It is the fastest method of drilling and especially useful in unconsolidated formations.
6. It can handle alternate hard and soft formations with ease and the danger of accidents
is lesser. In quick sands, clays, etc., cable tool method is likely to give troubles, as
there is a danger of freezing.
2.7 Completion of a Tube-well. During drilling the well hole by any of the above
methods, care should be taken to see that the hole remains straight and vertical. A common
specification allows a deviation of 15 cm from the vertical in a length of 30 m. After the bore
hole has been constructed or drilled, the well must be completed, so as to provide free
entrance of clear water into the well.
Casings and Screens. In consolidated formations, water enters the well hole directly,
and no casing is provided, because the surroundings are quite stable. But in unconsolidated
formations, a casing is necessary which supports the outside material and helps in freely
admitting water into the well.
For the entry of water, the casing should either contain perforations or its lower part
be replaced by a screen or a strainer. Perforations can be made in the field or at home.
Horizontal louvered openings are generally preferred, and their size is kept between De0 to
D70 of the surrounding soil. Generally, a separate screen forms the lowest part of the casing.
They are made from various corrosion-resistant metals. Plastic screens are also forming their
way in the market. Well-screens are very useful in sandy formations, so that the water
containing only a limited quantity of sand (below a given size) may e
bigger particles are screened and kept away from entering the well. However, the mesh size
of the screen is generally decided by the manufacturer for a given project, depending upon
the grain size distribution of the aquifer.
Gravel Packing. Many a times, a layer of gravel surrounding the screen casing, is
provided, so as to increase the effective well diameter and to keep the fine materials out of
the well. Such a well will have a greater specific capacity than the one of the same d
not surrounded by gravel. The thickness of the gravel may vary with the type of formation
and method of drilling. However, a minimum of 15 cm thickness is generally used. A section
of the gravel packed well is shown in Fig. 4'25.
2.8 Factors Affecting the Selection of a Particular Type of Pump.
The various factors which must be thoroughly considered while selecting a particular
type of a pump for a particular project are:
(i) Capacity of pumps
(ii) Importance of water supply scheme
(iii) Initial cost of pumping arrangement
(iv) Maintenance cost
93
screens are very useful in sandy formations, so that the water
containing only a limited quantity of sand (below a given size) may enter the well, and the
bigger particles are screened and kept away from entering the well. However, the mesh size
of the screen is generally decided by the manufacturer for a given project, depending upon
the grain size distribution of the aquifer.
Packing. Many a times, a layer of gravel surrounding the screen casing, is
provided, so as to increase the effective well diameter and to keep the fine materials out of
the well. Such a well will have a greater specific capacity than the one of the same d
not surrounded by gravel. The thickness of the gravel may vary with the type of formation
and method of drilling. However, a minimum of 15 cm thickness is generally used. A section
of the gravel packed well is shown in Fig. 4'25.
Factors Affecting the Selection of a Particular Type of Pump.
The various factors which must be thoroughly considered while selecting a particular
type of a pump for a particular project are:
Capacity of pumps
Importance of water supply scheme
l cost of pumping arrangement
screens are very useful in sandy formations, so that the water
nter the well, and the
bigger particles are screened and kept away from entering the well. However, the mesh size
of the screen is generally decided by the manufacturer for a given project, depending upon
Packing. Many a times, a layer of gravel surrounding the screen casing, is
provided, so as to increase the effective well diameter and to keep the fine materials out of
the well. Such a well will have a greater specific capacity than the one of the same diameter
not surrounded by gravel. The thickness of the gravel may vary with the type of formation
and method of drilling. However, a minimum of 15 cm thickness is generally used. A section
The various factors which must be thoroughly considered while selecting a particular
94
(v) Space requirements for locating the pupm
(vi) Number of units required
(vii) Total lift of water required
(viii) Quantity of water to be pumped
Truly speaking, reciprocating pumps are also outdated these days, and for all ordinary
conditions of pumping, the centrifugal types of rot dynamic pumps are frequently used these
days, as they provide satisfactory and economic service. However, pumps other than those of
centrifugal types may be used under extreme conditions. The choice between various types of
pumps is guided by the following considerations:
For very small discharge, the rotary pumps may prove to be equally satisfactory as the
centrifugal pumps, and less costly if the water to be pumped is free of sediment.
A centrifugal pump may pose operational problems when constant discharge is
needed at variable heads (because it requires a variable speed driving in that case) whereas,
the discharge through a reciprocating pump depends only on the speed of the pump. Hence,
under such circumstances, where water is to be pumped against very high but variable heads
with a higher suction lift, reciprocating pumps may be useful. However, they can be used
only when the water to be pumped is free of sediment, and ample finances are available for
installing the costly reciprocating pumps.
Centrifugal pumps are especially useful for pumping waste water and water
containing solids, although they are equally suitable for pumping treated waters. Even among
the centrifugal pumps, a choice is sometimes made out of the horizontal shaft centrifugal
pump and the vertical spindle bore hole pump and the submergible pump. The horizontal
pump is the cheapest and is used under a wide range of pumping conditions, but vertical
spindle and submergible pumps may be preferred for handling large quantities of water under
low heads and for wells and bore holes.
Air lift pumps may prove to be cheaper and, therefore, selected when water is
required to be pumped simultaneously from a number of wells; because in that case, a
common compressor unit can be used to feed all the pumps. However, their efficiency is
generally low.
The hydraulic ram and jet pumps may also be used under special circumstances, as
pointed out earlier.