session 11 (material resource planning, tmh)

Upload: ashok

Post on 14-Apr-2018

225 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    1/37

    Materials Requirements

    Planning(Session 11)

    1

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    2/37

    Material Requirements Planning (MRP)

    MRP Logic and Product Structure Trees

    Time Fences

    MRP Example

    MRP II and Lot Sizing

    Outline

    2

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    3/37

    Material Requirements Planning Materials requirements planning (MRP) is a

    means for determining the number of parts,components, and materials needed to produce

    a product MRP provides time scheduling information

    specifying when each of the materials, parts,and components should be ordered orproduced

    Dependent demand drives MRP

    MRP is a software system

    3

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    4/37

    Example of MRP Logic and Product

    Structure Tree

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    Product Structure Tree for Assembly A Lead TimesA 1 day

    B 2 days

    C 1 day

    D 3 days

    E 4 days

    F 1 day

    Total Unit Demand

    Day 10 50 A

    Day 8 20 B (Spares)

    Day 6 15 D (Spares)

    Given the product structure treefor A and the lead time anddemand information below, provide a materials requirements

    plan that defines the number of units of each component and

    when they will be needed

    4

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    5/37

    LT = 1 day

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    Order Placement 50

    First, the number of units of A are scheduled

    backwards to allow for their lead time. So, in the

    materials requirement plan below, we have to place

    an order for 50 units of A on the 9th day to receive

    them on day 10.

    5

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    6/37

    Next, we need to start scheduling the components that make up

    A. In the case of component B we need 4 Bs for each A.

    Since we need 50 As, that means 200 Bs. And again, we back

    the schedule up for the necessary 2 days of lead time.D a y : 1 2 3 4 5 6 7 8 9 1 0

    A R e q u ir e d 5 0

    O rd e r P la c e m e n t 5 0

    B R e q u i re d 2 0 2 0 0

    O rd e r P la c e m e n t 2 0 2 0 0

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    SparesLT = 2

    4x50=200

    6

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    7/37

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    LT=1 Order Placement 50B Required 20 200

    LT=2 Order Placement 20 200

    C Required 100

    LT=1 Order Placement 100

    D Required 55 400 300

    LT=3 Order Placement 55 400 300

    E Required 20 200LT=4 Order Placement 20 200

    F Required 200

    LT=1 Order Placement 200

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    40 + 15 spares

    Part D: Day 6

    Finally, repeating the process for all components, we have the

    final materials requirements plan:

    7

    7

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    8/37

    Master Production Schedule (MPS)

    Time-phased plan specifying how manyand

    whenthe firm plans to build each end item

    Aggregate Plan

    (Product Groups)

    MPS

    (Specific End Items)

    8

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    9/37

    Types of Time Fences

    Frozen No schedule changes allowed within this window

    Moderately Firm

    Specific changes allowed within product groups as

    long as parts are available

    Flexible

    Significant variation allowed as long as overall

    capacity requirements remain at the same levels

    9

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    10/37

    Example of Time Fences

    8 15 26

    Weeks

    FrozenModerately

    Firm Flexible

    Firm Customer Orders

    Forecast and available

    capacity

    Capacity

    10

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    11/37

    Material Requirements Planning

    System

    Based on a master production schedule, amaterial requirements planning system:

    Creates schedules identifying the specific parts

    and materials required to produce end items

    Determines exact unit numbers needed

    Determines the dates when orders for those

    materials should be released, based on lead

    times

    11

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    12/37The McGraw-Hill Companies, Inc., 2004

    Firm orders

    from known

    customers

    Forecasts

    of demand

    from random

    customers

    Aggregate

    product

    plan

    Bill of

    material

    file

    Engineering

    design

    changes

    Inventory

    record file

    Inventory

    transactions

    Master production

    Schedule (MPS)

    Primary reportsSecondary reports

    Planned order schedule for

    inventory and production

    control

    Exception reports

    Planning reports

    Reports for performance

    control

    Material

    planning

    (MRP

    computer

    program)

    12

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    13/37

    Bill of Materials (BOM) File Materials

    Parts

    Components

    Production sequence

    Modular BOM

    Subassemblies Super BOM

    Fractional options

    13

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    14/37

    Inventory Records File

    Each inventory item carried as a separate file

    Status according to time buckets

    Pegging

    Identify each parent item that created demand

    14

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    15/37

    Primary MRP Reports

    Planned ordersto be released at a future time Order release noticesto execute the planned

    orders

    Changes in due datesof open orders due torescheduling

    Cancellations or suspensionsof open orders due

    to cancellation or suspension of orders on themaster production schedule

    I nventory status data

    15

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    16/37

    Secondary MRP Reports

    Planning reports, for example, forecasting

    inventory requirements over a period of time

    Performance reportsused to determine

    agreement between actual and programmedusage and costs

    Exception reportsused to point out serious

    discrepancies, such as late or overdue orders

    16

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    17/37

    Additional MRP Scheduling

    Terminology

    Gross Requirements

    Scheduled receipts

    Projected available balance

    Net requirements

    Planned order receipt

    Planned order release

    17

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    18/37

    MRP Example

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Item On-Hand Lead Time (Weeks)

    X 50 2

    A 75 3

    B 25 1

    C 10 2

    D 20 2

    Requirements include 95 units (80 firm orders and 15 forecast) of X

    in week 10

    18

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    19/37

    A(2)

    X

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes2 As for

    each X

    19

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    20/37

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    B(1)A(2)

    X

    It takes

    1 B for

    each X

    20

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    21/37

    A(2) B(1)

    X

    C(3)

    It takes 3

    Cs for

    each A

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    21

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    22/37

    A(2) B(1)

    C(2)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 2

    Cs for

    each B

    22

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    23/37

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 5

    Ds for each

    B

    23

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    24/37

    Closed Loop MRP

    Production Planning

    Master Production Scheduling

    Material Requirements Planning

    Capacity Requirements Planning

    Realistic?No

    Feedback

    Execute:

    Capacity Plans

    Material Plans

    Yes

    Feedback

    24

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    25/37

    Manufacturing Resource Planning

    (MRP II)

    Goal: Plan and monitor all resources of a

    manufacturing firm (closed loop):

    manufacturing marketing

    finance

    engineering Simulate the manufacturing system

    25

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    26/37

    Lot Sizing in MRP Programs

    Lot-for-lot (L4L)

    Economic order quantity (EOQ)

    Least total cost (LTC)

    Least unit cost (LUC)

    Which one to use?

    The one that is least costly!

    26

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    27/37

    27

    Numerical # 1:

    Given the following product structure tree diagram, completethe MRP records for A, B, and C.

    A

    C B (2)

    C

    W k 4 5 6 7 8 9

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    28/37

    28

    Gross 5 15 18 8 12 22

    Scheduled

    Receipt

    PAB (21)

    P.O.Receipt

    P.O. Release

    Gross 40 40 40

    ScheduledReceipt 32

    PAB (20)

    P.O.Receipt

    P.O. Release

    PART A

    Q=20; LT=1;

    SS=0

    Gross

    Scheduled

    Receipt

    PAB (50)

    P.O.Receipt

    P.O. Release

    PART BQ=40; LT=2;

    SS=0

    PART C

    Q=L-4-L; LT=1;

    SS=10

    Week 4 5 6 7 8 9

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    29/37

    29

    A

    B(2) C (3)

    F(2)D(2) E(2)

    E(2)

    D(2)G(1)

    Numerical # 2:Draw the time-phased product structure tree.

    Parts L.T.

    A 1

    B 2

    C 1

    D 1

    E 2

    F 3

    G 2

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    30/37

    1 2 3 4 5 6 7 8

    30

    G

    D

    A

    B

    E

    F

    D

    E

    C

    Time-phased product structure of A

    Time in week

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    31/37

    31

    Questions:

    To ensure good master scheduling, a master

    scheduler must do which of the

    following?

    Never lose sight of the aggregate plan

    Identify and communicate all problems

    Be involved with customer order

    promising

    Be visible to all levels of management

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    32/37

    The purpose of a time fence is which of

    the following? Make sure the cows dont get out of

    the barn

    Control flow through the productionsystem

    Maximize sales to retailers

    All of the above

    None of the above

    32

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    33/37

    Which of the following is an objective under

    an MRP system? To improve customer service

    Minimize inventory investment

    Maximize production operatingefficiency

    All of the above

    None of the above

    33

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    34/37

    Which of the following is one of the three main

    inputs into an MRP system?

    BOM file

    Exception report

    Planning report

    All of the above, None of the above

    An MRP program accesses the status of a job

    according to specific time periods called which of

    the following?

    a. Peg record

    b. Time fence

    c. Time bucket

    d. Time clock, e. None of the above 34

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    35/37

    In MRP, workload per work center can be

    determined. When the work capacity isexceeded, which of the following options can

    be implemented to correct the imbalance of

    workload? Work overtime

    Renegotiate the due date and reschedule

    Subcontract to an outside shop All of the above

    None of the above

    35

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    36/37

    Which of the following are reasons why a

    Lot-For-Lot (L4L) method of lot sizing

    can be used in an MRP application? Minimizes carrying costs

    Sets planned orders to exactly match the

    net requirements

    Produces exactly what is needed

    Does not carry any units over into future

    periods

    All of the above

    36

  • 7/29/2019 Session 11 (Material Resource Planning, TMH)

    37/37

    End of Session

    37